Caroline County Pilot Caroline County Pilot Watershed Watershed Implementation Plan Implementation Plan (WIP) (WIP) Katheleen Freeman, AICP, Director Katheleen Freeman, AICP, Director Caroline County Department of Planning & Codes Caroline County Department of Planning & Codes Leslie Grunden, AICP Leslie Grunden, AICP Caroline County Department of Planning & Codes Caroline County Department of Planning & Codes MACO Winter Conference MACO Winter Conference January 2011 January 2011

Upload: airell

Post on 02-Feb-2016

46 views

Category:

Documents


0 download

DESCRIPTION

Caroline County Pilot Watershed Implementation Plan (WIP). Katheleen Freeman, AICP, Director Caroline County Department of Planning & Codes Leslie Grunden, AICP Caroline County Department of Planning & Codes MACO Winter Conference January 2011. General Process. - PowerPoint PPT Presentation

TRANSCRIPT

Page 1: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County PilotCaroline County PilotWatershed Watershed

Implementation PlanImplementation Plan(WIP)(WIP)

Caroline County PilotCaroline County PilotWatershed Watershed

Implementation PlanImplementation Plan(WIP)(WIP)

Katheleen Freeman, AICP, DirectorKatheleen Freeman, AICP, DirectorCaroline County Department of Planning & CodesCaroline County Department of Planning & Codes

Leslie Grunden, AICPLeslie Grunden, AICPCaroline County Department of Planning & CodesCaroline County Department of Planning & Codes

MACO Winter ConferenceMACO Winter ConferenceJanuary 2011January 2011

Katheleen Freeman, AICP, DirectorKatheleen Freeman, AICP, DirectorCaroline County Department of Planning & CodesCaroline County Department of Planning & Codes

Leslie Grunden, AICPLeslie Grunden, AICPCaroline County Department of Planning & CodesCaroline County Department of Planning & Codes

MACO Winter ConferenceMACO Winter ConferenceJanuary 2011January 2011

Page 2: Caroline County Pilot Watershed Implementation Plan (WIP)

General ProcessGeneral Process

• Volunteered in Winter 2009/2010Volunteered in Winter 2009/2010

• Pulled out our WRE & Past Watershed Pulled out our WRE & Past Watershed PlansPlans

• Gathered key stakeholdersGathered key stakeholders

• Initially excluded “interest groups”Initially excluded “interest groups”

• Contractor collected/compiled dataContractor collected/compiled data

Page 3: Caroline County Pilot Watershed Implementation Plan (WIP)

LAND USELAND USEAgricultural: 78% Agricultural: 78% (155,000(155,000 acres)Residential: 14% (28,000 Residential: 14% (28,000 acresacres)Public (exempt): 6% Public (exempt): 6% (11,200 acres)(11,200 acres)Commercial: 1% (2,562 Commercial: 1% (2,562 acresacres)Industrial: . 3% (507 Industrial: . 3% (507 acres)acres)

LAND USELAND USEAgricultural: 78% Agricultural: 78% (155,000(155,000 acres)Residential: 14% (28,000 Residential: 14% (28,000 acresacres)Public (exempt): 6% Public (exempt): 6% (11,200 acres)(11,200 acres)Commercial: 1% (2,562 Commercial: 1% (2,562 acresacres)Industrial: . 3% (507 Industrial: . 3% (507 acres)acres)

About Caroline County…About Caroline County…About Caroline County…About Caroline County…

Page 4: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County Caroline County SegmentshedsSegmentsheds(13)(13)

Caroline County Caroline County SegmentshedsSegmentsheds(13)(13)

Caroline County Caroline County HUC 8s (4)HUC 8s (4)and 12s (78)and 12s (78)

Caroline County Caroline County HUC 8s (4)HUC 8s (4)and 12s (78)and 12s (78)

Acreages

30,580

23,506

22,893

21,966

20,956

18,311

16,447

13,703

10,870

8,234

6,793

5,636

4,942

Page 5: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County Phase I Pilot Caroline County Phase I Pilot WIPWIPCaroline County Phase I Pilot Caroline County Phase I Pilot WIPWIP

Focus Sectors for Caroline County

•Agricultural land

•Septic Systems

•Minor Point Sources

•Developed Land

Established Target Sectors State-wide

•Major/minor point sources

•Urban & Agricultural Land

•Forests

•Septic Systems

•Atmospheric Deposition

Page 6: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County TN Targets Caroline County TN Targets (Draft July 2010)(Draft July 2010)Caroline County TN Targets Caroline County TN Targets (Draft July 2010)(Draft July 2010)

