blue screen (1)
TRANSCRIPT
-
7/31/2019 Blue Screen (1)
1/47
Energy Audit andEnergy Efficiency improvement of Thermal Power Plant
Presentation by Group#B3 Anusha KolliSumit Kumar VijaySandeep Gurnani
Abhinav AgarwalMukund Chandak
-
7/31/2019 Blue Screen (1)
2/47
Presentation by Group#B3
Abraham Lincoln (1809-1865)
-
7/31/2019 Blue Screen (1)
3/47
-
7/31/2019 Blue Screen (1)
4/47
Presentation by Group#B3
Energy Audit
An energy audit is an inspection,survey and analysis of energy flows for energy conservation in a building,process or system to reduce theamount of energy input into the systemwithout negatively affecting theoutputs(s).
The energy audit evaluates theefficiency of all building and processsystems that use energy. The energyauditor starts at the utility meters,locating all energy sources coming intoa facility. The auditor then identifiesenergy streams for each fuel, quantifiesthose energy streams into discretefunctions, evaluates the efficiency of
each of those functions, and identifiesenergy and cost savings opportunities.
-
7/31/2019 Blue Screen (1)
5/47
Flow chart of Energy Audit process
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
6/47
Energy audit methodology
Historical reviewPre planned walkthrough sheet
Make a detailed list of data requirements
Compute the mass and energy flow
Energy conservation opportunities
Energy saving options
Cost analysis
Final recommendationPrioritizing
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
7/47
Energy consuming parts of a typical thermal power plant
Boiler Condenser
Cooling water from sea
Chimney
Generator
Steam Line
Turbine
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
8/47
Typical Plant Losses Typical Boiler Losses
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
9/47
Typical Cycle Losses
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
10/47
Energy Audit of BoilersPerformance of Boiler and APH be established by measuring exit flue gas
TemperatureHeat loss due to heat in dry flue gas.Heat loss due to moisture in as fired fuel.Heat loss due to moisture from burning of hydrogen in fuelHeat loss due to moisture in air.
Heat loss due to surface radiation and convection.Heat loss due to formation of carbon monoxide.Heat loss due to combustibles in bottom and fly ash
Recommendations: Analyze Flue Gas for Proper Air/Fuel Ratio
Install Economizer to Preheat Boiler Feed Water Direct Warmest Air to Combustion IntakeReplace Obsolete Burners With More Efficient Ones
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
11/47
Methods to improve boiler efficiency
Increasing boiler efficiencies by 1 to 3 percent equivalent to savings of $600,000
to $1,700,000 per 450 MW boiler.
Optimizing fuel/air ratio
Installing economizer Reducing scale and deposits
Reducing blow down
Operating at peak efficiency
Preheating combustion air
Switching from steam to air atomization
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
12/47
Optimizing fuel/air ratio:- If the fuel is too much as compared to the air, incomplete combustion occurs. This will give
rise to carbon soot deposits inside the combustion chamber or even over the boiler tubes
- When there is more air than is required for combustion, the extra air becomes heated upand is finally discharged out to the atmosphere thereby wasting heat. N0x formation mayalso take place
- However, there are reasons for putting in some extra air for combustion - to compensatefor imperfect burner fuel-air mixing conditions, air density changes, control system "slop",
burner maintenance, fuel composition and viscosity variation, and imperfect atomizingsteam or air controls for burners.
Installing Economizer:- This is only appropriate if there are insufficient heat transfer surfaces in the boiler. The
economizer tubes may contain either circulating boiler water or circulating feed water.Because the temperature of the exhaust gases can be quite high, the economizer tubes
may be fitted with safety valves to avoid over-pressure damage. Also temperature controlof feed water is required to prevent pump airlock. To avoid corrosion, careful design isneeded to ensure that the exhaust flue gas temperature does not drop below the dewpoint.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
13/47
Reducing scale and deposits:- For any boiler operation, this is a must. The safety of the boiler is at stake. Any
- scale or deposits will lead to reduced heat transfer that will eventually lead to- overheating, reduction of mechanical strength of the steel and finally to bursting
Reducing blow down:- Blow down of boiler water is discharging hot water into the drains.
