cabinet committee report on power supply in nigeria 2007
DESCRIPTION
This document represents the full text of a committee report chaired by Mallam Nasir El-Rufai which was presented to President Obasanjo in April 2007 on the status of the electric power sector in Nigeria. During the three months duration of the Committee, we raised actual generation from 1550MW to 3200MW, and had 10,000MW on course to be achieved by December 2007. Sadly, we are now back to generating about 1500MW, meaning there has been no improvement in Nigeria's power sector in the past five years.TRANSCRIPT
REPORT OF THE PRESIDENTIAL COMMITTEE ON POWER
SUPPLY IMPROVEMENT IN THE SHORT AND MEDIUM TERM
MAY 2007
CONTENTS Endorsement Sheet 6 Executive Summary & Recommendations 7 Outline of Report 13 Membership of the Committee 15 Terms of Reference 18 Chapter One Background/Overview of the Power Sector 19 State of the Power Sector Pre-1999 19 Post 1999 to Date 21 Gas Supply Snapshots 24 Power Supply Crisis 26 Chapter Two Visitation to Ongoing and Existing Power Plants 27 Summary of Visitation 27 Recommendations from Visitation 32 Chapter Three Short Term Interventions 35 Gas Supply Improvement 35 Generation Improvement 36 Transmission Improvement 37 Distribution Improvement 37 Sector Reforms Issues & Regulation 38 Renewable Energy and Energy Efficiency Measures Improvement 40
Chapter Four Medium Term Intervention 43 Gas Portfolio Management 43 Gas Supply Status 44 Gas Supply Improvement 48 Generation Improvement 49 Potential Hydro Projects 50 Alternative Energy Sources/Power Generation Potential from Coal 55 Renewable Energy and Energy Efficiency 56 Human Asset Management 57 Annexure Annex I Reports of Visitation to Existing and Ongoing Power Plants Annex II Sub-committees Submission on Terms of Reference Annex III National Integrated Power Project: Financial Input to the Committee Annex IV List of Documents Reviewed Annex V Gazetted copy of MYTO Annex VI Minutes of Committee’s Meetings Figures Fig 1.1 Pre-1999 Government Funding of the Nigerian Power Sector
3
Fig. 1.2 Per Capita Electricity Consumption vs Per Capita GDP (Real Term) 2003 Fig 1.3 Electric Power Sector Funding 1999 – 2007 Fig 1.4 Sectoral Allocation of Approved Capital Expenditure 1999 – 2006 Fig 1.5 Annual Gas Consumption Fig 1.6 Energy Generation (GWH) 2000 – 2006 Fig 1.7 Existing Gas Plants and Capacities Fig 3.1 Pipeline Vandalisation Fig 4.1 Overview of Gas Supply Plan Tables Tab 1.1 Network Reinforcement 2000 – 2006
Tab 1.2 Gas Plan Supply Capacity Tab 2.1 Summary of Reports on Visitation to Power Plants Tab 3.1 Estimated Capacity of Explored Renewable Resources Tab 4.1 Gas Supply to Geregu, Omotosho, Papalanto and Alaoji Plants Tab 4.2 Gas Supply to National Integrated Power Projects Tab 4.3 Gas Supply to Joint Venture Power Plants Tab 4.4 Overhaul & Remedial Works in Existing Power Stations Tab 4.5 List of Independent Power Projects Licensed by Nigerian Electricity Regulatory Agency Tab 4.6 Operable Small Hydro in the Medium Term
4
Acronyms Bureau of Public Enterprises BPE Capital Expenditure CAPEX Economic Community of West African States ECOWAS Electric Power Sector Reform EPSR Electric Power Sector Reform Act EPSRA Electricity Corporation of Nigeria ECN Escravos Lagos Pipeline Systems ELPS Electric Power Research Institute EPRI Federal Government of Nigeria FGN Generating Companies Gencos Giga Watt Hour GWH Gross Domestic Product GDP Gas Supply Purchase Agreement GSPA Independent Power Producers IPP Joint Venture JV Kilo Volts KV Low Pour Fuel Oil LPFO Letter of Credit LC Million Standard Cubic Feet MSCF Mega Watt MW Mega Volt Ampere MVA Multi-Year Tariff Order MYTO National Integrated Power Project NIPP National Electric Power Authority NEPA National Economic Empowerment and Development Strategy NEEDS National Office for Technology Acquisition and Promotion NOTAP Niger Dams Authority NDA Nigerian Electricity Regulatory Commission NERC Nigerian Gas Company NGC Nigerian National Petroleum Corporation NNPC Nigerian Electricity Liability Management Company NELMCO Nigerian Electricity Supply Industry NESI Power Holding Company of Nigeria PHCN Power Sector Reform Act PSRA
5
Power Purchase Agreement PPA Public Private Partnership PPP Rural Electrification Agency REA Shell Petroleum Development Company SPDC Turn Around Maintenance TAM Trillion Cubic Feet TCF West African Power Pool WAPP
ENDORSEMENT Nasir Ahmad el-Rufa’i (OFR) Hon. Minister, Federal Capital Territory
Bala M. Borodo Hon. Minister, Mines & Steel Development
Frank Nweke Jr Hon. Minister, Information & Communication Turner Isoun Hon. Minister, Science & Technology J. O. Makoju Special Adviser to the President (Electric Power)
F. A. Somolu Senior Special Assistant to the President (Power Reform)
A. O. Adegbulugbe Special Adviser to the President (Energy)
Irene Chigbue Director-General, Bureau of Public Enterprises
Peter Odili Executive Governor, Rivers State Edmond Daukoru Hon. Minister, Energy Adamu Bello Hon. Minister, Agric & Water Resources Elias N. Mbam Hon. Minister of State (Finance) Funsho Kupolokun GMD, Nigerian National Petroleum Corporation Abubakar S. Sambo Director General, Energy Commission of Nigeria
Ransome Owan Chairman, Nigerian Electricity Regulatory Commission
J. O. Ayodele Power Holding Company of Nigeria
EXECUTIVE SUMMARY AND RECOMMENDATIONS
The Committee on Power Improvement was set up by His Excellency, President Olusegun
Obasanjo, GCFR in April 2007 under the Chairmanship of the Minister of Federal Capital
Territory, Nasir Ahmad el-Rufa’i, OFR to proffer short to medium term interventions
addressing the then dwindling Electric Power Supply situation in Nigeria. Following its
inauguration on 5th April 2007, the Committee, which comprised the major organizations
and key individuals in the Power Sector obtained and reviewed several documents.
Members also undertook study tours to fourteen (14) out of the seventeen (17) Power
Plants across the country.
1.0 SUMMARY
1.1 The fall in power generation prior to the setting up of the Committee, resulting
in power rationing and attendant load shedding called for concern. Generation
fell below 2,200MW on many occasions compared to the usual level of
3,500MW.
1.2 The fall in generation could be attributed to the vandalized gas pipeline along
Escravos and eventual drop in gas supply to Thermal Stations due to the
presence of condensate in the pipeline that necessitated “pigging”.
1.3 The presence of condensate in the pipelines was due to wet gas from Shell’s
Utorogu Plant and the demand pressure on the gas pipeline, which had
hitherto, fallen well below the usual level before the vandalization of 18th
February 2006.
1.4 The fall in generation can further be attributed to the shortfall in water system
in the Hydro Stations. As a result of the drop in gas supply, which also led to
the drop in the Thermal Stations, Hydro Plants that were on water management
were used to supplement power generation.
1.5 The need to find alternative sources of electric energy to supplement the
existing ones and to diversify fuel mix in the Sector cannot be overemphasized.
1.6 There is need to supplement the funding of the existing Power Plants,
Transmission and Distribution infrastructure.
1.7 Maintenance programs were not undertaken as and when due in the PHCN
System due to poor funding as it appeared that the existing infrastructure,
8
which are old and fragile were compromised with the funding of new
infrastructure.
1.8 There is need to further explore gas development for the Power Sector and
other sectors. Although natural gas exists in abundance, the production for
power generation is inadequate.
1.9 The residual PHCN issues with respect to its successor companies need to be
reviewed. It is obvious that the unbundling left some gaps in the coordination of
activities.
1.10 The Power Sector requires continuous funding especially when the tariff system
does not allow for economic return on investment. While the unbundling
activities went on, the funds for the continuous operation of PHCN
infrastructure was compromised. This has resulted in a situation where several
power and distribution transformers failed and cannot be replaced. Generation
and Transmission infrastructure have the same problem.
1.12 Practically all senior positions in this technology-intense Sector are manned by
Nigerians and this should be noted and encouraged. However, as a result of
years of inadequate funding, manpower development and capacity building in
the Power Sector were neglected. Consequently, the Sector is witnessing
shortage of requisite skills in adequate quantity and quality.
1.11 Timely completion of NIPP and FGN Power Projects is being hampered by delays
in the provision and processing of funds for the projects and by lingering
community issues.
2.0 RECOMMENDATIONS
2.1 SHORT TERM
2.1.1 Ongoing effort, following access to the vandalized Escravos Gas Pipeline,
should be sustained and completion of the repair work as scheduled in June
2007 ensured. Completion of the work will also minimize the presence of
condensate leading to “pigging”.
