Construction Process of a 3-storey bungalow

TRANSCRIPT

Page 1: Building Construction process

SCHOOL OF ARCHITECTURE• BUILDING• DESIGN

Centre for Modern Architecture Studies in Southeast Asia (MASSA)

Bachelor of Science (Honours) in Architecture

BUILDING CONSTRUCTION 1 [ARC 1523]

PROJECT 2: CONSTRUCTION ACTIVITY AND PROCESS

JOANNE BERNICE CHUA YUNN TZE 0315905

TUTOR: AR. CHIN TUCK HING

Page 2: Building Construction process

CONSTRUCTION PROCESS

WEEK 1

Activity 1: Survey Work

Duration: 7 days

Materials: -

Equipment: Surveying tripod, Theodolite, Dumpy level, Measuring tape, Excavator

Skilled Workers: Land surveyor (1), Soil investigator (1)

Technical Information: Built environment and natural surroundings of the site is studied, analysed

and data is collected. Trial pitting is carried out to examine soil condition. Excavation boundary is

indicated.

WEEK 2

Activity 1: Mobilization and Hoarding

Duration: 2-5 days

Materials: -

Page 3: Building Construction process

Equipment: Machineries, Hoarders

Skilled Workers: General workers (4)

Technical Information: The site office and construction machineries and equipment are transported

to the site.

Activity 2: Site Clearing

Duration: 14 days

Materials: -

Equipment: Backhoe loader, Excavator, Bulldozer operator (1), Chainsaws, Tipper truck,

Skilled Workers: Backhoe Loader Operator (1), Excavator operator(1), Bulldozer operator (1),

General workers (4), Truck driver (1)

Technical Information: Specific trees are removed and 300mm of top soil is excavated. The soil is

kept away or stored well for reuse due to its high water retentive characteristic.

WEEK 3

Activity 1: Site Clearing

Duration: 14 days

Materials: -

Equipment: Backhoe loader, Excavator, Bulldozer operator (1), Chainsaws, Tipper truck,

Skilled Workers: Backhoe Loader Operator (1), Excavator operator(1), Bulldozer operator (1),

General workers (4), Truck driver (1)

Technical Information: Specific trees are removed and 300mm of top soil is excavated. The soil is

kept away or stored well for reuse due to its high water retentive characteristic.

Page 4: Building Construction process

WEEK 4

Activity 1: Earthwork

Duration: 3-5 days

Materials: -

Equipment: Excavator, Compactor, Tipper truck

Skilled Workers: Excavator operator (1), Compactor operator (1), Truck driver (1)

technical information: The uneven land area is either compacted or filled with earth excavated from

site or transferred in to level the ground.

Activity 2: Setting Out

Duration: 3 days

Materials: Nails, Wooden pegs, Profile boards, Stakes, Builder’s line

Equipment: Hammer, Measuring tape, Theodolite, Dumpy level

Skilled Workers: Site Contractor (1), Site Engineer (1)

Page 5: Building Construction process

Technical Information: Measurements are taken and the boundary lines of the building are marked

clearly.

WEEK 5

Activity 1: Piling (Grid 5-6)

Duration: 10-14 days

Materials: Pre-Cast reinforced concrete piles

Equipment: Hydraulic piling hammer, Pile integrity tester

Skilled Workers: Hydraulic Piling Hammer Operator (1), General workers (6)

Technical Information: The first half of the piles are driven down The Pile integrity test (Load test) is

carried out to ensure the strength meet the requirement.

Page 6: Building Construction process

WEEK 6

Activity 1: Piling (Grid 1-4)

Duration: 10-14 days

Materials: Pre-Cast reinforced concrete piles

Equipment: Hydraulic piling hammer, Pile integrity tester

Skilled Workers: Hydraulic Piling Hammer Operator (1), General workers (6)

Technical Information: The second half of the piles are driven down The Pile integrity test (Load test)

is carried out to ensure the strength meet the requirement.

