brassengineeringinternational 151112220903 lva1 app6891
TRANSCRIPT
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
1/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
2/92
11/11/2015 Toromocho Tailings Pipelines Slide 2
The Tailings Pipelines were designed in two phases:
Tailings Pipelines Project Overview
• Expansion Phase
• Design Completed: 2015
• Nominal Capacity: 54,000 dry t/d• Design Capacity: 70,000 dry t/d
• Initial Phase
• Design to Startup: 2009 to 2014
• Nominal Capacity: 124,000 dry t/d• Design Capacity: 155,000 dry t/d
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
3/92
11/11/2015 Toromocho Tailings Pipelines Slide 3
Tailings Pipelines Project Overview
Initial System Design• Located in the District of Morococha, Yauli Province, Junin Region,
Peru.
• The Toromocho project mines copper, molybdenum, and silver with
respective grades of 0.48%, 0.019%, and 6.88 grams per ton
• Ore Reserve is estimated to 1526 million metric tons
• Pump Station elevation is 4523 masl and terminates 4.7 km
distance at 4777 masl (up hill).
• Due to pressure requirements the pump station uses 10 of the
largest positive displacement pumps (8 + 2 mode) operating in
parallel• Due to number of pumps it is the largest pump station of its kind
• Estimated Annual production:
• One million metric tons of copper,
• Ten thousand metric tons of molybdenum
• Four million ounces of silver
• And ~ 44 million metric tons of tailings
Expansion System Design• ~26 million metric tons annually of tailings• Stand alone system adding four additional pumps operating in
parallel
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
4/92
11/11/2015 Toromocho Tailings Pipelines Slide 4
Initial Tailings Pipeline
Process Design Criteria:
• Scope: from flange on P/S suction headers• Capacity:
• Nominal = 5176 t/h
• Design = 6470 t/h
• Pump Station Elevation: 4,520 masl
• Highest Discharge Elevation:• Phase I: 4,777 masl
• Phase II: 4,890 masl
• Pipeline length:
• Phase I: 4,707 m
• Phase II: 5,400m
• Tailings Slurry Concentration:• Minimum = 69%
• Maximum = 71%
• Actual experience tailings thickened to 65%
• Design Life: 30 years
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
5/92
11/11/2015 Toromocho Tailings Pipelines Slide 5
Slurry Characteristics:
• Sample taken from Pilot Testing
•Solid’s SG:Sample 1 and 2 = 2.77 (used fordesign) to 2.92
• Handling Tests: Shutdown / Restart ability
are good, no serious problems areforeseen
Initial Tailings Pipeline
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
6/92
11/11/2015 Toromocho Tailings Pipelines Slide 6
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500 6000
T h r o u g h p u t , d
r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
62.0%
63.0%
Limiting Velocity
Q 5.8 pumps
61.0%
64.0%
65.0%
66.0%
67.0%
68.0%
69.0%
70.0%
Nominal
Q 10 pumps
Design Tonnage
Q 8 pumps
60.0%
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Initial System Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
7/92
11/11/2015 Toromocho Tailings Pipelines Slide 7
Diameter 34.000 NPS Cw 68.80% % Capacity 158,939 dry t/d Sfac 1.100
Sample # 1 Q 5400.0 m3/h w-dot 6,622 dry t/h w-dot 158,939 dry t/d
Sample # 2 Q 5400.0 m3/h w-dot 6,622 dry t/h w-dot 158,939 dry t/d
Sample # 1 V 2.792 m/s -dH/dX, BP 24.369 m/km -dH/dX, NWT 11.437 m/km
Sample # 2 V 2.792 m/s -dH/dX, BP 18.660 m/km -dH/dX, NWT 10.528 m/km
Initial Cw, % 68.8% #Pumps 10 Speed, % 100%
Initial System 10 Pumps Operating @ 100 %
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
8/92
11/11/2015 Toromocho Tailings Pipelines Slide 8
Diameter 34.000 NPS Cw 67.50% % Capacity 153,653 dry t/d Sfac 1.100
Sample # 1 Q 5400.0 m3/h w-dot 6,402 dry t/h w-dot 153,653 dry t/d
Sample # 2 Q 5400.0 m3/h w-dot 6,402 dry t/h w-dot 153,653 dry t/d
Sample # 1 V 2.792 m/s -dH/dX, BP 18.209 m/km -dH/dX, NWT 10.849 m/km
Sample # 2 V 2.792 m/s -dH/dX, BP 15.319 m/km -dH/dX, NWT 10.054 m/km
Initial Cw, % 67.5% #Pumps 10 Speed, % 100%
