cdp_puri_unlocked
TRANSCRIPT
-
7/31/2019 CDP_Puri_Unlocked
1/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 1-
P U R I
City Development Plan
2006
Puri Municipality
Housing & UrbanDevelopment Department
City ManagersAssociation Orissa
City
ManagersC M A OAssociationOrissa
C M
A O
-
7/31/2019 CDP_Puri_Unlocked
2/260
-
7/31/2019 CDP_Puri_Unlocked
3/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 0-
Table of Contents
City Development Plan ForewordAcknowledgementExecutive Summary
1. City Development Plan Framework......................................................................... 1
1.1. Introduction..............................................................................................................1
1.2. Urbanization in India................................................................................................. 1
1.2.1. Urban Governance in India a Steps towards Decentralization......................................1
1.3. Urbanisation in Orissa ..............................................................................................2
1.3.1. Level of Urbanisation .......................................................................................................2
1.3.2. Urban Governance............................................................................................................3
1.4. Need for Development of the Urban Sector. ................................................................3
1.5. City Development Plan (CDP).....................................................................................5
1.5.1. The Guiding Principles .....................................................................................................5
1.5.2. Objectives of City Development Plan ...............................................................................7
1.5.3. City Development Planning Process ................................................................................7
2. Puri City Profile................................................................................................... 10
2.1. City Introduction.....................................................................................................10
2.2. Evolution of Puri Town ............................................................................................ 11
2.3. Structure of the Town..............................................................................................13
2.4. Topography of Puri Town.........................................................................................14
2.5. Climate ................................................................................................................... 14
2.6. Location & Linkages ................................................................................................ 15
2.7. Area and Population................................................................................................ 15
2.7.1. Socio-Economic Characteristics .....................................................................................16
2.8. Tourism ..................................................................................................................17
2.9. Development Plan Development Plan & Land use ..................................................... 17
2.10. City Growth Direction............................................................................................18
2.11. Administrative Boundaries and Areas ....................................................................18
2.12. Land Use of Puri Town A General Picture............................................................. 19
2.12.1. Trends of Development (1968 - 2004) .........................................................................20
2.12.2. Statutory Provisions Made For Master Plans/ Development Plans ...........................21
2.12.3. Emerging Issues ...........................................................................................................22
2.13. Puri Today............................................................................................................. 23
-
7/31/2019 CDP_Puri_Unlocked
4/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 1-
3. Temple Of Lord Jagannath ................................................................................... 24
3.1. Evolution of Jagannath Temple Complex .................................................................24
3.1.1. The Architecture of the abode of Lord Jagannath ........................................................24
3.2. The Daily Rituals in the Temple...............................................................................25
3.3. Revenue Generation and Expenditure of Jagannath Temple ..................................... 27
3.3.1. The Shri Jagannath Temple Fund .................................................................................27
3.3.2. The Temple Economy .....................................................................................................28
3.4. The Administration of Shri Jagannath Temple, Puri ................................................. 28
3.5. Temple as a main Source of City Income.................................................................. 30
4. Rath Yatra & the City Life.................................................................................... 31
4.1. Rath Yatra The Grand Car Festival ........................................................................ 31
4.2. Activities Associated With Chariot Construction before Rath Yatra ........................... 32
4.2.1. Collection of wood for Rath building .............................................................................32
4.2.2. Construction of Chariots ................................................................................................32
4.2.3. Activities associated:......................................................................................................33
4.3. Description of the Three Raths................................................................................. 33
4.4. Chronology of Rituals Associated With Rath Yatra.................................................... 34
4.4.1. Snana Purnima...............................................................................................................34
4.4.2. Anavasara Festival ........................................................................................................35
4.4.3. Nibhrita Festival .............................................................................................................35
4.4.4. Anga-Raga or Nava Yavana Festival ............................................................................35
4.4.5. Netrotsava.......................................................................................................................35
4.4.6. Rath Yatra.......................................................................................................................36
4.4.7. Bahuda Yatra (The Return Of Rath) ..............................................................................36
4.4.8. Suna Vesha.....................................................................................................................37
4.5. Special Infrastructural Provisions during Rath Yatra................................................ 38
4.5.1. Social Infrastructure.......................................................................................................38
4.5.2. Health..............................................................................................................................38
4.5.3. Security ...........................................................................................................................39
4.5.4. Public facilities and Arrangements during for Rath Yatra ...........................................40
4.6. Physical Infrastructure ............................................................................................ 40
4.6.1. Solid Waste Management ..............................................................................................40
4.6.2. Electricity ........................................................................................................................41
4.6.3. Water Supply ..................................................................................................................41
4.7. Significance of Rath Yatra in City Development Plan ................................................ 41
5. Puri- The Heritage city......................................................................................... 42
-
7/31/2019 CDP_Puri_Unlocked
5/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 2-
5.1. Regional Setting of Puri as Coastal Cultural Landscape............................................ 42
5.2. Legal Framework of Heritage Development ............................................................... 43
5.3. Institutional Framework ..........................................................................................44
5.4. Identification and Categorization of Heritage Components ........................................ 44
5.5. The Heritage Area.................................................................................................... 46
5.5.1. Criteria for delineation ...................................................................................................46
5.5.2. The Historic Delineation .................................................................................................47
5.5.3. The Ritualistic Delineation .............................................................................................48
5.6. Five Holy Tanks.......................................................................................................49
5.6.1. The Sahi structure........................................................................................................50
5.6.2. Mathas and Ashramas ..................................................................................................50
5.6.3. The Four Ashrams..........................................................................................................53
5.7. Cultural Heritage ....................................................................................................56
5.7.1. Dola Yatra.......................................................................................................................56
5.7.2. Chandan Yatra...............................................................................................................56
5.7.3. Snana Yatra....................................................................................................................56
5.7.4. The Chariots ...................................................................................................................57
5.7.5. Ratha Yatra (Chariot Festival) .......................................................................................58
5.7.6. Navakalevara .................................................................................................................59
5.8. Fairs and Festivals ..................................................................................................60
5.9. New Heritage Facilities ............................................................................................62
5.9.1. Puris Heritage Gateway................................................................................................62
5.10. Issues and Problems of Heritage in Puri ............................................................. 63
6. City Management and Governance ....................................................................... 64
6.1. Institutions ............................................................................................................. 64
6.2. Legal Framework.....................................................................................................64
6.3. Local Governments Framework................................................................................ 64
6.4. City Management ....................................................................................................65
6.5. About Puri Municipality........................................................................................... 66
6.5.1. Organisational Structure................................................................................................66
6.6. Organisastion Structure ..........................................................................................72
6.6.1. Puri Municipality.............................................................................................................72
6.6.2. WSS Institutional framework (Orissa) ...........................................................................73
6.7. Key Issues...............................................................................................................73
7. Urban Environment Infrastructure Services .......................................................... 75
-
7/31/2019 CDP_Puri_Unlocked
6/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 3-
7.1. Urban Environment ................................................................................................. 75
7.2. Solid Waste Management......................................................................................... 75
7.2.1. Solid Waste Management System practice in Puri Municipality..................................75
7.2.2. Quantity and Composition of Wastes............................................................................78
7.2.3. Problems with the Existing Solid Waste Management System....................................79
7.2.4. Performance Indicators ..................................................................................................79
