bim- pakistan case study

Upload: muhammad-faizan-khan

Post on 01-Jun-2018

237 views

Category:

Documents


1 download

TRANSCRIPT

  • 8/9/2019 BIM- Pakistan case study

    1/76

    i

    DEVELOPMENT OF BUILDING INFORMATION MODEL

    OF OEC TOWER G-9/4, ISLAMABAD

    By

    MUHAMMAD FAIZAN KHAN 2010-BE-CE-101(Group leader)

    USAID ADIL 2010-BE-CE-120

    FARZAN SOHAIL 2010-BE-CE-43

    UZAIR TAHIR 2010-BE-CE-124

    RAJA MEHRAN KHAN 2010-BE-CE-146

    (2010-NUST-BE-CIVIL)A report submitted in partial fulfillment

    ofthe requirements for the degree ofBachelors of Engineering

    InCivil Engineering

    NUST Institute of Civil Engineering (NICE)

    School of Civil and Environmental Engineering (SCEE)

    National University of Sciences and Technology, Islamabad, Pakistan.

    (2013)

  • 8/9/2019 BIM- Pakistan case study

    2/76

    ii

    This is to certify that theReport entitled

    DEVELOPMENT OF BUILDING INFORMATION MODEL

    OF OEC TOWER G-9/4, ISLAMABAD

    Submitted by

    MUHAMMAD FAIZAN KHAN 2010-BE-CE-101(Group leader)

    USAID ADIL 2010-BE-CE-120

    FARZAN SUHAIL 2010-BE-CE-43

    UZAIR TAHIR 2010-BE-CE-124

    RAJA MEHRAN KHAN 2010-BE-CE-146

    Has been accepted towards the partial fulfillment

    ofthe requirements

    forBachelors of Engineering in Civil Engineering

    _______________________Engr. Zia Ud Din

    Assistant Professor,

    Department of Construction Engineering and Management,

    National Institute of Transportation (NIT),

    School of Civil and Environmental Engineering (SCEE),

    National University of Sciences and Technology, Islamabad, Pakistan.

  • 8/9/2019 BIM- Pakistan case study

    3/76

    iii

    DEDICATED

    TO

    OUR PARENTS

  • 8/9/2019 BIM- Pakistan case study

    4/76

    iv

    TABLE OF CONTENTSCONTENTS PAGENO

    ACKNOWLDGEMENT ............................................................................................................ IX

    ABSTRACT .................................................................................................................................. X

    LIST OF ACRONYMS .............................................................................................................. XI

    LIST OF FIGURES .................................................................................................................. XII

    LIST OF TABLES ................................................................................................................... XIII

    INTRODUCTION......................................................................................................................... 1

    1.1 OBJECTIVES ................................................................................................................. 3

    1.2 REASONSANDJUSTIFICATIONS ............................................................................. 3

    1.2.1 Market Adoption and Growth ..................................................................................... 3

    1.2.2 User Experience .......................................................................................................... 3

    1.3 ADVANTAGESANDEDUCATIONALOUTCOMES ............................................... 4

    1.3.1 Improved Designs ....................................................................................................... 4

    1.3.2 Life Cycle Asset Management .................................................................................... 4

    1.3.3 Improved Visualization ............................................................................................... 5

    1.3.4 Less Wastage .............................................................................................................. 5

    1.3.5 Reduced Safety Requirements .................................................................................... 5

    1.3.6 Guidelines for Students ............................................................................................... 5

    1.3.7 Personal and Social Advantage ................................................................................... 6

    1.3.8 Forensic Analysis ........................................................................................................ 61.3.9 Facility Management .................................................................................................. 6

    1.4 AREASOFAPPLICATION........................................................................................... 6

    1.4.1 Improved Communication: ......................................................................................... 6

    1.4.2 Shop Drawings ............................................................................................................ 7

  • 8/9/2019 BIM- Pakistan case study

    5/76

    v

    1.4.3 Cost Estimation ........................................................................................................... 7

    1.4.4 Project Scheduling ...................................................................................................... 7

    1.4.5 Conflict, Interference and Collision Detection ........................................................... 7

    LITERATURE REVIEW ............................................................................................................ 92.1 BACKGROUND ............................................................................................................ 9

    2.2 BUILDINGINFORMATIONMODELING .................................................................. 9

    2.3 TECHNICALASPECTSOFBIM ................................................................................ 11

    2.3.1 Clash Controls ........................................................................................................... 11

    2.3.2 Analyses .................................................................................................................... 12

    2.3.3 Time Estimation (4D) ............................................................................................... 12

    2.3.4 Cost Estimation (5D) ................................................................................................ 13

    2.4 BIMLEVELS ............................................................................................................... 13

    2.4.1 Level 0Usage of BIM Software ............................................................................ 14

    2.4.2 Level 13D Coordination ....................................................................................... 14

    2.4.3 Level 2Analyzes, Time and Cost Estimation ........................................................ 14

    2.4.4 Level 3Integrated Model ....................................................................................... 14

    2.5 TECHNOLOGIESIMPLEMENTEDINBIM ............................................................. 15

    2.5.1 CAD Technology ...................................................................................................... 15

    2.5.2 Object CAD Technology: ......................................................................................... 16

    2.5.3 Parametric Building Modeling .................................................................................. 16

    2.6 BIMANDPROJECTMANAGER ............................................................................... 16

    2.6.1 Communication Benefits .......................................................................................... 17

    2.6.2 Quality Benefits ........................................................................................................ 17

    2.7 BIMANDCONSTRUCTIONMANAGEMENT ........................................................ 18

    2.7.1 Design Phase ............................................................................................................. 18

    2.7.2 Construction Phase.................................................................................................... 192.7.3 Management Phase ................................................................................................... 20

    2.8 ADVANTAGESOFBIM ............................................................................................. 20

    2.9 BIMIMPLEMENTATIONINREALLIFE ................................................................. 21

    2.9.1 Melbourne Stadium ................................................................................................... 21

    2.9.2 Water Treatment Plant-Walsh Group ....................................................................... 22

  • 8/9/2019 BIM- Pakistan case study

    6/76

    vi

    2.9.3 Krakow Stadium ....................................................................................................... 22

    2.10 BIMTOOLS ................................................................................................................. 23

    2.10.1 Autodesk Quantity Takeoff................................................................................... 24

    2.10.2 Autodesk Revit...................................................................................................... 24

    2.10.3 Autodesk Green Building Studio .......................................................................... 25

    2.10.4 Autodesk Navisworks ........................................................................................... 26

    METHODOLOGY ..................................................................................................................... 27

    3.1 SELECTIONOFTHETOPIC ...................................................................................... 28

    3.2 LITERATURESTUDY ................................................................................................ 28

    3.3 SITESELECTION........................................................................................................ 28

    3.4 DATACOLLECTION.................................................................................................. 28

    3.5 LEARNINGSOFTWARE ............................................................................................ 29

    3.6 3-DMODELING .......................................................................................................... 29

    3.7 CONSTRUCTIONPROCESSSIMULATION ............................................................ 30

    3.8 QUANTITYTAKEOFF ............................................................................................... 30

    3.9 CLASHDETECTION .................................................................................................. 32

    3.10 ENERGYANALYSIS .................................................................................................. 32

    3.11 ANALYSIS ................................................................................................................... 32

    3.12 CONCLUSION ............................................................................................................. 32

    3.13 PREPARINGREPORTANDPRESENTAION ........................................................... 33

    3.13.1 5D Model Submission........................................................................................... 33

    3.13.2 Preparation of Presentation ................................................................................... 33

    CASE STUDY ............................................................................................................................. 34

    4.1 PROJECTINTRODUCTION ....................................................................................... 34

    4.2 SPECIALFEATURESOFOECTOWER.................................................................... 36

    4.3 AREAOFOECTOWER .............................................................................................. 37

    4.4 3-DMODEL ................................................................................................................. 37

    4.4.1 Architectural Model .................................................................................................. 37

    4.4.1.1 Grids .................................................................................................................. 38

    4.4.1.2 Levels ................................................................................................................ 38

  • 8/9/2019 BIM- Pakistan case study

    7/76

    vii

    4.4.1.3 Plan Views ........................................................................................................ 39

    4.4.1.4 Walls ................................................................................................................. 39

    4.4.1.5 Floors ................................................................................................................ 39

