chadchan lift irrigation scheme zÀqÀzÀt kvÀ …€¦ ·  · 2016-12-16chadchan lift irrigation...

33
EXECUTIVE SUMMARY OF DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT PÀgÀqÀÄ ¥Àj¸ÀgÀ DWÁvÀ CAzÁfÃPÀgÀt ªÀgÀ¢AiÀÄ PÁAiÀÄðPÁj ¸ÁgÁA±À CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É VIJAYAPURA DISTRICT, KARNATAKA «dAiÀÄ¥ÀÄgÀ f¯Éè, PÀ£ÁðlPÀ KRISHNA BHAGYA JALA NIGAM LTD PÀÈμÁÚ ¨sÁUÀå d® ¤UÀªÀÄ ¤AiÀÄ«ÄvÀ CANAL ZONE NO. 2, RAMPUR (PA), SINDHAGI TQ, VIJAYAPURA, KARNATAKA PÁ®ÄªÉ ªÀ®AiÀÄ £ÀA.2, gÁA¥ÀÄgÀ (¦.J), ¹AzsÀV vÁ®ÆèPÀÄ, «dAiÀÄ¥ÀÄgÀ, PÀ£ÁðlPÀ CONSULTANTS ªÀgÀ¢ ¹zÀÝ¥Àr¹zÀªÀgÀÄ ENVIRONMENTAL HEALTH & SAFETY CONSULTANTS PVT LTD ªÉÄ. J¤égÁ£ïªÉÄAl¯ï ºÉ¯ïÛ CAqï ¸ÉÃ¦Ö PÀ£Àì¯ÉÖAmï ¥Éæ Ê.°. # 13/2, 1 ST MAIN ROAD, NEAR FIRE STATION, INDUSTRIAL TOWN, RAJAJINAGAR,BANGALORE-560 010 £ÀA. 13/2, ªÉÆzÀ®£Éà ªÀÄÄRå gÀ¸ÉÛ, CVß ±ÁªÀÄPÀ oÁuÉAiÀÄ ºÀwÛgÀ, PÉÊUÁjPÁ £ÀUÀgÀ, gÁeÁf£ÀUÀgÀ, ¨ÉAUÀ¼ÀÆgÀÄ - 10 NOVEMBER 2016

Upload: dothuan

Post on 09-Apr-2018

233 views

Category:

Documents


4 download

TRANSCRIPT

Page 1: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

EXECUTIVE SUMMARY OF

DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT

PÀgÀqÀÄ ¥Àj¸ÀgÀ DWÁvÀ CAzÁfÃPÀgÀt ªÀgÀ¢AiÀÄ PÁAiÀÄðPÁj ¸ÁgÁA±À

CHADCHAN LIFT IRRIGATION SCHEME

ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É

VIJAYAPURA DISTRICT, KARNATAKA

«dAiÀÄ¥ÀÄgÀ f¯Éè, PÀ£ÁðlPÀ

KRISHNA BHAGYA JALA NIGAM LTD

PÀȵÁÚ ¨sÁUÀå d® ¤UÀªÀÄ ¤AiÀÄ«ÄvÀ

CANAL ZONE NO. 2, RAMPUR (PA), SINDHAGI TQ, VIJAYAPURA, KARNATAKA

PÁ®ÄªÉ ªÀ®AiÀÄ £ÀA.2, gÁA¥ÀÄgÀ (¦.J), ¹AzsÀV vÁ®ÆèPÀÄ, «dAiÀÄ¥ÀÄgÀ, PÀ£ÁðlPÀ

CONSULTANTS

ªÀgÀ¢ ¹zÀÝ¥Àr¹zÀªÀgÀÄ

ENVIRONMENTAL HEALTH & SAFETY CONSULTANTS PVT LTD

ªÉÄ. J¤égÁ£ïªÉÄAl¯ï ºÉ¯ïÛ CAqï ¸ÉÃ¦Ö PÀ£Àì¯ÉÖAmï ¥ÉæöÊ.°.

# 13/2, 1ST MAIN ROAD, NEAR FIRE STATION, INDUSTRIAL TOWN, RAJAJINAGAR,BANGALORE-560 010

£ÀA. 13/2, ªÉÆzÀ®£Éà ªÀÄÄRå gÀ¸ÉÛ, CVß ±ÁªÀÄPÀ oÁuÉAiÀÄ ºÀwÛgÀ,

PÉÊUÁjPÁ £ÀUÀgÀ, gÁeÁf£ÀUÀgÀ, ¨ÉAUÀ¼ÀÆgÀÄ - 10

NOVEMBER 2016

Page 2: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

EXECUTIVE SUMMARY OF DRAFT ENVIRONMENTAL IMPACT ASSESSMENT REPORT

FOR

CHADCHAN LIFT IRRIGATION SCHEME at

VIJAYAPURA DISTRICT, KARNATAKA.

PROJECT BY

THE CHIEF ENGINEER

KRISHNA BHAGYA JALA NIGAM LTD

CANAL ZONE No. 2

RAMPURA, VIJAYAPURA - 586202

KARNATAKA

CONSULTANTS

ENVIRONMENTAL HEALTH & SAFETY CONSULTANTS PVT LTD

# 13/2, 1ST MAIN ROAD, NEAR FIRE STATION, INDUSTRIAL TOWN, RAJAJINAGAR,BANGALORE-560 010,

QCI NO. 51 AS PER PROVISIONAL ACCREDITATION REV. 47 NOVEMBER 07, 2016

NOVEMBER, 2016

DOCUMENT NO. EHSC/KBJNL/CLIS

Page 3: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 1

REVISION RECORD

Rev. No Date Purpose

EHSC/01 28.11.2016 Issued as Draft EIA Report for Comments and Suggestions

EHSC/02 01.12.2016 Issued as Draft EIA Report for submission to KSPCB for

conducting Environmental Public Hearing

Page 4: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 2

TABLE OF CONTENTS

1. Introduction ................................................................................................................ 4

2. Project Description ...................................................................................................... 4

2.1 Need for the project ............................................................................................... 6

2.2 Re-allocation of water for the proposed scheme ........................................................ 6

2.3 Command area of the project .................................................................................. 6

2.4 Irrigation Planning and structural components of the project ...................................... 7

2.5 Land Requirement .................................................................................................. 8

2.6 Existing cropping pattern details .............................................................................. 8

2.7 Proposed cropping pattern details ............................................................................ 8

2.8 Benefit cost ratio .................................................................................................... 9

3. Description of baseline environment .............................................................................. 9

3.1 Physical Environment .............................................................................................. 9

3.1.1 Climate & Meteorology ..................................................................................... 9

3.1.2 Ambient air quality ........................................................................................... 9

3.1.3 Ambient Noise levels ........................................................................................ 9

3.1.4 Geology and Minerals ..................................................................................... 10

3.1.5 Soil characteristics ......................................................................................... 10

3.1.6 Hydrology ..................................................................................................... 10

3.1.7 Surface Water................................................................................................ 10

3.1.8 Ground Water ................................................................................................ 10

3.1.9 Land use assessment ..................................................................................... 11

3.2 Biological Environment ............................................................................................. 11

3.2.1 Flora ................................................................................................................ 11

3.2.2 Fauna............................................................................................................... 12

4. Anticipated Environmental Impacts & Mitigation Measures ............................................. 12

4.1 Ambient Air Quality .............................................................................................. 13

4.2 Ambient Noise Level ............................................................................................. 13

4.3 Water Environment .............................................................................................. 14

4.4 Biological Environment .......................................................................................... 14

4.6 Evaluation Impacts ............................................................................................... 14

5. Analysis of Alternatives .............................................................................................. 20

6. Environmental Monitoring Program ............................................................................ 20

7. Social Impact Assessment .......................................................................................... 22

7.1 Demographic profile of the villages ........................................................................ 22

7.2 Impact of the project ............................................................................................ 22

8. Project Benefits ......................................................................................................... 23

