brochure - nzta waikato construction

14
PROJECT O V E R V I E W

Upload: business-review-australia

Post on 03-Apr-2016

224 views

Category:

Documents


3 download

DESCRIPTION

 

TRANSCRIPT

Page 1: Brochure - NZTA Waikato Construction

P R O J E C T O V E R V I E W

Page 2: Brochure - NZTA Waikato Construction

Waikato Expressway Project – NZ Transport:The Waikato Expressway Project: Collaboration for a Common GoalThe Transport Agency is delivering the 102km Waikato Expressway, one of New Zealand’s Seven

Roads of National Significance.

Written by: Laura Close Produced by: Bryan Giles

Page 3: Brochure - NZTA Waikato Construction

1 0 4

Waikato Expressway Project – NZ Transport:The Waikato Expressway Project: Collaboration for a Common GoalThe Transport Agency is delivering the 102km Waikato Expressway, one of New Zealand’s Seven

Roads of National Significance.

Written by: Laura Close Produced by: Bryan Giles

Page 4: Brochure - NZTA Waikato Construction

1 0 5 A u g u s t 2 0 1 4

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

THE WAIKATO EXPRESSWAY is a key highway project the New Zealand Government identified as one of the Roads of National Significance in 2009. The Expressway runs from the top of the Bombay Hills in the north through to just south of Cambridge and will provide a key link for Auckland, Waikato and Bay of Plenty which includes nearly half the country’s population and produces 40 per cent of GDP.

When complete, this 102km continuous divided four-lane highway will allow for a safer, quicker

way to get freight and people through New Zealand’s upper North Island.

The Expressway is being built in several sections, with some already completed, and will reduce travel times for through traffic by up to 35 minutes.

The New Zealand Transport Agency is responsible for the delivery of the $2.1 billion project, with Peter Simcock, the project services manager, in charge of managing the operations from the Transport Agency’s office in Hamilton.

Like any major infrastructure project, challenges have been

The 200m long bridge over the Karapiro Gully has been a challenging

engineering project on the Cambridge section.

Page 5: Brochure - NZTA Waikato Construction

C O N S T R U C T I O N

www.nzta .govt .nz/pro jects /wa ikato-expressway 1 0 6

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

Earthworks along Victoria Road on the Cambridge section.

encountered. But with constant, strong collaboration the agency has with contractors, workers, the surrounding community and Maori, the completed sections of the Waikato Expressway have thus far been on time or early, and on or under budget.

“A key to that has been our extensive consultation processes,” said Simcock. “We have a no-surprises policy with our stakeholders and the public, and I believe the project overall enjoys good community support because we have been consulting with them

all the way along.’’The consultation process has

included a combination of site visits, individual meetings, newsletters and public information days, plus strong website backup.

“We have also set up a Visitor Centre at the Cambridge section project site office where people can call in to view graphics, maps, a DVD, posters, pick up an information sheet and ask questions. It’s also been popular with group bookings.’’

Te Rapa section – Fulton HoganThe Te Rapa section of the

Page 6: Brochure - NZTA Waikato Construction

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

Waikato Expressway opened on 3 December, 2012. The 8km stretch of road was constructed by Fulton Hogan, and came in at around $194 million. Harry Wilson, the Transport Agency’s Waikato-Bay of Plenty regional director, attributed the ahead-of-schedule delivery to the collaboration within the Te Rapa Alliance, which included the agency, Opus International Consultants and Fulton Hogan.

“Procuring the Te Rapa section through a competitive alliance has delivered a first-class roading project for all stakeholders,” said Peter Murphy, the Transport Agency’s project manager for the Te Rapa section.

“The Te Rapa Alliance team has been able to successfully manage the scale and complexity of this project while working within the uncertainty of unresolved designation and property procurement matters. The team delivered the project at least 12 months earlier than could have been achieved through more traditional procurement methods.”

In total 300,000 square metres of road and six bridges were constructed, including the 150m long curved steel and concrete composite bridge over the North Island Main Trunk railway line. This effort took enormous resources,

including 25,000 tonnes of concrete and 2200 tonnes of reinforcing steel to build the bridges, 6000 metres of piles for the bridge foundations and 7000 square metres of anti-graffiti paint.

The section starts in the northwest corner of Hamilton City and extends into the Waikato district. It connects with the completed Ngaruawahia section to the north.

Ngaruawahia section – Fletcher ConstructionThe Ngaruawahia section of the Waikato Expressway opened on 16 December, 2013. The 12.3km project cost around $200 million, nearly $50 million under original estimates. Fletcher Construction was responsible for the four-lane road, which runs from Taupiri in the north, crossing flat farmland and the Waikato River before connecting with the completed Te Rapa section.

“The project was delivered using a Design and Construct model,” said Mercedes Santos, the Transport Agency’s project manager for the section. “This model provides greater flexibility to the contractor and enabled innovation and consequent cost savings.

