cameroon

25
AFRICAN DEVELOPMENT BANK ENERGY, ENVIRONMENT AND CLIMATE CHANGE DEPARTMENT REPUBLIC OF CAMEROON LOM-PANGAR HYDROELECTRIC PROJECT SUMMARY OF THE ENVIRONMENTAL AND SOCIAL IMPACT ASSESSMENT (ESIA) Project Team Team Leader J.B.NGUEMA- OLLO ONEC.1 3072 O. FALL ONEC.1 3820 J. FRANSSEN Consultant. ONEC.3 3905 Sector Division Manager V. ZONGO ONEC.1 2125 Sector Director H. CHEIKHOUROU ONEC 2034 Region Director M. KANGA ORCE 2047

Upload: seungbeom-kang

Post on 28-Nov-2014

58 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Cameroon

AFRICAN DEVELOPMENT BANK

ENERGY, ENVIRONMENT AND CLIMATE CHANGE DEPARTMENT

REPUBLIC OF CAMEROON

LOM-PANGAR HYDROELECTRIC PROJECT

SUMMARY OF THE ENVIRONMENTAL AND SOCIAL

IMPACT ASSESSMENT (ESIA)

Project Team

Team Leader J.B.NGUEMA-

OLLO

ONEC.1 3072

O. FALL ONEC.1 3820

J. FRANSSEN Consultant.

ONEC.3 3905

Sector Division Manager V. ZONGO ONEC.1 2125

Sector Director H.

CHEIKHOUROU

ONEC 2034

Region Director M. KANGA ORCE 2047

Page 2: Cameroon

2

Project Name Lom-Pangar Hydroelectric Project

Country Republic of Cameroon

Project Number P-CM-FA0-006

1. INTRODUCTION

1.1 The African Development Bank intends to contribute to financing the Lom-Pangar

Hydroelectric Project. This document summarizes the environmental and socio-economic

impact as well as the associated measures of the hydroelectric plant and power transmission

line which form part of the Lom-Pangar Hydroelectric Project. The Lom-Pangar project is in

line with continuous efforts to unlock the hydroelectric potential of the Sanaga Basin (5 665

MW) after the construction of the Edea uncontrolled stream plant (224 MW) in the 1950s, the

Song-Loulou hydroelectric dam (335 MW) in 1988, and the Mbakaou, Bamendjin and Mape

impounding dams in 1969, 1974 and 1981, respectively.

1.2 The site selected for the construction of the dam is characterized by the narrow Lom

valley situated between two hills. The impounding dam will be 40 m high with a capacity of

6 billion m3 covering a 540 km

2 area. The plant will be equipped with four generating units,

each having a nominal wattage of 7.5 MW for a guaranteed flow of 23 m3/s. The power plant

and output terminal will cover an area of 1 755 m2. The route of the transmission line from

the Lom-Pangar project site to Bertoua will run parallel with the secondary road (RD 30)

linking the station to Bertoua on a North-South course, skirting 19 villages located along the

road.

2. PROJECT DESCRIPTION AND JUSTIFICATION

2.1.1 Description

2.1.1 The project comprises the construction of an impounding dam, a 30 MW

hydroelectric plant at the foot of the dam, an HV output terminal and a 90/30 HV terminal in

Bertoua. The project includes rural electrification schemes in the East Region of Cameroon

with the construction of 740 km MV and LV lines and seventy 50 kVA and 25 kVA

distribution sub-stations, and the establishment of 40 000 service entrances and 100 street

lighting areas.

2.1.2 The Lom-Panger Hydroelectric Project underpins the strategy to tap Cameroon’s

hydroelectric power potential. The tapping and optimization of the 5 600 MW hydroelectric

potential of the Sanaga River mainly hinges on the construction of this impounding dam to

supply water during the low-flow period to the installations of the Song-Loulou power plant

and boost the production of the Edea plant, thus increasing the dependable power of the two

plants from 450 MW in 2010 to 659 MW in 2015, with an overall output capacity of 600

GWh. This output may reach 6 500 GWh, upon the completion of the Sanaga terminal

located downstream of Lom-Pangar (Nachtigal, Song Dong, Kikot, Song Mbengue, etc.).

2.1.3 The 105 km 90 kV high-voltage transmission line will help to make the network

more reliable and electrify some 150 localities in the East Region. It is therefore a

continuation of the project to strengthen and extend power transmission and distribution grids

which did not cover this region with an ever-growing energy demand. The rehabilitation and

extension of the MV/LV grid will increase the supply capacity, while service entrances and

Page 3: Cameroon

3

public lighting will help to improve the access of the population to electricity. The Bertoua

station will help interconnect the entire network in the East Region which currently has no

high-voltage line. The works to be carried out include: (i) the construction of transmission

and distribution lines by repowering the 30 KV network operated by AES-SONEL; (ii) the

supply of 50% of the installed power of the independent industrial power producers of the

region; and (iii) the connection of nine divisional headquarters and 140 localities with a

population of more than 200.

2.1.4 In view of its privileged position midway between Yaoundé and Ngaoundere, the

project could help to link the Eastern Isolated Grid from Bertoua to the Southern

Interconnected Grid by raising the Bertoua-Abong-Mbang and Yaounde-Ayos transmission

lines to 90 kV lines, and building a 90 kV line in the Ayos-Abong-Mbang section. The

project will mark the start of the interconnection of the Northern Grid pending the execution

of the project to link the electrical grids of Cameroon and Chad. Lastly, the implementation

of the Electrical Energy Transmission Network Master Plan will provide Cameroon with a

reference tool to chart the development of power generation and transmission units

throughout the country and to promote trade with neighbouring countries.

2.1.5 The Bank’s financing will cover: (a) the construction of the hydroelectric plant to tap

the water resources of the Lom and Pangar rivers; (b) the construction of the transmission

line; and (c) the electrification of the East Region.

2.1.2 Socio-economic Importance

2.2.1 The induced socio-economic benefits of the project will be visible in areas such as

urbanization, education, health, and life and property safety. Electrification will improve the

security of hospitals, cold chains and drinking water and the strengthening food safety in

rural areas. It will help to establish and improve the functioning of recreational centres. The

development of activities will help to generate income, reduce unemployment and improve

living conditions in rural areas, thus slowing down rural-to-urban migration of youth and

hence halting declining agricultural production and ensuring food security. Electrification

will promote urbanization and improve the living environment of the population, the safety of

life and property. In the project area, women are responsible for fetching firewood and

drinking water, providing domestic lighting as well as processing and preserving food and

agricultural produce. Women will be freed from day-to-day and recurrent household chores

and, hence, will devote themselves to income-generating activities that can improve the living

standards of their families. Besides these benefits, electrification will open up new horizons

for teachers and students in the information, training and education domains in the

communities concerned. This will further motivate teachers and students, thus improving the

school attendance rate and school performance.

2.2.2 Regarding climate warming, the project will contribute to reducing the country's

dependence on thermal energy and fossil fuels as well as the greenhouse gas (GHG) emission

rate per kWh generated. It will have a multiplier effect leading to the development of similar

projects.

2.2.3 In the East Region, the AES-SONEL network covers only 32% of the area. It is not

linked to other networks in Cameroon, namely the Southern Interconnected Grid (SIG) and

the Northern Grid. Out of a population of about 850 000, only 270 000 people live in areas

covered by AES-SONEL in the entire East Region. The rate of distribution was 65% in 2002

and 2003. In 2002, the Bertoua power plant produced 24 872 MWh.

Page 4: Cameroon

4

2.2 Analysis of Alternatives

Seven transmission route alternatives were considered, of which three are in the northern and

four in the southern parts of the Lom-Panger site. The optimal route was selected after a

multi-criteria analysis from the technical, economic, environmental and social standpoints.

The line chosen does not cross areas of difficult terrain. The corridor is relatively straight and

skirts rural settlement areas, including 19 villages located on the route.

3. CAMEROON’S INSTITUTIONAL FRAMEWORK FOR

ENVIRONMENTAL MANAGEMENT

3.1.1 Institutional Aspects

3.1.1 Inter-ministerial Committee on the Environment (ICE): it comprises 17

representatives from ministries concerned with environmental management and is chaired by

the Minister in charge of Environment. It expresses an opinion on all environmental impact

assessments.