9. Environmental Management Plan ................................................................................ 24

9.1 Command Area Development Plan ............................................................................ 28

9.1.1 Catchment Area Treatment (CAT) plan ................................................................... 28

9.1.1.1 Cost Estimates as per Soil conservation treatments suggested ............................ 29

9.1.2 Water Users‟ Association (WUA) .......................................................................... 29

9.1.2.1 Green belt development plan ........................................................................... 29

9.1.2.1.1 Plantation around intake canal and jack well cum pump house ...................... 29

9.1.2.1.2 Agro forestry activates in command area .................................................... 29

9.2 Fisheries Development Plan ...................................................................................... 30

9.3 Muck Disposal plan .................................................................................................. 30

9.4 Cost for implementing EMP ....................................................................................... 31

Page 5: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 3

LIST OF TABLES

Table 1 Salient Features of the project ............................................................................... 4 Table 2 List of benefitting villages ..................................................................................... 7 Table 3 Details of bifurcation of command area .................................................................. 7 Table 4 Details of zones in command area ......................................................................... 7 Table 5 Existing cropping pattern in the command area ...................................................... 8 Table 6 Proposed cropping pattern .................................................................................... 8 Table 7 Geological succession of the study area ................................................................ 10 Table 8 Land use / land cover classification in the study area ............................................ 11 Table 9 List of commonly found tree species in the study area ........................................... 11 Table 10 Criteria for evaluation of impacts ....................................................................... 15 Table 11 Evaluation of Impacts ....................................................................................... 16 Table 12 Environmental Monitoring Plan (2 years) ............................................................ 20 Table 13 Environmental Monitoring Program for Operation phase (3 years) ........................ 21 Table 14 Details of benefitting villages ............................................................................. 22 Table 15 Environment Management Plan ......................................................................... 24 Table 16 Green belt development Plan around intake canal and jack well ........................... 30 Table 17 Species recommended for green belt development .............................................. 30 Table 18 Muck disposal plan ........................................................................................... 30 Table 19 Cost for implementing Environmental Management Plan ...................................... 31

Page 6: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 4

1. Introduction

Chadchan Lift irrigation scheme envisages utilization of 1.2 TMC of water from the Bhima River near Holisankh Village, Indi Taluk and providing irrigation facility to 9215 ha of land during Khariff and Rabi season. SEAC has issued ToR for the project vide its letter No. SEIAA 04 IND 2016 dated 06.06.2016. The project has been accorded administrative approval from Govt., of Karnataka vide order no. WRD 142 KBN 2016 Bangalore dated 29.08.2016 and the total cost of the project is 413 Crores. The said EIA report includes the data on various field studies undertaken by the accredited experts including baseline environmental data collection from the study area during the study period July 2016 to September 2016, in line with the ToRs, anticipated impacts (identified, predicted & evaluated) on different components of the environment, delineating specific Environmental Management Plan (EMP) including Environmental Program along with the budgetary provisions to be undertaken by KBJNL stating responsibility of various parallel departments for effective implantation of the same.

2. Project Description

The proposed scheme envisages utilization of 1.2 TMC of water from the Bhima River near Holisankh Village, Indi Taluk and providing irrigation facility to 9215 ha of land during Khariff and Rabi season. The project will benifit 8 villages of Indi Taluk viz., Chadchan, Havinahala, Godihala, Halahalla, Baradol Tikke, Shiradona, Revathagaon and Nivaragi. The proposed irrigation is only during Khariff season and the intensity of irrigation will be100%.

Govt. of Karnataka vide Govt. order no. WRD 142 KBN 2016, Bangalore dated 29.08.2016 accorded administrative approval for the project

Table 1 Salient Features of the project

1 Name of the Scheme Chadchan Lift Irrigation Scheme

2 Name of the River Bhima

3 Geographical location of lift point Longitude - 75°33‟47”E Latitude - 16°14‟19”N

4 Location of the lift point Holisankh Village, Indi Taluk, Vijayapura district

5 Type of the Project Irrigation

6 Mode of Irrigation Gravity flow irrigation

7 Estimated cost of the project Rs. 413.20 Crores

8 Command area 9215 Ha

9 No. of benefitting villages 8

10 Allocated Water 1.2 TMC

11 Cropping pattern Khariff and Rabi

12 Irrigation Intensity 100%

13 Total land required 108.4 Ha

14 Total forest land required Nil

15 Submergence area Nil

16 Rehabilitation& Resettlement Nil

17 Power requirement 10 MVA, Source- GESCOM

18 Benefit Cost ratio 1.10

Page 7: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 5

Fig. 1 Location map of the project

Page 8: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 6

2.1 Need for the project

Proposed command areas Taluks are severely prone to erratic droughts due to lack of south-west monsoons. Drought causes agriculture a risky venture. Due to which people are constantly translocating to adjoining towns and cities. The people of the region have no other employment opportunities except agriculture and there is potential land bank to grow suitable crops in the region. Hence providing irrigation and stabilizing the agricultural production, provides a much needed relief to the people. It improves the per capita income and standard of living of the people. Further it utilizes the water and land resources and substantially improves GDP contribution from agriculture.

The cultivable area of Chadchan village, part of Havinal, Shiradona and other surrounding villages are left out and not getting irrigation water from any of the UKP schemes. These villages fall under Indi taluk of Vijayapura district located in the border of Karnataka and Maharashtra. The lands of these villages are almost at the tail end of Indi Branch Canal. Length of Indi Branch Canal is 172.0 Km and these villages are located at about Ch.168.0 Km.

Initially, as per the Master plan, these villages were proposed to be provided with Irrigation facility from either Indi Branch Canal or Indi Lift Canal. After detailed survey of Indi Branch Canal with designed bed fall these areas were left out as they were low lying elevation. The elevation of these villages is between RL 485.0 to RL 460.0 and bed level of Indi Branch Canal is RL 446.0. The distance from Km 168.0 of IBC to left out area is about 6.0 Km.

Alternatively, the areas of these villages are below the bed level of Indi Lift Canal but due to having achieved contemplated command area, the canal is terminated near Zalki before crossing NH-13. The distance from tail end of Indi Lift Canal to Chadchan area is about 15.0 Km.

The area being near to Bhima River and drought affected, does not receive water from any of the schemes planned under Upper Krishna Project. Farmers of this area and local leaders are pressing hard to provide Irrigation facility to this suffering command area.

2.2 Re-allocation of water for the proposed scheme

It is found that under Indi Branch Canal, the contemplated ICA of 1,31,260 Ha is not achieved physically. The notified command area of IBC as on date is 1,24,109 Ha and there is no scope for further extension of command area under IBC as the canal is tailed off at Maharashtra border. Hence there is a balance of 7150.0 Ha of command area under IBC.

Considering the cropping pattern of IBC (UKP Stage-II), there will be a savings of 47.146 MCM or 1.665 TMC of water under IBC. This balance area along with the left out areas of Chadchan and surrounding villages (2065 ha) are considered for providing irrigation facilities under the present project.

It is not possible to irrigate 9215.0 Ha out of savings of 1.665 TMC from Indi Branch Canal, by adopting the above cropping pattern. Hence, Annual water requirement for the proposed scheme is works out to be 49.305 MCM or 1.741 TMC.

On study of topography of the command area it is found that after delivery chambers the command area is in falling contour and both the branch canals runs in ridge line with several drops. It is proposed to make use of this available natural head and provide the distribution system with closed conduit. This will increase the overall efficiency of project from 51% to 75%. Hence there will be reduction in requirement of water and the water requirement for the proposed scheme will be 33.41 MCM or 1.18 TMC. However, remaining 0.56 TMC of water will be utilised at later stages of the project either for tank filling to recharge the ground water or to supply the drinking water. Hence, the water allocation for the scheme is within the award of KWDT.

2.3 Command area of the project

The command area of 9,215 ha is spread across Indi Taluk of Vijaypura District. 8 villages will be benefitted under this scheme and they are as follows.

