12-1 Aggregate Planning 

William J. Stevenson

Operations Management

8th edition

Page 2: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 2/29

12-2 Aggregate Planning 

CHAPTER

12

Aggregate Planning

McGraw-Hill/IrwinOperations Management, Eighth Edition, by William J. Stevenson

Copyright © 2005 by The McGraw-Hill Companies, Inc. All rights reserved.

Page 3: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 3/29

12-3 Aggregate Planning 

Planning HorizonPlanning Horizon

 Aggregate planning : Intermediate-range

capacity planning, usually covering 2 to 12

months.

Short

range

Intermediate

range

Long range

Now 2 months 1 Year  

Page 4: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 4/29

12-4 Aggregate Planning 

y Short-range plans (Detailed plans)

y Machine loading

y Job assignments

y Intermediate plans (General levels)

y Employment

y Output

y Long-range plans

y Long term capacity

y Location / layout

Over view of Planning LevelsOver view of Planning Levels

Page 5: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 5/29

12-5 Aggregate Planning 

Planning SequencePlanning Sequence

Business PlanEstablishes operations

and capacity strategies

Aggregate plan

Establishes

operations capacity

Master schedule Establishes schedules

for specific products

Corporate

strategies

and policies

Economic,

competitive,

and political

conditions

Aggregate

demand

forecasts

Figure 12.1

Page 6: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 6/29

12-6 Aggregate Planning 

y R esources

y Workforce

y Facilities

y Demand forecast

y Policies

y Subcontracting

y Overtime

y Inventory levels

y Back orders

y Costs

y Inventory carrying

y Back orders

y Hiring/firing

y Overtime

y Inventory changes

y subcontracting

Aggregate Planning InputsAggregate Planning Inputs

Page 7: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 7/29

12-7 Aggregate Planning 

y Total cost of a plan

y Projected levels of inventory

y Inventory

y Output

y Employment

y Subcontracting

y Backordering

Aggregate Planning OutputsAggregate Planning Outputs

Page 8: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 8/29

12-8 Aggregate Planning 

Aggregate Planning StrategiesAggregate Planning Strategies

y Proactive

y Alter demand to match capacity

y R eactive

y Alter capacity to match demand

y Mixed

y Some of each

Page 9: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 9/29

12-9 Aggregate Planning 

y Pricing

y Promotion

y Back orders

y New demand

DemandOptionsDemandOptions

Page 10: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 10/29

12-10 Aggregate Planning 

y Hire and layoff workers

y Overtime/slack time

y Part-time workers

y Inventories

y Subcontracting

CapacityOptionsCapacityOptions

Page 11: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 11/29

12-11 Aggregate Planning 

Aggregate Planning StrategiesAggregate Planning Strategies

y Maintain a level workforce

y Maintain a steady output rate

y Match demand period by period

y Use a combination of decision

variables

Page 12: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 12/29

12-12 Aggregate Planning 

Basic StrategiesBasic Strategies

y Level capacity strategy:

y Maintaining a steady rate of regular-timeoutput while meeting variations in demand

 by a combination of options.

y Chase demand strategy:

y Matching capacity to demand; the planned

output for a period is set at the expecteddemand for that period.

Page 13: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 13/29

12-13 Aggregate Planning 

Chase ApproachChase Approach

y Advantages

y Investment in inventory is low

y

Labor utilization in highy Disadvantages

y The cost of adjusting output rates and/or 

workforce levels

Page 14: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 14/29

12-14 Aggregate Planning 

Level ApproachLevel Approach

y Advantages

y Stable output rates and workforce

y

Disadvantagesy Greater inventory costs

y Increased overtime and idle time

y R esource utilizations vary over time

Page 15: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 15/29

12-15 Aggregate Planning 

1. Determine demand for each period

2. Determine capacities for each period

3. Identify policies that are pertinent

4. Determine units costs

5. Develop alternative plans and costs

6. Select the best plan that satisfies objectives.Otherwise return to step 5.

Techniques for Aggregate PlanningTechniques for Aggregate Planning

Page 16: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 16/29

12-16 Aggregate Planning 

Cumulative GraphCumulative Graph

1 2 3 4 5 6 7 8 9 10

Cumulative

production

Cumulative

demand   C

      u  m      u   l  a   t   i  v  e  o      u   t  p

      u   t   /   d  e  m  a  n   d

Figure 12.3

Page 17: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 17/29

12-17 Aggregate Planning 

Average InventoryAverage Inventory

Average

inventoryB

eginning Inventory + Ending Inventory2=

Page 18: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 18/29

12-18 Aggregate Planning 

Mathematical TechniquesMathematical Techniques

 Linear programming : Methods for obtainingoptimal solutions to problems involvingallocation of scarce resources in terms of cost minimization.

