career episode three wheatstone upstream project done

6
Career Episode three PE1.1 Introduction This episode describes a position that I participated in Wheatstone Upstream Project. The geographical location of the worksite: Australia Client name: Chevron/Allseas/AGC The title of the position occupied: QCQC Engineer or Mechanical Engineer Project name: Wheatstone Upstream Project PE1.2 Project objective Design and fabrication of export trunk line and multiple production pipeline structures Installation of 220-km, 44-inch concrete-coated export pipeline Installation of 34-km, 24-inch CRA-clad production pipelines Installation of 34-km, 14-inch CRA-clad utility pipelines Installation of 34-km, 6-inch carbon steel MEG flow lines Installation of subsea structures (including 14 PLETs, 6 in- line tees and 41 counteract structures) Flooding, gauging and testing (FGT) of pipeline

Upload: david-mark

Post on 21-Jan-2017

347 views

Category:

Education


1 download

TRANSCRIPT

Page 1: Career episode three wheatstone upstream project done

Career Episode three

PE1.1 Introduction

This episode describes a position that I participated in Wheatstone Upstream Project.

The geographical location of the worksite: Australia

Client name: Chevron/Allseas/AGC

The title of the position occupied:   QCQC Engineer or Mechanical Engineer

Project name: Wheatstone Upstream Project

PE1.2 Project objective

Design and fabrication of export trunk line and multiple production pipeline structures

Installation of 220-km, 44-inch concrete-coated export pipeline

Installation of 34-km, 24-inch CRA-clad production pipelines

Installation of 34-km, 14-inch CRA-clad utility pipelines

Installation of 34-km, 6-inch carbon steel MEG flow lines

Installation of subsea structures (including 14 PLETs, 6 in-line tees and 41 counteract

structures)

Flooding, gauging and testing (FGT) of pipeline

Page 2: Career episode three wheatstone upstream project done

COE Managers

Accounting

Production Quality Trade & IT

Human Resource

ControlMarketing

QCQC Engineer or Mechanical Engineer Maintenance/

Senior Mechanical Engineer

Figure.1 my position

PE1. My responsibilities Chevron Project Engineer on the Wheatstone Project. Presently

working within platform engineering team. Prior to that worked as field engineer for offshore

dredging, rock dumping, pipelay, trunk line shore pull and FCGT.

Implementing and working to the Quality Management System Procedures and work instructions

according to Chevron & All Seas. Working to AWS D1.1-2010 and DNV-OS-F101-Submarine

Pipeline Systems.

. Coordinate NDT & PWHT.

. Final Visual Inspection of all welds.

. Qualify and maintain WPS & Welders Qualifications.

Page 3: Career episode three wheatstone upstream project done

. Perform Inspections in accordance with ITP's.

. Random recording and verification of welding operators to qualified

WPS.

. Coordinate and manage repair of welds and maintain welder repair register.

. Identify and segregate non-conforming products.

. Ensure welding consumables are correctly stored and maintained as per manufacturer's

recommendations, verify and sign off certificates.

. Archiving of product documentation.

. Calibration of inspection and testing equipment.

. Other duties as determined by the Project Quality Manager, on specific contracts.

Personal Engineering Activity

PE1.5

Chevron Project Engineer - Wheatstone Upstream Platform Engineering.

Responsible for Mechanical, Piping and HVAC Engineering disciplines.

Responsible for managing 2x engineering service contractors. Responsibilities include

commercial governance, technical assurance and scheduling.

Management of Change Coordinator for Wheatstone Platform. Role requires me to review all

proposed changes and provide preliminary assessment of whether change is acceptable.

PE1.6

Chevron Package Engineer - Wheatstone Upstream Secondary Stabilization Project. Office

based position with regular site visits.

Responsible for quarry production. Required regular quarry visits to ensure rock production met

Page 4: Career episode three wheatstone upstream project done

quality and schedule requirements. Client Representative onboard dredging and rock dumping

vessels for up to 3 weeks at a time. When in the office I worked on commercial analysis,

document review, scheduling, letter writing, quality assurance, readiness reviews and

coordination of trench acceptance.

PE1.7

Wheatstone Upstream Trunk line Design Team.

Focused on the design of the Wheatstone Trunk line crossings.

Involved with testing being undertaken at the UWA O-Tube facility as part of the Wheatstone

Project and Stable pipe JIP program. This work was a continuation of my final year thesis

involving the mini O-Tube at UWA.

PE1.8

Chevron Field Engineer - Wheatstone Upstream Trunk line Installation Package. Site based

rotational position.

Responsibilities included but were not limited to answering of technical queries, quality

assurance, HSE management and resolving onsite issues. Field engineer for Trunk line shore

pull, onshore hydrotest pond construction and Flood, Clean, Gauge and Hydrotest (FCGT) of

trunk line.

Client Representative onboard pipelay barge. Prior to mobilization I assisted with gaining

regulatory approvals from Pilbara Port Authority and Wheatstone Downstream.

PE1.9

Chevron Project Engineer on the Wheatstone Project. Presently working within platform

engineering team. Prior to that worked as field engineer for offshore dredging, rock dumping,

pipelay, trunk line shore pull and FCGT. I completed a bachelor degree in mechanical

engineering from Washington global university