7.2.5. Issues:.............................................................................................................................80
7.3. Preservation of Water Bodies ................................................................................... 80
7.3.1. Issues:.............................................................................................................................81
7.4. Beach Development .................................................................................................81
7.4.1. Issues:.............................................................................................................................82
7.5. City Beautification- Parks and Green Spaces ........................................................... 82
7.5.1. Issues:.............................................................................................................................83
7.6. Public Toilets .......................................................................................................... 83
7.6.1. Issues:.............................................................................................................................84
7.7. Environmental quality............................................................................................. 84
7.7.1. Air Quality.......................................................................................................................84
7.7.2. Water pollution ...............................................................................................................85
7.7.3. Environment in Festive Seasons....................................................................................85
7.7.4. Issues of Concern ...........................................................................................................86
7.8. Diasaster Management............................................................................................ 86
7.8.1. Issues of Concern ...........................................................................................................87
8. Urban Infrastructure Services............................................................................... 88
8.1. Infrastructure services............................................................................................. 88
8.2. Water Supply .......................................................................................................... 88
8.2.1. Existing Infrastructure ...................................................................................................88
8.2.2. Analysis of Current Situation ........................................................................................90
8.2.3. Source .............................................................................................................................90
8.2.4. Demand & Supply ..........................................................................................................91
8.2.5. Revenue collection & Augmentation ..............................................................................93
8.2.6. Performance Indicators ..................................................................................................94
8.2.7. Issues and Problems ......................................................................................................94
8.3. Sewerage System..................................................................................................... 95
8.3.1. Existing Situation ...........................................................................................................95
8.3.2. Performance Indicators ..................................................................................................97
8.4. Storm water Drainage.............................................................................................. 97
-
7/31/2019 CDP_Puri_Unlocked
7/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 4-
8.4.1. Analysis of the Current Situation ..................................................................................97
8.4.2. Performance Indicators ..................................................................................................98
8.4.3. Issues and Problems of Storm water Drainage ............................................................98
8.5. Street Lighting......................................................................................................... 99
8.5.1. Performance Indicators ..................................................................................................99
8.5.2. Issues:.............................................................................................................................99
8.6. Roads & Transport ................................................................................................ 100
8.6.1. Grand Road ................................................................................................................. 101
8.6.2. Performance Indicators ............................................................................................... 103
8.6.3. Issues ........................................................................................................................... 103
8.7. Cost Recovery on Infrastructure Services ............................................................... 103
8.7.1. Water & Sanitation Sector........................................................................................... 104
8.7.2. The challenge in WSS sector....................................................................................... 104
8.7.3. Some of the steps undertaken on Water Sector Reform are: .................................... 105
8.7.4. Some of the steps in proposal for Management improvements initiation include:... 105
8.8. Waste Management ............................................................................................... 106
9. Urban Poverty and Slum Development.................................................................107
9.1. Institutional Framework on Poverty Allevation .......................................................107
9.2. Existing Situation.................................................................................................. 107
9.2.1. Growth Trends in Slums ............................................................................................. 108
9.2.2. Socio-Economic Characteristics .................................................................................. 109
9.2.3. Current Status of Services in Slums........................................................................... 109
9.3. Growth Analysis & Information Gaps ..................................................................... 109
9.4. Slum Improvement Programmes ............................................................................110
9.4.1. National Slum Development Programme (NSDP)........................................................ 111
9.4.2. Valmiki Ambedkar Awas Yojana (VAMBAY).............................................................. 111
9.4.3. Swarna Jayanti Shehri Rojgar Yojna (SJSRY)........................................................... 112
9.4.4. 6.2.4 Development of Women and Children In Urban Areas (DWCUA).................... 112
9.4.5. Issues:.......................................................................................................................... 113
10. Municipal Finance ............................................................................................114
10.1. Legal Framework................................................................................................. 114
10.2. Financial Status at a Glance................................................................................ 114
10.2.1. Revenue Account ....................................................................................................... 115
10.2.2. Revenue Income ........................................................................................................ 116
10.2.3. Own Sources.............................................................................................................. 116
10.3. Revenue Expenditure ..........................................................................................117
-
7/31/2019 CDP_Puri_Unlocked
8/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 5-
10.4. Credit Worthiness................................................................................................ 118
10.4.1. Issues ......................................................................................................................... 119
11. Stakeholders Consultation ................................................................................120
11.1. The Process......................................................................................................... 120
11.1.1. Participation Techniques Used ................................................................................. 120
11.2. Stakeholder Discussions...................................................................................... 123
11.3. Results................................................................................................................ 126
11.4. Key outcomes......................................................................................................127
12. Vision and Strategic Direction...........................................................................128
12.1. The Process......................................................................................................... 128
12.2. VISION 2030 .......................................................................................................128
12.2.1. Strategic directions for the City ................................................................................ 129
12.3. Connected and Accessible City............................................................................. 131
12.3.1. Strategic direction 1.1 ............................................................................................... 132
12.3.2. Strategic direction 1.2 ............................................................................................... 134
12.3.3. Strategic Direction 1.3............................................................................................... 135
12.3.4. Strategic direction 1.4 ............................................................................................... 136
12.3.5. Strategic direction 1.5 ............................................................................................... 137
12.3.6. Strategic direction 1.6 ............................................................................................... 138
12.3.7. Indicators for a Connected and Accessible City ...................................................... 139
12.4. Innovative Heritage Tourism Business City .......................................................... 140
12.4.1. Strategic direction 2.1 ............................................................................................... 141
12.4.2. Strategic direction 2.2 ............................................................................................... 142
12.4.3. Strategic direction 2.3 ............................................................................................... 143
12.4.4. Strategic direction 2.4 ............................................................................................... 144
12.4.5. Indicators for Innovative Heritage Tourism Business City ..................................... 145
12.5. Inclusive and Engaging City................................................................................. 146
12.5.1. Strategic direction 3.1 ............................................................................................... 147
12.5.2. Strategic Direction 3.2............................................................................................... 148
12.5.3. Strategic direction 3.3 ............................................................................................... 149
12.5.4. Strategic direction 3.4 ............................................................................................... 150
12.5.5. Strategic direction 3.5 ............................................................................................... 151
12.5.6. Strategic direction 3.6 ............................................................................................... 152
12.5.7. Strategic direction 3.7 ............................................................................................... 153
12.5.8. Strategic direction 3.8 ............................................................................................... 154
12.5.9. Strategic direction 3.9 ............................................................................................... 155
12.5.10. Indicators for an Inclusive and Engaging City ...................................................... 156
-
7/31/2019 CDP_Puri_Unlocked
9/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 6-
12.6. Environmentally Responsive City ......................................................................... 157
12.6.1. Strategic direction 4.1 ............................................................................................... 158
12.6.2. Strategic direction 4.2 ............................................................................................... 159
12.6.3. Strategic direction 4.3 ............................................................................................... 160
12.6.4. Strategic direction 4.4 ............................................................................................... 161
