cave ins and subpart q

Upload: andrea-ramos-taping

Post on 05-Apr-2018

223 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Cave Ins and Subpart Q

    1/63

    1

    Chapter 10

    Subparts P through U and Related

    Safety Practices

  • 7/31/2019 Cave Ins and Subpart Q

    2/63

    2

    Major Topics

    Subpart P: Excavations

    Subpart Q: Concrete and Masonry Construction

    Subpart R: Steel Erection

    Subpart S: Tunnels, Shafts, Caissons,Cofferdams and Compressed Air

    Subpart T: Demolition

    Subpart U: Blasting and Use of Explosives

  • 7/31/2019 Cave Ins and Subpart Q

    3/63

    3

    Subpart P

    Excavations.

    Cave-ins.

    Other Hazards.It contains the

    Following sections:

    1926.6501926.651

    1926.652

  • 7/31/2019 Cave Ins and Subpart Q

    4/63

    4

    Excavations and Related Safety Practices

    Every year in the United States, about 200construction workers engaged in trenchwork die. The most common hazards of

    excavation accidents include cave-ins,contact with energized power sources orconductors, toxic atmospheres, loose

    rocks, rising water and the collapse ofnearby structures or equipment.

  • 7/31/2019 Cave Ins and Subpart Q

    5/63

    5

    Excavations: General Requirements andRelated Safety Practices

    An excavation is a man-made cut, cavity ortrench in the ground made by removing earth.

    The most common form of excavation in

    construction is the trench, which is a narrowexcavation that is deeper than it is wide and isno wider than 15 feet.

    Subpart P applies to open excavations exceptsurface mines and certain house foundationexcavations.

  • 7/31/2019 Cave Ins and Subpart Q

    6/63

    6

    Planning Requirements

    Traffic in the vicinity of the excavation.

    Proximity of structures or equipment to the excavation.

    Soil factors.

    Surface and ground water. Weather.

  • 7/31/2019 Cave Ins and Subpart Q

    7/63

    7

    On-Site Inspections

    OSHA requires daily inspection by a competent personto detect possible problems or hazards in excavationsand in the vicinity of excavations.

    Inspections must also be made following heavy rains orany man-made activities that might de-stabilize theexcavation.

  • 7/31/2019 Cave Ins and Subpart Q

    8/63

    8

    Cave-Ins: General Requirements andRelated Safety Practices

    A cave-in is a collapse of a geologic formation,mine or structure.

    Excavation cave-ins are a major source of

    fatalities within the construction industry eachyear.

  • 7/31/2019 Cave Ins and Subpart Q

    9/63

    9

    Support Systems

    OSHA requires that workers in excavations be protectedby one of the following methods:

    Sloping and benching the sides of the excavation;

    Supporting the sides of the excavation;

    Placing a shield between the side of the excavationand the work area in the excavation.

  • 7/31/2019 Cave Ins and Subpart Q

    10/63

    10

    Sloping of the sides of an excavation no less than 1.5(horizontal) :1 (Vertical) helps to ensure worker safety in

    excavation up to 20feet deep.

  • 7/31/2019 Cave Ins and Subpart Q

    11/63

    11

    Excavations dug in this configurations are called benched.

  • 7/31/2019 Cave Ins and Subpart Q

    12/63

    12

    Trench shield can be used toprotect workers from cave-ins.

  • 7/31/2019 Cave Ins and Subpart Q

    13/63

    13

    Specific Safety Precautions

    Construction companies that undertake excavation workare required to provide support systems, such asshoring, bracing, or underpinning, to adequately stabilizestructures in the vicinity of an excavation.

    These structures include walls, buildings, towers,sidewalks and pavements.

  • 7/31/2019 Cave Ins and Subpart Q

    14/63

    14

    Installation and Removal ofProtective Systems

    Installing protective systems can be just as dangerousas working in an excavation. Consequently, OSHArequires the following safe practices when installingprotective systems:

    Make sure that all structural members of the supportsystem are properly and securely connected.

    Make sure that no structural component of a supportsystem is overloaded.

