blue screen (1)

Upload: royaladdicted

Post on 04-Apr-2018

222 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/31/2019 Blue Screen (1)

    1/47

    Energy Audit andEnergy Efficiency improvement of Thermal Power Plant

    Presentation by Group#B3 Anusha KolliSumit Kumar VijaySandeep Gurnani

    Abhinav AgarwalMukund Chandak

  • 7/31/2019 Blue Screen (1)

    2/47

    Presentation by Group#B3

    Abraham Lincoln (1809-1865)

  • 7/31/2019 Blue Screen (1)

    3/47

  • 7/31/2019 Blue Screen (1)

    4/47

    Presentation by Group#B3

    Energy Audit

    An energy audit is an inspection,survey and analysis of energy flows for energy conservation in a building,process or system to reduce theamount of energy input into the systemwithout negatively affecting theoutputs(s).

    The energy audit evaluates theefficiency of all building and processsystems that use energy. The energyauditor starts at the utility meters,locating all energy sources coming intoa facility. The auditor then identifiesenergy streams for each fuel, quantifiesthose energy streams into discretefunctions, evaluates the efficiency of

    each of those functions, and identifiesenergy and cost savings opportunities.

  • 7/31/2019 Blue Screen (1)

    5/47

    Flow chart of Energy Audit process

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    6/47

    Energy audit methodology

    Historical reviewPre planned walkthrough sheet

    Make a detailed list of data requirements

    Compute the mass and energy flow

    Energy conservation opportunities

    Energy saving options

    Cost analysis

    Final recommendationPrioritizing

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    7/47

    Energy consuming parts of a typical thermal power plant

    Boiler Condenser

    Cooling water from sea

    Chimney

    Generator

    Steam Line

    Turbine

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    8/47

    Typical Plant Losses Typical Boiler Losses

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    9/47

    Typical Cycle Losses

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    10/47

    Energy Audit of BoilersPerformance of Boiler and APH be established by measuring exit flue gas

    TemperatureHeat loss due to heat in dry flue gas.Heat loss due to moisture in as fired fuel.Heat loss due to moisture from burning of hydrogen in fuelHeat loss due to moisture in air.

    Heat loss due to surface radiation and convection.Heat loss due to formation of carbon monoxide.Heat loss due to combustibles in bottom and fly ash

    Recommendations: Analyze Flue Gas for Proper Air/Fuel Ratio

    Install Economizer to Preheat Boiler Feed Water Direct Warmest Air to Combustion IntakeReplace Obsolete Burners With More Efficient Ones

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    11/47

    Methods to improve boiler efficiency

    Increasing boiler efficiencies by 1 to 3 percent equivalent to savings of $600,000

    to $1,700,000 per 450 MW boiler.

    Optimizing fuel/air ratio

    Installing economizer Reducing scale and deposits

    Reducing blow down

    Operating at peak efficiency

    Preheating combustion air

    Switching from steam to air atomization

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    12/47

    Optimizing fuel/air ratio:- If the fuel is too much as compared to the air, incomplete combustion occurs. This will give

    rise to carbon soot deposits inside the combustion chamber or even over the boiler tubes

    - When there is more air than is required for combustion, the extra air becomes heated upand is finally discharged out to the atmosphere thereby wasting heat. N0x formation mayalso take place

    - However, there are reasons for putting in some extra air for combustion - to compensatefor imperfect burner fuel-air mixing conditions, air density changes, control system "slop",

    burner maintenance, fuel composition and viscosity variation, and imperfect atomizingsteam or air controls for burners.

    Installing Economizer:- This is only appropriate if there are insufficient heat transfer surfaces in the boiler. The

    economizer tubes may contain either circulating boiler water or circulating feed water.Because the temperature of the exhaust gases can be quite high, the economizer tubes

    may be fitted with safety valves to avoid over-pressure damage. Also temperature controlof feed water is required to prevent pump airlock. To avoid corrosion, careful design isneeded to ensure that the exhaust flue gas temperature does not drop below the dewpoint.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    13/47

    Reducing scale and deposits:- For any boiler operation, this is a must. The safety of the boiler is at stake. Any

    - scale or deposits will lead to reduced heat transfer that will eventually lead to- overheating, reduction of mechanical strength of the steel and finally to bursting

    Reducing blow down:- Blow down of boiler water is discharging hot water into the drains.

