cec025 - rail track code

Upload: aldertpath

Post on 07-Aug-2018

234 views

Category:

Documents


3 download

TRANSCRIPT

  • 8/21/2019 CEC025 - Rail Track Code

    1/410

    RAILTRACK

    COMPANY STANDARDS

    INFORMATION NOTICE

    For Printer Users

    RT/CE/C/025 contains colour on the following electronic pages:

    26, 30, 43, 66, 77-79, 83, 95, 97, 98, 128, 134, 135, 149, 163-165, 168, 169,

    174, 175, 178, 196, 197, 217, 219, 222, 265, 268, 272, 293, 294, 337-340, 343,

    349, 354, 360, 363, 368-370 & 384Colour pages may be purchased separately from:The Railtrack Document Centre@ RapidocTel: 01344 404446Fax: 01344 714440Email: [email protected]

    On to Document

  • 8/21/2019 CEC025 - Rail Track Code

    2/410

    RT/CE/C/025

    Issue: 1

    Date: February 2001

    RAILTRACK LINE CODE OFPRACTICE

    The Structural Assessment of Underbridges

    Copyright 2001 Railtrack PLCAll rights reserved. No part of this publication may be reproduced, stored in a

    retrieval system, or transmitted, in any form or by any means, electronic,

    mechanical, photocopying, recording or otherwise, without the prior written

    permission of Railtrack PLC.

    Endorsement and Authorisation

    Endorsed by:

    Kim Teager, Professional Head Of Structures Engineering

    Accepted for Issue by:

    Graham Morris, Head Of Corporate Standards

    Authorised by

    This publication, including the dataand information relating thereto, is

    not to be used, disseminated,

    stored in a retrieval system,

    reproduced, copied or adapted

    either in whole or in part without

    the express written permission of

    RAILTRACK p l c .

    Published & Issued by

    Railtrack plc

    Railtrack House

    Euston Square

    L O N D O NNW1 2 E E

    2001 RAILTRACK PLC

  • 8/21/2019 CEC025 - Rail Track Code

    3/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges Page 2 of 11

    SUMMARY

    This Code of Practice provides recommendations for the parameters and methods to

    be used for the assessment of underbridges owned by Railtrack.

    ISSUE RECORD

    This Code of Practice will be updated when necessary by distribution of a complete

    replacement or revised sections. Amended or additional parts of revised pages will

    be marked by a vertical black line in the margin. Due to the extensive number of

    revisions compared with Issue 1 such changes have not be marked in this Issue.

    ISSUE 1 DATE February 2001 COMMENTS: New Code of Practice

    to provide a limit state code for

    assessment of underbridges in respect ofsteel, wrought iron, and concrete and

    composite bridges, and to codify

    permissible assessment parameters and

    methods for under bridges formed from

    other materials of construction.

    RESPONSIBILITIES AND DISTRIBUTION

    This Code of Practice should be used by persons undertaking the assessment of

    underbridges and by those responsible for managing the process of bridge assessment

    carried out by others.

    IMPLEMENTATION

    This Code of Practice should be complied with from April 2001.

    DISCLAIMER

    Railtrack PLC has used its best endeavours to ensure that the content, layout and

    text of this document are accurate, complete and suitable for its stated purpose. It

    makes no warranties, express or implied, that compliance with the contents of this

    document shall be sufficient to ensure safe systems of work or operation. Railtrack

    PLC will not be liable to pay compensation in respect of the content or subsequent

    use of this document for any purpose other than its stated purpose or for any

    purpose other than that for which it was prepared except where it can be shown to

    have acted in bad faith or there has been wilful default.

    SUPPLY

    Paper copies of this document will be available to Railtrack staff on request to the Document

    Controller. Copies of this document will be available to other organisations from Technical

    Indexes (01334 404409).

  • 8/21/2019 CEC025 - Rail Track Code

    4/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges Page 3 of 11

    CONTENTS

    SECTION 1 INTRODUCTION

    SECTION 2 ASSESSMENT PHILOSOPHY

    SECTION 3 INSPECTION FOR ASSESSMENT

    SECTION 4 LOADING FOR ASSESSMENT

    SECTION 5 STEEL AND WROUGHT IRON STRUCTURES

    SECTION 6 MASONRY ARCHES

    SECTION 7 CONCRETE STRUCTURES

    SECTION 8 COMPOSITE STRUCTURES

    SECTION 9 CAST IRON STRUCTURES

    SECTION 10 TIMBER STRUCTURES

    SECTION 11 SUBSTRUCTURES

    SECTION 12 BEARINGS

    APPENDIX A ASSESSMENT OF STEEL AND WROUGHT

    IRON

    APPENDIX B ASSESSMENT OF CONCRETE STRUCTURES

    APPENDIX C ASSESSMENT OF COMPOSITE STRUCTURES

    APPENDIX D FATIGUE ASSESSMENT OF STEEL AND

    WROUGHT IRON

    APPENDIX E MODEL BRIDGE ASSESSMENT REPORT

    APPENDIX F INFORMATIVE ANNEX

  • 8/21/2019 CEC025 - Rail Track Code

    5/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 4 of 11

    CONTENTS

    1. INTRODUCTION...................................................................................................................4

    1.1 Purpose................................................................................................................................4

    1.2 Scope....................................................................................................................................4

    1.3 Units .....................................................................................................................................5

    1.4 Definitions and Abbreviations.........................................................................................6

    1.5 Competency .......................................................................................................................6

    1.6 Procedures for Quantitative Assessment.....................................................................7

    1.7 Qualitative Assessment Procedures............................................................................10

    1.8 Railtrack s Technical Approval Procedures ...............................................................10

    1.9 Reporting...........................................................................................................................101.10 Informative Annex.........................................................................................................11

    1. INTRODUCTION

    1.1 Purpose

    The purpose of this Code of Practice is to recommend applicable standards and

    analytical methods which may be used to determine the load carrying capacity of

    existing Railtrack underbridges, in terms of British Standard Units of Type RA1

    loading. The load carrying capacity is determined in the context of the performance

    requirements of an underbridge. The requirements are that the bridge meets safety

    and serviceability criteria whilst regularly carrying rail traffic up to a level of traffic

    load and speed in accordance with operational system requirements.

    1.2 Scope

    This Code of Practice may be used for the assessment of all Railtrack owned

    underbridges and is applicable for permissible speeds up to a maximum 125 mph.

    This Code of Practice provides recommendations for the assessment of underbridges

    constructed from steel, wrought iron, cast iron, concrete, timber, or composite

    steel/concrete construction. Recommendations for masonry arches, substructures

    and bearings are also included. Limit state principles are used for underbridges of

    steel, wrought iron, concrete and steel/concrete composite construction.

    Permissible stresses or allowable loads are used for other materials and forms of

    construction.

    Where appropriate, guidance on the use of simple and more rigorous methods of

    analysis is given. Unusual forms of construction such as cable stayed, moveable or

    combined road/rail bridges are not specifically covered, but the principles outlined

    may be applied in checking the elements of such structures.

  • 8/21/2019 CEC025 - Rail Track Code

    6/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 5 of 11

    Requirements for the assessment of superstructures and supports under accidental

    loading conditions are excluded from this document.

    1.3 Units

    The S.I. system of units is adopted throughout this Code of Practice unless otherwise

    stated.

    In the course of assessment frequent reference may have to be made to existing

    records which may be presented in Imperial Units. Great care should be exercised in

    the conversion between the two systems of units. The following table gives

    conversion factors for some of the most commonly occurring units.

    PROPERTY IMPERIAL UNIT

    METRIC

    equivalent of

    IMPERIAL UNIT

    METRIC

    UNIT

    Length inch 2.5400 cm

    foot 0.3048 m

    yard 0.9144 m

    mile 1.6093 km

    chain 20.1168 m

    Area inch 645.1600 mm

    inch 6.4516 cm

    foot 0.0929 m

    yard 0.8361 m

    Volume inch 16.387 cm

    foot 0.0283 m

    yard 0.7646 m

    Mass lb 0.4536 kg

    ton 1016 kg

    ton 1.0160 tonnes

    Modulus inch 16387 mm

    inch 16.387 cm

    Inertia inch4 416200 mm4

    inch4 41.62 cm4

    Speed mph 1.6093 kph

  • 8/21/2019 CEC025 - Rail Track Code

    7/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 6 of 11

    Table 1.1

    Conversion Factors

    1.4 Definitions and Abbreviations

    For the purpose of this Code of Practice the following definitions apply:

    Bridgemeans a structure of one or more spans whose prime purpose is to carry

    traffic or services over an obstruction or gap.