    4.4.1.6 Openings ........................................................................................................... 39

    4.4.1.7 Doors and Windows .......................................................................................... 40

    4.4.1.8 Ceilings ............................................................................................................. 40

    4.4.1.9 Ramps ............................................................................................................... 40

    4.4.1.10 Columns ............................................................................................................ 40

    4.4.1.11 Other Components ............................................................................................ 41

    4.4.2 Structural Model ....................................................................................................... 41

    4.4.2.1 Floors Slabs ....................................................................................................... 41

    4.4.2.2 Beams ................................................................................................................ 414.4.2.3 Columns ............................................................................................................ 41

    4.4.2.4 Walls ................................................................................................................. 41

    4.4.2.5 Stairs ................................................................................................................. 42

    4.4.2.6 Foundations ....................................................................................................... 42

    4.4.3 HVAC Model ............................................................................................................ 42

    4.4.3.1 Loading system template................................................................................ 42

    4.4.3.2 Linking architectural model .............................................................................. 42

    4.4.3.3 Creating work space .......................................................................................... 43

    4.4.3.4 Pipes and ducts .................................................................................................. 43

    4.4.3.5 Pipe and duct fittings ........................................................................................ 43

    4.4.3.6 Mechanical equipment ...................................................................................... 43

    4.4.4 Electrical Model ........................................................................................................ 43

    4.4.4.1 System template: ............................................................................................... 43

    4.4.4.2 Linking Revit architectural model: ................................................................... 44

    4.4.4.4 Types of electrical equipment installed ............................................................ 44

    4.4.4.5 Creating a circuit system:.................................................................................. 45

    4.4.5 Plumbing Model........................................................................................................ 46

    4.5 QUANTITYTAKEOFF ............................................................................................... 47

    4.6 SCHEDULE .................................................................................................................. 47

  • 8/9/2019 BIM- Pakistan case study

    8/76

    viii

    4.7 CLASHDETECTION .................................................................................................. 48

    4.8 ENERGYANALYSIS .................................................................................................. 49

    4.9 QUANTITYCOMPARISON ....................................................................................... 50

    4.10 PROBLEMSFACED ................................................................................................... 50

    4.11 SUMMARY .................................................................................................................. 51

    CONCLUSIONS AND RECOMENDATIONS ....................................................................... 52

    5.1 REVIEWOFOBJECTIVES ......................................................................................... 52

    5.2 CONCLUSIONS........................................................................................................... 52

    5.3 RECOMMENDATIONS .............................................................................................. 52

    REFERENCES ............................................................................................................................ 53

    APPENDIX -1.............................................................................................................................. 55

    APPENDIX -2.............................................................................................................................. 56

    APPENDIX-3............................................................................................................................... 57

    APPENDIX-4............................................................................................................................... 58

    APPENDIX-5............................................................................................................................... 59

    APPENDIX-6............................................................................................................................... 60

    APPENDIX-7............................................................................................................................... 61

    APPENDIX-8............................................................................................................................... 62

    APPENDIX-9............................................................................................................................... 63

  • 8/9/2019 BIM- Pakistan case study

    9/76

    ix

    ACKNOWLDGEMENT

    We are thankful to Allah Almighty for bestowing upon us the strength to accomplish this project.

    We would like to express our profound sense of reverence and deep regards to our supervisorAssistant Professor Zia Ud Din. His exemplary encouragement and constant guidance was the

    driving force behind the successful completion of the project. We are indebted to Consultant

    Civil Engineer at PRIMACO Mr. Waqas Ather, for providing us the necessary assistance and

    information regarding the project.

    Last but not the least we would like to pay our earnest gratitude to our parents and our colleagues

    for their incredible support and assistance.

  • 8/9/2019 BIM- Pakistan case study

    10/76

    x

    ABSTRACT

    Time and cost are major constraints of every construction project. But most of the projects fail to

    complete within the estimated budget and schedule. The main reason behind this failure is lackof coordination between different project stakeholders. With the introduction of CAD technology

    these hurdles have been minimized. But, still the coordination environment was lacking.

    Advancements in technology yielded new approach towards construction known as BIM.

    BIM stands for Building Information Modeling. It is a new way of approaching design and

    documentation of the building project. It is a comprehensive tool used for designing, initiating,

    executing, monitoring, controlling and completing a less time consuming and cost effective

    construction project. It encompasses the entire lifecycle of the building including operations. It

    provides a 3-D Model that helps in defining and simulating the building, its delivery and

    operations with the help of integrated tools. The feature of embedding quantity estimation and

    time scheduling together with a 3-D model makes it a 5-D model. In addition to the 5D model

    other technical aspects of BIM includes clash detection and energy analysis.

    5-d model of a building facility was developed in this project with different features of BIM were

    analyzed. The tools used in this project were Autodesk Revit, Autodesk Navisworks, Autodesk

    Green Building Studio and Autodesk Quantity Take off for 3-D modeling, scheduling, clash

    detection, energy analysis and cost estimation respectively. The project reflected theimprovements in quantities and number of change orders with the use of BIM by comparing the

    actual quantities with results obtained from model developed.

  • 8/9/2019 BIM- Pakistan case study

    11/76

    xi

    LIST OF ACRONYMS

    3D Three Dimensional x,y,z

    CAD Computer Aided DrawingBIM Building Information Modeling

    2D Two Dimensional x,y

    MEP Mechanical, Electrical and Plumbing

    CMM Capability Maturity Model

    4-D Fourth dimension-Scheduling

    5-D Fifth dimensionCost Estimation

    NBIMS National Building Information ModelingStandards

    IT Information Technology

    PM Project Manager

    OEC Overseas Employees Corporation

    PVC Polyvinyl Chloride

    IPD

    EOBI

    Integrated Project Delivery

    Employees Old-Age Benefits Institution

  • 8/9/2019 BIM- Pakistan case study

    12/76

    xii

    LIST OF FIGURES

    FIGURE 1.1 CONSTRUCTION AND NON-FARM LABOR PRODUCTIVITY INDEX ........ 2

    FIGURE 1.2 AREAS OF APPLICATION OF BIM (DISPENZA, 2010). .................................. 8FIGURE 2.1 FULLY FUNCTIONAL BIM (JIMNEZ ET AL., 2001).................................... 10

    FIGURE 2.2 CLASH DETECTION........................................................................................... 12

    FIGURE 2.3 COMPARISON BETWEEN DIFFERENT TECHNOLOGIES (AGC, 2005) ..... 15

    FIGURE 2.4 BIM MODELS ...................................................................................................... 19

    FIGURE 2.5 BENEFITS OF BIM (YAN & DAMIAN, 2008) .................................................. 21

    FIGURE 2.6 KRAKOW STADIUM COMPLEX SPIRAL STRUCTURE ............................... 22

    FIGURE 3.1 FLOW CHART OF THE RESEARCH METHODOLOGY ................................ 27

    FIGURE 3.2 INTEGRATED MODEL....................................................................................... 30

    FIGURE 3.3 QUANTITY TAKEOFF WORKING ................................................................... 31

    FIGURE 4.1 OEC TOWER SOUTH EAST ARTISTIC VIEW ................................................ 34

    FIGURE 4.2 OEC TOWER NORTH WEST VIEW .................................................................. 35

    FIGURE 4.3 OEC TOWER UNDER CONSTRUCTION ......................................................... 36

    FIGURE 4.4 SCHEDULE SCREENSHOT ............................................................................... 48

    FIGURE 4.5 DUCT BEND AND PLUMBING PIPE CLASH ................................................ 49

    FIGURE 4.6 HVAC AND PLUMBING PIPES CLASH ........................................................... 49

    http://c/Users/Faizan/Documents/fyp%20report%206%20june2014.docx%23_Toc391361062http://c/Users/Faizan/Documents/fyp%20report%206%20june2014.docx%23_Toc391361062
  • 8/9/2019 BIM- Pakistan case study

    13/76

    xiii

    LIST OF TABLES

    TABLE 2.1 BIM TOOLS .......................................................................................................... 23

    TABLE 4.1 PROJECT STAKEHOLDERS .............................................................................. 35

    TABLE 4.2 AREAS OF OEC TOWER .................................................................................... 37

    TABLE 4.3 FLOOR LEVELS ................................................................................................... 39

    TABLE 4.4 QUANTITY ESTIMATE SUMMARY ................................................................ 47

    TABLE 4.5 CLASH DETECTION SUMMARY ..................................................................... 49

    TABLE 4.6 QUANTITY COMPARISON ................................................................................ 50

  • 8/9/2019 BIM- Pakistan case study

    14/76

    1

    INTRODUCTION

    The construction industry in Pakistan has long been criticized all over the world for being

    inefficient and resource consuming. The reason behind the criticism is their unorthodox approach

    to construction which is much disorganized and utterly uneconomical (N. Azhar, Farooqui, &

    Ahmed, 2008). There is a room for improvement in every phase of construction. The

    construction industry has been facing an alarming situation in terms of labor productivity which

    is on the decrease since 1960, but it is worth noticing that process industries have increased their

    labor productivity. Thus, there is a dire need to balance out the situation to prevent wastage and

    cost overruns (Teicholz, 2004).

