chapter-1 introductionenvironmentclearance.nic.in/.../eia/22032020lemk1qx7eia_.pdfeia for up...

299
EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-1 Introduction Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31 HSIIDC Limited Authorized Signatory CHAPTER-1 INTRODUCTION 1.0 INTRODUCTION Modern Industrial Estate comprising of about 620 acres was set up at Kundli by the Haryana govt. on the side of NH-1 at Haryana-Delhi border to give relief to Delhi from its increasing industrial pressure. Plots of various categories ranging from 10 Marla plots to two acres have been carved out. In this area different industries related to footwear, iron & fabrication, plastic goods, pharmaceuticals, chemicals, confectionary / food processing, auto mobiles ancillaries and electronic & electrical good etc. have been established. There is an existing CETP of capacity 4 MLD which was constructed about 15 years ago on approx 28,105 sq. m (7 Acres ) of triangular shaped land in Phase IV, HSIIDC, Kundli to treat the effluent of this area (Phase I to IV). The outlet of the treated effluent is being disposed off directly in the drain running besides the CETP. Now with the increase in industrial activities in the area (Phase III, IV, IV sector-56), the quantity of effluent at the CETP is expected to increase and hence it has become necessary to increase the capacity of the existing system from 4 MLD to 10 MLD. The proposed up gradation is coming up within the same premises. Total estimated cost including O&M, Power, Chemicals, Sludge disposal and Departmental Over head expenses will be Rs. 45.86 Crores and Total Estimated capital investment will be Rs. 21.02 crores for the proposed CETP up-gradation. The project falls under “item 7(h) of Schedule of Environment Clearance Notification dated 14th September, 2006, i.e. Common Effluent Treatment Plant, under Category –“B”. However, due to presence of Haryana-Delhi interstate boundary at a distance of 2.3 Km in S direction the proposed project will be treated as Category “A” project. As per the EIA Notification and subsequent amendments, “if any of the existing or proposed member units of the said CETP produces or proposes to produce any product

Upload: others

Post on 16-Feb-2021

3 views

Category:

Documents


0 download

TRANSCRIPT

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    CHAPTER-1

    INTRODUCTION

    1.0 INTRODUCTION

    Modern Industrial Estate comprising of about 620 acres was set up at Kundli by the

    Haryana govt. on the side of NH-1 at Haryana-Delhi border to give relief to Delhi

    from its increasing industrial pressure. Plots of various categories ranging from 10

    Marla plots to two acres have been carved out. In this area different industries related

    to footwear, iron & fabrication, plastic goods, pharmaceuticals, chemicals,

    confectionary / food processing, auto mobiles ancillaries and electronic & electrical

    good etc. have been established. There is an existing CETP of capacity 4 MLD which

    was constructed about 15 years ago on approx 28,105 sq. m (7 Acres ) of triangular

    shaped land in Phase IV, HSIIDC, Kundli to treat the effluent of this area (Phase I to

    IV). The outlet of the treated effluent is being disposed off directly in the drain

    running besides the CETP.

    Now with the increase in industrial activities in the area (Phase III, IV, IV sector-56),

    the quantity of effluent at the CETP is expected to increase and hence it has become

    necessary to increase the capacity of the existing system from 4 MLD to 10 MLD.

    The proposed up gradation is coming up within the same premises.

    Total estimated cost including O&M, Power, Chemicals, Sludge disposal and

    Departmental Over head expenses will be Rs. 45.86 Crores and Total Estimated

    capital investment will be Rs. 21.02 crores for the proposed CETP up-gradation.

    The project falls under “item 7(h) of Schedule of Environment Clearance

    Notification dated 14th September, 2006, i.e. Common Effluent Treatment Plant,

    under Category –“B”. However, due to presence of Haryana-Delhi interstate

    boundary at a distance of 2.3 Km in S direction the proposed project will be treated

    as Category “A” project.

    As per the EIA Notification and subsequent amendments, “if any of the existing or

    proposed member units of the said CETP produces or proposes to produce any product

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    requiring environmental clearance, then the CETP shall need environmental

    clearance”. Proposed CETP involves the treatment of waste water from the

    Metallurgical Industries which requires Environment Clearance. Therefore, the project

    requires a prior environmental clearance from MoEF&CC, New Delhi.

    M/s HSIIDC has retained the services of Gaurang Environmental Solutions, Jaipur to

    undertake Environmental Impact Assessment (EIA) studies for assessing the impact of

    the Up gradation of existing CETP from 4 MLD to 10 MLD capacity on various

    environmental parameters in the study area and to prepare an Environment Management

    Plan (EMP) for negating the adverse impacts of the project to obtain Environment

    Clearance from MoEF&CC, New Delhi.

    The application for prior Environmental Clearance (Form-1) was uploaded on dated

    07.03.2019. Project was consider in 40th Expert Appraisal Committee (Infra-2) (S. No.

    40) Dated 23rd April’ 2019. Project was reconsider for Terms of Reference in in 43rd

    Expert Appraisal Committee (Infra-2) (S. No. 43.3.10) Dated 20-22 August’ 2019 and

    the project was granted with standard Terms of Reference vide letter no. F. No.10-

    23/2019-IA-III Dated 31st October 2019 by MoEF&CC. Copy of Terms of Reference

    is enclosed as Annexure I. Baseline studies for the project were carried out during

    December’2018 to February’ 2019 (winter season).Public consultation for the project

    has been exempted as the proposed up gradation of existing CETP area falls under the

    notified industrial area. The industrial area notification gazette is enclosed as

    Annexure -VII.

    The proposed up gradation of existing common effluent treatment plant will be based

    on physical & chemical treatment for removal of excessive inorganic COD, TSS &

    BOD beside removal of color & maintenance of equalized & constant PH & Flow rate

    prior to biological process i.e. Activated Sludge process based on extended aeration

    principal. That after biological Treatment process treated effluent shall be further

    treated in pressure Filter, Carbon filter and shall be disinfected with chlorine before

    final disposal for reuse being designed on the concept of Zero liquid discharge.

    Waste water thus generated by the associated industries will be lifted through

    dedicated pipeline system after meeting the pre treatment discharge standards

    prescribed by HSIIDC. Waste water generated from Pharmaceutical and chemical

    member industry will be treated by themselves and treated water will be discharge as

    per standards prescribed by HSPCB and CPCB. The waste water after treatment shall

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    meet the discharge standards laid down by MoEF&CC and HSPCB. It has been

    proposed by HSIIDC to reuse treated effluent for irrigation, watering of parks &

    greens etc. which will require multimedia filtration with Pressure Filter, Activated

    Carbon Filter followed by disinfection for removal of coliforms and helminthes so as

    to achieve Zero liquid discharge.

    The HSIIDC has always taken lead in providing best possible infrastructure facilities

    in all the Industrial Estates. Accordingly it has been decided that Disposal works

    Common Effluent Treatment Plant & Disposal of Treated Effluent as per CPHEEO

    Norms be designed and got executed at site.

    This Environmental Impact Assessment (EIA) report has been prepared to provide

    information on the potential environmental, social and economic impacts of the

    project. It also aims to make recommendations for mitigation of the potential negative

    impacts and enhancement of the positive ones. Baseline data generation including

    detailed field survey was carried out and potential environmental impacts of the

    project activities were identified, assessed and documented. This report has been

    prepared as per the Terms of References (Standard ToR issued by MoEF&CC, New

    Delhi), EIA Notification, 2006 & amendments.

    1.2 IDENTIFICATION OF PROJECT & PROJECT PROPONENT

    1.2.1 Identification of Project

    There is an existing CETP of capacity 4 MLD which was constructed about 15 years

    ago on approx 28,105 sq. m (7 Acres ) of triangular shaped land in Phase IV,

    HSIIDC, Kundli to treat the effluent of this area (Phase I to IV). The outlet of the

    treated effluent is being disposed off directly in the drain running besides the CETP.

    Now with the increase in industrial activities in the area (Phase III, IV, IV sector-56),

    the quantity of effluent at the CETP is expected to increase and hence it has become

    necessary to increase the capacity of the existing system from 4 MLD to 10 MLD

    capacity (based on extend aeration system) coming up at Phase-IV, Industrial Estate,

    Kundli, Sonipat, Haryana.

    The proposed project falls under “item 7(h) of Schedule of Environment Clearance

    Notification dated 14th September, 2006 and as on date amended on date 17th April’

    2015, i.e. Common Effluent Treatment Plant, under Category –“B”. However, due

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    to presence of Haryana-Delhi interstate boundary at a distance of 2.3 Km in S

    direction the proposed project will be treated as Category “A” project. As per the

    EIA Notification and subsequent amendments, “if any of the existing or proposed

    member units of the said CETP produces or proposes to produce any product requiring

    environmental clearance, then the CETP shall need environmental clearance”.

