case study 8 maintenance of boilers[1]
TRANSCRIPT
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
1/55
Operation & Maintenance
of Boilers
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
2/55
OPERATION, MAINTENANCEOF BOILERS
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
3/55
Would like to touch upon someimportant factors
Operation Tuning combustion is the most important
aspect
Maintenance Preventive Predictive
RLA
Care of boilers
Performance monitoring Trouble shooting Reducing tube failures
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
4/55
General Boiler Operation
Design & power production have becomesophisticated
Basic operating principles still apply
Combustion safety & proper steam /water cooling are essential Before firing no lingering combustible material
Purge is essential 25% of max air flow
Once combustion established air/fuel ratio tuning
Other parameters to be checked & maintained
General safety considerations Pressure parts failure remain major concern
CO2 NOx &SOx are to be optimised
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
5/55
Boiler Operation
Pre-commissioning operation
Initial start-up operation first Commissioning operation
Alkali boil out
Chemical cleaning
Steam boiling
Safety valve floating
Trial runs Stabilization operation Regular operation
Cold start-up
Warm start-up
Hot start-up
Shutting down Normal
Emergency
Operation for guarantee run
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
6/55
Boiler Operation (Cont)
Marginal difference in operationbased on type of boiler Natural circulation
Once through Fluidized bed
Bubbling bed
Circulating
Pressurized
Chemical recovery
Stoker fired
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
7/55
Key operation functions
Burner adjustments Fuel air ratio
Carbon burn out
Pollutant optimization
Excess air adjustments Fuel conditions
Pressure & temperature liquid fuel
Particle size & primary air
Feed water & boiler water conditioning Soot blower operation
Primary air to secondary air ratio
Wind-box settings
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
8/55
Typical operator walk down check list
Look for valve & valve packing leak
Discoloration, hotspots on casing / ductwork or vapor leak
Open all inspection door & check for slag accumulation
Listen for tube leak
Check for unusual noises, overheating & adequatelubrication on all motors
Look for leaks in gage glasses & water columns
Check that no soot blowers are stuck & no leak
Tilting tangential for uniformity in all corners
Check secondary air damper setting At firing floor check for fuel leak coal, oil & gas
Check all vertical coal pipe for plugging or over heating
Inspect ash pit for bridging
Check level of water in ash hopper& bottom seal trough
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
9/55
Typical operator walk down check list(Cont)
At the pulverizers check for Gear case oil temp, flow & temperature
Excessive spillage or malfunction of pyrite system
Indications for mill fire
Unusual noise
Coal leaks
At air-heaters check Soot blower leakage
Drive motor, support & guide bearing lubrication &cooling water
Cleanliness of air side through observation port
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
10/55
COMBUSTION AIR REGIMETUNING
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
11/55
COMBUSTION AIR REGIME TUNINGHINTS
Indian high ash coals result in highprimary air requirements -primaryCombustion Dilution
Sec. Air distribution at requiredelevation is very important
Avoid / reduce all unwanted sec. Air at
any location And divert them to other needy
elevation.
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
12/55
COMBUSTION AIR REGIME TUNINGACTION
Keep mill air flow just above settling velocity.
Do pitot traverse to check primary air flow
Keep reducing primary air - settling start
Slight furnace disturbance
Increase by primary air 1-2 t/hr
Keep total air flow - 20% excess air @ eco out
Close all fuel air dampers if VM less than 20 - 22% Lookflame front - decide for higher VM coal
Keep wind box pr. 100 - 150 mm - better distributionAcross elevation.
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
13/55
COMBUSTION AIR REGIME TUNINGACTION - Cont
Wall Blower Optimisation
Change in SH spray without change inother parameters indicates furnacedeposit increase
SH spray increase above a particularlevel (to be determined for each boiler)operate wall blowers
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
14/55
COMBUSTION AIR REGIME TUNINGOTHER TIPS
Check % VM in Coal by Hcl Leaching Once ina Month If VM > 20% and Flame Front AwayFrom Nozzle
FC/VM Ratio Vs % FA Comb. Is Very Good for500 Mw Unit - Establish This for Your Plant
+50 Retention for Bottom Ash
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
15/55
COMBUSTION AIR REGIME TUNINGOTHER TIPS Cont
Wind Box Damper Setting for Completion ofCombustion and Bottom Ash Collection
Increase LRSB Operation for Fouling Type
Ash in Coal And Exit Gas Temp. Control Change in SH Spray Pattern Due to Change
in Radiation Heat Transfer Because ofChange Combustion Completion Elevation.
