chapter 14 | stakeholder consultation and public involvement
TRANSCRIPT
Chapter 9 | Biological Impacts and Management Measures
Chapter 14 | Stakeholder Consultation and Public
Involvement
Mako Gold Project
Environmental and Social Impact Assessment
FINAL
Chapter 14 | Stakeholder Consultation and Public Involvement
14 STAKEHOLDER CONSULTATION AND PUBLIC INVOLVEMENT ............................ 14-1
14.1 Introduction ............................................................................................................................................................. 14-1
14.2 Objectives ................................................................................................................................................................. 14-1
14.3 National and International Stakeholder Engagement Context ............................................................. 14-1
14.3.1 National Legislation ................................................................................................................................ 14-1
14.3.2 IFC Guidelines for Stakeholder Engagement ................................................................................. 14-2
14.4 The Company’s Approach to Stakeholder Engagement .......................................................................... 14-3
14.5 Stakeholder Identification and Analysis ........................................................................................................ 14-3
14.6 Stakeholder Engagement Structures .............................................................................................................. 14-4
14.6.1 Inter-ministerial Committee................................................................................................................. 14-5
14.6.2 Independent Group of Experts ........................................................................................................... 14-5
14.6.3 Local Consultative Committee ............................................................................................................ 14-5
14.7 Information Disclosure ......................................................................................................................................... 14-5
14.7.1 Technical baseline study results ......................................................................................................... 14-5
14.7.2 ESIA Terms of Reference ........................................................................................................................ 14-6
14.7.3 Preliminary ESIA and Feasibility Study results ............................................................................... 14-6
14.7.4 DFS/ESIA report and Management plans ....................................................................................... 14-6
14.8 Stakeholder Consultation Completed to Date ............................................................................................ 14-8
14.8.1 Summary of Consultation Outcomes ............................................................................................ 14-14
14.9 Continuing Consultation for completion of the ESIA ............................................................................. 14-19
14.10 Grievance Management ..................................................................................................................... 14-21
14.11 Stakeholder Involvement in Project Monitoring ....................................................................... 14-22
14.12 Reporting to Stakeholders ................................................................................................................ 14-22
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-1
14 STAKEHOLDER CONSULTATION AND PUBLIC INVOLVEMENT
14.1 Introduction
Throughout the ESIA process, consultations and disclosure of Project information has been undertaken with
National, Regional, Department and Sub-prefecture government officials, the local community, and a variety of
other key stakeholders. Formal consultations included workshops and meetings. Informal consultation
included regular discussions and the inclusion of local residents and local government staff in studies and
surveys. Project information has been disclosed through various means including formal reports, workshops,
village assemblies and focus group discussions. Consultation for this Project builds upon existing community
and government relationships formed through exploration activities.
This chapter summarises the consultation undertaken and the associated outcomes before and during the
drafting of the ESIA. Strategies for ongoing consultation throughout the life of the Project, as well as a
description of the proposed grievance mechanism, are also discussed. Planning for further stakeholder
engagement to support construction and operations is presented in the Stakeholder Engagement Plan
(Volume C).
14.2 Objectives
The overall goal of stakeholder engagement for the Mako Gold Project is to improve Project design and
implementation strategies, build understanding to ensure the long-term viability of the Project and to enhance
potential Project benefits. The specific objectives of the stakeholder consultation for the Mako Gold Project
ESIA are to:
1. Provide a structured means for the local community and government to have input into the ESIA
process;
2. Ensure that stakeholders are informed of the Company activities regarding the Mako Gold Project;
3. Actively seek community input into the assessment of potential environmental and social impacts of
the proposed Project mine activities and identification of management/mitigation measures to ensure
consideration of stakeholder interests in the planning and development of the Project; and
4. Reduce the potential for community disaffection that can result from a lack of understanding of the
Project and the permitting process.
14.3 National and International Stakeholder Engagement Context
14.3.1 National Legislation
In Senegal, stakeholder engagement in the ESIA process is defined by the 2001 Environment Code as the
“involvement of people in the decision making process and has three stages including information,
consultation and public hearing”. Article L53 of the Code states that “the participation of populations reflects
the desire to democratize the process of decision making and is guaranteed by the state in the direction of
decentralization and regionalization”. The 2003 Mining Code also requires that the mining titleholder consult
with the concerned local government.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-2
Ministerial Order No. 9468 defines procedures for public participation in the ESIA process. The Order presents
public participation as a component of the Environmental Impact Assessment which is required at all stages of
project ESIA’s to improve decision making.
14.3.2 IFC Guidelines for Stakeholder Engagement
Stakeholder consultation should be conducted throughout each phase of the Project life cycle, from Pre-
construction through to Closure. Ideally, a good consultation process will be (IFC, 2007):
Targeted at those most likely to be affected by the Project;
Early enough to scope key issues and have an effect on the Project decisions to which they relate;
Informative, as a result of relevant information being disseminated in advance;
Meaningful to those consulted because the content is presented in a readily understandable format and
the techniques used are culturally appropriate;
Two-way so that both sides have the opportunity to exchange views and information, to listen, and to
have their issues addressed;
Gender-inclusive through awareness that men and women often have differing views and needs;
Localised to reflect appropriate timeframes, context, and local languages;
Free from manipulation or coercion;
Documented to keep track of who has been consulted and the key issues raised;
Reported back in a timely way to those consulted, with clarification of next steps; and
Ongoing as required during the life of the Project.
