biogeorge paper # 04086
TRANSCRIPT
-
8/10/2019 Biogeorge Paper # 04086
1/15
Plant Experience with Dosing Optimisation of an
Environmentally Friendly Biocide
Hugh FallonContact Energy
Hellabys RdOtara, Auckland
George J. Licina
Structural Integrity Associates3315 Almaden Expressway, Suite 24
San Jose, CA 95118
ABSTRACT
Initial experience with an environmentally friendly biocide at a brackish water-cooled power
plant showed that the biocide was very effective in controlling microbiological fouling of piping andcondenser tubes. Subsequent activities demonstrated that the biocide could be used more economically
by closely tracking the biocides effectiveness on biofilm activity using an electrochemical biofilmactivity monitor.
Keywords: biocide, monitoring, biofilms, water treatment, cooling water
BACKGROUND
Water treatment, usually with biocides, is the most common approach for mitigation ofmicrobiologically influenced corrosion (MIC) based upon its ease of use. However, the use of a biocide
treatment alone is rarely effective for an already fouled system. The most commonly used biocides areoxidising agents that can also aggravate a corrosion condition that may have been established initially by
microbiological activity, but which may proceed with no further microbiological involvement. In suchcases, the use of a biocide, especially an oxidising biocide, may prevent further infestation but it can alsoprovide alternative and stronger half-reactions that fuel the corrosion activity. Biocide treatments alone
-
8/10/2019 Biogeorge Paper # 04086
2/15
are only likely to be effective when microbes actively participate in the corrosion process (e.g., bycatalysis of the reduction of oxygen, or by cathodic depolarisation in anaerobic systems), or when
microbes provide alternative reactions that exacerbate corrosion. In summary, biocide treatments are avery effective preventivemeasure against MIC; however, the condition of the corrosion process must
be well understood before biocide treatment is used to remediate an apparent MIC condition.
Contact Energy LTD own and operate the Otahuhu B 380 MW gas-fired single-shaft combined
cycle power station, located in South Auckland, New Zealand (Figure 1). Estuarine water is supplied to
the main cooling water system where the recirculation rate to a 2-pass titanium-tube condenser is some20,000 m3/hr. The velocity through the condenser tubes is 2 m/s. A hybrid 8-cell cooling tower is used
for heat rejection. The design T across the condenser is 9.9C. System losses (evaporation and purge
water) are made up continuously to the main system. Over 22,000 m3of make-up water are taken fromthe estuary each day to maintain the design cycles of concentration of 1.25.
The conductivity of the brackish make-up water can vary significantly between the low and hightide cycles; by as much as 15 mS/cm. Seasonal variations are also notable due to high rainfall totals
during winter and spring. In general, the make-up water conductivity varies between 5 and 35 mS/cmbetween June and November. During the warmer months the average conductivity is more stable, and
changes tend to occur gradually in the range 35 to 50 mS/cm.
The make-up water is treated continuously with industrial grade bleach to provide a free halogen
residual of between 0.5 to 0.8 mg/l. A proprietary stabilised bromine-based biocide is added to therecirculating water system to augment the primary (make-up) oxidant dosing. The bromine product is a
unique, biomimetic, stabilised liquid bromine biocide, with excellent microbiological and biofilmcontrol properties, while exhibiting lower toxicity and lower reactivity than traditional oxidisingbiocides. A total halogen residual in the range 0.1 to 0.40 mg/l is maintained in the main system. All
residuals were reported in plant data as chlorine for convenience and for direct comparison with on-linechlorine analysers. However, the estuarine nature of the water and the injection of the stabilised brominebiocide ensure that the residuals consist of bromine in a mixture of free, stabilised and combined
species. A proprietary scale inhibitor is also dosed to the recirculating water.
That treatment has effectively controlled MIC and biofouling throughout the cooling system.
Biocide Optimisation
Originally, the cooling water chemistry on the plant was quite reactive and the effects of foulingin the system were assessed off-line without the aid of any on-line techniques; clearly without any
predictive indicators. Plant policy was to apply chemicals to provide fixed, target residuals. If aperformance or fouling problem were noted, the amounts of chemicals would be increased. Thechemical program was expensive while this policy was maintained.