    Proposed CETP involves the treatment of waste water from the Metallurgical

    Industries which requires Environment Clearance. Thus, the project requires

    environmental clearance. Project details are summarized as under:-

    Table 1.1: Brief details of the project

    S.

    No.

    Particulars Details

    1 Project Up gradation of existing CETP from 4

    MLD to 10 MLD capacity based on extend

    aeration system

    2 Promoter HSIIDC Limited

    3 Location Phase-IV, Industrial Estate, Kundli,

    Sonipat, Haryana

    4 Capacity Capacity Existing Proposed Total

    CETP 4 6 10

    5 Total Plot Area for Industrial

    Estates (Phase I, II, III & IV) 620 Acres

    6

    Total Plot Area

    Particula

    rs

    Existing Proposed Total

    Total plot

    area

    28,105

    sq. m

    (7 Acres

    )

    Within the

    existing

    premises

    28,105

    sq. m

    (7

    Acres )

    S. No.

    Particulars Existing (Sq.m)

    Proposed (Sq.m)

    Total (Sq.m)

    %

    1 Plant area 16,196.91 -- 16,196.91 57.63

    2 Green Area 5,160.08 -- 5,160.08 18.36

    3 Road &

    footpaths 2,481.68

    --

    2,481.68 8.83

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    4 Others Open

    area 4,266.33

    --

    4,266.33 15.18

    5 Total 28,105 -- 28,105 100

    7 Man Power Particula

    rs

    Existing Proposed Total

    Manpowe

    r

    13 no 30 during

    constructi

    on phase

    13 –

    operati

    on

    phase

    30 –

    constru

    ction

    phase

    8 Power Requirement and Source Particular

    s

    Existing Proposed Total

    Power and

    Source

    275 KW UHBVN Supply

    425 KW UHBVN Supply

    700 KW UHBVN Supply

    D.G. Set 300kVA (200 kVA:1No. + 100 kVA:1No.) Fuel used: HSD

    500 kVA (1No.) Fuel used: HSD

    3nos. 200kVA:1No. 100kVA:1No 500kVA:1No.

    9 Water Requirement and Source Particula

    rs

    Existing Proposed Total

    Water

    demand

    and

    3 KLD 0.6 – domestic use 2.4 KLD - chemical dosing

    3 KLD - chemical dosing

    6 KLD 0.6 – domestic use 5.4 KLD - chemical dosing

    source HSIIDC Industrial Water supply

    10 Waste Water generation Domestic waste water generation - 0.4 KLD

    Total Waste water Quantity for Existing CETP

    Capacity – 3927 KLD (3.93 MLD)

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Total Waste water Quantity for proposed CETP

    Capacity – 5252 KLD (5.25 MLD)

    11 Estimated Project Cost Total estimated cost including O&M, Power,

    Chemicals, Sludge disposal and

    Departmental Over head expenses will be Rs.

    45.86 Crores and Total Estimated capital

    investment will be Rs. 21.02 crores for the

    proposed CETP up-gradation.

    1.2.2 Identification of Project Proponent

    The details of the project proponent are given below:

    Name of the

    applicant

    HSIIDC Limited

    Name and address Mr. Arun Garg AGM (IA)

    HSIIDC Office, Industrial Estate, Kundli, Distt.- Sonipat

    Status of Project Expansion project (Freshly applied for Environmental

    Clearance)

    Copy of Land document is attached as Annexure II.

    1.3 BRIEF DESCRIPTION OF PROJECT

    1.3.1 Nature of the Project

    The proposed project Up gradation of existing CETP from 4 MLD to 10 MLD

    capacity based on extend aeration system coming up at Phase-IV, Industrial Estate,

    Kundli, Sonipat, Haryana over an area of 28,105 sq.m.(7 acre).

    The proposed project falls under “item 7(h) of Schedule of Environment Clearance

    Notification dated 14th September, 2006 and as on date amended on date 17th

    April’ 2015, i.e. Common Effluent Treatment Plant, under Category –“B”.

    However, due to presence of Haryana-Delhi interstate boundary at a distance of 2.3

    Km in S direction the proposed project will be treated as Category “A” project.

    As per the EIA Notification and subsequent amendments, “if any of the existing or

    proposed member units of the said CETP produces or proposes to produce any product

    requiring environmental clearance, then the CETP shall need environmental

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    clearance”. Proposed CETP involves the treatment of waste water from the

    Metallurgical Industries which requires Environment Clearance. Therefore, the project

    requires a prior environmental clearance from MoEF&CC, New Delhi. Thus, the

    project requires environmental clearance.

    1.3.2 Size of the Project

    Project facilities are as under:

    S. No. Project Capacity

    1. Common Effluent Treatment Plant (based on

    extend aeration system)

    Up gradation of existing

    CETP from 4 MLD to 10

    MLD capacity

    1.3.3 Location of the Project

    The proposed up gradation is coming up within the existing premises. The existing

    CETP is situated at Phase-IV, Industrial Estate, Kundli, Sonipat, Haryana.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure: 1.1 Location Map

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure: 1.2 Google Map

    The latitude longitude of the project site is as under:

    1 2

    Latitude : 280 53’11.71” N Longitude: 770 7’ 51.32” E

    Latitude : 280 53’4.37” N Longitude: 770 7’ 51.43” E

    3 4

    Latitude: 280 53’4.35” N Longitude: 770 7’42.44” E

    Latitude: 280 53’4.88” N Longitude: 770 7’ 42.45” E

    The project site falls in Survey of India Toposheet No. 53 H/1, 53 D/13, 53 H/5 and

    53 G/4. Geographical location of the project site is shown in Figure-1.3.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure-1.3: Geographical Location of The Project (10 km)

    1.3.4 Project Importance to the Country / Region

    Establishment of effluent treatment plants for individual industries especially in the

    small scale sector in the various industrial estates in India, to produce the effluent of

    desired quality before discharge is not feasible in the Indian context. Firstly, because

    it is expensive on both the capital and operating cost front and secondly, there is no

    guarantee of performance by the individual industries. Further, the disposal of treated

    effluents is also problematic as every individual industry cannot reach the water body

    through its own pipeline nor can it purchase land for inland irrigation. Thus,

    Government of India floated the idea of Common effluent treatment plant to

    overcome these problems. Accordingly Ministry of Environment, Forest & Climate

    Change, Government of India instructed the various State Pollution Control Boards to

    examine the possibilities of establishing CETP’s in various industrial estates. In

    response to the directive issued by the Central Governments, the State Governments

    started identifying the various locations for CETP’s. Establishment of CETP has

    following advantages:

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    • Saving in Capital and Operating cost of treatment plant. The Common treatment

    is always cheaper than small scattered treatment units.

    • Contribution of nutrient and diluting potential make the complex industrial waste

    more amenable to degradation.

    • The neutralization and equalization of heterogeneous waste makes its treatment

    techno-economically viable.

    • Professional and trained staff can be made available for operation of CETP which

    is not possible in case of individual plants.

    • Disposal of treated wastewater & sludge becomes more organized.

    • Reduced burden of various regulatory authorities in ensuring pollution control

    requirement.

    Water is our most important resource. The available supply of fresh water is an

    absolute deadline beyond which no community, state or nation can ever go. When

    humanity runs out of clean water, everything stops. That is the end of road for a man

    and his activities. Saving our clean water is thus a must. When untreated or

    inadequately treated waste waters are discharged, these have adverse affect on the

    body of water into which these wastes are disposed. The type of treatment of waste

    water would depend upon the use of effluent itself or of receiving body of water into

    which effluent is discharged. The degree of treatment of waste water would further

    depend upon the discharge of receiving body of water. If small quantity of waste

    water is discharged in a river or into the sea, the degree of treatment would be much

    less than if the same quantity of waste water is discharged into a small stream. When

    receiving body of water is already polluted because of discharge of waste into it, the

    extent of new discharge of waste into it would be limited.

    Waste water thus generated by the associated industries will be lifted through

    dedicated pipeline system after meeting the pre treatment discharge standards

    prescribed by HSIIDC. The waste water after treatment shall meet the discharge

    standards laid down by MoEF&CC and HSPCB. Waste water generated from

    Pharmaceutical and chemical member industry will be treated by themselves and

    treated water will be discharge as per standards prescribed by CPCB. It has been

    proposed by HSIIDC to reuse treated effluent for irrigation, watering of parks &

    greens etc. which will require multimedia filtration with Pressure Filter, Activated

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Carbon Filter followed by disinfection for removal of coliforms and helminthes so as

    to achieve Zero liquid discharge.