Activity 2: Pile capping (Grid 5-6)

Duration: 10-14 days

Materials: Concrete Grade 30, Steel Rebar reinforcement, Timber formwork

Equipment: Rebar bending machine (1), Cement mixer (1),

Skilled Workers: Rebar benders (2), General workers (6)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 7: Building Construction process

WEEK 7

Activity 1: Pile capping (Grid 1-4)

Duration: 10-14 days

Materials: Concrete Grade 30, Steel Rebar reinforcement, Timber formwork

Equipment: Rebar bending machine (1), Cement mixer (1),

Skilled Workers: Rebar benders (2), General workers (6)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: Stump on pile cap (Grid 5-6 )

Duration: 7–14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formwork

Equipment: Concrete Vibrator (1), Rebar bending machine(1), Carpentry equipment, Theodolite

Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4), Land surveyor (1)

Technical Information: The height of the stump is adjusted to keep the floor levelled. Steel rebar are

bended to form a cage and put into position with starter bar protruding outwards. Concrete is

poured into the erected formwork and is left to cure.

Page 8: Building Construction process

WEEK 8

Activity 1: Stump on pile cap (Grid 1-4 )

Duration: 7–14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formwork

Equipment: Concrete Vibrator (1), Rebar bending machine (1), Carpentry equipment, Theodolite

Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4), Land surveyor (1)

Technical Information: The height of the stump is adjusted to keep the floor levelled. Steel rebar are

bended to form a cage and put into position with starter bar protruding outwards. Concrete is

poured into the erected formwork and is left to cure.

Activity 2: Ground beam (Grid 5-6 )

Duration: 7–14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General workers (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 9: Building Construction process

WEEK 9

Activity 1: Ground beam (Grid 1-4 )

Duration: 7–14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General workers (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: Ground floor slab (Grid 4-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Damp Proof

Membrane (DPM), Screed

Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry

equipment

Skilled Workers: Carpenters (2), Rebar Bender (1), General workers (4)

Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure. Next, a layer

of DPM is applied on the top of the concrete and was covered with a layer of screed to level the slab.

Page 10: Building Construction process

WEEK 10

Activity 1: Ground floor slab (Grid 1-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks, Damp Proof

Membrane (DPM), Screed

Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry

equipment

Skilled Workers: Carpenters (2), Rebar Bender (1), General workers (4)

Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure. Next, a layer

of DPM is applied on the top of the concrete and was covered with a layer of screed to level the slab.

Activity 2: Ground floor columns (Grid 4-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry

equipment

Skilled worker: Carpenter (2) , Rebar bender (2), General worker (4)

Technical information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 11: Building Construction process

WEEK 11

Activity 1: Ground floor columns (Grid 1-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry

equipment

Skilled worker: Carpenter (2) , Rebar bender (2), General worker (4)

Technical information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: First floor beam (4-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 12: Building Construction process

WEEK 13

Activity 1: First floor beam (1-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: First floor slab (Grid 4-6 )

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry

equipment

Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 13: Building Construction process

WEEK 13

Activity 1: First floor slab (Grid 1-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry

equipment

Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: First floor columns (Grid 4-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry

equipment

Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)

Technical information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 14: Building Construction process

WEEK 14

Activity 1: First floor columns (Grid 1-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry

equipment

Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)

Technical information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: Second floor beam (Grid 4-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 15: Building Construction process

WEEK 15

Activity 1: Second floor beam (Grid 1-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: Second floor slab (Grid 4-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry

equipment

Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 16: Building Construction process

WEEK 16

Activity 1: Second floor slab (Grid 2-4)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Vibrator(1), Rebar bending machine(1), Concrete mixer(1), Carpentry

equipment

Skilled Workers: Carpenter(2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar are bended to form a mesh and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure

WEEK 17

Activity 1: Second floor columns (Grid 2-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry

equipment

Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)

Technical information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 17: Building Construction process

WEEK 17

Activity 1: Second floor columns (Grid 2-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks

Equipment: Concrete Mixer(1), Concrete vibrator (1) , Rebar bending machine(1), Carpentry

equipment

Skilled worker: Carpenter (2) , Bar bender (2), General worker (4)

Technical information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

WEEK 18

Activity 1: Third floor beam (Grid 2-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Page 18: Building Construction process

WEEK 19

Activity 1: Third floor beam (Grid 2-6)

Duration: 14 days

Materials: Concrete Grade 30, Steel rebar reinforcement, Timber formworks,

Equipment: Concrete mixer (1), Concrete Vibrator(1), Rebar bending machine(1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (3)

Technical Information: Steel rebar are bended to form a cage and put into position with starter bar

protruding outwards. Concrete is poured into the erected formwork and is left to cure.

