chapter 2 line balancing no pics
TRANSCRIPT
-
7/29/2019 Chapter 2 Line Balancing No Pics
1/24
Chapter 2: Line BalancingChapter 2: Line Balancing
IE 5511 Human Factors
Professor Hayes
-
7/29/2019 Chapter 2 Line Balancing No Pics
2/24
Line BalancingLine Balancing
Line: an assembly line composed of several
work stations, at which specific operations
are performed.To work effectively, with no work pile-ups
between stations, the line must be balanced,
e.g. work must get through eachworkstation in roughly the same amount of
time.
-
7/29/2019 Chapter 2 Line Balancing No Pics
3/24
Line BalancingLine Balancing
Goals: To meet production goals,
Maximize output.
Common Approaches to Line Balancing:
1. Estimating the number of operators for a givennumber of stations,
2. Work element sharing: grouping activities perwork elements into stations or jobs performed
by a single person (some times multiple peoplework in concert at a single station or machine)
-
7/29/2019 Chapter 2 Line Balancing No Pics
4/24
Estimating theEstimating the
number of operatorsnumber of operatorsIn a perfectly balanced line, alloperations
at allstation would take identicaltime.
Efficiency would be 100 %
However, this rarely happens!!
100 % efficiency is rarely achievable,
A more reasonable goal is 95 % efficiency.
(However, even that may not be achievable
depending on the nature of the operations).
-
7/29/2019 Chapter 2 Line Balancing No Pics
5/24
Estimating the number ofEstimating the number of
OperatorsOperatorsTo achieve a given rate of production, R,
N operators are needed (total).
(1) N = R x AM = R x SM
EDesired
Rate of Production
Number of
Operators
Needed
Allowed Minutes: total time
between pieces (e.g. AM =
time of slowest operation)
Efficiency
(expressed as fraction)
Standard Minutes:
Time it actually takes
to complete an operation
on average
-
7/29/2019 Chapter 2 Line Balancing No Pics
6/24
Procedure for DeterminingProcedure for Determining
the Number of Operatorsthe Number of Operators
needed to meet production goals.needed to meet production goals.
Assumptions. You have already determined:
the numberof workstations, theirsequence
the operations that will be performed at each one.
Goals. To:
Meetproduction goals given to you by your management,
Balance the workloadbetween stations by putting more
workers at the slower stations,
Reduce idle time
-
7/29/2019 Chapter 2 Line Balancing No Pics
7/24
Procedure: Estimating the Number of OperatorsProcedure: Estimating the Number of Operators
Givens: Production goal, operation sequence.
Step 0: (Prior to the analysis) Perform time studies for eachoperation using experienced operators in order to obtainstandard times (SM).
Step 1: Convert theproduction rate, R, into the sametime units as your standard times.
Step 2: (optional) Estimate the total number ofoperators for the line using Equation (1) (see previousslides)
Step 3: Estimate the number of operators needed foreach operation,
Step 4: Identify theslowestoperation given the numberof operators computed in previous step,
Step 5: Test: have you met the production goal?Step 6: Adjust. Add more operators, negotiate to
reduce the production goal, or try additional methods.
-
7/29/2019 Chapter 2 Line Balancing No Pics
8/24
Example: Estimating the Number of OperatorsExample: Estimating the Number of Operators
Givens: Production goal: 700 units/day where 1 day =
8 hours.
Operation sequence: Op1, Op2, Op3, Op4,
Op5, Op6, Op7, Op8.
Step 0: (Prior to the analysis) Perform time
studies for each operation using
experienced operators in order to obtainstandard times in minutes (SM).
-
7/29/2019 Chapter 2 Line Balancing No Pics
9/24
Example:Example:
Estimating the Number of OperatorsEstimating the Number of OperatorsStep 1: Convert theproduction rate, R, into the
same time units as your standard times.