Page 9: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 7

Table 2 List of benefitting villages

Sl.No District Taluk Benefitting Villages Command area (ha)

1

Vijayapura Indi

Chadchan 2720.38

2 Havinal 1569.29

3 Godihala 913.26

4 Halahalli 1301.42

5 BaraddolaTikke 1924.38

6 Shiradona 483.43

7 Revatagoan 207.68

8 Neevaragi 95.16

Total 9215.00

Table 3 Details of bifurcation of command area

Sl. No. Command Command area (ha)

1 East command 4588.00

2 West command 4627.00

Total 9215.00

2.4 Irrigation Planning and structural components of the project

An intake channel (100 m) is proposed to lift the water from Bhima River. A jack well cum pump house will be constructed to pump the water to the Delivery chambers of East and West command through a MS rising main of 14.4km (East) and 18.10 Km (West) length and 1.2 m diameter. The RL of delivery chambers is kept at RL 484.300 m (East) and RL 489.300 m (West). The technical details of the project are given below;

Table 4 Details of zones in command area

A. Lift Location

Name of the river Bhima

Lift Point Holisankh Village, Indi Taluk, Vijaypura District

Ground Level RL 425.641 m

CBL 413.700 m

Delivery Level 604.00 m

B. Intake Canal

Length 100.0 m

Bed width 1.70 m

Side slope 1.5:1

Free board 0.60 m

C. Jackwell cum pump house

East command West command

No. of Pumps 2 working + 1

standby 2 working + 1

standby

Total Power Requirement 4.67 MVA 5.25 MVA

Electrical Sub-station

110 KV/6.6 KV outdoor type with 2 no‟s ( 1 working + 1 standby) of 10.0 MVA

power transformer is proposed

D. Rising Main

East command West command

Length 14400 18100

Diameter 1200 1200

Peak Discharge (Cumecs) 1.942 1.958

Design discharge (Cumecs) 1.942 1.958

Discharge for each Row 1.942 1.958

Page 10: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 8

(Cumecs)

Velocity considered (m/s) 1.717 1.731 E. Delivery Chambers

East command West command

Ground level at Delivery Chamber

RL 484.300m RL 489.300 m

Bed level RL 484.200 m RL 488.500 m

Full supply level RL 485.000 m RL 489.500 m

Capacity of sump with 1.50 minutes retention capacity

RL174.78 Cum 176.22 Cum

Size 15.0 m × 15.0 m RL 14.0 m × 14.0 m

Height 1.75 m RL 1.95m

Delivery level RL 485.000 m RL 489.500 m

Top level of delivery pipe RL 485.150 m RL 489.650 m

2.5 Land Requirement

The proposed project requires 108.4 Ha for implementation of the project. The land required is only for construction of Jack well cum pump house, Intake canal and Delivery chambers. No forest land is required for the project. The required land will be acquired as per the Right to Fair Compensation and Transparency in Land Acquisition Act, 2015.

2.6 Existing cropping pattern details

Table 5 Existing cropping pattern in the command area

Sl. No. Season Crop Percent (%) 1

Khariff

Maize (Hy.) 5

2 Jowar 12

3 Ground nut 12

4 Bajra 12

5 Pulses 10

6 Other Oil seeds 6

Sub-Total 57

1 Rabi

Wheat 4

2 Jowar 29

Sub-Total 33

1 Bi-seasonal

Cotton 5

2 Vegetables 5

Sub-Total 10

Total 100

2.7 Proposed cropping pattern details

In view of introducing flow Irrigation system in the entire command area of 9215 Ha, the following cropping pattern (for Khariff and Rabi Season) is proposed.

Table 6 Proposed cropping pattern

Sl. No. Season Crop Percent (%) 1

Khariff

Maize (Hy.) 20

2 Jowar 15

3 Ground nut 20

4 Sunflower 5

5 Pulses 5

Sub-Total 65

1

Rabi

Local Jowar 10

2 Safflower 5

3 Gram 5

Page 11: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 9

Sl. No. Season Crop Percent (%) 4 Sunflower 5

5 Groundnut 5

6 Wheat 5

Sub-Total 35

Total 100

2.8 Benefit cost ratio

The benefit cost ratio has been worked out to 1.10 considering the annual administrative expenses, depreciation charges and electrical energy charges.

3. Description of baseline environment

Collecting the baseline environmental status of the project area helps to ascertain the magnitude of impacts that are likely to be caused due to the proposed project on different environmental components. It also helps to identify critical environmental attributes required to be monitored during and after the proposed development. To assess the baseline environmental status, command area, 10 Km radius from the main project components were considered and the data was collected during the period Monsoon (July 2016 – September 2016). In addition to the baseline environmental monitoring, field inspection in the study area, collection of secondary information for all the environmental components and discussions with the officials and local public were conducted by the experts to establish realistic information on the area with respect to the project.

3.1 Physical Environment

3.1.1 Climate & Meteorology

Air borne pollutants is dispersed by atmospheric motion. Knowledge of these motions, which range in scale from turbulent diffusion to long-range transport by weather systems, is essential to simulate such dispersion and quality of impacts of air pollution on the environment. The purpose of EIA is to determine whether concentrations are likely to encounter at fixed locations (known as the receptor), due to the given sources (locations and rates of emission known) under idealized atmospheric conditions.

Secondary information with respect to meteorological data (Temperature, Relative Humidity, Rainfall, Wind speed and Wind direction etc.) were collected from Vijayapura and Bagalkot meteorological observatory.

3.1.2 Ambient air quality

According to preliminary investigations, the ambient air quality in the study area is found to be good, in the absence of industrial growth in the command area. However, as part of the baseline data collection and in order to understand the status of ambient air quality during the study area, 2 ambient air quality monitoring stations were established and continuously monitored during the study period. AAQM was carried out on 24hrly basis on weekly twice mode continuously for one single month in Monsoon season (July 2016 – September 2016).

The results of ambient air quality reveal that, PM10 was in the range between 56.58 – 62.72g/m3,

PM2.5 was in the range between 20.86 -22.86g/m3. SO2 and NO2 are in the range between 3.67 –

3.81g/m3 and 10.34 – 11.19g/m3 respectively. Whereas NH3 ranged between 14.89 –

14.91g/m3, CO and O3 were 0.82 – 0.84g/m3 and 1.38 -1.51g/m3 respectively. The air quality index in the study area is found to be satisfactory for PM10 and for PM2.5, NO2, SO2, NH3, CO and O3 it was found to be good. Benzene, Benzo(a) Pyrene and all heavy metals were found to be BDL.

3.1.3 Ambient Noise levels

The results of ambient noise levels were compared with Residential standards and results reveal that, the noise levels in the study area ranging from 43.97 – 47.8 dB (A) for day time and 36.53 – 38.81 dB (A) for night time during Monsoon season. Overall, the noise levels in all the seasons

Page 12: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 10

were observed to be within the CPCB standards. Overall, the noise levels in the seasons were observed to be well within the CPCB standards.

3.1.4 Geology and Minerals

The main rock type observed in the command area is Basalt belonging to Deccan Traps of various flows belonging to Upper Cretaceous to Lower Eocene Age. Geology map is given below.

Table 7 Geological succession of the study area1

Laterite Recent Cainozoic

Basalt Mahabaleshwar Formation

Sahayadri Group Upper Cretaceous to Lower

Eocene

Deccan Trap Purandargarh Formation

Diveghat Formation

3.1.5 Soil characteristics

Geographically, the district lies in the tract of the Deccan Plateau. The upland soil being shallow, the villagers are generally confined to the banks of the streams and are far away from one another. The Bhima Valley has plains and consists of rich tracts of deep black soil stretching from west to east.

Deep to very deep black soils (Vertisols) - more than 90cm depth

Medium Black soils (Vertisols and inceptisols) - 22.5 cm to 90 cm depth

Red sandy loam - (22.5 cm to 90cm depth)

Shallow heavy or fine textured.

