ce-311 2 sewers and sewer netwrok- design construction and maintenance

97
 S. Sarkar Pradeep Kumar Sewers and Sewer Networks Design, Construction and Maintenance  

Upload: shubham-bansal

Post on 07-Oct-2015

33 views

Category:

Documents


2 download

DESCRIPTION

maintanence and design construction

TRANSCRIPT

  • S. Sarkar

    Pradeep Kumar

    Sewers and Sewer Networks Design, Construction and Maintenance

  • RAW WATER

    TREATED WATER

    WASTEWATER

    TEATED WASTEWATER

    WASTEWATER TREATMENT PLANT

    WATER TREATMENT PLANT

  • Classification of Sewers

    Domestic or Industrial Sewers

    Storm Sewers

    Combined Sewers

    They are designed to carry wastewater generated from domestic establishments or small- and medium- sized industrial establishments in a municipal area but not storm-water

    They are designed to carry off only stormwater and groundwater but excludes sewage from domestic and/ or industrial source

    They are designed to carry off stormwater, domestic and industrial wastewater

  • Advantages and Disadvantages of Combined Sewers

    It is initially economical to set up a combined sewer rather than separately installing domestic sewers and stormwater sewers

    During dry season lack of stormwater causes a low flow rate. Low flow rate gives rise to low velocity of flow. At low velocities, due to less turbulence, the deposition of sewage solids are more. Result is siltation and consequent foul odor generation due to degradation of the settled solids.

    In contrast, during wet or rainy seasons, the flow rate is very high. Therefore, pumping costs are more, causing high operation and maintenance cost.

    Pumps that are designed to operate at high flow rate to tackle the wet season flow, runs in low flow condition in dry season which is an inefficient operation that consumes more power than usual.

    Due to the above reasons, combined sewers are not generally recommended by the manual of sewerage and sewage treatment, Government of India

  • Estimation of Quantity of Sanitary Sewage

    The sewers are designed to carry:

    Spent water from a community Some groundwater Fraction of the stormwater Industrial wastewater for small establishments

    The sanitary sewers are designed to carry the wastewater from the above sources to a sewage/wastewater treatment plants

    Carrying capacity of the sewers depends on: 1. Present and 2. Future quantities of flow rate expected.

    Thus, it is important to estimate the design flow rate for the sewers to be constructed.

  • Estimation of Sewage Flowrate

    Two Parameters: 1. The contributing population, and 2. Per capita (per person) flowrate of

    sewage

    Both of these quantities depend on the design period

    Design period: The length of the time up to which the capacity of a sewer will be adequate is called a design period.

    Normally design period for a sewerage system is considered as 30 years

    But, mechanical rotating equipment such as pumps are designed for 15 years

  • Forecasting the Population

    Prospective population of the project area (may be a city, town or a metropolitan area)

    Methods: Demographic population projection Arithmetical increase method Incremental Increase method Geometrical Increase method Growth rate Graphical method Logistic method Method of density

    Where is the forecast found for design purposes?

    Normally for a city, population growth forecasts are found from the master-plan prepared by town planning or other relevant authorities.

    What to do when masterplan or planners documents are unavailable?

  • Floor-Space Index Based Calculation

    1. From the city-plan find out the % of the total area available for residential development

    2. Actual total floor area = Area for residential development X Floor Space Index (FSI)

    3. Find out floor area required for one person or assume it depending on the available data from the city. Normally it is 9 sqm/ person.

    4. Find out the density of population per hectare

    5. Multiply the density with the total area of the city to find out the total population

    This total population can be used for estimating the quantity of total sewage flow.

  • Example: Finding out population density based on Floor Space Index method

    A well-planned city has following areas earmarked for its development in the planning stage: Roads- 20%; Gardens- 15%; Schools 5%; markets and Commerical places 2%; Hospital and medical facilities 2% and rest is residential area. The Floor Space Index (FSI) for the city is fixed at 2. If the floor area is 9 sqm/ person, find out the projected population density of the city in numbers/ hecatare.

    Residential Area (%) = 100 (20+15+5+2+2) = 56

    Actual Floor Area = Area of the land X FSI

    Population that can reside in the area= Actual Floor area / Area required by a person

    = 0.56X2 /9

    Population density (numbers / hectare) = 0.56X2X10000/9 = 1244

    numbers / sqm

  • Per Capita Sewage Flow rate

    Ideally the entire amount of water used by a community should appear as the total flow in a sanitary sewer

    Water is lost due to:

    Evaporation Loss Seepage into ground Leakges

    The dry weather flowrate is slightly less than the per capita water consumption

    For very dry and arid regions, Average sewage flowrate 40% of water consumption rate

    In well-paved and well-developed areas, Average sewage flowrate 90% of water consumption rate

    Conservative estimate is 80% of water consumption rate

    Design water consumption in India = 130 LPCD (litre per capita per day)

    Design minimum wastewater flow in India = 100 LPCD

  • Variations in Flow and Peak Factor

    Time of the day

    Flo

    w r

    ate

    Water consumption varies from hour to hour. Along with daily variations, there also are seasonal variations.