Initial System 10 Pumps Operating @ 100 %
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
NominalTonnage
Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
9/92
11/11/2015 Toromocho Tailings Pipelines Slide 9
Diameter 34.000 NPS Cw 60.00% % Capacity 125,946 dry t/d Sfac 1.100
Sample # 1 Q 5400.0 m3/h w-dot 5,248 dry t/h w-dot 125,946 dry t/d
Sample # 2 Q 5400.0 m3/h w-dot 5,248 dry t/h w-dot 125,946 dry t/d
Sample # 1 V 2.792 m/s -dH/dX, BP 8.877 m/km -dH/dX, NWT 8.747 m/km
Sample # 2 V 2.792 m/s -dH/dX, BP 8.584 m/km -dH/dX, NWT 8.351 m/km
Initial Cw, % 60.0% #Pumps 10 Speed, % 100%
Initial System 10 Pumps Operating @ 100 %
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
10/92
11/11/2015 Toromocho Tailings Pipelines Slide 10
Diameter 34.000 NPS Cw 60.00% % Capacity 73,049 dry t/d Sfac 1.100
Sample # 1 Q 3132.0 m3/h w-dot 3,044 dry t/h w-dot 73,049 dry t/d
Sample # 2 Q 3132.0 m3/h w-dot 3,044 dry t/h w-dot 73,049 dry t/d
Sample # 1 V 1.619 m/s -dH/dX, BP 3.633 m/km -dH/dX, NWT 3.257 m/km
Sample # 2 V 1.619 m/s -dH/dX, BP 3.731 m/km -dH/dX, NWT 3.095 m/km
Initial Cw, % 60.0% #Pumps 8 Speed, % 73%
Initial System 8 Pumps Operating @ 72.5 %
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
11/92
11/11/2015 Toromocho Tailings Pipelines Slide 11
Diameter 34.000 NPS Cw 67.00% % Capacity 87,964 dry t/d Sfac 1.100
Sample # 1 Q 3132.0 m3/h w-dot 3,665 dry t/h w-dot 87,964 dry t/d
Sample # 2 Q 3132.0 m3/h w-dot 3,665 dry t/h w-dot 87,964 dry t/d
Sample # 1 V 1.619 m/s -dH/dX, BP 13.402 m/km -dH/dX, NWT 4.018 m/km
Sample # 2 V 1.619 m/s -dH/dX, BP 10.830 m/km -dH/dX, NWT 3.722 m/km
Initial Cw, % 67.0% #Pumps 8 Speed, % 73%
Initial System 8 Pumps Operating @ 72.5 %
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
12/92
11/11/2015 Toromocho Tailings Pipelines Slide 12
Diameter 34.000 NPS Cw 68.80% % Capacity 127,151 dry t/d Sfac 1.100
Sample # 1 Q 4320.0 m3/h w-dot 5,298 dry t/h w-dot 127,151 dry t/d
Sample # 2 Q 4320.0 m3/h w-dot 5,298 dry t/h w-dot 127,151 dry t/d
Sample # 1 V 2.234 m/s -dH/dX, BP 23.053 m/km -dH/dX, NWT 7.672 m/km
Sample # 2 V 2.234 m/s -dH/dX, BP 16.932 m/km -dH/dX, NWT 7.060 m/km
Initial Cw, % 68.8% #Pumps 8 Speed, % 100%
Initial System 8 Pumps Operating @ 100 %
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
3000
3500
4000
4500
5000
5500
6000
6500
7000
2500 3000 3500 4000 4500 5000 5500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings System - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
13/92
11/11/2015 Toromocho Tailings Pipelines Slide 13
Pipeline Routing and Impoundment
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
14/92
11/11/2015 Toromocho Tailings Pipelines Slide 14
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
15/92
11/11/2015 Toromocho Tailings Pipelines Slide 15
Impoundment and Tailings Dam
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
16/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
17/92
11/11/2015 Toromocho Tailings Pipelines Slide 17
Impoundment and Tailings Dam
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
18/92
11/11/2015 Toromocho Tailings Pipelines Slide 18
Impoundment and Tailings Dam
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
19/92
11/11/2015 Toromocho Tailings Pipelines Slide 19
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
20/92
11/11/2015 Toromocho Tailings Pipelines Slide 20
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
21/92
11/11/2015 Toromocho Tailings Pipelines Slide 21
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
22/92
11/11/2015 Toromocho Tailings Pipelines Slide 22
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
23/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
24/92
11/11/2015 Toromocho Tailings Pipelines Slide 24
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
25/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
26/92
11/11/2015 Toromocho Tailings Pipelines Slide 26