3.1.2 Ministry of Environment and Protection of Nature (MINEP): is in charge of

formulating, implementing and evaluating government’s environmental policy, including

environmental assessment and mainstreaming environmental considerations in all

development plans and programmes.

3.1.3 Ministry of Forestry and Wildlife: is responsible for formulating, implementing and

evaluating government’s forestry and wildlife policy. In this capacity, it is particularly

responsible for: (1) managing and protecting national forests; and (2) controlling the

implementation of reforestation, forest inventory and management programmes.

3.1.4 Ministry of Energy and Water Resources (MINEE): MINEE's mission is to

formulate, implement and evaluate government’s energy and water production, transportation

and distribution policy. It is responsible for developing government’s energy and water

strategies, and promoting new energies in accordance with Decree No. 2005/87 of 29 March

2005. It is the direct supervisory authority of the Lom-Panger hydroelectric and high-voltage

transmission line project in view of its priority position in the energy policy of the East

Region. It is the supervisory authority of electricity, gas, oil and water production,

transportation, storage and distribution establishments and companies, and the Cameroon

Petroleum Depot Company.

3.2 Regulatory Aspects

3.2.1 Impact Assessments: the conduct of impact assessments falls within a regulatory

framework defined by Cameroon’s legislation and guidelines contained in the November

2000 Report of the World Commission on Dams. At the national level, the environmental

management policy is based on framework documents, including the National Report on the

State of the Environment in Cameroon drafted in preparation for the 1992 Rio Summit, the

National Forestry Action Plan (NFAP) of November 1995, the National Environmental

Management Plan (NEMP) of February 1996, the Forestry and Environment Sector Plan

(FESP) initiated in 1999, and the Cameroon National Biodiversity Action Plan, a strategy

paper which is still being prepared.

Page 5: Cameroon

5

3.2.2 The main statutory instruments related to environmental management and

applicable to the project are:

Law No. 96/12 of 5 August 1996 which lays down the legal framework for

environmental management and introduces notably the environmental impact

assessment approach. Accordingly, Decree No. 2005/577 of 23 February 2005

lays down procedures for the conduct of environmental impact assessments;

Law No. 98/15 of 14 July 1998 relating to establishments classified as

dangerous, unhealthy or obnoxious in accordance with the principles of

environmental management and public health protection;

Law No. 98/5 of 14 April 1998 laying down regulations governing water

resources and provisions to safeguard the principles of environmental

management and public health protection;

Law No. 94/1 of 20 January 1994 laying down forestry, wildlife and fisheries

regulations, which seeks to protect and regulate the use of forests, wildlife and

fishery resources;

Law No. 85/9 of 4 July 1985 laying down procedures governing expropriation

for public purposes and the conditions for compensation;

Laws governing the electricity sector.

3.2.3 Framework Law No. 96/12 of 5 August 1996 lays down conditions for the conduct

of impact assessments for “any development, labour or project which may endanger the

environment owing to its dimension, nature or the impact of its activities on the natural

environment”. This framework law is supplemented by a series of sector laws and decrees in

the environment and energy domains. It determines the basic format of an impact assessment

and develops the participatory approach principle. The categories of operations whose

implementation is subject to an impact assessment are listed in Order No. 70/MINEP of 22

April 2005 to establish categories of operations subject to environmental impact assessments.

It specifies the contents of a summary EIA and a detailed EIA report. Social infrastructure

projects like MV/LV electrical networks in rural areas require only a summary EIA. Impact

assessment approval procedures are the subject of Order No. 2005/577 of February 2005

which lays down the conditions of admissibility of EIAs and file study fees. The Minister of

Environment decides on the admissibility of an impact assessment on the recommendation of

the ICE. Other laws are not yet applicable due to the absence of enabling decrees and orders

which are still being drafted, namely:

Law No. 85/9 of 4 July 1985 to lay down procedures governing expropriation

for public purposes and the conditions for compensation;

Law No. 98/22 of 24 December 1998 to govern the electricity sector.

3.2.4 Statutory Instruments in the Social Domain: space management and land tenure

are governed by some 33 instruments: (i) land tenure: Ordinance 74/1 of 1974; (ii) State

lands: Ordinance 74/2 of 1974; (iii) expropriation for a public purpose and terms and

conditions of compensation: Ordinance 74/3 of 1974; (iv) terms and conditions for

Page 6: Cameroon

6

compensating owners of property destroyed. Civil society is governed by Law No. 99-14 of

22 December 1999 which regulates the functioning of non-governmental organizations

(NGOs) and lays down conditions for the emergence of NGOs capable of participating

effectively in poverty reduction and the accomplishment of public interest missions. The

participation of civil society in the energy sector is very low. Energy policies were

formulated without consultation with civil society.

3.2.5 The adoption of the participatory approach and the dissemination of information are

mandatory in the conduct of impact assessments. Part IV, Section 74 et seq of Framework

Law No. 96-12 of August 1996 contains special provisions concerning impact assessments.

Furthermore, the validation of impact assessments is subject to the opinion of the Inter-

ministerial Committee on the Environment, which is not made public. This could explain the

low participation of the public in the approval of environmental impact assessments, which is

an important step in the process. This situation is remedied by donors.

3.2.6 Two main instruments govern women’s empowerment: (i) Decree No. 97/148/PM of

8 April 1997 to form a National Steering Committee for the Economic Empowerment of

Rural Women and the Improvement of Women’s Living Conditions; and (ii) Decree No.

2000/001/PM of 4 January 2000 to organize and lay down the functioning of women’s

empowerment centres.

3.2.7 EDC’s Environmental Management Capacity: EDC has a Sub-department of

Safety, Environment and Regional Development (SDSEDR) which is one of the four sub-

departments1 of the Lom-Pangar Project Management. SDSEDR is responsible for the day-

to-day management, monitoring and evaluation of all environmental and social aspects of the

project, notably the supervision of environmental impact assessments, the monitoring of

environmental aspects of construction works, the management of compensations,

displacements and resettlements, and ESMP implementation. It comprises three services:

Safety, Environment and Regional Development.

(i) The Safety Service comprises three units: Site Security, Safety and Health. Its

mission will be to secure the Lom-Pangar project area notably by protecting

the park, controlling population implosion, etc. It will also ensure site security

(life and property safety, road safety, health, etc.).

(ii) The Environment Service will be in the vanguard of ESMP implementation.

It comprises three units: Physical and Biological Environments, Monitoring of

the Environmental Aspects of Construction Works, and Implementation of the

ESMP’s Environmental Component. Its mission will be to ensure that field

and site operations comply with ISO 140012 standards. It is expected to

guarantee the integrity and preservation of the ecosystem of the project area by

monitoring in particular the level of pollution of the biophysical environment

(water, soil, air, ecosystem), to ensure compliance with standards of good

environmental practices during construction operations, notably through

1 The other three sub-departments are: Finance, Civil Engineering and Hydrology, and Electro-mechanics. 2 ISO 14001 is the most commonly used standard of the ISO 14000 series of standards concerning environmental management.

Following the ISO 14001 approach closely enables the company to be better perceived by bodies in charge of environmental issues, for instance Regional Directorates of Environment in charge of ensuring compliance with the regulations in force. If a company is ISO

14001 certified, that does not imply that it does not pollute or that it complies with environmental regulations, but only that it has taken

steps to try to achieve the objectives it set in its own action plan.

Page 7: Cameroon

7

periodic inspections, and to prepare and participate in the implementation as

well as monitoring and evaluation of the ESMP of the Lom-Pangar project.

(iii) The Regional Development Service has three units: Social and Economy,

Resettlement Action Plan (RAP) Implementation, and Implementation of the

ESMP Social Component. It will manage all socio-economic issues related to

the Lom-Pangar project. It will be directly responsible for the aspects of RAP

implementation regarding the coordination and implementation of

establishment, evaluation and compensation operations, and resettlement of

people who lost property for a public purpose. It will promote local

employment and the participation of local entrepreneurs in the Lom-Pangar

project, and maintain cooperation and working relations with non-

governmental organizations (NGOs).

