  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    1/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    25thJuly 2013

    Comprehensive Disaster Management Programme II

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    2/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP II PROJECT SUMMARY

    Country Bangladesh

    Title of the Project Comprehensive Disaster Management Programme 2010-2014(CDMP-II)

    Project ID 00073416

    Implementing Agency Ministry of Disaster Management and Relief

    Co-Implementing Partners 13 Departments of 12 Ministries

    Universities and Training InstitutesDisaster Management Committees

    Sub-Implementing Agencies

    National Project Director Mohammad Abdul Qayyum, Additional Secretary, GoB

    Project Period January 2010 - December 2014

    Date of Approval 24 May 2010

    Project Budget US$ 76.16 million

    Funded By GoB, DFID, EU, Norway, Sida, AusAID, UNDP

    Contact Person Dr. Puji Pujiono, Project Manager

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    3/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    A TWO-PHASED PROGRAMME TO SUPPORT GOVERNMENT VISION

    GOAL

    Reduce Bangladeshs vulnerability to adverse naturalevents through technical assistance in risk reduction and

    comprehensive disaster management activities.OBJECTIVES

    To strengthen the capacity of the disaster management

    system to reduce unacceptable risk and improve response

    and recovery management at all levels.

    Comprehensive Disaster Management Programme

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    4/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP II OUTCOME AREAS

    1Professionalising

    DM System6Community

    levelCCA

    4Preparedness& Response

    2

    Rural RiskReduction

    3

    Urban RiskReduction

    Disaster and

    Climate

    Resilient

    Bangladesh5

    Mainstreaming

    MODMRDDM

    PARTNERDEPTS / MINS

    DMCsLOC. ADMINS

    MSUUNDP

    UNIVERSITIESTRG INSTS.

    NGOSCIVIL SOCIETY

    PRIVATE SECTORS

    DELIVERYMECHANISMS

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    5/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP II: EXPECTED KEY RESULTS

    Established and fully operational the DM Regulatory Framework

    Strengthened capacities of MoDMR and DDM

    DRR & CCA integration in the partner ministries and departments

    Improved functioning of Disaster Management Committees at all levels

    Expanded CPP in all coastal districts

    Developed earthquake maps of 9 cities for risk-integrated urban planning

    Established Urban volunteers corps

    Expanded DMIC at national and in all districts & upazilas

    Increased allocation of Govt. budget on DRR&CCA

    Reduced risks through structural and non- structural interventions

    Improved resilience of the vulnerable communities and sectors both at rural and urban

    settings

    Significant reduction of death, vulnerabilities and loss from future disasters

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    6/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP IISUMMARY PROGRESS [2010-June 2013]

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    7/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    KEY ACHIEVEMENTSTechnical backstopping and policy support to MoDMR

    SAARC PoA 2014-2020

    7 rules - national and local level DMCs and response groups, involvementof NGOs and individuals in DM, Requisition of resources, services, building,

    transport etc., Constitution of Disaster Management Fund, & Relief Depot:,

    Award, Recognition, and Honorarium, for outstanding contribution in DM

    Post HFA/MDG/SD BD country position

    SOD/DM Act/Shelter Guideline translation

    Professionalizing DM system Networks with 26 (of targeted 43) training & educational

    institutions; DM integrated curricula for class III-XII;

    supplementary learning books; Bachelor, DM Degree &

    diploma courses introduced by DU, BRUR, PSTU, NSU, BUP,

    etc.

    10 e-learning centres, book support to 24 institutions

    Promoting Bangladesh as a global leader in DM

    AAGP, AMCDRR, GPDRR.

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    8/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    PROMOTING BD AS A GLOBAL LEADER IN DM

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    9/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Mainstreaming DRR&CCA Across Government Depts.

    50 DTWs, 38 RWH, 1 underground water reservoir installed (DPHE)

    378 officers and 1680 farmers trained; 4012 demos in 52 Upazilas; controlroom established (DAE)

    1,415 urban response agencies trained; 18,977 urban volunteer formed (FSCD)

    6 training courses organized; CC knowledge network restarted, sectoral

    guidelines (DoE)

    >200 officers trained; DRR&CCA department action plan drafted (DoWA)

    DRR &CCA content incorporated in textbooks for Class III-X (NCTB)

    Officers trained; maps produced; equipment procured (GSB)

    Weather modeling started (BMD)

    Prediction modeling started, data collection and processing ongoing (FFWC)

    Training ongoing; model villages are being developed (DLS, DOF, DAE)

    Non-structural vulnerability guideline; National Crisis Management Centre

    established; field hospitals under process (DGHS)

    CDMP II KEY ACHIEVEMENTS cont.