- However, blow down is necessary to maintain the boiler water concentration of - dissolved solids that are necessary for conditioning the boiler water. The
- dissolved solids are necessary for preventing boiler corrosion and scaling.
- As steam is generated from the evaporation of water, the remaining water
- in the boiler becomes more and more concentrated. This must be drained away- during blowdown.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
14/47
Operating at peak efficiency:- When operating two or more boilers, improved efficiency can sometimes be
obtained by unequal sharing of the load so that the combined load operates atpeak efficiency
Preheating combustion air:- Any heat loss from the skin of the boiler to the boiler room can be utilized back
for combustion
- By preheating the intake air the combustion in the furnace becomes moreefficient
Switching from steam to air atomization:- For burners with steam atomization, switching to air atomization will naturally
- result in less steam consumption overall and better boiler efficiencies. This is- only applicable for heavy fuel oil burners
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
15/47
Energy Audit of steam Turbine cycles and its auxiliaries
Turbine cycle heat rateHP and IP cylinders efficiencyTurbine pressure surveyTTD & DCA of HP / LP heaters performance
Condenser performance i.e- Condenser back pressure after duly considering the effect of present C.W inlet temp.
C.W flow, heat load on condenser and air ingress to condenser vis--vis designconditions
- C.W side pressure drop in condenser
Cycle lossesPerformance of turbine glandsEjector performance
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
16/47
Energy Audit of steam turbine
Performance parameters need to be determined are (according to ASMEPTC 6)
heat rate (b) generator output (c) steam flow,
(d) steam rate (e) feed water flow
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
17/47
Energy Audit of CHP
Major equipment:- Crushers
- Conveyors
- Feeders
- Tipplers- Stacker-Reclaimers
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
18/47
Measurement andObservation to be made- Drive speed, belt speed, roller
conditions, belt conditions andbelt loading with respect to
design- Power consumption of equipments (load and no-loadconditions)
- Loss of energy in the coal instock yard due to spontaneouscombustion
- Equipments operations andthroughout comparison withdesign conditions
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
19/47
Data collection of CHP
Design details of overall CHP- Capacity, specific power consumption etc.
Process flow diagramTrack hoppers
- Number, length, capacity, power, layout etc.Paddle feeders- Number, capacity, travel, speed, power
Wagon tippler - Number, type, capacity, maximum weight, time cycle, motor rating
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
20/47
Crushers- Number, type, capacity, coal size at inlet and outlet, motor rating, power
consumption, number of vibrating feeders
Coal Design parameters and sizesBelt Conveyors- Capacity , number, speed, width, motor rating power consumption
Stacker Reclaimer - Quantity, capacity, travel speed. Number of buckets and length of boom, motor
rating
Other EquipmentsVibrating feeders, dust suppression system pumps , belt feeders,
dust extraction fans etc
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
21/47
Energy conservation possibilities
Performance improvement options:- Possibilities in Improving the throughput this is a major energy saving area
which offers substantial saving at minimum investment.
- Reducing the idling time.
- Increasing the loading.- Modifications and changes in coal feeding circuits.
- Need for automation and controls.
- Identification of combination of various least power consuming equipments andrecommending merit order operation.
