building response to tunnelling-induced ground subsidence: some … · 2013. 6. 19. · type and...
TRANSCRIPT
-
Building response to tunnelling-induced ground subsidence: some case histories from tiie
Jubilee Line Extension
Graham Robert Taylor
A thesis submitted in fulfilment of the requirements for the degree of Doctor of Philosophy and the Diploma of Imperial College London
April 2005
-
Abstract
Abstract Tunnelling-induced ground subsidence, particularly at station locations and
complex junctions can distort and damage overlying buildings and infrastructure. The
mechanisms, which control this soil-structure interaction problem, are not well
understood. The imposition of ground treatment processes further complicates matters.
There are few published case histories of building response to serve as precedent for
future works. The integration of construction activities with building response is
fundamental to furthering the understanding of this complex problem.
The construction of the JLE in London provided an opportunity to monitor in
detail, the response of structures to tunnelling-induced ground subsidence. The
objective of this thesis was to compile comprehensive case histories for a number of
buildings above London Bridge underground station on the JLE to further the
understanding of the mechanisms involved. This has been achieved by collating all
available archival data for each building and then assimilating the corresponding
time-line, relating the response of the building to the various tunnelling and ground
treatment phases. Particular emphasis was given to the initiation and propagation of
cracks, the three-dimensional building response and the horizontal strains generated by
the passage of the subsidence trough through the building footprint. The results of
these studies are several fully-documented, analysed and interpreted case histories,
which illustrate the response of a number of buildings of varying age, nature, foundation
type and configuration to complex large-scale, underground construction and associated
ground treatment processes.
Surface settlement development above London Bridge underground station is
largely as expected given the construction sequencing and application of protective
measures, as is its distribution. However, the influence of geological features on the
settlement recorded is highlighted. The recorded settlements during underground
construction vary up to about 75 mm in magnitude.
Most of the case history buildings generally respond in a relatively rigid manner
overall to the sub-surface works. Two do, however, exhibit relatively flexible behaviour
overall; a relatively more rigid response is displayed by both structures prior to the
cessation of compensation grouting ground treatment operations in the vicinity. In all
-3-
-
Abstract
cases an abrupt increase in vertical displacement is recorded on the cessation of
compensation grouting. The in-plane horizontal strains estimated are generally less
than 500 microstrain, the value of limiting tensile strain delineating the 'negligible' and
'slight'damage categories (Burland, 1995); the strains following the cessation of
compensation grouting operations are little different to those measured before. The
actual damage recorded, between categories 0 and 2, was generally superficial in
nature and confined largely to the finishes. The buildings were considered structurally
sound throughout underground construction. Deformation generally resulted from the
resumption of movement along pre-existing features; the pre-existing condition of the
building fabric has a significant influence on subsequent building behaviour. In some
cases the severity of the damage sustained in the interim was greater than at the end of
construction. The influence of relative stiffness in crack initiation and subsequent
propagation is also highlighted; a concentration of cracking is observed around the
stiffer structural elements. In addition, the phenomenon of twist has been quantified for
several of the case history buildings at London Bridge; no damage has been directly
attributed to this aspect.
The behaviour of the case history buildings and the effects of the ground
treatment in the long term are also verified; movements in the three years following the
end of construction, equivalent to an average annual rate of settlement of between 2
and 3 mm, are observed throughout the site. These observations are consistent with
those reported for Waterloo Station on the JLE (Harris, 2002).
-4-
-
Acknowledgements
Acknowledgements I would like to dedicate this thesis to my parents, and my sister, who have been a
constant source of inspiration and support throughout my life.
I would also like to thank Professor John Burland for giving me the opportunity to become involved in this research project. Without his guidance, encouragement and assistance throughout, the thesis would not have been produced in its current form.
The research presented in this thesis was funded by EPSRC and LUL, and was part of a collaborative programme between Imperial College and Cambridge University. LUL, GCG and CIRIA were industrial collaborators in the research programme. The funding and collaboration of all parties is gratefully acknowledged. Grateful thanks are also due to the members of the Research Programme Progress Group, including Professor John Burland, Professor Robert Mair, Dr Jamie Standing, Dr Kenichi Soga, Niki Franzius, Paul Dimmock, Dimitrios Selemetas, Jarungwit Wongsaroj, David Harris and Mike Black.
Staff on the JLEP and at LUL, too numerous to mention, contributed to the research presented in this thesis and all their efforts are gratefully acknowledged. Special thanks are due to Ray Gardiner, Alan Drake and Ivan Chudleigh at LUL, David Harris of GCG, Mike Black of CLRL and Fin Jardine (formerly of CIRIA) for their help in compiling the various data. Thanks are also due to Kieran Dineen (formerly of Geotechnical Observations) and his staff, for their help in carrying out the long term monitoring at London Bridge. The help and advice of Mr James Sutherland during building inspections is also gratefully acknowledged. Data was also supplied by Robert Allen (formerly of the CTW JV) and Gerwyn Price of CMCS.
All the members (past and present) of the academic staff in the Soils Mechanics Section have contributed to my work through their teaching, suggestions at colloquia or in subsequent discussions. I would like to thank them for their support. In this regard, special thanks are due to Jamie Standing, who was always available to discuss any problems that I might have encountered in my work.
Without the support of the technical and administrative staff, the research produced by the Section would be lacking. On this project, grateful thanks are due to Steve Ackerley for his help with IT, and to Graham Keefe for providing some ad-hoc field equipment. Thanks also to Sue (and Charlotte) for always having smiley faces.
It has been a great privilege to have been a member of the Soil Mechanics Research Group at Imperial College. The nature of research is such that the support of friends and colleagues is integral to its success. During my membership of the group, I have made many new friends and colleagues. I wish everyone all the best in their chosen careers.
-5-
-
Table of Contents
Table of Contents Abstract 3
Acknowledgements 5
Table of contents 7
List of tables 17
List of figures 19
List of plates 41
List of symbols and abbreviations 43
Chapter 1 Introduction 47
1.1 Introduction 47
1.2 Background 47
1.3 Previous investigations 48
1.4 Aims of research 49
1.5 Layout of thesis 50
Chapter 2 Ground response to soft ground tunnelling 53
2.1 Introduction 53
2.2 The tunnelling process 54
2.2.1 Open-face shield tunnelling 54
2.2.2 Sprayed Concrete Lining 57
2.2.3 Hand Excavation 58
2.2.4 Pilot tunnels 59
2.3 Ground movements due to tunnelling and their prediction.. 60
2.3.1 The surface settlement trough 60
2.3.2 Trough width parameter 61
2.3.3 Longitudinal surface settlement profile 61
2.3.4 Horizontal movements 62
2.3.5 Sub-surface movements 62
2.3.6 Multiple tunnels 64
2.3.7 Shafts 64
2.3.8 Long term behaviour 65
Chapter 3 Soil-structure interaction 69
3.1 Introduction 69
3.2 Definitions: foundation movements 70
3.3 Historical background 70
-7-
-
Table of Contents
3.4 Building deformation 71
3.5 Influence of building stiffness 75
3.6 Numerical modelling 77
3.7 Piled foundations 77
3.8 Three-dimensional behaviour 77
3.9 Damage classification 79
3.10 Assessment of risk 81
3.10.1 Potential damage assessment 81
Protective measures 85
4.1 Introduction 85
4.2 The tunnel design process 85
4.3 In-tunnel measures 86
4.4 Ground treatment 88
4.4.1 Permeation grouting 88
4.4.1.1 TAMs 89
4.4.2 Compensation grouting 91
4.4.2.1 Grout mix 95
4.4.2.2 Exclusion zone 95
4.4.2.3 Grout/ground response efficiency factor 96
4.4.2.4 The design of compensation grouting facilities.96
4.5 Ground improvement 97
4.6 Structural strengthening 98
The Jubilee Line Extension Project 99
5.1 Introduction 99
5.2 Geology, geomorphology and hydrogeology 100
5.2.1 The geological succession 100
5.2.2 The London Clay Formation 101
5.2.3 The units of the London Clay Formation 101
5.2.4 Scour hollows 103
5.2.5 Hydrogeology 104
5.3 London Bridge 105
5.3.1 Ground conditions 105
5.3.2 Groundwater conditions 106
Chapter 4
Chapter 5
-
Table of Contents
Chapter 6 The underground works 109
6.1 London Bridge 109
6.2 Tunnelling 111
6.2.1 Running/station tunnels 113
6.2.2 Station concourse tunnel 115
6.2.3 Western escalator shaft 117
6.2.4 Interlocking Machine Room tunnel 118
6.2.5 Western ventilation tunnel and shaft 119
6.2.6 Western emergency escape shaft 121
6.2.7 Station cross-passages 121
6.2.8 JLE/Northern Line interchange passage 122
6.2.9 Eastern escalator shaft 124
6.2.10 Eastern ventilation tunnel and shaft 127
6.2.11 Station tunnel cable adit 129
6.2.12 Temporary works grouting shaft 130
6.2.13 Eastern emergency escape shaft 130
6.2.14 Temporary works grouting adit 131
6.3 Ground treatment 132
6.3.1 Permeation grouting 132
6.3.1.1 Western escalator shaft 133
6.3.1.2 Western ventilation shaft 133
6.3.1.3 Western emergency escape shaft... 134
6.3.1.4 Eastern escalator shaft 134
6.3.1.5 Station tunnel cable adit 135
6.3.1.6 Temporary works grouting shaft 136
