chapter 1: introduction - nhai.org.innhai.org.in/spw/agreement/contract agrement part-1.pdf ·...
TRANSCRIPT
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-1
Feasibility Report
CHAPTER 1: INTRODUCTION
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-2
Feasibility Report
CHAPTER 1: INTRODUCTION
TABLE OF CONTENTS 1.1 Project Background……………………………………………………….. 1-1 1.2 Objectives of Consultancy Services………………………………………. 1-2 1.3 Scope of Consultancy Services…………………………………………… 1-3 1.4 The Project Highway……………………………………………………… 1-3 1.5 Progress Achieved………………………………………………………… 1-4 1.6 Offices…………………………………………………………………….. 1-5 1.7 Purpose and Contents of this Report…………………………………….... 1-6 1.7.1 Purpose of this Report…………………………………………….. 1-6 1.7.2 The Draft Feasibility Report………………………………………. 1-7 1.7.3 Contents of this Report……………………………………………. 1-7
LIST OF FIGURES Figure 1.1 Index Map of Project Highway………………………………….. 1-4
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-3
Feasibility Report
CHAPTER 1
INTRODUCTION
1.1 Project Background
Government of India has approved to convert 6500 km of existing 4-lane National
Highways into six lane National Highways under a separate phase namely Phase-V of
National Highway Development project (NHDP). The six laning of existing four lane
National Highways sections are to be executed through Public Private Partnership (PPP)
on Build, Operate and transfer (BOT) basis, following Design-Build-Finance-Operate
(DBFO) pattern. Sections envisaged under six laning comprise the Golden Quadrilateral
(5,700 km) and some other sections of 800 km in length.
The National Highways Authority of India has been entrusted with the development,
maintenance and management of such of the National Highways as entrusted to it by the
Government of India. The NHDP Phase-V has also been entrusted to National Highways
Authority of India.
The six laning of the projects has essentially been conceived as a retrofitting job on
existing four lane National Highways causing minimum possible inconvenience to the
traffic. It should be planned in such a way that improved highway is safe, efficient and
convenient to the users as well as public living adjacent to the highway. At present
NHAI is collecting toll on the four lanes completed sections, which would be continued
till the appointed date. Thereafter, the Concessionaire would be entitled to collect toll.
The main feature of the NHDP Phase-V is that the Concessionaire would be entitled to
collect toll even during the construction period.
The Belgaum-Dharwad 80 km long section of National Highway No. 4, which falls in the
Mumbai-Chennai arm of Golden Quadrilateral and has been widened to 4-lanes recently,
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-4
Feasibility Report
is also proposed to be included for 6-laning project under NHDP V. The intention of this
specific consultancy project is to study and report on the feasibility of retrofitting the
existing NH-4 from Belgaum to Dharwad in the State of Karnataka from its existing
situation (4 lane highway) to 6-lane highway.
The Feasibility Reports thus prepared contain, inter alia, the scheme and lay out of the
development of the highway and the project facilities, and costing. The report will form
the basis on which a Financial Consultant and a legal consultant, appointed separately,
will prepare an RFP document for inviting bids from private entrepreneurs to award a
BOT (Toll) concession. The concession will be on DBFO pattern, wherein the
concessionaire shall, in accordance with a model concession agreement approved by the
Government, take full responsibility to carryout the detailed design, construction,
maintenance and operation of the project highway and the project facilities conforming to
the standards specified in the said agreement. He will eventually transfer the project to
NHAI after expiry of the concession period in a state as specified in the concession
agreement. The Feasibility Report is to provide all the technical details, based on which
realistic bids are received from the prospective bidders.
1.2 Objectives of Consultancy Services
Objectives of the consultancy services are to prepare a proposal to retrofit a six-lane
cross-section on to the existing 4-lane highway in a manner which ensures,
(i) Enhanced safety of the traffic, the road users and the people living close to the
highway;
(ii) Enhanced operational efficiency of the highway;
(iii) Fulfillment of the access needs of the local population;
(iv) Minimal adverse impact on the road users and the local population due to
construction;
(v) Feasible and constructible options for the project with least cost options.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-5
Feasibility Report
1.3 Scope of Consultancy Services
The scope of Consultancy Services comprises of preparation of Feasibility Study Report
for converting the existing 4-lane highway to 6-lane standards, conforming to the Manual
for specification and standards for 6-lane National Highways of the Ministry of Shipping
Road Transport and Highways. In addition to above, the consultant is required to prepare
Technical Schedules and provide assistance to NHAI in bidding process.
In addition to above, contract documents, and preliminary cost estimates for the works
are also to be prepared by the Consultant in a form, which allows the construction and the
rehabilitation works to be carried out on BOT basis.
1.4 The Project Highway
The Project Highway is Belgaum-Dharwad Section of NH–4 (79.355 km long
approximately). An Index /Location map of the Project Highway is given in Figure 1.1.
The start of Project Highway would be km 515 and the end point of the Project Highway
would be km 433 (junction of NH-4 and Hubli-Dharwad bypass). The details of the
existing project highway are given in Chapter 2.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-6
Feasibility Report
1.5 Progress achieved
The Consultant has established a project office at Dharwad for the duration of this
project. The office accommodates some of the key and support personnel. All the Key
personnel were mobilized. Support personnel have been utilized from the regular staff
available at the Head office and Delhi office. The Team members have visited the site as
and when required, collected relevant available data from the NHAI and Supervision
Consultants, conducted field surveys and investigations, and met concerned officers of
NHAI and the Supervision Consultants.
The Consultants submitted the Inception Report on 11.11.2007. The Inception Report
indicated the methodology the Consultant proposed to follow to complete the job. It also
brought out the data on existing road and some of the field surveys conducted. Thereafter
the strip plans were prepared and submitted to NHAI on 11.01.2008. The proposal for
widening of the project road for the existing 4- lane was also prepared. The proposal was
Figure 1.1: Index Map of Project Highway
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-7
Feasibility Report
presented at NHAI on 9th February 2008, in a meeting chaired by the Member
(Technical). The suggestions made in the meeting on the widening proposal have been
duly considered and incorporated.
Thereafter, we had public consultations to ascertain their requirements. The Draft
Feasibility Report was submitted on 3rd April, 2008. A presentation on the report was
made at NHAI on 1st July, 2008 in a meeting chaired by the Member (Technical). In the
meeting, two suggestions made were for 7.0 m width of service road and 20 m span for
additional vehicular underpasses. The prestent submission is the Final Feasibility Report.
The report highlights the various surveys conducted in the field and their analysis. The
suggestions made by NHAI officials and representatives of affected towns / villages have
been duly considered in making the widening proposal presented in this report.
1.6 Offices:
The head office of the Consultant is located as under:
M/s. Consulting Engineers Group Limited (CEG)
E-12, Moji Colony, Malviya Nagar,
Jaipur – 302017
Tel: +91-141-2520899; 2521899; 2520556; 2520526
Fax: +91-141-2521348
Email: [email protected]; [email protected]
URL: www.cegindia.com
The site office has been established at Dharwad and is located as under:
H.No.: 313, 2nd Main,
1st cross, Narayanpur,
Dharwad – 580008
Tel. No: +91-0836-2748929
Fax No: +91-0836-2748939
Contact Person: Mr. Vivek Naidu, Project Co-ordinator (Mobile No: 9341054393)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-8
Feasibility Report
With a view to have close interaction with NHAI HQ, CEG have also established their
office at New Delhi as under:
208, DDA Local Shopping Complex
H Block, Vikas Puri
New Delhi 110018
Tel: +91 11 2854 2899, 2854 1403
Fax: +91 11 2854 1404
Email: [email protected]
Contact Person: Dr. V.K.Sood, Vice President (Mobile: 9871080538)
Email: [email protected]
1.7 Purpose and Contents of this Report
1.7.1 Purpose of this Report
As per Contract the following reports and documents are to be submitted by
the Consultants to NHAI
Inception Report: This shall give the details of the work plan, methodology, task
assignment and scheduled completion of various activities (already submitted).
Strip Plans with alternatives (already submitted).
Draft Feasibility Report
Final Feasibility Report
Technical Schedules (A to D)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-9
Feasibility Report
1.7.2 The Draft Feasibility Report
This report contain, inter alia, the details of field studies conducted, analysis made, data
collected, scheme for widening, proposed design standards, and preliminary cost
estimates for discussion with NHAI.
1.7.3 Contents of this Report
1. Introduction
2. Existing Features of the Project Highway
3. Engineering Surveys and Investigation
4. Traffic Studies and Analysis
5. Pavement Evaluation and Preliminary design
6. Condition Survey and analysis of Structures
7. Project Facilities
8. Design Standards
9. Proposals for Widening and Retrofitting
10. Environment & Social Impact Assessment
11. Estimate of Quantities and Costs
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-10
Feasibility Report
CHAPTER 2: EXISTING FEATURES OF
THE PROJECT HIGHWAY
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-11
Feasibility Report
CHAPTER 2: EXISTING FEATURES OF THE PROJECT HIGHWAY
TABLE OF CONTENTS
2.1 Profile of Karnataka State………………………………………………... 2-1 2.2 Climate…………………………………………………………………… 2-2 2.3 Geography and Terrain…………………………………………………... 2-2 2.4 Soil Type…………………………………………………………………. 2-2 2.5 Land Use…………………………………………………………………. 2-2 2.6 Project Highway…………………………………………………………. 2-4 2.7 Development/Up-Gradation History…………………………………….. 2-4 2.8 Topography ……………………………………………………………… 2-5 2.9 Alignment………………………………………………………………… 2-5 2.10 Settlements/Built Up Sections…………………………………………… 2-5 2.11 Bypasses…………………………………………………………………... 2-8 2.12 Right of Way……………………………………………………………… 2-8 2.13 Service Roads…………………………………………………………….. 2-12 2.14 Carriageway, shoulder and median……………………………………... 2-13 2.15 Pavement Type and Condition……………………………………………. 2-15 2.16 Bridges and Culverts and other stretches…………………………………. 2-18 2.17 Rail-Road Structures……………………………………………………… 2-18 2.18 Junctions and Intersections……………………………………………….. 2-18 2.19 Grade Separated Structures………………………………………………. 2-19 2.20 Connection with Project Highway………………………………………... 2-20 2.21 Wayside Amenities……………………………………………………... 2-22 2.22 Utilities……………………………………………………………………. 2-33 2.23 Typical Cross Sections of existing 4 lane highway………………………. 2-34 2.24 Current Traffic……………………………………………………………. 2-46 2.25 Accidents and Safety……………………………………………………... 2-47
LIST OF TABLES
Table 2.1 (a) Design Chainage and Corresponding Chainage as per km stones 2-6 Table 2.1 (b) Design Chainage and Corresponding Chainage as per km stones 2-7 Table 2.2 Major Settlements/Built Up Sections……………………………. 2-7 Table 2.3 Existing Right of Way Details…………………………………... 2-8 Table 2.4 Details of Existing Service Roads……………………………….. 2-12 Table 2.5 Details of Existing 6 lane carriageway stretches………………… 2-14 Table 2.6 Details of Pavement (Left Hand Side)…………………………... 2-16 Table 2.7 Detail of Pavement (Right Hand Side)………………………… 2-17 Table 2.8 Details of Bridges and Culverts…………………………………. 2-18 Table 2.9 List of At Grade Junctions………………………………………. 2-19 Table 2.10 Details of Grade Separated Structures…………………………... 2-19 Table 2.11 Location and Type of Connection on LHS……………………… 2-20 Table 2.12 Location and Type of Connection on RHS……………………… 2-21
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-12
Feasibility Report
Table 2.13 Existing Way Side Amenities…………………………………… 2-22 Table 2.14 (a) Inventory of Existing Signages………………………………….. 2-24 Table 2.14 (b) Inventory of Existing Signages………………………………….. 2-29 Table 2.15 Traffic Count November-December 2005………………………. 2-46 Table 2.16 Traffic Count December 2007-January 2008……………………. 2-46 Table 2.17 Traffic Count December 2007-January 2008……………………. 2-47
LIST OF FIGURES
Figure 2.1 National Highway Network Karnataka State……………………. 2-3 Figure 2.2 Typical Highway Cross Section in Fill (with overlay and new flexible
pavement)…………………………………………………………….. 2-35
Figure 2.3 Typical Highway Cross Section in Cut (with proposed new flexible pavement)……………………………………………………………
2-35
Figure 2.4 Typical Highway Cross Section in Fill (with total new flexible pavement)…………………………………………………………….
2-36
Figure 2.5 Typical Highway Cross Section in Fill (with total overlay)…………. 2-36 Figure 2.6 Typical 6 Lane Carriageway Cross Section in Fill (with total new
flexible pavement)……………………………………………………. 2-37
Figure 2.7 Typical Highway Cross Section in Fill (with overlay and new flexible pavement over existing shoulder)…………………………………….
2-37
Figure 2.8 Typical 6 Lane Carriageway Cross Section in Fill (with total new rigid pavement)…………………………………………………..................
2-38
Figure 2.9 Typical 6 Lane Carriageway Cross Section in Cut (with total new rigid pavement)…………………………………………………........
2-38
Figure 2.10 4-Lane Carriageway in CH. 0.000 to 500.000 Package-II …………. 2-39 Figure 2.11 4-Lane Carriageway in CH. 500.000 to 2800.000 Package-II ……… 2-39 Figure 2.12 4-Lane Carriageway in CH. 2800.000 to 3600.000 Package-II ……. 2-40 Figure 2.13 4-Lane Carriageway in CH. 3600.000 to 5200.000 Package-II …….. 2-40 Figure 2.14 4-Lane Carriageway in CH. 6000.000 to 6910.000 Package-II …….. 2-41 Figure 2.15 4-Lane Carriageway in CH. 6910.000 to 9300.000 Package-II ………. 2-41 Figure 2.16 4-Lane Carriageway in CH. 12100.000 to 14450.000 Package-II …… 2-42 Figure 2.17 4-Lane Carriageway in CH. 14450.000 to 15900.000 Package-II ….. 2-42
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-13
Feasibility Report
CHAPTER 2
EXISTING FEATURES OF THE PROJECT HIGHWAY
2.1 Profile of Karnataka State
Karnataka is a State in the southern part of India. It was created on November 1, 1956,
with the passing of the States Reorganization Act. Originally known as the State of
Mysore, it was renamed Karnataka in 1973.
Karnataka is bordered by the Arabian Sea to the west, Goa to the northwest, Maharashtra
to the north, Andhra Pradesh to the east, Tamil Nadu to the southeast, and Kerala to the
southwest.
Karnataka has a total land area of 1, 91,791 sq. km and accounts for 5.83% of the total
area of the country (measured at 3,288,000 sq. km). This puts it in eighth place in terms
of size.
About 38,724 sq. km of Karnataka (i.e. 20% of the state's geographic area) is covered by
forests. The forests are classified as reserved, protected, village and private forests. The
percentage of forested area is slightly less than the all-India average of about 23%, and
significantly less than the 33% prescribed in the National Forest Policy.
There are 29 districts in Karnataka. Each district is governed by a District Commissioner
or District Magistrate. The districts are further divided into sub-divisions, which are
governed by sub-divisional magistrates. Sub-divisions comprise blocks containing
Panchayat (village councils) and town municipalities.
According to the 2001 census of India, the total population of Karnataka is 52,850,562, of
which 26,898,918 (50.89%) are male and 25,951,644 (49.11%) are female, or 1000 males
for every 964 females. This represents a 17.25% increase over the population in 1991.
The population density is 275.6 per sq. km and 33.98% of the people live in urban areas.
The literacy rate is 66.6% with 76.1% of males and 56.9% of females being literate. It
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-14
Feasibility Report
occupies ninth place in terms of population. The population density which stands at 275
persons per sq. km is considerably lower than the all-India average of 324.
Karnataka has a railway network with a total length of approximately 3,089 kilometers.
Karnataka has one major port, the New Mangalore Port, and ten other minor ports. The
total lengths of National Highways and State Highways in Karnataka are
3,973 kilometers and 9,829 kilometers, respectively. A map showing the National
Highways in Karnataka State is given in Figure. 2.1.
2.2. Climate
Karnataka experiences four reasons. The winter in January and February is followed
by summer between March and May, the monsoon between June and September, and
the post – monsoon season from October till December.