- Use of natural daylight through conveyor galleries and use of fire resistanttranslucent sheet.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
22/47
-
7/31/2019 Blue Screen (1)
23/47
Presentation by Group#B3
Ash Handling Plant
Major Energy Consumers
Ash water pumps
Ash slurry series pumps
The contribution of wet ash handling plant in auxiliary power consumptionvaries between 1.5 to 2%Major Objectives in AHP
Evaluation of ash water ratio
Analysis of higher consumption of water if anyComparison of the ash water ratio with design value, P.G. Test value andprevious energy audit valuesEquipment's performance
-
7/31/2019 Blue Screen (1)
24/47
Data collection of AHP
Line diagramDetailed Specification pertaining to- Type
- Handling capacity
- Percentage ash collection rates- Fly ash and bottom ash extraction capacities
- Operating hours
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
25/47
PG test values/design values of - Coal parameters
- Ash generation
- Ash to water ratio
- Slurry velocities- No.of pumps involved
Energy consumption details
Water consumption details
Performance characteristic curves of all pumps
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
26/47
Operating parameters of AHP
Water supply rate
Water velocity
Discharge
HeadValve position
Temperature
Operating hours and schedule
Pressure drop in systemPump/motor speed
Load of the plant
Discharge throttle valve positionFlow control frequency
% loading of pump on flow andhead
% loading on motor
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
27/47
While conducting the energy audit of the pumping, the following aspects needto be explored in detail for Optimization / improving the ash to water ratios
- Possibilities of reducing the operating hours of the AHP- Adequacy of pipe sizes- Improvement of pumping systems and drives.- Use of energy efficient pumps
- Replacement of inefficient pumps
- Use of high efficiency motors
- High Performance Lubricants: The low temperature fluidity and high temperature
stability of high performance lubricants can increase energy efficiency byreducing frictional losses.
- Booster pump application
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
28/47
Electrical Systems
Transformers: Assessment of the health & Transformer load loss of GT, UAT, Station Servicetransformers etcIdentification of possible Energy conservation options in this area
Motors: Assessment of Loading condition of HT and LT motors of Boiler area, Turbine area andBalance of Plant area
Assessment of operating parameters like load variation, Power factor, of HT and LTmotors consuming power more than 50 KWIdentification of possible Energy conservation options in this area (with latest techniques)Recommendations:
Replace Over-Size Motors and Pumps with Optimum SizeUtilize Energy-Efficient Belts and Other Improved MechanismsUse Most Efficient Type of Electric Motor
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
29/47
-
7/31/2019 Blue Screen (1)
30/47
Energy Audit of BoP
Compressed Air system:Free Air Delivery i.e. Capacity evaluation of the Plant and Instrument air compressorsChecking volumetric efficiency of compressors
Assessment of compressed air leakage quantity
Assessment of Energy performance of the air compressors/ specific power consumptionStudy of the compressed air network and suggest suitable energy savingoptionsRecommendations:
Install Compressor Air Intakes in Coolest locationsReduce the Pressure of Compressed Air to the Minimum RequiredEliminate Leaks in Inert Gas and Compressed Air Lines/Valves
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
31/47
Ash Plant:Performance of ash Slurry pumps through power measurement and flow measurement
Ash water ratio assessment and recommendations for optimization in water and power consumption
Cooling Tower Performance: It shall include establishment of Liquid/Gas ratioFan efficiency as the ratio of shaft power developed and the work done by the fanCooling Tower Effectiveness, approach and range.Cooling capacity.
Coal Handling Plant:
Input Power measurement of all the key equipment of the CHP area like: Paddlefeeders, Conveyors, Stacker & Re-claimer, Wagon Tipplers, Crushers,
Establishment of specific energy performance indicators.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
32/47
Presentation by Group#B3
Instrumentation and control
Evaluate the instrumentation available in the plant and identify the locations here onlinemeasurements are necessary for efficiency calculations however unavailable
Recommendation regarding type of instrument, installation details, make etc.
Measuring instrumentation at coal handling plant, ash handling system, Raw water andwaste water system
Thermal Insulation including radiation losses:
Heat loss calculationInsulation of Boiler, Air and Flue gas path and Steam pipingSurface temperature measurement at the damaged and Hot spot area by infraredtemperature indicator.Estimation of Heat loss in the hot spots and damaged insulation area
DM PlantCapacity utilization and power consumption of all major drives.Performance evaluation of pumps.
-
7/31/2019 Blue Screen (1)
33/47
Presentation by Group#B3
Cooling water system
Assessment of cooling tower capacity and efficiency / effectiveness
Evaluate circulating water pump flow rate, head developed, pressure of pumping systemand power consumption
Assessment of condenser heat load, deviation indicated in respect of the CW pumpperformance
Water circulation, condenser efficiency, and turbine heat rate
Assessment of Vacuum system and fan performanceFire Fighting system
Input Power measurement of all the key equipment of the Fire system like hydrant, spray(Electric & Diesel),Jockey Pump, Booster PumpEstablishment of specific energy performance indicators
APC & performanceEvaluation of unit auxiliary power consumption & performance including specific energyConsumption ( SEC) of critical drives where output parameters is available on line, coolingwater pumps, CHP (including Performance of Locomotives, Loaders, Dozers, Proclaim andtipplers), AHP, FOPH, WTP and Cooling Towers using power analyzers.