(iv) Concerning human resources, in addition to the SDSEDR Deputy Director and

three service heads, 21 senior and junior officers and three administrative

officers will be recruited before the approval of the LPHP. The SDSEDR

Deputy Director will be under the direct supervision of the Lom-Pangar

Project Director, who himself will report directly to the EDC General

Manager. The SDSEDR will be responsible for the overall technical oversight

of the implementation and monitoring/evaluation of the ESMP as well as the

CRP. Under the strategic supervision of the Office of the EDC General

Manager and the Project Management, this sub-department will manage

several ESMP activities as well as the Permanent Secretariat for the

Coordination of Regional Operations, the interface between key Cameroonian

ministerial departments, particularly the Ministry of Forestry and Wildlife

(MINFOF), as well as COTCO for issues related to the adaptation of the Chad-

Cameroon pipeline. Lastly, the SDSEDR will also play a central role in social

communication with the local population as well as other civil society,

production private sector and media representatives.

3.2.8 Decentralized Services of Technical Ministries: the services operating in the study

area are decentralized services of the Ministries in charge of Environment; Energy and Water

Resources; Land Tenure; Territorial Administration; Health, etc. Decentralization, a public

administration technique, is based on the principle of community-based management

effectiveness; it helps to establish a sphere of specific competences for the benefit of regional

and local authorities, and grants them sufficient autonomy in the management of local issues.

3.2.9 NGOs: NGOs operating in the project area are involved in community forestry

development, support to rural entrepreneurs, social development and rural economy

(microcredit, savings, household budget, etc.), and HIV/AIDS control. They are also involved

in the areas of health, education, housing, subsistence economy and development of non-

timber forest products.

4. DESCRIPTION OF THE PROJECT ENVIRONMENT

4.1.1 Natural Environment

4.1.1 The study area is located in the forest-savannah transition zone. Phyto-

geographically, this zone is entirely within the semi-deciduous rain forest. In general, the

Page 8: Cameroon

8

study area has a wide variety of natural environments with limited species diversity. The

evaluation of the importance of the zone in terms of the existence of rare or endemic species

is hampered particularly by lack of knowledge on the identification and distribution of plants

in the region.

4.1.2 The hydroelectric plant will be located at the foot of the dam of which it is part. The

existing biotope consists of river banks and a gallery forest of little importance, giving way to

clearings and grassy savannah. Ninety per cent of the sectors crossed by the HV line consist

of forest land and 10% of farmland (43 ha). It will be constructed along roads and rural tracks

in order to interfere as little as possible with ecosystems.

4.1.3 The natural environment has been altered by human-induced activity. The heavy

poaching of wildlife and overexploitation of plants perpetuated a few years back are now

being controlled by the Ministry of Forestry and Wildlife with the support of the French

Development Agency and companies like CAMRAIL, COTCO and EDC. The zone to the

north, along the Deng-Deng National Park, has a very rich wildlife variety, as evidenced by

the presence of primates. Its forest habitat, which was once threatened by illegal logging and

poaching and which is now under control, is fairly intact. It is thought to contain 200 gorillas

and 100 chimpanzees which are fully protected. The zone situated in the south of Deng-Deng

along RD 30 is of limited importance with regard to wildlife. It consists of forest habitats that

are strongly influenced by the presence of man: dwelling zones, crops, community forests

under exploitation, etc.

4.2 Human Environment

4.2.1 Demography: the population of the area is 8 100 (1 400 households) for 19

localities; the growth rate is said to be low: 1.6% per annum. About 20 different ethnic

groups have been identified in the study area, of which three indigenous groups accounting

for three-quarters of the population. These include, in order of importance, the Pol (50.2%),

the Baya (15.2%) and the Képéré (6.9%). The non-native groups include, in order of

importance, the Maka, known as the “Maka of the North” (23.2%), the Bobili (1.6%), the

Bamiléké (0.6%), the Hausa (0.4%), the Babouté (0.3%), and the Bassa and Akpwakoum

(0.2% each). Then, groups originating in the East Region include the Akpwakoum (0.1%),

the Badjoué (0.1%) and the Kaka (0.1%). Groups originating in the Centre include the

Ewondo (0.1%), the Mvogkani (Eton, 0.1%), the Bamvélé (0.1%) and the Yambassa (0.1%).

Groups from the northern regions include the Bororo (0.1%) and the Bulu (0.1%). Results of

focus group discussions revealed the existence other groups like the Condumassa (0.1%) and

the Fulfude (0.1%) and finally groups originating in the South Region. In general, the results

of focus group discussions conducted in the villages show that relations between the different

ethnic groups in the area are very cordial.

4.2.2 Concerning gender, there is wide gender inequality with regard to education and

vocational training. Although women play a key role in households, the situation is different

outside the family where they are hardly given the opportunity to speak and remain in the

background. Two-thirds of houses are traditional; drinking water of poor quality is fetched

from wells (56% of families), springs and rivers. The area has six senior government primary

schools, one secondary school and two junior government primary schools. Road

infrastructure includes the tarred RN 1, the earth ND 30 and several old earth roads. Traders

come to collect rural produce. The area has been divided into three health zones (integrated

health centres). The main diseases are dysentery, malaria, intestinal parasitic diseases,

respiratory infections, STDs and AIDS.

Page 9: Cameroon

9

4.2.3 Economic and Social Activities: the plant and HV transmission line will be located

in a mostly forest and agricultural zone. In the entire project area (including the reservoir and

the dam), there are about 19 villages comprising 328 families whose farmlands and forests

will be damaged. Agriculture, which is the main economic activity, accounts for 64% of

family income, followed by hunting (14%) and fishing (8%). These sectors provide the

largest number of jobs in communities and are said to employ about 70% of the active

population. Secondary economic activities include stockbreeding (5%), handicraft, logging

(3%) and petty trade (4%) which is carried out by men and women depending on the products

sold.

4.2.4 Land Tenure: two systems, the modern (Land Code of 1974) and the customary law

land tenure systems, coexist in Cameroon. Land boundaries are generally marked by fruit

trees, forest edges and streams. Conflicts are managed through traditional, customary, or

administrative procedures. Land disputes are settled by administrative arbitration as the rural

populations do not have a land titling culture. Nevertheless, customary law recognizes land

ownership in different villages. All population displacements within the framework of the

Lom-Pangar project have been carried out according to the OP 4.12 of the World Bank.

There is no land problem in the project area as there is enough arable land. Cameroonian

legislation and the World Bank’s OP 4.12 are applied. Where these two sets of rules differ,

the project will apply the one that is more favourable to people affected by the project. This is

the case with houses, for example, which are compensated according to their replacement

value (according to World Bank rules) and not on the basis of their actual value (according to

Cameroonian law).

4.2.5 Archaeological Heritage: it comprises vestiges dating back to the 9th

and 13th

centuries, the oldest elements are thought to date back to the Stone Age, indicating that the

Lom valley was more populated in the past than today. Sacred sites are said to have been

identified in nine villages. These often include trees, sites marked by the presence of water

and sometimes artefacts (tombs, esplanade, etc.). It seems that the only archaeological site is

the Bertoua grotto.

4.2.6 Lifestyle: the population of the project area lead a relatively modern lifestyle. Most

villages have generators for lighting and satellite television.

5. PROJECT ALTERNATIVES

The project is indispensable and no environmentally, socially or financially acceptable

alternative has been presented. The without-project alternative cannot be chosen because it

would prevent the development of the Sanaga basin on which the economy of a large part of

the country depends.

6. POTENTIAL IMPACT, MITIGATIVE AND COMPENSATORY

MEASURES

6.1.1 Impact of Plant Construction

6.1.1 The entire Lom-Pangar project comprises the following components: (i) the dam per

se. The Lom-Pangar impounding dam which is 46 m high covers an area of approximately

540 km², for a payload of 6 billion m3; (ii) a hydroelectric plant which lies at the foot of the

Page 10: Cameroon

10

dam and has a capacity of 30 MW aimed at increasing the electricity supply capacity in the

East Region currently served by diesel-fired power plants. Power will be transmitted to

Bertoua by a 105 km-long 90 kV line; (iii) a Belabo-Satando-Mbaki-Mansa-Deng Deng

access road and the dam site located near the present Lom-Pangar village; (iv) a workers’

camp, a working area and equipment depots on the right bank of the Lom river opposite

Lom-Pangar village; and (v) the creation of Deng Deng National Park. This component is a

compensatory measure of the dam project. The power plant and high-voltage transmission

line project is part of the dam project, without which there would be no need for it. The areas

of impact of the two projects overlap. Part of the infrastructure to be constructed (access

roads, workers’ housing estate) will be for both projects.