12.6.5. Strategic direction 4.5 ............................................................................................... 162
12.6.6. Indicators for an Environmentally Responsible City ............................................... 163
13. Projects Identification ......................................................................................164
13.1. The Project Development ..................................................................................... 164
13.2. Population Projection........................................................................................... 164
13.3. Project Identification & Prioritisation.................................................................... 165
13.3.1. Preservation of heritage Project ................................................................................ 168
13.3.2. Projects for Heritage Promotional Infrastructure ..................................................... 171
13.3.3. Heritage-related City Level infrastructure Project ................................................... 175
13.3.4. Heritage-development including Basic Services to Urban Poor Project .................. 179
13.3.5. Tourism Infrastructure Project .................................................................................. 180
13.3.6. Projects for Environment Infrastructure ................................................................... 182
13.3.7. Projects for Strengthening Urban Governance......................................................... 183
14. Financial Plan: Investment Estimate .................................................................186
14.1. The Process......................................................................................................... 186
14.2. Capital Investment Plan....................................................................................... 186
14.2.1. Process....................................................................................................................... 187
14.3. Project Identification............................................................................................ 187
14.4. Strategies............................................................................................................ 187
14.4.1. Strategic Capital Investment .................................................................................... 187
14.4.2. Facility Siting............................................................................................................. 188
14.4.3. Decision Making ........................................................................................................ 188
14.4.4. Plan Funding ............................................................................................................. 188
14.4.5. Agencies..................................................................................................................... 188
14.5. Project Estimates................................................................................................. 190
14.5.1. Sector Wise Estimates............................................................................................... 192
14.5.2. Institution wise Investment Estimates..................................................................... 195
14.6. Strategy for Project Funding ................................................................................197
14.6.1. Broad Reforms Measure ........................................................................................... 197
14.6.2. Holding Tax (Property Tax) ....................................................................................... 197
14.6.3. Accounting and Auditing........................................................................................... 198
14.6.4. Resource Mobilization and Revenue Enhancement................................................. 198
-
7/31/2019 CDP_Puri_Unlocked
10/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 7-
14.6.5. Streamlining and Strengthening of Revenue Base of the Puri Municipality .......... 198
14.6.6. UNDP-Government of India Project on Capacity Building for Decentralised Urban
Governance (2005-2007). ..................................................................................................... 198
14.6.7. Municipal Services Performance Measurement Programme ................................... 199
14.6.8. Urban Environment Management............................................................................. 200
14.6.9. Access of Urban Services to the Poor ....................................................................... 200
15. Reform Agenda and Timeline ............................................................................202
15.1. Agenda for Reform...............................................................................................202
15.2. Agenda for Reform...............................................................................................202
15.2.1. Mandatory Urban Reforms ....................................................................................... 203
15.2.2. Reforms at ULB Level ................................................................................................ 204
15.3. Issues placed for Approval of Govt. of Orissa ........................................................205
15.4. State Preparedness.............................................................................................. 206
15.4.1. Resource Mobilization and Revenue Enhancement................................................. 207
15.4.2. Municipal Services Performance Measurement Programme ................................... 210
15.4.3. New Municipal Law................................................................................................... 211
15.4.4. City Managers Association Orissa .......................................................................... 211
15.4.5. Annual Awards ......................................................................................................... 211
15.4.6. Municipal Accounting ................................................................................................ 211
15.4.7. Reform Agenda.......................................................................................................... 211
16. Implementation Framework..............................................................................216
16.1. Govt. of Orissa Reform Agenda............................................................................. 216
16.2. Heritage Cell .......................................................................................................217
16.3. Puri City Development Council ............................................................................217
16.4. Centre for Excellence........................................................................................... 218
16.5. Project Formulation & Management..................................................................... 218
16.6. State Water Sector Reform...................................................................................219
16.7. Poverty Alleviation and Community Development Programmess............................ 220
16.8. Solid Waste Management..................................................................................... 220
16.9. Local Government HIV/AIDS Programme ............................................................. 221
16.10. City Level Disaster Management Plan................................................................. 221
16.11. Participation in Clean Development Mechanism................................................. 222
16.12. Networking........................................................................................................ 222
16.13. Achieving the vision........................................................................................... 223
16.14. Triple bottom line accountability along with MDG ..............................................223
-
7/31/2019 CDP_Puri_Unlocked
11/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 8-
16.15. The Way Forward .............................................................................................. 224
17. Overview of City Development Plan & Vision 2030.............................................225
17.1. Quality of Life......................................................................................................225
17.2. The Landscape .................................................................................................... 226
17.3. Our Communities................................................................................................ 226
17.4. Getting Around.................................................................................................... 227
17.5. Livelihood............................................................................................................ 227
17.6. Cooperation.........................................................................................................227
-
7/31/2019 CDP_Puri_Unlocked
12/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 0-
City Development Plan Foreword
I am very proud to present Puri City Development Plan. This is a very exciting, visionary
document, which sets the agenda for the Council and the City for the next 20 years. We have
identified our vision Puri as a vibrant sustainable city with unique heritage and rich
legacy after several rounds of consultation with citizens, elected representatives, officials,
tourists, and media etc.
This CDP was prepared after extensive consultation with community and is the Puri
Municipalitys most important strategic document, outlining key issues and objectives for the
city as a whole.
City Development Planensures that its objectives and strategic directions are appropriate to
achieve the vision of our Citys position to address emerging issues and future challenges.
We have many positive attributes and enduring assets which provide us with one of the most
liveable city environments in India. These assets include a vibrant and diverse recreational,
cultural and arts environment; world-class heritage site and sea beaches and our built
heritage.
By 2030 the City is anticipated to grow significantly with the development works under the
JnNURM programmes. This is an exciting opportunity for the City to build on its proven
record as a great place for Heritage, Culture and Tourism.
Puri Municipality is committed to working towards the vision outlined in this document
during its next few years.
I dedicated this document to the people of Puri.
Jai Jagannath
Gourahari Pradhan
Chairman,
Puri Municipality
-
7/31/2019 CDP_Puri_Unlocked
13/260
-
7/31/2019 CDP_Puri_Unlocked
14/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 0-
ExecutiveExecutiveExecutiveExecutive SummarySummarySummarySummary
Introduction
The worlds urban population has been growing rapidly. According to UN estimates; over 60
percent of the world's population will live in cities by 2030. Indias urban population is 285.3million in the year 2001 which is 27.8 percentage of the total population. India hast 35
million plus cities. Among these there are 7 mega cities of which 3 with population above 10
million and 3 with population above 5 million. By the year 2021, it is expected that India will
have the greatest concentration of mega cities in the Asian region.
Urban Governance in India: step towards Decentralization
Municipal Governance in India exists since 1687 with the formation of Madras Municipal
Corporation and then Calcutta and Bombay Municipal Corporation in 1726. In early part of
the nineteenth century, almost all towns in India witnessed some form of municipal
Governance. In the year 1882 Lord Ripons resolution of local self-government laid the
foundation of democratic forms of municipal governance in India. In 1919 Government of
India Act incorporated the need of the resolution and the powers of democratically elected
government were formulated. In 1935 Government of India Act brought local government
under the purview of the state or provincial government and specific powers were given.
In 1992, again a major step towards the decentralization and empowerment of local
governments in India took place with the enactment of 74th Constitutional Amendment Act.
The Amendment calls for greater responsibilities and authorities for local governments by
recognizing it as a third tier government. Some of the important aspects include:
Planning for economic and social development and role of municipal government in
implementation of urban poverty alleviation projects
Increased responsibility for urban planning at the district and metropolitan levels
Greater authority to mobilize and use resources.
Urbanisation in Orissa
In Orissa out of the total population of 36,706,920 as on 1st March, 2001, 31,210,602 live in
rural area and 5,496,318 in urban area. The net addition of population in rural areas during
1991-2001 has been to the tune of 3685399 while in urban area it is 1261785. The
percentage wise decadal growth of population in rural and urban area during the decade is
13.8 and 29.78 percent respectively.
The percentage of urban population to the total population of the states stands at 14.97. The
percentage of urban population to total population in the 1991 Census was 13.33 percent.
Thus, there has been an increase of 1.64 percentage points in the proportion of urban
population in the state during 1991 2001.
-
7/31/2019 CDP_Puri_Unlocked
15/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 1-
Urban Governance in Orissa
The Housing and Urban Development Department is the apex institution of Government of
Orissa responsible for urban sector development in Orissa. The department has three
directorates i.e. Municipal Administration, Public Health Engineering and Town Planning.
