case study 8 maintenance of boilers[1]

Upload: -

Post on 06-Apr-2018

217 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    1/55

    Operation & Maintenance

    of Boilers

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    2/55

    OPERATION, MAINTENANCEOF BOILERS

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    3/55

    Would like to touch upon someimportant factors

    Operation Tuning combustion is the most important

    aspect

    Maintenance Preventive Predictive

    RLA

    Care of boilers

    Performance monitoring Trouble shooting Reducing tube failures

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    4/55

    General Boiler Operation

    Design & power production have becomesophisticated

    Basic operating principles still apply

    Combustion safety & proper steam /water cooling are essential Before firing no lingering combustible material

    Purge is essential 25% of max air flow

    Once combustion established air/fuel ratio tuning

    Other parameters to be checked & maintained

    General safety considerations Pressure parts failure remain major concern

    CO2 NOx &SOx are to be optimised

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    5/55

    Boiler Operation

    Pre-commissioning operation

    Initial start-up operation first Commissioning operation

    Alkali boil out

    Chemical cleaning

    Steam boiling

    Safety valve floating

    Trial runs Stabilization operation Regular operation

    Cold start-up

    Warm start-up

    Hot start-up

    Shutting down Normal

    Emergency

    Operation for guarantee run

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    6/55

    Boiler Operation (Cont)

    Marginal difference in operationbased on type of boiler Natural circulation

    Once through Fluidized bed

    Bubbling bed

    Circulating

    Pressurized

    Chemical recovery

    Stoker fired

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    7/55

    Key operation functions

    Burner adjustments Fuel air ratio

    Carbon burn out

    Pollutant optimization

    Excess air adjustments Fuel conditions

    Pressure & temperature liquid fuel

    Particle size & primary air

    Feed water & boiler water conditioning Soot blower operation

    Primary air to secondary air ratio

    Wind-box settings

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    8/55

    Typical operator walk down check list

    Look for valve & valve packing leak

    Discoloration, hotspots on casing / ductwork or vapor leak

    Open all inspection door & check for slag accumulation

    Listen for tube leak

    Check for unusual noises, overheating & adequatelubrication on all motors

    Look for leaks in gage glasses & water columns

    Check that no soot blowers are stuck & no leak

    Tilting tangential for uniformity in all corners

    Check secondary air damper setting At firing floor check for fuel leak coal, oil & gas

    Check all vertical coal pipe for plugging or over heating

    Inspect ash pit for bridging

    Check level of water in ash hopper& bottom seal trough

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    9/55

    Typical operator walk down check list(Cont)

    At the pulverizers check for Gear case oil temp, flow & temperature

    Excessive spillage or malfunction of pyrite system

    Indications for mill fire

    Unusual noise

    Coal leaks

    At air-heaters check Soot blower leakage

    Drive motor, support & guide bearing lubrication &cooling water

    Cleanliness of air side through observation port

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    10/55

    COMBUSTION AIR REGIMETUNING

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    11/55

    COMBUSTION AIR REGIME TUNINGHINTS

    Indian high ash coals result in highprimary air requirements -primaryCombustion Dilution

    Sec. Air distribution at requiredelevation is very important

    Avoid / reduce all unwanted sec. Air at

    any location And divert them to other needy

    elevation.

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    12/55

    COMBUSTION AIR REGIME TUNINGACTION

    Keep mill air flow just above settling velocity.

    Do pitot traverse to check primary air flow

    Keep reducing primary air - settling start

    Slight furnace disturbance

    Increase by primary air 1-2 t/hr

    Keep total air flow - 20% excess air @ eco out

    Close all fuel air dampers if VM less than 20 - 22% Lookflame front - decide for higher VM coal

    Keep wind box pr. 100 - 150 mm - better distributionAcross elevation.

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    13/55

    COMBUSTION AIR REGIME TUNINGACTION - Cont

    Wall Blower Optimisation

    Change in SH spray without change inother parameters indicates furnacedeposit increase

    SH spray increase above a particularlevel (to be determined for each boiler)operate wall blowers

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    14/55

    COMBUSTION AIR REGIME TUNINGOTHER TIPS

    Check % VM in Coal by Hcl Leaching Once ina Month If VM > 20% and Flame Front AwayFrom Nozzle

    FC/VM Ratio Vs % FA Comb. Is Very Good for500 Mw Unit - Establish This for Your Plant

    +50 Retention for Bottom Ash

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    15/55

    COMBUSTION AIR REGIME TUNINGOTHER TIPS Cont

    Wind Box Damper Setting for Completion ofCombustion and Bottom Ash Collection

    Increase LRSB Operation for Fouling Type

    Ash in Coal And Exit Gas Temp. Control Change in SH Spray Pattern Due to Change

    in Radiation Heat Transfer Because ofChange Combustion Completion Elevation.

