brentswingbridge · 2017. 6. 2. · spt/cpt values comments made ground concreteandbrick...
TRANSCRIPT
Amey Report Template – CON-GEN/Template/001/01
Brent Swing BridgeOptions ReportDocument reference: CO04300132/02
Revision: 03
Issued: May 2014
Service is our passion. People, our strength
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - i - Service is our passion. People, our strengthIssued: May 2014
Executive Summary
The purpose of this report is to consider alternative options for replacing the existing Brent Swing Bridge,Faversham, Kent. The options considered are as follows:
Option 1 Fixed bridge
Option 2 Swing bridge
Option 3 Lifting bridge
Option 4 Dutch style bascule bridge
Option 5 Major maintenance and strengthening
In developing the estimated costs for the above options, account has been taken for the need to repairand strengthen the existing abutments and the provision of a temporary diversion route via Brent Hill andDavington Hill.
Option 1
The least cost option is a reinforced concrete bridge utilising precast elements for speed of construction.
A period of 6 weeks will be required for the construction works phase with a road closure of 4 weeks.
The estimated cost for the construction for this option is £390,000.
Option 2
The swing bridge will comprise a steel bridge deck supported on a strengthened south abutment similar inform to the existing bridge.
A period of 13 weeks will be required for the construction works phase with a road closure of 12 weeks.
The estimated cost for the construction for this option is £970,000.
Option 3
The lifting bridge will require new foundations to be constructed behind the existing north abutment andwill comprise a steel bridge deck hinged at the north end.
A period of 12 weeks will be required for the construction works phase with a road closure of 11 weeks.
The estimated cost for the construction for this option is £1,150,000.
Option 4
The Dutch style bascule bridge will require new foundations to be constructed behind the existing northabutment and will comprise a steel bridge deck hinged at the north end with steel A frames andcounterweight above road level.
A period of 13 weeks will be required for the construction works phase with a road closure of 12 weeks.
The estimated cost for the construction for this option is £1,210,000
Option 5
Replacement of the existing opening mechanism and replacement with new. Strengthening of theexisting superstructure and abutments.
A period of 11 weeks will be required for the construction phase with a road closure for 9 weeks.
The estimated cost for the construction of this option is £642,000.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - ii - Service is our passion. People, our strengthIssued: May 2014
Location Plan
The site plan has been reproduced from an Ordnance Survey map, with the permission of Her
Majesty s Stationery Office, Crown copyright reserved licence No. 100019238. 2013.
Figure 1: Brent Swing Bridge
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - iii - Service is our passion. People, our strengthIssued: May 2014
Contents
1 Introduction .................................................................................................................. 1
1.1 Client brief ...................................................................................................................... 1
1.2 Report Revision 02......................................................................................................... 1
1.3 Report Revision 03......................................................................................................... 1
1.4 Aims of the feasibility ..................................................................................................... 1
1.5 Background .................................................................................................................... 1
1.6 Detailed Description of the Structure ............................................................................. 2
1.7 Photographs of the structure.......................................................................................... 3
2 Design Considerations ................................................................................................ 4
2.1 General........................................................................................................................... 4
2.2 Foundations and Abutments .......................................................................................... 4
2.3 Temporary Road Bridge................................................................................................. 4
2.4 Land Acquisition............................................................................................................. 5
2.5 Site Compound .............................................................................................................. 5
2.6 Road closures ................................................................................................................ 5
2.7 Pedestrians and Cyclists................................................................................................ 5
2.8 Power Supply ................................................................................................................. 6
2.9 Statutory Undertakers Plant ........................................................................................... 6
2.10 Opportunities for Enhancement ..................................................................................... 6
2.11 Design Criteria ............................................................................................................... 7
3 Options.......................................................................................................................... 8
3.1 General........................................................................................................................... 8
3.2 Option 1: Fixed Bridge ................................................................................................... 8
3.3 Option 2: Swing Bridge ................................................................................................ 10
3.4 Option 3: Lifting Bridge................................................................................................. 12
3.5 Option 4: Dutch Style Bascule Bridge.......................................................................... 14
3.6 Option 5: Major Maintenance and Strengthening ........................................................ 17
3.7 Cost Summary ............................................................................................................. 19
4 Traffic Impact Assessment ....................................................................................... 20
4.1 Traffic Impact Assessment........................................................................................... 20
5 Environmental considerations ................................................................................. 21
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - iv - Service is our passion. People, our strengthIssued: May 2014
5.1 Emissions and Waste................................................................................................... 21
5.2 Air Quality..................................................................................................................... 21
5.3 Archaeology and Cultural Heritage .............................................................................. 21
5.4 Landscape.................................................................................................................... 21
5.5 Ecology and Nature Conservation ............................................................................... 22
5.6 Geology and Soils ........................................................................................................ 22
5.7 Material Use ................................................................................................................. 22
5.8 Noise and Vibration...................................................................................................... 23
5.9 Drainage and the Water Environment.......................................................................... 23
6 Geotechnical Considerations ................................................................................... 24
6.1 Background Geotechnical Information......................................................................... 24
6.2 Preliminary Geotechnical Advice ................................................................................. 25
6.3 Background information ............................................................................................... 25
7 Operation, Inspection and Maintenance.................................................................. 27
7.1 Operation of Moveable Bridge ..................................................................................... 27
7.2 Inspection and Maintenance ........................................................................................ 27
The above factors and the periods for inspection and maintenance have beenincluded in the appraisal of the whole life costs for each of the options. ..................... 28
7.3 Design Considerations ................................................................................................. 28
7.4 Health and Safety......................................................................................................... 28
8 Stakeholders............................................................................................................... 29
8.1 Stakeholder Consultation ............................................................................................. 29
8.2 Principal stakeholders .................................................................................................. 29
9 Discussion and Recommendations ......................................................................... 30
9.1 Cost comparison .......................................................................................................... 30
9.2 Time of construction..................................................................................................... 30
9.3 Operation and maintenance......................................................................................... 30
9.4 Advantages and Disadvantages .................................................................................. 30
9.5 Recommendations ....................................................................................................... 30
Appendix A Cost Estimate Coverage A-1
Appendix B Options Drawings B-1
Appendix C Temporary Diversion Route C.1
Appendix D M&E Inspection Report D.2Appendix E Bibliography E.1
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 1 - Service is our passion. People, our strengthIssued: May 2014
1 Introduction
1.1 Client brief
A feasibility options study for the replacement of Brent Swing Bridge, Faversham, Kent has
been requested by KCC. The study is to consider fixed, swing, lifting bridge and Dutch style
bascule options for the bridge deck replacement and will include estimated capital and Whole
Life Costs for each option. The report has been reviewed by the Brent Bridge Working Group
and will be submitted to Brent Bridge Steering Group for their consideration.
1.2 Report Revision 02
Revision 02 of the report incorporated the comparison of a Dutch style bascule bridge (option 4)
with the previously considered options.
The estimated costs for all options were reviewed and the report was updated to include more
detailed costs for the mechanical and electrical elements.
1.3 Report Revision 03
This version of the report, revision 03, incorporates option 5, proposed strengthening and major
maintenance.
1.4 Aims of the feasibility
The purpose of this study is to consider practicability and engineering buildability of the
alternative options taking into account the reuse of parts of the existing facility.
The report will review the operation and maintenance of the alternative options taking into
account the costs for ongoing maintenance.
This report does not consider the Acts of Parliament relating to the navigation rights at this
location, similarly it does not consider the responsibilities for operation and maintenance.
1.5 Background
The existing bridge is a two span structure carrying Bridge Road over Faversham Creek in
Faversham, Kent. It was originally constructed in 1881 to replace a sliding footbridge. The
superstructure of the bridge was strengthened in 1941 and replaced again in 1976.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 2 - Service is our passion. People, our strengthIssued: May 2014
The bridge ownership is uncertain but it is believed that the hydraulic machinery and opening
mechanism is owned by Medway Ports Authority (now owned by Peel Ports) which is
responsible for navigation in the Creek. Kent County Council has an interest in the deck as it
supports a highway crossing.
Structural assessment of the bridge, carried out in 1993 and 2012, determined that the
superstructure does not have the capacity to support dead and superimposed dead loads when
in the open position. It was also noted in the 2012 assessment report that; further loss of
section to critical main steel members had occurred, however this had not reduced the
capability of the bridge to carry current highway loading and a weight restriction was not
required at this time.
