budget based on villa type b

Upload: muhammadiqbalmughal

Post on 25-Feb-2018

215 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/25/2019 Budget Based on Villa Type b

    1/26

    COST BUDGETCONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)

    BAHRIA TOWN GARDEN CITY

    BUILT-UP FLOOR AREA = 5916 SFT

    S.NO DESCRIPTION UNIT QUANTITY

    LABOR (A) MACHINERY (B) MATERIAL (C)

    RATE (Rs) AMOUNT (Rs) %

    TOTAL COST UNIT COST TOTAL COST

    CONCRETE FRAME STRUCTURE WORKS

    1) EXCAVATION WORKS

    1.1

    Cft 13,228.00 0.85 11,243.80 0.07 925.96 12,169.76 0.95 12,566.60 - - 1.87 24,736.36 0.52%

    1.2

    Cft 12,338.00 1.15 14,188.70 0.09 1,110.42 15,299.12 2.80 34,546.40 - - 4.04 49,845.52 1.05%

    COST OF EXCAVATION WORKS RS 25,432.50 2,036.38 27,468.88 47,113.00 - 74,581.88 1.58%

    COST PER SFTRS 4.30 0.34 4.64 7.96 - 12.61

    2) CONCRETE WORKS

    2.1a

    Cft 866.29 10.62 9,200.00 0.85 736.35 9,936.35 3.75 3,248.59 64.50 55,875.71 79.72 69,060.64 1.46%

    2.1b

    Cft 644.63 10.62 6,845.97 0.85 547.94 7,393.91 3.75 2,417.36 64.50 41,578.64 79.72 51,389.90 1.09%

    2.2

    2.2.1 Raft and Column Footing ( 3,000 PSI ) Cft 2,703.76 8.85 23,928.28 0.90 2,433.38 26,361.66 7.10 19,196.70 104.76 283,245.90 121.61 328,804.25 6.95%

    2.2.2 Retaining Wall ( 3,000 PSI ) Cft - 8.85 - 0.90 - - 7.10 - - - 16.85 - -

    2.2.3 Columns ( 3,750 PSI ) Cft 574.00 8.85 5,079.90 0.90 516.60 5,596.50 7.10 4,075.40 113.84 65,344.16 130.69 75,016.06 1.59%

    2.2.4 Slabs ( 3,000 PSI ) Cft 2,644.23 8.85 23,401.44 0.90 2,379.81 25,781.25 7.10 18,774.03 102.76 271,721.07 119.61 316,276.35 6.68%

    2.2.5 Lintels & Beams ( 3,000 PSI ) Cft 1,732.89 8.85 15,336.08 0.90 1,559.60 16,895.68 7.10 12,303.52 102.76 178,071.78 119.61 207,270.97 4.38%

    7,654.88

    COST OF CONCRETE WORKS RS 83,791.67 8,173.68 91,965.35 60,015.60 895,837.26 1,047,818.17 22.14%

    COST PER SFT RS 14.16 1.38 15.55 10.14 151.43 177.12

    3) STEEL

    3.1 Column Footing Kg 6,099.68 3.10 18,909.01 0.20 1,219.94 20,128.95 0.40 2,439.87 55.00 335,482.40 58.70 358,051.22 7.57%

    3.2 Retaining Wall Kg - - - - - - - - - - - - -

    3.3 Kg 3,133.86 3.10 9,714.97 0.20 626.77 10,341.74 0.40 1,253.54 55.00 172,362.30 58.70 183,957.58 3.89%

    3.4 Slabs Kg - - - - - - - - - - - - -

    3.5 Slab, Lintels & Beams Kg 14,785.91 3.10 45,836.32 0.20 2,957.18 48,793.50 0.40 5,914.36 55.00 813,225.05 58.70 867,932.92 18.34%

    24,019.45

    KG/M3 110.76

    COST OF REINFORCEMENT WORKS RS 74,460.30 4,803.89 79,264.19 9,607.77 1,321,069.75 1,409,941.72 29.79%

    COST PER SFT RS 12.59 0.81 13.40 1.62 223.30 238.33

    4) FORMWORK

    4.1 Raft & Column Footing Sft 217.73 13.51 2,941.53 1.07 232.97 3,174.50 0.51 111.04 8.30 1,807.16 23.39 5,092.70 0.11%

    4.2 Retaining Wall Sft - - - 1.07 - - 0.51 - - - - - 0.00%

    4.3 Columns Sft 3,491.44 13.51 47,169.35 1.07 3,735.84 50,905.19 0.51 1,780.63 24.00 83,794.56 39.09 136,480.39 2.88%4.4 Slabs Sft 5,979.61 13.51 80,784.53 1.07 6,398.18 87,182.71 0.51 3,049.60 24.00 143,510.64 39.09 233,742.95 4.94%

    4.5 Lintels & Beams Sft 6,849.44 13.51 92,535.93 1.07 7,328.90 99,864.83 0.51 3,493.21 14.20 97,262.05 29.29 200,620.10 4.24%

    16,538.22

    M2/M3 7.09 135.00

    COST OF FORMWORK RS 223,431.34 17,695.89 241,127.23 8,434.48 326,374.41 575,936.14 12.17%

    COST PER SFT RS 37.77 2.99 40.76 1.43 55.17 97.35

    7)

    Sft 5,372.79 0.75 4,029.59 0.06 322.37 4,351.96 - - 2.66 14,291.62 3.47 18,643.58 0.39%

    ANTI-TERMITE WORKS RS 4,029.59 322.37 4,351.96 - 14,291.62 18,643.58 0.39%

    COST PER SFT RS 0.68 0.05 0.74 - 2.42 3.15

    6)Water Proofing as specified Sft 1,894.94 14.00 26,529.16 1.12 2,122.33 28,651.49 - - 56.00 106,116.64 71.12 134,768.13 2.85%

    WATERPROOFING WORKS RS 26,529.16 2,122.33 28,651.49 - 106,116.64 134,768.13 2.85%

    COST PER SFT RS 4.48 0.36 4.84 - 17.94 22.78

    11) OTHER WORKS

    11.01 Overhead water tank concrete Cft 147.39 8.85 1,304.40 0.90 132.65 1,437.05 7.10 1,046.47 104.76 15,440.58 121.61 17,924.10 0.38%

    11.02 Overhead water tank reinforcement Kg 558.66 3.10 1,731.85 0.20 111.73 1,843.58 0.30 167.60 56.00 31,284.96 59.60 33,296.14 0.70%

    11.03 Overhead water tank formwork Sft 450.00 13.51 6,079.50 1.07 481.50 6,561.00 0.51 229.50 8.30 3,735.00 23.39 10,525.50 0.22%

    11.04 PVC waterstop for OHWT Rft 20.00 25.00 500.00 0.18 3.60 503.60 - - 165.00 3,300.00 190.18 3,803.60 0.08%

    11.05 Manhole cover and insulation for OHWT Set 1.00 200.00 200.00 5.77 5.77 205.77 - - 2,500.00 2,500.00 2,705.77 2,705.77 0.06%

    11.06 Underground watertank concrete Cft 96.05 8.85 850.04 0.90 86.45 936.49 7.10 681.96 104.76 10,062.20 121.61 11,680.64 0.25%

    DIRECT UNIT

    COST

    DIRECT TOTAL

    COST

    INDIRECT

    UNIT COST

    INDIRECT

    TOTAL COST

    DIRECT &

    INDIRECT TOTAL

    COST

    UNIT

    COST

    Excavation in hard soil upto 1.5 m depth to obtain earth for

    embankments or to clear building sites etc.

    Earth Filling in area where required in 150 mm layers, borrow from

    other site and fill according to requirement and as directed by the

    engineer incharge.

    Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken

    stone graded in foundation as specified.

    Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken

    stone graded in foundation as specified.

    Providing and Placing reinforced cement concrete in different Grades

    using crushed or broken stone graded as specified in specificatins.

    Cutting, Bending & Fixing of Steel as per drawing as directed by

    engineer incharge.

    Columns @ 5.454 KG/CFT

    Providing, Fixing & Removal of formwork with good quality & smooth

    surface of concrete after removal, complete in all respect or as

    directed by the engineer incharge.