3.1.6 Hydrology

Bhima River forms Northern boundary with the Maharashtra State. Southern part of the Vijayapura District forms a catchment area of the Krishna while northern part of the catchment area of Bhima. Bhima River is an important tributary of Krishna River. A Major Dam has been constructed across the Krishna River near Almatti in the district. Don River is the tributary of the Krishna River and flows for about 160 Kms in a meandering course from west to east in the central part of the District. The water of this river is generally brackish. Drainage pattern is sub - dendritic to sub-parallel in nature and the drainage density varies from 0.49 to 1.02 Km/ Sq.Km. Average rainfall of the district is 578 mm. Climate varies from 20° C to 42.0°C.

3.1.7 Surface Water

The surface water quality analysis results reveal that, Conductivity and Total Hardness of the samples varied from 550 µs /cm at Lift Point near Holisankh -1073 µs /cm at Bori River and 164 mg/L at Downstream of Lift Point -368 mg/L at Bori River respectively. BOD of surface water ranges from 6 mg/L at Upstream of Lift Point -14 mg/L at Downstream of Lift Point. Sulphate and Chloride results varied from 57.8 mg/L at Doddahalla - 94.3 mg/L at Bori River and 43.9 mg/L at Upstream of Lift Point -131.9 mg/L at Bori River respectively. Total coliform was detected in all locations except Doddahalla. E.coli was detected in downstream area of lift point. Overall, the physic-chemical parameters of the surface water were found to be within the standards except for the Total Coliform and E.coli content in certain samples.

3.1.8 Ground Water

The Physico-chemical parameters for the Ground Water are within the standards. Conductivity values were found to be 1273 µs /cm at Chadchan Village and 1642 µs /cm at Bardol Village. Total Hardness detected was 508 mg/L and 532 mg/L at Chadchan Village and Bardol Village respectively. Sulphate values were found to be 181.6 mg/L and 177.4 mg/L at Chadchan Village and Bardol Village respectively. Total coliform and E. coli were absent in the ground water samples collected.

1

Geological Quandrangle Map (1998), Geological Survey of India, GoI

Page 13: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 11

3.1.9 Land use assessment

The results indicate that the core zone is dominated by crop lands followed by forest and water body. It also includes fallow land. The ground truth survey revealed that the crop land shown in the satellite imagery is coming in semi-arid region and farmers depend on monsoon for cultivation.

Table 8 Land use / land cover classification in the study area

Sl. No. Land use Area (Ha.) Percentage (%)

1 Agricultural plantation 2.073 0.022 2 Fallow land 30.718 0.333 3 Kharif + Rabi (Double Crop) 957.124 10.387 4 Kharif crop 6250.670 67.831 5 Lake / Tanks 47.016 0.510 6 Land with scrub 139.981 1.519 7 Land without scrub 22.108 0.240 8 Rabi crop 1694.404 18.387 9 River / Stream 45.041 0.489 10 River Island 0.087 0.001 11 Village 25.778 0.280

Total 9215.000 100.00

3.2 Biological Environment

3.2.1 Flora

A total of 52 species of trees, 19 species of shrubs, 42 species of herbs and 28 species of grasses found in the study area. All the species observed / recorded are common and no rare, endangered, threatened species found in the region.

Among 52 species recorded, Azadirachta indica found abundant compared to other species due to its close contact with black cotton soil and can withstand maximum temperatures. Acacia nilotica restricted to bunds of agricultural lands and river banks.

The other species recorded in the quadrates are Eucalyptus hybrid, Tamarindus indica, Albizzia lebbeck and Pongamia pinnata. Overall, the Shannon wiener diversity indices indicating lesser diversity of species in the study area.

Table 9 List of commonly found tree species in the study area

Sl.

No Common Name Botanical Name

Status as per

Red data book

IUCN Status

2015-4

1 Karijali Acacia nilotica Common Common

2 Kaggali Acacia catechu Common Common

3 Banni Acacia ferruginea Common Common

4 Bilijali Acacia leucophloea Common Common

5 Heddi Adina cordifolia Common Common

6 Bilpatre Aegle marmelos Common Common

7 Hebbevu Ailanthus excelsa Common Common

8 Sujjulu Albizia amara Common Common

9 Bage Albizia lebbeck# Common Common

10 Dindaga Anogeissus latifolia# Common Common

11 Halasu Artocarpus integrifolia# Common Common

12 Bevu Azadirachta indica# Common Common

13 Kaduhippe Madhuca indica# Common Common

14 Basavanapada Bauhinia racemosa# Common Common

15 Burga Bombax ceiba# Common Common

16 Mulgojjalu Bridelia retusa# Common Common

17 Muthaga Butea monosperma# Common Common

Page 14: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 12

18 Kakke Cassia fistula# Common Common

19 Huruglu Chloroxylon swietenia# Common Common

20 Sissoo Dalbergia sissoo# Common Common

21 Bettakanagalu Dillenia indica# Common Common

22 Thupra Diospyros melanoxylon# Common Common

23 Neelagiri Eucolyptus tereticornis# Common Common

24 Bela Feronia elephantum# Common Common

25 Shivane Gmelina arborea# Common Common

26 Thapsi Holoptelea integrifolia# Common Common

27 Mavu Mangifera indica# Common Common

28 Sampige Michelia champaca# Common Common

29 Akash Mallige Millingtonia hortensis# Common Common

30 Karibevu Murraya koenigii# Common Common

31 Honge Pongamia pinnata# Common Common

32 Kare Randia deumetorum# Common Common

33 Nerale Syzygium cumini# Common Common

34 Hunase Tamarindus indica# Common Common

35 Saguvani Tectona grandis# Common Common

36 Alale Terminalia chebula# Common Common

37 Hale Wrightia tinctoria# Common Common

38 Gojjaga Caesalpinia bonducella# Common Common

39 Srigandha Santalum album# Common Common

40 Gobbarada gida Gliricidia sepium# Common Common

41 Subabul Leucaena leucocephala# Common Common

42 Nelli kai Emblica officinalis# Common Vulnerable

43 Copper pod Peltophorum pterocarpum# Common Common

44 Sihihunase Pithecellobium dulce# Common Common

45 Echalu Phoenix sylvestris# Common Common

46 Gulmohar Delonox regia# Common Common

47 Gasagase Muntingia calabura# Common Common

48 Bugari mara Thespesia populnea# Common Common

49 Nimbe Citrus indica# Common Common

50 Jacaranda Jacaranda mimosifolia# Common Common

51 Pappaya Carica papaya# Common Common

52 Sapota Manilkara zapota# Common Common

Source: IUCN/Red data books: Karnataka Forest Department and Botanical Survey of India.

3.2.2 Fauna

The study area has poor diversity of wild animals. 9 species of mammals found in the region and are common to the region. The avian diversity is fairly good and 28 species of birds recorded in the region. Of which, Indian peafowl (Pavo cristatus) belongs to Schedule-I category and remaining species belongs to Schedule -IV of the Wildlife (Protection) Act, 1972. 15 Species of butterflies found in the study area and all are common to the region. No rare, endangered and threatened species found in the region.

4. Anticipated Environmental Impacts & Mitigation Measures

Due to the activities of the project, there will be potential impacts on the environment of varying magnitude. Most of the impacts are likely to occur during the construction phase of the project. The following sections reveal the impacts due to the project on the physical, biological and social environment. Impacts have been assessed based on the information collected from the screening and feasibility study reports, field surveys and additional secondary data collected as part of the study. The majority of the impacts are confined only during the construction stage.

Page 15: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 13

4.1 Ambient Air Quality

The construction of the project is expected to last approximately in 24 months. The initial site clearing will be followed by site preparation activities

Sources of air pollution

Pollution due to fuel combustion in equipments: The operation of construction equipments requires combustion fuel. Normally, diesel is used for such equipments. The major pollutant which gets emitted as a result of combustion of diesel is CO & HC.

Dust pollution: The operation of the trucks carrying construction materials to the site, batching plants during the construction phase is likely to generate fugitive emissions, which can move even up to 100 m in predominant wind direction.

Emissions due to usage of firewood for cooking at labor camps.

Due to operation of DG sets and excavation, laborers are prone to health problems.

The following mitigation measures will be followed to control potential emissions of fugitive dust during construction of the project:

High speed diesel (HSD) with low sulphur content will be used for the construction equipments/ vehicles which has low ash content.

