central station reference concept design online consultation
DESCRIPTION
You're invited to participate in the online consultation for the Central Station Reference Concept Design. In this consultation you will learn more about the preliminary designs for the LRT stations, surface stops and alignments and the City's Eglinton planning study. You can share your input with the project team by completing the survey at www.thecrosstown.ca.TRANSCRIPT
1
Welcome to the Central Station
Reference Concept Design
Online Consultation Please review the presentation and complete the
survey.
February 28, 2013 to March 14, 2013
2
Online Consultation Overview
February 28, 2013
Provide a brief Crosstown update
Update on the AFP Process
Present The Crosstown station and stop design philosophy
Provide latest details on locations of stations and stops
3
Crosstown Map
4
Overview
What is The Crosstown?
$4.9B Project ($2010) funded by the Province of Ontario
19 kilometres east-west Light Rail Transit (LRT) from Kennedy to Mt. Dennis,
including a tunnelled central section
New transit connections to Yonge, University-Spadina Subway, Scarborough
RT and GO Stouffville line and future connection to GO Kitchener line
Up to 26 stations
5
Overview
Where we are in the process
Tunnel Boring Machine (TBM) launch shaft approaching completion
Soil testing is currently underway from Don Mills Road to Weston Road
West tunnel contract awarded summer 2012
Conceptual design and requirements identification
What’s next
Utility relocation at station locations beginning with Keele Street in winter 2013
Construction of TBM launch and extraction shafts at Eglinton West station
TBMs arriving on site in spring 2013
Tendering of project
6
New Approach:
Alternative Financing and Procurement (AFP)
Public-private partnership models have been underway in Canada for 20 years
165 projects 21 transportation projects $51 billion total project value
Canada-wide examples Canada Line rapid transit project (Vancouver) Autoroute 25 (Montréal) Trans-Canada Highway (Atlantic Canada)
Ontario examples Pan Am games athletes village Ottawa Light Rail Transit Highway 407 East Phase 1 Rt. Hon. Herb Gray Parkway (formerly the Windsor-Essex Parkway)
7
Owner’s Role Changes with AFP
8
New Approach: Advantages of AFP
Increased capacity to bring projects to market
Transfer of risk
Appropriate risks transferred to private sector to ensure “on time, on budget”
delivery and value for money
Design, construction, cost escalation, schedule delays, operations,
maintenance, life cycle and financial risk
Cost certainty
Optimal cost combination: combines capital, maintenance and life cycle costs
Integration of design and construction
9
New Approach: Roles and Responsibilities in the Design
Build Finance Maintain Model Metrolinx Role
Design
• Overall scope (inclusion of
maintenance, operations,
etc.)
• Project-Specific Output
Specifications (with
Consultant team)
• Real Estate Acquisition (with
City of Toronto)
Build
• Oversee Construction Phase
• Quality Assurance
Finance
• Project Budget
• With Infrastructure Ontario, run a
competitive procurement
process; select the winning
contractor
Maintain
• Testing & Commissioning (with
Toronto Transit Commission)
• Safety Certification and Project
Acceptance
TTC to operate
• Integrated with existing TTC
system
10
Approach to new transit: Light Rail Transit
11
Approach to Station Design: Urban Design Principles
Locate station entrances and vents to limit the amount of frontage impacted
Explore opportunities to consolidate and locate above grade mechanical vent
shafts where their impacts on adjacent development can be minimized
Site station entrances and ventilation infrastructure with possible new
development in mind
Locate primary and secondary entrances so that they can help to contribute to
the creation of a consistent building setback
Minimize the impact of vents and other facilities through careful siting
12
Approach to Station Design: Architectural Principles
Station and stop designs should reflect their
civic role through high quality architecture and
urban design
Logos, station names, and signage should be
used boldly and consistently to reinforce station
identity
Signage and way finding shall be highly
standardized
Variation of treatments used to differentiate
stations
Stations can embrace the local context through
design or art installations
The Public Realm should be used as an
opportunity to enhance user experience and
integrate stations into their surroundings
13
Approach to Station Design: Safety and accessibility
Elevators will be included in all stations
Designated waiting areas will be included in all stations
Stations will use standard elements to make them familiar to passengers with
accessibility challenges
Integrate Crime Prevention Through Environmental Design principles into