The Urban Local Bodies (ULBs) are functioning under the Orissa Municipal Corporation Act
2003 and Orissa Municipal Act 1950. Similarly Development Authorities are functioning
under the Orissa Development Authority Act.
Jawaharlal Nehru National Urban Renewal Mission (Jn NURM)
Considering that state of cities is incompatible with the countrys socio-economic objectives
and Indias growing role in the world economy, the Government of India launched,
Jawaharlal Nehru National Urban Renewal Mission (JnNURM). Aimed at creating
economically productive, efficient, equitable and responsive cities, the Urban Renewal
Mission focuses on (i) improving and augmenting the economic and social infrastructure of
cities; (ii) ensuring basic services to the urban poor including security of tenure at affordable
prices; (iii) initiating wide-ranging urban sector reforms whose primary aim is to eliminate
legal, institutional and financial constraints that have impeded investment in urban
infrastructure and services; and (iv) strengthening municipal governments and their
functioning in accordance with the provisions of the Constitution (seventy-fourth)
Amendment Act, 1992. It provides for public disclosure of local spending decisions together
with earmarking of budgetary allocations for basic services to the poor.
The mission covers two Urban Local Bodies of Orissa namely Bhubaneswar and Puri. As
formulation of City Development Plan (CDP) is a mandatory requirement for accessing Jn
NURM funds, the Housing & Urban Development Department (H&UD) of Govt. of Orissa, as
part of its agenda to address cities development challenges faced by Orissa cities, have
initiated formulation of Puri CDP. In this context, the H&UD Department and Puri
Municipality involved City Managers Association Orissa (CMAO) to prepare the CDP for Puri.
Evolution of Puri Town
Located on the East Coast of India overlooking Bay of Bengal, Puri is located on a 67 km
stretch of sandy beach that extends from the Chilika Laketo the south of Puri town. The
Sun Temple of Konark is located on this beach at a distance of 35km north of Purl.
The town consists of the Temple of Lord Jagannath in its centre with eight quarters (Sahis)
radiating from it. The town colonies were called 'Sahis'. The population of the town composed
mostly priests and people attached to the various activities of the temple. Besides, there are
large numbers ofmathaswhich chiefly cluster round the temple. As the rituals of the temple
and Ratha Yatra became more elaborate, more people started living in Puri. Ordinary people
who have no contribution to rituals have also started living.
The town was originally built on sandy track which began from north and west towards
Cuttack and Ganjam road where the Madhupur or Matia stream is lined with the largest
tanks, Narendra, Mitiani, Markandeya and Siva Ganga. As the tributary of the river Matiani
draining into the sea dried up, it paved the way for the new direction of development of the
town in the southeast.
-
7/31/2019 CDP_Puri_Unlocked
16/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 2-
Location & Linkages
The town of Puri is located almost at the geographic centre of the District, and is bounded by
sea on South east. Mauza Sipaurubilla on West, Mauza Gopinathpur on the North and
Mauza Balukhand on the east surround it. Geographically Puri is located on 19 degree 18
minutes North latitude and 85 degree 51 minutes East longitude.
The Town is directly connected by broad gauge railway line with Khurda, a prominent
Railway junction in S.E. railway. It is about 499 kms. from Calcutta and 468 kms from
Vishakhapatnam. N.H.-203 connects the Town with the Capital city Bhubaneswar which is
about 60 kms. Moreover, this town is also well connected with Satapada via Brahmagiri
through N.H.-203 B and Konark through Marine drive road which comes under N.H.203 A.
The nearest Airport is at Bhubaneswar, which is approx. 60 Kms from the town of Puri.
Area and Population
The administrative jurisdiction of Puri Municipal area spreads over 16.3268 sq kms and
stretches along the sea-shore measuring about 5.00 kms. The entire municipal area is
divided in to 30 wards. As per 2001 census the population of Puri Town was 1,57,610 with a
growth rate of 26% during the period of 1991-2001. The growth rate of the town is less than
that of the state (urban) which is 30.28 % for the period 1991-2001.
Puri Today
Puri today is the forerunner of the Jagannath culture in Orissa, which saw the flowering of
several temples dedicated to Jagannath all over the world. It attracts millions of devotees
through out the year on different occasion.
Puri represents one of the four peethasestablished by Adi Sankaracharya, the other three
being Sringeri in south India, Dwarka in Saurashtra, and Badrinath in the Himalayas.
Chaitanya in 15th - 16th century popularized the worship of lord Jagannath.
The temple dominates the town in every sphere physical, social, cultural and
economic. The town of Puri has evolved around it so that an intricate web of relationship
exists between the temple and the town dwellers. There are many ancient settlements around
the temple precinct that are engaged in the temple activities and are responsible for providing
different materials for management of temple. Elaborate worship services are carried out
throughout the day here.
Puri as a town is more than thousand years old and being a religious town, the town is
based on Vaastu Purusha Mandalaand many meta-physical aspects have been interwoven
in planning of the town. There are as many as24 festivals
each year, the most importantbeing the Rath Yatra or the Car festival in the month June - July.
Puri, known all around the world for its Rath Yatra the cumulating point of all the festivals,
is celebrated in all pomp and grandeur. The annual Rath Yatra of Lord Jagannath is an
event only of its kind, which attracts more than 1 million people. The grand festival is
arranged with combined effort of Orissa Government and Temple Management committee.
Today tourism provides livelihood for almost 80% people of the town. The total economy
of town is depended on the inflow of tourist population. Rath Yatra being the most important
-
7/31/2019 CDP_Puri_Unlocked
17/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 3-
festival is also the one, which has a strong environmental, social, cultural, economic and
spatial impact on the town. The preparation for Rath Yatra starts months before the actual
festival.
The City Development Plan can never be complete without taking into consideration all the
ritualistic aspects of the Grand Festival and without giving a complete profile of all activities
and arrangement that are parts of Rath Yatra
The Architecture of the abode of Lord Jagannath
The temple of Jagannath built on an elevated ground about twenty feet above the level of the
surrounding area, presents an imposing sight and can be seen from miles away. The height
of the main temple or Vimana above the road level is 214. It is a fine specimen of
Pancharatha style of Orissian temple architecture.
The whole temple complex comprises of an area of 10.7 acres. The temple has four gates at
the eastern, southern, western and northern mid-points of the outer wall, known as
SINGHADWARA(Lions Gate), ASHWA DWARA( Horse Gate),VYAGHRA DWARA(Tigers Gate)
and HATHI GATE(Elephants Gate) .they are said to represent Dharma, Jnana, Vairagya and
Aishwarya. In front of the Singhadwara is installed the ARUNA STAMBHA made of single
solid chlorite stone and upon it beautiful Arun Squats in obeisance.
The Daily Rituals in the Temple
The word 'Jagannath' literary means the Lord of the universe. He is also 'Devadhideva' (Lord
of Lords) and Rajadhiraj (King of Kings) He is Purusottama the Supreme Purusa. The daily
and periodical rituals observed and performed in His service and worship since time
immemorial; bear the dignity and grandeur, which a supreme person is entitled to. The
details of rituals have been specified in certain texts in Sanskrit and Oriya. Neeti or ritual
signifies a particular type of religious rite.
Temple as a main Source of City Income
The whole region around Puri is influenced by the temple in various aspects as if the temple
is the most important employer of the town. It is the main market for agricultural products of
the whole region. For the preparation of mahaprasada the temple requires an immense
quantity of agricultural products like rice, ghee, vegetables etc. Several settlements produce
goods mainly for the temple and its pilgrims (pots, paintings etc).