With the cessation of commercial water borne traffic and the assessment result, it is understood
that the bridge has not been opened to boats since the late 1980’s/early 1990’s.
1.6 Detailed Description of the Structure
For the purposes of this report it is assumed that the bridge lies in a south to north direction.
Previous reports and records indicate that the substructure for the south abutment is formed by
mass concrete abutments supported on piled and spread foundations. No details are available
in the structure records for the north abutment.
The superstructure is a continuous deck formed of two steel girders and nine transverse beams.
The deck pivots about a pintle bearing located on top of the south abutment.
In the closed position the deck is a continuous two span structure, the tail end of the deck is
supported at the rear of the south abutment, an intermediate support at the front of the south
abutment and the deck nose is supported on the north abutment. When in the “open” position
the deck becomes a two span cantilever structure supported only by the south abutment on the
pintle bearing and the track at the tail end of the deck.
There are fenders fixed to the abutments and a pair of sluice gates at the west end of the
abutments.
The main elements of the superstructure are two 610 × 229 × 113 kg steel girders. There are
nine 356 × 127 × 39 kg steel beams fixed transversely above the lower flanges of the girders,
evenly spaced along the length of the deck. The deck surface is supported on six continuous
longitudinal inverted T beams on the transverse beams. The side cantilevers, supporting the
footways and parapets, are formed of nine built-up steel beams each side with single
longitudinal inverted T beams fixed at the top. The running surfaces of the road and footways
are formed of 15 mm thick steel deck plates.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 3 - Service is our passion. People, our strengthIssued: May 2014
The swing mechanism operates by lifting the deck off of the pier and north abutment using a
kentledge weight system at the south abutment and a hydraulic jack in the pintle between the
south abutment and the pier. The deck is then rotated about the pintle.
1.7 Photographs of the structure
Plate 1: Downstream Elevation
Plate 2: View across bridge from south
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 4 - Service is our passion. People, our strengthIssued: May 2014
2 Design Considerations
2.1 General
A detailed inspection of the bridge has not been undertaken as part of this feasibility study. The
assumptions made in this report are based upon the findings and recommendations provided in
the previous reports undertaken for KCC.
The mechanical and electrical (M&E) equipment was inspected by a specialist employed by
Amey on 17th April 2014. The inspection report concluded that the M&E equipment is
unserviceable and unsafe and should not be operated. See Appendix D.
2.2 Foundations and Abutments
Inspection records indicate that the existing abutments and their foundations are in fair
condition. However the Principal Inspection (PI) report (dated 2011) records that there is
differential settlement apparent at the north abutment.
It is not known whether the apparent settlement is an ongoing issue or whether it occurred
historically, further investigation is required before it can be determined whether the existing
abutments can be utilised to support the proposed bridge options. An allowance of £80,000 for
underpinning of the foundations of the north abutment has been made for each of the
alternative options.
The 2011 PI report also notes that the bearing pad to west end of the north abutment is
displaced. It is proposed that new bearing seats will be provided therefore this defect will be
eliminated as part of the design for the relevant alternative options.
The abutment walls exhibit eroded joints, cracks in the masonry and brickwork and isolated loss
of brick faces due to erosion. These repairs should be undertaken in conjunction with all four
proposed alternative options and costs of £23,000 have been allowed for undertaking this work
in each of the construction works estimates.
2.3 Temporary Road Bridge
Consideration has been given to providing a temporary bridge to minimise traffic disruption
whilst the construction works are being carried out. However there is insufficient space to allow
for the installation of a bridge at the existing bridge site.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 5 - Service is our passion. People, our strengthIssued: May 2014
Alternative locations for a temporary bridge have also been looked into, these would require the
diversion of traffic and significant civil engineering works to achieve a suitable solution. The
most likely locations would be upstream of the existing bridge, but the anticipated cost for
providing the temporary structure is disproportionate to the permanent replacement bridge
therefore it is not considered to be viable.
2.4 Land Acquisition
A land search has not been undertaken for the bridge replacement options. It is understood that
all land within the footprint of the existing structure is either designated as highway or owned by
the Port Authority.
All four of the alternative options are within the existing highway boundaries therefore no
additional land is required for the permanent works.
2.5 Site Compound
Space will be required for a site compound to accommodate site offices, messes and stores etc.
There is an area of land at the north-west corner of the bridge which could be used for this
purpose. Ownership of this area of land will need to be determined and the appropriate
arrangements agreed before commencement of the works.
2.6 Road closures
The proposed bridge replacement works will require a temporary road closure for part of the
duration of the construction works. A diversionary route can be provided via Brent Road and
Brent Hill, details of the proposed diversion are shown in Appendix C.
In addition, once the bridge has been reinstated to allow opening to river traffic there will be an
impact upon the local road network albeit only for a short period (not in excess of 10 minutes
per bridge opening assuming marine traffic can be controlled effectively).
There are currently no available traffic flow figures for Brent Road therefore an assessment of
the effect of these closures is not known.
Closure of the road to facilitate the works will require significant local consultation as the project
progresses.
2.7 Pedestrians and Cyclists
The existing bridge is the main route for pedestrians from the Brents area of Faversham to the
town centre, the bridge is also part of the National Cycle Route 1 (NCR1) which runs from
Dover to Scotland and crosses the bridge.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 6 - Service is our passion. People, our strengthIssued: May 2014
Access for pedestrians and cyclists will need to be maintained throughout the period of
construction. This could be achieved either by the provision of a footbridge adjacent to the
existing swing bridge or alternatively providing a pedestrian diversion via Flood Lane. Providing
a footbridge through the construction site will have significant health and safety implications and
the preferred alternative would be to divert pedestrians via Flood Lane. Improvements will be
required in Flood Lane to provide a suitable footway.
A Public Right of Way (PRoW) starts at the north-east corner of the bridge and runs along the
north bank of the creek to the east of the bridge. It is not envisaged at this stage the PRoW will
be affected by the construction works however it needs to be considered in future development
of the project.
2.8 Power Supply
It has been assumed that electricity supplies are available at either side of the bridge and that
these will be sufficient to power the plant and equipment required for the moveable bridge
options.
The condition, type and location of electricity supply will need to be confirmed for the
subsequent stage of design development.
Costs for connection to the existing supply have been allowed for in the options cost estimates
but no cost allowance has been made for providing new power supply.
2.9 Statutory Undertakers Plant
Responses to notices have been received from all of the statutory undertakers.
None are likely to be affected by any of the alternative options being considered.
2.10 Opportunities for Enhancement
Parts of the existing bridge are to be retained and brickwork repairs will be required. At this time
there would be the potential for replacing previous repairs with materials more sympathetic to
the original structure.
The three existing buildings adjacent to the bridge which house the existing M&E equipment
and controls for the bridge and lock gates may no longer be required, in whole or part. The
buildings no longer required for use could be demolished allowing greater space around the
bridge.
There would be the added benefit of widening the footways, improving safety for pedestrians.
However formal crossing points may be required at both ends of the bridge to allow pedestrians
to cross the road safely where the footway is only being widened on one side.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 7 - Service is our passion. People, our strengthIssued: May 2014
There is currently no fendering provided on either the upstream or downstream approaches to
the bridge. The consideration of use of the bridge by river traffic is not included in the scope of
this feasibility report and the cost for providing fendering has not been included in the option
costs. It is recommended that this should be considered if either of the moveable bridge options
is taken forward, the requirements for navigation lighting should also be considered.
2.11 Design Criteria
All options minimum 3.0 m wide carriageway
Minimum desirable footway width 1500mm
Minimum offset to parapet 0.45 m
Type N1 parapets with vertical infill to be used for options 1 to 4
Single-way traffic to be maintained as existing usage
Minimum headroom – 5.70 m
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 8 - Service is our passion. People, our strengthIssued: May 2014
3 Options
3.1 General
All of the following options include costs for underpinning of the abutment foundations and
significant repairs to the abutment wall brickwork and masonry.
Also included is the need to provide temporary access for pedestrians, the cost for providing a
temporary diversion via Flood Lane has been included in each of the options.