    For design purpose, sewers are always designed to carry maximum or peak flow rates, rather than designing it for average flowrate.

    Peak Factor (PF) = Maximum wastewater flow rate

    Average flow rate of wastewater

    Population Peak factor

    < 20,000 3.0

    20,000 50,000 2.5

    50,000 7,50,000 2.25

    > 7,50,000 2.0

    4 8 12 16 20 24

    Average

  • In addition, commercial and industrial contributions are to be considered into the total flow rate.

    Groundwater Infiltration into Sewer lines

    The sewers have joints. Some groundwater runoff may also seep into the sanitary sewers.

    The extent of groundwater infiltration into the sewers depend on the workmanship and the level of the groundwater table with respect to the sewers.

    Usually, for a sanitary sewer below the groundwater table the following values are taken,

    Minimum Maximum

    Liters/ha.d 5000 50000

    Liters per day/ manhole

    250 500

    Maximum sanitary flow rate = Average domestic flow rate X PF + infiltration flow rate

    PEAK FLOW RATE or MAXIMUM FLOW RATE

  • Area with Sufficient Urbanization Area with little or no urbanization

    More paved surface, higher imperviousness, less absorption by soil

    High volume of water on the surface, High runoff, needs quick evacuation to avoid flooding/ inundation

    RAINFALL

    How to evacuate this increased runoff? BUILD EFFICIENT STORM SEWER SYSTEM

  • Finding Out of Runoff

    Runoff quantity depends on:

    Rainfall Characteristics (Intensity, Duration and space-time distributions)

    Characteristics of the watershed surface (nature, permeability, slope, and landscaping)

    Time of concentration (time required for flow to reach the sewer)

    The design should be adequate to carry from a basin or watershed the maximum runoff caused by the design rainfall.

    Storm sewers are designed for a rainfall with particular frequency or return period. The design rainfall is fixed after economic considerations involving the Intensity-duration and frequency (IDF) curves in an area.

  • Case I

    tnttt

    tttt

    tttt

    nn

    0

    022

    011

    2

    Rainfall duration is t

    Time Runoff

    t0= 0 Q0 = Q(t=0) =0

    t1= t Q1=A1IC1

    t2=2t Q2=A2IC2

    tn=nt Qn=AnICn

    Rainfall over a watershed draining at a single discharge point

    I = Intensity of the rainfall A = Area C= Run-off coefficient

  • Case II Rainfall duration is 2t

    Time Runoff

    t0= 0 Q0 = Q(t=0)= 0

    t1= t Q1=A1IC1

    t2=2t Q2=A1IC1+A2IC2

    t3=3t Q3=A2IC2+A3IC3

    tn=nt Qn= An-1ICn-1+AnICn

    tn=(n+1)t Qn+1 =AnICn

    tn+2 =(n+2) t Qn+2 =0

  • Case III Rainfall duration is nt

    Time Runoff

    t0= 0 Q0 = 0

    t1= t Q1=A1IC1

    tj=jt

    t3=nt

    tn=(n+1)t

    tn=(2n-1)t Q2n-1=A1IC1

    tn+2 =2nt Q2n =0

    j

    k

    kkj ICAQ1

    n

    k

    kkn ICAQ1

    n

    k

    kkn ICAQ2

    1

  • A Few Observations

    If the duration of the rainfall is tn and tn is the time necessary for the water droplet to reach to the basin outlet from the hydraulically most distant place in the basin, the entire surface area of the basin contributes to the flow rate or the runoff observed from the basin.

    If the duration of the rainfall is longer than tn, the runoff value remains equal to the same as the case above, from the time tn until the end of the rainfall duration.

    If the duration of the rainfall is shorter than tn, the maximum runoff occurs at the end of the rainfall and is smaller than the runoff obtained for a precipitation of duration tn.

    The maximum runoff flow is always reached at the latest by the end of the rainfall.

    The maximum runoff due to a precipitation of uniform intensity I falling all over the drainage basin, and of duration tn (the longest time for water to travel to the outfall from the basin), is thus given by

    n

    k

    kk

    n

    k

    kkn CAIICAQ11

  • Rational Equation

    Q = 10 CIA

    Q = Run-off in cum/hr C= coefficient of run-off I= Intensity of design rainfall, mm/hr A = Area of drainage basin in hectares

    n

    k

    kk

    n

    k

    kkn CAIICAQ11

    In familiar terms, the above equation is thus given by,

    AICQ

    Values of C Absolutely impervious basin.1.0 Paved Areas0.9 Lawn and Gardens.0.15 Water-bound macadem roads0.45

  • The period of time after which the entire basin area starts contributing to the run-off is called the time of concentration. Varies from 3 to 30 minutes

    Maximum run-off is obtained from a rain having a duration equal to the time of concentration. SEWER

    OUTFALL

    DRAINAGE BASIN

    tC

    Time of Concentration (tc)

    The duration of such a rainfall is called critical rainfall duration and the intensity of such rainfall is known as critical rainfall intensity.

    fec ttt te

    tf

    SEWER OUTFALL

    te= time of entry

    tf= time of flow

    Sub-basin

  • Time of entry is the longest time required for a water droplet in an urban sub-basin to travel to a street inlet.