The IFC identifies eight key components of good stakeholder engagement, as illustrated in
Figure 14-1 below.
The following best practice guidelines will also continue to be considered by the Company in the
implementation of future stakeholder engagement activities:
Stakeholder Engagement: A Good Practice Handbook for Companies doing Business in Emerging
Markets. IFC (2007)
Doing Better Business through Effective Public Consultation and Disclosure. A Good Practice Manual.
IFC (1998)
Handling and Resolving Local Level Concerns and Grievances. ICMM (2009)
Community Development Toolkit. ICMM (2005).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-3
Figure 14-1 Key components of stakeholder engagement (IFC, 2009)
14.4 The Company’s Approach to Stakeholder Engagement
The Company aims to meet IFC standards which require that informed stakeholder consultation and
participation should be conducted throughout each phase of the Project life cycle, from Pre-construction
through to Closure (IFC, 2007).
The Company’s approach to stakeholder engagement focusses on the following core values:
Proactively engage to enable the early identification of potential issues and risks;
Generate ideas and alternative solutions on early design questions; and
Respect local culture and established political, social and economic relations.
14.5 Stakeholder Identification and Analysis
The IFC (2012) defines stakeholders as “persons or groups who are directly or indirectly affected by a project, as
well as those who may have interests in a project and/or the ability to influence its outcome, either positively or
negatively”. The following section provides an overview of Project stakeholders.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-4
For the Project, key stakeholder groups include Project Affected Villages, downstream water users, villages
along the site access route and the Government of Senegal (at local, regional and national levels). Additional
stakeholders include Project employees, financiers, insurers and shareholders, investors in other development
projects planned for the Project region, and non-government and other civil society organisations operating
in the region.
Key stakeholder groups have been identified and are presented in Table 14-1.
Table 14-1 Summary of key stakeholder groups
Stakeholder Groups Key Interests
Project Affected Villages/persons:
Downstream villages;
villages along access route;
host communities for Project
induced in-migration
The amenity of the Gambia River including water quality;
Access to social infrastructure (potable water, health posts, etc.);
Artisanal mining sites;
Employment and skill development;
Access routes;
Air quality and noise;
Cultural heritage;
Agro-pastoral activities.
Commune of Tombotonkoto:
Other villages in the
Commune of Tomboronkoto
Commune Council of
Tomboronkoto
Local development actors /
NGOs
The amenity of the Gambia River including water quality;
Access to social infrastructure (potable water, health posts, etc.);
Artisanal mining sites;
Employment and skill development;
Economic development;
Access routes;
Community health and safety;
Agro-pastoral activities.
Department of Kedougou;
Departmental Council of
Kedougou
Employment and skill development;
Economic development;
Access to social infrastructure (potable water, health posts, etc.)
Community health and safety.
Government and Multi-lateral
Institutions:
Administration and technical
agencies
OMVG, UNESCO and other
institutions
The amenity of the Gambia River including water quality;
Biodiversity values of the Gambia River and the Niokolo-Koba
National Park;
Economic development;
Community health and safety;
Cultural heritage;
Access to social infrastructure (potable water, health posts, etc.).
Conservation interests for Protected
Areas and Threatened species:
Research institutions
Conservation NGOs
Biodiversity values of the Gambia River and the Niokolo-Koba
National Park;
Threatened species and habitats.
14.6 Stakeholder Engagement Structures
A number of formal structures were established by the Company to facilitate information disclosure and
stakeholder consultation. The key structures are described below. Stakeholder engagement was also
conducted through a variety of other channels; these are described in Section 14.7 and Section 14.8.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-5
14.6.1 Inter-ministerial Committee
An Inter-ministerial Committee at the National level including representatives of relevant National
Departments was established in September 2014 under the direction of the Mining and Geology Department
of Senegal. The main objective of the Inter-ministerial Committee is to facilitate the Project approval process
including the ESIA.
14.6.2 Independent Group of Experts
An independent group of experts (GEI) was established in December 2014 to review the technical, social and
economic feasibility of the Company’s management framework for the protection of biodiversity associated
with the Mako Gold Project. The GEI is comprised of ecology specialists with backgrounds in academia, research,
government, consulting and non-government organisations.
14.6.3 Local Consultative Committee
In November 2014, the Company established a Local Consultative Committee (Groupe de Contact) to facilitate
consultation with representatives from Project Affected Villages. The Groupe de Contact has provided a forum
for the Company to present Project development plans and seek feedback from the community on potential
impacts, issues and opportunities. The Groupe de Contact comprises elected representatives (including women
and youth) from the villages of Mako, Niemenike, Tambanoumouya and Linguekoto; and two representatives
from the Municipal Council of Tomboronkoto.
The Company also established various ad hoc technical working groups (Groupes Techniques) to support the
analysis of specific issues, namely: economic development and employment; rural livelihood; urban livelihood;
artisanal mining; and livestock. These groups comprised key informants from Project Affected Villages. The
outcomes of the Groupes Technique were reported back to the Groupe de Contact to inform higher level
decision-making.
