Chapter 10Project Cash Flows and Risk
1
![Page 2: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/2.jpg)
2
Learning OutcomesChapter 10
Describe the relevant cash flows that must be forecast to make informed capital budgeting decisions.
Identify the relevant cash flows and perform a capital budgeting analysis for: (a) an expansion project and (b) a replacement project
Describe how the riskiness of a capital budgeting project is evaluated and how the results are incorporated in capital budgeting decisions.
Describe how capital budgeting decisions differ for firms that have foreign operations and for firms that only have domestic operations
![Page 3: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/3.jpg)
3
Cash Flow Estimation
Most important and most difficult step in the analysis of a capital project
Financial staff’s role includes:Coordinating other departments’ effortsEnsuring that everyone uses the same set
of economic assumptionsMaking sure that no biases are inherent in
forecasts
![Page 4: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/4.jpg)
4
Relevant Cash Flows
Cash Flow Versus Accounting Income
Incremental Cash Flows
![Page 5: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/5.jpg)
5
Unilate’s Accounting Profits Versus Cash Flows ($ thousands)
![Page 6: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/6.jpg)
6
Unilate’s Accounting Profits Versus Cash Flows
![Page 7: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/7.jpg)
7
Incremental Cash Flows
An Incremental Cash Flow is the change
in a firm’s net cash flow attributable to an investment project.
![Page 8: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/8.jpg)
8
Problems in Determining Incremental Cash Flows
Sunk Cost: A cash outlay that already has been incurred and cannot be recovered
Opportunity Cost: The return on the best alternative use of an asset
Externalities: The effect of accepting a project on the cash flows in other parts of the firm
Shipping and Installation Costs Inflation
![Page 9: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/9.jpg)
9
Identifying Incremental Cash Flows
Initial Investment Outlay: the incremental cash flows associated with a project that will occur only at the start of a project’s life
Incremental Operating Cash Flow: the changes in day-to-day cash flows that result from the purchase of a capital project and continue until the firm disposes of the asset
Terminal Cash Flow: the net cash flows that occur only at the end of a project’s life
![Page 10: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/10.jpg)
10
Incremental Operating Cash Flow
![Page 11: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/11.jpg)
11
Capital Budgeting Project Evaluation
Expansion Project: A project that is intended to increase sales; provides growth to the firm
Replacement Analysis: An analysis involving the decision of whether to replace an existing, still productive asset with a new asset
![Page 12: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/12.jpg)
12
Expansion Project Analysis of the Cash Flows
Initial Investment Outlay Cost of new asset $( 9,500) Shipping and installation ( 500) Increase in net working capital ( 4,000) Initial investment $(14,000)
![Page 13: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/13.jpg)
13
Expansion Project Analysis of the Cash Flows
![Page 14: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/14.jpg)
14
Expansion Project Net Salvage Value
![Page 15: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/15.jpg)
15
Expansion Project Analysis of the Cash Flows
![Page 16: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/16.jpg)
Expansion Project Cash Flow Time Line
16
![Page 17: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/17.jpg)
17
Replacement Project Analysis of the Cash Flows
![Page 18: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/18.jpg)
18
Replacement Project Cash Flow Time Line
![Page 19: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/19.jpg)
19
Incorporating Risk in Capital Budgeting Analysis
Stand-Alone Risk: the risk an asset would have if it were a firm’s only riskMeasured by the variability of the asset’s expected
returns Corporate (Within-Firm) Risk: risk not
considering the effects of stockholder’s diversificationMeasured by a project’s effect on the firm’s earnings
variability Beta (Market) Risk: part of a project’s risk that
cannot be eliminated by diversificationMeasured by the project’s beta coefficient
![Page 20: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/20.jpg)
20
Techniques for Measuring Stand-Alone Risk
Sensitivity Analysis: Key variables are changed and the resulting changes in the NPV and the IRR are observed.
Scenario Analysis: “Bad” and “good” sets of financial circumstances are compared with the most likely situation.
Monte Carlo Simulation: Probable future events are simulated on a computer.
![Page 21: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/21.jpg)
21
Sensitivity Analysis Graph
![Page 22: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/22.jpg)
22
Scenario Analysis
A risk analysis technique in which “bad” and “good” sets of financial circumstances are compared with a most likely, or base case, situation.
![Page 23: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/23.jpg)
23
Scenario Analysis
![Page 24: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/24.jpg)
24
Monte Carlo Simulation
A risk analysis technique in which probable future events are simulated on a computer, generating a probability distribution that indicates the most likely outcomes.
![Page 25: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/25.jpg)
25
Advantages/Disadvantages of Simulation Analysis
AdvantagesReflects probability of each inputShows range of NPVs, expected NPV, σNPV,
and CVNPV Disadvantages
Difficult to specify probability distributions and correlation
If inputs are bad, output will be bad: GIGO = Garbage In, Garbage Out!
![Page 26: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/26.jpg)
26
Corporate (Within-Firm) Risk
Risk that does not take into consideration the effects of stockholders’ diversification, it is measured by a project’s effect on the firm’s earnings variability.
![Page 27: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/27.jpg)
27
Beta (or Market) Risk and Required Rate of Return for a Project
Security Market Line equation:
rS = rRF + (rM - rRF)βS
Erie Steel is all equity financed, so cost of equity is also its averaged required rate of return, or cost of capital.
Erie’s β = 1.1; rRF = 8%; and rM = 12%
rS = 8% + (12% - 8%)1.1 = 12.4%
= Erie’s cost of equity Investors should be willing to give Erie money to
invest in average-risk projects.
![Page 28: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/28.jpg)
28
Required Rate of Return for a Project
rproj = the risk-adjusted required rate of
return for an individual project
rproj = rRF + (rM - rRF)proj
![Page 29: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/29.jpg)
29
Measuring Beta Risk for a Project
Pure Play Method: 1. Identify companies whose only business is
the project in question.
2. Determine the beta for each company.
3. Average the betas to find an approximation of proposed project’s beta.
![Page 30: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/30.jpg)
30
How Project Risk Is Considered in Capital Budgeting Decisions
Most firms use: Risk-Adjusted Discount Rate
Discount rate that applies to particularly risky stream of income
It is equal to the risk-free rate of interest plus a risk premium.
![Page 31: Chapter 10 Project Cash Flows and Risk 1. Learning Outcomes Chapter 10 Describe the relevant cash flows that must be forecast to make informed capital](https://reader035.vdocuments.mx/reader035/viewer/2022062318/5519cb7755034649768b46e8/html5/thumbnails/31.jpg)
31
Multinational Capital Budgeting Repatriation of Earnings: The process of
sending cash flows from a foreign subsidiary back to the parent company
Exchange Risk Rate: The uncertainty associated with the price at which the currency from one country can be converted into the currency of another country
Political Risk: The risk of seizure of a foreign subsidiary’s assets by the host country or unanticipated restrictions on cash flows to the parent company