Tidal variations will have a significant effect on the construction works, careful planning will be
required to programme the individual work phases to avoid disruption to the works.
3.2 Option 1: Fixed Bridge
3.2.1 Description of the proposed works
This alternative comprises the construction of a single span square deck over Faversham
Creek.
The bridge will utilise the existing abutments to support a precast reinforced concrete beam and
in situ deck slab. The deck will be seated upon precast reinforced concrete bank seats
constructed on top of the existing abutments.
Use of precast reinforced concrete elements has been selected for this option to reduce the
construction period thereby reducing the length of time required for closure of the road
compared with an in situ reinforced concrete deck form of construction.
Fill will be required to support both approaches to the bridge.
Alternative designs for the fixed bridge span have been investigated. The installation of a steel
deck would reduce the period for the site construction works, although its cost would be similar
to that for the precast beam option, the durability would be less than the concrete deck and the
whole life costs would be greater therefore this option has not been developed further.
3.2.2 Drawings and sketches
A sketch showing details of the proposed structure is included in Appendix B.
3.2.3 Estimated costs for design and construction
A summary of the items included in the following cost estimate is included in Appendix A.
The estimated scheme design and construction cost are detailed below:
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 9 - Service is our passion. People, our strengthIssued: May 2014
ItemCost£
Preliminaries 51000
Site Clearance 55500
Fencing 1000
Road Restraint Systems 8000
Earthworks 13500
Pavements 11500
Kerbs, Footways and Paved Areas 5500
Traffic Signs and Road markings 500
Street Lighting 500
Piling and Embedded Retaining Walls 96000
Structural Concrete 62000
Waterproofing to Structures 2000
Bridge Bearings 9500
Bridge Expansion Joints 10500
Brickwork, Blockwork & Stonework 23500
Contingencies (10%) 35050
Total 385,550
3.2.4 Whole life costs
The whole life costs for option 1 are as follows:
Option 1 60 Years 120 Years
Net Present Value (£) 431,000 451,000
3.2.5 Outline timescale for delivery
It is estimated that the bridge will take up to 6 weeks to construct.
If weekend working is permitted by the local authority it may be possible to reduce the
construction period for the bridge and hence reduce the amount of time required for closure of
the road. The programme indicates that a road closure will be required for approximately four
weeks.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 10 - Service is our passion. People, our strengthIssued: May 2014
3.2.6 Advantages
The main advantages of this option is that it will be the cheapest option to construct and
maintain it also has the shortest construction programme therefore is the least disruptive to the
travelling public and local businesses.
The bridge is located within a marine environment and is likely to be subjected to occasional
high water levels. Due to its reinforced concrete form of construction option 1 will be more
durable, in this type of environment, than the other options considered.
3.2.7 Disadvantages
The fixed bridge option will limit the size of watercraft on the navigable waterway and would
prevent the upper creek from effectively functioning as a navigable waterway.
3.3 Option 2: Swing Bridge
3.3.1 Description of the proposed works
The swing bridge alternative will be a like for like replacement of the existing structure but
increased in width.
For closure of the bridge; vehicle, cycle and pedestrian traffic will be controlled by automatic
lights and barriers at either end of the deck.
The bridge superstructure will be of steel construction similar in form to the existing structure, it
will pivot about a new pintle bearing located in the same position as the existing bearing.
The top of the south abutment will be reconstructed as a reinforced concrete slab this will
ensure safe access to inspect and maintain the new superstructure and mechanical and
electrical equipment. The new abutment slab will support the pintle bearing, tail wheel running
track and rear hydraulic wedges and jacking system. Around its perimeter the abutment slab will
be provided with a reinforced concrete wall perimeter this will protect the structure from sea
water ingress and protect the water environment from possible hydraulic oil spillages.
Hydraulic jacks and the motor drive unit will be located at the rear end of the tail span with
hydraulic operated stabilising wedges at the tail end of the deck.
Movement of the bridge deck will be automatically controlled in the following sequence:
Stop cars, pedestrians and cyclists
Release tail wedges and lower deck on the rear jacks so load is taken up on the tail
wheels
Engage motor drive and manoeuvre bridge deck into open position
Apply braking system and arrest movement of deck
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 11 - Service is our passion. People, our strengthIssued: May 2014
Closing the bridge will be a reversal of the above procedure.
3.3.2 Drawings and sketches
A sketch showing details of the proposed structure is included in Appendix B.
3.3.3 Estimated initial capital costs of carrying out the works
A summary of the items included in the following cost estimate is included in Appendix A.
The estimated scheme design and construction costs for option 2 are detailed below:
ItemCost
£
Preliminaries 56500
Site Clearance 55500
Fencing 1000
Road Restraint Systems 10000
Drainage and Service Ducts 2500
Earthworks 2500
Pavements 11000
Kerbs, Footways and Paved Areas 5000
Traffic Signs and Road markings 500
Street Lighting 500
Electrical 68000
Piling and Embedded Retaining Walls 96000
Structural Concrete 44000
Protection of Steelwork Against Corrosion 15000
Waterproofing to Structures 2000
Bridge Expansion Joints 21000
Brickwork, Blockwork & Stonework 23500
Special Structures Designed by the Contractor
Breakdown of costs:
• Superstructure design, fabrication and installation:
• Fabrication and supply of M&E equipment
• Design, Installation and commissioning of M&E equipment
460500
(175000)
(125500)
(160000)
Contingencies (10%) 87500
Total 962,500
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 12 - Service is our passion. People, our strengthIssued: May 2014
3.3.4 Whole life costs
The whole life costs for option 2 are as follows:
Option 2 60 Years 120 Years
Net Present Value £1,246,000 £1,379,000
3.3.5 Outline timescale for delivery
It is estimated that the bridge will take up to 13 weeks to construct with a road closure required
for approximately 12 weeks.
3.3.6 Advantages
In case of a mechanical failure during either opening or closing of the bridge it would be
relatively easy to manually manoeuvre the bridge back into position.
This option would provide navigation access to the upper basin of Faversham Creek.
3.3.7 Disadvantages
There will be ongoing costs for management and maintenance of the mechanical and electrical
equipment.
3.4 Option 3: Lifting Bridge
3.4.1 Description of the proposed works
This alternative will require the construction of a large retraction pit to accommodate the lifting of
the deck at the tail end of the bridge. Due to the extent of the existing south abutment
foundations and the proximity to existing buildings at the south end of the bridge it is considered
that the most practicable location for the retraction pit is behind the existing north abutment. The
pit will need to be sufficiently large enough to allow for the movement of the tail end of the deck
and to accommodate the bearings and hydraulic lifting equipment.
The bridge superstructure will be of steel construction similar to that proposed for the swing
bridge option. Raising the deck will be achieved by hydraulic rams pushing up on the soffit of
the deck just in front of the pivot resulting in the main span lifting clear of the water way.
For closure of the bridge; vehicle, cycle and pedestrian traffic will be controlled by automatic
lights and barriers at either end of the deck.
Operation of the bridge will be automatically controlled in the following sequence:
Stop road, cycle and pedestrian traffic
Engage hydraulic rams and raise bridge deck into open position
The control system slows the bridge down as it reaches the fully raised position.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 13 - Service is our passion. People, our strengthIssued: May 2014
Closing the bridge will be a reversal of the above procedure. The deck will land on a shock
absorber to bring the deck to a controlled stop as it reaches the fully lowered position.
3.4.2 Drawings and sketches
A sketch showing details of the proposed structure is included in Appendix B.
3.4.3 Estimated initial capital costs of carrying out the works
A summary of the items included in the following cost estimate is included in Appendix A.
The estimated scheme design and construction costs for option 3 are detailed below:
ItemCost£
Preliminaries 66000
Site Clearance 55500
Fencing 1000
Road Restraint Systems 8000
Drainage and Service Ducts 2500
Earthworks 12500
Pavements 11000
Kerbs, Footways and Paved Areas 5000
Traffic Signs and Road markings 500
Street Lighting 500
Electrical 68000
Piling and Embedded Retaining Walls 180500
Structural Concrete 22500
Protection of Steelwork Against Corrosion 12000
Waterproofing to Structures 2500
Bridge Expansion Joints 21000
Brickwork, Blockwork & Stonework 23500
Special Structures Designed by the Contractor
Breakdown of costs:
• Superstructure design, fabrication and installation:
• Fabrication and supply of M&E equipment
• Design, Installation and commissioning of M&E equipment
547000
(150000)
(247000)
(150000)
Contingencies (10%) 104000
Total 1,143,500
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 14 - Service is our passion. People, our strengthIssued: May 2014
3.4.4 Whole life costs
The whole life costs for option 3 are as follows:
Option 3 60 Years 120 Years
Net Present Value £1,455,000 £1,537,000
3.4.5 Outline timescale for delivery
It is estimated that the bridge will take up to 12 weeks to construct with a road closure required
for approximately 11 weeks.
