bid set drawing submission enterprise hall roof

167
DGS-30-248 (Rev. 04/15) GEORGE MASON UNIVERSITY FAIRFAX, VIRGINIA BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF REPLACEMENT Fairfax, VA PROJECT CODE NO: 247-A9247-015 DATE: February 19, 2021 MTFA Architecture, PLLC 3200 Lee Highway Arlington, VA 22207

Upload: others

Post on 19-Jan-2022

5 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

DGS-30-248

(Rev. 04/15)

GEORGE MASON UNIVERSITY FAIRFAX, VIRGINIA

BID SET DRAWING SUBMISSION

ENTERPRISE HALL ROOF REPLACEMENT

Fairfax, VA

PROJECT CODE NO: 247-A9247-015

DATE: February 19, 2021

MTFA Architecture, PLLC

3200 Lee Highway

Arlington, VA 22207

Page 2: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

DGS-30-248

(Rev. 04/15)

GEORGE MASON UNIVERSITY FAIRFAX, VIRGINIA

BID SET DRAWING SUBMISISON

ENTERPRISE HALL ROOF REPLACEMENT

Fairfax, VA

PROJECT CODE NO: 247-A9247-015

DATE: February 19, 2021

MTFA Architecture, PLLC

3200 Lee Highway

Arlington, VA 22207

Page 3: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

SEALS PAGE

Enterprise Hall Roof Replacement

George Mason University, Fairfax VA

PC: 247-A9247-015

ARCHITECT OF RECORD

MTFA Architecture, PLLC 3200 Lee Highway Arlington, VA 22207

________________________________________ February 19, 2021

Dale M. Leidich, RA, AIA

Principal

Page 4: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

BID SET DRAWING SUBMISSION

Enterprise Hall Roof Replacement

George Mason University, Fairfax VA

PC: 247-A9247-015

DRAWING INDEX

GENERAL

CS101 – COVER SHEET

WATERPROOFING

A101 – ROOF PLAN AND DETAILS

A501 – ROOF DETAILS

A502 – ROOF DETAILS

A503 – ROOF DETAILS

Page 5: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

BID SET DRAWING SUBMISSION Enterprise Hall Roof Replacement George Mason University, Fairfax VA

PC: 247-A9247-015

TABLE OF CONTENTS GENERAL

Cover Seals Page Drawing Index

BIDDING INFORMATION DGS FORM HECO FORM

Invitation for Bids N/A N/A Instructions to Bidders N/A HECP-7A-EB Bid Form N/A N/A Standard Performance Bond N/A HECO-10 Standard Labor & Material Payment Bond N/A HECO-10/1 Standard Bid Bond N/A HECO-10.2

GENERAL CONDITIONS & FORMS - the following forms are not included in the Project Manual, but are available from https://facilities.gmu.edu/resources/heco-dgs-forms/

General Conditions of the Construction Contract DGS-30-054

Contract Between Owner & Contractor HECO-9

Workers Compensation Insurance Certificate HECO-9a

General Contractor Estimate for Change Order HECO-GC-1

Subcontractor Estimate for Change Order HECO-SC-1

Sub-Subcontractor for Estimate for Change Order HECO-SS-1

Schedule of Values and Certificate for Payment HECO-12

Affidavit of Payment and Claims HECO-13

Certificate of Completion by AE HECO-13.1

Certificate of Substantial Completion by AE HECO-13.1a

Final Report of Structural & Special Inspections HECO-13.1b

Certificate of Substantial Completion by Inspector HECO-13.1c

Certificate of Completion by Contractor HECO-13.2

Certificate of Partial or Substantial Completion by Contractor HECO-13.2a

Checklist for Beneficial Occupancy HECO-13.3b

Project Completion Report HECO-14

Submittal Register Form DGS-30-364

Page 6: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

SPECIFICATIONS

DIVISION 01 - GENERAL REQUIREMENTS

010000

Special Conditions

011000 Summary 013100 Project Management and Coordination 013200 Construction Progress Documentation 013300 Submittal Procedures 014000 Quality Requirements 014000 References 014250 Testing and Inspection Services 015000 Temporary Facilities 016000 Product Requirements 017310 Cutting and Patching 017700 Closeout Procedures 017823 Operation and Maintenance Data 017839 Project Record Documents 017900 Demonstrations and Training

DIVISION 02 – EXISTING CONDITIONS

024119 Selective Demolition

DIVISION 03 - CONCRETE

Not Used

DIVISION 04 – MASONRY

042000 Unit Masonry DIVISION 05 - METALS

055213 Pipe Tube Railings

DIVISION 06 – WOOD, PLASTICS AND COMPOSITES

061000 Rough Carpentry

Page 7: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

DIVISION 07 - THERMAL AND MOISTURE PROTECTION

070150 Preparation for Roof Replacement 075113 Built-up Asphalt Roofing 076200 Sheet Metal Flashing and Trim 078100 Applied Fireproofing 079200 Joint Sealants

DIVISION 08 - OPENINGS

Not Used

DIVISION 09 - FINISHES

099100 Painting

DIVISION 10 - SPECIALTIES

Not Used

DIVISION 11 - EQUIPMENT

Not Used

DIVISION 21 – FIRE SUPPRESSION

Not Used DIVISION 22 - PLUMBING

Not Used

DIVISION 23 – HEATING VENTILATING AND AIR CONDITIONING

Not Used

DIVISION 26 - ELECTRICAL

Not Used

DIVISION 27 – COMMUNICATIONS

Not Used

Page 8: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

DIVISION 28 – ELECTRONIC SAFETY AND SECURITY

Not Used

DIVISION 31 – EARTHWORK

Not Used

DIVISION 32 – EXTERIOR IMPROVEMENTS

Not Used

DIVISION 33 - UTILITIES

Not Used

Page 9: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Invitation for Bids (Rev. 06/17) Page 1 of 3

NOTICE OF INVITATION FOR BIDS (IFB) Sealed bids are invited for the Enterprise Hall Roof Replacement project on George Mason’s Fairfax, Virginia Campus’ Project Code: 247-A9247-015. The project is generally described as the roof replacement at Enterprise Hall and includes, but may not be limited to, demolition of the existing built-up roof systems, masonry veneer and parapet repairs, limited sealant removal and replacement, and a new horizontal life-safety system. In accordance with Executive Order No. 51 dated 23 March 2020, Bids shall be submitted electronically through Mason’s Construction Management Software Program, e-Builder using the Bidding Portal. This link provides guidelines - https://gmufacilities.freshdesk.com/support/solutions/articles/33000234600-e-builder-bidding-portal-information Due to the COVID-19, Mason is requiring all who wish to perform a site visit to follow the COVID-19 guidelines outlined by Mason’s Safe Return to Campus - https://www2.gmu.edu/Safe-Return-Campus, the CDC and the Commonwealth of Virginia. BIDDERS ARE REQUIRED to notify Mason, by email, if you plan on performing a site visit. Bid Officer, Michele Kelly, [email protected] or Mason’s Project Manager, Christy Hogan at [email protected] In accordance with Executive Order No. 51 dated 23 March 2020, Bids will be received electronically through Mason’s Construction Management Software Program, e-Builder using the Bidding Portal. The deadline for submitting bids is 2:00 P.M. sharp, as determined by the Bid Officer, on Tuesday, 15 June 2021. Procedures for submitting a bid, claiming an error, withdrawal of bids and other pertinent information are contained in the Instructions to Bidders, which is part of the Invitation for Bids. Withdrawal due to error in bid shall be permitted in accord with Section 9 of the Instructions to Bidders and § 2.2-4330, Code of Virginia. The Owner reserves the right to reject any or all bids. The bids will be opened and read aloud utilizing Mason’s Microsoft Teams Meeting Software beginning at 2:00 P.M., on Wednesday, 16 June 2021 and all bidders who wish to attend the Virtual Bid Opening are required to notify the Bid Officer, Michele Kelly by 5:00pm on Tuesday, 15 June 2021 at [email protected] Project Bonding Requirement HECO-10 – Standard Performance Bond X Required Not Required HECO-10.1 – Standard Labor & Material Payment Bond X Required Not Required HECO-10.2 – Standard Bid Bond X Required Not Required eVA Vendor Registration: The bidder or offeror shall be a registered vendor in eVA. Registration requirements can be found on the eVA Website - https://eva.virginia.gov/register-now.html An Optional On-Site Pre-Bid Meeting will be held on Tuesday, 25 May 2021 at 10:00am at Mason’s Facilities Administration Building in Conference Room 102. All Bidders who wish to attend this Optional On-Site Pre-Bid Meeting ARE REQUIRED to following guidelines outlined in Attachments D & E. All bidders are also required to notify the Bid Officer if you plan to attend the meeting by email at [email protected] by Monday, 24 May 2021. For Location refer to Attachment F - Fairfax Campus Map_Directions_Parking. Bidders Questions MUST BE SUBMITTED through e-Builder on or before Wednesday, 02 June 2021 with responses issued by Addendum.

Page 10: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Invitation for Bids (Rev. 06/17) Page 2 of 3

The contract shall be awarded on a lump sum basis as follows: The Total Base Bid Amount including any properly submitted and received bid modifications plus such successive Additive Bid Items as the Owner in its discretion decides to award in the manner set forth in Paragraph 12 of the Instructions to Bidders (HECO-7A-EB). ‘Notice of Award’ or ‘Notice of Intent to Award’ will be posted on eVA, Virginia. Department of General Services’ central electronic procurement website, at https://eva.virginia.gov Contractor registration is required in accordance with Section 54.1-1103 of the Code of Virginia. See the Invitation for Bids for additional qualification requirements. It is the policy of George Mason University to contribute to the establishment, preservation, and strengthening of small, women and minority owned businesses (SWaM), as certified by the Commonwealth of Virginia’s Department of Small Business and Supplier Diversity (SBSD), and to encourage their participation in Mason’s procurement activities. To this end, Mason has established an overall SWaM participation goal of 50% for fiscal Year 2021 and encourages Contractors to provide for the participation of SWaM businesses through partnerships, joint ventures, subcontracts, or other contractual opportunities. Refer to Attachment H - dgs-30-361_04-15_small- business-report-format-pilot. Attachment H must be submitted with the bid submission. The Invitation for Bid for the above project, including the drawings and the specifications containing the information necessary for bidding, may be obtained from the Virginia Department of General Services’ central electronic procurement website, at https://eva.virginia.gov or can also be found on Mason’s e-Builder site at the link provided below: https://bidders.e-builder.net/landing?bidpackageid=f83c78ea-1aa0-47eb-a291-04812c5495ad NOTE: Once the contractor has registered / created an account in e-Builder, the above public link will need to be utilized to reach the bid package. Mason utilizes the e-Builder Construction Management Software Program to manage construction projects. Information, steps and guidelines regarding General Contractor processes can be found by following the link provided - https://gmufacilities.freshdesk.com/support/solutions/folders/33000208553 The awarded contractor will be responsible for contacting Mason’s e-Builder Team for all appropriate and necessary training required to utilize our system properly during the construction phase of this project. Mason e-Builder Team Email - [email protected] Electronic Access Cards Contractors are responsible for electronic access cards that are issued by Mason for awarded contracts on our campuses. It's the responsibility of the contractor to return the access card(s) issued upon final completion of the project. If a card(s) are lost, stolen, misplaced or not return upon final completion, the contractor will be responsible for the cost incurred, which is $100.00 per card issued. Bid Submission Document Requirements

1. Bid Form must be completed and signed by contractor with bid submission 2. Any addendums issued during the bidding period must be executed and submitted with bid

submission. 3. Contractor is required to submit a schedule of values, utilizing Attachment G (HECO-12 Form) with

bid submission. Submission of SOV is not approval. 4. Contractor is required to submit a project schedule utilizing the project dates stated within this

Invitation for Bid with bid submission. Submission of project schedule is not approval. 5. Attachment H - DGS-30-361_04-15_small-business-report-format-pilot

Page 11: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Invitation for Bids (Rev. 06/17) Page 3 of 3

PROJECT DATES Solicitation Date: 14 May 2021 Optional On-Site Pre-Bid Meeting: 25 May 2021 @ 10:00am Bidders Questions Due: 02 June 2021 Bidders Questions w/Responses Due: 04 June 2021 Bid Submission Due: 15 June 2021 @ 2:00pm Bid Opening: 16 June 2021 @ 2:00pm Project Award: 28 June 2021 Substantial Completion: 31 December 2021 Final Completion will be thirty (30) calendar days from date of Substantial Completion.

Page 12: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 1 of 11

INSTRUCTIONS TO BIDDERS

The Invitation For Bids (IFB) consists of the Notice, this Instructions To Bidders, Invitation for Bid Form, the Bidders Question Form, the General Conditions of the Construction Contract, the Supplemental General Conditions (if any), the Special Conditions (if any), the Forms to be used, and the Scope of Work

as described by the Plans and Specifications, other documents listed in the Specifications, and any addenda which may be issued, all of which request qualified bidders to submit competitive prices or bids

for providing the described work on the project.

eVA Vendor Registration: The bidder or offeror shall be a registered vendor in eVA. For

registration requirements follow this link – https://eva.virginia.gov/register-now.html

1. CONDITIONS AT SITE OR STRUCTURE: Bidders shall visit the site and shall be responsible forascertaining pertinent local conditions such as location, accessibility, general character of the siteor building, and the character and extent of existing conditions, improvements or work within oradjacent to the site. Claims, as a result of failure to have done so, will not be considered by theOwner. See Section 7 of the General Conditions entitled "Conditions at Site."

2. EXPLANATIONS TO BIDDERS: No oral explanation in regard to the meaning of drawings and

specifications will be made and no oral instructions will be given before the award of the contract.

The Owner shall not be responsible for any conclusions, assumptions or interpretations made by

bidders during the preparation of bids that are contrary to the drawings and specifications and their

clear intent. Discrepancies, conflicts, errors, omissions or doubts as to the meaning of drawings

and specifications shall be communicated in writing to the Architect / Engineer for interpretation.

Bidders must so act to assure that questions reach Mason by the date shown on Invitation for Bid toallow a sufficient time for an addendum to reach all bidders before the submission of their bids. If,

however, there are two (2) weeks or less between the first bid advertisement and the time set for

receipt of bids, then bidders must submit questions so that they reach Mason by the date

shown in the Invitation for Bid. Any interpretation made will be in the form of an addendum

to the specifications and/or drawings, which will be forwarded to all bidders, and its receipt

shall be acknowledged by the bidder on Bid Form. If such discrepancies, conflicts, errors,

omissions or doubts are reasonably apparent or should have been reasonably apparent to the

bidder, and the bidder failed to submit questions to Mason in the time and manner required herein

and the Contract is awarded to the bidder, then any claims shall be deemed waived and the

bidder shall not be entitled to additional compensation or time, or entitled to sue the

Owner based on such discrepancies, conflicts, errors, omissions, or doubts.

3. TIME FOR COMPLETION:

(a) "Time for Completion" shall be designated by the Owner on the Invitation for Bid or other Pre-Biddocuments and shall mean the number of consecutive calendar days following the issuance ofthe Notice to Proceed which the Contractor has to substantially complete all Work required by

Page 13: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 2 of 11

the Contract. In some instances, the Time for Completion may be stated in the form of a Contract Completion Date based on a stipulated date of Notice to Proceed.

Unless otherwise specified, the Contractor shall achieve Final Completion within thirty (30) calendar days after the date of Substantial Completion.

(b) When the Notice to Proceed is issued, it will state a Contract Completion Date, which has beenset by the Owner based on date of the Notice to Proceed and the Time for Completion.

(c) The Contractor, in preparing and submitting their bid, is required to take into consideration normalweather conditions. Normal weather does not mean statistically average weather, but rather

means a range of weather conditions which might be anticipated, (i.e., conditions which are notextremely unusual). Normal weather conditions shall be determined from the public historical

records available, including the U.S. Department of Commerce, Local Climatological DataSheets, Oceanic and Atmospheric Administration/Environmental Data and Information Service,National Climatic Center and the National Weather Service. The data sheets to be used shall

be for the locality or localities closest to the site of the work. No additional compensation will bepaid to the Contractor because of adverse weather conditions; however, an extension of time

for abnormal weather will be considered by the Owner as indicated in the General Conditions.

(d) If the Owner designates the public historical climatological records to be used, the bidder shalluse those records in computing bids. If the Owner requests each bidder to indicate the records

used, each bidder may select the public historical climatological records upon which they will relyin computing his bid. In the latter situation, each bidder shall designate in the space provided

which of such climatological data records was used when formulating his bid. A bidder's failureto designate climatological records when submitting a bid shall not disqualify their bid, but shallconstitute a waiver of the right to claim any extension of time as the result of abnormal weather.

In either case, the bid submitted and the time of completion shall be presumed to have beenbased upon normal weather derived from the climatological records used.

4. PREPARATION AND SUBMISSION OF BIDS:

(a) In accordance with Executive Order No. 51 dated 23 March 2020, Bids shall be submitted electronically through Mason’s Construction Management Software Program, e -Builder using the Bidding Portal - utilizing this link - https://gmufacilities.freshdesk.com/support/solutions/articles/33000234600-e-builder-bidding-portal-information. A signed Bid Form shall be

uploaded with the submission to affirm the bid and any issued Addendums and bonds

required by the bid documents. Erasures or other changes in a bid must be explained or noted

over the signature of the bidder. Bids containing any conditions, omissions, unexplained

erasures, alterations or items not called for in the proposal, or irregularities of any kind,

may be rejected by the Owner as being incomplete or nonresponsive.

(b) Each bid must give the complete legal name and full business address of the bidder and be signed by the bidder, or the bidder's authorized representative, with his /her usual signature. Bids by partnerships must be signed in the partnership name by one of the general partners of the partnership or an authorized representative, followed by the designation/title of the person signing, and a list of the partners. Bids by joint ventures must be signed in the joint venture

Page 14: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 3 of 11

name by one of the joint venturers or an authorized representative of one of the joint venturers, followed by the designation/title of the person signing, and a list of the joint venturers. Bids by corporations must be signed with the legal name of the corporation followed by the name of the

state in which it is incorporated and by the signature and title of the person authorized to bind it in this matter. The name of each person signing shall be typed or printed below the signature.

A signature on a bid by a person who identifies his title as "President," "Secretary," "Agent" or other designation without disclosing the principal firm, shall be held to be the bid of the individual signing. When requested by the Owner, satisfactory evidence of the authority of the officer

signing on behalf of the corporation shall be furnished. Trade or fictitious names may be referenced by using "t/a _ _ _ ," but bids shall be in the legal name of the person or entity

submitting the bid.

(c) If a Contract is for one hundred twenty thousand dollars ($120,000) or more, or if the total value

of all construction, removal, repair or improvements undertaken by the bidder within any twelve -

month period is seven hundred fifty thousand dollars ($750,000) or more, the bidder is required under Title 54.1, Chapter 11, Section 1100, Code of Virginia, as amended, to be licensed in

Virginia as a "Class A Contractor." If a Contract is for ten thousand dollars ($10,000) or more, but less than one hundred twenty thousand dollars ($120,000), or if the total value of all construction, removal, repair or improvements undertaken by the bidder within any twelve -

month period is one hundred fifty thousand dollars ($150,000) or more, but less than seven hundred fifty thousand dollars ($750,000), the bidder is required to be licensed in Virginia as a

"Class B Contractor." The bidder shall note on the Invitation for Bid Form containing the bid whichever of the following notations is appropriate and insert his Contractor license/registration number:

Licensed Class A Virginia Contractor No. or

Licensed Class B Virginia Contractor No.

If the bidder is not properly licensed in Virginia at the time the bid is submitted, or if the bidder

fails to provide this information on the bid and fails to promptly provide said Contractor license number to the Owner in writing when requested to do so before the opening of bids, he/she shall be deemed to be in violation of Section 54.1-1115 of the Code of Virginia, as amended, and his

bid will not be considered.

(d) The Board for Contractors has interpreted its regulations to mean "a licensed Contractor can

bid on a contract which contains work outside his license classification(s) as long as he subcontracts those items for which he is not qualified to perform to licensed contractors with the

appropriate License Classification and the work of the second party is incidental to the contract." Therefore, the Owner may, as a part of determining whether the bidder is "responsible," require

the apparent low bidder to submit a listing of his subcontractors along with the license number and classification or specialty of each.

(e) The bidder must also place its Employer Identification Number (SSN or FEIN) in the space

provided on the Bid Form.

Page 15: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 4 of 11

(f) Every bidder organized as a stock or nonstock corporation, limited liability company, business trust, or limited partnership or registered as a registered limited liability partnership must be authorized to transact business in the Commonwealth as a domestic or foreign business entity

if so required by Title 13.1 or Title 50 of the Code of Virginia, as amended, or as otherwise required by law. Any bidder organized or authorized to transact business in the Commonwealth

pursuant to Title 13.1 or Title 50 must include in its bid the identification number issued to it by the State Corporation Commission. Any bidder that is not required to be authorized to transact business in the Commonwealth as a foreign business entity under Title 13.1 or Title 50 or as

otherwise required by law shall include in its bid or proposal a statement describing why the bidder or offeror is not required to be so authorized. A bidder required to be authorized to

transact business in Virginia that fails to provide the required information shall not receive an award unless a waiver of this requirement and of any administrative policies and procedures established to implement Section 2.2-4311.2 of the Code of Virginia, as amended, is granted

by the chief executive of the Owner.