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
27/92
11/11/2015 Toromocho Tailings Pipelines Slide 27
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
28/92
11/11/2015 Toromocho Tailings Pipelines Slide 28
Discharge Points
Di h P i t
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
29/92
11/11/2015 Toromocho Tailings Pipelines Slide 29
Discharge Points
Di h P i t
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
30/92
11/11/2015 Toromocho Tailings Pipelines Slide 30
Discharge Points
Di h P i t
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
31/92
11/11/2015 Toromocho Tailings Pipelines Slide 31
Discharge Points
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
32/92
11/11/2015 Toromocho Tailings Pipelines Slide 32
System Hydraulics
I iti l S t SS H d li
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
33/92
11/11/2015 Toromocho Tailings Pipelines Slide 33
Initial System SS Hydraulics
Conventional Slurry
I iti l S t SS H d li
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
34/92
11/11/2015 Toromocho Tailings Pipelines Slide 34
Initial System SS Hydraulics
Bingham Plastic Slurry
Conventional Slurry
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
35/92
11/11/2015 Toromocho Tailings Pipelines Slide 35
Pump Duty
• Geho: TZPM 2000 (largest PD pump)• Continuous Service
• Flow Capability: 655 m3/h each
•Initial System used 540 m3/h each
• Expansion System used 650 m3/h each
• Pressure Capability:
• Normal: 8,100 kPa
• w/ GLORES modification: 11,000 kPa
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
36/92
11/11/2015 Toromocho Tailings Pipelines Slide 36
Pump Station Design
Pump Station Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
37/92
11/11/2015 Toromocho Tailings Pipelines Slide 37
Pump Station Design
Pump Station Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
38/92
11/11/2015 Toromocho Tailings Pipelines Slide 38
Pump Station Design
Pump Station Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
39/92
11/11/2015 Toromocho Tailings Pipelines Slide 39
Pump Station Design
Pump Station Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
40/92
11/11/2015 Toromocho Tailings Pipelines Slide 40
Pump Station Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
41/92
11/11/2015 Toromocho Tailings Pipelines Slide 41
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
42/92
11/11/2015 Toromocho Tailings Pipelines Slide 42
Toromocho Tailings Pipelines
Several unique difficulties in Mechanical Design of Toromocho Tailings
Pump Station
• Tailings pump station is situated on an earthwork bench and the space
available for piping was not sufficient to accommodate the preferred
pump station design
• Pump station is located in harsh, mountainous conditions 4,520m above
sea level
• Pump station will experience high pressures and flows and the
possibility of large pressure fluctuations
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
43/92
11/11/2015 Toromocho Tailings Pipelines Slide 43
Toromocho Tailings Pipelines
Pipe Stress Analysis
Preferred Pump Discharge Arrangement
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
44/92
11/11/2015 Toromocho Tailings Pipelines Slide 44
Toromocho Tailings Pipelines
Preferred pump station layout
• Pump discharge will incorporate bends to take the pipe from the pump
discharge nozzle to the station floor. Once on the floor the piping will
connect to the anchored discharge manifold
• Piping is much easier to restrain because pipe supports can be mounted
directly to platforms on the floor
• Pipe bends between the discharge nozzle and the discharge manifoldcreate flexibility in the piping
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
45/92
11/11/2015 Toromocho Tailings Pipelines Slide 45
Toromocho Tailings Pipelines
The Toromocho Tailings Pump Station is located on an bench only about
40m wide
• BRASS developed a station arrangement in which the discharge manifold