3.4.6 Advantages
This option would provide navigation access to the upper basin of Faversham Creek.
3.4.7 Disadvantages
Deep foundations required for retraction pit will require special measures for confined space
working during construction and maintenance. In addition continuous pumping is likely to be
required to ensure the construction works are free of water.
There will be ongoing costs for management and maintenance of the mechanical and electrical
equipment.
3.5 Option 4: Dutch Style Bascule Bridge
3.5.1 Description of the proposed works
This alternative is similar to option 3 however the counterbalance for the deck will be positioned
at high level carried by balance beams located on each side of the bridge. The balance beams
will be supported on steel “A” frames.
The bridge superstructure will be of steel construction similar to that proposed for the previous
bascule bridge option. Raising the deck will be achieved by hydraulic rams pushing up on the
balance beams located in front of the “A” frame pivot resulting in the main span lifting clear of
the water way.
Due to the extent of the existing south abutment foundations and the proximity to existing
buildings at the south end of the bridge it is considered that the most practicable location for the
retraction pit is behind the existing north abutment. The pit will need to be sufficiently large
enough to allow for the movement of the tail end of the deck and to accommodate the bridge
bearings.
For closure of the bridge; vehicle, cycle and pedestrian traffic will be controlled by automatic
lights and barriers at either end of the deck.
Operation of the bridge will be automatically controlled in the following sequence:
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 15 - Service is our passion. People, our strengthIssued: May 2014
Stop road, cycle and pedestrian traffic
Engage hydraulic rams and raise bridge deck into open position
The control system slows the bridge down as it reaches the fully raised position.
Closing the bridge will be a reversal of the above procedure. The deck will land on a shock
absorber to bring the deck to a controlled stop as it reaches the fully lowered position.
3.5.2 Drawings and sketches
A sketch showing details of the proposed structure is included in Appendix B.
3.5.3 Estimated initial capital costs of carrying out the works
A summary of the items included in the following cost estimate is included in Appendix A.
The estimated scheme design and construction costs for option 4 are detailed below:
ItemCost
£
Preliminaries 66000
Site Clearance 55500
Fencing 1000
Road Restraint Systems 8000
Drainage and Service Ducts 2500
Earthworks 7000
Pavements 11000
Kerbs, Footways and Paved Areas 5000
Traffic Signs and Road markings 500
Street Lighting 500
Electrical 68000
Piling and Embedded Retaining Walls 180500
Structural Concrete 12000
Protection of Steelwork Against Corrosion 14000
Waterproofing to Structures 3000
Bridge Expansion Joints 21000
Brickwork, Blockwork & Stonework 23000
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 16 - Service is our passion. People, our strengthIssued: May 2014
ItemCost£
Special Structures Designed by the Contractor
Breakdown of costs:
• Superstructure design, fabrication and installation:
• Fabrication and supply of M&E equipment
• Design, Installation and commissioning of M&E equipment
614500
(190000)
(259500)
(165000)
Contingencies (10%) 109000
Total 1,202,000
3.5.4 Whole life costs
The whole life costs for option 4 are as follows:
Option 4 60 Years 120 Years
Net Present Value £1,531,000 £1,655,000
3.5.5 Outline timescale for delivery
It is estimated that the bridge will take up to 13 weeks to construct with a road closure required
for approximately 12 weeks.
3.5.6 Advantages
This option would provide navigation access to the upper basin of Faversham Creek.
3.5.7 Disadvantages
Deep foundations required for retraction pit will require special measures for confined space
working during construction and maintenance. In addition continuous pumping is likely to be
required to ensure works are free of water.
Maintenance of the hydraulic cylinders and balance beam bearings will entail working at height.
In addition to gain access to these elements it will be necessary to close the road to traffic which
may require maintenance work being undertaken outside of normal working hours (i.e. at during
night time road closure).
There will be ongoing costs for management and maintenance of the mechanical and electrical
equipment.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 17 - Service is our passion. People, our strengthIssued: May 2014
3.6 Option 5: Major Maintenance and Strengthening
3.6.1 Description of the proposed works
This option would require a complete refurbishment of the bridge and strengthening of the
lateral steel joists to ensure that the structure could bear the dead and superimposed dead
loads when in an open position. It would also require replacement of the M&E equipment,
which was last tested in June 2006.
The refurbishment and major maintenance of the bridge would require repainting, resurfacing,
abutment strengthening, replacement of the bearings and strengthening of the transverse
members and kentledge area. This option would not include containments parapets.
It would be necessary to close Bridge Road while the works were carried out and a temporary
diversion for HGV traffic and pedestrians provided. This would require accommodation works
on Brent Road, Brent Hill and Flood Lane.
An inspection of the M&E equipment has been carried out by Amey. The inspection found that
whilst the equipment appears to be in reasonably good condition externally, its operational
integrity could not be determined. It was noted that the bridge deck has moved toward the north
abutment, probably due to braking effects from heavy vehicles, and the lifting piston and pintle
bearing are misaligned.
The inspection highlighted safety issues regarding operation of and the protection around the
pressure weights and operation of the pump wheel. The report also cast doubt on the level of
manual handling required to open the bridge. The report concluded that due to these
uncertainties and doubts regarding the method of closing the road for opening, the bridge in its
current condition should remain closed to navigation.
Previous preliminary design proposals by Jacobs have also recommended that access to the
kentledge area and operating mechanisms for inspection and maintenance should be improved
by the provision of an access manhole in the deck of the south span and a gallery area on the
south abutment.
It is estimated that the bridge has a remaining life of 40 years, after which it will require
replacement. This has been included in the whole life cost shown below, assuming a
replacement cost similar to that of option 2.
3.6.2 Drawings and sketches
A drawing showing details of the existing structure is included in Appendix B.
3.6.3 Estimated initial capital costs of carrying out the works
A summary of the items included in the following cost estimate is included in Appendix A.
The estimated scheme design and construction costs for option 5 are detailed below:
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 18 - Service is our passion. People, our strengthIssued: May 2014
ItemCost£
Preliminaries 44000
Site Clearance 1000
Fencing 1000
Pavements 11000
Traffic Signs and Road markings 500
Electrical 68000
Piling and Embedded Retaining Walls 96000
Protection of Steelwork Against Corrosion 31500
Waterproofing to Structures 2000
Bridge Bearings 20000
Brickwork, Blockwork & Stonework 23500
Special Structures Designed by the Contractor
Breakdown of costs:
• Fabrication and supply of M&E equipment
• Design, Installation and commissioning of M&E equipment
285500
(125500)
(160000)
Contingencies (10%) 58000
Total 642,000
3.6.4 Whole life costs
The whole life costs for option 5 are as follows:
Option 5 60 Years 120 Years
Net Present Value £1,267,000 £1,365,000
3.6.5 Outline timescale for delivery
It is estimated that the strengthening and maintenance works will take up to 11 weeks to
construct with a road closure required for approximately 9 weeks.
3.6.6 Advantages
In case of a mechanical failure during either opening or closing of the bridge it would be
relatively easy to manually manoeuvre the bridge back into position.
This option would provide navigation access to the upper basin of Faversham Creek.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 19 - Service is our passion. People, our strengthIssued: May 2014
3.6.7 Disadvantages
There will be ongoing costs for management and maintenance of the mechanical and electrical
equipment. The maintenance of any reused parts of the existing M&E equipment might require
a higher number of site visits than for options 2, 3 and 4.This option does not provide any
improvements to the bridge i.e. widened footways and carriageway; containment parapets;
replacement pedestrian fencing.
3.7 Cost Summary
The estimated budget costs and whole life costs are summarized in the table below.