2.1.2 Discussions with Shell on the upgrade of the Utorogu Gas Plant must
commence immediately. The choice of appropriate well selection to limit liquid
production should also be explored.
9
2.1.3 The expansion process of the ELPS capacity should be expedited. The contract
should be awarded immediately.
2.1.4 NNPC should be directed to, as a matter of urgency, commence a project to
link the Eastern Natural Gas Network to the Western Gas Network for greater
flexibility and to enable diversion of supply capacity in the East to the West
and vice-versa.
2.1.5 Completion of the on-going PHCN Power Stations in Geregu, Omotosho,
Ibom I, Olorunsogo and Alaoji should be expedited to ensure that power
generation is improved. The adjoining Transmission Line projects to evacuate
the power generated should be hastened to ensure completion.
2.1.6 The FGN should sustain funding for PHCN Headquarters to cover common
industry liabilities (gas supply, laboratory, etc) during transition.
2.1.7 The FGN should provide funds to complete some of the ongoing rehabilitation
of/repairs in Afam, Delta III & IV, Sapele, Kainji, Jebba and Egbin Power
Stations. Transmission and Distribution infrastructure also need a lot of
interventions to replace obsolete equipment and damaged transformers.
2.1.8 Revitalization of existing Finance Committee, which consists of the Federal
Ministry of Energy, Federal Ministry of Finance, National Integrated Power
Project, Central Bank of Nigeria and the Accountant General of the Federation
to resolve observed bottlenecks and facilitate the administration of financial
issues in respect of all NIPP projects.
2.1.9 To ensure quick intervention in power generation, Egbin Power Station must
keep adequate stock of LPFO at all times. This will ensure Unit ST04 can
produce electricity in the absence of gas.
2.1.10 The FGN should strengthen the coordination framework during the transition
in a manner that ensures the enhancement of sector efficiency.
2.1.11 In order to consolidate the progress made in the reforms in the Sector,
managed transition process effectively, attract private investment and
increase competition, NERC needs to introduce the new tariff regime without
further delay.
2.1.12 The risk faced by Generating Companies need to be addressed through
effective Securitization if further investment in the Sector must be attracted.
Stakeholders should meet and conclude on the package for securitization.
10
2.1.13 The transition trading arrangements, especially as they concern the
participation of NELMCO in the procurement of new capacity, the use of
vesting contracts and the phased introduction of bilateral contracting need to
be firmly resolved and implemented.
2.1.14 The National Energy Policy, Renewable Energy Master Plan and the National
Energy Master Plan should be instituted through an Act of National Assembly.
2.1.15 There is a need to develop and site Small Hydro Plants and Solar-based village
pilot schemes.
2.1.16 Immediate provision of the required funds to BPE to settle severance
packages for PHCN staff that will be affected by the restructuring exercise. All
labor related issues should be completed as quickly as possible.
2.1.17 A skills gap analysis in the Power Sector needs to be carried out to determine
the existing skills and competencies, identify areas of deficiency, and
recommend appropriate measures for skills and capacity development.
2.2 MEDIUM TERM
2.2.1 The major portfolio interventions presently embarked upon by NNPC to
enhance seamless management of gas supply to Power Plants must be given
adequate support by all the Government agencies and regulatory bodies
involved.
2.2.2 The central issue of integrated resource planning particularly as it relates to
bridging the wide gap between demand and supply of electric power energy
must be given top priority. The issues raised in the 25-year Power Sector
Development Report should be implemented to forestall further crises.
2.2.3 There is the need to adopt NNPC’s proposed legislative intervention, which
makes it mandatory for gas operators to meet domestic demand before
export.
2.2.4 Adequate measure to ensure improvement and protection of gas supply to
existing and on-going Power Plants must be fully entrenched.
2.2.5 Shell and other producers of natural gas for electricity generation should be
directed to upgrade the performance of their flow stations to ensure that gas
supply for power generation meets the specifications in Gas Supply Purchase
Agreement (GSPA).
11
2.2.6 Comprehensive rehabilitation of the ageing Power Plants (thermal and hydro)
through execution of units overhaul and remedial works is mandatory in order
to achieve optimum plant performance to curb incessant equipment failure
and frequent system collapses.
2.2.7 Enhance the timely completion of on-going power expansion projects by
ameliorating all the identified bottlenecks - financial, technical and
environmental.
2.2.8 Facilitate further expansion of the nation’s power generation base through
provision of attractive and investor friendly incentives to create a conducive
climate for active participation in power production.
2.2.9 Explore and exploit the abundant alternative renewable energy sources to
achieve increased availability and wider spread of electric power supply in the
country.
2.2.10 Actualize the realization of Hydropower projects through installation of
turbines in known completed dams and development of identified hydropower
potential sites.
2.2.11 Establish appropriate staffing structure for the Sector through the
implementation of the recommended phased restructuring of PHCN staff,
injection of competent and qualified manpower and development of
specialized training institution to address the human capacity requirements of
the Sector.
2.2.12 The need to adopt the energy mix strategy for the generation of power
cannot be overemphasized. The present arrangement where generation
capacity is over 2:1 in favour of thermal needs to be balanced, considering the
inadequacy of gas supply in the short and medium term. Future
overdependence of power generation on thermal should be reviewed and
efforts geared towards active participation in other generation fuel sources.
2.2.13 There is need for the FGN to provide an investor friendly environment for the
utilization of the abundant coal reserve for power generation.
2.2.14 The process of procuring spare parts for the Power Plants should be relaxed
especially for emergency cases, to ensure speedy repairs.
2.2.15 Power Plants spare parts manufacturers should be encouraged to setup
manufacturing plants in the country to ensure availability.
12
2.2.16 For new Power Projects, there is need for the involvement of State and Local
authorities at conceptualization stage to curb community restiveness. Also,
various project site options should be considered and selection made based on
willingness of communities to facilitate peaceful work on site.
2.2.17 The two-pronged approach of strengthening existing institutions for capacity
building and encouraging the Private Sector to establish a world-class training
institute for manpower development should be adopted.
13
OUTLINE OF REPORT
This report is divided into four (4) chapters as enumerated below:
Chapter One (1) provides an overview of the Electric Power Sector from inception in
1886, through the era of Niger Dams Authority, Electricity Corporation of Nigeria, National
Electric Power Authority (NEPA) and the Power Holding Company of Nigeria (PHCN) Plc
being an entity that was recently created in furtherance of the reform programme for the
Sector.
The chapter highlights issues regarding funding in the sector; generation capacity in
relation to other emerging economies like Iran and South Africa; and, the state of
infrastructure pre-1999. It presents key reform activities of the Obasanjo Administration
including the milestones achieved by the reform implementation agency, the Bureau of
Public Enterprises (BPE), which include the unbundling of PHCN, creation of successor
companies, establishment of a sector regulator, Nigeria Electricity Regulation Commission
(NERC) and a Rural Electrification Agency (REA).
Finally, the chapter identifies the challenges that culminated in the dwindling power
availability in the country and the resulting crisis that led to the constitution of the
Committee on Power Improvement by Mr. President.
Chapter Two (2) reports the fact-finding visits to Hydro and Thermal Power Plants by
the Committee. It presents general and specific challenges/problems that have hindered
their smooth operations and proffers recommendations.
Chapter Three (3) proposes interventions necessary in the short term with regards to
gas generation, transmission and distribution infrastructure; and, funding for the Sector.
The chapter also identifies issues that need to be addressed to enable the reform
programme for the sector to succeed.
Chapter Four (4) proposes medium term interventions required to drastically improve
efficiency in the Power Sector. Amongst others, this chapter emphasizes the need for
14
integrated resource planning and coordination that takes into consideration, demand and
supply levels and growth of the sector. It highlights the need for policies that will make
gas readily available to new Power Plants at completion and meet future expansion plans
of existing plants. It suggests that urgent remedial works need to be undertaken in
relevant Power Plants while stressing the need for timely completion of on-going projects.
It also notes the need to develop incentives to attract investments in the Sector; the need
to develop small hydro stations and other sources of renewable energy; and, the need to
address funding and human capacity issues in the sector.