2.3. Geography and Terrain
The Project Highway traverses through two districts viz. Dharwad and Belgaum.
Belgaum is located at 15.87° N and 74.5° E. It has average elevation of 751 meters
above sea level. The Project Highway passes through plain and rolling terrain in most of
its length. However, it traverses through hilly terrain in some stretches.
2.4. Soil Type
The Project Highway, in general, traverses through predominantly moorum type of soil,
formed by weathering action of the rock.
2.5. Land Use
While the predominant land use between Dharwad and Belgaum is agriculture, the
industrialization and urbanization are increasing at Dharwad and Belgaum ends.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-15
Feasibility Report
Figure 2.1 National Highway Network Karnataka State
sssssssssssssssssssssssssssssssssssssss
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-16
Feasibility Report
2.6 Project Highway
The National Highway No. 4 runs between Chennai and Mumbai. In the Chennai-
Bangalore section km 0.0 is at Chennai and increases towards Bangalore. Between
Bangalore and Mumbai km 0.0 is at Bangalore and increases towards Mumbai. The
Project Highway is situated between km 433 (end of Hubli-Dharwad bypass) and km
515.0 (after crossing Belgaum city and Kakati Industrial area) of Bangalore-Mumbai
section of NH-4. In the Belgaum bypass portion the actual length is short by 1.8 km
as km stones are fixed based on old alignment of NH-4, which has been subsequently
bypassed. The km 505/600 on existing alignment merges with km 507/400 of old
alignment. There are also minor realignments at various other locations in between
km 433.0 and km 495.0 (package III) due to which the length as on ground does not
match with the kilometer stones fixed. The total length of the Project Highway is
79.355 km.
2.7 Development/Up-Gradation History
The Project Highway was 2-lane National Highway, which has been upgraded to 4-
lanes during the period 2001-2007 as part of NHDP-I (formerly called as Golden
Quadrilateral). The up-gradation to 4-lanes has been done by the National Highways
Authority of India through two separate civil works contracts from its budgetary
resources. The Contract Package-I is between Haveri and Hubli (south end of Hubli-
Dharwad bypass) and is outside the Project Highway. Contract Package-II is between
km 495 to 515 and has been declared complete on 31st March 2007. The contract
Package-III is between km 433.0 and km 495.0 has been declared complete on 30th
June 2007.
The present Six-Laning project is combination of package II & III of Four-Laning of
Belgaum-Dharwad stretch. The km stones fixed do not have exactly 1000 m distance
between them, may be due to realignment/improvements taken place in due course of
time. In the survey of Dharwad-Belgaum 4-lane project (Package III) km 0.0 was
taken at km 434.0 and subsequently it was extended backwards to km 433.0 to
accommodate a flyover. In Package II Chainage 0.0 was taken at km 495.0, which
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-17
Feasibility Report
increases towards Pune. The Good for Construction as well as As-Built Drawings
follow the Chainage system as above. The Chainage indicated on the structures is also
with reference to RD from km 434/000 taken as 0.000. The designs Chainage and
corresponding Chainage as per km stones for Package III and Package II are given in
Table 2.1 (a) and (b).
2.8. Topography
The Project Highway passes through plain and rolling terrain in most of its length
except through hilly terrain between km 487 and km 490.
2.9 Alignment
The alignment has been designed for minimum speed of 80 km per hour. However
most of the alignment has been improved to cater for higher speed up to 100 km per
hour.
The vertical gradient is less than 3% in most of the length except in hilly section and
at some isolated locations where the gradient up to 6% exists.
2.10 Settlements/Built Up Sections
There are a number of settlements along the Project Highway. Details of Major
settlements/built up sections are given in Table 2.2.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-18
Feasibility Report
Table 2.1 (a): Design Chainage and Corresponding Chainage as per km stones in Package III
Chainage as per design
Chainage as per km Stone
Chainage as per design
Chainage as per km Stone
-1175 433/000 32000 466/475 0 434/000 33000 467/525
1000 435/000 34000 468/550 2000 436/000 35000 469/575 3000 437/000 36000 470/600 4000 438/000 37000 471/575 5000 439/000 38000 472/600 6000 440/000 39000 473/623 7000 441/000 40000 474/595 8000 442/000 41000 475/688 9000 443/000 42000 476/715 10000 444/025 43000 477/750 11000 445/025 44000 478/725 12000 446/025 45000 479/775 13000 447/025 46000 480/800 14000 448/125 47000 481/829 15000 449/119 48000 482/850 16000 450/138 49000 483/875 17000 451/069 50000 484/890 18000 452/075 51000 485/945 19000 453/075 52000 497/000 20000 454/150 53000 488/050 21000 455/125 54000 489/050 22000 456/200 55000 490/489 23000 457/238 56000 491/075 24000 458/300 57000 492/075 25000 459/300 58000 493/100 26000 460/300 59000 494/200 27000 461/375 60000 495/000 28000 462/500 29000 463/438 30000 464/450 31000 465/475
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-19
Feasibility Report
Table 2.1 (b): Design Chainage and Corresponding Chainage as per km stones in Package II
Chainage as per design
Chainage as per km Stone
Chainage as per design
Chainage as per km Stone
000 495/000 10600 505/600
(507/400) 1000 496/000 11000 507/800 2000 497/000 12000 508/800 3000 498/000 13000 509/800 4000 499/000 14000 510/800 5000 500/000 15000 511/800 6000 501/000 16000 512/800 7000 502/000 17000 513/800 8000 503/000 18000 9000 504/000 18180 515/000
10000 505/000
Table 2.2: Major Settlements/Built Up Sections
Location Details Belur The main industrial area of Dharwad district.
The biggest industry of TATA division TELCON exists here. There is a road connecting centre for Garag taluk.
Tegur A number of restaurants exist along the road side. This is a intersection for Tegur, Ramapur and to other villages.
Kittur A historical place of Dharwad district, where a fort of freedom fighter Rani Channamma exists. This is a road connecting centre for Khanapur taluk.
MK Hubli A commercial area and major educational institutions exists. Hirebagewadi There is a road connecting centre for Bailhingal taluk. Belgaum Major city of Karnataka State. The National Highway 4A
meets the Project Highway at Belgaum. Although bypass is existing, lot of ribbon development has taken place all along the bypass
Kakti A commercial/industrial area along the road side.
Apart from the above mentioned towns, there are many small settlements along the
corridor.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-20
Feasibility Report
2.11 Bypasses
The existing Project Highway has only one bypass to Belgaum city (km 498 to km
507/600). On the Southern end the Project Highway joins 30 km long Hubli-Dharwad
bypass, which is still a two lane facility being operated under BOT scheme.
2.12 Right of Way
The existing right of way is 50 m in Kakati Industrial area (2 km) and 60 m in most of
remaining section. At isolated locations the ROW is less than 50 m. The details of
existing ROW as per data provided by the PD, NHAI, Dharwad is given in Table 2.3.
Table 2.3: Existing Right of Way Details
Chainage Left (m) Right (m) Total (m) 433.000-433.100 30.0 30.0 60.0 433.100-433.400 34.0 34.0 68.0 43.3400-437.000 30.0 30.0 60.0 437.000-437.100 40.0 40.0 80.0 437.100-437.200 45.0 45.0 90.0 437.200-437.300 34.0 34.0 68.0 437.300-445.300 30.0 30.0 60.0 445.300-445.400 48.0 48.0 96.0 445.400-445.500 58.0 58.0 116.0 445.500-445.600 38.0 38.0 76.0 445.600-446.400 30.0 30.0 60.0 446.400-446.700 32.0 32.0 64.0 446.700-446.900 36.0 36.0 72.0 446.900-456.800 30.0 30.0 60.0 456.800-457.000 28.0 28.0 56.0 457.000-473.500 30.0 30.0 60.0 473.500-473.600 60.0 60.0 120.0 473.600-473.700 100.0 100.0 200.0 473.700-473.900 120.0 120.0 240.0 473.900-474.900 32.0 32.0 64.0 474.900-480.000 30.0 30.0 60.0 480.000-480.100 46.0 46.0 92.0 480.100-480.200 40.0 40.0 80.0 480.200-494.900 30.0 30.0 60.0
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-21
Feasibility Report
Chainage Left (m) Right (m) Total (m) 494.900-495.000 27.5 27.5 55.0 495.000-495.100 24.5 24.5 49.0 495.100-495.200 28.0 28.0 56.0 495.200-495.300 35.5 35.5 71.0 495.300-495.400 28.0 28.0 56.0 495.400-495.500 23.5 23.5 47.0 495.500-495.700 24.0 24.0 48.0 495.700-495.800 30.0 30.0 60.0 495.800-495.900 36.0 36.0 72.0 495.900-496.000 28.5 28.5 57.0 496.000-496.100 25.5 25.5 51.0 496.100-496.200 30.0 30.0 60.0 496.200-496.300 34.0 34.0 68.0 496.300-496.400 35.0 35.0 70.0 496.400-496.500 30.0 30.0 60.0 496.500-496.600 24.0 24.0 48.0 496.600-496.900 25.5 25.5 51.0 496.900-497.000 24.5 24.5 49.0 497.000-497.100 26.0 26.0 52.0 497.100-497.200 25.0 25.0 50.0 497.200-497.300 53.0 53.0 106.0 497.300-497.400 76.0 76.0 152.0 497.400-497.500 87.0 87.0 174.0 497.500-497.550 78.0 78.0 156.0 497.550-497.600 50.5 50.5 101.0 497.600-497.650 30.0 30.0 60.0 497.650-497.700 26.0 26.0 52.0 497.700-497.800 24.0 24.0 48.0 497.800-497.900 35.0 35.0 70.0 497.900-498.000 44.0 44.0 88.0 498.000-498.100 55.0 55.0 110.0 498.100-498.200 35.0 35.0 70.0 498.200-498.700 30.0 30.0 60.0 498.700-498.800 29.0 29.0 58.0 498.800-498.900 30.0 30.0 60.0 498.900-499.000 31.5 31.5 63.0 499.000-499.100 33.0 33.0 66.0 499.100-499.300 30.0 30.0 60.0 499.300-499.500 29.0 29.0 58.0 499.500-499.600 31.0 31.0 62.0 499.600-499.700 30.0 30.0 60.0 499.700-499.800 29.0 29.0 58.0 499.800-499.900 28.0 28.0 56.0
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-22
Feasibility Report
Chainage Left (m) Right (m) Total (m) 499.900-500.000 32.0 32.0 64.0 500.000-500.100 33.0 33.0 66.0 500.100-500.200 31.5 31.5 63.0 500.200-500.300 30.0 30.0 60.0 500.300-500.400 32.0 32.0 64.0 500.400-501.000 30.0 30.0 60.0 501.000-501.200 29.0 29.0 58.0 501.200-501.500 30.0 30.0 60.0 501.500-501.600 29.0 29.0 58.0 501.600-502.500 30.0 30.0 60.0 502.500-502.600 32.0 32.0 64.0 502.600-502.700 39.0 39.0 78.0 502.700-502.800 32.0 32.0 64.0 502.800-502.900 29.0 29.0 58.0 502.900-503.000 28.0 28.0 56.0 503.000-503.100 31.5 31.5 63.0 503.100-503.300 33.5 33.5 67.0 503.300-503.400 34.0 34.0 68.0 503.400-503.500 35.0 35.0 70.0 503.500-503.600 31.0 31.0 62.0 503.600-503.700 30.0 30.0 60.0 503.700-503.900 27.0 27.0 54.0 503.900-504.000 28.0 28.0 56.0 504.000-504.100 28.5 28.5 57.0 504.100-504.200 29.5 29.5 59.0 504.200-504.300 31.0 31.0 62.0 504.300-504.400 30.0 30.0 60.0 504.400-504.500 30.5 30.5 61.0 504.500-504.600 32.0 32.0 64.0 504.600-504.700 30.0 30.0 60.0 504.700-504.800 27.0 27.0 54.0 504.800-504.900 28.0 28.0 56.0 504.900-505.000 28.5 28.5 57.0 505.000-505.100 40.0 40.0 80.0 505.100-505.200 42.0 42.0 84.0 505.200-505.300 28.5 28.5 57.0 505.300-505.400 27.0 27.0 54.0 505.400-505.700 25.0 25.0 50.0 505.700-505.800 26.5 26.5 53.0 505.800-505.900 23.5 23.5 47.0 505.900-506.000 19.0 19.0 38.0 506.000-506.100 19.5 19.5 39.0 506.100-506.400 30.0 30.0 60.0
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-23
Feasibility Report
Chainage Left (m) Right (m) Total (m) 506.400-506.500 33.0 33.0 66.0 506.500-506.600 65.0 65.0 130.0 506.600-506.700 29.0 29.0 58.0 506.700-506.800 27.5 27.5 55.0 506.800-507.000 28.0 28.0 56.0 507.000-507.100 29.0 29.0 58.0 507.100-507.200 27.0 27.0 54.0 507.200-507.300 24.5 24.5 49.0 507.300-507.400 23.5 23.5 47.0 507.400-507.500 23.0 23.0 46.0 507.500-507.600 21.5 21.5 43.0 507.600-507.700 20.5 20.5 41.0 507.700-507.800 20.0 20.0 40.0 507.800-507.900 27.0 27.0 54.0 507.900-508.000 35.0 35.0 70.0 508.000-508.100 45.0 45.0 90.0 508.100-508.200 30.0 30.0 60.0 508.200-508.400 20.0 20.0 40.0 508.400-508.600 21.5 21.5 43.0 508.600-508.700 22.5 22.5 45.0 508.700-508.800 22.0 22.0 44.0 508.800-508.900 21.5 21.5 43.0 508.900-509.000 29.0 29.0 58.0 509.000-509.100 34.0 34.0 68.0 509.100-509.200 26.8 26.8 53.6 509.200-509.300 27.0 27.0 54.0 509.300-510.900 25.0 25.0 50.0 510.900-511.000 32.0 32.0 64.0 511.000-511.100 47.0 47.0 94.0 511.100-511.200 43.0 43.0 86.0 511.200-511.300 30.0 30.0 60.0 511.300-511.400 27.0 27.0 54.0 511.400-511.500 35.5 35.5 71.0 511.500-511.600 30.0 30.0 60.0 511.600-511.700 31.5 31.5 63.0 511.700-511.800 42.0 42.0 84.0 511.800-511.900 40.0 40.0 80.0 511.900-512.500 35.5 35.5 71.0 512.500-515.000 30.0 30.0 60.0
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-24
Feasibility Report
2.13 Service Roads
Service road of width varying from 4 m to 7 m has been provided on considerable
length on either side of the Project Highway. In general the width of service road is 4
m in rural sections and 5.5 m to 7 m in built up sections. The details of the existing
service roads are given in Table 2.4.
Table 2.4 : Details of Existing Service Roads
4.0 m wide Service Road L.H.S. R.H.S.
Sr. No.
Chainage (km) Chainage (km) From To Length (m) From To Length (m)
1 433.990 434.775 785 433.250 436.625 3375 2 435.410 436.625 1215 436.750 439.550 2800 3 436.750 439.625 2875 439.750 444.150 4400 4 439.750 445.850 6100 444.300 446.450 2150 5 446.875 447.750 875 446.825 447.596 771 6 447.920 449.250 1330 447.875 449.225 1350 7 449.575 457.450 7875 449.275 456.575 7300 8 457.650 458.375 725 456.675 457.850 1175 9 459.150 463.650 4500 458.175 459.000 825
10 464.000 465.550 1550 459.150 459.600 450 11 465.850 466.690 840 462.225 465.650 3425 12 466.760 469.700 2940 465.775 469.875 4100 13 470.150 472.350 2200 470.025 472.400 2375 14 472.550 472.875 325 472.500 472.975 475 15 473.125 474.150 1025 473.775 475.350 1575 16 475.100 482.444 7344 475.575 476.000 425 17 482.856 483.650 794 476.200 482.444 6244 18 484.875 487.260 2385 482.856 483.200 344 19 489.050 490.475 1425 483.900 487.200 3300 20 490.575 493.880 3305 489.100 490.225 1125 21 495.000 495.860 860 490.575 493.675 3100 22 496.180 497.200 1020 496.345 497.650 1305 23 505.280 505.420 140 510.200 510.900 700
Total Length (m) = 52433 Total Length (m) = 53089
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-25
Feasibility Report
5.5 m wide Service Road L.H.S. R.H.S.