    Termite Proofing in area where required with approved material from

    main contractor, according to requirement and as directed by the

    engineer incharge.

    mailto:Columns@%205.454%20KG/CFTmailto:Columns@%205.454%20KG/CFT
  • 7/25/2019 Budget Based on Villa Type b

    2/26

    11.07 Underground watertank reinforcement Kg 325.00 3.10 1,007.50 0.20 65.00 1,072.50 0.30 97.50 56.00 18,200.00 59.60 19,370.00 0.41%

    11.08 Underground watertank formwork Sft 432.00 13.51 5,836.32 1.07 462.24 6,298.56 0.51 220.32 8.30 3,585.60 23.39 10,104.48 0.21%

    11.09 PVC waterstop for UGWT Rft 28.00 25.00 700.00 0.18 5.04 705.04 - - 165.00 4,620.00 190.18 5,325.04 0.11%

    11.10Waterproofing for UGWT wall (with Bitumen) Sft 140.00 28.00 3,920.00 2.04 285.60 4,205.60 0.17 23.80 5.33 746.20 35.54 4,975.60 0.11%

    11.11 Gully trap (2 Nos) & Manhole (1 No) Cft 73.50 15.00 1,102.50 1.20 88.20 1,190.70 0.17 12.50 85.00 6,247.50 101.37 7,450.70 0.16%

    11.14 Boundary wall RCC Cft 210.00 8.85 1,858.50 0.90 189.00 2,047.50 7.10 1,491.00 104.76 21,999.60 121.61 25,538.10 0.54%

    11.15 Boundary wall Lean Concrete Cft 92.00 8.85 814.20 0.90 82.80 897.00 7.10 653.20 104.76 9,637.92 121.61 11,188.12 0.24%

    11.17 PCC (1:4:8) for walkway Cft 184.92 10.62 1,963.85 0.85 157.18 2,121.03 3.95 730.43 64.50 11,927.34 79.92 14,778.81 0.31%

    COST OF OTHER WORKS RS 27,868.66 2,156.76 30,025.42 5,354.28 143,286.90 178,666.60 3.78%

    COST PER SFT RS 4.71 0.36 5.08 0.91 24.22 30.20

    COST OF CONCRETE FRAME STRUCTURE WORKS RS 465,543.22 37,311.30 502,854.52 130,525.13 2,806,976.58 3,440,356.22 72.69%

    COST PER SFT RS 78.69 6.31 85.00 22.06 474.47 581.53

    5) BLOCK WORK

    Cft 4,053.55 13.43 54,439.18 1.07 4,337.30 58,776.48 0.20 810.71 50.33 204,015.17 65.03 263,602.36 5.57%

    8) Plaster works

    Sft 15,156.29 8.50 128,828.47 0.68 10,306.28 139,134.75 0.20 3,031.26 8.01 121,401.88 17.39 263,567.88 5.57%

    BLOCKWORKS & PLASTERING WORKS RS 183,267.65 14,643.58 197,911.23 3,841.97 325,417.05 527,170.24 11.14%

    COST PER SFT RS 30.98 2.48 33.45 0.65 55.01 89.11

    9) EMBEDDED ITEMS FOR ELECTRICAL WORKSSft 5,916.00 5.33 31,532.28 0.55 3,253.80 34,786.08 0.30 1,774.80 63.53 375,843.48 69.71 412,404.36 8.71%

    10) EMBEDDED ITEMS FOR PLUMBING WORKS Sft 5,916.00 5.07 29,994.12 0.53 3,135.48 33,129.60 0.27 1,597.32 44.50 263,262.00 50.37 297,988.92 6.30%

    COST OF ELECTRICAL & PLUMBING WORKS RS 61,526.40 6,389.28 67,915.68 3,372.12 639,105.48 710,393.28 15.01%

    COST PER SFT RS 41,991.77 10.40 1.08 11.48 0.57 108.03 120.08

    11) OTHER WORKS

    11.12 Plastering of Tank and Manholes Sft 383.00 8.50 3,255.50 0.68 260.44 3,515.94 0.17 65.11 8.00 3,064.00 17.35 6,645.05 0.14%

    11.13 Boundary wall brickwork Cft 420.00 13.00 5,460.00 1.04 436.80 5,896.80 0.17 71.40 8.01 3,364.20 22.22 9,332.40 0.20%

    11.16 Boundary wall Plastering Sft 2,240.00 8.50 19,040.00 0.68 1,523.20 20,563.20 0.17 380.80 8.01 17,942.40 17.36 38,886.40 0.82%

    COST OF OTHER WORKS RS 27,755.50 2,220.44 29,975.94 517.31 24,370.60 54,863.85 1.16%

    COST PER SFT RS 4.69 0.38 5.07 0.09 4.12 9.27

    OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKSRS 272,549.55 23,253.30 295,802.85 7,731.40 988,893.13 1,292,427.37 27.31%

    COST PER SFT RS 46.07 3.93 50.00 1.31 167.16 218.46

    COST OF CONCRETE FRAME STRUCTURE WORKS (A) : 465,543.22 37,311.30 502,854.52 130,525.13 2,806,976.58 3,440,356.22 72.69%

    COST PER SFT 78.69 6.31 85.00 22.06 474.47 581.53

    OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS (B) : 272,549.55 23,253.30 295,802.85 7,731.40 988,893.13 1,292,427.37 27.31%

    COST PER SFT 46.07 3.93 50.00 1.31 167.16 218.46

    Covered Area (Sft) 5,916.00 5,916.00 5,916.00 5,916.00 5,916.00 5,916

    TOTAL COST (A+B) : 738,093 60,565 798,657 138,257 3,795,870 4,732,784 100.00%

    COST PER SFT 124.76 10.24 135.00 23.37 641.63 800.00

    ADD: CONTINGENCIES FOR ANY OTHER COST - - - - - - 0.00%

    TOTAL BUDGETED COST PER SFT: 124.76 10.24 135.00 23.37 641.63 800.00 800.00

    % OF BUDGETED COST : 15.60% 1.28% 16.88% 2.92% 80.20% 100.00%

    DIRECT LABOUR TOTAL LABOUR MACHINERY MATERIAL TOTAL AMOUNT

    (A) (B) (A+B) (C) (D) (A+B+C+D)

    TOTAL CONTRACT COST : 73,808,016 6,057,984 79,866,000 13,825,692 379,588,308 473,280,000

    TOTAL BUDGETED COST : 57,272,796 6,057,984 63,330,780 12,595,164 379,588,308 455,514,252

    POSSIBLE COST SAVING : 16,535,220 - 16,535,220 1,230,528 - 17,765,748

    OTHER ASSOCIATED WORK FOR GREY

    STRUCTURE

    Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand

    Mortar (1:4) In Super Structure , including form work, curing etc

    complete in all respect or as directed by the engineer incharge.

    Applying 13mm thick cement and sand plaster (1:4) to be trowelled

    smooth with steel trowel to brick or block wall,as Directed by the

    engineer incharge.

    INDIRECTLABOUR

  • 7/25/2019 Budget Based on Villa Type b

    3/26

    COST BUDGETCONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)

    BAHRIA TOWN GARDEN CITY

    BUILT-UP FLOOR AREA = 5916 SFT

    S.NO DESCRIPTION UNIT QUANTITY LABOR (A) MACHINERY (B) MATERIAL (C) RATE (Rs) AMOUNT (Rs)

    %

    TOTAL COST UNIT COST TOTAL COST

    CONCRETE FRAME STRUCTURE WORKS

    1) EXCAVATION WORKS

    1.1

    Cft 13,228.00 0.85 11,243.80 0.07 925.96 12,169.76 0.95 12,566.60 - - 1.87 24,736.36 0.52%

    1.2

    Cft 12,338.00 1.15 14,188.70 0.09 1,110.42 15,299.12 2.80 34,546.40 - - 4.04 49,845.52 1.05%

    COST OF EXCAVATION WORKS RS 25,432.50 2,036.38 27,468.88 47,113.00 - 74,581.88 1.58%

    COST PER SFT RS 4.30 0.34 4.64 7.96 - 12.61

    2) CONCRETE WORKS

    2.1a

    Cft 866.29 10.62 9,200.00 0.85 736.35 9,936.35 3.75 3,248.59 64.50 55,875.71 79.72 69,060.64 1.46%

    2.1b

    Cft 644.63 10.62 6,845.97 0.85 547.94 7,393.91 3.75 2,417.36 64.50 41,578.64 79.72 51,389.90 1.09%

    2.2

    2.2.1 Raft and Column Footing ( 3,000 PSI ) Cft 2,703.76 8.85 23,928.28 0.71 1,919.67 25,847.95 7.08 19,142.62 104.76 283,245.90 121.40 328,236.46 6.94%

    2.2.2 Retaining Wall ( 3,000 PSI ) Cft - - - - - - - - - - - - -

    2.2.3 Columns ( 3,750 PSI ) Cft 574.00 8.85 5,079.90 0.71 407.54 5,487.44 7.08 4,063.92 113.84 65,344.16 130.48 74,895.52 1.58%

    2.2.4 Slabs ( 3,000 PSI ) Cft 2,644.23 8.85 23,401.44 0.71 1,877.40 25,278.84 7.08 18,721.15 102.76 271,721.07 119.40 315,721.06 6.67%