    According to a research, poor project site management, delays between design and procurementphases, incorrect methods of cost estimation and improper planning are one of the major reasons

    for cost overruns in the construction industry of Pakistan. As it can be seen from the researches

    the main factor behind the downfall is the lack of project integration and coordination. Thus,

    with the aid of new technology and digitized environment these hurdles can be triumph over (N.

    Azhar et al., 2008).

    Impact of technology on construction industry has been positive. The transformation from

    manual drafting to computer aided drafting was huge step up in construction industry. It

    revolutionized the whole construction industry the design issues were reduced and 2-D CAD

    environment provided the user friendly environment to the users to design the building

    components. It yielded better results and fewer conflicts than the manual drafting (Hergunsel,

    2011).

    As manual drafting was hectic, user was more prone to errors and to edit these drawings required

    them to be redrawn. The remedy in the shape of CAD environment was perfect at that time.

    These 2-D CAD drawings mimic the manual hand drafting in digitized platform which allows

    the user to edit them, make revisions and to minimize the complexity of drawings with use oflayer features. But, as the process industries progressed by leaps and bounds with an aid of

    modern technology as shown in the figure where we can see that Non-Farm productivity is

    increasing with the time. CAD could not keep pace with the process industries in the modern era

    as it can be seen from the figure 1.1 that construction productivity did not progressed and the

    Chapter 1

  • 8/9/2019 BIM- Pakistan case study

    15/76

    2

    new technology was required to keep pace with the other industries related to the construction

    industry (Eastman, Teicholz, Sacks, & Liston, 2008).

    Figure 1.1 Construction and Non-Farm Labor Productivity Index (Hergunsel, 2011)

    To minimize the wastage, cost overrun, inefficiency and conflicts. There was need of a fullycoordinated and digitized environment to overcome the limitations of CAD technologies and to

    increase the labor productivity. Thus, Building information approach was formulated to cater for

    these limitations and is the remedy for modern era construction issues.

    Today BIM has revolutionized the construction industry .It is the latest technology which is

    being widely accepted around the globe. A Building Information Model is a data-rich, object-

    oriented 3-D representation of the building project, from which appropriate data as per user

    requirement can be extracted to generate information that can be helpful to make decisions and

    improve the process of delivering the project (AGC, 2005).

    Since the introduction of BIM technology, the potential of software in construction management

    has profoundly increased. A Building Information Model contains as much information related

    to the building project as can be incorporated. This information can include performance

  • 8/9/2019 BIM- Pakistan case study

    16/76

    3

    information obtained throughout the lifecycle of the project, the buildings features and

    characteristics and functions of the building (Yan & Damian, 2008).

    1.1 OBJECTIVES

    The main objectives of this research were:

    I. To develop a 3D Model of a facility using Autodesk Revit for virtual representation of

    the real Project.

    II. To develop a simulated schedule of the project with the help of Autodesk Navisworks.

    III. To perform material takeoff of the project using Autodesk Quantity Takeoff software.

    IV. To perform clash detection between different models using Autodesk Navisworks.

    V. To perform energy analysis of the model using Autodesk Green Building Studio.

    1.2

    REASONS AND JUSTIFICATIONS

    The reasons and justifications for selection of the project are:

    1.2.1 Market Adoption and Growth

    Many experienced users are realizing the benefits of BIM modeling such as better

    communication, improved productivity, and greater chances of winning over the client. This is

    because of the fact that BIM helps in improving coordination between different departments inthe project team due to increased overlapping and integration. This helps in further improving

    productivity, enhancing quality control andstrengthening communication systems. A survey has

    shown that out of a 100 BIM experts, 82 experts have responded that BIM usage has been very

    beneficial in improving the productivity of their firm. BIM usage is not only increasing in the

    construction industry but many new firms are starting to adopt this technology (Dobson, 2004).

    1.2.2 User Experience

    The increasing use of BIM corresponds with a wholly pragmatic assessment of the general

    impact on the BIM users business practices. As users begin to see its vast benefits, they deepen

    their involvement with BIM. More than half of the users claim that BIM has had a very positive

    impact on their respective firms.

    A recent survey shows that in Construction Industry:

    http://thesaurus.com/browse/strengthenhttp://thesaurus.com/browse/correspondhttp://thesaurus.com/browse/correspondhttp://thesaurus.com/browse/strengthen
  • 8/9/2019 BIM- Pakistan case study

    17/76

    4

    I. 61% of Contractors believe that BIM is good for their Company.

    II. Many architects see BIM has been helpful in improving their businesses.

    III. Every 4 Clients out of 10 have reported that BIM has been productive for their projects

    IV. Furthermore, it has been found, that expert users are:

    V. More than three times likely to claim that BIM has resulted in improved efficiency for

    their internal activities (Dobson, 2004).

    VI. More than Four times likely to claim that BIM has resulted in improved efficiency for

    their peripheral activities (Dobson, 2004).

    The ability of a user to perform data analysis and extract information comes with skill and

    experience in using BIM tools. More experts are shown to use BIM tools for quantity takeoff of

    materials, scheduling of activities and cost estimation of the project as compared to beginners.

    1.3

    ADVANTAGES AND EDUCATIONAL OUTCOMES

    Building Information Modeling will be the lightening beacon in the future construction industry.

    The advantages of BIM are numerous as it covered every field of the construction from concept

    to conclusion. It has made a lot of complexities simple and has lightened the burden of drafting,

    documentation etc. The software evolution and new technologies in construction has been a very

    helpful tool in promoting BIM (Young, Jones, & Bernstein, 2008).

    Following are more useful benefits of BIM as discussed in Building Information Modeling byMcGraw Hill construction (Young et al., 2008):

    1.3.1 Improved Designs

    Building proposals can be analyzed on basis of cost and quality comparison, design efficiency as

    well as real time simulations can be performed. Further changes can be made to the already

    chalked out plans to improve performance and create a better design for the building.

    1.3.2 Life Cycle Asset Management

    Life cycle of a building is defined as the life of a building from its conception to its construction,

    maintenance and finally demolition. Building Information models provide the necessary

    Building information codes to help the user in different activities related to the life cycle of the

    facility.

  • 8/9/2019 BIM- Pakistan case study

    18/76

    5

    1.3.3 Improved Visualization

    BIM produces models that are far superior in quality as well as in the quantity of data stored in

    them. For students and clients, BIM is an excellent starting point in helping visualize the

    physical features and characteristics of a project. This makes communicating the complex

    aspects of the building design to the new user very easy.

    1.3.4 Less Wastage

    BIM facilitate in calculating the precise amount of material quantity from the model through

    quantity takeoff so that neither an excessive order is placed for the materials nor is there any

    storage problem caused on the project site. The schedule also provides the user with an idea of

    when the equipments and materials should be brought on site to avoid any delays and also

    minimize the chance of any damage caused to the materials due to weather or other factors. This

    in turn results in less material wastage as well as efficient use of labor force and equipment.

    1.3.5 Reduced Safety Requirements

    Many special features of BIM make the facilities more hazard proof such as a process known as

    Fire Protection Modeling. This process ensures that the design can be re evaluated for public

    safety and the best possible steps can be taken in order to make the facility more safe for theoccupants in case of a fire breakout. Safety risks can also be evaluated before the construction

    phase even begins. The project manager is free to review the project complex tasks and activities

    beforehand in order to reduce the risks for any potential injury or damage.