    - However, blow down is necessary to maintain the boiler water concentration of - dissolved solids that are necessary for conditioning the boiler water. The

    - dissolved solids are necessary for preventing boiler corrosion and scaling.

    - As steam is generated from the evaporation of water, the remaining water

    - in the boiler becomes more and more concentrated. This must be drained away- during blowdown.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    14/47

    Operating at peak efficiency:- When operating two or more boilers, improved efficiency can sometimes be

    obtained by unequal sharing of the load so that the combined load operates atpeak efficiency

    Preheating combustion air:- Any heat loss from the skin of the boiler to the boiler room can be utilized back

    for combustion

    - By preheating the intake air the combustion in the furnace becomes moreefficient

    Switching from steam to air atomization:- For burners with steam atomization, switching to air atomization will naturally

    - result in less steam consumption overall and better boiler efficiencies. This is- only applicable for heavy fuel oil burners

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    15/47

    Energy Audit of steam Turbine cycles and its auxiliaries

    Turbine cycle heat rateHP and IP cylinders efficiencyTurbine pressure surveyTTD & DCA of HP / LP heaters performance

    Condenser performance i.e- Condenser back pressure after duly considering the effect of present C.W inlet temp.

    C.W flow, heat load on condenser and air ingress to condenser vis--vis designconditions

    - C.W side pressure drop in condenser

    Cycle lossesPerformance of turbine glandsEjector performance

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    16/47

    Energy Audit of steam turbine

    Performance parameters need to be determined are (according to ASMEPTC 6)

    heat rate (b) generator output (c) steam flow,

    (d) steam rate (e) feed water flow

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    17/47

    Energy Audit of CHP

    Major equipment:- Crushers

    - Conveyors

    - Feeders

    - Tipplers- Stacker-Reclaimers

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    18/47

    Measurement andObservation to be made- Drive speed, belt speed, roller

    conditions, belt conditions andbelt loading with respect to

    design- Power consumption of equipments (load and no-loadconditions)

    - Loss of energy in the coal instock yard due to spontaneouscombustion

    - Equipments operations andthroughout comparison withdesign conditions

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    19/47

    Data collection of CHP

    Design details of overall CHP- Capacity, specific power consumption etc.

    Process flow diagramTrack hoppers

    - Number, length, capacity, power, layout etc.Paddle feeders- Number, capacity, travel, speed, power

    Wagon tippler - Number, type, capacity, maximum weight, time cycle, motor rating

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    20/47

    Crushers- Number, type, capacity, coal size at inlet and outlet, motor rating, power

    consumption, number of vibrating feeders

    Coal Design parameters and sizesBelt Conveyors- Capacity , number, speed, width, motor rating power consumption

    Stacker Reclaimer - Quantity, capacity, travel speed. Number of buckets and length of boom, motor

    rating

    Other EquipmentsVibrating feeders, dust suppression system pumps , belt feeders,

    dust extraction fans etc

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    21/47

    Energy conservation possibilities

    Performance improvement options:- Possibilities in Improving the throughput this is a major energy saving area

    which offers substantial saving at minimum investment.

    - Reducing the idling time.

    - Increasing the loading.- Modifications and changes in coal feeding circuits.

    - Need for automation and controls.

    - Identification of combination of various least power consuming equipments andrecommending merit order operation.

    - Use of natural daylight through conveyor galleries and use of fire resistanttranslucent sheet.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    22/47

  • 7/31/2019 Blue Screen (1)

    23/47

    Presentation by Group#B3

    Ash Handling Plant

    Major Energy Consumers

    Ash water pumps

    Ash slurry series pumps

    The contribution of wet ash handling plant in auxiliary power consumptionvaries between 1.5 to 2%Major Objectives in AHP

    Evaluation of ash water ratio

    Analysis of higher consumption of water if anyComparison of the ash water ratio with design value, P.G. Test value andprevious energy audit valuesEquipment's performance

  • 7/31/2019 Blue Screen (1)