Check PC Analysis on Rieve Distribution.Chart / Roslin-Rammler Chart
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
16/55
Energy Conservation
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
17/55
Energy Economic DecesionMaking
Life Cycle Costing
Using the Payback Period Method
Using the Life Cycle Costing
The Time Value of Money
Investment Decesion Making
Making Decession for Alternate Investments
Depreciation, Taxes & Tax Credit
Computer Analysis
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
18/55
boiler T
482.8 Mkcal/hr 420 Mkcal/hr 180.6 Mkcal/hr 172 Mkcal/hr
200 MW
120.7 t/h
4000 kcal/kg
87.0 %
37.4%
35.6 %
43.0 %2000 kcal/kwhr
2299 kcal/kwhr
2414 kcal/kwhr
auxpower 10 MW
PLANT EFFICIENCY & HEAT RATE
210
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
19/55
Improved Availability/ Reliability
Reducing boiler outage occurrencespressure part failures & other causes(increasing MTBF)
Reducing forced outage duration - onaccount of boiler pressure partfailures + other causes (reducingMTTR)
Reducing occurrences of partial outage -(restricted loading) of boilers
Reducing the duration of operation underpartial outage mode
E C ti M i
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
20/55
Energy Conservation Measures in
Boilers Improved Boiler Efficiency by Exit Gas
Temperature Reduction
Introduction of Variable Speed Drive Motors
SCAPH in By-Pass Duct of FD Fan Air Duct Low Excess Air Burners for Coal, Oil & Gas
Higher Pressure Cycle for Power Generation
On Line Water Chemistry Analyzers toReduce Continuous Blow Down
Micro Processor Controls to EnsureConsistency in Operating Parameter
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
21/55
Energy Conservation Measures inBoilers (Cont..)
Two Out of Three Logic for ReducingSpurious Trips
Measures to Reduce Tube Failures
Acoustic Tube Leak Detection System toReduce MTTR
Retrofits for Availability & PLFImprovements
Intelligent Soot Blowing
Boiler Performance Optimization On-Line(Under Trial &error)
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
22/55
Energy Conservation Measures inBoilers (Cont..)
High Energy Arc Igniters in Place of LDOIgniters
FBC & CFBC Technology for High Ash
Indian Coals & Difficult to Burn Fuels Combined Cycles & Co-generation Plants
Integrated Coal Gassification Combined
Cycle Plant ( Under Trial ) Once Through Super Critical Boiler for
Large Power Plants
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
23/55
Energy Conservation Measures inBoilers (Cont..)
For Old and Aged Boilers Improvements in Availability/ Reliability
Lost Capacity Restoration
Predictive Maintenance of Pressure Parts Residual Life Assessment of Pressure Parts
Thermal Performance Testing & Evaluation
Tuning of Combustion & Optimization
State-of-the-art Up-Grades Micro Processor Controls
Introduction Steam Traps Where ever Possible
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
24/55
WHERE RLA FIGURES IN
LIFE EXTENSION PROGRAMME (LEP)
PLANT CONDITION PERFORMANCE R L ADATA COLLECTION EVALUATION
PROBLEM AREAIDENTIFICATION
VARIOUS PROPOSALSFOR LIFE EXTENSION
F DONE IN PHASEDE FULL OUTEDBA
CK
PERFORMANCE EVALUATION
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
25/55
Why RLA Study Ageing of boilers consequent to creep /
fatigue stresses in pressure parts of boiler
Material degradation
due to corrosion,erosion and oxidation
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
26/55
Why RLA Study (Cont)
Operation of boiler at elevatedtemperatures more than design limit
Variations in coal quality
Deviations in Water Chemistry
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
27/55
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
28/55
Scanning Electron Micro Scope
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
29/55
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
30/55
Creep Cavity Level ClassificationSystem Proposed by Wedel & Neubauer
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
31/55
Run Repair Replace
Evaluates For All Phases
RLA
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
32/55
Trouble Shooting
Studying the problem, analyzing theproblem, finding the root cause of
the problem, taking the corrective &preventive action and takingpreventive to avoid recurrences infuture by pro - active action.