Sr. No.
Chainage (km) Chainage (km) From To Length (m) From To Length (m)
1 495.860 496.180 320 497.650 498.770 1120 2 498.600 498.770 170 498.850 499.040 190 3 498.850 500.365 1515 499.100 501.050 1950 4 503.900 504.380 480 501.500 504.380 2880 5 505.042 505.280 238 506.180 507.000 820 6 509.508 511.280 1772 509.090 510.000 910 7 511.750 515.000 3250 510.900 511.460 560 8 - - - 511.488 515.000 3512 Total Length (m) = 7745 Total Length (m) = 11942
7.0 m wide Service Road L.H.S. R.H.S.
Sr. No.
Chainage (km) Chainage (km) From To Length (m) From To Length (m)
1 434.775 435.410 635 436.625 436.750 125 2 436.625 436.750 125 439.550 439.750 200 3 439.625 439.750 125 444.150 444.300 150 4 449.250 449.575 325 446.450 446.825 375 5 458.375 459.150 775 449.225 449.275 50 6 465.550 465.850 300 456.575 456.675 100 7 469.700 470.150 450 458.000 458.175 175 8 472.350 472.550 200 459.000 459.150 150 9 474.150 475.100 950 465.650 465.775 125
10 483.650 484.875 1225 469.875 470.025 150 11 490.475 490.575 100 472.400 472.500 100 12 497.200 498.600 1400 476.000 476.200 200 13 500.365 503.900 3535 483.200 483.900 700 14 505.420 509.508 4088 490.225 490.575 350
Total Length (m) = 14233 Total Length (m) = 2950
2.14. Carriageway, Shoulder and Median
The existing National Highway is 4-lanes divided carriageway (2x7.0 m) with 1.5 m
wide paved and 2 m wide earthen shoulders on either side. The width of raised
median is generally 4.5 m between km 433 and 495 and 1.5 m between km 495 and
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-26
Feasibility Report
km 515. A width of 0.5 m of the median adjacent to the either side carriageway has
been paved.
There are some stretches in the Project Highway as per details in Table 2.5 in which
the carriageway width of 10.5 m has been provided. The length of such stretches is
10,178 m. Some of these sections are in Ghat Portion and others are in the
approaches to bridges / flyovers/ ROB.
Table 2.5: Details of Existing 6 lane Carriageway Stretches
S.No. From (km) To (km) Length
(m) Remarks 1 436/635 436/775 140 2 439/555 439/750 195 3 458/500 459/250 750 Before and after GS -1 4 464/950 466/275 325 5 470/270 470/600 330
6 473/580 473/950 370 Only RHS Main Carriageway (LHS is 2 Lane)
7 474/695 476/065 1370 Before and after GS – 2 8 484/590 485/745 1155 Before and after GS – 3 9 488/250 490/150 1900 Ghat Location 10 491/415 491/675 260 11 495/890 495/950 60 12 498/000 498/100 100 13 498/775 498/850 75 14 499/057 499/080 23 15 501/050 501/844 794 16 502/725 502/850 125 17 503/330 503/350 20 18 503/860 403/885 25 19 508/345 508/726 381 20 509/120 509/210 90 21 510/800 511/140 340
22 512/730 514/080 1350 Only RHS Main Carriageway (LHS is 2 Lane)
10,178 Total length
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-27
Feasibility Report
2.15. Pavement Type and Condition
The existing pavement is flexible on both sides carriageway between km 495 to km
515. Between km 433 and km 495 the pavement is rigid on one side and flexible on
other side. The side of rigid and flexible pavements changes frequently, in some
stretches rigid and flexible pavements are on both sides. The service roads are having
flexible pavement. The pavement condition is good in the entire section.
In Package III the length of flexible and rigid pavements are 54.527 km and 67.823
km respectively. The rigid part of pavement has rigid shoulders in 50.314 km and
flexible shoulders in 17.508 km. Details of existing pavement showing the type of
pavements & type of shoulders are given in Tables 2.6 and 2.7.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 2-28
Feasibility Report
Table 2.6
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-29
Feasibility Report
Table 2.7
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-30
Feasibility Report
2.16. Bridges and Culverts
There is one major bridge (Malprabha km 473.15, 9 spans of 24 m each), 5 minor
bridges, and 129 culverts (box and pipe) in the section between km 433 to km 495
(Dharwad-Belgaum project, Package III). In the Section between km 495 to km 515
including Belgaum bypass (Package II) there is one major bridge, two minor bridges
and 46 pipe culverts. Thus, there are total 2 major bridges and 7 minor bridges and
175 of culverts in the Project Highway. Package wise details are given in Table 2.8.
Table 2.8 Details of bridges and culverts
Item Package III (km 433.0 to km 495.0)
Package II (km 495.0 to km 515.0)
Total
Major bridge 1 1
2
Minor bridge 5 2 7
Culverts 129 46 175
All the new structures are having width same as in the approach road. The Malprabha
bridge has 3-lane carriageway with footpath on Dharwad-Belgaum lane and 2-lane
carriageway with 1.5 m wide footpaths on either side for Belgaum-Dharwad lane.
More details of Structures are given in Chapter 6 of this Report.
2.17. Rail-Road Structures
The railway line crosses project highway only at one location (km 502 on the
Belgaum bypass). A 6-lane Road-Over Bridge (ROB) plus a two lane bridge with
footpath for one side service road has been constructed as part of 4-lane project.
2.18. Junctions & Intersections
The Project Highway is having a number of major and minor junctions with National
Highways, State Highways and other category of roads. At all the major junctions
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-31
Feasibility Report
grade separators in the form of flyovers/grade separator and vehicular underpasses
have been constructed as part of 4-lane Projects. At 9 locations with intersection of
lower category of roads at grade junctions are existing, the details of which are given
in Table 2.9.
Table 2.9: List of At - grade Junctions
S.No. Intersection particulars
Location (km) Type (Major Structures)
1 To Kotur village 441.200 At grade junction with median opening 2 To Siganahalli
village 444.246 At grade junction with median opening
3 Venkarapur village 446.501 At grade junction with median opening 4 To Tegur village 449.382 At grade junction with median opening 5 Kittur junction 456.532 At grade junction with median opening 6 Ugarkod 463.250 At grade junction with median opening 7 Dastikoppa 472.425 At grade junction with median opening 8 Virkinkoppa 480.369 At grade junction with median opening 9 Bastawad 489.016 At grade junction with median opening
2.19 Grade Separated Structures
A large number of grade separated structures are existing on the Project Highway.
These have been provided with 3-lane carriageway for either side traffic. In addition,
a number of cattle passes and pedestrian underpasses/sub-ways to facilitate cross
movement of animals and pedestrians have also been provided. There is also one
viaduct over a grave yard in Package II. Details of such Structures provided as a part
of two 4-laning packages are given in Table 2.10.
Table 2.10: Details of Grade Separated Structures
Item Package III (km 433.0 to km 495.0)
Package II (km 495.0 to km 515.0)
Total
Flyover/Grade separator/Vehicular underpass
9 7 16
Cattle pass 22 Nil 22
Pedestrian underpass/sub-bay
2 6 8
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-32
Feasibility Report
Viaduct - 1 1
2.20 Connection with Project Highway
At present the Project Highway has been provided slip in and slip out on the left hand
side of the carriageways at a number of locations. At some locations, at grade
junctions with cross roads have also been provided. In general cross roads are
intercepted by service roads. The location and type of connection with the main
highway on the Left Hand Side (LHS) and Right Hand Side (RHS) are given in
Tables 2.11 and 2.12 respectively.
Table 2.11: Location and Type of Connection on LHS
Intersection particulars Location (km) Flyover 433.000 Slip in – Keradi Dhaba 433.990 Slip in – Mummigatti 436.280 Slip in – Garag cross 437.015 Slip in – Belur Industry 439.020 Slip out – Belur Industry 440.020 Slip out – Reliance outlet 441.300 Slip in –Ramapur cross 441.800 Signal – Siganahalli cross 444.150 Venkatapur 446.500 Slip in – Ramapur/Tegur 449.350 Dombarkopp IB 456.010 Slip in – Kittur/Alnawar Road 457.990 Slip out – Kittur 458.900 Slip in – Ambadagatti 463.215 Slip out – Abadagatti 463.620 Slip in – Hulikatti 465.200 Slip out – Hulikatti 465.905 Slip in – Itagi 469.100 Slip out - Itagi 470.250 Slip in – Dastikoppa 472.415 Slip in – MK Hubli 474.010 Slip out – MK Hubli 474.024 Slip in – Parishwada, Mutnal & Vinkinkoppa 480.380 Slip out – Service road end, Toll Plaza starts 482.450 Slip in – Hirebagewadi 485.900 Service road end –Hirebagewadi 488.200 Slip in – KK Koppa 490.007 Slip out – KK Koppa 497.607
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-33
Feasibility Report
Slip in - Bastawada & Kondaskoppa 494.108 Slip in – Halaga 495.020
Intersection particulars Location (km) Slip in – Belgaum city exit 497.630 Slip in – Belgaum city exit 498.610 Slip in – Belgaum 500.340 Slip in & out – Island 502.360 Slip out – Belgaum city 503.150 Slip in – SRP Hostel 504.270 Slip in – KLE Hospital 505.004 Slip out – KLE Hospital 505.200 Slip in – Kakati 510.480 Slip out – service road ends Kakti
513.080
Slip in – Honaga Service Road starts 513.390 Slip in – Bennalli 515.300
Table 2.12: Location and Type of Connection on RHS
Intersection particulars Location (km) Slip in – Narendra 433.700 Slip out – Garag 436.280 Slip in – Garag 437.300 Slip out – Belur Industrial 439.020 Slip in – Belur Industrial 440.200 Slip in – Kotur 441.800 Slip in – Siginahal li 441.150 Slip in – Venkatapur 446.500 Service road starts Venkatapur 447.600 Service road end Venkatapur 447.800 Slip in – Tegur 449.350 Slip in - Dombarkoppa 456.650 Slip out – Kittur 457.990 Slip in – Kittur 459.100 Service road starts Timmapur 465.800 Service road end – Ugarkod 462.300 Slip in – Ugarkod 463.215 Slip out – Hulikatti 465.010 Slip in – Hulikatti 465.900 Slip out – Itagi 469.100 Slip in – Itagi/Kadravalli 470.260 Slip in – Dastikoppa 472.415 Service road starts Malaprabha 473.100 Slip out – Service road MK Hubli 473.795
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-34
Feasibility Report
Slip in – MK Hubli 476.100 Slip out – Mutnal 480.380
Intersection particulars Location (km) Slip in – Mutnal 482.450 Toll Plaza 482.850 Slip out - Hirebagewadi 485.625 Slip in – Hirebagewadi 485.900 Slip in – Hirebagewadi 485.900 Service road starts 488.200 Balekollimatta 488.300 Slip out – Service road ends KK Koppa 489.975 Slip in – KK Koppa 491.790 Slip out – Bastawada 494.108 Slip in – Service road start 494.700 Slip out – Halaga Service road/ Tarihal village 495.450 Slip in – Belgaum road 496.350 Slip out – Belgaum road 497.630 Slip in – Halaga Belgaum 498.610 Slip out – Belgaum 500.340 Slip in – Belgaum city 503.010 Slip in – Service road Belgaum 504.190 Service road starts Belgaum 504.300 Slip out – Service road end – Indalga village 508.200 Slip in – KLE Hospital 509.130 Service road end – KLE Hospital 511.400 Slip in – Kakti 511.480 Slip in – KIADB 513.390
2.21 Wayside Amenities
Wayside amenities like petrol pumps, dhabas, workshops, pick up bus stops, etc.,
exist all along the Project Highway. List of way – side amenities is given in Table
2.13. The inventory of sign boards available on the highway is given in Table 2.14
(a) and (b)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-35
Feasibility Report
Table 2.13: Existing Way Side Amenities/ Structures
Sl No.