Rath Yatra The Grand Car Festival and City life
The precise time when the Grand festival of Rath Yatra started as part of Jagannath Culture
is not known. It is believed that during the reign of Ananga Bhima dev, when the temple was
renovated and the town was restructured, the concept of Rath Yatra was propagated. The
entire Rath Yatra is a symbolic humanisation of God. All rituals associated with the festival
demonstrate an attempt to bring the God down from His pedestal of glory to a more human
level. This annual festival has now acquired a grand scale and has become the identity
of the Town of Puri.
The Festival is celebrated in the June-July on the second day of the bright fortnight of the
month of Ashadha. People from all across Orissa and from various parts of India come to take
-
7/31/2019 CDP_Puri_Unlocked
18/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 4-
part in this auspicious occasion. Orissa witnesses the inflow of about 7 to 10 lakhs of
pilgrims during this Car Festival.
Significance of Rath Yatra in City Development Plan
The grand festival of Rath Yatra is important not only for the people of Orissa but also a
world famous event. It is a very important festival from the point of any development
programme as almost all levels of Govt. are involved in this event. Attracting more than one
million pilgrims & tourist on the festival and on an average of 5-6 Lakhs people during 10
days of Rath Yatra puts a tremendous pressure on the resources of the town.
City Management and Governance
The responsibility of providing citizens of Puri with basic urban services like water supply,
sewerage, waste management, street lighting, roads etc. are vested with various institutions
such as Puri Municipality, Puri Konark Development Authority, Public Health Engineering
Organisastion, Orissa Water Supply Sewerage Board etc.
The Puri Municipality was established in 1864 as Puri Improvement Trust. Further in the
year 1881 Puri Improvement Trust transformed into Puri Municipality. Post independenceperiod after the enactment of Orissa Municipal Act- 1950 the City administration is vested
with Puri Municipality and it is represented by Chairperson and councilors elected by the
people. The election is being conducted by the State Election Commission. Puri Municipality
has an elected council comprising elected representatives (Councilors) of 30 wards within the
Municipal area. The council is headed by Chairperson who is elected by the councilors. The
council meeting of Municipality takes place every month to decide on issues and Governance.
Duties entrusted to the Puri Municipality were to maintain cleanliness, arrangement for
street light and maintenance of roads etc
Infrastructure services
Development of Infrastructure is an indispensable part of any settlement. Traditional
settlement infrastructure consisted of water sources and storage, waste disposal, road
network, security etc., decentralized to a large extent creating self-sufficient communities.
Modern day urban areas are, on the other hand, heavily dependent on various networks of
infrastructure, a failure or lack of which severely deteriorates the quality of life of the people.
The high densities of the urban area require extensive, adequate infrastructure networks for
the smooth functioning of the city. A lack of adequate road network, wastewater treatment or
solid waste disposal system affects the natural environment through contamination of air,
water and land the basic building blocks of life.
-
7/31/2019 CDP_Puri_Unlocked
19/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 5-
Water Supply System Performance Indicators
SlNo
Parameter / Component Service Level Benchmark Commitment /Remarks
1 Water Supply / Source 127 lpcd 150 lpcd (+15%losses)
Low
2 Treatment Capacity 100% groundwater sourceutilized
100 percent Less
3 Storage 15 % of dailywater demand
33 percent Low
4 Distribution SystemCoverage
55 percent 85 percent Low
5 Non-Revenue Water 33 percent 15 percent High.Uneconomical
6 Cost Recovery 30 percent 85-90 percent
nominal
Significantly low
Underground Sewerage Scheme Performance Indicators
1 Collection SystemCoverage
10 percent 75 percent Very Low
2 STP Functionalitycharacteristics of Cities
StabilizationPond of 5 MLD
Capacity
ActivatedSludge Process
Inadequate andConventional
3 Revenue / O&M cost ratio > 95 percent Uneconomical
Storm Water Drains Performance Indicators
1 Major Drains CatchmentsArea
30 percent 100 percent Inadequate
2 Minor Drains Coverage(Drain Length / RoadLength)
40 percent 90 percent Inadequate
3 Hydraulic ConveyingCapacity of Major drains
Analysis notmade available
100-yearreturn flood, 2-hrs rainfall, 4-
hrs flow
Inundation proneareas. Masterplan required
Streetlight Performance Indicators
1 Spacing between Lamp posts 80 m
-
7/31/2019 CDP_Puri_Unlocked
20/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 6-
Preservation of Water Bodies
The holy city of Puri has six important sacred tanks which is historically and spiritually
important. Many tourists visit the sacred tank and take a dip during festivals and other
occasions.
1. Narendra tank2. Indradradumna tank
3. Markandaya tank4. Swetaganga tank5. Parbati sagar tank6. Chudanga tank.
Besides the above there are as many as sixty two ponds which have got an affiliation to the
community place (Akhadas and Jagaghar). These ponds are used by the locality for their day
to day needs. Musa river passes through Puri town and is in a very bad condition. The ponds,
tanks and the rivers needs restoration and conservation, as their improvement shall lead to
significant improvement of the environment quality.
Beach Development
Puri town has about 5 kms of natural sea beach. The magnificent sea beach at presentattracts considerable number of tourists round the year. Puri sea beach is home to world
famous Sand Art & Sculpture.
The city of Puri is bestowed with river mouth of River Mangala in its South & Nua Nai in its
North. These rivers and sea beach need protection, conservation & development to maintain
their uniqueness as well as to attract tourists for economic growth of the city.
Slums
Most of the slum dwellers of Puri belong to fisherman communities located at Penthakata,
Balinolia Sahi, Baliapanda. There are altogether 46 slum pockets in Puri with a total
population of 47,770. This constitutes almost 25% of the total population. Many of the slum
pockets are inhabited by migrant population who came to Puri in search of employment.
Basic character of the slum pockets are temporary houses, dilapidated structure, poor
ventilation, over crowding, inadequate lighting, absence of sanitation facility and lack of basic
physical and social services.
For improvement of slum condition Puri Municipality has been striving hard to provide basis
amenities. Various poverty alleviation programmes such as NSDP, SJSRY along with old age
pension, Orissa Disability Pension, BPL, Annapurna Aantodaya Anna Yojana and Balika
Samrdhi Yojana are implemented by Puri Municipality. Efforts have also been made by Puri
Municipality to organize the urban poor in to several self help groups to improve their
economic condition.
Regional Setting of Puri as Coastal Cultural Landscape
Considered to be one of the four holy 'Dhams'of India, the historic town of Puri is located on
the Bay of Bengal coast, along a distinctive 67 km stretch of sandy beaches which extends
from the Chilika lake to the south of Puri town to the delta of the Prachiriver to the north.
This stretch of sandy beach is interspersed with a number of ridges, some of which enclose
saltwater lagoons, & the World Heritage Site of Konark is also located along it towards the
north.
-
7/31/2019 CDP_Puri_Unlocked
21/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 7-
Legal Framework of Heritage Development
The heritage component of the Puri city includes monuments, religious places and sacred
sites, buildings of architectural significance or traditional values; history, any other. Various
institutions identified heritage components of the city. The culture department of Govt. of
Orissa has identified 387 Mathas, 4 Ashrams, 10 Dharmasalas and 200 temples. Similarly
in 19986-88, INTACH identified 147 temples, mathas, civic buildings, etc. The District
Gazetteer lists 130 Mathas or Monastic establishments, some believed to date from the
century AD as well as information related to the sacred tank complexes & temple complexes;
the list of 133 Mathas, 22 Jagaghars, 12 Dharamashala, 75 Lodging houses, traditional
Libraries. According to the Archaeological Survey of India (ASI) about 157 unprotected, 2
state protected and 2 ASI protected monuments are located within the city. The heritage
components of the city are owned by both public and private sector.