    24/47

    Data collection of AHP

    Line diagramDetailed Specification pertaining to- Type

    - Handling capacity

    - Percentage ash collection rates- Fly ash and bottom ash extraction capacities

    - Operating hours

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    25/47

    PG test values/design values of - Coal parameters

    - Ash generation

    - Ash to water ratio

    - Slurry velocities- No.of pumps involved

    Energy consumption details

    Water consumption details

    Performance characteristic curves of all pumps

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    26/47

    Operating parameters of AHP

    Water supply rate

    Water velocity

    Discharge

    HeadValve position

    Temperature

    Operating hours and schedule

    Pressure drop in systemPump/motor speed

    Load of the plant

    Discharge throttle valve positionFlow control frequency

    % loading of pump on flow andhead

    % loading on motor

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    27/47

    While conducting the energy audit of the pumping, the following aspects needto be explored in detail for Optimization / improving the ash to water ratios

    - Possibilities of reducing the operating hours of the AHP- Adequacy of pipe sizes- Improvement of pumping systems and drives.- Use of energy efficient pumps

    - Replacement of inefficient pumps

    - Use of high efficiency motors

    - High Performance Lubricants: The low temperature fluidity and high temperature

    stability of high performance lubricants can increase energy efficiency byreducing frictional losses.

    - Booster pump application

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    28/47

    Electrical Systems

    Transformers: Assessment of the health & Transformer load loss of GT, UAT, Station Servicetransformers etcIdentification of possible Energy conservation options in this area

    Motors: Assessment of Loading condition of HT and LT motors of Boiler area, Turbine area andBalance of Plant area

    Assessment of operating parameters like load variation, Power factor, of HT and LTmotors consuming power more than 50 KWIdentification of possible Energy conservation options in this area (with latest techniques)Recommendations:

    Replace Over-Size Motors and Pumps with Optimum SizeUtilize Energy-Efficient Belts and Other Improved MechanismsUse Most Efficient Type of Electric Motor

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    29/47

  • 7/31/2019 Blue Screen (1)

    30/47

    Energy Audit of BoP

    Compressed Air system:Free Air Delivery i.e. Capacity evaluation of the Plant and Instrument air compressorsChecking volumetric efficiency of compressors

    Assessment of compressed air leakage quantity

    Assessment of Energy performance of the air compressors/ specific power consumptionStudy of the compressed air network and suggest suitable energy savingoptionsRecommendations:

    Install Compressor Air Intakes in Coolest locationsReduce the Pressure of Compressed Air to the Minimum RequiredEliminate Leaks in Inert Gas and Compressed Air Lines/Valves

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    31/47

    Ash Plant:Performance of ash Slurry pumps through power measurement and flow measurement

    Ash water ratio assessment and recommendations for optimization in water and power consumption

    Cooling Tower Performance: It shall include establishment of Liquid/Gas ratioFan efficiency as the ratio of shaft power developed and the work done by the fanCooling Tower Effectiveness, approach and range.Cooling capacity.

    Coal Handling Plant:

    Input Power measurement of all the key equipment of the CHP area like: Paddlefeeders, Conveyors, Stacker & Re-claimer, Wagon Tipplers, Crushers,

    Establishment of specific energy performance indicators.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    32/47

    Presentation by Group#B3

    Instrumentation and control

    Evaluate the instrumentation available in the plant and identify the locations here onlinemeasurements are necessary for efficiency calculations however unavailable

    Recommendation regarding type of instrument, installation details, make etc.

    Measuring instrumentation at coal handling plant, ash handling system, Raw water andwaste water system

    Thermal Insulation including radiation losses:

    Heat loss calculationInsulation of Boiler, Air and Flue gas path and Steam pipingSurface temperature measurement at the damaged and Hot spot area by infraredtemperature indicator.Estimation of Heat loss in the hot spots and damaged insulation area

    DM PlantCapacity utilization and power consumption of all major drives.Performance evaluation of pumps.

  • 7/31/2019 Blue Screen (1)

    33/47

    Presentation by Group#B3

    Cooling water system

    Assessment of cooling tower capacity and efficiency / effectiveness

    Evaluate circulating water pump flow rate, head developed, pressure of pumping systemand power consumption

    Assessment of condenser heat load, deviation indicated in respect of the CW pumpperformance

    Water circulation, condenser efficiency, and turbine heat rate

    Assessment of Vacuum system and fan performanceFire Fighting system

    Input Power measurement of all the key equipment of the Fire system like hydrant, spray(Electric & Diesel),Jockey Pump, Booster PumpEstablishment of specific energy performance indicators

    APC & performanceEvaluation of unit auxiliary power consumption & performance including specific energyConsumption ( SEC) of critical drives where output parameters is available on line, coolingwater pumps, CHP (including Performance of Locomotives, Loaders, Dozers, Proclaim andtipplers), AHP, FOPH, WTP and Cooling Towers using power analyzers.

