building safety procedure safety - the vault...south africa continental africa australia americas...

21
RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 21 FEBRUARY 2017 ANGLOGOLD ASHANTI RESULTS BUILDING SAFETY PROCEDURE A siren will sound and information will be broadcast over the public address system. Move quickly to the nearest exit points, which are on both sides of the auditorium and at the back right hand corner. Please gather at the open car park behind Turbine Square where safety wardens will advise you on any additional procedures. SAFETY …in case of an emergency IS OUR FIRST VALUE 2 RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

Upload: others

Post on 26-Apr-2020

4 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

21 FEBRUARY 2017

ANGLOGOLD ASHANTI RESULTS

BUILDING SAFETY PROCEDURE

A siren will sound and information will be broadcast over the public address system.

Move quickly to the nearest exit points, which are on both sides of the auditorium and atthe back right hand corner.

Please gather at the open car park behind Turbine Square where safety wardens willadvise you on any additional procedures.

SAFETY…in case of an emergency

IS OUR FIRST VALUE

2RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

Page 2: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

Certain statements contained in this document, other than statements of historical fact, including, without limitation, those concerning the economic outlookfor the gold mining industry, expectations regarding gold prices, production, total cash costs, all-in sustaining costs, all-in costs, cost savings and otheroperating results, productivity improvements, growth prospects and outlook of AngloGold Ashanti’s operations, individually or in the aggregate, including theachievement of project milestones, commencement and completion of commercial operations of certain of AngloGold Ashanti’s exploration and productionprojects and the completion of acquisitions, dispositions or joint venture transactions, AngloGold Ashanti’s liquidity and capital resources and capitalexpenditures and the outcome and consequence of any potential or pending litigation or regulatory proceedings or environmental health and safety issues,are forward-looking statements regarding AngloGold Ashanti’s operations, economic performance and financial condition.

These forward-looking statements or forecasts involve known and unknown risks, uncertainties and other factors that may cause AngloGold Ashanti’sactual results, performance or achievements to differ materially from the anticipated results, performance or achievements expressed or implied in theseforward-looking statements. Although AngloGold Ashanti believes that the expectations reflected in such forward-looking statements and forecasts arereasonable, no assurance can be given that such expectations will prove to have been correct. Accordingly, results could differ materially from those set outin the forward-looking statements as a result of, among other factors, changes in economic, social and political and market conditions, the success ofbusiness and operating initiatives, changes in the regulatory environment and other government actions, including environmental approvals, fluctuations ingold prices and exchange rates, the outcome of pending or future litigation proceedings, and business and operational risk management.

For a discussion of such risk factors, refer to AngloGold Ashanti’s annual report on Form 20-F for the year ended 31 December 2015, which was filed withthe United States Securities and Exchange Commission ("SEC"). These factors are not necessarily all of the important factors that could cause AngloGoldAshanti’s actual results to differ materially from those expressed in any forward-looking statements. Other unknown or unpredictable factors could also havematerial adverse effects on future results. Consequently, readers are cautioned not to place undue reliance on forward-looking statements. AngloGoldAshanti undertakes no obligation to update publicly or release any revisions to these forward-looking statements to reflect events or circumstances after thedate hereof or to reflect the occurrence of unanticipated events, except to the extent required by applicable law. All subsequent written or oral forward-looking statements attributable to AngloGold Ashanti or any person acting on its behalf are qualified by the cautionary statements herein.

The financial information contained in this news release has not been reviewed or reported on by the Company's external auditors.

This communication may contain certain “Non-GAAP” financial measures. AngloGold Ashanti utilises certain Non-GAAP performance measures and ratiosin managing its business. Non-GAAP financial measures should be viewed in addition to, and not as an alternative for, the reported operating results orcash flow from operations or any other measures of performance prepared in accordance with IFRS. In addition, the presentation of these measures maynot be comparable to similarly titled measures other companies may use. AngloGold Ashanti posts information that is important to investors on the mainpage of its website at www.anglogoldashanti.com and under the “Investors” tab on the main page. This information is updated regularly. Investors shouldvisit this website to obtain important information about AngloGold Ashanti.

