boiler operation
DESCRIPTION
SOPTRANSCRIPT
Boiler Operation:Damper Opening: (cold state)
When the hot gases temperature at the cooler exhaust is at 350-400C then
10% inlet damper open
10% outlet damper open
90% by pass damper open
After 30 minutes
When temperature at cooler exhaust is at 450C then
20% inlet damper open
20% outlet damper open
80% by pass damper open
When the temperature at the super heater now reaches up to 400C then we take the boiler in line because our steam temperature & pressure reaches 310-350C and 1.2MPa respectively100% inlet damper open
100% outlet damper open
100% by pass damper closed
According to the careful estimation, opening of the damper with respect to time is enlisted as under:
Sr.NoOutlet Inlet Damper (%age) By Pass Damper (%age)Hot Gas Temperature (C)Time(min)
1109030
2208025045
3307030065
4406035085
55050400105
61000450120
Damper Opening(Hot State):When there is a stoppage for some hours, then the boiler still carries some temperature & pressure and in that case how, the damper opening will be executed .It is given as
Sr.NoOutlet Inlet Damper (%age) By Pass Damper (%age)Hot Gas Temperature (C)Time (min)
2208025015
3406030025
4604035035
5802040045
6100045060
Shut Down:-
Whenever there is a shutdown taken, the drains of steam lines are opened but the water should be there in the boiler so that shrinkage and other metallurgical effects can be avoided. Also the steam drum is filled with water, Hence the rusting effect is avoided to a larger extent.
On the other hand ,when there is a planned shut down and tubes are to be replaced, then boiler should be cooled down slowly under normal parameters. When the temperature goes down to the required or optimum value (40-50C) then drains will be opened followed by the cutting of the tubes for replacement.
Blow Downs:-
(They are installed on the headers and points)
Limitations:4-5 tons water is wasted for blow downs.
Dozing:
To attain parameter standards in boiler
To avoid scaling, corrosion
To improve efficiency
For smooth turbine operation
Drum:
Ph sphate (5-20)
Alkalivity(OH +ve)
PH
(10-12)
Hardness Removal Nil
To Remove O (.005)
For passivation of all boiler surfaces.
Drain valves are closed now
Auxiliary oil pump stops, Now the turbine is ready to be synchronized with the power plant.
Oil Pressures:
Lubricating oil pressure = 0.30MPa
Control Oil Pressure = 0.9MPa
Oil Temperature Inlet = 40~50C
Oil Temperature Outlet= 35~45C
Oil temperature should not be less than 35C
Maintain De-Aerator Vacuum = -0.080MPaMaintain Condenser Vacuum = -0.085~ -0.090MPa
Check vibrations of turbine front Bearing , turbine rear Bearing limits= 2~22m
Bearing Temperature should be 40~70 C
Axial displacement limits should be between (-0.3 ~ +0.3)
Condenser Hot level should be from (424 ~ 464mm)Steam Turbine
Before turbine start up:
1. cooling tower water level = 2800mm
2. Jet water tank level = 1500mm
3. Oil tank level = 234mm
4. De Aerator water level = 1600mm
Check all parameters and all drain valves should be opened.
Turbine Start Up:
Start the main auxiliary oil pump for 30 minutes before the turbine starts. Condensate pump and jet water pump start along with circulating water pump.
Reset turbine and ensure the both ESV are fully opened.
Open boiler stop valve from the headers
Open main stop valve of the turbine
Check steam temperature and pressure are normal.
Push Run button at 505 turbine control (turbine will start @ 600rpms limited) 600 rpm are maintained for 30 minutes
After 30 minutes, push ENTER + 1000+ ENTER=1000rpm
At 1000 rpm running time is 90 minutes. Next Enter+2600+Enter, the rpm will reach 2600 rpm
After 20 minutes, Enter +3000+ Enter, the speed will increased up to 3000rpm.
Before Pushing to the RUN command ensure the DCS system RESET and ALLOW Start Up and 505 system RESET
Reset guarding system , slightly move up the handle of emergency sliding valve, set the pressure of quick stop oil, turn clockwise start up control valve by 90(1839). Then start up oil pressure will slowly rise at 0.85MPa. Where quick stop control valve should be twirled counter clockwise. The quick stop oil pressure will slowly rise at 0.85MPa,and then start up control valve should be twirled counter clockwise by 90 with a result that start up oil pressure should become lower slowly and the closed quick stop valve opens gradually to full extent then Synchronization Process:
Inform the electrical operator to connect the grid after testing the governing valve tightness and the emergency breaker activation.
The operator shall focus on the air supply for the air sealing after synchronized,carefully monitor the sound and vibration, also dont forget to check the bearing oil temperature, the oil pressure of each system as well as the opening of governing/regulating valve. After every thing is going smooth , start the turbine protection.
When the generator was synchronized to the grid,emergency trip system should be put in to the practice. After grid connection, immediately load on 1000kw,for 10 minute and then increase the load to 3000kw at the speed of 150kw/min and maintaining it for the next 10 min. later on increase the load once time to 10000kw of the speed of 150kw/min
It was not recommended to perform no load running if without any special requirements. The generator shall be with 10% rated load at the moment connected with turbine. The back cylinder temperature will be less than 100C ~ 120C at no load running and less than 60C ~ 70C at no load running
Record all the parameters and on loading duration in the operation log book
Switch off the steam supply valve between the new steam and the bearing gland , and adjust the steam supply based on any steam leakage phenomenon at the turbine end.
Cooling water should be supplied to generator cooler and keep the inlet air temperature around 30~ 40C, If the inlet air temperature is over 40C.
Pay attention to adjust the normal position of the condensing water level(1/2 of the water level guage)
After the condensing water being test to be qualified , switch off the water discharge valve and open the valve to the de-aerator to supply water to the de-aerator.
Open the ejector pump, extract the condenser to vacuum.
Hot start time and vibration values:R/minminvibration value (mm)
speed accelerated 0~6003
0.03
warm unit 6005
speed accelerated 10003
warm unit 100010
speed accelerated 2600 5~60.10 over the critical state
warm unit 260050.03
speed accelerated 300030.03
Cold state start procedure:
Operations RPMTime (min)
speed rise to after driven the Rotor0~6002~3
check and Maintain60025~30
Smoothly raise speed to 600~10002~3
check and Maintain100025~30
Smoothly raise speed to 1000~26005~6
check and Maintain260015~20
speed accelerated to 2600~30002~3
Total6~95(min)
1. Switch on the AC and DC supplies from LTP Panel.
2. Turn on MK switch3. Start the DC field from Scada.
4. Check the generator voltage , shown on LTP Panel, when it reaches 6.3KV , generator is ready for synchronization.
5. From computer, select the breaker of generator. Give the synchronization command by clicking on synchronization start button
6. On synchroscope when the Dot reaches the mid point and turns green, that means voltage and frequency are matched and generator is synchronized.
7. Now turbine operator will start taking the load
8. Maintain the power factor around 0.95.