    1.4 SCOPE OF THE STUDY

    The zone comprising of 10 km radius around the project site is considered as the study

    area. The study area map is shown in Figure-1.3. The scope of study broadly includes:

    To conduct literature review and to collect data relevant to the study area;

    Generate field sampling results of environmental attributes to establish the

    baseline environmental status;

    Collate and compile secondary data including socio-economic data from

    published literature / Government publications;

    Estimate pollution loads that would be generated by the proposed project

    Evaluate the predicted impacts on various environmental attributes in the study

    area by using scientifically developed and widely accepted environmental

    impact assessment methodologies

    Preparing an Environment Management Plan (EMP) to mitigate the predicted

    impacts

    To identify critical environmental attributes required to be monitored and

    suggest Post Project Monitoring Plan and

    To carry out Risk Assessment and prepare suitable Disaster Management Plan

    Preparing an EIA report, in line with the standard TOR issued by MoEF&CC,

    New Delhi.

    To determine existing conditions of various environmental attributes, field

    studies have been conducted during December’ 2018 to February’ 2019

    covering Winter Season.

    The EIA/EMP report has been prepared in line with the Minutes of Meeting

    recommended by MoEF&CC, New Delhi. The compliance of Terms of Reference

    (regulatory scoping carried out as per TOR) in following Table-1.2.

    TABLE – 1.2

    COMPLIANCE TO TERMS OF REFERENCE

    S.

    No. Terms of References Points Compliance

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    1.

    Reasons for selecting the site with

    details of alternative sites

    examined/rejected/selected on

    merit with comparative statement

    and reason basis for selection. The

    examination should justify site

    suitability in terms of

    environmental angle, resources

    sustainability associated with

    selected site as compared to

    rejected sites. The analysis should

    include parameters considered

    along with weight age criteria for

    short-listing selected site.

    The existing CETP

    is located in HSIIDC Industrial area Kundli,

    Haryana where the effluent is being

    transported through pipeline network.

    Proposed up gradation is coming up within the

    same premises.

    The site is situated in notified industrial area,

    considering the environmental and economic

    feasibility.

    The transport of effluent will be through

    pipeline. Thus, it prevents any possibility of

    direct contact of untreated effluent with

    surface water.

    Proximity to effluent generating industries

    Uninterrupted power supply.

    Availability of power and water

    2.

    Details of the land use break-up

    for the proposed project. Details of

    land use around 10 km radius of

    the project site.

    This is up gradation of existing Common effluent

    Treatment Plant at HSIIDC IA, Kundli. The total plot

    area of the existing CETP is 28,105 sq.m which is 7

    acre. The proposed up gradation is coming up within

    the same premises. The land use breakup is as under:-

    S. No.

    Particulars Existing (Sq.m)

    Proposed (Sq.m)

    Total (Sq.m)

    %

    1 Plant area 16,196.91 -- 16,196.91 57.63

    2 Green Area 5,160.08 -- 5,160.08 18.36

    3 Road &

    footpaths 2,481.68

    --

    2,481.68 8.83

    4 Others Open

    area 4,266.33

    --

    4,266.33 15.18

    5 Total 28,105 -- 28,105 100

    Details of the land use around 10 Km radius of project site mentioned in section- 3.3 of

    chapter 3 of EIA Report.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    3.

    Details of member units, its

    production capacity, waste

    generation, characteristic and

    details of primary treatment

    provided by the member units.

    Preliminary treatment (based on specific

    requirements) will be done by member units before

    discharging their effluent into the CETP. Waste water

    generated from Pharmaceutical and chemical member

    industry will be treated by themselves and treated

    water will be discharge as per standards prescribed

    by CPCB. Details of member industries located in

    Phase I, II, III, IV, IV sector-56 are summarized as

    under:-

    WASTE WATER DETAILS FROM MEMBER UNITS FOR EXISTING CETP (4 MLD)

    S. No Types of Industries No of Industries Waste water generation in

    KLD

    1 Food Processing Unit 32 214

    2 Metallurgical 168 1253

    3 Plastic tubes 46 234

    4 Cement 1 10

    5 Chemical 20 227

    6 Paper Industry 4 24

    7 Agricultural 3 16

    8 Wood 5 24

    9 Pharmaceutical 14 82

    10 Cloths 63 981

    11 Rubber 27 222

    12 Computer 11 47

    13 Warehouse 19 134

    14 Packaging, plastic

    products & printing

    51 349

    15 Electronic 20 92

    16 Glass 4 58

    17 Leather & tanning 2 6

    18 Jwellery & accessories 7 57

    19 Miscellaneous 20 117

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    WASTE WATER DETAIL FROM MEMBER INDUSTRY FOR PROPOSED CETP (6 MLD)

    Total 617 3927

    S. No Types of Industries No of Industries Waste water generation in KLD

    1 Food Processing Unit 13 285

    2 Metallurgical 100 1694

    3 Plastic 33 440

    4 Cement/ Ceramics 5 64

    5 Chemical 09 117

    6 Paper Industry 1 12

    7 Agricultural 3 47

    8 Wood 6 83

    9 Pharmaceutical 13 156

    10 Textile 71 1020

    11 Rubber 12 229

    12 Computer 8 107

    13 Warehouse 3 52

    14 Packaging, plastic products

    & printing

    32 482

    15 Electronic 14 217

    16 Glass 1 20

    17 Leather & tanning 1 12

    18 Jwellery & accessories 3 40

    19 Miscellaneous 12 175

    Total 340 5252

    4. Details on present treatment and

    disposal systems. Existing effluent is presently being discharged into

    drainage as per HSIIDC Norms.

    5.

    Details of effluent collection

    system from member units level.

    Effluent will be collected through closed pipeline

    conveyance system. Member industries will

    discharge their effluent in the pipeline after meeting

    the pre treatment discharge standards prescribed by

    HSIIDC.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Member industries of CETP will be required to

    monitor specified quality parameters and flow rate of

    the effluent on daily basis and to submit the

    monitoring data to the CETP operator on regular

    basis. Continuous flow meters will also be installed at

    the outlet of the CETP to monitor the outlet effluent

    quantity.

    6. Details of hazardous waste

    collection, Sill proof arrangement.

    As per HWM Rules, 2016 and subsequent

    amendments, CETP sludge considered as Hazardous

    Waste.

    CETP sludge is collected at sludge drying beds which

    is properly lined and kept impervious.

    7. Examine and submit details of

    inlet characteristics.

    Effluent will be collected through closed pipeline

    conveyance system. Member industries will discharge

    their effluent in the pipeline after meeting the pre

    treatment discharge standards prescribed by HSIIDC &

    will be having following characteristics:

    S. No.

    Parameters Units Value

    1 pH -- 6 - 8.5

    2 BOD5 mg/l 450 3 COD mg/l 900 4 TSS mg/l 1200 5 Coliform MPN/100ml 1x107 6 Oil & Grease mg/l 100 7 Temperature oC 18-22 8 NH4- Nitrogen mg/l 45 9 TKN mg/l 40 10 TP as PO4 mg/l 10 11 Chromium mg/l 5 12 COD/ BOD ratio -- 2

    8.

    Details of the CETP with design

    parameters. Layout plan of CETP.

    And open spaces.

    The proposed project involves up gradation of existing

    Common Effluent Treatment Plant (CETP) from 4 to 10

    MLD capacities. The CETP is used for the treatment of

    waste water generated from Industrial Estates, Phase-IV,

    Kundli.

    S. Particulars Details

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    No

    1. Capacity 4 to 10 MLD

    2. Technology Extend Aeration System

    3. Status Proposed Up gradation of existing CETP

    4. Waste water generation

    Existing – 3927 KLD Proposed – 5252 KLD Total – 9179 KLD

    The CETP has been designed for following

    parameters:

    Influent Sewage Characteristics Parameters Units Value

    pH -- 6 - 8.5 BOD5 mg/l 450 COD mg/l 900 TSS mg/l 1200 Coliform MPN/100 ml 1x107 Oil & Grease mg/l 100 Temperature oC 18-22 NH4- Nitrogen mg/l 45 TKN mg/l 40 TP as PO4 mg/l 10 Chromium mg/l 5 COD/ BOD ratio -- 2

    Treated effluent Characteristics after secondary Treatment

    Parameters Units Value pH -- 7-7.5 BOD5 mg/l ≤10 COD mg/l ≤20 TSS mg/l ≤20 Coliform MPN/100 ml ≤10000 Oil & Grease mg/l ≤5 Temperature oC ≤1 NH4- Nitrogen mg/l ≤2 TP as PO4 mg/l ≤0.1 Chromium mg/l >0.2

    Treated effluent Characteristics after Tertiary Treatment

    Parameters Units Value pH -- 7-8.5 BOD5 mg/l

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    COD mg/l

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    at the CETP. CETP for storage of Chemicals & Sludge as follows

    Description Quantity

    Chemical House 01

    Sludge Storage Shed 01

    13.