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    10/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP II KEY ACHIEVEMENTS cont.Early Warning Preparedness

    Interactive Voice Recording (IVR) systemwith six mobile operators

    District and Upazila DMC Chair and

    Member Secretary mobile phone database

    for bulk SMS with emergency management

    instruction

    Introduced flash flood early warning with

    FFWC

    Ongoing model improvement to increase

    flood early warning lead time from 3 to 5

    days

    CPP expanded to 5 new Upazilas1,200 radio sets to 14 licensed community

    radio broadcasters

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    11/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP II KEY ACHIEVEMENTS cont.

    Emergency Response Preparedness

    Institutionalised countrywide twice-a-year school drillsconducted drills in last IDDR and NDPD

    480 teachers, 1,200 Upazila education officers and

    school instructors trained on school safety drill

    Emergency preparedness support to 37,000 families

    2,000 improved parachutes with BAF for emergency

    relief airdrop

    2 airport contingency plans with staff preparedness

    training

    DMIC network established and expanded in all 64

    DRROs, 485 PIO offices

    DMIC is being transferred to DDMNDRCC established and fully operational

    Regular SitReps during disaster onset

    Regular updating incident database

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    12/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Training

    1,510 of targeted 2,000 construction professionals

    trained on safety construction

    1,415 response professionals

    19,000 of targeted 30,000 urban volunteers

    6,544 CPP volunteers

    60 volunteers for landslide community early warning

    200+ PIOs, 8 batches on ArcGIS

    1,000 Upazila DMC members

    CDMP II KEY ACHIEVEMENTS

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    13/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CDMP II KEY ACHIEVEMENTS cont.

    Assessment and research to generate knowledge and

    scenarios

    Completed 4 studies on drought, non-farm

    livelihoods, drought, climate parameters and

    inundation mapping;

    Produced 1,700 union fact sheets

    Ongoing expansion of earthquake risk and

    vulnerability mapping from 3 to 9 cities

    Building database for Dhaka and Chittagong

    ongoing Risk integrated Mymensingh City Development

    Strategic Planning ongoing

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    14/31

    LDRRF AT A GLANCE

    (in thousand USD)

    STATUS as of June 13Covered 34 districts, 78Upazilas

    and 261 Unions

    Completed 42 projects and 869

    schemes

    Ongoing 193 projects and 1050

    schemes

    PRINCIPLES

    LDRRF is a pilot, must be exemplaryRisks as the cornerstone of

    interventions

    Covering all the targeted districts

    Empowering the local administration

    Pursuing quality and accountabilityTimely and systematic

    Inflow Total Year-wise Projected Expenditure (US$ in million)

    Year RRR URR Total

    ProDoc: $ 13.5m

    Norway: $ 15.6m

    Australia: $ 8 m

    2010-12 12.0 2.5 14.50

    2013 10.00 4.00 14.00

    2014 5.10 1.50 6.60

    Total: $37.1m 2010-2015 27.10 8.00 35.10

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    15/31

    Details of Projects with LDRRF SupportRural Schemes

    Interventions Completed Ongoing

    Road cum

    Embankment

    11 118

    Killa - 27

    Reverse Osmosis

    Plant

    - 3

    Plinth Raising 109 1668

    Improved Stove - 9

    Disaster Resilient

    Houses

    20 209

    Tube-Well(D.T.W &S.T.W)

    101 672

    Sanitary Latrine 480 1618

    Pond Excavation - 19

    Pond Re-Excavation - 178

    Canal Re-excavation - 36

    Urban Schemes

    Interventions Unit Progress(%)

    Strom Sewer 26.1km 60

    U drain, box culvert,

    canal excavation

    672m 12

    DRH 360 60

    Rural Schemes

    Interventions Completed Ongoing

    Seed Money for IGA - 15

    Comp. projects - 35

    PSF 80 -

    RWH 4 -

    Water Distribution 60 -Retaining Wall - 13

    Repair of Cyc. Shltr. - 13

    Recharge Well - 4

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    16/31

    CDMP/stakeholder roles during Mahasen

    6,500 CDMP trained CPP volunteers in 5 Upazilas deployed

    62,500calls to the activated IVR 10 rounds of bulk SMS from DDM to DMC officials

    14editions of DMIC SitReps and 1 update

    Rapid assessment of stakeholders

    preparedness:

    UDMCs scored high in the performance

    UDMCs are not aware enough of their SOD-

    sanctioned roles & responsibilities

    UDMCs need to prepare contingency plans

    with required budgets

    CPP volunteers are enthusiastic but need

    token incentives to keep up spirit (mobile

    phone bill, quality gear, more training)

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    17/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    RANA PLAZA: THE LESSONSCDMP investment payoff:

    Deployment and coordination of trained rescuers from FSCDand allied professionals

    Trained urban volunteers (around 600)

    Use of equipment

    Appropriate search-and-rescuemethodologies

    Policy and awareness imperatives:

    Implementation of Building Code

    Retrofitting capacity improvement

    Fire and building safety awareness

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    18/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    CUMULATIVE FINANCIAL PROGRESSAS OF JUNE 2013

    S/L Outcome Areas Cum.