If awarded a Contract, the bidder shall not allow its existence to lapse or its certificate of authority

or registration to transact business in the Commonwealth, if so required under Title 13.1 or Title 50, to be revoked or cancelled at any time during the term of the Contract. Doing so shall be deemed to be a violation of Section 2.2-4311.2 and the bidder understands and agrees that

the Owner may void the Contract if the bidder fails to comply with this provision.

5. BID GUARANTEE:

(a) Any bid (including the Total Base Bid plus all Additive Bid Items) which exceeds five hundred thousand dollars ($500,000) unless waived in the bid documents shall be accompanied by a

George Mason University Standard Bid Bond, Form HECO-10.2, payable to the Owner as obligee in an amount equal to five percent (5%) of the amount of the bid. A Bid Bond may be required for projects having bids of less than five hundred thousand dollars ($500,000) if such

requirement is stated in the Notice of Invitation for Bids. The Bid Bond must be issued by a surety company which is legally authorized by the Virginia State Corporation Commission to do

surety business in the Commonwealth of Virginia. Such Bid Bond shall guarantee that the bidder will not withdraw his bid during the period of thirty (30) calendar days following the opening of bids; that if his/her bid is accepted, he/she will enter into a formal Contract with the Owner in

accordance with the Contract Between Owner and Contractor, Form HECO-9, included as a part of the Bidding Documents; that he/she will submit a properly executed and authorized Standard

Performance Bond and Standard Labor and Material Payment Bond on the forms included in the bidding documents; and that in the event of the withdrawal of said bid within said period, or

failure to enter into said Contract and give said bonds within ten (10) calendar days after he/she has received notice of acceptance of his/her bid, the bidder shall be liable to the Owner for the difference between the amount specified in said bid and such larger amount for which the Owner

may contract with another party to perform the work covered by said bid, up to the amount of the bid guarantee. This amount represents the damage to the Owner on account of the default of

the bidder in any particular hereof. See §2.24336 of the Code of Virginia as amended.

Page 16: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 5 of 11

(b) See §2.2-4338 of the Code of Virginia for provisions allowing alternative forms of bid security inlieu of a Bid Bond. Forms of Security listed in §2.2-4338.B must be approved prior to submission

of a Bid on the Bid Receipt date and time to be acceptable as Bid Security.

(c) The Bid Bonds or other bid security will be returned to all except the three (3) lowest bidders

after the formal opening of bids. The remaining Bid Bonds or bid security will be returned to thebidders after the Owner and the accepted bidder have executed the Contract and the

Performance Bond and the Payment Bond have been approved by the Owner.

(d) If the required Contract and bonds have not been executed within thirty (30) calendar days after

the date of the opening of the bids, then the bond or other bid security of any bidder will bereturned upon his request, provided he/she has not been notified of the acceptance of his/her

bid prior to the date of such request.

6. WITHDRAWAL OR MODIFICATION OF BIDS: Bids may be withdrawn or modified prior to the deadline stated within the Invitation for Bid. E-mail modifications are not acceptable. The withdrawal or modification may be made by the person signing the bid or by an individual(s) who is authorized by him/her on the face of the bid. Written modifications, whether the original is delivered or electronically submitted in e-Builder, must be signed by the person making the modification or withdrawal. The modification must state specifically what is to be modified and by what amount or it must state the item to be modified and what the corrected amount should be. (e.g. “Deduct$25,000 from Part A and from the Total Base Bid Amount”; or “Add $23,456 to the Total Base Bid Amount”; or “Deduct $15,650 from the Additive # 2 amount”. A modification to “Deduct $25,000 from Part A” will only be applied to Part A and not to the Total Base Bid Amount) Unless otherwise specified by the Bidder in the modification, the modification will be applied to the TOTAL BASE BID AMOUNT shown on the Bid Form. (e.g. a modification stating only “Deduct $25,000” which is properly signed will be deducted from the Total Base Bid Amount shown on the Bid Form)

7. RECEIPT OF BIDS:

(a) In accordance with Executive Order No. 51 dated 23 March 2020, Bids will be received electronically through Mason’s Construction Management Software Program, e -Builder using the Bidding Portal utilizing this link - https://gmufacilities.freshdesk.com/support/solutions/articles/33000234600 on or before the date and the hour as stipulated in the Invitation for Bid

and may be modified by subsequent Addenda.

(b) It is the responsibility of the bidder to assure that his/her bid and any bid modifications are submitted through Mason’s Construction Management Software, e-Builder, for receipt of bids by the date and hour (deadline) set forth in receipt of bids. Therefore, it is the bidder’s responsibility to take into account all factors which may impact bid submission and to implement whatever actions are necessary to have the bid submitted prior to the bid receipt deadline. No bids or bod modifications submitted or offered after the date and hour designated for receipt of bids will be accepted or considered.

Page 17: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 6 of 11

(c) The Bid Officer is the Owner's representative designated to receive bids at the time and placenoted in the Invitation for Bid and to open the bids received at the appointed time.

(d) The official time used for the receipt of responses is determined by Mason’sConstruction Management Software, e -Builder. The software will not allow for bids to besubmitted after the time stated and that no further bids or bid modifications will be accepted. All

bids and bid modifications in the possession of the Bid Officer and his or her assistants at thetime the announcement is completed are deemed to be timely.

(e) In the event the bid receipt occurs during a period of suspended state business operations, thereceipt and opening will be delayed one (1) business day.

8. OPENING OF BIDS:

(a) Bids will be opened at the time and place stated in the Invitation for Bids or as modified bysubsequent Addenda, and their contents. The Bid Officer shall decide when the specified time

for bid opening has arrived. No responsibility will be attached to any officer or agent for thepremature opening of a bid not properly addressed and identified.

(b) The provisions of §2.2-4342 of the Code of Virginia as amended, shall be applicable to the

inspections of bids received.

(c) In the event the bid opening occurs during a period of suspended state business operations,the opening will be delayed until the next business day.

9. ERRORS IN BIDS: A bidder may withdraw his/her bid from consideration if the price bid was

substantially lower than the other bids due solely to a mistake therein, provided the bid wassubmitted in good faith, and the mistake was a clerical mistake as opposed to a judgment mistake,and was actually due to an unintentional arithmetic error or an unintentional omission of a quantity

of work, labor or material made directly in the compilation of a bid, which unintentional arithmeticerror or unintentional omission can be clearly shown by objective evidence drawn from inspection

of original work papers, documents and materials used in the preparation of the bid sought to bewithdrawn.

If a bid contains both clerical and judgment mistakes, a bidder may withdraw his/her bid from

consideration if the price bid would have been substantially lower than the other bids due solely tothe clerical mistake, that was an unintentional arithmetic error or an unintentional omissio n of a

quantity of work, labor or material made directly in the compilation of a bid that shall be clearlyshown by objective evidence drawn from inspection of original work papers, documents andmaterials used in the preparation of the bid sought to be withdrawn.

In accordance with §2.2-4330.B(ii) of the Code of Virginia, the bidder must submit to the Ownerhis/her original work papers, documents and materials used in the preparation of the bid. The bidder

shall give notice in writing of his claim of right to withdraw his bid within two (2) calendar days after

the conclusion of the bid opening procedure and shall submit original work papers with such notice.The bids shall be opened at the time designated in the Invitation for Bid, as amended by addendum.

This procedure shall not apply to when the entire bid is required to be submitted on a unit pricebasis.

Page 18: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 7 of 11

Failure of a bidder to submit his/her original work papers, documents and materials used in the preparation of his/her bid on or before the time and date when bid submissions are due as stated

within the Invitation for Bid shall constitute a waiver by that bidder of his/her right to withdraw his/her bid due to a mistake.

No bid may be withdrawn under this section when the result would be the awarding of the Contract on another bid of the same bidder or of another bidder in which the ownership of the withdrawing bidder is more than five (5%) percent.

No bidder who is permitted to withdraw a bid shall, for compensation, supply any material or labor

to or perform any subcontract or other work agreement for the person or firm to whom the Contract is awarded or otherwise benefit, directly or indirectly, from the performance of the project for which the withdrawn bid was submitted. The person or firm to whom the Contract was awarded and the

withdrawing bidder are jointly liable to the Owner in an amount equal to any compensation paid to or for the benefit of the withdrawing bidder without such approval.

If a bid is withdrawn under authority of this section, the lowest remaining bid shall be deemed to be the low bidder on the project.

If the Institution denies the withdrawal of a bid under the provisions of this section, it shall notify the bidder in writing stating the reasons for its decision and award the contract to such bidder at the bid price, provided such bidder is a responsible and responsive bidder.

10. REJECTION OF BIDS: The Owner reserves the right to cancel the Invitation for Bid, to reject anyand all bids at its sole discretion when such rejection is in the interest of the Owner, or to reject thebid of any bidder who is determined to be not responsive or not responsible. See §2.2-4319 Code

of Virginia, as amended.

11. DETERMINATION OF RESPONSIBILITY: Each bidder shall be prepared, if so requested by theOwner, to present evidence of his/her experience, qualifications and financial ability to carry out the

terms of the Contract.

Prior to award of the Contract, an evaluation will be made to determine if the low bidder has the capability, in all respects, to perform fully the Contract requirements and the moral and business

integrity and reliability which will assure good faith performance, and who has been prequalified, if required. Factors to be evaluated include, but are not limited to:

(a) sufficient financial ability to perform the Contract as evidenced by the bidder's ability to obtainpayment and performance bonds from an acceptable surety;

(b) appropriate experience to perform the Work described in the bid documents;

(c) any judgments entered against the bidder, or any officers, directors, partne rs or owners for

breach of a contract for construction;(d) any substantial noncompliance with the terms and conditions of prior construction contracts or

project orders with a public body without good cause where the substantial noncompliance isdocumented; or

(e) a conviction of the bidder or any officer, director, partner, project manager, procurementmanager, chief financial officer, or owner in the last five (5) years of a crime relating to

governmental or nongovernmental construction or contracting;

Page 19: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 8 of 11

(f) any current debarment of the contractor, any officer, director or owner, from bidding orcontracting by any public body of any state, any state agency, or any agency of the federalgovernment.

The Owner reserves the right to disqualify or refuse to accept the bid of any bidder who has been

convicted, or entered a plea of guilty or nolo contendere, in any federal or state court to any charge involving any unlawful, corrupt or collusive practice involving a public contract whether federal, state, or local, or who has been determined in any judicial proceeding to have violated any antitrust,

bid-rigging or collusive practice statute in connection with any public contract, or against whom such formal criminal prosecution or other judicial proceeding has been initiated.

A bidder who, despite being the apparent low bidder, is determined not to be a responsible bidder shall be notified in writing in conformance with the procedures in §2.2-4359 Code of Virginia, as

amended.

12. AWARD OF CONTRACT:

(a) Basis for Contract Award: The Contract, if awarded, will be awarded to the lowest responsiveand responsible bidder, if any, provided his/her bid is reasonable and it is in the best interest ofthe Owner to accept it and subject to the Owner's right to reject any and all bids and to waiveinformality in the bids and in the bidding. The Bid Form contains a multi-part Base Bid and may

contain Additive Bid Items. Determination of the lowest responsible bidder, if any, will be basedon the Total Base Bid Amount entered in the e-Builder system including any properlysubmitted bid modifications plus as many Additive Bid Items taken in sequence as the Ownerin its discretion chooses to Award. Where the sum of the values entered in the multiple parts do

not agree with the Total Base Bid amount, the Total Base Bid amount entered in the e-Buildersystem, including any properly submitted bid modifications, shall take precedence.

In the event that the Total Base Bid from the lowest responsible bidder exceeds available funds, the Owner may negotiate the Total Base Bid amount with the apparent low bidder to obtain a Contract price within available funds, pursuant to §2.2-4318 Code of Virginia, as amended, and

Section 12(c) herein.

(a) Informalities: The Owner reserves the right to waive any informality in the bids when such waiveris in the interest of the Owner.

(b) Negotiation With Lowest Responsible Bidder: If award of a Contract to the lowest responsiveand responsible bidder is precluded because of limitations on available funds, under the

provisions of §2.2-4318 Code of Virginia, the Owner reserves the right to negotiate the TotalBase Bid amount with the lowest responsive, responsible bidder to obtain a Contract price withinthe available funds. This may involve changes in either the features or scope of the work include

in the Base Bid. Such negotiations with the apparent low bidder may include reducing thequantity, quality, or other cost saving mechanisms involving items in the Total Base Bid.

Negotiations for Additive Bid Items are excluded. The Owner shall notify the lowest responsiveand responsible bidder that such a situation exists and the Owner and bidder shall then conducttheir negotiations in person, by mail, by telephone or by any means they find convenient. If an

acceptable Contract can be negotiated, the changes to the Invitation for Bid documents agreed

Page 20: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20) Page 9 of 11

upon in the negotiations shall be summarized in a "Post Bid Modification" and included in the Contract. If an acceptable Contract cannot be negotiated, the Owner shall terminate

negotiations and reject all bids.

(c) Notice of Intent to Award or Notice of Award: The Notice of Award or the Notice of Intent toAward will be posted at the Agency’s standard location for posting notices as shown on the“Notice of Invitation to Bid”. In addition the Agency may also post such notice on the Agency’s

Website and/or the DEB central electronic procurement Website. Any bidder or offeror whodesires to protest the award or decision to award a Contract shall submit the protest in writing

to the public body no later than ten (10) calendar days after the posting of the Notice of Awardor Notice of Intent to Award, whichever comes first (§2.2-4360 of the Code of Virginia).

13. CONTRACT SECURITY: For Contracts which exceed one hundred thousand dollars

($100,000.00), the Standard Performance Bond (Form HECO-10) and the Standard Labor andMaterial Payment Bond (Form HECO-10.1) shall be required, as specified in the Invitation for Biddocuments. See the General Conditions and §2.2-4437 and §2.2-4338 of the Code of Virginia, as

amended.

14. CERTIFICATION: The bidder, by his/her signature on the Bid Form, certifies that neither his/herorganization nor any of its officers, directors, partners or owners is currently barred from bidding on

contracts by any Agency of the Commonwealth of Virginia, or any public body or agency of anotherstate, or any agency of the federal government. See the statement "Disqualification of Contractors"in the Bid Form.

15. ETHICS IN PUBLIC CONTRACTING: The provisions, requirements and prohibitions as contained

in §2.2-4367 of the Code of Virginia, as amended, pertaining to bidders, offerers, contractors, andsubcontractors are applicable to this project.

16. BUILDING PERMITS: Because this is a Project of the Commonwealth of Virginia, codes or zoningordinances of local political subdivisions do not apply. However, the Virginia Uniform StatewideBuilding Code shall apply to the Work and shall be administered by the Building Official for State-

owned Buildings. The Building Permit will be obtained and paid for by the Owner. All other permits,local license fees, business fees, taxes, or similar assessments imposed by the appropriate political

subdivision shall be obtained and paid for by the Contractor. See Section 25 of the GeneralConditions for utility connection fees and services.

17. UTILIZATION OF SMALL BUSINESSES: It is the policy of George Mason University to maximizethe participation of small, women, and minority owned businesses (SWaM), as certified by the

Commonwealth of Virginia’s Department of Small Business and Supplier Diversity (SBSD). Theparticipation of these businesses directly and through partnerships, joint ventures, subcontracts

and other contractual opportunities may be encouraged by stating the requirements (if applicable)on the Invitation for Bids. The Invitation for Bid will state whether or not the contractor will be requiredto submit the dgs-30-361_04-15_small-business-report-format-pilot. The small business

procurement plan is the bidder’s proposed percentage of participation by small businesses in theoverall total base bid amount. If the bidder is a SBSD certified small business, the pr oposed

percentage of small business participation shall be entered as 100%. A bidder may enter aproposed percentage of small business participation of 0% and be considered responsive unless

Page 21: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

HECO-7A-EB (Rev. 04/20)

Page 10 of 11

the Bid Form states the Owner’s required percentage of small business participation, in which case the bidder shall enter a percentage equal to or greater than the Owner’s required small business

participation percentage in order to be considered responsive.

18. BID DOCUMENTS: Bid Documents are the property of the Owner and no paper sets will be madeavailable for bidders. A deposit is not required for downloading of electronic construction documents

through Mason’s Construction Management Software, e-Builder.

19. GENERAL CONDITIONS: The General Conditions of the Construction Contract, CO-7, areincorporated in the bid documents. If the General Conditions are incorporated by reference, the

bidder may obtain a copy of the current edition of the General Conditions of the ConstructionContract, CO-7 at no cost from the DGS Forms Center (https://dgs.virginia.gov/search/documents-

and-forms/?filter=DEB).

20. PREBID CONFERENCE: See the Invitation for Bid for requirements for a Pre-Bid Conference and

whether such conference is mandatory or optional.

21. INSPECTION OF BID DOCUMENTS: Copies of the Invitation for Bids documents including Plansand Specifications and the General Conditions of the Construction Contract, CO-7, current edition,will be available for download within Mason’s Construction Management Software, e -Builder.

22. DRUG-FREE WORKPLACE REQUIRED: Bidders are reminded that §2.2-4312 of the Code ofVirginia requires that the during the performance of the Project Order resulting from this solicitation,the contractor agrees to (i) provide a drug-free workplace for the contractor's employees; (ii) post

in conspicuous places, available to employees and applicants for employment, a statementnotifying employees that the unlawful manufacture, sale, distribution,

dispensation, possession, or use of a controlled substance or marijuana is prohibited in the contractor's workplace and specifying the actions that will be taken against employees for violations

of such prohibition; (iii) state in all solicitations or advertisements for employees placed by or on behalf of the contractor that the contractor maintains a drug-free workplace; and (iv) include the

provisions of the foregoing clauses in every subcontract or purchase order of over $10,000, so that the provisions will be binding upon each subcontractor or vendor.

For the purposes of this section, "drug-free workplace" means a site for the performance of work done in connection with a specific Project Order awarded to a contractor in accordance with this solicitation, the employees of whom are prohibited from engaging in the unlawful manufacture, sale,

distribution, dispensation, possession or use of any controlled substance or marijuana during the performance of the Project Order. Paragraphs which have been added or revised since prior edition

are identified with a line to the right of the paragraph.

NOTE: These HECO-7A-EB, Instructions to Bidders, have been created specifically for the use of George Mason University.

These Instructions to Bidders have significant legal implications and shall not be altered or modified. Nothing in the HECO -7A- EB, Instructions to Bidders, shall be amended or deleted or its intent changed, except by an approved and properly issued

‘Supplemental Instruction to Bidders’. George Mason University makes no representation as to their suitability for any other purpose.

Page 22: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Standard Bid Form

(Rev. 06/17) Page 1 of 3

BID FORM

Date: 14 May 2021 Project: Enterprise Hall Roof Replacement Location: Fairfax, Va Campus Project Code: 247-A9247-015

To: George Mason University Facilities Administration 4400 University Drive, MSN 1E4 Fairfax, Virginia 22030 In compliance with and subject to your Invitation for Bids and the documents therein specified, all of which are incorporated herein by reference, the undersigned bidder proposes to furnish all labor, equipment, and materials and perform all work necessary for construction of this project, in accordance with the Plans and Specifications dated 19 February 2021, and the Addenda noted below, as prepared by MTFA Architecture, PLLC at 3200 Lee Highway, Arlington, Virginia 22207 for the consideration of the following amount: BASE BID (including the following parts but excluding work in Additive Bid Items): PART A. Lump sum price for construction of the roof replacement at Enterprise Hall in accordance with the Plans and Specifications dated 19 February 2021 PART A = ________________________________________ Dollars ($ ).

TOTAL BASE BID AMOUNT (Sum of PART A) IS: _________________________________________________ DOLLARS ($ ) Contract award will be based on the TOTAL BASE BID AMOUNT as entered into Mason’s Construction Management Software Program, e-Builder (including any properly submitted bid modifications) plus as many Additive Bid Items taken in sequence as the Owner in its discretion decides to award. The bidder has relied upon the following public historical climatological records: The National Weather Service – Fairfax, Virginia. The undersigned understands that time is of the essence and agrees that the date for Substantial Completion of the entire project shall be on or before 31 December 2021 based on a Notice authorizing Work to proceed on or before 28 June 2021 , and Final Completion shall be achieved within 30 consecutive calendar days after the date of Substantial Completion as determined by the A/E.

Page 23: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Standard Bid Form (Rev. 06/17) Page 2 of 3

* * * * * * * * * * * *

Acknowledgment is made of receipt of the following Addenda:

.