    PSRmeans Permanent Speed Restriction.

    Provisionally Sub-standard Bridgemeans a Bridge that has been assessed at the

    Level 1 assessment stage of the Bridge Assessment process to have a safe load

    capacity less than the RA Capacity of the route. The Bridge remains Provisionally

    Sub-standard until it is confirmed on completion of the Bridge Assessment that the

    safe load capacity is not less than the RA Capacity of the route or the Bridge is

    classified as a Sub-standard Bridge.

    Serviceability Limit State (SLS)means the condition at which the behaviour of a

    Bridge becomes unsatisfactory to the extent that it can no longer satisfactorilyperform its function under service loads.

    Sub-standard Bridgemeans a Bridge where, following completion of a Bridge

    Assessment, action(s) is (are) required to protect the safety of the Bridge. A Bridge

    remains classified as Sub-standard until actions are taken to remove the applied

    controls, or the RA Capacity of the route is amended to not more than the safe load

    capacity of the Bridge.

    TSRmeans Temporary Speed Restriction.

    Ultimate Limit State (ULS)means the condition at which the Bridge, or one of

    its constituent parts, would fail due to loss of equilibrium, fatigue induced

    deterioration, or exceedance of its collapse strength.

    Railtrack Director s Nomineemeans the Structures Engineer with formally

    delegated responsibility for the assessment of underbridges within the Railtrack Zone.

    1.5 Competency

    The skills, expertise and training of those persons responsible for, and carrying out,

    the assessment should be appropriate to the nature and complexity of the structureunder consideration.

  • 8/21/2019 CEC025 - Rail Track Code

    8/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 7 of 11

    1.6 Procedures for Quantitative Assessment

    The assessment should commence with a definition of the assessment objective. A

    clear statement of the required load carrying capacity should be made. In particular,

    it should state specifically the existing RA capacity of the structure, the existing RA

    capacity of the route and whether an increased structure capacity greater than that of

    the route is required. The initial assessment (Level 1) should generally comprise

    three distinct phases as follows:

    1. Desk Study

    All available information relevant to the structure, including record drawings,

    inspection and maintenance records, details of past performance and previous

    assessments, and any available ground investigation data should be collatedand examined. The documents should be verified for correctness and in

    particular, whether they were updated after previous works on the structure.

    2. Inspection for Assessment

    A detailed examination of the structure is required to verify the form of

    construction, its dimensions and the nature and condition of the structural

    parts.

    3. Analysis

    Based on the information obtained from the first two phases of theassessment process, structural analysis to determine the distribution of forces

    within the structure and the load capacity of the structural parts is required in

    most cases.

    In order to determine the adequacy of a particular structure with the minimum

    degree of effort, the assessment should be carried out in levels of increasing

    refinement and complexity, with the initial level (Level 1) being based on the most

    conservative distributions of loads and analytical assumptions. If the structure is

    shown to be inadequate in relation to the required load carrying capacity at this level,

    assessment work should continue, with subsequent levels seeking to removeconservatism in the assessment where this can be justified. Subsequent more detailed

    levels may use:

    more refined structural analysis;

    more precise estimates of loading based on real vehicles;

    material properties based on testing of materials samples;

    supplementary load testing.

    As illustrated in Figure 1.1 the process is cyclical in nature, each cycle being at an

    increasingly refined level until a decision on the adequacy of the bridge is reached.Conceptually it is useful to envisage levels of assessment as follows:

  • 8/21/2019 CEC025 - Rail Track Code

    9/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 8 of 11

    Level 1 Simplest level using assumptions known to be conservative.

    Level 2 Use of more refined analysis and better structural idealisation. This

    level may also include use of data on materials strengths based on mill

    test certificates or recent material tests on another similar structure.

    Level 3 Use of a bridge specific live loading based on the known traffic and/or

    the use of tests on materials samples or the use of worst credible

    strengths or the use of load tests.

    Where, by inspection, it is considered that greater benefit may be gained by theadoption if live loading based on real trains than from a more refined analysis, the

    assessment may progress from Level 1 directly to level 3.

    The conclusion from the assessment should be subjected to a plausibility check. In

    particular, discrepancies between the results of structural analysis, indicating

    inadequacy say, and the real structural condition, for example no sign of distress or

    failure, should be explained.

  • 8/21/2019 CEC025 - Rail Track Code

    10/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 9 of 11

    Analytical

    assessment?

    Qualitative assessment

    Review structurePass

    Further investigation

    and review

    Level 1 assessment

    Analysis

    Provisionallysub-standard structure

    Urgent safety

    measures?

    Implement

    measures

    Level 2-3 assessment

    Assessment report

    Urgent safety

    measures

    Review assessment

    objective

    Implement

    measures

    Review assessmentobjective

    Yes

    No

    No

    YesYes

    No

    Sufficientcapacity/

    adequate condition?

    Operational restrictions

    /repair/upgrade?

    Review past performance and inspection data.

    Decide assessment objective.

    Bridge

    management

    programme

    Periodic

    inspection

    Maintenance

    Performancereview

    Fail

    Pass Pass

    Pass

    Fail

    Fail

    Fail

    Yes

    No

    Review safety measures

    Figure 1.1

    Assessment Process Flow Diagram

  • 8/21/2019 CEC025 - Rail Track Code

    11/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 10 of 11

    1.7 Qualitative Assessment Procedures

    For some types of structure where no established method of quantitative theoretical

    assessment exists and where increased capacity is not required, assessment may be

    made qualitatively on the basis of satisfactory past performance. Structures for which

    this procedure may be considered are spandrel and dry stone walls, retaining walls,

    jack arches, substructures and foundations. The requirements for assessment on this

    basis are:

    the structure has demonstrated satisfactory performance over a long periodof time (over 5 years) since any significant repairs or alteration;

    careful inspection does not reveal significant damage, distress ordeterioration;

    review of the structure confirms its force transfer system;

    predicted future deterioration will not jeopardise safety;

    no significant changes in the loads and actions on the Bridge are anticipated.

    Where the assessing engineer proposed a qualitative method of assessment, this shall

    be justified and recorded in accordance with Railtrack s Technical Approval

    Procedures.

    1.8 Railtrack s Technical Approval ProceduresAll assessments shall be subject to Railtrack s Technical Approval Procedures for

    assessment.

    Irrespective of whether the assessment is to be carried out on a quantitative or

    qualitative basis, the chosen method should be recorded and justified within the

    Form AA. Where a qualitative method is proposed for the assessment of one of the

    structure types identified in Clause 1.7, reference to this document may be deemed

    to be sufficient justification for adoption of the method.

    For the assessment of Bridges or structural elements which are outwith the scope ofthis document, the method of assessment should be agreed within the Technical

    Approval Procedure by Railtrack s Professional Head of Structures Engineering.

    1.9 Reporting

    When the assessment has been completed, a report should be prepared detailing the

    various stages of the process, together with the results. A suitable format for the

    assessment report is given in Appendix E. Summary tables for reporting the

    assessment results have been included in Appendix E for metallic structures, masonry

    arches and concrete structures. These summary tables should be completed and

    incorporated in the final report where applicable.

  • 8/21/2019 CEC025 - Rail Track Code

    12/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 1 - Introduction Page 11 of 11

    1.10 Appendices

    Additional notes and further information relating to the assessment of underbridges

    are contained in Appendices A to F. Clauses within each appendix are numbered

    sequentially from 1.0 and are followed by a letter denoting the appendix to which

    they belong. For example Clause 4.1.1B indicates Clause 4.1.1 of Appendix B.

    1.11 Informative Annex

    Background information on the derivation of certain clauses of this code of practice

    and guidance on its usage is contained in Appendix F. It should be noted that this

    Appendix is not intended to give comprehensive guidance, and should not be assumed

    to indicate all aspects of a structure that should be checked in the course of an

    assessment.