14.7 Information Disclosure
This section identifies key elements of information disclosure through the ESIA and feasibility phases of the
Project. Table 14-3 below presents a summary of disclosed information for each stakeholder group.
14.7.1 Technical baseline study results
The Company commenced technical baseline studies in August 2012 and continuing through 2013. This
included: surface and ground water quality monitoring; ecology surveys; air quality and noise monitoring;
socio-economic, land and water use surveys; archaeology and cultural heritage surveys. The results of these
surveys defined priority environmental and social features, key issues and potential impacts. These broad
studies subsequently informed the design and conduct of targeted technical studies in 2014 and 2015.
The results of these baseline studies have been shared with a range of stakeholders at key Project milestones,
including:
Disclosure of technical baseline reports on ecology and water resources to relevant government
departments, research agencies, multi-lateral agencies and non-government organisations;
Multi-stakeholder workshops on terrestrial and aquatic biodiversity; and
Village level assemblies and focus group discussion on land and water use;
Dissemination of the draft Terms of Reference for the ESIA.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-6
14.7.2 ESIA Terms of Reference
In March 2014, the Company submitted an environmental and social scoping document and draft Terms of
Reference (TOR) for the Mako Gold Project ESIA for approval by DEEC. The scoping document and draft TOR
was distributed to various government and non-government organisations. A copy of the scoping document
and draft TOR is provided in Volume A (Appendix 1).
Public consultation was undertaken to disseminate the scoping document and draft TOR at the local,
Commune and Regional levels from March 4 to March 21, 2014. The Company was supported in this
consultation by the Direction of Mines and Geology, and the administrative authorities of Bandafassi Sous-
prefecture. A summary of the consultations that took place are outlined below in Table 14-2 and a record of
consultation is provided in Volume A (Appendix 9).
Table 14-2: Summary of initial government consultation
Date Meeting Venue Participants
4 March 2014 Tomboronkoto
Commune workshop
Rural Council of
Tomboronkoto
Rural Council (now Commune) of Tomboronkoto,
representatives from the Project affected
settlements (Tambanoumouya, Linguekoto,
Niemenike and Mako) and NGOs
5-6 March 2014 Village level assembly Tambanoumouya,
Linguekoto,
Niemenike and
Mako
Community
11 March 2014 Regional workshop Kedougou Kedougou Administrative and Technical
Agencies
17-21 March
2014
One-on-one meetings Kedougou Non-government organisations
The draft TOR was updated based on feedback received by the Company during this consultation and formal
comments received from DEEC and DMG in May 2014 (refer Volume A, Appendix 1). A revised TOR was
subsequently submitted to DEEC in August 2014 and approved.
14.7.3 Preliminary ESIA and Feasibility Study results
The preliminary findings of the ESIA and Feasibility Study were presented to 13 villages located within 10 km
and/or downstream of the Project Development Area from January 26-30 2015. Information disclosed at these
village assemblies included the preferred Project design arrangement; potential issues and impacts; the Project
permitting process; and mechanisms for community feedback.
From April 20 to May 11, and as recommended by the Inter-ministerial Committee set up for the Mako Gold
Project, the preliminary ESIA findings were presented to various Government technical agencies and
administrative authorities at regional and national levels, including the Municipal Council of Tomboronkoto.
Minutes and meetings held during this process are included in Appendix 9.
14.7.4 DFS/ESIA report and Management plans
In accordance with Senegalese regulations, the draft ESIA report for the Mako Gold Project was submitted to
the Government for approval. Refer Chapter 3 (Section 3.3.3), for a description of the permitting process for an
ESIA. An integral component of the permitting process is public consultation, including the requirement for a
public hearing (audience publique). The public hearing for the Project was conducted on 21 November in
Kedougou. The meeting was attended by Project-affected villages. The meeting minutes are provided in
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-7
Volume A, Appendix 9. Feedback received during this consultation has been incorporated into the preparation
of this final ESIA report and is summarised in Table 14-9.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-8
Table 14-3: Summary of disclosed information
Phase of Disclosure Information Disclosed Stakeholder Groups
Scoping and screening Project design options;
Preliminary baseline study findings.
Project affected villages
Commune of Tomboronkoto
Government and non-government
agencies
Pre-feasibility Project design options and preferred
design;
Baseline study results;
Key issues and potential impacts;
Draft Terms of Reference for ESIA
Project affected villages
Commune of Tomboronkoto:
Government technical and
administrative authorities
Multi-lateral institutions
Research organisations
Local development actors / NGOs
Feasibility and ESIA Project design;
Baseline study results;
Impact assessment results.
Project affected villages
Commune of Tomboronkoto:
Government technical and
administrative authorities
Multi-lateral institutions
Research organisations
Local development actors / NGOs
14.8 Stakeholder Consultation Completed to Date
The Company’s approach to engagement is participatory and emphasises a high degree of engagement with
all stakeholders and regular and direct consultation with those most affected by the Project. The Company has
aimed to provide those affected with as much information about the Project as possible – and ensure that all
major inputs, conclusions and recommendations are shared with and validated by those affected by the Project.