Unpaved roads in the project construction site are watered frequently as necessary to prevent fugitive dust. All vehicles carrying construction materials are covered with tarpaulin to avoid spillage of construction materials. Regular water sprinkling will be undertaken (3 times a day) to avoid fugitive dust emissions.

All the trucks carrying construction materials to the site shall be inspected regularly and shall have valid Pollution under Control (PUC) certificate.

Labours camps shall be provided with LPG facilities.

Usage of PPEs like nose masks will be provided for construction labours.

4.2 Ambient Noise Level

During construction phase, various sources of noise pollution arise due to operation of machineries like concrete plant, cranes, batch plants, Crane, Generator, Tractor, Welder/Torch, Vibrating Hopper etc.,

Other source of noise pollution includes movement of vehicles for unloading of construction materials, fabrication, handling of equipments.

Construction activities are expected to produce noise levels in the range of 80 – 95 dB (A).

Various measures proposed in spite of noise levels are lower than the prescribed standard values as per CPCB, are presented below.

DG sets are placed on the rubber cushion padding, enclosed and maintained well in good condition. It is encased and barricaded & taken to all places where it will be used. This reduces the noise level in and around the source by 4 dB.

Construction activities shall be restricted only to day time and there should not be any construction during evening and night hours to avoid the psychological effects on surrounding population and biota.

During construction time, possible chances of number of trucks coming to the project area is more carrying debris, muck etc and the drivers of these vehicles must be instructed with sign boards and not to use shrill horns for any purpose.

Controlled blasting will be undertaken wherever necessary to minimize the noise even though it is cost effective.

PPEs such as, ear plugs and ear muffs will be provided to the workers.

Page 16: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 14

Periodic maintenance and servicing of construction equipments/ vehicles.

Acoustic enclosures will be provided for DG sets

4.3 Water Environment

The quality of water resources both surface and ground water may also deteriorate if solid waste management practices are not adopted in the labour camps of the project during peak construction phase.

Improper treatment of sewage from labor camps leads to infiltration into the subsurface soil and finally affects the ground water of the region. This will create unaesthetic conditions in the site, attracts mosquitoes/flies, thereby chances of deteriorating the health of the workers in unhygienic conditions. Improper disposal of construction debris, used oil, diesel for DG sets, etc will result in ground water contamination and in turn affecting drainage of the area.

The mitigation measures include;

The sewage generated from the labour camps shall be treated in the Septic Tank and Soak Pits designed and constructed as per IS 2470 Part-I & Part-II.

There will be no open discharge of sewage from labour camps and the labour camps will be provided with sufficient bathrooms and toilets. Periodical health check-ups for labors will be done.

Construction debris will be reused at site, used oil generated from the DG sets will be stored separately and handed over to KSPCB authorized recyclers.

During construction of intake canal, the river course and the point of contact of intake canal will be provided with sand bags

4.4 Biological Environment

During construction, due to the fugitive dust, photosynthetic activity would be reduced and leads of wilting of plants.

Use of river water for domestic needs by labors will bear riverine water pollution and affects aquatic biota.

Use of fire wood for labor camps results in cutting of trees.

Construction equipment / vehicles washing leads to oil spillages into river and leads to reduction in dissolved oxygen levels.

Improper disposal of construction materials and domestic wastes leads eutrophication.

Mitigation measures:

Periodical water sprinkling in and around the construction areas including access roads to avoid fugitive dust generation.

Labor camps shall be located 1 Km away from the river course and imposing restrictions for not using the river water for domestic purpose.

Labors camps shall be provided with LPG facilities.

Construction equipment / vehicles washing shall be undertaken at authorized service stations.

Security personnel near river course and sign boards will be erected to educate the labors.

4.6 Evaluation Impacts

Matrix method was used to identify interactions between various project activities and environmental parameters and components. Later, a weightage of 1-10 shall be given to the impacts based on the significance of the impacts. The impacts are quantified „with‟ and „without‟ EMP. The criteria adopted for weightage are given below;

Page 17: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 15

Table 10 Criteria for evaluation of impacts

Sl.No Criteria Score

1 Minor impact 1-2

2 Medium impact 3-4

3 Significant impact 5-8

4 Major impact 9-10

Page 18: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 16

Table 11 Evaluation of Impacts

Sl.No.

Environmental Attributes

Project Activities

Nature of Impacts

Magnitude

Revers

ible

Irre

vers

ible

Long T

erm

Short

Term

Direct

Indirect

Posi

tive

Negative

Without

EM

P

With E

MP

A. Construction Phase

1.Impacts on Land Environment

1 Land

Construction of intake canal, pump house and rising main

M

Excavation for intake canal, rising main, main canal, etc

H

Vehicular movement M

2 Change in Topography Construction of intake canal, pump house and rising main

M - -

3 Loss of Productive Soil

Construction site, temporary offices, workers camps, stockyards

M

Construction of Haul roads

L

Excavation for canal H

4 Compaction of Soil Site Clearance L

Movement of vehicles L

5 Contamination of Soil Machinery and operation of the Diesel Generator Sets

M

Page 19: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 17

Sl.No.

Environmental Attributes

Project Activities

Nature of Impacts

Magnitude

Revers

ible

Irre

vers

ible

Long T

erm

Short

Term

Direct

Indirect

Posi

tive

Negative

Without

EM

P

With E

MP

Labor camps H

2. Impacts on Water Environment

1 Eutrophication Sewage from labor camp H

Muck disposal H

2 Change in River Water Quality

Construction of Intake canal, jack well cum pump house, DC, disnets

M

Diversion of river water H

Decomposition of sediments and deposition of organic matter

M

Washing of equipments L

Muck disposal M

3 Change in surface and ground water quality

Sewage from labor camp H

3. Impacts on Air Environment

1

Increase in dust concentration

Construction equipments, operation of DG sets,

M

Excavation H

2 Fugitive Emissions from various sources

Vehicular movement H

Loading and dislodging Use of sand, fine aggregates

M

Batching plant M

3

Increase in SO2, PM, NOx

Vehicular movement M

Operation of DG sets M

Page 20: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 18

Sl.No.

Environmental Attributes

Project Activities

Nature of Impacts

Magnitude

Revers

ible

Irre

vers

ible

Long T

erm

Short

Term

Direct

Indirect

Posi

tive

Negative

Without

EM

P

With E

MP

Fuel Combustion in equipments and Vehicles

M

Burning of fuels from construction workers

M

4 Impact on Human Health

Emission of Dust particles M

4. Impact on Noise Environment

1 Increase Noise Level Movement of vehicles M

Operation of D.G sets L

Movement of vehicles carrying raw materials

M

5. Impact on Biological Environment

1 Pressure on existing natural resources

Immigration of labor population

L

2 Reduced Photosynthetic activity, Wilting of plants

Transportation of construction materials

M

Site Clearance M

3. Impacts on Fishes and Aquatic Ecosystem

Increase in turbidity of water due to Washing of machineries

M

Sewage from labor camp H

6. Impact on Socio-economic Environment

1 Land acquisition Affecting livelihood H

2 Impact on Human Health

Due to water/air borne diseases, traffic movement

H

Page 21: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 19

Sl.No.

Environmental Attributes

Project Activities

Nature of Impacts

Magnitude

Revers

ible

Irre

vers

ible

Long T

erm

Short

Term

Direct

Indirect

Posi

tive

Negative

Without

EM

P

With E

MP

B. Operation Phase

1 Impacts on Land Environment

Application of natural fertilizers and pesticides

H

2 Impact on water environment

Application of fertilizers and pesticides

M

Page 22: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 20

5. Analysis of Alternatives

The cultivable area of Chadchan village, part of Havinal, Shiradona and other surrounding villages are left out and not getting irrigation water from UKP scheme.

These villages fall under Indi taluk of Vijayapura district located in the border of Karnataka and Maharashtra. The lands of these villages are almost at the tail end of Indi Branch Canal.