  • 8/21/2019 CEC025 - Rail Track Code

    13/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 1 of 8

    CONTENTS

    2. QUANTITATIVE ASSESSMENT PHILOSOPHY...............................................................1

    2.1 Applicability.........................................................................................................................1

    2.2 Basis for Quantitative Assessment.................................................................................1

    2.3 Assessment Situations ......................................................................................................1

    2.4 Limit States..........................................................................................................................3

    2.5 Assessment Load Values ..................................................................................................4

    2.6 Load Factors .......................................................................................................................4

    2.7 Assessment Load Effects ..................................................................................................6

    2.8 Assessment Resistance.....................................................................................................7

    2.9 Verification of Structural Adequacy...............................................................................8

    2. QUANTITATIVE ASSESSMENT PHILOSOPHY

    2.1 Applicability

    The analytical procedures for quantitative assessment given in this Section are

    applicable to most structural forms. They are not applicable to structures where

    analysis is impractical and where the original design was based on good construction

    practice of the time and no codes existed. In these cases assessment can be based on

    qualitative judgement of satisfactory past performance and the information obtained

    from assessment inspections. In all cases the purpose of assessment is to determine

    whether the bridge meets relevant safety and serviceability criteria, see Clause 1.1.

    2.2 Basis for Quantitative Assessment

    Assessment of steel, wrought iron, concrete and steel/concrete composite Bridges

    should be undertaken by the application of limit state principles. Bridges and

    structural elements constructed from cast iron, timber or masonry should be

    assessed on permissible stresses or loads.

    Irrespective of the basis on which a Bridge is to be assessed, the bridge is required to

    satisfy the Operational Safety Limit State requirements given in Clause 2.4(d).

    2.3 Assessment Situations

    The circumstances in which the Bridge is required to fulfil its function should be taken

    into account by selecting relevant situations for assessment. The situations should

    encompass all conditions that can reasonably be foreseen during use of the Bridge by

    rail traffic. The situations should be determined by making a critical selection of

    conditions arising due to dead and imposed load, live traffic loads and where relevant

    temperature and wind effects. The situations chosen, characterised by a dominant

    live load and one or more coexistent loads, should include the most adverse liveloads as follows:

  • 8/21/2019 CEC025 - Rail Track Code

    14/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 2 of 8

    Situation (1) Maximum vertical live load with coexistent transverse and longitudinal

    live loads;

    Situation (2) Maximum longitudinal live loads with coexistent minimum vertical and

    transverse live loads;

    Situation (3) Maximum transverse loads with coexistent minimum vertical and

    longitudinal live loads.

    In the above situations other live loads where required by Section 4 such as those due

    to wind and temperature should also be included where a more onerous loading may

    result.

    The values of maximum and minimum live loads for each situation are determined by

    multiplying the nominal live loads given in Section 4 by the applicable factors given in

    Table 2.1. The coexistent loads should be taken as zero if this results in a more

    onerous loading of the Bridge.

    SITUATION (1) SITUATION (2) SITUATION (3)

    Railway Live Loading

    Component

    Maximum Vertical +

    coexistent

    Longitudinal and

    Transverse

    Maximum

    Longitudinal +

    coexistent

    minimum Verticaland Transverse

    Maximum

    Transverse +

    coexistent

    minimum Verticaland Longitudinal

    Vertical:

    Type RA Loading 1.0 0.5 0.5

    Longitudinal:

    Traction & Braking 1.0 (0) 1.0 0.5 (0)

    Transverse:

    Nosing

    Centrifugal

    1.0 (0)

    1.0 (0)

    0.5 (0)

    0.5 (0)

    1.0

    1.0

    Table 2.1

    Factors for Combinations of Components of Railway Live Loading

    Partial factors for use in commonly occurring situations are given in Table 2.2. In

    special cases, other situations may arise and govern the assessment.

  • 8/21/2019 CEC025 - Rail Track Code

    15/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 3 of 8

    2.4 Limit States

    Where Bridges are to be assessed under the selected situations using limit state

    principles, the following should be considered:

    (a) Ultimate Limit State (ULS)

    The ULS is generally the governing condition for the assessment of

    underbridge capacity.

    This condition relates to the collapse strength of individual elements of the

    Bridge, and to the stability of a part or the whole of the Bridge when

    considered as a rigid body. To verify that an ultimate limit state is not

    reached, it is necessary to demonstrate that the criteria in the relevantSection of this Code of Practice are not exceeded under the application of

    ULS assessment loads.

    (b) Serviceability Limit State (SLS)

    Serviceability limit states are those situations where excessive deformations

    or a deterioration in structural condition may lead to a loss in utility of the

    Bridge such that remedial action may be required. Circumstances in which it

    may be necessary to carry out checks against SLS criteria are defined in

    Clauses 4.2.2A, 4.1.1B and 4.3.2C.

    (c) Fatigue Limit State

    The limit state for fatigue may be either an ULS or SLS. Where an assessment

    situation exists requiring fatigue evaluation (see Clause 4.3.2A) it should be

    checked taking the load factors fL and 3f equal to 1.0. For cast iron

    Bridges, see Section 9.

    (d) Operational Safety Limit State (OSLS)

    These conditions are attained when specified limits which govern the safe

    operation of the railway are reached. These limits will generally be related to

    the changes in structural deformation that occur under the passage of a trainand which, if exceeded may lead directly to derailment, or to degradation of

    the track which may, in time, have the same effect. They are limits of

    serviceability beyond which a Bridge is operationally unserviceable. Further

    information regarding OSLS requirements is given in Appendix F.

    For the bridge structure as a whole, an Operational Safety check should be made

    relating to track twist in accordance with Section 4. For some structures,

    Serviceability Limit States, such as bridge deflections and rotations, may also need to

    be checked. Appropriate criteria should be agreed in accordance with Railtrack s

    Technical Approval Procedures.

  • 8/21/2019 CEC025 - Rail Track Code

    16/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 4 of 8

    2.5 Assessment Load Values

    The assessment loads, *AQ , are determined from the nominal loads, KQ according to

    the equation:

    KfL

    *

    A QQ = Equation 2.1

    where:

    fL is a partial factor for each type of loading as given in Table 2.2.

    Nominal dead and superimposed dead loads may be determined using theinformation given in Section 4. Details of the nominal live loading and its application

    are also given in Section 4.

    2.6 Load Factors

    Dead and superimposed dead loads should be taken together with live loads using the

    factors given in Table 2.2 and in accordance with Section 4. Where it is necessary to

    consider loads, such as those due to wind or temperature, which are not defined in

    Section 4 of this Code of Practice, reference should be made to BD37/88: Loads for

    Highway Bridgesin accordance with Clause 4.4.

  • 8/21/2019 CEC025 - Rail Track Code

    17/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 5 of 8

    LOAD Limit

    State

    fL to be considered inCombination

    1 2 3

    Dead:

    Steel, wrought iron ULS 1.05

    SLS 1.0

    Cast iron ULS 1.1

    SLS 1.0

    Concrete, masonry, timber ULS 1.15

    SLS 1.0

    Superimposed dead:Ballast *1, *2 ULS 1.75

    SLS 1.2

    Track *3 ULS 1.2

    SLS 1.0

    Fill ULS 1.2

    SLS 1.0

    Services ULS 1.25

    SLS 1.0

    Live:

    The multiple components of LiveLoading should be considered to

    act in accordance with Clause 2.3

    ULSSLS

    1.4 *4

    1.11.2 *

    4

    1.01.2 *

    4

    1.0

    Wind:

    ULS

    SLS

    1.1

    1.0

    Temperature:

    Restraint to movement or due to

    frictional bearing restraint

    ULS

    SLS

    1.3

    1.0

    Table 2.2Values of Partial Factors (fL) for Loads in Combinations

    *1 A value of fL of 1.35 at ULS and 1.1 at SLS may be adopted provided the depth ofballast is controlled or dictated by the form of construction. Control measures may

    include datum plates or a Plimsoll line.

    *2 Ballast more than 300 mm below underside of sleepers may be considered as fill.

    *3 Track includes rails, fixings and sleepers, but excludes ballast between sleepers.

    *4 Subject to the approval of the Railtrack Director s Nominee a reduced value of 1.25

    for combination 1 and 1.1 for combinations 2 and 3 may be adopted where theloading is of a controlled nature as follows:

  • 8/21/2019 CEC025 - Rail Track Code

    18/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 6 of 8

    (a) There is reliable control over the trains that can enter the route in question,

    and

    (b) For vehicles which comprise any of the following:

    Locomotives;

    Locomotive hauled passenger and/ or mail trains;

    Other passenger and/ or mail trains;

    Cranes and track plant not able to carry loads whilst in travelling mode;

    Freight wagons where loading is physically controlled, for example fluid fuel

    tank wagons, closed grain or closed cement wagons;

    Standard coal hopper or similar wagons where the load is weighed beforedispatch.

    Reduced values of fL can only be assumed for other vehicles where every vehicleafter loading is weighed or is otherwise subject to proper assessment of weight,

    before details are submitted and accepted for such vehicles to cross the Bridge.