Key stakeholder engagement activities conducted during the pre-feasibilty, feasibility and ESIA phases of the
Mako Gold Project include, but are not limited to:
Disclosure of the Terms of Reference for the Environmental and Social Impact Assessment.
Consultation with local villages in the design and implementation of preliminary environmental and
social baseline studies. This has included household surveys; key informant interviews; focus groups
discussions and village meetings. Information has been collected in this way on socio-economic
conditions, water use, cultural heritage, artisanal mining, local ecological knowledge etc.
Conduct of comprehensive environmental and social baseline studies involving a range of research
institutes and scientific organisations, including: the ISE (L'Institut des Sciences de l'Environnement,
Université Cheikh Anta Diop); IFAN (Institut Fondamental d'Afrique Noire, Université Cheikh Anta Diop);
IUCN (Union internationale pour la conservation de la nature); Faculty of Science and Technology
(Université Cheikh Anta Diop) and UNESCO (United Nations Educational, Scientific and Cultural
Organisation).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-9
Collaboration with the Direction of National Parks and Direction of Forestry in the conduct of terrestrial
ecology surveys both within the Exploration Permit Area, and adjacent areas of the Niokolo-Koba
National Park.
Participative impact and mitigation planning with local villages, particularly relating to livelihoods, land
and water in the vicinity of the Mako Gold Project.
Development of livelihood pilot programs in Tambanoumouya and Linguekoto villages particularly
relating to livelihoods, land and water in the vicinity of the Mako Gold Project.
Partnership with the Tomboronkoto Commune in the realisation of its Local Development Plan including
activities that have improved access to clean water, health services, education materials and
opportunities for income generation.
Implementation of a grievance mechanism to assist in the validation and resolution of complaints arising
from Project exploration activities.
These activities have helped build mutually beneficial relationships in the Project affected villages and
informed preliminary design decisions. A summary of consultation completed to date can be found in Table
14-4 below. A detailed description of consultation activities is provided in the technical baseline reports
(Volume A, Appendices 1 to 9).
Plates 14-1 and 14-2 Women’s Focus Group Meetings in Sibikiling (left) and Segueko Bassari (right)
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-10
Table 14-4 Summary of consultations and surveys undertaken for the Mako Gold Project to date
Consultation Participants Method of Engagement Period
Draft ESIA Terms of Reference Project Affected Villages, Commune Council of
Tomboronkoto, government and administrative authorities,
Multi-state institutions, Research organisations, NGO
representatives
Village assemblies, workshops,
one-on-one meetings,
dissemination of reports
March – July 2014
Preliminary ESIA results Project Affected Villages, Commune Council of
Tomboronkoto, government and administrative authorities,
multi-state institutions, Research organisations, NGO
representatives
Village assemblies, workshops,
one-on-one meetings,
dissemination of reports
April – May 2015
Preliminary Project design and key
impacts
Project Affected Villages, Commune Council of
Tomboronkoto, government and administrative authorities
Village assemblies, workshops,
one-on-one meetings,
dissemination of reports
January – February 2015
Draft Biodiversity Action Plan Commune Council of Tomboronkoto, government and
administrative authorities, Research organisations, NGO
representatives
Workshop, one-on-one meetings,
dissemination of reports
August 2015
Biodiversity ‘no net loss’ strategy Commune Council of Tomboronkoto, government and
administrative authorities, multi-state institutions, Research
organisations, NGO representatives
Workshop, one-on-one meetings,
dissemination of reports
November 2013
Socio-economic, land and water use
assessment
Project Affected Villages Household surveys, population
census, focus group discussions,
village assemblies, key informant
interviews, field surveys and
ground-truthing
November 2012 and September
2013, August 2014
Women and youth Project Affected Villages Focus group discussions, key
informant interviews
November 2012, February and
March 2015
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-11
Artisanal mining surveys Artisanal miners, village chiefs, government authorities,
NGO representatives
Focus group discussions, key
informant interviews, field surveys
and ground-truthing
20 – 26 November 2012 and
March 2015
Participatory land-use surveys and
mapping
Project Affected Villages Focus group discussions, village
assemblies, key informant
interviews, field surveys and
ground-truthing
April and September 2013,
August 2014
Archaeology and cultural heritage
assessment
Project Affected Villages, research organisations Focus group discussions, key
informant interviews, transect
surveys and test-pitting
November 2012, April 2013, May
– June 2014
Terrestrial and aquatic ecology assessment Project Affected Villages, government authorities, research
organisations
Workshops, one-on-one meetings,
dissemination of reports, focus
group discussions, key informant
interviews, transect and
reconnaissance surveys
February, August-September
2013, June- July 2014
Social impact and mitigation planning,
including local economic participation
planning
Project Affected Villages, Commune Council of
Tomboronkoto, Chamber of Commerce, Chamber of
Trades, Microfinance organisations
Workshops, focus group
discussions, key informant
interviews, meetings,
demonstration and pilot
programmes
December 2014 – March 2015
Downstream water use assessment Project Affected Villages Focus group discussions, key
informant interviews, ground-
truthing
February – March 2015
Cumulative impact assessment Commune Council of Tomboronkoto, government
authorities
One-on-one meetings March 2015
Public audience Project Affected Villages Public meeting 21 November 2015
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-12
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-13
Plate 14-3 Water use survey – Men’s focus group in Kerekonko
Plate 14-4 Water use survey – Women’s focus group in Wassadou
Plate 14-5 Village consultation (youth) in Bomboya
Plate 14-6 Village Consultation in Badian 1
Plate 14-6 Village consultation in Soukouta
Plate 14-7 Village consultation in Dalakoy
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-14
14.8.1 Summary of Consultation Outcomes
Consultation has confirmed that Project stakeholders, including potentially affected villages are generally
supportive of the Project and appreciative of their involvement in the design and planning phases. The
opinions and suggestions of stakeholders obtained through the Stakeholder Engagement process have been
considered in the design of the Project and associated management plans.