From km
To km Side Amenity
1 434 435 LHS Power Grid 2 435 436 LHS Panjabi Dhaba 3 437 438 LHS Hotels 4 439 440 LHS Hotel - Santosh, Electronic Weigh Bridge 5 440 441 LHS IBP Petrol Pump, Hotels. Sl
No. From
km To km Side Amenity
6 441 442 LHS BP Petrol Pump, Ghar - Dhaba, Mulla - Dhaba & Reliance Petrol Pump
7 442 443 LHS Kotur - Govt. School, Mulla - Dhaba 8 446 447 LHS Venkatapur - Govt. School 9 447 448 LHS Guledkoppa - Govt. School
10 449 450 LHS Seven Loves - Dhaba 11 451 452 LHS Mulla - Dhaba 12 452 453 LHS Indian Oil Petrol Pump
13 457 458 LHS Gajraj - Hotel, Dhaba, IBP Petrol Pump & Auto Shops
14 458 459 LHS Bharat Oil Petrol Pump, Hotels 15 465 466 LHS Mulla - Dhaba 16 470 471 LHS Hotels 17 472 473 LHS Dastikoppa Govt. School, Govt. Hospital
18 474 475 LHS Indian Oil Petrol Pump, M.K. Hubli Govt. School, Hotels
19 475 476 LHS M.K. Hubli - Govt. Hospital & Police Station 20 482 483 LHS Krishna Hotel 21 483 484 LHS Hirebagewadi - APMC Market, Hotels 23 484 485 LHS Hotels 24 485 486 LHS Hirebagewadi - Govt. Hospital, Police Station 25 490 491 LHS Juice Factory (Clean Goods), Hotels 26 491 492 LHS Cement Pipe Manufacturing Factory
27 495 496 LHS Gopal Ginagouda Hospital, Halaga - Govt. School, Hotels
28 496 497 LHS Hotels 29 497 498 LHS Hotels 30 498 499 LHS Bharat Petrol Pump 31 500 501 LHS Auto shops
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-36
Feasibility Report
32 501 502 LHS Auto shops, Hotels 33 502 503 LHS Auto shops, Hotels 34 503 504 LHS Belgaum Cancer Hospital 35 504 505 LHS SRP Hostel 36 505 506 LHS KLE Hospital 37 506 507 LHS Indian Oil Petrol Pump 38 508 509 LHS Hotels 39 509 510 LHS Bharat Petrol Pump 40 510 511 LHS Hotels Sl
No. From
km To km Side Amenity
41 511 512 LHS Bharat Petrol Pump, Hotels 42 513 514 LHS Honaga - Govt. School 43 514 515 LHS Ganga - Dhaba, Sai - Dhaba
Table 2.14 (a): Inventory of Existing Signages
Left Hand Side S.No Chainage (km) Type of Sign Board
From To
1 433 434 Compulsory Keep Left Destination Sign Left Hand Curve NH Route Marker Sign 2 434 435 Right Hand Curve 3 436 437 Left Hand Curve Direction Sign Stop Sign Stop Sign 4 438 439 Right Hand Curve
5
439
440
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-37
Feasibility Report
Stop Sign Filling Station 6 440 441 Eating Place Repair Facility Stop Sign Right Hand Curve Left Hand Curve 7 441 442 Filling Station Repair Station Eating Facility Overtaking Prohibited Cross Road Filling Station Advance Direction Sign Stop Sign 8 442 443 Left Hand Curve Right Hand Curve 9 444 445 NH Route Marker Sign Overtaking Prohibited Cross Road Left Hand Curve Left Hand Curve
10 445 446 Right Hand Curve
11 446 447 Advance Direction Sign Overtaking Prohibited Cross Road Place Identification Left Hand Curve
12 447 448 Left Hand Curve Direction
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-38
Feasibility Report
13
449
450 Overtaking Prohibited Eating Place Cross Road Stop Right Hand Curve
14
450
451 Left Hand Curve Right Hand Curve
15 451 452 Left Hand Curve Eating Place
16 452 453 NH Route Marker Sign Filling Station Right Hand Curve
17 453 454
18 457 458 Eating Place Direction Repair Facility Direction
19 458 459 Direction Advance Direction Stop Compulsory Keep Left Place Identification Right Hand Curve
20 459 460 Left Hand Curve
21 460 461 NH Route Marker
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-39
Feasibility Report
Right Hand Curve
22 462 463 Direction Left Hand Curve
23 463 464 Overtaking Prohibited Direction Stop
24 464 465 Right Hand Curve
25 465 466 Right Hand Curve Stop Speed Limit Stop
26 466 467 Left Hand Curve
27 467 468 Left Hand Curve
28 468 469 Route Marker Sign
29 469 470 Direction Left Hand Curve Advance Direction Advance Direction Stop Overtaking Prohibited
30 470 471 Right Hand Curve
31 471 472 Direction Stop Sign
32 491 492
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-40
Feasibility Report
Stop Sign Speed Stop Sign
33 493 494 NH Route Marker Left Hand Curve Overtaking Prohibited Cross Road
34 494 495 Direction Stop Sign Direction Right Hand Curve Right Hand Curve
35 495 496 Overhead Sign Board Direction Hospital Cross Road Stop
36 497 499 Direction Advance Direction Stop
37 500 503 NH Route Marker Repair Facility Advance Direction Cross Road Advance Direction Advance Direction Advance Direction Cross Road No Entry Direction
38 503 504 Eating Place Stop
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-41
Feasibility Report
Overhead Sign Board Cross Road Advance Direction
39 504 505 Filling Station
40 505 506 Advance Direction
41
508
509 Advance Direction Cross Road
43 510 511 Filling Station DIRECTION
Table 2.14 (b): Inventory of Existing Signages
Right Hand Side
S.No Chainage (km) Type of Sign Board From To 1 498 497 Filling Station Advance Direction Cross Road Direction Stop 2 497 496 Advance Direction 3 496 495 Stop Overhead Sign Left Hand Curve 4 495 494 Left Hand Curve Cross Road Direction
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-42
Feasibility Report
Speed Limit 5 494 493 Left Hand Curve Right Hand Curve Nh Route Marker 6 492 491 Speed Limit Direction Advance Direction Stop Right Hand Curve 7 491 490 Left Hand Curve Direction 8 490 489 Advance Direction Stop Speed Limit NH Route Marker Right Hand Curve 9 489 488 Left Hand Curve Right Hand Curve Direction NH Route Marker Left Hand Curve
10 488 487 NH Route Marker Left Hand Curve
11 487 486 Left Hand Curve Filling Station Overhead Direction Advance Direction
12 486 483 Eating Place
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-43
Feasibility Report
Direction Right Hand Curve Overtaking Prohibited Advance Direction Stop Stop Right Hand Curve
13 483 482 Overhead Direction
14 481 480 Speed Limit Cross Road Stop
15 479 478 NH Route Marker
16 477 476 Speed Limit Direction
17 476 474 Right Hand Curve Stop
18 474 472 Speed Limit Advance Direction Stop Right Hand Curve Cross Hand Curve NH Route Marker
19 472 471 Left Hand Curve
20 471 469 Filling Station Direction Repair Facility Stop NH Route Marker Advance Direction
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-44
Feasibility Report
Speed Limit Stop
21 468 467 Right Hand Curve
22 467 466 Right Hand Curve
23
466
465 Direction Left Hand Curve Stop Stop
24 465 464 Left Hand Curve
25 463 462 Right Hand Curve Direction
26 462 461 Left Hand Curve
27 461 460 Right Hand Curve NH Route Marker Left Hand Curve
28 460 455
29 455 454 Direction
30 453 452 NH Route Marker
31 452 451 Right Hand Curve
32 451 450 Left Hand Curve
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-45
Feasibility Report
Right Hand Curve Left Hand Curve
33 450 449 Overtaking Prohibited Eating Place Direction Advance Direction Stop
34 449 448 NH Route Marker
35 448 447 Right Hand Curve
36 447 446 Stop Direction
37 446 445 Left Hand Curve Right Hand Curve
38 445 444 Right Hand Curve Direction Stop NH Route Marker
39 444 443 Left Hand Curve
40 442 441 Right Hand Curve Eating Place Direction
41 441 440 Right Hand Curve Eating Place
42 440 439 Stop Stop
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-46
Feasibility Report
43 439 438 NH Route Marker Right Hand Curve
2.22 Utilities
Utilities like telephone cables, O.F.C. lines, water pipelines and electric lines run
along and across the Project Highway. Some of the utilities would require to be re-
located to accommodate widening of main carriageway to 6-lanes and service roads
to 2-lane. Details/locations of all the utilities / OFC and trees are shown in the Strip
Plans submitted separately. The details of the utilities and trees which are required to
be shifted / cut are also shown in the Strip Plans.
2.23 Typical Cross Sections and Condition of existing highway
Typical cross sections of the existing 4/6 lane Project Highway are given in Figures
2.2 to 2.17. Typical features of the exiting Project Highway are shown in Photos 2.1
to 2.18.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-47
Feasibility Report
Fig 2.2-2.3
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-48
Feasibility Report
Fig 2.4-2.5
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-49
Feasibility Report
Fig 2.6-2.7
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-50
Feasibility Report
Fig2.8-2.9
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-51
Feasibility Report
fig2.10-2.11
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-52
Feasibility Report
fig2.12-2.13
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-53
Feasibility Report
fig2.14-2.15
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-54
Feasibility Report
Fig2.16-2.17
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-55
Feasibility Report
Photo 2.1: Km. 474 Major bridge 2 lane
bridge (Malprabha Bridge) on LHS Main Carriageway
Photo 2.2: Alignment in Hilly Section
Photo 2.3: Drainage Problem Photo 2.4: Restricted ROW
Photo 2.5: Grade Separator (Vehicular Underpass) 6-lane
Photo 2.6: Six Lane Flyover
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-56
Feasibility Report
Photo 2.7: ROB (2X3 lanes) for main Highway and 2 lanes for Service Road
Photo 2.8: Pedestrian Sub-Way
Photo 2.9: Problem Of Roadside Parking Photo 2.10: Problem Of Roadside Parking
Photo 2.11: High Embankment Stretches Photo 2.12: Toll Plaza at Hirebagewadi needs to be improvised
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-57
Feasibility Report
Photo 2.13: Median Plantation
Photo 2.14: ROW restricted
Photo 2.15: ROW restricted Photo 2.16: ROW restricted
Photo 2.17: ROW restricted in rural area Photo 2.18: Land Acquisition Problem (Service Road LHS, Venkatapur)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-58
Feasibility Report
2.24. Current Traffic
There is mixed traffic on the Project Highway comprising of trucks, buses, cars, two
wheelers, non-motorised vehicles, etc. The Supervision Consultants had carried out
traffic survey in Nov-Dec 2005 at km 483.600 (location of toll plaza) and the average
of 7-day count of tollable traffic is given in Table 2.15.
Table 2.15: Traffic Count Nov-Dec 2005
Number of Vehicles (and not Converted to PCU s)
Location Two Wheelers
Three Wheelers
Animal Driven Carts
Tractors Car/ Jeep/ Van
LCV Truck/ Bus
Multi Axle Vehicle
Total Tollable Vehicles
483.6 (1) (2) (3) (4) (5) (6) (7) (8) (5) to (8)
528 NIL 14 80 1090 582 2460 833 4965
The traffic composition as per 7 day count carried out by the Consultants during
December 2007 / January 2008, at km 486.000 and km 514.000 are given in Table
2.16.
Table 2.16: Traffic Count December 2007 – January 2008
Number of Vehicles
Location Two
Wheeler
Three
Wheeler
Non-
Motorised
Tractor Car / Jeep / Van
LCV Trucks Bus Total
Motorised Traffic
Total
Tollable
Traffic
No. PCU No. PCU
486.000 1898 184 242 150 2291 841 4006 1381 10751 21289 8519 19565
514.000 3714 345 1159 80 3405 1081 5494 1630 15748 28686 11610 26215
Another 7-day traffic survey was carried out at km 486.000 and km 514.000 in
February, 2008. The details are given in Table 2.17.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-59
Feasibility Report
Table2.17: Traffic Count February 2008
Number of Vehicles
Location Two
Wheeler
Three
Wheeler
Non-
Motorised
Tractor Car / Jeep / Van
LCV Trucks Bus Total
Motorised Traffic
Total
Tollable
Traffic
No. PCU No. PCU
486.000 1966 293 337 226 2305 1183 4501 1674 12148 24513 9663 22445
514.000 3228 370 465 44 3160 1501 5766 1559 15628 29118 11986 26996
2.25 Accidents and Safety
The safety of road user, be it a vehicle driver or pedestrian, is an important aspect to
be considered while designing a six – lane fast highway, with limited access
controlled facilities. The main issues identified for safety are wrong side driving,
overloading, uncontrolled access, pedestrian interference, head light glare, at grade
junctions, etc.
In order to bring improvements and to reduce the chance of accidents, the following
features are needed:
(i) A proper access control system should be put in place.
(ii) Proper treatment of the median to limit head light glare, and to prevent front
collision and wrong side driving.
(iii) Adequate signage to provide information to the user e.g. direction signs,
destinations, caution boards, education signage etc.
(iv) Proper horizontal and vertical geometry for the design speed.
(v) The essential features such as acceleration / deceleration zones, bus bays and
shelters, trucks lay bys, pedestrian / cattle / vehicular underpasses and their
approaches, proper turning radii, services roads with proper entry and exit
ramps.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-60
Feasibility Report
The existing 4 – lane highway is not as safe as it should be because of following
reasons:
(i) There is partial access control on the highway. There are too many slip in and
slip out roads without proper design.
(ii) The short distance and long distance traffic get mixed up since the service
roads provided are discontinued in many stretches and also the riding quality
of service roads is not good.
(iii) A number of at- grade junctions are provided without any advance intimation.
(iv) Some of the pedestrian sub bays provided are not user friendly.
(v) Inadequate facility for movement of traffic and pedestrians living both sides
of the villages through which the road passes.
Based on the site visit and discussions with the villagers / local police officials, the
following are identified as the locations and safety issues which need to be resolved.
(i) Wrong side driving
Wrong side driving has become a major source of accidents on our highways.
This is mainly because of lack of facility for movement from one side to the
other, lack of traffic sense and the illiteracy amongst the road users. Photos
2.19 to 2.21 show the wrong side driving at km 483.6 near toll plaza.
Photo 2.19: Wrong Side Driving Photo 2.20: Wrong Side Driving
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-61
Feasibility Report
Photo 2.21: Wrong Side Driving
(ii) Design and Signage Deficiency
The Dharwad bound carriageway has ghat section in km 490 – km 488. The
road is designed for a speed of 50 km / hr. The down grade between km 489 –
488 has a steep slope of about 6%, coupled with a sharp curve of 230 m
radius. Vehicles travel at higher speeds than the design speed. The head light
glare and the high speed lead to accident during night time.
(iii) Bus Stops and Pedestrian Subways
The bus stops are located on the main carriageways. As a result, the
passengers cross over the road for other side near the bus stops itself. Also,
since there is no pedestrian sub way provided in km 471, pedestrians cross
over the carriageway at the surface. This leads to accidents and fatal many a
times. Photos 2.22 to 2.23 show the pedestrians crossing the road and the
movement of traffic.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-62
Feasibility Report
Photo 2.22: Pedestrians Crossing Photo 2.23: Pedestrians Crossing
(iv) Overloading of Vehicles
The overloading of vehicle in volume, rather than the weight especially by
carts and tractors, is another problem which needs to be addressed. This
results in poor visibility for the fast moving traffic. The Photo 2.24 shows
overloaded vehicle observed on the road.
Photo 2.24: Overloaded Vehicles
(v) Proposed Facilities to Avoid Accidents
The improvements proposed on the project corridor include the following:
Widening to six lane
Closing of at – grade junctions
Provision of well designed service roads for movement of local
traffic
Provision of more pedestrian sub ways
Proper signage
Provision of vehicular under passes, where required
Traffic Enforcement
Provision of bus – bays and shelters on the service roads
Highway Patrol
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-63
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-64
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-65
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-66
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-67
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-68
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-69
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-70
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-71
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-72
Feasibility Report
CHAPTER 3: ENGINEEING SURVEYS,
INVESTIGATIONS AND
ANALYSIS
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-73
Feasibility Report
CHAPTER 3: ENGINEERING SURVEYS AND INVESTIGATIONS
TABLE OF CONTENTS
3.1 Data Collection…………………………………………………………... 3-1 3.2 Traffic Surveys…………………………………………………………... 3-1 3.3 Ground Surveys (ROW Verification)……………………………………. 3-2 3.4 Pavement Condition Survey and Roughness Measurement……………... 3-2 3.5 Materials Investigations…………………………………………………. 3-2 3.6 Inventory and Condition Survey of Bridges and Culverts………………. 3-5 3.7 Public Consultation ……………………………………………………… 3-5 3.7.1 General…………………………………………………………… 3-5 3.7.2 Public Consultation Meeting at M.K. Hubli……………………... 3-6 3.7.3 Public Consultation Meeting at Hirebagewadi…………………... 3-9 3.7.4 Public Consultation Meeting at Kakati Village………………….. 3-12
LIST OF TABLES
Table 3.1 Test Results of Soil from Borrow Areas…………………………… 3-3
LIST OF APPENDICES
Appendix 3.1 Details of Data Collected Appendix 3.2 Details of Minutes/Discussions and Letters to P.D. NHAI Appendix 3.3 Details of Public/Panchayat Meeting
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-74
Feasibility Report
CHAPTER 3
ENGINEEING SURVEYS AND INVESTIGATIONS
3.1 Data Collection
As per the Terms of Reference the start of the Project is with validation of the as-built
drawings. The Consultants made requests to the PD, NHAI Dharwad to provide
necessary data required for feasibility study, like as built drawings, right of way
details, etc. The Consultants also had a number of meetings with the PD, NHAI and
Team Leader of the Supervision Consultants. We have been able to collect some data
from various sources as given in Appendix 3.1, but the authenticated copies of the as-
built drawings have not been made available till this draft feasibility study report is
prepared and submitted. The Consultants also deputed its two Cad Engineers to help
scrutiny of the details submitted by the contractors, with a view to expedite
finalisation of as-built drawings. Preparation of Draft feasibility report has been
delayed on account of non-availability of as-built drawings. A copy of the letters
written to the PD, NHAI and record of the minutes/discussions held on the subject are
given in Appendix 3.2. In view of the delay already taken place, and reminders
received from NHAI, this report has been prepared based on the data collected and
additional surveys conducted such as topographic survey, video-photography of the
entire length, digital still photography, physical survey, etc. Details of various surveys
and investigations, which the Consultant carried out, for arriving at the widening
proposal, are given in this Chapter.
3.2 Traffic Surveys
The reconnaissance survey was conducted in October 2007 and it helped in
identification and understanding of homogeneous traffic sections, visible travel
pattern on the corridor, major traffic generators / attractors along and off the project
road, major intersections etc. Accordingly, various traffic surveys were planned to
capture the traffic and travel characteristics on the sections of the project corridor.
The surveys conducted in December 2007 - January 2008 included, classified traffic
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-75
Feasibility Report
volume count, origin-destination, intersection turning movement, pedestrian count,
speed & delay, axle load etc. The first traffic surveys were conducted between 29th
December 2007 to 5th January 2008, under the supervision of the Traffic Engineer.
The results from these traffic studies, including traffic projections, are discussed in
detail in Chapter 4 of this report. The traffic volume counts were done for 7 days,
both for up and down directions, at two locations viz. km 486 and km 514. Another
set of 7 days traffic volume count at these locations was done in February 2008. The
origin – destination and axle load surveys were done at two locations, viz. km 483.6
and km 514, for 24 hours, covering about 10 – 20% of the vehicles, on random
sample basis.
3.3 Ground Surveys (ROW Verification)
Topographic survey with Total Station has been conducted to collect information on
salient features of the existing highway and the available ROW. The details of
existing ROW and other features along the highway are presented in Chapter 2.
3.4 Pavement Condition Survey And Roughness Measurement
The pavement condition survey, along with a roughness survey was carried out in the
first week of January 2008. The survey included road inventory, pavement condition,
and IRI (roughness measurements) and structural evaluation. Details of pavement
condition survey are given in Chapter 5.