Activity 2: Ground floor staircase

Duration: 14 days

Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod

Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the

starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A

concrete test is carried out to ensure the strength meet the requirements after it was left to cure for

7 days.

Page 19: Building Construction process

WEEK 20

Activity 1: Ground floor staircase

Duration: 14 days

Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod

Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the

starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A

concrete test is carried out to ensure the strength meet the requirements after it was left to cure for

7 days.

Activity 2: First floor staircase

Duration: 14 days

Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod

Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the

starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A

concrete test is carried out to ensure the strength meet the requirements after it was left to cure for

7 days.

Page 20: Building Construction process

WEEK 21

Activity 1: First floor staircase

Duration: 14 days

Materials: Concrete Grade 35, Steel rebar reinforcement, Timber formworks, Adjustable steel rod

Equipment: Concrete mixer (1), Concrete Vibrator (1), Rebar bending machine (1), Carpentry

equipment

Skilled Workers: Carpenter (2), Rebar Bender (1), General worker (4)

Technical Information: Steel rebar is bended forming a mesh and put into position and tied with the

starter bar. Pre-mixed grade 35 concrete is ordered and poured into the formwork in one time. A

concrete test is carried out to ensure the strength meet the requirements after it was left to cure for

7 days.

WEEK 22

Activity 1: Roof truss assembling

Duration: 7-14 days

Materials: Aluminum roof truss components, Bolts and Nuts

Equipment: Steel Cutter (2), Welding machine (1)

Skilled Workers: General worker (2), Welding worker (2)

Technical information: After detailed calculation, the aluminum truss is ordered and is cut into

selected dimension and welded together at selected point.

Page 21: Building Construction process

WEEK 23

Activity 1: Roof truss assembling (continue)

Duration: 7-14 days

Materials: Aluminum roof truss components, Bolts and Nuts

Equipment: Steel Cutter (2), Welding machine (1)

Skilled Workers: General worker (2), Welding worker (2)

Technical information: After detailed calculation, the aluminum truss is ordered and is cut into

selected dimension and welded together at selected point.

Activity 2: Ground floor wall

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Page 22: Building Construction process

WEEK 24

Activity 1: Ground floor wall (cont)

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

WEEK 25

Activity 1: Ground floor wall (cont)

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Activity 2: First floor wall

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Page 23: Building Construction process

WEEK 26

Activity 1: First floor wall (cont)

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

WEEK 27

Activity 1: First floor wall (cont)

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Activity 1: Ground floor plastering

Duration: 14 -21 days

Material: Cementitious plaster

Equipment: Scaffolding, Plaster spray (1)

Skilled Worker: General worker (1), Plasterer (2)

Page 24: Building Construction process

Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain

from penetrating the walls. Smooth surface plastering shows up defect more easily than rough

surface hence, it is used indoor. Plaster is left to dry for a week.

WEEK 28

Activity 1: Second floor wall

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Activity 2: Ground floor plastering (cont)

Duration: 14 -21 days

Material: Cementitious plaster

Equipment: Scaffolding, Plaster spray (1)

Skilled Worker: General worker (1), Plasterer (2)

Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain

from penetrating the walls. Smooth surface plastering shows up defect more easily than rough

surface hence, it is used indoor. Plaster is left to dry for a week.

Page 25: Building Construction process

WEEk 29

Activity 1: Second floor wall (cont)

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Activity 2: First floor plastering

Duration: 14 -21 days

Material: Cementitious plaster

Equipment: Scaffolding, Plaster spray (1)

Skilled Worker: General worker (1), Plasterer (2)

Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain

from penetrating the walls. Smooth surface plastering shows up defect more easily than rough

surface hence, it is used indoor. Plaster is left to dry for a week.

WEEk 30

Activity 1: Second floor wall (cont)

Duration: 14-21 days

Materials: Clay Bricks, Cement mortar, Builder’s line, Wire mesh reinforcement

Equipment: Wheel barrow (2), Shovel (2), Groovers (5), Edges (5)

Skilled Workers: General Workers (6)

Page 26: Building Construction process

Technical Information: Clay bricks with dimension 100mmx 215mmx 75mm is applied with a layer of

mortar and stack together in desired bonding. A layer of wire mesh is laid on top of the bricks in

certain layer interval as reinforcement.