Table 14-5: to Table 14-8 below presents specific concerns raised during consultations with villages, specific
groups (women, youth) within villages, and government. Detailed minutes of meetings are included in
Appendix 9 of Volume A.
Throughout the design and planning stages of the Mako Gold Project, the Company has actively addressed the
issues and concerns raised during stakeholder consultation. For example, stakeholder consultation has directly
informed:
The location of the TMF and the decision to avoid impacts to the Wayako valley which is an important
area for agro-pastoral activities;
The alignment of the Main Access Road to avoid impacts to sensitive chimpanzee habitat and
minimise impacts to agricultural land;
The formulation of the social management plans including the Livelihood Restoration Plan and Local
Economic Participation Plan; and
The formulation of the Biodiversity Action Plan, including the draft Biodiversity Offset Strategy.
Table 14-5: Summary of village level concerns and where each of these issues have been addressed in the ESIA
Stakeholder
Group
Consultation Outcomes ESIA Section
Reference
Project Affected
Villages
(Tambanoumouya,
Linguekoto,
Niemenike, Mako;
Dalakoy and
Kerekonko)
Compensation for impacts to livelihood, land and water resources (agro-pastoral activities, artisanal mining, forestry resources);
Sections 11.2 to 11.8 and Livelihood Restoration Plan (Volume D).
Access to employment opportunities; Section 11.1 and Local Economic Participation Plan (Volume D).
In-migration and the impact on host villages (safety, public health, access to infrastructure and services);
Section 11.11.
Cultural heritage; Sections 11.9 and 11.10.
Skill development for the youth; Section 11.1 and Local Economic Participation Plan (Volume D).
Income generating activities for women; Section 11.14 and Local Economic Participation Plan (Volume D).
Public health and safety (road safety, hazardous materials, water quality, air quality, blasting);
Sections 11.12 and 11.13.
Livestock health and access to pasture; Section 11.3.
Pollution of water resources including the Gambia River. Section 11.7.
Downstream
Villages
(Bomboya and
Soukouta)
Pollution of water resources including the Gambia River; Section 11.7.
In-migration and the impact on host villages (safety, public health, access to infrastructure and services);
Section 11.11.
Public health and safety (hazardous materials, water quality); Sections 11.12 and 11.13.
Compensation for impacts to livelihood, land and water resources (agro-pastoral activities, artisanal mining, forestry resources).
Sections 11.2 to 11.8 and Livelihood Restoration Plan (Volume D).
Surrounding
Villages
Compensation for impacts to livelihood, land and water resources (agro-pastoral activities, artisanal mining, forestry resources);
Sections 11.2 to 11.8 and Livelihood
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-15
(Badian I, Badian II,
Badon-Sibikiling,
Senodji, Saint-
Etienne –
Niarikondo,
Laminia –
Sindakha)
Restoration Plan (Volume D).
Pollution of water resources including the Gambia River; Section 11.7.
Land rehabilitation following closure of the mine; Section 11.4 and Rehabilitation and Conceptual Mine Closure Plan (Volume E).
Skill development for the youth; Section 11.1 and Local Economic Participation Plan (Volume D).
Cultural heritage. Sections 11.9 and 11.10.
Table 14-6: Summary of concerns from the women’s focus groups (February – March 2015) and where each of
these issues have been addressed in the ESIA
Village Women’s Consultation Outcomes ESIA Section
Reference
Tambanoumouya,
Linguekoto,
Niemenike and
Mako
Compensation for impacts to livelihood, land and water resources, in particular artisanal mining and forestry resources;
Sections 11.1 to 11.8.
Cohabitation with the heavy vehicles, accessibility issue to Wayako valley;
Section 11.13.
In-migration and the impact on host villages (safety, public health, access to infrastructure and services);
Section 11.11.
Public health and safety (road safety, sexually transmitted diseases);
Sections 11.12 and 11.13.
Access to employment opportunities; Section 11.1 and Local Economic Participation Plan (Volume D).
Livestock health and access to pasture; Section 11.3.
Cultural heritage.
Sections 11.9 and 11.10.
Table 14-7: Summary of Concerns from the Youth’s Focus Groups (February – March 2015) and where each of
these issues have been addressed in the ESIA
Village Youth’s Consultation Outcomes ESIA Section
Reference
Tambanoumouya,
Linguekoto,
Niemenike and
Mako
Compensation for impacts to livelihood, land and water resources (agro-pastoral activities, artisanal mining, forestry resources);
Sections 11.1 to 11.8.
Livestock health and access to pasture; Section 11.3.