    2.2.5 Lintels & Beams ( 3,000 PSI ) Cft 1,732.89 8.85 15,336.08 0.71 1,230.35 16,566.43 7.08 12,268.86 102.76 178,071.78 119.40 206,907.07 4.37%

    7,654.88

    COST OF CONCRETE WORKS RS 83,791.67 6,719.25 90,510.92 59,862.50 895,837.26 1,046,210.65 22.11%

    COST PER SFT RS 14.16 1.14 15.30 10.12 151.43 176.84

    3) STEEL

    3.1 Column Footing Kg 6,099.68 2.56 15,615.18 0.20 1,219.94 16,835.12 0.40 2,439.87 55.00 335,482.40 58.16 354,757.39 7.50%

    3.2 Retaining Wall Kg - - - - - - - - - - - - -

    3.3 Kg 3,133.86 2.56 8,022.68 0.20 626.77 8,649.45 0.40 1,253.54 55.00 172,362.30 58.16 182,265.30 3.85%

    3.4 Slabs Kg - - - - - - - - - - - - -3.5 Slab, Lintels & Beams Kg 14,785.91 2.56 37,851.93 0.20 2,957.18 40,809.11 0.40 5,914.36 55.00 813,225.05 58.16 859,948.53 18.17%

    24,019.45

    KG/M3 110.76

    COST OF REINFORCEMENT WORKS RS 61,489.79 4,803.89 66,293.68 9,607.77 1,321,069.75 1,396,971.22 29.52%

    COST PER SFT RS 10.39 0.81 11.21 1.62 223.30 236.13

    4) FORMWORK

    4.1 Raft & Column Footing Sft 217.73 12.50 2,721.63 1.00 217.73 2,939.36 0.20 43.55 7.80 1,698.29 21.50 4,681.20 0.10%

    4.2 Retaining Wall Sft - - - - - - - - - - - - 0.00%

    4.3 Columns Sft 3,491.44 12.50 43,643.00 1.00 3,491.44 47,134.44 0.20 698.29 16.80 58,656.19 30.50 106,488.92 2.25%4.4 Slabs Sft 5,979.61 12.50 74,745.13 1.00 5,979.61 80,724.74 0.20 1,195.92 9.80 58,600.18 23.50 140,520.84 2.97%

    4.5 Lintels & Beams Sft 6,849.44 12.50 85,618.00 1.00 6,849.44 92,467.44 0.20 1,369.89 9.80 67,124.51 23.50 160,961.84 3.40%

    16,538.22 3,307.65

    M2/M3 7.09

    COST OF FORMWORK RS 206,727.76 16,538.22 223,265.98 6,615.30 186,079.17 412,652.80 8.72%

    COST PER SFT RS 34.94 2.80 37.74 1.12 31.45 69.75

    7)

    Sft 5,372.79 0.75 4,029.59 0.06 322.37 4,351.96 - - 2.66 14,291.62 3.47 18,643.58 0.39%

    ANTI-TERMITE WORKS RS 4,029.59 322.37 4,351.96 - 14,291.62 18,643.58 0.39%

    COST PER SFT RS 0.68 0.05 0.74 - 2.42 3.15

    6)Water Proofing as specified Sft 1,894.94 14.00 26,529.16 1.12 2,122.33 28,651.49 - - 56.00 106,116.64 71.12 134,768.13 2.85%

    WATERPROOFING WORKS RS 26,529.16 2,122.33 28,651.49 - 106,116.64 134,768.13 2.85%

    COST PER SFT RS 4.48 0.36 4.84 - 17.94 22.78

    11) OTHER WORKS

    11.01 Overhead water tank concrete Cft 147.39 8.85 1,304.40 0.71 104.65 1,409.05 7.08 1,043.52 104.76 15,440.58 121.40 17,893.15 0.38%

    11.02 Overhead water tank reinforcement Kg 558.66 2.56 1,430.17 0.20 111.73 1,541.90 0.30 167.60 56.00 31,284.96 59.06 32,994.46 0.70%

    11.03 Overhead water tank formwork Sft 450.00 12.50 5,625.00 1.00 450.00 6,075.00 0.17 76.50 8.80 3,960.00 22.47 10,111.50 0.21%

    11.04 PVC waterstop for OHWT Rft 20.00 2.20 44.00 0.18 3.60 47.60 - - 165.00 3,300.00 167.38 3,347.60 0.07%

    11.05 Manhole cover and insulation for OHWT Set 1.00 72.12 72.12 5.77 5.77 77.89 - - 2,500.00 2,500.00 2,577.89 2,577.89 0.05%

    11.06 Underground watertank concrete Cft 96.05 8.85 850.04 0.71 68.20 918.24 7.08 680.03 104.76 10,062.20 121.40 11,660.47 0.25%

    11.07 Underground watertank reinforcement Kg 325.00 2.56 832.00 0.20 65.00 897.00 0.30 97.50 56.00 18,200.00 59.06 19,194.50 0.41%

    11.08 Underground watertank formwork Sft 432.00 12.50 5,400.00 1.00 432.00 5,832.00 0.17 73.44 8.80 3,801.60 22.47 9,707.04 0.21%

    11.09 PVC waterstop for UGWTRft 28.00 2.20 61.60 0.18 5.04 66.64 - - 165.00 4,620.00 167.38 4,686.64 0.10%

    11.10Waterproofing for UGWT wall (with Bitumen) Sft 140.00 0.56 78.40 0.04 5.60 84.00 0.17 23.80 5.33 746.20 6.10 854.00 0.02%

    11.11 Gully trap (2 Nos) & Manhole (1 No) Cft 73.50 15.00 1,102.50 1.20 88.20 1,190.70 0.17 12.50 85.00 6,247.50 101.37 7,450.70 0.16%

    11.14 Boundary wall RCC Cft 210.00 8.85 1,858.50 0.71 149.10 2,007.60 7.08 1,486.80 104.76 21,999.60 121.40 25,494.00 0.54%

    11.15 Boundary wall Lean Concrete Cft 92.00 8.85 814.20 0.71 65.32 879.52 7.08 651.36 104.76 9,637.92 121.40 11,168.80 0.24%

    11.17 PCC (1:4:8) for walkway Cft 184.92 10.62 1,963.85 0.85 157.18 2,121.03 3.95 730.43 64.50 11,927.34 79.92 14,778.81 0.31%

    COST OF OTHER WORKS RS 21,436.78 1,711.39 23,148.17 5,043.48 143,727.90 171,919.56 3.63%

    COST PER SFT RS 3.62 0.29 3.91 0.85 24.29 29.06

    COST OF CONCRETE FRAME STRUCTURE WORKSRS 429,437.25 34,253.83 463,691.08 128,242.05 2,667,122.34 3,255,747.82 68.79%

    COST PER SFT RS 72.59 5.79 78.38 83.00 21.68 450.83 550.33

    5) BLOCK WORK

    Cft 4,053.55 13.43 54,439.18 1.07 4,337.30 58,776.48 0.20 810.71 50.33 204,015.17 65.03 263,602.36 5.57%

    8) Plaster works

    Sft 15,156.29 8.50 128,828.47 0.68 10,306.28 139,134.75 0.20 3,031.26 8.01 121,401.88 17.39 263,567.88 5.57%

    BLOCKWORKS & PLASTERING WORKS RS 183,267.65 14,643.58 197,911.23 3,841.97 325,417.05 527,170.24 11.14%

    COST PER SFT RS 30.98 2.48 33.45 0.65 55.01 89.11

    9) EMBEDDED ITEMS FOR ELECTRICAL WORKSSft 5,916.00 6.83 40,406.28 0.55 3,253.80 43,660.08 0.30 1,774.80 63.53 375,843.48 71.21 421,278.36 8.90%

    10) EMBEDDED ITEMS FOR PLUMBING WORKS Sft 5,916.00 6.57 38,868.12 0.53 3,135.48 42,003.60 0.27 1,597.32 44.50 263,262.00 51.87 306,862.92 6.48%

    COST OF ELECTRICAL & PLUMBING WORKS RS 79,274.40 6,389.28 85,663.68 3,372.12 639,105.48 728,141.28 15.39%

    COST PER SFT RS 13.40 1.08 14.48 0.57 108.03 123.08

    11) OTHER WORKS

    11.12 Plastering of Tank and Manholes Sft 383.00 8.50 3,255.50 0.68 260.44 3,515.94 0.17 65.11 8.00 3,064.00 17.35 6,645.05 0.14%

    11.13 Boundary wall brickwork Cft 420.00 13.00 5,460.00 1.04 436.80 5,896.80 0.17 71.40 8.01 3,364.20 22.22 9,332.40 0.20%