DISCLAIMER

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 3

Ron Largent

International

VenkatIntroduction

AGENDA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 4

Graham Ehm

Projects & Exploration

Christine Ramon

Financials

01 Chris SheppardSouth Africa

Region

VenkatConclusion

02 03

04 05 06

Page 3: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

POSITIONED TO CREATE VALUE THROUGH THE CYCLE

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 5

Focus on sustainable improvements to margins and cash flow

Consistent delivery on targets; improving cost management on key metrics

Improving balance sheet flexibility and elimination of high cost debt

Maintaining optionality to deliver value-adding growth

Ongoing portfolio improvements and rationalisation, decisive action on operations

Working towards zero harm through the elimination of high consequence events

Responding decisively and proactively to create sustainable value through the cycle Responding decisively and proactively to create sustainable value through the cycle

1,115

1,067

2016 H2

2016

929

875

2016 H2

2016

2016 – KEY INDICATORS

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 6

AISC $/oz

14%of 2016 production

520 kozAustralia

27%of 2016 production

967 kozSouth Africa

36%of 2016 production

1,321 kozContinental Africa

23%of 2016 production

820 kozAmericas

AISC $/oz

958

904

2016 H2

2016

AISC $/oz

1,205

1,081

2016 H2

2016

AISC $/oz

*After once off bond redemption costs**AISC based on World Gold Council standardRounding may result in computational discrepancies.

HIGHLIGHTS H2 2016• Strong safety performance; fatality-free fourth quarter

• Free cash flow $170m, up 55% from $110m in H2 2015

• Production up 8% from H1 2016

2016 Group production

3.628MozH2 2016 production of 1.883Moz

2016 HIGHLIGHTS • Free cash flow $278m*, up 97% from 2015

• Dividend resumed after c.3-year hiatus - ZAR 130 cents per share (approximately US 10 cents per share)

• Reduced net debt level $1.92bn

• All-in sustaining costs** $986/oz within revised guidance

• Significant safety improvements – >6 months with no operating fatality in SA

• Reserves 50.1mozs, substantially offsetting depletion

Page 4: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

FOCUS ON SAFETY – PROGRESS REPORT

7

5.00

7.00

9.00

11.00

13.00

15.00

17.00

19.00

0

5

10

15

20

25

30

35

2007 2008 2009 2010 2011 2012 2013 2014 2015 2016

AIF

R

Fat

aliti

es

Group Safety Statistics

Fatals (Act) AIFR

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

• No fatalities in Q4 2016; 158 fatality-free days in SA unit at year-end

• 2016 safety milestones in SA:• one million fatality-free shifts at Mponeng,

Kopanang and Moab Khotsong• Two million fatality-free shifts in Vaal River

Region• Moab Khotsong achieved full year fatality-free

in September• Surface Operations achieved full year with no

lost-time injuries

• Reportable environmental incidents continues to improve, falling to one in 2016. (Improvement of 75% year-on-year and 94% since 2012)

Safety remains our highest priority. Safety remains our highest priority.

16

10

54

1

2012 2013 2014 2015 2016

Environmental Incidents

WE CONTINUE TO DELIVER ON OUR COMMITMENTS

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 8

Our foundation and the quality of our business was further strengthened in 2016 as we delivered on key commitments

Our foundation and the quality of our business was further strengthened in 2016 as we delivered on key commitments

2016Commitments Delivered

Further improved safety and sustainability performance

Continue to enhance marginsand cash flow

Effect South Africa operational turnaround

Advance low capital, high return brownfields opportunities

Extend asset lives through focused exploration

Revisit Obuasi feasibility study; assess all options

Move Colombia projects up value curve; reduce holding cost

WIPWIP

WIP

Continue debt reduction to improve balance sheet flexibility

Page 5: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

DISCIPLINED APPROACH TO GROWTH

9

• Prioritise margins over growth; inward investment preferred over M&A

• Improving production mix through:• efficiency improvements, operational flexibility and

mine-plan changes• high-return, low-risk, self-funded brownfield projects

• Careful stage-gating to ensure optimal capital allocation

• Full evaluation of country/project risks

• Mid-teen returns targeted through the cycle

Our focus is to improve net asset value in a sustainable way, through strict capital allocationOur focus is to improve net asset value in a sustainable way, through strict capital allocation

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

0 500 1000 1500

2016 All-In Cost

3-Year Low

Reserve Price

3-Year Avg

3-Year High

Gold $/oz

Spo

t gol

d pr

ice

AGA Mineração [Current LOM:2032]

Pre-strip Teberebieorebody; extend LOM, improve optionality

Increase ORD; significant exploration potential remains

Siguiri [Current LOM:2027]

Iduapriem [Current LOM:2026]

Increase Cuiaba ORD; improve mining flexibility related to geotechnical conditions

New combination plant increases endowment and production, and lowers cost

Sulphide plant extends mine life increases production

Tropicana [Current LOM:2026]

Invest in gold recovery improvements

Mining, processing enhancements to improve margins and LOM

Sustaining Growth

DISCIPLINED INWARD INVESTMENT – 2017 FOCUS AREAS

10

Capital expenditure in 2017 will be focused on improving portfolio quality, extending life and improving operational flexibility

Capital expenditure in 2017 will be focused on improving portfolio quality, extending life and improving operational flexibility

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

Mponeng [Current LOM: >2050]

B120 progressing, with Phase 1 development continuing

Sadiola [Current LOM: 2027]

*LOM forecast based on current business plans; subject to change.

