case study 1: large western pine mill
TRANSCRIPT
75 MMBF annual production (log scale)Clears, Shop, Boards, DimensionUSFS timber valuation study
• Lumber size statistics• Headrig results
Case Study 1: Large Western Pine Sawmill
.025 in.Within-Board Variation (sw)
.036 in.Between-Board Variation (sb)
.044 in.Total Variation (st)
1.532 in.Average Measured Size (X)
.023 in..025 in.Within-board variation
.011 in..036 in.Between-board variation
.026 in..044 in.Total variation
1.501 in.1.532 in.Average measured size
After corrective
action
Before corrective
action
Case Study 1: Large Western Pine SawmillStatistics Before & After Corrective Action
Case Study 1: Large Western Pine SawmillStatistics Before & After Corrective Action
Headrig—gradual lumber thickness increase throughout the 1st shift
During 1st shift—cold hydraulic oil expanded as it warmed up, causing drift in linear position setworks
Corrected within one week for less than $10K
Cut total variation over 40%
Recalculating target size—increased the mill’s overall recovery by 0.4%
Cast Study 1: Western Pine SawmillCast Study 1: Western Pine Sawmill
0.4% annual log savings =
75 MMBF x 0.4% = ____ MMBF savings
Translate this into real dollars
300 MBF x $____/MBF log cost
What’s the payback period
$10K / $150K x 250 days = ____ days
Cast Study 1: So What’s the Payback?What is a reasonable payback period?Cast Study 1: So What’s the Payback?What is a reasonable payback period?
Day-to-Day Gang Edger Total Variation (st)
Week 1 Week 3Week 2
Case Study 2:Medium-Size Softwood Dimension Mill
Case Study 2:Medium-Size Softwood Dimension Mill
Sawfiling problem with gang edger
Reduced sawing variation & target sizes
Improved lumber recovery
Able to purchase logs
Mill was going to close
Saved 80 jobs!!!
Case Study 2:Medium-Size Softwood Dimension Mill
Case Study 2:Medium-Size Softwood Dimension Mill
Improve process performance
Sawing machine centers– Identify & locate problems– Improve sawing accuracy
Increase lumber recovery
Case Study 3:Medium-Size Hardwood Sawmill
Case Study 3:Medium-Size Hardwood Sawmill
Circular saw headrig
Gang resaw(fixed saws)
Operator target size 1.125 in. 1.125 in.
Calculated target size 1.135 in. 1.080 in.
Ave. measured size 1.179 in. 1.130 in.
Total sawing var. 0.044 in. 0.010 in.
Between-piece var. 0.037 in. 0.004 in.
Within-piece var. 0.023 in. 0.009 in.
Size control study
Calculated Target Size(1.135 in.)
Critical Minimum Size(1.063 in.)
Average Measured Size(1.179 in.)
Headrig 4/4 Oak HistogramHeadrig 4/4 Oak Histogram
1.05 in. 1 o 1.06 1 o 1.07 1 o1.08 5 ooo1.09 1 o1.10 5 ooo1.11 9 ooooo1.12 24 oooooooooooo1.13 28 oooooooooooooo1.14 26 ooooooooooooo1.15 35 oooooooooooooooooo1.16 56 oooooooooooooooooooooooooooo1.17 56 oooooooooooooooooooooooooooo1.18 47 oooooooooooooooooooooooo1.19 45 ooooooooooooooooooooooo1.20 33 ooooooooooooooooo1.21 26 ooooooooooooo1.22 29 ooooooooooooooo1.23 10 ooooo1.24 12 oooooo1.25 7 oooo1.26 4 oo1.27 3 oo1.28 2 o1.29 2 o1.30 1 o 1.31 01.32 1 o1.33 1 o 1.34 4 oo1.35 3 o1.36 0 1.37 0 1.38 1 o 1.39 1 o
0.9 1.0 1.1 1.2 1.3 1.4----+---------+---------+---------+---------+---------+---------
-----------A--------A----
---A------A-----A-------A-----------A-------A-----A--
---A------------A------------A---A-
---------A---------A------A--
--A------A--
---A------A---A-
-A-----A------
---A-------A---
--A-----A------A---
----+---------+---------+---------+---------+---------+---------0.9 1.0 1.1 1.2 1.3 1.4
Headrig 4/4 Oak Variation Range GraphHeadrig 4/4 Oak Variation Range Graph
___ Average Measured Size
___ Calculated Target Size
___ Critical Minimum Size (CMS)
--- Piece Range
A Piece Average