 Linear decision rule: Optimizing techniquethat seeks to minimize combined costs, usinga set of cost-approximating functions to

obtain a single quadratic equation.

Page 19: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 19/29

12-19 Aggregate Planning 

Summary of Planning TechniquesSummary of Planning Techniques

Technique Solution Characteristics

Graphical/charting Trial and

error 

Intuitively appealing, easy to

understand; solution not

necessarily optimal.

Linear programming

Optimizing Computerized; linear assumptions not always valid.

Linear 

decision r ule

Optimizing Complex, requires considerable

effort to obtain pertinent cost

information and to constr uct

model; cost assumptions notalways valid.

Simulation Trial and

error 

Computerized models can be

examined under a variety of 

conditions.

Table 12.7

Page 20: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 20/29

12-20 Aggregate Planning 

y Services occur when they are rendered

y Demand for service can be difficult to predict

y

Capacity availability can be difficult to predict

y Labor flexibility can be an advantage in

services

Aggregate Planning in Ser vicesAggregate Planning in Ser vices

Page 21: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 21/29

12-21 Aggregate Planning 

Aggregate Plan to Master ScheduleAggregate Plan to Master Schedule

Aggregate

Planning

Disaggregation

Master

Schedule

Figure 12.4

Page 22: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 22/29

12-22 Aggregate Planning 

y Master schedule: The result of disaggregatingan aggregate plan; shows quantity and timing

of specific end items for a scheduled horizon.

y Rough-cut capacity planning : Approximate balancing of capacity and demand to test the

feasibility of a master schedule.

Disaggregating the Aggregate PlanDisaggregating the Aggregate Plan

Page 23: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 23/29

12-23 Aggregate Planning 

Master SchedulingMaster Scheduling

y Master schedule

y Determines quantities needed to meet demand

y Interfaces with

y Marketing

y Capacity planning

y Production planning

y

Distribution planning

Page 24: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 24/29

12-24 Aggregate Planning 

Master Scheduler Master Scheduler 

y Evaluates impact of new orders

y Provides delivery dates for orders

y Deals with problems

y Production delays

y R evising master schedule

y Insufficient capacity

Page 25: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 25/29

12-25 Aggregate Planning 

Master Scheduling ProcessMaster Scheduling Process

Master Scheduling

Beginning inventory

Forecast

Customer orders

Inputs Outputs

Projected inventory

Master production schedule

Uncommitted inventory

Figure 12.6

Page 26: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 26/29

12-26 Aggregate Planning 

ProjectedOnProjectedOn--hand Inventoryhand Inventory

Projected on-hand

inventory

Inventory from

 previous week 

Current week¶s

requirements-=

Page 27: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 27/29

12-27 Aggregate Planning 

ProjectedOnProjectedOn--hand Inventoryhand Inventory

64 1 2 3 4 5 6 7 8

Forecast 30 30 30 30 40 40 40 40

Customer Orders

(committed) 33 20 10 4 2

Projected on-hand

inventory 31 1 -29

JUNE JULY

Beginning

Inventory

Customer orders are

larger than forecast in

week 1

Forecast is larger than

Customer orders in week 2

Forecast is larger than

Customer orders in week 3

Figure 12.8

Page 28: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 28/29

12-28 Aggregate Planning 

Time Fences inMPSTime Fences inMPS

Period

³f rozen´

(f irm or 

f ixed)

³slushy´

somewhat

firm

³liquid´

(open)

Figure 12.12

1 2 3 4 5 6 7 8 9

Page 29: Ch 12 Aggregate Planning

5/12/2018 Ch 12 Aggregate Planning - slidepdf.com

http://slidepdf.com/reader/full/ch-12-aggregate-planning 29/29

12-29 Aggregate Planning 

Solved Problems: Problem 1Solved Problems: Problem 1