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
33/55
Boiler Tube Failures
Boiler Tube Failures - main cause offorced outages in electric utility steamgenerating boilers
Single tube Failure in a 500 MW Rs. 5to 6 Crores (replacement powercharges for 3-4 days to repair) besides
affecting Plant Morale.
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
34/55
Boiler Tube Failures (22 Primary Mechanisms)Stress Rupture Short Term Overheating
High Temperature Creep
Dissimilar Metal Welds
Fatigue Vibration
Thermal
Corrosion
Water-side Corrosion
Caustic Corrosion Hydrogen Damage
Pitting
Stress Corrosion Cracking
Erosion
Fly Ash Falling Slag
Soot Blower
Coal Particle
Fire-side Corrosion Low Temperature
Waterwall - Coal Ash - Oil Ash
Lack of Quality Control Maintenance cleanin
damage Chemical Excursion damage
Material Defects
Welding Defects - indicates that such problems have not been reported in India
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
35/55
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
36/55
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
37/55
LONG TERM OVERHEATINGOVERHEATING, CREEPINCORRECT MATERIAL
OVERHEATING BULGING, SATELLITE SCALE CRACKINGOVERHEATING WATERSIDE DEPOSITS
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
38/55
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
39/55
Tube Failures (Areawise)
Ceiling SH
1%
Div.Panel
2%
Reheater
9%
Wall RH
2%
Waterwall
33%
Economiser
16%
Platen SH
6%
LTSH
16%
SCW
15%
Tube Failures (Causewise)
Overheating
9%
Pitting
3%
Steam
Erosion
6%
Shop Weld
6%
Site Weld
16%
Matl. mix-up
3%
P.F.Erosion
4%
Mech.Rubbing
5%
Ash Erosion
28%
Attach.Weld
20 %
Based on NTPC 500 MW boiler tube failure data
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
40/55
Design Improvements for ReducedTube Failure
Lower flue gas velocity over tube banks
Plain tube in-line arrangement of heat
transfer surface Optimum end caps to avoid preferential gas
flow
Erosion shields / cassette baffles Erosion allowance for leading tubes
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
41/55
Design Improvements for ReducedTube Failure (Cont)
Higher flexibility in SH / RH nipples
Redesigned flexible connectors for pendanttype SH coils
Improved supports for LTSH / Eco. Coils
Improved seal plate connection for bottomhopper
Modified LTSH inlet tube connection
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
42/55
Impact Of Coals On TubeFailures
&
Design Improvements for
Tube Failure Reduction
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
43/55
DETERIORATION OF COAL QUALITY AVAILABLE FORPOWER GENERATION OVER THE PERIOD
1970s 1989s 1990s
PROXIMATE ANALYSIS
FIXED CARBON % 36.5 32.4 25.0VOLATILE MATTER % 25.5 21.6 18.0
MOISTURE % 10.0 16.0 12.0
ASH % 28.0 30.0 45.0
HHV kcal/kg 4750 4050 3000HGI 50 50 50
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
44/55
COAL / ASH HANDLED
HHV kcal/kg 4750 4050 3000
UNIT RATING mw 210 500 210 500 210 500
ASH % 28 28 30 30 45 45
FUEL FIRED t/h 110 272 129 319 174 430
ASH PRODUCED t/h 30.8 76.2 38.7 95.7 78.3 193.5
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
45/55
INDIAN COAL Vs USA COAL
PARAMETER INDIAN UNIT USA UNIT
210 MW 500 MW 210 MW 500MWHEAT DUTY mcal/h. 454 1070 454 1070
FUEL FIRED mkcal/h. 520 1215 520 1215
HHV kcal/kg. 3800 3800 6000 6000
QUANTITY OF FUEL t/h. 137 320 87 202.5
AVERAGE ASH CONTENT % 40 40 8 8
QUANITY OF ASH t/h. 55 128 7 16.2
Problems Associated With
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
46/55
Problems Associated WithCoals
Deteriorating heating value of the coal
Inconsistent coal properties
Presence of extraneous matters in coal
High quantum of ash with high percentageof quartz
Highly abrasive nature of coal ash
Due to low sulphur content extremely highelectrical resistivity of ash
C S d
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
47/55
Case Study
670 T/hr boiler, natural circulation and with tangential firingsystem
The furnace size is 1386 x10592 mm
6 bowl mills, with five mills catering to full load of boiler
Designed for an excess air operation of 20%
The design coal proximate analysis.