6.3.1.7 Eastern emergency escape shaft.... 136
6.3.2 Compensation grouting 136
6.4 Northern Line Works 139
6.4.1 Borough High Street southern escalator shaft 140
6.4.2 Ground treatment 141
Chapter? Instrumentation and monitoring 143
7.1 Introduction 143
7.2 Error and uncertainty 144
7.3 Surface instrumentation 144
7.3.1 Precision levelling 144
7.3.1.1 Equipment 145
-9-
-
Table of Contents
7.3.1.2 Procedure 149
7.3.1.3 Measurement accuracy 149
7.3.1.4 Data reduction 151
7.3.1.5 Precision level monitoring point locations
152
7.3.2 Facade monitoring 153
7.3.2.1 Equipment 154
7.3.2.2 Procedure 155
7.3.2.3 Uncertainty and sources of error 155
7.3.2.4 Analysis of measurements 157
7.3.3 Crack monitoring 158
7.3.3.1 Equipment and procedure 159
7.3.3.2 Accuracy and potential errors 161
7.3.3.3 Analysis of readings 161
7.3.4 Electrolevel beams 165
7.3.4.1 Principles of electrolevel devices 166
7.3.4.2 Equipment and procedure 167
7.3.4.3 Processing measurements 167
Chapter 8 London Bridge 173
8.1 Introduction 173
8.2 Background 173
8.2.1 St Thomas's Hospital 174
8.2.2 The Industrial Revolution and the Railway Age 177
8.2.2.1 The Surface Railways 177
8.2.2.2 The Underground 179
8.2.3 World War II 180
8.2.4 Post-war 181
8.3 Case History Buildings 181
8.3.1 London Bridge Post Office 181
8.3.2 Alam House 183
8.3.3 The Southwark Cathedral Chapter House 183
8.3.3.1 Building Description 183
8.3.3.2 Building Condition 186
8.3.4 Collegiate House 187
8.3.5 Mary Sheridan House 190
8.3.6 Telephone House 192
-10"
-
Table of Contents
8.3.7 The BT Building 194
8.3.8 Fielden House 195
8.4 Potential Damage Assessnnent 196
8.5 Protective Measures 199
8.5.1 The Southwark Cathedral Chapter House 199
8.5.2 The BT Building 199
8.5.3 Fielden House 199
Chapter 9 Overall surface settlement response 201
9.1 Introduction 201
9.2 Surface settlement database 202
9.3 Construction sequence 204
9.4 Surface settlement behaviour 205
9.4.1 Longitudinal response 206
9.4.1.1 Section A-A 207
9.4.1.2 Section B-B 210
9.4.1.3 Section C-C 213
9.4.2 Transverse response 216
9.4.2.1 Section D-D 216
9.4.2.2 Section E-E 219
9.4.2.3 Section F-F 223
9.4.2.4 Section G-G 227
9.4.2.5 Section H-H 230
9.5 Summary 233
Chapter 10 London Bridge Street 237
10.1 Introduction 237
10.2 Telephone House 239
10.2.1 Observed behaviour 242
10.2.1.1 Time-settlement response 242
10.2.1.2 Longitudinal facade profiles 246
10.2.1.3 Distortion 250
10.2.1.4 Total station monitoring 252
10.2.1.4.1 Vertical displacements 253
10.2.1.4.2 In-plane horizontal movements 253
10.2.1.4.3 In-plane horizontal strains 254
10.2.1.4.4 Out-of-plane horizontal movements. 256
10.2.1.5 Cross wall behaviour 258
- 1 1 -
-
Table of Contents
10.2.1.6 Twist 260
10.2.2 Dannage recorded 262
10.2.2.1 Junction with London Bridge Street arches 262
10.2.2.2 Eastern end of Telephone House 264
10.2.3 Summary 265
10.3 The BT Building 268
10.3.1 Observed behaviour 270
10.3.1.1 Time-settlement response 270
10.3.1.2 Longitudinal facade profiles 271
10.3.1.3 Distortion 273
10.3.1.4 Total station surveying 275
10.3.1.4.1 Vertical displacements 276
10.3.1.4.2 In-plane horizontal movements 276
10.3.1.4.3 Construction joint behaviour 276
10.3.1.4.4 In-plane horizontal strains 278
10.3.1.4.5 Out-of-plane horizontal movements. 279
10.3.1.5 Transverse behaviour 281
10.3.1.6 Compensation grouting 282
10.3.1.7 Twist 282
10.3.2 Damage recorded 284
10.3.3 Summary 284
10.4 Fielden House 286
10.4.1 Observed behaviour 288
10.4.1.1 Time-settlement response 288
10.4.1.2 Longitudinal facade profiles 291
10.4.1.3 Distortion 293
10.4.1.4 Total station monitoring 295
10.4.1.4.1 Vertical displacements 296
10.4.1.4.2 In-plane horizontal movements 296
10.4.1.4.3 In-plane horizontal strains 296
10.4.1.4.4 Out-of-plane horizontal movements.. 297
10.4.1.5 Transverse behaviour 298
10.4.1.6 Compensation grouting 300
10.4.1.7 Twist 301
10.4.2 Damage recorded 302
10.4.2.1 Junction with London Bridge Street arches 302
- 1 2 -
-
Table of Contents
10.4.2.2 Eastern stairwell 304
10.4.3 Summary 305
10.5 London Bridge Post Office 306
10.5.1 Observed behaviour 309
10.5.1.1 Time-settlement response 309
10.5.1.2 Longitudinal facade profiles 313
10.5.1.3 Distortion 315
10.5.1.4 Cross wall behaviour 316
10.5.1.5 Compensation grouting 318
10.5.1.6 Twist 319
10.5.2 Damage recorded 320
10.5.3 Summary 321
10.6 Conclusions 322
Chapter 11 St Thomas Street 325
11.1 Introduction 325
11.2 Alam House 327
11.2.1 Observed behaviour 330
11.2.1.1 Time-settlement response 330
11.2.1.2 Longitudinal facade profiles 331
11.2.1.3 Distortion 333
11.2.1.4 Cross wall profiles 334
11.2.1.5 Twist 335
11.2.2 Damage recorded 336
11.2.3 Summary 336
11.3 The Southwark Cathedral Chapter House 337
11.3.1 Observed behaviour 340
11.3.1.1 Time-settlement response 342
11.3.1.1.1 Bell tower 342
11.3.1.1.2 Chapel 344
11.3.1.2 Distortion 345
11.3.1.2.1 Bell tower 345
11.3.1.2.2 Chapel 348
11.3.1.3 Behaviour in real-time 350
11.3.2 Damage recorded 352
11.3.2.1 Bell tower 354
11.3.2.2 Chapel 356
-13-
-
Table of Contents
11.3.3 Summary 360
11.4 Collegiate House 363
11.4.1 Observed behaviour 365
11.4.1.1 Time-settlement response 365
11.4.1.2 Longitudinal facade profiles 368
11.4.1.3 Distortion 370
11.4.1.4 Behaviour in real-time 371
11.4.2 Damage recorded 372
11.4.3 Summary 376
11.5 Mary Sheridan House 377
11.5.1 Observed behaviour 380
11.5.1.1 Time-settlement response 380
11.5.1.2 Longitudinal facade profiles 383
11.5.1.3 Distortion 384
11.5.1.4 Electrolevel beams 384
11.5.2 Damage recorded 387
11.5.3 Summary 389
11.6 Conclusions 391
Chapter 12 Conclusions and recommendations 395
12.1 Introduction 395
12.2 Aim of research 396
12.3 Compilation of Case Histories 396
12.4 Overall surface settlement response 397
12.5 Building behaviour 399
12.6 Protective measures 404
12.7 Long term movements 406
12.8 Instrumentation 408
12.9 Potential damage assessment 409
12.10 Recommendations 411
12.10.1 Future research 411
12.10.2Future practice 412
References 415
-14-
-
Table of Contents
Appendices
A - Ground Investigation 429
B - JLEP C104 As-built drawings 431
C - Geological Reports 435
D - Pre-construction Structural Surveys 437
E - Pre-construction Schedules of Defects 439
F - Structure Settlement Reports 441
G - The Southwark Cathedral Chapter House 443
Volume 2
Tables, figures and plates for chapters
-15-
-
List of Tables
List of Tables 1.1 Case history buildings 445
2.1 Open-face shield tunnelling: construction sequence (after Fujita, 1989) 447
3.1 Definitions of foundation movement (after Burland and Wroth, 1975) 449
3.2 Allowable total settlements of foundations (after Lake et al., 1992) 450
3.3 Summary of limiting deformations (after I.Struct.E., 1978) 451
3.4 Relationship between limiting tensile strain and damage category 452
3.5 Classification of visible damage to walls with particular reference to ease
of repair of plaster and brickwork or masonry (after Burland et al., 1977) 453
6.1 Station tunnel enlargements: stoppages 455
6.2 Station cross passages: sequence of excavation 456
7.1 Monitoring of case history buildings at London Bridge 457
7.2 Uncertainty in geotechnical instrumentation and monitoring: terms and
definitions 458
7.3 Types of error 459
8.1 Building geometry 461
8.2 Damage assessment 462
12.1 London Bridge: general summary 463
12.2 London Bridge: summary of settlements and slopes 464
12.3 London Bridge: summary of deformation parameters 465
-17-
-
List of Figures
List of Figures 1.1 The City and South London Railway (also showing extensions made after
incorporation into the Underground group) 467
2.1 Typical mechanised open-face tunnelling shield (after Mair, 2001) 469 2.2 Definition of volume loss (after Standing and Burland, 2005) 469 2.3 Sources of ground loss (after Attewell et al., 1986) 470 2.4(a) The SCL method: Type 1 excavation sequence (after ICE, 1996) 471 2.4(b) The SCL method: Type 2 excavation sequence (after ICE, 1996) 472 2.4(c) The SCL method: Type 3 excavation sequence (after ICE, 1996) 473 2.4(d) The SCL method: Type 4 excavation sequence (after ICE, 1996) 473 2.5(a) Influence of pilot tunnel in reducing ground movements for a hand-excavated
tunnel in stiff clay without a shield (a) sources of ground movement in the absence of a pilot tunnel (after Mair, 1993) 474
2.5(b) Influence of pilot tunnel in reducing ground movements for a hand-excavated tunnel in stiff clay without a shield (b) effect of pilot tunnel in restricting ground movements (after Mair, 1993) 474
2.6 The surface settlement trough (after Attewell et al., 1986) 475 2.7 Idealised transverse surface settlement profile with normal distribution
(from Lake et al., 1992) 475 2.8 Idealised longitudinal surface settlement profile with cumulative normal
distribution form (from Lake et al., 1992) 476 2.9 Transverse surface displacements and strains shortly after tunnelling
(from Lake et al., 1992) 476 2.10 Variation of sub-surface settlement trough width parameter with depth for
tunnels in clay (after Mair et al., 1993) 477 2.11 Twin tunnels: superposition of individual settlement profiles
(after Addenbrooke, 1996) 478 2.12 Settlement profiles above twin tunnels on the Washington D.C. Metro
(after Cording and Hansmire, 1976) 478 2.13 Settlement induced by shaft sinking (after New and Bowers, 1994) 479 2.14 Horizontal movement induced by shaft sinking
(after New and Bowers, 1994) 479
3.1 Two-dimensional components of deformation (after Geddes, 1984) 481 3.2 Definitions of ground and foundation movement
(after Burland and Wroth, 1975) 481 3.3 Cracking of simple beam in bending and shear (from Addenbrooke, 1996)482 3.4 Relationship between A/(LG) and L/H for rectangular beams deflecting due
to combined bending and shear (after Burland and Wroth, 1975) 482 3.5 Cracking of model brick walls in sagging and hogging
(after Burland and Wroth, 1975) 483 3.6 Damage in relation to angular distortion and horizontal extension strain
(from Boscardin and Cording, 1989) 484 3.7(a) Influence of horizontal strain on (A/L)/e for (a) bending strain governing
(after Burland, 1995) 484 3.7(b) Influence of horizontal strain on (A/L)/e for (b) diagonal strains governing
(after Burland, 1995) 484 3.7(c) Influence of horizontal strain on (A/L)/e for (c) combination of (a) and (b)
(after Burland, 1995) 484
-19-
-
List of Figures