    Examine and submit details of

    sludge / solid waste generated and

    method of disposal. MoU in this

    regard

    Details of sludge / solid waste generated and method

    of disposal is mentioned as under. Copy of MoU for

    disposal of existing solid waste is enclosed as

    Annexure – XVI.

    S.

    No.

    Particulars Category Quantity Mode of

    disposal Existing Proposed Total

    1. ETP Sludge 34.3 1000 Kg/day

    1500 Kg/day

    2500 Kg/day

    Collection, Storage in HWSA, Transportation and sent to GEPIL site for disposal

    2. Domestic solid waste

    -- 5.2 kg/day -- 5.2 kg/day Handled by Municipal Corporation, Kundli

    14.

    Details of water requirement,

    source and water balance chart.

    Particulars Existing Proposed Total

    Water

    demand

    3 KLD 0.6 – domestic use 2.4 KLD - chemical dosing

    3 KLD - chemical dosing

    6 KLD 0.6 – domestic use 5.4 KLD - chemical dosing

    Source HSIIDC Industrial Water supply

    Details of the water requirement along with water

    balance chart are mentioned in section – 2.4.3 of

    Chapter 2 in EIA Report.

    The flow diagram of Water Balance is shown in Fig.

    2.5 of Chapter – 2 in EIA Report.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    15.

    Details of green belt. 5160.08 sq. m. (18.36%) of plant area will be under green

    cover as per CPCB norms.

    Total Plot Area : 28,105 sq. m.

    Total Green Area : 5160.08 sq. m. (18.36%)

    Tree Required : Total Plot area /80

    : 28,105/80

    : 351.31 (says 351)

    Tree Provided : 370 nos.

    S. No Botanical Name Common

    Name

    Total

    1 Azadirachta indica Neem 72

    2 Dalbergia sissoo Shisham 74

    3 Cassia Fistual Amaltash 76

    4 Ficus Religiosa Peepal 70

    5 Ficus Benghalensis Bargad 78

    Total 370

    Details of green belt development is mentioned in section

    10.3.8 of chapter-10 in EIA Report.

    16.

    Details of performance

    monitoring, lab facility with

    technical persons.

    Laboratory facility is available with technical staff,

    Organizational structure mentioned in the report.

    CETPs’ organizational chart including the details of

    laboratory personals have been mentioned in Chapter

    6 of EIA Report.

    17.

    Details of litigation pending

    against the project, if any, with

    direction /order passed by any

    Court of Law against the Project

    should be given.

    There is no litigation pending against project.

    Affidavit regarding the same is enclosed as

    Annexure-XIII.

    18.

    The cost of the Project (capital

    cost and recurring cost) as well as

    the cost towards implementation of

    EMP should be clearly spelt out.

    Environmental management plan Budget

    Capital Cost – 99 lacs

    Recurring Cost – 11.8 lacs

    The detail for the same is mention in chapter – 10 in

    EIA Report.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    19. Details of water meters for inflow

    and outflow monitoring etc.

    Magnetic flow meter has already been installed at

    Inlet & outlet of the CETP.

    20.

    Any further clarification on

    carrying out the above studies

    including anticipated impacts due

    to the project and mitigative

    measure, project proponent can

    refer to the model ToR available

    on Ministry website

    http://moef.nic.in/Manual/CETPs.

    Complied with

    Addition ToR

    I Importance and benefits of the

    project.

    Importance and benefits of the project is mentioned

    in section 1.3.4 of chapter-1 in EIA Report.

    ii

    A chapter on Quantification and

    Characterization of inlet

    characteristic including

    methodology adopted.

    Quantification and Characterization of inlet

    characteristic is elaborated in Section – 2.6 of

    Chapter-2 of EIA Report.

    iii Process flow diagram of the

    proposed CETP.

    Process flow diagram is mentioned in figure 2.6 of

    chapter 2 in EIA Report.

    iv Layout plan of CETP. Layout plan of CETP is mentioned in figure-2.4 of

    chapter – 2 in EIA Report.

    v Cost of project and time of

    completion.

    Total estimated cost including O&M, Power,

    Chemicals, Sludge disposal and Departmental Over

    head expenses will be Rs. 45.86 Crores and Total

    Estimated capital investment will be Rs. 21.02 crores

    for the proposed CETP up-gradation.

    The implementation schedule for the up gradation of

    existing CETP project is twenty four months from the

    date of sanction.

    vi Area earmarked for CETP. The existing CETP plant is situated in 28,105 sq.m (7

    acre) area. There will be up gradation of existing CETP

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    capacity from 4 MLD to 10 MLD. The up gradation is

    coming up with in the same premises. Thus, there will

    be no additional land required.

    vii

    Method for conveyance of effluent

    from the individual industrial unit

    to CETP.

    Effluent will be collected through closed pipeline

    conveyance system. Member industries will

    discharge their effluent in the pipeline after meeting

    the pre treatment discharge standards prescribed by

    HSIIDC. Waste water generated from Pharmaceutical

    and chemical member industry will be treated by

    themselves and treated water will be discharge as per

    standards prescribed by HSPCB and CPCB.

    Member industries of CETP will be required to

    monitor specified quality parameters and flow rate of

    the effluent on daily basis and to submit the

    monitoring data to the CETP operator on regular

    basis. Continuous flow meters will also be installed at

    the outlet of the CETP to monitor the outlet effluent

    quantity.

    viii

    Explore the option to recycle the

    treated effluent to individual

    industrial unit instead or

    discharging outside.

    It has been proposed by HSIIDC to reuse treated

    effluent for irrigation, watering of parks & greens etc.

    which will require multimedia filtration with Pressure

    Filter, Activated Carbon Filter followed by disinfection

    for removal of coliforms and helminthes so as to

    achieve Zero liquid discharge.

    ix Reuse and Recycle option of

    treated effluent.

    It has been proposed by HSIIDC to reuse treated

    effluent for irrigation, watering of parks & greens etc.

    which will require multimedia filtration with Pressure

    Filter, Activated Carbon Filter followed by disinfection

    for removal of coliforms and helminthes so as to

    achieve Zero liquid discharge.

    x

    List of hazardous waste to be

    handled and their source along

    with mode of transportation.

    Detail about hazardous waste generated, handled and

    their source along with mode of transportation is as

    under:-

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    S.

    No.

    Particulars Category Quantity Mode of

    disposal Existing Proposed Total

    1. ETP Sludge 34.3 1000 Kg/day

    1500 Kg/day

    2500 Kg/day

    Collection, Storage in HWSA, Transportation and sent to TSDF site for disposal

    xi

    Other chemicals and materials

    required with quantities and

    storage capacities.

    The details about raw materials and chemicals are

    mentioned in section – 2.7.2 of chapter – 2 in EIA

    Report.

    xii

    Details of temporary storage

    facility for storage of hazardous

    waste at project site.

    In existing unit, sludge generated from CETP has

    been storage in closed room with proper ventilation

    and sent to GEPIL site for disposal. After up

    gradation sludge storage will be maintain the same.

    xiii

    Details of pre-treatment facility of

    hazardous waste at proposed

    incinerator site.

    Not Applicable as this is a up gradation of Common

    Effluent Treatment Plant project

    xiv

    Details of air Emission, effluents,

    hazardous/solid waste generation

    and their management.

    Details of air Emission, effluents, hazardous/solid

    waste generation and their management are

    mentioned in Chapter -4 of EIA Report.

    xv Hazard identification and details of

    proposed safety systems.

    Details for the same is elaborated in chapter-7 of EIA

    Report.

    xvi

    Layout maps of proposed Solid

    Waste Management Facilities

    indicating storage area, plant area,

    greenbelt area, utilities etc.

    Not Applicable as this is a common effluent

    treatment plant.

    xvii Disaster Management Plan. Disaster Management Plan is elaborated in chapter -7

    of EIA Report.

    xviii Status of court case pending

    against the project.

    There is no court case pending against the project.

    xix Plan for Corporate Environment

    Responsibility (CER) as specified

    Total Project cost -21.02 Cr.