station design
Light colours will be used to improve safety and efficiency
Incorporate fully glazed station entrances to maximize light
14
Approach to Station Design: Public Realm Elements
Public Realm
Implementation of streetscape, furniture, and tree planting standards
Widen sidewalks within station area
Stations entrances will be identified by a consistent pylon sign
Some stations will include landscaped plazas which will:
• Compliment the design of the station
• Include pedestrian level lighting
• Include trees, hard and soft landscaping
15
Approach to Station Design: Public Art
Stations will feature public art
Artwork will be integrated with
architectural finishes or
elements of the stations and
plazas
Surface stops may also include
public art
16
Reference Concept Design
Stations are shown as a Reference Concept Design (RCD)
Reference Concept Designs, or functional designs, are used in the AFP model
as inputs to the development of the Request for Proposal (RFP)
The functional design is intended to identify the location of entrances, exits and
ancillary station (ventilation) equipment
Functional designs are not intended to provide architectural details for stations
The AFP partner will be developing designs for the stations and these will be
subject to public input
17
EGLINTON WEST STATION
18
Eglinton West – Allen Station
Local Context: Demand
19
Eglinton West – Allen Station
Local Context: Demand
20
Eglinton West – Allen Station
Plan View
21
Eglinton West – Allen Station
Preliminary Station Concept
22
Eglinton West Allen Station
Profile View
23
Challenges of interchange stations
Interchange stations are much more complex to build than inline
stations for many reasons:
Little clearance between existing subway and new deeper station platform
which would require underpinning of existing subway structure
Existing subway stations and bus terminals must remain in operation during
construction
Complex stations being built in already built-up areas
Interchanges with surface transit must be incorporated
Opportunities for natural light will be difficult due to depth of stations
Vertical movement must provide proper connectivity between two platform
levels
Clear wayfinding signage needed for efficient passenger flow
Resolution of code issues arising from the integration with existing structures
24
BATHURST STATION
25
Bathurst Station
Local Context: Demand
26
Bathurst Station
Local Context: Land Use
27
Bathurst Station
Plan View
28
Bathurst Station
Preliminary Station Concept
29
Bathurst Station
Profile View
30
Bathurst Station
Primary Entrance
31
Bathurst Station
Secondary Entrance
32
CHAPLIN STATION
33
Chaplin Station
Local Context: Demand
34
Chaplin Station
Local Context: Land Use
35
Chaplin Station
Plan View
36
Chaplin Station
Preliminary Station Concept
Looking East
37
Chaplin Station
Entrance Locations Primary Entrance Secondary Entrance
Secondary Entrance
38
AVENUE STATION
39
Avenue Station
Local Context: Demand
40
Local Context: Land Use
41
Avenue Station
Plan View
42
Avenue Station
Preliminary Station Concept
43
Avenue Station
Longitudinal Section
44
Avenue Station
Profile View
45
Avenue Station
Primary Entrance
46
YONGE STATION
47
Eglinton Yonge Station
Local Context: Land Use
48
Eglinton – Yonge Station
Local Context: Demand
49
Eglinton Yonge Station
Plan View
50
Eglinton Yonge Station
Preliminary Design Concept
51
Eglinton Yonge Station
Profile View
52
Eglinton Yonge Station
Longitudinal Section
53
MOUNT PLEASANT STATION
54
Mount Pleasant
Local Context: Demand
55
Local Context: Land Use
56
Mount Pleasant
Plan View
57
Mount Pleasant Station
Preliminary Station Concept
58
Mount Pleasant Station
Longitudinal Section
Possible
Future
Entrance
59
Mount Pleasant Station
Profile View
60
Mount Pleasant Station
Primary Entrance
61
BAYVIEW STATION
62
Bayview Station
Local Context: Demand
63
Local Context: Land Use
64
Bayview Station
Plan View
02/21/2013
65
Bayview Station
Preliminary Design Concept
02/21/2013
66
Bayview Station
Longitudinal Section
67
Bayview Station
Profile View
68
Bayview Station
Primary Entrance
69
LAIRD STATION
70
Laird Station
Local Context: Demand
71
Local Context: Land Use
72
Laird Station
Plan View
73
Laird Station
Preliminary Station Concept
74
Laird Station
Longitudinal Section
75
Laird Station
Profile View
76
Laird Station
Primary Entrance
77
Traction Power Substation
Traction power substations (TPSS) provide
system power to light rail vehicles
For underground stations TPSS are
integrated with stations building
They are planned with an average spacing
of 1.5 km along surface sections and 2 km
along underground sections
Integrated with adjacent landscape
Final locations still to be determined
• Keele
• Dufferin
• Bathurst
• Yonge
• Bayview
• Don Mills
• Wynford
• Jonesville
• Warden
78