    Kirpichs model:

    385.0

    77.00195.0

    s

    FLte

    L= maximum distance travelled by the water on the surface

    s= average slope of the route travelled by water

    F = friction factor

    Surface type F

    Rural watershed (flat ground) 1.0

    Grass surface 2.0

    Concrete or Asphalt surface 0.4

    Concrete channel 0.2

    Time of flow is the time required for water to travel to a sewage outfall from the street inlet in the urban sub-basin. It is always computed considering that the pipe is running full.

    21

    321sR

    nv

    v

    Lt f

  • Typical Rainfall Intensity-Duration-Frequency Curves R

    ain

    fall

    Inte

    nsi

    ty, m

    m/h

    r

    Duration, minutes

    The curves can vary from place to place and the shape of the curve follows different patterns.

    kt

    aI

    kt

    aI

    n

    n

    x

    tb

    CNI

    )(

    I ( rainfall intensity) and T (duration) are variables; other terms are constants that can be found out from fitting the curve with the field data obtained.

  • How to find out the design maximum run-off of a basin?

    1. Decide on the frequency of rainfall on which the design will be based on. Lets assume it is twice in a year (that means we shall allow flooding to occur on average twice in a year).

    2. From the contour map of the area find out the time of concentration of the basin (say 15 minutes)

    3. Find out the rainfall intensity corresponding to the time of concentration. (TOC = duration of rainfall )

    4. Apply Rational Formula to find out the maximum or design runoff

  • /1.2 ha

    /2.4 ha

    /1.8 ha

    /120 m

    /180 m

    Find out the maximum design runoff at the discharge point Assume: C = 0.3 (Entire area), 5-year frequency, vel. In sewers = 0.6 m/s

    200

    25

    175

    75

    100

    125

    150

    50 R

    ain

    fall

    Inte

    nsi

    ty, m

    m/h

    r

  • Flow time in sewer from MH 1 MH 2 = (120 m)/ (0.6 m/s) (60 s/ min) = 3.3 min Flow time in sewer from MH 2 MH 3 = (180 m)/ (0.6 m/s) (60 s/ min) = 5.0 min Time of concentration from remote points of 3 separate areas to MH 3: Area 1: 5.0 + 3.3 + 5.0 = 13.3 min Area 2: 5.0 + 3.3 = 8.3 min Area 3: 8.0 min (inlet time only) Max. time conc. = Duration of rainfall = 13.3 min I = 110 mm/hr. for 5-year frequency Sum of CA values = 0.3 (1.2 + 2.4 + 1.8) = 1.62 Q = 10 x 110 x 1.62 = 1782 m3/hr.

  • HYDRAULIC DESIGN OF SEWERS

    Design of sewers are done assuming steady-state conditions. Steady-state means that the discharge or flow-rate at a point remains time-invariant.

    Objectives:

    1. Carry the peak flow rate for which the sewer is designed

    2. Transport suspended solids in such a manner that the siltation in a sewer is kept to a minimum

    This is directly connected with the maximum achievable velocity in the sewers. We do not want the sewage pipe materials to get worn out. The wastewater manual recommends a maximum velocity of 3 m/s.

    This condition gives us an idea about the minimum velocity that has to be maintained inside a sewer during a low flow period.

  • Sewers versus Treated Water Conduits

    SEWER WATER CONDUITS

    1. They are never designed to run full; there is always an empty space provided at the top.

    1. They are always designed to run full.

    Reasons: a) Biodegradation causes generation of gases like methane, hydrogen sulfide, ammonia etc. which can get dissolved if running under pressure. b) At same slopes, the velocity and carrying capacity is more when it runs partially full.

    2. It is unpressurised. It maintains a gravity flow; It is laid in gradients or slopes.

    2. It is pressurized. Normally, we do not worry about the slope of the water mains or lines when we lay them.

  • Minimum Velocity in a Sewer

    The velocity should be such that:

    A) It will not allow the particles to settle inside the sewer

    B) Even if there is a deposition, it will promote scouring of the particles so that it can self-cleanse itself

    The generation of Self-cleansing velocity should occur within the sewer for at least once in a day.