    CSR – 1% (as per Brownfield project) – 21 lac

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    under Ministry’s Office

    Memorandum vide F.No. 22-

    65/2017-IA.III dated 1st May,

    2018 shall be prepared and

    submitted along with EIA Report.

    Detail about same is elaborated in chapter-8 of EIA

    Report.

    xx

    A tabular chart with index for

    point wise compliance of above

    ToRs.

    Noted and Complied with

    General Guidelines

    i The EIA document shall be printed

    on both sides, as for as possible.

    Noted and Complied with

    ii All documents should be properly

    indexed, page numbered.

    Noted and Complied with

    iii Period/date of data collection

    should be clearly indicated.

    Monitoring has been done during December’ 2018 to

    February’ 2019 covering winter season.

    iv

    Authenticated English translation

    of all material provided in

    Regional languages.

    Noted and Complied with

    v

    The letter/application for EC

    should quote the MoEF&CC File

    No and also attach a copy of the

    letter prescribing the ToR.

    Noted and Complied with

    vi

    The copy of the letter received

    from the Ministry on the ToR

    prescribed for the project should

    be attached as an Annexure to the

    final EIA-EMP Report.

    Noted and Complied with

    vii

    The Final EIA-EMP report

    submitted to the Ministry must

    incorporate the issues mentioned

    in ToR. The index of the final

    EIA-EMP report, must indicate the

    Noted and complied with

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    specific chapter and page no of the

    EIA-EMP report where the

    specific ToR prescribed by the

    Ministry have been incorporated.

    Questionnaire related to the project

    (posted on MoEF&CC website)

    with all sections duly filled in shall

    also be submitted at the time of

    applying for EC.

    viii Grant of ToR does not mean grant

    of EC

    Noted and Complied with

    1.5 STRUCTURE OF THE REPORT

    This EIA Report has been structured as follows:

    Chapter 1: Introduction: Provides a background to the project, identification of the

    project and project proponent, brief description of the project, details of the project

    proponent, scope of the study and structure of this report.

    Chapter 2: Project description: Provides details of project, infrastructure required,

    technology and process description of bio medical waste management, information on

    the needs and desirability of the project and sources of pollution with pollution

    control measures.

    Chapter 3: Description of the Environment: Provides description of the receiving

    Environment details, the specialist study baseline conditions identified for the project

    within 10 km radius from the project site.

    Chapter 4: Anticipated Environmental Impact and Mitigation Measures:

    describe the EIA methodology and impacts identified during the EIA process,

    providing the anticipated impacts during the various project phases.

    Chapter 5: Analysis of alternatives: provides the different site and technology

    alternatives which were considered for the project.

    Chapter 6: Environment Monitoring program: provides the monitoring schedule

    and implementation plan during the construction and operation phase of the project.

    Chapter 7: Additional Studies: has the information about risk and hazard

    assessment and details of disaster management plan.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana

    Promoter: HSIIDC Limited Chapter-1 Introduction

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Chapter 8: Project benefits: associated with the proposed project are discussed in

    this chapter.

    Chapter 9: Environmental Cost Benefit Analysis: Description of the

    Environmental benefits of the project

    Chapter 10: EMP: Description of the administrative aspects of ensuring that

    mitigative measures are implemented and their effectiveness monitored, after

    approval of the EIA

    Chapter 11: Summary & Conclusion

    Chapter 12: Disclosure of Consultants engaged.

    **********

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    CHAPTER-2

    PROJECT DESCRIPTION

    This chapter deals with the technical details of the Up gradation of existing CETP from 4 MLD

    to 10 MLD capacity based on extend aeration system, process and technology description and

    details of infrastructure.

    2.1 TYPE OF PROJECT

    There is an existing CETP of capacity 4 MLD which was constructed about 15 years ago

    on approx 28,105 sq. m (7 Acres ) of triangular shaped land in Phase IV, HSIIDC,

    Kundli to treat the effluent of this area (Phase I to IV). The outlet of the treated effluent

    is being disposed off directly in the drain running besides the CETP.

    Now with the increase in industrial activities in the area (Phase III, IV, IV sector-56), the

    quantity of effluent at the CETP is expected to increase and hence it has become

    necessary to increase the capacity of the existing system from 4 MLD to 10 MLD. The

    proposed up gradation is coming up within the premises.

    The proposed project falls under “item 7(h) of Schedule of Environment Clearance

    Notification dated 14th September, 2006, i.e. Common Effluent Treatment Plant,

    under Category –“B”. However, due to presence of Haryana-Delhi interstate

    boundary at a distance of 2.3 Km in S direction the proposed project will be treated

    as Category “A” project.

    As per the EIA Notification and subsequent amendments, “if any of the existing or

    proposed member units of the said CETP produces or proposes to produce any

    product requiring environmental clearance, then the CETP shall need environmental

    clearance”. Proposed CETP involves the treatment of waste water from the

    Metallurgical Industries which requires Environment Clearance. Therefore, the project

    requires a prior environmental clearance from MoEF&CC, New Delhi.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    2.2 NEED FOR THE PROJECT

    Establishment of effluent treatment plants for individual industries especially in the

    small scale sector in the various industrial estates in India, to produce the effluent of

    desired quality before discharge is not feasible in the Indian context. Firstly, because it

    is expensive on both the capital and operating cost front and secondly, there is no

    guarantee of performance by the individual industries. Further, the disposal of treated

    effluents is also problematic as every individual industry cannot reach the water body

    through its own pipeline nor can it purchase land for inland irrigation. Thus,

    Government of India floated the idea of Common effluent treatment plant to

    overcome these problems. Accordingly Ministry of Environment, Forest & Climate

    Change, Government of India instructed the various State Pollution Control Boards to

    examine the possibilities of establishing CETP’s in various industrial estates. In

    response to the directive issued by the Central Governments, the State

    Governments started identifying the various locations for CETP’s.

    Establishment of CETP has following advantages:

    • Saving in Capital and Operating cost of treatment plant. The Common

    treatment is always cheaper than small scattered treatment units.

    • Contribution of nutrient and diluting potential make the complex industrial

    waste more amenable to degradation.

    • The neutralization and equalization of heterogeneous waste makes its treatment

    techno-economically viable.

    • Professional and trained staff can be made available for operation of CETP

    which is not possible in case of individual plants.

    • Disposal of treated wastewater & sludge becomes more organized.

    • Reduced burden of various regulatory authorities in ensuring pollution control

    requirement.

    Water is our most important resource. The available supply of fresh water is an

    absolute deadline beyond which no community, state or nation can ever go. When

    humanity runs out of clean water, everything stops. That is the end of road for a man

    and his activities. Saving our clean water is thus a must. When untreated or

    inadequately treated waste waters are discharged, these have adverse affect on the

    body of water into which these wastes are disposed. The type of treatment of waste

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    water would depend upon the use of effluent itself or of receiving body of water into

    which effluent is discharged. The degree of treatment of waste water would further

    depend upon the discharge of receiving body of water. If small quantity of waste

    water is discharged in a river or into the sea, the degree of treatment would be much

    less than if the same quantity of waste water is discharged into a small stream. When

    receiving body of water is already polluted because of discharge of waste into it, the

    extent of new discharge of waste into it would be limited.

    The project is for common effluent treatment plant to treat the effluent being

    generated from the industries located in the industrial estate ((Phase I to IV – existing

    CETP, Phase III, IV, IV sector-56 – proposed CETP). Waste water thus generated by

    the associated industries will be lifted through dedicated pipeline system after meeting

    the pre treatment discharge standards prescribed by HSIIDC. The waste water after

    treatment shall meet the discharge standards laid down by MoEF&CC and HSPCB. It

    has been proposed by HSIIDC to reuse treated effluent for irrigation, watering of

    parks & greens etc. which will require multimedia filtration with Pressure Filter,

    Activated Carbon Filter followed by disinfection for removal of coliforms and

    helminthes so as to achieve Zero liquid discharge.

    2.3 LOCATION OF THE PROJECT

    The project site is coming up at Phase-IV, Industrial Estate, Kundli, Sonipat, Haryana.

    The general location map of the project is shown in Figure 2.1, which provides a

    regional location map of the proposed site relative to its surroundings. The site is

    located near National Highway NH-1, which is about 1.2 Km towards WSW from the

    site. SH-57, which is about 10.6 Km towards E from the site. Site will be enforced

    with secured entrance procedures. The entire footprint of the site will be fenced off

    with security fencing.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure 2.1: General Location Map

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure 2.2: Google Map

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure 2.3: HSIIDC Industrial Estate Layout Plan showing Transportation of

    Waste Water

    Details

    Phase I Industrial plots: 106 nos.