    Check PC Analysis on Rieve Distribution.Chart / Roslin-Rammler Chart

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    16/55

    Energy Conservation

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    17/55

    Energy Economic DecesionMaking

    Life Cycle Costing

    Using the Payback Period Method

    Using the Life Cycle Costing

    The Time Value of Money

    Investment Decesion Making

    Making Decession for Alternate Investments

    Depreciation, Taxes & Tax Credit

    Computer Analysis

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    18/55

    boiler T

    482.8 Mkcal/hr 420 Mkcal/hr 180.6 Mkcal/hr 172 Mkcal/hr

    200 MW

    120.7 t/h

    4000 kcal/kg

    87.0 %

    37.4%

    35.6 %

    43.0 %2000 kcal/kwhr

    2299 kcal/kwhr

    2414 kcal/kwhr

    auxpower 10 MW

    PLANT EFFICIENCY & HEAT RATE

    210

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    19/55

    Improved Availability/ Reliability

    Reducing boiler outage occurrencespressure part failures & other causes(increasing MTBF)

    Reducing forced outage duration - onaccount of boiler pressure partfailures + other causes (reducingMTTR)

    Reducing occurrences of partial outage -(restricted loading) of boilers

    Reducing the duration of operation underpartial outage mode

    E C ti M i

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    20/55

    Energy Conservation Measures in

    Boilers Improved Boiler Efficiency by Exit Gas

    Temperature Reduction

    Introduction of Variable Speed Drive Motors

    SCAPH in By-Pass Duct of FD Fan Air Duct Low Excess Air Burners for Coal, Oil & Gas

    Higher Pressure Cycle for Power Generation

    On Line Water Chemistry Analyzers toReduce Continuous Blow Down

    Micro Processor Controls to EnsureConsistency in Operating Parameter

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    21/55

    Energy Conservation Measures inBoilers (Cont..)

    Two Out of Three Logic for ReducingSpurious Trips

    Measures to Reduce Tube Failures

    Acoustic Tube Leak Detection System toReduce MTTR

    Retrofits for Availability & PLFImprovements

    Intelligent Soot Blowing

    Boiler Performance Optimization On-Line(Under Trial &error)

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    22/55

    Energy Conservation Measures inBoilers (Cont..)

    High Energy Arc Igniters in Place of LDOIgniters

    FBC & CFBC Technology for High Ash

    Indian Coals & Difficult to Burn Fuels Combined Cycles & Co-generation Plants

    Integrated Coal Gassification Combined

    Cycle Plant ( Under Trial ) Once Through Super Critical Boiler for

    Large Power Plants

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    23/55

    Energy Conservation Measures inBoilers (Cont..)

    For Old and Aged Boilers Improvements in Availability/ Reliability

    Lost Capacity Restoration

    Predictive Maintenance of Pressure Parts Residual Life Assessment of Pressure Parts

    Thermal Performance Testing & Evaluation

    Tuning of Combustion & Optimization

    State-of-the-art Up-Grades Micro Processor Controls

    Introduction Steam Traps Where ever Possible

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    24/55

    WHERE RLA FIGURES IN

    LIFE EXTENSION PROGRAMME (LEP)

    PLANT CONDITION PERFORMANCE R L ADATA COLLECTION EVALUATION

    PROBLEM AREAIDENTIFICATION

    VARIOUS PROPOSALSFOR LIFE EXTENSION

    F DONE IN PHASEDE FULL OUTEDBA

    CK

    PERFORMANCE EVALUATION

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    25/55

    Why RLA Study Ageing of boilers consequent to creep /

    fatigue stresses in pressure parts of boiler

    Material degradation

    due to corrosion,erosion and oxidation

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    26/55

    Why RLA Study (Cont)

    Operation of boiler at elevatedtemperatures more than design limit

    Variations in coal quality

    Deviations in Water Chemistry

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    27/55

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    28/55

    Scanning Electron Micro Scope

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    29/55

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    30/55

    Creep Cavity Level ClassificationSystem Proposed by Wedel & Neubauer

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    31/55

    Run Repair Replace

    Evaluates For All Phases

    RLA

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    32/55

    Trouble Shooting

    Studying the problem, analyzing theproblem, finding the root cause of

    the problem, taking the corrective &preventive action and takingpreventive to avoid recurrences infuture by pro - active action.