Public health and safety (road safety, air quality, noise); Sections 11.12 and 11.13.
Access to employment opportunities; Section 11.1 and Local Economic Participation Plan (Volume D).
Youth training; Section 11.1 and Local Economic Participation Plan (Volume D).
In-migration and the impact on host villages (safety, public health, access to infrastructure and services).
Section 11.11.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-16
Table 14-8: Summary of consultation outcomes from regional and national agencies (April – May 2015) and
where each of these issues have been addressed in the ESIA
Authority/
Agency
Issues / Recommendations ESIA Section
Reference
Prefet de
Kedougou
Informed consultation with Administrative authorities; Sections 14.4 to 14.8.
Consider the establishment of an artisanal mining corridor to improve coexistence with artisanal miners;
Section 11.5.
Respect management commitments; Section 15.2.
Improve access to community infrastructure and services. Sections 11.1, 11.11 and 11.12.
Conseil
Departemental
de Kedougou
Support skill development programmes for local youth; Section 11.1 and Local Economic Participation Plan (Volume D).
Improve access to community infrastructure and services; Sections 11.1, 11.11 and 11.12.
Respect management commitments. Section 15.2.
Brigade Puits et
Forages de
Kedougou
Improve access to community infrastructure and services (Mako village has a significant deficit in the availability of potable water);
Sections 11.1, 11.11 and 11.12.
Strengthen the capacity of community water management committees;
Section 11.7.
Service
Regional
d’Appui au
developpement
local
Informed consultation and participation of government agencies; Sections 14.4 to 14.8.
Support the Tomboronkoto Council with the elaboration of the Commune Development Plan;
Sections 11.1 and 11.11.
Respect management commitments.
Section 15.2
Sapeurs
pompiers
Public safety (transport of hazardous materials and bushfires).
Sections 11.12 and 11.13.
Conseil
Municipal de
Tomboronkoto
Respect management commitments in Operation and post-Closure phases;
Section 15.2.
Support the Tomboronkoto Council with the elaboration of the Commune Development Plan;
Sections 11.1 and 11.11.
Improve access to community infrastructure and services.
Sections 11.1, 11.11 and 11.12.
IREF de
Kedougou
Under the biodiversity offset programme, consider the broader area including the ZIC (Zone d’Intérêt Cynégétique);
ESIA Section 10.2.2 and 10.3.2. In addition, the biodiversity offsets programme has considered the broader area, including areas currently impacted by poaching, to develop and implement offsets that will achieve no net loss on biodiversity. The cultural value and use associated with biodiversity by the community is addressed in the Livelihood Restoration Plan (Volume D).
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-17
Authority/
Agency
Issues / Recommendations ESIA Section
Reference
Develop research programs in preparation for the rehabilitation phase.
Rehabilitation and Conceptual Mine Closure Plan (Volume E), Sections 4.2 and 6.3.
Service
Regional Mines
et Geologie
Consider the establishment of an artisanal mining corridor to improve coexistence with artisanal miners;
Section 11.5.
Support artisanal miners, especially women, to comply with national regulations.
Sections 11.5 and 11.14 as well as the Livelihood Restoration Plan (Volume D).
DREEC de
Kedougou
Provide technical documents with details on design and construction standards;
Key technical details on design and construction standards are provided in Sections 4.1 to 4.5.
Respect the regulatory requirements for classified installations; Sections 4.1 to 4.5 and Risk Assessment (Volume B).
Evaluate the capability of the Regional Environmental Monitoring Committee and strengthen the capacity of this institution as appropriate.
Section 15.2.4.
Service
Regional
Securité Sociale
et Travail de
Kedougou
Provide a detailed breakdown of job opportunities and recruitment planning during different phases of the development of the Project.
Sections 4.1 to 4.5.
Service
Regional
Elevage de
Kedougou
Under the livelihood restoration programme, integrated agriculture and livestock management is considered a favourable activity.
Livelihood Restoration Plan (Volume D), Section 6.
Direction
Regionale du
Développement
Rural (DRDR)
Under the livelihood restoration programme, market gardening is considered a favourable activity;
Livelihood Restoration Plan (Volume D), Section 11.2.
Support skill development programmes for local youth.
Section 11.1 and Local Economic Participation Plan (Volume D).
Gendarmerie Government is planning to strengthen public security through the establishment of a Gendarmerie post in Mako village;
Noted.
Consider the establishment of an artisanal mining corridor to improve coexistence with artisanal miners.
Section 11.5.
Service
Regional Action
Sociale
Develop a good communication system with local populations; Chapter 14 and Stakeholder Engagement Plan (Volume C).
Support local health authorities with the implementation of their public health programs in the Project area;
Sections 11.11 and 11.12.
Take into account vulnerable groups as part of the Company’s social activities.
Section 11.15.
Support local health authorities with the implementation of their public health programmes in the Project area;
Sections 11.11 and 11.12.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-18
Authority/
Agency
Issues / Recommendations ESIA Section
Reference
Service
Regional de la
Santé
Target women in the implementation of public health programmes.
Sections 11.12 and 11.14.
Sous-Prefet de
Bandafassi
Prepare local populations for the potential impacts of in-migration; Section 11.11.