    11.16 Boundary wall Plastering Sft 2,240.00 8.50 19,040.00 0.68 1,523.20 20,563.20 0.17 380.80 8.01 17,942.40 17.36 38,886.40 0.82%

    COST OF OTHER WORKS RS 27,755.50 2,220.44 29,975.94 517.31 24,370.60 54,863.85 1.16%

    COST PER SFT RS 4.69 0.38 5.07 0.09 4.12 9.27

    OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKSRS 290,297.55 23,253.30 313,550.85 7,731.40 988,893.13 1,310,175.37 27.68%

    COST PER SFT RS 49.07 3.93 53.00 52.00 1.31 167.16 221.46

    COST OF CONCRETE FRAME STRUCTURE WORKS (A) : 429,437.25 34,253.83 463,691.08 128,242.05 2,667,122.34 3,255,747.82 68.79%

    COST PER SFT 72.59 5.79 78.38 83.00 21.68 450.83 550.33

    290,297.55 23,253.30 313,550.85 7,731.40 988,893.13 1,310,175.37 27.68%

    COST PER SFT 49.07 3.93 53.00 52.00 1.31 167.16 221.46

    Covered Area (Sft) 5,916.00 5,916.00 5,916.00 5,916.00 5,916.00 5,916

    TOTAL COST (A+B) : 719,735 57,507 777,242 135,973 3,656,015 4,565,923 96.47%

    COST PER SFT 121.66 9.72 131.38 22.98 617.99 771.79

    ADD: CONTINGENCIES FOR ANY OTHER COST 2.70 0.36 3.05 1.99 22.59 28.21 3.53%

    TOTAL BUDGETED COST : 124.36 10.08 134.43 24.97 640.57 799.98 800.00

    % OF BUDGETED COST : 15.54% 1.26% 16.80% 3.12% 80.07% 100.00%

    DIRECT LABOUR TOTAL LABOUR MACHINERY MATERIAL TOTAL AMOUNT

    (A) (B) (A+B) (C) (D) (A+B+C+D)

    TOTAL CONTRACT COST : 73,568,690 5,960,892 79,529,581 14,774,645 378,963,668 473,280,000

    TOTAL BUDGETED COST : - - - - - -

    POSSIBLE COST SAVING : 73,568,690 5,960,892 79,529,581 14,774,645 378,963,668 473,280,000

    DIRECT UNIT

    COST

    DIRECT TOTAL

    COST

    INDIRECT

    UNIT COST

    INDIRECT

    TOTAL COST

    DIRECT &

    INDIRECT

    TOTAL COST

    UNIT

    COST

    Excavation in hard soil upto 1.5 m depth to obtain earth for

    embankments or to clear building sites etc.

    Earth Filling in area where required in 150 mm layers, borrow from

    other site and fill according to requirement and as directed by the

    engineer incharge.

    Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken

    stone graded in foundation as specified.

    Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken

    stone graded in foundation as specified.

    Providing and Placing reinforced cement concrete in different Grades

    using crushed or broken stone graded as specified in specificatins.

    Cutting, Bending & Fixing of Steel as per drawing as directed by

    engineer incharge.

    Columns @ 5.454 KG/CFT

    Providing, Fixing & Removal of formwork with good quality & smooth

    surface of concrete after removal, complete in all respect or as

    directed by the engineer incharge.

    Termite Proofing in area where required with approved material from

    main contractor, according to requirement and as directed by the

    engineer incharge.

    OTHER ASSOCIATED WORK FOR GREY

    STRUCTURE

    Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand

    Mortar (1:4) In Super Structure , including form work, curing etc

    complete in all respect or as directed by the engineer incharge.

    Applying 13mm thick cement and sand plaster (1:4) to be trowelled

    smooth with steel trowel to brick or block wall,as Directed by the

    engineer incharge.

    OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS

    (B) :

    INDIRECTLABOUR

    mailto:Columns@%205.454%20KG/CFTmailto:Columns@%205.454%20KG/CFT
  • 7/25/2019 Budget Based on Villa Type b

    4/26

    COST BUDGETCONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)

    BAHRIA TOWN GARDEN CITY

    BUILT-UP FLOOR AREA = 5916 SFT

    S.NO DESCRIPTION UNIT QUANTITY

    LABOR (A) MACHINERY (B) MATERIAL (C)

    RATE (Rs) AMOUNT (Rs) %

    TOTAL COST UNIT COST TOTAL COST

    CONCRETE FRAME STRUCTURE WORKS

    1) EXCAVATION WORKS

    1.1

    Cft 13,228.00 0.48 6,349.44 0.07 925.96 7,275.40 0.95 12,566.60 - - 1.50 19,842.00 0.44%

    1.2

    Cft 12,338.00 - - 0.09 1,110.42 1,110.42 1.80 22,208.40 - - 1.89 23,318.82 0.51%

    COST OF EXCAVATION WORKS RS 6,349.44 2,036.38 8,385.82 34,775.00 - 43,160.82 0.95%

    COST PER SFT RS 1.07 0.34 1.42 5.88 - 7.30

    2) CONCRETE WORKS

    2.1a

    Cft 866.29 4.00 3,465.16 0.85 736.35 4,201.51 3.75 3,248.59 64.50 55,875.71 73.10 63,325.80 1.39%

    2.1b

    Cft 644.63 4.00 2,578.52 0.85 547.94 3,126.46 3.75 2,417.36 64.50 41,578.64 73.10 47,122.45 1.03%

    2.2

    2.2.1 Raft and Column Footing ( 3,000 PSI ) Cft 2,703.76 4.00 10,815.04 0.90 2,433.38 13,248.42 7.10 19,196.70 104.76 283,245.90 116.76 315,691.02 6.93%

    2.2.2 Retaining Wall ( 3,000 PSI ) Cft - 4.00 - 0.90 - - 7.10 - - - 12.00 - -

    2.2.3 Columns ( 3,750 PSI ) Cft 574.00 4.00 2,296.00 0.90 516.60 2,812.60 7.10 4,075.40 113.84 65,344.16 125.84 72,232.16 1.59%

    2.2.4 Slabs ( 3,000 PSI ) Cft 2,644.23 4.00 10,576.92 0.90 2,379.81 12,956.73 7.10 18,774.03 102.76 271,721.07 114.76 303,451.83 6.66%

    2.2.5 Lintels & Beams ( 3,000 PSI ) Cft 1,732.89 4.00 6,931.56 0.90 1,559.60 8,491.16 7.10 12,303.52 102.76 178,071.78 114.76 198,866.46 4.37%

    7,654.88

    COST OF CONCRETE WORKS RS 36,663.20 8,173.68 44,836.88 60,015.60 895,837.26 1,000,689.72 21.97%

    COST PER SFT RS 6.20 1.38 7.58 10.14 151.43 169.15

    3) STEEL

    3.1 Column Footing Kg 6,099.68 2.50 15,249.20 0.20 1,219.94 16,469.14 0.40 2,439.87 55.00 335,482.40 58.10 354,391.41 7.78%

    3.2 Retaining Wall Kg - - - - - - - - - - - - -

    3.3 Kg 3,133.86 2.50 7,834.65 0.20 626.77 8,461.42 0.40 1,253.54 55.00 172,362.30 58.10 182,077.27 4.00%

    3.4 Slabs Kg - - - - - - - - - - - - -

    3.5 Slab, Lintels & Beams Kg 14,785.91 2.50 36,964.78 0.20 2,957.18 39,921.96 0.40 5,914.36 55.00 813,225.05 58.10 859,061.37 18.86%

    24,019.45

    KG/M3 110.76

    COST OF REINFORCEMENT WORKS RS 60,048.63 4,803.89 64,852.52 9,607.77 1,321,069.75 1,395,530.05 30.64%

    COST PER SFT RS 10.15 0.81 10.96 1.62 223.30 235.89

    4) FORMWORK

    4.1 Raft & Column Footing Sft 217.73 10.00 2,177.30 1.07 232.97 2,410.27 0.51 111.04 8.30 1,807.16 19.88 4,328.47 0.10%

    4.2 Retaining Wall Sft - - - 1.07 - - 0.51 - - - - - 0.00%4.3 Columns Sft 3,491.44 10.00 34,914.40 1.07 3,735.84 38,650.24 0.51 1,780.63 24.00 83,794.56 35.58 124,225.44 2.73%

    4.4 Slabs Sft 5,979.61 10.00 59,796.10 1.07 6,398.18 66,194.28 0.51 3,049.60 24.00 143,510.64 35.58 212,754.52 4.67%

    4.5 Lintels & Beams Sft 6,849.44 10.00 68,494.40 1.07 7,328.90 75,823.30 0.51 3,493.21 14.20 97,262.05 25.78 176,578.56 3.88%

