black belt project storyboard template example

27
Pick-Up Order Lead Time Project Storyboard The Bahama Bistro Sample Storyboard Visit GoLeanSixSigma.com for more Lean Six Sigma Resources

Upload: goleansixsigmacom

Post on 15-Apr-2017

2.803 views

Category:

Education


0 download

TRANSCRIPT

Page 1: Black Belt Project Storyboard Template Example

Pick-Up Order Lead Time Project Storyboard

The Bahama Bistro Sample Storyboard

Visit GoLeanSixSigma.com for more Lean Six Sigma Resources

Page 2: Black Belt Project Storyboard Template Example

Executive Summary

Page 3: Black Belt Project Storyboard Template Example

Key Words(Specific to the Bahama Bistro)

• Pick-Up Order Lead Time: Total cycle time from the moment the customer places their order to the moment they receive their food.

• Packaging Process: All tasks related to placing food into take-out containers, selecting utensils, napkins and condiments and then placing them all into a bag

• Pick-Up Wait Time: The cycle time from the moment a Pick-up customer walks in the door to the moment their order is made available to them

• Condiments: Mini-bottles of hot sauce, limes, salt and pepper

Page 4: Black Belt Project Storyboard Template Example

Project Charter

Page 5: Black Belt Project Storyboard Template Example

VOC Translation Matrix

Key Take Away: Project needs to address overall Lead time which will impact customer wait time as well as food temperature

Page 6: Black Belt Project Storyboard Template Example

SIPOC: Pick-Up Order Process

Key Take Away: The scope of this project goes from the point of receiving the customer order to the point at which food is available

Page 7: Black Belt Project Storyboard Template Example

Detailed Map – Pick-Up Process

Key Take Away: The process needs more analysis – packaging segment seems to take longer than expected

Page 8: Black Belt Project Storyboard Template Example

Data Collection Plan

Key Take Away: Cashier was largely responsible for all data collection – the team adjusted job duties to accommodate

Page 9: Black Belt Project Storyboard Template Example

Gage R&R: Pick-Up Order Wait Time

Key Take Away: The measurement system variation was less than 10% for collection of wait time data – Measurement Systems were good!

Page 10: Black Belt Project Storyboard Template Example

Baseline Data• Total Pick-up Order Cycle Time• Average time is 27 minutes

Key Take Away: The baseline process was not capable of reaching project goal of 20 minutes

Goal of 20 minutes

Page 11: Black Belt Project Storyboard Template Example

Fishbone Diagram & 5 Whys

Key Take Away: Root Cause Analysis will focus on Packaging process, condiment prep and availability of staff

Page 12: Black Belt Project Storyboard Template Example

Process Map Analysis

Key Take Away: Mapping highlighted packaging as a potential root cause of pick-up order delay

Page 13: Black Belt Project Storyboard Template Example

One-Sample T-Test

Key Take Away: Packaging pick-up orders was taking longer than 6 minutes. Improvement focused on the packaging process

Null: There is no difference between the current process and the 6 minute historic averageAlternative: The current average is not equal to the historic average

Page 14: Black Belt Project Storyboard Template Example

Hypothesis Testing Results

Key Take Away: Hypothesis tests confirmed that the process has gotten worse and that packaging was a key area of focus

Page 15: Black Belt Project Storyboard Template Example

Impact Effort Matrix

Key Take Away: The team planned to implement the three solutions in the low effort/high impact quadrant

Page 16: Black Belt Project Storyboard Template Example

To-Be Map Segment

Key Take Away: Improvements to materials, process and cross-training resulted in faster lead time overall

Page 17: Black Belt Project Storyboard Template Example

Before & After Time Data

Key Take Away: Implemented solutions decreased total cycle time and achieved project goal of less than 20 minutes

Page 18: Black Belt Project Storyboard Template Example

Implementation Plan

Key Take Away: This implementation Plan was key in terms of all team members knowing their role in the roll-out

Page 19: Black Belt Project Storyboard Template Example

Packing Type DOE

Key Take Away: This Design of Experiments was instrumental in selecting the new Pick-Up order packaging

Page 20: Black Belt Project Storyboard Template Example

Risk Management

Key Take Away: Cross-Training mitigated the risk of overloading the chef during peak hours

Page 21: Black Belt Project Storyboard Template Example

Monitoring & Response Plan

Key Take Away: The monitoring plan factors in both the leading indicators of packaging time and customer wait time along with the project “Y”

Page 22: Black Belt Project Storyboard Template Example

Control Chart of Project Y

Key Take Away: The team is continuing to work on the special causes of variation – and the Upper Control Limit of 23 minutes is the Response Plan trigger

Page 23: Black Belt Project Storyboard Template Example

Transfer Opportunities

Key Take Away: The improvements implemented at one location can easily be translated to other locations – time to spread the wealth!

Page 24: Black Belt Project Storyboard Template Example

Appendix

Page 25: Black Belt Project Storyboard Template Example

Wait Time Hypothesis Test

Key Take Away: There was a difference between the historical median and the current median for customer wait time – it was taking longer!

Page 26: Black Belt Project Storyboard Template Example

Communication Plan

Key Take Away: The Communication Plan was instrumental in making sure everyone knew what was happening with the project at all times

Page 27: Black Belt Project Storyboard Template Example

P- Chart of “Late” PackagingProportion of Late Packaging – June

Key Take Away: The P-Chart turned out to be the best visual for Packaging time – by deriving discrete data from continuous data the positive trend was obvious