    Phase II Industrial Plots: 92 nos.

    Phase –III (EPIP) Industrial Plots: 189 nos.

    Phase-IV Industrial Plots: 656 nos.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure 2.4: Plant Layout

    The details of environmental setting are given in Table-2.1.

    Table-2.1 Environmental Setting of the Site

    S. No. Particulars Details

    1

    “Up gradation of existing Common Effluent Treatment Plant from 4 MLD to 10 MLD

    capacity”

    Khasra No Phase-IV, Industrial Estate, Kundli

    Village --

    District Sonipat

    State Haryana

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    S. No. Particulars Details

    2

    Coordinates

    1 2

    Latitude : 280 53’11.71” N Longitude: 770 7’ 51.32” E

    Latitude : 280 53’4.37” N Longitude: 770 7’ 51.43” E

    3 4

    Latitude: 280 53’4.35” N Longitude: 770 7’42.44” E

    Latitude: 280 53’4.88” N Longitude: 770 7’ 42.45” E

    3 Plant site elevation above MSL 214 m above MSL

    4 Geographical location in Survey

    of India toposheet

    Toposheet No. 53 H/1, 53 D/13, 53 H/5 and 53 G/4

    5 Plant site topography Plain

    6 Present land use at the site

    The proposed up gradation project shall be executed on

    the existing land only which is already under the

    industrial use. Hence, there will be no change in the land

    use.

    7 Nearest highway • National Highway NH-1 - 1.2 Km towards WSW

    • SH-57 - 10.6 Km towards E

    8 Nearest railway station • Narela Railway Station - 6.2 Km towards SW

    • Sonipat Railway station – 16.0 Km towards NW

    9 Nearest airport Indira Gandhi International Airport - 36.5 Km towards

    S

    10 Nearest village Sonipat - 15 km towards NW

    11 Villages within 1 km radius None

    12 Hills/valleys None

    13 Archaeologically important

    places None

    14

    Protected areas as per Wildlife

    Protection Act,1972 (Tiger

    reserve, Elephant reserve,

    Biospheres, National parks,

    Wildlife sanctuaries, community

    reserves and conservation

    reserves)

    None within the study area

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    S. No. Particulars Details

    15 Reserved / Protected Forests

    • Mamupur P.F. - 3.1 km towards SSW

    • Ogha R.F - 9.3 km towards SW

    • Bawana R.F - 10.0 km towards SW

    • Niwara R.F -12.0 km towards NNE

    16 Water Bodies

    • Drain No. 8 - Nearest to the site towards N

    • Naahri Mukhya Vitrika - 3.6 KM towards W

    • Harsana Vitrika - 4.7 Km towards NW

    • Yamuna River - 8.3 Km towards ESE

    • Alipur Dem - 9.8 Km towards E

    • Bawana Vitrika - 12.2 Km towards SW

    17 Seismicity Seismic Zone-IV as per IS 1893 (Part I): 2002 High

    Damage Risk Zone

    18 Defence Installations None

    19 List of Industries in the

    surrounding

    There are footwear, iron & fabrication, plastic goods,

    pharmaceuticals, chemicals, confectionary / food

    processing, auto mobiles ancillaries and electronic &

    electrical good etc. have been established.

    20 Soil type Sandy loams to loamy sands

    21 Depth of water table *Pre-monsoon depth to water level - 1.57-24.84 mbgl

    *Post-monsoon depth to water level - 0.64 m-22.46 m

    22 Major crops Wheat, Rice, Maize, Gram

    23 Socio-economic factors No R&R issues involved

    2.4 SIZE OR MAGNITUDE OF OPERATION

    The There is an existing CETP of capacity 4 MLD which was constructed about 15

    years ago on approx 28,105 sq. m (7 Acres ) of triangular shaped land in Phase IV,

    HSIIDC, Kundli to treat the effluent of this area (Phase I to IV). The outlet of the

    treated effluent is being disposed off directly in the Drain No. 8 running besides the

    CETP.

    Now with the increase in industrial activities in the area (Phase III, IV, IV sector-56),

    the quantity of effluent at the CETP is expected to increase and hence it has become

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    necessary to increase the capacity of the existing system from 4 MLD to 10 MLD.

    Details of project facilities are as under.

    TABLE-2.2 Details of The Proposed Facilities

    S. No. Parameter Description

    1 Total Plot Area for Industrial

    Estates (Phase I, II, III & IV) 620 Acres

    2 Total plot area for CETP 28,105 sq.m.(7 acre)

    3 Land-Use

    The proposed up gradation project shall be

    executed on the existing land only which is

    already under the industrial use. Hence, there will

    be no change in the land use.

    4 Project Capacity Up gradation of existing common effluent

    treatment plant from 4 MLD to 10 MLD

    5 Power Requirement

    Particulars Existing Proposed Total

    Power and

    Source

    275 KW

    425 KW 700 KW

    D.G. Set 300kVA (200 kVA:1No. + 100 kVA:1No.) Fuel used: HSD

    500 kVA (1No.) Fuel used: HSD

    3nos. 200kVA:1No. 100kVA:1No 500kVA:1No.

    6 Source of Power

    Source:- UHBVN Supply

    HSD – 15 ltr/hr – existing

    25 ltr/hr – proposed

    7 Employment

    Particulars Existing Proposed Total

    Manpower 13 no

    operation

    phase

    30 during

    constructio

    n phase

    13 –

    operatio

    n phase

    30 –

    construct

    ion

    phase

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    S. No. Parameter Description

    8 Water Requirement

    Particular

    s

    Existing Proposed Total

    Water

    demand

    3 KLD 0.6 – domestic use 2.4 KLD - chemical dosing

    3 KLD - chemical dosing

    6 KLD 0.6 – domestic use 5.4 KLD - chemical dosing

    9 Source of Water HSIIDC Industrial Water supply

    10 Waste water generation

    Domestic waste water generation - 0.4 KLD

    Total Waste water Quantity from Phase I to IV,

    Kundli IE for Existing CETP Capacity – 3927 KLD

    Total Waste water Quantity from Phase III, IV, IV

    sector-56 Kundli, IE for proposed CETP Capacity

    – 5252 KLD

    11 Project Cost

    Total estimated cost including O&M, Power,

    Chemicals, Sludge disposal and Departmental

    Over head expenses will be Rs. 45.86 Crores and

    Total Estimated capital investment will be Rs.

    21.02 crores for the proposed CETP up-gradation

    2.4.1 Infrastructure

    This is up gradation of exiting Common Effluent Treatment Plant project. The existing

    unit already has all the basic amenities like adequate industrial sheds, sanitation facilities,

    drinking water arrangements, Restrooms, Canteen, first aid facility etc. HSIIDC has

    established its own water supply arrangement for the Industrialist at HSIIDC IE Kundli.

    There will be no separate designated temporary sites for construction workers.

    2.4.2. Land Requirement

    The proposed up gradation project shall be executed on the existing land only. The

    total plot area of the project is 28,105 sq.m, which is 7 acre. The ownership of the

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    land is with HSIIDC (IE) itself. Land documents is given as Annexure II. The land

    use break up is provided below in Table-2.3.

    TABLE-2.3 Land Use Breakup

    S. No.

    Particulars Existing (Sq.m)

    Proposed (Sq.m)

    Total (Sq.m)

    %

    1 Plant area 16,196.91 -- 16,196.91 57.63

    2 Green Area 5,160.08 -- 5,160.08 18.36

    3 Road &

    footpaths 2,481.68

    --

    2,481.68 8.83

    4 Others Open

    area 4,266.33

    --

    4,266.33 15.18

    5 Total 28,105 -- 28,105 100

    2.4.3 Water Requirement

    Total fresh water requirement for existing project is 3 KLD. For domestic purposes

    0.6 KLD water will be required. HSIIDC has established its own water supply

    arrangement for the Industrialist at HSIIDC IE Kundli. There will be use of some

    water for the preparation of sensitive dosing chemicals to be used in the treatment

    process to an extent of 2.4 KLD. After up gradation man power will be same, thus

    water demand for domestic purposes will remain same. There will be use of some

    water for the preparation of sensitive dosing chemicals to be used in the treatment

    process to an extent of 3 KLD. The flow diagram of existing and proposed Water

    Balance is shown in Fig. 2.5 (a) and Fig. 2.5 (b):-

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    Figure – 2.5 (a) Existing Water Balance

    Figure – 2.5 (b) Proposed Water Balance

    393 KLD (10% losses)

    Industrial Effluent 3927 KLD

    Preparation of Dosing Chemicals 2.4 KLD

    Total Fresh Water 3 KLD

    Domestic use 0.6 KLD

    Septic Tank Soak Pit 0.4 KLD

    CETP 4 MLD Capacity

    4,000 KLD Effluent

    Treated Water

    3,534 KLD

    Recycle = 3,463

    KLD

    Conveyance Loss (2 %) =

    71 KLD

    Green Belt Development / industrial use for member industry

    Phase I, II, III & IV

    525 KLD (10% losses)

    Industrial Effluent 5252KLD

    Preparation of Dosing Chemicals 3

    KLD Total Fresh Water 3 KLD

    CETP 6 MLD Capacity

    6000 KLD Effluent

    TREATED

    WATER 4727 KLD

    Recycle

    4632 KLD

    Conveyance Loss (2 %) =

    95 KLD

    Green Belt Development/ industrial use for member industry

    Phase III, IV and IV sector 56

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    2.4.4 Power Requirement

    Power requirement for the project is as under:-

    Particulars Existing Proposed Total

    Power and

    Source

    275 KW

    UHBVN Supply

    425 KW

    UHBVN Supply

    700 KW UHBVN

    Supply

    D.G. Set 300kVA

    (200 kVA:1No.