    16,538.22

    M2/M3 7.09

    COST OF FORMWORK RS 165,382.20 17,695.89 183,078.09 8,434.48 326,374.41 517,886.99 11.37%

    COST PER SFT RS 27.96 2.99 30.95 1.43 55.17 87.54

    7)

    Sft 5,372.79 - - 0.06 322.37 322.37 - - 2.66 14,291.62 2.72 14,613.99 0.32%

    ANTI-TERMITE WORKS RS - 322.37 322.37 - 14,291.62 14,613.99 0.32%

    COST PER SFT RS - 0.05 0.05 - 2.42 2.47

    6)Water Proofing as specified Sft 1,894.94 6.00 11,369.64 1.12 2,122.33 13,491.97 - - 56.00 106,116.64 63.12 119,608.61 2.63%

    WATERPROOFING WORKS RS 11,369.64 2,122.33 13,491.97 - 106,116.64 119,608.61 2.63%

    COST PER SFT RS 1.92 0.36 2.28 - 17.94 20.22

    11) OTHER WORKS

    11.01 Overhead water tank concrete Cft 147.39 4.00 589.56 0.90 132.65 722.21 7.10 1,046.47 104.76 15,440.58 116.76 17,209.26 0.38%

    11.02 Overhead water tank reinforcement Kg 558.66 2.50 1,396.65 0.20 111.73 1,508.38 0.30 167.60 56.00 31,284.96 59.00 32,960.94 0.72%

    11.03 Overhead water tank formwork Sft 450.00 10.00 4,500.00 1.07 481.50 4,981.50 0.51 229.50 8.30 3,735.00 19.88 8,946.00 0.20%

    11.04 PVC waterstop for OHWT Rft 20.00 25.00 500.00 0.18 3.60 503.60 - - 165.00 3,300.00 190.18 3,803.60 0.08%

    11.05 Manhole cover and insulation for OHWT Set 1.00 200.00 200.00 5.77 5.77 205.77 - - 2,500.00 2,500.00 2,705.77 2,705.77 0.06%

    11.06 Underground watertank concrete Cft 96.05 4.00 384.20 0.90 86.45 470.65 7.10 681.96 104.76 10,062.20 116.76 11,214.80 0.25%

    11.07 Underground watertank reinforcement Kg 325.00 2.50 812.50 0.20 65.00 877.50 0.30 97.50 56.00 18,200.00 59.00 19,175.00 0.42%

    11.08 Underground watertank formwork Sft 432.00 10.00 4,320.00 1.07 462.24 4,782.24 0.51 220.32 8.30 3,585.60 19.88 8,588.16 0.19%11.09 PVC waterstop for UGWT Rft 28.00 25.00 700.00 0.18 5.04 705.04 - - 165.00 4,620.00 190.18 5,325.04 0.12%

    11.10Waterproofing for UGWT wall (with Bitumen) Sft 140.00 28.00 3,920.00 2.04 285.60 4,205.60 0.17 23.80 5.33 746.20 35.54 4,975.60 0.11%

    11.11 Gully trap (2 Nos) & Manhole (1 No) Cft 73.50 15.00 1,102.50 1.20 88.20 1,190.70 0.17 12.50 85.00 6,247.50 101.37 7,450.70 0.16%

    11.14 Boundary wall RCC Cft 210.00 4.00 840.00 0.90 189.00 1,029.00 7.10 1,491.00 104.76 21,999.60 116.76 24,519.60 0.54%

    11.15 Boundary wall Lean Concrete Cft 92.00 4.00 368.00 0.90 82.80 450.80 7.10 653.20 104.76 9,637.92 116.76 10,741.92 0.24%

    11.17 PCC (1:4:8) for walkway Cft 184.92 4.00 739.68 0.85 157.18 896.86 3.95 730.43 64.50 11,927.34 73.30 13,554.64 0.30%

    COST OF OTHER WORKS RS 20,373.09 2,156.76 22,529.85 5,354.28 143,286.90 171,171.03 3.76%

    COST PER SFT RS 3.44 0.36 3.81 0.91 24.22 28.93

    COST OF CONCRETE FRAME STRUCTURE WORKSRS 300,186.20 37,311.30 337,497.50 118,187.13 2,806,976.58 3,262,661.21 71.63%

    COST PER SFT RS 50.74 6.31 57.05 19.98 474.47 551.50

    5) BLOCK WORK

    Cft 4,053.55 13.43 54,439.18 1.07 4,337.30 58,776.48 0.20 810.71 50.33 204,015.17 65.03 263,602.36 5.79%

    8) Plaster works

    Sft 15,156.29 8.50 128,828.47 0.68 10,306.28 139,134.75 0.20 3,031.26 8.01 121,401.88 17.39 263,567.88 5.79%

    BLOCKWORKS & PLASTERING WORKS RS 183,267.65 14,643.58 197,911.23 3,841.97 325,417.05 527,170.24 11.57%

    COST PER SFT RS 30.98 2.48 33.45 0.65 55.01 89.11

    9) EMBEDDED ITEMS FOR ELECTRICAL WORKS Sft 5,916.00 5.33 31,532.28 0.55 3,253.80 34,786.08 0.30 1,774.80 63.53 375,843.48 69.71 412,404.36 9.05%

    10) EMBEDDED ITEMS FOR PLUMBING WORKS Sft 5,916.00 5.07 29,994.12 0.53 3,135.48 33,129.60 0.27 1,597.32 44.50 263,262.00 50.37 297,988.92 6.54%

    COST OF ELECTRICAL & PLUMBING WORKS RS 61,526.40 6,389.28 67,915.68 3,372.12 639,105.48 710,393.28 15.60%

    COST PER SFT RS 10.40 1.08 11.48 0.57 108.03 120.08

    11) OTHER WORKS

    11.12 Plastering of Tank and Manholes Sft 383.00 8.50 3,255.50 0.68 260.44 3,515.94 0.17 65.11 8.00 3,064.00 17.35 6,645.05 0.15%

    11.13 Boundary wall brickwork Cft 420.00 13.00 5,460.00 1.04 436.80 5,896.80 0.17 71.40 8.01 3,364.20 22.22 9,332.40 0.20%11.16 Boundary wall Plastering Sft 2,240.00 8.50 19,040.00 0.68 1,523.20 20,563.20 0.17 380.80 8.01 17,942.40 17.36 38,886.40 0.85%

    COST OF OTHER WORKS RS 27,755.50 2,220.44 29,975.94 517.31 24,370.60 54,863.85 1.20%

    COST PER SFT RS 4.69 0.38 5.07 0.09 4.12 9.27

    OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKSRS 272,549.55 23,253.30 295,802.85 7,731.40 988,893.13 1,292,427.37 28.37%

    COST PER SFT RS 46.07 3.93 50.00 1.31 167.16 218.46

    COST OF CONCRETE FRAME STRUCTURE WORKS (A) : 300,186.20 37,311.30 337,497.50 118,187.13 2,806,976.58 3,262,661.21 71.63%

    COST PER SFT 50.74 6.31 57.05 83.00 19.98 474.47 551.50 551.50

    -

    272,549.55 23,253.30 295,802.85 7,731.40 988,893.13 1,292,427.37 28.37%

    COST PER SFT 46.07 3.93 50.00 52.00 1.31 167.16 218.47 218.46

    Covered Area (Sft) 5,916.00 5,916.00 5,916.00 5,916.00 5,916.00 5,916

    TOTAL COST (A+B) : 572,736 60,565 633,300 125,919 3,795,870 4,555,089 100.00%

    COST PER SFT 96.81 10.24 107.05 21.29 641.63 769.97

    ADD: CONTINGENCIES FOR ANY OTHER COST - - - - - - 0.00%

    TOTAL BUDGETED COST PER SFT: 96.81 10.24 107.05 21.29 641.63 769.97 769.97

    % OF BUDGETED COST : 12.57% 1.33% 13.90% 2.77% 83.33% 100.00%

    DIRECT LABOUR INDIRECT LABOUR TOTAL LABOUR MACHINERY MATERIAL TOTAL AMOUNT

    (A) (B) (A+B) (C) (D) (A+B+C+D)

    TOTAL BUDGETED COST : 57,272,796 6,057,984 63,330,780 12,595,164 379,588,308 455,514,252

    DIRECT UNIT

    COSTDIRECT TOTAL COST

    INDIRECT

    UNIT COST

    INDIRECT TOTAL

    COST

    DIRECT &

    INDIRECT TOTAL

    COST

    UNIT

    COST

    Excavation in hard soil upto 1.5 m depth to obtain earth for

    embankments or to clear building sites etc.

    Earth Filling in area where required in 150 mm layers, borrow from

    other site and fill according to requirement and as directed by the

    engineer incharge.

    Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken

    stone graded in foundation as specified.

    Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken

    stone graded in foundation as specified.

    Providing and Placing reinforced cement concrete in different Grades

    using crushed or broken stone graded as specified in specificatins.

    Cutting, Bending & Fixing of Steel as per drawing as directed by

    engineer incharge.

    Columns @ 5.454 KG/CFT

    Providing, Fixing & Removal of formwork with good quality & smooth

    surface of concrete after removal, complete in all respect or as

    directed by the engineer incharge.

    Termite Proofing in area where required with approved material from

    main contractor, according to requirement and as directed by the

    engineer incharge.

    OTHER ASSOCIATED WORK FOR GREY

    STRUCTURE

    Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand

    Mortar (1:4) In Super Structure , including form work, curing etc

    complete in all respect or as directed by the engineer incharge.

    Applying 13mm thick cement and sand plaster (1:4) to be trowelled

    smooth with steel trowel to brick or block wall,as Directed by the

    engineer incharge.

    OTHER ASSOCIATED WORK FOR GREY STRUCTURE WORKS

    (B) :

    mailto:Columns@%205.454%20KG/CFTmailto:Columns@%205.454%20KG/CFT
  • 7/25/2019 Budget Based on Villa Type b

    5/26

    BOQ I!"-03

    RATE ANALYSIS OF 400 !00 !00 "" T#$%& 'o%& "ao*r+.

    S.No ETAILS-*$t Rate er 100 S

    /t+ Rate er *$t

    "ATERIA

    123.75 Nos Rs. 29.00 P.No.

    Mortar Reu!re" #or 100 $FT %lo&' (or' 10.)4 CFT

    Cement * +PC ,. 0.55 %a-s Rs. 350.00 P.%a-

    $an" 3.20 C#t Rs. 1).00 P.C#t

    all T!es ).00 No Rs. 35.00 P.No

    Tota (A).

    LA'O-R.

    Mason 2.0 No Rs. 500.00 er "a

    aour 3.0 No Rs. 300.00 er "a

    %a!st! 2.0 No Rs. 300.00 er "a

    $&aol"er 0.3 No Rs. 350.00 er "a

    Tota (').

    2 Ite3 Rate.

    Comos!te Rate #or 100 $FT Tota (A').

    Comos!te Rate #or one $FT.

    S3$tted '+. C#e%&ed '+.

    Providing and laying cement concrete Hollow block masonry walls of specied strength

    specication, using machine made blocks (approved quality of ne and course aggregat

    cement sand mortar, in any shape, length or height, laid at specied levels, including co

    #all ties as per drawing including racking out $oints cutting, curing etc, complete in all r

    conforming to the requirements of drawings, specications and to the entire satisfactio

    Con&ete %lo&'s *16 )6 )6,8n&lu"!n- 10 asta-e.

  • 7/25/2019 Budget Based on Villa Type b

    6/26

    BOQ I!"-03

    T

    A3o*t

    Rs. 3:5)).75

    Rs. 192.50

    Rs. 57.0

    Rs. 2)0.00

    R. 4,11.5

    R. 41.19

    Rs. 1:000.00

    Rs. 900.00

    Rs. 00.00

    Rs. 105.00

    R. !,605.00

    R. !6.05

    Rs. :724.00

    Rs. 7.24

    Aroved '+.

    s per

    ) laid in 1!

    t of sca"olding,

    spects and

    of the %ngineer

  • 7/25/2019 Budget Based on Villa Type b

    7/26

    BOQ I!"-2#1

    RATE ANALYSIS OF 40007SI CONCRETE

    S.No ETAILS-*$t Rate er C-".

    /t+ Rate er *$t

    "ATERIAL

    a. Con&rete ;el!

    me&an!&al

  • 7/25/2019 Budget Based on Villa Type b

    8/26

    BOQ I!"-2#1

    A3o*t

    Rs. 1.40

    Rs. 3.07

    Rs. 4.50

    Rs. 3.54

    Rs. .19

    Rs. 0.))

    Rs. 10.2

    Rs. 75.12

    Aroved '+.

    &ement &on&rete o#

    !n- trou- ele&tro

    sat!s#a&t!on o# te

  • 7/25/2019 Budget Based on Villa Type b

    9/26

    BOQ I!"-5#1

    RATE ANALYSIS OF CONCRETE FOR COL-"NS

    S.No ETAILS-*$t Rate er C-".

    /t+ Rate er *$t

    "ATERIAL

    a. Con&rete ;el!

  • 7/25/2019 Budget Based on Villa Type b

    10/26

    BOQ I!"-5#1

    A3o*t

    Rs. 125.00

    Rs. .25

    Rs. 1.9)

    Rs. 2.44

    Rs. 0.))

    Rs. 1.13

    Rs. 137.70

    Rs. 1.77

    Rs. .19Rs. 0.))

    Rs. ).)5

    Rs. 14.55

    Aroved '+.

    ment &on&rete Ra#t:n-: &ur!n- all as er

  • 7/25/2019 Budget Based on Villa Type b

    11/26

    BOQ I!"-5#2$5#5

    RATE ANALYSIS OF CONCRETE FOR OT8ER STR-CT-RE

    S.No ETAILS-*$t Rate er C-".

    /t+ Rate er *$t

    "ATERIAL

    a. Con&rete ;el!

  • 7/25/2019 Budget Based on Villa Type b

    12/26

    BOQ I!"-5#2$5#5

    A3o*t

    Rs. 99.50

    Rs. 4.9)

    Rs. 1.9)

    Rs. 2.44

    Rs. 0.))

    Rs. 1.13

    Rs. 110.90

    Rs. 1.77

    Rs. .19Rs. 0.))

    Rs. ).)5

    Rs. 119.75

    Aroved '+.

  • 7/25/2019 Budget Based on Villa Type b

    13/26

    BOQ I!"-06

    RATE ANALYSIS OF STEEL REINFORCE"ENT

    S.No ETAILS-*$t Rate e

    /t+ Rate er

    "ATERIAL

    a. $teel %ar #rom aro

  • 7/25/2019 Budget Based on Villa Type b

    14/26

    BOQ I!"-06

    r ".TON

    *$t A3o*t

    P.KG Rs. 5.00

    P.KG Rs. 7.20

    Rs. 3.1

    a (A). Rs. 75.)1

    P. >our Rs. 1.75

    P. >our Rs. 1.97

    a ('). Rs. 3.72

    (A ' ). Rs. 79.53

    Aroved '+.

    t 0:000 s! er s. !n& !el"

    e "ra(!n-s !n os!t!on on M.$.

    at an e!-t an" an os!t!on

    a-e an" roll!n- mar-!n sall e

  • 7/25/2019 Budget Based on Villa Type b

    15/26

    BOQ I!"-7#3

    RATE ANALYSIS OF FOR":OR; FOR COL-"NS

    No ETAILS-*$t Rate er SFT

    /t+ Rate er *$t

    "ATERIAL

    . Plas#orm 1.00 $FT Rs. 13.00 P.$FT

    . Mol" +!l @ 5 $m (!t 1 !tre 0.20 tr Rs. 10.04 P.$FT

    $teel Na!ls 0.15 K- Rs. ).)3 P.$FT

    . G.8. $eets or ?n#or seen 8tems et&. 0.03 $FT Rs. 34.39 P.$FT

    . $a&er %lo&'s *a

  • 7/25/2019 Budget Based on Villa Type b

    16/26

    BOQ I!"-7#3

    n-!neer.

    A3o*t

    Rs. 13.00

    Rs. 2.01

    Rs. 1.32

    Rs. 1.03

    Rs. 0.42

    Rs. 17.)0

    Rs. 5.03

    Rs. 7.50

    Rs. 12.50

    Rs. 30.30

    Aroved '+.

  • 7/25/2019 Budget Based on Villa Type b

    17/26

    BOQ I!"-7#1%7#2

    RATE ANALYSIS OF FOR":OR; FOR :ALLS

    No ETAILS-*$t Rate er SFT

    /t+ Rate er *$t

    "ATERIAL

    . Plas#orm 1.00 $FT Rs. .00 P.$FT

    . Mol" +!l @ 5 $m (!t 1 !tre 0.20 tr Rs. 10.04 P.$FT

    $teel Na!ls 0.15 K- Rs. ).)3 P.$FT

    . G.8. $eets or ?n#or seen 8tems et&. 0.03 $FT Rs. 34.39 P.$FT

    . $a&er %lo&'s *a

  • 7/25/2019 Budget Based on Villa Type b

    18/26

    BOQ I!"-7#1%7#2

    n-!neer.