Option DescriptionBudget works
estimate60 year WLC 120 year WLC
1 Single span fixed bridge £385,550 £431,000 £451,000
2 Replacement swing bridge £962,500 £1,246,000 £1, 379,000
3 Lifting bridge £1,143,500 £1,455,000 £1,537,000
4 Bascule bridge £1,202,000 £1,531,000 £1,655,000
5 Maintenance and strengthening £642,000 £1,267,000 £1,365,000
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 20 - Service is our passion. People, our strengthIssued: May 2014
4 Traffic Impact Assessment
4.1 Traffic Impact Assessment
Initial consultation with KCC’s officer responsible for Swale District, has been undertaken to
discuss the scope for the Traffic Impact Assessment (TIA).
It was agreed at the scoping meeting that a fully classified traffic count should be undertaken on
the existing bridge to determine existing traffic levels during peak periods. This work isn’t
required at this feasibility stage of project development but will be required for subsequent
preliminary and detail design stages. This would allow an initial appraisal of the likely impacts of
closing the bridge for the following scenarios:
Full closure of the bridge during the construction period;
Temporary closure of the bridge when operation has been reinstated.
It was also agreed that following this initial appraisal a further meeting would be held with KCC
to determine whether any further assessment would be required to determine potential impacts
on surrounding junctions and/or diversion routes.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 21 - Service is our passion. People, our strengthIssued: May 2014
5 Environmental considerations
An initial environmental scoping assessment has been undertaken as part of this feasibility
study.
The following sections are a brief summary of the findings of the desk study which will need to
be considered and addressed by the designer and contractor at the subsequent stages of the
scheme’s development.
5.1 Emissions and Waste
As it is likely that the overall cost of the works for this scheme will exceed £300,000 a site waste
management plan (SWMP) will be required.
5.2 Air Quality
The site does not lie within an Air Quality Management Area (AQMA).
The works will take place on Bridge Road; the site is therefore impacted by vehicle exhaust
emissions and the local residents could be affected.
5.3 Archaeology and Cultural Heritage
The bridge site lies within the Faversham designated conservation area and a search of the
English Heritage website indicates that there are several Listed Buildings located within 300m of
the site. However the search has not identified any Scheduled Ancient Monuments, Registered
Parks and Gardens, Registered Battlefields or World Heritage Sites within the search radius.
Further assessment will be required for subsequent stages of scheme development and the
local Conservation Officer should be contacted to determine as to whether consent is required
as the works lie within a designated conservation area.
5.4 Landscape
The site does not lie within an Area of Outstanding Natural Beauty (AONB).
The scheme will involve aesthetic changes, although the visual impact will vary depending on
what option is chosen. Options 3 and 4 both have visual impact due the lifting of the bridge deck
during the opening phase. Option 4 will have the greatest visual impact due to the elements
which will be permanently visible further afield
The site lies in an area covered by the Landscape Information System (K-LIS) and is
characterised as Eastern Swale Marshes. This landscape character area commonly has the
following features:
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 22 - Service is our passion. People, our strengthIssued: May 2014
Remote, wild and exposed;
Broad skies. Pervasive influence of sea and sky. Creeks, ditches, sea walls.
Grazing marsh; wild birds and grazing animals;
Creekside townscape and waterside buildings; and
Poorly managed fences. Intrusion of power lines.
The site lies within a relatively low lying area and it is predicted that landscape impacts will vary
depending on which bridge design option is chosen. It could be argued that options 3 and 4
(lifting bridge options) will have the most impact upon local landscape as both visible further
afield when raised and option 4 will have structural elements permanently visible.
5.5 Ecology and Nature Conservation
There are no Special Areas of Conservation (SACs) within the a 2km radius of the site however
the Swale is a Site of Special Scientific Interest (SSSI), Special Protection Area (SPA) and is
also a Ramsar. The south bank of the Swale is also a Local Nature Reserve (LNR).
N.B. SPA’s and Ramsar Sites are classed as Designation European Conservation Sites.
Natural England will need to be consulted at subsequent stages of scheme design
development.
According to the National Biodiversity Network (NBN) there are records of bats being present
within the vicinity of the proposed works. Before any works are undertaken an ecologist should
visit the site to determine whether further surveys are required in relation to the presence of
bats.
5.6 Geology and Soils
Further assessment of contamination of the proposed bridge site will be required to determine
as to whether any remediation may be required before the bridge construction works can go
ahead.
5.7 Material Use
No further assessment is envisaged however the following should be considered as the scheme
is further developed:
Sourcing local materials to minimise associated transportation costs.
All waste should be segregated appropriately and stored in a safe manner.
Sub-contractors removing waste from site must possess a current waste carriers license
and all waste processing/disposal sites must also be appropriately licensed.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 23 - Service is our passion. People, our strengthIssued: May 2014
Consider whole life cost of materials as those that require less maintenance are more
durable.
Consider the presence of Asbestos particularly in the historic mechanical and electrical
equipment.
5.8 Noise and Vibration
Noise sensitive receptors within close proximity to these works include residential properties
and a place of worship The Parish Church of St Mary of Charity which is located approximately
275m to the east of the bridge site.
The following mitigation measures need to be considered:
Noise and vibration should be controlled and limited as far as reasonably practicable so
that sensitive receptors are protected from excessive noise and vibration from
construction.
Best Practicable Means shall be employed to minimise noise levels during construction.
Working hours should be strictly followed.
Advance notice of works should be given to local businesses and residents.
Where local residents are affected by the works, timing and phasing of work during the
construction phase should be considered.
5.9 Drainage and the Water Environment
The site does not lie within a Groundwater Source Protection Zone (SPZ), although a zone III
SPZ lies approximately 25m southeast of the site. The site does however lie within a
Groundwater Vulnerability Area classed as a principal aquifer.
The site also lies in an area vulnerable to flooding every 1 in 100 years.
As the works will take place within 10m of a primary river, consultation with the Environment
Agency must be undertaken to determine as to whether consent will be required for the works to
go ahead.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 24 - Service is our passion. People, our strengthIssued: May 2014
6 Geotechnical Considerations
6.1 Background Geotechnical Information
No historical information is available for the bridge however geotechnical investigation work has
been undertaken in the vicinity of the bridge location and has been reviewed for this report.
It is understood that the ground investigation was located a short distance to the west of the
site, on the northwest side of Faversham Creek, but the exact location is unknown. The
investigation comprised one percussive borehole to 22m depth and five 3m deep trial pits.
The strata encountered in the borehole is summarised in the table below:
Strata Description Thickness
(m)
SPT / CPT
values
Comments
Made
ground
Concrete and brick
rubble over clay with
flint and brick gravel
1.8 - Hydrocarbon contamination
was noted at 0.75m depth.
Alluvium Soft / firm clay
becoming very soft
2.7 7 at 1.8m
1 at 4m
Hydrocarbon contamination
was noted at 2.5m depth.
Head /
Alluvium?
Shattered flint sand,
gravel, cobbles and
boulders
0.8 22 at 5m
Thanet
Beds
Medium dense fine
sandy clay/silt with
occasional coarse
sand and fine flint
gravel at the top
4.2 26 at 8m
Upper
Chalk
Weak to very weak
white Chalk with
shattered flints.
Becoming hard
below 17.5m
12.5 41 at 9.5m
21 at 11m
22 at 12.5m
40 at 15.5m
50 at 17m
81 at 20m
>50 at 21m
Unfortunately the SPT values are not energy corrected so should be used for guidance only.
Groundwater strikes were recorded at depths of 4.6m rising to 4.45m, 7.2m rising to 5.55m and
9.3m rising to 1.4m. Subsequent monitoring indicated that groundwater was at between 1.25m
and 2.89m depth.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 25 - Service is our passion. People, our strengthIssued: May 2014
The trial pits encountered between 0.7m and 3.0m of made ground over alluvium. The made
ground varied in composition from sandy / gravelly brick and clinker to dark slightly organic clay
with some flint and brick gravel. A concrete slab was also encountered in TP2 between 0.57m
and 0.7m depth and the remnants of buried walls were recorded in TP1 and TP3. The alluvium
is described as soft to very soft organic clay with occasional flint gravel. Hydrocarbon odour
was recorded in TP2 at 0.7m.
Near neutral pH levels were recorded during the ground investigation and all of the soluble
sulphate levels were less than 0.5g/l.