Geita [Current LOM 2025]

Sunrise Dam [Current LOM:2031]

Page 6: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

INVESTING IN STABLE AND SUSTAINABLE OUTCOMES

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 11

-

1,000

2,000

3,000

4,000

5,000

2016 2017F 2018F 2019F 2020F 2021F

South Africa Continental Africa Australia Americas

-

200

400

600

800

1,000

2016 2017F 2018F 2019F 2020F 2021F

South Africa Continental Africa Australia Americas

Sustaining Capex ($m)Production (koz)

Total tonnes treated OP + milled UG¹ (‘000)

-

0.50

1.00

1.50

2.00

2.50

3.00

2016 2017F 2018F 2019F 2020F 2021F

Average Recovered Grade² (g/t)

-

10,000

20,000

30,000

40,000

50,000

2016 2017F 2018F 2019F 2020F 2021F

South Africa Continental Africa Australia Americas

¹excludes placed heap leach mining²excluding Surface and Dumps ³All projections are based on current assumptions and are subject to change given amongst other things prevailing conditions; excludes potential Obuasi and Colombia developments/projects

Ron Largent Outgoing Chief Operating

Officer: International

SUCCESSION PLANNING FOR INTERNATIONAL OPERATIONS

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 12

Ludwig EybersIncoming Chief Operating

Officer: International

• Ron Largent retiring after exemplary career spanning nearly 30 years, most recently overseeing restructuring and subsequent significant turnaround of our International Operations into world-class portfolio

• Ludwig, a mining engineer, has worked closely with Ron for several years and has held accountability for planning and production in the International Portfolio since appointment at Deputy COO: International last year

• Formerly EVP Continental Africa, responsible for turnaround of our largest operating region:

- oversaw significant restructuring, with 44% productivity gains, in a ‘dollarized’ environment- led gains in safety, a significant drop in AIFR, and large improvement in environmental performance - Continental Africa is AngloGold Ashanti’s largest cash generator

• More than two decades of mining experience, including senior technical, operating and project management roles

• Worked in senior roles in Ghana, Australia and South Africa

Page 7: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

Ron Largent

International

VenkatIntroduction

AGENDA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 13

Graham Ehm

Projects & Exploration

Christine Ramon

Financials

01 Chris SheppardSouth Africa

Region

VenkatConclusion

02 03

04 05 06

FOCUS ON SAFETY – KEY INTERVENTIONS

14

Consistent, intensive focus on embedding safety culture and embracing latest technologies has helped improve safety

Consistent, intensive focus on embedding safety culture and embracing latest technologies has helped improve safety

Strategic Interventions across AngloGold Ashanti• Major Hazard Management programme• Large-scale training to improve overall safety capability• Lessons from reporting high-potential incidents

Specific SA Interventions Include• Improved seismic coverage• Increased backfill placement• Mining cycle changes • Pre-conditioning• Netting and bolting• Locomotive technology

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

Page 8: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

A SUBSTANTIAL INVESTOR IN SOUTH AFRICA

AngloGold Ashanti remains a significant investor in its SA production base, which employs c. 28,000 people and has a potential future spanning several decades. The viability of this business needs to be ensured by ensuring costs are actively managed

AngloGold Ashanti remains a significant investor in its SA production base, which employs c. 28,000 people and has a potential future spanning several decades. The viability of this business needs to be ensured by ensuring costs are actively managed

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 15

Cash Operating Cost(Labour, electricity, consumables, etc.)