    1.3.6 Guidelines for Students

    The projects being done on BIM will provide a guideline to newcomers. If you want to

    understand today, you have to search yesterday (Pearl S. Buck). Newcomers need not to face allthe problems that are currently being faced. The guideline will include the daily life construction

    processes etc.

  • 8/9/2019 BIM- Pakistan case study

    19/76

    6

    1.3.7 Personal and Social Advantage

    The projects on BIM will be an exposure to the latest technology being used in modern

    construction industry. This would help the students to work on more productive disciplines rather

    than textbook disciplines which would pave way for new construction era.

    1.3.8 Forensic Analysis

    Forensic analysis is the science of analyzing the results obtained after investigating a happened

    incident and then documenting the causes based on evidences. Forensic analysis can be

    facilitated significantly using building information modeling as BIM graphically visualizes the

    potential damages, leaks and evacuation plans (S. Azhar, Hein, & Sketo, 2008).

    1.3.9

    Facility Management

    Facility management is the vast field which includes the coordination of buildings, office blocks,

    schools, shopping centers, hotels and hospitals in a way to achieve maximum efficient system.

    BIM in this field is used for the operations of renovation, space planning and maintenance (S.

    Azhar et al., 2008).

    1.4 AREAS OF APPLICATION

    Almost every area of construction industry is covered by BIM. Its influence is on every fieldincluding the design phase, construction phase and management phase. It provides a platform for

    the digitized construction which would be very useful in reducing change orders and schedule

    delays. Areas of application of BIM can be seen from the figure 1.2. The results of this project

    can be applied for:

    1.4.1 Improved Communication:

    BIM can greatly improve the cross department communication as well as between different

    parties like clients, financers etc that are attached to the project and helps to remove any

    confusions held by the parties. One of the main reasons why project managers and contractors

    prefer to use BIM over other 3D software is that the 3D model obtained through BIM is a much

    realistic conception and therefore helps the client in deciding what kind of a facility they want to

    build.

  • 8/9/2019 BIM- Pakistan case study

    20/76

    7

    1.4.2 Shop Drawings

    BIM helps in generating high quality shop drawings for various building systems and features.

    The shop drawing produced for the building can be anything from a detailed isometric image of

    the Plumbing lines in the facility to the site layout. An example is that once the building model

    design is complete; one can easily produce the MEP (Mechanical, Electrical and Plumbing) shop

    drawings. These shop drawings can be used by the contractors to visualize different components

    of the building.

    1.4.3 Cost Estimation

    BIM Software often includes a very useful cost estimation feature. The quantity of all the

    materials used the facility are estimated by the estimation tool and costs are calculated based on a

    set standard of prices for each material. The software calculates the costs for all materials andadds them up in the end to give the total cost estimate. The number of labors and their working

    hours can be used to calculate the total estimate of the project.

    1.4.4 Project Scheduling

    Project scheduling tool allows the user to link up different sets of activities with the

    corresponding elements in the BIM model. By linking these activities, the user is able to obtain a

    bar chart of the project schedule which helps the project managers to find out any conflicts

    between different activities and plan a clash free schedule. By comparing the planned and real

    schedules, the project manager is able to better plan the course and speed of activities.BIM also

    provides the construction project simulation which aids in visualizing the actual construction

    project.

    1.4.5 Conflict, Interference and Collision Detection

    BIM models are made in 3-D space so every single object created is visually accessible.

    Therefore any clash and interference among pipes, beams, columns and electrical wiring can

    easily be detected (Jimnez, Thomas, & Torras, 2001).

    These detections help in saving a lot of time and money. This is possible when there are reduced

    numbers of change orders and the clashes can be easily visualized.

  • 8/9/2019 BIM- Pakistan case study

    21/76

    8

    All the applications of BIM can be seen in figure 1.2

    Figure 1.2 Areas of application of BIM (Dispenza, 2010).

  • 8/9/2019 BIM- Pakistan case study

    22/76

    9

    LITERATURE REVIEW

    2.1 BACKGROUND

    The development of the country is very much influenced by the advancement in its constructionindustry. There is a dire need of infrastructure and buildings in every underdeveloped country in

    order to pave way for the economic growth of the country.Building construction progress has

    been hampered by the economic losses and decreased labor productivity. The economic losses

    were caused by the defects in the design due to which the prefabricated components of the

    building are not suitable thus the whole component has to be replaced when there is a design

    failure such as constructability issues during the construction.

    In 1974 Chuck Eastman and five other authors presented a paper in which they explained the

    chief means of communication used in building design and construction processes which were

    drawings, including notes and specifications. They mentioned few problems which were

    i. In 2D drawings at least two drawings are required for understanding the structure thus

    one dimension is shown twice. 2D drawings also become redundant as different items are

    shown in two different drawings at different scale. All this means if a change is to be

    done in any drawing it has to be changed in all drawings.

    ii. Large efforts are required to keep the design up-to-date. But even with all this hard work

    there is a possibility that information somewhere is obsolete and non-consistent.iii. For analysis of construction, information has to be taken manually from drawings which

    is laborious work

    They also suggested a solution, that is to create a computer system that could save and control

    design information at great detail. This was named as building description system (Eastman et

    al., 2008).

    The solution to the above mentioned problems is BIM and it plays an important role in

    developing a proper model of a building which represents every aspect and runs the analysis of

    the building.

    2.2

    BUILDING INFORMATION MODELING

    The construction industry has been facing a dramatic change to (I) increase; efficiency,

    productivity, infrastructure value, quality and sustainability, (ii) reduce; lifecycle costs, lead

    Chapter 2

  • 8/9/2019 BIM- Pakistan case study

    23/76

    10

    times and duplications, via effective collaboration and communication of stakeholders. Digital

    construction seeks to integrate processes throughout the entire lifecycle by utilizing building

    information modeling (BIM) systems as it can be seen in figure 2.1 (S. Azhar et al., 2008).

    Figure 2.1 Fully Functional BIM (Jimnez et al., 2001).

    BIM stands for building information modeling. It is anew and revolutionary approach for the

    designing, construction and management of buildings.BIM is viewed in this proposal according to the following definition of BIM. According to the

    White paper published by Autodesk BIM is defined as:-

    Building information modeling is an approach to building design, construction, and

    management. It supports the continuous and immediate availability of project design scope,

    schedule, and cost information that is high quality, reliable, integrated, and fully coordinated.

    Though it is not itself a technology, it is supported to varying degrees by different technologies

    (autodesk, 2003).

    The main function of BIM is to create a 3-D model in digital form which depicts the real life

    environments .It provides the features to run the maintenance program after the completion of

    the building. In order to have maximum control over the project there is a need of different

    models including Architectural, Structural, MEP, resource management and others including a

  • 8/9/2019 BIM- Pakistan case study

    24/76

    11

    detailed schedule. So, BIM is referred to a combined model where models from different

    disciplines are merged (Lahdou & Zetterman, 2011).

    The purpose of the building construction is achieved when the building is functional. Building is

    functional when purpose of the facility completely or partly serves. Thus, BIM is a digital

    depiction of physical and functional characteristics of a facility. It is a shared information

    resource about a facility forming consistent basis for decisions during its life-cycle (NBIMS,

    2007).

    BIM provides the focal point for the project stakeholders. All the data required by any type of

    stakeholder will be available through BIM. The project location and the environmental impact on

    the project is a new feature of BIM. The building location provides the information about the

    impact of natural surroundings, temperature and effect of sunlight. So, building information

    model describe the geometry, geographic information spatial relationships, quantities andcharacteristics of building elements, material inventories, cost estimates and schedule of

    performance. This model can be used to express the entire building life cycle (Bazjanac, 2006).

    2.3 TECHNICAL ASPECTS OF BIM

    Different BIM functions are explained which are attached to each BIM level support.

    2.3.1 Clash Controls

    BIM model of different disciplines can be checked at same moment for any type of geometrical

    design errors. Those areas where these models overlap each other when they are brought together

    can easily be altered and can be made error free(Eastman et al., 2008).

    To perform clash controls in BIM Autodesk provides a tool named Autodesk Navisworks. The

    reports can be generated to identify these clashes and there affects on the structure. The

    alternatives are also suggested in order to get out of these critical situations with relative ease.

    Controlling clashes helps in minimizing change orders and redesigns (Eastman et al., 2008).

