brassengineeringinternational 151112220903 lva1 app6891

Upload: cbt71

Post on 07-Aug-2018

214 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    1/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    2/92

    11/11/2015 Toromocho Tailings Pipelines Slide 2

    The Tailings Pipelines were designed in two phases:

    Tailings Pipelines Project Overview

    • Expansion Phase

    • Design Completed: 2015

    • Nominal Capacity: 54,000 dry t/d• Design Capacity: 70,000 dry t/d

    • Initial Phase

    • Design to Startup: 2009 to 2014

    • Nominal Capacity: 124,000 dry t/d• Design Capacity: 155,000 dry t/d

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    3/92

    11/11/2015 Toromocho Tailings Pipelines Slide 3

    Tailings Pipelines Project Overview

    Initial System Design• Located in the District of Morococha, Yauli Province, Junin Region,

    Peru.

    • The Toromocho project mines copper, molybdenum, and silver with

    respective grades of 0.48%, 0.019%, and 6.88 grams per ton

    • Ore Reserve is estimated to 1526 million metric tons

    • Pump Station elevation is 4523 masl and terminates 4.7 km

    distance at 4777 masl (up hill).

    • Due to pressure requirements the pump station uses 10 of the

    largest positive displacement pumps (8 + 2 mode) operating in

    parallel• Due to number of pumps it is the largest pump station of its kind

    • Estimated Annual production:

    • One million metric tons of copper,

    • Ten thousand metric tons of molybdenum

    • Four million ounces of silver

    • And ~ 44 million metric tons of tailings

    Expansion System Design• ~26 million metric tons annually of tailings• Stand alone system adding four additional pumps operating in

    parallel

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    4/92

    11/11/2015 Toromocho Tailings Pipelines Slide 4

    Initial Tailings Pipeline

    Process Design Criteria:

    • Scope: from flange on P/S suction headers• Capacity:

    • Nominal = 5176 t/h

    • Design = 6470 t/h

    • Pump Station Elevation: 4,520 masl

    • Highest Discharge Elevation:• Phase I: 4,777 masl

    • Phase II: 4,890 masl

    • Pipeline length:

    • Phase I: 4,707 m

    • Phase II: 5,400m

    • Tailings Slurry Concentration:• Minimum = 69%

    • Maximum = 71%

    • Actual experience tailings thickened to 65%

    • Design Life: 30 years

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    5/92

    11/11/2015 Toromocho Tailings Pipelines Slide 5

    Slurry Characteristics:

    • Sample taken from Pilot Testing

    •Solid’s SG:Sample 1 and 2 = 2.77 (used fordesign) to 2.92

    • Handling Tests: Shutdown / Restart ability

    are good, no serious problems areforeseen

    Initial Tailings Pipeline

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    6/92

    11/11/2015 Toromocho Tailings Pipelines Slide 6

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500 6000

       T    h   r   o   u   g    h   p   u   t ,    d

       r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    62.0%

    63.0%

    Limiting Velocity

    Q 5.8 pumps

    61.0%

    64.0%

    65.0%

    66.0%

    67.0%

    68.0%

    69.0%

    70.0%

    Nominal

    Q 10 pumps

    Design Tonnage

    Q 8 pumps

    60.0%

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Initial System Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    7/92