R12.6 billion

Growth Capital, Exploration and Evaluation Costs(Drilling and studies for future production, projects)

R2.1 billion

Sustaining Capital Investment(Investment in asset integrity and projects to ensure future sustained future production)

R2.7 billion

Total R17.4 billion

SA Operating and Capital Expenditure 2016

Cash Operating Costs Growth Capital, Exploration and Evauation Costs Capital Investment

R17.4 Billion2016

SOUTH AFRICA OPERATIONS OVERVIEW

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 16

*World Gold Council standard

Total cash costsAll-in sustaining costs*

Production koz

Costs $/oz

• At the West Wits, • Mponeng delivered strong results assisted by the ‘de-

risk mine plan’ formulated in 2015 to improve safety• TauTona experienced production challenges during

the year following 2 seismic incidents

• At Vaal River,• Moab Khotsong saw an increase in volume mined,

with additional face length created, 3% higher grades and a 5% increase in the Mine Call Factor

• Kopanang experienced significant safety related stoppages through the year, in addition to face time constraints, due to mining in the extremities of the lease area

• Surface Operations produced 187,000oz at a total cash costs of $899/oz, compared to 193,000oz at a total cash cost of $912/oz in the previous year.

• The uranium plant at MWS was recommissioned in the H2 2016. Recoveries are expected to improve due to the optimisation of the plant circuit.

967

1,004

481

486

505

500

2016 FY

2015 FY

2016 H2

2016 H1

2015 H2

2015 H1

896

881

984

809

867

894

1,081

1,088

1,205

958

1,079

1,097

2016 FY

2015 FY

2016 H2

2016 H1

2015 H2

2015 H1

The weaker exchange rate was largely offset by lower production volumes partially due to safety-related stoppages along with cost inflationary pressures including annual power tariff increases and salary adjustments

The weaker exchange rate was largely offset by lower production volumes partially due to safety-related stoppages along with cost inflationary pressures including annual power tariff increases and salary adjustments

Page 9: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

Safety West Wits Vaal River• Continue to reinforce clear roles,

schedules and work routines to encourage safe practices

• Establish adoption processes that support sustainable practices and improved safety and health outcomes

• Studying infrastructure and operational synergies to further operating efficiencies

• Option studies to optimise end of life of mine at TauTona/Savuka in particular

• P500 efficiency initiatives well embedded; integral part of operations

• Vaal River optimization with aim to effect overall cost savings and orderly surface-footprint reduction

Surface Ops Mponeng B120 Technology• Offset the drop in MOD grade by

increasing throughput

• In addition to P500 savings, leverage procurement

• Stepping up implementation of Enterprise Development projects for local communities

• Focus on Phase 1 build up to steady state as a foundation for further brownfields growth

• Study combined CLR/VCR extraction approach, moving from PFS to FS

• Focus remains on TauTona with clear stage-gates for project success aimed at achieving desired machine/system efficiencies

• Consultations aimed at obtaining regulator approval for continuous operations

2017 PRIORITIES – SOUTH AFRICA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 17

Working towards zero harm is our number one priorityWorking towards zero harm is our number one priority

Ron Largent

International

VenkatIntroduction

AGENDA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 18

Graham Ehm

Projects & Exploration

Christine Ramon

Financials

01 Chris SheppardSouth Africa

Region

VenkatConclusion

02 03

04 05 06

Page 10: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

INTERNATIONAL OPERATIONS OVERVIEW

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 19

The International operations continue to perform well despite local inflationary pressures, and operational challenges at Kibali

The International operations continue to perform well despite local inflationary pressures, and operational challenges at Kibali

• Continental Africa delivered 1.321Moz at total cash cost of $717/oz in 2016 compared to 1.435Moz at $678/oz in 2015• Impacted by challenges at Kibali and planned lower

production at Geita; strong performances from Iduapriem and Siguiri

• Americas produced 820,000oz in 2016 at total cash cost of $578/oz compared to 831,000oz at $576/oz in 2015• Impacted by lower year-on-year contribution from Brazil;

Argentina delivers record production result

• Australia produced 520,000oz for 2016 at total cash cost of $793/oz compared to 560,000oz at $702/oz for 2015• Lower contribution from Tropicana mainly due to the

planned reduction in grade. Grade streaming to be reintroduced in H2 2017

• Sunrise Dam saw increased underground ore production, improved grades and higher mill throughput

*World Gold Council standard

Total cash costsAll-in sustaining costs*

Production koz

Costs $/oz

2,661

2,826

1,402

1,259

1,448

1,378

2016 FY

2015 FY

2016 H2

2016 H1

2015 H2

2015 H1

689

653

707

670

638

669

929

823

981

873

806

840

2016 FY

2015 FY

2016 H2

2016 H1

2015 H2

2015 H1

2017 PRIORITIES – INTERNATIONAL

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 20

Sunrise Dam Tropicana Siguiri Geita

• Commence recovery enhancement project, resource extension drilling and underground materials handling study