is at the same elevation as the discharge nozzle
• Eliminated the space between the pump discharge and manifold taken
up by the two pipe bends
• Reduced piping flexibility to absorb temperature expansion andcontraction
Pipe Stress Analysis
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
46/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
47/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
48/92
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
49/92
11/11/2015 Toromocho Tailings Pipelines Slide 49
g p
This is a seemingly small change in length. When the Elastic
Modulus of the pipe is considered the force that can bedeveloped is easily enough to overstress piping and pump
nozzles if the system is too rigid.
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
50/92
11/11/2015 Toromocho Tailings Pipelines Slide 50
g p
The stiffness and location of pipe supports were carefully analyzed and
many iterations of the design were considered before a final solution was
reached
• Caesar II simulations were run to analyze the pipe stresses
• Two main over stress issues needed to be solved. Both issues were most
severe when low temperature pipe contraction was considered
• straight pump discharge lines pull the discharge manifold laterally
• large S-bend located after the discharge manifold stretched by the
contracting manifold
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
51/92
11/11/2015 Toromocho Tailings Pipelines Slide 51
g p
S-Bend
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
52/92
11/11/2015 Toromocho Tailings Pipelines Slide 52
g p
• To reduce stress on the manifold and pump nozzles, BRASS used flexible
supports which allow the manifold piping to move laterally as the pipe
contracts
•
Over stress issue at the S-bend not as easy to fix
• Possible solution: fix the manifold piping with very rigid supports
• Prevent the manifold piping from pulling on the S-bend as
strongly
• Has the effect of increasing the pump nozzle loads to
unacceptable levels
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
53/92
11/11/2015 Toromocho Tailings Pipelines Slide 53
g p
After a number of design iteration BRASS discovered that a special support
needed to be designed
• Support must be very rigid in the axial direction of the piping and
simultaneously flexible in the lateral direction
• Developed large plate oriented in the direction of the pipe axis
• Reinforcing ribs were added to achieve the required lateral and vertical
stiffness.
• Support is located near the middle of the discharge manifold
Pipe Stress Analysis
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
54/92
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
55/92
11/11/2015 Toromocho Tailings Pipelines Slide 55
Even small pressure pulsations can cause large deflection in piping if the
excitation frequency of the pump is close to the natural frequency of the
piping
• The first mode of vibration of the piping should be signifigantly greater
than the pump’s nominal frequency of excitation and must be greater
than the pump’s maximum excitation to ensure no resonant vibration
will take place
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
56/92
11/11/2015 Toromocho Tailings Pipelines Slide 56
Frequency of Excitation Calculation
60
)( nrpmi fe
e f : Frequency of Excitation (Hz)
i : Numbers of pistons
rpm : Rotations per minute
n : Fundamental frequency, n=1,2,3…..
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
57/92
11/11/2015 Toromocho Tailings Pipelines Slide 57
The pump’s nominal frequency of excitation is 4Hz and maximum
frequency of excitation is 5 Hz
• Upon first analysis BRASS found that the piping natural frequency was
too low, due to the flexible supports
• A number of iterations were made to adjust the stiffness and location of
supports to increase the piping natural frequency
• The piping natural frequency was increased to approximately 6Hz. This ishigh enough to prevent resonant vibration.
Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
58/92
11/11/2015 Toromocho Tailings Pipelines Slide 58
The stress and flexibility analysis of the Toromocho
Tailings Pump Station presented numerous unique
engineering challenges. BRASS Engineering
International was able to develop a design which
overcame the space limitations, harsh environment,
and possible harmonic resonance of the pipe causedby pressure pulsation.
Pipe Stress Analysis
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
59/92
11/11/2015 Toromocho Tailings Pipelines Slide 59
Pre-com, Com, Startup
Pre-com, Com, Startup
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
60/92
11/11/2015 Toromocho Tailings Pipelines Slide 60
Nitrogen charged Pulsation dampeners
Low, Medium, and High Pressure Pre-charge
Pre-com, Com, Startup
Early pre commissioning problems
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
61/92
11/11/2015 Toromocho Tailings Pipelines Slide 61
Urethane lined pipe was welded on causing the lining to be compromised
Early pre-commissioning problems
Pre-com, Com, Startup
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
62/92
11/11/2015 Toromocho Tailings Pipelines Slide 62
Photo shows field constructed “Y” on pump discharge line
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
63/92
11/11/2015 Toromocho Tailings Pipelines Slide 63
Expansion System Design
Expansion System Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
64/92
11/11/2015 Toromocho Tailings Pipelines Slide 64
Process Design Criteria:
• Scope: from bottom of thickeners• Capacity:
• Nominal = 2250 t/h
• Design = 2916 t/h
• Pump Station Elevation: 4,520 masl
• Highest Discharge Elevation: 4,777 masl
• Pipeline length: 4707 m
• Tailings Slurry Concentration:
• Minimum = 60.0%
• Maximum = 68.8%
• Based upon existing system the actual
experience tailings thickened to 65%
• Design Life: 5 years
Expansion System Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
65/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
66/92
Expansion System Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
67/92
11/11/2015 Toromocho Tailings Pipelines Slide 67
1000
1500
2000
2500
3000
3500
1300 1500 1700 1900 2100 2300 2500 2700
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings System Expansion - Sample 2
Q 2.4 pumps
62.0%
63.0%
Limiting Velocity
61.0%
64.0%
65.0%
66.0%
67.0%
68.0%
69.0%
70.0%
Nominal
Q 4 pumps
Design Tonnage
Q 3 pumps
60.0%
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Operating Range
pa s o Sys e es g
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
68/92
Expansion System 4 Pumps Operating @ 100 %
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
69/92
11/11/2015 Toromocho Tailings Pipelines Slide 69
Diameter 24.000 NPS Cw 65.00% % Capacity 69,982 dry t/d Sfac 1.100
Sample # 1 Q 2600.0 m3/h w-dot 2,936 dry t/h w-dot 70,464 dry t/d
Sample # 2 Q 2600.0 m3/h w-dot 2,916 dry t/h w-dot 69,982 dry t/d
Sample # 1 V 2.800 m/s -dH/dX, BP 20.244 m/km -dH/dX, NWT 14.036 m/km
Sample # 2 V 2.800 m/s -dH/dX, BP 30.402 m/km -dH/dX, NWT 15.560 m/km
Expansion Cw, % 65.0% #Pumps 4 Speed, % 100%
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
1000
1500
2000
2500
3000
3500