    A3o*t

    Rs. .00

    Rs. 2.01

    Rs. 1.32

    Rs. 1.03

    Rs. 0.42

    Rs. 10.)0

    Rs. 5.03

    Rs. 7.50

    Rs. 12.50

    Rs. 23.30

    Aroved '+.

  • 7/25/2019 Budget Based on Villa Type b

    19/26

    BOQ I!"-7#4%7#5

    RATE ANALYSIS OF FOR":OR; FOR 'EA"S AN SLA'S

    No ETAILS-*$t Rate er SFT

    /t+ Rate er *$t

    "ATERIAL

    . Plas#orm 1.00 $FT Rs. 4.00 P.$FT

    . Mol" +!l @ 5 $m (!t 1 !tre 0.20 tr Rs. 10.04 P.$FT

    $teel Na!ls 0.15 K- Rs. ).)3 P.$FT

    . G.8. $eets or ?n#or seen 8tems et&. 0.03 $FT Rs. 34.39 P.$FT

    . $a&er %lo&'s *a

  • 7/25/2019 Budget Based on Villa Type b

    20/26

    BOQ I!"-7#4%7#5

    n-!neer.

    A3o*t

    Rs. 4.00

    Rs. 2.01

    Rs. 1.32

    Rs. 1.03

    Rs. 0.42

    Rs. ).)0

    Rs. 5.03

    Rs. 7.50

    Rs. 12.50

    Rs. 21.30

    Aroved '+.

  • 7/25/2019 Budget Based on Villa Type b

    21/26

    'a$% "ater$a Rate S+ '+ E3o+er

    ETAILS Rate Re3ar&

    "ATERIAL

    Con&rete *14), Rs. 2:15.00 / C?M

    Con&rete *3750 P$8, #or C+?MN$ Rs. 4:414.00 / C?M

    Con&rete *3000 P$8, #or +ter $tru&ture Rs. 3:514.00 / C?M

    $teel G0 Rs. 53:000.00 / M. Ton

  • 7/25/2019 Budget Based on Villa Type b

    22/26

    $?MMHRI +F %?;GTT; +FF8C PN$

    $R J ;$CR8PT8+N ?N8T TI

    1 RNTH +F $THFF >+?$

    a, M+NT>I RNTH MT> 1)

    , MH8NTNHNC F$ MT> 1)

    &, CTR8C8TI MT> 1)

    ", $?8 GH$ MT> 1)

    e, CHNR$ C+$T MT> 1)

    #, ;R8NK8NG M8NRH HTR MT> 1)

    -, F?RN8$>8NG $

    2 +FF8C $THFF $HHR8$

    "ALAYSIAN

    a, PR+=CT ;8RCT+R MT> 1)

    , F8NHNC HN; HCC+?NT$ MHNHGR MT> 1)

    3 LOCAL STAFF

    a, PR+=CT MHNHGR MT> 1)

    , C+N$TR?CT8+N MHNHGR MT> 1)

    &, H;M8N/>R MHNHGR MT> 1)

    ", CTR8CH NG8NR MT> 1)

    e, MC>HN8CH NG8NR MT> 1)

    #, C+NTRHCT$ C?T8L MT> 1)

    -, PH/8T C++R;8NHT+R MT> 1)

    , ;+C?MNT C+NTR+R MT> 1)

    , +FF8C %+I MT> 1)', T8MKPR MT> 1)

    m, C++K MT> 1)

    n, ;R8LR MT> 1)

    4 H8R T8CKT$ TR8P$ 12

    5 P?RC>H$ +F $H++N CHR 1500CC ?N8T 1

    F? HN; MH8NTNHNC ?N8T 1)

    7 M;8CH H+HNC MT> 1)

    ) NTRTH8MNT$/ F++; D ;R8NK$ MT> 1)

    TOTAL

  • 7/25/2019 Budget Based on Villa Type b

    23/26

    $ +F 6CM$6

    RHT HM+?NT *R$,

    42:000 75:000

    2:000 3:000

    20:000 30:000

    1:500 27:000

    3:000 54:000

    4:500 )1:000

    100:000

    750:000 13:500:000

    250:000 4:500:000

    )0:000 1:440:000

    5:000 1:170:000

    70:000 1:20:000

    40:000 720:000

    30:000 540:000

    35:000 30:000

    35:000 30:000 420:000.00

    25:000 450:000

    12:000 21:00015:000 270:000

    10:000 1)0:000

    12:000 21:000 1:429:000

    0:000 720:000

    1:000:000 1:000:000

    20:000 30:000

    15:000 270:000

    10:000 1)0:000

    !9,666,000

  • 7/25/2019 Budget Based on Villa Type b

    24/26

    C+MP?THT8+N +F %?;GTT

    $R J ;$CR8PT8+N ?N8T TI

    1 $T8MHT; C+N$TR?CT8+N C+$T

    a, $HFHR8 L8H ?N8T % ?N8T 100

    2 MHNHGMNT F @ 10

    3 $$ +FF8C PN$$

    4 $$ PR+P+$; PR+=CT 8NCNT8L$ MT>

    '-

  • 7/25/2019 Budget Based on Villa Type b

    25/26

    ; PR+F8T

    HM+?NT *R$,

    591 )00 473:2)0:000

    10 47:32):000

    .27 *29::000,

    714:500 0.91 *4:2)7:002,

    12,2=4,99

    2.)3

    %?8T?PF++R HRH

    *$FT,%?;GTT;C+$T/ $FT

    %H$8C$HHRI/MT>

  • 7/25/2019 Budget Based on Villa Type b

    26/26

    COST BUDGET

    CONSTRUCTION OF SAFARI VILLAS TYPE - B (GREY STRUCTURE)BAHRIA TOWN GARDEN CITY

    BUILT-UP FLOOR AREA = 5916 SFT

    S.NO DESCRIPTION UNITS QUANTITY LABOR (A) MACHINERY (B) MATERIAL (C) RATE (Rs) AMOUNT (Rs)

    UNIT COST TOTAL COST UNIT COST TOTAL COST

    1) EXCAVATION WORKS

    1.1Cft 13,228.00 0.85 11,243.80 0.07 925.96 12,169.76 0.95 12,566.60 - - 1.87 24,736.36

    1.2

    Cft 12,338.00 1.15 14,188.70 0.09 1,110.42 15,299.12 2.80 34,546.40 - - 4.04 49,845.52

    2) CONCRETE WORKS

    2.1a

    Cft 866.29 5.00 4,331.45 0.85 736.35 5,067.80 3.75 3,248.59 64.50 55,875.71 74.10 64,192.09

    2.1b

    Cft 644.63 5.00 3,223.15 0.85 547.94 3,771.09 3.75 2,417.36 64.50 41,578.64 74.10 47,767.082.2

    2.2.1 Raft and Column Footing ( 3,000 PSI ) Cft 2,703.76 5.00 13,518.80 0.71 1,919.67 15,438.47 7.08 19,142.62 104.76 283,245.90 117.55 317,826.99

    2.2.2 Retaining Wall ( 3,000 PSI ) Cft - - - - - - - - - - - -

    2.2.3 Columns ( 3,750 PSI ) Cft 574.00 5.00 2,870.00 0.71 407.54 3,277.54 7.08 4,063.92 113.84 65,344.16 126.63 72,685.62

    2.2.4 Slabs ( 3,000 PSI ) Cft 2,644.23 5.00 13,221.15 0.71 1,877.40 15,098.55 7.08 18,721.15 102.76 271,721.07 115.55 305,540.78

    2.2.5 Lintels & Beams ( 3,000 PSI ) Cft 1,732.89 5.00 8,664.45 0.71 1,230.35 9,894.80 7.08 12,268.86 102.76 178,071.78 115.55 200,235.44

    7,654.88

    3) STEEL

    3.1 Column Footing Kg 6,099.68 2.20 13,419.30 0.20 1,219.94 14,639.24 0.40 2,439.87 55.00 335,482.40 57.80 352,561.50

    3.2 Retaining Wall Kg - - - - - - - - - - - -

    3.3 Kg 3,133.86 2.20 6,894.49 0.20 626.77 7,521.26 0.40 1,253.54 55.00 172,362.30 57.80 181,137.11

    3.4 Slabs Kg - ### - - - - - - - - - -

    3.5 Slab, Lintels & Beams Kg 14,785.91 2.20 32,529.00 0.20 2,957.18 35,486.18 0.40 5,914.36 55.00 813,225.05 57.80 854,625.60

    24,019.45

    KG/M3 110.76

    4) FORMWORK

    4.1 Raft & Column Footing Sft 217.73 10.00 2,177.30 1.00 217.73 2,395.03 0.20 43.55 7.80 1,698.29 19.00 4,136.874.2 Retaining Wall Sft - - - - - - - - - - - -