A more sensible approach was considered to be the application of chemicals, especially thebiocides, according to the system demand and the system performance. That biocide optimisation effortis a wide-ranging and thorough instrumentation project with the aim of using the smartest technology tofully monitor and optimise the system. As a part of that program, the plant installed two
BI?GEORGE electrochemical biofilm activity probes (Figure 2), a DATS model heat exchanger,and other instruments in a test program intended to evaluate the suitability of the probe for use at the
plant, then to use the probe output data as part of a water treatment control management system, whichwould add biocide on a schedule and at concentrations that would keep system surfaces free of biofilm
-
8/10/2019 Biogeorge Paper # 04086
3/15
-
8/10/2019 Biogeorge Paper # 04086
4/15
polarisation cycle that is applied. As shown in other systems, the electrochemical biofilm probe will foulquite quickly (in a few days) and the trends for applied and generated currents will rise to significant
values compared to the baseline if there is significant fouling potential in the system.
In the course of the optimisation activity, probes have been isolated from the biocide treatedflow, have been exposed outside of the system in a bucket of make-up water, and have been exposed inboth inlet and outlet streams.
RESULTS
Initial Exposures
Figures 6 and 7 illustrate the initial performance. When the probe was exposed to the biocide-
treated water at a flow comparable to that experienced by the condenser tubes, little or no evidence ofany biofilm activity was seen, which was consistent with visual examinations of system surfaces. This
behaviour was not unexpected as noted above. There were indications of biofilm on April 29th and June12th, however, in both cases, the system itself was able to clean up the probe.
Those initial results led to modifications of the flow conditions experienced by the probe,starting with a period of stagnation.
Effects of Flow Rate and Biocide Treatments
The objective of subsequent changes in the exposure of the biofilm probe in terms of flow ratesand exposure to biocide were intended to permit the probe to foul, then to observe the response of theapplied and generated currents to biocide dosing. In general, those conditions showed that once a system
(including the probe surfaces) is fouled, it may not be easy to establish the previously clean conditions.It should also be pointed out that since the biofilm probe will be encouraging biofilm formation even
while the water has oxidant in it, non-polarised surfaces may be recovered with more ease than the probeelectrodes. Finally, the changes in flow and dosing conditions past the probe permitted the biofilm'sresponse to stress to be observed.
As shown in Figure 8, on July 16th , the biofilm probe was exposed to dead leg conditions (i.e.,
flow through the condenser outlet tapping point was isolated). In addition, the applied potential wasincreased from 200 to 400 mV and the applied potential time was increased from 1 hour to 90 minutes.Baseline and alarm setpoints were not reset. The intent was to observe when and if the probe would foul,
then to introduce process water to it and to note the response of that biofilm to flow.
As of July 18th the applied current trend started to increase dramatically. There was a coincident
large negative deviation on the generated current trend at the same time.
On July 30th 2002 at 10:16, the process flow was introduced to the biofilm probe again at a lowflow of less than 1-liter per minute. The applied current decreased somewhat from its earlier peak and
was then steady, up to July 31st, when both the applied and generated trends started to increasesignificantly.
-
8/10/2019 Biogeorge Paper # 04086
5/15
On August 7th 2002, flow past the biofilm probe was measured as 0.6 litres per minute. Biocide(stabilised liquid bromine) dosing was increased (from a 10% pump stroke setting to 20%) for
approximately seven hours. The overall flow out of the rack was set to about 1.25 litres per minute forthis time period. The generated current began to decrease from 12:15 on the same day.
On August 13th at 08:35 the flow from the rack was increased to about 6 l/min and the next daythe bromine biocide dosing was doubled (10% to 20%) from 08:00 to 14:00. Between August 17th and
22nd, the rack flow decreased from 6 to 3 litres per minute, due to some mud accumulation further down
the drain line, which decreased the flow rate over a number of days, and both the generated and appliedcurrent trends were starting to increase again.
On August 22nd at 15:30, the probe was swapped over to the inlet line tapping point (the line that
furnished the DATS) with a flow of 28 l/min. The toxicitywould only be slightly higher on the inlet sideof the condenser; as such, this is more an indication of the effect of flow on the biofilm than the effect of
toxicity.
At 15:00 on September 3rd2002, the applied potential was again changed downward, from 400
mV applied for 90 minutes to 200 mV for 1 hour. Those adjustments reflect the pre-July 16th settings.Between August 22nd when the probe location tapping was changed, and September 3rd when the
potential and time were changed, the applied current and generated currents changed from 3.4A and0.15A, respectively (both being quite steady), to values after the setting changes of 1.75A and (still)
0.15A, respectively. On Friday September 6th , when the bromine biocide dosing was turned off from10:45 to 15:15, the generated current values did not change significantly.
On September 10th 2002 the bromine biocide dosing schedule was changed from a continuous
mode to a1 hour off/1 hour on schedule from 19:00 to 08:00 on the 11th . The applied and generatedcurrent trends appeared to show a slight decrease during this on/off test. Note that the hypochloritedosing was on as normal to the make-up water during that time.