If notice of acceptance of this bid is given to the undersigned within thirty (30) calendar days after the date of opening of bids, or any time thereafter before this bid is withdrawn, the undersigned will execute and deliver a contract in the prescribed form (Contract Between George Mason University and Contractor, Form HECO-9) within ten (10) calendar days after the contract has been presented to him for signature. The required payment and performance bonds, on the forms prescribed, shall be delivered to the Owner along with the signed Contract.

Immigration Reform and Control Act of 1986: The undersigned certifies that it does not and shall not during the performance of the Contract for this project violate the provisions of the Federal Immigration Reform and Control Act of 1986, which prohibits employment of illegal aliens, or knowingly employ an unauthorized alien as defined in the Federal Immigration Reform and Control Act of 1986.

DISQUALIFICATION OF CONTRACTORS: By signing this bid or proposal, the undersigned certifies that this Bidder or any officer, director, partner or owner is not currently barred from bidding on contracts by any Agency of the Commonwealth of Virginia, or any public body or agency of another state, or any agency of the federal government, nor is this Bidder a subsidiary or affiliate of any firm/corporation that is currently barred from bidding on contracts by any of the same. We have attached an explanation of any previous disbarment(s) and copies of notice(s) of reinstatement(s).

Either the undersigned or one of the following individuals, if any, is authorized to modify this bid prior to the deadline for receipt of bids by writing the modification and signing his name on the face of the bid, on the envelope in which it is enclosed, on a separate document, or on a document which is telefaxed to the Owner:

I certify that the firm name given below is the true and complete name of the bidder and that the bidder is legally qualified and licensed by the Virginia Department of Professional and Occupational Regulation, Board for Contractors, to perform all Work included in the scope of the Contract.

Virginia License No.: Bidder: (Name of Firm)

Contractor Class: By:

Page 24: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Standard Bid Form

(Rev. 06/17) Page 3 of 3

(Signature) Specialty: (Print Name) Valid until: Title:

FEIN/SSN: Business Address: Email Address: Telephone: Fax: If General Partnership (List Partners’ Name): If Corporation, affix Corporate Seal & list State of Incorporation: State: (Affix Corporate Seal Here)

Virginia State Corporation Commission ID No.: _______________________; or If Contractor is a foreign business entity not required to be authorized to transact business in the Commonwealth under Titles 13.1 or 50 of the Code of Virginia, or as otherwise required by law, please provide an explanation as to why such entity is not required to be so authorized:

Mason’s Annual SWaM Goal: 50% Contractor’s Proposed SWaM Participation: % (Required) (Contractor must insert percentage)

Page 25: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SPECIAL CONDITIONS 010000 - 1

SECTION 010000 – SPECIAL CONDITIONS

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and General Provisions of Contract, including General and SupplementaryConditions and Division 1 Specification sections, apply to the work of this section.

1.2 SPECIAL REPORTS

A. General: Except as otherwise indicated, submit special reports directly to Owner within

one day of occurrence requiring special report, with copy to Owner's Representative and

others affected by occurrence.

B. Reporting Unusual Events: When an event of unusual and significant nature occurs at

site prepare and submit a special report listing chain of events, persons participating,

response by Contractor's personnel, evaluation of results of effects, and similar pertinent

information. When such events are known or predictable in advance, advise Owner in

advance at earliest possible date.

C. Reporting Accidents: Prepare and submit special report of significant accidents, at site

and anywhere else work is in progress. Record and document data and actions; comply

with industry standards. For this purpose, a significant accident is defined to include

events sustained, or where the event posed a significant threat of loss or personal injury.

1.3 WORKING HOURS

A. Normal working hours shall be between the hours of 7:00 a.m. and 5:00 p.m., Monday

through Friday. Work outside normal working hours must be coordinated with and

authorized by the Owner.

1.4 PROJECT MEETINGS

A. The Contractor shall attend all project meetings scheduled or called for by the Owner or

the Owner's Representative. The Contractor shall be given a minimum of 48 hours

notice of such meetings and shall be prepared to discuss project schedule and cost

status. Typically project meetings will occur twice per month.

Page 26: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

010000 - 2 SPECIAL CONDITIONS

1.5 WORK SITE DAMAGES

A. Any damage to the Owner's property resulting from this work shall be repaired to Owner'ssatisfaction at the Contractor's expense.

1.6 DELIVERY AND STORAGE

A. It shall be the responsibility of the Contractor to make all arrangements for delivery,unloading, receiving and storing the materials during installation. The Owner will notassume any responsibility for receiving these shipments. Contractor shall makenecessary arrangements for equipment security and storage space during installation.

1.7 PARKING

A. Facilities for Contractor parking will be very limited and determined at the pre-

construction meeting.

B. Temporary Parking Permit(s)/Decal(s) must be purchased by the Contractor for each

Sub-Contractor or employee vehicle to be parked at the site. Vehicles without authorized

Permits/Decals will be ticketed.

C. Permit(s)/Decal(s) may be purchased from:Parking Services – Tel: 703-993-2710, web: https://transportation.gmu.edu/parking-services/George Mason University, 4400 University Drive – MSN 1G4, Fairfax, VA. 22030

1.8 STAGING AND STORAGE

A. The location of an area for staging and storage will be coordinated with the contractorafter award of the contract to allow coordination between the university and thecontractor requirements.

1.9 CONDUCT OF CHARACTER

A. No smoking shall be allowed on the property or within the project site. The Contractor’s

employees and subcontractors shall be required to conduct themselves in a professional

manner at all times on the job site. The Contractor shall be responsible for enforcing

such conduct, No profanity, lewd conduct or other unacceptable behavior deemed

offensive by the Owner’s representative shall be tolerated.

Page 27: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SPECIAL CONDITIONS 010000 - 3

1.10 LAYOUT OF WORK

A. All work under this contract shall be constructed in accordance with the dimensions

shown on the drawings and as directed by the A/E. The contractor shall be responsible

for all layout work.

B. The A/E may check all or any portion or work, and the Contractor shall afford allnecessary assistance to the A/E in carrying out such checks. Any deficiencies noticedby the A/E shall be corrected in a timely manner by the contractor. Such checking bythe A/E shall not relieve the Contractor of any responsibilities for the accuracy orcompleteness of his work.

1.11 CLEAN-UP

A. As the work progresses, the contractor shall remove from the site, all debris and surplusmaterials daily, so as to maintain the area in a neat and presentable condition. TheContractor shall restore all disturbed areas used for construction, storage of materialsand access to the job to its original condition prior to construction. All debris associatedwith the construction of this project shall become the property of the Contractor and shallbe removed from Owner’s property. The Contractor is responsible for disposing of thedebris in an appropriate and safe manner. The disposal of solid waste in open dumpsis prohibited.

1.12 PREVENTION OF NUISANCE FROM NOISE ETC.

A. The Contractor shall be responsible for curtailing noise, smoke, fumes, or any othernuisance resulting from his operations within the limitation set by law and as directed bythe Owner or A/E.

1.13 PROTECTION OF PROPERTY AND EXISTING UTILITIES AND STRUCTURE

A. Contractor shall be responsible for the preservation of property adjacent to work project

site against damage or injury as a result of his operations under this Contract. Any

damage or injury occurring on account of any act, omission or neglect on the part of the

Contractor, shall be restored in a proper and satisfactory manner or replaced by, and at

the expense of the Contractor.

B. Contractor shall comply with safety regulations as required by the law and as may be

prescribed by the local authorities having jurisdiction and shall, when so directed,

properly correct any unsafe conditions created by or unsafe practices on the part of his

employees.

C. Where existing utilities and structural elements are indicated on the drawings, it shall be

understood that all of the existing utilities and elements affecting the work may not be

shown and that the locations of those shown are approximate only. It shall be the

responsibility of the Contractor to ascertain the actual extent and exact locations of the

existing utilities.

D. The work shall be carried out in a manner to prevent disruption of existing services andto avoid damage to the existing utilities. Temporary connections shall be provided, as

Page 28: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

010000 - 4 SPECIAL CONDITIONS

required, to insure non-interruption of existing services. Any damage resulting from the work of this Contractor shall be promptly repaired by the Contractor at his own expense in a manner approved by the A/E subject to any authority having jurisdiction. The Contractor shall be responsible for the cost of their own repairs or work performance for them by others.

E. For work where existing utilities must be shut down to facilitate the work, the following procedure shall be followed:

• Contractor must provide Owner’s Inspector &/or Project Manager 48 hours notice (calendar days).

• Once notice from the contractor is received, Owner’s Inspector provides concurrent 48 hours notice (calendar days) via an outage form.

• For shutdowns that involve disabling the fire alarms or sprinklers, a fire watch in accordance with EHS guideline will be required. The guidelines of Fire Watch are provided at the following

link: https://public.huddle.com/b/KndMpB/index.html It is the contractor's responsibility to familiarize themselves with the expectations of the guidelines.

• During the Fire Watch, the contractor is expected to perform the watch and keep records in accordance with EHS Fire Watch guide. These records are to be

turned in to the Construction Manager/ Project Manager for incorporation in to the

file at the completion of the fire watch.

• These requirements do not alter the Hot Work permit requirements.

1.14 FIRE PROTECTION

A. Free and unobstructed access shall be maintained at all times to means of egress, fire extinguishing equipment, fire hydrants and other life safety equipment and systems.

B. If the work on the project involves hot work, a hot work permit is required. Hot work is defined as operations that include cutting, welding, thermal welding, brazing, soldering, grinding, thermal spraying, thawing pipe, installation of torch-applied roof systems or any other similar activity. The following procedure shall be followed:

• Contractor must provide Owner’s Inspector &/or Project Manager 48 hours notice (business days) prior to proposed work.

• Once notice from the contractor is received, Owner’s Inspector provides concurrent 48 hours notice (business days) via a hot work permit form.

• The guidelines of Hot Work are provided at the following

link: https://public.huddle.com/b/jYNykp/index.html It is the Contractor's responsibility to familiarize themselves with the expectations of the guidelines.

1.15 BARRICADE, WARNING SIGNS AND LIGHTS

A. Contractor shall provide, erect and maintain strong and suitable barricades, danger signs

and warning lights as may be required for the safety of all those employed in the work,

visiting the construction site, and for the general public, personnel and students.

Page 29: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SPECIAL CONDITIONS 010000 - 5

1. Comply with the requirements of chapter 33, “Safeguards during construction” ofthe Virginia Uniform Statewide Building Code (VUSBC), Latest Edition.

1.16 DRAWINGS -SPECIFICATIONS DISCREPANCIES

A. If discrepancies should occur in the Contract Documents, the Contractor shall notify theA/E. The drawings shall not be scaled for dimensions.

1.17 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions of

site beyond area in which the Work is indicated.

1. Owner Occupancy: Owner will maintain operations throughout the duration of theproject. Cooperate with Owner during construction operations to minimizeconflicts and facilitate Owner usage. Perform the Work so as not to interfere withOwner’s operations.

2. Driveways and Entrances: Keep driveways and entrances serving premises clearand available to Owner, Owner’s employees, and emergency vehicles at alltimes. Do not use these areas for parking or storage of materials.a. Schedule deliveries to minimize use of driveways and entrances.b. Schedule deliveries to minimize space and time requirements for storage of

materials and equipment on-site.

B. Use of Existing Building: Maintain existing building in a clean condition throughout

construction period. Repair damage caused by construction operations. Protect building

and its occupants during construction period.

C. Access to the site for construction vehicles and equipment shall be restricted to areas

indicated in the drawings or as approved by the Owner.

D. Delivery and storage of all materials and equipment shall be coordinated with the Ownerin order not to interfere with the normal operations of any facilities.

1.18 WORK UNDER OTHER CONTRACTS

A. Separate Contract: Owner reserves the right to award separate contract(s) for

performance of certain construction operations at Project site on substantial completion

of certain parts of the Project in accordance with Section 10 of the General Conditions

of Contract.

1.19 ASBESTOS CONTAINING MATERIALS

A. No Asbestos containing materials shall be used in the construction of this project.

General insulation and mechanical insulation suppliers shall provide written certification

that these materials do not contain asbestos.

PART 2 -PRODUCTS (Not Applicable)

Page 30: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

010000 - 6 SPECIAL CONDITIONS

PART 3 -EXECUTION

3.1 GENERAL INSTALLATION PROVISIONS

A. Pre-Installation Conferences: Well in advance of installation of every major unit of work

which requires coordination and interfacing with other work, meet at project site with

installers and representative of manufacturers and fabricators who are involved in or

affected by unit of work, and in its coordination or integration with other work which has

preceded or will follow.

B. Manufacturer's Instructions: Where installations include manufactured products, comply

with manufacturer's applicable instructions and recommendations for installation, to

extent these are more explicit or more stringent than requirements indicated in the

Contract Documents.

C. Inspect each item of materials immediately prior to installation, and reject damaged and

defective items.

D. Provide attachment and connection devices and methods for securing work properly as

it is installed; true to line and level, and within recognized industry tolerances if not

otherwise indicated. Allow for expansions and building movements. Provide uniform

joint widths in exposed work, organized for best possible visual effect. Refer

questionable visual-effect choices to Owner's Representative for final decisions.

E. Recheck measurements and dimensions of the work, as an integral step of starting each

installation.

F. Install work during conditions of temperature, humidity, exposure, forecasted weather,

and status of project completion which will ensure best possible results for each unit of

work, in coordination with entire work. Isolate each unit of work from non-compatible

work, as required to prevent deterioration.

G. Coordinate enclosure (closing-in) of work with required inspections and tests, so as tominimize necessity of uncovering work for that purpose.

3.2 PROTECTION OF WORK

A. General: During handling and installation of work at project site protect work in progress

and adjoining work on a basis of perpetual maintenance. Apply suitable protective

covering on newly installed work where reasonably required to ensure freedom from

damage or deterioration at time of substantial completion.

B. Limiting Exposures of Work: To extent possible through reasonable control andprotection methods, supervise performance of work in a manner and by means whichwill ensure that none of the work, whether completed or in progress, will be subjected toharmful, dangerous, damaging, or otherwise deleterious exposures during constructionperiod. Such exposures include (where applicable, but not by way of limitation) static

Page 31: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SPECIAL CONDITIONS 010000 - 7

loading, dynamic loading, internal pressures, external pressures, high or low temperatures, thermal shock, high or low humidity, water, ice, solvents, chemicals, light, radiation, puncture, abrasion, heavy traffic, soiling, bacteria, insect infestation, combustion, electrical current, high speed operation, improper lubrication, unusual wear, misuse, incompatible interface, destructive testing, misalignment, excessive weathering, unprotected storage, improper shipping/handling, theft and vandalism.

3.3 HOUSEKEEPING

A. Trash Disposal:

1. Keep project site free from accumulations of waste materials. Remove cartons, crates, wrappings, lunch trash and other trash daily.

2. Provide trash receptacles in convenient site locations. 3. Do not burn paper, trash or other material on site.

B. Excess Material:

1. Remove excess and temporary materials from Owner's property. 2. Keep paved public streets clean, by cleaning daily or more often if necessary of

earth and debris spillage from trucking involved in construction operations.

C. Recyclable Material:

1. The University is making an effort to “green” their campus. The contractor has the option to coordinate with the University’s recycling waste program to divert excess materials being taken offsite.

2. The contractor should verify what items currently can be accepted into the recycling dumpsters located near the maintenance storage yard. Items such as metal, white paper, mixed paper, tires, pallets, furniture etc. are examples of recyclable materials.

3.4 ENVIRONMENTAL PROTECTION

A. Noise Abatement:

1. Comply with all noise abatement ordinances. 2. Equip internal combustion engines and compressors with mufflers to reduce

noise to a minimum.

B. Pollution Control:

1. Comply with all anti-pollution ordinances. 2. Keep areas dampened to prevent dust from rising due to construction. 3. See drawings for additional requirements for erosion and sediment control. 4. Disposal of solid waste in open dumps is prohibited.

3.5 HAZARDOUS MATERIALS

A. The Contractor shall provide the Owner with a list of hazardous materials at least 48 hours before bringing the materials on site.

Page 32: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

010000 - 8 SPECIAL CONDITIONS

3.6 INTERRUPTION OF SERVICES

A. As required for construction purposes, interruption of existing services shall be scheduled for the shortest practical period of time. This applies to the relatively long outages, as well as the relatively short outages required for tie-in with or interruption of existing systems which interface with this construction. The Contractor shall be required to coordinate such outages with and obtain approval in advance from the Owner. The Contractor may be required to schedule such outages during off hours or periods of minimum use of the service, such as evenings or weekends.

3.7 SITE PROTECTION

A. Any damage to the trees and plantings near the construction site operations shall be

restored to their original condition as directed prior to final inspection.

B. Existing site improvements, trees, and plants on the site and immediately adjacent thereto or within areas Contractor is permitted to use in pursuing the work shall be adequately protected from damage during construction.

3.8 STAGING AREA

A. The Contractor shall erect and maintain necessary barricades and protective measures

to protect personnel and the public from injury due to such storage and construction

operations.

END OF SECTION

Page 33: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SUMMARY 011000-1

SECTION 011000 - SUMMARY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and SupplementaryConditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes:

1. Project information.2. Work covered by Contract Documents.3. Use of Premises4. Coordination with occupants.5. Work restrictions.6. Specification and drawing conventions.7. Fire Protection Codes

B. Related Section:

1. Division 01 Section "Temporary Facilities and Controls" for limitations andprocedures governing temporary use of Owner's facilities.

1.3 PROJECT INFORMATION

A. Project Identification: Enterprise Hall Roof Replacement, PC 247-A9247-015.

1. Project Location: George Mason University, Fairfax Campus, 4400 UniversityDrive, Fairfax, Virginia 22030

B. Owner: George Mason University, Commonwealth of Virginia

C. Architect/Engineer: MTFA Architecture, PLLC, 3200 Lee Highway, Arlington, VA 22207

1.4 WORK COVERED BY CONTRACT DOCUMENTS

A. The Work of the Project is defined by the Contract Documents and consists of thefollowing:

1. The Work includes roof replacement at Enterprise Hall and includes, but may notbe limited to, demolition of the existing built-up roof systems, masonry veneer andparapet repairs, limited sealant removal and replacement, and the installation of ahorizontal life-safety system.

Page 34: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

011000-2 SUMMARY

Type of Contract

1. Project will be constructed under a single prime contract.

1.5 USE OF PREMISES

A. Use of Site: Limit use of premises to work in areas indicated. Do not disturb portions ofsite beyond areas in which the Work is indicated.

1. Limits: confine construction operations to construction areas indicated. Coordinatewith Owner to identify acceptable site staging areas and acceptable access routes.

2. Owner Occupancy: Owner will occupy the site during entire construction period.Coordinate with Owner during construction operations to minimize conflicts andfacilitate Owner usage. Perform the Work so as not to interfere with Owner’soperations. Notify the Owner not less than 72 hours in advance of activities thatwill affect Owner's operations.

3. Driveways and Entrances: Keep driveways and entrances serving premises clearand available to Owner, Owner’s employees, and emergency vehicles at all times.Do not use these areas for parking or storage of materials.a. Schedule deliveries to minimize use of driveways and entrances.b. Schedule deliveries to minimize space and time requirements for storage of

materials and equipment on-site.

1.6 WORK RESTRICTIONS

A. On-Site Work Hours: Limit work in the existing building to normal business working hoursof 7:00 a.m. to 5:00 p.m., Monday through Friday, except as otherwise indicated.

1. Weekend Hours: Only with approval from owner.2. Early Morning Hours: Coordinate with owner for restrictions on noisy work before

normal business hours.3. Hours for Utility Shutdowns: Shall coordinate with owner, provide minimum of 72-

hour notice.4. Hours for each activity associated with excessive noise will be reviewed by the

owner and direction will be provided as to when the activity can take place.

B. Existing Utility Interruptions: Do not interrupt utilities serving facilities occupied by Owneror others unless permitted under the following conditions and then only after providingtemporary utility services according to requirements indicated:

1. Notify Construction Manager and Owner not less than 72-hour in advance ofproposed utility interruptions.

2. Do not proceed with utility interruptions without Construction Manager or Owner'swritten permission.

C. Nonsmoking Building: Smoking is not permitted within adjacent buildings or within 25feet of entrances, operable windows, or outdoor air intakes.

Page 35: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SUMMARY 011000-3

1.7 CONSTRUCTION DOCUMENTS

A. During demolition and construction comply with the following:

1. Virginia Work Area Protection Manual2. 2015 Virginia Statewide Fire Protection Code and NFPA 241 requirements for

roofing installations as well as all other applicable prevailing building codes.

1.8 SPECIFICATION AND DRAWING CONVENTIONS

A. Specification Content: The Specifications use certain conventions for the style oflanguage and the intended meaning of certain terms, words, and phrases when used inparticular situations. These conventions are as follows:

1. Imperative mood and streamlined language are generally used in theSpecifications. The words "shall," "shall be," or "shall comply with," depending onthe context, are implied where a colon (:) is used within a sentence or phrase.