-
7/31/2019 Blue Screen (1)
34/47
Water system
Presentation by Group#B3
Water consumption in a coal based thermal power plant
Area Quantity with ashwater recycling(m 3 /hr)
Consumption(m 3 /MW)
%
Ash handling 4180 2.0 41.4
Cooling towers 3270 1.5 30.4
DM water 260 0.13 2.6
Drinking water (colony +plant)
640 0.32 6.3
Coal handling 130 0.065 1.3
Fire fighting 476 0.37 4.7Others 1334 0.66 13.2
total 10090 5.0 100
-
7/31/2019 Blue Screen (1)
35/47
A thermal power plant of 210 MW capacity recycles approximately 2000m3/hr ash water.
Reducing water consumption from 5.86 liter/kWh to 4.9 liter/kWh resultsin reduction of 16 percent in water consumption and savings of Rs.15.8million/annum in water bill
By systematic water audit and quantifying water flows at each pumpingstation, one can carry out water balance with a reasonable accuracy.
Based on water audit studies in a number of thermal power stations,some of the measures can be taken which will give major savings both in
terms of water and Energy
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
36/47
Measures
Optimizing ash water ratioRecycling ash water from ash dyke
Increasing cycles of concentration (COC)
Reducing drinking water consumption
Reducing leaks and over flows
Installation of effluent treatment plant
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
37/47
Optimizing ash water ratio
In wet ash handling power plants, about 50-60 percent of water isconsumed just for ash handling.
Typical design ash water ratios are around 1:5 for fly ash and 1:8 for bottom ash. However, the actual combined ash water ratios are around1:20.
For every percent reduction of ash water ratio, there is a saving potentialof 60 m3/hr of water. In addition to water savings, the associated auxiliarypower consumption reduction would be 0.2 MU/annum for every ashwater ratio reduction
After initiating water conservation measures, many thermal power plantshave brought down their ash water ratios to a reasonable level to 1:10 to1:12.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
38/47
Recycling ash water from ash dyke
About 60 percent of water is consumed for ash handling purpose alone.The ash slurry is sent to ash dykes, which are normally located about 14-15 km away from the main power plant. After the ash gets settled in theash dyke, the clear water can be recycled. This water can be re-used for ash handling purpose after minor treatment (if necessary).
A thermal power plant of 210 MW capacity recycles approximately 2000m3/hr ash water. By reducing water consumption from 5.86 liter/kWh to4.9 liter/kWh results in reduction of 16 percent in water consumption andsavings of Rs. 15.8 million/annum in water bill (@ Rs. 1/kL of raw water).
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
39/47
Increasing cycles of concentration (COC)
The maximum water loss in the thermal power plants is in the cooling towers,in the form of evaporation. We need around 180 m3/hr cooling water flow tothe condenser to generate 1 MW.Expected evaporation ratio for every 1 MW of power generation is 2.6 m3/hr.For a 210 MW power plant, the expected evaporation loss would be 550m3/hr. To compensate this evaporation loss, the blow down losses and driftneed to provide make up water Normally the cooling towers are designed for a COC(ratio of dissolved solidsin circulating water to make up water) of around 3. To keep COC of 3, weneed to provide a blow down of around 275 m3/hr, for a 210 MW power plant.By increasing COC, the blow down quantity can be reduced. By externalwater treatment and adding water treatment chemicals, COC of even 10 canbe reached. By increasing COC from 3 to 10, we can reduce the blow downquantity drastically from 275 m3/hr to30 m3/hr, which is a savings of 88percent.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
40/47
Reducing leaks and over flows
Lot of water leaks from Valves, Flanges, Taps, Fire fighting hoses, under ground fire fighting lines, cooling tower basin, gardening hoses etc takesplace
Overflows from cooling towers of AC plants, Air washers, and Overheadtanks due to non-functioning of float systems are also there
Huge water leaks from the condenser pipe ducts are noticed.