Source Source SectorSector

Current Current LoadLoad

(million (million lbs)lbs)

Initial Target Initial Target LoadLoad

(million lbs)(million lbs)

% % ReductioReductio

nn

Minor Minor MunicipalMunicipal 0.0240.024 0.0140.014 42%42%

UrbanUrban 0.0460.046 0.0370.037 20%20%

AgricultureAgriculture 1.2931.293 1.1301.130 13%13%

SepticSeptic 0.0910.091 0.0620.062 32%32%

TotalTotal 1.631.63 1.411.41 13%13%

Page 7: Caroline County Pilot Watershed Implementation Plan (WIP)

Water Resources ElementWater Resources ElementWater Resources ElementWater Resources Element

Municipal and County WREs contain Municipal and County WREs contain assessments of:assessments of:– Nonpoint Source Nutrient Load by Land UseNonpoint Source Nutrient Load by Land Use

– Nonpoint Source BMPsNonpoint Source BMPs

– Point Source Nutrient Loads (WWTPs)Point Source Nutrient Loads (WWTPs)

– Nitrogen Loads from Septic SystemsNitrogen Loads from Septic Systems

Municipal and County WREs contain Municipal and County WREs contain assessments of:assessments of:– Nonpoint Source Nutrient Load by Land UseNonpoint Source Nutrient Load by Land Use

– Nonpoint Source BMPsNonpoint Source BMPs

– Point Source Nutrient Loads (WWTPs)Point Source Nutrient Loads (WWTPs)

– Nitrogen Loads from Septic SystemsNitrogen Loads from Septic Systems

Page 8: Caroline County Pilot Watershed Implementation Plan (WIP)

WIP Assessment of Loads and WIP Assessment of Loads and BMPsBMPsWIP Assessment of Loads and WIP Assessment of Loads and BMPsBMPs

– Nonpoint Source Nutrient Load by Land UseNonpoint Source Nutrient Load by Land Use

– Nonpoint Source BMPs Implemented to date (urban Nonpoint Source BMPs Implemented to date (urban and ag)and ag)

– 2009 Point Source Nutrient Loads (WWTPs)2009 Point Source Nutrient Loads (WWTPs)

– Estimated Nitrogen Loads from Septic SystemsEstimated Nitrogen Loads from Septic Systems

Same basic process used in preparation of WRESame basic process used in preparation of WRE

– Nonpoint Source Nutrient Load by Land UseNonpoint Source Nutrient Load by Land Use

– Nonpoint Source BMPs Implemented to date (urban Nonpoint Source BMPs Implemented to date (urban and ag)and ag)

– 2009 Point Source Nutrient Loads (WWTPs)2009 Point Source Nutrient Loads (WWTPs)

– Estimated Nitrogen Loads from Septic SystemsEstimated Nitrogen Loads from Septic Systems

Same basic process used in preparation of WRESame basic process used in preparation of WRE

Page 9: Caroline County Pilot Watershed Implementation Plan (WIP)

About the Agricultural SectorAbout the Agricultural Sector

– MDA restricts access to BMP data (privacy).MDA restricts access to BMP data (privacy).

– SCD staff know from experience which programs SCD staff know from experience which programs and farms offer the best potential for reductions.and farms offer the best potential for reductions.

– SCD has limited staff to install, track, and report SCD has limited staff to install, track, and report BMPs for about 100,000 acres of farmland.BMPs for about 100,000 acres of farmland.

– Data on BMPs is kept in individual farm files.Data on BMPs is kept in individual farm files.– Voluntary are not all trackedVoluntary are not all tracked

About the Agricultural SectorAbout the Agricultural Sector

– MDA restricts access to BMP data (privacy).MDA restricts access to BMP data (privacy).

– SCD staff know from experience which programs SCD staff know from experience which programs and farms offer the best potential for reductions.and farms offer the best potential for reductions.

– SCD has limited staff to install, track, and report SCD has limited staff to install, track, and report BMPs for about 100,000 acres of farmland.BMPs for about 100,000 acres of farmland.