3.8 Damage category in relation to deflection ratio and horizontal tensile strain for hogging mode of deformation with L/H=1 (from Burland, 1995) 485
3.9 Relationship between (3^a/(A/L) and H/L for beams with both central point loads and uniformly distributed loads, with the neutral axis at the lower edge (after Burland et al., 2004) 485
3.10 Damage category in relation to estimated cumulative crack widths (after Boone, 1996) 486
3.11 Comparison of observed and greenfield site settlements for the Mansion House (after Frischmann et al., 1994) 486
3.12 Modification factors for deflection ratio in hogging and sagging (after Potts and Addenbrooke, 1996) 487
3.13(a) Definition of twist (a) torsion of a single rod (from Franzius, 2004) 487 3.13(b) Definition of twist (b) the angle of twist per unit length
(from Franzius, 2004) 487 3.14 Idealised twist of a building footprint (after Franzius, 2004) 488
4.1 Face support: spiles (after Harris, 2001) 489 4.2 Barrel vaulting and excavation in parts (after Harris, 2001) 489 4.3 Principle of permeation grouting (after CIRIA, 2000) 490 4.4 Tube a manchette (TAM): typical details (after CIRIA, 2000) 490 4.5 TAM installation and operation (after Jardine, 2001) 491 4.6 Hydrofracture injection record (after Raabe and Esters, 1990) 492 4.7 Principle of compensation grouting (after Harris, 2001) 492 4.8 Grouting techniques (after Harris, 2001) 493 4.9 Grouting pressures; settlement compensation (after CIRIA, 2000) 494 4.10 Compensation grouting: example of grout exclusion zone 495 4.11 Ground improvement: pipe arch (after Harris, 2001) 496 4.12 Ground improvement: cut-off or curtain wall (after Harris, 2001) 496
5.1 The Jubilee Line Extension: plan alignment and geological profile 497 5.2 Geological map of the London Basin (from Simpson et al., 1989) 498 5.3 Sub-divisions within the London Clay Formation (from Hight et al., 2003) 499 5.4 Locations of suspected faults and scour hollows at London Bridge 500 5.5 Possible scour feature at London Bridge (based on Mott, Hay & Anderson)501 5.6 London Bridge: exploratory hole location plan 502 5.7 Piezometric profiles at Waterloo: effect of drainage to tunnel ( after
Hight etal., 1993) 503
6.1 London Bridge: complex transport interchange 505 6.2(a) JLE London Bridge Station: general layout of station complex 506 6.2(b) JLE London Bridge Station: general layout of station tunnels 507 6.3 JLE London Bridge Station: schematic view of station complex 508 6.4 SCL: Type 4 cross-sectional detail (after ICE, 1996) 509 6.5 SCL: Type 3 excavation sequence (after ICE, 1996) 509 6.6 Station tunnels: invert detail 510 6.7 Running/Station Tunnels: transition zones 510 6.8(a) Station Tunnels: pilot tunnel progress 511 6.8(b) Station Tunnels: pilot tunnel incremental excavation progress 511 6.9(a) Station Tunnels: progress of enlargement works 512 6.9(b) Station Tunnels: enlargement works incremental excavation progress 512 6.10(a) Concourse Tunnel: plan and section 513 6.10(b) Concourse Tunnel: cross sections at junctions with escalator shafts 513 6.11(a) Concourse Tunnel: pilot tunnel progress 514
- 2 0 -
-
List of Figures
6.11 (b) Concourse Tunnel: pilot tunnel incremental excavation progress 514 6.12(a) Concourse Tunnel: progress of enlargement works 515 6.12(b) Concourse Tunnel: enlargement works incremental excavation progress 515 6.13 Western Escalator Shaft 516 6.14 Interlocking Machine Room Tunnel 517 6.15 Western Ventilation Tunnel: plan and sections 518 6.16(a) Western Ventilation Shaft: plan 519 6.16(b) Western Ventilation Shaft: section 520 6.17(a) Western Emergency Escape Shaft: plans 521 6.17(b) Western Emergency Escape Shaft: sections 522 6.18(a) JLE/NL Interchange Passage: plan 523 6.18(b) JLE/NL Interchange Passage: section 524 6.19 JLE/NL Interchange Passage: construction sequence #1 525 6.20 JLE/NL Interchange Passage: construction sequence #2 526 6.21 JLE/NL Interchange Passage: overbridge pilot headings 527 6.22(a) JLE/NL Interchange Passage: typical breakout details 528 6.22(b) JLE/NL Interchange Passage: typical support details for hand excavation
works 528 6.23(a) Eastern Escalator: Lower Inclined Shaft - plan 529 6.23(b) Eastern Escalator: Lower Inclined Shaft - section 530 6.24 Eastern Escalator: Intermediate Horizontal Concourse 531 6.25 Eastern Escalator: Upper Inclined Shaft - plan and section 532 6.26(a) Eastern Escalator: (proposed) construction sequence #1 533 6.26(b) Eastern Escalator: (proposed) construction sequence #2 534 6.27(a) Eastern Escalator: breakout from the Long Subway Tunnel - plan 535 6.27(b) Eastern Escalator: breakout from the Long Subway Tunnel - Section B-B 536 6.27(c) Eastern Escalator: breakout from the Long Subway Tunnel - Section A-A 537 6.28 Eastern Ventilation Shaft: plan and sections 538 6.29(a) Eastern Ventilation Tunnel: plan 539 6.29(b) Eastern Ventilation Tunnel: developed section 540 6.30 Station Tunnel Cable Adit 541 6.31 Temporary Works Grouting Shaft 541 6.32(a) Eastern Emergency Escape Shaft: plan 542 6.32(b) Eastern Emergency Escape Shaft: sections 543 6.33 Temporary Works Grouting Adit 544 6.34 Permeation Grouting Treatment Areas 545 6.35 Compensation Grouting Treatment Areas 546 6.36(a) Compensation Grouting TAMs: the C-Series 547 6.36(b) Compensation Grouting TAMs: the E-Series 548 6.36(c) Compensation Grouting TAMs: the Phase I T-Series 549 6.36(d) Compensation Grouting TAMs: the Phase II T-Series 550 6.36(e) Compensation Grouting TAMs: the V-Series 551 6.37 Compensation Grouting: typical sections 553 6.38 Compensation Grouting: grout exclusion zone 555 6.39 Northern Line Borough High Street escalator shaft 555
7.1 BRE monitoring sockets and levelling plugs 557 7.2 Typical JLEP monitoring socket and levelling plug 557 7.3 Precision level monitoring point locations 558 7.4 Deflection ratio variation 559 7.5(a) Total station theodolite (a) schematic diagram 560 7.5(b) Total station theodolite (b) collimation errors 560
- 2 1 -
-
List of Figures
7.6 Total station distance measurements: the influence of temperature and relative humidity 560
7.7(a) Avongard tell-tale: conventional version 561 7.7(b) Avongard tell-tale: hinged version 561 7.8(a) Reference disc layouts: (a) two discs 562 7.8(b) Reference disc layouts: (b) three discs 562 7.8(c) Reference disc layouts: (c) four discs 562 7.8(d) Reference disc layouts: (d) multiple discs 562 7.9 In-plane relative rigid body displacements 562 7.10 Relationships between displacement components and gauge length
variations: three discs, rigid body relative translation 563 7.11(a) Relationships between displacement components and gauge length
variations; four discs (a) rigid-body translation, UgVg 564 7.11 (b) Relationships between displacement components and gauge length
variations: four discs (b) rigid-body rotation, cp 564 7.12 Diagram showing the assumptions made in deriving the expressions for
the vectors of displacement 565 7.13(a) Relative error in gauge length variation as a function of (a) magnitude 566 7.13(b) Relative error in gauge length variation as a function of (b) direction of
relative displacement 566 7.14 Metal disc arrangements recommended by the BRE (1989) 567 7.15 Metal disc arrangements recommended by the CIRIA LINK Research Team
567 7.16 The electrolevel: basic operating principle 568 7.17 The electrolevel beam: typical details 569 7.18(a) Electrolevel strings: positions of electrolevels 570 7.18(b) Electrolevel strings: calculation model 570 7.19 Electrolevel strings: components of displacement 571 7.20 Example of electrolevel beam validation 573 7.21 Variation of relative vertical displacement 573 7.22 Gross anomalies between electrolevel data and precision levelling
measurements 575
8.1 Southwark: London Bridge 577 8.2 Map of Southwark dated 1530 578 8.3 Plan of St Thomas's Hospital in 1800 579 8.4 Extract from John Rocque map of 1747 580 8.5 Plan of St Thomas's Hospital in about 1853 581 8.6 Schematic of railway development at London Bridge 582 8.7 Extract from Ordnance Survey map of 1872 583 8.8 Extract from Ordnance Survey map of 1894 584 8.9 Extract from Ordnance Survey map of 1916 585 8.10 Extract from Ordnance Survey map of 1952 586 8.11 Section through the centre-line of the Long Subway tunnel 587 8.12 General Arrangement: existing and proposed tunnels of the Northern Line
beneath Borough High Street 588 8.13(a) Existing sub-surface infrastructure at Borough High Street/London Bridge
Street junction: plan of upper level tunnels 589 8.13(b) Existing sub-surface infrastructure at Borough High Street/London Bridge
Street junction: plan of lower level tunnels 590 8.13(c) Existing sub-surface infrastructure at Borough High Street/London Bridge
Street junction: Section A-A 591
- 2 2 -
-
List of Figures
8.13(d) Existing sub-surface infrastructure at Borougin Higli Street/London Bridge Street junction: Sections B-B and C-C 592
8.13(e) Existing sub-surface infrastructure at Borougli High Street/London Bridge Street junction: plan of the eastern end of the Long Subway tunnel 593
8.13(f) Existing sub-surface infrastructure at Borough High Street/London Bridge Street junction: Sections A-A and B-B through the Long Subway tunnel 594
8.14 Existing sub-surface infrastructure at Borough High Street/London Bridge Street junction: WW II air-raid shelter access tunnel 595
8.15 Location plan of case history buildings 596 8.16 The Southwark Cathedral Chapter House 597 8.17(a) The Southwark Cathedral Chapter House and Collegiate House: plan of
the basements 598 8.17(b) The Southwark Cathedral Chapter House and Collegiate House: ground
floor plans 599 8.17(c) The Southwark Cathedral Chapter House: plan of the first floor 600 8.18 Collegiate House 600 8.19 Mary Sheridan House 601 8.20 Fielden House 601 8.21 (a) The BT Building: plan of structural protective measures 602 8.21 (b) The BT Building: structural protective measures - Section C-C 603 8.21 (c) The BT Building: structural protective measures - Sections A-A and B-B 604 8.22 Fielden House: structural protective measures 605
