2012-2017 Texoma Comprehensive Economic Development Strategy (CEDS)Development Process and Timeline
Last Updated 12/06/2011
Note 1: This Timeline is based on the minimum requirements outlined under 13 C.F.R Section303.7; a recent survey citing that 60% of COGs respondents had 1 to 2 FTEs working onC&ED related activities, and secondary sources citing that the strategic planning process requiresa minimum of 1,000 or more hours.
Quick Specs
Reconnaissance Surveys: 3Interviews: 50-60Public Hearings: 12Strategy Committee Meetings: 4TCOG Governing Body Engagement Sessions: 3
December 7, 2011- January 13, 2012: Recruit Strategy Committee1. Engage TCOG Governing Body on December 15, 2011
a. Strategy Committee will meet 4 times, providing necessaryfeedback and support for the CEDS. Must have 51% Private Sectorrepresentation and good geographic representation. Give TCOGGB list of private sector industries we are seeking representationfrom.
b. Recruit individuals that a good fits for the committee byrecommendation of TCOG Board and others.December 15, 2011- January 13, 2011: Conduct 3 Reconnaissance Surveys
1. 3 quick tours of several communities in the region by individuals notfrom Texoma. TCOG staff will record their impressions of the area as amethod of indicating community needs and possible planning goalsand objectives
a. Answer questions like:i. What is the general character of the community?
ii. How do people use the land?iii.
How are people housed?iv. How do people travel?
v. What public services are available?vi. How do people make a living here?
vii. What are the characteristics of the people?viii. What are the planning resources of this area?
-
8/3/2019 CEDS Texoma Economic Strategy Timeline and Process
2/4
January 13, 2012- February 1, 2012: Conduct TCOG GB and StrategyCommittee interviews
1. Up to 25 interviews2. Education on their roles as TCOG GB members or Strategy Committee
members in this CEDS process3. Collect thoughts and opinions about a broad list of area needs in their
community, local economy, and for regionalism in Texoma.
February 1- February 7, 2012: Schedule 1st Strategy Committee Meeting1. Review of the CEDS schedule and explain the process2. Educate them on the role of the strategy committee and the EDA
requirements3. Schedule hard dates and times for the 2nd, 3rd, and 4th meetings of the Strategy
Committee
February 1- February 22, 2012: Conduct Additional Interviews1. Talk with individuals of diverse set of expertise, interests, and geographic
location2. Collect thoughts and opinions about needs in their community, local
economy, and regionalism in Texoma.
February 23- March 2, 2012: Start Preparation of Presentation on StatisticalData & Interview Insights for Strategy Committee & Public Hearings
Week of March 5, 2012: Strategy Committee Meeting #2
1. Review statistical data and insights gleaned from interviews about the needsin Texoma2. Collect feedback from the strategy committee about the needs identified and
encourage their support in public hearing meetings from March 19- March 30(review the schedule with them)
March 9 March 16, 2012: TCOG Staff Prepare for Public Hearing Series #11. Handouts about our region2. Presentation of CEDS process and then statistical data and interview insights3. Prepare the feedback tool for public hearing participants
a. Perhaps a list of broad themes and requesting open ended feedbackand thought about each. We will collect that paper as feedback.b. Open the floor for any comments and feedback after the presentation.
March 19- March 30, 2012: Public Hearing Series #1 (6)1. Review of statistical data and interview insights. Review (education) of CEDS
planning process.
2. Collect feedback from public hearing attendees about regional needs.
-
8/3/2019 CEDS Texoma Economic Strategy Timeline and Process
3/4
April 2- April 20, 2012: TCOG Staff Build and Development Goals,Objectives, and Performance Measures
1. Conduct SWOT analysis based upon all needs identified2. Build a list of corresponding policies, goals, objectives, programs, and
activities that address SWOT items3. Development Regional Strategies, Performance Measures and Benchmarks
for each policy, goal, objective, program or activitya. Strategiesb. Outputsc. Outcomes
Week of April 23, 2012: Strategy Committee Meeting #31. Review the SWOT analysis2. Refine policies, goals, objectives, programs, and activities for clarification3. Identify any that might not be there4. Prioritize areas
April 20- April 30, 2012: TCOG Staff Prepare for Series #2 of PublicHearings
1. Development method of presenting information2. Prepare a feedback tool that asks about priority of goals, objectives, etc3. Leave room/time for further feedback on any these materials- new goals, new
benchmarks, clarification, etc
May 1- May 11: Series #2 Public Hearings (6)1. Review the SWOT analysis2. Refine policies, goals, objectives, programs, and activities for clarification3. Identify any that might not be there4. Prioritize areas
May 11- May 16: Formalize the feedback about goals and objectives so theyare included with materials in the Board Focus Group
1. Prepare a summary2. Prepare a feedback tool for the TCOG GB to return to us that has their
individual votes on the refinement of objectives/strategies the subsequent
priorities thereof.
-
8/3/2019 CEDS Texoma Economic Strategy Timeline and Process
4/4
May 17, 2012: TCOG Governing Body Focus Group on Goals/Objectives &Priorities
1. Review the SWOT analysis2. Refine policies, goals, objectives, programs, and activities for clarification3. Identify any that might not be there4. Prioritize areas5. Review and vote on refinement of objectives/strategies and their priorities
May 18- May 31: Compile Final CEDS for Review and Submission
June 1, 2012: Strategy Committee Meeting #41. Review and comment on final CEDS document for submission to TCOG
Governing Body
June 13, 2012: Submit Final CEDS Document for June TCOG Governing BodyMeeting
June 21, 2012: TCOG Governing Body Review and Approval of Submission to EDA
June 22, 2012: Submit CEDS to EDA