capstone project iee545 cjg

Upload: chris-weinkauf

Post on 03-Jun-2018

216 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/11/2019 Capstone Project IEE545 CJG

    1/12

    Team CJG

    Capstone

    ProjectI E E 5 4 5 - D r. To r r e s -G a r c i a

    SM ELECTRONICSCOST SAVINGS THROUGH SIMULATION

    ANALYSIS

  • 8/11/2019 Capstone Project IEE545 CJG

    2/12

    Chris WeinkaufQuality Systems Plant ManagerB.S. 2012 Chemical EngineeringContact: [email protected]

    J ohnathon WrightApplications EngineerB.S. 2012 Mechanical EngineeringContact: [email protected]

    * G abriel SilvaSr. Software EngineerB.S. 2004 Computer ScienceContact: [email protected]

    PROJECT TEAM

  • 8/11/2019 Capstone Project IEE545 CJG

    3/12

    Project Introduction GabrielProblemProject PurposeAssumptions

    Model ChrisKey PartsDesignInteractive video

    Results/Conclusions JohnathonResultsRecommendationsSuggested future research

    OUTLINE

  • 8/11/2019 Capstone Project IEE545 CJG

    4/12

    ProblemFactory:

    Key Issues:Single input conveyor with maximum capacity of 40 partsSingle input conveyor accepts random part typesFourth line requires significant setup/process/jam time

    PROJECT INTRODUCTION

  • 8/11/2019 Capstone Project IEE545 CJG

    5/12

    Project Purpose?Determine cost of lines A,B, and C shutting down

    Analyze design and efficiency of theSingle input conveyorFourth and final line (cells 1-8)

    Analyze alternatives to improve cost reductionAdd more pallets

    $17K + $3K for each new palletBenefit: More parts to work in the fourth line

    Add 3 additional buffer conveyors

    $56KBenefit:

    Additional space to store partsBatches of parts fed into fourth line reducing required setup time

    Can consider both alternatives

    PROJECT INTRODUCTION

  • 8/11/2019 Capstone Project IEE545 CJG

    6/12

    AssumptionsNegligible transfer time from input conveyor to line 4Cell 8 will first take a new part even if cell 7 is ready to transfer to itLimitation on the number pallets is 48

    Two year ROI to consider an alternative

    PROJECT INTRODUCTION

  • 8/11/2019 Capstone Project IEE545 CJG

    7/12

    Key PartsFour different models required for comparison

    1. Current Process (no modifications)2. Extra Pallets

    3. Buffer Lines for Parts A, B, and C4. Buffer Lines and Extra Pallets

    Modules Types within the ModelPart Entry into the Holding ConveyorAutomatic CellsManual CellsCell 8Completed Part ExitLost Part Exit

    ARENA MODEL

  • 8/11/2019 Capstone Project IEE545 CJG

    8/12

    DesignCommon Modules

    Cell 8Automatic Cells

    Manual CellsCompleted Part ExitLost Part Exit

    ARENA MODEL

  • 8/11/2019 Capstone Project IEE545 CJG

    9/12

    Model DifferencesExtra Pallets do not change the model logic

    Only difference is more pallets are available

    Main difference between Normal Process and Buffer Lines Models is

    the Entry Module

    ARENA MODEL

  • 8/11/2019 Capstone Project IEE545 CJG

    10/12

    ARENA MODEL

  • 8/11/2019 Capstone Project IEE545 CJG

    11/12

    M1 is the model of current systemM2 is the model of adding additional pallets (resources).M3 is the model of adding buffer lines ($56k investment).M4 is the model of the production line with buffer lines andadditional pallets combined (M2+M3).

    Objective: Maximize Profit.Comparing M1M2

    Comparing M1M3

    Comparing M1M4

    RESULTS

  • 8/11/2019 Capstone Project IEE545 CJG

    12/12

    RecommendationsBuffer Lines Meet 2YR ROI criteria and should be implemented.

    $56K initial cost, approximately $75,000 (+25k) return after 2 years.

    Additional pallets showed no effect on results and should NOT be

    implemented ($17K initial investment, plus $3K per pallet).Suggested Future Research

    Consider upgrading tools with faster loading and processing times.Analyze the buffer line system to find batch sizes that maximizeproduction.

    Consider making individual production lines for each par t, or movingto a larger production facility to maximize profits.

    CONCLUSION