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    33/55

    Boiler Tube Failures

    Boiler Tube Failures - main cause offorced outages in electric utility steamgenerating boilers

    Single tube Failure in a 500 MW Rs. 5to 6 Crores (replacement powercharges for 3-4 days to repair) besides

    affecting Plant Morale.

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    34/55

    Boiler Tube Failures (22 Primary Mechanisms)Stress Rupture Short Term Overheating

    High Temperature Creep

    Dissimilar Metal Welds

    Fatigue Vibration

    Thermal

    Corrosion

    Water-side Corrosion

    Caustic Corrosion Hydrogen Damage

    Pitting

    Stress Corrosion Cracking

    Erosion

    Fly Ash Falling Slag

    Soot Blower

    Coal Particle

    Fire-side Corrosion Low Temperature

    Waterwall - Coal Ash - Oil Ash

    Lack of Quality Control Maintenance cleanin

    damage Chemical Excursion damage

    Material Defects

    Welding Defects - indicates that such problems have not been reported in India

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    35/55

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    36/55

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    37/55

    LONG TERM OVERHEATINGOVERHEATING, CREEPINCORRECT MATERIAL

    OVERHEATING BULGING, SATELLITE SCALE CRACKINGOVERHEATING WATERSIDE DEPOSITS

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    38/55

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    39/55

    Tube Failures (Areawise)

    Ceiling SH

    1%

    Div.Panel

    2%

    Reheater

    9%

    Wall RH

    2%

    Waterwall

    33%

    Economiser

    16%

    Platen SH

    6%

    LTSH

    16%

    SCW

    15%

    Tube Failures (Causewise)

    Overheating

    9%

    Pitting

    3%

    Steam

    Erosion

    6%

    Shop Weld

    6%

    Site Weld

    16%

    Matl. mix-up

    3%

    P.F.Erosion

    4%

    Mech.Rubbing

    5%

    Ash Erosion

    28%

    Attach.Weld

    20 %

    Based on NTPC 500 MW boiler tube failure data

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    40/55

    Design Improvements for ReducedTube Failure

    Lower flue gas velocity over tube banks

    Plain tube in-line arrangement of heat

    transfer surface Optimum end caps to avoid preferential gas

    flow

    Erosion shields / cassette baffles Erosion allowance for leading tubes

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    41/55

    Design Improvements for ReducedTube Failure (Cont)