    These vehicles include freightliner container wagons, open top wagons for

    aggregates, spoil or waste and wagons for track infrastructure maintenance or

    renewal.

    2.7 Assessment Load EffectsThe assessment load effects, *AS , are obtained from the assessment loads by the

    relation:

    ( )*Af*

    A QS ofeffects3= Equation 2.2A

    ( )KfLf*

    A QS = ofeffects3 Equation 2.2B

    Note: For steel and wrought iron only (Section 5), 3f is applied within the

    resistance *R (see Clause 2.8) such that:

    *

    A

    *

    A QS ofeffects= Equation 2.3A

    KfL

    *

    A QS = ofeffects Equation 2.3B

    where:

    3f is a factor that takes account of inaccurate assessment of the effects of

    loading, such as unforeseen stress distribution in the structure, inherent

    inaccuracies in the calculation model, and variations in the dimensional

    accuracy from measured values. The effects of the assessment loads should

  • 8/21/2019 CEC025 - Rail Track Code

    19/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 7 of 8

    be obtained by the use of analytical procedures applicable to the form of

    construction.

    The factor 3f should normally be taken as 1.1 for ULS and 1.0 for SLS. 3f

    may be taken as 1.0 for the ultimate limit state for members where the

    following conditions (a), (b) and (c) are all met:

    (a) members are either:

    (i) Rail bearers or cross girders of steel, wrought iron or

    composite construction that are assumed to be simply

    supported, or;

    (ii) Main girders of steel, wrought iron or steel/concrete

    composite bridges with skew not greater than 25 (If main

    girders are continuous, any splices should be welded or made

    with HSFG bolts or rivets, and have cover plates to both

    flanges) or;

    (iii) Main beams of reinforced or prestressed concrete bridges with

    skew not greater than 25 that are assumed to be simply

    supported.

    (b) load effects are based upon static distribution within the structure;

    (c) geometric dimensions of the members are verified during inspection.

    2.8 Assessment Resistance

    The assessment resistance, *AR , of any structural element is the calculated resistance,*R , of that element, making appropriate allowance for any deterioration identified.

    The calculated resistance, *R , determined from material strengths and measuredsection properties should be calculated from the following equation:

    ( )mk* fR = function Equation 2.4

    Except for steel and wrought iron structures only where (Section 5):

    ( )( )3function fmk* fR = Equation 2.5

    where:

  • 8/21/2019 CEC025 - Rail Track Code

    20/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 2 - Assessment Philosophy Page 8 of 8

    kf is the characteristic (or nominal) strength of the material;

    m is a partial factor for material strength.

    Values ofk

    f andm

    are given in Sections 5, 7 and 8 according to the material ofconstruction.

    For those materials where the calculated resistance is determined on a permissible

    stress basis, the following may be applied:

    ( )p* fR function= where pf is the material permissible stress.

    2.9 Verification of Structural Adequacy

    Structures should be deemed to be capable of carrying a specified level of assessment

    loading when the following relationship is satisfied:

    *

    A

    *

    A SR >

  • 8/21/2019 CEC025 - Rail Track Code

    21/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 1 of 18

    CONTENTS

    3. INSPECTION FOR ASSESSMENT .......................................................................................1

    3.1 General ................................................................................................................................1

    3.2 Requirements prior to Inspection..................................................................................2

    3.3 Inspection for Loading ......................................................................................................2

    3.4 Inspection for Resistance.................................................................................................3

    3.4.1 General ........................................................................................................................3

    3.4.2 Metal Bridges ..............................................................................................................4

    3.4.3 Masonry Arch Bridges ..............................................................................................7

    3.4.4 Reinforced and Prestressed Concrete Bridges.................................................13

    3.4.5 Composite Bridges..................................................................................................153.4.6 Timber Bridges.........................................................................................................15

    3.4.7 Substructures............................................................................................................16

    3.4.8 Bearings......................................................................................................................17

    3.5 Report on Inspection......................................................................................................18

    3. INSPECTION FOR ASSESSMENT

    3.1 General

    This Section gives recommendations for the inspection of underbridges, following the

    desk study of existing information. The purpose of the inspection is to obtain

    information required for the structural assessment and determination of safe load

    carrying capacities. The principles outlined below may be applied to all types of

    underbridge, and all materials of construction referred to in this Code of Practice.

    Inspection for assessment is necessary to verify the form of construction, the

    dimensions of the structure and the nature and condition of the structural

    components. Inspection should cover not only the condition of individual

    components but also the condition of the structure as an entity, noting especially any

    signs of distress and possible causes.

    Should the inspection reveal a defect which is believed to seriously compromise the

    structures ability to carry load safely, the Railtrack Directors Nominee is required to

    be advised urgently in order that consideration may be given to the appropriate

    emergency action to be instructed. Examples of defects that may require urgent

    action to maintain the safety of the Bridge would include cracks in metallic structures,

    or in the case of a masonry arch bridge if part of the arch is sagging.

    Where practicable, advantage should be taken of the presence of scaffolding forrepairs/painting, the removal of ballast, longitudinal timbers, walkway boarding,

  • 8/21/2019 CEC025 - Rail Track Code

    22/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 2 of 18

    periods of low water etc. which may improve access for inspection of concealed and

    otherwise inaccessible parts.

    Where reasonably practicable Bridges should be observed under rail traffic and any

    signs of abnormal movement such as excessive deflection, working of connections,

    vibration or movement should be noted and considered as part of the assessment.

    Where possible, these observations should be made under the passage of the heaviest

    rail traffic using the Bridge.

    When inspection is to be carried out in the hours of darkness the Bridge should first

    be observed in daylight.

    The skill, expertise and training of the person carrying out the inspection should be

    appropriate to the complexity of the structure being assessed. This person should be

    involved in the subsequent assessment process.

    Where the taking of samples is considered necessary to confirm material parameters

    or condition, the number, position and size of samples to be taken and any

    consequential making good is required to be agreed by the Railtrack Directors

    Nominee. With regard to metallic structures, material testing should generally only

    be used to confirm the material types, allowing the adoption of typical material

    properties form Table A2 for assessment. Only in circumstances where this process

    shows the material to be untypical should additional testing be undertaken to confirm

    the yield stress and other appropriate material properties. Guidance on material

    identification, sampling and testing is included in Appendix F.

    3.2 Requirements prior to Inspection

    Prior to undertaking an inspection of a Bridge all existing information pertaining to

    the Bridge should be examined, including as-built drawings, soils data, past assessment

    and examination reports and details of mineral extraction, as appropriate. This

    examination may be useful in determining what further information should be

    obtained from the inspection and which items require special attention. Special

    attention should be paid to checking whether previously identified defects have

    worsened.

    Emergency reporting arrangements should be established and inspection personnel

    advised of these in advance of all site activities.

    3.3 Inspection for Loading

    The inspection should enable the material type and all dimensions necessary to

    calculate an accurate estimate of the dead and superimposed dead loads to be

    determined.

  • 8/21/2019 CEC025 - Rail Track Code

    23/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 3 of 18

    The position of tracks, rail joints (e.g. fish plated, welded and expansion) or switchesand crossings (within 18 metres of the bridge bearings) relative to the Bridge and

    whether timber or concrete sleepers are installed should be recorded.

    Track cant, radii, permissible speeds and any PSR or TSR should also be recorded

    where appropriate.

    The presence of longitudinal timbers, methods of fastening and positions of joints and

    notches in timbers should be recorded.

    Where the Bridge carries ballasted tracks, the overall ballast depth and depth to

    underside of sleepers should be determined. The extent and height of any ballastheaped on the bridge should also be noted, and the level relative to any control

    marks recorded.

    The location, number, size and type of services and service troughs should be

    recorded.

    3.4 Inspection for Resistance

    3.4.1General

    The Bridge should be inspected to record all the parameters needed to determine:

    the strength of elements and joints, including any observed defects, such ascracks, loss of section due to corrosion, settlement, defective materials,

    damage etc.;

    the form of the structure to enable, in particular, assessment of dynamiceffects (see Section 4).

    This inspection should be carried out within touching distance.

    The inspection should supplement and provide confirmation of any informationobtained from existing records, particularly:

    dimensions of internal sections that may not be related to external features;

    strengthening and repairs that may not appear on record drawings, as theseelements may limit the load carrying capacity of the Bridge.

    All constituent parts of the structure should be inspected in sufficient detail so that

    their respective strengths can be determined. In some cases sampling of materials

    may be required. Those parts not inspected should be recorded clearly and reasons

    given.