(Objective: to increase recoveries and improve underground tonnages)

• Execution of Long Island Study, resumption of grade streaming and optimisation of expanded processing plant

(Objective: improve mill-feed grade)

• Execute on hard-rock combination plant project

• Project fully approved, long-lead items ordered

• Plan and build 39MW power plant

(Objective: Increase production, lower cost, extend mine life)

• First full-year underground mining/development at Star & Comet;

• Start Nyankanga underground;test Geita Hill

• Underground exploration to increase resource

• Build 40 MW power plant

(Objective: Increase production, extend mine life)

Iduapriem CVSA Serra Grande Mineração

• Execute on pre-stripping at Teberebie

• Confirm exploration potential of Block 1

(Objective: Increase grade, extend mine life)

• Focus on site/regional exploration

• Completion of option review of regional resources

(Objective: Extend mine life)

• Developing high-grade Palmeiras and Inga ore bodies

• Accelerate regional exploration

• Drilling and evaluation of recent Orinoco JV

(Objective: Increase production, extend mine life)

• Accelerate ore-reserve development at Cuiaba to improve mining flexibility

• Continue drilling satellite ore bodies

• Evaluate ore sorting prototypes• Implementation of ore sorting at

Córrego do Sítio

(Objective: Increase production, extend mine life)

Page 11: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

TROPICANA: OPERATIONAL EXCELLENCE IN PROGRESS

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 21

Optimising Tropicana Life of Mine (Long Island Study)

Current Operational Value Enhancement

• Over past six months: Reserve up 1.1Moz for 3.4Moz contained gold; Resource up 1.5Moz for >8Moz contained gold**

• Potential for further 7-year life extension

• Optimisation using Tropicana pit for waste dumping

• Completed plant expansion to 7.5Mpta in 2016

• Plan now for 7.6Mpta to 7.9Mpta over next 12 months

• Mining intensified with 600t shovel; grade streaming resumes

0

200

400

600

800

1000

1200

0

50,000

100,000

150,000

200,000

250,000

300,000

350,000

400,000

2013 2014 2015 2016 2017E

$/ozoz

Production* AISC

317,000oz mid point

attributable

*Attributable 70%

We have used innovative thinking to optimise the mine at nominal capital cost in the near- to medium-term, whilst a long-term future is taking shape

We have used innovative thinking to optimise the mine at nominal capital cost in the near- to medium-term, whilst a long-term future is taking shape

**Net of depletion

Payback achieved within

first 3 years

TROPICANA: LONG ISLAND STUDY TIMELINE

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 22

Long Island Study

Update

Long Island Study

Finalisation

Business Plan Update

Operational Readiness

Long Island Commences

H2 2016• Model update, optimisation and

scheduling • Mineral Resource and Ore

Reserve update • Long Island Drilling continuing

2017• Capture Long Island outcome in

Business Plan

2019• Initial cutback to commence once

Tropicana pit is mined to full depth

2018• Long Island operational

readiness preparation

H1 2017• 2017 model update, optimisation and scheduling• Update Ore Reserve & Mineral Resource• Update LOM plan

WIP

Optimise steady state operations

Page 12: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

Ron Largent

International

VenkatIntroduction

AGENDA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 23

Graham Ehm

Projects & Exploration

Christine Ramon

Financials

01 Chris SheppardSouth Africa

Region

VenkatConclusion

02 03

04 05 06

ORE RESERVE AND MINERAL RESOURCE UPDATE

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 24

Our exploration programme is yielding good results with most of the year’s depletion offset by reserve gains whilst resources see an increase

Our exploration programme is yielding good results with most of the year’s depletion offset by reserve gains whilst resources see an increase

45

50

55

51.70 -3.90 1.10 0.60 0.50 0.40 -0.30 50.10

Dec 2015 Depletion Tropicana AGA Mineracao Siguiri Sunrise Dam Kibali Dec 2016

Reconciliation of Ore Reserve 2016 vs.2015

190

200

210

220

207.80 -4.40 5.50 2.20 1.50 1.30 1.20 0.90 0.90 0.80 -0.80 -1.00 -0.60 -0.60 214.70

Dec 2015 Depletion Obuasi Mponeng Tropicana SunriseDam

AGAMineracao

Siguiri Geita Other Kibali MoabKhotsong

TauTona Kopanang Dec 2016

Reconciliation of Mineral Resource 2015 vs. 2016

Page 13: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

VALUE-DRIVING PORTFOLIO IMPROVEMENTS - BROWNFIELDS

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 25

This snapshot of our Brownfields opportunities highlights tremendous value within the portfolio