1300 1500 1700 1900 2100 2300 2500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings System Expansion - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Expansion System 4 Pumps Operating @ 100 %
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
70/92
11/11/2015 Toromocho Tailings Pipelines Slide 70
Diameter 24.000 NPS Cw 60.00% % Capacity 61,170 dry t/d Sfac 1.100
Sample # 1 Q 2600.0 m3/h w-dot 2,564 dry t/h w-dot 61,537 dry t/d
Sample # 2 Q 2600.0 m3/h w-dot 2,549 dry t/h w-dot 61,170 dry t/d
Sample # 1 V 2.800 m/s -dH/dX, BP 13.744 m/km -dH/dX, NWT 12.670 m/km
Sample # 2 V 2.800 m/s -dH/dX, BP 19.498 m/km -dH/dX, NWT 13.644 m/km
Expansion Cw, % 60.0% #Pumps 4 Speed, % 100%
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
1000
1500
2000
2500
3000
3500
1300 1500 1700 1900 2100 2300 2500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings System Expansion - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Expansion System 4 Pumps Operating @ 60 %
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
71/92
11/11/2015 Toromocho Tailings Pipelines Slide 71
Diameter 24.000 NPS Cw 60.00% % Capacity 36,702 dry t/d Sfac 1.100
Sample # 1 Q 1560.0 m3/h w-dot 1,538 dry t/h w-dot 36,922 dry t/d
Sample # 2 Q 1560.0 m3/h w-dot 1,529 dry t/h w-dot 36,702 dry t/d
Sample # 1 V 1.680 m/s -dH/dX, BP 7.272 m/km -dH/dX, NWT 4.991 m/km
Sample # 2 V 1.680 m/s -dH/dX, BP 14.555 m/km -dH/dX, NWT 5.416 m/km
Expansion Cw, % 60.0% #Pumps 4 Speed, % 60%
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
1000
1500
2000
2500
3000
3500
1300 1500 1700 1900 2100 2300 2500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings System Expansion - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Expansion System 4 Pumps Operating @ 60 %
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
72/92
11/11/2015 Toromocho Tailings Pipelines Slide 72
Diameter 24.000 NPS Cw 64.00% % Capacity 40,885 dry t/d Sfac 1.100
Sample # 1 Q 1560.0 m3/h w-dot 1,715 dry t/h w-dot 41,159 dry t/d
Sample # 2 Q 1560.0 m3/h w-dot 1,704 dry t/h w-dot 40,885 dry t/d
Sample # 1 V 1.680 m/s -dH/dX, BP 12.884 m/km -dH/dX, NWT 5.442 m/km
Sample # 2 V 1.680 m/s -dH/dX, BP 23.753 m/km -dH/dX, NWT 6.042 m/km
Expansion Cw, % 64.0% #Pumps 4 Speed, % 60%
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
1000
1500
2000
2500
3000
3500
1300 1500 1700 1900 2100 2300 2500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings System Expansion - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Expansion System 4 Pumps Operating @ 100 %
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
73/92
11/11/2015 Toromocho Tailings Pipelines Slide 73
Diameter 24.000 NPS Cw 68.80% % Capacity 77,370 dry t/d Sfac 1.100
Sample # 1 Q 2600.0 m3/h w-dot 3,248 dry t/h w-dot 77,959 dry t/d
Sample # 2 Q 2600.0 m3/h w-dot 3,224 dry t/h w-dot 77,370 dry t/d
Sample # 1 V 2.800 m/s -dH/dX, BP 34.202 m/km -dH/dX, NWT 15.713 m/km
Sample # 2 V 2.800 m/s -dH/dX, BP 46.561 m/km -dH/dX, NWT 17.960 m/km
Expansion Cw, % 68.8% #Pumps 4 Speed, % 100%
0.001
0.010
0.100
1.000
10.000
10 100 1000 10000 100000 1000000 10000000
f
Re
He = 0
Rec
1000
1500
2000
2500
3000
3500
1300 1500 1700 1900 2100 2300 2500
T h r o u g h p u t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings System Expansion - Sample 2
.
.
.
.
.
.
.
.
.
.
.
.