Public heritages are being owned by Shri Jaganath Temple Administration and
Commissioner of Endowment Govt. of Orissa
Private ownership belongs to Sahis, Aakhadaand Jagagharas, etc.
Moveable Heritage i.e Palm Tree Pothis, Yatri Records of Pandas covering
undivided India & Nepal,
Natural Heritage Natural Sea Beach, Rivers, water bodies
Legal Framework
Ancient Monument and Preservation Act, 1904
Ancient Monuments and Archeological Sites and Remains Act, 1958
The Orissa Ancient Monuments Preservation Act, 1956
Institutional Framework
The maintenance of Heritage monuments are done by the ASI, State Archeology and Temple
Trusts. Where as waste cleaning, street lighting, water supply and other infrastructure to the
heritage sites are being maintained by the Puri Municipality and PHEO. Similarly OrissaTourism Development Corporation, Department of Tourism and Culture of Govt. of Orissa are
the agencies responsible for the promotion and publicity of the Heritage Monuments.
Although the Puri Municipality has no direct role in preservation of heritage but it along with
Puri Konark Development Authority are responsible to restrict un-authorized encroachments,
safety of the building and protection of heritage area.
Five Holy Tanks
There are 5 important tanks in the town; in addition there are a number of smaller ponds
strewn along the periphery of the town. The main tanks are
Narendra tank
Markandeya tank Shwetaganga tank
Indradyumna tank
Parvatisagar tank
These tanks are fed by rainwater as well as groundwater and are therefore perennial sources
of water. The waters are used for bathing, washing, various household requirements in
addition to religious ceremonies and rites. They are an intrinsic part of the life of the town
-
7/31/2019 CDP_Puri_Unlocked
22/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 8-
The Sahi structure
The 'Sahis' of Puri; are characterized by a distinctive settlement pattern & cohesive
communities, open spaces, water harvesting & storage elements, a concentration of
heritage buildings & complexes, streetscapes & street network with 'chhakas' or chowk
intersections & two types of mainly residential narrow streets & mixed use Sahis with
wider streets. These 'Sahls' are Harachandi Sahi & Basel! Sahi on the west; Goudabada
Sahi on the south-west; Bali Sahi and Manikarnika Sahi on the south; Matimandapa
Sahi with Kalaikadevi Sahi on the south-east; Dolamandapa Sahi on the east;
Markandeswar Sahi & Chudang Sahi on the north.
Mathas and Ashramas
Centering round the great temple of Lord Jagannath, many a Matha (Monasteries) grew up
gradually in course of time in this holy town. In the past, many Saints and Sadhus had come
to Puri to have darshan of Lord Jagannath. They came in contact with and influenced the
Gajapati Kings through their philosophical doctrines. The saints and sadhus establishedtheir monasteries on the lands donated to them by the kings and wealthy persons. The Maths
continued preaching their respective doctrines and also performed certain ritual services in
the Jagannath Temple. With endowed properties and lands, the heads of the Maths were able
to maintain their institutions. Lands were donated to the Maths for `Amritmanohi'- the
proceeds thereof were spent in offering `Bhoga' to Lord Jagannath and the `Mahaprasad' thus
obtained, were distributed among the pilgrims, pupils, ascetics, and beggars.
The Four Ashrams
Connected with certain rituals of the temple of Jagannath, there are four Ashrams
(hermitages) in Puri town. These are Angira Ashram, Pandu Ashram, Markandeya Ashram
and Parasara (Ugrasena) Ashram.
Fairs and Festivals
It is popularly said Puri City celebrates thirteen important festivals in twelve months.
However, in reality the city has various festivals all across the year. Importantly all these
festivals are not only linked with the culture and heritage of Orissa but also of India. These
activities are directly and indirectly linked with the cities employment and economic
development potential. It is estimated that around 80% of cities income is linked with
heritage related activities.
-
7/31/2019 CDP_Puri_Unlocked
23/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 9-
Major Fair and Festival
Sl.No. Major Festivals Oriya Month Month Days Visitors
1 DevasnanPurnima
Jyestha Purnima June 1 100000
2 Shree Gundicha(Car Festivals)
Asadha SuklaDwitiya to Dasami
June &July
1 1200000
2 i Shree Gundicha(Car Festivals) Asadha SuklaDwitiya to Dasami June &July 8 1600000
3 Bahuda Asadha SuklaDasami
July 1 800000
4 Suna Vesa Asadha SuklaEkadasi
July 1 1500000
5 DakshinayanYatra
Karkata Sankranti July-Aug 1 80000
6 ParsvaParivartan Yatra
Bahadrab SuklaEkadasi
August 1 200000
7 DebothapanYatra
Kartika SuklaEkadasi
Oct. 1 60000
8 Odhan Sasthi Margasira Sukla
Sasthi
Nov. 1 50000
9 Pusyabhisekh Pausa Purnima Dec. 1 100000
10 Uttarayan Yatra Makar Sankranti Jan. 1 200000
11 Dolo Yatra Falguna SuklaDasami to Purnima
March 5 500000
12 Damanak Yatra Chaitra SuklaChaturdasi
April 1 50000
13 Chandan Yatra Akshay TritiyaBaisakha SuklaTrutiya
May 21 1200000
Municipal Finance
For the purpose of financial assessment, financial data pertaining to the last five years (2000-
01 to 2004-05) were analysed. The Puri Municipality maintains & approves its budget as per
the rules laid down in Orissa Municipal Act 1950. The current accounting system is on a
cash basis and income and expenditure heads are also maintained on a cash basis. All the
expenses towards regular maintenance are treated as revenue expenditure, and all income as
Revenue Receipt.
Financial Status at a Glance
The finances of Puri Municipality have been reviewed for the five-year period ending in FY
2004-05. The items of both receipts and expenditure are classified under revenue income and
expenditure as per their sources and uses. In 2004-05, the revenue income of Puri
Municipality was Rs. 4, 89, 37,777. In absolute terms the revenue expenditure in 2004-05
was Rs. 4, 50, 44,724 and the revenue account surplus in 2004-05 was Rs. 38, 93,053
-
7/31/2019 CDP_Puri_Unlocked
24/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 10-
Performance of Key Financial Indicators
Indicators 2000-
1
2001-
2
2002-
3
2003-
4
2004-
5
Average Benchmark Remarks
Operating Ratio 99.94 100.80 99.40 102.14 92.04 98.86 Less than
1
Satisfactory
Share of Own Sources toTotal Income
15.58 14.87 16.43 24.20 22.76 18.77 More than30-40
percent
NotSatisfactory
Establishment
Expenditure as compare
to total revenue income
46.81 40.3 45.01 45.28 49.79 45.44 Less
than30-40
percent
Not
Satisfactory
Establishment
Expenditure as compare
to total revenue
expenditure
53.89 46.01 40.72 45.06 45.28 46.19 Less
than40 -
45 percent
Not
Satisfactory
Holding Tax Collection
Performance
45% 50% 55% 55% 60% 53% More than
85 percent
Not
Satisfactory
Outstanding Loan to
revenue income
- - - - - - Less than
25 percent
Vision and Strategic Direction
Puri City Development Plan envisages conservation and preservation of its glorious Heritage
with a vision for future reflecting the aspirations of the city and its stakeholders to present a
new story through interaction and debate in deciding
what we want,
what weve done,
and what we have to do to create the sustainable future we want.