Length of Indi Branch Canal is 172.0 km and these villages are located at about Ch 168.0 km. Initially, as per the Master plan, these villages are proposed to be provided with Irrigation facility from either Indi Branch Canal or Indi Lift Canal.

After detailed survey of Indi Branch Canal with designed bed fall these area were left out due to higher elevation. The elevation of these villages is between RL 485.0 to RL 460.0 and bed level of Indi Branch Canal is RL 446.0.

The distance from km 168.0 of IBC to this left out area is about 6.0km. Alternatively, the areas of these villages are below the bed level of Indi Lift Canal but due to having achieved contemplated command area, the canal is terminated near Zalki before crossing NH-13.

The distance from tail end of Indi Lift Canal to Chadchan area is about 15.0 km. The area being near to Bhima River and drought affected do not receive water from any of the schemes planned under Upper Krishna Project.

Therefore, Chadchan LIS is proposed to irrigate 9215 Ha of dry land by utilizing 1.2 TMC of water.

6. Environmental Monitoring Program

The purpose of the monitoring program is to ensure that the objectives of the project is achieved through the mitigation measures and result in desired benefits to environment and local population of the region.

Table 12 Environmental Monitoring Plan (2 years)

Environmental Parameters

Parameters to be Monitored

Frequency of Monitoring

Locations Responsibility Estimated Cost in Rs.

Surface water quality of Bhima

river

pH, Temperature,

EC, TDS Alkalinity, TH,

DO, BOD, COD, NO3,

PO4, Cl, SO4, Na, K, Ca, Mg,

Silica, Oil & grease, MPN, Total coliform

Fortnightly once until

completion of Intake canal

Near lift point, Downstream

and Upstream of lift point

(3 No.)

Contractors or agencies

appointed by KBJNL

8,000/-

Ground water quality

pH, Temperature,

EC, TDS Alkalinity,

TH,NO3, PO4, Cl, SO4, Na, K, Ca, Mg, Silica, Oil & grease, MPN, Total

Once in a month

Chadchan, Bardol (2 No.)

Contractors or agencies

appointed by KBJNL

6,000/-

Page 23: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 21

coliform

Soil Quality

pH, EC, Mg, Ca, Alkalinity,

Cl, Na, K, Organic

Carbon, K, PO4, SAR, N and Salinity

Once in a month

Near lift point, Havinal,

Chadchan, Halahalla,

Bardol (5 No.)

Contractors or agencies

appointed by KBJNL

12,900/-

Air Quality PM10, PM2.5, NO2 and SO2

Monthly Near lift point,

Chadchan (2No.)

Contractors or agencies

appointed by KBJNL

12,000/-

Noise Levels Leq Day, Leq Night in dB(A)

Monthly once until

completion of construction

works

Near lift point, Chadchan

(2No.)

Contractors or agencies

appointed by KBJNL

8,000/-

Subtotal/ Month 46,900/-

Subtotal – A – for 24 months 11,25,600/-

Aquatic life Limnological and biological

studies

Six monthly once until completion

Near lift point (1 No.)

Contractors or agencies

appointed by KBJNL

60,000/-

Health check ups

Spirometry, Pulse

Oxymetry, Blood Test,

Lung Function Test, Eye test, Physical fitness

tests

Six monthly once until completion

Labour camp (1 No.)

Contractors or Doctors / PHC appointed by

KBJNL

2,00,000/-

Subtotal/ 6 Month 2,60,000/-

Subtotal – A – for 24 months 10,40,000/-

Total 21,65,600/-

Table 13 Environmental Monitoring Program for Operation phase (3 years)

Environmental Parameters

Parameters to be Monitored

Frequency of

Monitoring Locations Responsibility

Estimated Cost in Rs.

Surface water quality of

Bhima river

pH, Temperature, EC, TDS

Alkalinity, TH, DO, BOD, COD, NO3, PO4, Cl,

SO4, Na, K, Ca, Mg, Silica, Oil & grease, MPN, Total coliform

Quarterly once for 3

years

Near lift point, Downstream

and Upstream of lift point, Doddahalla, Bori river (5 No.)

Agencies appointed by

KBJNL 7,900/-

Soil Quality

pH, EC, Mg, Ca, Alkalinity, Cl, Na,

K, Organic Carbon, K, PO4,

SAR, N and

Quarterly once for 3

years

Near Lift point,

Havinal, Chadchan, Halhalli,

Agencies appointed by

KBJNL 14,000/-

Page 24: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 22

Salinity Bardol (5 No.)

Subtotal/ 3 Month once 21,900/-

Subtotal – A – for 3 years 2,62,800/-

Aquatic life Limnological and biological

studies

Yearly once for 3 years

Near intake canal (1 No.)

Agencies appointed by

KBJNL 50,000/-

Subtotal – B for 3 years 50,000/-

Total 3,12,800/-

Based on the above and as per the guidelines of MoEF under the supervision of Executive Engineer, KBJNL, IBC, O&M Division, KBJNL, six monthly compliance reports will be submitted to Regional Office of MoEF, Bengaluru.

In order to verify the effectiveness of monitoring program, Regional Office, MoEF, Bengaluru and Regional Office, KSPCB, Vijayapura will be the enforcing agency to monitor the project activities.

7. Social Impact Assessment

Chadchan Lift Irrigation Scheme is proposed to irrigate an area of 9,215Ha by lifting 1.20 T.M.C of water from Bhima River during Khariff and Rabi season. The project aims at providing irrigation facility to 8 villages of Indi taluk. Benefiting villages include Chadchan, Havinahala, Godihala, Halahalli, Baradol, Shiradona, Revatagoan and Neevaragi.

7.1 Demographic profile of the villages

The total population of the eight villages is 40871. Out of which, 21017 is male and 19854 is female.

Table 14 Details of benefitting villages

Sl. No.

Name of the villages Total Population

Total male population

Total Female population

1 Chadchan 15542 7923 7619

2 Havinahala 3389 1792 1597

3 Godihala 2219 1130 1089

4 Halahalli 1645 834 811

5 Baradol 6495 3346 3149

6 Shiradona 3309 1733 1576

7 Revatagoan 3991 2046 1945

8 Neevaragi 4281 2213 2068

Total 40871 21017 19854

7.2 Impact of the project

During the project construction phase and operation-management phase additional employment will be generated.

The only negative impact is that 288 acres of agricultural land spreading across 8 villages will be lost for the project construction purposes and they will be sufficiently compensated as per rules. Since no residential or commercial properties affected, there is no need for any displacement and hence resettlement /rehabilitation is not involved.

Villagers have some additional demands for construction of linking roads, sanitation facilities etc which will also be duly attended by the Govt., especially since this backward villages are in the hit list for the developmental interventions.

So overall impact of the project is positive which will bring long term development/ growth in the development map of these villages.

Page 25: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 23

8. Project Benefits

The CLIS is proposed to provide economically viable and socially acceptable irrigation practices for the command area. Irrigation is important to the health of the agricultural industry. Improving the viability of individual farming and increasing the efficiency and economic stability of the command area taluks and also contributing to the economic and social objectives of the Karnataka State are the expected outcomes of the proposed scheme. Some of the important project benefits are given below:

Agricultural linkages will be considerably improved.

The project improves total farm output and hence raises farm income.

Project improves yields through reduced crop loss due to erratic, unreliable or insufficient rainfall. The details before and after the advent of irrigation is given below.

It allows a greater area of land to be used for crops in areas where rain fed production is impossible or marginal. Due to the implementation of the scheme 9215 Ha will be under irrigation.

Extensive agricultural production supplies raw materials to the nearby small scale industries thereby increasing the economy in the region.

Altogether, population of 40,871 belongs to 7945 families in the command area will be benefitted directly under the scheme.

Direct employment opportunities for 150 members during construction phase and 30 members during operation phase of the project. Further, indirectly labor opportunities will be substantially improved since larger area will be brought under irrigation.

It improves fodder crops and in turn dairy farming in the command area.

Increased benefits of water conservation through closed conduit irrigation for the entire 9215 Ha of command area.