6.1.2 Positive Impact: the main socio-economic benefits for the population will include

the creation of jobs for the local population to offset unemployment in the region; improved

road infrastructure and opening up of the area; and improved living conditions. The inevitable

deforestation of the site (gallery forest on the banks of the river) is offset by the sale of

marketable logs for timber or firewood. The rehabilitation of rural access roads will help

open up the surrounding villages for trade.

6.1.3 Negative Impact: the construction of the plant will entail the clearing of 210 ha; it

will be part of the construction of the dam dyke and will therefore have no specific impact

because the effects are similar to those generated by the construction of the dam dyke to

which it is joined: the works will impact the modified soil structure; machinery will pollute

the air; and dyke works will increase the turbidity of the river. Measures have been taken to

reduce water pollution as much as possible. The felling of the gallery forest will have very

little negative impact on common flora and marginal terrestrial wildlife. Fish will move

depending on the works being carried out and will recolonize the reach after the works. Since

the dam and plant are located in a sparsely populated area, no family will be displaced. The

domestic site of senior officers and workers necessitated the construction of two platforms in

the forest that were completely deforested, but were only partially levelled in order to

preserve the landscape value of their respective sites, as specified in the RAP appended

hereto.

6.1.4 Indirect Impact: the indirect impact of the construction of the hydroelectric plant

will include a major oxygen deficit at the bottom layers of the reservoir, during the operation

period, associated with low pH value, nitrogenous and phosphorus salt concentrations. This

phenomenon will be caused by the decomposition of submerged vegetation, a process that

uses oxygen dissolved in water3. These in-depth deoxygenated water masses cannot be

developed by fishing activities. However, they may be discharged with sludge through

periodic bottom draining. The churning of water will help to ensure its re-oxygenation.

6.2 Impact of the Construction of HV/MV/LV Lines

6.2.1 Positive Impact: the inhabitants of villages located along the route of the

transmission line will be compensated for damage to private property. The socio-economic

opportunities offered by the project that are beneficial to the local communities will include:

job creation, improved road infrastructure and opening up of some villages, the revival of

3 The anaerobic decomposition of organic matter in the soil causes the formation of submerged dissolved elements such as ammonium

(NH4 +), ferrous iron (Fe 2 +), methane (CH4) which is 20 times more harmful than CO2, carbon dioxide (CO2) and hydrogen sulfide

(H2S). The amount of greenhouse gas (CH4 and CO2) emitted into the atmosphere depends on the evolution kinetics of these elements

in the reservoir.

Page 11: Cameroon

11

economic activities, improvement of the living conditions of people living along the line,

particularly women (exploitation of arboriculture products and sale of farm produce). Easy

access to microcredit in areas directly benefitting from the project will enable the population

to invest in different business and craft sectors. The old LV line which previously served the

villages and is now abandoned will be rehabilitated and its route will be maintained to

minimize impact on the natural environment. Rural electrification will help implement a new

approach to development (mechanized grinding of food, possibility of drinking water supply

and access to family health and to the cold chain; electrification of schools, dispensaries,

houses and development of handicraft activities (mechanical workshops, sheet metal

workshops, joinery shops, sewing shops, hairdressing salons, barbershops, etc.); household

comfort and access to media like TV, radio, and eventually the Internet.

6.2.2 Temporary Negative Impact: the construction of the transmission line will

necessitate civil engineering works on its route between the dam site and the Bertoua station.

The foreseeable impact will be generated by the use of machinery which will result in some

modifications of the components of the physical environment (soil compaction and

pollution); sound and air quality nuisances will be caused by the operation of machines.

6.2.3 The impact of the transmission line on Deng-Deng forest biodiversity will be related

to the deforestation of a 528 ha corridor; most species of high commercial value have already

been exploited by the villages. The regeneration of shrub species along the line will restore a

very similar substitution biotope during the line’s operation phase. The destruction of

endangered, endemic species and loss of biodiversity are unlikely because the corridor is

small in size and few endangered species have been identified in the area. However, the

installation or development of invasive species due to the disruption of the ecosystem is

possible. Their development will be controlled by the regular maintenance of open spaces.

6.2.4 Construction activities and noises caused by the building of the HV line will disrupt

and temporarily displace local wildlife; after the works, the wildlife will return to its former

territory and native vegetation will regenerate around the project facilities. The destruction of

habitat near the Deng-Deng National Park will affect only a band of between 0 and 50 metres

on the eastern edge of the area. The area bordered by the high-voltage line is a marginal

fringe of the habitat of large primates; the impact on these species will therefore be limited.

6.2.5 The loss of farmland will be threefold: (i) temporary loss of use related to the

opening up of rural roads and the implantation of construction sites; (ii) loss of use of land

associated with the construction of pylons; and (iii) losses related to the development of plots

due to the implantation of pylons on irrigated land. There will be no system of spray

irrigation via ramps and pins. These different losses will be compensated as specified in the

RAP. Land use by the HV line will impose only very few permanent constraints on

agricultural activities, unless they are prejudicial to the safety of the line (cutting of fruit

trees); they will only result in the establishment of easements. The height of the conductor

cables of an overhead power line can be adapted to the nature of traditional farming activities

(orchards and irrigation). The main constraint will stem from the presence of pylons which

are generally about 300 m apart. The location of pylons somewhat reduces cultivable areas

and may impede land development. The opening up of easements in view of their permanent

nature may be more constraining than the positioning of the line. It should be recalled that all

these constraints are temporary and will disappear at the end of the construction of the line.

Page 12: Cameroon

12

6.2.6 With regard to land, pylon construction routes will be temporary just like the

passage through seasonal crop farms during the pulling of lines. Conditions under which

stockbreeding is carried out will not be disrupted. At the end of construction works, the

regeneration of vegetation within the corridor will delimit a new pasture zone. These works

could result in the loss of farm income. The presence of foreign workers could spark off

relational conflicts in villages along the route during the construction period.

6.2.7 Permanent Negative Impact: the area requisitioned for the construction of the plant

and transmission line is included in the impact of the dam construction project. The main

expected impact will concern the displacement of 16 houses in three villages as the route will

be away from villages. The farmland affected by the transmission line is not large as the

population density is relatively low: losses will involve 328 households and will concern

41.35 ha of farmland. The number of trees and perennial crops affected is 23 000, of which 5

000 plantains and 9 000 old cacao and coffee trees, and a village rubber plantation (141 trees)

in Mansa. There will also be increased pressure on land, increased land clearing, agricultural

intensification and soil degradation. No archaeological vestige is listed in the works zone.

6.2.8. According to information obtained from surveys carried out by the HV Line

Identification and Assessment Commission (EOC), the different categories of people and

property affected are: 19 villages; 855 households; 48 ha, that is 561 m² per household, of

food crops; 41 149 trees and perennial crops, of which 7 649 banana trees, 7 342 old plantain

and 15 051 cacao and coffee trees; 64 tombs, of which 60 earth and 4 cement tombs; 16

houses, of which 11 in Kané, 2 in Koumé Goffi and 3 in Kambo Cassi; 6 round huts, of

which 2 in Kano and 4 in Koume Goffi. Therefore, expropriation concerns only 16 families

(transmission line site) and has no major socio-cultural and economic impact because the

families have been resettled in the same village with their consent. In view of expected

population movements and zones that may be more or less disturbed by this population

implosion, the total surface area likely to be affected in varying degrees is about 1 666 ha,

that is 0.7% of the overall surface area. Electromagnetic waves from the HV line will

constitute a health hazard for the population that would decide to illegally build their homes

in the line corridor.

6.3 Impact during the Plant and Line Operation Phase

6.3.1 Benefits to the Population: the power plant and high-voltage transmission line

project will first of all benefit the population who will be connected to the electrical grid,

mainly the inhabitants of the major towns, notably Bertoua, and rural communities connected

to Bertoua by the existing 30 kV line. The impact will include: (i) the improvement of the

quality of MV and LV distribution by reducing to a minimum the number and duration of

power cuts; and (ii) the development of the economic sector throughout the region. The

development of the East interconnected grid should increase the number of inhabitants and,

eventually, industries directly benefitting from the project. Therefore, potential benefits will

mainly depend on the rural electrification project that will soon be implemented thanks to the

construction of the hydroelectric plant at the foot of the Lom-Pangar dam.