  • 8/21/2019 CEC025 - Rail Track Code

    24/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 4 of 18

    For buried members and those with hidden parts, excavation of trial holes etc.,

    should be considered where there is doubt about the above parameters, especiallywhere such parameters could be critical. Care should be exercised to ensure that

    there is no permanent damage caused to the structure by such excavations.

    3.4.2Metal Bridges

    3.4.2.1General

    Prior to the inspection, a preliminary review of the structure, should be undertaken

    to identify and assess potentially fatigue prone components and details.

    The location, extent and remaining section of members where corrosion or otherforms of deterioration has occurred should be recorded accurately (preferably in

    sketch form) to enable calculations to be made of section properties. The extent of

    corrosion should also be established where metal sections are in contact with timber

    decking or longitudinal timbers.

    The location, nature and extent of distortion of structural elements resulting from

    bridge strikes should be recorded.

    Samples should be taken where required for testing to determine yield stress or

    other material properties. Signs of poor quality and inferior metal should be notedand further tests carried out if appropriate.

    All cast iron members should be checked for the presence of cracks and blow holes

    especially in tensile areas. The location and extent of such defects should be

    recorded.

    Where suspension bolts support a live load carrying member, particularly where their

    failure could directly lead to collapse of the member, consideration should be given to

    removal of a bolt or plate for inspection purposes. The stability of the structure must

    be maintained after removal of these components.

    Evidence of water seepage which may have contributed to corrosion of parts that are

    not directly amenable to inspection should be noted. Exploration to establish the

    extent of any corrosion should be considered.

    Loose or missing bolts or rivets, rivets with severely corroded heads and any

    working or rust staining of any connections should be recorded.

    The dimensions and condition of free spanning longitudinal timbers should be

    recorded.

  • 8/21/2019 CEC025 - Rail Track Code

    25/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 5 of 18

    The verticality, and magnitude and direction of horizontal bow of top flanges of maingirders as required by Clause 9.8.2A plus details of the end restraints including those

    for vehicle restraint should be recorded. Out of flatness of web panels should also be

    recorded.

    For half through type bridges with solid web or truss girders the presence of and

    condition of features which may be contributory to compression flange stability

    should be noted such as:

    (i) cross girder to main girder connections including the relative locations of

    vertical stiffeners;(ii) signs of loose or working elements such as rivets, bolts or packings;

    (iii) presence of concrete or other haunching or infilling to the main girders;

    (iv) other connections between floor and main girders such as troughing, plate or

    timber floor, resting onto the bottom flange etc.;

    (v) trimmers or end cross girders and any infilling at or adjacent to the bearings;

    (vi) type of bearings and whether they or any infilling or haunching is providing

    torsional restraint to the main girders. A note should be made of any wear,

    cracking or spalling of bedstones;(vii) details and location of bearing stiffeners, end plates and other stiffening local

    to the bearings;

    (viii) verticality of the main girders at the bearings. Magnitude, shape and direction

    of horizontal bow of the main girder top flanges. A note should be made of

    any additional movements of the main girders under live loading.

    3.4.2.2Fatigue

    Members particularly susceptible to fatigue should be closely examined for visible

    cracks so far as reasonably practicable. In particular close attention should be paid tothe details shown in Figure 3.1 which are known to be fatigue susceptible. In addition

    to these, areas of severe and/or pitted corrosion around areas which have been

    subjected to mechanical damage and distortions, such as may arise from vehicle

    impact should be closely examined.

    Where visible cracks are found, their extent should be measured and recorded.

  • 8/21/2019 CEC025 - Rail Track Code

    26/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 6 of 18

    NOTCHED RAILBEARERS

    LIABLE TOFATIGUECRACK

    WELDED DOUBLER ENDS

    LIABLE TOWELDUNDERCUT

    FATIGUE CRACK

    RIVET HOLES INTENSION AREAS

    CRACK

    LIABLE TOFATIGUECRACK

    NOTCHED CROSS GIRDER END

    WELDED ATTACHMENTSAT FLANGE EDGES

    STRESSRAISER

    STRESSRAISER

    ENDS OF TRUSS MEMBERS

    TENSIO

    N COMPRESSION

    CRACK

    WELDED REPAIRSOR

    ATTACHMENTSTO

    RIVETED MEMBERS

    ATTACHMENTSWELDED

    WELDED REPAIRPATCH

    Figure 3.1

    Fatigue Susceptible details

  • 8/21/2019 CEC025 - Rail Track Code

    27/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 7 of 18

    3.4.3Masonry Arch Bridges

    3.4.3.1General

    The external fabric should be inspected. The arch barrel should be inspected to

    ascertain all the information needed to determine the loading and resistance in

    accordance with Section 6. This information should be recorded on the arch data

    sheets on Figures 3.2 and 3.3. In particular the following information should be

    determined:

    (i) thickness of the arch ring carrying rail traffic (this may not be the same as the

    number of rings visible on the face) and its shape;

    (ii) nature and condition of the brickwork, stonework and mortar, including thelocation and extent of any crushing, and the direction of bonding in the case of

    skew bridges;

    (iii) thickness of the joints and the depth of any mortar loss;

    (iv) presence of cracks, their width, length, position and number;

    (v) location and extent of any loss of section due to spalling or damage by vehicles

    from bridge strikes;

    (vi) location of any displaced voussoirs and displacement across cracks;

    (vii) deformation of the arch barrel from its original shape;

    (viii) the presence and effectiveness of any previous strengthening such as saddling,

    stitching, grouting or strengthening rings;

    (ix) the presence and extent of any ring separation, which may be deemed to have

    occurred if the engineer has any reasons to believe that the ring is not acting

    integrally with the rest of the arch;

    (x) haunching over abutments and piers of multispan structures.

    On site measurements should be made in imperial units and then converted to metricprior to commencement of assessment analysis.

    If part of the arch exhibits a significant change in profile from that described in

    previous reports, the bridge should not be assessed but the condition of the bridge

    reported to Railtrack immediately.

    Where there is uncertainty about the above information a site investigation should be

    considered, including trial holes where necessary. Probing into the construction

    should be carried out where the strength of the bridge is in doubt or if internal scour

    and leaching of the fill is suspected.

  • 8/21/2019 CEC025 - Rail Track Code

    28/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 8 of 18

    The extent and location of water seepage should be recorded. The colour and

    nature of any leachates should be closely examined for signs of brick or stone slurrythat may indicate internal movement.

    Parapets and spandrel walls should be inspected for evidence of any defects and their

    extent recorded on Figures 3.2 and 3.3, including, but not limited to:

    tilting, bulging or sagging;

    lateral movement of parapet or spandrel wall relative to the face of the archbarrel;

    lateral movement of parapet or spandrel wall accompanied by longitudinalcracking of the arch barrel;

    weathering and lack of pointing;

    cracking, splitting and spalling;

    loosening of any coping stones;

    presence, location and details of ties, straps and patress plates.

  • 8/21/2019 CEC025 - Rail Track Code

    29/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 9 of 18

    LINE OR

    BRANCH

    MAP REFERENCE

    NEAREST

    STATION

    BRIDGE No. M C LINE REFERENCE

    ARCH PROFILE SEMICIRCULAR

    SPAN DIMENSION

    (SQUARE)

    SEGMENTAL

    SPAN DIMENSION

    (SKEW)

    ELLIPTICAL

    NUMBER OF RINGS PARABOLIC

    POINTED

    C ARCH

    A

    A

    = ===

    SPAN

    ELEVATION LOOKING :

    SECTION A-A

    The following information should be recorded above:

    A. SKETCH PROFILE OF SURFACE BALLAST AND TRACKS.

    B. DIMENSION FROM TOP OF PARAPET TO SOFFIT OF

    ARCH.