9.1 Locations of section lines 607 9.2 Section A-A: precision level monitoring point locations 608 9.3 Section B-B: precision level monitoring point locations 609 9.4 Section C-C: precision level monitoring point locations 610 9.5 Section D-D: precision level monitoring point locations 611 9.6 Section E-E: precision level monitoring point locations 612 9.7 Section F-F: precision level monitoring point locations 613 9.8 Section G-G: precision level monitoring point locations 614 9.9 Section H-H: precision level monitoring point locations 615 9.10 JLE London Bridge underground station: construction/monitoring sequence
616 9.11 (a) Section A-A time-settlement profiles: 24 May 1994 to 24 May 1995 617 9.11 (b) Section A-A time-settlement profiles: 4 May 1995 to 21 December 1995 617 9.11 (c) Section A-A time-settlement profiles: 19 October 1995 to 29 March 1996 618 9.11 (d) Section A-A time-settlement profiles: 23 January 1996 to 17 June 1996 618 9.11 (e) Section A-A time-settlement profiles: 1 June 1996 to 28 October 1996 619 9.11(f) Section A-A time-settlement profiles: 13 September 1996 to 4 January 1997
619 9.11 (g) Section A-A time-settlement profiles: 1 December 1996 to 11 June 1997 620 9.12(a) Section B-B time-settlement profiles: 24 May 1994 to 24 May 1995 621 9.12(b) Section B-B time-settlement profiles: 4 May 1995 to 21 December 1995 621 9.12(c) Section B-B time-settlement profiles: 19 October 1995 to 29 March 1996 622 9.12(d) Section B-B time-settlement profiles: 23 January 1996 to 17 June 1996 622 9.12(e) Section B-B time-settlement profiles: 1 June 1996 to 28 October 1996 623 9.12(f) Section B-B time-settlement profiles: 13 September 1996 to 4 January 1997
623 9.12(g) Section B-B time-settlement profiles: 1 December 1996 to 11 June 1997 624 9.13(a) Section C-C time-settlement profiles: 24 May 1994 to 24 May 1995 625 9.13(b) Section C-C time-settlement profiles: 4 May 1995 to 21 December 1995 625 9.13(c) Section C-C time-settlement profiles: 19 October 1995 to 29 March 1996 626
-23-
-
List of Figures
9.13(d) Section C-C time-settlement profiles: 23 January 1996 to 17 June 1996 626 9.13(e) Section C-C time-settlement profiles: 1 June 1996 to 28 October 1996 627 9.13(f) Section C-C time-settlement profiles: 13 September 1996 to 4 January 1997
627 9.13(g) Section C-C time-settlement profiles: 1 December 1996 to 11 June 1997 628 9.14(a) Section D-D time-settlement profiles: 24 May 1994 to 24 May 1995 629 9.14(b) Section D-D time-settlement profiles: 4 May 1995 to 21 December 1995 629 9.14(c) Section D-D time-settlement profiles: 19 October 1995 to 29 March 1996 630 9.14(d) Section D-D time-settlement profiles: 23 January 1996 to 17 June 1996 630 9.14(e) Section D-D time-settlement profiles: 1 June 1996 to 28 October 1996 631 9.14(f) Section D-D time-settlement profiles: 13 September 1996 to 4 January 1997
631 9.14(g) Section D-D time-settlement profiles: 1 December 1996 to 11 June 1997 632 9.15(a) Section E-E time-settlement profiles: 24 May 1994 to 24 May 1995 633 9.15(b) Section E-E time-settlement profiles: 4 May 1995 to 21 December 1995 633 9.15(c) Section E-E time-settlement profiles: 19 October 1995 to 29 March 1996 634 9.15(d) Section E-E time-settlement profiles: 23 January 1996 to 17 June 1996 634 9.15(e) Section E-E time-settlement profiles: 1 June 1996 to 28 October 1996 635 9.15(f) Section E-E time-settlement profiles: 13 September 1996 to 4 January 1997
635 9.15(g) Section E-E time-settlement profiles: 1 December 1996 to 11 June 1997 636 9.16(a) Section F-F time-settlement profiles: 24 May 1994 to 24 May 1995 637 9.16(b) Section F-F time-settlement profiles: 4 May 1995 to 21 December 1995 637 9.16(c) Section F-F time-settlement profiles: 19 October 1995 to 29 March 1996 638 9.16(d) Section F-F time-settlement profiles: 23 January 1996 to 17 June 1996 638 9.16(e) Section F-F time-settlement profiles: 1 June 1996 to 28 October 1996 639 9.16(f) Section F-F time-settlement profiles: 13 September 1996 to 4 January 1997
639 9.16(g) Section F-F time-settlement profiles: 1 December 1996 to 11 June 1997 640 9.17(a) Section G-G time-settlement profiles: 24 May 1994 to 24 May 1995 641 9.17(b) Section G-G time-settlement profiles: 4 May 1995 to 21 December 1995 641 9.17(c) Section G-G time-settlement profiles: 19 October 1995 to 29 March 1996 642 9.17(d) Section G-G time-settlement profiles: 23 January 1996 to 17 June 1996 642 9.17(e) Section G-G time-settlement profiles: 1 June 1996 to 28 October 1996 643 9.17(f) Section G-G time-settlement profiles: 13 September 1996 to 4 January 1997
643 9.17(g) Section G-G time-settlement profiles: 1 December 1996 to 11 June 1997 644 9.18(a) Section H-H time-settlement profiles: 24 May 1994 to 24 May 1995 645 9.18(b) Section H-H time-settlement profiles: 4 May 1995 to 21 December 1995 645 9.18(c) Section H-H time-settlement profiles: 19 October 1995 to 29 March 1996 646 9.18(d) Section H-H time-settlement profiles: 23 January 1996 to 17 June 1996 646 9.18(e) Section H-H time-settlement profiles: 1 June 1996 to 28 October 1996 647 9.18(f) Section H-H time-settlement profiles: 13 September 1996 to 4 January 1997
647 9.18(g) Section H-H time-settlement profiles: 1 December 1996 to 11 June 1997 648 9.19 Section A-A: longitudinal profiles during Period 11 649 9.20 Section A-A: longitudinal profiles during Period 13 649 9.21 Section A-A: longitudinal profiles during Period 15 650 9.22 Section B-B: longitudinal profiles during Period 11 650 9.23 Section B-B: longitudinal profiles during Period 13 651 9.24 Section B-B: longitudinal profiles during Period 15 651 9.25 Section C-C: longitudinal profiles during Period 11 652 9.26 Section C-C: longitudinal profiles during Period 15 652
-24-
-
List of Figures
9.27 Section D-D: transverse profiles during Periods 6, 7 & 8 653 9.28 Section D-D: transverse profiles during Periods 11, 12 & 13 653 9.29 Section D-D: transverse profiles during Period 19 654 9.30 Section E-E: transverse profiles during Periods 5, 6, 7 & 8 654 9.31 Section E-E: transverse profiles during Period 13 655 9.32 Section E-E: transverse profiles during Period 15 655 9.33 Section E-E: transverse profiles during Period 19 656 9.34 Section F-F: transverse profiles during Period 8 656 9.35 Section F-F: transverse profiles during Periods 13 & 14 657 9.36 Section F-F: transverse profiles during Periods 15 & 16 657 9.37 Section F-F: transverse profiles during Period 19 658 9.38 Section G-G: transverse profiles during Periods 12 & 13 658 9.39 Section G-G: transverse profiles during Periods 14, 15, 16, 17 & 18 659 9.40 Section G-G: transverse profiles during Periods 19 & 20 659 9.41 Section H-H: transverse profiles during Period 4 660 9.42 Section H-H: transverse profiles during Period 11 660 9.43 Section H-H: transverse profiles during Period 19 661 9.44 Grout intensity contour plot - Period 4 663 9.45 Grout intensity contour plot - Periods 5 to 8 665 9.46 Grout intensity contour plot - Period 11 667 9.47 Grout intensity contour plot - Period 13 669 9.48 Grout intensity contour plot - Period 15 671 9.49 Grout intensity contour plot - Period 19 673
10.1.1 London Bridge: building location plan 675
10.2.1 Telephone House: the underground works 676 10.2.2 Telephone House: compensation grouting TAM layout. 676 10.2.3 Telephone House: grout injection with time 677 10.2.4 Telephone House: building timeline during underground construction 678 10.2.5 Telephone House: overall grout intensity contour plot 679 10.2.6 Telephone House instrumentation: precision level monitoring point location
plan 679 10.2.7 Telephone House instrumentation: elevation showing locations of total
station retro-reflective targets 680 10.2.8 Telephone House instrumentation: electrolevel beam layout plan 680 10.2.9 Telephone House instrumentation: crack monitoring location plan 681 10.2.10 Telephone House: time-settlement profiles 682 10.2.11 Telephone House facade settlement profiles: northeast-facing, front facade
(a) Period 6 683 10.2.11 Telephone House facade settlement profiles: northeast-facing, front facade
(b) Period 7 683 10.2.11 Telephone House facade settlement profiles: northeast-facing, front facade
(c) Period 8 683 10.2.11 Telephone House facade settlement profiles: northeast-facing, front facade
(d) Period 10 683 10.2.11 Telephone House facade settlement profiles: northeast-facing, front facade
(e) Period 11 683 10.2.12 Telephone House facade settlement profiles: southwest-facing, rear facade
(a) Period 5 684 10.2.12 Telephone House facade settlement profiles: southwest-facing, rear facade
(b) Period 7 684
-25-
-
List of Figures
10.2.12 Telephone House facade settlement profiles: southwest-facing, rear facade (c) Period 8 684
10.2.12 Telephone House facade settlement profiles: southwest-facing, rear facade (d) Period 10 684
10.2.12 Telephone House facade settlement profiles: southwest-facing, rear facade (e) Period 11 684
10.2.13 Telephone House facade settlement profiles: northeast-facing, front facade in Period 5 (a) 685
10.2.13 Telephone House facade settlement profiles: northeast-facing, front facade in Period 5 (b) 685
10.2.13 Telephone House facade settlement profiles: northeast-facing, front facade in Period 5 (c) 685
10.2.13 Telephone House facade settlement profiles: northeast-facing, front facade in Period 5 (d) 685
10.2.13 Telephone House facade settlement profiles: northeast-facing, front facade in Period 5 (e) 685
10.2.14 Telephone House facade settlement profiles: southwest-facing, rear facade in Period 5 (a) 686
10.2.14 Telephone House facade settlement profiles: southwest-facing, rear facade in Period 5 (b) 686
10.2.14 Telephone House facade settlement profiles: southwest-facing, rear facade in Period 5 (c) 686
10.2.14 Telephone House facade settlement profiles: southwest-facing, rear facade In Period 5 (d) 686
10.2.14 Telephone House facade settlement profiles: southwest-facing, rear facade in Period 5 (e) 686
10.2.15 Telephone House: grout intensity contour plot for Period 5 687 10.2.16(a) Telephone House front facade: variation of slope with time 687 10.2.16(b) Telephone House front facade: variation of slope with time (west) 688 10.2.16(c) Telephone House front facade: variation of slope with time (east) 688 10.2.17(a) Telephone House front facade: variation of deflection ratio with time
(west) 689 10.2.17(b) Telephone House front facade: variation of deflection ratio with time
(east) 689 10.2.18 Telephone House front facade: variation of deflection ratio over entire