6.3.2 Risks: the formation of an electric arc or contact of lines with trees can cause a fire

in wooded areas. This risk is low but it exists, particularly in the event where cables swing

under the effect of the wind or when the vegetation under the lines is too tall. The risk of fire

outbreak varies according to season and is logically greater in the dry season. There is also a

risk of breakage of cables and falling of pylons under the influence of various factors.

Page 13: Cameroon

13

6.3.3 Positive Impact Enhancement: it will directly depend on: (i) the quality of

equipment maintenance under the responsibility of the Project Supervisor; and (ii) the

implementation of a complementary rural electrification project. Easy access to bank loans

and microcredit in the direct project areas will enable the population to invest in different

business and handicraft sectors which will raise the population’s standard of living.

Regarding social benefits, the project will help to improve and develop handicraft activities

and SMIs/SMEs, as well as the standard of living of the rural and urban population

(improvement in housing, job opportunities and development of recreational activities).

6.3.4 A Local Community Development Support Plan (involving 8 000 people) will be

included in the construction project. Measures will be taken to establish medium- and long-

term financial (microfinance) and monitoring instruments. Recommended actions will

include: the protection of the cultural heritage and payment of compensation for damage

caused, social infrastructure (construction of schools, rural electrification plan, construction

or rehabilitation of drinking water points, agricultural supervision, improvement of farming

practices and farmers’ organizations and improvement of productivity). An education and

health sensitization campaign will be carried out. The operation phase will be characterized

by the sustained implementation of the ESMP planned to run for eight to ten years with a

mechanism that guarantees the implementation of actions beyond this planned period by

establishing a long-term ESMP financing system based on deductions from charges on water

or electricity produced by the plant at the foot of the impounding dam. During the operation

phase, compensation payments and population displacements will be completed and PAP

attendant measures will be more or less at an advanced stage. The project ESMP will go

beyond PAPs in terms of compensation actions.

6.3.5 In general, electrification will help to make the living environment pleasant for the

entire population. In localities in the project area, many community socio-educational

structures (health centres, primary schools, secondary schools, adult literacy centres, etc.) will

be built. The difficult and precarious working conditions of the population will be improved

thanks to the permanent supply of electricity. School success rates and efficiency of health

centres, and other facilities (maternities) will be enhanced. The availability of electricity will

also help to develop multimedia centres to hook up the rural communities of the East Region

to cyberspace.

6.3.6 Gender: in the project area, women account for approximately 52% of the

population and are very active in traditional sectors. Eighty per cent of them are actively

involved in farming and 20% in petty trade. The permanent supply of electricity will help to

free them from recurrent chores so that they can devote themselves to income-generating

activities likely to improve their living conditions and reduce poverty. Given the key role

that women play in socio-economic activities in the project area, the provision of sufficient

and regular power will boost their specific activities (mechanized grinding of food, water

supply, sale of water and refrigerated products, catering, handicrafts, dressmaking, dyeing,

hairdressing, etc.). Easy access to modern energy, the intensification and acceleration of their

substitution for traditional energies to meet household energy needs will have a significant

positive impact on the well-being of the target population and their access to the media

(radio, TV, education, etc.). Women’s household constraints will be reduced gradually to the

benefit of educational and/or income-generating activities due to access to electricity.

Page 14: Cameroon

14

6.4 Impact Mitigation Measures

6.4.1 The decentralized regional services of the key ministries involved in the project

(Environment; Energy; Social Affairs; Health; Labour; etc.) will ensure that the measures

recommended are effectively implemented. During its works supervision missions, the ADB

will also ascertain that operations are properly executed in accordance with project

provisions.

6.4.2 Site Preparation and Works Phase: before the commencement of works, the local

residents will be informed about temporary constraints on access to certain sites for safety

reasons. Regarding cultural aspects and in the event of accidental discovery of ancient

vestiges, the EDC will report such discovery to the Divisional Office. Construction sites are

located far from sensitive sites and will be permanently and clearly marked (by signposts,

flashing lights, etc.), and protected by safety barriers defined in coordination with the

municipal council’s roads service. Diversion routes will be organized. Machines used will

comply with the technical and safety standards of their manufacturers and will be equipped

with sound-proofing devices to reduce sound nuisance during construction works as much as

possible. The level of exhaust fumes will comply with the manufacturer’s standards. Soil

rammed during construction works will be churned up to restore its natural ventilation and

pedological properties; herbaceous, shrubby or woody vegetation destroyed will be replaced.

Various wastes will be disposed of; all sites will be rehabilitated.

6.4.3 Domestic sites will have the appropriate health-care facilities required; the sewage

and various solid wastes of domestic sites will be collected for disposal. Quarries will be

rehabilitated after the completion of works. The EDC will acquire the surface areas needed

through amicable agreement. They will be drained and only traffic areas will be concreted.

To prevent the risk of contamination of the water table with oils, watertight vats will be

constructed and placed under station transformers and connected to an isolated sealed pit to

recover any leaks. It should be noted that this type of transformer does not contain pyralene

or other liquid dioxin compounds.

6.4.4 All land needed for the construction of transmission lines will be temporarily

occupied and could be restored for farming after the completion of works. Works will be

executed during the dry season; access roads will be reduced to a strict minimum to ensure

the maximum protection of the soil structure and avoid site degradation. Machines will be

consistent with international standards and specifications for noise and exhaust fumes. Oils

and fuels will be stored off-land in watertight vats to enable the recovery of leakages or

accidental spills. Measures will be taken to prevent erosion risks on slopes by building levees

(as in terrace cultivation).

6.4.5 Works will preferably be organized after harvests to minimize the cost of

compensation for rights-of-way and loss of food crop harvests as much as possible;

compressed soil (haulage on access roads) will be churned up at the end of works to a depth

of 50 cm. To the extent technical constraints would allow, pylons will be mounted on sites

that cause the least inconvenience to crops near paths, roads and boundaries of parcels. The

height of pylons will take into account existing constraints (irrigation, orchards, etc.).

Contractors will also ensure that project sites are cleaned by removing all debris and residues.

Page 15: Cameroon

15

6.4.6 Recruitment, worker management and working conditions must comply with

national regulations and international standards. An independent commission will specifically

ensure that the following points are respected: (i) the physical fitness of applicants should be

evaluated; (ii) each worker will be given basic training on safety and hygiene rules at work

sites; and (iii) wages will be equal to or higher than the minimum wage fixed by law. The

settlement of workers on the right bank will limit benefits in terms of job opportunities for the

population of Ouami, Deng Deng and other localities. The project’s ESMP is robust enough

to create compensatory economic opportunities (construction of social infrastructure, Touraké

bridge, fishing, farming, etc.) for the inhabitants of this area.

6.4.7 The construction of the power plant and transmission line will be preceded by the

harvesting of trees located on the line route. The sectors concerned have been targeted and

will be exploited by companies already operating in these sectors or will be subject to the

signing of specific logging contracts. Most people affected by the project are involved in

community forest exploitation in the area.

6.4.8 During the Operation Phase: periodic maintenance work will be carried out to

ensure that the soil is disturbed as little as possible. No direct measures will be taken to

reduce noise produced by transformers and transmission lines, except by placing them in

locations far away from dwellings and by building appropriate fences. The line route will be

regularly maintained (pruning of trees). EDC will, as a precautionary measure, ensure that no

house is built under the HV transmission line in view of the health hazards caused by

electromagnetic fields. It will compensate all owners of houses located in the danger zone.

The visual impact of installations will be offset by plantations which will create a tree screen.

The visual impact of the transmission line will be realized by situating the route near the road

(to also avoid useless and costly access development works). Fire hazards along the line route

will be prevented by regular and standard maintenance of the line and regular cutting of tree

branches that can cause short circuiting.

7. ENVIRONMENTAL RISK MANAGEMENT

7.1 Greenhouse Gas Emissions

7.1.1 Direct Impact: the quantity of GHG produced by the Lom-Pangar impounding dam

has been estimated by two thematic studies:

the study of alternatives is based on data on CO2 and CH4 emission from the

Petit Saut hydroelectric project in Guyana (3 500 hm3 for 310 km²) as well as

on studies carried out on the Nam Theun II project in Laos4. The result of

estimates, updated for a quantity of submerged vegetation corresponding to

about 6.4 million tons of carbon, is 21 million tons of emitted CO2;

according to the study on vegetation, this same quantity is estimated at 24

million tons of CO2.