    C. DIMENSIONS FROM TOP OF PARAPET TO RAIL LEVEL.

    D. DIMENSIONS BETWEEN PARAPETS.

    E. POSITIONS OF TRACK ON STRUCTURE.

    F. TYPE OF SLEEPER AND TRACK

    Figure 3.2Arch Data Sheet 1

  • 8/21/2019 CEC025 - Rail Track Code

    30/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 10 of 18

    Figure 3.3

    Arch Data Sheet 2

    GENERAL FAULTS

    MAP REFERENCE

    BRIDGE No. M C LINE REFERENCENEARESTSTATION

    ARCHRINGMATERIAL

    HARD STONE

    MEDIUM STONE

    ENGINEERING BRICKS

    BUILDING BRICKS

    CONCRETE

    OTHER (STATE) :

    ARCH RING JOINTS

    LIMESTONE

    MORTAR ARCH RINGMATERIAL

    GOODSOUND OR FRIABLE

    TYPE OF LAYINGRANDOMSQUAREDCOURSED

    CORRECT BONDINGREGULAR JOINTS

    YES NO

    WIDTH OF JOINTS

    UP TO 6mm6mm TO

    12mmOVER 12mm

    DEPTH OF JOINTS

    0mm (FLUSH TO FACE)

    UP TO 12mm

    12mm TO 0.1 OF RINGTHICKNESS

    OVER 0.1 OF RING THICKNESS

    YES NO IF YES' GIVE DETAILSDIAGONAL CRACKS FROMSPRINGING TO CENTRE

    ARCHRING

    LONGITUDINAL CRACKS INSOFFITTRANSVERSE CRACKS INSOFFITRADIAL DISPLACEMENT OFINDIVIDUAL STONE OR BRICKSPERMANENTDEFORMATIONCONSTANTLY WET

    OR DAMPDIFFERENTIAL SETTLEMENTSPREADCRACKS AT QUARTER POINTSBULGINGCRACKSMOVEMENTSCONCRETE SLAB OR SADDLEGROUTED MATERIALWELL COMPACTED MATERIALS

    ABUTMENTS&/OR PIERSSPANDRELWALLS

    WINGWALLS

    FILLINGNOT KNOWN

    WEAK MATERIALS EVIDENCED BY`TRACKING' OF SURFACE

    LINE ORBRANCH

    SOFT STONE

  • 8/21/2019 CEC025 - Rail Track Code

    31/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 11 of 18

    3.4.3.2

    Cracking in Masonry ArchesThe inspection should investigate all cracks in an effort to establish their size and

    depth, any associated displacement and their age. Old cracks, which probably

    occurred soon after the bridge was built, and are no longer propagating, may usually

    be ignored. Recent cracks, on the other hand, usually show clean faces, with possibly

    small and loose fragments of masonry. Although appearing as shear of the bricks or

    masonry, cracks normally follow an irregular line through the mortar. For this

    reason, care should be taken in checking that the defects are cracks and not

    deficiencies of the pointing material.

    Cracks in abutments may generally be ignored unless they are new or growing. Ifcracks in abutments are caused by subsidence they may have affected the arch ring.

    The possible causes of cracks in the arch are noted below:

    longitudinal cracks outside the centre third of the arch between the spandrelsand the arch ring may be caused by shear stresses generated by the spanwise

    deformation of the arch relative to the spandrels under the passage of live

    load (see Figure 3.4);

    longitudinal cracks within the centre third of the bridge emanating from theabutments may be due to varying amounts of subsidence in different places

    along the length of the abutment, and are dangerous if large, because suchcracks tend to indicate secondary breaking up;

    longitudinal cracks along the centre of a twin track bridge, spreading outwardsfrom the midspan area, may be caused by the stresses generated by the arrival

    on the bridge of trains travelling in opposite directions;

    transverse cracks, usually found near the quarter points, due to permanentdeformation of the arch, may be caused by partial collapse of the arch or

    movement at the abutments;

    Diagonal cracks normally start near the sides of the arch at the springing andspread up towards the centre of the bridge at the crown may be due to a

    subsidence at the sides of the abutment. Diagonal cracks indicate that the

    bridge could be in a dangerous state. Where diagonal cracks meet or cross,

    there is a possibility that a portion at the joint could be punched out, as shown

    in Figure 3.5 below, and therefore, action should be taken as soon as possible

    to prevent this happening;

    cracks in the corners and abutments of skewed arch bridges may be due tothe differential resistance provided by the backfill.

  • 8/21/2019 CEC025 - Rail Track Code

    32/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 12 of 18

    (a)

    (c) (b)

    Spandrel wallsFace of abutment

    Figure 3.4

    Plan on Arch showing Longitudinal Cracks

    a) Between arch ring and spandrels out with middle third

    b) From abutment within middle third

    c) Along centreline

    Could be punched out

    Diagonal cracks from arch springing

    Figure 3.5

    Diagonal Cracking in Arch

  • 8/21/2019 CEC025 - Rail Track Code

    33/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 13 of 18

    3.4.3.3 I nspection of Jack Arches

    The inspection of a jack arch deck should record the following information:

    (i) the geometric configuration of the jack arches and their supporting members;

    (ii) the presence of arch ties, details of their size, spacing, condition and position

    within the height of the arch;

    (iii) rotations or horizontal displacement of a supporting member;

    (iv) transversely braced bottom flange of a supporting member;

    (v) inadequate support to springings, for example, corrosion of the bottom flange

    of supporting beam over a horizontal length or loss of bedding mortar;

    (vi) cracking at the crown of the arch due to spreading of springings;

    (vii) distortion and any associated cracking of the jack arch barrel;

    (viii) arch cracking associated with substructure cracking or distress.

    3.4.4Reinforced and Prestressed Concrete Bridges

    A covermeter survey should be undertaken to check the cover and the location of

    reinforcing bars and prestressing tendons particularly in critical areas. If there are no

    drawings, if the available drawings do not give sufficient detail for assessment, or if

    there is evidence that the bridge is not as shown in the drawings, further investigationwill be required. Other evidence may arise from records, from the covermeter

    survey, or from other findings of the inspection. Further investigation usually consists

    of a more comprehensive covermeter survey supplemented by local exposures of

    reinforcement to determine its size and confirm the position of critical bars. It will

    not normally be practical or desirable to expose sufficient reinforcing or prestressing

    steel to fully determine, its position, cross-sectional area and condition. When it is

    considered necessary to locally expose reinforcement, the extent and depth to be

    removed and method of making good is required to be agreed by the Railtrack

    Directors Nominee.

    The worst credible strength of concrete should generally be derived from tests

    carried out on cores in accordance with BS 6089. Cores are destructive and cannot

    generally be taken at the critical locations of an element; hence interpretation or

    extrapolation is necessary to arrive at worst credible strengths in these locations.

    To assist in interpreting or extrapolating the results of core tests, an integrated

    programme of testing which may include destructive, semi-destructive (e.g. near

    surface) and non-destructive tests is necessary for each element. Care and

    judgement is required in selecting the locations and numbers of samples for such

    tests. The non-destructive tests can be used to give an indication of whether the area

  • 8/21/2019 CEC025 - Rail Track Code

    34/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 14 of 18

    of concrete from which the cores are taken is representative of the concrete in the

    critical areas.

    For reinforcement or prestressing tendons and bars, a worst credible strength should

    be obtained by testing samples taken from the element being assessed. It should be

    noted that bars of different sizes are likely to have significantly different yield

    strengths. Removal of prestressing steel for sampling will alter the stress distribution

    in the concrete section and the change should be allowed for in the assessment

    calculations.

    The extent and nature of spalling, corrosion of reinforcement, rust staining, crazing

    or soft or friable concrete should be recorded. Where cracking is present thefollowing information should be obtained:

    details of position, extent and widths of significant or unusual cracks;

    details of any cracks showing evidence of rust staining;

    all cracks over approximately 0.2 mm wide;

    all flexural cracks in prestressed elements.

    Consideration should be given to undertaking additional tests to determine

    constituents and condition of the concrete. The tests may include tests for chloride,

    half cell potential, sulphates, carbonation, alkali silica reaction or ettringite formation

    and cement content. However, in general these tests are not required unless there is

    other evidence of the associated forms of deterioration.

    For post-tensioned concrete structures the fundamental design and construction

    details should be established by a desk study, prior to the inspection for assessment,

    as outlined in BA 50/93: Post-tensioned Concrete Bridges. Planning, Organisation and

    Methods for Carrying Out Special Inspections. The inspection should follow the

    procedures for Special Inspections as described in BA 50/93, if the bridge may be at

    risk of sudden failure following tendon corrosion or if the integrity of transverse

    prestressing is to be assumed in the subsequent analysis of the adequacy of the

    structure.

    Any evidence of distress should be recorded, especially evidence of rust staining,

    spalling, cracking or water penetration at anchorage or tendon positions. In

    particular unexpected cracking and unexpected or changing deflection should be

    recorded. Further investigation is required whenever there is evidence that suggests

    tendon corrosion. Corrosion of tendons in post-tensioned members may not be

    visually manifest during inspection. For pretensioned concrete members, significant

    tendon corrosion usually causes visible rust staining and cracking of the cover

    concrete.