Respect the administrative process for the occupation of land by Project infrastructure.
Section 11.4.
Service
Régional
Hydrologie de
Tambacounda
Informed consultation and participation of technical agencies in work programme.
Sections 14.5 to 14.11.
Service
Régional
Hygiène de
Tambacounda
The Hygiene Services have to the authority to monitor drinking water quality provided by the Company to Project personnel;
Noted.
Informed consultation and participation of technical agencies in work programme;
Sections 14.5 to 14.11.
Strengthen the capacity of the Commune of Tomboronkoto to manage solid waste.
Section 11.11.
Service
Régional de
l’Hydraulique de
Tambacounda
Support the operation of the Regional Environmental Monitoring Committee and strengthen the capacity of this institution as appropriate;
Section 15.2.4.
Respect all regulatory requirements concerning the use of water resources by the Company.
Section 3.3.1.
Service
Régionale du
Parc National du
Niokolo-Koba
Avoid negative impacts on the Gambia River and the NKNP Biodiversity Action Plan (Volume C).
Collaborate with the NKNP Monitoring Division on biodiversity monitoring in the NKNP ;
Biodiversity Action Plan (Volume C).
Respect management commitments as presented in the ESMMP; Section 15.2.
Allocate appropriate resources to rehabilitation of the Project area.
Rehabilitation and Conceptual Mine Closure Plan (Volume E).
IUCN Support the government of Senegal with the provision of the Project ESIA report;
ESIA Study Report (Volume A).
Specifically assess the impacts of the Project on the Gambia River, chimpanzee habitat and gallery forest;
Sections 10.1 to 10.4
Ensure that the Project is compliant with IUCN guidelines on development adjacent to World Heritage site;
Biodiversity Action Plan (Volume C).
Any activities within the NKNP should be consistent with the recommendations of the UNESCO World Heritage Committee.
Biodiversity Action Plan (Volume C).
Direction de la
Gestion et de la
Planification des
Ressources en
Eau
Share all water monitoring data with the DGPRE; Section 15.2.5.
Request the Company to collaborate with the DGPRE on the monitoring of water resources.
Sections 15.2.5 and 15.3.
Direction des
Parcs Nationaux
Consider the potential impacts of Project induced in-migration on the incidence of poaching;
Sections 10.2 and 11.6.
Consider cumulative impacts of the Project with others development in the region;
Chapter 13.
Assess the impacts of the Project on terrestrial and aquatic ecology, and propose management and mitigation measures.
Sections 10.1 to 10.4.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-19
Authority/
Agency
Issues / Recommendations ESIA Section
Reference
Direction des
Eaux et For ts ;
Chasse et
Conservation
des Sols
Informed consultation and participation of government technical agencies, especially concerning the conservation of threatened species;
Biodiversity Action Plan (Volume C).
Consider measures to protect biodiversity values in areas outside of the NKNP.
Biodiversity Action Plan (Volume C).
Direction de la
Protection Civile
Appropriately mitigate the risks to public safety; Sections 11.12 and 11.13.
Prepare an emergency response plan for the Project.
Sections 11.12 and 11.13 (and provided in ESMMP, Volume C, and EDD, Volume B).
Table 14-9: Summary of concerns expressed during the Public Audience (21 November 2015) and where each of
these issues have been addressed in the ESIA
Village Public Audience Outcomes ESIA Section
Reference
Tambanoumouya,
Linguékoto,
Niéméniké, Mako,
Dalakoy,
Kérékonko,
Bomboya,
Soukouta, Badian
I, Badian II, Badon-
Sibikiling, Sénodji,
Saint-Étienne –
Niarikondo, and
Laminia –
Sindakha
Compensation for impacts to livelihood, land and water resources Sections 11.2 to 11.8 and Livelihood Restoration Plan (Volume D).
Pollution of water resources including the Gambia River Section 11.7.
In-migration and the impact on host villages (safety, access to local resources including water and forestry products)
Section 11.11
Access to employment opportunities Section 11.1 and Local Economic Participation Plan (Volume D).
Youth training Section 11.1 and Local Economic Participation Plan (Volume D).
Income generating activities Section 11.14 and Local Economic Participation Plan (Volume D).
Land rehabilitation following closure of the mine Section 11.4 and Rehabilitation and Conceptual Mine Closure Plan (Volume E).
Ensure that standards are followed by Project Contractors Ch. 9 – 12.
Improve access to community infrastructure and services Sections 11.1, 11.11 and 11.12.
14.9 Continuing Consultation for completion of the ESIA
The preliminary stakeholder engagement program to be undertaken for completion of the ESIA and in
preparation for the commencement of Project Construction is presented in Table 14-9. This includes the
establishment of stakeholder engagement tools and direct engagement activities.
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-20
Engagement processes are by their nature unpredictable, and so the program outlined below is a tentative
proposal for discussion with those affected, and therefore aspirational and subject to change.
Table 14-10: Preliminary Stakeholder Engagement Program
Objective / Activity Key Steps
Ensure that social and
environmental standards and
guidelines are followed by Project
Contractors
Develop social and environmental standards and guidelines for Project
Contractors
Detail stakeholder engagement requirements for Contractors
Ensure requirements are included in every Project contract
Monitor compliance
Put in place a consultation
database
Finalize engagement tools – what will be inputted into the database? How
will this information be collected?