    11/11/2015 Toromocho Tailings Pipelines Slide 7

    Diameter  34.000 NPS Cw 68.80% % Capacity 158,939  dry t/d Sfac 1.100 

    Sample # 1 Q 5400.0 m3/h w-dot 6,622  dry t/h w-dot 158,939  dry t/d

    Sample # 2 Q 5400.0 m3/h w-dot 6,622  dry t/h w-dot 158,939  dry t/d

    Sample # 1 V 2.792 m/s -dH/dX, BP 24.369 m/km -dH/dX, NWT 11.437 m/km

    Sample # 2 V 2.792 m/s -dH/dX, BP 18.660 m/km -dH/dX, NWT 10.528 m/km

    Initial Cw, % 68.8% #Pumps 10 Speed, % 100%

    Initial System 10 Pumps Operating @ 100 %

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    8/92

    11/11/2015 Toromocho Tailings Pipelines Slide 8

    Diameter  34.000 NPS Cw 67.50% % Capacity 153,653  dry t/d Sfac 1.100 

    Sample # 1 Q 5400.0 m3/h w-dot 6,402  dry t/h w-dot 153,653  dry t/d

    Sample # 2 Q 5400.0 m3/h w-dot 6,402  dry t/h w-dot 153,653  dry t/d

    Sample # 1 V 2.792 m/s -dH/dX, BP 18.209 m/km -dH/dX, NWT 10.849 m/km

    Sample # 2 V 2.792 m/s -dH/dX, BP 15.319 m/km -dH/dX, NWT 10.054 m/km

    Initial Cw, % 67.5% #Pumps 10 Speed, % 100%

    Initial System 10 Pumps Operating @ 100 %

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    NominalTonnage

    Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    9/92

    11/11/2015 Toromocho Tailings Pipelines Slide 9

    Diameter  34.000 NPS Cw 60.00% % Capacity 125,946  dry t/d Sfac 1.100 

    Sample # 1 Q 5400.0 m3/h w-dot 5,248  dry t/h w-dot 125,946  dry t/d

    Sample # 2 Q 5400.0 m3/h w-dot 5,248  dry t/h w-dot 125,946  dry t/d

    Sample # 1 V 2.792 m/s -dH/dX, BP 8.877 m/km -dH/dX, NWT 8.747 m/km

    Sample # 2 V 2.792 m/s -dH/dX, BP 8.584 m/km -dH/dX, NWT 8.351 m/km

    Initial Cw, % 60.0% #Pumps 10 Speed, % 100%

    Initial System 10 Pumps Operating @ 100 %

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    10/92

    11/11/2015 Toromocho Tailings Pipelines Slide 10

    Diameter  34.000 NPS Cw 60.00% % Capacity 73,049  dry t/d Sfac 1.100 

    Sample # 1 Q 3132.0 m3/h w-dot 3,044  dry t/h w-dot 73,049  dry t/d

    Sample # 2 Q 3132.0 m3/h w-dot 3,044  dry t/h w-dot 73,049  dry t/d

    Sample # 1 V 1.619 m/s -dH/dX, BP 3.633 m/km -dH/dX, NWT 3.257 m/km

    Sample # 2 V 1.619 m/s -dH/dX, BP 3.731 m/km -dH/dX, NWT 3.095 m/km

    Initial Cw, % 60.0% #Pumps 8 Speed, % 73%

    Initial System 8 Pumps Operating @ 72.5 %

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    11/92

    11/11/2015 Toromocho Tailings Pipelines Slide 11

    Diameter  34.000 NPS Cw 67.00% % Capacity 87,964  dry t/d Sfac 1.100 

    Sample # 1 Q 3132.0 m3/h w-dot 3,665  dry t/h w-dot 87,964  dry t/d

    Sample # 2 Q 3132.0 m3/h w-dot 3,665  dry t/h w-dot 87,964  dry t/d

    Sample # 1 V 1.619 m/s -dH/dX, BP 13.402 m/km -dH/dX, NWT 4.018 m/km

    Sample # 2 V 1.619 m/s -dH/dX, BP 10.830 m/km -dH/dX, NWT 3.722 m/km

    Initial Cw, % 67.0% #Pumps 8 Speed, % 73%

    Initial System 8 Pumps Operating @ 72.5 %

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    12/92

    11/11/2015 Toromocho Tailings Pipelines Slide 12

    Diameter  34.000 NPS Cw 68.80% % Capacity 127,151  dry t/d Sfac 1.100 

    Sample # 1 Q 4320.0 m3/h w-dot 5,298  dry t/h w-dot 127,151  dry t/d

    Sample # 2 Q 4320.0 m3/h w-dot 5,298  dry t/h w-dot 127,151  dry t/d

    Sample # 1 V 2.234 m/s -dH/dX, BP 23.053 m/km -dH/dX, NWT 7.672 m/km

    Sample # 2 V 2.234 m/s -dH/dX, BP 16.932 m/km -dH/dX, NWT 7.060 m/km

    Initial Cw, % 68.8% #Pumps 8 Speed, % 100%

    Initial System 8 Pumps Operating @ 100 %

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    3000

    3500

    4000

    4500

    5000

    5500

    6000

    6500

    7000

    2500 3000 3500 4000 4500 5000 5500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings System - Sample 2