    This feature has been very effective as it identifies clashes before construction unlike the manualdrafting where the clashes were identified during the construction which caused costly delays

    and the projects could not be completed within budget. Clash detection feature is shown in

    figure 2.2.

  • 8/9/2019 BIM- Pakistan case study

    25/76

    12

    Figure 2.2 Clash detection

    2.3.2 Analyses

    Analyses on energy usage can be done by synchronizing a BIM model to those tools which

    determine the isolating ability of a structure and it can analyze total usage for heating and

    cooling for that structure in extreme conditions. This makes the structure more energy efficient

    and cost economical. (Eastman et al., 2008).

    2.3.3

    Time Estimation (4D)

    The time estimation tool, more commonly known as 4D, links the objects present in the

    information of a building with plan of time. This link then helps in visualizing the projects

    schedule. Moreover, it can be used by users to simulate the building location and construction at

    random time frames. Such project modeling provides important data and helps the user in

    foreseeing errors which rear their ugly head later on creating a problem for the user. Autodesk

    provide the perfect platform to provide this feature in Autodesk Navisworks. The simulation of

    construction in real world is run in this tool which makes it easy to communicate and sequence

    different activities .Schedule from Primavera can be imported into the project (Eastman et al.,

    2008).

    Clash betweenpipes

  • 8/9/2019 BIM- Pakistan case study

    26/76

    13

    2.3.4 Cost Estimation (5D)

    The cost estimation tool (also known as 5D) allows all the elements in the 3D design to be

    connected with a set price list for all the materials. Although, price lists are mostly based on the

    volume cost of materials but it can also include the cost of the laborers and equipment cost. This

    provides the user with a more detailed cost estimate of the project. Such as detailed cost estimate

    in the early design phases creates a better understanding of the financial implications in terms of

    design changes and therefore, decisions regarding materials and construction can be evaluated

    from an economical standpoint. Autodesk provide this feature in Autodesk Quantity Takeoff

    (Eastman et al., 2008).

    2.4

    BIM LEVELS

    The capability maturity model (CMM), which was developed by NIBMS, defined the

    organizational level of a model and provided the users with an opportunity to evaluate their

    procedures based on a wider array of technical objectives.

    The basic aim of using CMM is to create a tool for calculating the level of maturity in a building

    information model by analyzing it against an established criterion and provide that information

    to the project stakeholders. The term maturity depicts that to which extent the features of BIM

    are implemented. On the horizontal axis of the matrix there are eleven spheres of concern, for

    example: data richness, life-cycle views and roles or disciplines. The vertical axis on the otherhand contains ten levels of maturity. Ten is considered to be the greatest level of maturity from

    the Appendix-1.

    Different communities form their own criteria to calculate the level of maturity regarding the

    utilization of BIM. The maturity regarding utilization of BIM in Ramboll is described by levels

    ranging from 0 to 3, where 0 is the lowest and 3 is the highest level of progression. The parts of

    BIM which are included in BIM levels are specified. What parts of BIM which are included in

    each BIM level is specified. This proves to be the driving force behind the task managers to

    progress to next BIM level which makes the projects successful. The task mangers can expedite

    their projects for some monetary advantages by moving up to next BIM levels. Utilization of

    BIM is very effective for most of the communities so most communities tend rate their success

    on the basis of BIM levels (Teicholz, 2004).

  • 8/9/2019 BIM- Pakistan case study

    27/76

    14

    BIM levels are as follows:

    2.4.1 Level 0Usage of BIM Software

    During this level 3D model is only used in the design phase and there is no coordinated

    integration with other parametric models or fulfils requirements regarding documenting of all

    information exchange that takes place i.e. the concept of 5D model is not implemented (S. Azhar,

    Carlton, Olsen, & Ahmad, 2011)

    2.4.2 Level 13D Coordination

    For BIM Level 1, a satisfactory level of coordination of functions between the different

    disciplines (civil, electrical and mechanical disciplines and project hierarchy) is achieved. Clash

    controls are performed as models of all the disciplines are integrated (S. Azhar et al., 2011)

    At this level of BIM information flow within the project team is structured and identified tomake common goals which would be achieved later on which would help to achieve the main

    objective of the project.

    2.4.3 Level 2Analyzes, Time and Cost Estimation

    At level 2 in BIM, level 1 and more additional BIM services which requires multi disciplinary

    data input are provided. In this level certain services are available which include energy

    analyzers and basic variant of time and cost estimation (S. Azhar et al., 2011).

    In this level schedule development and cost estimation are performed with the inclusion of

    effects due to the building orientation, water harvesting techniques due to which building water

    consumption will be less and sustainable materials which helps in reduction of materials used.

    Thus, paving way for energy efficient building (Hergunsel, 2011).

    2.4.4 Level 3Integrated Model

    At level 3, a simpleton model is not enough and further complex models are needed to operate.

    Services from both level one and two are provided with an extremely well coordinated and

    integrated model between many disciplines. This level integrates all the data including 5-D

    model and energy analyzing data, This level needs high level of effort as data needs to be

    updated periodically so that maintenance program can be run effectively (S. Azhar et al., 2011)

  • 8/9/2019 BIM- Pakistan case study

    28/76

    15

    2.5 TECHNOLOGIES IMPLEMENTED IN BIM

    BIM is an approach not a technology so it does requires suitable technologies to implement

    effectively. Figure 2.3 describe the comparison between different technologies. These

    technologies are:

    Figure 2.3 Comparison between different technologies (AGC, 2005)

    2.5.1 CAD Technology

    This technology supports drafting automation effectively but modern construction requires high

    level of competence. Using this software can demand high level of effort by maintainingstandards such as layers and naming standards. This requires the user to be efficient, highly

    skilled and disciplined, due to which high level programmers are required to do this job.

  • 8/9/2019 BIM- Pakistan case study

    29/76

    16

    2.5.2 Object CAD Technology:

    It aims to replicate the building components in CAD drawing, by focusing on the 3D dimensions

    and geometry of the building facility, the generation of documentation from that 3D drawing and

    by extracting object data from the building components in order to be able to generate

    information about object parameters and quantities. (AGC, 2005)

    In object CAD the 3D geometry is used but this becomes really complex for larger projects as

    more than one floors are made it also requires a lot discipline and care should be taken while

    using this technology, not much liberty is provided to make plans with ease. As the manual

    correction is required in CAD technology it also requires the same pattern to implement the

    corrections.

    2.5.3

    Parametric Building Modeling

    Parametric building modeling corresponds to the decision support system in the Financial

    Community. This provides an integrated system that can be used to simulate the behavior of a

    real-world system. These systems blend a Data model (geometry and lengths) with a Behavioral

    model (change management). In this technology basically the building model is fully coordinated

    throughout the model i.e. every building component is related to each other. If there is a change

    in one component then the consequences of the change is applied throughout the related

    components such as if the door height is to be altered then automatically the wall above it will be

    altered accordingly. This provides the basic interrelated information which lessens the work

    effort. Autodesk Revit is an efficient tool which provides the platform to implement this

    technology (AGC, 2005).

    2.6

    BIM AND PROJECT MANAGERA

    Can BIM be used for Project Management? How Project Managers are influenced by BIM?

    These are some questions which arise in ones mind. But after the thorough study of literature it

    was concluded that the benefits found in projects using BIM are more than the challenges,

    moreover the benefits found are aligned with the function of a Project Manager.

    The literature showed that there is a dire need for integration of Project teams and collaboration

    of all parties.BIM could be used effectively for the integration of Project teams and collaboration

    of all Parties. The Project can be performed in a combined manner to save Cost, time and to

  • 8/9/2019 BIM- Pakistan case study

    30/76

    17

    work within the scope. A survey was carried out to understand the influence of BIM on the role

    of project manager and it states that 50% of the response showed that project manager should be

    proficient in BIM and 24% response was that project manager should be in charge of BIM-

    management. Many studies have shown that BIM is a tool that goes far beyond its designed

    functions. Therefore, the Project Manager should always lead in BIM Management just like he

    has to lead in all other departments of IT systems in Complex Projects. Although there are some

    difficulties and challenges faced in the implementation phase of BIM technology but this can be

    overcome by investing for the sufficient training of Staff in the use of BIM (Jimnez et al.,

    2001).