    Higher flexibility in SH / RH nipples

    Redesigned flexible connectors for pendanttype SH coils

    Improved supports for LTSH / Eco. Coils

    Improved seal plate connection for bottomhopper

    Modified LTSH inlet tube connection

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    42/55

    Impact Of Coals On TubeFailures

    &

    Design Improvements for

    Tube Failure Reduction

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    43/55

    DETERIORATION OF COAL QUALITY AVAILABLE FORPOWER GENERATION OVER THE PERIOD

    1970s 1989s 1990s

    PROXIMATE ANALYSIS

    FIXED CARBON % 36.5 32.4 25.0VOLATILE MATTER % 25.5 21.6 18.0

    MOISTURE % 10.0 16.0 12.0

    ASH % 28.0 30.0 45.0

    HHV kcal/kg 4750 4050 3000HGI 50 50 50

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    44/55

    COAL / ASH HANDLED

    HHV kcal/kg 4750 4050 3000

    UNIT RATING mw 210 500 210 500 210 500

    ASH % 28 28 30 30 45 45

    FUEL FIRED t/h 110 272 129 319 174 430

    ASH PRODUCED t/h 30.8 76.2 38.7 95.7 78.3 193.5

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    45/55

    INDIAN COAL Vs USA COAL

    PARAMETER INDIAN UNIT USA UNIT

    210 MW 500 MW 210 MW 500MWHEAT DUTY mcal/h. 454 1070 454 1070

    FUEL FIRED mkcal/h. 520 1215 520 1215

    HHV kcal/kg. 3800 3800 6000 6000

    QUANTITY OF FUEL t/h. 137 320 87 202.5

    AVERAGE ASH CONTENT % 40 40 8 8

    QUANITY OF ASH t/h. 55 128 7 16.2

    Problems Associated With

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    46/55

    Problems Associated WithCoals

    Deteriorating heating value of the coal

    Inconsistent coal properties

    Presence of extraneous matters in coal

    High quantum of ash with high percentageof quartz

    Highly abrasive nature of coal ash

    Due to low sulphur content extremely highelectrical resistivity of ash

    C S d

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    47/55

    Case Study

    670 T/hr boiler, natural circulation and with tangential firingsystem

    The furnace size is 1386 x10592 mm

    6 bowl mills, with five mills catering to full load of boiler

    Designed for an excess air operation of 20%

    The design coal proximate analysis.

    Fixed carbon : 25.0%

    Volatile matter : 20.0%

    Moisture : 15.0%

    Ash : 40.0%

    Grindability index : 80 HGI

    High heating value : 3200 kcal/kg

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    48/55

    Case Study (Cont) The Proximate Analysis, Ultimate Analysis & Coal Ash Analysis Of

    The 6 Samples Of Coal Fired During Trials

    TRIAL NUMBER 1 2 3 4 5 6 7

    PROXIMATE ANNALYSIS

    MOISTURE % 6.08 7.06 7.02 6.86 8.37 6.54 7.1

    VOLATILE MATTER % 21.14 22.14 22.05 21.85 22.04 20.93 21.14

    ASH % 46.7 41.35 41.78 41.87 40.58 46.13 44

    FIXED CARBON % 26.08 29.47 29.15 29.42 29.01 26.4 27.76

    HHV Kcal/Kg 3086 3402 3396 3367 3416 3098 3172

    ULTIMATE ANNALYSIS

    CARBON % 33.65 37.86 37.17 37.28 37.69 34.05 35.43

    HYDROGEN % 2.23 2.55 2.53 2.52 2.51 2.3 2.46

    SULPHUR % 0.51 0.5 0.55 0.5 0.5 0.54 0.58

    NITROGEN % 0.95 0.89 1.05 0.9 0.95 1.02 1.07

    OXYGEN % 5.01 5.05 5.52 5.39 4.89 4.64 4.76

    ASH ANALYSIS

    SiO2 % 61.8 61 62.1 59.6 60.8 61.4 60.8

    Fe2O3 % 17.2 16.9 17.4 14 15.9 15.2 13.7TiO2 % 0.7 0.9 0.9 0.8 0.8 0.7 0.7

    Al2O3 % 8.6 9 8.1 10.7 9.8 10 9.6

    CaO % 7.6 7.9 7.5 10.6 8 7.8 9.7

    MgO % 3.4 3.7 3.2 3.3 3.9 4.1 4.8

    Na2O % 0.1 0.2 0.1 0.2 0.1 0.2 0.1

    K2O % 0.3 0.3 0.2 0.4 0.3 0.3 0.3

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    49/55

    Case Study (Cont)

    The Flame Temperatures Taken During All The Six Trials

    ELVATION TRIAL 1 TRIAL 2 TRIAL 3 TRIAL 4 TRIAL 5 TRIAL 6 TRIAL 7

    METER TEMPERATUR IN DEGREE CENTIGRADE

    14.2 800 815 850 780 813 823 825 NOTE: THE TRIALS WERE CARRIED OUT IN

    17.1 1066 1086 1108 1073 1076 1054 1009 THE 670 T/Hr BOILER AT LOADS THAT

    20.4 1120 1110 1150 1150 1175 1155 1070 WAS TO BE MAINTAINED BY THE TURBIN

    23.2 1217 1213 1211 1263 1250 1225 1140

    26 1180 1240 1210 1291 1275 1255 1215

    29 1246 1254 1267 1291 1250 1235 1275

    32.4 1211 1261 1251 1266 1232 1220 1282

    35.7 1192 1243 1229 1212 1181 1195 1246

    41.9 1172 1163 1148 1100 1117 1115 1210

    44.5 1170 1150 1125 1025 1065 1055

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    50/55

    Case Study (Cont)

    The Details Of The Winbox Auxiliary Air Dampers SettingFF FF AT 10% OPEN FF OPEN AT 80%