    When temporary removal of a structural component ofa support system is necessary, first install another totake its place.

    Coordinate the installation of support systems closely

    with excavation work.

  • 7/31/2019 Cave Ins and Subpart Q

    15/63

    15

    Materials and Equipment OSHA has established the following safe practices and

    requirements:

    Companies must use the materials and equipmentthat are free of defects.

    Manufactured materials and equipment must be usedin strict accordance with the manufacturerspecifications.

    Immediately remove from service any material orequipment that is deemed to be unsafe by acompetent person.

    Materials or equipment removed form service cannotbe returned to service without inspection by aregistered professional engineer.

  • 7/31/2019 Cave Ins and Subpart Q

    16/63

    16

    Other Hazards: Requirements andRelated Safety Practices

    Fall, Load and Equipment Hazards.

    Water Accumulation Hazards.

    Hazardous or Toxic Atmospheres.

    Access and Egress Hazards.

  • 7/31/2019 Cave Ins and Subpart Q

    17/63

    17

    Fall, Load and Equipment Hazards OSHAs requirements and safe practices with regards to

    falls, loads and equipment are as follows:

    Construct retaining devices around excavations or keep allequipment and loads back form the edge at least 2 feet.

    Provide protective barricades or other equivalent means to

    guard against falling rock, soil or other materials.

    Do not allow people to work on sloped or benchedexcavation walls at levels above other workers in theexcavation.

    Provide warning systems that alert workers andoperators of equipment that they are coming too nearthe edge of the excavation.

  • 7/31/2019 Cave Ins and Subpart Q

    18/63

    18

    Warning systems should be used to alert workers when they are

    approaching an excavation

  • 7/31/2019 Cave Ins and Subpart Q

    19/63

    19

    Water Accumulation Hazards

    Workers should not be allowed to perform their duties inan excavation in which water is accumulating, unless theappropriate precautions have been taken to remove thewater.

    These precautions are as follows:

    Properly functioning water-removal equipment.

    Excavations that are subject to runoff.

  • 7/31/2019 Cave Ins and Subpart Q

    20/63

    20

    Hazardous or Toxic Atmospheres

    Before allowing a worker to enter an excavation that is 4feet or more deep or that could reasonably be expectedto have a hazardous atmosphere, a competent personmust test the atmosphere.

    If a hazardous condition is determined to exist, workers

    must use the appropriate respiratory protection devicesand ventilation of the excavation must be undertaken.

    Emergency rescue equipment must be made readilyavailable if a hazardous atmosphere might exist or

    develop in the excavation. There must be an observer present at all times when the

    worker is in the confined space.

  • 7/31/2019 Cave Ins and Subpart Q

    21/63

  • 7/31/2019 Cave Ins and Subpart Q

    22/63

    22

    What's wrong with thispicture?

  • 7/31/2019 Cave Ins and Subpart Q

    23/63

    23

    What's wrong with thispicture?

    He is working alone at the bottom ofalmost a 22 ft. deep vertical trench.

    Excavated soil has been stockpiled at the

    very edge of the trench, adding to the

    pressure on the trench walls.

    Neither a ramp nor ladder has been

    provided for the worker to escape.

    Finally there is nothing to protect him

    from a cave-in; no sloping back of the

    trench walls, no shoring of the walls, andno shielding of the worker.

  • 7/31/2019 Cave Ins and Subpart Q

    24/63

    24

    CASE STUDY:

    "OSHA Proposes $210,000 in PenaltiesFollowing Trenching Fatality"

    OSHA Regional News (Birmingham, AL )

    February 22, 2006 OSHA has issued citations against a utility contractor

    and proposed penalties totaling $210,000, following theinvestigation of a fatal accident at a Clay, Ala.,

    construction site. OSHA began an inspection at theSteeple Chase subdivision after being notified that aworker was trapped in a collapsed trench. Rescueattempts failed.