Fixed carbon : 25.0%
Volatile matter : 20.0%
Moisture : 15.0%
Ash : 40.0%
Grindability index : 80 HGI
High heating value : 3200 kcal/kg
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
48/55
Case Study (Cont) The Proximate Analysis, Ultimate Analysis & Coal Ash Analysis Of
The 6 Samples Of Coal Fired During Trials
TRIAL NUMBER 1 2 3 4 5 6 7
PROXIMATE ANNALYSIS
MOISTURE % 6.08 7.06 7.02 6.86 8.37 6.54 7.1
VOLATILE MATTER % 21.14 22.14 22.05 21.85 22.04 20.93 21.14
ASH % 46.7 41.35 41.78 41.87 40.58 46.13 44
FIXED CARBON % 26.08 29.47 29.15 29.42 29.01 26.4 27.76
HHV Kcal/Kg 3086 3402 3396 3367 3416 3098 3172
ULTIMATE ANNALYSIS
CARBON % 33.65 37.86 37.17 37.28 37.69 34.05 35.43
HYDROGEN % 2.23 2.55 2.53 2.52 2.51 2.3 2.46
SULPHUR % 0.51 0.5 0.55 0.5 0.5 0.54 0.58
NITROGEN % 0.95 0.89 1.05 0.9 0.95 1.02 1.07
OXYGEN % 5.01 5.05 5.52 5.39 4.89 4.64 4.76
ASH ANALYSIS
SiO2 % 61.8 61 62.1 59.6 60.8 61.4 60.8
Fe2O3 % 17.2 16.9 17.4 14 15.9 15.2 13.7TiO2 % 0.7 0.9 0.9 0.8 0.8 0.7 0.7
Al2O3 % 8.6 9 8.1 10.7 9.8 10 9.6
CaO % 7.6 7.9 7.5 10.6 8 7.8 9.7
MgO % 3.4 3.7 3.2 3.3 3.9 4.1 4.8
Na2O % 0.1 0.2 0.1 0.2 0.1 0.2 0.1
K2O % 0.3 0.3 0.2 0.4 0.3 0.3 0.3
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
49/55
Case Study (Cont)
The Flame Temperatures Taken During All The Six Trials
ELVATION TRIAL 1 TRIAL 2 TRIAL 3 TRIAL 4 TRIAL 5 TRIAL 6 TRIAL 7
METER TEMPERATUR IN DEGREE CENTIGRADE
14.2 800 815 850 780 813 823 825 NOTE: THE TRIALS WERE CARRIED OUT IN
17.1 1066 1086 1108 1073 1076 1054 1009 THE 670 T/Hr BOILER AT LOADS THAT
20.4 1120 1110 1150 1150 1175 1155 1070 WAS TO BE MAINTAINED BY THE TURBIN
23.2 1217 1213 1211 1263 1250 1225 1140
26 1180 1240 1210 1291 1275 1255 1215
29 1246 1254 1267 1291 1250 1235 1275
32.4 1211 1261 1251 1266 1232 1220 1282
35.7 1192 1243 1229 1212 1181 1195 1246
41.9 1172 1163 1148 1100 1117 1115 1210
44.5 1170 1150 1125 1025 1065 1055
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
50/55
Case Study (Cont)
The Details Of The Winbox Auxiliary Air Dampers SettingFF FF AT 10% OPEN FF OPEN AT 80%
F
EF ALL FUEL AIR ALL FUEL AIR ALL FUEL AIR ALL FUEL AIR
E DAMPER AT 5% OPEN DAMPER AT 5% OPEN DAMPER AT 5% OPEN DAMPER AT 5% OPEN
DE
D ALL AUX. AIR DAMPER
CD AT 30% OPEN AUX. AIR DAMPER AUX. AIR DAMPER AUX. AIR DAMPER
C GRADUALY REDUCED GRADUALLY OPENED GRADUALLY OPENEDBC FROM 60% AT AA FROM 10% AT AA FROM 10 % AT AA
B TO 12% AT FF TO 50% AT FF TO 50% AT EF
AB
A AA AT 60% OPEN
AA
TRIALS TRIAL 1 TRIAL 2 TRIAL 3 & TRIAL 4 TRIAL 5 & TRIAL 6
MILS IN A B D E F A B D E F A B D E F ( 3 ) B C D E F (5)
OPERATION A B C D E ( 4 ) A B C E F (6)
BOILER LOAD 496 T/Hr 496 T/Hr 480 T/Hr & 596 T/Hr 608 T/Hr & 604 T/Hr
SH SPARY 70 T/Hr 75 T/Hr 85 T/Hr & 60 T/Hr 75 T/Hr & 77T/Hr