2. Specification requirements are to be performed by Contractor unless specificallystated otherwise.

B. Division 01 General Requirements: Requirements of Sections in Division 01 apply to theWork of all Sections in the Specifications.

C. Drawing Coordination: Requirements for materials and products identified on theDrawings are described in detail in the Specifications. One or more of the following areused on the Drawings to identify materials and products:

1. Terminology: Materials and products are identified by the typical generic termsused in the individual Specifications Sections.

2. Abbreviations: Materials and products are identified by abbreviations scheduledon Drawings.

3. Keynoting: Materials and products are identified by reference keynotesreferencing Specification Section numbers found in this Project Manual.

1.9 MISCELLANEOUS PROVISIONS

A. Pre-installation Conferences: Conduct a pre-installation conference at Project sitebefore each construction activity that requires coordination with other construction.

1. At a minimum, hold Pre-installation conferences for the following:

Specifications Section 042000 - Unit Masonry Specifications Section 075113 - Built-up Asphalt Roofing Specifications Section 110100 - Horizontal Life Line Safety Systems

Page 36: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

011000-4 SUMMARY

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 011000

Page 37: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PROJECT MANAGEMENT AND COORDINATION 013100 - 1

SECTION 013100 - PROJECT MANAGEMENT AND COORDINATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative provisions for coordinating construction operations on Project including, but not limited to, the following: 1. Coordination 2. Administrative and supervisory personnel. 3. Project meetings. 4. Requests for Interpretation (RFIs).

B. Each contractor shall participate in coordination requirements. Certain areas of responsibility will be assigned to a specific contractor.

1.3 DEFINITIONS

A. RFI: Request from Contractor seeking interpretation or clarification of the Contract Documents.

1.4 COORDINATION

A. Coordination: Coordinate construction operations included in different Sections of the Specifications to ensure efficient and orderly installation of each part of the Work. Coordinate construction operations, included in different Sections, that depend on each other for proper installation, connection, and operation.

1.5 ADMINISTRATIVE AND SUPERVISORY PERSONNEL

A. Key Personnel: Within 15 days of starting construction operations, submit a list of Key Personnel assignments, including superintendent and other personnel in attendance at Project site. Identify individuals and their duties and responsibilities; list addresses and telephone numbers, including home, office, and cellular telephones numbers and email addresses. Provide names, addresses, and telephone numbers of individuals assigned as standbys in the absence of individuals assigned to Project.

1.6 PROJECT MEETINGS

A. General: Schedule and conduct meetings and conferences at Project site, unless otherwise indicated.

1. Attendees: Inform participants and others involved, and individuals whose presence is required, of date and time of each meeting. Notify Owner’s Representative of scheduled meeting dates and times.

Page 38: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

013100 - 2 PROJECT MANAGEMENT AND COORDINATION

2. Agenda: Prepare the meeting agenda. Distribute the agenda to all invited attendees in advance of the meeting.

3. Minutes: Record significant discussions and agreements achieved. Distribute the meeting minutes to everyone concerned.

B. Progress Meetings: Conduct progress meetings at bi-weekly intervals. Coordinate dates of meetings with preparation of payment requests.

C. Preconstruction Conference: Schedule a preconstruction conference before starting construction, at a time convenient to Owner, but no later than 15 days after execution of the Agreement. Hold the conference at Project site or another convenient location. Conduct the meeting to review responsibilities and personnel assignments. Owner will prepare agenda, conduct meeting and record minutes.

D. Pre-installation Conferences: Conduct a pre-installation conference at Project site before each construction activity that requires coordination with other construction.

1. General Contractor is responsible for recording significant conference discussions, agreements, and disagreements, including required corrective measures and actions. Distribute minutes with three days of the conference.

2. Distribute minutes of the meeting to each party present and other parties requiring information including the Owner.

3. Do not proceed with installation if the conference cannot be successfully concluded. Initiate whatever actions are necessary to resolve impediments to performance of the Work and reconvene the conference at the earliest feasible date.

4. At a minimum, hold Pre-installation conferences for the following: Specifications Section 042000 - Unit Masonry Specifications Section 075113 - Built-up Asphalt Roofing Specifications Section 110100 - Horizontal Life Line Safety Systems

1.7 REQUESTS FOR INTERPRETATION (RFIs)

A. Procedure: Immediately on discovery of the need for interpretation of the Contract Documents, and if not possible to request interpretation at Project meeting, prepare and submit an RFI in the form specified.

1. RFIs shall originate with Contractor. 2. Coordinate and submit RFIs in a prompt manner so as to avoid delays in

Contractor's work or work of subcontractors.

B. Content of the RFI: Include a detailed, legible description of item needing interpretation and the following:

1. Project name. 2. Date. 3. Name of Contractor.

Page 39: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PROJECT MANAGEMENT AND COORDINATION 013100 - 3

4. Name of Architect. 5. Project number 6. RFI number, numbered sequentially. 7. RFI subject 8. Specification Section number and title and related paragraphs, as appropriate. 9. Drawing number and detail references, as appropriate. 10. Field dimensions and conditions, as appropriate. 11. Contractor's suggested solution(s). If Contractor's solution(s) impact the

Contract Time or the Contract Sum, Contractor shall state impact in the RFI. 12. Contractor's signature. 13. Attachments: Include drawings, descriptions, measurements, photos, Product

Data, Shop Drawings, and other information necessary to fully describe items needing interpretation.

a. Supplementary drawings prepared by Contractor shall include dimensions, thicknesses, structural grid references, and details of affected materials, assemblies, and attachments.

C. RFI Log: Prepare, maintain, and submit a tabular log of RFIs organized by the RFI number. Submit log weekly.

PART 2 - PRODUCTS (Not Used)

PART 3 - EXECUTION (Not Used)

END OF SECTION 013100

Page 40: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

CONSTRUCTION PROGRESS DOCUMENTATION 013200 - 1

SECTION 013200 - CONSTRUCTION PROGRESS DOCUMENTATION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for documenting the progress of construction during performance of the Work, including the following:

1. Contractor's Construction Schedule. 2. Special reports.

PART 2 - PRODUCTS

2.1 CONTRACTOR'S CONSTRUCTION SCHEDULE, GENERAL

A. Procedures: Comply with procedures contained in AGC's "Construction Planning & Scheduling."

B. Time Frame: Extend schedule from date established for the Notice of Award to date of Substantial Completion.

1. Contract completion date shall not be changed by submission of a schedule that shows an early completion date, unless specifically authorized by Change Order.

2. Activities: Treat each story or separate area as a separate numbered activity for each principal element of the Work.

C. Constraints: Include constraints and work restrictions indicated in the Contract Documents and as follows in schedule, and show how the sequence of the Work is affected. 1. Owner-Furnished Products: Include a separate activity for each product. Include

delivery date indicated in Division 01 Section "Summary." Delivery dates indicated stipulate the earliest possible delivery date.

2. Work stages: Indicate important stages of construction for each major portion of the Work.

3. Area Separations: Identify each major area of construction for each major portion of the Work. Indicate where each construction activity within a major area must be sequenced or integrated with other construction activities.

D. Milestones: Include milestones indicated in the Contract Documents in schedule, including, but not limited to, the Notice to Proceed, Substantial Completion, and Final Completion, include submittals to AARB, DEB, and other required federal, state and local agencies and Owner reviews.

E. Mason Review period: The GC’s schedule shall reflect a review period for Mason to review concurrent with the DEB review of the documents for any shop drawing

Page 41: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

013200 - 2 CONSTRUCTION PROGRESS DOCUMENTATION

submissions. Review comments shall be sent to the Contractor within the three week time period. The General Contractor shall provide written responses to all comments within three weeks of receiving comments from Mason.

2.2 REPORTS

A. Submit daily reports directly to Owner. Reports shall be numbered consecutively and all sections shall be completed or noted as “not applicable”. Reports shall contain detailed remarks each day, including, but not limited to progress on the job, problems discovered, and discussions with Mason staff. Reports shall be submitted to the Owner’s representative each day for the previous workday.

1. All correspondence shall be in English.

2.3 SPECIAL REPORTS

A. General: Submit special reports directly to Owner within one day of an occurrence. Distribute copies of report to parties affected by the occurrence.

B. Reporting Unusual Events: When an event of an unusual and significant nature occurs at Project site, whether or not related directly to the Work, prepare and submit a special report. List chain of events, persons participating, response by Contractor's personnel, evaluation of results or effects, and similar pertinent information. Advise Owner in advance when these events are known or predictable.

PART 3 - EXECUTION

3.1 CONTRACTOR'S CONSTRUCTION SCHEDULE

A. Contractor's Construction Schedule: Provide as specified in the General Conditions of the Contract.

B. Distribution: Distribute copies of approved schedule to Architect, Owner, and other

parties identified by Contractor with a need-to-know schedule responsibility.

END OF SECTION 013200

Page 42: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SUBMITTAL PROCEDURES 013300 - 1

SECTION 013300 - SUBMITTAL PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for the submittal schedule and administrative and procedural requirements for submitting Shop Drawings, Product Data, Samples, and other submittals.

B. Related Sections:

1. Section 01 Section “Closeout Procedures” for submitting warranties, project record documents and operation and maintenance manuals.

1.3 DEFINITIONS

A. Action Submittals: Written and graphic information that require Engineer’s and/or Owner’s Representative’s responsive action.

B. Informational Submittals: Written and graphic information that do not require Engineer’s and/or Owner’s Representative’s responsive action. Submittals may be rejected for not complying with requirements.

C. File Transfer Protocol (FTP): Communications protocol that enables transfer of files to and from another computer over a network and that serves as the basis for standard Internet protocols. An FTP site is a portion of a network located outside of network firewalls within which internal and external users are able to access files.

D. Portable Document Format (PDF): An open standard file format licensed by Adobe Systems used for representing documents in a device-independent and display resolution-independent fixed-layout document format.

1.4 SUBMITTAL ADMINISTRATIVE REQUIREMENTS

1. Engineer will furnish Contractor digital data drawing files of the Contract Drawings for use in preparing Shop Drawings and Project record drawings.

a. Engineer makes no representations as to the accuracy or completeness of digital data drawing files as they relate to the Contract Drawings.

b. Contractor shall execute a data licensing agreement in the form of an Agreement form acceptable to the Owner and Engineer.

B. Coordination: Coordinate preparation and processing of submittals with performance of construction activities.

Page 43: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

013300 - 2 SUBMITTAL PROCEDURES

1. Coordinate each submittal with fabrication, purchasing, testing, delivery, other submittals, and related activities that require sequential activity.

2. Submit all submittal items required for each Specification Section concurrently unless partial submittals for portions of the Work are indicated on approved submittal schedule.

3. Submit action submittals and informational submittals required by the same Specification Section as separate packages under separate transmittals.

4. Coordinate transmittal of different types of submittals for related parts of the Work so processing will not be delayed because of need to review submittals concurrently for coordination.

a. Engineer and/or Owner’s Representative reserves the right to withhold action on a submittal requiring coordination with other submittals until related submittals are received.

C. Processing Time: Allow time for submittal review, including time for resubmittals, as follows. Time for review shall commence on Owner’s Representative’s receipt of submittal. No extension of the Contract Time will be authorized because of failure to transmit submittals enough in advance of the Work to permit processing, including resubmittals.

1. Initial Review: Allow 7 days for initial review of each submittal. Allow additional time if coordination with subsequent submittals is required. Owner’s Representative will advise Contractor when a submittal being processed must be delayed for coordination.

2. Intermediate Review: If intermediate submittal is necessary, process it in same manner as initial submittal.

3. Resubmittal Review: Allow 7 days for review of each resubmittal. 4. Sequential Review: Where sequential review of submittals by Engineer's

consultants, Owner, or other parties is indicated, allow 14 days for initial review of each submittal.

5. Concurrent Consultant Review: Where the Contract Documents indicate that submittals may be transmitted simultaneously to consultants, allow 7 days for review of each submittal. Submittal will be returned to Owner’s Representative before being returned to Contractor.

D. Identification and Information: Place a permanent label or title block on each paper copy submittal item for identification.

1. Indicate name of firm or entity that prepared each submittal on label or title block. 2. Provide a space approximately 4 by 5 inches on label or beside title block to

record Contractor's review and approval markings and action taken by Owner’s Representative.

Page 44: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SUBMITTAL PROCEDURES 013300 - 3

3. Include the following information for processing and recording action taken:

a. Project name. b. Date. c. Name of Engineer. d. Name of Owner’s Representative. e. Name of Contractor. f. Name of subcontractor. g. Name of supplier. h. Name of manufacturer. i. Submittal number or other unique identifier, including revision identifier.

1) Submittal number shall use Specification Section number followed by a decimal point and then a sequential number (e.g., 061000.01). Resubmittals shall include an alphabetic suffix after another decimal point (e.g., 061000.01.A).

j. Number and title of appropriate Specification Section. k. Drawing number and detail references, as appropriate. l. Location(s) where product is to be installed, as appropriate. m. Other necessary identification.

E. Deviations: Identify deviations from the Contract Documents on submittals.

F. Additional Paper Copies: Unless additional copies are required for final submittal, and unless Owner’s Representative observes noncompliance with provisions in the Contract Documents, initial submittal may serve as final submittal.

1. Submit one copy of submittal to concurrent reviewer in addition to specified number of copies to Engineer and/or Owner’s Representative.

G. Transmittal: Assemble each submittal individually and appropriately for transmittal and handling. Transmit each submittal using a transmittal form. Engineer and/or Owner’s Representative will return submittals, without review, received from sources other than Contractor.

1. Transmittal Form: Provide locations on form for the following information:

a. Project name. b. Date. c. Destination (To:). d. Source (From:). e. Names of subcontractor, manufacturer, and supplier. f. Category and type of submittal. g. Submittal purpose and description. h. Specification Section number and title. i. Indication of full or partial submittal. j. Drawing number and detail references, as appropriate. k. Transmittal number, numbered consecutively. l. Submittal and transmittal distribution record. m. Remarks.

Page 45: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

013300 - 4 SUBMITTAL PROCEDURES

n. Signature of transmitter.

2. On an attached separate sheet, prepared on Contractor's letterhead, record relevant information, requests for data, revisions other than those requested by Owner’s Representative on previous submittals, and deviations from requirements in the Contract Documents, including minor variations and limitations. Include same identification information as related submittal.

H. Resubmittals: Make resubmittals in same form and number of copies as initial submittal.

1. Note date and content of previous submittal. 2. Note date and content of revision in label or title block and clearly indicate extent

of revision. 3. Resubmit submittals until they are marked with approval notation from Engineer’s

action stamp.

I. Distribution: Furnish copies of final submittals to manufacturers, subcontractors, suppliers, fabricators, installers, authorities having jurisdiction, and others as necessary for performance of construction activities. Show distribution on transmittal forms.

J. Use for Construction: Use only final submittals that are marked with approval notation from Engineer’s action stamp.

PART 2 - PRODUCTS

2.1 SUBMITTAL PROCEDURES

A. General Submittal Procedure Requirements: Prepare and submit submittals required by individual Specification Sections. Types of submittals are indicated in individual Specification Sections.

1. Submit electronic submittals via email as PDF electronic files.

a. Engineer will return annotated file. Annotate and retain one copy of file as an electronic Project record document file.

2. Closeout Submittals and Maintenance Material Submittals: Comply with requirements specified in Division 01 Section "Closeout Procedures."

3. Certificates and Certifications Submittals: Provide a statement that includes signature of entity responsible for preparing certification. Certificates and certifications shall be signed by an officer or other individual authorized to sign documents on behalf of that entity.

a. Provide a digital signature with digital certificate on electronically-submitted certificates and certifications where indicated.

b. Provide a notarized statement on original paper copy certificates and certifications where indicated.

B. Product Data: Collect information into a single submittal for each element of construction and type of product or equipment.

Page 46: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SUBMITTAL PROCEDURES 013300 - 5

1. If information must be specially prepared for submittal because standard publisheddata are not suitable for use, submit as Shop Drawings, not as Product Data.

2. Mark each copy of each submittal to show which products and options areapplicable.

3. Include the following information, as applicable:

a. Manufacturer's catalog cuts.b. Manufacturer's product specifications.c. Standard color charts.d. Statement of compliance with specified referenced standards.e. Testing by recognized testing agency.f. Application of testing agency labels and seals.g. Notation of coordination requirements.h. Availability and delivery time information.

4. For equipment, include the following in addition to the above, as applicable:

a. Wiring diagrams showing factory-installed wiring.b. Printed performance curves.c. Operational range diagrams.d. Clearances required to other construction, if not indicated on accompanying

Shop Drawings.

5. Submit Product Data before or concurrent with Samples.6. Submit Product Data in the following format:

a. PDF electronic file.

C. Shop Drawings: Prepare Project-specific information, drawn accurately to scale. Do notbase Shop Drawings on reproductions of the Contract Documents or standard printeddata.

1. Preparation: Fully illustrate requirements in the Contract Documents. Include thefollowing information, as applicable:

a. Identification of products.b. Schedules.c. Compliance with specified standards.d. Notation of coordination requirements.e. Notation of dimensions established by field measurement.f. Relationship and attachment to adjoining construction clearly indicated.g. Seal and signature of professional engineer if specified.

2. Sheet Size: Except for templates, patterns, and similar full-size drawings, submitShop Drawings on sheets at least 8-1/2 by 11 inches but no larger than 30 by 42inches.

3. Submit Shop Drawings in the following format:

a. PDF electronic file.

Page 47: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

013300 - 6 SUBMITTAL PROCEDURES

D. Contractor's Construction Schedule: Comply with requirements specified in General Conditions.

E. Application for Payment: Comply with requirements specified in General Conditions.

F. Schedule of Values: Comply with requirements specified in General Conditions.

G. Subcontract List: Prepare a written summary identifying individuals or firms proposed for each portion of the Work, including those who are to furnish products or equipment fabricated to a special design. Include the following information in tabular form:

1. Name, address, and telephone number of entity performing subcontract or supplying products.

2. Number and title of related Specification Section(s) covered by subcontract. 3. Drawing number and detail references, as appropriate, covered by subcontract. 4. Submit subcontract list in the following format:

a. PDF electronic file.

H. Coordination Drawings: Comply with requirements specified in Division 01 Section "Project Management and Coordination."

I. Qualification Data: Prepare written information that demonstrates capabilities and experience of firm or person. Include lists of completed projects with project names and addresses, contact information of architects and owners, and other information specified.

J. Welding Certificates: Prepare written certification that welding procedures and personnel comply with requirements in the Contract Documents. Submit record of Welding Procedure Specification and Procedure Qualification Record on American Welding Society (AWS) forms. Include names of firms and personnel certified.

K. Installer Certificates: Submit written statements on manufacturer's letterhead certifying that Installer complies with requirements in the Contract Documents and, where required, is authorized by manufacturer for this specific Project.

L. Manufacturer Certificates: Submit written statements on manufacturer's letterhead certifying that manufacturer complies with requirements in the Contract Documents. Include evidence of manufacturing experience where required.

M. Product Certificates: Submit written statements on manufacturer's letterhead certifying that product complies with requirements in the Contract Documents.

N. Material Certificates: Submit written statements on manufacturer's letterhead certifying that material complies with requirements in the Contract Documents.

O. Material Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting test results of material for compliance with requirements in the Contract Documents.

P. Product Test Reports: Submit written reports indicating current product produced by manufacturer complies with requirements in the Contract Documents. Base reports on

Page 48: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SUBMITTAL PROCEDURES 013300 - 7

evaluation of tests performed by manufacturer and witnessed by a qualified testing agency, or on comprehensive tests performed by a qualified testing agency.

Q. Research Reports: Submit written evidence, from a model code organization acceptable to authorities having jurisdiction, that product complies with building code in effect for Project. Include the following information:

1. Name of evaluation organization. 2. Date of evaluation. 3. Time period when report is in effect. 4. Product and manufacturers' names. 5. Description of product. 6. Test procedures and results. 7. Limitations of use.

R. Preconstruction Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of tests performed before installation of product, for compliance with performance requirements in the Contract Documents.

S. Compatibility Test Reports: Submit reports written by a qualified testing agency, on testing agency's standard form, indicating and interpreting results of compatibility tests performed before installation of product. Include written recommendations for primers and substrate preparation needed for adhesion.

T. Field Test Reports: Submit reports indicating and interpreting results of field tests performed either during installation of product or after product is installed in its final location, for compliance with requirements in the Contract Documents.

U. Maintenance Data: Comply with requirements specified in Division 01 Section "Operation and Maintenance Data."

V. Design Data: Prepare and submit written and graphic information, including, but not limited to, performance and design criteria, list of applicable codes and regulations, and calculations. Include list of assumptions and other performance and design criteria and a summary of loads. Include load diagrams if applicable. Provide name and version of software, if any, used for calculations. Include page numbers.