length of front facade with time 690 10.2.19(a) Telephone House: total station surveying - vertical displacements 690 10.2.19(b) Telephone House: total station surveying - variation of vertical displacements
with height 691 10.2.19(c) Telephone House: total station surveying - variation of vertical displacements
along top row of targets 691 10.2.19(d) Telephone House: total station surveying - variation of vertical displacements
along bottom row of targets 692 10.2.20(a) Telephone House: variation in incremental in-plane horizontal strain
with time 693 10.2.20(b) Telephone House: variation in cumulative in-plane horizontal strain
with time 694 10.2.21 Telephone House: in-plane horizontal strains developed during enlargement
of eastbound station pilot tunnel 695 10.2.22 Telephone House: out-of-plane horizontal movements in Period 5
(a) Section AA 696 10.2.22 Telephone House: out-of-plane horizontal movements in Period 5
(b) Section BB 696
- 2 6 -
-
List of Figures
10.2.22 Telephone House; out-of-plane horizontal movements in Period 5 (c) Section CC 696
10.2.22 Telephone House; out-of-plane horizontal movements in Period 5 (d) Section DD 696
10.2.22 Telephone House; out-of-plane horizontal movements in Period 5 (e) Section EE 696
10.2.23 Telephone House; out-of-plane horizontal movements in Periods 6 to 12 (a) Section AA 697
10.2.23 Telephone House; out-of-plane horizontal movements in Periods 6 to 12 (b) Section BB 697
10.2.23 Telephone House; out-of-plane horizontal movements in Periods 6 to 12 (c) Section CC 697
10.2.23 Telephone House; out-of-plane horizontal movements in Periods 6 to 12 (d) Section DD 697
10.2.23 Telephone House: out-of-plane horizontal movements in Periods 6 to 12 (e) Section EE 697
10.2.24 Telephone House: relative vertical displacements profiles from electrolevel beams - Periods 4 & 5 (a) A-Series 698
10.2.24 Telephone House; relative vertical displacements profiles from electrolevel beams - Periods 4 & 5 (b) E-Series 698
10.2.24 Telephone House: relative vertical displacements profiles from electrolevel beams - Periods 4 & 5 (c) F-Series 698
10.2.24 Telephone House: relative vertical displacements profiles from electrolevel beams - Periods 4 & 5 (d) C-Series 698
10.2.25 Telephone House: relative vertical displacements profiles from electrolevel beams - Period 7 (a) A-Series 699
10.2.25 Telephone House: relative vertical displacements profiles from electrolevel beams - Period 7 (b) E-Series 699
10.2.25 Telephone House: relative vertical displacements profiles from electrolevel beams - Period 7 (c) F-Series 699
10.2.25 Telephone House; relative vertical displacements profiles from electrolevel beams - Period 7 (d) C-Series 699
10.2.26 Telephone House: relative vertical displacements profiles from electrolevel beams - Period 8 (a) A-Series 700
10.2.26 Telephone House; relative vertical displacements profiles from electrolevel beams - Period 8 (b) E-Series 700
10.2.26 Telephone House: relative vertical displacements profiles from electrolevel beams - Period 8 (c) F-Series 700
10.2.26 Telephone House; relative vertical displacements profiles from electrolevel beams - Period 8 (d) C-Series 700
10.2.27 Telephone House facade settlement profiles: front and rear in Period 7 (a) 1 March 1996 701
10.2.27 Telephone House facade settlement profiles; front and rear in Period 7 (b) 3 May 1996 701
10.2.27 Telephone House facade settlement profiles: front and rear in Period 7 (c) 3 June 1996 701
10.2.27 Telephone House facade settlement profiles; front and rear in Period 7 (d) 13 June 1996 701
10.2.28 Telephone House facade settlement profiles; front and rear in Period 7 (a) 18 June 1996 702
10.2.28 Telephone House facade settlement profiles: front and rear in Period 7 (b) 18 July 1996 702
-27-
-
List of Figures
10.2.28 Telephone House facade settlement profiles: front and rear in Period 7 (c) 25 August 1996 702
10.2.28 Telephone House facade settlement profiles: front and rear in Period 7 (d) 14 September 1996 702
10.2.29 Telephone House facade settlement profiles: front and rear in Period 7 (a) 14 September 1996 703
10.2.29 Telephone House facade settlement profiles: front and rear in Period 7 (b) 28 October 1996 703
10.2.29 Telephone House facade settlement profiles: front and rear in Period 7 (c) 11 November 1996 703
10.2.29 Telephone House facade settlement profiles: front and rear in Period 7 (d) 29 November 1996 703
10.2.30 Telephone House facade settlement profiles: front and rear in Period 7 (a) 29 November 1996 704
10.2.30 Telephone House facade settlement profiles: front and rear in Period 7 (b) 21 January 1997 704
10.2.30 Telephone House facade settlement profiles: front and rear in Period 7 (c) 11 February 1997 704
10.2.30 Telephone House facade settlement profiles: front and rear in Period 7 (d) 22 March 1997 704
10.2.31 Telephone House: areas of damage 705 10.2.32 Telephone House: cracking at the interface between the building and the
arches of London Bridge Street 705 10.2.33 Telephone House: crack movement versus time for Crack THC1 706 10.2.34 Telephone House: crack behaviour along the interface with the London
Bridge Street arches 706 10.2.35(a) Telephone House: cracks on third floor 707 10.2.35(b) Telephone House: cracks on second floor 707 10.2.36 Telephone House: variation of movement with time, Crack THC6 708 10.2.37 Telephone House: cracking in the sub-basement 708
10.3.1 The BT Building: the underground works 709 10.3.2 The BT Building: compensation grouting TAM layout 709 10.3.3 The BT Building: grout injection with time 710 10.3.4 The BT Building: building timeline during underground construction 711 10.3.5 The BT Building: grout intensity contour plot 712 10.3.6 The BT Building instrumentation: precision level monitoring point location
plan 712 10.3.7 The BT Building instrumentation: total station retro-reflective target
location plan 713 10.3.8 The BT Building instrumentation: electrolevel beam layout plan 713 10.3.9 The BT Building instrumentation: crack monitoring location plan 714 10.3.10 The BT Building: time-settlement profiles 715 10.3.11 The BT Building facade settlement profiles: northeast-facing front facade
(a) Period 4 - Station Tunnel Enlargements 716 10.3.11 The BT Building facade settlement profiles: northeast-facing front facade
(b) Period 7 - Eastern Escalator Shaft - Stage 1 716 10.3.11 The BT Building facade settlement profiles: northeast-facing front facade
(c) Period 9 - Eastern Escalator Shaft - Stage 3 716 10.3.11 The BT Building facade settlement profiles: northeast-facing front facade
(d) Period 10 - Station Concourse/Eastern Escalator Shaft Transition 716 10.3.11 The BT Building facade settlement profiles: northeast-facing front facade
(e) Period 11 - Eastern Escalator Shaft - Stage 5 716
- 2 8 -
-
List of Figures
10.3.12 The BT Building facade settlement profiles; southwest-facing rear facade (a) Period 4 - Station Tunnel Enlargements 717
10.3.12 The BT Building facade settlement profiles: southwest-facing rear facade (b) Period 7 - Eastern Escalator Shaft - Stage 1 717
10.3.12 The BT Building facade settlement profiles: southwest-facing rear facade (c) Period 9 - Eastern Escalator Shaft - Stage 3 717
10.3.12 The BT Building facade settlement profiles: southwest-facing rear facade (d) Period 10 - Station Concourse/Eastern Escalator Shaft Transition 717
10.3.12 The BT Building facade settlement profiles: southwest-facing rear facade (e) Period 11 - Eastern Escalator Shaft - Stage 5 717
10.3.13(a) The BT Building variation of slope with time along front facade 718 10.3.13(b) The BT Building variation of slope with time along front facade:
spans 1332-1333 and 1333-1334 718 10.3.13(c) The BT Building variation of slope with time along front facade:
spans 1331 -1332 and 1334-1335 719 10.3.14(a) The BT Building variation of slope with time along rear facade:
both spans 719 10.3.14(b) The BT Building variation of slope with time along rear facade:
span 1787-1788 720 10.3.14(c) The BT Building variation of slope with time along rear facade:
span 1789-1790 720 10.3.15 The BT Building: variation in deflection ratio with time along the front
facade 721 10.3.16 The BT Building total station surveying in-plane horizontal movements at
construction joints (a) Telephone House 722 10.3.16 The BT Building total station surveying in-plane horizontal movements at
construction joints (b) The BT Building (West) 722 10.3.16 The BT Building total station surveying in-plane horizontal movements at
construction joints (c) The BT Building (East) 722 10.3.16 The BT Building total station surveying in-plane horizontal movements at
construction joints (d) Fielden House 722 10.3.17(a) The BT Building: incremental in-plane horizontal strains 723 10.3.17(b) The BT Building: cumulative in-plane horizontal strains 724 10.3.18 The BT Building: in-plane horizontal strains developed in response to east-
and westbound station tunnel enlargements 725 10.3.19 The BT Building: total station surveying out-of-plane horizontal
movements (a) Section AA 726 10.3.19 The BT Building: total station surveying out-of-plane horizontal
movements (b) Section BB 726 10.3.19 The BT Building: total station surveying out-of-plane horizontal
movements (c) Section CC 726 10.3.19 The BT Building: total station surveying out-of-plane horizontal
movements (d) Section DD 726 10.3.20 The BT Building: total station surveying out-of-plane horizontal
movements (a) Section AA 727 10.3.20 The BT Building: total station surveying out-of-plane horizontal
movements (b) Section BB 727 10.3.20 The BT Building: total station surveying out-of-plane horizontal
movements (c) Section CC 727 10.3.20 The BT Building: total station surveying out-of-plane horizontal
movements (d) Section DD 727 10.3.21 The BT Building relative vertical displacement profiles: D-Series
electrolevel beam string (a) Period 4 - Station Tunnel Enlargements 728
-29-
-
List of Figures
10.3.21 The BT Building relative vertical displacement profiles: D-Series electrolevel beam string (b) Period 7 - Eastern Escalator Shaft - Stage 1 728
10.3.22 The BT Building: variation of twist with time 728 10.3.23 The BT Building: areas of damage 729 10.3.24 The BT Building: cracking in internal basement flank walls 729