This snapshot of our Brownfields opportunities highlights tremendous value within the portfolio

Project Main Scope Capex Production AISC Mine Life

Siguiri Expansion

Treat fresh/transitional material

$158M¹ over 2 years

300koz pa c. $900/ozInitially adds 4

years from 2019

Sadiola Sulphides**

Treat hard rock material $410M 300koz pa c. $900/oz Adds 10 years

TOTAL $568MOver 3 years

¹ Approved scope change for owner build power station reduces cost and increases project NPV.** Contingent on investment decision which is dependent on various approvals and permits awaited from the Government of Mali

c$570M OF CAPITAL TO DEVELOP WELL OVER 4Moz AT SIGNIFICANTLY LOWER COSTS

STEP-OUT PROJECTS PROVIDE LONG-TERM OPTIONS

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 26

This snapshot of our step-out growth opportunities highlight tremendous hidden value within the portfolio

This snapshot of our step-out growth opportunities highlight tremendous hidden value within the portfolio

Project Main Scope for 2017 Update

Gramalote,Colombia

Pre-feasibility targeted for year-end

• Permitted project• Successful PFS completion will result in resource-to-

reserve conversion• Current resource 3.475Moz attributable

Obuasi,Ghana

• Preparing new Amendment to Programme of Mining Operations

• Review all future options

• Fenced operational area cleared of illegal mining activity, work continues to remove the rest

• Identified illegal mining holes within fenced area closed

Mponeng,South Africa

Optimisation study around current phased approached

• Will seek to explore improvements around logistics, face time availability, work cycles, seismic risk management and costs

AIMING TO DAYLIGHT VALUE OF UNDER-APPRECIATED ASSETS

Page 14: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

KIBALI – STRONG RECOVERY

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 27

131123

150

182

0

10

20

30

40

50

60

70

80

90

0

20

40

60

80

100

120

140

160

180

200

Q1 2016 Q2 2016 Q3 2016 Q4 2016

%koz

Production vs. Recovery

Gold Production Recovery

1,640 1,681

2,093

2,300

0

0.5

1

1.5

2

2.5

3

0

500

1000

1500

2000

2500

Q1 2016 Q2 2016 Q3 2016 Q4 2016

g/t

kt

Tonnes Treated vs. Grade

Throughput/Runtime Grade

Kibali recovered well from a challenging start to the year, with a firm foundation in place for the longer term

Kibali recovered well from a challenging start to the year, with a firm foundation in place for the longer term

*figures shown at 100%

PRODDUCTION_WASTEPASS

PRODUCTION OPA_4

MHL_HAULAGE_SOUTH

MHL_HAULAGE_NORTH

Conveyor level transfer station in progress (CV01)

CRUSHER  INCLINE

C_ INCLINE

KIBALI – SHAFT OPERATIONS SCHEDULED BY YEAR-END

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 28

Construction of the metallurgical facility and infrastructure• Construction of Ambarau hydropower plant continued during the quarter; first power rescheduled to Q1• Construction at Azambi, third hydropower plant, has commenced• Expansion of ultra-fine grind capacity, to improve full sulphide-feed recoveries, continued to schedule; commissioning

planned for Q1 2017

Declines• Underground ramp-up continued in Q4 2016, ore from underground operations 454,713t • Development profile in line with Q3 at 3.5km to ensure sufficient ore from shaft operations scheduled for later in 2017

Vertical shaft• Off-shaft development on schedule for commissioning in Q4 2017

Page 15: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

GREENFIELDS EXPLORATION STRATEGY

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 29

*According to SNL (2016)

• Primary focus on countries with synergies to optimise cost and opportunities, targeting >6Moz discovery with high margin, low capital potential by 2019

• Greenfields Exploration team delivers ounces consistently at <$25/oz

• Credited* with share in eight discoveries from 2001-2015 hosting 73.3Moz attributable gold in reserves and resources

• Most gold discovered by any of the profiled companies, almost twice that of nearest competitor