2.2 DELEGATED-DESIGN SERVICES

A. Performance and Design Criteria: Where professional design services or certifications by a design professional are specifically required of Contractor by the Contract Documents, provide products and systems complying with specific performance and design criteria indicated.

1. If criteria indicated are not sufficient to perform services or certification required, submit a written request for additional information to Engineer.

B. Delegated-Design Services Certification: In addition to Shop Drawings, Product Data, and other required submittals, submit digitally-signed PDF electronic file of certificate,

Page 49: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

013300 - 8 SUBMITTAL PROCEDURES

signed and sealed by the responsible design professional, for each product and system specifically assigned to Contractor to be designed or certified by a design professional.

1. Indicate that products and systems comply with performance and design criteria in the Contract Documents. Include list of codes, loads, and other factors used in performing these services.

PART 3 - EXECUTION

3.1 CONTRACTOR'S REVIEW

A. Action and Informational Submittals: Review each submittal and check for coordination with other Work of the Contract and for compliance with the Contract Documents. Note corrections and field dimensions. Mark with approval stamp before submitting to Engineer and Owner’s Representative.

B. Project Closeout and Maintenance/Material Submittals: Refer to requirements in Division 01 Section "Closeout Procedures."

C. Approval Stamp: Stamp each submittal with a uniform, approval stamp. Include Project name and location, submittal number, Specification Section title and number, name of reviewer, date of Contractor's approval, and statement certifying that submittal has been reviewed, checked, and approved for compliance with the Contract Documents.

3.2 ENGINEER’S ACTION

A. General: Engineer will not review submittals that do not bear Contractor's approval stamp and will return them without action.

B. Action Submittals: Engineer and/or Owner’s Representative will review each submittal, make marks to indicate corrections or modifications required, and return it. Engineer and/or Owner’s Representative will stamp each submittal with an action stamp and will mark stamp appropriately to indicate action.

C. Informational Submittals: Engineer and/or Owner’s Representative will review each submittal and will not return it, or will return it if it does not comply with requirements. Engineer and/or Owner’s Representative will forward each submittal to appropriate party.

D. Partial submittals prepared for a portion of the Work will be reviewed when use of partial submittals has received prior approval from Owner’s Representative.

E. Incomplete submittals are not acceptable, will be considered nonresponsive, and will be returned without review.

F. Submittals not required by the Contract Documents may not be reviewed and may be discarded.

END OF SECTION 013300

Page 50: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

REFERENCES 014200 - 1

SECTION 014200 -REFERENCES

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 1 Specification Sections, apply to this Section.

1.2 DEFINITIONS

A. General: Basic Contract definitions are included in the Conditions of the Contract.

B. "Approved": The term "approved," when used in conjunction with Owner’s

Representative's action on Contractor's submittals, applications, and requests, is

limited to Owner’s Representative's duties and responsibilities as stated in the

Conditions of the Contract.

C. "Directed": Terms such as "directed," "requested," "authorized," "selected,"

"approved," "required," and "permitted" mean directed by Owner’s Representative,

requested by Owner’s Representative, and similar phrases.

D. "Indicated": The term "indicated" refers to graphic representations, notes, or

schedules on Drawings; or to other paragraphs or schedules in Specifications and

similar requirements in the Contract Documents. Terms such as "shown," "noted,"

"scheduled," and "specified" are used to help the user locate the reference.

E. "Regulations": The term "regulations" includes laws, ordinances, statutes, and lawful

orders issued by authorities having jurisdiction, as well as rules, conventions, and

agreements within the construction industry that control performance of the Work.

F. "Furnish": The term "furnish" means to supply and deliver to Project site, ready for

unloading, unpacking, assembly, installation, and similar operations.

G. "Install": The term "install" describes operations at Project site including unloading,

temporary storage, unpacking, assembling, erecting, placing, anchoring, applying,

working to dimension, finishing, curing, protecting, cleaning, and similar operations.

H. "Provide": The term "provide" means to furnish and install, complete and ready for the intended use. I. "Installer": An installer is Contractor or another entity engaged by Contractor, as an employee, subcontractor, or contractor of lower tier, to perform a particular construction operation, including installation, erection, application, and similar operations.

J. "Project site" is the space available for performing construction activities, either

exclusively or in conjunction with others performing other work as part of Project.

The extent of Project site is shown on the Drawings and may or may not be identical

with the description of the land on which Project is to be built.

Page 51: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

014200 - 2 REFERENCES

1.3 INDUSTRY STANDARDS

A. Applicability of Standards: Unless the Contract Documents include more stringent

requirements, applicable construction industry standards have the same force and

effect as if bound or copied directly into the Contract Documents to the extent

referenced. Such standards are made a part of the Contract Documents by

reference.

B. Publication Dates: Comply with standards in effect as of the date of the Contract

Documents, unless otherwise indicated.

C. Conflicting Requirements: Where compliance with two or more standards is

specified and the standards establish different or conflicting requirements for

minimum quantities or quality levels, comply with the most stringent requirement.

Refer uncertainties and requirements that are different, but apparently equal, to

Owner’s Representative for a decision before proceeding.

1. Minimum Quantity or Quality Levels: The quantity or quality level shown or

specified shall be the minimum provided or performed. The actual installation

may comply exactly with the minimum quantity or quality specified, or it may

exceed the minimum within reasonable limits. To comply with these

requirements, indicated numeric values are minimum or maximum, as

appropriate, for the context of the requirements. Refer uncertainties to Owner’s

Representative for a decision before proceeding.

D. Copies of Standards: Each entity engaged in construction on Project must be familiar

with industry standards applicable to its construction activity. Copies of applicable

standards are not bound with the Contract Documents.

1. Where copies of standards are needed to perform a required construction

activity, obtain copies directly from the publication source and make them

available on request.

E. Abbreviations and Names: Abbreviations and acronyms are frequently used in the Specifications and other Contract Documents to represent the name of a trade association, standards-developing organization, authorities having jurisdiction, or other entity in the context of referencing a standard or publication. Where abbreviations and acronyms are used in the Specifications or other Contract Documents, they mean the recognized name of these entities. Refer to Gale Research's "Encyclopedia of Associations" or Columbia Books' "National Trade & Professional Associations of the U.S.

END OF SECTION

Page 52: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TESTING AND INSPECTION SERVICES 014250 - 1

SECTION 014250 – TESTING AND INSPECTION SERVICES

PART 1 -GENERAL

1.1 RELATED DOCUMENTS

A. The General Provisions of Contract, including General and Supplementary Conditions and Division 1 Specification sections, apply to work of this section.

1.2 DESCRIPTION

A. The Owner will employ and pay for the services of independent testing agencies to perform on-site inspection of work in progress.

B. Provide all other testing in the Base Bid amount.

C. Required inspection and testing services are intended to assist in determination of probable compliance of work with requirements, but do not relieve Contractor of responsibility for those compliances, or for general fulfillment of requirements of Contract Documents. Specified inspections and tests are not intended to limit Contractor's quality control program.

1.3 SUBMITTALS

A. The testing agency shall submit two copies of test/inspection reports, including agency's analysis of results and recommendations to the Owner's Representative and shall submit copies directly to governing authorities where required or requested.

1.4 TEST SAMPLES

A. Test samples as the Owner's Representative may deem necessary will be procured from

the various materials or equipment delivered by the Contractor for use in the work.

B. If any of these test samples fail to meet the contract requirements, such materials or

equipment shall be subject to removal and replacement by the Contractor with materials

or equipment meeting Contract requirements, or at the discretion of the Owner the

installed defective material and equipment may be permitted to remain in place subject

to a proper adjustment of the Contract Sum.

C. If tests reveal failure of materials to comply with Contract requirements, the costs of such

tests made necessary by such failure shall be charged to the Contractor by Change

Order.

1.5 QUALIFICATION OF AGENCIES

A. Except where manufacturer's testing facilities are indicated as acceptable, independent

testing laboratories specializing in required services shall comply with "Recommended

Requirements for Independent Laboratory Qualification" by ACIL.

B. Individuals performing inspections and testing must be certified by the Institute of

Page 53: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

014250 - 2 TESTING AND INSPECTION SERVICES

Certified Engineering Technicians or other recognized comparable organizations.

C. Laboratories shall be licensed to operate in Virginia.

PART 2 -PRODUCTS (Not Applicable)

PART 3 -EXECUTION

3.1 TESTING AND INSPECTION AGENCIES' RESPONSIBILITIES

A. Cooperate with Owner's Representative and Contractor; provide qualified personnel.

B. Perform specified inspections, sampling and testing of materials and methods of

construction. Comply with specified standards. Ascertain compliance of materials with

requirements of projects.

C. Promptly notify Owner's Representative and Contractor of observed irregularities or

deficiencies of work or products.

D. Promptly submit written report of each test and inspection.

E. Perform additional tests and inspections at request of Owner's Representative.

F. Attend progress meetings.

3.2 CONTRACTOR'S RESPONSIBILITIES

A. Cooperate with laboratory personnel, provide access to work, and to manufacturer's

operations.

B. Secure and deliver to laboratory adequate quantities of representational samples of

materials proposed to be used which require testing.

C. Furnish copies of manufacturer's test reports of products as required.

D. Furnish incidental labor and facilities as follows: 1. To provide access to work to be tested. 2. To obtain and handle samples at project site or at source of product to be tested. 3. To facilitate and inspections and tests. 4. For storage and curing of test samples.

E. Make arrangements with laboratory or agency and pay for additional samples, and tests

required when initial tests indicate work does not conform to Contract Documents.

3.3 SPECIAL INSPECTIONS

Page 54: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TESTING AND INSPECTION SERVICES 014250 - 3

A. Owner's Inspections: The Owner and/or his representative shall observe the work at

various stages of completion in order to verify compliance with contract requirements.

END OF SECTION

Page 55: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TEMPORARY FACILITIES AND CONTROLS 015000 - 1

SECTION 015000 - TEMPORARY FACILITIES AND CONTROLS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes requirements for temporary utilities, support facilities, and security and protection facilities.

1. Temporary utilities include, but are not limited to, the following: a. Temporary electric power and light. b. Telephone and fax service. c. Sanitary facilities and drainage. d. Lighting.

2. Support facilities include, but are not limited to, the following: a. Construction entrance. b. Dewatering facilities and drains. c. Project identification and temporary signs. d. Waste disposal facilities. e. Field offices (for Contractor’s use) f. Construction aids and miscellaneous services and facilities.

3. Security and protection facilities include, but are not limited to, the following: a. Environmental protection. b. Storm water control. c. Tree and plant protection. d. Pest control. e. Site enclosure (barrier) fence. f. Security enclosure and lockup. g. Barricades, warning signs, and lights. h. Temporary enclosures.

B. Related Sections:

1. Division 01 Section "Summary" for work restrictions and limitations on utility interruptions.

1.3 USE CHARGES

A. General: Installation and removal of and use charges for temporary facilities shall be included in the Contract Sum unless otherwise indicated. Allow other entities to use temporary services and facilities without cost, including, but not limited to, Owner’s representatives, testing agencies, and authorities having jurisdiction.

B. Water and Sewer Service from Existing System: Water from Owner's existing water system is available for use with temporary metering and subject to payment of use

Page 56: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

015000 - 2 TEMPORARY FACILITIES AND CONTROLS

charges. Provide connections and extensions of services as required for construction operations.

C. Electric Power Service from Existing System: Electric power from Owner's existing system is available for use with temporary metering and subject to monthly payment of use charges. Provide connections and extensions of services as required for construction operations.

1.4 QUALITY ASSURANCE

A. Regulations: Comply with industry standards and applicable laws and regulations of Authorities having jurisdiction including, but not limited to, the following:

1. Virginia Department of Transportation. 2. Health and safety regulations. 3. Utility company regulations. 4. Police, fire department, and rescue squad rules. 5. Environmental protection regulations.

B. Comply with NFPA 241 “Standard for Safeguarding Construction, Alterations, and Demolition Operations,” ANSI, A10 Series standards for “Safety Requirements for Construction and Demolition,” and NECA Electrical Design Library “Temporary Electrical Facilities.”

1. Electric Service: Comply with NECA, NEMA, and UL standards and regulations for temporary electric service. Install service to comply with NFPA 70.

C. Tests and Inspections: Arrange for authorities having jurisdiction to test and inspect each temporary utility before use. Obtain required certifications and permits.

1.5 PROJECT CONDITIONS

A. Temporary Use of Permanent Facilities: Engage installer of each permanent service to assume responsibility for operation, maintenance, and protection of each permanent service during its use as a construction facility before Owner's acceptance, regardless of previously assigned responsibilities.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Chain-Link Fencing: Minimum 2-inch (50-mm), 0.148-inch- (3.8-mm-) thick, galvanized steel, chain-link fabric fencing; minimum 6 feet (1.8 m) high with galvanized steel pipe posts; minimum 2-3/8-inch- (60-mm-) OD line posts and 2-7/8-inch- (73-mm-) OD corner and pull posts with 1-5/8-inch- (42-mm-) OD top rails. Fence posts shall be installed 3’6” into the ground, but need not be set in concrete, except gate posts.

Page 57: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TEMPORARY FACILITIES AND CONTROLS 015000 - 3

2.2 TEMPORARY FACILITIES

A. Field Offices, General: Prefabricated or mobile units with serviceable finishes, temperature controls, and foundations adequate for normal loading.

B. Common-Use Field Office: Of sufficient size to accommodate needs of Owner, Construction Manager, and construction personnel office activities and to accommodate project meetings specified in other Division 01 Sections. Keep office clean and orderly. Furnish and equip offices as follows:

1. Furniture required for Project-site documents including file cabinets, plan tables, plan racks, and bookcases.

2. Conference room of sufficient size to accommodate meetings of 10 individuals. Provide electrical power service and 120-V ac duplex receptacles, with not less than 1 receptacle on each wall. Furnish room with conference table, chairs, and 4-foot- (1.2-m-) square tack and marker boards.

3. Drinking water. 4. Heating and cooling equipment necessary to maintain a uniform indoor

temperature of 68 to 72 deg F (20 to 22 deg C). 5. Lighting fixtures capable of maintaining average illumination of 20 fc (215 lx) at

desk height.

C. Storage and Fabrication Sheds: If required, provide sheds sized, furnished, and equipped to accommodate materials and equipment for construction operations.

1. Store combustible materials apart from building.

2.3 EQUIPMENT

A. Fire Extinguishers: Portable, UL rated; with class and extinguishing agent as required by locations and classes of fire exposures.

1. Comply with NFPA 10 and NPFA 241 for classification, extinguishing agent, and size required by location and class of exposure.

B. HVAC Equipment: Unless Owner authorizes use of permanent HVAC system, provide vented, self-contained, liquid-propane-gas or fuel-oil heaters with individual space thermostatic control.

1. Use of gasoline-burning space heaters, open-flame heaters, or salamander-type heating units is prohibited.

2. Heating Units: Listed and labeled for type of fuel being consumed, by a testing agency acceptable to authorities having jurisdiction, and marked for intended use.

3. Permanent HVAC System: If Owner authorizes use of permanent HVAC system for temporary use during construction, provide filter with MERV of [8] at each return air grille in system and remove at end of construction and clean HVAC system as required in Division 01 Section "Closeout Procedures".

C. Air Filtration Units: HEPA primary and secondary filter-equipped portable units with four-stage filtration. Provide single switch for emergency shutoff. Configure to run continuously.

Page 58: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

015000 - 4 TEMPORARY FACILITIES AND CONTROLS

D. Temporary Toilet Units: Provide self-contained, single-occupant toilet units of the chemical aerated recirculation, or combustion type. Provide units properly vented and fully enclosed with a glass-fiber-reinforced polyester shell or similar nonabsorbent material.

E. Drinking-Water Fixtures: provide drink-water fountains or containerized, tap-dispenser, bottled-water drinking-water units, including paper cup supply.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Use qualified personnel for installation of temporary facilities. Locate facilities where they will serve Project adequately and result in minimum interference with performance of the Work. Relocate and modify facilities as required by progress of the Work.

1. Locate facilities to limit site disturbance as specified in Division 01 Section "Summary."

B. Provide each facility ready for use when needed to avoid delay. Do not remove until facilities are no longer needed or are replaced by authorized use of completed permanent facilities.

3.2 TEMPORARY UTILITY INSTALLATION

A. General: Install temporary service or connect to existing service.

1. Arrange with utility company, Owner, and existing users for time when service can be interrupted, if necessary, to make connections for temporary services.

B. Sewers and Drainage: Provide temporary utilities to remove effluent lawfully.

1. Connect temporary sewers to municipal system as directed by authorities having jurisdiction.

C. Water Service: Install water service and distribution piping in sizes and pressures adequate for construction.

D. Water Service: Connect to Owner's existing water service facilities. Clean and maintain water service facilities in a condition acceptable to Owner. At Substantial Completion, restore these facilities to condition existing before initial use.

E. Sanitary Facilities: Provide temporary toilets, wash facilities, and drinking water for use of construction personnel. Comply with requirements of authorities having jurisdiction for type, number, location, operation, and maintenance of fixtures and facilities.

1. Toilets: Use of Owner's existing toilet facilities will NOT be permitted. Provide portable chemical toilets. Comply with regulations and health codes for type, number (minimum of two), location, and maintenance of facilities.

Page 59: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TEMPORARY FACILITIES AND CONTROLS 015000 - 5

F. Electric Power Service: Connect to Owner's existing electric power service. Maintain equipment in a condition acceptable to Owner.

G. Electric Power Service: Provide electric power service and distribution system of sufficient size, capacity, and power characteristics required for construction operations.

1. Install electric power service. 2. Connect temporary service to Owner's existing power source, as directed by

Owner.

H. Lighting: Provide temporary lighting with local switching that provides adequate illumination for construction operations, observations, inspections, and traffic conditions.

1. Install and operate temporary lighting that fulfills security and protection requirements without operating entire system.

2. Install lighting for Project identification sign.

I. Telephone Service: Provide temporary telephone service in common-use facilities for use by all construction personnel. Install one telephone line(s) for each field office.

1. Provide additional telephone lines for the following:

a. Provide a dedicated telephone line for each facsimile machine in each field office.

b. Provide one telephone line(s) for Owner's use.

2. At each telephone, post a list of important telephone numbers.

a. Police and fire departments. b. Ambulance service. c. Contractor's home office. d. Engineers' offices. e. Owner's office. f. Principal subcontractors' field and home offices.

3. Provide superintendent with cellular telephone or portable two-way radio for use when away from field office.

3.3 SUPPORT FACILITIES INSTALLATION

A. General: Comply with the following:

1. Provide construction for temporary offices, shops, and sheds located within construction area or within 30 feet (9 m) of building lines that is noncombustible according to ASTM E 136. Comply with NFPA 241.

2. Maintain support facilities until Owner schedules Substantial Completion inspection. Remove before Substantial Completion. Personnel remaining after Substantial Completion will be permitted to use permanent facilities, under conditions acceptable to Owner.

Page 60: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

015000 - 6 TEMPORARY FACILITIES AND CONTROLS

B. Temporary Use of Permanent Roads and Paved Areas: Locate temporary roads and paved areas in same location as permanent roads and paved areas. Construct and maintain temporary roads and paved areas adequate for construction operations. Extend temporary roads and paved areas, within construction limits indicated, as necessary for construction operations.

1. Coordinate elevations of temporary roads and paved areas with permanent roads and paved areas.

2. Prepare subgrade and install subbase and base for temporary roads and paved areas according to Division 31 Section "Earth Moving."

3. Recondition base after temporary use, including removing contaminated material, regrading, proofrolling, compacting, and testing.

4. Delay installation of final course of permanent hot-mix asphalt pavement until immediately before Substantial Completion. Repair hot-mix asphalt base-course pavement before installation of final course according to Division 32 Section "Asphalt Paving."

C. Traffic Controls: Comply with requirements of authorities having jurisdiction.

1. Protect existing site improvements to remain including curbs, pavement, and utilities.

2. Maintain access for fire-fighting equipment and access to fire hydrants.

D. Parking: Use designated areas of Owner's existing parking areas for construction personnel.

E. Dewatering Facilities and Drains: Comply with requirements of the Virginia Erosion & Sediment Control Handbook and Division 31 “Dewatering.” Maintain Project site, excavations, and construction free of water.

1. Dispose of rainwater in a lawful manner that will not result in flooding Project or adjoining properties nor endanger permanent Work or temporary facilities.

2. Remove snow and ice as required to minimize accumulations.

F. Project Signs: Provide Project signs as indicated. Unauthorized signs are not permitted.

1. Temporary Signs: Provide other signs as indicated and as required to inform public and individuals seeking entrance to Project.

a. Provide temporary, directional signs for construction personnel and visitors.

2. Maintain and touchup signs so they are legible at all times.

G. Waste Disposal Facilities: The Contractor is responsible for maintain a clean site free of litter and debris, including removing waste from the site to the appropriate facilities. The Contractor shall comply with the requirements of the Virginia Erosion & Sediment Control Handbook.