3.5 Materials Investigations
A number of borrow areas were used during the 4 laning work. There are a number of
borrow areas which still have adequate and appropriate quantity of soil for 6 laning
work. Some of these borrow areas were investigated during the field visits for quality
and quantity verification of the material available. The samples collected from the
borrow areas were subjected to detailed laboratory studies. The results are presented
in Tables 3.1. As seen from the Table, good quality soil is available along the
Project Highway, within reasonable load, for the widening works.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 3-76
Feasibility Report
Table 3.1: Test Results of Soil from Borrow Areas Sl. No.
Borrow Area
Lead from
NH -4 Depth Sieve Analysis
Liquid Limit
Plastic Limit
Plasticity Index
MDD gm/cc
OMC %
Free Swell Index (%)
CBR (%)
Gravel
% Sand
% Silt - Clay
%
at 97 % MDD
1 437 RHS 1860 m up to 0.5 m 42.25 29.08 28.67 47 24 23 2.1 8.90 19.0 15
0.5 to 1.0 m 38.70 28.18 33.12 50 24 26 2.06 9.10 23.8 13
2 444 LHS 625 m 0.75 to 1.5 m 41.13 22.65 36.22 45 23 22 2.10 8.82 20.0 22
up to 0.75 m 36.10 29.65 34.25 49 23 26 2.05 9.31 20.0 18
3 450 RHS 1100 m up to 1.0 m 33.65 22.08 44.27 48 23 25 1.95 11.67 14.3 15
1.0 to 2.0 m 37.35 45.83 16.82 45 23 22 1.98 11.42 14.3 15
4 456 LHS 550 m up to 0.75 m 22.30 17.35 60.35 48 26 22 1.92 10.53 14.3 18
0.75 to 1.5 m 26.40 29.30 44.30 47 25 22 2.8 8.92 14.3 19
5 470 LHS 1050 m up to 0.75 m 43.10 32.95 23.95 56 23 33 1.89 11.12 30.0 14
0.75 to 1.5 m 40.50 35.55 23.95 53 25 28 2.02 9.85 25.0 17
6 471 LHS 700 m up to 1.0 m 33.50 42.53 23.97 47 25 22 2.10 9.36 25.0 24
1.0 to 2.0 m 37.40 35.40 27.20 47 26 21 2.07 9.43 23.1 22
7 480 RHS 100 m up to 0.75 m 1.18 56.87 41.95 58 33 25 1.9 13.50 13.6 14
0.75 to 1.5 m 9.20 54.35 36.45 59 29 30 1.92 13.86 13.0 15
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-77
Feasibility Report
3.6 Inventory And Condition Survey of Bridges and Culverts
The Senior Bridge Engineer, along with a team of bridge / field engineers, carried out
the inventory and condition survey of the complete project road from 29th December
2007 to 15th January 2008. Visual inspection was done to find out the deficiencies in
the structures. At some bridge locations, due to water logging in the entire waterway,
it was not possible to inspect the structure from beneath. Type of expansion joints in
the old existing bridges could not be ascertained as they were covered with
bituminous overlays at most the bridge locations. The details of the structure are
given in Chapter 6.
3.7 Public Consultation
3.7.1 General
Keeping in view, the requirement of Public Consultation, as satisfied in TOR clause
4.9, the Consultant held Public Consultation meetings along the Project Highways.
The meetings were held in the month of February, 2008. The Public Consultation
meetings were held at the following places, and were finalized in Consultation with
NHAI and Police Officials:
1. M.K. Hubli
2. Hirebagewadi
3. Kakati
The meetings were held with the general public, elected representatives of Gram
Panchayat, Zilla Parishad and other key personnel of the area. The NHAI officials
also participated in the meetings. The proposal of six laning of the Dharwad –
Belgaum section of NH – 4, covering widening of the existing pavement carriageway,
improvements in the service roads, provision of vehicular / pedestrian crossings,
safety aspects etc were explained to the participants. The details of the deliberations
are given here.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-78
Feasibility Report
3.7.2 Public Consultation Meeting at M.K. Hubli
The meeting was held on 26th February, 2008 in the office of the village Panchayat.
21 persons from the general public, Gram Panchayat and Zilla Parishad, as per
attendance list given below, participated in the meeting.
The following points emerged during the discussion:
a. The existing pedestrian subway at km 475 is not being used because of its
poor design and the lack of facilities. It is not safe for the ladies to use the
facility because there is no light. It is being used by some anti social elements
and filth.
b. Bus bays and shelter shall be provided on both sides on the service roads.
c. The damaged parts of the service roads in km 472 shall be repaired,
level raised and adequate cross – drainage works provided. There are
some of the cattle walks which are submerged under water because of the
poor drainage condition. As a result, they are not being used.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-79
Feasibility Report
d. There is need to provide a new pedestrian subway at appropriate location, to
enable the pedestrians of different age group to cross over to the other side.
e. There is need for a bridge, across Malprabha River for vehicles like
carts, tractors etc to cross over.
A copy of the Panchayat resolution along with the list of participants, is given in
Appendix 3.3. Views of Public Consultation meeting and the condition of existing
facilities are shown in Photos 3.1 to 3.10.
Photo 3.1: Consultants explaining the 6 – laning proposal
Photo 3.2: The participants expressing their views
Photo 3.3: Approach to the pedestrian crossing
Photo 3.4: Participants explaining the problems faced
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-80
Feasibility Report
Photo 3.5: Inside view of the C-D work used
as pedestrian crossing Photo 3.6: NHAI Official responding to the
participants
Photo 3.7: Ponding of water in cattle crossing Photo 3.8: Poor drainage condition at cattle crossing
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-81
Feasibility Report
Photo 3.9: Damaged service road due to poor drainage condition
Photo 3.10: Consultants taking note of demands of the participants
3.7.3 Public Consultation Meeting at Hirebagewadi
The meeting at Hirebagewadi was held on 27th February, 2008 in the Panchayat
office. The representatives from the village, Gram Panchayat, Zilla Parishad attended
the meeting. A total of 27 persons, as per the attendance list given below,
participated in the meeting.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-82
Feasibility Report
The participants were explained of the widening proposals. Various problems being
experienced by the villagers as a result of the recently completed four laning work
were expressed by them. The following points emerged as a result of the discussion:
a. The pedestrian survey provided at km 486 should be relocated and redesigned
keeping in view the poor drainage facility leading to accumulation of water
during rainy season and the bad light.
b. A new pedestrian subway shall be provided near Karnataka Cottage and
connected through smooth gradient with the service roads on both sides.
c. The service roads shall be widened and strengthened to serve the needed
purpose.
d. Street light shall be provided on the service roads.
e. No toll shall be charged from villagers who have land on the other side of the
Toll Plaza, since they have given their lands for the 4 - laning work.
f. Adequate cross drainage works shall be provided in order to drain out the
water. At many locations on the service roads the provision of CD works is
necessary for the smooth flow of water from one side to the other.
g. One vehicular underpass shall be provided in km 481 to enable the movement
of traffic from Belgaum side to state highway leading to Parashwad.
h. One of the two openings of CD work provided at km 483.8 shall be
converted into pedestrian subway and the other half shall work as cross
drainage work.
i. Poor geometrics at km 488, coupled with head light glare at night, leads to
accident.
j. There is need to provide adequate arrangement for movement of pedestrians
and also for drainage of water to the village storage pond.
Some glimpses of the meeting are shown in Photos 3.11 to 3.18.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-83
Feasibility Report
Photo 3.11: Consultants explaining the proposal to the participants
Photo 3.12: Participants discussing the proposal amongst themselves
Photo 3.13: Consultants taking note of the view of the participants
Photo 3.14: The participants explaining the problems
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-84
Feasibility Report
Photo 3.15: Interaction between Consultants and the participants
Photo 3.16: Consultants on visits with the participants
Photo 3.17: Participants expressing the view point
Photo 3.18: Poor Condition of the drains
3.7.4 Public Consultation Meeting at Kakati Village
The consultation meeting at Kakati Village was held at the Panchayat office on 28th
February, 2008. The Consultant and the NHAI officials explained to the villagers of
the proposed six laning work. The meeting was attended by the Gram Panchayat
representatives, businessmen and the local residents. The participants expressed their
grievances arising due to construction of 4 – laning work and the provision of
inadequate service roads. The villagers are experiencing lot of difficulties.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-85
Feasibility Report
The following points emerged during the discussion.
a. The lack of structures provided on the highway for movement of pedestrians
and vehicles from one side to other. The business of the local residents has
been severely affected.
b. The underpass provided at km 511.420 shall be widened and height raised for
smooth movement of the buses and trucks.
c. The drains provided are not affective and create water logging of the
area.
d. The service roads shall be widened and strengthened to the required
standards.
e. Bus bays and shelters should be provided on service roads on both sides of
the highway.
f. A new pedestrian subway shall be provided in km 511.
Some glimpses of the meeting are shown in Photos 3.19 to 3.28.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-86
Feasibility Report
Photo 3.19: Consultants explaining the proposals to the participants
Photo 3.20: View of meeting with participants
Photo 3.21: Participants expressing their views Photo 3.22: Villagers participation in the
meeting
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-87
Feasibility Report
Photo 3.23: Consultants expressing views on villagers demands
Photo 3.24: Interaction between the participants and the Consultants
Photo 3.25: Consultants expressing their view
points Photo 3.26: Consultants taking note of
villagers needs
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-88
Feasibility Report
Photo 3.27: Interaction between Consultants and the villagers
Photo 3.28: NHAI officials interaction with the villagers
The suggestions made by the villagers / road users during the Public Consultation meetings
as above have been duly considered and provisions made in the six laning proposals, as
feasible.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-89
Feasibility Report
CHAPTER 4: TRAFFIC STUDIES AND
ANALYSIS
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-90
Feasibility Report
CHAPTER 4: TRAFFIC STUDIES AND ANALYSIS
TABLE OF CONTENTS
4.1 General………………….………………………………………………..... 4-1 4.2 Traffic Survey Planning & Schedule………………………………………. 4-1
4.2.1 Reconnaissance Survey..……………………….……………….... 4-1
4.2.2 Traffic Surveys and their Locations…………………………….... 4-2
4.2.3 Details of Surveys………………………………………………… 4-4
4.3 Traffic Analysis ………………………………………………………….... 4-10 4.3.1 Comparison Of Two Rounds Of Traffic Count…………………. 4-10 4.3.2 Travel Characteristics………………………………………….... 4-11
4.3.2.1 General………………………………………………….. 4-11 4.3.2.2 Development of Origin – Destination Matrices………… 4-12 4.3.2.3 Commodity Movement Characteristics…………………. 4-19
4.3.3 Axle Load Survey………………………………………………... 4-19
4.3.4 Speed Characteristics…………………………………………….. 4-21
4.3.5 Traffic Survey For Slip In / Slip Out Service Road……………… 4-21
4.4 Traffic Forecasting…………………………………………………………. 4-27
4.4.1 Traffic Forecasting Techniques………………………………….. 4-27 4.4.1.1 Traffic Growth by Past Trends…………………………. 4-27
4.4.1.2 Growth Pattern of Registered Vehicles………………… 4-28
4.4.1.3 Growth Pattern of Economic Indicators………………... 4-31
4.4.1.4 Estimation of Transport Demand Elasticity……………. 4-32
4.4.1.5 Estimation of Traffic Growth…………………………... 4-34
4.4.2 Recommend Traffic Growth……………………………………… 4-35
LIST OF TABLES
Table 4.1 Traffic Surveys, Location and Duration……………………….... 4-2 Table 4.2 (a) Weekly Average Traffic Data at km 486.300 (Dec-Jan 2008)…… 4-6 Table 4.2 (b) Weekly Average Traffic Data at km 514.00 (Dec-Jan 2008)…… 4-7 Table 4.3 (a) Weekly Average Traffic Data at km 486.300 (Feb 2008)………... 4-8 Table 4.3 (b) Weekly Average Traffic Data at km 514.00 (Feb 2008)………… 4-9 Table 4.4 No. of Vehicles Interviewed for O – D Survey………………… 4-10 Table 4.5 Comparison of Two Sets of Traffic Surveys…………………… 4-11 Table 4.6 (a) O-D Matrix at km 483.60………………………………………. 4-13
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-91
Feasibility Report
Table 4.6 (b) O-D Matrix at km 514.00………………………………………. 4-16 Table 4.7 Distribution of vehicle Trips by Commodity at km 483.600…..... 4-19 Table 4.8 Distribution of vehicles trips by commodity at km 514……….... 4-19 Table 4.9 Vehicle Damage Factors………………………………………... 4-20 Table 4.10 Total Projected Traffic (MSA) over Design Life……………..... 4-21 Table 4.11 Corridor Travel Speeds in the Project Area……………………… 4-21 Table 4.12 (a) Traffic Survey Information Pertaining to Slip In/Out and
Service Road (LHS)…………………………………………...... 4-23
Table 4.12 (b) Traffic Survey Information Pertaining to Slip In/Out and Service Road (RHS)………………………………………………………
4-25
Table 4.13 Traffic Growth by Past Trends………………………………….. 4-28 Table 4.14 Growth of Registered Vehicle in Karnataka State………………. 4-29 Table 4.15 (a) Growth of Economic Indicators……………………………….... 4-31 Table 4.15 (b) Projected Growth of Economic Indicators……………………… 4-31 Table 4.16 (a) Summary of Indicators Growth (%)……………………………. 4-33 Table 4.16 (b) Calculation of Elasticity for Karnataka State………………….. 4-33 Table 4.16 (c) Comparison of Elasticity by different Methods………………... 4-33 Table 4.17 Transport Demand Elasticity…………………………………… 4-34 Table 4.18 Estimated Traffic Growth (%)………………………………….. 4-34 Table 4.19 Monthly Sale of Motor Sprit and High Speed Diesel in
Karnataka ……………………………………………………... 4-35
Table 4.20 Projected Future Traffic……………………………………… 4-37
LIST OF FIGURES Figure 4.1 (a) Growth Trend of Cars ………………………………………….. 4-30 Figure 4.1 (b) Growth Trend of Buses………………………………………… 4-30 Figure 4.1 (c) Growth Trend of Trucks………………………………………... 4-30 Figure 4.1 (d) Growth Trend of 2 Wheelers…………………………………… 4-30 Figure 4.2 Growth of Economic Indicators………………………………... 4-20 Figure 4.3 Showing Sale of High Speed Diesel in Karnataka……………... 4-35
LIST OF APPENDICES
Appendix 4.1 (a) Detailed Day-wise Traffic Volume Count at km 486.300 Appendix 4.1 (b) Detailed Day-wise Traffic Volume Count at km 514.00 Appendix 4.2 (a) Year-wise Projected Traffic for 20 years at km 486.300 Appendix 4.2 (b) Year-wise Projected Traffic for 20 years at km 514.00 Appendix 4.3 (a) Details of Commodity carried and Axle Load Data at km 483.60 Appendix 4.3 (b) Details of Commodity carried and Axle Load Data at km 514.00
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-92
Feasibility Report
CHAPTER 4
TRAFFIC STUDIES AND ANALYSIS
4.1 General
The 79.355 km long project corridor on NH – 4 starts from Dharwad (km 433) and
ends after Belgaum (at km 515) and is part of the Chennai – Mumbai Golden
Quadrilateral corridor. The present project involves the assessment and evaluation
of the feasibility to convert the existing 4 – lane corridor to a 6 lane facility with
partial / full access control, through provision of service roads, grade separators and
other features to ensure safety. This chapter discusses the various traffic surveys
conducted, their analysis, travel characteristics and traffic projections etc. with the
following objectives.
Establish base year traffic demand
Capacity assessment based on demand forecasting for next 25 years (up to
year 2032)
Identification of travel pattern & influence area of the project stretch
Pattern of commodity movement
Deriving Growth Factor for traffic demand Forecasting
Estimation of corridor traffic including traffic diversion, if any
Enable preliminary design of project facilities
4.2 Traffic Survey Planning & Schedule
4.2.1 Reconnaissance Survey
The Consultants carried out a reconnaissance survey of the project corridor
during October 2007 to understand the general traffic and travel characteristics on the
corridor. There are number of important settlements (major / minor) along the
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-93
Feasibility Report
corridor. Some of the important settlements along the corridor are given Table 2.2
of Chapter 2.
The Belgaum city, located along the corridor, has been provided with bypass
offering varying levels of service.