    F

    EF ALL FUEL AIR ALL FUEL AIR ALL FUEL AIR ALL FUEL AIR

    E DAMPER AT 5% OPEN DAMPER AT 5% OPEN DAMPER AT 5% OPEN DAMPER AT 5% OPEN

    DE

    D ALL AUX. AIR DAMPER

    CD AT 30% OPEN AUX. AIR DAMPER AUX. AIR DAMPER AUX. AIR DAMPER

    C GRADUALY REDUCED GRADUALLY OPENED GRADUALLY OPENEDBC FROM 60% AT AA FROM 10% AT AA FROM 10 % AT AA

    B TO 12% AT FF TO 50% AT FF TO 50% AT EF

    AB

    A AA AT 60% OPEN

    AA

    TRIALS TRIAL 1 TRIAL 2 TRIAL 3 & TRIAL 4 TRIAL 5 & TRIAL 6

    MILS IN A B D E F A B D E F A B D E F ( 3 ) B C D E F (5)

    OPERATION A B C D E ( 4 ) A B C E F (6)

    BOILER LOAD 496 T/Hr 496 T/Hr 480 T/Hr & 596 T/Hr 608 T/Hr & 604 T/Hr

    SH SPARY 70 T/Hr 75 T/Hr 85 T/Hr & 60 T/Hr 75 T/Hr & 77T/Hr

    RH SPARY 21 T/Hr 21 T/Hr 21 T/Hr & NIL T/Hr NIL T/Hr

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    51/55

    Case Study (Cont)

    The Flame Temperature Profile

    PARAMETER IN THE X- AXIS IS FLAME TEMPERATURE IN DEGREE CELSIUS

    PARAMETER IN THE Y- AXIS IS BOILER PEEP HOLE ELEVATION FROM WHERE THE TEMPERATURE IS MEASURED

    FIGURE:4

    TRIAL 1

    0

    10

    20

    30

    40

    50

    0 500 1000 1500

    TRIAL 2

    0

    10

    20

    30

    40

    50

    0 500 1000 1500

    TRIAL 4

    0

    10

    20

    30

    40

    50

    0 500 1000 1500

    TRIAL 5

    0

    10

    20

    30

    40

    50

    0 500 1000 1500

    TRIAL 6

    0

    10

    20

    30

    40

    50

    0 500 1000 1500

    0

    10

    20

    30

    40

    50

    0 500 1000 1500

    TRIAL 3

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    52/55

    Conclusion The combustion behaviour of coals can very widely hence

    combustion optimisationis a must for boilers It can be concluded from the flame temperature study thatfor low reactive coals the air distribution plays a veryimportant roll

    The height at which the maximum quantity of the

    hydrocarbon to be burnt will depend upon the reactivity,the petrographic characteristic and the burning profile ofthe coal being fired

    Understanding the type of coal being fired andcorrespondingly making proper operational adjustments /modification will help in combustion optimisation and

    reduction of unburned carbon in bottom ash / fly ash. The high ash coals are found to give large variation in

    properties due to its virtue of formation which also affectsthe carbon loss in the boiler and needs a regular watchand tuning of the operational regime

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    53/55

    Boiler Losses Operator ControllableEfficiency

    Dry gas Loss

    Excess air

    Exit gas temperature

    Air ingress

    Fouling

    Tempering air

    Tramp air

    Carbon loss

    Excess air

    Air regime

    Mill fine ness

    Factors Affecting Dry Gas Loss

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    54/55

    1 Coal

    Moisture

    Carbon

    Gross CV

    2 Air temperature entering AH

    Ambient

    SCAPH

    3 Gas temperature

    AH leakage

    AH entering air temperature

    AH entering gas temperature

    Boiler load

    FW temperature

    X ratio of AH

    Tempering airAir ingress

    4 Gas quantity

    Excess air

    AH leakage

  • 8/3/2019 Case Study 8 Maintenance of Boilers[1]

    55/55

    The various factors (coal property, design,

    operating condition) that influence carbon loss

    Coal rank and quality Coal Petrographic characteristics Characteristics and quantum of carbonaceous shale Presence of low melting inorganic in coal ash Residence time available for combustion in furnace

    Type of burners and numbers Type of milling system and primary air control system Fineness of pulverised coal - Percentage of coarser particles Primary air to secondary air ratios Excess air at the burner/furnace and distribution of air into the

    burner/furnace Burner Tilt position