  • 7/31/2019 Cave Ins and Subpart Q

    25/63

    25

    Agency investigators determined that employees had beenworking in an 18-foot-deep trench with excavated soil piled10 feet high at the edge of the trench walls. The company

    received four willful citations, with proposed penalties of$196,000, for allowing workers to ride on an excavator bucketand then jump into trenches; failing to provide employeeswith adequate means to enter and exit trenches; placing

    excavated materials within two feet of trench walls;inadequately shoring and sloping trench walls, and failing toconduct daily inspections and remove employees from thesite when hazardous conditions were observed.

    OSHA also issued four serious citations, with proposedpenalties of $14,000, for allowing employees to work undersuspended loads of sewer pipes and for failing to trainemployees and provide them with hard hats, drinking waterand bathroom facilities.

  • 7/31/2019 Cave Ins and Subpart Q

    26/63

    26

    Subpart Q

    Subpart Q covers the requirements andrelated safety practices for concreteconstruction and masonry work.

    It contains the following sections: 1926.700 to 1926.706

  • 7/31/2019 Cave Ins and Subpart Q

    27/63

    27

    General Requirements and RelatedSafety Practices for Concrete Work

    OSHA specifies requirements and safe practices thatapply to all types of concrete work. The generalrequirements are:

    Before any type of load can be placed on a concretestructure or any concrete portion of a structure anindividual qualified in the field of structural design mustdetermine that the structure or the portion of a structurebeing used can support the load.

    Workers involved in tying or placing reinforcing steel at

    heights of 6 feet or more above any working surface mustwear the appropriate fall protection devices.

    When reinforcing strands are tensioned at the job site,workers should not be allowed behind the jack during thetensioning process.

  • 7/31/2019 Cave Ins and Subpart Q

    28/63

    28

    Concrete buckets must be equipped with safety latchesto prevent accidental or premature dumping. Workersshould not be allowed to work underneath concrete

    buckets when they are being lifted or elevated. Protruding reinforcing bars must be guarded to prevent

    impalement if a worker falls on one.

  • 7/31/2019 Cave Ins and Subpart Q

    29/63

    29

    Concrete Equipment and Tools

    General requirements for the concrete equipment andtools are summarized as:

    Equipment such as saws, mixers, screens and pumpsmust be properly locked out and tagged out before

    workers are allowed to perform routine maintenanceduties on them.

    Concrete mixers with loading skip of 1 cubic yard orlarger must be equipped with a mechanical means of

    clearing the skip of material. Electrically powered, rotating trowel machines must

    be equipped with an automatic shutoff switch thatactivates if the operator releases the handles.

  • 7/31/2019 Cave Ins and Subpart Q

    30/63

    30

    Concrete pumping systems that use pipes fordischarging the concrete must be equipped with pipesupports that are rated for at least 100 percentoverload.

    Workers who use a pneumatic hose to apply cement,sand or water mixture must wear appropriate headand face protection.

    Masonry saws must be equipped with a guard over

    the blade and a method for retaining blade fragments.

    Concrete Equipment and Tools

  • 7/31/2019 Cave Ins and Subpart Q

    31/63

    31

    Cast-In-Place Concrete: Requirementsand Related Safety Practices

    The term cast-in-place meansthat the concrete is poured(cast) at the job site (in place)into forms that are constructedor assembled at the site.

    It involves the followingactivities:

    1. Building or assemblingforms

    2. Placing rebar into theforms.

    3. Pouring concrete

    4. Treating the surface of theconcrete.

  • 7/31/2019 Cave Ins and Subpart Q

    32/63

    32

    Requirements and safety practices forcast-in-place concrete

    Forms must be designed and built to withstand allvertical and lateral loads that might be applied to them.

    Shoring equipment must be inspected before erection toensure that it meets the specifications set forth in the

    engineering drawings.

    Reinforcing bars for vertical components of the structuremust be properly supported to prevent overturning orcollapse.

    Forms and shores must remain in place until it has beendetermined by a standard test approved by the ASTMthat the concrete has cured sufficiently to support its ownweight and that of any superimposed loads

  • 7/31/2019 Cave Ins and Subpart Q

    33/63

    33

    Pre-Cast Concrete: Requirements andRelated Safety Practices

    Pre-cast concrete is poured in forms at a location off theconstruction.