7.1.2 Given the complexity of the phenomena involved and the limited number of

experiments successfully carried out, notably in the tropical zone, the theoretical bases and

4 These dams were built within a similar bioclimatic context and the size of their reservoir is similar to that of Lom-Pangar. Furthermore,

they are the subject of thorough environmental and social monitoring.

Page 16: Cameroon

16

measurements of reservoir emissions are still not reliable. However, the results presented

above give an acceptable order of magnitude. In fact, the quantity of CO2 likely to remain in

the atmosphere is expected to be less than the quantity released because part will be re-fixed

by water. Since this is a global phenomenon, it is difficult to estimate the quantities

concerned; some estimates indicate that half of the CO2 released into the atmosphere is fixed

in oceans. If no hydroelectric project is implemented on River Sanaga after Lom-Pangar, the

quantity of GHG produced by the equivalent thermal alternative over 100 years is 17 million

tons of CO2 equivalent, compared to 21 million tons emitted by the Lom-Pangar impounding

dam. The Lom-Pangar dam alone will therefore produce more GHG than the equivalent

thermal alternative.

7.1.3 If one considers the future tapping of the hydroelectric potential of the Sanaga to

meet growing energy demand in the medium-term, this result is strongly in favour of Lom-

Pangar. The first conclusion is that over the 100-year reference period, the Lom-Pangar

impounding dam will emit approximately seven times less GHG than a thermal alternative

rendering the same service: 21 million tons as against 140 million tons, on the assumption

that the Nachtigal project will be implemented in 2014 in the “status quo” scenario or in 2010

in the “development” scenario. However, distribution over time is different. During the first 7

or 15 years following priming, the Lom-Pangar project will, for the two scenarios, emit more

CO2 equivalent than a thermal alternative playing the same role. The trend will be reversed in

the decades ahead: the thermal alternative will continue to emit GHG whereas the dam

emissions will drop. The commissioning of new hydroelectric projects (Song Bengue and the

extension of Song-Loulou, for example) underscores the advantage of the Lom-Pangar dam

in terms of emitted GHG: from the twentieth year, the trend will change in favour of

hydroelectricity.

7.1.4 Another factor, the stoppage of photosynthetic activity in growing plant formations

increases the level of GHG in the atmosphere. Under normal weather conditions, they form

carbon sinks, but will not be able to serve as carbon fixers after the zones concerned are

flooded. Among the formations present on the dam right-of-way, only forest regrowth and

partly, of course, young forests can be considered as sinks. The forest regrowth and young

forests represent approximately 2 400 ha, that is 7.4% to 7.8% of the total forested area.

Estimates of carbon fixing by natural forest regrowth in the tropical zone are less than 2 tons

of carbon per ha per year for the first 20 years and 0.5 ton of carbon per ha per year for the

following years (source IPCC, 1996). The corresponding figures for carbon dioxide are

approximately 7 tons and 2 tons. Thus, contribution to greenhouse effect by increasing

carbon dioxide content through the flooding of the reservoir would be a little over 600 000

tons of carbon dioxide over 100 years.

7.1.5 Indirect and Induced Impact: the entire Lom-Pangar project will contribute to

climate warming whose indirect effects are many, and are felt worldwide and likely to vary

significantly from one area of the globe to another. Many works are underway to sharpen

knowledge of consequences at the local level.

7.1.6 Compensatory Mechanism: the release of greenhouse gases from the decomposition

of vegetation in the reservoir will be offset by various measures aimed at preserving

biodiversity in the project area: (i) creation of the Deng-Deng National Park (Joint

Biodiversity Conservation and Long-term Great Apes Survival Programme); (ii) proper

management of the reservoir to reduce the anaerobic decomposition of organic matter by

organizing forced marling to enhance aerobic decomposition; (iii) the logging of marketable

Page 17: Cameroon

17

timber which can be processed into lumber, which would help to raise CO2 emission levels

from 40 000 tons to 60 000 tons; (iv) increasing the value of timber through charcoal

production. Furthermore, two types of complementary actions will be implemented to reduce

GHG emissions. The first will act on the quantities of GHG emitted at the beginning of

operation of the dam (targeted clearing, partial priming, frequent marling, compensatory

afforestation, etc.). The second will be the optimization of the GHG-free power generation

chain.

7.2 Prevention of Dam Failure Risk

7.2.1 Administrative Responsibility: MINEE, which is the technical supervisory authority

of EDC, is also responsible for ensuring that dam construction activities (WB-funded project)

are in line with the country’s energy policy. The project will appoint an Expert Panel to

ensure that the structure complies with trade practices to help reduce failure risk and establish

an early warning system. In this connection, MINEE will be particularly responsible for

controlling the following aspects: (i) progressive filling (in stages) of the dam according to a

plan to be formulated; and (ii) sensitization of the population of the localities located

downstream of the dam on potential failure risk and its consequences, as well as on what to

do to prevent this risk.

7.2.2 Risks Run: dam failure would cause loss of hundreds of lives mainly in the towns

and villages located along River Sanaga, but would be significantly reduced with the

establishment of an early warning system. The economic consequences would be catastrophic

owing to the destruction of many vital facilities.

7.2.3 Dam Safety Plan: it will be prepared by the Contractor and will include: (i) the

identification of parts of the dam system under construction that may pose problems during

the operation of the dam and cause failure; (ii) an internal plan for communication of such

information; (iii) the list of actions and decisions taken to increase the dam’s robustness and

minimize its failure risk; (iv) measurement and warning mechanisms set up to identify and

measure defects in sensitive parts; and (v) the procedures established to prevent and/or

manage any structural accident during the filling of the dam. The provisional Dam Safety

Plan will be presented to the Project Supervisor and the Client not less than six months before

the start-up of works for comments. The detailed plan will be submitted not less than four

months before the start of works.

8. ENVIRONMENTAL AND SOCIAL MANAGEMENT PLAN (ESMP)

8.1 Implementation and Monitoring of the ESMP

8.1.1 The ESMP will be implemented under State control by the Sub-department of

Safety, Environment and Regional Development of the Lom-Pangar Project, under the

Project Director, assisted by a consultant who has already been recruited. Many Cameroonian

government departments will be directly involved in the future implementation of the ESMP

and, in the short term, the implementation of the CCES. At national level, the departments

concerned must include their interventions in their work programmes, but their interventions

will be more coordinated at the local/regional level. Accordingly, by a regional decision

dated 18 April 2009, the Governor of the East Region established a Monitoring, Facilitation

and Support Committee (abbreviated as CSFA) of the Lom-Pangar ESMP, to be chaired by

the Governor himself or his representative.

Page 18: Cameroon

18

8.1.2 Based on data on the Lom-Pangar ESMP, a plethora of Cameroonian government

departments and communities will be involved in the future implementation of the Plan: 18

ministries at the national level, and the representatives of the East Region, the Lom-Pangar

ESMP Monitoring, Facilitation and Support Committee, the Lom et Djérem Divisional

Office, the Lom et Djérem, and Belabo and Bétaré Oya Sub-divisional Offices and Municipal

Councils, at the local level. The efficient implementation of the ESMP will largely depend on

the quality of relationships between EDC and the Cameroonian administration.

8.1 Schedule

8.2.1 The schedule concerning monitoring by the ADB of the environmental and social

component of the project is as follows:

MONITORING OF THE ENVIRONMENTAL AND SOCIAL COMPONENT

Award and signing of contracts PIU /Contractor/Consulting

Engineer June 2012

Commencement of works

PIU / Contractor / Consulting

Engineer

September 2012 Establishment: Control and

Environmental/Social Monitoring

Unit

Environmental and social supervision ADB - EDC - MINEP 1 mission every

six months

Completion of works PIU / Contractor / Consulting

Engineer September 2015

Environmental and social audit of

works ADB

Borrower’s project completion report PIU November 2015

Project completion report PIU/ADF

January 2016 Analysis of environmental and social

spinoffs

ADF and S/Department of

Environment of EDC, MINEP

8.3 Monitoring During the Design and Construction Phases

8.3.1 Project Team: from the onset, it has benefitted from advice from the Ministry of

Environment, the Ministry of Energy and Water Resources, and the SDSEDR of EDC.