15
MEMBERSHIP OF THE COMMITTEE
1. Nasir Ahmad el-Rufa’i OFR - Chairman
Minister of Federal Capital Territory
2. Peter Odili - Member
Executive Governor, Rivers State
3. Edmond Daukoru - Member
Minister of Energy
4. Frank Nweke Jr. - Member
Minister of Information & Communication
5. Bala M. Borodo - Member
Minister of Mines & Steel Development
6. Adamu Bello - Member
Minister of Agric & Water Resources
7. Elias N. Mbam - Member
Minister of State (Finance)
8. J. O. Makoju - Member
Special Adviser to the President (Electric Power)
9. F. A. Somolu - Member
Senior Special Assistant to the President (Power Reform)
10. A. O. Adegbulugbe - Member
Special Adviser to the President (Energy)
16
11. Funsho Kupolokun - Member
Group Managing Director
Nigerian National Petroleum Corporation
12. Ransome Owan - Member
Chairman, Nig. Electricity Regulatory Commission
13. Irene Chigbue - Member
Director-General, Bureau of Public Enterprises
14. Abubakar S. Sambo - Member
Director General, Energy Commission of Nigeria
15. J. O. Ayodele - Secretary
Power Holding Company of Nigeria
16. Hauwa Yabani - Secretariat
Special Assistant to the FCT Minister
TECHNICAL TEAM
17. S. Maigida - Power Holding Company of Nigeria (PHCN)
18. M. A. Ganiyu - PHCN
19. J. A. Akinola - Federal Ministry of Agriculture and Water
Resources
20. H. Nggada - Federal Ministry of Energy
21. Sam J. Agbogun - Bureau of Public Enterprises
17
22. Gabby Meheux - Nigerian National Petroleum Corporation
23. A. A. Esan - UNIDO Regional Centre
24. O. C. Iloeje - Nigerian Electricity Regulatory Commission
(NERC)
25. Usman Abba Arabi - NERC
26. C. O. Ukabiala - NERC
27. O. N. Ekpenyong - Energy Commission of Nigeria (ECN)
28. I. J. Dioha - ECN
29. Christian C. Okeke - Federal Capital Territory Administration
18
TERMS OF REFERENCE
1. Review the current electric power situation in the country.
2. Proffer short term interventions to improve the situation.
3. Review the ongoing power sector reforms and comment as appropriate.
4. Identify other energy sources and energy efficiency measures.
5. Make recommendations for medium term interventions.
6. Identification of asset management & infrastructure needs and suggestions on
human resource transformation and sector funding.
7. Conclusions and recommendations.
19
CHAPTER ONE
1.1 BACKGROUND/OVERVIEW OF THE POWER SECTOR
1.1.1 Evolution of the Power Sector
Electric power supply in Nigeria dates back to 1886 when two (2) small generating
sets were installed to serve the then Colony of Lagos. By an Act of Parliament in
1951, the Electricity Corporation of Nigeria (ECN) was established, and in 1962, the
Niger Dams Authority (NDA) also established for the development of Hydro Electric
Power. However, a merger of the two (2) was made in 1972 to form the National
Electric Power Authority (NEPA), which as a result of unbundling and the power
reform process, was renamed Power Holding Company of Nigeria (PHCN) in 2005.
1.1.2 State of the Sector Pre-1999
The Power Sector before 1999, was in a deplorable state due to poor funding and
inadequate infrastructural development. For over ten (10) years prior to 1999, the
Sector did not witness substantial investments in infrastructure, (see fig. 1.1), while
poor funding left the existing infrastructure in a state of decay.
FFiigg.. 11..11
GGoovveerrnnmmeenntt FFuunnddiinngg ooff tthhee NNiiggeerriiaann PPoowweerr SSeeccttoorr ((11997744 –– 22000011))
0
50
100
150
200
250
300
350
400
450
500
1974
1975
1976
1977
1978
1979
1980
1981
1982
1983
1984
1985
1986
1987
1988
1989
1990
1991
1992
1993
1994
1995
1996
1997
1998
1999
2000
2001
Mill
ions
$
Period of poor Funding & Neglect of the Nigerian Power sector
20
The lack of maintenance and replacement of damaged equipment led to a wide gap
between demand and supply. Generation went down from the installed capacity of about
5,600MW to an average of about 1,750MW, as compared to a load demand of 6,000MW.
At the same time, only nineteen (19) out of the seventy nine (79) installed generating
units were in operation. The net implications of the above on the Power Sector include but
are not limited to massive load shedding, voltage and control problems, frequent system
collapse, public outcry and bad image for the Utility and above all, low economic activities
due to high cost of self generation.
Whereas power generation capacity in Nigeria was about the same with Iran (about
2,000MW) in the 70’s, today Iran has a generation capacity of over ten (10) times that of
Nigeria. Similarly, South Africa has capacity of over 36,000MW, while Egypt generates over
23,000MW.
Figure 1.2 below shows the per capita electricity consumption versus per capita Gross
Domestic Product (GDP) for selected countries with similar history of economic
development as Nigeria.
Per Capita Electricity Consumption versus Per Capita GDP (Real Term) 2003
0
1000
2000
3000
4000
5000
6000
7000
8000
9000
0.00 5000.00 10000.00 15000.00 20000.00 25000.00
Per Capita GDP (Real Term) (2000US$/Cap)
Per C
apita
Ele
ctric
it C
onsu
mpt
ion
(kW
h/C
ap)
Fig 1.2
Nigeria India Algeria
China Brazil
Libya
S/ Africa
Saudi Arabia
Singapore
ChileMalaysia
Low Income
Countries
Middle Income
Countries
High Income
Countries
21
1.1.3 Post 1999 to Date
The Government expressed its determination to tackle the poor state of the
Power Sector and the first step was the setting up of a Technical Board, to
amongst others;
! Address the issue of collapsing infrastructure;
! Rehabilitate some of the generating stations, transmission and distribution
infrastructure;
! Commence the unbundling of NEPA for improvement in efficiency; and,
! Prepare grounds for private sector participation.
The Technical Board between 2000 and 2001 embarked on the above and
succeeded in improving generation capacity from 1,800MW to just below
4,000MW. In addition, the Power Sector Reform Act (PSRA) was passed and
signed into law in 2005, which gave birth to PHCN and the restructuring
exercise to, amongst others, achieve:
- Development of competitive electricity market and creation of market
operations;
- Creation of Successor Companies out of the PHCN Structure;
- Private Sector Participation (Independent Power Plants (IPPs), Joint
Venture (JV) - IPPs etc) ;
- Establishment of Regulatory Agency; and,
- Establishment of a Rural Electrification Agency
With the support and commitment of the Federal Government, the Sector
began to witness better funding. For example, a total of N249 billion was
injected into the Sector between 1999 to date (See Fig. 1.3) as inflow to the
existing infrastructure, while another N250 billion has so far been expended
on new projects under the National Integrated Power Project (NIPP).
22
Electric Power Sector Funding 1999 to 2007
Fig 1.3
These have led to substantial improvements in generation capacity, transmission and
distribution networks. A phenomenal increase in PHCN’s monthly revenue was also
experienced from about N2 billion to over N7 billion monthly.
A lot of infrastructural projects were also completed, including the Abuja-Shiroro 330kV
project, Owerri-Ahoada 132kV project, Kano-Azare 132kV project, Ikeja-West-Sakete
330kv (Benin Republic) under the WAPP (ECOWAS) project, 34 Transmission Substations
reinforcement projects, and the Afam V Power Station expansion project. (See fig 1.4)
38
!"#$%&'(!"#$%&'( )((%#'$*%+,%-,)..&%/"0,1)234,5666,)((%#'$*%+,%-,)..&%/"0,1)234,5666,77 899:899:
-
5,000.0
10,000.0
15,000.0
20,000.0
25,000.0
30,000.0
35,000.0
40,000.0
1999 2000 2001 2002 2003 2004 2005 2006 YearGener ation Tr ansmission Distr ibution
Fig 1.4
Electric Power Sector Funding from 1999 to 2007
0200400600800
100012001400160018002000
1999
2000
2001
2002
2003
2004
2005
2006
2007
Year
Mill
ion
Dol
lars
23
Table 1.1 below shows the summary of network reinforcement between 2000 and
2006, while Fig. 1.5 also shows the gas consumption pattern to support the
increase in generation witnessed during the same period.
Table 1.1
Fig. 1.5
Annual energy generation increased from 22,000GWh to above 35,000GWh
between 2000 and 2006 (See Fig. 1.6)
Network )einforcement /2000 2 20064
63.312,2507,500Distribution Capacity (MVA)
36.415,00011,000Transmission Capacity (MVA)
71.536.021.0Bulk Energy Delivered (GWH)
85.03,7762,500Highest Daily Peak (MW)
48.54,0902,753Installed Available Capacity (MW)
% Change20062000
63.312,2507,500Distribution Capacity (MVA)
36.415,00011,000Transmission Capacity (MVA)
71.536.021.0Bulk Energy Delivered (GWH)
85.03,7762,500Highest Daily Peak (MW)
48.54,0902,753Installed Available Capacity (MW)
% Change20062000
0.00
50.00
100.00
150.00
200.00
250.00
300.00
350.00
1992 1993 1994 1995 1996 1997 1998 1999 2000 2001 2002 2003 2004 2005 2006
x 10
00m
scf
Annual Gas Consumption
24
Fig 1.6
1.1.4 Gas Supply Snapshots
A total of ten (10) operational Gas Plants supply about 920mmscf/d of gas to all existing
PHCN Power Plants (See Fig 1.7). This translates to a generating capacity of 3,200MW
(2,400MW in the West and 800MW in East) on full load.
Fig1.7
Across most of these Gas Plants, there has been a steady decline in supply capacity
ultimately resulting in a loss of about 500mmscf/d (55%) of installed capacity (Table 1.2).
This in turn has resulted in the drop of generating capacity to an all time low of about
1,350MW.
-
5,000
10,000
15,000
20,000
25,000
30,000
35,000
40,000
2000 2001 2002 2003 2004 2005 2006
Ye a r
GW
H
Energy Generation (GWH), 2000 – 2006
25
Table 1.2 Gas Plant Supply Capacity
The challenge of gas supply to Power Plants in the medium term is of even greater
concern. This is because of the unprecedented step up in gas demand to fuel many new
PHCN and IPP Plants towards the end of 2007. This step up in demand equally applies to
other domestic sectors such as fertilizer, methanol and other similar plants. The
corresponding reserves requirement in this case is equally enormous. Consequently, minor
operational interventions will not mitigate this impending challenge of reserves and supply
development.