  • 7/31/2019 Blue Screen (1)

    34/47

    Water system

    Presentation by Group#B3

    Water consumption in a coal based thermal power plant

    Area Quantity with ashwater recycling(m 3 /hr)

    Consumption(m 3 /MW)

    %

    Ash handling 4180 2.0 41.4

    Cooling towers 3270 1.5 30.4

    DM water 260 0.13 2.6

    Drinking water (colony +plant)

    640 0.32 6.3

    Coal handling 130 0.065 1.3

    Fire fighting 476 0.37 4.7Others 1334 0.66 13.2

    total 10090 5.0 100

  • 7/31/2019 Blue Screen (1)

    35/47

    A thermal power plant of 210 MW capacity recycles approximately 2000m3/hr ash water.

    Reducing water consumption from 5.86 liter/kWh to 4.9 liter/kWh resultsin reduction of 16 percent in water consumption and savings of Rs.15.8million/annum in water bill

    By systematic water audit and quantifying water flows at each pumpingstation, one can carry out water balance with a reasonable accuracy.

    Based on water audit studies in a number of thermal power stations,some of the measures can be taken which will give major savings both in

    terms of water and Energy

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    36/47

    Measures

    Optimizing ash water ratioRecycling ash water from ash dyke

    Increasing cycles of concentration (COC)

    Reducing drinking water consumption

    Reducing leaks and over flows

    Installation of effluent treatment plant

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    37/47

    Optimizing ash water ratio

    In wet ash handling power plants, about 50-60 percent of water isconsumed just for ash handling.

    Typical design ash water ratios are around 1:5 for fly ash and 1:8 for bottom ash. However, the actual combined ash water ratios are around1:20.

    For every percent reduction of ash water ratio, there is a saving potentialof 60 m3/hr of water. In addition to water savings, the associated auxiliarypower consumption reduction would be 0.2 MU/annum for every ashwater ratio reduction

    After initiating water conservation measures, many thermal power plantshave brought down their ash water ratios to a reasonable level to 1:10 to1:12.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    38/47

    Recycling ash water from ash dyke

    About 60 percent of water is consumed for ash handling purpose alone.The ash slurry is sent to ash dykes, which are normally located about 14-15 km away from the main power plant. After the ash gets settled in theash dyke, the clear water can be recycled. This water can be re-used for ash handling purpose after minor treatment (if necessary).

    A thermal power plant of 210 MW capacity recycles approximately 2000m3/hr ash water. By reducing water consumption from 5.86 liter/kWh to4.9 liter/kWh results in reduction of 16 percent in water consumption andsavings of Rs. 15.8 million/annum in water bill (@ Rs. 1/kL of raw water).

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    39/47

    Increasing cycles of concentration (COC)

    The maximum water loss in the thermal power plants is in the cooling towers,in the form of evaporation. We need around 180 m3/hr cooling water flow tothe condenser to generate 1 MW.Expected evaporation ratio for every 1 MW of power generation is 2.6 m3/hr.For a 210 MW power plant, the expected evaporation loss would be 550m3/hr. To compensate this evaporation loss, the blow down losses and driftneed to provide make up water Normally the cooling towers are designed for a COC(ratio of dissolved solidsin circulating water to make up water) of around 3. To keep COC of 3, weneed to provide a blow down of around 275 m3/hr, for a 210 MW power plant.By increasing COC, the blow down quantity can be reduced. By externalwater treatment and adding water treatment chemicals, COC of even 10 canbe reached. By increasing COC from 3 to 10, we can reduce the blow downquantity drastically from 275 m3/hr to30 m3/hr, which is a savings of 88percent.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    40/47

    Reducing leaks and over flows

    Lot of water leaks from Valves, Flanges, Taps, Fire fighting hoses, under ground fire fighting lines, cooling tower basin, gardening hoses etc takesplace

    Overflows from cooling towers of AC plants, Air washers, and Overheadtanks due to non-functioning of float systems are also there

    Huge water leaks from the condenser pipe ducts are noticed.