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    13/92

    11/11/2015 Toromocho Tailings Pipelines Slide 13

    Pipeline Routing and Impoundment

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    14/92

    11/11/2015 Toromocho Tailings Pipelines Slide 14

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    15/92

    11/11/2015 Toromocho Tailings Pipelines Slide 15

    Impoundment and Tailings Dam

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    16/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    17/92

    11/11/2015 Toromocho Tailings Pipelines Slide 17

    Impoundment and Tailings Dam

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    18/92

    11/11/2015 Toromocho Tailings Pipelines Slide 18

    Impoundment and Tailings Dam

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    19/92

    11/11/2015 Toromocho Tailings Pipelines Slide 19

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    20/92

    11/11/2015 Toromocho Tailings Pipelines Slide 20

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    21/92

    11/11/2015 Toromocho Tailings Pipelines Slide 21

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    22/92

    11/11/2015 Toromocho Tailings Pipelines Slide 22

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    23/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    24/92

    11/11/2015 Toromocho Tailings Pipelines Slide 24

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    25/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    26/92

    11/11/2015 Toromocho Tailings Pipelines Slide 26

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    27/92

    11/11/2015 Toromocho Tailings Pipelines Slide 27

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    28/92

    11/11/2015 Toromocho Tailings Pipelines Slide 28

    Discharge Points

    Di h P i t

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    29/92

    11/11/2015 Toromocho Tailings Pipelines Slide 29

    Discharge Points

    Di h P i t

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    30/92

    11/11/2015 Toromocho Tailings Pipelines Slide 30

    Discharge Points

    Di h P i t

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    31/92

    11/11/2015 Toromocho Tailings Pipelines Slide 31

    Discharge Points

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    32/92

    11/11/2015 Toromocho Tailings Pipelines Slide 32

    System Hydraulics

    I iti l S t SS H d li

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    33/92

    11/11/2015 Toromocho Tailings Pipelines Slide 33

    Initial System SS Hydraulics

    Conventional Slurry

    I iti l S t SS H d li

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    34/92

    11/11/2015 Toromocho Tailings Pipelines Slide 34

    Initial System SS Hydraulics

    Bingham Plastic Slurry

    Conventional Slurry

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    35/92

    11/11/2015 Toromocho Tailings Pipelines Slide 35

    Pump Duty

    • Geho: TZPM 2000 (largest PD pump)• Continuous Service

    • Flow Capability: 655 m3/h each

    •Initial System used 540 m3/h each

    • Expansion System used 650 m3/h each

    • Pressure Capability:

    • Normal: 8,100 kPa

    • w/ GLORES modification: 11,000 kPa

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    36/92

    11/11/2015 Toromocho Tailings Pipelines Slide 36

    Pump Station Design

    Pump Station Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    37/92

    11/11/2015 Toromocho Tailings Pipelines Slide 37

    Pump Station Design

    Pump Station Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    38/92

    11/11/2015 Toromocho Tailings Pipelines Slide 38

    Pump Station Design

    Pump Station Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    39/92

    11/11/2015 Toromocho Tailings Pipelines Slide 39

    Pump Station Design

    Pump Station Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    40/92

    11/11/2015 Toromocho Tailings Pipelines Slide 40

    Pump Station Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    41/92

    11/11/2015 Toromocho Tailings Pipelines Slide 41

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    42/92

    11/11/2015 Toromocho Tailings Pipelines Slide 42

    Toromocho Tailings Pipelines

    Several unique difficulties in Mechanical Design of Toromocho Tailings

    Pump Station

    • Tailings pump station is situated on an earthwork bench and the space

    available for piping was not sufficient to accommodate the preferred

    pump station design

    • Pump station is located in harsh, mountainous conditions 4,520m above

    sea level

    • Pump station will experience high pressures and flows and the

    possibility of large pressure fluctuations

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    43/92

    11/11/2015 Toromocho Tailings Pipelines Slide 43

    Toromocho Tailings Pipelines

    Pipe Stress Analysis

    Preferred Pump Discharge Arrangement

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    44/92

    11/11/2015 Toromocho Tailings Pipelines Slide 44

    Toromocho Tailings Pipelines

    Preferred pump station layout

    • Pump discharge will incorporate bends to take the pipe from the pump

    discharge nozzle to the station floor. Once on the floor the piping will

    connect to the anchored discharge manifold

    • Piping is much easier to restrain because pipe supports can be mounted

    directly to platforms on the floor

    • Pipe bends between the discharge nozzle and the discharge manifoldcreate flexibility in the piping