1.1.5 Gas Supply Challenges
The shortfall in gas supply to power projects has been occasioned by a number of
challenges, which can be addressed with respect to short and medium term perspectives.
In the short term, recent disruptions of gas supply have been attributed to two (2)
developments. Firstly, there has been a major increase in pipeline vandalisation (over
thirty (30) cases in 2006) which was followed by host community interruptions at areas
where repairs are required. The second development involves condensate build-up in gas
supply pipelines.
The Nigerian Gas Company (NGC) supplies gas to PHCN plants at Egbin via the Escravos -
Lagos Pipeline Systems (ELPS) which is sourced from Chevron and Shell Petroleum
Development Company (SPDC). In February 2006, the ELPS was vandalised by the host
community of Gbaramatu in Delta State. Subsequently, the Community prevented
Nigerian National Petroleum Corporation (NNPC) engineers from gaining access to areas
of damage to undertake prompt and effective repairs with the resultant effect of the
entire Chevron supplies from Escravos being shut off for over a year. The loss of gas
26
supplies from Chevron in turn resulted in the SPDC supplies being the only gas supply
source to the Egbin Power Plant. Historically, SPDC’s Utorogu Gas Plant consistently
introduced gas with high condensate content into the pipeline and this was mitigated by
the much drier gas from Chevron. The resulting disruption had a further unintended effect
of increasing the condensate in the pipeline which led to reduced gas supplies. This was
also compounded by threat of equipment damages with ingress of condensate.
The estimated Proven Gas Reserves is about 181 TCF whilst available Proven Reserves
over a 20-year horizon is limited to about 130 TCF. The Gas Master Plan Study of NNPC
shows that significant reserves (about 50TCF) are cap gas which will eventually be
available in the longer term, say about 15 - 20yrs, from now. Additional gas reserves will
also only be available from later year oil production. Although estimated gas reserves is
about 181 TCF, almost 40% of these will not be available in the short term as they are in
gas caps and not available until much after the production of oil.
1.1.6 Power Supply Crisis
The Sector experienced a dip in power generation primarily from 18th February 2006 due
to the vandalized gas pipeline at Escravos in the Niger Delta area. In year 2007, a major
negative development also took place in the gas supply to Egbin as a result of the
presence of high condensate in the pipeline. Starting from around 18th February 2007,
condensate drop out in the gas had built up to a dangerous level which necessitated
‘pigging’ and eventual temporary shut down of Egbin Complex (Egbin being the largest
Power Plant with the capacity for contributing about 30% of total power generation).
As a result of the loss of over 700MW from Egbin Complex, power generation dropped to
an average of 2,200MW, since some of the Hydro Stations were also experiencing
seasonal water shortage. This led PHCN to embark upon massive load shedding with
consequent deterioration in power supply delivery. In the light of this, the Federal
Government intervened to assist in fast tracking all measures that can be possible to bring
up generation. This also triggered the resolve of the Federal Government to set up this
Special Committee charged with the responsibility of reviewing the Power Sector and
proffering short to medium term solutions to its compounding challenges/problems.
27
CHAPTER TWO 2.0 SUMMARY OF REPORTS ON VISITATION TO POWER PLANTS
Table 2.1
Observed Problems/Findings S/No Station/ Capacity (MW)
Contractor/ Consultant
Financial Technical Environmental Remarks
1 Gbarain, Bayelsa State (225)
Rockson Engineering
Delay in Letter of Credit (LC). Reimbursement by NIPP awaited. Workers wages demand above FGN minimum wage.
Withdrawal of Experts due to kidnappings and militant activities.
Site closures due to youth restiveness. Flooded location as site – sand filling.
Youth disturbances may elongate target.
2 Ibom Power, Ikot Abasi (190, Phase I) (500, Phase II)
PB Power (Group 5)
US $25m bridge facility (Phase I). CBN refusal on foreign exchange payments to Contractors. NOTAP non-approval – Form A.
Eket-Uyo-Itu 132KV line (Phase I) outstanding. Ikot-Abasi-Ikot Ekpene Transmission (trx) line (Phase II) also outstanding.
Youth restiveness. Power evacuation facilities could delay delivery of equipment.
3 Odukpani, Calabar, Cross River (561MW)
Marubeni Engineering
Letter of Credit in operation hence minimal problem.
Lack of adequate surface water – Combined cycle. Delay in gas pipeline award.
Youths restiveness and incessant demands disrupting work. Four (4) interruptions experienced so far.
Delay in delivery of power/
4 Egbin, Ikorodu, Lagos State (1,320)
Marubeni Engineering
Market Operators transfer inadequate for major repairs and capital spares. Procurement process for spares and equipment subject to Government bureaucracy.
Continuous shortage of gas and TAM not implemented. Inadequate LPFO reserve/ logistics of supply. Lack of capacity building in terms of business and commercial activities.
28
Observed Problems/Findings S/No Station/ Capacity (MW)
Contractor/ Consultant
Financial Technical Environmental Remarks
5 Olorunsogo, Ogun State (335)
SEPCO and Construction Corporation, China
Non-opening of LC for 330KV Trx lines. Delayed payments. Non-signing of PLC contract.
33KV Trx line at Ewekoro still awaited. 330KV Trx line delay. Gas yet to be supplied on site.
Community related issues still outstanding.
6 Omotosho, Ondo State (335)
China Machinery and Equipment (Import-Export) Corporation (CMEC)
330KV Trx line yet to be completed. Communication facility to NCC, Oshogbo not yet in place. 33KV Trx line for alternate cold start not in place. Inadequate source of water supply in dry season.
Outstanding community related issues.
Phase I commissioned 17th April, 2007.
7 Omoku (Rivers State) (230)
Rockson Engineering, Steag
Delays in the issuance of Letter of Credit. Contractor’s loan for land compensation not repaid. Various payments to Contractor outstanding. Outstanding liabilities of PHCN on the project not yet taken over by NIPP.
Gas pipeline construction yet to Start. Trx line construction yet to commence.
Latest change in plant concept delaying completion date (3 months).
8 Egbema (Imo State) (338)
Rockson Engineering, Steag
The LC for the remainder of the contract yet to be established. Contractor’s loan for land compensation not repaid.
The construction of gas pipeline outstanding. Contractor loan for land compensation not repaid.
Community problems caused work stoppages.
29
Observed Problems/Findings S/No Station/ Capacity (MW)
Contractor/ Consultant
Financial Technical Environmental Remarks
Various payments to Contractor outstanding. Outstanding liabilities of PHCN on the project not yet taken over by NIPP.
Militant activities hindering presence of Technical Assistants (Foreigners). Outstanding decision on request for 5km road by community.
9. Alaoji (Abia State) (504)
Rockson Engineering, PB Power
Letter of Credit not adequately funded and established for other payments. Increased project risk to the contractor due to delays in consolidation of change orders in contract. Contractor’s loan for land compensation not repaid. Various payments to Contractor outstanding. Outstanding liabilities of PHCN on the project not yet taken over by NIPP.
Gas pipeline construction yet to commence. Contract for the 330KV evacuation line yet to be awarded.
Militant activities hindering presence of Technical Assistants (Foreigners).
10. Shiroro Hydro (Niger State) (600)
Owned by Federal Government of Nigeria
Due Process compliance in the purchase of spare parts and other consumables causes delays.
Spillway gate No. 4 not operational, seal ruptured. Concrete superstructure of spillway gate No. 4 defective. There are cracks in the Power House in several places.
Threat of low water supply to the dam reservoir due to over use and insufficient rainfall in Kaduna River Basin.
30
Observed Problems/Findings S/No Station/ Capacity (MW)
Contractor/ Consultant
Financial Technical Environmental Remarks
A five (5) year inspection of the dam report not complied with. Silting constitutes future threat to operations of the station. Comprehensive overhauling of dam since 1983, yet to be done.
11 Kainji (Niger State)
Owned by Federal Government of Nigeria
Indebtedness (N200.7m) for incurred expenditure and staff salary arrears (12½%).
Plant is old without major comprehensive overhauling. A 3 years circle flood has destroyed units IG5. Inadequate training of technical staff. Substantial power can be generated especially during flood period.
It was observed that out of the regular staff, 568 are non-technical while 282 are technical. This arrangement is inefficient and should receive immediate attention.
12 Jebba (Niger State) (540)
Owned by Federal Government of Nigeria
Water leakages through the expansion joints to the power house walls. Spillway outlet massively eroded its banks; Navigation lock vandalized, needs replacement.
13 Afam Power Station (VI)
SPDC The Financial and legal matters are handled in the SPDC head office.
Security threats by the Youth of Anyana Community. Much money is spent on pacifying them.
31
Observed Problems/Findings S/No Station/ Capacity (MW)
Contractor/ Consultant
Financial Technical Environmental Remarks
14 Geregu (Kogi State) 414MW
Siemens Inadequate supply of gas for the third turbine. Insufficient water for generator cooling.
Shortage of accommodation for operational staff.