Objectives of City Development Plan
The main objective of the CDP is to have a planned growth of the city in the desired direction
and to project Puri as a Global Tourism Business City of Eastern India, guided by a shared
vision for citys development. The CDP makes basic policy choices and provides a flexible
framework for adapting to real conditions over time. The objective includes:
Preserve & Conserve Heritage & Culture
Improve urban services to facilitate development of Heritage and promote tourism
Improve Environmental Conditions
Improve Conditions of Urban Poor
Image Building of the city
Strengthen Preparedness for Citys Disaster Management
The City Development Plan has included: (1) an identification of needs based on a review of
existing plans and policies, interviews with local citizens, business owners and other
-
7/31/2019 CDP_Puri_Unlocked
25/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 11-
stakeholders, and an analysis of existing conditions, including field reconnaissance surveys
of the communitys physical fabric; (2) the preparation of potential alternatives for
consideration; and (3) the development of broad directives and specific recommendations.
Community input has been central to the planning process. Each phase of the process has
been organized around a public meeting to ensure the Plan is well-informed with public
sentiment and opinion.
o Situation Analysis
o Stakeholder Consultations
o Public Forum
o Vision Identification
o Formulation of Goals & Strategies
o City Finance Plan
o Reform Agenda
o Approval by the Council along with Draft MoA
Community input has been central to the planning process. Each phase of the process has
been organized around a public meeting to ensure the Plan is well-informed with publicsentiment and opinion. The meetings included a kick of meeting and four subsequent
workshops with the public. Simeltounsly consultations were held at the policy, legislative and
state levels.
City Development Plan 2030 is Puri Citys primary planning strategy. It sets out what we
believe must happen over the years to achieve our vision for the City of Puri in 2030. Our
vision for the City of Puri to bePuri as a vibrant sustainable city with unique heritage
and rich legacy.
Strategic directions for the City
The strategic directions for the City are outlined under four inter-related themes. Each
strategic direction has a set of objectives to achieve it. These strategic directions are also the
basis of the Citys Corporate Plan, known as City Development Plan, which guides Councils
operations and activities. Issues may be addressed under more than one theme. For example,
transport is addressed under the Connected and Accessible City, Inclusive and Engagement
and Environmentally Responsible City themes. These directions are organized around four
themes:
Theme 1 Connected and accessibility
Theme 2 Environmentally Responsive City
Theme 3 Inclusive and Engaging City
Theme 4 Innovative Heritage Tourism Business City
Achieving the vision
Puri Municipal Council understands that realising the vision will require the cooperation of
all those who have a stake in the City of Puris future. Puri Municipal Council will develop
and maintain strong relationships with Government of Orissa, the business and wider
community, and other key stakeholders to take opportunities to achieve our vision. Puri
Municipal Council will contribute by providing:
-
7/31/2019 CDP_Puri_Unlocked
26/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 12-
o Strong municipal governance;
o Leadership, support and education;
o Delivery of a range of key city services;
o Maintenance of city infrastructure and assets (for example, its heritage, parks,
gardens, roads, and social infrastructure);
o An efficient and effective integrated regulatory environment;
o Marketing of the citys culture, characteristics, advantages and abilities;
o Innovative and integrated strategic and corporate planning;
o Advocacy on the needs of the residential and business communities;
o Networks of businesses, agencies and community groups;
o Partnerships, agreements and alliances with key stakeholders; and
o Sponsorship of events, businesses, festivals and other initiatives.
The Project DevelopmentPuri Municipality and its stakeholders identified Cities vision Puri as a vibrant sustainable
city with unique heritage and rich legacywith healthy, sustainable future and celebrate
its strengths as a vibrant, diverse City of natural beauty nestled around Lord Jagannath
Temple and Seashore of Bay of Bengal and able to achieve our full potential through access
to clean air, safe water and food, shelter, education, satisfying employment, spirituality and
culturally by weigh of social, health, economic and environmental costs, benefits and risks
equally when making decisions. Puri Municipal Council will work with all who have a stake in
the City of Puris future to realize this vision and will simultaneously pursue:
Preservation of Heritage
Improvement of Environmental quality
Economic prosperity
Social equity.
Project Identification & Prioritisation
The projects identification has been done based on the VISION identified by the Municipal
Council through various detailed stakeholders consultation and discussion with various
levels of Govt. Utmost concern is given Puri as Heritage city and all its projects must linked
the development heritage and must benefit poorest of the Poor in the city.
The stakeholders of the city combined its all projects for the Mission to ensure that city comeup as an international Heritage city as desired in its vision. All stakeholders are committed to
implement respective projects in a combined effort. The projects were shared by various
stakeholders including Puri Municipality, Shri Jagannath Temple Trust, Orissa Tourism
Development Corporation, Department of Tourism / Culture / Handicrafts, District
Administration, National Highway Authority and Works Department etc. Similarly, like a
share vision stakeholders have taken responsibility of various projects to overcome financial
and institutional issues of the city. Some of the activities and institution includes:
-
7/31/2019 CDP_Puri_Unlocked
27/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 13-
Institutional Activities in Puri CDP
Areas Institutions
Heritage Preservation and Promotion Shri Jagannath Temple Administration,Archaeological Survey of India, StateArchaeology
Heritage Promotional Infrastructure Puri Municipality
Awareness Campaign Shri Jagannath Temple Administration, Puri
Municipality
City Level Infrastructure Puri Municipality, PHED, Works Departmentetc
Slum Development Puri Municipality
Tourism Infrastructure Orissa Tourism Development Corporation /Department of Tourism
Disaster Management Puri Municipality, District Administration
Promotion of Handicrafts Department of Industries
Project Estimates
The total estimated investment required for providing efficient services to the present
population and future population of Puri city by the year 2031 is about Rs. 1828 Crores at
present prices. The table below presents the identified and the reason that led to
prioritisation of the projects. About 54.65 percent of the total investment has been worked
out for programmes like inner city revitalisation, preservation & conservation of heritage
structures etc. They account for Rs. 999.00 Crores. However the detailed estimates of all
projects would be finalised only after preapration of Detailed Project Rport (DPRs) of each
projects during the mission period.