    4.3 Columns Sft 3,491.44 10.00 34,914.40 1.00 3,491.44 38,405.84 0.20 698.29 16.80 58,656.19 28.00 97,760.32

    4.4 Slabs Sft 5,979.61 10.00 59,796.10 1.00 5,979.61 65,775.71 0.20 1,195.92 9.80 58,600.18 21.00 125,571.81

    4.5 Lintels & Beams Sft 6,849.44 10.00 68,494.40 1.00 6,849.44 75,343.84 0.20 1,369.89 9.80 67,124.51 21.00 143,838.24

    16,538.22

    M2/M3 7.09

    5) BLOCK WORK

    Cft 4,053.55 13.43 54,439.18 1.07 4,337.30 58,776.48 0.20 810.71 50.33 204,015.17 65.03 263,602.36

    6)Water Proofing as specified Sft 1,894.94 14.00 26,529.16 1.12 2,122.33 28,651.49 - - 56.00 106,116.64 71.12 134,768.13

    7)

    Sft 5,372.79 0.75 4,029.59 0.06 322.37 4,351.96 - - 2.66 14,291.62 3.47 18,643.58

    8) Plaster works

    Sft 15,156.29 8.00 121,250.32 0.68 10,306.28 131,556.60 0.20 3,031.26 8.01 121,401.88 16.89 255,989.74

    COST OF CIVIL WORKS RS 495,734.74 47,186.02 542,920.76 123,732.89 2,848,811.49 3,515,465.14

    COST PER SFT RS 83.80 7.98 91.77 20.91 481.54 594.23

    9) EMBEDDED ITEMS FOR ELECTRICAL WORKS Sft 5,916.00 6.83 40,406.28 0.55 3,253.80 43,660.08 0.30 1,774.80 63.53 375,843.48 71.21 421,278.36

    10) EMBEDDED ITEMS FOR PLUMBING WORKS Sft 5,916.00 6.57 38,868.12 0.53 3,135.48 42,003.60 0.27 1,597.32 44.50 263,262.00 51.87 306,862.92

    COST OF ELECTRICAL & PLUMBING WORKS RS 79,274.40 6,389.28 85,663.68 3,372.12 639,105.48 728,141.28

    COST PER SFT RS 13.40 1.08 14.48 0.57 108.03 123.08

    11) OTHER WORKS11.01 Overhead water tank concrete Cft 147.39 8.85 1,304.40 0.71 104.65 1,409.05 7.08 1,043.52 104.76 15,440.58 121.40 17,893.15

    11.02 Overhead water tank reinforcement Kg 558.66 2.56 1,430.17 0.20 111.73 1,541.90 0.30 167.60 56.00 31,284.96 59.06 32,994.46

    11.03 Overhead water tank formwork Sft 450.00 12.50 5,625.00 1.00 450.00 6,075.00 0.17 76.50 8.80 3,960.00 22.47 10,111.50

    11.04 PVC waterstop for OHWT Rft 20.00 2.20 44.00 0.18 3.60 47.60 - - 165.00 3,300.00 167.38 3,347.60

    11.05 Manhole cover and insulation for OHWT Set 1.00 72.12 72.12 5.77 5.77 77.89 - - 2,500.00 2,500.00 2,577.89 2,577.89

    11.06 Underground watertank concrete Cft 96.05 8.85 850.04 0.71 68.20 918.24 7.08 680.03 104.76 10,062.20 121.40 11,660.47

    11.07 Underground watertank reinforcement Kg 325.00 2.56 832.00 0.20 65.00 897.00 0.30 97.50 56.00 18,200.00 59.06 19,194.50

    11.08 Underground watertank formwork Sft 432.00 12.50 5,400.00 1.00 432.00 5,832.00 0.17 73.44 8.80 3,801.60 22.47 9,707.04

    11.09 PVC waterstop for UGWT Rft 28.00 2.20 61.60 0.18 5.04 66.64 - - 165.00 4,620.00 167.38 4,686.64

    11.10Waterproofing for UGWT wall (with Bitumen) Sft 140.00 0.56 78.40 0.04 5.60 84.00 0.17 23.80 5.33 746.20 6.10 854.00

    11.11 Gully trap (2 Nos) & Manhole (1 No) Cft 73.50 15.00 1,102.50 1.20 88.20 1,190.70 0.17 12.50 85.00 6,247.50 101.37 7,450.70

    11.12 Plastering of Tank and ManholesSft 383.00 8.50 3,255.50 0.68 260.44 3,515.94 0.17 65.11 8.00 3,064.00 17.35 6,645.05

    11.13 Boundary wall brickwork Cft 420.00 13.00 5,460.00 1.04 436.80 5,896.80 0.17 71.40 8.01 3,364.20 22.22 9,332.40

    11.14 Boundary wall RCC Cft 210.00 8.85 1,858.50 0.71 149.10 2,007.60 7.08 1,486.80 104.76 21,999.60 121.40 25,494.00

    11.15 Boundary wall Lean Concrete Cft 92.00 8.85 814.20 0.71 65.32 879.52 7.08 651.36 104.76 9,637.92 121.40 11,168.80

    11.16 Boundary wall Plastering Sft 2,240.00 8.50 19,040.00 0.68 1,523.20 20,563.20 0.17 380.80 8.01 17,942.40 17.36 38,886.40

    11.17 PCC (1:4:8) for walkway Cft 184.92 10.62 1,963.85 0.85 157.18 2,121.03 3.95 730.43 64.50 11,927.34 79.92 14,778.81

    -

    COST OF OTHER WORKS RS 49,192.28 3,931.83 53,124.11 5,560.79 168,098.50 226,783.41

    COST PER SFT RS 8.32 0.66 8.98 0.94 28.41 38.33

    COST FOR CIVIL, ELECTRICAL, PLUMBING & OTHER WORKS 624,201.42 57,507.13 681,708.55 132,665.80 3,656,015.47 4,470,389.83

    Covered Area (Sft) 5,916.00 5,916.00 5,916.00 5,916.00 5,916.00 5,916.00

    CHECK

    COST PER SFT 105.51 9.72 115.23 22.42 617.99 755.64 755.6

    ADD: CONTINGENCIES FOR ANY OTHER COST 6.76 1.32 36.28 44.36

    TOTAL BUDGETTED COST : 122.00 23.74 654.26 800.00 800.00

    13.96% 1.29% 15.25% 2.97% 81.78%

    DIRECT LABOUR INDIRECT LABOUR TOTAL LABOUR MACHINERY MATERIAL TOTAL AMOUNT

    (A) (B) (A+B) (C) (D) (A+B+C+D)

    MH8M?M C+$T +F C+N$TR?CT8+N 71!97"!#$.$$ 5!75$!71".$$ 7#!$91!%$$.$$ 1"!7#!7#.$$ "7#!961!%1%.$$ 7"!%#$!$$$.$$

    BUD&ETTED LABOUR COST 6%!%$!1%.$$ 5!75$!71".$$ 6#!17$!#55.$$

    COST SA'IN& 9!55"!""#.$$ - 9!9%$!"5.$$

    DIRECT UNIT

    COST

    DIRECT TOTAL

    COST

    INDIRECT

    UNIT COST

    INDIRECT TOTAL

    COST

    DIRECT &

    INDIRECT TOTAL

    COST

    Excavation in hard soil upto 1.5 m depth to obtain earth for embankments

    or to clear buildin sites etc.

    Earth Filling in area where required in 150 mm layers, borrow from other

    site and fill according to requirement and as directed by the engineer

    incharge.

    Laying 3" Thick (PCC 1:4:8) of cement concrete using crushed or broken stone

    graded in foundation as specified.

    Laying 2" Thick (PCC 1:4:8) of cement concrete using crushed or broken stone

    graded in foundation as specified.

    Providing and Placing reinforced cement concrete in different Grades using

    crushed or broken stone graded as specified in specificatins.

    Cutting, Bending & Fixing of Steel as per drawing as directed by engineer

    incharge.

    Columns @ 5.454 KG/CFT

    Providing, Fixing & Removal of formwork with good quality & smooth

    surface of concrete after removal, complete in all respect or as directed by

    the engineer incharge.

    Laying Block Work (8" x 8" x 16" & 4" x 8" x 16") in Cement Sand Mortar

    (1:4) In Super Structure , including form work, curing etc complete in all

    respect or as directed by the engineer incharge.

    Termite Proofing in area where required with approved material from main

    contractor, according to requirement and as directed by the engineer

    incharge.

    Applying 13mm thick cement and sand plaster (1:4) to be trowelled

    smooth with steel trowel to brick or block wall,as Directed by the engineer

    incharge.

    mailto:Columns@%205.454%20KG/CFTmailto:Columns@%205.454%20KG/CFT