32
2.1 RECOMMENDATIONS FROM VISITATION TO POWER PLANTS
2.1.1 General Recommendations on Thermal Plants:
(a) Prompt payment of approved invoices to contractors;
(b) Strengthen relations between host communities through continuous dialogue
and corporate social responsibility;
(c) Improve security of project sites;
(d) Site studies and soil tests to be carried out before handing over to contractors;
(e) Provision of emergency fund for urgent maintenance and upgrade of
equipment in existing plants;
(f) Outstanding letters of credit, as per contract schedule, should be issued
immediately by NIPP to contractor;
(g) Plant concept and site should be firmly established before award of contract to
avoid major mid-stream changes;
(h) Strengthening of existing Finance Committee, which consists of the Federal
Ministry of Energy, Federal Ministry of Finance, National Integrated Power
Project, Central Bank of Nigeria and the Accountant General of the Federation
to resolve observed bottlenecks and facilitate the administration of financial
issues in respect of all NIPP projects;
(i) To curb community restiveness, there is need for the involvement of state and
local authorities at the conceptualization stage;
(j) Various project site options should be considered and selection should be
made based on willingness of communities to facilitate peaceful and
harmonious work on sites;
(k) Ensure Turn Around Maintenance (TAM) activities are carried out as and when
due; and,
(l) Construction of housing facilities for the Plant staff.
2.1.2 Specific Recommendations on Thermal Plants:
Geregu:
(a) Impress on NGC to make gas available for the firing of the third unit when this is
completed in mid-May 2007.
33
Egbin:
(a) Ensure adequate Low Poor Fuel Oil (LPFO) strategic reserve; and,
(b) Address boilers problem.
Olorunsogo:
(a) Accelerate the sourcing of line materials required for the construction of the 330
KV Transmission Line.
Omotosho:
(a) Consider re-awarding the 33KV cold-start line to another contractor in order to
expedite action; and,
(b) Construction of a bigger water reservoir on site because shortage of water is
envisaged during the dry season.
Omoku:
(a) The Contractors and Project Consultant should review the work schedule with a
view to fast-tracking the project.
Egbema:
(a) The Contractor should synchronize the completion of both the Power Plant and
associated Transmission project;
(b) Addax and Shell should ensure the completion of the 12km gas supply pipeline
before commissioning in November 2007;
(c) The 5km road requested by the Mmahu community should be constructed but
linked with sustained community peace; and,
(d) Repayment of loan for land/crop compensation to the Contractor.
Alaoji:
(a) Repayment of loan for land/crop compensation to the Contractor;
(b) Contract for NIPP 330KV evacuation line should be awarded;
(c) Contractor’s loan for land compensation not repaid;
(d) Various payments to Contractor outstanding; and,
(e) Outstanding liabilities of PHCN on the project not yet taken over by NIPP.
34
2.1.3 General Recommendations on Hydro Plants
The cause of current low production levels from the Hydro Plants in the country is due to
seasonal water inadequacy. The following are recommended for improved water supply
to Hydro Plants:
(a) Bathymetric survey to determine level of silting with appropriate measures;
(b) Funds should be made available for scheduled maintenance;
(c) Five year compulsory inspection of Dams to be carried out; and,
(d) Structural overhaul of plant’s facilities to be undertaken as and when due.
2.1.4 Specific Recommendation on Hydro Plants:
Shiroro:
(a) Spillway G4 seal to be repaired; and,
(b) Divert water from Gurara to Kainji lake to shore-up water availability.
Kainji:
(a) Special fund required to pay a debt N144.8M incurred on repairs;
(b) Four open pits to be revisited for possible generation capacity expansion; and,
(c) The three year flood cycle should be harnessed for improved generation.
Jebba:
(a) Need to stop water leakage through expansion joints to avoid flooding;
(b) Lake dredging to remove logs that constitute debris;
(c) Rehabilitation of eroded spillway banks to avoid flooding and environmental
degradation; and,
(d) Repair of damaged navigation lock.
35
CHAPTER THREE
3.0 SHORT TERM INTERVENTIONS
The Committee has come up with measures for improvement in the short-term
(defined as zero to ninety days). These were guided by the following issues;
a. Gas Supply challenges and availability in the right quantities and quality.
b. Power Generation, Transmission, Distribution and Power Sector Reform
related issues.
c. Funding related issues, especially with respect to the new Successor
Companies of PHCN.
3.1 GAS SUPPLY IMPROVEMENT
3.1.1 Gas Supply Shortfall
As stated earlier, the Gas Supply to existing Power Plants in the country is about
400 mmscf/d compared to the total gas requirement of about 920 mmscf/d. This
was occasioned by the damage to the Escravos Gas Pipeline and the subsequent
restriction of access to the damaged pipeline which prevented prompt and
effective repairs. Additional supply challenges also resulted from condensate
build-up in the Escravos Pipeline.
Figure 3.1 below shows the points of vandalization and the dates they occurred.
Fig 3.1
PIPELINE VANDALISATION NGC Statistics
There was over 30 cases of major gas pipeline vandalization in 2006, representing a major increase compared with previous years. Denied access has prevented prompt and effective repairs
36
3.1.2 Gas Supply Interventions
In consideration of the current gas supply challenges, a number of interventions have
become imperative. These are:
! Expedite repair works on the vandalized Escravos Pipeline to ensure completion
by June 2007.
! Initiate discussions with Shell on the upgrade of the Utorogu Gas Plant in order to
limit condensate production and ensure appropriate well selection to limit liquid
production.
! According to the NNPC, the expansion of the ELPS capacity is being pursued on a
fast track basis with contract award expected in Q2 2007.
3.2 GENERATION IMPROVEMENT
The major draw back in the supply of electricity in Nigeria is the big gap between
demand and supply. Presently, the supply of electricity even with many of the plants
running is very much short of meeting the demand. The following are therefore
recommended:
3.2.1 Completion and Upgrade of Power Plants
a. Completion of Geregu Power plant slated for May 2007. At the moment, the
Power Plant delivers 276MW into the Grid. When the Plant is finally completed in
May 2007, an extra 138MW can be delivered into the system.
b. Completion of Omotosho and Olorunsogo Power Stations, each of which will
deliver 335MW to the system. While Omotosho will be completed by June 2007,
Olorunsogo will be completed by July, 2007.
c. Completion of the various repair programs in Delta, III and Delta IV which can
bring back about 200MW additional generation.
d. Completion of Ibom I Power Station for additional power of 300MW.
e. Ensure adequate stock of LPFO in Egbin to provide continuous backup especially
during any gas supply disruption.
f. Provision of supplementary funding for all the existing Power Stations to carry
out minor maintenance and stock some fast moving spares.
37
3.2.2 Financial Implications
In all, to assist in raising the generation in the existing Power Plants to their near
optimum capacity, a total sum of N2.8b will be required for the procurement of fast
moving items such as filters, all the Generation Stations (breakdown attached as
Annex III).
3.3 TRANSMISSION IMPROVEMENT
Transmission improvement can be embarked upon in the replacement of obsolete
Circuit breakers, Reactors, Transformers, Current and Voltage Transformers and
relays system. New transmission lines can be accommodated under the Medium
Term arrangement. However, some of the on-going transmission line
reinforcement projects can be on fast track to support increased generation
resulting from actions in 3.2 above.
3.3.1 Financial Implications
A sum of N4.7b will be required to address the immediate bottlenecks in this
Sector (see breakdown in Annex III).
3.4 DISTRIBUTION IMPROVEMENT
Since the reform program started in 2004, there has been a total neglect in
funding to the Distribution Sector on the assumption that they are to be
privatized. This has created a situation whereby the existing aged infrastructure
break down and no replacements are made. The successor companies are not
getting enough funds to address the ageing systems despite increased revenue
from sales. The fact is that the Power Purchase Agreements (PPAs) signed with
AGIP and AES with a monthly commitment of about N2.4 billion is an added
burden on PHCN revenue without adequate tariff to cushion them.
3.4.1 Financial Implications
A recent survey made on the Short Term intervention revealed that a sum of N6.9
billion will be required to address the immediate need to replace damaged
transformers and other equipment (see breakdown in Annex III).
38
3.5 SECTOR REFORMS ISSUES AND REGULATION
3.5.1 PHCN Liaison Unit
There is a need to come up with a framework for the coordination of the Power
Sector. The need for a coordination center cannot be overemphasized while
bearing in mind that there are issues of common concern that may affect several
successor companies, which no company may be able to address alone. For
example, the issue of gas and water management for companies sharing the
same water flow needs to be coordinated. Energy crises can not be addressed by
one company alone, but by concerted efforts of stakeholders.
3.5.2 Reform and Regulation
In spite of of the progress of the Power Sector reforms, a number of issues have
to be addressed in the short term and appropriate measures taken in order to
consolidate the gains made, manage the transition process effectively, attract
private investment, increase competition and set the Sector firmly towards the
medium term. Some of these issues are discussed below:
3.5.2.1 Tariff Reform
The most important risk factor faced by existing and prospective operators in the
Nigerian Electricity Supply Industry (NESI), is the current reality of insufficient
liquidity in the Sector to ensure recovery of costs and adequate returns on
investment. NERC has developed a Multi-Year Tariff Order (MYTO) to address the
issue. The Order provides a 15-year tariff path for the Sector, recalculates the
tariff every five years and slightly modifies the values annually, depending on
changes in fuel prices, exchange rate and inflation rate. In compliance with the
requirement of Electric Power Sector Reform Act (EPSRA), NERC has gazetted and
published the tariff methodology (copy attached as Annex V) prior to its
implementation. In order to permit the successor companies to achieve the
independence necessary for effective operation in the Sector and remove the
financial risk referred to above, NERC needs to introduce the new tariff regime
without further delay.