  • W

    W cos

    W sin

    Drag Force RSw

    If the block (Particle) has a unit length and unit width and thickness is dp , then

    From the force balance, when the particle is on the verge of slipping down the plane,

    sinW

    Volume

    WeightSubmergedsubmrged

    )])(g*d*nV)-V[(1

    wnVVV

    ])[1( wdn

    buyoancy)g*d*V(1

    s V

    ]1[)1( sw Sn

    psub dW *1*1*

    sin]1)[1( psww dSnRS

    R= Hydraulic mean radius S= Slope of the channel

    ps dSR

    kS ]1[ sin)1( nk

    pss dSkR

    Rn

    SRn

    v )1(111

    21

    32

    21

    32

    pss dSkR

    nv )1(

    16

    1

    Where,

    SELF-CLEANSING VELOCITY

  • Self-Cleansing Velocity

    pSS DSkRn

    V )1(1

    6

    1

    n = roughness coefficient R = Hydraulic Mean Radius =

    P

    A

    A= Area of the channel P= Wetted perimeter of the channel

    Ss = Specific gravity of the particle

    k = Dimensionless constant, 0.04 for granular particles, 0.8 for organic matters

    DP = Diameter of the particle for which the sewer will be designed, this is the maximum particle size the sewer can safely carry

    Sewers are always designed to attain the self cleansing velocities

  • JAPAN

  • D

    d

    /2 /2

    ]2

    cos22

    [DD

    d ]2

    cos1[2

    1

    D

    d

    2

    4DA

    360.

    4

    2 Da 2

    cos2

    *2

    sin2

    *2

    1*2

    DD

    ]2

    sin

    360[

    4

    2

    Da

    ]2

    sin

    360[

    A

    a

  • D

    d

    /2 /2

    4

    4

    2

    D

    D

    D

    P

    AR

    ]2

    sin3601[

    4

    D

    p

    ar

    DP

    360*

    Dp

    360

    360*

    D

    D

    P

    p

    ]2

    sin3601[

    R

    r

  • D

    d

    /2 /2

    2/13/21 SRn

    V

    2/13/21 srn

    v

    3/23/2

    3/2

    3/2

    2

    sin3601

    R

    r

    R

    r

    V

    v

    3/2

    2

    sin3601

    2

    sin

    360*

    .

    .

    V

    v

    A

    a

    VA

    va

    Q

    q

  • D

    d

    /2 /2

    ]2

    cos1[2

    1

    D

    d

    ]2

    sin3601[

    R

    r

    3/2

    2

    sin3601

    V

    v

    3/2

    2

    sin3601

    2

    sin

    360

    Q

    q

    In all the above expressions, is the only variable, all other parameters are constant. Thus at different values of , the above proportional elements can be easily calculated

  • d/D a/A v/V q/Q

    1.00 1.00 1.00 1.00

    0.9 0.949 1.124 1.066

    0.8 0.858 1.140 0.988

    0.7 0.748 1.120 0.838

    0.5 0.5 1.000 0.500

    0.4 0.373 0.902 0.337

    Capital Letters denote the situation when the sewers run full

    Maximum velocity is achieved when the sewers are designed to run at 80% of the full depth.

  • Designing Sewer Systems

    Sewers are designed taking consideration of 30 years.

    Population in the initial years of the design period are low compared to the design population at the end of design period

    Peak flow rate in the initial years is low compared to the designed peak flow rate (ultimate peak flow)

    Sizing should be such that it will attain the self-cleansing velocity at the average design flow rate or at least at the maximum flow rate at the beginning of the design period.

  • s

    1000

    2/13/21 srn

    v

    ]2

    sin3601[

    4

    D

    p

    ar

    3/2

    2

    sin3601

    V

    vVelocity at partially full flow

    Velocity at full flow

    For Partially-full flow v is not influenced by the diameter of the pipe, rather is much influenced by the slope of the channel

  • After finding the minimum slope required, the pipe size is decided on the basis of ultimate design peak flow rate and the permissible depth of flow. Adoption of the above slopes would ensure minimum flow velocity of 0.6 m/s

    Minimum size for a public sewer is 150 mm diameter

    Minimum size for a public sewer in hilly terrain is 100 mm diameter

    FROM THE SEWAGE TREATMENT MANUAL, GOI

  • Gravity Sewer: Minimum Pipe Slope for Attaining Vmin= 0. 6 m/s

    Diameter (mm)

    Discharge (lps)

    Slope (m/m)

    n= 0.013 n= 0.015

    200 19 0.0033 0.0044

    250 30 0.0025 0.0033

    300 40 0.0019 0.0026

    400 75 0.0013 0.0017

    450 95 0.0011 0.0015

    500 115 0.001 0.0013

    600 170 0.0008 0.0010

    700 230 0.0006* 0.0008

    900 380 0.0004* 0.0006*

    A slope below 0.0008 becomes practically difficult for construction purposes

    Sewers with flat slopes may be required to avoid excessive excavation where surface slopes are flat or change in the elevation is small.