  • 7/31/2019 Cave Ins and Subpart Q

    34/63

    34

    Pre-Cast Concrete: Requirements andRelated Safety Practices

    The most common uses of pre cast concreteconstruction bridges, parking garages, commercialbuildings and multi-story residential building

    Pre-cast concrete components must be properly

    supported until they are permanently attached to preventoverturning or collapse.

    Lifting mechanisms must be capable of supporting atleast five times the anticipated load.

    Workers should not be allowed to work under pre-castcomponents that are in the process of being erected.

  • 7/31/2019 Cave Ins and Subpart Q

    35/63

    35

    Lift-Slab Concrete: Requirements andRelated Safety Practices

    Lift-slab concrete operations involve fabricating pre-castconcrete components with lifting hardware embedded inthem.

    Jacks and other equipment used to lift the slabs must be

    clearly marked to show the manufacturers specificationsfor lift capacity.

    Jacking and lifting equipment must be able to support atleast 2 times the anticipated load and must not be

    used beyond their rated capacity. The maximum number of lifting units in a slab is 14, but

    the preferred number is the minimum necessary to allowthe operator to keep the slab level to within prescribed

    tolerances.

  • 7/31/2019 Cave Ins and Subpart Q

    36/63

    36

    Masonry Construction: Requirementsand Related Safety Practices

    Masonry involves the use of bricks orblocks as the primary building material.

    Stability is an issue with masonryconstruction. Consequently masonry walls

    more than 8 feet in height must besupported to prevent collapse.

    Bracing used to support a masonry wallunder construction must remain in placeuntil permanent supporting elements of

    the structure are in place. In addition tobracing, a limited access zone must beestablished wherever a masonry wall isbeing constructed.

  • 7/31/2019 Cave Ins and Subpart Q

    37/63

    37

    Subpart R

    Subpart R covers the requirements andrelated safety practices for structural steelconstruction and assembly.

    It contains the following sections: 1926.750 to 1926.761

  • 7/31/2019 Cave Ins and Subpart Q

    38/63

    38

    Structural Steel Construction

    Steel construction is a specialized field within thebroader field of construction. It has its own uniquehazards, which result in an average of 35 deaths and2300 lost time injuries every year.

    The hazards most commonly associated with steelerection work include working under loads; hoisting,landing, and placing decking and steel joists; columnstability; double connections; and falling to lower levels.

    -

  • 7/31/2019 Cave Ins and Subpart Q

    39/63

    39

    , -Plan, and Construction Sequence:Requirements and Related Safety

    Practices

    Steel erection cannot begin until the concrete used infootings has either: a) cured to at least 75% of its

    intended minimum compressive design strength; or b)has cured sufficiently to support the loads that will beimposed during erection.

    There must also be sufficient room for operation.

    There must be adequate roads into and through theconstruction site

  • 7/31/2019 Cave Ins and Subpart Q

    40/63

    40

    Hoisting and Rigging: Requirementsand Related Safety Practices

    Cranes used in steel erection must undergo a thoroughvisual inspection before each shift to ensure that allcontrols and mechanisms are in proper and safe workingorder.

    The capacity of must have a safety factor of at least 5:1.

  • 7/31/2019 Cave Ins and Subpart Q

    41/63

    41

    Column Anchorage: Requirements andRelated Safety Practices

    OSHAs SteelErection Standardrequired that allcolumns be

    anchored by aminimum of fouranchor bolts.

  • 7/31/2019 Cave Ins and Subpart Q

    42/63

    42

    Beams and Columns: Requirementsand Related Safety Practices

    When beams are being secured to columns, they mustnot be released from the hoisting lines until secured byat least two bolts per connection.

    One of the more hazardous tasks for steel erectionworkers is making double connections.