The plant was shut down for the weekend on Friday September 13th . Just before shutdown the
recirculating water temperature was a fairly steady 25C. Over the weekend, the recirculating watertemperature went as low as 6.5C (on the 14th). Bromine biocide dosing was from 08:00 to 16:00 for the
14th and 15th. The plant restarted on the 15th at 17:00 and the recirculating water got to 31.5C by 20:00.
On Monday Sep 16th, the bromine biocide dosing was set to a 1-hour off/ 1 hour on schedule.
The applied current decreased from 1.43A on the morning of the 13th to 1.11A on the morning of the
17th while the generated current remained steady at -0.08A. All or part of the applied current reductionmay have been due to the temperature shock during the weekend.
On Tuesday September 17th , samples (swabs) were taken from the biofilm surfaces, the BioBox
(a transparent Perspex box with a tortuous flow path, which encourages sedimentation and fouling), andthe recirculating water corrosion coupon. Water samples were taken from the probe tapping point (upperlevel) and the BioBox. This completed this dead-leg/biofilm production trial.
In parallel with the tests of the on-line probe (as detailed above), an identical probe was exposed
to another set of controlled test conditions. Initially, the unit was left suspended in a bucket of untreatedseawater to which some sugar was added. The unit went quickly into alarm on a high applied current.The biofilm activity on that probe peaked on July 19th with significant scatter in the trend plots. The
applied current levels had begun to decrease significantly after July 19 th . The probe in the bucket test
-
8/10/2019 Biogeorge Paper # 04086
6/15
-
8/10/2019 Biogeorge Paper # 04086
7/15
levels that are consistent with, and in some cases, better than, the baseline conditions that weredetermined in the initial phases of the study.
Figure 12 shows the relative chemical treatment costs for the plant over the past 2 years. The
electrochemical biofilm activity probe has been incorporated into an overall water treatmentmanagement system that hasallowed the site to optimise the use of the stabilised bromine-based biocideto the extent that a 25% saving in chemical costs has been realised to. Further, total savings of up to 40%
compared to pre-optimisation costs are expected in the medium term as the dosing is changed to a fully
performance-based approach, with the electrochemical biofilm probe systemas an integral part of theoverall biocide management program.
The biocide optimisation activities are continuing as the plant begins to approach its goal of
continuously exposing the probe to actual process water that has been treated less aggressively withbiocide such that the biocide content of the water is just sufficient to keep surfaces clean. These
activities have continued to show that the stabilised bromine biocide is effective and that tools such asthe electrochemical biofilm probe are effective in helping to optimise those treatments such that theplant has already reduced biocide usage.
CONCLUSIONS
The electrochemical biofilm activity probe was shown to be sensitive to biofilm formation in theplant system.
The electrochemical biofilm activity probe system definitely promoted preferential biofilmdevelopment on the sensor probe. That aspect of the system providesa useful lead factor for the plant,
where fouling will develop on the probe before it becomes established on the general non-polarisedsurfaces of the main system.
Biofilm can become readily established if dosing control is lost; biofilm can also develop instagnant areas.
Once established, biofilm is not easily removed, to the extent that it would be difficult to re-establish the previously clean conditions of the plant.
Maintaining clean conditions on the biofilm probe surfaces ensures the main plant conditions are
also clean. Sessile analysis of the probe and cooling system surfaces supports this claim.
The stabilised liquid bromine biocide is clearly effective in maintaining surfaces free of biofilms,
whether those surfaces are heat exchanger tubes or probe electrodes.
The biocide was also demonstrated to effectively return a probe surface with some
microbiological fouling to a condition consistent with a clean surface.
The electrochemical biofilm activity probe has been incorporated into a total water treatmentmanagement system that is allowing the site to optimise the use of the stabilised bromine-based biocide
to the extent that a 25% saving in chemical costs have been realised to date.
-
8/10/2019 Biogeorge Paper # 04086
8/15
Further total savings of up to 40% compared to pre-optimisation costs are expected in themedium term as the dosing is changed to a fully performance-based approach, with the electrochemical
biofilm probe systemas an integral partof the overall biocide managementprogram.
ACKNOWLEDGMENTS
The authors gratefully acknowledge the cooperation and support of Mr John Rickerby, Mr. Harry
Habib and Mr. Ralph Woulfe of Contact Energy Limited, Mr. Elie Tanos of Chemtrack,and Mr. RoyMenzies of Ondeo-Nalco.
REFERENCES
1. G. J. Licina, George Nekoksa, The Influence of Water Chemistry and Biocide Additions on theresponse of an On-line Biofilm Monitor, CORROSION/95, Paper No. 527, NACE International,
1995.