    The slope and size of the sewer should be such that the velocity of flow shall increase progressively or shall remain steady throughout the length of the sewer.

    Sewers shall have slope steeper than or equal to the ground slope, otherwise the minimum ground cover may not be maintained through out the length of the sewer.

  • What will be the diameter of the sewer designed with the following conditions: a) Population to be served: Present = 50,000; Design= 100,000; b) Water consumption: Present = 130 lpcd; Design = 180 lpcd c) 80 % of supplied water appears as wastewater d) Self-cleansing velocity to maintained in the sewer = 0.6 m/s; e) Maximum velocity in the sewer 3 m/s; f) Minimum size of the sewer = 150 mm; g) Peak factor = 2.5 h) n=0.015 i) Average Ground Slope = 1 in 5000

    d/D a/A v/V q/Q

    1.00 1.00 1.00 1.00

    0.9 0.949 1.124 1.066

    0.8 0.858 1.140 0.988

    0.7 0.748 1.120 0.838

    0.5 0.5 1.000 0.500

    0.4 0.373 0.902 0.337

  • Slope to be provided = s=0.8 in 1000 = 0.8/1000 = 0.0008

    We want the sewer to run 80% full at its ultimate peak flowrate. From the chart q/Q = 0.988 when d/D =0.8

    Q = A.V

    STEP 1. Find out the average flowrate and maximum flow rate at present and after the design period

    STEP 2. Find out the optimum slope to be provided

    STEP 3. Find out the size based on the ultimate peak flowrate.

    2/13/21 sRn

    V 2

    4

    DA

    4

    4

    2

    D

    D

    D

    P

    AR

    2/1

    3/22

    *4

    1*

    4. s

    D

    n

    DVAQ

    Time Average flowrate Peak factor Peak flowrate

    Present 50,000* 130*0.8 L/d=0.06 cum/s 2.5 0.15 cum/s

    Design 100,000* 180*0.8 L/d= 0.167 cum/s 2.25 0.375 cum/s

    Q = 0.375/0.988 = 0.380

  • Q=0.380 m3/s S= 0.0008 n =0.015

    380.0)0008.0(*4

    *015.0

    1*

    4

    2/1

    3/22

    DDD = 850 mm

    2/1

    3/22

    *4

    *1

    *4

    . sD

    n

    DVAQ

    (OK)

    m/s 671.0)0008.0(4/850.0015.0

    11 2/13/22/13/2 sRn

    V

    > 0.6 m/s

    cum/s 381.0671.0*4

    )85.0(.

    2

    VAQ

  • Velocity is maximum when the depth of flow d = 0.8 D

    At d/D = 0.8, v/V = 1.140

    For a circular channel running under gravity,

    Hence, vmax = 1.140*0.671 m/s = 0.765m/s < 3 m/s (Maxm. Velocity allowable)

    O.K. At the average flowrate q, q/Q =(0.167/0.381)=0.44

    From the proportionality table, extrapolating, v/V = 0.97

    Hence, v = 0.94* 0.671 m/s = 0.65 m/s >0.6 m/s

    O.K. At the peak present flowrate q1, q1/Q =(0.15/0.381)=0.39

    v/V = 0.93 Hence, v = 0.93* 0.671 m/s = 0.62 m/s >0.6 m/s OK

  • Sewerage System

    Dr. Sudipta Sarkar

  • Preliminary Requirements

    It is meant for the transport stormwater and wastewater from the generation point to the treatment plant. So it should be laid as deep as possible so that all wastewater or storm water flow can be collected and transported.

    Erosion and corrosion resistant. Should be structurally strong enough to resist impact loads or overburden and live loads

    Size and slope to be designed to carry the peak load as well as to carry average flow in such a manner that the deposition shall be minimized.

    Maintenance should be easy, economical and safe for the workers.

    Aims of the design are: a) make the system operational and b) Economical to build and c) make the system durable through out its entire design life

  • Layout of Sewer Lines

    Steps followed for making the layout:

    Selection of an outlet or disposal points

    Fixing limits to the drainage area or zone boundaries

    Finalizing the location of Trunk and Main sewers

    Finalizing the location of Pumping stations wherever necessary

    Trunk sewer is the sewer in the network with the largest diameter that extends farthest from the sewage outfall

    All other sewers are considered as branches

    Whenever two sewers meet at a point, the incoming one with larger diameter is called the main sewer.