Ron Largent

International

VenkatIntroduction

AGENDA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 30

Graham Ehm

Projects & Exploration

Christine Ramon

Financials

01 Chris SheppardSouth Africa

Region

VenkatConclusion

02 03

04 05 06

Page 16: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

KEY METRICS: COMPARATIVE PERFORMANCE

31

2016 H2 2015 H2 Change (%)

Gold Price Received ($/oz) 1,274 1,113 14

Gold Production* (kozs) 1,883 1,953 -4

Total cash costs ($/oz) 780 699 12

All-in sustaining costs ($/oz) 1,058 897 18

All-in costs ($/oz) 1,155 991 17

Adjusted EBITDA ($m) 767 679 13

Adjusted EBITDA margin (%) 36.1 34.5 5

Tax ($m) 138 96 44

Interest cost ($m) 72 103 -30

Working capital inflows ($m) 26 61 -57

Free cash flow ($m)** 170 110 55

Net Debt ($m) 1,916 2,190 -13

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

*excluding discontinued operations**including bond redemption premium

FOCUS ON MARGINS – PROGRESS REPORT

32

We remain focused on margins while we reinvest in low-capital, high return options within the business

We remain focused on margins while we reinvest in low-capital, high return options within the business

1,597

1,312 1,341

1,170

1,017 9931,052 1,034 1,005

920 928 937860

911

1,058

700

900

1100

1300

1500

1700

1900

2100

Q42012

Q12013

Q22013

Q32013

Q42013

Q12014

Q22014

Q32014

Q42014

Q12015

Q22015

Q32015

Q42015

2016H1

2016H2

$/o

z

All-in sustaining costs, All-in costs and Average gold price

All-in sustaining costs* Average gold price All-in costs*

*World Gold Council standard adjusted to exclude stockpile and NRV adjustments

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

HALF YEAR

NUMBERS

Page 17: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

640

660

680

700

720

740

760

780

800

699 -8 34 39 5 -3 2 12 780

H2 2015 Exchange Inflation Volume andgrade

Stockpiles andinventory

By products Efficiency Other H2 2016

H2 Cash Cost $/oz vs. Prior Year

COST PERFORMANCE

33

Inflation, lower grades, and higher sustaining capex have pushed costs higherInflation, lower grades, and higher sustaining capex have pushed costs higher

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

800

850

900

950

1,000

1,050

1,100

897 81 4 21 1 57 -3 1,058

H2 2015 Cash Costs RetrenchmentCosts

Rehab and othernon cash costs

ExplorationCosts

Sustaining capex Inventory andOther

H2 2016

All-in sustaining cost $oz soldExcluding Stockpile NRV and other adjustments

AHE RECONCILIATION

34RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

$m2015 AHE 49

Gold Price 312

Ounces sold (241)

Effects of weakening local currencies 169

Effects of inflation (124)

Net finance costs 61

Reduced income from associates (57)

Increased depreciation (32)

Other movements 6

2016 AHE 143

Once-off costs:

DB pension fund costs 12

Net impact of once-off taxes and FX on deferred tax balance (32)

Legal fees and provisions 7

2016 AHE Normalised 130

Page 18: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

Undrawn facilities*At 31 December 2016

*Total calculated with ZAR facility at R13.7311/$ (excluding DMTNP), AUD facility at 0.7215$ to A$

A$265m

R2.2bn

US$1.010bn

US$215mCash

$1.576bn

BALANCE SHEET FLEXIBILITY

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 35

Highest cost debt redeemed using our US dollar RCF and internal cash generation; ample liquidity, no near-dated maturities, and sufficient covenant headroom

Highest cost debt redeemed using our US dollar RCF and internal cash generation; ample liquidity, no near-dated maturities, and sufficient covenant headroom

Last-12-months adjusted EBITDA ratio based on restated results

Net debt and Net debt to Adjusted EBITDA

1.811.70

1.942.02 1.95

1.54 1.49 1.47 1.441.26 1.24

1500

2000

2500

3000

3500

0.5

1

1.5

2

2.5

3

3.5

Q22014

Q32014

Q42014

Q12015

Q22015

Q32015

Q42015

Q12016

Q22016

Q32016

Q42016

Net

deb

t $m

Net

deb

t to

Adj

uste

d E

BIT

DA

Net debt to Adjusted EBITDA Net debt

POSITIVE CASH FLOW MOMENTUM SUPPORTS RESUMPTION OF DIVIDEND

36

We continue to deliver on our strategy of improving free cash flows even in a volatile environmentWe continue to deliver on our strategy of improving free cash flows even in a volatile environment

*2015 adjusted for bond redemption premium of $61m on part settlement of $1.25bn bonds and for Obuasi redundancy costs and Rand Refinery loan in 2014**2016 Adjusted for bond redemption premium on settlement of remaining $1.25bn bonds

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

-666 -1064

142 202*308**

2012 2013 2014 2015 2016

Free Cash Flow Generation (Adjusted FCF) $m

Dividend policy – 10% of free cash flow generated by the business for that year, before growth capex, subject to the board’s discretion

Page 19: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

Guidance Notes

Production (000oz) 3,600 – 3,750

- Obuasi in limited operations phase with no production anticipated in 2017. No provision for any unforeseen operational disruptions, power-related stoppages, or changes to asset portfolio and/or operating mines.- Note that there is, as always, a strong negative impact expected in

the first half of the year given the slow start-up in SA following the holiday break, and interruptions around the Easter break.