6.2 Preliminary Geotechnical Advice
Shallow foundations bearing on the made ground and or alluvium are not recommended and
therefore a piled foundation, founding in the underlying Thanet Beds / Upper Chalk, will be
necessary.
Some difficulty may be experienced during excavation / piling if buried obstructions (remnants of
walls, or concrete slabs etc.), or if flint gravel / cobbles / boulders are encountered.
The piles may need to be temporarily or permanently cased through the made ground and
alluvium to ensure the bores stay open.
Excavations are likely to encounter groundwater at relatively shallow depth and therefore a
cofferdam or an appropriate method of controlling groundwater is likely to be required to keep
the excavations dry. It may also be necessary to case the pile bores to seal out the
groundwater.
If hydrocarbon contamination is suspected at the site then a phased contamination assessment
is likely to be required to assess the risk to site workers, the water course and groundwater.
A ground investigation is recommended in order to determine the ground and groundwater
conditions at the site. For preliminary design, this should comprise two 25m deep boreholes,
one either side of the water course, with in situ testing and sampling. Standard geotechnical
laboratory testing (likely to be moisture content, plasticity, grading, pH and sulphate) and
contamination screening should be undertaken.
6.3 Background information
A drawing dating from 1988 indicates that foundation to the south bearings comprises timber
piles, with cast iron shoes, founding in gravel. Unfortunately the length of the piles is not shown
on the drawing.
The records of the British Geological Survey (BGS) indicate that the site is underlain by
superficial alluvium and head brickearth over solid geology comprising Thanet Sand Formation
over the Seaford Chalk Formation.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 26 - Service is our passion. People, our strengthIssued: May 2014
The BGS records also indicate that there a number of historic boreholes near the site, dating
from 1962 and older. None of the logs for these boreholes contain engineering descriptions or
in situ test results. They do however indicate that the strata present in the vicinity of the site
comprises;
Strata Thickness (m)
Made ground 0.45 to 0.9
Alluvium 2.1 to 4.3
Head Brickearth 0.9 to 4.5
Thanet Beds Below 10.85m in one exploratory hole
Upper Chalk Below 15m in one exploratory hole
According to the records of the Environment Agency the site lies immediately adjacent to an
Inner Zone (zone 1) groundwater catchment area. The site overlies a major aquifer of high
leaching potential. The superficial deposits are designated as being secondary A aquifer, as is
the Thanet Sand. The chalk bedrock is a principal aquifer.
There are a number of small historic landfill sites and an authorised landfill in fairly close
proximity to the site, but no further records are available on the EA website (see screen print
below).
The site plan has been reproduced from an Ordnance Survey map, with the permission of
Her Majesty’s Stationery Office . Crown copyright reserved licence No. 100019238. 2013.
The site lies in an EA designated flood area, at risk from rivers or sea without defences.
.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 27 - Service is our passion. People, our strengthIssued: May 2014
7 Operation, Inspection and Maintenance
7.1 Operation of Moveable Bridge
It is understood that the operation of the moveable bridge options will be the responsibility of
Medway Ports ltd (part of Peel Ports Group).
Discussion with fabricators suggests that the period of time required for a bridge opening will be
approximately 8 to 10 minutes but this will be dependent upon the type of control system
implemented. A fully automated system with “single button” operation of the signals, barriers
and moveable bridge has been allowed for in the estimated costs.
7.2 Inspection and Maintenance
All five alternative options will require General Inspections (GI) undertaken on a biennial basis
and Principal Inspections (PI) undertaken every six years.
Options 2, 3, 4 and 5 will also require regular inspection and maintenance of the M&E
equipment. The requirements for inspections and maintenance are shown in the table below:
Type Period Estimated Cost
Inspection, and maintenance,
including greasing of moving
parts.
6 months £1000
As above, plus a full review of
electrical components
Annually £2000
Full inspection and Report Every 5 years £6000
Option 4 will require special arrangements for the maintenance and inspection of the M&E
equipment due to some of the elements being at height, requiring either a mobile elevated
working platform or scaffold tower to gain access to the equipment. It would be necessary to
close the road whilst this work is undertaken and it is envisaged that the maintenance work may
need to be undertaken at night to avoid disruption to vehicular traffic. This would add in the
region of £1000 cost to each maintenance visit.
It is possible that installing replacement M&E equipment into the existing footprint will
necessitate additional maintenance work for option 5.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 28 - Service is our passion. People, our strengthIssued: May 2014
The bridge is located in a low lying area and is liable to be inundated with flood water under
extreme climatic and cyclic tidal conditions. This will result in some elements/ components of
the structure being subjected to contamination with water borne chlorides from seawater. The
structure is deemed to be located in a severe exposure environment which may result in the
early replacement of some of the structures components.
The above factors and the periods for inspection and maintenance have been included in the
appraisal of the whole life costs for each of the options.
7.3 Design Considerations
When designing the M&E equipment for controlling and moving the bridge due consideration
shall be given to providing access to inspect, maintain and replace the equipment.
If necessary, jacking points need to be included in the design to allow for these operations to be
carried out safely. Repainting of the structure will be required on a number of occasions
throughout the service life of the structure and this will need to be considered at the detail
design stage to avoid undertaking in a confined space.
7.4 Health and Safety
The moving bridge options present significant hazards to operation, inspection and
maintenance, hazard management will need to be fully developed in co-ordination between the
civil engineering and M&E designers at future stages of design development.
Of particular concern will be the restriction of public access to the bridge site whilst the bridge is
moving. A closed circuit television system (CCTV) is considered necessary to ensure that the
operator has full visibility of sight restricted areas when opening or closing the bridge. A cost of
£30,000 has been allowed for provision and installation of the CCTV in the relevant option cost
estimates.
Maintenance and inspection for option 4 would entail working at height requiring special
equipment and possibly working outside of normal working hours. In addition there is a risk that
failure of the hydraulic rams or pipes could result in an oil spillage, consideration would need to
be given during the detailed design stage to investigate mitigation for this risk e.g. provide
containment to the items of equipment which could fail or leak oil. The designers will also be
required to provide a manual for operation and maintenance for the structure.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 29 - Service is our passion. People, our strengthIssued: May 2014
8 Stakeholders
8.1 Stakeholder Consultation
Stakeholder liaison was excluded from the scope for this report. However local businesses have
been contacted to discuss the implications of closure of the road due to the construction works.
The effects of proposed work should be planned with full consideration of the impact on all
stakeholders and all reasonable measures to eliminate or mitigate detrimental effects should be
taken.
It is recommended that a full public consultation exercise should be carried out during the
preliminary design stage for the scheme.
8.2 Principal stakeholders
The principal stakeholders identified at this stage include the following organisations and
groups:
Road users
River users
Kent CC Education & Learning Department
Swale District Council
Faversham Town Council
Environment Agency
Natural England
Medway Ports Ltd (Peel Ports)
Emergency services (Police, Fire and Rescue and Ambulance )
Statutory Undertakers
BMM Weston
Shepherd Neame Brewery
Brents Tavern PH
The Albion PH
Little Moon Beams (Day Nursery)
Brent Industrial Estate
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 30 - Service is our passion. People, our strengthIssued: May 2014
9 Discussion and Recommendations
9.1 Cost comparison
It can be seen from the cost summaries included in Section 3 above that Option 1 has the
lowest capital and whole life costs. It is also considered that this option would require the least
ongoing maintenance.
For the moving bridge options; option 5 has the lowest budget cost for design and construction.
However, the whole life costs for options 2 and 5 are very similar such that the cost for option 2
is marginally lower over 60 years and marginally higher over 120 years. There is little to choose
between options 3 and 4, both have similar costs for design and construction however the
whole life costs for option 4 are the greatest of all the considered options.
9.2 Time of construction
Option 1 will be the quickest of the three options to construct and therefore will result in less
disruption to the public.
Options 2, 3, 4 and 5 have similar construction periods and also require a road closure for a
similar length of time.
9.3 Operation and maintenance
Options 2, 3, 4 and 5 will require significantly more attendance for inspection and maintenance
than option 1. The cost for this work has been included in the whole life costs for each option.