2. G.J. Licina, L.P. Venhuis, Biocide Optimization Using an On- line Biofilm Detector, International
Water Conference, Paper 00-060, October 2000.
3. G.J. Licina, Monitoring Biofilms on Metallic Surfaces in Real Time, CORROSION/2001, PaperNo. 442, NACE, Houston, TX, 2001.
4. M.H. Dorsey, et al., Monitoring for Corrosion and Microbiological Activity in a Cooling WaterSystem, CORROSION/2002, Paper No. 441, NACE-International, 2002.
5. G.J. Licina, Experience with On-Line Monitoring of Biofilms in Plant Applications, CoolingTechnology Institute, 2003.
6. P.G. Kutzora, L.B Peterson, G.J. Licina, Monitoring Biofilms on Cooling Water System Surfaces,
Electric Utility Chemistry Workshop, University of Illinois, 2003.
7. W.E. Garrett, G.J. Licina, "Monitoring Microfouling in a Once-Through Service Water System",
Eighth EPRI Service Water System Reliability Improvement Seminar, 1995.
8. G.J. Licina, Optimizing Biocide Additions via Real Time Monitoring of Biofilms,CORROSION/2004, Paper No. 04582.
-
8/10/2019 Biogeorge Paper # 04086
9/15
TABLE 1RESULTS FROM SWABS FROM BIOFILM ELECTRODES AND EPOXY PROBE BODY
Electrodes Titanium Epoxy Titanium Epoxy
Date 9/17/2002 10/25/2002 10/25/2002 10/31/2002 10/31/2002
Microscopic Examination
(1000X Magnification)
Sludge + - - - -Siliceous Material - + - + -
Protozoa - - - - -
Nematodes - - - - -
Diatoms + - - - -
Unicellular Algae + - - - -
Filamentous Algae - - - - -
Unicellular Bacteria +++ - - - -
Filamentous Bacteria - - - - -
Amphipods (Larvae,nymphs etc)
Yeast/Filamentous Fungi - - - -
Culturing( CFU/ml)
Yeasts ND ND ND ND ND
Moulds 100 10 10 10 10
TVC at 25 Deg C 14000 21000 800 21000 800
Anaerobic SRB ND 10 ND 10 ND
Total Anaerobic Bacteria 600 50 600 50
Pseudomonas ND 13000 700 13000 700
Clostridium ND 50 ND 50 ND
Heterotrophic Iron ppt.
Bacteria
100 200 20 200 20
Nitrifying Bacteria ND ND ND ND ND
Denitrifying Bacteria ND ND ND ND ND
-
8/10/2019 Biogeorge Paper # 04086
10/15
FIGURE 1 - Aerial photograph of the site
FIGURE 2 - Electrochemical Biofilm Activity Probe
-
8/10/2019 Biogeorge Paper # 04086
11/15
FIGURE 3 - Results from Biofilm Optimisation Study Brackish Water-cooled Incineration Plant (fromReference 2)
FIGURE 4 - Probe Tapping on Cooling Water Return Line
FIGURE 5 - View of Probe Installed in Tap
-
8/10/2019 Biogeorge Paper # 04086
12/15
Applied Current Data
C99-101/399-109
0.0
0.5
1.0
1.5
2.0
4/10/2002
4/17/2002
4/24/2002
5/1/2002
5/8/2002
5/15/2002
5/22/2002
5/29/2002
6/5/2002
6/12/2002
6/19/2002
6/26/2002
7/3/2002
AppliedCurrent,microA
mps
FIGURE 6 - Applied Current Trend April 2002-June 2002 (Color code: Yellow = baseline beingestablished; Green = probe is clean; Red = probe is fouled)
Generated Current Data
C99-101/399-109
-1.00
-0.80
-0.60
-0.40
-0.20
0.00
0.20
0.40
0.60
0.80
1.00
4/10/2002
4/17/2002
4/24/2002
5/1/2002
5/8/2002
5/15/2002
5/22/2002
5/29/2002
6/5/2002
6/12/2002
6/19/2002
6/26/2002
7/3/2002
GeneratedCurrent,mic
roAmps
FIGURE 7 - Generated Current Trend Aril 2002 June 2002
-
8/10/2019 Biogeorge Paper # 04086
13/15
Otahuhu CCPP