39
3.5.2.2 Securitization
With the recently gazetted MYTO, it is now certain that the tariff will not rise to
the level of:
a) being able to attract Private Sector investment; and,
b) provide the revenue need of the industry within the first few years of its
introduction.
Furthermore, the Distribution Companies are yet to demonstrate their ability to
collect revenues efficiently and regularly pay for the power purchased. These risks
faced by Generating Companies need to be addressed through effective
securitization, if the required investments are to be attracted to the Sector. The
stakeholders, especially the Ministry of Finance, NERC and BPE need to urgently
come up with a securitization package for the Sector. In doing so, it needs to be
stressed that the scheme should be applicable to all generators (other than
existing IPPs, whose risks are already accounted for in their PPAs) who are
exposed to the above-mentioned risks. A securitization scheme that discriminates
against some generators will introduce an uneven playing field, which will be
unhealthy for the market.
3.5.2.3 Market Structure and Trading Arrangements
The BPE has indicated its intention to review the market structure, with the
possibility of increasing the number of Distribution Companies. At the same time,
it has advertised the existing successor companies and received expressions of
interest towards their privatization. A stable market structure needs to be put in
place quickly in order to give clarity and confidence to those who may wish to
participate in the privatization process. In this regard, the three (3) stage market
structure design from transition through short to medium and long terms should
be retained.
In the same vein, the transition trading arrangements – especially as they
concern the participation of NELMCO in the procurement of new capacity, the use
of vesting contracts and the phased introduction of bilateral contracting – need to
be firmly resolved and implemented by NERC and BPE.
40
3.5.2.4. Residual Management Issues
A number of issues need to be resolved before one can conclude the winding up
processes of the PHCN Headquarters. Management restructuring of the
companies needs to be carried out (without prejudice to the privatization
programme) to ensure the introduction of the management style and
methodologies, staff orientation and skills required by the new market order.
Furthermore, full independence requires in particular, financial independence. The
degree to which the successor companies are free to take independent financial
decisions needs to be looked into.
The issues of common services, the Central Workshop and Stores, the Meter Test
Stations, Central Laboratories and Central Electric Energy Policy and Information
center need to be addressed, including the procurement of high capital goods and
equipment, and technology options that will also prevent proliferation.
Finally, it needs to be recognized that it is not practical to abruptly remove the
coordinating role of PHCN Headquarters in respect of the Business Units (now
Successor Companies). It is proposed that this role be wound down gradually in
a planned sequence so as to avoid disruptions in the operation of the power
supply. One of the committees headed by BPE is putting together a new structure
for the supervision of the sector that will address this issue.
This structure should have a Central Technical Committee and a Central Operation
Coordination Unit to oversee the day-to-day operations of all Successor
Companies in the transition stage.
3.6 RENEWABLE ENERGY AND ENERGY EFFICIENCY MEASURES
IMPROVEMENT
The country is blessed with renewable energy resources like flowing water such
as rivers, streams, waterfall, irrigation, canal and dams. Additionally, solar, wind,
biomass (solid and liquid waste) as well as other new energy technology sources
41
like ocean and tidal waves, geothermal and hydrogen fuels exist, can be exploited
using available and matured technology.
The estimated capacity of explored renewable resources in Nigeria is given in the
table below.
Table 3.1 Estimated Capacity of Explored Renewable Resources
Energy Source Capacity
Small Hydropower 3,500MW
Large Hydropower 11,500MW
Biomass - Fuel wood 13,071,464 hectres (Forest land, 1981)
Biomass - Animal Waste 61million tonnes/yr
Biomass - Crop Residue 83 million tonnes/yr
Solar Radiation 3.5 - 7.0 kWh/m2-day
Wind 2 - 4 m/s (annual average) at 10m
height
Source: Energy Commission of Nigeria
3.6.1 Renewable Energy
In order to harness these renewable energy resources, the following are recommended:
! Institutionalization of the National Energy Policy, the Renewable Energy Master
Plan and the National Energy Master Plan through an Act of the National
Assembly;
! Developing and siting of Small Hydro Plants and Solar-based village pilot
schemes;
! Establishing Renewable Electricity Generation Trust Fund under the auspices of
Energy Commission of Nigeria for pilot/demonstration projects;
! Providing adequate incentives to promote the demand, supply and local
manufacture of renewable energy components and systems; and,
! Intensifying Research, Development and Production in renewable energy
technologies, including especially, technology adaptations.
42
3.6.2 Energy Efficiency and Conservation Measures
Energy is wasted in all sectors of the nation’s economy. Hence, huge savings can be
achieved through the following recommended measures:
! Encouraging National Energy Assessment programmes like Energy Auditing in
Industries, Households, Transport, public buildings, institutions, etc;
! Creating the enabling environment through economic and fiscal incentives to
attract investors;
! Promoting Human Capacity Building on Energy Efficiency and conservation in the
nation’s Energy Sector; and,
! Promotion of the use of energy efficient appliances in generation, transmission,
distribution and usage/consumption.
43
CHAPTER FOUR
4.0 MEDIUM TERM INTERVENTION
The Committee has also come up with measures for improvement in the Medium
Term (beyond ninety days and up three years). These were guided by the
following issues:
! Low power generation and constant power interruptions resulting from poor
maintenance and lack of rehabilitation;
! Constant disruption due to lack of spare units;
! Gas supply issues (availability and quality of gas supply to Power Stations);
! Vandalization of gas pipelines;
! Low levels of water resource at dams for hydro power during the dry season;
! Matters relating to staffing and manpower development;
! Consideration of renewable energy options, provision of incentives for
investors and an overall investor friendly environment;
! Securitization; and,
! Delay in completion of NIPP projects.
4.1. GAS PORTFOLIO MANAGEMENT
NNPC is championing major portfolio interventions to manage gas supply to Power
Plants. Presidential consent was secured to rationalize current export projects resulting
in the freezing of Nigeria LNG Limited’s Train 7 and ExxonMobil LNG projects with
immediate effect. Accordingly, NNPC is to engage the NERC on aligning the licensing of
new Power Plants with gas availability.
The Corporation is managing the growth of future export projects with the
recommendation that the execution of such projects be contingent on exploration
success whilst capacity of future projects will also be aligned with size of exploration
find. It has been proposed that future commitments to export now be contingent on
exploration activities.
44
In addition, it has become necessary to manage the phasing of domestic projects such
as fertilizer, methanol and other similar projects. Current supply plans are limited to only
initial Greenfield plant of the respective investors. All immediate plans for expansion
have to be delayed until post 2015 when additional gas supplies are anticipated.
NNPC is also undertaking medium-term legislative interventions. The Corporation is
concluding a gas supply and pricing regulation which stipulates that all operators in the
country make a mandatory reserves allocation for the domestic sector. Compliance with
domestic obligation will be a pre-requisite for export supply. This will mitigate the
preferential focus on export and alleviate the medium to longer term supply challenge.
NNPC is also developing a Gas Infrastructure Blueprint which proposes pipeline linkage
between the east and west network, links the South to the North via Abuja to Kaduna
and opens up the eastern axis. In addition, it proposes Central Processing Facilities as a
standard, which will strip liquids off Natural Gas and produce dry gas as a standard into
the gas grid. The proposal also envisions strategic redundancy to mitigate sabotage.
4.2 GAS SUPPLY STATUS
Irrespective of the challenges to meet gas requirements for power, a number of gas
supply projects have been initiated to supply gas to the under listed power projects in
the country (Tables 4.1, 4.2 & 4.3 and Fig 4.3).
Table 4.1 Gas Supply to GOPA Power Plants
Power
Plant
Power
Capacity
(MW)
Gas
Requirement
(MMscf/d)
Status
Geregu 414 138 Gas supplied in December 2006; Phase 2
Pipeline ready by December 2007.
Omotosho 335 120 Pipeline and Station Facilities completed; Hot
tie-in completed in March 2007; Gas supply
commenced in March 2007.
45
Olorunsogo
/ Papalanto
335 120 Pipeline tested and civil works completed;
Metering System has been cleared at Lagos
Port; Gas supply commenced in April 2007.
Alaoji 504 140 Design and procurement in progress;
Completion scheduled for October 2007; Gas
supply to come from Imo River Supply
System.
Table 4.2 Gas Supply to NIPP Projects
Power
Plant
State Power
Capacity
(MW)
Gas
Requirement
(MMscf/d)
Status
Calabar Cross
River
500 140 Pipeline and Station design &
procurement in progress with
completion planned for August 2008.
Egbema Imo 350 100 Pipeline and Station Facilities design &
procurement in progress with
completion planned for August 2007.
40 MMscf/d to be available in Q3 2007
& 60 MMscf thereafter.
Gbarain Bayelsa 250 70 Pipeline and Station Facilities design &
procurement in progress with
completion planned for September
2007.
Ikot Abasi
Ibom 1 & 2
Akwa
Ibom
188/500 60/140 Gas is available for supply.