Activity 2: First floor plastering (cont)

Duration: 14 -21 days

Material: Cementitious plaster

Equipment: Scaffolding, Plaster spray (1)

Skilled Worker: General worker (1), Plasterer (2)

Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain

from penetrating the walls. Smooth surface plastering shows up defect more easily than rough

surface hence, it is used indoor. Plaster is left to dry for a week.

WEEk 31

Activity 1: Roof installation (1st Floor)

Duration: 7- 14 days

Materials: Concrete, EDPM rubber, insulation, vapour control layer, timber formwork

Equipment: Mobile Crane

Skilled Workers: General worker (4), Mobile crane operator (1)

Technical information: The roof is inclined for the rain water to flow off the roof. Vapour control

layers are normally considered essential under insulation in warm roof constructions to reduce the

risk of condensation. Thermal insulation reduces heat from going into the building. EPDM rubber act

as a waterproofing membrane.

Activity 2: Second floor plastering

Duration: 14 -21 days

Material: Cementitious plaster

Equipment: Scaffolding, Plaster spray (1)

Page 27: Building Construction process

Skilled Worker: General worker (1), Plasterer (2)

Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain

from penetrating the walls. Smooth surface plastering shows up defect more easily than rough

surface hence, it is used indoor. Plaster is left to dry for a week.

Activity 3: Ground Floor Tiling

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

WEEk 32

Activity 1: Second floor plastering (cont)

Duration: 14 -21 days

Material: Cementitious plaster

Equipment: Scaffolding, Plaster spray (1)

Skilled Worker: General worker (1), Plasterer (2)

Technical Information: Rough surface plastering is usually used outdoor because it prevents the rain

from penetrating the walls. Smooth surface plastering shows up defect more easily than rough

surface hence, it is used indoor. Plaster is left to dry for a week.

Activity 2: Ground Floor Tiling (cont)

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

WEEK 33

Activity 1: Ground Floor Tiling (cont)

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Page 28: Building Construction process

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Activity 2: First floor tiling

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Activity 1: Roof installation (2nd Floor)

Duration: 7- 14 days

Materials: Concrete, EDPM rubber, insulation, vapour control layer, timber formwork

Equipment: Mobile Crane

Skilled Workers: General worker (4), Mobile crane operator (1)

Technical information: The roof is inclined for the rain water to flow off the roof. Vapour control

layers are normally considered essential under insulation in warm roof constructions to reduce the

risk of condensation. Thermal insulation reduces heat from going into the building. EPDM rubber act

as a waterproofing membrane.

Page 29: Building Construction process

WEEK 34

Activity 1: First floor tiling (cont)

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Activity 2: Ground floor Painting – undercoat

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

Page 30: Building Construction process

WEEK 35

Activity 2: First floor tiling (cont)

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Activity 3: Ground floor Painting – undercoat (cont)

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

WEEK 36

Activity 1: Second floor tiling

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Activity 2: Ground floor Painting – undercoat (cont)

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

Page 31: Building Construction process

WEEK 37

Activity 1: Second floor tiling (cont)

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Activity 2: First floor Painting – undercoat

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

WEEK 38

Activity 1: Second floor tiling (cont)

Duration: 14-21 days

Materials: Ceramic tiles, Cement mortar, Silicone sealant

Equipment: Spirit level (1), Groovers (3), Tile cutter (1), Carpenter’s square (1)

Skilled Worker: General worker (2)

Technical Information: The dimensions of the place is taken and calculated and tiles are cut into

suitable shapes before placing.

Page 32: Building Construction process

Activity 2: First floor Painting – undercoat (cont)

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

WEEK 39

Activity 1: First floor Painting – undercoat (cont)

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

Activity 2: Ground floor Painting – First coat

Duration: 14 days

Materials: First coat

Equipment: Paint brush (3), Point roller (3), Scaffolding

Skilled Worker: Painter (5)

Technical Information: Painting for finishing should be done after the plastering and undercoating

are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few

layers for better surface finishes.

WEEK 40

Activity 2: Ground floor Painting – First coat (cont)

Duration: 14 days

Materials: First coat

Equipment: Paint brush (3), Point roller (3), Scaffolding

Skilled Worker: Painter (5)

Technical Information: Painting for finishing should be done after the plastering and undercoating

are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few

layers for better surface finishes.