    Budget

    2010 2011 2012 2013 as

    of May

    Cum.

    Exp.

    % of

    Total

    1 Professionalizing the DM 2,210 109 242 315 200 866 39%

    2 Rural Risk Reduction 25,416 260 848 5,525 3,208 9,841 39%

    3 Urban Risk Reduction 14,221 22 359 1,859 1,109 3,349 24%

    4 Response Preparedness 6,206 448 1,186 1,072 310 3,016 49%

    5 Mainstreaming DRR/CCA 10,765 104 2,600 2,353 217 5,273 49%

    6 Community-Level CCA 1,750 152 271 185 83 691 39%

    7 Technical Assistance 10,112 1,085 1,504 1,557 607 4,753 47%

    GMS 4,527 508 41 863 - 1,412 31%

    Total Donor Fund75,207 2,688 7,050 13,729 5,735 29,202 39%

    GOB 961 40 79 88 34 241 25%

    GRAND TOTAL76,168 2,728 7,129 13,817 5,769 29,442 39%

    Figure in Thousand USD

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    19/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    GOVERNANCE SYSTEM

    Comprehensive Disaster Management Programme (CDMP II)

    Ministry of Disaster Management & Relief

    PROJECT GOVERNANCE

    Project Steering Committee- Multi-year work plan approval, Policy,

    strategic guidance, periodic progress review

    Project Board

    - Quarterly workplan and progress review

    NPD and UNDP - Annual workplan

    approval

    Outcome GOVERNANCE

    Coordination Committee

    Technical Advisory Groups

    Technical Working Group (TWG)

    under each departments

    LDRRF GOVERNANCE

    LDRRF Technical Review Committee

    LDRRF Approval Committee

    LDRRF Project Progress Review Committee

    Project Implementation Committee

    Monitoring Committee at upazila level

    M&E GOVERNANCE

    MoDMR

    UNDP

    National Project Director

    International Project Manager

    International Operation Manager

    Outcome leads

    Specialists/ Analysts

    M&E Unit

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    20/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    ORGANISATIONAL STRUCTURE

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    ICT SPRural Risk Rd.SP

    Urban RiskRd. SP

    ResponsePrep. SP

    Org Dev SP CCA SP ( M&E SP (

    Cap. Bld.

    Analyst (

    Field Prog.

    Mon. Ass. (1)

    Prog. Assistant

    CRA Analyst

    Field Prog. &

    Mon. Ass. (5)

    Field Prog. &

    Mon. Ass. (1)

    KnowledgeMgt. SP

    LDRRF SP

    Intermns CO. O

    DMIC Unit

    (2 Ass.)

    GIS Analyst Adaptation

    Analyst

    Prog. AssistantProg. Assistant

    Proj Manager

    DNPD

    )

    Operations Manager

    Prog. Assistant

    = Direct supervision by

    PM/LEAD ADVISER

    Comm. SP

    Advocacy & Com.

    Officer

    Field Prog &

    Mon. Ass.

    (1)

    Learning Dev.SP

    Engineers

    (4)

    Outcome: 1 1 3 5

    4

    4 4 6 All22 & partly 3 All

    NPD

    = Overall guidance

    UNDP Cluster

    (Assurance function)

    Monitoring

    Officer (Vacant)

    DP

    Dev. Partners

    Programme Associate

    Short-term

    consultants as

    per need

    Consultants for

    special surveys

    MoDMR

    Secretary DMR

    RRMC RBM

    Monitoring Assistance

    UNDP

    CD & DCD (P)

    = Specialists supervision of

    subordinate staff

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    21/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    STEERING COMMITTEE

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    1.To provide strategic guidance and policy

    direction, including up-stream linkageswith policy directions and developments.

    2.To coordinate and resolve any inter

    ministerial or cross-sectoral issues.

    3.To periodically review the overall project

    progress and provide guidance on major

    operational issues, including tripartite

    reviews.

    4.To establish and maintain linkages with

    key institutions under BCCSAP.