10.4.1 Fielden House: the underground works 731 10.4.2 Fielden House: compensation grouting TAM layout 731 10.4.3 Fielden House: grout injection with time 732 10.4.4 Fielden House: building timeline during underground construction 733 10.4.5 Fielden House: grout intensity contour plot 734 10.4.6 Fielden House instrumentation: precision level monitoring point location
plan 734 10.4.7 Fielden House instrumentation: total station retro-reflective target location
plan 735 10.4.8 Fielden House instrumentation: electrolevel beam layout plan 735 10.4.9 Fielden House instrumentation: crack monitoring location plan 736 10.4.10 Fielden House: time-settlement profiles 737 10.4.11 Fielden House facade settlement profiles: northeast-facing front facade
(a) Period 4 - Westbound Station Tunnel Enlargement 738 10.4.11 Fielden House facade settlement profiles: northeast-facing front facade
(b) Period 9 - Eastern Ventilation Tunnel - Stage 1 738 10.4.11 Fielden House facade settlement profiles: northeast-facing front facade
(c) Period 10 - Eastern Ventilation Tunnel - Stage 2 738 10.4.11 Fielden House facade settlement profiles: northeast-facing front facade
(d) Period 11 - Eastern Ventilation Tunnel - Stage 3 738 10.4.11 Fielden House facade settlement profiles: northeast-facing front facade
(e) Period 12 - Eastern Ventilation Shaft - Lower Section 738 10.4.12 Fielden House facade settlement profiles: southwest-facing rear facade
(a) Period 4 - Westbound Station Tunnel Enlargement 739 10.4.12 Fielden House facade settlement profiles: southwest-facing rear facade
(b) Period 9 - Eastern Ventilation Tunnel - Stage 1 739 10.4.12 Fielden House facade settlement profiles: southwest-facing rear facade
(c) Period 10 - Eastern Ventilation Tunnel - Stage 2 739 10.4.12 Fielden House facade settlement profiles: southwest-facing rear facade
(d) Period 11 - Eastern Ventilation Tunnel - Stage 3 739 10.4.12 Fielden House facade settlement profiles: southwest-facing rear facade
(e) Period 12 - Eastern Ventilation Shaft - Lower Section 739 10.4.13(a) Fielden House time-slope behaviour: spans 1336-1339, 1337-1339
and 1338-1339 740 10.4.13(b) Fielden House time-slope behaviour: spans 1336-1339
and 1336-1337 741 10.4.13(c) Fielden House time-slope behaviour: spans 1336-1339
and 1337-1338 742 10.4.13(d) Fielden House time-slope behaviour: spans 1336-1339
and 1336-1338 743 10.4.13(e) Fielden House time-slope behaviour: spans 1793-1794, 1794-1795
and 1336-1339 744 10.4.13(f) Fielden House time-slope behaviour: spans 1336-1339, 1791-1792
and 1791-1214 745 10.4.14 Fielden House: variation of deflection ratio with time for
spans 1793-1794-1795 746 10.4.15(a) Fielden House: incremental in-plane horizontal strains 747
-30-
-
List of Figures
10.4.15(b) Fielden House: cumulative in-plane horizontal strains 748 10.4.16 Fielden House: in-plane horizontal strains developed in response to
westbound station tunnel enlargement 749 10.4.17(a) Fielden House: total station surveying out-of-plane horizontal
movements (a) Section AA 750 10.4.17(b) Fielden House: total station surveying out-of-plane horizontal
movements (b) Section BB 750 10.4.17(c) Fielden House: total station surveying out-of-plane horizontal
movements (c) Section CC 750 10.4.17(d) Fielden House: total station surveying out-of-plane horizontal
movements (d) Section DD 750 10.4.18 Fielden House electrolevel beam strings: relative vertical displacements
(a) Period 4 - Westbound Station Tunnel Enlargement A-Series Electrolevel Beam String 751
10.4.18 Fielden House electrolevel beam strings: relative vertical displacements (b) Period 4 - Westbound Station Tunnel Enlargement
E-Series Electrolevel Beam String 751 10.4.18 Fielden House electrolevel beam strings: relative vertical displacements
(c) Period 9 - Eastern Ventilation Tunnel - Stage 1 A-Series Electrolevel Beam String 751
10.4.18 Fielden House electrolevel beam strings: relative vertical displacements (d) Period 9 - Eastern Ventilation Tunnel - Stage 1
E-Series Electrolevel Beam String 751 10.4.19 Fielden House: areas of damage 752 10.4.20 Fielden House: cracking in internal masonry wall of the sub-basement 752 10.4.21 Fielden House: variation of crack width with time for cracks FHC1 and
FHC2 753 10.4.22(a) Fielden House: cracking in the floor of the sub-basement 754 10.4.22(b) Fielden House: cracking in the ceiling of the sub-basement 754 10.4.23 Fielden House: cracking at the junction between the structure and brickwork
arches of London Bridge Street 755 10.4.24 Fielden House: behaviour of cracks FHC3, FHC4 and FHC5 over time 756
10.5.1 LBPO: the underground works 757 10.5.2(a) LBPO compensation grouting TAM layout: the C- and Phase I T-Series 757 10.5.2(b) LBPO compensation grouting TAM layout: the V-Series 758 10.5.2(c) LBPO compensation grouting TAM layout: the Phase II T-Series 758 10.5.3 LBPO: grout injection with time 759 10.5.4 LBPO: building timeline during underground construction 760 10.5.5 LBPO: overall grout intensity contour plot 761 10.5.6 LBPO instrumentation: precision level monitoring point location plan 761 10.5.7 LBPO instrumentation: electrolevel beam layout plan 762 10.5.8 LBPO instrumentation: crack monitoring location plan 763 10.5.9 LBPO: time-settlement profiles 764 10.5.10 LBPO: settlements developed in response to the excavation of the JLE/NL
interchange passage and western escalator shaft 765 10.5.11 LBPO: time-settlement curves 765 10.5.12 LBPO facade settlement profiles: northeast-facing facade
(a) Period 4 - Eastbound Station Tunnel Pilot 766 10.5.12 LBPO facade settlement profiles: northeast-facing facade
(b) Period 6 - Eastbound Station Tunnel Enlargement 766 10.5.12 LBPO facade settlement profiles: northeast-facing facade
(c) Period 8 - Station Concourse Pilot and Western Ventilation Tunnels 766
-31-
-
List of Figures
10.5.12 LBPO facade settlement profiles; northeast-facing facade (d) Period 9 - Station Concourse Tunnel Enlargement 766
10.5.12 LBPO facade settlement profiles; northeast-facing facade (e) Period 11 - JLE/NL Interchange Passage 766
10.5.13 LBPO facade settlement profiles; southwest-facing facade (a) Period 4 - Eastbound Station Tunnel Pilot 767
10.5.13 LBPO facade settlement profiles; southwest-facing facade (b) Period 6 - Eastbound Station Tunnel Enlargement 767
10.5.13 LBPO facade settlement profiles; southwest-facing facade (c) Period 8 - Station Concourse Pilot and Western Ventilation Tunnels 767
10.5.13 LBPO facade settlement profiles; southwest-facing facade (d) Period 9 - Station Concourse Tunnel Enlargement 767
10.5.13 LBPO facade settlement profiles; southwest-facing facade (e) Period 11 - JLE/NL Interchange Passage 767
10.5.14 LBPO facade settlement profiles; northeast- and southwest-facing facades (a) Period 13A - JLE Western Escalator Shaft, JLE/NL Interchange Passage and NL Southern Escalator Shaft 768
10.5.14 LBPO facade settlement profiles; northeast- and southwest-facing facades (b) Period 13A - JLE Western Escalator Shaft, JLE/NL Interchange Passage and NL Southern Escalator Shaft 768
10.5.14 LBPO facade settlement profiles; northeast- and southwest-facing facades (c) Period 13B - JLE Western Escalator Shaft, JLE/NL Interchange Passage and NL Southern Escalator Shaft 768
10.5.14 LBPO facade settlement profiles; northeast- and southwest-facing facades (d) Period 13B - JLE Western Escalator Shaft, JLE/NL Interchange Passage and NL Southern Escalator Shaft 768
10.5.15(a)LBPO; variation in longitudinal slope with time 769 10.5.15(b)LBPO: variation in transverse slope with time 769 10.5.16 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 6 (a) C-Series 770 10.5.16 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 6 (b) D-Series 770 10.5.16 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 6 (c) E-Series 770 10.5.16 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 6 (d) A-Series 770 10.5.17 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 8 (a) C-Series 771 10.5.17 LBPO electrolevel beam strings: relative vertical displacement profiles in
Period 8 (b) D-Series 771 10.5.17 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 8 (c) E-Series 771 10.5.17 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 8 (d) A-Series 771 10.5.18 LBPO electrolevel beam strings: relative vertical displacement profiles in
Period 9 (a) C-Series 772 10.5.18 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 9 (b) D-Series 772 10.5.18 LBPO electrolevel beam strings; relative vertical displacement profiles in
Period 9 (c) E-Series 772 10.5.18 LBPO electrolevel beam strings: relative vertical displacement profiles in
Period 9 (d) A-Series 772
-32-
-
List of Figures
10.5.19 LBPO facade settlement profiles; northeast- and southwest-facing facades in Period 6 (a) 5 September 1995 773
10.5.19 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 6 (b) 27 November 1995 773
10.5.19 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 6 (c) 15 January 1996 773
10.5.20 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 8 (a) 24 March 1996 774
10.5.20 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 8 (b) 3/4 May 1996 774
10.5.20 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 8 (c) 18 May 1996 774
10.5.20 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 8 (d) 24 June 1996 774
10.5.21 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 9 (a) 11 June 1996 775
10.5.21 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 9 (b) 15 July 1996 775
10.5.21 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 9 (c) 14 August 1996 775
10.5.21 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 9 (d) 13 September 1996 775
10.5.22 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 11 (a) 4 November 1996 776
10.5.22 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 11 (b) 11 November 1996 776
10.5.22 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 11 (c) 21 November 1996 776
10.5.22 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 11 (d) 9 December 1996 776
10.5.23 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 13 (a) 23 January 1997 777
10.5.23 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 13 (b) 18 February 1997 777
10.5.23 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 13 (c) 11 March 1997 777
10.5.23 LBPO facade settlement profiles: northeast- and southwest-facing facades in Period 13 (d) 28 April 1997 777
10.5.24 LBPO: areas of damage 778
11.1.1 St Thomas Street: building location plan 779