9.4 Advantages and Disadvantages
Options 2, 3, 4 and 5 would enable access for water craft access the upper basin of Faversham
Creek however the fixed bridge (option 1) will limit the size of watercraft on the navigable
waterway and would prevent the upper creek from effectively functioning as a navigable
waterway.
9.5 Recommendations
If the scheme is to be developed to preliminary and detail design stages it is recommended that
the following information is obtained:
Topographical survey
Geotechnical investigation and report
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - 31 - Service is our passion. People, our strengthIssued: May 2014
Environmental assessment
Traffic impact assessment
In addition the costs for the following will need to be considered:
Provision of power supply
Fendering
Dredging of the basin
Repair to lock gates
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - A-1 - Service is our passion. People, our strengthIssued: May 2014
Appendix A Cost Estimate Coverage
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - A-2 - Service is our passion. People, our strengthIssued: May 2014
Item Coverage
Preliminaries Construction site accommodation, offices
stores etc.
Traffic and pedestrian diversions.
Site Clearance Clearing site.
Demolition of existing structures.
Fencing Temporary fencing to secure site.
Road Restraint Systems Parapets and pedestrian guard railings.
Drainage and Service Ducts Drainage system.
Earthworks Excavation, Fill material and topsoiling.
Pavements Road construction.
Kerbs, Footways and Paved Areas Kerbing and footways.
Traffic Signs and Road markings Re-erection of signs and new white lines.
Street Lighting Re-erection of lighting columns.
Electrical Connection to electricity supply.
Automatic barriers and lights.
CCTV.
Underwater power/ communications link.
Piling and Embedded Retaining Walls Underpinning of existing abutment
foundations.
Piling for retraction pit foundations.
Structural Concrete Reinforced concrete (RC) elements
including:
In situ RC deck slab.
Precast bridge beams, bank seats
and walls
In situ RC retraction pits
Protection of Steelwork Against Corrosion Protective paint system to steel members
Waterproofing to Structures Waterproofing system to reinforced
concrete members i.e. retraction pits and
bridge deck
Bridge Expansion Joints Nosing joints at abutments
Brickwork, Blockwork & Stonework Masonry repairs to existing abutment walls
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - A-3 - Service is our passion. People, our strengthIssued: May 2014
Item Coverage
Special Structures Designed by the
Contractor
Design, fabrication, installation and
commissioning of the following:
Steel bridge deck.
Steel frames and counterweights
Mechanical equipment
Electrical control system
The cost estimates do not include the following:
Scheme design development
Land licences or acquisition
Provision of power supply
Fendering
Dredging of the basin
Repairs to lock gates
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - B-1 - Service is our passion. People, our strengthIssued: May 2014
Appendix B Options Drawings
500 1500 3000 1500 500
150
11 No. Precast Prestressedbeams (Type SBB S8)
500
300
7980 (clear span)3520 3520
Masonry / Brickwork repairsrequired to both abutments
File ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\101 rev02-option 1.dwg0 100
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A3
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
JWSLRCSL14.11.2013
Other
BRENT SWING BRIDGEKCC Structure No. 1277
STRUCTURES
OPTION 1:FIXED BRIDGE
As Shownmm
CO04300132/30/101 02
PLANScale 1:100
EAST ELEVATIONScale 1:100
TYPICAL CROSS SECTION LOOKING SOUTHScale 1:50
1000 high vehicle parapetN1/W2 with vertical infill
100 slab100 surfacing1:40 1:40
Spray applied waterproofing membrane
Kerb lines to be tied intoexisting kerbs at both ends
1000 high guardrailing at approaches
NOTES1. All measurements are in millimetres unless
stated otherwise. All levels are in metres.2. Do not scale from this drawing, use written
dimensions only.
01 Minor amendments RC SL 15.11.1302 Elevation revised RC SL 14.02.14
5500 11000
Pintle bearing
Nose bearings
Tail wheel track
LC of pintlebearing
Masonry / Brickwork repairsrequired to both abutments
Automatic barrierand warning lights
15003000450
Deck plate
UB main beamsTransoms @ 2000 c/cTee stiffeners
Proprietary combined water-proofing and anti-skid surfacing
Stiffeners at 2000 crs.
LC of pintle bearing
Insitu reinforced concreteabutment slab
File ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\102 rev03-option 2.dwg0 100
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A3
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
JWSLRCSL14/11/2013
Other
BRENT SWING BRIDGEKCC Structure No. 1277
STRUCTURES
OPTION 2:SWING BRIDGE
As Shownmm
CO04300132/30/102 03
Nose bearing
Precast reinforced concretebearing beam and ballast wall
1000 high vehicle parapet N1/W2 with vertical infill
Kentledge
PumpHouse
Hydraulic wedgesand jacks
NOTES1. All measurements are in millimetres unless
stated otherwise. All levels are in metres.2. Do not scale from this drawing, use written
dimensions only.
Kerb lines to be tied intoexisting kerbs at both ends
1000 high guardrailing at approaches
01 Minor amendments RC SL 15.11.1302 Sect. B-B amended AJM SL 19.11.13
PLANScale 1:100
EAST ELEVATIONScale 1:100
TYPICAL CROSS SECTION LOOKING SOUTHScale 1:50
02 Redrawn AJM SL 18.02.14
Deck to lift clear of watercourse
Line of handrail stepped toallow for rotation of deck
NOTES1. All measurements are in millimetres unless
stated otherwise. All levels are in metres.2. Do not scale from this drawing, use written
dimensions only.
File ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\107 revp0, 108 revp0-option 3.dwg0 100
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A3
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
AJMSLRCSL19.11.2013
Other
BRENT SWING BRIDGEKCC Structure No. 1277
STRUCTURESOPTION 3:
LIFTING BRIDGEEAST ELEVATION Sht 1
As Shownmm
CO04300132/30/107 01
EAST ELEVATION (OPEN)Scale 1:100
EAST ELEVATION (CLOSED)Scale 1:100
01 Power pack &hydraulic ram movedinto retraction pit
RC SL 25.02.14
NOTES1. All measurements are in millimetres unless
stated otherwise. All levels are in metres.2. Do not scale from this drawing, use written
dimensions only.
File ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\107 revp0, 108 revp0-option 3.dwg0 100
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A3
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
AJMSLRCSL19.11.2013
Other
BRENT SWING BRIDGEKCC Structure No. 1277
STRUCTURESOPTION 3:
LIFTING BRIDGEEAST ELEVATION Sht 2
As Shownmm
CO04300132/30/108 01
EAST ELEVATION (HALF OPEN)Scale 1:100
01 Power pack &hydraulic ram movedinto retraction pit
RC SL 25.02.14
NOTES1. All measurements are in millimetres unless
stated otherwise. All levels are in metres.2. Do not scale from this drawing, use written
dimensions only.
File ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\109 revp0, 110 revp0, 111 revp0, 112 revp0-option 4.dwg0 100
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A3
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
AJMSLRCSL13.02.14
Other
BRENT SWING BRIDGEKCC Structure No. 1277
STRUCTURESOPTION 4:
BASCULE BRIDGEEAST ELEVATION Sht 1
As Shownmm
CO04300132/30/109 P0
EAST ELEVATION (CLOSED)Scale 1:100
Deck to lift clearof watercourse
NOTES1. All measurements are in millimetres unless
stated otherwise. All levels are in metres.2. Do not scale from this drawing, use written
dimensions only.
File ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\109 revp0, 110 revp0, 111 revp0, 112 revp0-option 4.dwg0 100
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A3
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
AJMSLRCSL13.02.14
Other
BRENT SWING BRIDGEKCC Structure No. 1277
STRUCTURESOPTION 4:
BASCULE BRIDGEEAST ELEVATION Sht 2
As Shownmm
CO04300132/30/110 P0
EAST ELEVATION (OPEN)Scale 1:100
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - C.1 - Service is our passion. People, our strengthIssued: May 2014
Appendix C Temporary Diversion Route
Brent Swing Bridge
Two way
Single way working undertraffic signal control
3 way signals required atBrent Hill/Davington HillJunction
DIVERSION ROUTEFile ref - p:\d - projects\co04300132 - brent swing bridge\102.drawings\01. working\1700 structures\options\105 rev01-route diversion.dwg
0
Drawing No
Project Name
Drawing Title
Original Drg Size :Scale :
Client
Dimensions :A4
Rev
Revision details
Date:
Drawn:
Chkd:Appd:
Design:
Rev
100
As constructedFor constructionFor tenderFor comment
Chkd Appd Date
Preliminary
cCopyright Amey
www.amey.co.uk
AJMSLRCSL19.11.2013
Other
BRENT SWING BRIDGEKCC STRUCTURE
No. 1277
STRUCTURES
DIVERSION ROUTE
As Shown-
CO04300132/30/105 01
Ordnance Survey Map with the permission
of the Controller of Her Majesty's Stationery Office.