During construction works, the Project Supervisor as well as the representatives of the

relevant ministries and their regional services will ensure compliance with the laws in force:

protection of the physical, natural and human environments. The construction of various

engineering structures will be carried out within the framework of a quality control plan in

line with the measures contained in the Environmental and Social Management Plan.

Contractors in charge of constructing engineering structures will submit their own

environmental and social management plans, demonstrating their knowledge of

environmental and social issues, for validation by MINEP and EDC before the

commencement of work. The main challenges in constructing the impounding dam include

wildlife preservation within a context of the risk of population influx and increased poaching,

Page 19: Cameroon

19

and illegal logging. The air, soil, and water in the area are of good quality and measures will

be taken to ensure their protection during the site preparation phase.

8.3.2 Measures Recommended: measures recommended within the framework of the

construction of the power plant and HV transmission line are: the formulation of plans for the

recruitment of workers for the work sites and the transmission line that meet ADB

requirements concerning local employment. The CCES will be developed accordingly;

control of access to work sites; management of workers’ housing estate, movements and

transportation; road safety measures concerning the movement of staff in charge of the

transportation of goods produced from construction sites and works; health screening during

recruitment and information on STIs, including AIDS; health follow-up in construction sites;

site safety plan; waste management during the construction phase; measures to protect animal

and plant life; development of a commercial area for local trade; prohibition of the opening of

roads near protected areas.

8.3.3 Responsibility of the Client: it will be assumed by EDC, while the EDC

“Environment” Unit will assume that of the Project Supervisor. Contractors will implement

measures while the EDC and the Ministry of Environment will be responsible for control.

8.3.4 Follow-up of the Construction of the Hydroelectric Plant and Transmission

Line: to reduce cost and the impact on the environment, the construction of the plant will be

synchronized with that of the dam. Measures that will be adopted for the dam sites will

directly benefit the hydroelectric plant project. Where the plant is constructed after the dam,

the site management principles will be the same, but will be implemented on a scale adapted

to that of the plant project alone. The construction site, the construction of sub-stations and

the transmission line will be carried out independently of that of the plant.

8.4. Monitoring During the Operation Phase

8.4.1 Monitoring of Ecosystems and Biodiversity: the Project Supervisor will work in

collaboration with the NGOs involved in primate protection, in particular forest protection.

Specific risk sectors will be identified with the help of the NGOs and devices for displaying

cables will be positioned in accordance with accepted standards.

8.4.2 Monitoring of Noise Emissions and Electric and Magnetic Fields: these

parameters will be measured periodically in work stations and in houses near lines and sub-

stations. International standards set by WHO for public exposure limits will be respected.

8.4.3 Follow-up of the Population’s Grievances: as part of the participatory approach

involving the population, a grievance register will be opened in the municipal councils

covered by various project components. The population will be invited to enter their remarks

in the register. EDC will respond to complaints made and take all necessary steps to address

them. Where complaints concern radio, TV and computer disruptions, EDC will conduct the

necessary investigations to identify the exact cause of the disruptions and ways of addressing

them.

8.5 Supervision Plan: In light of the numerous environmental and social impacts of the

project, a comprehensive supervision plan has been developed. With respect to the ADB,

there will be joint missions with operations experts (an environmentalist/ a socio economist)

Page 20: Cameroon

20

and environmental and social compliance experts (a safeguards expert). The following table

details the supervision plan:

The Supervision Plan

Date Activity Mission composition

3rd

trimester

2011

Launching

Engineer/ Task Manager

Procurement Expert

Disbursement Expert

Environmentalist/Socio Economist

Safeguards Expert

1st

trimester

2012

Supervision

Engineer/ Task Manager

Environmentalist/Socio Economist

Safeguards Expert

3rd

trimester

2012

Supervision

Engineer/ Task Manager

Economist/ Financial Analyst

Environmentalist/Socio Economist

Safeguards Expert

2nd

trimester

2013

Supervision

Engineer/ Task Manager

Environmentalist/Socio Economist

Safeguards Expert

4th

trimester

2013

Mid-term

Review

Engineer/ Task Manager

Disbursement Expert

Environmentalist/Socio Economist

Safeguards Expert

2nd

trimester

2014

Supervision

Engineer/ Task Manager

Environmentalist/Socio Economist

Safeguards Expert

4th

trimester

2014

Supervision

Engineer/ Task Manager

Economist/ Financial Analyst

Environmentalist/Socio Economist

Safeguards Expert

2nd

trimester

2015

Supervision

Engineer/ Task Manager

Environmentalist/Socio Economist

Safeguards Expert

4th

trimester

2015

Supervision Engineer/ Task Manager

Economist/ Financial Analyst

2nd

trimester

2016

Completion

Engineer/ Task Manager

Economist/ Financial Analyst

Environmentalist/Socio Economist

Safeguards Expert

8.6 Financing ESMP Activities: the Government's plan to mitigate the environmental

impact of the entire project (financed by WB, EIB, AFD, ADB, etc.) comprises six main

components: (i) mitigation of the biophysical impact, including the Deng-Deng Reserve; (ii)

Page 21: Cameroon

21

resettlement and compensation of the affected population; (iii) restoration of the income of

the affected rural population; (iv) construction of rural infrastructure (RICP); (v) mitigation

of possible impact on health; and (vi) the safety of the population downstream of the dam.

The financing of ESMP activities under the ADB project will cover impact caused by the

construction of the plant, two sub-stations and a transmission line. The overall budget of the

ESMP and RAP will be CFAF 2.71 billion. The tables below summarize ESMP and RAP

cost breakdown by plan and by component:

SUMMARY OF ESMP COST BREAKDOWN

Component CFAF

Protection and consolidation of knowledge of natural environments 33 000 000

Protection of terrestrial habitats and wildlife 429 000 000

Total natural resource management plan 462 000 000

Management of population implosion and personnel movement and

transportation of goods during construction 51 000 000

Health and safety during construction 0

Environmental protection 0

Total construction impact management plan 51 000 000

Cross-cutting activities 900 000 000

Compensation and resettlement of the displaced population RAP

Protection of the cultural heritage and compensation RAP

Community facilities 125 000 000

Health and drinking water 198 000 000

Support for economic activities: farming and livestock component 306 000 000

Total local community development support plan 1 529 000 000

Grand total 2 042 000 000

SUMMARY OF RAP COST BREAKDOWN

Component CFAF

A Individual compensation and resettlement costs 445 125 000

Compensation for fruit trees 227 585 000

Compensation corresponding to one year of food crops 132 000 000

Houses and other buildings 85 540 000

B Collective compensation for villages and camps to be relocated 4 935 000

C Action specific to agriculture 33 000 000

D Project Supervision 75 000 000

Assistance to vulnerable persons and conflict management arrangements 5 000 000

Cost of Technical Unit; Project Supervisor for 3 years 50 000 000

Facilitation by administrative staff, elected officials and chiefdoms 10 000 000

Site monitoring, legal advice 5 000 000

Monitoring and evaluation 2 000 000

Independent audit 3 000 000

Total A+B+C+D 558 060 000

Miscellaneous and contingencies 20 % 111 612 000

Grand total 669 672 000

Page 22: Cameroon

22

9. PUBLIC CONSULTATION AND DISSEMINATION OF INFORMATION

9.1 Information and Public Consultation Mechanisms: from 2003 to date, EDC has

regularly consulted the population and regional authorities during the project design phase

and the preliminary identification of the line corridor and sites for the construction of

transformer stations. EDC and contractors carrying out topographical works will try to reduce

as much as possible the impact on land with the collaboration of landowners affected by the

project. All information relating to the conduct of the project will be transmitted to civil

society, NGOs, administrative authorities and inhabitants of the project area. Damage to

homestead property by line construction works, the opening of access roads, the setting up of

construction sites, and the construction of sub-stations has been identified by the Contractor

for works, in charge of identifying the damage caused and assessing its cost. The list of

persons affected by the project was validated at various administrative and customary levels,

and briefings held within the framework of the Identification and Assessment Commission

chaired by the Governor of the East Region, and consultations conducted by EDC. The

concerned persons are aware of the compensation measures recommended. The consultation

of the population will continue during all project phases. A consultation and complaint

register has been opened in the Communication Centres set up by EDC to ensure the

traceability of such consultation and consideration of the population’s expectations.