0.9 1.0 1.1 1.2 1.3 1.4---------+---------+---------+---------+---------+---------+----
--A---A---A-
---A----A--A---A---A----A--
-A---A---A--A--A----A-
---A-----A-----A -A--A-A--A--A--A -A-
--A---A -A---A--A-A-
--A-A-
---------+---------+---------+---------+---------+---------+----0.9 1.0 1.1 1.2 1.3 1.4
Gang Edger 4/4 Oak Variation Range GraphGang Edger 4/4 Oak Variation Range Graph
___ Average Measured Size
___ Calculated Target Size
___ Critical Minimum Size (CMS)
--- Piece Range
A Piece Average
1.2891.279 | | |
Upper 1.269 oControl = 1.2591 in. 1.259 ------------------------------Limit 1.249
1.239 o | | |1.229 1.219 o 1.209 o o1.199 | o o |
Average 1.189 oo o o oMeasured = 1.1785 in. 1.179 -o----------------o-o-----ooo-Size 1.169 o o o
1.159 oo o o | |1.149 o o1.139 o o o1.129 1.119 | | |
Lower 1.109 Control = 1.0979 in. 1.099 ------------------------------Limit 1.089
1.079 1.069
Headrig 4/4 Oak - Average Control ChartHeadrig 4/4 Oak - Average Control Chart
Pretty GoodStatistical Control
Pretty GoodStatistical Control
One Point Out of ControlOne Point Out of Control
0.200 0.190 | | |0.180 0.1700.160
Upper 0.150 | | |Control = 0.1401 in. 0.140 -------------------------------Limit 0.130
0.120 0.110 | | |0.100 o0.090 0.080 o o o0.070 o oo | | o o|
Average 0.060 o o oBetween 0.050 o oPiece = 0.0429 in. 0.040 --o---o------------o-----------Range 0.030 o | | oo |
0.020 o o oLower 0.010 o o oControl = 0.0000 in. 0.000 -o----------o---o------------o-Limit
Headrig 4/4 Oak - Between Piece Control ChartHeadrig 4/4 Oak - Between Piece Control Chart
Good Statistical ControlGood Statistical Control
Headrig 4/4 Oak Specification Chart1.2981.2901.2821.2741.266 | | | | | |1.258
Upper Tolerance 1.250 ---------------------------------------------------------------1.242 o o o o o o 1.234 o | | oo |o o o | o |1.226 oo o o oo oo o o o 1.218 o o o o o o o o oo o o oo 1.210 o o o o o o o o o 1.202 o oo o o| o oo| o o | o o o o o |ooo o |1.194 ooo o o oo oo o ooo o oo ooo ooo 1.186 o o o o ooo o o o oo o oo oo oo oo 1.178 ooo oo o o oo o oo o oo oo o oooo ooooo 1.170 oooo oo| oo o oo| o o oo| ooo oo o oooo o oo o o1.162 ooo oooo o ooo o o ooooo o o oo o o o 1.154 o o o o oo o o o ooooooo o ooo o ooo1.151 o o o o o o o ooooooo o o oo oo 1.143 o o o o | o o oo | | o ooo | o o | ooo1.135 o o o o o o o o o o o
Nominal Size 1.127 -------o-o-o--oo---o------o--o----o------o------oo----o---oo--1.119 o o o o oo o oo1.111 | o o | o | o | o o1.103 o o o o o 1.095 o1.087 o o 1.079 | o | o | | o | |1.071 o
Lower Tolerance 1.063 --------------------------------------------------------------1.0551.047 | | | | | |
Out of SpecificationOut of Specification
Gang Edger 4/4 Oak Specification ChartGang Edger 4/4 Oak Specification Chart
1.266 | | | 1.258
Upper Tolerance 1.250 ---------------------------------------1.242 1.234 | | | 1.226 1.218 1.210 1.202 | | | 1.194 1.186 1.178 1.170 | | | 1.162 o 1.154 o o o o 1.151 ooo oo o o o o 1.143 o oo o oo ooooo oo ooo ooo oo oo 1.135 ooo oo oo oooooooooooooo oooooooooo
Nominal Size 1.127 -oooooo-oooooooooooooooooooo-oo-ooooo--1.119 oooo ooooo oooooooooo oo o o oo1.111 o ooo o ooooo o| o 1.103 o oo o 1.095 o oo o 1.087 o 1.079 | | | 1.071
Lower Tolerance 1.063 ---------------------------------------1.055 1.047 | | |
In SpecificationIn Specification
Headrig– Good statistical control—however…– Does not accurately saw lumber– Setworks need to be replaced & tracks straightened– Adjust target size after repairs (improve recovery)
Gang edger– In good repair– Accurately saws lumber
Case Study 3:Medium-Size Hardwood Sawmill
Case Study 3:Medium-Size Hardwood Sawmill