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Contingency
Operating Ranges:
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
74/92
11/11/2015 Toromocho Tailings Pipelines Slide 74
1000
2000
3000
4000
5000
6000
7000
1300 1800 2300 2800 3300 3800 4300 4800 5300 5800
T h r o u g h p
u t ,
d r y
t / h
Flow, m3/h
Initital Toromocho Tailings Systems - Comparison
62.0%
63.0%
Limiting Velocity
Q 5.8 pumps
61.0%
64.0%
65.0%
66.0%
67.0%
68.0%
69.0%
70.0%
Nominal
Q 10 pumps
Design Tonnage
Q 8 pumps
60.0%
Limiting Velocity
Nominal
Design TonnageQ 4 pumps
Design Tonnage
Limiting Velocity
Nominal Tonnage
Operating Range
Limiting Velocity
Nominal Tonnage
Design Tonnage
Operating Ranges:
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
75/92
11/11/2015 Toromocho Tailings Pipelines Slide 75
0
2000
4000
6000
8000
10000
12000
1000 2000 3000 4000 5000 6000 7000 8000 9000
T h r o u g h p u
t ,
d r y
t / h
Flow, m3/h
Toromocho Tailings Systems - Complete Operating Range
62.0%
63.0%
Limiting Velocity
Q 5.8 pumps
61.0%
64.0%
65.0%
66.0%
67.0%
68.0%
69.0%
70.0%
Initial Nominal
Q 10 pumps
Initial Design Tonnage
Q 8 pumps
60.0%
Limiting Velocity
Exansion Nominal
Expansion Design
Q 4 pumps
w-14 pump
Total NominalTonnage
Total Design Tonnage
Initial Design Tonnage
Initial Limiting Velocity
Initial Nominal Tonnage
Operating Ranges
Expan Limiting Velocity
Expan Nominal Tonnage
Expan Design
Tonnage
Both @ Design Tonnage
Both @ Nominal Tonnages
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
76/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
77/92
i h l i Sl
Expansion System SS Hydraulics
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
78/92
11/11/2015 Toromocho Tailings Pipelines Slide 78
Bingham Plastic Slurry
Conventional Slurry
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
79/92
Expansion System Mechanical Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
80/92
11/11/2015 Toromocho Tailings Pipelines Slide 80
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
81/92
Expansion System Mechanical Design
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
82/92
11/11/2015 Toromocho Tailings Pipelines Slide 82
Available space for the new discharge pipe
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
83/92
Expansion System Mechanical DesignP/S West Side feed and discharge
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
84/92
11/11/2015 Toromocho Tailings Pipelines Slide 84
P/S West Side feed and discharge
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
85/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
86/92
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
87/92
11/11/2015 Toromocho Tailings Pipelines Slide 87
Expansion System Pipe Stress Analysis
Toromocho Tailings Pipelines
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
88/92
11/11/2015 Toromocho Tailings Pipelines Slide 88
The expansion system pipe stress analysis was more straight forward than
the work done for the original system
• 4 pumps spaced far apart allow the discharge manifold to be more
flexible
• Elevated piping still required to avoid existing piping and structures
under the platform
• Only one discharge manifold
• More lateral space
• Pipe bends used to bring discharge to station floor for East side
pumps increasing piping flexability
Expansion Pipe Stress Analysis
Pipe Stress Analysis
Expansion System Plant Discharge
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
89/92
11/11/2015 Toromocho Tailings Pipelines Slide 89
Expansion System, Plant Discharge
Acknowledgements
Brian Peer:
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
90/92
11/11/2015 Toromocho Tailings Pipelines Slide 90
Brian Peer:
Brian Peer is a Mechanical Engineer specializing
in mechanical piping design and pipe stressanalysis.
Brian Peer was responsible for the Toromocho
Tailings Pipeline Pump Station Stress andFlexibility Analysis.
Leroy Worthen:
Mr. Worthen served as commissioning and
start-up engineer for the project.
Acknowledgements
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
91/92
11/11/2015 Toromocho Tailings Pipelines Slide 91
Dr. George Shou (presentation reviewer):
VP and Chief engineer, BRASS EngineeringInternational, USA
Dr. Shou has over 30 years experience in slurry
pipeline engineering.
He was the project manager for basic
engineering, detailed engineering, construction
support and commissioning. Wushan Copper
tailings paste pipeline, 6km, 450 and 330mmOD, in China. The pipeline was successfully
commissioned in September 2009.
-
8/20/2019 Brassengineeringinternational 151112220903 Lva1 App6891
92/92
The End&Thank you