    + 100 kVA:1No.)

    500 kVA

    (1No.)

    3nos.

    200kVA:1No.

    100kVA:1No

    500kVA:1No.

    Fuel HSD: 15 l/ hr/ DG

    set

    HSD: 25 l/ h HSD: 15 l/ hr/ DG

    set (200 kVA

    100 KVA – 2 nos )

    HSD: 25 l/ h DG

    Set (1no. 500 kVA)

    2.4.5 Manpower

    Local workers will be hired from the nearby villages. The details of the existing and

    proposed manpower are as under:-

    Particulars Existing Proposed Total

    Manpower 13 no 30 during

    construction

    phase

    13 – operation

    phase

    30 – construction

    phase

    2.5 PROPOSED SCHEDULE AND APPROVAL FOR

    IMPLEMENTATION

    2.5.1 Proposed Schedule for Implementation

    The implementation schedule for the proposed project is twenty four months from the

    date of sanction.

    2.5.2 Approval for Implementation

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    The ground activities will be started after receipt of Environment Clearance from

    MoEF&CC, New Delhi and subsequent Consent to Establish from Haryana State

    Pollution Control Board.

    2.6 TECHNOLOGY AND PROCESS DESCRIPTION OF COMMON

    EFFLUENT TREATMENT PLANT

    At present 4 MLD capacity CETP is functional for treated effluent of Indl Estate Kundli

    (Phase I to IV). The treated effluent is being disposed off in drain no. 8 by pumping

    system through 200 mm dia PVC pipe line. At present, the average inflow is approx. 4

    MLD & will reach 5 MLD within a year. Presently, the Indl. Estate sector-38 Ph-I has

    fully been developed and in Mega Food Park area, the maximum number of plots are

    under construction. The present arrangement will be inadequate and needs to be

    upgraded to treat the maximum discharge of 10 MLD.

    The existing treatment process which has been adopted for the 4 MLD CETP which is

    functioning is Extended Aeration process. The upgradation of the treatment plant has

    been proposed using the similar treatment process so that there is a parity with the

    existing system as well as the existing structures can be used to 5 the maximum

    possible extent. Detailed design report has been prepared using the existing

    Equalization tanks, Aeration system and Secondary clarifier system, which will be

    augmented with new units which are necessary and compatible with the existing

    structures has been mentioned hereunder. Moreover, Extended Aeration process which

    is most technically and financially viable treatment process, has been recommended for

    adoption as the treated effluent parameters even after secondary treatments meets the

    Pollution Control Board norms at the lowest power consumption. The methods range

    from physico- chemical to biological & in the latter group from aerobic to anaerobic.

    RAW EFFLUENT CHARACTERISTICS

    Member industries of CETP will be required to monitor specified quality parameters

    and flow rate of the effluent on daily basis and to submit the monitoring data to the

    CETP operator on regular basis. Continuous flow meters will also be installed at the

    outlet of the CETP to monitor the outlet effluent quantity.

    The effluent characteristics of mix type industrial units has been assessed as under for

    designing of CETP. It is presumed that most of the industrial unit shall have their own

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    treatment plants & shall have consent from Haryana state Pollution Control Board to

    discharge treated effluent in to the common sewers. The values given in Table below,

    are considered in design:

    Influent Sewage Characteristics

    S. No. Parameters Units

    1 pH 6 - 8.5

    2 BOD5, mg/ L 450

    3 COD, mg/ L 900

    4 TSS, mg/ L 1200

    5 Coliform, MPN/100ml 1x107

    6 Oil & Grease mg/L 100

    7 Temperature, Co. 18-22

    8 NH4- Nitrogen, mg/ L 45

    9 TKN, mg/ L 40

    10 TP as PO4, mg/ L 10

    11 Chromium mg/L 5

    12 COD/ BOD ratio 2

    Treated effluent Characteristics after secondary Treatment

    S. No. Parameters Units

    1 pH 7-7.5

    2 BOD5, mg/ L ≤10

    3 COD, mg/ L ≤20

    4 TSS, mg/ L ≤20

    5 Coliform, MPN/100ml ≤10000

    6 Oil & Grease mg/L ≤5

    7 Temperature, Co. ≤1

    8 NH4- Nitrogen, mg/ L ≤2

    9 TP as PO4, mg/ L ≤0.1

    10 Chromium mg/L >0.2

    Treated effluent Characteristics after Tertiary Treatment

    S. No. Parameters Units

    1 pH 7-8.5

    2 BOD5, mg/ L

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    6 Oil & Grease mg/L

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    1. Raw effluent intake & bar screen chamber

    1 @ 30.0MLD Nil 30.0MLD

    2. Collection cum-Pumping tank

    2 @ 5.0MLD Nil 10.0MLD

    3. Grit Chamber Nil 1 @ 30 MLD 30MLD

    3. Receiving Chamber Nil 1 @ 30.0MLD 30 MLD

    4. Mechanical Fine Screen Nil 1 @ 30.0MLD 30.0MLD

    5. Collection cum Distribution Box

    Nil 1 @ 30.0MLD 30.0MLD

    6. Equalization Tank 1 @ 10.0MLD Nil 10.0MLD

    7. Flash Mixer Nil 1 @ 10.0MLD 10.0MLD

    8. Flocculator (Existing Primary Clarifier to be converted)

    10.0MLD Nil 10.0MLD

    9. Primary Clarifier Nil 10.0MLD 10.0MLD

    10. Extended Aeration Reactor 2 @ 10.0MLD 2 @ 10.0MLD 40.0MLD

    11. Secondary Clarifier 1 @ 10.0MLD 1 @ 10.0MLD 20.0MLD

    12. Collection cum Distribution channel

    1 @ 10.0MLD Nil 10.0MLD

    13. Secondary Treated Effluent Collection Sump.

    60 minutes as its retention Time

    Nil 60 minutes as its retention

    Time

    14. Centrifuge 3 @ 10.0MLD Nil 30MLD

    15. Pressure Filtration 1 @ 10MLD Nil 10 MLD

    16. Activated Carbon Filter 1 @ 10 MLD Nil 10.0MLD

    17. Disinfection. 1 @ 10.0MLD Nil 10.0MLD

    Selection of Treatment Process

    The existing treatment process which has been adopted for the 4 MLD CETP which is

    functioning is Extended Aeration process. The up-gradation of the treatment plant has

    been proposed using the similar treatment process so that there is a parity with the

    existing system as well as the existing structures can be used to the maximum possible

    extent. Detailed design report has been prepared using the existing Equalization tanks,

    Aeration system and Secondary clarifier system, which will be augmented with new

    units which are necessary and compatible with the existing structures has been

    mentioned hereunder. Moreover, Extended Aeration process which is most technically

    and financially viable treatment process, has been recommended for adoption as the

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    treated effluent parameters even after secondary treatments meets the Pollution

    Control Board norms at the lowest power consumption.

    Some Waste Water Treatment Methods & their Characteristics:-

    The methods range from physico- chemical to biological & in the latter group from

    aerobic to anaerobic. The quick overview for the same is given as hereunder: -

    Treatment Methods Biological Physical Chemical Aerobic Anaerobic Suspended Growth Attached Growth Suspended

    Growth Attached Growth

    Activated Sludge Trickling Filters UASB Moving Bed Bio Reactors

    Screening & Grit Removal

    Extended Aeration Rotating Bio Reactors

    Anaerobic ponds.

    Submerged Bio Reactors.