– Data on BMPs is kept in individual farm files.Data on BMPs is kept in individual farm files.– Voluntary are not all trackedVoluntary are not all tracked

What we learnedWhat we learnedWhat we learnedWhat we learned

Page 10: Caroline County Pilot Watershed Implementation Plan (WIP)

About minor treatment plantsAbout minor treatment plants

•3 minor plants 3 minor plants

•Relatively high avg daily concentrations of TN & TP Relatively high avg daily concentrations of TN & TP – One had avg TN concentration of 40 mg/l (2007)One had avg TN concentration of 40 mg/l (2007)

•All three have Inflow & Infiltration (I&I) problemsAll three have Inflow & Infiltration (I&I) problems

•One has sewage lagoon overflows during heavy One has sewage lagoon overflows during heavy rain rain

•No BRF funding availableNo BRF funding available for minor plant upgrades for minor plant upgrades

About minor treatment plantsAbout minor treatment plants

•3 minor plants 3 minor plants

•Relatively high avg daily concentrations of TN & TP Relatively high avg daily concentrations of TN & TP – One had avg TN concentration of 40 mg/l (2007)One had avg TN concentration of 40 mg/l (2007)

•All three have Inflow & Infiltration (I&I) problemsAll three have Inflow & Infiltration (I&I) problems

•One has sewage lagoon overflows during heavy One has sewage lagoon overflows during heavy rain rain

•No BRF funding availableNo BRF funding available for minor plant upgrades for minor plant upgrades

What we learnedWhat we learnedWhat we learnedWhat we learned

Page 11: Caroline County Pilot Watershed Implementation Plan (WIP)

About septic systemsAbout septic systems

• Approximately 11,100 systemsApproximately 11,100 systems

– about 1,200 located in Critical Area.about 1,200 located in Critical Area.

• To date 43 BAT replacement systems have been To date 43 BAT replacement systems have been installed using BRFinstalled using BRF

• Caroline County’s share of BRF for first half of Caroline County’s share of BRF for first half of FY2011 (July-Dec 2010) is $97,000; 6 upgrades. FY2011 (July-Dec 2010) is $97,000; 6 upgrades.

• Using BRF, it will take 266 years to complete upgradesUsing BRF, it will take 266 years to complete upgrades

About septic systemsAbout septic systems

• Approximately 11,100 systemsApproximately 11,100 systems

– about 1,200 located in Critical Area.about 1,200 located in Critical Area.

• To date 43 BAT replacement systems have been To date 43 BAT replacement systems have been installed using BRFinstalled using BRF

• Caroline County’s share of BRF for first half of Caroline County’s share of BRF for first half of FY2011 (July-Dec 2010) is $97,000; 6 upgrades. FY2011 (July-Dec 2010) is $97,000; 6 upgrades.

• Using BRF, it will take 266 years to complete upgradesUsing BRF, it will take 266 years to complete upgrades

What we learnedWhat we learnedWhat we learnedWhat we learned

Page 12: Caroline County Pilot Watershed Implementation Plan (WIP)

Other things we figured outOther things we figured outOther things we figured outOther things we figured out

•The County has no direct regulatory authority The County has no direct regulatory authority over our over our three three major pollutant sectorsmajor pollutant sectors

•No county-wide system in place to track, monitor No county-wide system in place to track, monitor and report activities across sectorsand report activities across sectors

•Most of our 10 towns will need assistance with Most of our 10 towns will need assistance with planning, implementing, maintaining and planning, implementing, maintaining and reporting BMPs.reporting BMPs.

•The County has no direct regulatory authority The County has no direct regulatory authority over our over our three three major pollutant sectorsmajor pollutant sectors

•No county-wide system in place to track, monitor No county-wide system in place to track, monitor and report activities across sectorsand report activities across sectors

•Most of our 10 towns will need assistance with Most of our 10 towns will need assistance with planning, implementing, maintaining and planning, implementing, maintaining and reporting BMPs.reporting BMPs.

Page 13: Caroline County Pilot Watershed Implementation Plan (WIP)

Where does that leave Where does that leave us?us?Where does that leave Where does that leave us?us?•County does has input in all three sectorsCounty does has input in all three sectors

•County is a logical hub for tracking, County is a logical hub for tracking, monitoring and reporting data for WIPmonitoring and reporting data for WIP

•County logical facilitator of cooperative County logical facilitator of cooperative planning effort between sectors and planning effort between sectors and agencies.agencies.

•County does has input in all three sectorsCounty does has input in all three sectors

•County is a logical hub for tracking, County is a logical hub for tracking, monitoring and reporting data for WIPmonitoring and reporting data for WIP

•County logical facilitator of cooperative County logical facilitator of cooperative planning effort between sectors and planning effort between sectors and agencies.agencies.