    Secretary, MoDMR (Chair)

    Joint Secretary (DM), MoDMR DG, Department Disaster Management

    GOB: Finance Div. Planning Commission, ERD, IMED

    Implementing Partner Ministry

    UNDP

    Development partners European Commission (EC)

    UK Aid (DFID)

    Swedish International Development Cooperation

    Agency (Sida)

    Norwegian Embassy

    Australian Aid (AUSAID

    CSOs

    Observers by invitation

    NPD, CDMP II (Member Secretary)

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    22/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    PROJECT COORDINATION COMMITTEE

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    To review & input AWP

    To review QWP

    Coordinate Focal Points.

    To review progress and resolve

    issues

    To address broader coordination

    To supervise knowledge and

    learning

    To regularly update on progress

    and key issues.

    NPD, CDMP II (Chair) Program Manager, UNDP

    Development Partners (as and when required)

    Focal Points (as and when required)

    Project Manager, CDMP II (Secretary)

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    23/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    LDRRF COMMITTEES

    Approval Committee

    Technical Committee

    Review Committee

    Upazilla Monitoring Team

    PIC

    NPD (Chair)

    UNDP Ast. Country Director

    DG, DDM

    CSO

    Proj Mgr (Member Secretary)

    Proj Mgr (Chair)

    Director, DDM

    UNDP Prog. Mgr CSO

    LDRRF Mgr (Member Secretary)

    Joint Secretary (DM)

    Chief Planning

    Director DDM

    LDRRF Mgr (Member Secretary)

    UP Chairman

    UP Members

    Social Elites

    Comprehensive Disaster Management Programme (CDMP II)

    Ministry of Disaster Management & Relief

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    24/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    QUALITY ASSURANCE MECHANISM

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Technical Advisory Groups (TAG) in partner Depts

    DG

    PD

    Project Leader

    CDMP Focal Point

    Task Technical Advisory Group (TAG) for specific purposes (projects

    and studies/researches)

    Experts

    Project personnel

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    25/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    OVERSIGHT MECHANISMS

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    1. GOBFAPADIMED

    ERD

    2. MoDMR:Monthly Coord. Meeting

    DPA

    Divisional bi-monthly CoordinationMeeting

    1. UNDP Annual Review

    Quarterly reports

    Missions

    2. Dev. Partners Audits

    Missions

    Joint

    Medium Term Review

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    26/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Planning FlowProject Document - TAPP

    Annual Work Plan

    Multiyear Budget

    Years Budget

    Quarterly Work Plan Quarters Budget

    Outcome Plan

    Activity Plan

    Outcome Budget

    Activity Budget

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    27/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Delivery Mechanism Implementing Departments/Ministries Implementing institutions (Universities, NGOs, etc.)

    LDDRF

    contracts City Corporations/Municipalities

    Upazilla DMCs

    Union DMCs

    NGOs Outsourcing to specialised agencies/Institutions

    Collaborations (UN Projects, I/NGOs)

    Instruments

    -MOUs

    -LOAs

    -Financial Agreements

    -Outsourcing under the PPR

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    28/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Procurement Modalities National Execution (GOB/NPD under the PPR)

    Grants

    Contracts

    Operational

    Direct Country Office Support (UNDP)

    Capital investment / equipment Larger technical procurements

    + Personnel recruitment

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    29/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    www.cdmp.org.bdCDMP II

    1. Deliberately structured installments2. Exercising frequent visits by CDMP

    3. Engaging Upazila officials through phone/emails

    4. Encouraging partners visits/engagement

    5. Activating local level oversight mechanisms with / throughthe PICs and DMCs (participatory M&E)

    6. Implementing activity/process tracking and result

    monitoring framework

    7. Evaluating outcome of completed projects

    OVERSIGHT, M & E

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    30/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    EXTERNAL REVIEWS ROM-EU (2011)

    ICAI-British Parliament (2011)

    UNDP Regional Technical Reviews (2010, 2011,

    2012)

    Mid Term Review (2012)

    FAPAD Annual Audit (2010, 2011, 2012)

    DFID Annual Reviews2011, 2013

    CDMP Impact Assessment - ongoing

  • 7/23/2019 CDMP II-Parliamentary Standing Committee Meeting

    31/31

    Comprehensive Disaster Management Programme Phase (CDMP II)

    Ministry of Disaster Management & Relief

    Thank you

    For more information contact:Comprehensive Disaster Management Programme (CDMP II)

    United Nations Development Programme (UNDP)

    Disaster Management & Relief Bhaban (6th Floor)

    92-93 Mohakhali C/A, Dhaka-1212, Bangladesh

    Tel: (+88 02) 989 0937, 882 1255 Website: www.cdmp.org.bd