    Another challenge was the existence of certain Software related issues which did not allow the

    unleashing of full potential of BIM. The research suggested that the PM must contribute towards

    solving these issues rather than considering it as an excuse to not use BIM (Jimnez et al., 2001).But the main question arises how BIM can benefit the project manager. The task of the project

    manager is to deliver a successful project. A successful project can be defined as the Project

    delivered on time, within budget and within the scope.

    BIM provides certain benefits which would help the project manager to deliver a successful

    project, the benefits are:

    2.6.1

    Communication BenefitsThe communication between different stakeholders improves with the help of BIM. The main

    reason behind it is the development of a 3-D model which is easy to understand unlike a 2-D

    Model which has to be imagined to visualize it in reality and not enough information can be

    included in such models.BIM allows for less costly and time consuming visualizations which are

    impossible using traditional modeling. The clarity and depiction of real world model helps to

    communicate with different stakeholders (Lahdou & Zetterman, 2011).

    2.6.2

    Quality Benefits

    The quality of a project can be improved with the help of a 3-D model which helps all the

    stakeholders involved to understand their roles and their objectives. The data need to be entered

    once in the BIM unlike traditional models which makes cumbersome and complex computations.

    The process of documentations is also improved. Reports can be generated in any format and can

    include the required data. The clashes can be controlled in a Project as all the models are

  • 8/9/2019 BIM- Pakistan case study

    31/76

    18

    integrated in one model and clashes are detected and can be corrected. The model includes the

    input of different stakeholders which provides s[specific information to the respective

    stakeholders (Lahdou & Zetterman, 2011).

    The benefits above can create mutual understanding between client and the project manager

    because of the clear goals and objectives. This takes both client and the project manager on same

    page. BIM utilized in design phase helps in creating schedules. This helps in calculating the

    budget. BIM linked with time helps in planning the construction execution process .It provides

    better control over the project. Cost estimates provides better control of economic aspects of

    BIM and can optimize the value a client can obtain from the investment (Lahdou & Zetterman,

    2011).

    2.7

    BIM AND CONSTRUCTION MANAGEMENT

    There are three major areas of Construction Management which are as follows:

    2.7.1 Design Phase

    It is a duty of an architect to balance the scope, cost and schedule of the Project. If there are ill-

    timed changes then it will adversely affect relations between client and the consultant. Using

    BIM all the data is available straight away and in updated form so that project related decisionscan be taken swiftly and effectively.

    BIM allows project team to make changes in designs during design phase without any

    backbreaking and manual checking work because when there is a correction to be made in design

    while not using BIM, the correction needs to be implemented to every related component

    manually in order to make the design ready. The check and balance is also required to see if all

    the related areas are corrected but in BIM the change is coordinated throughout the related

    components and less time will be consumed. All the design and documentation work can be done

    concurrently rather than one after the other.

    BIM coordinates the change and its consequences made in the certain point of project throughout

    the project lifecycle automatically. The design team can deliver the work faster. BIM eliminated

    the coordination mistakes and improve the quality of work. The three different models are shown

    in figure 2.4.

  • 8/9/2019 BIM- Pakistan case study

    32/76

    19

    Figure 2.4 BIM models

    The four thorough Case Studies of BIM implementation for precast concrete design by mid-sized

    structural engineering firms, reported by Kaner, Sacks, Kassian and Quitt revealed that the

    designs were error free which improved the labor productivity with the help of BIM (Eastman et

    al., 2008).

    2.7.2 Construction Phase

    BIM makes available concurrent information on Building quality, schedule and cost. Builder can

    speed up quantification for estimation, production of updated estimates and construction

    planning. The consequences of procured products can be studied using BIM by using a virtualconstruction tool of BIM which helps in locating the defects in the building before physical

    construction is even started, so corrected procured products (e.g. prefabricated beams) can be

    ordered and plans can be prepared quickly. BIM ensures less time and money is spent on process

    and administration issues because of high document quality and better construction planning.

    The digitized nature of BIM releases the complexity of manual documentation process by

    automatic generation of reports.

    In a large health care project due to BIM/VDC (software) there were zero-conflicts and 100%

    prefabrication and maximum labor productivity with zero accident in the field. With 6 months

    savings on schedule and $9 million on the cost (Eastman et al., 2008).

  • 8/9/2019 BIM- Pakistan case study

    33/76

    20

    2.7.3 Management Phase

    BIM provides digital record of renovation and improve move planning and management. It

    accelerates the adaption of standard building sample to site conditions for businesses. Physical

    information about the building is also available such as financial data and furniture inventory etc.

    Consistent access to this information improves both revenue and cost management in the

    operation of the build.

    2.8

    ADVANTAGES OF BIM

    Building information modeling supports the continuous and immediate availability of project,

    design scope, schedule, and cost information that is high quality, reliable, integrated, and fully

    coordinated (AGC, 2005).

    The advantages are:

    I. Better Coordination

    II. High quality work

    III. Low cost

    IV. Time saving

    V. High labor productivity

    VI. Environmental Impact

    VII. Safety provisionsVIII. Pre-fabrication

    IX. Less work force

    X. Less conflicts

    XI. Visual aids

    XII. Record Data

    XIII. Maintenance Program

    XIV. Less changes

    A research at the Stanford University research center on BIM revealed that

    i. Up to 40% elimination of unbudgeted change.

    ii. Cost estimation accuracy 3%.

    iii. 80% reduction in time taken for cost estimation

    iv. 7% reduction in project time

  • 8/9/2019 BIM- Pakistan case study

    34/76

    21

    v. 10% clash detection which saves the budget.

    In many projects millions of dollars have been save by using BIM. Time delays have been

    provided. Designs have been corrected with the help of contractors services and BIM. This

    all is done in a coordinated way so that no time is wasted correcting the remaining of the

    project. Digital process helps in getting work done without a lot of manpower just few

    technicians are required to operate this software. The figure 2.5 shows the acknowledgement

    about BIM from the top eight construction companies in UK and USA.

    Figure 2.5 Benefits of BIM (Yan & Damian, 2008)

    2.9

    BIM IMPLEMENTATION IN REAL LIFE

    Some of the examples of implementation of BIM in real life are:

    2.9.1 Melbourne Stadium

    Studies have shown that use of BIM on Projects has resulted in a 500% return on investment,

    while the use of Bentley structural for scheduling and documenting yielded only a 200%

    return. Final optimization results through BIM have shown a 10% savings in roof tonnage in the

    steel members with an ideal roof profile.

    This was possible only due to the optimization studies (time and money saving designs) and the

    function of BIM to compare different structures which proved helpful in eliminating the errors.

  • 8/9/2019 BIM- Pakistan case study

    35/76

    22

    2.9.2 Water Treatment Plant-Walsh Group

    Using Bentley Structures 20 conflicts in the design and construction phase were discovered. This

    helped the organization to save $90,000 and 7 weeks of delay due to the comprehensive 3D

    model of BIM which was easy to understand and revealed minor details which were very

    effective as a truss was designed incorrectly as it was overlapping a steel beam by 6-inches.

    2.9.3 Krakow Stadium

    Generative component is an efficient BIM tool provided Bentley systems. A highly complex

    spiral structure was designed for the stadium within little amount of time and avoided time

    delays with the ability of BIM software Generative components to design complex geometry

    without reworking the documentation process allowed them analyze different spiral geometric

    structures as shown in figure 2.6.

    Figure 2. 6 Krakow Stadium complex spiral structure

  • 8/9/2019 BIM- Pakistan case study

    36/76

  • 8/9/2019 BIM- Pakistan case study

    37/76

    24

    The tools used in the current project are Autodesk Revit, Autodesk quantity takeoff, Autodesk

    Navisworks and Autodesk Green building studio. These software are user friendly and are easily

    accessible. The tools used in this project are:

    2.10.1 Autodesk Quantity Takeoff

    Autodesk quantity takeoff helps to calculate and estimate materials more swiftly, accurately and

    easily. Cost estimators can create synchronized, comprehensive project views that combine

    important information from building information modeling (BIM) tools such as Revit

    Architecture, Revit Structure, and Revit MEP with images geometry and data from other tools.