4.2.2 Traffic Surveys and their Locations
Considering the apparent travel pattern, the traffic surveys to be conducted and their
locations were identified. Following surveys have been conducted to meet the
objectives of the study and TOR requirements:
Classified Traffic Volume Count Survey for 7 days at two locations, two
times
Origin – Destination survey for 24 hours at 2 locations
Turning Movement count for 12 Hours at 10 locations
Pedestrian Count survey for 12 Hours at 5 locations
Speed and Delay survey on project corridor
Movement of traffic a service road
Axle Load survey for 1 day at 2 locations
The traffic surveys were conducted during December 2007 to February 2008. All the
traffic surveys were conducted following the relevant IRC and MORTH guidelines.
The list of surveys and survey locations along with the schedule are given in Table
4.1.
Some glimpses of traffic surveys are shown in Photos 4.1 to 4.7.
Table 4.1: Traffic Surveys, Location and Duration
S.No. Traffic Survey Location Frequency Duration 1. Classified Traffic
Volume Count km 486.300 and
km 514.00 Twice 7 days each
2. O-D Survey km 483.600 and km 514.00
Once 12 hours each
3. Turning Movement 10 Once 12 hours each 4. Pedestrian Count
Survey 5 Once 12 hours each
5. Speed and Delay - Once - 6. Movement of
Traffic on Service - Once -
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-94
Feasibility Report
Road 7. Axle Load Survey km 483.6 and
km 514.00 Once 1 day each
Photo 4.1: OD Survey at Km 483.6 Photo 4.2: Axle Load Survey at Km 483.6
Photo 4.3: Rear Axle of Truck Being
Weighed Photo 4.4: Trucks Line Up at Toll Plaza
Photo 4.5: Extent of Heavy Load Carried Photo 4.6: Axle Load Survey at Toll Plaza
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-95
Feasibility Report
By Multi Axle Truck
Photo 4.7: View of 10 Bay Toll Plaza Provided at Km 483.6
4.2.3 Details of Surveys
The details of various traffic surveys are presented in the following subsections.
4.2.3.1 Classified Traffic Volume Count Surveys: Two sets of 7 days classified traffic
volume count surveys were conducted at two locations viz. km 486.3 and km
514.00. The compiled survey data as average of the weak, separately for the
two rounds, are presented in Tables 4.2 (a) & (b) and 4.3 (a) & (b). The
detailed day-wise data for the two sets is given in Appendix 4.1 (a) & 4.1 (b).
4.2.3.2 Origin and Destination Survey: 24 hour O-D Surveys were conducted at km
483.6, the Hirebagewadi toll plaza, and at km 514.00 to determine the traffic
flow pattern and area of influence by their origin and destination that would
have an impacts on growth trend of traffic. The O-D survey was conducted on
random sample basis to cover both passenger and fright traffic. The number
of vehicles interviewed for O-D survey is given in Table 4.4.
4.2.3.3 Axle Load Survey: The axle load surveys were conducted for 24 hours, round
clock, at km 483.600 and km 514.00. The surveys were undertaken for study
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-96
Feasibility Report
of axle load pattern for design of the pavement, separately for the up and
down traffic. The survey covered an average of about 15 percent commercial
vehicles, mostly the trucks.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-97
Feasibility Report
Table 4.2 (a)
In A3 paper
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-98
Feasibility Report
Table 4.2 (b)
In A3 paper
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-99
Feasibility Report
Table 4.3 (a)
In a3 paper
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-100
Feasibility Report
Table 4.3 (b)
In A3 paper
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-101
Feasibility Report
Table 4.4: No. of Vehicles Interviewed for O – D Survey
Survey Location Passenger Vehicles
Freight Vehicle
Total
Car Bus
Hirebagewadi Toll Plaza (km 483.6) 651 224 945 1820 End of Dharwad – Belgaum Stretch (km 514)
515 74 598 1187
4.3 Traffic Analysis
The data (primary and secondary) collected has been analyzed to obtain information
on ADT, Seasonal Variation, AADT, traffic composition, Peak Hour Design Traffic,
Average Journey and Running Speed, Speed and Delay, Travel Pattern and
Commodity movement pattern, Traffic Demand Forecasting and Accident
Information. This information along with other relevant parameters, formed part of
the basic input for the design and evaluation of the recommended improvement.
These are discussed in the following paragraphs.
4.3.1 Comparison of Two Rounds of Traffic Count
Classified traffic volume count surveys conducted during December 2007/ January –
08 and February 2008 have been analysed to assess the average daily traffic. Since
the second set of counts is considered as confirmative, the results are not used in any
analysis other than comparing with the previously collected traffic data. The compiled
data and comparison for 2 rounds of average daily traffic, at km 486.3 and km 514, is
presented in Table 4.5.
The two traffic counts at two different locations show change in traffic with passage
of time. The change is different for different categories of motorised / non –
motorised vehicles. At km 486.300, while there is increase in bus and truck traffic in
the range of 10-20%, the increase in cars is only about 5%. There is increase in non-
traffic by 40-50%. However, there is decrease in the two / three wheeler. In the case
of traffic at km 514.000, except for the truck traffic which has shown an increase by
about 5%, the rest of vehicle categories have shown decrease in volume up to about
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-102
Feasibility Report
50%. The above change in traffic is indicative only, since the period over which
change has been observed is too small. The location at km 514.00 has urban effect.
Table 4.5: Comparison of Two Sets of Traffic Surveys
S.No Location Set Bus Trucks LCV Car/Van/ Jeep
Two + Three
Wheelers
Tractors Non Motorised
1 486.000 1 1381 4006 841 2291 4059 150 243 2 1674 4501 1183 2305 2259 226 337
2 514.000 1 1630 5494 1081 3405 4073 79 1159 2 1558 5768 1500 3161 3597 44 465
4.3.2 Travel Characteristics
4.3.2.1 General
The survey was conducted on random sample basis to cover both passenger
and freight vehicles. The drivers / occupants of the vehicles were interviewed
and all relevant information such as origin, destination, trip length, frequency
etc., was collected. In addition, the information regarding trip purpose in case
of passenger vehicles, and commodity and load in case of freight vehicles was
also collected and analyzed. The sample size for goods and passenger
vehicles covered in the O-D Survey is already presented in Table 4.4.
Road side interview method was adopted for conducting the survey. The
pertinent information in respect of travel characteristics, including the
following were collected during these interviews.
Origin and Destination of the trip
Trip Length
Number of Trips
Trip Time
Number of Passengers
Commodity Type and Load
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-103
Feasibility Report
The O – D survey was limited to only cars and buses in passenger vehicles
category and trucks (LCV, 2 Axle/ 3 Axle, MAV) in freight vehicles
category.
4.3.2.2 Development of Origin – Destination Matrices
The data collected was coded for further analysis. Major zones attracting /
generating traffic are Nipani, Belgaum, Dharwad, other part of Karnataka
and the states of Maharashtra, Tamil Naidu, A.P, Goa, Gujarat, Delhi and
Kerala.
After coding of origin – destination data, vehicle – wide O – D matrices
were developed. Both the combined and separate O – D matrix of freight
and passenger vehicles were developed for the various O - D locations. On
the basis of O – D matrices, travel pattern of the moving vehicles on the
project road has been analysed.
The O-D matrices for cars, buses and commercial vehicles for the two
locations at km 483.6 and km 514.00 are given in Tables 4.6 (a) and (b)
respectively.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-104
Feasibility Report
Table 4.6 (a): Commercial Vehicles O-D Matrix at km 483.6
Destination Nippani Belgaum Dharwad
Other Part Of
K.A Maharashtra Chennai A.P Goa Gujarat Delhi Kerala Punjab Rajasthan TOTAL Origin
Nippani 1 1 2
Belgaum 16 63 6 8 93
Dharwad 8 1 4 1 14
Other Part Of K.A 2 112 25 119 2 4 3 267
Maharashtra 26 4 225 4 60 1 1 39 360
Chennai 4 55 59
A.P 4 7 11
Goa 2 2
Gujarat 2 23 6 1 32
Delhi 7 15 13 3 38
Kerala 3 45 2 50
Punjab 4 1 5
Rajasthan 1 2 8 1 12
Total 2 167 21 360 269 75 1 1 7 39 3 945
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-105
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-106
Feasibility Report
Table 4.6 (a): Cars O - D Matrix at km 483.6
Destination Nippani Belgaum Dharwad
Other Part of K.A Maharashtra Chennai A.P Goa Gujarat Delhi Kerala Punjab Rajasthan TOTAL
Origin
Nippani 1 8 2 11
Belgaum 33 101 5 4 3 146
Dharwad 1 72 2 22 1 98
Other Part of K.A 2 169 2 80 1 254
Maharashtra 6 9 86 6 11 1 3 122
Chennai 3 3
A.P 1 2 3
Goa 8 8
Gujarat 1 1 2
Delhi 1 1
Kerala 2 2
Punjab
Rajasthan 1 1
Total 3 249 43 208 122 15 6 5 651
Table 4.6 (a): Bus O - D Matrix at km 483.6
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-107
Feasibility Report
Destination Nippani Belgaum Dharwad Other Part of K.A Maharashtra Chennai A.P Goa Gujarat Delhi Kerala Punjab Rajasthan Total Origin
Nippani 1 1
Belgaum 26 45 2 73
Dharwad 13 3 16
Other Part Of K.A 67 2 30 99
Maharashtra 3 27 1 2 33
Chennai 1 1
A.P
Goa 1 1
Gujarat
Delhi
Kerala
Punjab
Rajasthan
TOTAL 80 30 75 37 2 224
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-108
Feasibility Report
Table 4.6 (b): Commercial Vehicles O- D Matrix at km 514
Destination Nippani Belgaum Dharwad Other Part of K.A Maharashtra Chennai A.P Goa Gujarat Delhi Kerala Rajasthan Punjab Origin TOTAL
Nippani 33 4 10 47
Belgaum 15 2 17
Dharwad 1 14 15
Other Part of K.A 1 10 5 176 9 201
Maharashtra 36 7 155 3 13 6 220
Chennai 1 1 42 1 45
A.P 5 5
Goa 2 2
Gujarat 1 12 8 21
Delhi 2 2 4
Kerala 1 12 13
Rajasthan 5 1 1 7
Punjab 1 1
TOTAL 3 80 11 191 280 14 13 6 598
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-109
Feasibility Report
Table 4.6 (b): Bus O - D Matrix at km 514
Destination Nippani Belgaum Dharwad Other Part Of K.A Maharashtra Chennai A.P Goa Gujarat Delhi Kerala Total Origin
Nippani 1 1
Belgaum 10 21 31
Dharwad 1 1
Other Part Of K.A 2 10 1 13
Maharashtra 2 1 23 1 27
Chennai
A.P
Goa 1 1
Gujarat
Delhi
Kerala
Total 2 1 36 33 2 74
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-110
Feasibility Report
Table 4.6 (b): Cars O - D Matrix at km 514
Destination Nippani Belgaum Dharwad Other Part Of K.A Maharashtra Chennai A.P Goa Gujarat Delhi Kerala Punjab Rajasthan Total Origin
Nippani 3 6 13 1 1 24
Belgaum 8 1 39 121 10 179
Dharwad 5 1 6
Other Part Of K.A 1 10 12 68 1 1 93
Maharashtra 10 26 133 3 9 3 7 8 199
Chennai 1 1
A.P 1 1
Goa 4 1 5
Gujarat 1 2 1 4
Delhi 1 1
Kerala 1 1
Punjab
Rajasthan 1 1
Total 9 14 43 201 205 21 3 8 2 8 1 515
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-111
Feasibility Report
4.3.2.3 Commodity Movement Characteristics
The data collected under the Origin – Destination survey has been analysed.
For the analysis purpose various commodities are grouped in to 7 broad
categories. The summary of the distribution of vehicles by commodity carried
is presented in Table 4.7 and Table 4.8.
Table 4.7: Distribution of vehicle Trips by Commodity at km 483.600
S. No.
Commodity Type No of Vehicles Percentage
1 Empty 20 2.12 2 Petroleum / Chemicals 47 4.98 3. Goods 741 78.41 4 Construction Materials 15 1.58 5 Machinery 17 1.80 6 Metal / ore 13 1.37 7 Parcel 92 9.74
Total 945 100.00
Table 4.8: Distribution of vehicles trips by commodity at km 514
As can be seen from above Tables, the number of vehicles carrying the goods is
higher than the other commodities.
4.3.3 Axle Load Survey
Axle load surveys were conducted at two locations on the project corridor, one at
km 483.6 (Hirebagewadi) and the other at km 514 (after Belgaum) to understand
the loading pattern for in the design of pavement. The Table 4.9 presents the
S. No. Commodity Type No of Vehicles Percentage 1 Empty 22 3.68 2 Petroleum / Chemicals 85 14.21 3. Goods 324 54.18 4 Construction Materials 58 9.70 5 Machinery 4 0.67 6 Metal / ore 6 1.00 7 Parcel 99 16.56
Total 598 100.00
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-112
Feasibility Report
average vehicle damage factors (VDF), observed at the two locations for different
vehicle types.
The average VDFs are used to estimate design traffic load in terms in million
standard axles (MSA). The axle repetitions for the various sections of the corridor
calculated for the 20 years design (by the year 2030) are estimated in the range of
92 to 204 MSA. Table 4.10 presents the projections of the standard axles for 30
years period. The details of traffic projections at these two locations, in terms of
number of vehicles and PCUs, over the 20 years period also given in Appendix 4.2
(a) and 4.2 (b). The compiled data on commodities carried out and the individual
axles along with the vehicle wise detailed analysis for the two locations, is given at
Appendix 4.3 (a) and (b).
Table 4.9: Vehicle Damage Factors
Location (km)
Vehicle Type
DIRECTION
Dharwad – Belgaum
Belgaum – Dharwad Average
483.6 2A 3A MA WA
2.66 4.05 5.54 3.28
3.64 4.27 8.85 4.12
3.7 514 2A
3A MA WA
4.15 5.62
- 4.57
3.42 5.47 25.72 4.55
4.56
2A – 2 Axle, 3A – 3 Axle, MA – Multi Axle
WA – Weighted Average
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-113
Feasibility Report
Table 4.10: Total Projected Traffic (MSA) over Design Life
Year Dharwad – Belgaum Belgaum – Dharwad
LHS RHS LHS RHS
2008 2.864 2.427 4.268 5.0348 2010 9.253 7.841 1.378 1.626 2025 7.887 6.684 1.175 1.386 2030 1.159 9.822 1.727 2.0371 2040 2.086 1.7678 3.108 3.666
4.3.4 Speed Characteristics
Speed and delay survey has been conducted for the entire length of project
corridor. The results are tabulated and presented below in Table 4.11. This data
has been used in assessing the relative service levels offered by the project
corridor. It can be noted that the effective speeds are lower than the current
design speed.
Table 4.11: Corridor Travel Speeds in the Project Area (km/hr)
Corridor/Section Run 1 Run 2 Average Up Down Avg. Up Down Avg.
Dharwad – Belgaum 70 75 72.5 72 74 73 73
4.3.5 Traffic Survey for Slip In / Slip Out Service Road
In the entire reach of 79.355 km from Dharwad to Belgaum there are a total of 42
slip in / out roads on the left side and 37 slip in / out roads on the right side. One
day survey at these roads was conducted to study the movement of traffic to and
from the main carriageway and the use of service road. The traffic survey data,
separately for left and right side carriageways is shown in Tables 4.12 (a) and
(b).
As seen from the Tables 4.12 (a) and (b), there is some traffic on the slip roads,
but the traffic on service road is very little. The traffic on slip in / out roads is
because of the movements for the villages connected by the main highway. The
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-114
Feasibility Report
traffic on service road is very low, main reason seems to be that there is not
continuous habitation along the highway in the reach km 433 – 495. However, in
the reach from km 495 – 515, there is some traffic on the service road because of
the Belgaum city.
The low traffic on the service roads could also be due to the fact the roads were
not continuous all through out and also for majority of the length there are single
lane only. With the 6 – laning of the NH – 4, the number of the slip in / out roads
will be reduced and the geometric standards of the service roads will improve.