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    45/92

    11/11/2015 Toromocho Tailings Pipelines Slide 45

    Toromocho Tailings Pipelines

    The Toromocho Tailings Pump Station is located on an bench only about

    40m wide

    • BRASS developed a station arrangement in which the discharge manifold

    is at the same elevation as the discharge nozzle

    • Eliminated the space between the pump discharge and manifold taken

    up by the two pipe bends

    • Reduced piping flexibility to absorb temperature expansion andcontraction

    Pipe Stress Analysis

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    46/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    47/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    48/92

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    49/92

    11/11/2015 Toromocho Tailings Pipelines Slide 49

    g p

    This is a seemingly small change in length. When the Elastic

    Modulus of the pipe is considered the force that can bedeveloped is easily enough to overstress piping and pump

    nozzles if the system is too rigid.

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    50/92

    11/11/2015 Toromocho Tailings Pipelines Slide 50

    g p

    The stiffness and location of pipe supports were carefully analyzed and

    many iterations of the design were considered before a final solution was

    reached

    • Caesar II simulations were run to analyze the pipe stresses

    • Two main over stress issues needed to be solved. Both issues were most

    severe when low temperature pipe contraction was considered

    • straight pump discharge lines pull the discharge manifold laterally

    • large S-bend located after the discharge manifold stretched by the

    contracting manifold

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    51/92

    11/11/2015 Toromocho Tailings Pipelines Slide 51

    g p

    S-Bend

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    52/92

    11/11/2015 Toromocho Tailings Pipelines Slide 52

    g p

    • To reduce stress on the manifold and pump nozzles, BRASS used flexible

    supports which allow the manifold piping to move laterally as the pipe

    contracts

    Over stress issue at the S-bend not as easy to fix

    • Possible solution: fix the manifold piping with very rigid supports

    • Prevent the manifold piping from pulling on the S-bend as

    strongly

    • Has the effect of increasing the pump nozzle loads to

    unacceptable levels

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    53/92

    11/11/2015 Toromocho Tailings Pipelines Slide 53

    g p

    After a number of design iteration BRASS discovered that a special support

    needed to be designed

    • Support must be very rigid in the axial direction of the piping and

    simultaneously flexible in the lateral direction

    • Developed large plate oriented in the direction of the pipe axis

    • Reinforcing ribs were added to achieve the required lateral and vertical

    stiffness.

    • Support is located near the middle of the discharge manifold

    Pipe Stress Analysis

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    54/92

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    55/92

    11/11/2015 Toromocho Tailings Pipelines Slide 55

    Even small pressure pulsations can cause large deflection in piping if the

    excitation frequency of the pump is close to the natural frequency of the

    piping

    • The first mode of vibration of the piping should be signifigantly greater

    than the pump’s nominal frequency of excitation and must be greater

    than the pump’s maximum excitation to ensure no resonant vibration

    will take place

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    56/92

    11/11/2015 Toromocho Tailings Pipelines Slide 56

    Frequency of Excitation Calculation

    60

    )(   nrpmi fe    

    e f    : Frequency of Excitation (Hz)

    i : Numbers of pistons

    rpm : Rotations per minute

    n : Fundamental frequency, n=1,2,3….. 

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    57/92

    11/11/2015 Toromocho Tailings Pipelines Slide 57

    The pump’s nominal frequency of excitation is 4Hz and maximum

    frequency of excitation is 5 Hz

    • Upon first analysis BRASS found that the piping natural frequency was

    too low, due to the flexible supports

    • A number of iterations were made to adjust the stiffness and location of

    supports to increase the piping natural frequency

    • The piping natural frequency was increased to approximately 6Hz. This ishigh enough to prevent resonant vibration.

    Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    58/92

    11/11/2015 Toromocho Tailings Pipelines Slide 58

    The stress and flexibility analysis of the Toromocho

    Tailings Pump Station presented numerous unique

    engineering challenges. BRASS Engineering

    International was able to develop a design which

    overcame the space limitations, harsh environment,

    and possible harmonic resonance of the pipe causedby pressure pulsation.

    Pipe Stress Analysis

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    59/92

    11/11/2015 Toromocho Tailings Pipelines Slide 59

    Pre-com, Com, Startup

    Pre-com, Com, Startup

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    60/92

    11/11/2015 Toromocho Tailings Pipelines Slide 60

    Nitrogen charged Pulsation dampeners

    Low, Medium, and High Pressure Pre-charge

    Pre-com, Com, Startup

    Early pre commissioning problems

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    61/92

    11/11/2015 Toromocho Tailings Pipelines Slide 61

    Urethane lined pipe was welded on causing the lining to be compromised

    Early pre-commissioning problems

    Pre-com, Com, Startup

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    62/92

    11/11/2015 Toromocho Tailings Pipelines Slide 62

    Photo shows field constructed “Y” on pump discharge line

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    63/92

    11/11/2015 Toromocho Tailings Pipelines Slide 63

    Expansion System Design

    Expansion System Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    64/92

    11/11/2015 Toromocho Tailings Pipelines Slide 64

    Process Design Criteria:

    • Scope: from bottom of thickeners• Capacity:

    • Nominal = 2250 t/h

    • Design = 2916 t/h

    • Pump Station Elevation: 4,520 masl

    • Highest Discharge Elevation: 4,777 masl

    • Pipeline length: 4707 m

    • Tailings Slurry Concentration:

    • Minimum = 60.0%

    • Maximum = 68.8%

    • Based upon existing system the actual

    experience tailings thickened to 65%

    • Design Life: 5 years

    Expansion System Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    65/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    66/92

    Expansion System Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    67/92

    11/11/2015 Toromocho Tailings Pipelines Slide 67

    1000

    1500

    2000

    2500

    3000

    3500

    1300 1500 1700 1900 2100 2300 2500 2700

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings System Expansion - Sample 2

    Q 2.4 pumps

    62.0%

    63.0%

    Limiting Velocity

    61.0%

    64.0%

    65.0%

    66.0%

    67.0%

    68.0%

    69.0%

    70.0%

    Nominal

    Q 4 pumps

    Design Tonnage

    Q 3 pumps

    60.0%

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Operating Range

    pa s o Sys e es g

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    68/92

    Expansion System 4 Pumps Operating @ 100 %

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    69/92

    11/11/2015 Toromocho Tailings Pipelines Slide 69

    Diameter  24.000 NPS Cw 65.00% % Capacity 69,982  dry t/d Sfac 1.100 

    Sample # 1 Q 2600.0 m3/h w-dot 2,936  dry t/h w-dot 70,464  dry t/d

    Sample # 2 Q 2600.0 m3/h w-dot 2,916  dry t/h w-dot 69,982  dry t/d

    Sample # 1 V 2.800 m/s -dH/dX, BP 20.244 m/km -dH/dX, NWT 14.036 m/km

    Sample # 2 V 2.800 m/s -dH/dX, BP 30.402 m/km -dH/dX, NWT 15.560 m/km

    Expansion Cw, % 65.0% #Pumps 4 Speed, % 100%

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    1000

    1500

    2000

    2500

    3000

    3500

    1300 1500 1700 1900 2100 2300 2500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings System Expansion - Sample 2

      .

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Expansion System 4 Pumps Operating @ 100 %

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    70/92

    11/11/2015 Toromocho Tailings Pipelines Slide 70

    Diameter  24.000 NPS Cw 60.00% % Capacity 61,170  dry t/d Sfac 1.100 

    Sample # 1 Q 2600.0 m3/h w-dot 2,564  dry t/h w-dot 61,537  dry t/d

    Sample # 2 Q 2600.0 m3/h w-dot 2,549  dry t/h w-dot 61,170  dry t/d

    Sample # 1 V 2.800 m/s -dH/dX, BP 13.744 m/km -dH/dX, NWT 12.670 m/km

    Sample # 2 V 2.800 m/s -dH/dX, BP 19.498 m/km -dH/dX, NWT 13.644 m/km

    Expansion Cw, % 60.0% #Pumps 4 Speed, % 100%

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    1000

    1500

    2000

    2500

    3000

    3500

    1300 1500 1700 1900 2100 2300 2500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings System Expansion - Sample 2

      .