    Trunk Sewer Outfall

  • Nomenclature System Followed in Sewer Systems

    Trunk Sewer

    3 2

    4

    L.3.1

    R.3.1

    R.3.2

    L1.R.3.1.1

    L1.R.3.1.2

    L2.R.3.1.1 L2.R.3.1.2

    Outfall

    Network

    manhole

  • Most common location of laying sanitary sewer is along the center of the streets

    House

    House

    The individual domestic connections can be from either side of the streets

    For very wide streets the sewers are laid on each side of the streets in the curb or under the sidewalk

    House

    House

    Street

    Street

    Sewer

    Sewer

    Sewer

    To avoid any contamination sewer lines are never laid near to the water mains. If it is unavoidable, the sewers are encased in concrete

    Slope of the sewers generally follow the natural slope of the ground or the street

  • Design Approach

    1. On a map of the area locate all the sewer lines and measure the contributory area to each of the sewer lines or points.

    2. Also, draw the longitudinal section or profiles of the sewer lines. Mark on the profile view the critical points such as basements of the low lying houses, levels of existing sewers, disposal points, etc.

    3. Design all the branch sewers, main sewers and trunk sewers, starting from the farthest point in the network and based on the following considerations: a) A self cleansing velocity is maintained at present peak flow b) The sewer should run 0.8 full at the design ultimate peak flow c) Minimum velocity of 0.6 m/s is obtained d) Maximum velocity should not be beyond 3 m/s

  • Example of a Profile of a Sewer Line

  • A view inside a sewer in London

  • Sewer Appurtenances

    These are devices necessary (except pipes and conduits) for proper functioning of the sanitary, storm and combined sewers

    The appurtenances include: 1. Manhole 2. Drop Manhole 3. Lampholes 4. Gully-traps 5. Intercepting chambers 6. Flushing tanks 7. Street Inlets 8. Siphons 9. Grease traps 10. Side-flow weirs 11. Leaping weirs 12. Venturi flumes 13. Outfall structures

  • MANHOLES

    Manholes are RCC or masonry chambers, constructed at suitable intervals along the sewer lines, for providing access to the inside of the sewers.

    Helps in: a) Joining the sewer pipes b) Inspection and cleaning of pipes c) Maintenance d) Ventilation if manholes are perforated

    Water main

    Electric cable

    Gutter Curb manhole

    Sewer

    Manholes are provided at every transition points such as bends, junction, change of gradient, or change in diameter

    Between two adjacent manholes, the sewer line runs straight with constant slope or gradient

  • Types of Manholes

    Manholes with Depth less than 0.9 m

    A. Shallow manholes

    Suitable for branch sewers or places at no heavy traffic

    It is also called an inspection chamber

    Manholes with Depth 1.5 m

    B. Normal or Medium manholes

    Heavy cover is provided at the top

    May be either square or rectangular (1m X 1m and 1.2m X 1m

    900X 800 mm

  • Manholes with Depth> 1.5 m

    C. Deep Manholes

    Heavy cover is provided at the top

    May be either square or rectangular or circular

    Size in the upper portion is reduced by offset

  • Access shaft: Minimum size is 0.75 X 0.6 m

    Working chamber: Provides working space for inspection and cleaning operations, Minimum size 1,2 m X 0.9 m or 1.2 m dia; minimum height is 1.8 m

    Benching: concreted portion sloping towards semicircular or U -shaped bottom part of the main sewer, the slope facilitates the entry of sewage into the main sewer

    Steps or ladders: for accessing

  • DROP MANHOLE

    It is used when a branch sewer joins a main sewer at a height more than 600 mm above the main sewer or the drop is more than 600 mm.

    Advantages: 1) Steep gradients in the branch sewer can be avoided ; 2) The sewage from the branch sewers may fall on the person working; This is avoided.

    Plug Inspection Arm

  • FLUSHING MANHOLE

    Provided where it is not possible to gain enough flow so as to maintain a self-cleansing velocity.

    Often such condition is prevalent at the beginning of the branch sewers.

    Generally provided at the head of the sewers where enough storage is provided to generate a high velocity to flush out the obstructions

  • Automatic Flushing Tanks

  • Curb Inlet

    Gratings

  • Different Types of Street Inlets

    GUTTER TYPE

    CURB TYPE INLETS

    COMBINATION MULTIPLE TYPE INLETS

  • CATCH BASINS

    SEWER

    A Type of Street Inlet

    The basin helps in settling the grit, sand, debris, etc. before the storm water enters the sewer line

    Hood prevents the escape of the foul gases into the sewer line and network

  • Oil and Grease Trap

    Generally located near the sources which can generate oil and grease- contaminated wastewater. Restaurants, garages, automobile repair workshops

    Oil and grease in the sewer system can : a) sticks to the inner surface of sewers and reduces the sewer capacity; b)entraps suspended matter, further reducing the capacity; c) adversely affect the performance of wastewater treatment plants

  • REGULATOR OR OVERFLOW DEVICES OR STORM-RELIEF WORKS

    The regulators are provided to avoid overloading of sewers, pumping stations, treatment plant or disposal arrangements by diverting excess flow to relief sewers or overflow stream.