    It can also calculate areas and count the building components manually or automatically and can

    export them to Excel and to create DWF format.

    i. Take-off in minutes automaticallyPerform a take-off on an entire building

    information model (BIM) in just minutes through integration of 2D and 3D design data.

    ii. Greater flexibility than typical databases or spread sheetsPerform interactive

    examination of 3D models for material cost estimating purposes.

    iii. Dynamic countingCount and quantify design data quickly and easily.

    iv. More efficient manual take-offsupports the take-off of JPG, TIF, PDF, and other no

    intelligent image formats.

    v. Share, query, and clarifyGenerate quantities linked to specific objects. Mark up and

    round-trip your comments.

    vi. Faster and more insightful quantity reportsCreate summaries and detailed quantity

    surveying reports quickly and easily.

    2.10.2 Autodesk Revit

    Revit software is specifically developed for building information modeling (BIM), enabling

    design and construction professionals to take ideas from concept to construction with

    coordinated and consistent model-based approach. Revit is single software that includes features

    for architectural design, MEP and structural engineering. Its model can be imported into other

    BIM tools in order to perform other BIM functions such as clash detection, energy analysis and

    scheduling etc.

  • 8/9/2019 BIM- Pakistan case study

    38/76

    25

    Some of the features of REVIT are:

    i. Bidirectional associabilityany change in one aspect of a model is reflected throughout

    the model.

    ii. Parametric componentsit uses intelligent building components to improve design

    accuracy.

    iii. BIM platformprovides a platform for building information modeling by exporting the

    model to other tools to perform other functions.

    iv. Realistic Modelthe 3D model obtained depicts the realistic model with an ability to be

    edited.

    v. Flexibilitythe software provides an environment where every designer can work

    including an Architect, MEE and structural designer.

    vi. Work sharingprovides an environment where a single Project model can be accessedby different users and changes can be made in

    certain areas by the respective users. .

    vii. Energy Analysissupport sustainable design decision making.

    viii. Improved schedulesSchedule enhancements with Parameters, Filter & Grand Totals.

    2.10.3 Autodesk Green Building Studio

    It is energy analysis software which helps designers and architects to perform energy analysis,

    optimize energy consumptions and work toward carbon neutral building designs during the early

    processes of the construction project. It is cloud based software. The concept of Green building

    can be achieved through this software as it allows analyzing buildings and provides the

    alternative materials to develop a sustainable model. Some of its features are:

    I. Building energy analyseswhole building energy analyses calculates total energy use

    and carbon emission of a building on annual, monthly and daily basis using global

    database of weather information

    II. Weather Datait gives user the access to numerous weather stations which arecompiled from many trusted sources.

    III. Water usageestimates water usage inside and outside of the building.

    IV. Solar radiationvisualizes incident solar radiation on window surfaces over any period.

    V. Day lightingReceive qualification for LEED day lighting credit.

  • 8/9/2019 BIM- Pakistan case study

    39/76

    26

    VI. Shadows and reflectiongives the shadows and reflection data with respect to sun

    path.

    2.10.4 Autodesk Navisworks

    Navisworks features enable coordination, construction simulation, and project analysis for

    integrated project review. It provides users advanced tools to simulate scheduling and perform

    clash detection. It enables coordination, construction simulation and project analysis for

    integrated projects.

    I. Clash detection and interference checkingforesee and avoid possible clash and

    interference problems before construction, reducing change orders and delays.

    II. Model file and data aggregationModel publishing and data and model aggregation

    tools enable user to integrate design and construction data into a single integrated model.III. 5D project scheduling includes time and costSimulate construction project

    scheduling in 5D to visually analyze project activities and reduce delays and sequencing

    problems regarding the project.

    IV. Photorealistic model renderingUse photorealistic model rendering capabilities to

    develop animations in 3D and images.

  • 8/9/2019 BIM- Pakistan case study

    40/76

    27

    METHODOLOGY

    In order to meet the pre-defined objective, this chapter presents the research methodology

    adopted. The sequence by which this particular project will be progressed is presented in a flowdiagram shown below:

    Figure 3.1 Flow Chart of the research methodology

    Chapter 3

  • 8/9/2019 BIM- Pakistan case study

    41/76

    28

    The steps followed are explained below:-

    3.1

    SELECTION OF THE TOPIC

    In order to carry out the project BIM was selected as BIM provides the modern tools for

    construction and allows the user to maintain the focus on other important issues.

    3.2

    LITERATURE STUDY

    In previous chapter some important terminologies were mentioned and discussed which proved

    helpful in studying BIM and its uses including better visual effects, prefabrication, project

    planning and management and cost control. Literature study was facilitated by attending lectures

    and presentation more over official website of Autodesk and thesis were studied, case studies

    including Krakow stadium, Marina bay front pedestrian bridge, Melbourne Stadium and research

    books related to BIM were consulted. This helped to understand and gain the required

    information about BIM.

    3.3

    SITE SELECTION

    Literature study and site selection were performed simultaneously. For the quest of building site

    different buildings were visited in Islamabad including MARI Petroleum Ltd. (G-10), State Life

    Tower (Blue Area), Grand Hyatt Hotel (Constitution Avenue) and OEC Tower, (G-9/4). OECTower G-9/4, Islamabad was a suitable site and feasible in all aspects. Thus, with the aid

    National University of Science and Technology and PRIMACO officials the building was

    formally selected.

    3.4 DATA COLLECTION

    Data collection and understanding is very important in order to process the data into very useful

    in information. Thus, Architectural drawings were provided by the site officials to kick start theproject and with the passage of time structural and MEP drawings were provided as per

    requirements. But data collection requires some official permits to share some confidential data.

    But still there are some aspects of data which are left to be desired.

  • 8/9/2019 BIM- Pakistan case study

    42/76

    29

    3.5 LEARNING SOFTWARE

    The Project progress depends on a certain tool. Thus, Autodesk Revit , Autodesk Quantity

    Takeoff, Autodesk Navisworks and Autodesk Green Building Studio were selected tools for

    modeling, material take off, scheduling and energy analysis respectively. The reasons behind

    selecting these tools were there availability and special access for students to these tools with the

    help of student licenses. Different tutorials were used for the process of learning. The main

    sources for these tutorials were youtube.com, Lynda.com, Autodesk and NUST provided certain

    resources to learn the software.

    3.6

    3-D MODELING

    3-D modeling can only be performed when the user is familiar with the software. A 3D model is

    a three dimensional model of three different disciplines of construction i.e. Architecture,

    Structure, MEP (Mechanical, Electrical and Plumbing). Modeling of these three different models

    was done separately and with the feature of Revit 2013 these three models were linked together.

    Using copy monitor feature these three models were coordinated. Architectural model consists of

    basic walls, flooring, finishes openings doors and other architecture components. This model was

    made with the aid of architectural template available in the internet. The different views of the

    model can be seen in the Appendix section.

    Structure model consist of beams, columns, reinforced walls and structural items.Reinforcements were given to the framing components and structural analysis was performed in

    order to verify the design.

    MEP model consist of fittings, fixtures, HVAC, electrical and mechanical components which

    aided for mechanical purposes. A general integrated 3D model can be seen in the figure given

    below. Plumbing model consists of fire pipes, water pipes, joints, water sprinklers, bends and

    drainage pipes etc. The HVAC consist of ventilation system of the building and cooling and

    heating systems of the building with temperature sensors. Electrical systems include electrical

    wiring, lighting fixtures and sockets etc.

    All these models were created with a help of manual 2D drawings. A general integrated model is

    shown in figure 3.2.

  • 8/9/2019 BIM- Pakistan case study

    43/76

    30

    Figure 3.2 Integrated model

    3.7 CONSTRUCTION PROCESS SIMULATION

    Scheduling is important in order to take note of the time. Autodesk Navisworks Manage was

    used for scheduling purpose. The integrated 3-D model was exported from Autodesk Revit in a

    NWC format. The model NWC format file was imported into Autodesk Navisworks Manage.

    The schedule was imported from Primavera P6 into the model in Navisworks. The activities and

    building components were linked together to create a simulation using a tool called timeliner.

    Different project elements were assigned the related activities to form a simulated schedule. The

    construction process could be visualized over the span of time.

    3.8 QUANTITY TAKEOFF

    Much BIM software have integrated Cost estimation tools which can easily extract material

    quantities from the BIM 3-D Model and then use the unit price method to calculate the total cost

    of all materials.By using the cost estimation tool in BIM construction materials, equipment and labor force

    needed for work can be co-related with the resources available on the project. For example, for

    laying the foundation, a concrete Mixer is required, several skilled labors as well as many

    reinforcement bars and bags of concrete, along with the usual concrete checks and safety

  • 8/9/2019 BIM- Pakistan case study

    44/76

    31

    precautions needed on the sight etc. BIM can be used to breakdown each work package into

    smaller units and analyze step by step all the related tasks. This helps the user to optimize the

    work flow and the quantity of equipment, materials and labor needed for each task such as

    number of laborers needed for a specific task, which in turn results in greater optimization of the

    entire construction phase.