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Expansion System 4 Pumps Operating @ 60 %

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    71/92

    11/11/2015 Toromocho Tailings Pipelines Slide 71

    Diameter  24.000 NPS Cw 60.00% % Capacity 36,702  dry t/d Sfac 1.100 

    Sample # 1 Q 1560.0 m3/h w-dot 1,538  dry t/h w-dot 36,922  dry t/d

    Sample # 2 Q 1560.0 m3/h w-dot 1,529  dry t/h w-dot 36,702  dry t/d

    Sample # 1 V 1.680 m/s -dH/dX, BP 7.272 m/km -dH/dX, NWT 4.991 m/km

    Sample # 2 V 1.680 m/s -dH/dX, BP 14.555 m/km -dH/dX, NWT 5.416 m/km

    Expansion Cw, % 60.0% #Pumps 4 Speed, % 60%

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    1000

    1500

    2000

    2500

    3000

    3500

    1300 1500 1700 1900 2100 2300 2500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings System Expansion - Sample 2

      .

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Expansion System 4 Pumps Operating @ 60 %

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    72/92

    11/11/2015 Toromocho Tailings Pipelines Slide 72

    Diameter  24.000 NPS Cw 64.00% % Capacity 40,885  dry t/d Sfac 1.100 

    Sample # 1 Q 1560.0 m3/h w-dot 1,715  dry t/h w-dot 41,159  dry t/d

    Sample # 2 Q 1560.0 m3/h w-dot 1,704  dry t/h w-dot 40,885  dry t/d

    Sample # 1 V 1.680 m/s -dH/dX, BP 12.884 m/km -dH/dX, NWT 5.442 m/km

    Sample # 2 V 1.680 m/s -dH/dX, BP 23.753 m/km -dH/dX, NWT 6.042 m/km

    Expansion Cw, % 64.0% #Pumps 4 Speed, % 60%

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    1000

    1500

    2000

    2500

    3000

    3500

    1300 1500 1700 1900 2100 2300 2500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings System Expansion - Sample 2

      .

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Expansion System 4 Pumps Operating @ 100 %

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    73/92

    11/11/2015 Toromocho Tailings Pipelines Slide 73

    Diameter  24.000 NPS Cw 68.80% % Capacity 77,370  dry t/d Sfac 1.100 

    Sample # 1 Q 2600.0 m3/h w-dot 3,248  dry t/h w-dot 77,959  dry t/d

    Sample # 2 Q 2600.0 m3/h w-dot 3,224  dry t/h w-dot 77,370  dry t/d

    Sample # 1 V 2.800 m/s -dH/dX, BP 34.202 m/km -dH/dX, NWT 15.713 m/km

    Sample # 2 V 2.800 m/s -dH/dX, BP 46.561 m/km -dH/dX, NWT 17.960 m/km

    Expansion Cw, % 68.8% #Pumps 4 Speed, % 100%

    0.001

    0.010

    0.100

    1.000

    10.000

    10 100 1000 10000 100000 1000000 10000000

             f

    Re 

    He = 0

    Rec

    1000

    1500

    2000

    2500

    3000

    3500

    1300 1500 1700 1900 2100 2300 2500

       T    h   r   o   u   g    h   p   u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings System Expansion - Sample 2

      .

    .

    .

     

    .

    .

    .

    .

    .

    .

    .

    .

     

    .

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Contingency

    Operating Ranges:

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    74/92

    11/11/2015 Toromocho Tailings Pipelines Slide 74

    1000

    2000

    3000

    4000

    5000

    6000

    7000

    1300 1800 2300 2800 3300 3800 4300 4800 5300 5800

       T    h   r   o   u   g    h   p

       u   t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Initital Toromocho Tailings Systems - Comparison

