blake lapthorn new construction act seminar
DESCRIPTION
Blake Lapthorn held a breakfast seminar on the new Construction Act which comes into force on 1 October at its Oxford office on 21 September and Southampton office on 23 September.TRANSCRIPT
The Construction Act 2009 Are you ready?
Richard WadePartner, Head of Construction
21 September 2011
A short history …
Sir Michael Latham “Constructing the Team” (1994) 30 recommendations made; two adopted:-– adjudication – payment
Housing Grants (Construction and Regeneration) Act 1996“The Scheme”Some limited adoption (in practice) of other recommendations (such as project bank accounts)
The Construction Act 1996
Two key recommendations of LathamIntroduction of mandatory provisions for payment and dispute resolution via adjudicationTwo perceived effects– Improved cashflow (including outlawing of “pay when
paid” clauses)– Quicker and cheaper means of resolving disputes– But ….
Never “recession tested”
The Construction Act 2009
Amends the 1996 Act
March 2004: Gordon Brown (as Chancellor) announces review of Construction Act against background of continuing payment problems
Formal consultations in 2005 and 2007
Local Democracy, Economic Development and Construction Act 2009 (Part 8)
The key features of the new Act
Removal of requirement for construction contract to be in writing
Potentially significant amendments to existing provisions for payment
Minor amendments to adjudication provisions
Contracts other than in writing covered
RJT Consulting Engineers v DM EngineeringRJT Consulting Engineers v DM Engineering (2002) (2002)
Carillion Construction v Devonport Royal DockyardCarillion Construction v Devonport Royal Dockyard(2003)(2003)
Section 107 repealed: oral or oral/partly written contracts within scope of Act
BUT provisions relating to adjudication (eight “compliance points”) must be in writing to comply with s108
AMENDMENTS TO PAYMENT PROVISIONS
PAYMENT The Weakness in the 1996 Act
Section 110(1)(a) Contracts must have adequate mechanism for determining what payments become due and when
This is essential for operating ss.111 & 112 (withholding and suspension)
Likelihood that majority of contracts do not have adequate mechanism
‘Scheme’ not helpful: just contains list of what may be included in interim payments together with due dates and final payment dates
Two instances identified in new Act– Where due payment date determined solely by provision
of notice of sum due to payee (s110(1D)); or
– Where payment conditional upon performance of obligations (or decision relating thereto) under another contract (s 110A)
What falls short of ‘Adequate Mechanism’ (under LDEDC)?
Principle underpinning Adequate Mechanism – Revision of Payment Notices
Payer must pay notified sum on or before the final date for payment (s111)
New provisions for payment notices (ss110A and 110B)
‘Notified’ Sum
The sum specified in notice issued by:– payer– payee– payee (where payer fails to issue notice)
Notices must comply with new s110A – replacing s110(2) requiring payer to issue payment noticeIf payer fails to issue, payee may issue ‘default’ notice (s110B)Notices to be issued no later than five days after payment due dateAmount of sum considered due must be stated together with basic calculation
Payer’s Failure to Issue Notice
Payee can issue notice instead but final date for payment extended from expiry of five days – Note: potential impact on cashflow
But final date for payment intact if payee issues application before payment due date (provided such application is required/permitted by contract)
If contract not Act-compliant paragraph 9 of new Scheme applies giving payee similar redress
Notice to pay less
Payer can issue notice of intention to pay less than notified sum – s111(3)
Notice must indicate sum payer considers due on date notice is served and basis of calculation
Must be given no later than the “prescribed period” before date for payment
Payment Procedure Example one
Payer/payee to issue notified sum
Notified sum to be discharged
(on/before final day for payment)
5 days
Payment due date
Final Datefor payment
Payment Procedure Example two
Payer/payee issues
notified sum
Payer issues “Pay Less”
Notice
Reduced notified sum discharged
5 days Prescribedperiod
Final datefor payment
Payment duedate
Payment Procedure Example three
Payer fails to issue notified sum
Payee operates default
procedure
Extended by
3 days
5 days 3 daysFinal date for
paymentPaymentdue date
‘Conditional’ Payment – the end of ‘pay when certified’?
“Adequate mechanism” requirement not satisfied where:-– payment made conditional on performance of
obligations under another contract or decision by any person as to whether such obligations have been performed
(New sub-section 110(1A))
Conditional Payment (cont.)
Will 110(1A) actually outlaw pay-when-certified clauses?
Will 110(1A) conflict with current s113?
Pay-when-paid exemption in s113 not removed
Other Changes
No requirement to pay sum due where payee became insolvent after prescribed period and contract permits payer not to pay sum due in this event (Melville Dundas –v- Wimpey)
Improvement to suspension (s112) allowing payee:-
– (a) to suspend work only in relation to part (or all) of works and;
– (b) to recover reasonable compensation for “costs and expenses reasonably incurred” during suspension
AMENDMENTS TO ADJUDICATION PROVISIONS
Timetable
Currently; time runs from referral being sent or received?
New Scheme (para7(3)); adjudicator to notify parties of date Referral received – time runs from receipt
Slip Rule
replacement of case law; Bloor v Bowman (2000)New s108(3)(A)Contracts must include provisions that adjudicator has power to correct and clerical/typographical error arising by accident/omissionLack of clarity about time for correction (except where new Scheme applies – para 22A)
Costs in Adjudication
New s108A
Agreement allocating “costs relating to the adjudication” ineffective unless made in writing after giving notice of intention to refer the dispute to adjudication
This also refers to the fees and expenses of the adjudicator
Tolent clauses to be disallowed - TCC had begun to address in Yuanda v WW Gear (2010)
Verdict?
Improvement in payment provisions but complexities remain; still “lean” towards payer?
Abolition of s107 (written contracts) welcome
Abolition of Tolent clauses welcome
Single adjudication procedure advocated in some quarters but is this too intrusive into freedom of contract?
Progress
Final amendments made to Bill during 3rd reading in the Lords on 29 April 2009
Received 2nd Reading in the Commons 1 June 2009
Committed to a Public Bill Committee 1 June 2009
3rd Reading in the Commons 13 October 2009
Act of Parliament (following Royal Assent) 12 November 2009
Into force on ….. 1 October 2011!
The Construction Act 2009 Are you ready?
Richard WadePartner, Head of Construction
21 September 2011