    There are two main fundamentals of cost estimation in BIM, one is pricing and the other is

    quantity takeoff. The quantity takeoff tool analyzes the 3D BIM model and extracts the

    quantities of all the materials into a database such as a MS Excel file. A cost estimator needs to

    have extensive estimation skills and knowledge in order to extract accurate information from the

    model, even to the point of breaking down of an activity into several components in order to get

    a better estimation.

    Once the estimations are extracted from the model, the estimator has to input the unit prices ofall different materials, labor hours etc. In this way, the estimation tool can multiply the estimated

    quantities with the unit prices to produce a highly accurate cost of the project.

    The other tool used efficiently in BIM is Autodesk Quantity Takeoff. This tool performs the

    quantity takeoff directly from the 3-D model made in compatible modeling tool. The cost, labor

    hours and productivity are calculated with the factors added into the software. The working of

    Autodesk quantity estimation can be seen from the figure 3.3:

    Figure 3.3 Quantity Takeoff working

  • 8/9/2019 BIM- Pakistan case study

    45/76

    32

    3.9 CLASH DETECTION

    Every Project has design issues. The main design issue is the clash of designs of different

    disciplines e.g. clash between MEP and structure design. These issues can be costly as they cause

    delays and costly change orders. The main reason behind these clashes is the lack of coordination

    between personnel of different disciplines.BIM provides certain tools to minimize these clashes

    in the design phase. But still a lot has been left to be desired. So another feature BIM provides to

    identify clashes between different disciplines after the designs have been completed. Thus

    Autodesk Navisworks was used in this project to identify clashes. Models form different

    disciplines were imported into Navisworks and process was run in order to identify clashes. The

    reports of the clashes detected were generated which could be useful to send to other

    stakeholders to make changes to their design respectively.

    3.10

    ENERGY ANALYSIS

    Nowadays a lot of emphasis is laid on sustainable design and green building. In order to run the

    energy analysis of the project Autodesk Green building studio was used. The integrated 3-D

    model was imported in to the software. The location of the building was entered, data period was

    entered and the energy results were obtained. The heating and cooling loads were identified. The

    shadow data, water usage and carbon emission data was resulted.

    3.11

    ANALYSIS

    By the end of estimating costs, the aim of having 5D model was achieved. At that stage there

    was a requirement of checking all the work that was done so far so that errors and omissions

    could be traced and eliminated. In final review the data obtained from models was checked. The

    data obtained from the 5-D model was then compared to original site data which yielded the

    impact of BIM on a certain facility.

    3.12

    CONCLUSION

    After analyzing the project it was crystal clear impact of BIM in managing the project and then

    the conclusions were drawn about the methods that could be deployed for having a better

    management and control over the project.

  • 8/9/2019 BIM- Pakistan case study

    46/76

    33

    3.13 PREPARING REPORT AND PRESENTAION

    The final phase of the project included:

    3.13.1 5D Model Submission

    5D Model of the building was submitted in form of softcopy.

    3.13.2 Preparation of Presentation

    Presentation for the final defense was prepared and the project was presented and demonstrated.

  • 8/9/2019 BIM- Pakistan case study

    47/76

    34

    CASE STUDY

    4.1

    PROJECT INTRODUCTION

    All phases of BIM are to be implemented in the Government Project of Employees Old age

    Benefit Institution (EOBI) in G-9/4 sector, Islamabad named as Overseas Employees

    Corporation (OEC) Tower. The total

    covered area of the project is 190,000 square

    feet. The plot size of the project is 120 X

    300. Floor area ratio of the building is 1:3.

    The build floors consist of two basements,

    one ground floor and nine floors. Builders

    Associates is the firm contracted to build the

    project. This was designed by Sohail A.

    Khan Associates (SAKA). Pakistan Real

    Estate Investment & Management Company

    (PRIMACO) is a firm which represents theclient (EOBI) and handles the queries

    regarding construction. The MEP

    consultants of the projects are Fahim, Nanji

    and desouza pvt. Ltd. The project was

    started in April, 2012 and was to be

    completed by November, 2013.But due to

    some reasons the project was not completed

    at the targeted date but the latest date proposed for its completion is 20 November, 2014. The

    detail about the stakeholders can be extracted from table 4.1.

    Chapter 4

    Figure 4.1 OEC Tower South East Artistic view

  • 8/9/2019 BIM- Pakistan case study

    48/76

    35

    Stakeholder Role Information

    EOBI Client www.eobi.gov.pk

    PRIMACO Construction Manager www.primaco.com

    SAKA Consultant saka.net.pk

    Builders Associates Contractor www.buildersltd.com

    Fahim, Nanji & desouza Pvt.

    Ltd.MEP consultant www.fnd.com.pk

    Table 4.1 Project stakeholders

    The site can be seen from the following figure 4.2 and figure 4.3.

    Figure 4.2 OEC Tower North West view

  • 8/9/2019 BIM- Pakistan case study

    49/76

    36

    Figure 4.3 OEC Tower under construction

    4.2

    SPECIAL FEATURES OF OEC TOWERA few distinct and sustainable features of the building which make it different from other

    building are:

    Vertical Plantations

    Solar Panels at the roof

    Rain water storage and harvesting

    Re-use of building waste water for external irrigation

    Drip irrigation Impulse Ventilation system for car park area

    Smoke management system

    Water based Fire Suppression system including fire sprinkler system

    Dedicated fire water storage to provide 60 minutes of fire suppression capability

    Supervision and Monitoring of fire suppression system at fire alarm panel

    Waste Management system

    Emergency exit tunnel Storm water drainage system for roof and plot.

  • 8/9/2019 BIM- Pakistan case study

    50/76

    37

    4.3 AREA OF OEC TOWER

    Initially at the time of tender, in June 2011, the project was supposed to be a 10+3 story building.

    Consisting of 10 floors of office building and below it had to be 3 basements for parking

    facilities etc. at that time the total covered area was estimated to be 220,000 sft. But due to lack

    of funds, the scope of project was changed and a basement was removed from the scope of

    project leaving behind 190,000 sft covered area divided upon a 10+2 story building.

    Areas of the floor can be seen from table 4.2.

    AREAS OF OEC TOWER

    AREA DESCRIPTION DIMENSIONS (Ft) APPROX. AREA

    TOTAL PLOT AREA 120X300 36,000 sft

    BUILT UP AREA-

    (Covered area of building & lawns etc)200,000 sft

    COVERED AREA-

    (Building area)190,000 sft

    Table 4.2 Areas of OEC Tower

    4.4 3-D MODEL

    Project yielded a 3-D Model of a Building facility. Using conventional methods, architects are

    only able to draw a Two-Dimensional Model of the facility whether by Manual Drafting or by

    using AutoCAD. The end product i.e. the integrated 3D model of the building was of the exact

    same dimensions and features. Autodesk Revit was used for this task. Models from different

    disciplines were integrated to develop an integrated 3-D model. The integrated model was used

    for material takeoff which was used in estimating costs. The clashes between different models

    were also detected. So the integrated 3-D model was essential for other features of BIM. The

    integrated 3-D model consisted of following models:

    4.4.1 Architectural Model

    During the project the architectural model was developed initially. In the process of developing

    of architectural model different components of the building were involved including walls,

  • 8/9/2019 BIM- Pakistan case study

    51/76

    38

    floors, stairs, roof, elevators, openings, doors, columns and curtain wall etc. The 3-D views, plan

    views, section views, the elevations and legends of the architecture model can be seen in

    appendix-2, the components involved in the model are as follows:

    4.4.1.1Grids

    First of all the grids were drawn in order to provide reference to other building components. The

    vertical grids were given the notation in the form of numbers whereas the horizontal grids were

    given the notation in the form of alphabets. The same grid was used for other building models.

    4.4.1.2Levels

    The levels were drawn in the model after the drafting of grids. Levels depict the elevations of

    different building floors. Every level was given a specific elevation as provided in the buildingdrawings. The levels were handful