    By bringing underground fire fighting lines to over ground, attendingvarious water leaks, providing ball and cock float systems for overheadtanks and smaller cooling towers, 3-5 percent water consumption can

    easily be reduced.

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    41/47

    Installation of effluent treatment plant

    A typical thermal power plant will have a 3-4 main drains. All this drainwater gets collected and finally goes out of the plant boundary.The measured drain quantities alone are found to be in the range of 800-1000 m3/hr.

    By installing effluent water treatment plants and recycling this water for

    the ash handling purpose, 80-90 percent of this water can be saved.

    Presentation by Group#B3

    Based on the water flows measurements in different thermal power stations and comparing them with design values and practically achievablefigures, savings worth Rs. 3.3 crore/annum, equivalent to 40 percent water use reduction have been identifiedSince there is a close nexus between water and energy, energy savings to

    the tune of 3.57 MU/annum is also identified

    .

    Potential

  • 7/31/2019 Blue Screen (1)

    42/47

    Total Electrical System Audit Including Lighting

    Assessment of the loading pattern of installed transformer to identify measures for reduction of lossesPower consumption by each AC system by using power measurement analyzersincluding Cooling effect and humidityPerformance of air compressors by using power measurement analyzersElectrical parameters like current, voltage, power factor and power by using power

    measurement analyzers Assessment of health of capacitors and adequacy of the existing VAR compensationsystemHT/LT motor consuming power more than 50 KW need to be checked for measuringelectrical parameters and performanceLighting of Main plant including office building lux measurement and power consumption(day/night phase wise)Distribution lossesHarmonic analysisIdentification of Energy Conservation opportunities

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    43/47

    Cost Analysis of Heat Exchanger

    Presentation by Group#B3

    Cost of Heat Exchanger, Pump, Piping ,Insulation and Storage Tank: Rs1,65,000(Approximate)

    COP of Refrigerator increases by roughly 15%.Savings:308 units per month

    Savings from Water Heaters : 2928 units(Replacing 9 geysers)

    Total Monthly Savings:3236 unitsTotal Monthly Savings in Rupees: Rs 18,768

  • 7/31/2019 Blue Screen (1)

    44/47

    Cost analysis

    Presentation by Group#B3

    S.No Recommended measure Electricitysaved per month

    Savings inRs per month

    Capitalinvestment

    Pay backperiod

    1 Use solar water heater instead of geyser

    3600Kwh 20,880 7,80,000 3 years

    2 Use automatic washingmachine instead of manual

    48Kwh 278.4 10,075 3.1years

  • 7/31/2019 Blue Screen (1)

    45/47

    Final recommendation

    Heat Exchanger must be implemented, as its payback period is least andeffectiveness highest.

    Solar Water Heaters are generally efficient but water temperatures would

    slightly decrease in the rainy season.

    Automatic washing machines saves more energy and its payback periodis also less. In the long run they are more efficient than manual machines.

    The total amount of electricity that can be saved=6884 Kwh per month.Roughly Rs40,000

    Presentation by Group#B3

  • 7/31/2019 Blue Screen (1)

    46/47

    References

    Energy Audit done Energo Engg Projects Ltd at Kolaghat unit ASME standards (PTC)

    Wikipedia

    www.google.com

    www.sciencedirect.com

    www.googlesholar.com

    www.cea.nic.in

    www.actsys.com

    www.indiapower.org

    www.iea-estap.org

    http://www.reduct.com/news/BoilerEfficiency1.ht m

    Presentation by Group#B3

    http://www.google.com/http://www.sciencedirect.com/http://www.googlesholor.com/http://www.cea.nic.in/http://www.actsys.com/http://www.indiapower.org/http://www.iea-estap.org/http://www.reduct.com/news/BoilerEfficiency1.htmhttp://www.reduct.com/news/BoilerEfficiency1.htmhttp://www.iea-estap.org/http://www.indiapower.org/http://www.actsys.com/http://www.cea.nic.in/http://www.googlesholor.com/http://www.sciencedirect.com/http://www.google.com/
  • 7/31/2019 Blue Screen (1)

    47/47

    THANK YOU