The standard times, SM, have been expressed inminutes, while R is in days, so:
R = 700 units/day = 1.458 units/min
480 min/day
Also compute the desired cycle time (rate at whichunits exitline)
cycle time = 1 = 0.685 min/unit
R
-
7/29/2019 Chapter 2 Line Balancing No Pics
10/24
Example:Example:
Estimating the Number of OperatorsEstimating the Number of Operators
Step 2:(optional) Estimate the total number
of operators, N, required to meet production
goal, using Equation (1) :
-
7/29/2019 Chapter 2 Line Balancing No Pics
11/24
Example:Example:
Estimating the Number of OperatorsEstimating the Number of OperatorsStep 3: Estimate the number of operators
needed foreach operation,
Step 4: Identify theslowestoperation given
the number of operators computed in
previous step,
Step 5: Test: have you met the productiongoal?
-
7/29/2019 Chapter 2 Line Balancing No Pics
12/24
Number of operators neededNumber of operators needed
for each operationfor each operation
to achieve production goalsto achieve production goals
Cycle time = 1/R
-
7/29/2019 Chapter 2 Line Balancing No Pics
13/24
Calculate reduced cycle times atCalculate reduced cycle times at
each station when using multipleeach station when using multiple
operatorsoperators
SM / Number of Operators
New cycle time at
station when using
multiple operators
-
7/29/2019 Chapter 2 Line Balancing No Pics
14/24
Calculate reduced cycle times atCalculate reduced cycle times at
each station when using multipleeach station when using multiple
operatorsoperators
SM / Number of Operators
New cycle time at
station when using
multiple operators
Your production line will only be as fast as your slowest worker.Does this line meet the desired cycle time (0.685)?
-
7/29/2019 Chapter 2 Line Balancing No Pics
15/24
Work Element SharingWork Element Sharing
A line can sometimes be balanced with less
costby rearranging the sub-work elements
(e.g. activities composing a work element)For example, by giving activities from the
busiestelement to elements with idle time.
-
7/29/2019 Chapter 2 Line Balancing No Pics
16/24
Properties of Work ElementsProperties of Work Elements
What is a work element?How big should a work element be?
Assemble items in
box
Load Styrofoam
block
Load book
Grasp
block
Move block
to box
Orient
Block
Release
Block
Work Element
Sub-work elements
Sub-sub work elements
-
7/29/2019 Chapter 2 Line Balancing No Pics
17/24
Work Element PropertiesWork Element Properties
Work elements can be represented atvarious levels of abstraction or detail
Work elements can almost always be sub-divided into smaller elements.
The appropriate representation depends onthe task and situation.
-
7/29/2019 Chapter 2 Line Balancing No Pics
18/24
Work Element Sharing:Work Element Sharing:
GEs Line BalancingGEs Line Balancing
A Procedure for AssigningA Procedure for AssigningWork Elements to StationsWork Elements to Stations
Given:
Precedence graph Production goal (e.g. 300 units per shift)
Shift duration (e.g. 450 minutes)
Number of workstations (e.g. 6 workstations)
Decided how to assign elements to workstations so
as to meet production goals withoutviolating
precedence constraints!
-
7/29/2019 Chapter 2 Line Balancing No Pics
19/24
A Precedence Graph forA Precedence Graph for
Assembly OperationsAssembly Operations
The graph should only contain necessary orderings.
Any unnecessary constraints make it harder to achieve
efficiency.
P d l ti 1 i b f
-
7/29/2019 Chapter 2 Line Balancing No Pics
20/24
Precedence relations: 1 = y is before x
-
7/29/2019 Chapter 2 Line Balancing No Pics
21/24
Compute positional weighs,Compute positional weighs,
Record immediate predecessors,Record immediate predecessors,
Sort from biggest positional weightSort from biggest positional weight
-
7/29/2019 Chapter 2 Line Balancing No Pics
22/24
-
7/29/2019 Chapter 2 Line Balancing No Pics
23/24
The Final Assembly LineThe Final Assembly Line
A streamlined version:A streamlined version:
(00) (02)
(01) (03)
(05) (06)
(04)
(08) (07) (09) (10)
Station 1
Station 2
Station 3
Station 4 Station 5Station 6
-
7/29/2019 Chapter 2 Line Balancing No Pics
24/24
A stream-lined version of theA stream-lined version of the
Assembly lineAssembly line
(00) (02)
(01) (03)
(05) (06)
(04)
(08) (07) (09) (10)