    The overloading is caused by excess flow coming in a pipeline due to heavy rainfall or excess stormwater. As they are not expected to carry huge pollutant load, the excess stormwater can be safely disposed of to natural streams without any treatment.

    Three types of Regulator devices: a) Leaping Weir b) Side-flow or Overflow weir c) Siphon spillway

  • Leaping Weir

    Arrangement consists of an opening at the invert of a storm drain through which the normal storm flow is taken into an intercepting sewer and excess flow leaps over the combined sewer to flow to a neighboring stream

    INCOMING FLOW

    Intercepting Sewer

  • Overflow or Side-flow Weir

    Excess water is allowed to overflow the combined sewer in the manhole, from where it is taken to another channel that leads to stormwater drain or manhole.

    The weir length has to be sufficiently long for effective regulation

  • Siphon Spillway

    Air Line

    Receiving Stream Sewer

    Spillway

  • Different Cross-sectional Shapes of Sewers

    Most widely used cross-sectional shape is a circular-section sewer. The reasons behind the preferences are: a) A circular section provides the maximum area of flow for a given

    perimeter, therefore higher value of hydraulic mean radius.

    P

    AR

    2/13/21 sRn

    V

    It is the most efficient section, among all possible variations

    b) It uses the minimum amount of materials for is manufacture, therefore it is economical to use such a section

    c) Manufacture is easy and convenient

    d) Structurally more stable (without any corners, hence load is evenly distributed all around

    e) Chances of deposition is less

  • d/D a/A v/V q/Q

    1.00 1.00 1.00 1.00

    0.9 0.949 1.124 1.066

    0.8 0.858 1.140 0.988

    0.7 0.748 1.120 0.838

    0.5 0.5 1.000 0.500

    0.4 0.373 0.902 0.337

    0.3 0.252 0.776 0.196

    0.2 0.143 0.615 0.088

    Advantages of a circular sewer diminishes when the sewer is not running at least half-full

    Lesser the discharge, poorer is the performance

  • OVOID OR EGG-SHAPED SEWER

    At low discharges 2- 15% higher velocities are available for these type of sections compared to Hydraulically Equivalent Circular Sections

    Standard Oval Shaped Sewers

    New Type Oval Shaped Sewers

    Hydraulically Equivalent Section: Two sewers of different shape (i.e. different sections) are said to be of hydraulically equivalent when they carry the same discharge when running full at the same slope.

    d/D v/V

    Ovoid circular

    0.25 0.7 0.698

    0.20 0.62 0.61

    0.10 0.44 0.4

    0.05 0.29 0.25

  • Design of Ovoid-Shaped Sewers

    1. Calculate the approximate diameter of a hydraulically equivalent circular sewer that would carry the same discharge at the same slope as the ovoid-shaped sewer.

    2. Top horizontal diameter of the Ovoid-sewer = 0.84 X Diam. of the circular sewer

    3. Find out the other dimensions from the following figures, according to the type of sewer to be designed

  • Horse-Shoe Type of Sections

  • Open-Drain Sections

    P

    AR

    2/13/21 sRn

    V

    VAQ *

  • Design a gravity flow trunk sanitary sewer for the area . The trunk sewer is to be laid along Peach Avenue starting at 4th Street and ending at 11th Street. Assume that the that the following design criteria have been developed based on an analysis of local conditions and codes: 1. For design period use the saturation

    period. 2. For population densities use the data given

    in the table.

    3. For residential WW flows use the data given in the table. 4. For commercial and industrial flows (average): a. Commercial 20 m3 /ha . d b. Industrial - 30 m3 /ha . d

  • 5. For institutional flows (average): College - 400 m3 / d (5330 students x 75 L/ student . d)/ (1000 L/ m3 ) 6. For infiltration allowance: a. For residential areas, obtain the peak infiltration values from the fig. (b):

    b. For commercial, industrial, and institutional areas also obtain the peak infiltration values from the fig. (b). However, to take into account that the total length of sewers in these areas will generally be < that in residential areas, use only 50% of the actual area to compute the infiltration allowance.

  • 7. For infiltration allowance Assume steady flow 8. Peaking Factors: a. Residential Use the curve, fig. (c) b. Commercial 1.8 c. Industrial 2.1 d. Institutional (school) 4.0

    Pe

    akin

    g Fa

    cto

    r

    9. Hyd. Design Eq. Manning Eq. , n = 0.0013, Use Fig. 6 -10 (Nomogram) 10. Min. pipe size As per local Bldg. Code, 200 mm 11. Min. velocity 0.75 m/s 12. Min cover As per local Bldg. Code, 200 mm, 2.0 m

  • Solution: 1. Lay out the trunk sewer. Draw a line to represent the proposed sewer [Fig. (a)]. 2. Locate the no. of MHs: (a) Change in direction (b) Change in slope (c) Pipe junctions (d) Upper end of sewers (e) Intervals: 90 120 m or less (As per Code) Identify each MH with a no. In Fig. (a), only MHs at major junctions numbered. In an actual design, intermediate MHs to be located and numbered.