Summary of sector wise Invest estimate
Sl.No Sector
Projects Total Funding( InCrore)
%
A Heritage Preservation
1 Preservation of ancient temples, Mathas /Monasteries and other Built Heritage
100.005.47
2 Preservation of ancient and sacred WaterBodies
30.001.64
3 Preservation of Community OwnedJagaghara, sacred water bodies andimmovable heritage
18.00
0.98
4 Heritage Museum inside Shri Gundichatemple
5.000.27
5 Upgradation & Development of the HeritageGarden (42acre )of Shri Jagannatha Temple
at Jagannatha Balav Matha
10.00
0.55
6 Development of Parikrama around ShriJaganath Temple and Shri Gundicha Templecomplexes
0.50
0.03
7 Development of Parikrama around ShriGundicha Temple complexes
0.500.03
8 Landscaping around Heritage area 3.00 0.16
9 Development of Swargadwar 2.00 0.11
10 Heritage Awareness IEC 1.00 0.0511 Sea and River front Development 100.00 5.47
B Heritage Promotional Infrastructure
1Security Measures in Shri Jagannath Templeand Heritage Places
4.00
0.22
2 Viewing Tower for Foreign Tourists 5.00 0.27
-
7/31/2019 CDP_Puri_Unlocked
28/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 14-
Sl.No Sector
Projects Total Funding( InCrore)
%
3 Development of Bicycle Lanes and PedestrianNetwork
7.000.38
4 Development of Heritage Circuits 1.00 0.05
5 Divine Discourse Convention Centre 10.00 0.55
6 Construction of Night Shelters (for 10000Pilgrims)
20.001.09
7 Urban Hatt & Amphitheater 10.00 0.55
8 Heritage Gateway & Interpretation Centre 2.00 0.11
9 Street Furniture, City Beautification (signage,traffic lights, landscaping, etc)
1.000.05
10 Provision of Public Toilets near Heritage Sites 3.00 0.16
11 Water Supply 450.00 24.62
12 Major Roads / Bridges / Flyovers 156.00 8.53
13 Inner City Revitalization 60.00 3.28
C City Level Infrastructure
1 Street lighting 10.00 0.55
2 Municipal Roads 50.002.74
3 Subways 40.00
2.194 Sewerage 45.00 2.46
5 Development of Storm Water Drain System 90.00 4.92
6 Social Infrastructure 100.00 5.47
7 Animal Protection 8.00 0.44
8 Slaughterhouse & Ghosala 2.00 0.11
9 Upgradation of Town Hall 2.00 0.11
D Basic Services to Urban Poor 0.00 0.00
1 Housing & Infrastructure 90.00 4.92
2 Livelihood Support Programme 40.00 2.19
3 Economic Opportunity Complex 10.00 0.55
4 Social Amenities (Community Toilets, Halls
etc)
25.00
1.37E Environment Infrastructure
1 Green Infrastructure 5.00 0.27
2 Environment Monitoring Infrastructure 10.00 0.55
3 Solid Waste Management 35.001.91
F Tourism Infrastructure 0.00 0.00
1 Dev. of Bus & Truck Terminus 25.00 1.37
2 Development of Parking Lots 20.00 1.09
3 Development of Heritage (Urban) Villages 22.00 1.20
4 Beach Cleaning Mechanism 5.00 0.27
5 Tourism Information Centre 15.00 0.82
6 Eco Friendly Tourist Vehicle 8.00 0.44
7 Capacity Building & Database Dev.Information System
2.000.11
8 Water Sports & Maritime Aquarium &Museum
120.006.56
9 International Convention Centre 30.00 1.64
G Urban Governance 0.00 0.00
1 e-Governance 3.00 0.16
2 Capacity Building 3.00 0.16
3 Disaster Management Mechanism 4.00 0.22
4 Research & Development 10.00 0.55
-
7/31/2019 CDP_Puri_Unlocked
29/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 15-
Heritage
Preservation,
14.77
Urban
Governance,
1.09
Heritage
Promotional
Infrastructure,
39.88
City Level
Infrastructure,
18.98
Basic Serices
to Urban Poor,
9.03
Tourism
Infrastructure,
13.51
Environment
Infrastructure,
2.74
Sl.No Sector
Projects Total Funding( InCrore)
%
Total 1828.00 100.00
Sector Wise Estimates
59.88% of the total identified investment is proposed in the Heritage Promotional
Infrastructure sector. Some of the projects includes towards up-gradation, Inner City
Revitalization, new construction, widening and strengthening works, bridges, flyovers, traffic
management systems and junction improvements. Among the total investments 14.97%
accounts for Heritage Preservation. Some of the projects includes in this category are
Preservation of ancient temples, Mathas / Monasteries and other Built Heritage, Preservation
of ancient and sacred Water Bodies, Heritage Museum inside Shri Gundicha temple,
Upgradation & Development of the Heritage Garden (42acre )of Shri Jagannath Temple at
Jagannath Balav Matha, Development of Parikrama around Shri Jaganath Temple
complexes, Development of Parikrama around Shri Gundicha Temple complexes,
Landscaping around Heritage area, Development of Swargadwar, Heritage Awareness IEC
and Sea and River front Development.
Sector wise InvestmentsCode Sector Sector Total %
A Heritage Preservation 270.00 14.77
B Heritage Promotional Infrastructure 729.00 39.88
C City Level Infrastructure 347.00 18.98
D Basic Serices to Urban Poor 165.00 9.03
E Environment Infrastructure 50.00 2.74
F Tourism Infrastructure 247.00 13.51
G Urban Governance 20.00 1.09
(A-G) Total 1828.00 100.00
Similalry 18.98%
investments accounts for
City level infrastructure.
9.03% of the total
investment is proposed for
Basic Services for Urban
Poor, involving urban poor
and the slums
development. Tourism
Infrastructes counts for
13.51% and Environemnt
Infrastructure for 2.74%.
Institution wise Investment Estimates
The total estimated investment required for providing efficient services to the present
population and future population of Puri city by the year 2031 is about Rs. 1828 Crores at
present prices. The table below presents the identified Institution wise Investment Estimates
of the projects. Of the total invest JnNURM share is 80%, Govt. of Orissa 8.33%, Puri
Municipality 2.63%, Jagannath Temple Administration 1.09%, OTDC / Dept. Tourism /
Culture 0.71%, PHEO 2.71%, National Highway 0.22%, Works Dept. 0.91%, Industries Dept.
-
7/31/2019 CDP_Puri_Unlocked
30/260
Puri Municipality Puri City Development Plan
City Managers Association Orissa - 16-
Year wise capital utilisastion
26.5
310.4
357.9
374.6
347.3
274.65
136.65
0
50
100
150
200
250
300
350
400
2006-
07
2007-
08
2008-
09
2009-
10
2010-
11
2011-
12
2012-
13
Year
Funds
0.05% and Peoples Public Private Patnership (PPPP-P4) will have share of 3.35%. P4 will
basically substitute the stae Govt and certain institions investments in total share i.e Water
Sports & Maritime Aquarium & Museum, International Convention Centre etc.
Institution wise Investments
Funding Source Investment inCrore %
JNNURM 1462.40 80.00GOO 152.20 8.33
Puri Municipality 48.10 2.63
Jagannath Temple Trust 20.00 1.09
OTDC / Dept. Tourism / Culture 13.00 0.71
PHED 49.50 2.71
National Highway 4.00 0.22
Works Dept. 16.60 0.91
Industries Dept. 1.00 0.05
PPPP 61.20 3.35
Total Funding 1828.00 100.00
Agency wise Capital Investment Plan 2006-2013
Agency 06-07 07-08 08-09 09-10 10-11 11-12 12-13 Total
Puri
Municipality 9.5 97.4 114.9 92.9 84.1 62.35 19.85 481
JagannathTemple Trust 5.5 39.5 55 36 22.5 26 15.5 200
OTDC / Dept.Tourism /Culture 0 18.5 27 31.7 28.2 12.3 12.3 130
PHED 6 60 60 110 110 104 45 495
NationalHighway 0 10 10 10 10 0 0 40
Works Dept. 5 30 20 31 30 30 20 166
IndustriesDept. 0 1.5 2.5 2.5 2.5 1 0 10
PPPP 0.5 53.5 68.5 60.5 60 39 24 306
Total 26 256.9 289.4 314.1 287.3 235.65 112.65 1828
The Capital Investment
Plan (CIP) has been
prepared for a period of 7
years (FY 2006-07 to FY
2012-13). The phasing has
been worked out based on
the priorities assigned by
the stakeholders and
preparedness of the
service providing agencies
to prepare the DPR and
initiate implementation of
the proposals. The chart
besides provides an
insight into the year-wise utilization of the capital during the Plan period.
-