Page 33: Building Construction process

Activity 1: Second floor Painting – undercoat

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

WEEK 41

Activity 1: Second floor Painting – undercoat (cont)

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

Activity 2: First floor Painting – First coat

Duration: 14 days

Materials: First coat

Equipment: Paint brush (3), Point roller (3), Scaffolding

Skilled Worker: Painter (5)

Page 34: Building Construction process

Technical Information: Painting for finishing should be done after the plastering and undercoating

are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few

layers for better surface finishes.

WEEK 42

Activity 1: Second floor Painting – undercoat (cont)

Duration: 21 days

Materials: Wall Sealer

Equipment: Paint brush (3), Point roller (3)

Skilled Worker: Painter (5)

Technical Information: Sealer is used to seal the holes, hairline cracks of the walls to prevent

absorption of moisture and paint. By applying a layer of sealer, it gives the wall an adhesive base for

the paint to stick on firmly without having bubbling and waterborne stain.

Activity 2: First floor Painting – First coat (cont)

Duration: 14 days

Materials: First coat

Equipment: Paint brush (3), Point roller (3), Scaffolding

Skilled Worker: Painter (5)

Technical Information: Painting for finishing should be done after the plastering and undercoating

are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few

layers for better surface finishes.

Page 35: Building Construction process

WEEK 43

Activity 1: Second floor Painting – First coat

Duration: 14 days

Materials: First coat

Equipment: Paint brush (3), Point roller (3), Scaffolding

Skilled Worker: Painter (5)

Technical Information: Painting for finishing should be done after the plastering and undercoating

are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few

layers for better surface finishes.

WEEK 44

Activity 1: Second floor Painting – First coat

Duration: 14 days

Materials: First coat

Equipment: Paint brush (3), Point roller (3), Scaffolding

Skilled Worker: Painter (5)

Technical Information: Painting for finishing should be done after the plastering and undercoating

are completely dried up to prevent bubbling of the wall due to the moisture. Painting requires few

layers for better surface finishes.

Activity 2: Ground floor openings

Durations: 7 days

Materials: Door & window frame

Equipment: Spirit level, Measuring tape

Skilled Workers: General Workers (4)

Technical Information: The door frame is placed in position and aligned after the brick wall is done.

Architrave is added after the door/window frame is added.

Page 36: Building Construction process

WEEK 45

Activity 1: Ground floor Railings, Doors and Windows installation

Durations: 7 days

Materials: Variety of doors and windows, railings

Equipment: Bolts and Nuts, Screwdriver and related toolkit.

Skilled worker: General workers (4)

Technical information: The doors and windows are mounted to ensure the house is lockable before

the fittings is installed

Activity 2: First floor openings

Durations: 7 days

Materials: Door & window frame

Equipment: Spirit level, Measuring tape

Skilled Workers: General Workers (4)

Technical Information: The door frame is placed in position and aligned after the brick wall is done.

Architrave is added after the door/window frame is added.

Page 37: Building Construction process

WEEK 46

Activity 1: First floor Railings, Doors and Windows installation

Durations: 7 days

Materials: Variety of doors and windows, railings

Equipment: Bolts and Nuts, Screwdriver and related toolkit.

Skilled worker: General workers (4)

Technical information: The doors and windows are mounted to ensure the house is lockable before

the fittings is installed

Activity 2: Second floor openings

Durations: 7 days

Materials: Door & window frame

Equipment: Spirit level, Measuring tape

Skilled Workers: General Workers (4)

Technical Information: The door frame is placed in position and aligned after the brick wall is done.

Architrave is added after the door/window frame is added.

Page 38: Building Construction process

WEEK 47

Activity 1: Second floor Doors and Windows installation

Durations: 7 days

Materials: Variety of doors and windows, railings

Equipment: Bolts and Nuts, Screwdriver and related toolkit.

Skilled worker: General workers (4)

Technical information: The doors and windows are mounted to ensure the house is lockable before

the fittings is installed.

WEEK 48

Activity 1: Electrical Supply

Duration: 14 days

Materials: Copper Cables (different sizes), Kilowatt hour meter

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts,

Skilled Workers: Electric Technician (2), Plumbers (2)

Technical Information: Incoming electricity cables are brought into the house and connected to a

circuit box in the house to facilitate the electricity works later on.

Activity 2: Water Supply

Duration: 14 days

Materials: PVC pipes (different sizes), Water flow meter

Equipment: Spanner, Plyers, Pipe cutter

Skilled Workers: Plumbers (2)

Technical Information: Incoming water supply are brought into the house and connected to the

water flow meter to facilitate the plumbing works later on.