ONLINE PROBE (Condenser Outlet BioGeorge Probe)
Generated Current Data Jul 16 to Sep 17 2002
16/9/200219:00ST-70dosingoff(TIM
ER1)
15/9/200216:55:Plantre-star
13/9/200220:55:Plantshutdown
10/09/2002:ST-70dosingoff(TIMER1)
06/09/2002:ST-70dosingofffo
r4.5hours
03/09/02:EAPPto200mVfor
1hour
22/08/02:Pro
beswappedfrom
Outlet
toIn
lettappingpoint
16/07/02:Dead-legestablished;IAPPt
o400mV(from
200mV)for90min(from(60min)
30/07/02:Processflowre-establis
hed;Sampleflow=0.5
l/min
07/08/02:Processflowincreasedto1.25l/min;
7-hourST-40testwithtwicetheproductra
te
13/08/02:Processflow
incr
easedto6l/min
16/08/02:Flowdecreasedto3l/min
-0.40
-0.20
0.00
0.20
0.40
0.60
0.80
1.00
1.20
1.40
1.60
1.80
2.00
2.20
07/15/02
07/18/02
07/21/02
07/24/02
07/27/02
07/30/02
08/02/02
08/05/02
08/08/02
08/11/02
08/14/02
08/17/02
08/20/02
08/23/02
08/26/02
08/29/02
09/01/02
09/04/02
09/07/02
09/10/02
09/13/02
09/16/02
09/19/02
GeneratedCurrent,microAmp
FIGURE 8 - Generated Current Trend July 2002 through September 2002
Otahuhu CCPP
Applied Current Data
ONLINE Probe
0.0
0.1
0.2
0.3
0.4
0.5
0.6
0.7
9/30/2002 10/7/2002 10/14/2002 10/21/2002
AppliedCurrent,
microAmps
FIGURE 9 - Continuous exposure to treated cooling water
-
8/10/2019 Biogeorge Paper # 04086
14/15
Otahuhu CCPP
26June 03 YTD
Applied Current Data
0.0
0.5
1.0
1.5
2.0
2.5
3.0
26-Jun-03
3-Jul-03
10-Jul-03
17-Jul-03
24-Jul-03
31-Jul-03
7-Aug-03
14-Aug-03
21-Aug-03
28-Aug-03
4-Sep-03
11-Sep-03
Date
AppliedCurrent,microAmps
FIGURE 10 - Applied Current History 2003
Otahuhu CCPP
26June 03 YTD
Generated Current Data
PlanttripJuly15th,14:1
Watertemp28degreest
10degreesCelsius
PlantstartJuly17th,13:30
Watertempto28degreesCelsiu
5-dayplantoutagebegin
Dead-legintroduced
PlantstartJuly23rd,15:00
Watertempto30degreesCelsiu
Errorinprobe,July31st,10:0
Probefunctional,Aug7th,10:
P
robeinitialisedJune26t
Flow=30l/min
-1.00
-0.80
-0.60
-0.40
-0.20
0.00
0.20
0.40
0.60
0.80
1.00
23-Jun-03
25-Jun-03
27-Jun-03
29-Jun-03
1-Jul-03
3-Jul-03
5-Jul-03
7-Jul-03
9-Jul-03
11-Jul-03
13-Jul-03
15-Jul-03
17-Jul-03
19-Jul-03
21-Jul-03
23-Jul-03
25-Jul-03
27-Jul-03
29-Jul-03
31-Jul-03
2-Aug-03
4-Aug-03
6-Aug-03
8-Aug-03
10-Aug-03
12-Aug-03
14-Aug-03
16-Aug-03
18-Aug-03
20-Aug-03
22-Aug-03
24-Aug-03
26-Aug-03
28-Aug-03
30-Aug-03
1-Sep-03
3-Sep-03
5-Sep-03
7-Sep-03
Date
Genera
tedCurrent,microAmps
FIGURE 11 - Generated Current History 2003
-
8/10/2019 Biogeorge Paper # 04086
15/15
Otahuhu B Combined Cycle Power Station
Total Chemical Cost Trend for Cooling Water Treatment
Plant
Outage
Plant
Outage
Optimization Project
Commences
Projection for
2004
08-Feb-01
22-Mar-01
03-May-01
14-Jun-01
26-Jul-01
06-Sep-01
18-Oct-01
29-Nov-01
10-Jan-02
21-Feb-02
04-Apr-02
16-May-02
26-Jun-02
08-Aug-02
19-Sep-02
31-Oct-02
12-Dec-02
23-Jan-03
06-Mar-03
17-Apr-03
29-May-03
10-Jul-03
21-Aug-03
02-Oct-03
13-Nov-03
25-Dec-03
05-Feb-04
18-Mar-04
29-Apr-04
10-Jun-04
22-Jul-04
02-Sep-04
14-Oct-04
25-Nov-04
RelativeChemicalCostfor
CoolingWaterTreatment
FIGURE 12. Relative Chemical Costs from Initial Biocide Optimisation Activities