  • 7/31/2019 Cave Ins and Subpart Q

    43/63

    43

    Falling Object: Requirements andRelated Safety Practices

    Objects falling from a higherlevel and injuring employeesworking at a lower level is aconcern in steel erection.

    Consequently, the SteelErection Standard requiresthat all materials, equipment,

    and tools used by workerswho are aloft be properlysecured against falling.

  • 7/31/2019 Cave Ins and Subpart Q

    44/63

    44

    Fall Protection: Requirements andRelated Safety Practices

    Falls from higher to lower levels represent the greatesthazard in steel erection.

    Consequently, OSHA requires fall protection foremployees working at heights greater than 15 feet.

  • 7/31/2019 Cave Ins and Subpart Q

    45/63

    45

    Training: Requirements and RelatedSafety Practices

    OSHA requires that personnel who work in steel erectionhave the necessary training.

    This training must include

    reorganization of fall hazards;

    use and proper operation of fall protection system;

    correct procedures for erecting, maintaining,disassembling, and inspecting fall protectionsystems;

    procedures for preventing falls through holes andother openings;

    S b t S

  • 7/31/2019 Cave Ins and Subpart Q

    46/63

    46

    Subpart S Subpart S covers the construction of

    underground tunnels, shafts, chambers and

    passageways.

    It contains the following sections: 1926.800 to 1926.804

    Underground Construction:

  • 7/31/2019 Cave Ins and Subpart Q

    47/63

    47

    Underground Construction:Requirements and Related Safety

    Practices Underground construction has its own set of unique

    hazard.

    The principal hazards are: safety instruction,

    access and egress,

    check-in and check-out procedures,

    hazardous classifications,

    gassy operations,

    air monitoring, ventilation,

    illumination,

    fire control,

    hot work, and

    emergencies.

    Safety Instruction

  • 7/31/2019 Cave Ins and Subpart Q

    48/63

    48

    Safety Instruction Workers who will be involved in underground construction

    operations must first receive the proper training.

    Training must focus on

    Air monitoring

    Ventilation

    Communication

    Flood control

    Equipment: mechanical and personal protective

    Explosives: fire prevention, and fire protection

    Emergency procedures: check-in, check-out, and evacuationplans.

    Access and Egress Employers are required to provide safe access and egress to

    underground construction sites.

    Unauthorized entry must be both prohibited and prevented.

  • 7/31/2019 Cave Ins and Subpart Q

    49/63

    49

    Check In and Check Out Procedures

    Employers must use an appropriate check-in and check-outprocedure to keep track of employees who work

    underground.

    Gassy Operations

    In underground construction work there are potentially gassy

    operations and confirmed gassy operations. Safetyprecautions for gassy operations include the following as aminimum:

    Ventilation.

    Prohibiting the use of diesel

    equipment

    Prohibiting smoking or other forms

    of ignition in or near the work area.

    Maintaining a fire watch if any

    hot work is to be performed.

  • 7/31/2019 Cave Ins and Subpart Q

    50/63

    50

    Air Monitoring

    A competent person must be assigned to conduct air-monitoring courses to ensure that the ventilation available is

    sufficient and to record measurements of potentiallyhazardous gasses.

    Ventilation

    Contractors are required to provide an adequate supply offresh air to all underground sites.

    Illumination

    Contractors are required to provide proper illumination in allunderground sites. When explosives are to be handledunderground, a distance of 50 feet must be maintainedbetween any heading and the lighting.

  • 7/31/2019 Cave Ins and Subpart Q

    51/63

    51

    Fire Prevention and Control

    Open flames and fires are prohibited in undergroundconstruction sites. Smoking should be discouraged in

    underground sites.

    Hot Work

    When performing hot work in underground,

    noncombustible barriers must be installed in or over ashaft.

    Emergencies

    Rescue teams or services must be provided atconstruction sites in which 25 or more employees workunderground. A designated person must be available tocall for emergency assistance and to maintain an accuratehead count of those working underground.