9.2 Programming of Meetings: the Project Supervisor as well as consulting firms held

participatory meetings during the preparation of studies. These meetings will continue during

the site preparation, works execution and operation phase to:

relativize the importance of land issues;

present the importance of the project from a social (public health and

education) and socio-economic (development of agricultural and handicraft

activities, stockbreeding, food and trade sectors, initiation of SMEs-SMIs,

women’s empowerment, job creation through power generation) standpoint, as

well as improvement of family welfare, etc.;

present ecological and biodiversity problems;

show the urgent need to execute the project in view of its positive contribution

to: (i) the reduction of pockets of poverty; and (ii) the promotion of

development;

take into account the visual impact of the facilities to be built or rehabilitated;

etc.

10. COMPLIMENTARY INITIATIVES

10.1 Revision of Applicable “Expropriation and Resettlement Procedures”

10.1.1 EDC has defined the exact positions of all sub-stations as well as routes of lines to

be constructed. The total population affected by this project is known and consists of 855

households, of which 16 will be displaced within their localities. So far, dam and plant site

preparatory works have not necessitated the displacement of the population. The impact

assessments and the ESMP which have been prepared present the resettlement and land

acquisition policy framework to be implemented by EDC. It complies with Cameroonian

laws and development bank procedures. The ESMP covers: land acquisition for sub-stations

and pylons; the relocation of houses located directly under HV lines; compensation for loss of

sources of farm income linked to the right-of-way of pylons; compensation for damage due to

temporary use of land for access roads and work sites.

Page 23: Cameroon

23

10.1.2 The process that will be applied takes into account Cameroonian laws as well as

ADB recommendations regarding involuntary resettlement of the population. Concerning

developed land, the law provides that the following right holders are entitled to

compensation: landowners, tenants or occupants, life tenants, owners of trees or any

installation or equipment, and people carrying out a commercial activity on the land.

However, the ADB is extending the right to compensation to a third category of displaced

persons who do not have a legal right or customary claim over the land they occupy in the

project area. They will be entitled to resettlement assistance in lieu of compensation. Without

infringing Cameroonian laws, at least land, houses and facilities will be placed at the disposal

of this marginalized population5.

10.2 EDC’s Capacity Building Programme

10.2.1 Under the project, a feasibility study to build the institutional capacity of the 19

ministries involved in the project and its environmental and social impact will be carried out.

The needs identified, worth a total of CFAF 3.2 billion, will concern technical (particularly

logistic support) as well as human capacity building, with the recruitment of more personnel,

the implementation of appropriate training programmes and acquisition of necessary

documents. The budget is distributed over the four years of project implementation.

10.2.2 For its part, EDC has a Sub-department of Safety, Environment and Regional

Development (SDSEDR) comprising a Safety Service, an Environment Service and a

Regional Development Service supported by environment and social affairs experts. This

sub-department, which will supervise the implementation of the project and monitor its

operation, is currently assisted by an international expert. One of the first tasks assigned this

consultant is to define and assess the specific environmental and social needs of EDC. In its

capacity as Project Supervisor, EDC is responsible for monitoring the RAP. Furthermore,

environmental and social audits will be carried out periodically during project preparation

and implementation.

10.3 Other Actions Planned by the ADB

10.1.1 The Environmental and Social Management component of the project includes

individual compensation and resettlement, collective compensation of villages and camps,

specific agricultural activities, environmental monitoring as well an information, education,

and communication campaign (IEC) on the negative impact of the project and recommended

mitigative measures, as well as actions to control energy use (MCE), which will contribute to

sensitizing subscribers to ensure less and judicious consumption of available electrical

energy. The project will also carry out specific commercial activities to increase the number

of subscribers and cover as many people as possible, particularly the most underprivileged

segment of the population. It will also introduce prepayment meters to reduce non-technical

losses and fraud.

11. CONCLUSION

11.1 The project components financed by the ADB, namely the hydroelectric plant, the

sub-station and the HV transmission line, have been classified under the Bank’s

5 These include indigenous groups, ethnic, religious and linguistic minorities and stockbreeders that may have rights of usufruct over land

and other resources expropriated for the project.

Page 24: Cameroon

24

Environmental and Social Category 1. They were the subject of detailed environmental and

social assessments conducted within the framework of the overall environmental and social

assessment of the entire project. An Environmental and Social Management Plan specific to

the ADB project has been prepared.

11.2 The corridor of the HV power transmission line will necessitate the felling and

pruning of trees (approximately 528 ha of forest ecosystem); some sections of the line will be

located in wetlands (marshes). The socio-economic impact will boil down to the destruction

of food crops (about 48 ha). The Deng-Deng National Park covering a surface area of nearly

59 000 ha has been set up to compensate for the loss of biodiversity due to the construction of

the dam and creation of the reservoir.

11.3 During the operation phase, the impact in the interconnected zones will, on the

whole, be positive and will mainly concern social domains (new opportunities for economic

diversification and enhanced public service efficiency). The project takes into account

climate warming by developing a significant hydropower potential. The Bertoua thermal

power plant will be shut down, but will be maintained as ancillary equipment.

12. REFERENCES AND CONTACTS

12.1 The feasibility studies of the dam and transmission line were completed in 2006. The

final designs of the dam, hydroelectric plant and transmission line were completed in 2010.

Feasibility studies for the electrification of the East Region were completed in 2007 and the

final designs in 2009. The socio-economic surveys of the area were conducted in 2008 and

environmental and social impact assessments were finalized in 2011 with World Bank

financing. The studies include the Environmental and Social Management Plan (ESMP)

incorporating the Natural Resources Management Plan (NRMP), the Construction Impact

Management Plan (CIMP), the Local Community Development Support Plan (LCDSP) and

the Compensation and Resettlement Plan (CRP).

12.2 The following studies were carried out on behalf of Cameroon’s Electricity Sector

Regulatory Agency (ARSEL) and the Ministry of Energy and Water Resources:

(i) Reformulation of the Impact Assessment and Environmental and Social

Management Plan of the Lom-Pangar Dam - Compensation and Resettlement

Plan (CRP) of the Plant and Transmission Line Component, January 2011;

(ii) Reformulation of the Impact Assessment and Environmental and Social

Management Plan of the Lom-Pangar Dam, January 2011;

(iii) Lom-Pangar Dam Project - Regional Development Plan, January 2011;

(iv) Cumulative Impact Assessment of the Lom-Pangar Dam Project, including a

Regional Development Plan, October 2010;

(v) Reformulation of the Environmental and Social Assessment of the Lom-

Pangar Hydroelectric Project. Environmental and Social Assessment (ESA)

Report, January 2011;

(vi) Background of the Integration of Environmental and Social Aspects in the

Project Design, July 2010;

Page 25: Cameroon

25

(vii) Feasibility Study of the Archaeological Resource Management Plan, January

2011;

(viii) Implementation of Compensation for Biodiversity: Deng-Deng National Park,

January 2011;

(ix) Progress Report of the Health Component, January 2011;

(x) Institutional Capacity Building Feasibility Study, June 2010.

12.3 CONTACTS

Electricity Development Corporation (EDC)

Théodore NSANGOU

Director General of EDC

B.P. 15 111 YAOUNDE

Republic of Cameroun

Tel : (237) 22.23.10.89

Fax : (237)22.23.11.13

E-mail : [email protected]

Alphonse EMADAK, PhD

Assistant Director, Security, Environment and Regional Development

Lom Pangar Project Secretariat

P.O. Box 15 111 Yaoundé - Cameroon

Tel: +237 77 75 65 93 / 94 28 73 65

Email: [email protected]

African Development Bank

Valentin ZONGO Division Manager, Energy 1

African Development Bank

Energy, Environment and Climate Change Department

BP 323 - 1002 Tunis Belvédère, Tunisia

Tel : (216) 71 10 33 52

Email : [email protected]

Kurt LONSWAY Division Manager, Environment and Climate Change

African Development Bank

Energy, Environment and Climate Change Department

BP 323 - 1002 Tunis Belvédère, Tunisia

Tel : (216) 71 10 33 13

Email : [email protected]