11.2.1 Alam House: the underground works 780 11.2.2 Alam House: compensation grouting TAM layout 780 11.2.3 Alam House: grout injection with time 781 11.2.4 Alam House: building timeline during underground construction 782 11.2.5 Alam House: overall grout intensity contour plot 783 11.2.6 Alam House instrumentation: precision level monitoring point location plan783 11.2.7 Alam House instrumentation: electrolevel beam layout plan 784 11.2.8 Alam House: time-settlement profiles 785 11.2.9 Alam House southwest-facing facade settlement profiles
(a) Period 7 - Station Tunnel Enlargements & IMR Tunnel 786
-33-
-
List of Figures
11.2.9 Alam House southwest-facing facade settlement profiles (b) Period 8 - Quiet 786
11.2.9 Alam House southwest-facing facade settlement profiles (c) Period 11 - Station Concourse Tunnel Enlargement 786
11.2.9 Alam House southwest-facing facade settlement profiles (d) Period 12 - Quiet 786
11.2.9 Alam House southwest-facing facade settlement profiles (e) Period 13 - Western Escalator Shaft 786
11.2.10(a) Alam House: variation of slope with time in longitudinal plane 787 11.2.10(b) Alam House: variation of slope with time in transverse plane 787 11.2.10(c) Alam House: variation of slope with time for both longitudinal and
transverse planes 788 11.2.11 Alam House: variation of deflection ratio with time 788 11.2.12 Alam House: relative vertical displacement profiles for D-Series
electrolevel beam string (a) Period 7 - Station Tunnel Enlargements 789
11.2.12 Alam House: relative vertical displacement profiles for D-Series electrolevel beam string (b) Period 8 - Quiet 789
11.2.12 Alam House: relative vertical displacement profiles for D-Series electrolevel beam string (c) Period 11 - Station Concourse Tunnel Enlargement 789
11.2.12 Alam House: relative vertical displacement profiles for D-Series electrolevel beam string (d) Period 12 - Quiet 789
11.2.13 Alam House: assumed relative vertical displacement profiles for eastern gable-end wall (a) Period 7 - Station Tunnel Enlargements 790
11.2.13 Alam House: assumed relative vertical displacement profiles for eastern gable-end wall (b) Period 8 - Quiet 790
11.2.13 Alam House: assumed relative vertical displacement profiles for eastern gable-end wall (c) Period 11 - Station Concourse Tunnel Enlargement 790
11.2.13 Alam House: assumed relative vertical displacement profiles for eastern gable-end wall (d) Period 12 - Quiet 790
11.3.1 The Southwark Cathedral Chapter House: the underground works 791 11.3.2(a)The Southwark Cathedral Chapter House: compensation grouting TAM
layout - the V-Series 791 11.3.2(b)The Southwark Cathedral Chapter House: compensation grouting TAM
layout - the Phase I T-Series 792 11.3.2(c)The Southwark Cathedral Chapter House: compensation grouting TAM
layout - the Phase II T-Series 792 11.3.3 The Southwark Cathedral Chapter House: grout injection with time 793 11.3.4 The Southwark Cathedral Chapter House: building timeline during
underground construction 794 11.3.5 The Southwark Cathedral Chapter House: overall grout intensity contour
plot 795 11.3.6 The Southwark Cathedral Chapter House instrumentation: precision level
monitoring point location plan 795
-34-
-
List of Figures
11.3.7(a) The Southwark Cathedral Chapter House instrumentation: electrolevel beam layout plan - basement 796
11.3.7(b) The Southwark Cathedral Chapter House instrumentation: electrolevel beam layout plan - ground floor 797
11.3.8 The Southwark Cathedral Chapter House instrumentation: tie-rod locations around the bell tower 798
11.3.9 The Southwark Cathedral Chapter House instrumentation: locations of 'pseudo' plumblines on bell tower 799
11.3.10(a) The Southwark Cathedral Chapter House instrumentation: crack monitoring location plan - basement 800
11.3.10(b) The Southwark Cathedral Chapter House instrumentation: crack monitoring location plan - ground floor 801
11.3.10(c) The Southwark Cathedral Chapter House instrumentation: crack monitoring location plan - first floor 802
11.3.11 The Southwark Cathedral Chapter House instrumentation: tensioned wire transducers location plan 803
11.3.12 The Southwark Cathedral Chapter House: variation with time of the in-plane horizontal strains and temperatures measured for the tie-rods on the northeast-facing elevation of the bell tower 804
11.3.13 The Southwark Cathedral Chapter House: time-settlement profiles for the bell tower 805
11.3.14 The Southwark Cathedral Chapter House: time-settlement profiles for the chapel 806
11.3.15 The Southwark Cathedral Chapter House: variation in North-South relative in-plane horizontal movement plotted against variation in East-West relative in-plane horizontal movement for 'pseudo' plumblines on bell tower 807
11.3.16 The Southwark Cathedral Chapter House: variation in relative in-plane horizontal movement with time for 'pseudo' plumblines on southwest-facing elevation of tower 808
11.3.17 The Southwark Cathedral Chapter House: variation in relative in-plane horizontal movement with time for 'pseudo' plumbline on southeast-facing elevation of tower 809
11.3.18 The Southwark Cathedral Chapter House: variation in relative in-plane horizontal movements during construction of the concourse tunnel 810
11.3.19 The Southwark Cathedral Chapter House: grout intensity contour plot during formation of the concourse tunnel 811
11.3.20 The Southwark Cathedral Chapter House: variation of tilt with time for southwest-facing elevation of bell tower - 'pseudo' plumblines and precision levelling 812
11.3.21 The Southwark Cathedral Chapter House: variation in slope with time for front facade of chapel 813
11.3.22 The Southwark Cathedral Chapter House: variation in slope with time for front facade of chapel during formation of concourse tunnel 814
11.3.23 The Southwark Cathedral Chapter House: grout intensity contour plot during enlargement of concourse pilot tunnel 815
11.3.24 The Southwark Cathedral Chapter House: variation in relative movement of tensioned wire transducers with time across chapel hall 816
11.3.25 The Southwark Cathedral Chapter House: variation in relative movement of tensioned wire transducers with time longitudinally in chapel hall 817
11.3.26 The Southwark Cathedral Chapter House: variation in relative movement of tensioned wire transducers during enlargement of concourse pilot tunnel 818
-35-
-
List of Figures
11.3.27 The Southwark Cathedral Chapter House; relative vertical displacements from electrolevel beam strings (a) B-Series (1-8) - Station Tunnel Pilots 819
11.3.27 The Southwark Cathedral Chapter House: relative vertical displacements from electrolevel beam strings (b) B-Series (9-18) - Station Tunnel Pilots 819
11.3.27 The Southwark Cathedral Chapter House: relative vertical displacements from electrolevel beam strings (c) A-Series (4-8) - Station Tunnel Pilots 819
11.3.27 The Southwark Cathedra! Chapter House: relative vertical displacements from electrolevel beam strings (d) A-Series (10-14) - Station Tunnel Pilots 819
11.3.28 The Southwark Cathedral Chapter House: relative vertical displacements from electrolevel beam strings (a) E-Series - Concourse Tunnel Pilot 820
11.3.28 The Southwark Cathedral Chapter House: relative vertical displacements from electrolevel beam strings (b) E-Series - Enlargement to Concourse Tunnel Pilot 820
11.3.28 The Southwark Cathedral Chapter House: relative vertical displacements from electrolevel beam strings (c) D-Series - Concourse Tunnel Pilot 820
11.3.28 The Southwark Cathedral Chapter House: relative vertical displacements from electrolevel beam strings (d) D-Series - Enlargement to Concourse Tunnel Pilot 820
11.3.29 The Southwark Cathedral Chapter House: areas of damage 821 11.3.30 The Southwark Cathedral Chapter House: variation in crack width with
time for bell tower cracks, nos. CHBT7 & CHBT12 822 11.3.31 The Southwark Cathedral Chapter House: variation in crack width with
time for bell tower cracks, nos. CHBT1 & CHBT3 823 11.3.32 The Southwark Cathedral Chapter House: variation in crack width with
time for chapel cracks, nos. CHCh2 & CHCh3 824 11.3.33 The Southwark Cathedral Chapter House: variation in crack width with
time for chapel cracks, nos. CHChI & CHCh12 825 11.3.34 The Southwark Cathedral Chapter House: variation in crack width with
time for crypt cracks, nos. CHCptI, CHCpt14, CHCpt17 & CHCpt19 826 11.3.35 The Southwark Cathedral Chapter House: variation in crack width with
time for chapel cracks, nos. CHCh4 & CHCh7 827
11.4.1 Collegiate House: the underground works 829 11.4.2(a) Collegiate House: compensation grouting TAM layout (a) V-Series 829 11.4.2(b) Collegiate House: compensation grouting TAM layout
(b) Phase II T-Series 830 11.4.3 Collegiate House: grout injection with time 831 11.4.4 Collegiate House: building timeline during underground construction 832 11.4.5 Collegiate House: overall grout intensity contour plot 833 11.4.6 Collegiate House instrumentation: precision level monitoring point
location plan 833 11.4.7 Collegiate House: time-settlement profiles 834 11.4.8(a) Collegiate House facade settlement profiles: collective southwest-facing
front facade (a) Station Tunnel Pilots 835 11.4.8(b) Collegiate House facade settlement profiles: collective southwest-facing
front facade (b) Enlargements to Station Tunnel Pilots 835
-36-
-
List of Figures
11.4.8(c) Collegiate House facade settlement profiles: collective southwest-facing front facade (c) Concourse Tunnel Pilot 835
11.4.8(d) Collegiate House facade settlement profiles: collective southwest-facing front facade (d) Enlargement to Concourse Tunnel Pilot 835
11.4.8(e) Collegiate House facade settlement profiles: collective southwest-facing front facade (e) Pilot Headings for JLE/NL Interchange Passage 835
11.4.9(a) Collegiate House facade settlement profiles: collective southwest-facing front facade - station tunnel pilots (a) 836
11.4.9(b) Collegiate House facade settlement profiles: collective southwest-facing front facade - station tunnel pilots (b) 836
11.4.9(c) Collegiate House facade settlement profiles: collective southwest-facing front facade - station tunnel pilots (c) 836
11.4.9(d) Collegiate House facade settlement profiles: collective southwest-facing front facade - station tunnel pilots (d) 836
11.4.9(e) Collegiate House facade settlement profiles: collective southwest-facing front facade - station tunnel pilots (e) 836