The project requires only 108.4 Ha for implementation of the scheme and does not envisage rehabilitation and resettlement.

No tree cutting involved and no forest land required for implementation of the scheme. Agro forestry shall be taken up in command area and it improves the ecosystem services.

Page 26: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA Report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 24

9. Environmental Management Plan

Although agriculture is usually associated with its positive impacts on human life, irrigation practices may be associated with impacts on environmental conditions, which may eventually curtail the sustainability of irrigation projects. For this reason, Environmental Impact Assessment (EIA) has been recognized as an integral part of the early planning studies of irrigation projects in order to identify any expected negative impacts and suggest the necessary mitigation plans to curb these impacts through formation of Environmental Management Plan (EMP).

Table 15 Environment Management Plan

Project Activity Impacts Mitigation measures

Advantage Location

Responsibility

& Monitoring

Agency

Time frame

A. Construction Phase

1. Air Environment

Fuel combustion

from construction equipments

Emission of

pollutants (PM, SO2)

High speed Diesel

with low sulphur content will be used

for the construction equipments/

vehicles which has

low ash content

Reduction in

pollutants level

Intake canal, jack well cum

pump house, Construction of canals.

Contractor &

KBJNL

Throughout the construction

period

(24 months)

Vehicular

movement and operation of

batching plants

Dust pollution

Water sprinkling and vehicles should

be covered with

tarpaulin, speed limit restrictions

Reduction in fugitive emissions

Intake canal, jack well cum

pump house, access roads, around construction site,

disnets

Contractor & KBJNL

Water sprinkling - 3 times/day

Burning of fire

wood

Emission of

pollutants (C, SO2)

Labor camps supplied with LPG

facility

Reduction in emission

levels Labor camp

Contractor &

KBJNL

Throughout the construction

period (24 months)

Page 27: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA Report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 25

Project Activity Impacts Mitigation measures

Advantage Location

Responsibility

& Monitoring

Agency

Time frame

Operation of DG

sets, excavation

Health problems to

labors

Usage of Nose

masks

Healthy working

environment

Intake canal, jack well cum pump house, access roads,

around construction site, disnets

Contractor

&KBJNL

Throughout the construction

period (24 months)

2. Noise Environment

Operation of DG

sets and usage of

construction equipments

Increase is noise

levels

PPEs such as, ear plugs and ear muffs

will be provided to

the workers, Acoustic enclosures

for DG sets

Reduction in noise

levels

Intake canal, jack well cum

pump house, access roads,

around construction site, disnets

Contractor

&KBJNL

Throughout the

construction

period (24 months)

Vehicular

Movement

Increase is noise

levels

Construction activities shall be

restricted only to day time

Reduction in noise

levels

Intake canal, jack well cum pump house, access roads,

around construction site, disnets

Contractor

&KBJNL

Throughout the construction

period (24 months)

3. Water Environment

Sewage from labor camps

Surface and ground water pollution

Treatment through septic tank and

soak pit

Reduction in pollution load

Labor camps Contractor

&KBJNL

Throughout the construction

period

(24 months)

Stagnation of

water

Mosquito breeding

grounds

Providing proper

sanitary facilities

Healthy environment

Labor camps Contractor &KBJNL

Throughout the

construction period

(24 months)

Excavation and operation of DG

sets

Muck generation, blockage of natural

drains and

contamination of ground water

Reuse of muck at site, disposal of

used oil KSPCB

authorized preprocessors

Reduction in surface and ground water

contamination Intake canal, jack well cum

pump house, disnets Contractor &

KBJNL

Throughout the

construction period

(24 months)

Page 28: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA Report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 26

Project Activity Impacts Mitigation measures

Advantage Location

Responsibility

& Monitoring

Agency

Time frame

Construction of intake canal

Increase in turbidity levels in river

Provision of sand bags

Healthy aquatic ecosystem

Intake canal Contractor &KBJNL

4 Months

4. Soil Environment

Construction of labor camps, stock

yards

Loss of fertile soil Waste land will be used for erection of

labor camps

Land resource optimization

Waste land Contractor

&KBJNL

Throughout the construction

period

(24 months)

Maintenance of DG

sets and construction

machineries

Soil contamination Maintenance at

service centers

Reduction in soil

contamination

Intake canal, jack well cum

pump house, access roads, around construction site,

disnets

Contractor &KBJNL

Throughout the

construction period

(24 months)

5. Solid and Hazardous waste Environment

Excavation Change in hydraulic regime

Reuse of excavated earth

Natural drainage pattern maintained Intake canal, jack well cum

pump house, disnets

Contractor

&KBJNL

Throughout the construction

period (24 months)

Improper dumping

of solid waste from labor camps

Water pollution Labor camps at 1

km away from river, Disposal to

Municipal Authorities

Reduction in siltation

and eutrophication

Intake canal and river course

Contractor &

KBJNL

Throughout the

construction

period (24 months)

6. Biological Environment

Construction activities

Wilting of plants Water sprinkling Normal photosynthetic

activity

Intake canal, jack well cum pump house, access roads,

around construction site,

disnets

Contractor

&KBJNL

Throughout the construction

period

(24 months)

Labor camps Riverine water

pollution

Labor camps at 1

km away from

river, restrictions for not using the

river water

Zero water pollution

Labor camps Contractor

&KBJNL

Throughout the construction

period (24 months)

Use of fire wood Cutting of trees LPG for labor Positive ecosystem Labor camps and its Contractor Throughout the

Page 29: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive summary Vijayapura, Karnataka of Draft EIA Report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 27

Project Activity Impacts Mitigation measures

Advantage Location

Responsibility

& Monitoring

Agency

Time frame

camps services surrounding &KBJNL construction period

(24 months)

Washing of construction

equipments

Reduced DO levels Washing at authorized service

stations

Aquatic system maintained

Bhima river Contractor

&KBJNL

Throughout the construction

period (24 months)

7. Socio-economic environment

Land acquisition Affecting livelihood Compensation as RFCLA&TRR Act

2013

Sustainability for livelihood

opportunities

Chadchan, Havinal, Godihala, Halahalli, Baradol Tikke,

Shiradona, Revatagoan,

Neevaragi

KBJNL 6 months

Vehicular

movement

Health problems Water sprinkling

and movement of

vehicles carrying raw materials only

during night time.

Healthy environment

Chadchan Village, Indi taluk Contractor

&KBJNL

Throughout the construction

period (24 months)

B. Operation phase

Excess application

of fertilizers and pesticides

Soil and water

contamination

Awareness on

organic farming practices

Reduction in pollution

load Command area

KBJNLand

Water user Associations

3 years

Page 30: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 28

9.1 Command Area Development Plan

9.1.1 Catchment Area Treatment (CAT) plan

Karnataka is a pioneer in implementing watershed program since 1983.Dry land development boards were constituted at in the divisional level, model watersheds, district level macro watershed programs, DPAP, DDP, IWDP, WGDP, RVP, NWDPRA and more recently from April 2008 Integrated Watershed Development program (IWMP).A state level perspective and Strategic Plan (SPSP) is prepared for the state and entire area (120.85 lakh ha) is contemplated to be treated by the end of XIV the plan period, on 90:10 ratio between center and state. Further, all programs aimed at enhancing irrigation use efficiency are brought under PMKSY to provide her kheth KO Pani and to increase crop yield per drop of water. As a result all the watershed programs are implemented under this activity.

In the district of Vijayapura, soil and moisture conservation program are being implemented since 1970s and some of the areas are revisited to take up post bund maintenance and similar activities. Desert Development program is implemented to saturate the rain fed areas for sustainable crop production activities.

Some of the methods suggested for soil conservation for CLIS catchment area are given below.

1. Broad based contour bunding on slopes (1-8%)

Outward cross slope of 1-8%

Longitudinal slope of 8%

Length of terrace, 20-35 m

Width of terrace, 3 to 5.5 m

2. Riser (earthen or stone)

Steep batters of, 0.25:1 3 Earthen shoulder bund

0.5 m base, 0.3 m height,01 m top

3. Stone bunding or fencing when stone is easily available.

0.3 m base, 0.2 m height, 0.1 m top

Followed by earthen bund of 0.1 m top

4. Land leveling

Low (bottom) flat deep areas leveled.