Identify user requirements – who will use it? How?
Record all interactions with stakeholders
Monitor and maintain database – on-going
Set up the grievance management
system
Review grievance system structure
Advertise the system
Establish grievance register
Set up grievance system to receive and addresses concerns raised by
stakeholders
Set up Commitment Registry Review all Project social and environmental commitments, timeframe,
responsible, and cost as defined in the ESIA
Establish a simplified commitment registry
Recruit additional staff (pending
Project status)
Vulnerable Persons Officer / Grievance Management Officer
Procurement / Human resource outreach people
Other staff as needed
Disclosure of Permit Status Disclosure of permit approval – Regional, Commune, and village level
Formalise engagement with
Conseil Municipale and Groupe de
Contact
Reformulate the Stakeholder Engagement Structure at the Conseil
Municipale and Groupe de Contact
Validate through village Focus Group Discussions
Formalise Local Employment
Thematic Working Group (TWG)
Establish TWG – to meet on a quarterly basis.
Review Local Economic Participation Plan
Develop minimum requirements for recruitment and pre-employment
training
Build recruitment database
Hold discussions on local employment and provide an update on the
recruitment process and related skill requirement
Engage agency to implement recruitment process
Formalise Local Procurement
Thematic Working Group (TWG)
Establish TWG – to meet on a quarterly basis.
Review Local Economic Participation Plan
Determine minimum requirements for procurement
Develop registration and administrative process for procurement
Develop Local Supplier Database
Hold discussions on local procurement and provide an update on the
procurement process, requirements and provide trainings and guidelines
Formalise the Biodiversity
Thematic Working Group (TWG)
Establish TWG – to meet on a quarterly basis
Review Biodiversity Action Plan
Confirm the technical and social feasibility of the proposed biodiversity
offset sites
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-21
Objective / Activity Key Steps
Identify implementation activities to support the biodiversity offset
program
Formalise the Land Acquisition
and Livelihoods Restoration
Thematic Working Group (TWG)
Establish TWG – to meet on a monthly basis
Begin formal discussions on land acquisition and mitigation measures
Formal registration of land, assets and livelihoods
Prepare collective and individual agreements for the restoration of impacts
Finalise the Livelihood Restoration Plan
Commune Development Plan
(PDC)
In consultation with the Commune Council, confirm the process and
schedule for preparation of the PDC, and the scope of the Company’s
participation.
Mobilise technical and financial assistance to support the preparation of the
PDC, as agreed with the Commune Council.
Provide input to the preparation for the PDC as appropriate.
14.10 Grievance Management
The Company currently maintains a simplified grievance mechanism to support Project exploration activities.
The informal resolution process involves the Mako Exploration Camp Manager, village and commune-level
leaders, and the sous-prefet where necessary.
The Company will develop a Grievance Mechanism, adapted from the IFC’s Guide to Designing and
Implementing Grievance Mechanisms (2008).
A Grievance Mechanism receives and addresses concerns raised by stakeholders in a transparent, constructive,
timely, confidential (if desired), culturally appropriate and accessible manner.
This Grievance Management System will comprise four basic mechanisms:
First Order Mechanism:
Informal resolution process;
Stakeholder concerns discussed with Company representatives;
Questions and concerns likely to be resolved within these informal interactions.
Second Order Mechanism:
Formal management of difficult and/or written grievances by the Grievance Management
Officer through the following stages – Registration, Reporting, Validation, Investigation, and
Resolution.
Third Order Mechanism:
Presentation of grievances to a multi-stakeholder forum for example a Consultation
Committee (Groupe de Contact) with the involvement of the Sous-prefecture for discussion
and resolution;
Forum will serve as an important and trusted arbiter in complicated grievances;
Minutes and a written report will be provided to the complainant.
Fourth Order Mechanism:
Involves the formal judicial system;
Mako Gold Project
Environmental and Social Impact Assessment
FINAL 14-22
The Company will inform those who prefer litigation of their rights, entitlements and the
existence of any legal aid.
The Grievance mechanism is further detailed in the Stakeholder Engagement Plan (Volume C).
14.11 Stakeholder Involvement in Project Monitoring
The Project will require coordination with a number of institutional structures at all levels of Government. The
Company will work with the existing Regional Environmental Monitoring Committee (Comité Régional de Suivi
Environnemental et Social, CRSE) to enable the Government of Senegal to conduct independent monitoring of
the Project. The CRSE will be used to monitor current and future Company’s activity within the Kedougou
Region across the construction, operations and closure phases of the Mako Gold Project.
14.12 Reporting to Stakeholders
The Company will report regularly on the environmental and social performance of the Project to stakeholders.
The Company will prepare a quarterly operations report to summarise its environmental and social
performance and significant activities, incidents and events for that report. The report will include a summary
of stakeholder engagement activities and key indicators and will be submitted to the relevant Senegalese
authorities. The Company will also prepare an Annual Sustainability Report to summarise stakeholder
engagement activities, business and sustainability performance for each calendar year, which will be made
available to stakeholders.
Reporting practices are further detailed in the ESMMP and the Stakeholder Engagement Plan (Volume C).