Page 14: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County Caroline County Phase II WIP StrategiesPhase II WIP Strategiesfor for Non-Point Source Nutrient Non-Point Source Nutrient ReductionsReductions

Caroline County Caroline County Phase II WIP StrategiesPhase II WIP Strategiesfor for Non-Point Source Nutrient Non-Point Source Nutrient ReductionsReductions

Page 15: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County WIP Caroline County WIP StrategiesStrategies*DRAFT**DRAFT*

Caroline County WIP Caroline County WIP StrategiesStrategies*DRAFT**DRAFT*

Establish a County-based BMP Establish a County-based BMP monitoring, tracking and reporting monitoring, tracking and reporting program with partners.program with partners.

Use data to drive accountabilityUse data to drive accountability

Assess where regulatory changes Assess where regulatory changes may be needed if milestones are not may be needed if milestones are not achieved.achieved.

Establish a County-based BMP Establish a County-based BMP monitoring, tracking and reporting monitoring, tracking and reporting program with partners.program with partners.

Use data to drive accountabilityUse data to drive accountability

Assess where regulatory changes Assess where regulatory changes may be needed if milestones are not may be needed if milestones are not achieved.achieved.

Page 16: Caroline County Pilot Watershed Implementation Plan (WIP)

Non-Point Source Agricultural Strategies:Non-Point Source Agricultural Strategies:

Assess segmentshed agricultural loads and identify priority Assess segmentshed agricultural loads and identify priority farms in each shed.farms in each shed.

Conduct on-site assessments to identify opportunities for Conduct on-site assessments to identify opportunities for new or additional BMPs.new or additional BMPs.

Coordinate water control structure installations in PDAs Coordinate water control structure installations in PDAs with BMPs for roadside ditches.with BMPs for roadside ditches.

Establish erosion and drainage control standards for all Establish erosion and drainage control standards for all ditches.ditches.

Non-Point Source Agricultural Strategies:Non-Point Source Agricultural Strategies:

Assess segmentshed agricultural loads and identify priority Assess segmentshed agricultural loads and identify priority farms in each shed.farms in each shed.

Conduct on-site assessments to identify opportunities for Conduct on-site assessments to identify opportunities for new or additional BMPs.new or additional BMPs.

Coordinate water control structure installations in PDAs Coordinate water control structure installations in PDAs with BMPs for roadside ditches.with BMPs for roadside ditches.

Establish erosion and drainage control standards for all Establish erosion and drainage control standards for all ditches.ditches.

Caroline County WIP StrategiesCaroline County WIP Strategies*DRAFT**DRAFT*

Page 17: Caroline County Pilot Watershed Implementation Plan (WIP)

Non-Point Source Developed Land Strategies:Non-Point Source Developed Land Strategies:

Incorporate standards for environmental site design in Incorporate standards for environmental site design in County/municipal codes.County/municipal codes.

Retrofit stormwater systems on County and Retrofit stormwater systems on County and municipal municipal properties.properties.

Expand TDR Program to reduce new development on Expand TDR Program to reduce new development on septic systemsseptic systems

Establish Drainage Ditch District with controls Establish Drainage Ditch District with controls similar similar to Critical Area.to Critical Area.

Non-Point Source Developed Land Strategies:Non-Point Source Developed Land Strategies:

Incorporate standards for environmental site design in Incorporate standards for environmental site design in County/municipal codes.County/municipal codes.

Retrofit stormwater systems on County and Retrofit stormwater systems on County and municipal municipal properties.properties.

Expand TDR Program to reduce new development on Expand TDR Program to reduce new development on septic systemsseptic systems

Establish Drainage Ditch District with controls Establish Drainage Ditch District with controls similar similar to Critical Area.to Critical Area.

Caroline County WIP StrategiesCaroline County WIP Strategies*DRAFT**DRAFT*

Page 18: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County WIP Caroline County WIP StrategiesStrategies*DRAFT**DRAFT*

Caroline County WIP Caroline County WIP StrategiesStrategies*DRAFT**DRAFT*

Septic Strategies:Septic Strategies:

Target priority septics in Critical Area for BRF Target priority septics in Critical Area for BRF upgrades to insure biggest bang for the buck.upgrades to insure biggest bang for the buck.

Establish septic districts with regular inspection and Establish septic districts with regular inspection and pump-out cyclespump-out cycles

Assess septic failure areas for potential for Assess septic failure areas for potential for establishment of small or innovative community establishment of small or innovative community systemssystems

Assess feasibility of connecting rural subdivisions to Assess feasibility of connecting rural subdivisions to public systems (denied access policy).public systems (denied access policy).