Ihovbor /
Eyaen
Edo 500 140 Pipeline and Station Facilities design &
procurement in progress with
completion planned for September
2007. 65 MMscf/d from PANOCO in
December 2007; 45 MMscf/d from
NPDC in October 2007; 30 MMscf/d
from Chevron in Q2 2008.
46
Power
Plant
State Power
Capacity
(MW)
Gas
Requirement
(MMscf/d)
Status
Sapele Delta 500 140 Pipeline and Station Facilities design &
procurement in progress with
completion planned for September
2007. Gas supply from ELP System.
Omoku Rivers 120/150 24/70 Phase 1 operational & gas fully
available; Phase 2 to be available from
Amenam Field.
TOTAL 3,208 760
Table 4.3 Gas Supply to JV Power Plants
Power
Plant
Location State Power
Capacity
(MW)
Gas
Requirement
(MMscf/d)
Status
NAOC 1 Okpai Delta 480 70 Now in operation
NAOC 2 Okpai Delta 450 70 To be operational by mid-
2009. PPA negotiation in
progress.
Chevron Agura Lagos 780 120 Site works to commence
soon. Operational by mid-
2009.
ExxonMobil Qua Iboe Akwa
Ibom
500 150 Start-up by mid-2009. PPA
negotiation to commence
soon.
Shell 1 Afam V Rivers 650 120 Takeover yet to be
concluded. PHCN staff final
benefits yet to be resolved.
Shell 2 Afam VI Rivers 400 60 Completion of Unit 1
initially scheduled for
March 2007 impeded by
security situation now
47
Power
Plant
Location State Power
Capacity
(MW)
Gas
Requirement
(MMscf/d)
Status
rescheduled for July 31
2007.
Total Obite Rivers Completion planned for
mid-2009. PPA negotiation
to commence soon.
TOTAL 3,636 660
Fig 4.1 Overview of Gas Supply Plan
Finally, the continued management of the Niger Delta situation is imperative to enable
uninterrupted supply and development of new supplies. Based on the proposed strategic
interventions, it is anticipated that the shortfall in gas supply to power will be mitigated
in the future to realize the full generating potential of the power plants.
48
4.3 GAS SUPPLY IMPROVEMENTS
Gas supply issues which form a major cause of the crises in power supply from
the beginning of the year requires intervention in the medium term to ensure
continued and improved supply of gas to the thermal stations. While it was
important to note that condensate build up in gas pipeline caused short term loss
of over 50% in power generation from the thermal stations, pipeline vandalization
brought about between 55% and 85% in supply restriction in the western and
eastern gas plants especially in the ELPS. The total gas requirement of about
920mmscf/d for domestic use dropped to 400mmscf/d.
Medium term interventions recommended include:
4.3.1 Integrated Resource Planning
! There is the need to embark on integrated resource planning taking into
consideration demand and supply in the Power Sector. A 25-year study has
been done on power demand projection and generation expansion
planning in the country. Reports have been generated from this, which
identity power requirement for year 2005 to 2030 as well as clear resource
allocations for integrated resource planning to determine the order of
magnitude estimates and ways to close the gap between supply and
demand of electricity across the country.
! The draft Energy Master Plan developed for the country should be adopted
and implemented to prevent further crises in the power sector.
! The Ministry of Energy should coordinate construction of Power Plants with
the construction of gas pipelines at the same time. The Ministry should in
coordinating construction ensure that rural electrification programmes are
integrated into demand projections to ensure that power is available while
embarking on or authorizing rural electrification projects.
4.3.2 Other Recommendations
! Sustained maintenance (Pigging) of pipelines to prevent power interruption
and damage caused by the quality of gas supply arising from the
condensate from the gas supply industry. Improvement of gas quality to
minimize condensate ingress to the power station necessitates the
49
increasing of capacity for liquids stripping at plants and upgrading of the
Shell (Utorogu) Gas Plant to limit the production of condensate in the
pipeline (discussion with SPDC is required).
! Policies should be put in place to make it mandatory to satisfy domestic
consumption of gas before export. This will ensure that enough gas is
obtained locally to feed the Power Plants and for other domestic uses.
! Increase security surveillance of pipelines and installation of high-tech
electronic monitoring devices and sensors. The involvement of the
community along the route of the pipeline in the surveillance and
monitoring of pipeline will be of added advantage. To obtain the
cooperation of the communities, developmental programmes (i.e. provision
of electricity, water, hospitals, schools, etc) for host communities by
NGC/NNPC/JV/Gencos partners should be put in place.
! NGC/NNPC should synchronize its pipeline expansion programs and other
related gas infrastructural development programme to meet up with the
gas thermal plant expansion programmes of the FGN and Licensed IPPs so
that gas will be available to the plant upon completion.
! New export projects to be conditional on exploration success.
! Ensure that correct supply plans are indeed delivered taking into account
the Niger Delta situation.
! Encourage integrated Gas gathering and exploration.
! FGN should fast track planned expansion of gas network in the country
through specific legislation and financial backing (which could include the
bond market). The passage of the Bill on gas issues with the House of
Assembly should be expatiated to encourage private participation.
! Future gas plant operators to consider floating power plants near gas
reserves.
! Incorporate Natural Gas Storage facilities for strategic reserves.
4.4 GENERATION IMPROVEMENT
4.4.1 Overhaul and Remedial Works in Existing Power Stations
Overhauls on units and remedial works in existing Power Plants should be carried
out to address the problem of power shortage and frequent system collapses
50
witnessed in the power supply. Table 4.4 below shows that about 2,784MW will
be added to the system if the overhaul and remedial works are done in the listed
Stations. These will also restore the functionality of the Stations.
Table 4.4
Station Unit Problem Power
Improvement
(MW)
Remark
Kainji 1G5
1G9-10
Damaged and
requiring complete
overhaul.
Limited to 50MW due
to age of the machine,
requiring overhaul.
120
180
7 out of the 8 units in
the Station have not
been overhauled since
commissioning from
1969-1972.
Water Management
needed.
Egbin Unit 3
Unit 6
Unit 2
Unit1,2,3
Out on boiler fault
Out on boiler fault
Major Overhaul
required
Remedial work
220
220
Gas limitations.
Sapele All units Complete overhaul of
gas and stream
turbines
950
Ughelli GT3-5
GT16,19
Faulty transformer
Awaiting Rehabilitation
45
200
Afam Major Overhaul 849
Total 2,784
4.4.2 Potential Hydro Projects
4.4.2.1 Installation of Turbines in Completed Dams
! Dadin Kowa - 34MW
! Oyan - 9MW
! Ikere Gorge - 6MW
51
! Bakolori - 3.4MW
! Gurara - 30MW
Total - 82.4MW
4.4.2.2 Potential Hydropower Sites
Lokoja (1,950MW), Onitsha (750MW), Makurdi (600MW), Yola (350MW), Gembu
(130MW), Sarki Danko (45MW), Gudo (40MW), Kiri (40MW), Richa I (35MW),
Richa II (25MW), Kombo (45MW), Gwaran (30MW), Ifon (30MW), Mistakuku
(20MW), Zurubu (20MW), Kurra I (15MW), Kurra II (25MW), Isom (10MW),
Kafanchan (5MW), Zungeru (950MW). Total Capacity: 5,115MW.
Table 4.5 Operable Small Hydro that can be Utilized in the Medium Term
S/No. River State Installed Capacity
[MW]
Status
1 *Bakolori Kano 3.0 Operated for a short while and packed up since 1993.
2 *Tiga Kano 6.0 Dam construction completed but Electro-mechanical equipment never installed.
3 *Ikere Gorge, Iseyin
Oyo 6.0 Dam construction completed but Electro-mechanical equipment never installed.
4 *Oyan Ogun 9.0 Dam construction completed but Electro-mechanical equipment never installed.
5 Dadinkowa Dam
Gombe 34 Dam construction completed but Hydropower Component yet to be awarded.
6 Challawa Gorge Dam
Kano 7.0 Dam construction completed but Electro-mechanical equipment never installed.
4.4.3 On-going Power Projects
The timely completion of the on-going projects embarked upon by the Government
will boost the generation capacity of the country. The projects are expected to be
completed between 2007 and 2008 and will add about 3,270MW to the system. The
conversion of some of the units from single combustion gas turbines to the combine
52
cycle gas turbines will contribute additional generation to grid beyond 2008. To
actualize the time lines for these projects, payments (due and pending) should be
effected to avoid delay in the project completion. Also, the problems of the
restiveness in the Niger Delta Region should be addressed by the Government.
4.4.4 Licensed IPP
Table 4.2 below is the list of IPPs licensed by NERC to engage in the business of
power generation. The Power Plants are expected to become operational within
four (4) years from the date of issue of licenses and about 5,854.5MW will be
added to the grid by year 2010 when completed.