  • a. Column 1 5, Identify lines, Summarize data b. Column 6 13, Obtain cumulative peak domestic flows

    3. Prepare design tables. Comments:

    Table 1

  • c. Column 14 18, Obtain cumulative peak commercial flows d. Column 19 23, Obtain cumulative peak industrial flows

    Table 2

  • e. Column 24 26, Obtain cumulative peak institutional flows f. Column 27 28, Obtain cumulative average and peak flows g. Column 29 32, Obtain infiltration allowance

    h. Column 33 Total Cumulative Peak Design Flow Columns 28 + 32

    Table 3

  • i. Columns 35 38 , Sewer Design, Mannings Eq., n = 0.013 , v > 0.75 m/s j. Columns 39 42, Layout Data Column s 39/40 Ground surface elevations obtained by interpolation from Fig. (a) Column s 41/42 Sewer invert elevations (By Trial and Error from Work Sheet)

    Table 4

  • 0.1

    21

    m

    3/s

    0.0018 m/m

    0.3

    30

    m

    3/s

    0.0009 m/m

  • Line 2-3: q/Q=0.313/0.330 =0.95 d/D=0.86 v/V=1.04

  • WORK SHEET

    (1) Plot ground surface elevations, working backwards (2) Sketch invert and crown (3) Line 1: Locate the invert of the upper end of the pipe Upper Invert Elevation=Ground surface depth of cover pipe wall thickness pipe dia. = 20.00 m - 2.00 m - 0.05 m - 0.45 m =17.5 m Lower Invert Elevation= Upper Invert Elevation-(Slope of sewer)x(Length of sewer) 17.5 m - (0.0018 m/m) x (707 m) =16.23 m Check: Depth of Cover Adequate/ Not adequate ? =19.00 m (16.23 m + 0.45 m + 0.05 m) = 2.27 m OK If Depth of Cover Not adequate / too shallow Two alternatives: (1) Repeat with a lower invert elevation, or (2) A steeper slope

  • Depth of cover

    Wall thickness

    Ground surface

    Inside top Crown

    Inside bottom Invert Bottom

  • Some Other Important Considerations

    (1) When a MH is located at a sewer junction: Outlet sewer invert elevation is fixed by the invert level of the lowest inlet sewer (2) If the pipe size increases: The crowns of the two pipes must be matched at the MH To avoid the backing up of WW in to the smaller pipe. An example: Increase in size from 450 mm 750 mm at MH 2

    450 mm dia. 750 mm dia.

    16.23 m 16.23 m +0.45 m -0.75 m =15.93 m

    15.93 m -(0.0009 m/m)x(707 m) =15.29 m

    Sewer junction

  • Example of a Profile of a Sewer Line

  • Small Bore Sewer System

    They are designed to carry only the liquid part of the domestic sewage generated for off-site treatment or disposal

    Septic Tank or interceptor tank

    Sewer

    Solids are separated at a septic tank or at the aqua-privies before the sewage reaches the sewers

    The advantages: a) The sewer can have less velocity and flowrate

    as it receives only settled wastewater b) Economic as it requires less cost of

    excavation, material and treatment c) Upgradation from on-site treatment system to

    conventional treatment system is easily done d) Maintenance of strict sewer gradients is not

    required as there is no self-cleansing velocity requirement

    Minimum diameter of the sewer pipes is recommended to be 100 mm

  • Small Bore Sewer System

    The small bore sewer system outfall can be any of the following:

    a)The conventional sewer system b) Waste stabilization ponds c) Any other low cost treatment systems followed by fish ponds or land-based disposal with precautions

    Limitations:

    a) Interceptor tank requires periodical cleaning and disposal of solids b) Any illegal connection without any interceptor tank shall ruin the

    system. So, strict vigilance is required.

  • Shallow Sewer System

    These are modification of surface drain with covers and consist of a network of pipework laid in the areas away from the places where heavy sewage loads are expected.

    Pipes are laid in flat gradients following the natural slope of the ground. The minimum depth is 0.4 m

    System contains: a) House connections b) Inspection

    chambers c) Laterals d) Street-collector

    sewers e) Pumping stations

    The laterals are minimum diameter 100 mm

    The street collectors have a minimum diameter of 150 mm

  • Shallow Sewer System

    Suitability of the system:

    1. High density habitats such as slums or squatter settlements ( with population density more than 170 per hectre)

    2. Ground-condition is adverse and on-site disposal is not possible 3. Sewage has to be disposed of and minimum water consumption is 25 lpcd.

    Limitations: a) It is suitable when suitable ground slope is available b) Unless flushed out at peak flowrates, there is a possibility of solids

    deposition if there is not enough ground slope available c) May require frequent cleaning