    Coagulation

    Aerated Lagoons Land treatment. Flocculation Waste Stabilization ponds.

    Roof Zone Reed Beds

    Settling

    Sequential Batch Reactor.

    Vermistabilization Sludge Thickening.

    Membrane Bio Reactor.

    Moving Bed Bio Reactors

    Sludge dewatering

    Submerged Bio Reactors.

    Filtration.

    Colour Removal Chlorination De chlorination Ion Exchange softening

    or Demineralization. Ultra Filtration Reverse Osmosis

    Sewage Treatment Processes may be generally classified as Primary, Secondary &

    Tertiary. The general yard stick of evaluating a performance of sewage treatment plants

    is the degree of reduction of BOD as such & total coliforms.

    The selection of process will depend upon whether primary, secondary or tertiary

    treatment is required to meet with the parameters prescribed by the respective pollution

    control boards or local bodies whichever is stricter. In addition environment impact &

    other consideration in planning treatment facilities are required to be considered for

    selection of processes are illustrated as here under: -

    a) Environment Impact Considerations: -

    - Downstream hydrology & aquatic ecosystem.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    - Ground water pollution potential.

    - Odour, aerosol spray, mosquito nuisance.

    - Effect on nearby land use & land values.

    - Rehabilitation of effected people.

    - Discharge Standards.

    - Toxic in food chain.

    - Nitrates & Chemical pollution of water resources.

    - Bathing water quality.

    - Health of plant operators/ farm workers.

    - Plant operation & maintenance aspects.

    - Green belt & land escaping.

    b) Engineering & Site considerations: -

    - Selection of design period.

    - Sufficiency of site area available.

    - Topography of the general area to be served, location of pumping station & contours

    at the available site.

    - Available hydraulic head, high flood level, level of the irrigation land or HFL of the

    available drain/ water body receiving the treated effluent.

    - Ground water depth & land disposal facility of treated effluent.

    - Soil Bearing Capacity & type of strata at the proposed site.

    c) Process performance, energy, operation & maintenance: -

    Process considerations involve below mentioned factors which affect the choice of

    treatment methods & design criteria: -

    - Waste water flow & characteristics.

    - Degree of treatment required.

    - Performance fluctuations, sustainability & reliability.

    - Land availability.

    - Power availability.

    - Operating equipments requirements & its indigenous availability.

    - Skilled staff availability.

    - Extent of sludge production & disposal requirements.

    - Loss of head through plant & available head.

    - Ease of stage wise extension of plant with time.

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    - Energy conservations.

    - Energy/ power generations.

    - Carbon Credit as per KYOTO Protocol.

    Proposed Treatment Process:

    It is stipulated that the proposed CETP shall be based on physical & chemical treatment

    for removal of excessive inorganic COD, TSS & BOD5 beside removal of color &

    maintenance of equalized & constant PH & Flow rate prior to biological process i.e.

    Activated Sludge process based on extended aeration principal. That after biological

    Treatment process Treated effluent shall be further treated in pressure Filter, Carbon

    filter and shall be disinfected with chlorine before final disposal in drain.

    A. Physical Treatment

    The existing system has structures which needs to be improvised with new structures to

    meet the requirement of the CETP.

    The adequacy of the existing structures has been checked only those modifications/

    additional structures are proposed which are essentially required.

    However, the replacement of existing electromechanical equipment’s has been

    proposed since the same has outlived its performance period and the material of

    construction has been used as Mild Steel which has been corroded.

    The details of the structures included in the CETP is given below:

    Inlet Pipe: - The existing inlet pipe is of size 800 mm diameter. The invert of the inlet

    pipe is 196.0 m. The inlet pipe has been found to be adequate to discharge peak flow (3

    times the average flow) at a velocity of 0.7 m/sec.

    Receiving chamber:- The existing Receiving chamber is of size 3m x 1m x 5.5 m

    depth. The chamber is capable of accommodating flow for 30 seconds. Hence no

    additional Receiving chamber has been proposed.

    Coarse Screen chamber:- The existing coarse screen chamber is of size 6m x 4m x 5

    m deep. It is proposed to convert the existing Screen chamber to mechanical coarse

    screen chamber. The present structure can be modified by constructing concrete

    partition walls to accommodate 3 nos. mechanical Coarse Screen (2W mechanical + 1

    SB mechanical ) suitable for channel size 6.0 m x 1.16 m x 0.7 SWD + 0.3 FB.

    Effluent Inlet Sump:- At present there is a circular Effluent Inlet chamber which is

    pumping effluent directly to the Equalization Chamber. The size is 10m dia. + 3 m

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    SWD. The existing size is adequate to accommodate effluent for HRT 10 min at peak

    flow of 30 MLD. The Effluent Inlet sump will be utilized to pump effluent to the fine

    screen chamber.

    Replacement of existing submersible pumps with non-clog submersible sewage pumps

    as here under have been proposed: - 417 M^3/ Hr. @ 15MWC, 4Nos. (3W+1SB).

    Non clog submersible sewage pumps have been proposed keeping in view the depth of

    the incoming sewer and high water table.

    Mechanical fine screen, oil and grease trap:- There is no existing fine screen

    chamber with oil and grease trap. Therefore a new mechanical Fine screen chamber 3

    nos (2 W+1 SB) is proposed with oil and grease trap to accommodate flow of 10 MLD

    with 3.0 peak factor.

    Equalization Tank:- There is an existing Equalization tank of size 27 m diameter and

    SWD 3.75 m. The tank can accommodate average flow of 416.67 m3/hr for 5 hours. It

    is proposed to utilize the existing Equalization tank as there will be intermittent

    discharge of different characteristics from mix of industries. It is proposed to install air

    diffusing system like aspirators in the Equalization tank to enhance the oxidation

    process of the pollutants. Thereafter the equalized effluent shall be pumped in to the

    flash mixer. Replacement of all existing effluent pump has been proposed in the DPR

    as the capacity of the pumps has been enhanced for 10 MLD plant.

    B. Chemical Treatment

    Flash Mixer:- At present there is no flash mixer is installed. The equalized effluent is

    being pumped to the existing primary clarifier. It is proposed to construct a flash mixer

    of size 2.55m x1.70m x 1.5m SWD + 0.40m FB. The equalized effluent will be pumped

    into the flash mixer for mixing of ferrous alum & lime. It is proposed to convert the

    existing Primary Clarifier of 13m dia. and 3.0 m SWD into a Flocculator. The

    coagulated effluent from the Flash mixer shall flow into the Flocculator with concentric

    flocculation unit after addition of fast settling chemical viz. Polyelectrolyte.

    Flocculator:- A separate Primary Clarifier has been proposed to be built besides the

    existing one. The same has been proposed because the existing Primary clarifier is

    inadequate to handle the effluent of 10 MLD. As mentioned above the existing Primacy

    clarifier – 1 no. will be converted into a flocculator. In the Flocculator, the effluent

    mixed with ferrous sulphate, ferrous chloride and Lime solution in the flash mixer will

    result in formation of flocs. Addition of polyelectrolyte is also proposed to thicken the

  • EIA for Up gradation of existing CETP from 4 MLD to 10 MLD capacity at Kundli, Sonipat, Haryana Promoter: HSIIDC Limited Chapter-2 Project Description

    Gaurang Environmental Solutions Pvt. Ltd. Report Ref: GESPL/228/2019/EIA/31

    HSIIDC Limited Authorized Signatory

    flocs. Though a flocculator is designed for 30 min HRT but the existing structure will

    provide an HRT of 55 min which will add efficiency to the system. The size of the

    Flocculator designed for HRT 55 minutes is 13 m dia. x 3 m SWD.- 1 no.

    Primary Clarifier:- A clarifier is a settling zone where the flocs formed at the

    flocculator settles. A new Primary clarifier is proposed besides the existing structure to

    allow clarification of the incoming effluent. The size of the Clarfication unit is circular

    tank of 21.2 m diameter and 3.0 m SWD. This physically & Chemically treatment shall

    remove colour, oil & Grease, correct PH, remove TSS at least by 70% & COD/ BOD5

    by 50/ 30% respectively.

    Effluent Characteristics after primary Treatment.

    BOD5, mg/L 360.00

    TSS , mg/L 540.00

    COD, mg/ L 675.00

    C. Biological Treatment

    Aeration Tank:- At present there are two nos. of rectangular Aeration tank of size

    43m x 13m x 3m SWD. The existing tanks are inadequate to handle 10 MLD effluent.

    Hence it is proposed to provide further 2 nos. Aeration tank of length 43m x 22m x

    3m SWD. This physically & Chemically treated effluent shall fl