“The health and safety record was a highlight of the project with very few incidents and those were of a minor

Page 7: Brochure - NZTA Waikato Construction

C O N S T R U C T I O N

www.nzta .govt .nz/pro jects /wa ikato-expressway 1 0 8

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

nature. The agency takes health and safety on site very seriously, and so we take great pride when our projects are delivered in safe work environments.”

Construction of the Ngaruawahia section began in September 2011 and included seven bridges, six of which are overbridges and a new 142-metre bridge over the Waikato River.

Santos expressed her gratitude for Fletcher Construction’s hard work on the project: “With their expertise and willingness to go the extra mile, we have shaved $50 million off the estimated cost and got the road open before Christmas.’’

The Rangiriri section, looking from north to south, will see SH1 shift away from

the historic village towards the Waikato River.

“Procuring the Te Rapa section through a competitive alliance has delivered a first-class roading project for all stakeholders.” – Te Rapa section Project Manager Peter Murphy

Cambridge section – HEB ConstructionConstruction began on the Cambridge section of the Waikato Expressway in

Page 8: Brochure - NZTA Waikato Construction

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

40 Tironui Rd, Takanini Auckland 2112, [email protected]:

0212 464 997OFFICE:

INGAL CIVIL PRODUCTS

www.ingalcivil.co.nz

September 2013 and the 16km stretch has an estimated cost of around $230 million. The project is expected to be completed by the end of 2016. HEB Construction is the contractor on the project.

Around 300 to 350 staff and subcontractors are on site at peak and to date 650,000 cubic metres of earth has been moved. There are eight bridges to be constructed in this stretch of the Expressway and on completion the Cambridge section will contain about 360,000

newly-planted trees. This section is predicted to reduce traffic through the picturesque rural town of Cambridge by up to 10,000 vehicles a day.

As the longest Expressway section that has been worked on to date, there have been several challenges for HEB Construction and the Transport Agency to overcome. One of the eight bridges is over the Karapiro Gully and is one of the biggest structures built in the region in recent times. The bridge

“The Rangiriri project has provided plenty of challenges.”– Rangiriri Project Manager Peter Murphy. “We are constructing a new Expressway through an area of national historic and cultural significance. Working with a good team and taking the time to thoroughly engage with all our stakeholders will reward us with a project that we can all be proud of.”

Page 9: Brochure - NZTA Waikato Construction

C O N S T R U C T I O N

www.nzta .govt .nz/pro jects /wa ikato-expressway 1 1 0

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

is 200 metres long and 40 metres above the bed of the gully, with piles between 40 and 60 metres deep.

“There have also been, and will continue to be, a number of temporary road closures and diversion routes that change through the course of the project development,” said Peter Simcock, Project Services Manager at the Transport Agency.

HEB Construction’s contractor representative Gary Budden has said that their good progress thus far wouldn’t have been possible without the goodwill of nearby residents and travellers.

“We’ve established a haul road along the site, closed some roads, put up temporary traffic signals, created a diversion road, and moved a lot of earth … and right through it all the people have been wonderful,” Budden said. “I think they really ‘get’ what we are doing here and what will be achieved.”

The Cambridge section of the Waikato Expressway starts south of

the existing Tamahere interchange and runs for 16km, ending just south of Cambridge where it connects with the existing SH1.

Rangiriri section – Fletcher Construction The Rangiriri section is also currently under construction. Work on this 4.8km project is scheduled for completion in 2016. The estimated cost of this section is $106 million; Fletcher Construction is the main contractor.

When complete, the section will connect the Longswamp and Ohinewai sections of the Expressway and improve connectivity between Auckland and Huntly and further south. The project is being delivered using an Early Contractor Involvement model (ECI), which allows for the contractor to be involved in the design phase and ensures designs developed are robust, constructible and are appropriately staged.

During the last summer season,

“This model provides greater flexibility to the contractor and enabled innovation and consequent cost savings.”

Page 10: Brochure - NZTA Waikato Construction

1 1 1 A u g u s t 2 0 1 4

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

more than 75,000 cubic metres of earth was moved each month. Like the other sections of the Waikato Expressway, bridges are a large part of the construction work. Current efforts on the project include stabilised earth-retaining walls at the interchange bridges and structural work at the Rangiriri bridge. The Expressway route is away from the current SH1 alignment which cuts through the historic Rangiriri village – scene of a fierce battle between Maori and colonial troops in 1863.

“The Rangiriri project has provided plenty of challenges,” said Peter Murphy, the Transport Agency’s project manager for this section. “We are constructing a new expressway through an area of national historic and cultural significance. Working with a good team and taking the time

to thoroughly engage with all our stakeholders will reward us with a project that we can all be proud of.”