  • 8/21/2019 CEC025 - Rail Track Code

    35/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 15 of 18

    3.4.5Composite Bridges

    The steel and concrete elements of composite bridges or composite members known

    to have been designed for composite behaviour should be inspected in accordance

    with Clauses 3.4.2 and 3.4.4 as appropriate. For other bridges or members where

    concrete (or brick jack arches) is in contact or surrounds steel or wrought iron

    members then inspection should be used to decide whether composite behaviour can

    be assumed using Appendix A or Appendix C. It should be noted (see Clause 8.3.1C)

    that composite behaviour of cross girders is not to be assumed in Type A or other

    filler beam type decks less than 300 mm deep where there is no encasement above

    the top flange or below the bottom flange.

    For concrete slabs supported on steel or wrought iron beams the steel/ metal

    interfaces should be examined especially near the supports for signs of:

    corrosion;

    fretting;

    relative longitudinal slip;

    vertical separation;

    cracking or spalling of concrete.

    Any relative movement should be recorded including any under live loading.

    For cased beams the soffit (and other surfaces where practicable) should be examined

    for signs of:

    rust forcing or leakage;

    separation of or hollowness of the casing concrete.

    For filler beams or concrete or brick arch decks the soffit (and other surfaces where

    practicable) should be examined for signs of:

    corrosion; relative longitudinal slip;

    separation;

    cracking or spalling of concrete.

    Where the infill consists of unreinforced concrete or brickwork or is unknown then

    probing should be undertaken to prove the presence of dense material in contact

    with the beam before composite behaviour can be assumed in assessment.

    For concrete infilled troughs, probing or other inspection should be undertaken to

    determine the depth and condition of concrete above the crests before composite

    behaviour can be assumed in assessment.

  • 8/21/2019 CEC025 - Rail Track Code

    36/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 16 of 18

    3.4.6Timber Bridges

    The timber should be inspected, noting the presence of any protective coatings and

    searching for the presence of rot or infestation (especially around metal fixings and

    where there is standing water round piers in estuary waters). Heart rot may only be

    detected by probing. The use of pressure sensitive, non-destructive drilling

    techniques should be considered. Inspection for splitting and rot should be carried

    out especially in areas of notching. Care should be taken not to transfer fungal spores

    to sound timber by the use of contaminated tools. Any holes drilled should be made

    good with sound timber dowels. Particular attention should be paid to timber in

    contact with metal.

    If site inspection indicates modifications to the structure, especially to primary

    members, and weak timber is suspected, or if the species is unknown, samples should

    be taken for identification of the timber.

    3.4.7Substructures

    It is not normally possible to inspect the foundations, but where they are exposed, for

    example in tidal waters, their condition should be checked. Any defects present and

    their extent should be noted; defects may include cracking, erosion, disintegration or

    corrosion of reinforcement.

    Dimensional checks are required for preparing sketches for analysis or for

    confirmation of record drawings. The dimensional checks may require excavation or

    probing to determine depth and the extent of foundations. Care should be taken to

    ensure that exploratory work does not impair stability or damage underground

    services.

    In river beds and banks the removal of material by scouring, from around the base of

    piers or abutments may lead to undermining of the foundations, especially during

    flooding. Whilst assessment of the susceptibility of a substructure to scour is outside

    the scope of this standard, evidence of scour holes and approximate dimensionswhere possible should be recorded. The presence and type of scour protection

    should be recorded.

    Foundation deficiencies usually appear as movements which may be sufficiently large

    to cause tilting, cracking or excessive movements at joints or bearings. In arch bridge

    foundations movement or arch spreading is generally apparent from cracks showing

    distress in the arch rings and spandrels; diagonal cracking may be indicative of

    differential settlement of the foundations.

    All accessible parts of the substructures should be examined and any defects,including extent, and possible causes recorded.

  • 8/21/2019 CEC025 - Rail Track Code

    37/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 17 of 18

    Some typical substructure defects are:

    tilting and rotation, in any direction;

    rocking;

    cracking, splitting and spalling;

    erosion beneath water level;

    weathering and other material deterioration, including lack of pointing formasonry and brickwork;

    vegetation intrusion; lack of effective drainage;

    internal scour and leaking of fill;

    settlement of structure;

    settlement of fill.

    Movement of substructures is likely to be caused by foundation movements.

    Differential foundation movements may be evident on abutment or pier walls in the

    form of vertical or inclined cracks.

    The effects that any observed substructure movement may have on the

    superstructure or deck should be investigated. For example, differential settlement

    will cause a twist in the deck; inspection may reveal dislocated bearings. Where

    continuous decks are encountered, substructure movements may be evident from

    signs of distortion or distress consistent with a sag over the settling support or

    hogging over intermediate adjacent supports.

    Movement of substructure may be related to the support of spans of unequal length

    or character.

    In arch bridges, predominantly horizontal cracks in piers or abutments may be the

    result of the arch spreading.

    3.4.8Bearings

    Bearings if present, should be inspected so that the general condition and efficiency or

    operation of the bearings can be established. The following should be noted:

    general condition of bearings and their type and articulation;

    any binding or jamming, looseness, or reaching limits of rotational or

    translational movement, or vertical movement under live load; condition of seating bedding and plinth;

  • 8/21/2019 CEC025 - Rail Track Code

    38/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 3 - Inspection for Assessment Page 18 of 18

    whether correct operation of the bearings is prevented or impaired, such asby structural members built into abutment or pier;

    for metal girder bridges, where applicable, whether the bearings are fulfillingtheir function of providing end torsional restraint.

    In bridges without bearings or where the bearings have failed to function correctly,

    there may be local crushing or cracking, especially where supports are stone or

    brickwork.

    3.5 Report on Inspection

    A report containing all the relevant information obtained from the inspection should

    be produced. The report should include:

    a description of the structure including details of any services carried;

    a description of the condition of the structure including any repairs and adiscussion of the effect of any significant defects on the operational safety and

    assessment of the structure;

    sketches, drawings or photographs identifying the nature, location and extentof any defects;

    sketches giving as measured dimensions;

    other photographs, including general views and specific details.

  • 8/21/2019 CEC025 - Rail Track Code

    39/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 4 - Loading for Assessment Page 1 of 33

    CONTENTS

    4. LOADING FOR ASSESSMENT.............................................................................................1

    4.1 Dead Loads .........................................................................................................................1

    4.2 Superimposed Dead Loads..............................................................................................2

    4.2.1 Ballast ...........................................................................................................................2

    4.2.2 Track ............................................................................................................................2

    4.2.3 Services ........................................................................................................................2

    4.2.4 Miscellaneous..............................................................................................................2

    4.3 Railway Live Load ..............................................................................................................3

    4.3.1 Vertical Static Loading ..............................................................................................3

    4.3.2 Dynamic Effects..........................................................................................................74.3.3 Dispersal of Railway Live Loading onto the Structure.....................................25

    4.3.4 Nosing ........................................................................................................................28

    4.3.5 Centrifugal Load.......................................................................................................29

    4.3.6 Longitudinal Loads...................................................................................................30

    4.3.7 Load Combinations .................................................................................................31

    4.3.8 Elements Supporting More Than One Track.....................................................31

    4.3.9 Structures Carrying Light Rail Systems...............................................................32

    4.4 Other Live Loads.............................................................................................................32

    4.4.1 Wind Loads...............................................................................................................32

    4.4.2 Temperature.............................................................................................................32

    4.5 Operational Safety Requirements................................................................................33

    4.5.1 Track Twist ...............................................................................................................33

    4.6 Accidental Loads from Vehicles....................................................................................33

    4.6.1 Bridges over Highways ...........................................................................................33

    4.6.2 Intersection Bridges ................................................................................................33

    4.6.3 Train Derailments on Bridges ...............................................................................33

    4. LOADING FOR ASSESSMENT

    4.1 Dead Loads

    The dead loads should, where possible, be based on dimensions verified during the

    inspection. For assessment Level 1 analysis the applicable values of unit weight given

    in Table 4.2 should be used. Where, however, the initial assessment shows

    inadequacies, or there is doubt about the nature of a particular material, tests should

    be carried out to determine actual densities.

  • 8/21/2019 CEC025 - Rail Track Code

    40/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 4 - Loading for Assessment Page 2 of 33

    4.2 Superimposed Dead Loads

    4.2.1Ballast

    The superimposed dead load due to ballast should be based on the measured depth

    with unit weight 1800 kg/m.

    4.2.2Track

    Where applicable, the superimposed dead loads due to track components given in

    Table 4.1 may be used. Where a different configuration of sleepers and rails has been

    identified during the inspection, the self weight to be used should be determined by

    measurement of dimensions of the configuration and by reference to data on weights

    of components produced by the manufacturer.