Mill replaced headrig carriage & tracks– Able to secure financing for upgrading the mill– Improved lumber recovery– Accurately sawn lumber– Fewer customer complaints about thick & thin
lumber
Case Study 3:Medium-Size Hardwood Sawmill
Case Study 3:Medium-Size Hardwood Sawmill
Case Study ConclusionsWhat is the common ground for success?
Case Study ConclusionsWhat is the common ground for success?
Results-driven—no elaborate company-wide activity-focused quality program was necessary for achieving measurable bottomline resultsIn each case study– A problem was identified and a solution formulated– Appropriate corrective action was taken– Measurable results—the problem was solved!– Bottomline business performance improved
Positive results were captured quickly
Results Driven Approach to Improving Quality
& Productivity
Results Driven Approach Results Driven Approach to Improving Qualityto Improving Quality
& Productivity& Productivity
Too often quality programs center on activities rather than resultsQuality programs are easily derailed when the focus is activity-centeredEnds become confused with means—processes confused with outcomesKey to successful improvement is to focus on producing measurable results
—Harvard Business Review
OverviewOverview
Activity-Centered ProgramsActivity-Centered Programs
Many companies spend vast resources on a variety of activities with little improvement in quality, productivity, or business performance. Payoffs are meager at best. Eventually companies abandon potentially useful QC techniques because the focus is on activities, not producing bottomline results.
—Harvard Business Review
Results-driven efforts bypass lengthy preparations and aim at quick, measurable gains. Investment is less. Improvement goals are short term. Top management takes action because they lead directly toward improved results—not promises of someday hopeful gain.
Results-Driven EffortsResults-Driven Efforts
—Harvard Business Review
Key Benefits of a Results-Driven Approach to Improvement
Key Benefits of a ResultsKey Benefits of a Results--Driven Driven Approach to ImprovementApproach to Improvement
Quality improvement tools are introduced only when needed
Trial & error reveals what works
Frequent reinforcement energizes the improvement process
Management builds on previous successes
Start With One Project &Do Something!
Start With One Project &Start With One Project &Do Something!Do Something!
1. Get top management commitment to solve one quality problem
2. Form an improvement team to solve the problem—who?
3. Use problem-solving methodology4. Solve the problem—Do Something!5. Report results & acknowledge the team6. Disband the team7. Build on success—next problem
INSANITY—doing the same things the same way and expecting to see a difference.
—Roger Miliken
Final ThoughtsAn Important Definition
Final ThoughtsAn Important Definition
Final ThoughtsSawmilling is a Complex Business
Final ThoughtsSawmilling is a Complex Business
Sawmilling is all about doing the right thing most of the time—success is ALL in the details.
Of all the primary wood breakdown industries, sawmilling offers the greatest number of ways to convert logs into useable products
In other words—sawmilling offers the greatest number of way to screw up
It takes commitment, time, money, and lots of energy to convert the promise of potential into power of performance.
It is not a question of can you afford to improve quality, but can you afford not too!
Final ThoughtsQuality or Else
Final ThoughtsQuality or Elseor Else
Final ThoughtsDO SOMETHING!
Final ThoughtsDO SOMETHING!
Just remember there are three kinds of people...people who make things happen...people who watch things happen...people who wonder what happened