Based upon or reproduced from the TR06SW1:10,000
01 Redrawn AJM SL 19.11.13
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - D.2 - Service is our passion. People, our strengthIssued: May 2014
Appendix D M&E Inspection Report
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - E.1 - Service is our passion. People, our strengthIssued: May 2014
Brent Swing Bridge, structure ref. 1277 – Visual Inspection 17th April 2014
Review comments of Medway Ports - Bridge Operations Document and Peel Ports – Marine
Operations - Report on Lifting Mechanism
The brief was to review the Mechanical and Electrical operating system of the Brent Swing
Bridge. The review was undertaken by Derek Cox (Amey). Also present were
representatives from Kent County Council (KCC), Peel Ports and Dave Dale (Amey)
While it was possible to gain access to most areas, any information regarding the principle of
operation, in relation to what was clearly pumping equipment, was not readily available on the
day of the site visit.
However, various Internet searches and the Jacobs Principle Inspection of November 2011
indicate the lifting mechanism is hydraulic, although anecdotal information gained from
engineers familiar with the bridge suggests that the lifting action is achieved by utilising water
pressure.
Documents supplied by Peel Ports provided information on the operation of the mechanism.
Medway Ports Marine Department – Bridge Operations
It would appear that the purpose of the hand-operated pump is to raise the
accumulator. (Large weights in the pump house)
The opening process/raising of the bridge is achieved by movement of hydraulic
water pressure that is applied to the lifting ram located under the bridge after opening
and closing a series of hand-valves in the pump-house.
There appear to be options of gaining bridge movement from fully open to fully closed
by utilising the winch located close to the pump house and a travelling block. This
seems to involve relocating the winch hook to different locations of the bridge and
handrail during its rotation and securing the travelling block to the storeroom opposite
the pump house. In all likelihood the winch would only be used if it proved difficult to
move the bridge manually.
Review Comments:
The current method of closing the highway is outdated when compared to modern
standards and it is unlikely that the current gates and red-lamp for nighttime closures
could be accepted under current standards.
The integrity of the associated pipework and operational readiness of the control
valves and the lifting ram mentioned in the procedure are unknown.
The accumulator lowering area within the pump house is unguarded.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - E.2 - Service is our passion. People, our strengthIssued: May 2014
Report Findings:
The Brent Swing Bridge has not been operated for over 15 years and whilst the
pumping equipment in the pump house at the south east corner of the bridge looks
in fairly good external condition, its operational integrity is unknown.
The principle of operation also remains unknown, but it would appear that the piston
inside the large ram sited below the pintle bearing engages with the bearing when
pressure is applied and raises the structure off of the north and south abutments and
central bearing points.
The structure, when raised, balances on the ram piston and it is assumed that the
rotation/swinging motion is manually applied to the southern end of the bridge. It is
unclear if this is a single man operation, but there is a cable winch in the pintle area
close to the pump house and a hook locating ring fixed to the south west kerb area
beneath the pedestrian railing and it is understood that this was used to overcome
any difficulties initially encountered when moving the structure.
Also located at the southern end of the structure are the Kentledge box and bridge
tilt wheels.
The deck superstructure appears to have moved and is now in contact with the
northern abutment face. Consequently there is a visible misalignment between the
lifting ram piston and pintle bearing such that the ram is no longer in contact with the
pintle bearing.
Although not clearly visible, it is understood that there is uncertainty regarding the
integrity of the steelwork securing the pintle bearing to the bridge deck.
Housed in the north west building is a 12 Volt DC hydraulic power pack, batteries,
charger and a small quantity of electrical relays and timers that when triggered by
float switches, control the small flap/gate situated at the base of the north sluice gate.
Both the south east and north west buildings have a single-phase 240-volt AC power
supply. Both are metered, which would indicate they are separate incomers.
Summary:
The importance of the structure from a highway access perspective was emphasised by KCC
and while a live test of the equipment might be considered worthwhile, the potential disruption
would likely be unacceptable.
As documented above, the operational procedure is unknown, but clearly within the pump
house there are large weights currently at ceiling height and it is assumed that these lower
imparting pressure into the hydraulic lifting system. From a health and safety perspective, if
these weights do lower then this area must be securely protected. It is also unclear what the
function of the pump is and how much effort is needed to operate it, but there is clearly limited
space to turn the hand-wheel and the grip appears to be fixed, and would therefore not rotate
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - E.3 - Service is our passion. People, our strengthIssued: May 2014
within the operators grip. It is also doubtful that the manual effort needed to rotate the
structure would meet current manual handling regulations.
Given the clear uncertainties regarding the integrity of the installed equipment, the tranverse
joists, the operational procedure, the associated pipework and the current method of closing
the highway, it is recommended that the bridge remains closed to navigation.
The extract from the Jacobs PI report of 2011 is included below.
8.0 – Jacobs Conclusion
The structure is in fair to poor condition and several significant faults have been identified.
Intrusive investigation works and remedial works have been recommended for different
elements of the structure, depending upon whether or not the bridge is to be opened in future.
It is a matter of concern that several inaccessible items, which must be assumed to be in poor
condition, as explained in the commentary on section 7.1, and cannot readily be inspected or
maintained.
For example the south bearings might be visible with the aid of an endoscope, but it is not
possible to assess their condition, or to maintain them.
It must be noted also that the paint system is known to be lead based, so that any
strengthening and maintenance operations will require special protection to be put in place for
the safety of the workforce and the environment.
The recommendations tabulated in section 7.1 are the basic measures needed to maintain
the stability of the existing structure.
A full list of recommendations will form part of the Feasibility Report referred to in item 2.2
because the work recommended will depend to some extent upon the results of the structural
assessment, residual life and fatigue life assessment.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - E.4 - Service is our passion. People, our strengthIssued: May 2014
Peel Ports – Marine Operations 23rd October 2007
Report on Road Lifting Mechanism at Faversham
Pump and accumulator proved operational under local test within the pump house.
The ram under the bridge was not tested, as this would require raising the bridge.
Poor condition of road closure barriers
The wheels on the turntable are covered in debris and would need testing before any
movement of the bridge was attempted
Review Comments:
The report confirms the hydraulic fluid is a 50/50 mixture of water and antifreeze that
should be drained and replaced. It does not establish if there is a mains water
supply. In addition and when drained, the current fluid would be classed as
hazardous waste and therefore need to be disposed of accordingly.
It is assumed that the 20mm deflection of the bridge at the northern abutment when
heavy vehicles pass over has now been addressed.
Conclusion:
The condition of the structure is documented in the Jacobs Principal Inspections Report of
November 2011. Peel Ports reported the condition of the Road lifting mechanism in October
2007.
Both reports cast doubt on the integrity of certain areas of the structure, its operational
readiness in relation to the installed equipment and compliance with current traffic
management requirements.
It is also unclear if there has been a recent risk assessment carried out in relation to the
operating procedure and whether there would be manual handling issues relating to moving
the structure.
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - E.1 - Service is our passion. People, our strengthIssued: May 2014
Appendix E Bibliography
Project Name Brent Swing Bridge
Document Title Options Report
Doc. Ref.: CO04300132/02 Rev 03 - E.2 - Service is our passion. People, our strengthIssued: May 2014
STRUCTURE RECORD REPORTS:
Brent Swing Bridge – Feasibility Report (April 2012) - Jacobs
Brent Swing Bridge - Principal Inspection Report (November 2011) – Jacobs 2011
Historical Report on Brent Swing Bridge – KCC Structure No. 1277 (October 2004)
Hydraulic Mechanism(s) Testing Report (Untitled). Medway Ports memorandum 7th June 2006.
Report on Road Lifting Mechanism. Medway Ports unreferenced report 23rd October 2007.