chapter 3. planning(project management)

Upload: ahmad-siddiq

Post on 13-Apr-2018

238 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/26/2019 Chapter 3. Planning(Project Management)

    1/26

    PL NNING THE PROJECT

    If the problems arise during the life of a project, our first

    hunch would be that the project was not properly planned.

    The planning will be used by PM as a map of the route fromthe project start and finish

    Contain the sufficient information

  • 7/26/2019 Chapter 3. Planning(Project Management)

    2/26

    Key Elements of a Project Plan

    Key Elements

    Overview

    Objectives

    GeneralApproach

    ContractualAspects

    Schedules

    Resourcesrequirement

    Personnel

    RiskManagement

    EvaluationMethods

  • 7/26/2019 Chapter 3. Planning(Project Management)

    3/26

    Key Elements of a Project Plan

    Overview

    brief description of project

    deliverables

    milestones

    expected profitability and competitive effects

    intended for senior management

    Objectives

    detailed description of projects deliverables

    project mission statement

  • 7/26/2019 Chapter 3. Planning(Project Management)

    4/26

    Key Elements of Project Plan

    General approach

    technical and managerial approaches

    relationship to other projects

    deviations from standard practices

    Contractual aspects

    agreements with clients and third parties

    reporting requirements

    technical specifications

    project review dates

    compliance with legal/environmental constraints

  • 7/26/2019 Chapter 3. Planning(Project Management)

    5/26

    Schedules

    outline of all schedules and milestones

    Resource requirements estimated project expenses

    overhead and fixed charges

    Personnel special skill requirements

    necessary training

    special legal arrangements (such as non-disclosure agreements)

    Key Elements of Project Plan

  • 7/26/2019 Chapter 3. Planning(Project Management)

    6/26

    Risk management

    listing of potential disasters

    late subcontractor deliveries, bad weather, unreasonable

    deadlines, equipment failure, changes in project scope, etc.

    Evaluation methods

    evaluation procedures and standards

    procedures for monitoring, collecting, and storing data on

    project performance

    Elements of a Project Master Plan

  • 7/26/2019 Chapter 3. Planning(Project Management)

    7/26

    The Project Charter

    A Project Charter consists of most, if not all, of the nine

    items described in the project plan plusthe sign-off on

    the plan by all major stakeholders

    The signers include a representative of the project

    sponsor, the client user, the project manager, the program

    manager (if the project is part of an overall program) and

    other concerned stakeholders

  • 7/26/2019 Chapter 3. Planning(Project Management)

    8/26

    Project Managers Initial Tasks

    Review the project objectives project scope plus

    expected desirable outcomes

    Understand the expectations that the organization, the

    client, and other stakeholders have for the project.

    Identify who among senior managers has a major

    interest in the project.

    Determine if anything about the project is a typical.

  • 7/26/2019 Chapter 3. Planning(Project Management)

    9/26

    The Launch Meeting - Invitation List

    At least one representative from senior management

    Managers from functional areas that will contribute to

    the project

    [Perhaps] highly specialized technical experts

  • 7/26/2019 Chapter 3. Planning(Project Management)

    10/26

    Project Launch Meeting

    Senior management introduces project manager

    Project manager chairs meeting

    develop general understanding of the functional inputs the

    project will need may brainstorm the problem

    may review a tentative budget and develop preliminary plan

    ImportantResults

    scope understood and temporarily fixed

    functional managers understand their responsibilities and

    have committed to developing the initial plan

  • 7/26/2019 Chapter 3. Planning(Project Management)

    11/26

    Developing the Project

    Hierarchical planning process

    begin with projects objectives

    list major activities needed to achieve objectives (level 1

    activities)

    delegate level 1 activities to individuals or functional areas to

    develop list of level 2 activities

    degree of detail should be same within a given level

    The outcome of this hierarchical planning is

    the development of a Work Breakdown

    Structure (WBS) for the project

  • 7/26/2019 Chapter 3. Planning(Project Management)

    12/26

    The Project Action Plan

    Construction of project WBS

    Project activities identified and arranged in successively

    finer detail (i.e., by levels)

    Type and quantity of each required resource identified for

    each activity

    Predecessors and task durations estimated for each activity

    All project milestones identified

    Individual or group assigned to perform the work identified

    for all activities

  • 7/26/2019 Chapter 3. Planning(Project Management)

    13/26

  • 7/26/2019 Chapter 3. Planning(Project Management)

    14/26

    A Partial WBS (Gozinto Chart) for an Annual TributeDinner Project

  • 7/26/2019 Chapter 3. Planning(Project Management)

    15/26

    The Project Master Schedule3-15

    The Project Master Schedule is created by

    combining milestones, task durations, and

    predecessors

    This master schedule allows the project

    manager to compare actual and planned task

    durations and resource usage

  • 7/26/2019 Chapter 3. Planning(Project Management)

    16/26

    RACI Matrix

    A table with the project tasks derived fromthe WBS

    It helps organize the project team by clarifying

    the responsibilities of the project team

    members

  • 7/26/2019 Chapter 3. Planning(Project Management)

    17/26

    Example of a RACI Matrix

  • 7/26/2019 Chapter 3. Planning(Project Management)

    18/26

    MIND MAPPING

    Mind mapping is a visual approach that closely

    mirrors the way the human brain records and stores

    informationIn addition to its visual nature, this methodology

    has the advantage of tapping in to the creative

    potential of multiple team members

    Mind mapping is an entertaining approach that

    helps generate enthusiasm and involvement

  • 7/26/2019 Chapter 3. Planning(Project Management)

    19/26

    Developing A Mind Map3-19

  • 7/26/2019 Chapter 3. Planning(Project Management)

    20/26

  • 7/26/2019 Chapter 3. Planning(Project Management)

    21/26

  • 7/26/2019 Chapter 3. Planning(Project Management)

    22/26

    Approaches to Integration Management3-23

    One approach to integration management is knownas Parallel Tasking (PT) (a.k.a. simultaneousengineering) which involves carrying out stepsconcurrently rather than sequentially

    helps minimize conflict across functional groups

    reduces project duration

    Another approach is to identify and map theinterdependencies between members of the projectteam

  • 7/26/2019 Chapter 3. Planning(Project Management)

    23/26

    An Interface Mapping of a Silicon Chip DesignProject

    3-24

  • 7/26/2019 Chapter 3. Planning(Project Management)

    24/26

    A Coordination Structure Model for Project Management

    3-25

    System Responsibility

    Coordination Structure

    Work Breakdown Structure

    Event and Activity Basedscheduling models

    Changes orDifficulties

    Proposed

    Feedback Conventional Feedback

  • 7/26/2019 Chapter 3. Planning(Project Management)

    25/26

    Design Structure Matrix3-26

    Traditional project management tools (such as

    Gantt charts and precedence diagrams) tend to

    focus on those tasks that have to be completed in

    order for other to start

    Often a more important question is: what

    information is needed from other tasks to complete

    specific task?

  • 7/26/2019 Chapter 3. Planning(Project Management)

    26/26

    DSM for Project with Six Activities and ConcurrentActivities

    3-27

    a b c d e f

    a

    b X O

    c X O

    d X X X

    e X

    f X X X

    tasks to be completed concurrently

    X -- information flow

    O -- potential rework situation

    a b c d e f

    a

    b X X

    c X X

    d X X X

    e X

    f X X X

    X -- information flow