Costs All-in sustaining costs ($/oz) 1,050 – 1,100 Assumptions : ZAR14.25/$, $/A$0.75, BRL3.40/$ and AP16.50/$;

Brent $58/bl. (All averages for the year); AISC includes group corporate costsTotal cash costs ($/oz) 750 – 800

OverheadsCorporate costs ($m) 80 – 90 Inflation and retention of critical skills and skills development

Expensed exploration and study costs ($m) 170 – 190 Including equity accounted joint ventures

Capex

Total ($m) 950 – 1,050

Sustaining Capex ($m) 830 – 900Stay-in-business, ore-reserve development, asset integrity; Includes increases particularly at Geita, AGA Mineração, and Sunrise Dam

Non-sustaining Capex ($m) 120 – 150 Includes project capital for projects at Siguiri, Kibali and Mponeng

Depreciation & Amortisation ($m) 850

Depreciation & Amortisation

included in equity accounted earnings ($m)125 Earnings of associates and joint ventures

Interest and finance costs ($m) - income statement 140

Interest and finance costs ($m) – cash flow 135 Affected by timing of coupon payments

Other operating expenses ($m) 85 Primarily includes the costs of limited operations related to Obuasi

SENSITIVITIES (based on $1200/oz gold price and the same assumptions used for guidance)

AISC ($/oz) Cash flow before any taxes ($m)

10% change in the oil price ~4% ~14

10% change in local currency ~$60 ~100

10% change in the gold price ~$4 ~430

50koz change in production ~$14 ~55

GUIDANCE - 2017

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 37

Both production and cost estimates assume neither labour interruptions or power disruptions, nor changes to asset portfolio and/or operating mines and have not been reviewed by our external auditors. Other unknown or unpredictable factors could also have material adverse effects on our future results and no assurance can be given that any expectations expressed by AngloGold Ashanti will prove to have been correct. Please refer to the Risk Factors section in AngloGold Ashanti's annual report on Form 20-F for the year ended 31 December 2015, filed with the SEC.

Ron Largent

International & Projects

VenkatIntroduction

AGENDA

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 38

Graham Ehm

Projects & Exploration

Christine Ramon

Financials

01 Chris SheppardSouth Africa

Region

VenkatConclusion

02 03

04 05 06

Page 20: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

2013 2014 2015 2016

CONSISTENTLY MEETING OUR COMMITMENTS

39

Consistently meeting or exceeding our commitments is a cornerstone of our strategy and is fundamental to our investment case

Consistently meeting or exceeding our commitments is a cornerstone of our strategy and is fundamental to our investment case

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016

Annual Production (continuing operations)Moz

Production Guidance

COMMITMENTS FOR 2017

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016 40

Focus remains on ensuring stable, consistent outcomes in a volatile environmentFocus remains on ensuring stable, consistent outcomes in a volatile environment

2017Commitments

Further improve safety and sustainability performance

Continue to enhance margins and cash flow

Execute on low capital, high return brownfields projects

Proactively manage debt and improve financial flexibility

Return to dividend paying statusContinue moving long-term projects up value curve

Move to sustainable resolution at Obuasi

Continued focus on turn around in SA and Kibali

Page 21: BUILDING SAFETY PROCEDURE SAFETY - The Vault...South Africa Continental Africa Australia Americas ¹excludes placed heap leach mining ²excluding Surface and Dumps ³All projections

INVESTMENT CASE – VALUE CATALYSTS

41

1. High-quality portfolio of long-life, pure gold assets with strong leverage to energy and currencies

4. Decisive strategic responses cements ability to weather lower gold price

5. Balance sheet flexibility - appropriate liquidity, covenant and maturities

6. Well developed engagement model ensures strong stakeholder relationships and license to operate

2. Transparent, decisive management team focused on delivery and shareholder value

3. Prioritising margins over production growth – focus on cost and capital discipline

for value uplift and a sustainable, long-term mining business

A strong investment case with several catalysts…

RESULTS FOR THE HALF YEAR & YEAR ENDED DECEMBER 2016