    C i R i d R l d

  • 7/31/2019 Cave Ins and Subpart Q

    52/63

    52

    Caissons: Requirements and RelatedSafety Practices

    A Caisson is an airtight andwatertight structure in whichconstruction work can bedone underground or

    underwater. If a caisson is to be

    suspended at any time whenwork is being done in it and

    the bottom of the excavationis 9 feet or more, a shieldmust be erected to protectemployees.

    C ff d R i d

  • 7/31/2019 Cave Ins and Subpart Q

    53/63

    53

    Cofferdams: Requirements andRelated Safety Practices

    A Cofferdam is a watertightenclosure that can be pumpeddry so that constructionactivities can take place.

    A means must provide toprevent flooding if overtoppingof the cofferdam by highwaters is possible.

    At least two means of rapidexit must be provided withcofferdams.

    C d Ai R i t d

  • 7/31/2019 Cave Ins and Subpart Q

    54/63

    54

    Compressed Air: Requirements andRelated Safety Practices

    Any time work is beingdone undercompressed air, theremust be at least one

    competent personreadily available who isfamiliar with all aspectsof working in these

    conditions.

    Fig: Tunneling inCompressed air without

    a shield.

    S b t T

  • 7/31/2019 Cave Ins and Subpart Q

    55/63

    55

    Subpart T

    Subpart T covers the requirements and related safetypractices for demolition.

    It contains the following section: 1926.850 to 1926.860

  • 7/31/2019 Cave Ins and Subpart Q

    56/63

    56

    Preparatory Operations

    A critical first step before undertaking a demolitionoperation is to obtain a comprehensive engineeringsurvey of the structure that is to be demolished. Thissurvey helps to guard against premature or unplannedcollapse of the structure in question.

    Once the engineering survey has been completed, allutilities (gas, electricity and other energy sources) aredisconnected and turned off.

    Openings in floors and walls are covered or sealed.

    If combustible materials are present in the structure,firefighting equipment must be available in nearby to thesite.

  • 7/31/2019 Cave Ins and Subpart Q

    57/63

    57

    Subpart U

    It covers the requirements for blasting and the use ofexplosives on construction sites.

    It contains the following 1926.900 to 1926.914

    Bl ti G l P i i d

  • 7/31/2019 Cave Ins and Subpart Q

    58/63

    58

    Blasting: General Provisions andRelated Safety Practices

    All types of heat and spark producing devices areprohibited near explosives.

    Explosives that are not being used must be stored in alocked magazine.

    All explosives must be counted for at all times. Blasting operations conducted above ground should be

    completed during daylight hours.

    Blasting: General Provisions and

  • 7/31/2019 Cave Ins and Subpart Q

    59/63

    59

    Blasting: General Provisions andRelated Safety Practices

    No person is allowed to handle explosives while underthe influence of drugs.

    Warning signs should be prominently displayed to warnagainst the use of radio transmitters within 1000 feet ofthe blasting site

    Other Req irements in Blasting

  • 7/31/2019 Cave Ins and Subpart Q

    60/63

    60

    Other Requirements in BlastingOperations

    Before beginning the

    preparations for blasting,contractors should postwarning signs that explainthe code of blasting

    signals around the blastingarea. Initiating devicesmay not be stored in thesame area with otherexplosives.

    Other Requirements in Blasting

  • 7/31/2019 Cave Ins and Subpart Q

    61/63

    61

    Other Requirements in BlastingOperations

    Initiating devices may not be stored in the same areawith other explosives.

    There is to be no smoking within 50 feet of explosivesand detonators.

    Other Requirements in Blasting

  • 7/31/2019 Cave Ins and Subpart Q

    62/63

    62

    Other Requirements in BlastingOperations

    Avoid the use of electric blasting caps in any area whereextraneous electrical charges might be present thatcould cause an unplanned detonation.

    Before initiating detonation, the blaster in charge makes

    sure that all extra explosives, detonators, and otherextraneous materials have been removed from the blastarea and properly stored.

    No attempt can be made to remove an unexploded

    charge. It must be re-primed and re-detonated, orwashed out with water.