H. Waste Disposal Facilities: Provide waste-collection containers in sizes adequate to handle waste from construction operations. Comply with requirements of authorities having jurisdiction.

Page 61: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TEMPORARY FACILITIES AND CONTROLS 015000 - 7

I. Lifts and Hoists: Provide facilities necessary for hoisting materials and personnel.

1. Truck cranes and similar devices used for hoisting materials are considered "tools and equipment" and not temporary facilities.

J. Existing Elevator Use: Use of Owner's existing elevators will be permitted, provided elevators are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore elevators to condition existing before initial use, including replacing worn cables, guide shoes, and similar items of limited life.

1. Do not load elevators beyond their rated weight capacity. 2. Provide protective coverings, barriers, devices, signs, or other procedures to

protect elevator car and entrance doors and frame. If, despite such protection, elevators become damaged, engage elevator Installer to restore damaged work so no evidence remains of correction work. Return items that cannot be refinished in field to the shop, make required repairs and refinish entire unit, or provide new units as required.

K. Temporary Stairs: Until permanent stairs are available, provide temporary stairs where ladders are not adequate.

L. Existing Stair Usage: Use of Owner's existing stairs will be permitted, provided stairs are cleaned and maintained in a condition acceptable to Owner. At Substantial Completion, restore stairs to condition existing before initial use.

1. Provide protective coverings, barriers, devices, signs, or other procedures to protect stairs and to maintain means of egress. If stairs become damaged, restore damaged areas so no evidence remains of correction work.

3.4 SECURITY AND PROTECTION FACILITIES INSTALLATION

A. Environmental Protection: Provide protection, operate temporary facilities, and conduct construction as required to comply with environmental regulations and that minimize possible air, waterway, and subsoil contamination or pollution or other undesirable effects.

1. Comply with work restrictions specified in Division 01 Section "Summary."

B. Temporary Erosion and Sedimentation Control: Comply with requirements of Virginia Erosion & Sediment Control Handbook, requirements specified in Division 31 Section "Site Clearing."

C. Temporary Erosion and Sedimentation Control: Provide measures to prevent soil erosion and discharge of soil-bearing water runoff and airborne dust to undisturbed areas and to adjacent properties and walkways, according to erosion and sediment control drawings.

1. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross tree- or plant- protection zones.

2. Inspect, repair, and maintain erosion and sedimentation control measures during construction until permanent vegetation has been established.

Page 62: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

015000 - 8 TEMPORARY FACILITIES AND CONTROLS

3. Clean, repair, and restore adjoining properties and roads affected by erosion and sedimentation from the project site during the course of the project.

4. Remove erosion and sedimentation controls and restore and stabilize areas disturbed during removal.

D. Stormwater Control: Comply with requirements Virginia Erosion & Sediment Control Handbook. Provide barriers in and around excavations and subgrade construction to prevent flooding by runoff of stormwater from heavy rains.

E. Tree and Plant Protection: Comply with requirements specified in Division 32 “Plants.”

1. Tree and Plant Protection: Install temporary fencing located as indicated or outside the drip line of trees to protect vegetation from damage from construction operations. Protect tree root systems from damage, flooding, and erosion.

2. Tree Protection: contractor shall take all precautions necessary to protect existing trees scheduled to remain against injury or damage, including cutting, breaking, or skinning of roots, trunks or branches; smothering by stockpiled construction materials, excavated materials or vehicular traffic within branch spread. a. Interfering branches of trees scheduled to remain may be removed when

acceptable to the University. It cannot be assumed that permission will be granted. The Contractor must obtain permission from GMU prior to such activities.

b. Repair trees scheduled to remain and damaged by construction operations in a manner acceptable to GMU. Repair damaged trees promptly to prevent progressive deterioration caused by damage.

3. Tree Replacement: should an existing tree be damaged to the extent that it is deemed to be a complete loss by GMU, or if, due to the Contractor's negligence, a tree on the construction site dies within one year of project completion, the Contractor shall replace the tree according to the following requirements: a. Tree Replacement Formula: One square inch of caliper lost will equal one

square inch of caliper replaced. This formula is based on tree trunk diameter at breast height. Example: loss of one 12" caliper (same as 6" radius) tree would require replacement with nine (9) 4" caliper trees. [Area of Circle =

3.14 x r2

= 3.14x(62

)= 3.14x(36)= 113.04 sq. in. Assuming 4" caliper trees (same as 2” radius) will be planted as replacements, calculate the area of a

4" caliper tree: 3.14 x (22

)= 12.56 sq. in. Divide the area of the 4" caliper tree into the area of the 12" caliper tree to determine the number of 4" caliper trees required to replace the loss of the 12" caliper tree. 113.04/12.56= 9 trees.]

b. Installation: Contractor will be responsible for planting the replacement tree(s) at a location designated by GMU. Installation practices and a one year guarantee shall hold as described in Section 02900 - Planting.

c. Materials: The replacement tree(s) shall be of the same species and variety as the tree(s) lost. If the species and variety is not available, a substitute must be proposed in writing to the GMU and approved by GMU. The Contractor will be notified of approval of substitution within seven days. Minimum caliper of replacement tree(s) shall be 4".

4. Repair and replacement of trees scheduled to remain and damaged by construction operations or lack of adequate protection during construction operations shall be at Contractor's expense.

Page 63: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TEMPORARY FACILITIES AND CONTROLS 015000 - 9

F. Pest Control: Engage pest-control service to recommend practices to minimize attraction and harboring of rodents, roaches, and other pests and to perform extermination and control procedures at regular intervals so Project will be free of pests and their residues at Substantial Completion. Obtain extended warranty for Owner. Perform control operations lawfully, using environmentally safe materials.

G. Site Enclosure Fence: Before construction operations begin, furnish and install a 6’ high chain-line fence around the entire construction area. The Contractor is responsible to erect, maintain and, upon direction by the Owner, remove the fence and restore the area to its original condition.

1. Extent of Fence: As required to enclose entire Project site or portion determined sufficient to accommodate construction operations and prevent people and animals from easily entering site except by entrance gates.

2. Maintain security by limiting number of keys and restricting distribution to authorized personnel. Furnish one set of keys to Owner.

H. Security Enclosure and Lockup: Install temporary enclosure around partially completed areas of construction. Provide lockable entrances to prevent unauthorized entrance, vandalism, theft, and similar violations of security. Lock entrances at end of each work day.

I. Barricades, Warning Signs, and Lights: Comply with requirements of authorities having jurisdiction for erecting structurally adequate barricades, including warning signs and lighting.

J. Temporary Egress: Maintain temporary egress from existing occupied facilities as indicated and as required by authorities having jurisdiction.

K. Covered Walkway: Erect protective, covered walkway for passage of individuals through or adjacent to Project site. Coordinate with entrance gates, other facilities, and obstructions. Comply with regulations of authorities having jurisdiction.

1. Construct covered walkways using scaffold or shoring framing. 2. Provide overhead decking, protective enclosure walls, handrails, barricades,

warning signs, exit signs, lights, safe and well-drained walkways, and similar provisions for protection and safe passage.

3. Paint and maintain appearance of walkway for duration of the Work.

L. Temporary Enclosures: Provide temporary enclosures for protection of construction, in progress and completed, from exposure, foul weather, other construction operations, and similar activities.

1. Where heating or cooling is needed and permanent enclosure is not complete, insulate temporary enclosures.

M. Temporary Fire Protection: Install and maintain temporary fire-protection facilities of types needed to protect against reasonably predictable and controllable fire losses. Comply with NFPA 241.

1. Prohibit smoking in construction areas.

Page 64: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

015000 - 10 TEMPORARY FACILITIES AND CONTROLS

2. Supervise welding operations, combustion-type temporary heating units, and similar sources of fire ignition according to requirements of authorities having jurisdiction.

3. Develop and supervise an overall fire-prevention and -protection program for personnel at Project site. Review needs with local fire department and establish procedures to be followed. Instruct personnel in methods and procedures. Post warnings and information.

4. Provide temporary standpipes and hoses for fire protection. Hang hoses with a warning sign stating that hoses are for fire-protection purposes only and are not to be removed. Match hose size with outlet size and equip with suitable nozzles.

3.5 MOISTURE AND MOLD CONTROL

A. Contractor's Moisture-Protection Plan: Avoid trapping water in finished work. Document visible signs of mold that may appear during construction.

B. Exposed Construction Phase: Before installation of weather barriers, when materials are subject to wetting and exposure and to airborne mold spores, protect as follows:

1. Protect porous materials from water damage. 2. Protect stored and installed material from flowing or standing water. 3. Keep porous and organic materials from coming into prolonged contact with

concrete.

3.6 OPERATION, TERMINATION, AND REMOVAL

A. Supervision: Enforce strict discipline in use of temporary facilities. To minimize waste and abuse, limit availability of temporary facilities to essential and intended uses.

B. Maintenance: Maintain facilities in good operating condition until removal.

1. Maintain operation of temporary enclosures, heating, cooling, humidity control, ventilation, and similar facilities on a 24-hour basis where required to achieve indicated results and to avoid possibility of damage.

C. Temporary Facility Changeover: Do not change over from using temporary security and protection facilities to permanent facilities until Substantial Completion.

D. Termination and Removal: Remove each temporary facility when need for its service has ended or no later than Substantial Completion. Complete or, if necessary, restore permanent construction that may have been delayed because of interference with temporary facility. Repair damaged Work, clean exposed surfaces, and replace construction that cannot be satisfactorily repaired.

1. Materials and facilities that constitute temporary facilities are property of Contractor.

2. Remove temporary roads and paved areas not intended for or acceptable for integration into permanent construction. Where area is intended for landscape development, remove soil and aggregate fill that do not comply with requirements for fill or subsoil. Remove materials contaminated with road oil, asphalt and other

Page 65: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

TEMPORARY FACILITIES AND CONTROLS 015000 - 11

petrochemical compounds, and other substances that might impair growth of plant materials or lawns. Repair or replace street paving, curbs, and sidewalks at temporary entrances, as required by the Owner.

3. At Substantial Completion, repair, renovate, and clean permanent facilities used during construction period. Comply with final cleaning requirements specified in Division 01 Section "Closeout Procedures."

END OF SECTION 015000

Page 66: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PRODUCT REQUIREMENTS 016000 - 1

SECTION 016000 – PRODUCT REQUIREMENTS

PART 1 - GENERAL

1.1 SUMMARY

A. Section includes administrative and procedural requirements for selection of prod-ucts for use in Project; product delivery, storage, and handling; manufacturers' standard warranties on products; special warranties; and comparable products.

B. Related Requirements:

1. Specification 01 42 00 References for applicable industry standards for prod-ucts specified.

1.2 DEFINITIONS

A. Products: Items purchased for incorporating into the Work, whether purchased for Project or taken from previously purchased stock. The term "product" includes the terms "material," "equipment," "system," and terms of similar intent.

1. Named Products: Items identified by manufacturer's product name, including make or model number or other designation, shown or listed in manufacturer's published product literature that is current as of date of the Contract Docu-ments.

2. New Products: Items that have not previously been incorporated into another project or facility, except that products consisting of recycled-content materials are allowed, unless explicitly stated otherwise. Products salvaged or recycled from other projects are not considered new products.

3. Comparable Product: Product that is demonstrated and approved through submittal process, or where indicated as an approved product substitution, to have the indicated qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics that equal or exceed those of specified product.

B. Substitutions: Changes in products, materials, equipment, and methods of construc-tion from those required by the Contract Documents and proposed by Contractor are considered substitutions. No substitutions will be considered after the date for the receipt of bids.

1. Substitutions requested by Bidders during bidding period and accepted by the Owner prior to award of Contract.

2. Revisions to Contract Documents requested by the Owner or Architect.

C. Basis-of-Design Product Specification: A specification in which a single manufactur-er's product is named and accompanied by the words “basis-of-design” or “design standard,” including make or model number or other designation, to establish the significant qualities related to type, function, dimension, in-service performance, physical properties, appearance, and other characteristics for purposes of evaluat-ing comparable products of other manufacturers.

D. Manufacturer's Warranty: Preprinted written warranty published by individual man-ufacturer for a particular product and specifically endorsed by manufacturer to Owner.

E. Special Warranty: Written warranty required by or incorporated into the Contract Documents, either to extend time limit provided by manufacturer's warranty or to provide more rights for Owner.

Page 67: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

016000 - 2 PRODUCT REQUIREMENTS

1.3 SUBMITTALS

A. Product List: Submit a list, in tabular from, showing specified products. Include ge-neric names of products required. Include manufacturer's name and proprietary product names for each product.

1. Coordinate product list with Contractor's Construction Schedule and the Sub-mittals Schedule.

2. Completed List: Within 30 days after date of commencement of the Work, submit 2 copies of completed product list. Include a written explanation for omissions of data and for variations from Contract requirements.

3. Architect's Action: If necessary, Architect will respond in writing to Contractor within 7 (seven) days of receipt of completed product list. Architect's response will include a list of unacceptable product selections and a brief explanation of reasons for this action. Architect's response, or lack of response, does not constitute a waiver of requirement that products comply with the Contract Doc-uments.

a. Use product specified if Architect does not issue a decision on use of a comparable product request within time allocated.

B. Use product specified if Architect does not issue a decision on use of a comparable product request within time allocated.

1.4 QUALITY ASSURANCE

A. Compatibility of Options: If Contractor is given option of selecting between two or more products for use on Project, product selected shall be compatible with products previously selected, even if previously selected products were also options.

1. Each contractor is responsible for providing products and construction meth-ods compatible with products and construction methods of other contractors.

2. If a dispute arises between contractors over concurrently selectable but in-compatible products, Architect will determine which products shall be used.

B. Nameplates: Except for required labels and operating data, do not attach or imprint manufacturer's or producer's nameplates or trademarks on exposed surfaces of products that will be exposed to view in occupied spaces or on the exterior.

1. Labels: Locate required product labels and stamps on a concealed surface or, where required for observation after installation, on an accessible surface that is not conspicuous.

2. Equipment Nameplates: Provide a permanent nameplate on each item of ser-vice-connected or power-operated equipment. Locate on a visually accessible but inconspicuous surface. Include information essential for operation, includ-ing the following:

a. Name of product and manufacturer. b. Model and serial number. c. Capacity. d. Speed. e. Ratings.

3. See individual identification sections in Divisions 21, 22, 23, 26, 27, and 28, as applicable, for additional identification requirements.

Page 68: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PRODUCT REQUIREMENTS 016000 - 3

1.5 PRODUCT DELIVERY, STORAGE, AND HANDLING

A. Deliver, store, and handle products using means and methods that will prevent dam-age, deterioration, and loss, including theft. Comply with manufacturer's written in-structions.

B. Delivery and Handling:

1. Schedule delivery to minimize long-term storage at Project site and to prevent overcrowding of construction spaces.

2. Coordinate delivery with installation time to ensure minimum holding time for items that are flammable, hazardous, easily damaged, or sensitive to deterio-ration, theft, and other losses.

3. Deliver products to Project site in an undamaged condition in manufacturer's original sealed container or other packaging system, complete with labels and instructions for handling, storing, unpacking, protecting, and installing.

4. Inspect products on delivery to ensure compliance with the Contract Docu-ments and to ensure that products are undamaged and properly protected.

C. Storage:

1. Store products to allow for inspection and measurement of quantity or count-ing of units.

2. Store materials in a manner that will not endanger Project structure. 3. Store products that are subject to damage by the elements, under cover in a

weathertight enclosure above ground, with ventilation adequate to prevent condensation.

4. Protect foam plastic from exposure to sunlight, except to extent necessary for period of installation and concealment.

5. Comply with product manufacturer's written instructions for temperature, hu-midity, ventilation, and weather-protection requirements for storage.

6. Protect stored products from damage and liquids from freezing. 7. Provide a secure location and enclosure at Project site for storage of materials

and equipment by Owner's construction forces. Coordinate location with Owner.

1.6 PRODUCT WARRANTIES

A. Warranties specified in other Sections shall be in addition to, and run concurrent with, other warranties required by the Contract Documents. Manufacturer's disclaim-ers and limitations on product warranties do not relieve Contractor of obligations under requirements of the Contract Documents.

B. Special Warranties: Prepare a written document that contains appropriate terms and identification, ready for execution. Submit a draft for approval before final execution.

1. Manufacturer's Standard Form: Modified to include Project-specific infor-mation and properly executed.

2. Specified Form: Forms are included with the Specifications. Prepare a written document using appropriate form properly executed.

3. Refer to other Division’s sections for specific content requirements and partic-ular requirements for submitting special warranties.

C. Submittal Time: Comply with requirements in Specification 01 78 36 Warranties.

PART 2 - PRODUCTS

Page 69: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

016000 - 4 PRODUCT REQUIREMENTS

2.1 PRODUCT OPTIONS

A. General Product Requirements: Provide products that comply with the Contract Documents, that are undamaged, and unless otherwise indicated, that are new at time of installation.

1. Provide products complete with accessories, trim, finish, fasteners, and other items needed for a complete installation and indicated use and effect.

2. Standard Products: If available, and unless custom products or nonstandard options are specified, provide standard products of types that have been pro-duced and used successfully in similar situations on other projects.

3. Owner reserves the right to limit selection to products with warranties not in conflict with requirements of the Contract Documents.

4. Where products are accompanied by the term "as selected," Architect will make selection.

5. Where products are accompanied by the term "match sample," sample to be matched is Architect's.

6. Descriptive, performance, and reference standard requirements in the Speci-fications establish "salient characteristics" of products.

B. Product Selection Procedures: Procedures for product selection include the follow-ing:

1. Product: Where Specification paragraphs or subparagraphs titled "Product" name a single product and manufacturer, provide the product named.

a. Substitutions will not be considered, unless otherwise indicated. b. Sole product may be indicated by the phrase: "Subject to compliance

with requirements, provide the following: …"

2. Manufacturer/Source: Where Specification paragraphs or subparagraphs ti-tled "Manufacturer" or "Source" name single manufacturers or sources, pro-vide a product by the manufacturer or from the source named that complies with requirements.

a. Substitutions will not be considered, unless otherwise indicated. b. Sole manufacturer/source may be indicated by the phrase: "Subject to

compliance with requirements, provide products by the following: …"

3. Products: Where Specification paragraphs or subparagraphs titled "Products" introduce a list of names of both products and manufacturers, provide one of the products listed that complies with requirements.

a. Substitutions will not be considered, unless otherwise indicated.

4. Manufacturers: Where Specification paragraphs or subparagraphs titled "Manufacturers" introduce a list of manufacturers' names, provide a product by one of the manufacturers listed that complies with requirements.

a. Substitutions will not be considered, unless otherwise indicated.

5. Available Products: Where Specification paragraphs or subparagraphs titled "Available Products" introduce a list of names of both products and manufac-turers, provide one of the products listed. Comply with provisions in "Compa-rable Products" Article to obtain approval for use of an unnamed product.

Page 70: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PRODUCT REQUIREMENTS 016000 - 5

6. Available Manufacturers: Where Specification paragraphs or subparagraphs titled "Available Manufacturers" introduce a list of manufacturers' names, pro-vide a product by one of the manufacturers listed. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed prod-uct.

7. Basis-of-Design Products: Where Specification paragraphs or subparagraphs titled “Basis-of-Design Product” or “Design Standard” are included and also introduce or refer to a list of manufacturers' names, provide either the specified product or a comparable product by another manufacturer. Drawings and Specifications indicate sizes, profiles, dimensions, and other characteristics that are based on the product named. Comply with provisions in "Comparable Products" Article to obtain approval for use of an unnamed product.

a. Submissions or substitutions will not be considered, unless otherwise indicated.

8. Visual Matching Specification: Where Specifications require matching an es-tablished Sample, select a product (and manufacturer) that complies with re-quirements and matches Architect's sample. Architect's decision will be final on whether a proposed product matches satisfactorily.

a. If no product available within specified category matches satisfactorily and complies with other specified requirements, comply with provisions of the Contract Documents on "substitutions" for selection of a matching product.

9. Visual Selection Specification: Where Specifications include the phrase "as selected from manufacturer's colors, patterns, textures" or a similar phrase, select a product (and manufacturer) that complies with other specified require-ments.

a. Standard Range: Where Specifications include the phrase "standard range of colors, patterns, textures" or similar phrase, Architect will select color, pattern, or texture from manufacturer's product line that does not include premium items.

b. Full Range: Where Specifications include the phrase "full range of col-ors, patterns, textures" or similar phrase, Architect will select color, pat-tern, or texture from manufacturer's product line that includes both standard and premium items.

2.2 PRODUCT SUBSTITUTIONS

A. Timing: Architect will consider requests for substitution if submitted in accordance with the Instructions to Bidders, and Specification 01 25 01 Pre-Bid Product Substi-tution Procedures prior to receipt of bids. Requests received after that time will not be considered.