Bench terraces are also leveled by cut and fill.

5. Land slide control

Vegetative means

6.Goole

Water channels conveying water from natural springs as well as rainwater.

Same design delivers 5-50 liters/min in winter and 100-500 liters/min during rainy season.

Needs improvement in regulation.

7.Khatta/khala

Earthen ponds collecting discharge water of & seepage water.

Page 31: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 29

9.1.1.1 Cost Estimates as per Soil conservation treatments suggested

Area to Treated (ha) – 9210 ha

No. of Check dams (ha) – 35

Cost (Rs. Lakhs) – 175

Plantations (ha) – 9215

Cost (Rs. Lakh) – 297

9.1.2 Water Users’ Association (WUA)

The modern irrigation management aims at high efficiency of water conveyance and appropriate methods of water application, through participatory irrigation management at each stage of irrigation development. In Karnataka, it is essential to promote and implement the theme of participatory irrigation management in all the Irrigation projects through formation of Water Users‟ Association. The construction of OFD works will be taken up after formation of WUAs under the supervision of CADA, Belgaum.

The efficient management of irrigation water for maximizing productivity requires, firstly the efficient on farm water management and secondly the optimization of the use of water and land, through appropriate methods of water application. The efficient on-farm water management is related to water delivery system and allied works in the command area, which distributes the water to each farm. The items of works pertaining to on farm water management are termed as “On Farm Development Works”.

The On Farm Development works comprise of the following,

Maintenance of disnets, sumps

Control structures

Maintenance of Automation

Surface Drainage system

Farm roads

Land forming (Smoothening / grading/leveling)

9.1.2.1 Green belt development plan

9.1.2.1.1 Plantation around intake canal and jack well cum pump house

Green belt development activities will be taken up on either side of the intake canal and in and around jack well cum pump house along with canal bank plantation.

9.1.2.1.2 Agro forestry activates in command area

Agro-forestry refers to the practice of Agriculture and Forestry in the same piece of land. The Karnataka Forest Department (KFD) has accorded high emphasis on farm forestry as a component in the afforestation program. The sector of Agro-forestry or Farm Forestry has a good potential as most of the agriculture lands are devoid of any trees, in the district. The trees if planted on the bunds and on the boundary of the lands protect the crops from the desiccating high winds and also provide additional income from the trees to the farmer apart from providing him fodder and fuel as well.

Silvi-Pasture refers to the planting of the trees in a predominately grassland so as to provide fodder all the year round. This afforestation is aimed at not only addition of tree species, but also addition of highly nutritive and palatable grass species in the area, thereby providing much needed nutritious fodder to the livestock population.

Page 32: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 30

Table 16 Green belt development Plan around intake canal and jack well

Area proposed for Green belt

No. of saplings

Source for saplings

Time frame Responsible agency for implementation

Intake canal 30 Vijayapura KFD Nursery

After completion of inspection path works

KBJNL

Jack well cum pump house

50 After completion of site works

KBJNL

Command area 10/ ha First 2 years - 46075 Next 2 years - 46075

KBJNL and KFD

Main Canal Bank Plantation (19.45 Km)

3890 (1per

every 5 m)

After completion of inspection path works

KBJNL and KFD

Table 17 Species recommended for green belt development

Sl.No Local Name Botanical Name Sl.No Local Name Botanical Name

1 Ala Ficus bengalensis 17 Kadugeru Semecarpus anacardium

2 Basari Ficus infectoria 18 Kadivala Stephegyne parviflora

3 Beete Dalbergia latifolia 19 Kadnugge Moringa pterygosperma

4 Buruga Bombax ceiba 20 Kakke Cassia fistula

5 Dindiga Anogeissus latifolia 21 Kanagalu Dillenia pentagyna

6 Godda Lannea coromandclica 22 Kaval Careya arborea

7 Goni Ficus mysorensis 23 Mathi Terminalia tomentsa

8 Hebbalasu Artocarpus hirsuta 24 Muthuga Butea monosperma

9 Honne Pterocarpus marsupium 25 Nandi Lagerstroemea lanceolata

10 Hunalu Terminalia paniculata 26 Nelli Emblica officinalis

11 Ippe Madhuca Indica 27 Neralu Syzygium cumini

12 Jagalaganti Diospyros montana 28 Shivani Gmelina arborea

13 Jambe Xylia xylocarpa 29 Tadasalu Grewia tilaefolia

14 Saguvani Tectona grandis 30 Tare Terminalia bellerica

15 Yethiga Adina cordifolia 31 Hunase Tamarindus indica

16 Mavu Mangifera indica 32 Honge Pongamia pinnata

33 Huruglu Chloroxylon swietenia 34 Bevu Azadirachta indica

9.2 Fisheries Development Plan

Rs. 5 lakhs is earmarked for development of fisheries of Bhima river near lift location and intake canal area in due consultation with Fisheries Dept., Fingerlings of Mrigal, Catla and Rohu will be released to Bhima river and as per as possible to avoid exotic fish species like Tilapia.

9.3 Muck Disposal plan

Table 18 Muck disposal plan

Total excavated

quantity cum

Service Road and Inspection Path

Formation of embankment

Filling trenches

Land leveling Construction of CD works

691125 207337.5 103668.75 276450 69112.5 34556.25

Page 33: CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ …€¦ ·  · 2016-12-16CHADCHAN LIFT IRRIGATION SCHEME ZÀqÀZÀt KvÀ ¤ÃgÁªÀj AiÉÆÃd£É ... LIST OF TABLES Table 1 Salient

Chadchan lift irrigation scheme in Executive Summary Vijayapura, Karnataka of Draft EIA report

Krishna Bhagya Jala Nigam Ltd EHS Consultants Pvt Ltd, Bangalore 31

9.4 Cost for implementing EMP

Table 19 Cost for implementing Environmental Management Plan

Item Particulars Estimated Cost in Rs.

I. Construction Phase

A. Air Pollution Control

Water sprinkling 400/- x 2 tractors x 3 trips per day x 24 month's 25 days

(excluding rainy season and holidays)

2,00,000.00

Personnel protective equipments Lumpsum 25,000.00

Chimney to DG sets Lumpsum 25,000.00

LPG as cooking fuel 4 cylinders per unit x 25 units x 550 x 2 years

6,00,000.00

Sub-total A 8,50,000.00

B. Noise Pollution Control

Personnel protective equipments Lumpsum 25,000.00

Sub-total B 25,000.00

C. Water Pollution Control

Septic and soak pit Lumpsum 50,000.00

Sand bags Lumpsum 25,000.00

Sub-total C 75,000.00

D. Solid & Hazardous Waste Management

Solid waste collection bins with shed Lumpsum 25,000.00

Hazardous waste collection area with shed

Lumpsum 25,000.00

Sub-total D 50,000.00

E. Biological Environment

Plantation around intake canal and jack well

80 saplings x 500 Rs 40,000.00

Agro forestry development 92150 saplings x 10 Rs 9,21,500.00

Fisheries development Lumpsum 5,00,000.00

Canal bank plantation 19.45 Km X 1 sapling/5m = 3890 saplings x 1900 Rs

73,91,000.00

Sub-total E 88,52,500.00

F. Socio-economic Environment

Land acquisition 288 Acres x 4.32 cr x 2 x 100 solatium

17,28,00,000.00

Awareness and Training 5 lakhs per year x 3 years 15,00,000.00

Sub-total F 17,43,00,000.00

G. Environmental Monitoring during construction period

Sub-total G 21,65,600.00

Total (A-G) 18,63,18,100.00

II. Operation Phase

Environmental Monitoring for 3 years 3,12,800.00

Green Belt mainatainence for 3 years 15,00,000.00

Awareness and Training for 3 years 15,00,000.00

Soil conservation measures and implementation of CAT plan for 5 years 4,72,00,000.00

Total 5,05,12,800.00