This will lead to generation of more traffic on the service roads.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-115
Feasibility Report
Table 4.12 (a)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-116
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-117
Feasibility Report
Table 4.12(b)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-118
Feasibility Report
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-119
Feasibility Report
4.4 Traffic Forecasting
The traffic forecasting has been done based on the elasticity of transport demand
keeping in view present growth in registration of vehicles, economic indicators like
Net State Domestic Product, Per Capita Income, and Net National Domestic Product
and by Past Trends.
The elasticity of transport demand for next 20 years at 5 year interval has been
suggested and compared with elasticity recommended in IRC:SP:19-2001 and
Road Development Plan Vision-2021 (MoRTH).
4.4.1 Traffic Forecasting Techniques
The current year traffic will continue to grow with the growth rate estimates of past
trends up to year 2010. For further projections, various growth rates techniques are
applied. Various growth rate methods are:
(a) 7.5% per annum for all vehicles.
(b) Trend growth of various vehicles categories.
(c) Projected Growth rate of revenue assumed in the concessionaire’s cash flow.
(Toll collection data)
(d) Growth determined from secondary socio economic data and elasticity factors.
4.4.1.1 Traffic Growth by Past Trends
7 day Traffic volume count was carried out in Dec, 2007/Jan, 2008 at km 486
of NH-4. The Traffic growth in above data is shown in Table 4.13. However,
traffic data of earlier studies / reports which was conducted in January, 2000
at km 486 is also used.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-120
Feasibility Report
Table 4.13: Traffic Growth by Past Trends
Traffic Count Station
Year Vehicle Category
CARS BUSES TRUCKS LCV
km 486 Jan 2000 1503 939 4110 819 Jan 2008 2291 1381 4026 841
Growth Rate (%) 6.2 5.6 - (0.3) 0.4
Note: Since NH 4A connecting Belgaum to Goa was not in traffic worthy condition,
the commercial vehicles bound for Goa are using alternate routes. This
appears to be reason for low growth in commercial vehicles.
4.4.1.2 Growth Pattern of Registered Vehicles
The growth pattern of registered vehicles in preceding five years has been
shown in Table 4.14. High growth in trucks indicates growth in Net State
Domestic Product (NSDP) and Net National Product (NNP).
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-121
Feasibility Report
Table 4.14: Growth of Registered Vehicles in Karnataka State
S.No. Year
No. of Vehicles
Log (No. of vehicles)
Car, Jeep,
Van Buses Truck
M/C &
Two-
Wheeler
Three-
Wheeler
Car,
Jeep,
Van
Buses Truck
M/C &
Two-
Wheeler
Three-
Wheeler
1 2001-02 401739 66637 137939 2868595 160954 5.604 4.824 5.140 6.458 5.207
2 2002-03 452469 73200 148025 3245652 174151 5.656 4.865 5.170 6.511 5.241
3 2003-04 495182 80791 161122 3556741 188591 5.695 4.907 5.207 6.551 5.276
4 2004-05 571110 88260 179570 3957760 202300 5.757 4.946 5.254 6.597 5.306
5 2005-06 674601 94875 219200 4512910 213721 5.829 4.977 5.341 6.654 5.330
Coefficient
in equation. 0.0551 0.0388 0.0486 0.0480 0.0311
Growth
Rate 13.54% 9.35% 11.85% 11.68% 7.43%
**Source: Table 2.4 Vehicle Registration, March 1990 - March 2006, page 2-7 of "Feasibility Study of State Roads for proposed
KSHIP-II"
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-122
Feasibility Report
The Log (no. of Vehicles) was plotted year wise for each category of vehicles to determine
the growth rate by Log-Regression Method. The following Figure 4.1 (a) to Figure 4.1 (d)
show the trend lines and accordingly vehicle-wise growth rates of registered vehicles during
last five years have been calculated and shown in Table 4.14 .
Figure 4.1 - : Passenger Occupancy Composition
Figure 4.1 (a): Growth Trend of Cars
Figure 4.1 (b):Growth Trend of Buses
Figure 4.1 (c): Growth Trend of Trucks
Figure 4.1 (d): Growth Trend of 2 Wheelers
Car Jeep Van
y = 0.0551x + 5.5426R2 = 0.9877
5.55
5.60
5.65
5.70
5.75
5.80
5.85
0 2 4 6Year
Log(
Vehi
cles
)
Buses
y = 0.0388x + 4.7873R2 = 0.9969
4.804.824.844.864.884.904.924.944.964.985.00
0 2 4 6Year
Log(
Vehi
cles
)
Trucks
y = 0.0486x + 5.0766R2 = 0.9522
5.10
5.15
5.20
5.25
5.30
5.35
5.40
0 2 4 6Year
Log(
Vehi
cles
)
Three-Wheelers
y = 0.0311x + 5.1784R2 = 0.995
5.20
5.30
5.40
0 2 4 6Year
Log(
Vehi
cles
)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-123
Feasibility Report
4.4.1.3 Growth Pattern of Economic Indicators
The basic economic indicators that affect the transport demand are Net
National Product (NNP), Per Capita Net State Domestic Product (PCNSDP)
and Net State Domestic Product (NSDP). Past growth rate and projected
growth rate of economic indicators are as given in Table 4.15 and shown in
Figure 4.2.
Table 4.15 (a): Growth of Economic Indicators
S. No. Year
NNP* NSDP ** PCNSDP ** Log
At Constant Prices (1999-2000) (Rs in crores)
At Constant Prices (1999-2000) (Rs in crores)
At Constant Prices (1999-2000) (Rs)
NNP NSDP PCNSDP
1 2001-02 1,743,466 9359285 17553 6.241 6.971 4.244 2 2002-03 1,805,830 9813043 18182 6.257 6.992 4.260 3 2003-04 1,963,544 10113660 18504 6.293 7.005 4.267 4 2004-05 2,104,520 11239536 20315 6.323 7.051 4.308 5 2005-06 2,306,894 12110704 21629 6.363 7.083 4.335 Coefficient in equation.
0.0310 0.0283 0.0230
Growth Rate 7.39% 6.73% 5.43% *Source: http://mospi.nic.in\press-release-31Jan 2008.pdf **Source: http://des.kar.nic.in/mainpage.asp?option=5
Year
NNP Growth NSDP PCNSDP PCNSDP At const. prices (Rs in crores) NNP
At const. prices (Rs in crores)
NSDP At const. prices (Rs)
Growth rate
2005 2,306,894.00 12,110,704.00 21629.00 2008 2,865,047.51 7.49% 14,744,808.59 6.78% 25583.00 5.76% 2013 4,149,623.68 7.69% 20,603,162.58 6.92% 34866.00 6.39% 2018 6,063,360.68 7.88% 28,978,111.88 7.06% 48995.00 7.04% 2023 6,063,360.66 8.09% 41,043,705.70 7.21% 71053.00 7.72% 2028 13,328,561.16 8.30% 58,540,857.41 7.36% 104304.00 7.98%
Table 4.15 (b): Projected Growth of Economic Indicators
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-124
Feasibility Report
Figure 4.2: Growth of Economic Indicators
4.4.1.4 Estimation of Transport Demand Elasticity
Transport demand is influenced by change in economic parameters. Transport
demand elasticity is a measure of change in transport demand with respect to
change in economic parameters. The growth of 2-wheelers, cars and buses
depends on growth rate of Per Capita Net State Domestic Product and rate of
Population Growth whereas growth of trucks depends on growth rate of Net
State Domestic Product and Net National Product. The elasticity for passenger
& freight traffic has been worked out by following relationship.
For passenger vehicles : E = G/((1+Gp)*(1+Gpci)-1)
E=G/6.98
For trucks : E = G/(0.67*NSDP+0.33*NNP)
NNP
y = 6.2031e0.0049x
R2 = 0.9829
6.200
6.240
6.280
6.320
6.360
6.400
0 2 4 6Y ear
NSDP
y = 6.936e0.004x
R2 = 0.9601
6.920
6.960
7.000
7.040
7.080
7.120
0 2 4 6
Year
Log
PCNSDP
y = 4.2145e0.0054x
R2 = 0.94
4.200
4.240
4.280
4.320
4.360
0 2 4 6Y ear
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-125
Feasibility Report
E= G/7.01
For Buses E=G/Growth rate of NSDP
E=G/6.78
Where, E = Elasticity
G = Growth Rate
Gp = Growth Rate of Population
Gpci = Growth Rate of per Capita Income
Based on the above relationship, elasticity has been worked out for Karnataka
State and compared with the other available sources to arrive at rational value
as shown in Tables 4.16 (a), (b) and (c).
Table 4.16 (a): Summary of Indicators Growth (%)
Year Gp Gpci NSDP NNP Upto 2008 1.16 5.76 6.78 7.49 2008-2013 1.05 6.39 6.92 7.69 2013-2018 0.91 7.04 7.06 7.88 2018-2023 0.71 7.72 7.21 8.09 2023-2028 0.50 7.98 7.36 8.30
Table 4.16 (b): Elasticity for Karnataka State
Car, Jeep, Van
Buses Truck M/C & 2-Wheeler
Three Wheeler
Growth rate of Vehicles as per registration (G) 13.54% 9.35% 11.85% 11.68% 7.43%
Factor (F) 6.98 6.78 7.01 6.98 6.98 E= (G/F) 1.94 1.38 1.69 1.67 1.06
Table 4.16 (c) Comparison of Elasticity by different Methods
Car, Jeep, Van
Buses Truck M/C & 2-Wheeler
Three Wheeler
Elasticity as per calculation = (G/F) 1.94 1.38 1.69 1.67 1.06 Elasticity as per SP-19 2.00 1.60 - 2.50 2.50 Elasticity as per vision 2021 (MoRT&H) 1.70 1.40 1.50 - -
Elasticity adopted 1.70 1.38 1.50 1.67 1.00
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-126
Feasibility Report
The elasticity calculated for Car, 2-Wheelers, 3-Wheelers and Tractors is on higher side.
Minimum value from the above has been recommended.
Since values of elasticity tend to decrease in future years, the values of elasticity as indicated
in Table 4.17 have been suggested for calculating vehicle growth at an interval of 5 years.
While calculating the future traffic growth, seasonal factor is also applied.
Table 4.17: Transport Demand Elasticity
Year Car, Jeep, Van
Buses Truck M/C & 2-Wheeler
Three Wheeler
Tractors & Trailers
Upto 2008 1.70 1.38 1.50 1.67 1.00 1.25 2008-2013 1.70 1.38 1.50 1.67 1.00 1.25 2013-2018 1.53 1.24 1.35 1.51 0.90 1.13 2018-2023 1.38 1.12 1.22 1.36 0.81 1.01 2023-2028 1.24 1.01 1.09 1.22 0.73 0.91
4.4.1.5 Estimation of Traffic Growth
Based on the above stipulations, projected traffic growth rates have been
worked out at an interval of 5 years as indicated in Table 4.18.
Table 4.18: Estimated Traffic Growth (%)
Year Car, Jeep, Van Buses Truck M/C & 2-
Wheeler Three Wheeler
Tractors & Trailers
Upto 2008 11.87 9.3 10.52 11.68 6.98 8.77 2008-2013 12.75 9.54 10.76 12.55 7.50 8.97
2013-2018 12.26 8.76 9.90 12.07 7.21
8.25
2018-2023 11.68 8.05 9.11 11.50 6.87 7.59
2023-2028 10.55 7.40 8.39 10.39 6.21 6.99
The various values of seasonal factor for different months are given in Table 4.19 and shown
in Figure 4.3.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-127
Feasibility Report
Table 4.19: Monthly Sale of Motor Sprit and High Speed Diesel in Karnataka
Month Sale of MS+HSD (in KL) Seasonal Factors Apr-05 266750 0.9160 May-05 266500 0.9170 Jun-05 239500 1.0200 Jul-05 246500 0.9910 Aug-05 197500 1.2370 Sep-05 230000 1.0620 Oct-05 239500 1.0200 Nov-05 215000 1.1360 Dec-05 263500 0.9270 Jan-06 250000 0.9770 Feb-06 237500 1.0290 Mar-06 279680 0.8740 Av Monthly Sale 244328
Figure 4.3: Showing Sale of High Speed Diesel in Karnataka.
4.4.2 Recommended Traffic Growth
All the techniques used for traffic growth estimation have been examined except
Revenue Growth technique because Toll Plaza is recently installed and do not have
the enough revenue collection data.
Monthly Sale of Motor Spirit and High Speed Diesel in Karnataka
0
50000
100000
150000
200000
250000
300000
Feb-05 Apr-05 May-05 Jul-05 Sep-05 Oct-05 Dec-05 Feb-06 Mar-06
Months
Sale
of S
M+H
SD (i
n K
L)
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 4-128
Feasibility Report
The analysis shows that the growth rate estimated by Registered Vehicles and
Economic indicator technique is more than 10%. The data analysis is for the whole
of Karnataka state and we are considering only the Dharawad – Belgaum (NH-4)
stretch. There is no separate data available for this section. The growth rate worked
out from the analysis of past trend is 0-6% for different categories of vehicles.
Hence, the growth rate of 5% for all types of vehicles appears to be reasonable and
has been considered in the assessment of future traffic. The assessed future total and
tollable traffic is given in Table 4.20.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-129
Feasibility Report
Table - 4.20 - PROJECTED FUTURE TRAFFIC Location Km : 486.300
Motorised Traffic Non Motorised Traffic
Oth
er N
on m
otor
ised
V
ehic
les
Tot
al T
raff
ic
Thr
ee W
heel
er/A
uto
Ric
ksha
w
Car
/Jee
p/T
axi
BUS
LC
V
Truck Agri. Tractor
Cyc
le
Cyc
le R
icks
haw
Animal drawn
Min
i
Stan
dard
2 A
xle
(6 w
heel
er)
3 A
xle
(10
Whe
eler
)
Atr
icul
ated
/Sem
i A
tric
ulat
ed
Mul
ti A
xle
With
Tra
iler
With
out t
raile
r
Bul
lock
Car
t
Hor
se/c
amel
NO PCU NO
293 2305 277 1397 1183 2885 1328 274 14 151 75 268 21 45 3 0 12485 25652.5 9663 374 2942 354 1783 1510 3682 1695 350 18 193 96 342 27 57 4 0 15934 32740 12333 477 3755 451 2276 1927 4699 2163 446 23 246 122 437 34 73 5 0 20337 41785 15740 609 4792 576 2904 2459 5998 2761 570 29 314 156 557 44 94 6 0 25955 53330 20089 777 6116 735 3707 3139 7655 3524 727 37 401 199 711 56 119 8 0 33126 68064 25639 992 7806 938 4731 4006 9770 4497 928 47 511 254 908 71 152 10 0 42279 86868 32722 1266 9962 1197 6038 5113 12469 5740 1184 61 653 324 1158 91 194 13 0 53959 110869 41763
Location Km : 514.000 370 3160 364 1194 1501 4120 1409 237 1 24 20 457 3 3 0 2 16093 30130 11986 472 4033 465 1524 1916 5258 1798 302 1 31 26 583 4 4 0 3 20539 38454 15298 603 5147 593 1945 2445 6711 2295 386 2 39 33 744 5 5 0 3 26214 49079 19524 769 6569 757 2482 3120 8565 2929 493 2 50 42 950 6 6 0 4 33456 62638 24918 982 8384 966 3168 3983 10932 3738 629 3 64 53 1213 8 8 0 5 42700 79944 31802
10931 1253 10701 1233 4043 5083 13952 4771 803 3 81 68 1548 10 10 0 7 54497 102031 4058913951 1599 13657 1573 5160 6487 17806 6090 1024 4 104 86 1975 13 13 0 9 69553 130220 51803
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-130
Feasibility Report
CHAPTER 6: CONDITION SURVEY AND
ANALYSIS OF STRUCTURES
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-131
Feasibility Report
CHAPTER 6: CONDITION SURVEY AND ANALYSIS OF STRUCTURES
TABLE OF CONTENTS
6.1 Introduction 6-1 6.2 Cross Drainage Structures 6-1 6.2.1 Major Bridge 6-2 6.2.2 Minor Bridge 6-5 6.2.3 Culverts 6-8 6.3 Grade separated structures 6-19 6.3.1 Flyover/Grade Separator/Vehicular Underpass 6-19 6.3.2 Cattle Crossings 6-22 6.3.3 Pedestrian Underpass/sub-bay 6-24 6.4 Rail-Road Structures 6-24
LIST OF TABLES
Table 6.1 Number of Bridges and Culverts 6-1 Table 6.2 Details of existing major bridges and Viaduct 6-4 Table 6.3 Details of existing minor bridges 6-6 Table 6.4 Pipe Culvert (km 495 to km 515) 6-9 Table 6.5 Details of Box Culverts 6-10 Table 6.6 Details of Pipe Culverts 6-14 Table 6.7 Number of Grade Separated Structures 6-19 Table 6.8 Details of Flyover/Grade Separator/Vehicular Underpass 6-20 Table 6.9 Details of Existing Cattle Crossings 6-23 Table 6.10 Details of Existing Pedestrian Underpass/sub-bay 6-25 Table 6.11 Details of ROB 6-26
CHAPTER 6
CONDITION SURVEY AND ANALYSIS OF STRUCTURES
6.1 Introduction
A visual inspection of the existing structures on the Project Highway was carried
out during December 2007-February 2008. Relevant structural and General
Arrangement drawings as per DPR, Good for Construction and As-built drawings
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-132
Feasibility Report
were also collected from the NHAI and Supervision Consultants for the two
contract packages and studied. The Condition Survey reports of the earlier DPR
Consultants were also collected and studied.