Septic Strategies:Septic Strategies:

Target priority septics in Critical Area for BRF Target priority septics in Critical Area for BRF upgrades to insure biggest bang for the buck.upgrades to insure biggest bang for the buck.

Establish septic districts with regular inspection and Establish septic districts with regular inspection and pump-out cyclespump-out cycles

Assess septic failure areas for potential for Assess septic failure areas for potential for establishment of small or innovative community establishment of small or innovative community systemssystems

Assess feasibility of connecting rural subdivisions to Assess feasibility of connecting rural subdivisions to public systems (denied access policy).public systems (denied access policy).

Page 19: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County Caroline County Phase II WIP StrategiesPhase II WIP Strategiesfor for Point Source Nutrient Point Source Nutrient ReductionsReductions

Caroline County Caroline County Phase II WIP StrategiesPhase II WIP Strategiesfor for Point Source Nutrient Point Source Nutrient ReductionsReductions

Page 20: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County WIP Caroline County WIP StrategiesStrategies*DRAFT**DRAFT*

Caroline County WIP Caroline County WIP StrategiesStrategies*DRAFT**DRAFT*

Point Source Strategies:Point Source Strategies:

– New regional ENR treatment plant for the northern New regional ENR treatment plant for the northern portion of the Countyportion of the County

– Will reduce nitrogen load from 17,000 lbs/yr to 5,000 lbs/yrWill reduce nitrogen load from 17,000 lbs/yr to 5,000 lbs/yr

– Concentrated Animal Feedlot Operations (CAFO) permits Concentrated Animal Feedlot Operations (CAFO) permits now required for medium to large operationsnow required for medium to large operations

– approximately 89 in Countyapproximately 89 in County

Point Source Strategies:Point Source Strategies:

– New regional ENR treatment plant for the northern New regional ENR treatment plant for the northern portion of the Countyportion of the County

– Will reduce nitrogen load from 17,000 lbs/yr to 5,000 lbs/yrWill reduce nitrogen load from 17,000 lbs/yr to 5,000 lbs/yr

– Concentrated Animal Feedlot Operations (CAFO) permits Concentrated Animal Feedlot Operations (CAFO) permits now required for medium to large operationsnow required for medium to large operations

– approximately 89 in Countyapproximately 89 in County

Page 21: Caroline County Pilot Watershed Implementation Plan (WIP)

Caroline County WIP StrategiesCaroline County WIP Strategies*DRAFT**DRAFT*

Caroline County WIP StrategiesCaroline County WIP Strategies*DRAFT**DRAFT*

Upper Choptank Watershed (164,000 acres) Upper Choptank Watershed (164,000 acres) 8 Segmentsheds (13 total)8 Segmentsheds (13 total)

ReductionReduction

  SECTORSECTORNitrogen Nitrogen

(lbs)(lbs)Phosphorus Phosphorus

(lbs)(lbs)

Total Agricultural Total Agricultural ReductionsReductions     741,049741,049 54,52054,520

Total Urban ReductionsTotal Urban Reductions 51,50951,509 10,66910,669

Total Septic ReductionsTotal Septic Reductions 32,88632,886 N/AN/A

TOTALTOTAL 825,444825,444 65,18965,189

% Reductions Non Point % Reductions Non Point SourcesSources 46%46% 53%53%

Page 22: Caroline County Pilot Watershed Implementation Plan (WIP)

Non Point Source Cost ($)

TN Reduced (lbs)

TP Reduced (lbs)

TNCost/lb

TPCost/lb

Agricultural $11,482,679 189,412 20,110 $61 $571

Urban $34,735,000 51,509 10,669 $674 $3,256

Septic $16,640,000 17,935 0 $928 n/a

Point Source Cost ($)TN Reduced

(lbs)TP Reduced

(lbs)TN

Cost/lbTP

Cost/lb

NCWS WWTP $25,000,000 9,342 784 $2,676 $31,885

TOTAL $87,857,679 268,197 31,563

Estimated Costs of Nutrient Reductions

Page 23: Caroline County Pilot Watershed Implementation Plan (WIP)

Contact InformationContact Information

Katheleen Freeman, Katheleen Freeman, DirectorDirector

Caroline County Caroline County Department of Department of

Planning & CodesPlanning & Codes

403 S. 7403 S. 7thth Street, Ste. 210 Street, Ste. 210

Denton, MD 21629Denton, MD 21629

410-479-8100410-479-8100

[email protected]@carolinemd.orgg

Leslie Grunden, AICPLeslie Grunden, AICP

Caroline County Caroline County Department of Department of