53
Table 4.6 List of IPPs Licensed by NERC
S/NO NAME OF LICENCEE ISSUED DATE
EXPIRY DATE
TYPE OF LICENCE
SITE LOCATION
STATE PHASES (MW)
PHASE I
PHASE II
PHASE III
1 Ethiope Energy Ltd. 24/8/2006 23/8/2016 Electricity Generation
Ogorode, Spele
Delta 1,390 1,410 -
2 Farm Electricity Supply Ltd.
24/8/2006 23/8/2016 Electricity Generation
Ota Ogun 150
-
3 ICS Power 24/8/2006 23/8/2016 Electricity Generation
Alaoji Abia 120 504 -
4 Supertek Nigeria Ltd. 24/8/2006 23/8/2016 Electricity Generation
Akwete Abia 480 204 316
5 Ikorodu Ind. Power Ltd.
7/12/2006 6/12/2016 Embedded Electricity Generation
Ikorodu Lagos 39 - -
6 Ewekoro Power Ltd. 7/12/2006 6/12/2016 Off-Grid Electricity Generation
Ewekoro Ogun 12.5 - -
7 Mabon Limited 7/12/2006 6/12/2016 Electricity Generation
Dadin Kowa Gombe 39 - -
54
S/NO NAME OF LICENCEE
ISSUED DATE
EXPIRY DATE
TYPE OF LICENCE
SITE LOCATION
STATE PHASES (MW)
PHASE I
PHASE II
PHASE III
8 Geometric Power Aba Ltd.
7/12/2006 7/12/2016 Embedded Electricity Generation
Aba Abia 140 - -
9 Westcom Technologies & Energy Services Ltd.
23/2/2007 22/2/2017 Generation (Grid)
Shagamu Ogun 1000
10 Westcom Technologies & Energy Services Ltd.
23/2/2007 22/2/2008 Generation (Off-Grid)
Lekki Lagos 50
11 Anita Energy Ltd 12/4/2007 11/4/2017 Generation (Grid)
Agbara Ogun 90
12 Bresson Energy Nig Ltd.
12/4/2007 11/4/2017 Generation (Grid)
Magboro Ogun 60
Total:
3,420.5
2,118 316
Grand Total
5,854.5
55
In order to ensure the speedy implementation (construction) of the Plants by the
licensees and to guarantee healthy operating environment, NERC and other relevant
agencies should intervene in the short to medium term to:
! Identify incentives for IPPs;
! Finalise the Multi-Year Tariff Order;
! Develop vesting contracts and securitization in conjunction with BPE;
! Encourage long term buy-out of JV IPPs so as to free them to concentrate on
their core business of oil exploration;
! Encourage the exploration and utilization of coal for power plant utilization;
! Encourage the use of power infrastructure bonds as incentives/asset class so
as to source funds and use these bonds as instruments to raise capital for
construction of Power Pants;
! Encourage the development of Zungeru project as another source of Hydro
Power supply to the system;
! Setup Risk Management Unit at Debt Management Office/Ministry of Finance
to deal with contingent liabilities; and,
! Support Central Bank of Nigeria Bill to put foreign reserve of 5% as loans for
power infrastructure to target of up to 50MW new generation capacity as a
guarantee fund. This will serve as project finance assistance.
4.4.4. Alternative Energy Sources and Energy Efficiency Measures
4.4.4.1 Power Generation Potentials from Coal
The country is blessed with abundant coal resource. The proven coal reserve in the
country stands at 6.39 million metric tons while the inferred reserve could be as high as
2.75billion metric tons. Following the preliminary report on potential coal resources and
power generation development opportunities in the country by Behre Bolbear and
Company (USA)-Inc of February 2006, it was found that there is a good probability that
the reserve can support coal-fired power generation in the range of 7,000MW to
8,000MW. The report also remarked that the coal resource on the east side of
Anambra Basin could support 10,000MW to 15,000MW of power generation. It was
further remarked by the report that coal situation in the country presents excellent
opportunity for a company, or consortium of companies with expertise in coal mining
56
and power generation to develop a business with a life cycle of forty (40) to sixty (60)
years with excellent growth opportunities.
4.4.4.2 National Energy Policy on Coal Utilization
Part of the provisions of National Energy Policy is to pursue vigorously a comprehensive
program of resuscitating the coal industry and engage in extensive exploration activity
to maintain high level of coal reserves. The objective of the policy, which is relevant to
power generation, is the promotion of effective utilization of coal for complementing
the nation’s energy needs and as industrial feedstock.
The activities recommended by the Policy for the re-introduction of the use of coal for
power generation are:
(1) Reactivation of Oji River coal fired Power Plant; and,
(2) Establishment of other coal fired Power Plants in the country.
It is thus recommended that the FGN should commence the utilization of the abundant
coal reserve in the country for power generation and other uses as it is done in other
countries of the world which have high level of coal reserve. The justification for power
generation from coal is numerous and includes the following:
(1) Provision of gainful employment;
(2) Improvement in the country’s energy mix;
(3) Provision of better electric power supply system which is free from the
vagaries associated with gas supply and seasonal variations in the water
inflow to the hydro stations occasionally worsened by drought; and,
(4) Provision of additional base load generation system required in the country.
4.5. RENEWABLE ENERGY AND ENERGY EFFICIENCY MEASURES
In the light of availability of renewable energy resources and energy efficiency and
conservation measures, the following interventions are recommended:
4.5.1 Renewable energy
! Conduct comprehensive survey/mapping and feasibility studies on 90 sub-
hydrological area basins to determine small and medium hydropower potential in
Nigeria.
57
! Refurbish the abandoned small and medium scale hydropower projects (Oyan Dam
(9 MW) and Tiga (6MW)) initiated by the Federal Ministry of Agriculture and Water
Resources.
4.5.2 Energy Efficiency & Conservation Measures
! Establish Energy Labeling, Standards and Codes for Appliances;
! Develop parameters for energy saving/efficiency appliances; and,
! Promote the use of energy efficient appliances in generation, transmission,
distribution and usage/consumption.
4.6 HUMAN ASSET MANAGEMENT
The Power Sector is currently overstaffed with unskilled workforce whilst skilled
personnel and competencies are lacking in the core operational areas. This imbalance is
as a result of years of inadequate funding of manpower development programmes and
embargo on employment in PHCN. Recommendations on improvement of Human
Resources in the Sector are discussed below.
4.6.1 Restructuring of PHCN
The implementation strategy recommended comprises:
! Phase retrenchment exercise to align with the privatization programme
! Provide pre-disengagement training to the affected staff.
! Allow voluntary retirement subject to acceptance by management.
! Make funds available before embarking on the rightsizing exercise and be mindful
of core-staff required to sustain smooth operations.
! Involve all stakeholders, particularly labour unions.
! A three-phased retrenchment plan is proposed below:
o Phase I - 6,006 workers
o Phase II - 3,000 workers
o Phase III - 3,660 workers
Total - 12,666workers
58
Current staff strength is 45,906 comprising of 36,834 permanent staff and 9,082
temporary/contract staff. The phase 1, with a total number of staff of 6,006 will require
a sum of N22.3 billion as severance package.
4.6.2 Skills Gap Analysis
A couple of studies have shown that NEPA, when it existed, was overstaffed. In fact,
the National Economic Empowerment and Development Strategy (NEEDS) envisaged
that staffing in PHCN would be reduced by 15% as labour productivity was adjudged
very low.
There is no doubt that the increase in generation capacity to the over 150,000MW
required to make Nigeria an industrializing country implies a massive requirement of
adequate and differing skills to manage the transition and cope with the growth. Across
the entire Power Sector, a mix of skills is required including Engineers, Technicians, etc.
This is currently a major challenge for the Power Sector and the country. It seems to
be a paradox, as while on the one hand there is excess labour in the PHCN which
requires some right-sizing, there is also the need to increase appropriate manpower to
meet the rapid expansion expected in the Sector.
The above implies that there is a need for a skills gap analysis in view of the
requirements for meeting the country’s power supply projection. Accordingly, there is a
need to undertake the following:
! Take an inventory of existing skills and competencies, and the requirements for power
generation, distribution and transmission;
! Highlight the areas for capacity building initiatives;
! Develop a structured approach to obtain relevant skills; and,
! Establish a framework for continuous assessment and addressing of manpower needs.
A skills gap analysis was conducted in 2004 in relation to a pilot project and the
following areas for intervention were identified:
! Engineering
! System Operations
! Protection
! Customer Service
! SCADA System Operations
! Transmission System Operations
! General Management
59
! Transmission Management
Planning
! General Safety
! Load Planning and Estimation
! Demand Planning and Estimation
! Economic Operations
! Network Performance Analysis
! Regulatory Compliance
! Utility Management Financing
and Accounting
! Project Management
! Network Design and
Maintenance
! Metering
! Community Relation
However, it is imperative to carry out a more comprehensive skills gap analysis to
reflect current competency status and recommend appropriate interventions.
4.6.3 Training and Capacity Development
4.6.3.1 Competent and Qualified Manpower
It is recommend that the process of rightsizing in the Power Sector should also be
accompanied by active search and recruitment of highly qualified and well trained
Nigerians from all over the world. While Nigeria has its peculiarities, the input-output
ratios and quality indicators in the Power Sector should as much as possible be
comparable to best standards across the globe.
4.6.3.2 Training Institutions
A two-pronged approach is hereby recommended. The first is to strengthen existing
training institutions in the country. Secondly, a Public Private Partnership should be
initiated whereby the Government can partner with the Private Sector to establish a
world class training institute. A good example is the Electric Power Research Institute
(EPRI) in the USA, which is a consortium of utilities.
There is also a need for the establishment of a National Power Institute that will
coordinate, train and develop skilled personnel necessary to adequately support the
electricity industry.