6.2 Cross Drainage Structures
There are 2 major bridges, 7 minor bridges and 175 numbers of culverts in the
Project Highway. There is also one viaduct in Package II. Package wise details
are given in Table 6.1.
Table 6.1 Number of bridges and culverts
Item Package III (km 433.0 to km 495.0)
Package II (km 495.0 to km 515.0)
Total
Major bridge 1 1
2
Minor bridge 5 2 7
Culverts 129 46 175
Viaduct - 1 1
6.2.1 Major bridges
Details of existing major bridges are given in Table 6.2. Inventory survey report
of existing major bridges is given in Appendix 6.1. A brief description of each of
the major bridge is given below.
i) Major bridges at km 473.150
A major river Malprabha crosses the Project Highway in km 474. There
are three separate bridges across Malprabha River at km 473.150. Initially
a submersible bridge was there, followed by a 2-lane high level bridge and
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-133
Feasibility Report
another 3-lane high level bridge as part of up-gradation to 4-lanes during
2001-2006. Two high level bridges are having 9 spans of 24 m each. The
superstructure of both the bridges is simply supported Reinforced
Concrete T-Beam cum Slab type. Total length of bridge is 216 m. There is
another submersible bridge on the left hand side. It gets submerged during
rainy season and remains submerged up to November/December
depending upon the rainfall. During dry season this is used as service road
by local traffic. This bridge is proposed to be retained for use as at present.
a) The old bridge for Dharwad-Pune side traffic lanes is having 2-
lane (7.5 m) carriageway with 1.5 m wide footpaths and RCC
Pedestrian railings on either side. It has well foundations and RCC
substructure. The total top width including railing and footpaths is
11.0 m. The overall condition of the existing bridge is good. Minor
repairs are required for the footpath pre-cast slabs. RCC railings
have been provided at the outer end of the bridges. The footpath on
the median side is of no use in a 4/6 lane Highway, but it can not
be used as carriageway, because of inadequate design. Since the
bridge is having well foundations, and T-beam type superstructure,
it can not be widened to 3-lanes. The options available are either to
construct a new 3-lane bridge in place of existing 2-lane Bridge or
to construct another 2-lane bridge by the side of existing bridge.
Since existing bridge is structurally sound, it may not be proper to
dismantle it prematurely. As per the present day traffic and future
projections, the 2-lane bridge may cater to traffic up to the year
2020 at level of service C/D.
In view of the above, it is proposed to retain the existing old
bridge as such without adding any new structure. This would
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-134
Feasibility Report
be included as variation/deviation in Schedule-D of the
Concession Agreement.
As per 6-lane Manual crash barrier is required to be provided
between carriageway and footpath. We propose metal beam type
crash barrier on either side of the carriageway. The old pedestrian
railing is also to be replaced on the outer side by steel railing to
match with the new bridge railing. Similarly, the expansion joints
are to be replaced by new strip seal type joints.
b) The new Malprabha bridge is on Pune-Dharwad side traffic lanes
and is having 3-lane (11 m) carriageway with 1.5 m wide footpath
and Steel Pedestrian railings on the outer side and concrete crash
barriers on both sides of the carriageway. It has RCC bored cast in
place pile foundations and RCC piers and abutments. The total top
width including railing and footpaths is 13.75 m. It was
constructed during 2002-2006 as part of 4-laning project. The
overall condition of the existing bridge is very good. Since the
bridge is having 3-lane carriageway and a footpath, no further
widening is proposed.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-135
Feasibility Report
Table 6.2: Details of Existing Major Bridges and Viaduct S.No. Location
(km) Side Span
Arrangement [No x Length
(m)]
Total length
of bridge
(m)
Type of Super Structure
Type of sub-
structure
Type of foundation
Carriageway Width (m)
Footpath width (m)
Total Width
(m)
Adequacy of Water
way
Remarks
1 2 3 4 5 6 6 6 12 12
1 473.150 LHS 9 X 24 m 216.000 PSC Girder RCC Well 7.5 2 x 1.5 m 11 A Not to be widened
1 473.150 RHS 9 X 24 m 216.00 PSC Girder RCC Pile 11 1 X 1.5
m 13.75 A Not to be widened
2 498.810 LHS 4 X 3 X 5 m 71.240 RCC Box RCC Box RCC Box 11.25 1 X 1.5
m 13.75 A Not to be widened
2 498.810 RHS 4 X 3 X 5 m 71.240 RCC Box RCC Box RCC Box 11.25 1 X 1.5
m 13.75 A Not to be widened
Via-duct
1 509.150 LHS 2 X 30 m + 1 X 10
m 76.606 PSC Girder + RCC RCC
RCC - Open 12.0 - 13.0 A Not to be widened
1 509.150 RHS 2 X 30 m + 1 X 10
m 76.606 PSC Girder + RCC RCC
RCC - Open 12.0 - 13.0 A Not to be widened
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-136
Feasibility Report
ii) Major Bridge at km 498.810
At this location there was one 2-lane RCC Box type bridge 71.24 m long
having 4-units of 3-cell, 5m span and 3 m height each, which was
constructed during nineties as part of Belgaum bypass to pass the
discharge of a Nalla. While preparing the DPR for 4-laning of this section,
it was observed that the vertical clearance provided was not adequate, as a
result during heavy floods the water heads up on the up stream side and
causes flooding in the area. Therefore, it was decided to increase the vent
height. At present there are two identical RCC box type structures, one for
each direction of traffic, which were constructed during 2001-2004 as part
of 4-lane work. The carriageway width is 11.25 m and overall width is
13.75 m, which include crash barriers on either side of carriageway, 1.5 m
wide footpath on outer side and pedestrian railing on the outer side. No
further widening is proposed. Photo 6.3 shows picture of the bridges.
(iii) Viaduct at km 509.150
While preparing DPR for 4-lane project highway it was found necessary to
construct a viaduct for the villagers to cross for reaching a well and also to
facilitate approach to the grave yard on the right side of the road, it was
decided to construct a viaduct having 2 spans of 30 m and one span of 10
m (over a grave). There are two identical structures having 12.0 m wide (
3-lane) carriageway each and overall width of 13.0 m inclusive of crash
barriers.
No further widening is proposed.
6.2.2 Minor bridges
Details of existing minor bridges are given in Table 6.3. Inventory survey report
of existing minor bridges is given in Appendix 6.2. A brief description of each of
the minor bridge is given below.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-137
Feasibility Report
On A3 paper
Table 6.3
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-138
Feasibility Report
i) Minor Bridge at km 440.659
The existing bridges, two numbers for main carriageway are having same
3 lane wide carriageway. Both the bridges are of RCC Box type. The
condition of all the components is very good.
ii) Minor Bridge at km 453.856
The existing bridges, two numbers for main carriageway are having 3 lane
carriageway of 11.0 m. The bridge for Dharwad-Pune side traffic is RCC
Box type and that on Pune- Dharwad side traffic is RCC solid slab type
having 1-span of 8 m. The condition of all the components is very good.
iii) Minor Bridge at km 478.054
The existing bridges, two numbers for main carriageway are having 3 lane
carriageway (11.0 m). The bridge for Dharwad-Pune side traffic is RCC
Slab type and that on Pune- Dharwad side traffic is RCC Box type having
3-span of 8 m. The condition of all the components is very good.
iv) Minor Bridge at km 483.507
The existing bridges, two numbers for main carriageway are having 3 lane
carriageway (11 m). The bridge for Dharwad-Pune side traffic is RCC
Slab type and that on Pune- Dharwad side traffic is RCC Box type having
3-span of 8 m. The condition of all the components is very good.
v) Minor Bridge at km 491.268
The existing bridges, two numbers for main carriageway are having 3 lane
carriageway width (11.0 m). The bridge for Dharwad-Pune side traffic is
RCC Slab type and that on Pune- Dharwad side traffic is RCC Box type
having 1-span of 10.5 m. The condition of all the components is very
good.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-139
Feasibility Report
vi) Minor Bridge at km 499.060
At this location there was one 2-lane RCC Box type 17.8 m long bridge
having 1-unit of 3-cell, 5m span and 3 m height, which was constructed
during nineties as part of Belgaum bypass to pass the discharge of a Nalla.
While preparing the DPR for 4-laning of this section, it was observed that
the vertical clearance provided was not adequate, as a result during heavy
floods the water heads up on the up stream side and causes flooding in the
area. Therefore, it was decided to increase the vent height. At present there
are two identical RCC box type structures, one for each direction of
traffic, which were constructed during 2001-2004 as part of 4-lane work.
The carriageway width is 11.25 m and overall width is 13.75 m, which
include crash barriers on either side of carriageway, 1.5 m wide footpath
on outer side and pedestrian railing on the outer side. No further widening
is required.
vii) Bridge at km 513.26
Historically there was one stone masonry arch bridge having narrow width.
Subsequently, one 2-lane wide bridge having 3 spans of 12.6 m each without
footpaths was constructed. Later during 2001-2006 another 3-lane bridge for
Pune-Dharwad side traffic was constructed as part of 4-lane project. Thus there
are three bridges existing at present. The old narrow bridge is being used as
service road and is proposed to be retained. The second bridge is in distressed
condition and some rehabilitation works are in progress. This bridge is proposed
to be dismantled and a new 3-lane bridge is proposed at this location for
Dharwad-Pune side traffic
6.2.3 Culverts
km 495.0 to 515.0
In this section there are Hume pipe culverts at 71 locations. The diameter of pipes
in Main Carriageway is 900 mm to 1200 mm whereas on service road pipes of
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-140
Feasibility Report
diameter 600 mm have also been used. All the pipe culverts are having formation
width same as of road in the approaches. Water way is found to be adequate.
Details are given in Table 6.4.
Table 6.4: Pipe Culvert (km 495 to km 515)
S.No. Description SR-LHS MCW SR-RHS
1 600 mm dia Pipe Culverts 5 0 11
2 900 mm dia Pipe Culverts 28 31 25
3 1000 mm dia Pipe Culverts 13 13 11
4 1200 mm dia Pipe Culverts 2 2 0
Total no. of Pipe Culverts 48 46 47
In km 433 to 495
In this section 69 box culverts there are in the main carriageway and 26 box
culverts in the service road. In addition there are 59 pipe culverts. Overall there
are 59 box culverts and 130 pipe culverts. Details of box and pipe culverts are
given in Table 6.5 and Table 6.6 respectively. All the pipe culverts and box
culverts are having carriageway as the top width of approach road. All these
structures require widening by 3.5 m in outer side.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-141
Feasibility Report
Table 6.5
On A 3 paper
1st
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-142
Feasibility Report
2nd
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-143
Feasibility Report
3rd
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-144
Feasibility Report
4th
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-145
Feasibility Report
Table 6.6
On A-3 paper
1st
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-146
Feasibility Report
2nd
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-147
Feasibility Report
3rd
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-148
Feasibility Report
4th
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-149
Feasibility Report
5th
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-150
Feasibility Report
6.3 Grade separated structures
There are 47 grade separated structures comprising of 16 flyovers/grade
separators/vehicular underpasses, 22 cattle passes, 8 pedestrian sub-
bays/underpasses and one viaduct. Spread of such Structures package-wise are
given in Table 6.7.
Table 6.7: Number of Grade Separated Structures
Item Package III (km 433.0 to km 495.0)
Package II (km 495.0 to km 515.0)
Total
Flyover/Grade separator/Vehicular underpass
9 7 16
Cattle pass 22 Nil 22
Pedestrian underpass/sub-bay
2 6 8
The inventory of existing grade separated structures is given in Appendix
6.3 to 6.5.
6.3.1 Flyover/Grade separator/Vehicular underpass
The details of existing Flyover/Grade separator/Vehicular underpasses are given
in Table 6.8. Three types of designations have been given to the existing
structures, viz., flyover and grade separator (for structures having more than 10 m
wide opening), and vehicular underpass for structures having opening of 10 m.
All the three types of structures serve the same purpose, i.e., provide movement of
vehicles at two different grades.
Consultancy Services for 6 Laning of Belgaum-Dharwad section of NH-4 (NHDP V/MC-II/BOT/DPR/19)
Consulting Engineers Group Ltd 6-151
Feasibility Report
Table 6.8: Details of Existing Vehicular Underpasses S.No. Location
(km) Side Span
Arrangement [No x Span
(m)]
Vertical clearance
(m)
Total length of structure
(m)
Type of Super Structure
Type of sub-
structure
Type of foundation
Type of Retaining
walls
Carriageway Width (m)
Footpath width (m)
Total Width
(m)
Remarks
1 2 3 4 5 6 7 8 9 10 11 12 13 14 1 433.050 LHS 3x21.5m 5.500 64.500 RCC T-beam RCC RCC Open R.E. 7.5 - 8.5 Not to be widened 2 433.705 BOTH 1x10 m 5.500 12.800 RCC Box RCC Box RCC Box R.W. 2x10.5 m - 26.5 Not to be widened 3 439.625 BOTH 1x10 m 5.500 12.800 RCC Box RCC Box RCC Box R.W. 2x10.5 m - 26.5 Not to be widened 4 458.560 BOTH 1x23 m 5.500 7.600 RCC T-beam RCC RCC Open R.E 2X11 m - 24.5 Not to be widened 5 465.715 BOTH 1x10 m 5.500 12.800 RCC Box RCC Box RCC Box R.W. 2x10.5 m - 26.5 Not to be widened 6 468.838 BOTH 1x10 m 5.500 12.800 RCC Box RCC Box RCC Box R.W. 2x10.5 m - 26.5 Not to be widened 7 474.514 BOTH 2x10 m 5.500 23.000 RCC Box RCC Box RCC Box R.E 2X11 m - 24.5 Not to be widened 8 484.311 BOTH 2X10 m 5.500 9.700 RCC Box RCC Box RCC Box R.E 2X11 m - 24.5 Not to be widened 9 490.900 BOTH 1x10 m 5.500 12.800 RCC Box RCC Box RCC Box R.W. 2x10.5 m - 26.5 Not to be widened
10 498.050 BOTH 2X.21 m 5.500 43.200 RCC Voided Slab RCC Open -Raft
R.W. (to be wall) 2X11 m 2 X 1.5 m 28.5 Not to be widened
11 501.083 BOTH 2X20 m 5.500 40.500 RCC Girder RCC Pile R.E. 2X11 m 2 X 1.5 m 28.5 Not to be widened 12 502.775 BOTH 2X20 m 5.500 40.500 RCC Girder RCC RCC Open R.E. 2X11 m 2 X 1.5 m 28.5 Not to be widened 13 503.870 BOTH 1X21 m 5.500 21.500 RCC Voided Slab RCC RCC Open R.W. 2X11 m 2 X 1.5 m 28.5 Not to be widened 14 508.385 BOTH 2X20 m 5.500 40.500 RCC Girder RCC RCC Open R.E. 2X11 m 2 X 1.5 m 28.5 Not to be widened 15 510.889 BOTH 1X21 m 5.500 21.500 RCC Voided Slab RCC RCC Open R.E. 2X11 m 2 X 1.5 m 28.5 Not to be widened