    Component Mass

    Single Bullhead Rail 47.07 kg/m

    Single Type 113A Rail 56.22 kg/m

    Single UIC 60 Rail 60.22 kg/m

    Conductor Rail 75.2 kg/m

    Concrete Sleeper (Type F40 for use with 113A Rail)*11 300 kg

    Concrete Sleeper (Type G44 for use with UIC 60 Rail)*11

    315 kgTimber Sleeper 94 kg

    Chair for Bullhead Rail 21 kg

    *1 Includes shoulder, clips and rail pads.

    Table 4.1

    Permanent Way Component Weights

    4.2.3Services

    The superimposed dead load resulting from service cables and ducting should bedetermined, where possible, from examination and measurement during the

    inspection or from information provided by the service owner. Where this is not

    possible, any assumptions made regarding such equipment should be clearly stated in

    the assessment calculations.

    4.2.4Miscellaneous

    Miscellaneous items such as walkways which are not deemed to be part of the

    structure should be considered as superimposed dead load. The nature and

    dimensions of such items should be established during the inspection, and the partial

    factor fL for dead load applicable to the material (given in Table 2.2) should be used.

  • 8/21/2019 CEC025 - Rail Track Code

    41/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 4 - Loading for Assessment Page 3 of 33

    Material11

    Unit Weights kg/m

    Metal AluminiumCast Iron

    Wrought Iron

    Steel

    27507200

    7700

    7850

    Concrete Reinforced or Prestressed

    Plain

    Breeze Block

    2400

    2300

    1400

    Masonry Engineering Brickwork

    Other Brickwork

    Granite

    Sandstone

    2400

    2100

    2600 to 2930

    2200 to 2400

    Timber2 Softwood

    Hardwoods generally

    Jarrah

    Greenheart

    640 typical (480 to 720)

    640 to 1200

    840 to 960

    1040 to 1200

    Fill Sand (dry)

    Sand (saturated)

    Hardcore

    Crushed Slag

    Packed Stone RubbleEarth (dry, compact)

    Earth (moist, compact)

    Puddled Clay

    1600

    2000

    1920

    1440

    22401600

    1800

    1920

    Asphalt

    Macadam

    2300

    2560

    1 Reference may also be made to BS 648 and BS 5268: Part 2: 1996.

    2 Wide range of unit weights because of the variability of timber. For densities

    of specific timber types refer to BS 5268: Part 2: 1996

    Table 4.2

    Density of Materials used in Bridge Construction

    4.3 Railway Live Load

    4.3.1Vertical Static Loading

    4.3.1.1Route Availabil ity (RA) Number

    The assessment of a Bridge should be determined in terms of its Route Availability(RA) number, that is its safe traffic load capacity. Route Availability numbers generally

  • 8/21/2019 CEC025 - Rail Track Code

    42/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 4 - Loading for Assessment Page 4 of 33

    range from the lowest capacity RA0 to the highest at RA15 represented by 25 British

    Standard Units (BSUs) of Type RA1 loading respectively as shown by Table 4.3.R.A. NUMBER RANGE OF BSUs

    IN GROUP

    RANGE OF SINGLE AXLE

    WEIGHTS IN GROUP

    RA0 Up to 10.99 units Under 13.96 tonnes

    RA1 11.00 to 11.99 units 13.97 to 15.23 tonnes

    RA2 12.00 to 12.99 units 15.24 to 16.50 tonnes

    RA3 13.00 to 13.99 units 16.51 to 17.77 tonnes

    RA4 14.00 to 14.99 units 17.78 to 19.04 tonnes

    RA5 15.00 to 15.99 units 19.05 to 20.31 tonnes

    RA6 16.00 to 16.99 units 20.32 to 21.58 tonnes

    RA7 17.00 to 17.99 units 21.59 to 22.85 tonnesRA8 18.00 to 18.99 units 22.86 to 24.12 tonnes

    RA9 19.00 to 19.99 units 24.13 to 25.39 tonnes

    RA10 20.00 to 20.99 units 25.40 to 26.66 tonnes

    RA11 21.00 to 21.99 units 26.67 to 27.93 tonnes

    RA12 22.00 to 22.99 units 27.94 to 29.20 tonnes

    RA13 23.00 to 23.99 units 29.21 to 30.47 tonnes

    RA14 24.00 to 24.99 units 30.48 to 31.74 tonnes

    RA15 25.00 units and over 31.75 tonnes and over

    Table 4.3

    Route Availability Classification for Bridges

    Type RA1 loading excludes dynamic effects which should be added in accordance

    with Clause 4.3.2 and are dependent upon train speed. RA numbers should therefore

    be determined according to a given train speed. In some cases it may be necessary to

    determine more than one RA number for a given Bridge, for example RA6 at

    100 mph representing passenger trains (normally the permissible speed) and RA10 at

    60 mph for freight trains.

    The number of units of Type RA1 loading that the Bridge can carry should be

    determined by calculating the live load capacity factor, C, as defined below:

    loadingRA1Typeofunits20ofEffects

    CapacityLoadLive=C Equation 4.1

    Capacity in terms of units of Type RA1 loading = C20

    The RA number of the Bridge should be obtained from Table 4.3.

  • 8/21/2019 CEC025 - Rail Track Code

    43/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 4 - Loading for Assessment Page 5 of 33

    Where the assessed RA number is below the RA of the line, the effects under static

    EUDLs for the real (actual) permitted vehicles and combinations, together withdynamic factors for their respective permitted speeds, may be considered acceptable.

    It should be noted that the RA effect of vehicles on a specific span (loaded length) is

    often less than the RA classification for the vehicle which has to allow for a full range

    of Bridge spans.

    4.3.1.2RA1 Loading

    The static loading used to determine the RA number is shown in Figure 4.1 for

    20 units of Type RA1 loading. The Short Lengths configuration should be used when

    it produces more onerous effects than the axle and uniformly distributed load model.

    65kN/m

    4x200kN 4x150kN 4x200kN 4x150kN

    1.51.81.82.71.51.51.5 1.51.51.54.01.81.8 1.81.82.7

    2x250kN

    1.8

    SHORT LENGTHS

    2.4

    Figure 4.120 Units of Type RA 1 Loading

    Note 1: 20 units of Type RA1 loading is equivalent to Route Availability RA10without allowance for dynamic effects.

    4.3.1.3Equivalent Unif ormly Di stributed Loading

    For simply supported spans (with the exception of Masonry Arches, see Section 6),Type RA1 loading may be represented by an Equivalent Uniformly Distributed Load

    (EUDL). Table 4.4 gives EUDL and maximum end shear values for simply supportedspans for 20 units of Type RA1 loading. The EUDL values equate with the maximumbending moment within the span that occurs under RA1 loading.

    For continuous spans the values in Table 4.4 are not strictly applicable, and loadingshould be as shown in Figure 4.1. This loading should be considered as a whole, butany parts of the loading that reduce the effects on the part of the element beingconsidered should be omitted.

    4.3.1.4Application of Loads

    Type RA1 loading should be applied to each track and such as to produce the

    maximum effect in the part of the element being considered.

  • 8/21/2019 CEC025 - Rail Track Code

    44/410

    RAILTRACK LINE CODE OF PRACTICE RT/CE/C/025

    Issue: 1

    Date: February 2001

    The Structural Assessment of Underbridges

    Section 4 - Loading for Assessment Page 6 of 33

    (SPAN)

    (m)

    EUDL

    (kN

    END

    SHEAR(kN)

    SPAN

    (m)

    EUDL

    (kN)

    END

    SHEAR(kN)

    1.2 500 250 9.4 1105 640

    1.4 500 250 9.6 1121 650

    1.6 500 250 9.8 1137 659

    1.8 500 250 10.0 1152 668

    2.0 500 269 11.0 1219 707

    2.2 500 291 12.0 1282 752

    2.4 500 308 13.0 1351 792

    2.6 500 322 14.0 1411 835

    2.8 500 335 15.0 1475 873

    3.0 500 346 16.0 1547 9073.2 513 356 17.0 1620 947

    3.4 532 364 18.0 1687 983

    3.6 554 372 19.0 1760 1017

    3.8 574 378 20.0 1837 1055

    4.0 594 384 22.0 1983 1146

    4.2 618 390 24.0 2126 1233

    4.4 643 395 26.0 2265 1319

    4.6 667 401 28.0 2415 1405

    4.8 689 417 30.0 2547 1488

    5.0 709