    62.0%

    63.0%

    Limiting Velocity

    Q 5.8 pumps

    61.0%

    64.0%

    65.0%

    66.0%

    67.0%

    68.0%

    69.0%

    70.0%

    Nominal

    Q 10 pumps

    Design Tonnage

    Q 8 pumps

    60.0%

    Limiting Velocity

    Nominal

    Design TonnageQ 4 pumps

    Design Tonnage

    Limiting Velocity

    Nominal Tonnage

    Operating Range

    Limiting Velocity

    Nominal Tonnage

    Design Tonnage

    Operating Ranges:

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    75/92

    11/11/2015 Toromocho Tailings Pipelines Slide 75

    0

    2000

    4000

    6000

    8000

    10000

    12000

    1000 2000 3000 4000 5000 6000 7000 8000 9000

       T    h   r   o   u   g    h   p   u

       t ,

        d   r   y

       t    /    h

    Flow, m3/h

    Toromocho Tailings Systems - Complete Operating Range

    62.0%

    63.0%

    Limiting Velocity

    Q 5.8 pumps

    61.0%

    64.0%

    65.0%

    66.0%

    67.0%

    68.0%

    69.0%

    70.0%

    Initial Nominal

    Q 10 pumps

    Initial Design Tonnage

    Q 8 pumps

    60.0%

    Limiting Velocity

    Exansion Nominal

    Expansion Design

    Q 4 pumps

    w-14 pump

    Total NominalTonnage

    Total Design Tonnage

    Initial Design Tonnage

    Initial Limiting Velocity

    Initial Nominal Tonnage

    Operating Ranges

    Expan Limiting Velocity

    Expan Nominal Tonnage

    Expan Design

    Tonnage

    Both @ Design Tonnage

    Both @ Nominal Tonnages

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    76/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    77/92

    i h l i Sl

    Expansion System SS Hydraulics

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    78/92

    11/11/2015 Toromocho Tailings Pipelines Slide 78

    Bingham Plastic Slurry

    Conventional Slurry

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    79/92

    Expansion System Mechanical Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    80/92

    11/11/2015 Toromocho Tailings Pipelines Slide 80

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    81/92

    Expansion System Mechanical Design

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    82/92

    11/11/2015 Toromocho Tailings Pipelines Slide 82

    Available space for the new discharge pipe

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    83/92

    Expansion System Mechanical DesignP/S West Side feed and discharge

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    84/92

    11/11/2015 Toromocho Tailings Pipelines Slide 84

    P/S West Side feed and discharge

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    85/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    86/92

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    87/92

    11/11/2015 Toromocho Tailings Pipelines Slide 87

    Expansion System Pipe Stress Analysis

    Toromocho Tailings Pipelines

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    88/92

    11/11/2015 Toromocho Tailings Pipelines Slide 88

    The expansion system pipe stress analysis was more straight forward than

    the work done for the original system

    • 4 pumps spaced far apart allow the discharge manifold to be more

    flexible

    • Elevated piping still required to avoid existing piping and structures

    under the platform

    • Only one discharge manifold

    • More lateral space

    • Pipe bends used to bring discharge to station floor for East side

    pumps increasing piping flexability

    Expansion Pipe Stress Analysis

    Pipe Stress Analysis

    Expansion System Plant Discharge

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    89/92

    11/11/2015 Toromocho Tailings Pipelines Slide 89

    Expansion System, Plant Discharge

    Acknowledgements

    Brian Peer:

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    90/92

    11/11/2015 Toromocho Tailings Pipelines Slide 90

    Brian Peer:

    Brian Peer is a Mechanical Engineer specializing

    in mechanical piping design and pipe stressanalysis.

    Brian Peer was responsible for the Toromocho

    Tailings Pipeline Pump Station Stress andFlexibility Analysis.

    Leroy Worthen:

    Mr. Worthen served as commissioning and

    start-up engineer for the project.

    Acknowledgements

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    91/92

    11/11/2015 Toromocho Tailings Pipelines Slide 91

    Dr. George Shou (presentation reviewer):

    VP and Chief engineer, BRASS EngineeringInternational, USA

    Dr. Shou has over 30 years experience in slurry

    pipeline engineering.

    He was the project manager for basic

    engineering, detailed engineering, construction

    support and commissioning. Wushan Copper

    tailings paste pipeline, 6km, 450 and 330mmOD, in China. The pipeline was successfully

    commissioned in September 2009.

  • 8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891

    92/92

    The End&Thank you