2.3 COMPARABLE PRODUCTS

A. Where products or manufacturers are specified by name, submit the following, in addition to other required submittals, to obtain approval of an unnamed product. Architect will consider requests for the evaluation of comparable products when re-quests are submitted in accordance with the Instructions To Bidders, prior to date for receipt of bids:

Page 71: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

016000 - 6 PRODUCT REQUIREMENTS

1. Evidence that the proposed product does not require extensive revisions to the Contract Documents, that it is consistent with the Contract Documents and will produce the indicated results, and that it is compatible with other portions of the Work.

2. Detailed comparison of significant qualities of proposed product with those named in the Specifications. Significant qualities include attributes such as performance, weight, size, durability, visual effect, and specific features and requirements indicated.

3. Evidence that proposed product provides specified warranty. 4. List of similar installations for completed projects with project names and ad-

dresses and names and addresses of architects and owners, if requested. 5. Where specification sections indicate a product as a design standard and in-

clude model number, and/or product name and color of the product, include in the request a representative sample portion of the product with finish color matching the design standard.

6. Full sized samples, if requested. 7. The submission must clearly indicate that it is for a “Comparable Product.” 8. Incomplete “Comparable Product” submissions will not be considered.

PART 3 - EXECUTION (NOT USED)

END OF SECTION 01 60 00

Page 72: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

CUTTING AND PATCHING 017310 - 1

SECTION 017310 - CUTTING AND PATCHING

PART 1 - GENERAL

1.1 SUMMARY

A. This section includes procedural requirements for cutting and patching in existing work.

B. Definition: Cutting and patching includes cutting into existing construction to provide for the installation or performance of other work and subsequent fitting and repair required to restore surfaces to their original condition. Drilling holes for fasteners and similar operations are not "cutting and patching".

C. Refer to other sections for other requirements and limitations applicable to cutting and patching individual parts of the Work.

D. Coordinate cutting and patching with demolition requirements as specified in section 02 4119 Selective Demolition.

1.2 SUBMITTALS

A. Cutting and Patching Plan: In accordance with section 01 3300, submit a proposal, describing procedures at least 14 calendar days in advance of the time cutting and patching will initially be performed.

1. Include the following information, as applicable:

a. Description of the extent of cutting and patching required. Show how it will be performed and indicate why it cannot be avoided.

b. Description of the anticipated results in terms of changes to existing construction. Include changes to structural elements and operating components as well as changes in appearance and other significant visual elements.

c. List of products to be used and entities that will perform work.d. Dates and hours of operation when cutting and patching will be performed.e. List utilities that will be disturbed or otherwise be affected by work, including

those that will be relocated and those that will be out-of-service temporarily. Indicate how long utility service will be disrupted.

f. Compatibility and cohesion characteristics of patching compounds with adjacent materials.

g. Details and engineering calculations showing integration of reinforcement with the original structure, where cutting and patching involve adding reinforcement to structural elements.

h. Temporary protection of existing structures, surfaces, finishes, equipment, etc. to remain in place during construction.

Page 73: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason University

Project ID No. 247-A9247-015

017310 - 2 CUTTING AND PATCHING

B. Approval by GMU to proceed with cutting and patching does not waive the right to later require complete removal and replacement of unsatisfactory work.

C. Samples: Provide cutting and patching samples for the following items within 14 calendar days after notice to proceed in order that special reviews and coordination can be arranged with approval authorities

1.3 QUALITY CONTROL

A. Requirements for Structural Work: Do not cut and patch structural elements in a manner that would change their load-carrying capacity or load-deflection ratio.

1. The cutting and patching plan shall include but not be necessarily be limited to work required at the following structural elements:

a. Foundation construction.b. Bearing and retaining walls.c. Structural concrete.d. Structural steel.e. Lintels.f. Timber and primary wood framing.g. Structural decking.h. Stair systems.i. Miscellaneous structural metals.j. Exterior curtain-wall construction.k. Equipment supports.l. Piping, ductwork, vessels, and equipment.m. Structural systems of other construction.

B. Operational Limitations: Do not cut and patch operating elements, safety related systems, or related components in a manner that would result in reducing their capacity to perform as intended, or that would result in increased maintenance or decreased operational life or safety.

1. The cutting and patching plan shall include but not be limited to work required on the following operating elements or safety related systems:

a. Primary operational systems and equipment.b. Air or smoke barriers.c. Water, moisture, or vapor barriers.d. Membranes and flashings.e. Fire protection systems.f. Noise and vibration control elements and systems.g. Control systems.h. Communication systems.i. Conveying systems.j. Electrical wiring systems.k. Operating systems of other construction.l. Intrusion detection systems.m. Automated access control systems.

Page 74: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

CUTTING AND PATCHING 017310 - 3

n. Internet, data and telephone lines.

C. Visual Requirements: Do not cut and patch construction exposed on the exterior or in occupied spaces in a manner that would reduce the building's aesthetic qualities. Do not cut and patch construction in a manner that would result in visual evidence of cutting and patching. Remove and replace construction that is cut and patched in a visually unsatisfactorily manner.

1. Retain the original installer or fabricator to cut and patch exposed work if the original installer or fabricator is identified in the Contract Documents or is known to the Contractor and is available for the work.

2. If it is not possible to engage the original installer or fabricator, engage a Specialist who is specifically experienced in the work.

3. The cutting and patching plan shall include but not be limited to work required at the following visual elements:

a. Processed concrete finishes.b. Stonework and stone masonry.c. Ornamental metal.d. Matched-veneer woodwork.e. Preformed metal panels.f. Fire-stopping.g. Window wall system.h. Stucco and ornamental plaster.i. Acoustical ceilings.j. Finished wood flooring.k. Fluid-applied flooring.l. Carpeting.m. Aggregate wall coating.n. Wall covering.o. Mechanical system enclosures, cabinets, and covers.

1.4 EXISTING WARRANTIES

A. Replace, patch, and repair material and surfaces cut or damaged by methods and with materials in such a manner as not to void any existing warranties.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Use materials identical to existing materials to the maximum extent available.

B. For exposed surfaces, use materials that visually match existing adjacent surfaces to the fullest extent possible.

C. Use materials whose installed performance will equal or surpass that of existing materials.

Page 75: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason University

Project ID No. 247-A9247-015

017310 - 4 CUTTING AND PATCHING

PART 3 - EXECUTION

3.1 INSPECTION

A. Before cutting, examine surfaces to be cut and patched and conditions under which cutting and patching is to be performed. If unsafe or unsatisfactory conditions are encountered, take corrective action before proceeding.

B. Before proceeding with cutting and patching involving two or more trades, meet at the Project site with the entities providing or affected by the cutting and patching. Review areas of potential interference and conflict. Coordinate procedures and resolve potential conflicts before proceeding.

3.2 PREPARATION

A. Provide temporary support of work to be cut.

B. Protect existing conditions during cutting and patching to prevent damage. Provide protection from adverse weather conditions for portions of the Project that might be exposed during cutting and patching operations.

C. Avoid interference with use of adjoining areas or interruption of free passage to adjoining areas.

D. Bypass in-service existing pipe, conduit, or ductwork scheduled to be removed or relocated before cutting.

3.3 PERFORMANCE

A. Employ skilled workmen to perform cutting and patching. Proceed with cutting and patching at the earliest feasible time and complete without delay. Any adverse noise or odor producing work must be performed in accordance with Section 011000 Summary. Cutting: Cut existing construction using methods least likely to damage elements retained and adjoining construction. Where possible, review proposed procedures with the original installer and comply with the original installer's recommendations.

1. In general, use hand or small power tools designed for sawing or grinding, not for hammering and chopping.

2. Cut holes and slots as small as possible, neatly to size required, and with minimum disturbance of adjacent surfaces. Temporarily cover openings when not in use.

3. To avoid marring existing finished surfaces, cut or drill from the exposed or finished side into concealed surfaces.

4. Cut through concrete and masonry using silicon carbide or harder tipped tools. 5. Comply with requirements of applicable specification sections where cutting and

patching requires excavating and backfilling.6. After utility services are bypassed, cut-off pipe or conduit in walls or partitions to be

removed. Cap, valve or plug and seal the remaining portion of pipe or conduit to prevent entrance of moisture or other foreign matter after by-passing and cutting.

Page 76: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

CUTTING AND PATCHING 017310 - 5

B. Patching: Patch with durable seams that are as invisible as possible. Comply with specified tolerances.

1. Inspect and test patched areas to demonstrate integrity of the installation.2. Restore exposed finishes of patched areas and extend finish restoration into

adjoining construction in a manner that will eliminate evidence of patching and refinishing.

3. Where removed walls or partitions extends one finished area into another finished area, patch and repair floor and wall surfaces to provide an even surface of uniform color and appearance. Remove existing floor and wall coverings and replace with new materials, if necessary, to achieve uniform color and appearance.

4. Where patching occurs in a smooth painted surface, extend final paint coat over entire unbroken surface that contains the patch.

5. Patch, repair or re-hang existing ceilings as necessary to provide an even-plane surface of uniform appearance.

C. Perform cutting and patching work if listed in Division 1 "Summary - Work Restrictions" to be performed during Building Unoccupied Hours.

3.4 CLEANING

A. Clean areas and spaces where cutting and patching are performed. Completely remove all evidence of the Work.

B. Thoroughly clean piping, conduit, and similar features before applying paint, restored pipe coverings, or other finishing materials.

END OF SECTION 01 7310

Page 77: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

CLOSEOUT PROCEDURES 017700 - 1

SECTION 017700 - CLOSEOUT PROCEDURES

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes administrative and procedural requirements for contract closeout, including, but not limited to, the following:

1. Substantial Completion procedures. 2. Final completion procedures. 3. Warranties. 4. Final cleaning.

B. Related Sections: 1. Divisions 02 through 33 Sections for specific closeout and special cleaning

requirements for the Work in those Sections.

1.3 SUBSTANTIAL COMPLETION

A. Preliminary Procedures: Before requesting inspection for determining date of Substantial Completion, complete the following. List items below that are incomplete with request.

1. Prepare a list of items to be completed and corrected (punch list), the value of items on the list, and reasons why the Work is not complete.

2. Advise Owner of pending insurance changeover requirements. 3. Submit specific warranties, workmanship bonds, maintenance service

agreements, final certifications, and similar documents. 4. Obtain and submit releases permitting Owner unrestricted use of the Work and

access to services and utilities. Include occupancy permits, operating certificates, and similar releases.

5. Prepare and submit Project Record Documents, operation and maintenance manuals, final completion construction photographic documentation, damage or settlement surveys, property surveys, and similar final record information.

6. Deliver tools, spare parts, extra materials, and similar items to location designated by Owner. Label with manufacturer's name and model number where applicable.

7. Make final changeover of permanent locks and deliver keys to Owner. Advise Owner's personnel of changeover in security provisions.

8. Complete startup testing of systems. 9. Submit test/adjust/balance records. 10. Terminate and remove temporary facilities from Project site, along with mockups,

construction tools, and similar elements. 11. Submit changeover information related to Owner's occupancy, use, operation, and

maintenance. 12. Complete final cleaning requirements, including touchup painting.

Page 78: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

017700 - 2 CLOSEOUT PROCEDURES

13. Touch up and otherwise repair and restore marred exposed finishes to eliminate visual defects.

B. Inspection: Submit a written request for inspection for Substantial Completion. On receipt of request, Owner’s Representative will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare the Certificate of Substantial Completion after inspection or will notify Contractor of items, either on Contractor's list or additional items identified by Construction Manager, that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

2. Results of completed inspection will form the basis of requirements for final completion.

1.4 FINAL COMPLETION

A. Preliminary Procedures: Before requesting final inspection for determining final completion, complete the following:

1. Submit a final Application for Payment according to General Conditions. 2. Submit certified copy of Engineer’s and Owner’s Representative’s Substantial

Completion inspection list of items to be completed or corrected (punch list), endorsed and dated by Owner’s Representative. The certified copy of the list shall state that each item has been completed or otherwise resolved for acceptance.

3. Submit evidence of final, continuing insurance coverage complying with insurance requirements.

4. Submit pest-control final inspection report and warranty. 5. Instruct Owner's personnel in operation, adjustment, and maintenance of products,

equipment, and systems.

B. Inspection: Submit a written request for final inspection for acceptance. On receipt of request, Engineer will either proceed with inspection or notify Contractor of unfulfilled requirements. Engineer will prepare a final Certificate for Payment after inspection or will notify Contractor of construction that must be completed or corrected before certificate will be issued.

1. Reinspection: Request reinspection when the Work identified in previous inspections as incomplete is completed or corrected.

C. The General Contractor shall engage the services of a Virginia licensed land surveyor to locate and record all underground utilities installed as part of each contract. Survey shall show exact route of each utility invert or depth of cover and connection points to existing utilities. Identify, locate and dimension off of above-ground permanent improvements all manholes, catch basins, valve boxes or other structures.

1.5 LIST OF INCOMPLETE ITEMS (PUNCH LIST)

A. Organization of List: Include name and identification of each space and area affected by construction operations for incomplete items and items needing correction including, if necessary, areas disturbed by Contractor that are outside the limits of construction.

Page 79: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

CLOSEOUT PROCEDURES 017700 - 3

1. Organize list of spaces in sequential order. 2. Organize items applying to each space by major element. 3. Include the following information at the top of each page:

a. Project name. b. Date. c. Name of Engineer. d. Name of Contractor. e. Page number.

4. Submit list of incomplete items in the following format:

a. PDF electronic file. b. Three paper copies of product schedule or list, unless otherwise indicated.

Engineer will return two copies.

1.6 REPAIR OF THE WORK

A. A. Complete repair and restoration operations before requesting inspection for determination of Substantial Completion.

B. B. Repair, or remove and replace, defective construction.

1.7 WARRANTIES

A. Submittal Time: Submit written warranties on request of Owner for designated portions of the Work where commencement of warranties other than date of Substantial Completion is indicated.

B. On advice of Owner's legal counsel, revise first paragraph below to suit Project. Sometimes, extended warranties may be necessary.

C. Partial Occupancy: Submit properly executed warranties within 15 days of completion of designated portions of the Work that are completed and occupied or used by Owner during construction period by separate agreement with Contractor.

D. Organize warranty documents into an orderly sequence based on the table of contents of the Project Manual.

1. Bind warranties and bonds in heavy-duty, three-ring, vinyl-covered, loose-leaf binders, thickness as necessary to accommodate contents, and sized to receive 8-1/2-by-11-inch paper.

2. Provide heavy paper dividers with plastic-covered tabs for each separate warranty. Mark tab to identify the product or installation. Provide a typed description of the product or installation, including the name of the product and the name, address, and telephone number of Installer.

3. Identify each binder on the front and spine with the typed or printed title "WARRANTIES," Project name, and name of Contractor.

Page 80: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

017700 - 4 CLOSEOUT PROCEDURES

4. Scan warranties and bonds and assemble complete warranty and bond submittal package into a single indexed electronic PDF file with links enabling navigation to each item. Provide table of contents at beginning of document.

E. Provide additional copies of each warranty to include in operation and maintenance manuals.

PART 2 - PRODUCTS

2.1 MATERIALS

A. Cleaning Agents: Use cleaning materials and agents recommended by manufacturer or fabricator of the surface to be cleaned. Do not use cleaning agents that are potentially hazardous to health or property or that might damage finished surfaces.

1. Use cleaning products that meet Green Seal GS-37, or if GS-37 is not applicable, use products that comply with the California Code of Regulations maximum allowable VOC levels.

PART 3 - EXECUTION

3.1 FINAL CLEANING

A. General: Perform final cleaning. Conduct cleaning and waste-removal operations to comply with local laws and ordinances and Federal and local environmental and antipollution regulations.

B. Cleaning: Employ experienced workers or professional cleaners for final cleaning. Clean each surface or unit to condition expected in an average commercial building cleaning and maintenance program. Comply with manufacturer's written instructions.

1. Complete the following cleaning operations before requesting inspection for certification of Substantial Completion for entire Project or for a portion of Project:

a. Clean Project site, yard, and grounds, in areas disturbed by construction activities, including landscape development areas, of rubbish, waste material, litter, and other foreign substances.

b. Sweep paved areas broom clean. Remove petrochemical spills, stains, and other foreign deposits.

c. Rake grounds that are neither planted nor paved to a smooth, even-textured surface.

d. Remove tools, construction equipment, machinery, and surplus material from Project site.

e. Remove snow and ice to provide safe access to building. f. Clean exposed exterior hard-surfaced finishes to a dirt-free condition, free of

stains, films, and similar foreign substances. Avoid disturbing natural weathering of exterior surfaces. Restore reflective surfaces to their original condition.

g. Remove debris and surface dust from limited access spaces, including roofs, trenches, equipment vaults, manholes, and similar spaces.

h. Remove labels that are not permanent.

Page 81: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

CLOSEOUT PROCEDURES 017700 - 5

i. Touch up and otherwise repair and restore marred, exposed finishes and surfaces. Replace finishes and surfaces that cannot be satisfactorily repaired or restored or that already show evidence of repair or restoration.

1) Do not paint over "UL" and other required labels and identification, including mechanical and electrical nameplates.

2) Clean HVAC system in compliance with NADCA Standard 1992-01. Provide written report upon completion of cleaning.

j. Leave Project clean and ready for occupancy.

C. Pest Control: Engage an experienced, licensed exterminator to make a final inspection and rid Project of rodents, insects, and other pests. Prepare a report.

D. Construction Waste Disposal: Comply with waste disposal requirements in Division 01 Section "Temporary Facilities and Controls."

END OF SECTION 017700

Page 82: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

OPERATION AND MAINTENANCE DATA 017823 - 1

SECTION 017823 - OPERATION AND MAINTENANCE DATA

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for preparing operation and maintenance manuals, including the following:

1. Operation manuals. 2. Maintenance manuals.

1.3 SUBMITTALS

A. Initial Submittal: Submit 1 draft copy of each manual at least 15 days before requesting inspection for Substantial Completion. Include a complete operation and maintenance directory.

1. Final Submittal: Submit three copies of each manual in final form to Owner within 30 days of substantial completion.

1.4 COORDINATION

A. Where operation and maintenance documentation includes information on installations by more than one factory-authorized service representative, assemble and coordinate information furnished by representatives and prepare manuals.

PART 2 - PRODUCTS

2.1 MANUALS, GENERAL

A. Organization: Unless otherwise indicated, organize each manual into a separate section for each system and subsystem, and a separate section for each piece of equipment not part of a system. Each manual shall contain the following materials, in the order listed:

1. Title page. 2. Table of contents. 3. Manual contents.

B. Manual Contents: Organize into sets of manageable size. Arrange contents alphabetically by system, subsystem, and equipment. If possible, assemble instructions for subsystems, equipment, and components of one system into a single binder.

1. Binders: Heavy-duty, 3-ring, vinyl-covered, loose-leaf binders, in thickness necessary to accommodate contents, with clear plastic sleeve on spine to hold label describing contents and with pockets inside covers to hold folded oversize sheets.

Page 83: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

017823 - 2 OPERATION AND MAINTENANCE DATA

2. Dividers: Heavy-paper dividers with plastic-covered tabs for each section. 3. Protective Plastic Sleeves: Transparent plastic sleeves designed to enclose

diagnostic software diskettes for computerized electronic equipment. 4. Drawings: Attach reinforced, punched binder tabs on drawings and bind with text.

a. If oversize drawings are necessary, fold drawings to same size as text pages and use as foldouts.

b. If drawings are too large to be used as foldouts, fold and place drawings in labeled envelopes and bind envelopes in rear of manual. At appropriate locations in manual, insert typewritten pages indicating drawing titles, descriptions of contents, and drawing locations.

2.2 OPERATION MANUALS

A. Content: In addition to requirements in this Section, include operation data required in individual Specification Sections and the following information:

1. Equipment descriptions. 2. Performance and design criteria. 3. Operating standards. 4. Operating procedures. 5. Wiring diagrams. 6. Precautions against improper use. 7. License requirements including inspection and renewal dates.

2.3 SYSTEMS AND EQUIPMENT MAINTENANCE MANUAL

A. Content: For each piece of equipment, include source information, manufacturers' maintenance documentation, maintenance procedures, maintenance and service schedules, spare parts list and source information, maintenance service contracts, and warranty information.

PART 3 - EXECUTION – Not used.

END OF SECTION 017823

Page 84: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PROJECT RECORD DOCUMENTS 017839 - 1

SECTION 017839 - PROJECT RECORD DOCUMENTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for Project Record Documents, including the following:

1. Record Drawings. 2. Record Specifications.

PART 2 - PRODUCTS

2.1 RECORD DRAWINGS

A. Record Prints: Maintain and submit two sets of blue- or black-line white prints of the Contract Drawings and Shop Drawings.

1. Preparation: Mark Record Prints to show the actual installation where installation varies from that shown originally. Require individual or entity who obtained record data, whether individual or entity is Installer, subcontractor, or similar entity, to prepare the marked-up Record Prints.

a. Give particular attention to information on concealed elements that would be difficult to identify or measure and record later.

b. Accurately record information in an understandable drawing technique. c. Record data as soon as possible after obtaining it. Record and check the

markup before enclosing concealed installations.