    R f

  • 7/31/2019 Cave Ins and Subpart Q

    63/63

    References

    http://www.osha.gov/SLTC/etools/construction/images/rebar_1.jpg

    http://mattgray.org/trips/2004/weminuche/photos/ore_bucket_sky.jpg

    http://www.buildstore.co.uk/materials/images/masonryconstructionheader.jpg

    http://www.cdc.gov/eLCOSH/docs/d0500/d000533/3.jpg

    http://cache.viewimages.com/xc/3333144.jpg?v=1&c=ViewImages&k=2&d=4DAA13B573E1BD2FD9DF0C71D94B64A8A55A1E4F32AD3138

    http://www.geoconsol.com/photos/DFW%20Tunnel%20&%20Pipe.jpg

    http://kshitija.files.wordpress.com/2006/07/entry_fig3.gif

    http://www.funnyphotos.net.au/images/building-demolition1.jpg

    http://mining.mosaicprojects.net/images/millward_blasting.gif http://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htm

    http://www.jobsitesupply.com/img/cast-in-place_detail.jpg

    David L. Geotsch Construction Safety and Health

    http://www.osha.gov/SLTC/etools/construction/images/rebar_1.jpghttp://mattgray.org/trips/2004/weminuche/photos/ore_bucket_sky.jpghttp://www.buildstore.co.uk/materials/images/masonryconstructionheader.jpghttp://www.buildstore.co.uk/materials/images/masonryconstructionheader.jpghttp://www.cdc.gov/eLCOSH/docs/d0500/d000533/3.jpghttp://cache.viewimages.com/xc/3333144.jpg?v=1&c=ViewImages&k=2&d=4DAA13B573E1BD2FD9DF0C71D94B64A8A55A1E4F32AD3138http://cache.viewimages.com/xc/3333144.jpg?v=1&c=ViewImages&k=2&d=4DAA13B573E1BD2FD9DF0C71D94B64A8A55A1E4F32AD3138http://www.geoconsol.com/photos/DFW%20Tunnel%20&%20Pipe.jpghttp://kshitija.files.wordpress.com/2006/07/entry_fig3.gifhttp://www.funnyphotos.net.au/images/building-demolition1.jpghttp://mining.mosaicprojects.net/images/millward_blasting.gifhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://www.jobsitesupply.com/img/cast-in-place_detail.jpghttp://www.jobsitesupply.com/img/cast-in-place_detail.jpghttp://www.jobsitesupply.com/img/cast-in-place_detail.jpghttp://www.jobsitesupply.com/img/cast-in-place_detail.jpghttp://www.jobsitesupply.com/img/cast-in-place_detail.jpghttp://www.jobsitesupply.com/img/cast-in-place_detail.jpghttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://web.dcp.ufl.edu/hinze/OSHA-Subparts-U-Z.htmhttp://mining.mosaicprojects.net/images/millward_blasting.gifhttp://www.funnyphotos.net.au/images/building-demolition1.jpghttp://www.funnyphotos.net.au/images/building-demolition1.jpghttp://www.funnyphotos.net.au/images/building-demolition1.jpghttp://kshitija.files.wordpress.com/2006/07/entry_fig3.gifhttp://www.geoconsol.com/photos/DFW%20Tunnel%20&%20Pipe.jpghttp://cache.viewimages.com/xc/3333144.jpg?v=1&c=ViewImages&k=2&d=4DAA13B573E1BD2FD9DF0C71D94B64A8A55A1E4F32AD3138http://cache.viewimages.com/xc/3333144.jpg?v=1&c=ViewImages&k=2&d=4DAA13B573E1BD2FD9DF0C71D94B64A8A55A1E4F32AD3138http://www.cdc.gov/eLCOSH/docs/d0500/d000533/3.jpghttp://www.buildstore.co.uk/materials/images/masonryconstructionheader.jpghttp://www.buildstore.co.uk/materials/images/masonryconstructionheader.jpghttp://mattgray.org/trips/2004/weminuche/photos/ore_bucket_sky.jpghttp://www.osha.gov/SLTC/etools/construction/images/rebar_1.jpg