11.4.10(a) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargements to station tunnel pilots (a) 837
11.4.10(b) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargements to station tunnel pilots (b) 837
11.4.10(c) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargements to station tunnel pilots (c) 837
11.4.10(d) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargements to station tunnel pilots (d) 837
11.4.10(e) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargements to station tunnel pilots (e) 837
11.4.11 (a) Collegiate House facade settlement profiles: collective southwest-facing front facade - concourse pilot tunnel (a) 838
11.4.11 (b) Collegiate House facade settlement profiles: collective southwest-facing front facade - concourse pilot tunnel (b) 838
11.4.11 (c) Collegiate House facade settlement profiles: collective southwest-facing front facade - concourse pilot tunnel (c) 838
11.4.11 (d) Collegiate House facade settlement profiles: collective southwest-facing front facade - concourse pilot tunnel (d) 838
11.4.11 (e) Collegiate House facade settlement profiles: collective southwest-facing front facade - concourse pilot tunnel (e) 838
11.4.12(a) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargement to concourse pilot tunnel (a) 839
11.4.12(b) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargement to concourse pilot tunnel (b) 839
11.4.12(c) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargement to concourse pilot tunnel (c) 839
11.4.12(d) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargement to concourse pilot tunnel (d) 839
11.4.12(e) Collegiate House facade settlement profiles: collective southwest-facing front facade - enlargement to concourse pilot tunnel (e) 839
11.4.13(a) Collegiate House facade settlement profiles: collective southwest-facing front facade - pilot headings for JLE/NL interchange passage (a) 840
11.4.13(b) Collegiate House facade settlement profiles: collective southwest-facing front facade - pilot headings for JLE/NL interchange passage (b) 840
11.4.13(c) Collegiate House facade settlement profiles: collective southwest-facing front facade - pilot headings for JLE/NL interchange passage (c) 840
-37-
-
List of Figures
11.4.13(d) Collegiate House facade settlement profiles; collective southwest-facing front facade - pilot headings for JLE/NL interchange passage (d) 840
11.4.13(e) Collegiate House facade settlement profiles: collective southwest-facing front facade - pilot headings for JLE/NL interchange passage (e) 840
11.4.14 Collegiate House: variation of slope with time - front facade 841 11.4.15 Collegiate House: variation of slope with time - rear facade 842 11.4.16 Collegiate House: collective southwest-facing front facade - variation
of deflection ratio with time 843 11.4.17 Collegiate House: areas of damage 844 11.4.18 Collegiate House: variation in relative crack width with time for cracks
in the crypt 845 11.4.19(a) Collegiate House: variation in relative crack width with time for ground
floor cracks, nos. CollH2, CollH3, CollH4 & C0IIH6 846 11.4.19(b) Collegiate House: variation in relative crack width with time for ground
floor cracks, nos. CollH5, C0IIH8 & C0IIHIO 847 11.4.20 Collegiate House: extract from pre-construction defect survey 848 11.4.21 Collegiate House: variation in relative crack width with time for ground
floor cracks, nos. CollH3, CollH7, CollH9 & C0IIH11 849 11.4.22 Collegiate House: variation in relative crack width with time for ground
floor cracks, nos. C0IIHI, C0IIHI a & C0IIH6 850 11.4.23 Collegiate House: variation in relative crack width with time for cracks
on second floor 851
11.5.1 Mary Sheridan House: the underground works 853 11.5.2 Mary Sheridan House: compensation grouting TAM layout 853 11.5.3 Mary Sheridan House: grout injection with time 854 11.5.4 Mary Sheridan House: building timeline during underground construction 855 11.5.5 Mary Sheridan House: overall grout intensity contour plot 856 11.5.6 Mary Sheridan House instrumentation: precision level monitoring point
location plan 856 11.5.7 Mary Sheridan House instrumentation: electrolevel beam layout plan 857 11.5.8 Mary Sheridan House instrumentation: crack monitoring point location
plan 858 11.5.9 Mary Sheridan House: time-settlement profiles - Block 'A' 859 11.5.10Mary Sheridan House: time-settlement profiles - Block 'B' 860 11.5.11 Mary Sheridan House: variation of slope with time - Block 'A' 861 11.5.12Mary Sheridan House: variation of slope with time - Block 'B' 862 11.5.13(a) Mary Sheridan House: relative vertical displacements from M- and B-Series
electrolevel strings (a) M-Series - Concourse Tunnel Pilot 863 11.5.13(b) Mary Sheridan House: relative vertical displacements from M- and B-Series
electrolevel strings (b) M-Series - Enlargement to Concourse Tunnel Pilot 863 11.5.13(c) Mary Sheridan House: relative vertical displacements from M- and B-Series
electrolevel strings (c) B-Series - Concourse Tunnel Pilot 863 11.5.13(d) Mary Sheridan House: relative vertical displacements from M- and B-Series
electrolevel strings (d) B-Series - Enlargement to Concourse Tunnel Pilot 863
11.5.14(a) Mary Sheridan House: relative vertical displacements from A- and C-Series electrolevel strings (a) A-Series - Concourse Tunnel Pilot 864
11.5.14(b) Mary Sheridan House: relative vertical displacements from A- and C-Series electrolevel strings (b) A-Series - Enlargement to Concourse Tunnel Pilot 864
11.5.14(c) Mary Sheridan House: relative vertical displacements from A- and C-Series electrolevel strings (c) C-Series - Concourse Tunnel Pilot 864
-38-
-
List of Figures
11.5.14(d) Mary Sheridan House: relative vertical displacements from A- and C-Series electrolevel strings (d) C-Series - Enlargement to Concourse Tunnel Pilot 864
11.5.15(a) Mary Sheridan House; relative vertical displacements from D- and l-Series electrolevel strings (a) D-Series - Concourse Tunnel Pilot 865
11.5.15(b) Mary Sheridan House; relative vertical displacements from D- and l-Series electrolevel strings (b) D-Series - Enlargement to Concourse Tunnel Pilot 865
11.5.15(c) Mary Sheridan House; relative vertical displacements from D- and l-Series electrolevel strings (c) l-Series - Concourse Tunnel Pilot 865
11.5.15(d) Mary Sheridan House; relative vertical displacements from D- and l-Series electrolevel strings (d) l-Series - Enlargement to Concourse Tunnel Pilot 865
11.5.16(a) Mary Sheridan House; relative vertical displacements from H- and E-Series electrolevel strings (a) H-Series - Concourse Tunnel Pilot 866
11.5.16(b) Mary Sheridan House: relative vertical displacements from H- and E-Series electrolevel strings (b) H-Series - Enlargement to Concourse Tunnel Pilot
866 11.5.16(c) Mary Sheridan House: relative vertical displacements from H- and E-Series
electrolevel strings (c) E-Series - Concourse Tunnel Pilot 866 • 11.5.16(d) Mary Sheridan House: relative vertical displacements from H- and E-Series
electrolevel strings (d) E-Series - Enlargement to Concourse Tunnel Pilot 866
11.5.17 Mary Sheridan House: areas of damage 867 11.5.18 Mary Sheridan House: variation in relative crack width for cracks,
nos. MSH1, MSH15, MSH16& MSH18 868 11.5.19 Mary Sheridan House; variation in relative crack width for cracks,
nos. MSH5, MSH9, MSH10 & MSH20 869 11.5.20 Mary Sheridan House: variation in relative crack width for cracks,
nos. MSH23, MSH24 & MSH27 870
12.1 London Bridge: case history buildings 871 12.2 London Bridge: absolute settlements as of June 2000 872 12.3 London Bridge: post-construction, long-term settlements to June 2000 873
-39-
-
List of Plates
List of Plates I .1 London Bridge: case history buildings 875
8.1 LBPO: northern elevation 877 8.2 Alam House; front elevation 877 8.3(a) The Southwark Cathedral Chapter House 879 8.3(b) The Southwark Cathedral Chapter House: front elevation 879 8.3(c) The Southwark Cathedral Chapter House: 'nib'of LBPO 881 8.3(d) The Southwark Cathedral Chapter House: pre-existing cracking 881 8.4 Collegiate House: front elevation 883 8.5(a) Mary Sheridan House; front elevation of Blocks 'A' and 'B' 883 8.5(b) Mary Sheridan House: Block 'B' and single storey annex 885 8.6 Telephone House: front elevation 885 8.7 The BT Building; front elevation 887 8.8 Fielden House: front elevation 887
10.2.1 Telephone House; London Bridge Street pavement vaults 889 10.2.2 Telephone House: typical crack at interface, THC No.1 889 10.2.3 Telephone House: sub-vertical crack at interface, THC No.2 891 10.2.4 Telephone House: pre-existing cracking along arch of pavement vault 891 10.2.5 Telephone House: close-up of cracking along arch of pavement vault 893 10.2.6 Telephone House: sub-vertical crack beneath pavement light, THC No.2 893 10.2.7 Telephone House: crack at pavement lights/vault junction, THC No.2 895 10.2.8 Telephone House: configuration of recess between Telephone House and
the BT Building 895 10.2.9 Telephone House: cracking in northern wall of recess, THC Nos. 4-9 897 10.2.10 Telephone House: cracking in southern wall of recess, THC Nos. 4-9 897 10.2.11 Telephone House: close-up of cracking in recess, THC No. 6 899
I I . 1 The Southwark Cathedral Chapter House Chapel: historic movement at junction with LBPO. 901
11.2 Crack monitoring in the bell tower: current and historic, CHBT1 & CHBT3 901 11.3 The Old Operating Theatre Museum: continuation of full-height crack at junction
between the bell tower and chapel 903 11.4 Close-up of crack in Plate 11.3 903 11.5 Damage to the ceiling of The Old Operating Theatre Museum 905 11.6 The Southwark Cathedral Chapter House: view of junction with bell tower in
southwest corner 907 11.7 Cracking at junction between chapel and bell tower: CHChI, CHCh2 & CHCh3
907 11.8 Junction between bell tower and chapel at high level: cracking, crack monitoring
and protection to cornice 909 11.9 Detailed view of cracking at junction between bell tower and chapel; CHChI,
CHCh2 & CHCh3 909 11.10 Cracking in crypt of chapel at junction with bell tower: CHCptI 911 11.11 Cracking in celling of barrel-vaulted crypt; CHCptI 4 911 11.12 Close-up view of cracking in crypt at junction with the bell tower: CHCptI 913 11.13 Cracking in ceiling of northern vault of crypt adjacent to junction with the Porters
Lodge vau