Other challenges have included poor ground conditions and the quality of natural materials. The project crosses some very low-lying areas near the Waikato River. Significant ground improvement was required in order to support the embankment. The soils are of a very poor nature, and have been quite challenging for the contractors to work with.

Upcoming work – Huntly, Hamilton and Longswamp sections The Huntly section of the Waikato Expressway is in the physical works procurement stage, and will soon go to tender for detailed design and construction. The 15.4km project has a target contract award of April

“We’ve established a haul road along the site, closed some roads, put up temporary traffic signals, created a diversion road, and moved a lot of earth … and right through it all the people have been wonderful.” – Cambridge section HEB Construction’s Gary Budden “I think they really ‘get’ what we are doing here and what will be achieved.”

Page 11: Brochure - NZTA Waikato Construction

C O N S T R U C T I O N

www.nzta .govt .nz/pro jects /wa ikato-expressway 1 1 2

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

2015 and opening date of 2019. The estimated cost is around $470 million.

The section passes to the east side of the Huntly township and through the Taupiri Range, connecting to the completed Ngaruawahia section at Gordonton Road. It is expected to reduce traffic congestion and improve safety within the Huntly and Taupiri townships by significantly reducing through traffic.

The Hamilton section is in the secondary investigation and specimen design stage, with consenting processes under way. The 21.8km road – the longest stretch on the Expressway – has a target opening date of 2019 and is estimated at $790 million. It meets with the Ngaruawahia section in the north, runs to the east of Hamilton, and will connect to the existing Tamahere interchange and Cambridge section just south of Hamilton. Like the Huntly section, the Hamilton section is expected to reduce traffic congestion and improve safety on the local road network by reducing through traffic.

The 5.9km Longswamp section

is currently in the secondary investigation stage and has a target completion date of 2018. The $70 million project will link the already completed Mercer section to the north with the Rangiriri section to the south.

Collaboration with local Maori

Waikato Expressway map timeline

Jan 2014

Page 12: Brochure - NZTA Waikato Construction

1 1 3 A u g u s t 2 0 1 4

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

Maori are New Zealand’s indigenous people and they have strong cultural ties to the land. With a project of this magnitude, many Maori in the region are keenly interested in how projects will impact on land and waterways.

“There are areas along the length of the Expressway project, particularly around Rangiriri and Huntly, where there are sites sacred to Maori. As a consequence they have a very strong interest in the development of our projects and are keen to contribute in any way in order to ensure that the completed projects acknowledge the sacred nature of the sites,” said Simcock.

To ensure that Maori interests

are satisfactorily addressed, the Transport Agency engages closely with Waikato-Tainui, the main tribe in the region, and their representatives in the areas of the projects, and involves them throughout the investigation, design and construction phases of the projects.

Maori culture and custom have contributed to the projects’ landscaping designs. Wood carvings and story boards are erected at strategic locations along the Expressway to share Maori history. Maori are keenly interested in ensuring the natural vegetation is retained and, where possible, extended. They also

Opening day for the Ngaruawahia section in December 2013, with

traffic crossing the Waikato River.

Page 13: Brochure - NZTA Waikato Construction

C O N S T R U C T I O N

www.nzta .govt .nz/pro jects /wa ikato-expressway 1 1 4

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT

have a guardianship role when it comes to the protection of the surrounding waterways.

“All of the streams crossed by the Expressway flow into the Waikato River, and we have to comply with requirements to ensure that runoff from the Expressway does not contaminate any of those waterways,” commented Simcock.

The Transport Agency has strengthened its relationship with Maori through the Expressway project. And because of the project’s length that has meant involving various sub-tribes or iwi.

That sort of collaboration and consultation has been a feature of Expressway sections completed or under way, and is already being woven into the remaining three sections as they come on stream.

“With a project of this size a lot of effort goes into designation, investigation and design, getting consents, tendering etc and then getting on with the build. But if you have people on board and involved every aspect is made easier,” Simcock said.

Company Information

I N D U S T RY

NZ Transport Agency /

State Highways

H E A D Q U A RT E R S

Wellington, New

Zealand

F O U N D E D

2009

P R O D U C T S /

S E R V I C E S

The Waikato Expressway

is one of the seven state

highways called “Roads of

National Significance” in New

Zealand. It has significant

benefits, including reducing

travel times between

Auckland and Tirau (South

Cambridge) by 35 minutes

(total travel time now two

hours), significantly reducing

the number of fatal and

serious injuries crashes and

enabling economic growth.

When complete, this 102km continuous divided four-lane highway will allow for a safer, quicker way to get freight and people through New Zealand’s upper North Island.

Page 14: Brochure - NZTA Waikato Construction

WAIKATO EXPRESSWAY PROJECT – NZ TRANSPORT AGENCY

Address 50 Victoria Street, Private Bag 6995

Wellington

New Zealand

Tel. +64 4 894 5400 [email protected]

www.nzta.govt.nz/projects/waikato-expressway/