Page 39: Building Construction process

WEEK 49

Activity 1: Electrical Supply

Duration: 14 days

Materials: Copper Cables (different sizes), Kilowatt hour meter

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts,

Skilled Workers: Electric Technician (2), Plumbers (2)

Technical Information: Incoming electricity cables are brought into the house and connected to a

circuit box in the house to facilitate the electricity works later on.

Activity 2: Water Supply

Duration: 14 days

Materials: PVC pipes (different sizes), Water flow meter

Equipment: Spanner, Plyers, Pipe cutter

Skilled Workers: Plumbers (2)

Technical Information: Incoming water supply are brought into the house and connected to the

water flow meter to facilitate the plumbing works later on.

Activity 3: Ground Floor Electrical Plumbing (First - Fix)

Duration: 14 days

Materials: Copper Cables (different sizes), PVC pipes, socket box

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine

Skilled Workers: Electrician Plumbers (2)

Technical Information: The brick wall is hacked to hide the wiring pipe which runs perpendicularly

from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.

Page 40: Building Construction process

WEEK 50

Activity 1: Ground Floor Electrical Plumbing (First - Fix)

Duration: 14 days

Materials: Copper Cables (different sizes), PVC pipes, socket box

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine

Skilled Workers: Electrician Plumbers (2)

Technical Information: The brick wall is hacked to hide the wiring pipe which runs perpendicularly

from the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.

Activity 2: First Floor Electrical Plumbing (First - Fix)

Duration: 14 days

Materials: Copper Cables (different sizes), PVC pipes, socket box

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine

Skilled Workers: Electrician Plumbers (2)

Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from

the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.

Activity 3: Second Floor Electrical Plumbing (First - Fix)

Duration: 14 days

Materials: Copper Cables (different sizes), PVC pipes, Socket box, Junction box

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine

Skilled Workers: Electrician Plumbers (2)

Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from

the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.

Activity 4: Plumbing – Kitchens and Toilets

Duration: 14 days

Materials: PVC pipes (different sizes), Pipe joints,

Equipment: Spanner, Plyers, Pipe cutter

Skilled Workers: Plumbers (2)

Page 41: Building Construction process

WEEK 51

Activity 1: First Floor Electrical Plumbing (First - Fix)

Duration: 14 days

Materials: Copper Cables (different sizes), PVC pipes, socket box

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine

Skilled Workers: Electrician Plumbers (2)

Technical Information: Brick wall is hacked to hide the wiring pipe which runs perpendicularly from

the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.

Activity 2: Second Floor Electrical Plumbing (First - Fix)

Duration: 14 days

Materials: Copper Cables (different sizes), PVC pipes, Socket box, Junction box

Equipment: Voltmeter, Ammeter, Plyers, Screws and nuts, Hacking machine

Skilled Workers: Electrician Plumbers (2)

Technical Information:Brick wall is hacked to hide the wiring pipe which runs perpendicularly from

the top to the floor according UBBL requirements. The wall socket is fix after the wiring is done.

Activity 3: Plumbing – Kitchens and Toilets

Duration: 14 days

Materials: PVC pipes (different sizes), Pipe joints,

Equipment: Spanner, Plyers, Pipe cutter

Skilled Workers: Plumbers (2)

WEEK 52

Page 42: Building Construction process

Activity 1: Electrical & Sanitary fittings

Durations: 14 days

Materials: Wall sockets, Wall plugs and bathroom porcelain appliances

Equipment: Bolts and Nuts, Screwdriver and related toolkit.

Skilled worker: General worker (4)

WEEK 53

Activity 1: Grass turfing – External work

Duration: 7 days Materials: lawn turf rolls ( depends on the size of garden), bricks

Equipment: wheel barrow, gardening tool kits, water pipes

Skilled Workers: lawn turf layers(2), general workers (2)

Technical information: Soil preparation is done before laying the rolls of grass turf on the soil

surfaces. Previously excavated soil can be reused as the base of the courtyard. Loose stones and

building rubble will prevent the turves roots from making contact with the soil and could make the

turf die in patches. The top soil should then be thoroughly rotivated down to about the first 6 inches

to aerate it properly. It is then raked level and gently treaded down.

- END OF REPORT -