By bringing underground fire fighting lines to over ground, attendingvarious water leaks, providing ball and cock float systems for overheadtanks and smaller cooling towers, 3-5 percent water consumption can
easily be reduced.
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
41/47
Installation of effluent treatment plant
A typical thermal power plant will have a 3-4 main drains. All this drainwater gets collected and finally goes out of the plant boundary.The measured drain quantities alone are found to be in the range of 800-1000 m3/hr.
By installing effluent water treatment plants and recycling this water for
the ash handling purpose, 80-90 percent of this water can be saved.
Presentation by Group#B3
Based on the water flows measurements in different thermal power stations and comparing them with design values and practically achievablefigures, savings worth Rs. 3.3 crore/annum, equivalent to 40 percent water use reduction have been identifiedSince there is a close nexus between water and energy, energy savings to
the tune of 3.57 MU/annum is also identified
.
Potential
-
7/31/2019 Blue Screen (1)
42/47
Total Electrical System Audit Including Lighting
Assessment of the loading pattern of installed transformer to identify measures for reduction of lossesPower consumption by each AC system by using power measurement analyzersincluding Cooling effect and humidityPerformance of air compressors by using power measurement analyzersElectrical parameters like current, voltage, power factor and power by using power
measurement analyzers Assessment of health of capacitors and adequacy of the existing VAR compensationsystemHT/LT motor consuming power more than 50 KW need to be checked for measuringelectrical parameters and performanceLighting of Main plant including office building lux measurement and power consumption(day/night phase wise)Distribution lossesHarmonic analysisIdentification of Energy Conservation opportunities
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
43/47
Cost Analysis of Heat Exchanger
Presentation by Group#B3
Cost of Heat Exchanger, Pump, Piping ,Insulation and Storage Tank: Rs1,65,000(Approximate)
COP of Refrigerator increases by roughly 15%.Savings:308 units per month
Savings from Water Heaters : 2928 units(Replacing 9 geysers)
Total Monthly Savings:3236 unitsTotal Monthly Savings in Rupees: Rs 18,768
-
7/31/2019 Blue Screen (1)
44/47
Cost analysis
Presentation by Group#B3
S.No Recommended measure Electricitysaved per month
Savings inRs per month
Capitalinvestment
Pay backperiod
1 Use solar water heater instead of geyser
3600Kwh 20,880 7,80,000 3 years
2 Use automatic washingmachine instead of manual
48Kwh 278.4 10,075 3.1years
-
7/31/2019 Blue Screen (1)
45/47
Final recommendation
Heat Exchanger must be implemented, as its payback period is least andeffectiveness highest.
Solar Water Heaters are generally efficient but water temperatures would
slightly decrease in the rainy season.
Automatic washing machines saves more energy and its payback periodis also less. In the long run they are more efficient than manual machines.
The total amount of electricity that can be saved=6884 Kwh per month.Roughly Rs40,000
Presentation by Group#B3
-
7/31/2019 Blue Screen (1)
46/47
References
Energy Audit done Energo Engg Projects Ltd at Kolaghat unit ASME standards (PTC)
Wikipedia
www.google.com
www.sciencedirect.com
www.googlesholar.com
www.cea.nic.in
www.actsys.com
www.indiapower.org
www.iea-estap.org
http://www.reduct.com/news/BoilerEfficiency1.ht m
Presentation by Group#B3
http://www.google.com/http://www.sciencedirect.com/http://www.googlesholor.com/http://www.cea.nic.in/http://www.actsys.com/http://www.indiapower.org/http://www.iea-estap.org/http://www.reduct.com/news/BoilerEfficiency1.htmhttp://www.reduct.com/news/BoilerEfficiency1.htmhttp://www.iea-estap.org/http://www.indiapower.org/http://www.actsys.com/http://www.cea.nic.in/http://www.googlesholor.com/http://www.sciencedirect.com/http://www.google.com/ -
7/31/2019 Blue Screen (1)
47/47
THANK YOU