RH SPARY 21 T/Hr 21 T/Hr 21 T/Hr & NIL T/Hr NIL T/Hr
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
51/55
Case Study (Cont)
The Flame Temperature Profile
PARAMETER IN THE X- AXIS IS FLAME TEMPERATURE IN DEGREE CELSIUS
PARAMETER IN THE Y- AXIS IS BOILER PEEP HOLE ELEVATION FROM WHERE THE TEMPERATURE IS MEASURED
FIGURE:4
TRIAL 1
0
10
20
30
40
50
0 500 1000 1500
TRIAL 2
0
10
20
30
40
50
0 500 1000 1500
TRIAL 4
0
10
20
30
40
50
0 500 1000 1500
TRIAL 5
0
10
20
30
40
50
0 500 1000 1500
TRIAL 6
0
10
20
30
40
50
0 500 1000 1500
0
10
20
30
40
50
0 500 1000 1500
TRIAL 3
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
52/55
Conclusion The combustion behaviour of coals can very widely hence
combustion optimisationis a must for boilers It can be concluded from the flame temperature study thatfor low reactive coals the air distribution plays a veryimportant roll
The height at which the maximum quantity of the
hydrocarbon to be burnt will depend upon the reactivity,the petrographic characteristic and the burning profile ofthe coal being fired
Understanding the type of coal being fired andcorrespondingly making proper operational adjustments /modification will help in combustion optimisation and
reduction of unburned carbon in bottom ash / fly ash. The high ash coals are found to give large variation in
properties due to its virtue of formation which also affectsthe carbon loss in the boiler and needs a regular watchand tuning of the operational regime
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
53/55
Boiler Losses Operator ControllableEfficiency
Dry gas Loss
Excess air
Exit gas temperature
Air ingress
Fouling
Tempering air
Tramp air
Carbon loss
Excess air
Air regime
Mill fine ness
Factors Affecting Dry Gas Loss
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
54/55
1 Coal
Moisture
Carbon
Gross CV
2 Air temperature entering AH
Ambient
SCAPH
3 Gas temperature
AH leakage
AH entering air temperature
AH entering gas temperature
Boiler load
FW temperature
X ratio of AH
Tempering airAir ingress
4 Gas quantity
Excess air
AH leakage
-
8/3/2019 Case Study 8 Maintenance of Boilers[1]
55/55
The various factors (coal property, design,
operating condition) that influence carbon loss
Coal rank and quality Coal Petrographic characteristics Characteristics and quantum of carbonaceous shale Presence of low melting inorganic in coal ash Residence time available for combustion in furnace
Type of burners and numbers Type of milling system and primary air control system Fineness of pulverised coal - Percentage of coarser particles Primary air to secondary air ratios Excess air at the burner/furnace and distribution of air into the
burner/furnace Burner Tilt position