2. Content: Types of items requiring marking include, but are not limited to, the following:

a. Dimensional changes to Drawings. b. Revisions to details shown on Drawings. c. Actual equipment locations. d. Changes made by Change Order or Directive. e. Details not on the original Contract Drawings. f. Field records for variable and concealed conditions. g. Record information on the Work that is shown only schematically.

3. Mark the Contract Drawings or Shop Drawings, whichever is most capable of showing actual physical conditions, completely and accurately. If Shop Drawings are marked, show cross-reference on the Contract Drawings.

4. Mark record sets with erasable, red-colored pencil. Use other colors to distinguish between changes for different categories of the Work at same location.

Page 85: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

017839 - 2 PROJECT RECORD DOCUMENTS

5. Mark important additional information that was either shown schematically or omitted from original Drawings.

6. Note Change Directive numbers, alternate numbers, Change Order numbers, and similar identification, where applicable.

B. Record CAD Drawings: Immediately before inspection for Certificate of Substantial Completion, review marked-up Record Prints with Architect. When authorized, prepare a full set of corrected CAD Drawings of the Contract Drawings, as follows:

1. Format: Same CAD program, version, and operating system as the original Contract Drawings.

2. Format: DWG, Version 2016 (or most current), operating in Microsoft Windows operating system.

3. Incorporate changes and additional information previously marked on Record Prints. Delete, redraw, and add details and notations where applicable.

4. Refer instances of uncertainty to Architect for resolution.

C. Format: Identify and date each Record Drawing; include the designation "PROJECT RECORD DRAWING" in a prominent location.

1. Record Prints: Organize Record Prints and newly prepared Record Drawings into manageable sets. Bind each set with durable paper cover sheets. Include identification on cover sheets.

2. Record CAD Drawings: Organize CAD information into separate electronic files that correspond to each sheet of the Contract Drawings. Name each file with the sheet identification. Include identification in each CAD file.

3. Identification: As follows:

a. Project name. b. Date. c. Designation "PROJECT RECORD DRAWINGS." d. Name of Architect. e. Name of Contractor.

2.2 RECORD SPECIFICATIONS

A. Preparation: Mark Specifications to indicate the actual product installation where installation varies from that indicated in Specifications, addenda, and contract modifications.

1. Give particular attention to information on concealed products and installations that cannot be readily identified and recorded later.

2. Mark copy with the proprietary name and model number of products, materials, and equipment furnished, including substitutions and product options selected.

3. Record the name of manufacturer, supplier, Installer, and other information necessary to provide a record of selections made.

4. For each principal product, indicate whether Record Product Data has been submitted in operation and maintenance manuals instead of submitted as Record Product Data.

5. Note related Change Orders, Record Product Data, and Record Drawings where applicable.

Page 86: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PROJECT RECORD DOCUMENTS 017839 - 3

2.3 MISCELLANEOUS RECORD SUBMITTALS

A. Assemble miscellaneous records required by other Specification Sections for miscellaneous record keeping and submittal in connection with actual performance of the Work. Bind or file miscellaneous records and identify each, ready for continued use and reference.

PART 3 - EXECUTION

3.1 RECORDING AND MAINTENANCE

A. Submit to Owner two sets of record prints, one set of mylar record (corrected) drawings, two sets of record specifications and an electronic version on CD’s of drawings & specifications.

END OF SECTION 017839

Page 87: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

DEMONSTRATION AND TRAINING 017900 - 1

SECTION 017900 - DEMONSTRATION AND TRAINING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. This Section includes administrative and procedural requirements for instructing Owner's personnel, including the following:

1. Demonstration of operation of systems, subsystems, and equipment. 2. Training in operation and maintenance of systems, subsystems, and equipment.

1.3 QUALITY ASSURANCE

A. Instructor Qualifications: A factory-authorized service representative, complying with requirements in Division 01 Section "Quality Requirements," experienced in operation and maintenance procedures and training.

1.4 COORDINATION

A. Coordinate instruction schedule with Owner's operations. Adjust schedule as required to minimize disrupting Owner's operations.

PART 2 - PRODUCTS

2.1 INSTRUCTION PROGRAM

A. Program Structure: Develop an instruction program that includes individual training modules for each system and equipment not part of a system, as required by individual Specification Sections.

B. Training Modules: Develop a learning objective and teaching outline for each module. Include a description of specific skills and knowledge that participant is expected to master. For each module, include instruction for the following:

1. Basis of System Design, Operational Requirements, and Criteria

2. Project Documentation including O&M Manuals, warranties and

maintenance/service agreements.

3. Instructions for operations.

4. Troubleshooting.

5. Maintenance and cleaning including routine and preventive maintenance.

6. Repairs including spare parts required.

PART 3 - EXECUTION

END OF SECTION 017900

Page 88: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SELECTIVE DEMOLITION 024119 - 1

SECTION 024119 - SELECTIVE DEMOLITION

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Analysis and protections required to accommodate safe selective demolition. 2. Demolition and removal of selected portions of building or structure. 3. Demolition and removal of selected site elements. 4. Salvage of existing items to be reused or recycled. 5. Coordinating all Work with phasing, sequencing, and existing conditions on the

project site and adjacent to the project site.

B. Related Requirements:

1. Section 01 1000 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements.

1.3 DEFINITIONS

A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.

B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to Owner ready for reuse.

C. Remove and Reinstall: Detach items from existing construction, in a manner to prevent damage, prepare for reuse, and reinstall where indicated.

D. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.

E. Dismantle: To remove by disassembling or detaching an item from a surface, using gentle methods and equipment to prevent damage to the item and surfaces; disposing of items unless indicated to be salvaged or reinstalled.

Page 89: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

024119 - 2 SELECTIVE DEMOLITION

1.4 MATERIALS OWNERSHIP

A. Unless otherwise indicated, demolition waste becomes property of Contractor.

1.5 PREINSTALLATION MEETINGS

A. Predemolition Conference: Conduct conference at Project site.

1. Inspect and discuss condition of construction to be selectively demolished. 2. Review structural load limitations of existing structure. 3. Review and finalize selective demolition schedule and verify availability of

materials, demolition personnel, equipment, and facilities needed to make progress and avoid delays.

4. Review requirements of work performed by other trades that rely on substrates exposed by selective demolition operations.

5. Review areas where existing construction is to remain and requires protection.

1.6 INFORMATIONAL SUBMITTALS

A. Proposed Protection Measures: Submit report, including Drawings, that indicates the measures proposed for protecting individuals and property, for environmental protection, for dust control and, for noise control. Indicate proposed locations and construction of barriers.

B. Schedule of Selective Demolition Activities: Indicate the following:

1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity. Ensure Owner's building manager's and other tenants' on-site operations are uninterrupted.

2. Coordination of Owner's continuing occupancy of portions of existing building and of Owner's partial occupancy of completed Work.

C. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.

1.7 FIELD CONDITIONS

A. Owner will occupy portions of building immediately adjacent to selective demolition area. Conduct selective demolition so Owner's operations will not be disrupted.

B. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical. Coordinate extent of items to be removed by the Owner prior to construction with the Owner.

C. Notify Architect of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

D. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.

Page 90: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SELECTIVE DEMOLITION 024119 - 3

1. If suspected hazardous materials are encountered, do not disturb; immediately notify Architect and Owner. Hazardous materials will be removed by Owner under a separate contract.

2. The Owner will make available hazardous material report available to the Contractor.

E. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 COORDINATION

A. Arrange selective demolition schedule so as not to interfere with Owner's operations.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.

B. Standards: Comply with ASSE A10.6 and NFPA 241.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Verify that affected utilities have been disconnected and capped before starting selective demolition operations.

B. Review Project Record Documents of existing construction or other existing condition and hazardous material information provided by Owner. Owner does not guarantee that existing conditions are same as those indicated in Project Record Documents.

3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS

A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.

Page 91: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

024119 - 4 SELECTIVE DEMOLITION

3.3 PROTECTION

A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.

1. Provide protection to ensure safe passage of people around selective demolition area and to and from occupied portions of building.

2. Provide temporary weather protection, during interval between selective demolition of existing construction on exterior surfaces and new construction, to prevent water leakage and damage to structure and interior areas.

3. Protect walls, ceilings, floors, facades, walkways, grounds, and other existing finish work and conditions that are to remain or that are exposed during selective demolition operations.

4. Comply with requirements of Section 015000 "Temporary Facilities and Controls."

B. Temporary Shoring: Design, engineer, provide, and maintain shoring, bracing, and structural supports as required to preserve stability and prevent movement, settlement, or collapse of construction and finishes to remain, and to prevent unexpected or uncontrolled movement or collapse of construction being demolished or installed.

1. Provide the complete services of a qualified professional structural engineer to analyze existing conditions, engineer all aspects of selective demolition, engineer all protection necessary, engineer all shoring and supports necessary, and monitor the construction activities related to selective demolition.

2. Strengthen or add new supports when required during progress of selective demolition. Engineer all strengthening and support measures.

3. Provide engineered protection required to protect all aspects of this project and all adjacent properties and structures.

4. Provide all measures necessary to protect and preserve all operations and the certificate of occupancy of the existing building throughout construction. Maintain continued safe and easily identifiable access to the existing building for public and staff.

5. A qualified structural engineer shall at a minimum be licensed as a structural engineer in the Commonwealth of Virginia and have successfully completed numerous similar projects of shoring buildings during selective demolition where continued partial occupancy of the building and protection of surrounding sites was included in the scope.

C. Please refer to Section 021500, Shoring and Bracing, for additional requirements.

D. Remove temporary barricades and protections where hazards no longer exist.

3.4 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

Page 92: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SELECTIVE DEMOLITION 024119 - 5

1. Proceed with selective demolition systematically, from higher to lower level. Complete selective demolition operations above each floor or tier before disturbing supporting members on the next lower level.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain portable fire-suppression devices during flame-cutting operations.

5. Maintain fire watch during and for at least 24 hours after flame-cutting operations. 6. Maintain adequate ventilation when using cutting torches. 7. Locate selective demolition equipment and remove debris and materials so as

not to impose excessive loads on supporting walls, floors, or framing.

B. Site Access and Temporary Controls: Conduct selective demolition and debris-removal operations to ensure minimum interference with roads, streets, walks, walkways, and other adjacent occupied and used facilities.

C. Removed and Reinstalled Items:

1. Clean and repair items to functional condition adequate for intended reuse. 2. Pack or crate items after cleaning and repairing. Identify contents of containers. 3. Protect items from damage during transport and storage. 4. Reinstall items in locations indicated. Comply with installation requirements for

new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional for use indicated.

D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Architect, items may be removed to a suitable, protected storage location during selective demolition and cleaned and reinstalled in their original locations after selective demolition operations are complete.

3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS

A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.

B. Concrete: Demolish in sections. Cut concrete full depth at junctures with construction to remain and at regular intervals using power-driven saw, and then remove concrete between saw cuts.

Page 93: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

024119 - 6 SELECTIVE DEMOLITION

C. Roofing: Remove no more existing roofing than what can be covered in one day by new roofing and so that building interior remains watertight and weathertight. See Section 075449, Polyvinyl-Chloride (PVC) Roofing for new roofing requirements.

1. Remove existing roof membrane or built-up roof system, flashings, copings, and roof accessories.

2. Remove existing roofing system down to substrate. 3. Do not remove more roofing than is indicated to be removed.

3.6 DISPOSAL OF DEMOLISHED MATERIALS

A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction and recycle or dispose of them. Refer to Section 028212, Asbestos Abatement, for additional demolition and disposal requirements.

1. Do not allow demolished materials to accumulate on-site. 2. Remove and transport debris in a manner that will prevent spillage on adjacent

surfaces and areas. 3. Remove debris from elevated portions of building by chute, hoist, or other device

that will convey debris to grade level in a controlled descent.

B. Burning: Do not burn demolished materials.

3.7 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 02 4119

Page 94: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

UNIT MASONRY 042000 - 1

SECTION 042000 - UNIT MASONRY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Repointing brick masonry. 2. Resealing control joints. 3. Cleaning masonry (at repair areas).

B. Related Requirements:

1. Section 079200 “Joint Sealants” for materials and installation requirements for resealing control joints.

1.3 DEFINITIONS

A. Low-Pressure Spray: 100 to 400 psi; 4 to 6 gpm.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site:

1. Review methods and procedures related to brick masonry repair including, but not limited to, the following:

a. Verify brick masonry repair specialist's personnel, equipment, and facilities needed to make progress and avoid delays.

b. Materials, material application, sequencing, tolerances, and required clearances.

c. Quality-control program. d. Coordination with building occupants.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

Page 95: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

042000 - 2 UNIT MASONRY

1. Include construction details, material descriptions, dimensions of individual components and profiles, and finishes.

2. Include recommendations for product application and use. 3. Include test data substantiating that products comply with requirements.

B. Samples for Initial Selection: For the following:

1. Colored Mortar: Submit sets of mortar that will be left exposed in the form of sample mortar strips, 6 inches long by 1/2 inch wide, set in aluminum or plastic channels.

a. Have each set contain a close color range of at least three Samples of different mixes of colored sands and cements that produce a mortar matching existing, cleaned mortar when cured and dry.

b. Submit with precise measurements on ingredients, proportions, gradations, and source of colored sands from which each Sample was made.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For mason including field supervisors and mechanics.

B. Quality-control program.

1.7 QUALITY ASSURANCE

A. Mason: Engage an experienced masonry repair firm to perform work of this Section. Firm shall have completed work similar in material, design, and extent to that indicated for this Project with a record of successful in-service performance. Experience in only installing masonry is insufficient experience for masonry repair work.

1. Field Supervision: Brick masonry repair specialist firm shall maintain experienced full-time supervisors on Project site during times that brick masonry repair work is in progress.

2. Brick Masonry Repair Mechanic Qualifications: Each mechanic proposed for use on the project must have 5-years demonstrated similar experience to that required for this project. Each mechanic also must cut out and prepare 10 linear feet of joint and repoint 10 linear feet of joint on site for review by the Architect. Only approved mechanics will be allow to perform the repointing work required for this project.

B. Mockups: Prepare mockups of brick masonry repair to demonstrate aesthetic effects and to set quality standards for materials and execution and for fabrication and installation. Location and size of mock-ups will be determined at the preconstruction conference. Intent is to perform mock-ups on penthouse wall where work can be easily observed and reviewed.

1. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Architect specifically approves such deviations in writing.

Page 96: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

UNIT MASONRY 042000 - 3

2. Mockups will be used to review and verify pointing mortar material selections. 3. Subject to compliance with requirements, approved mockups may become part

of the completed Work if undisturbed at time of Substantial Completion.

1.8 DELIVERY, STORAGE, AND HANDLING

A. Deliver packaged materials to Project site in manufacturer's original and unopened containers, labeled with manufacturer's name and type of products.

B. Store cementitious materials on elevated platforms, under cover, and in a dry location. Do not use cementitious materials that have become damp.

C. Store sand where grading and other required characteristics can be maintained and contamination avoided.

1.9 FIELD CONDITIONS

A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit brick masonry repair work to be performed according to product manufacturers' written instructions and specified requirements.

B. Temperature Limits: Repair brick masonry only when air temperature is between 40 and 90 deg F and is predicted to remain so for at least seven days after completion of the Work unless otherwise indicated.

C. Hot-Weather Requirements: Protect masonry repairs when temperature and humidity conditions produce excessive evaporation of water from mortar and repair materials. Provide artificial shade and wind breaks, and use cooled materials as required to minimize evaporation. Do not apply mortar to substrates with temperatures of 90 deg F (32 deg C) and above unless otherwise indicated.

PART 2 - PRODUCTS

2.1 MANUFACTURERS

A. Source Limitations for Masonry Units: Obtain exposed masonry units of a uniform texture and color, or a uniform blend within the ranges accepted for these characteristics, from single source from single manufacturer for each product required.

B. Source Limitations for Mortar Materials: Obtain mortar ingredients of a uniform quality, including color for exposed masonry, from single manufacturer for each cementitious component and from single source or producer for each aggregate.

Page 97: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

042000 - 4 UNIT MASONRY

2.2 UNIT MASONRY, GENERAL

A. Masonry Standard: Comply with TMS 602/ACI 530.1/ASCE 6, except as modified by requirements in the Contract Documents.

B. Defective Units: Referenced masonry unit standards may allow a certain percentage of units to contain chips, cracks, or other defects exceeding limits stated. Do not use units where such defects are exposed in the completed Work.

C. Fire-Resistance Ratings: Comply with requirements for fire-resistance-rated assembly designs indicated.

1. Where fire-resistance-rated construction is indicated, units shall be listed and labeled by a qualified testing agency acceptable to authorities having jurisdiction.

2.3 BRICK

A. Clay Face Brick: Facing brick complying with ASTM C216 or hollow brick complying with ASTM C652, Class H40V (void areas between 25 and 40 percent of gross cross-sectional area).

1. Grade: SW. 2. Type: FBX. 3. Unit Compressive Strength: Provide units with minimum average net-area

compressive strength of 3350 psi. 4. Initial Rate of Absorption: Less than 30 g/30 sq. in. per minute when tested

according to ASTM C67. 5. Efflorescence: Provide brick that has been tested according to ASTM C67 and is

rated "not effloresced." 6. Surface Coating: Brick with colors or textures produced by application of coatings

shall withstand 50 cycles of freezing and thawing according to ASTM C67 with no observable

7. Application: Use where brick is exposed unless otherwise indicated. 8. Provide face brick matching color range, texture, and size of existing adjacent

brickwork.

2.4 MORTAR AND GROUT MATERIALS

A. Portland Cement: ASTM C150/C150M, Type I or II, except Type III may be used for cold-weather construction. Provide natural color or white cement as required to produce mortar color indicated.

1. Alkali content shall not be more than 0.1 percent when tested according to ASTM C114.

B. Hydrated Lime: ASTM C207, Type S.

C. Portland Cement-Lime Mix: Packaged blend of portland cement and hydrated lime containing no other ingredients.

Page 98: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

UNIT MASONRY 042000 - 5

D. Mortar Pigments: Natural and synthetic iron oxides and chromium oxides, compounded for use in mortar mixes and complying with ASTM C979/C979M. Use only pigments with a record of satisfactory performance in masonry mortar.

E. Colored Cement Products: Packaged blend made from portland cement and hydrated lime and mortar pigments, all complying with specified requirements, and containing no other ingredients.

1. Colored Portland Cement-Lime Mix 2. Formulate blend as required to produce color indicated or, if not indicated, as

selected from manufacturer's standard colors. 3. Pigments shall not exceed 10 percent of portland cement by weight.

F. Aggregate for Mortar: ASTM C144.

1. For mortar that is exposed to view, use washed aggregate consisting of natural sand or crushed stone.

2. For joints less than 1/4 inch thick, use aggregate graded with 100 percent passing the No. 16 sieve.

3. White-Mortar Aggregates: Natural white sand or crushed white stone. 4. Colored-Mortar Aggregates: Natural sand or crushed stone of color necessary to

produce required mortar color.

G. Cold-Weather Admixture: Nonchloride, noncorrosive, accelerating admixture complying with ASTM C494/C494M, Type C, and recommended by manufacturer for use in masonry mortar of composition indicated.

H. Water-Repellent Admixture: Liquid water-repellent mortar admixture intended for use with CMUs containing integral water repellent from same manufacturer.

I. Water: Potable.

2.5 EMBEDDED FLASHING MATERIALS

A. Metal Flashing: Provide metal flashing complying with SMACNA's "Architectural Sheet Metal Manual" and as follows:

1. Stainless Steel: ASTM A240, Type 304, 0.018 inch thick.

2. Fabricate through-wall flashing with snaplock receiver on exterior face where indicated to receive counterflashing.

3. Solder corners.

B. Flexible Flashing: Use the following to strip the through-wall flashing to the back-up wall unless otherwise indicated:

1. Flexible Flashing: Composite, self-adhesive, flashing product consisting of a pliable, butyl rubber compound, bonded to a high-density stainless steel sheet to produce an overall thickness of not less than 0.040 inch.

Page 99: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

042000 - 6 UNIT MASONRY

a. Accessories: Provide preformed corners, end dams, other special shapes, and seaming materials produced by flashing manufacturer.

C. Solder and Sealants for Sheet Metal Flashings: As specified in Section 076200 "Sheet Metal Flashing and Trim."

D. Adhesives, Primers, and Seam Tapes for Flashings: Flashing manufacturer's standard products or products recommended by flashing manufacturer for bonding flashing sheets to each other and to substrates.

E. Termination Bars for Flexible Flashing: Stainless steel bars 1/8 inch by 1 inch.

2.6 MISCELLANEOUS MASONRY ACCESSORIES

A. Weep/Cavity Vent Products: Use the following unless otherwise indicated:

1. Cellular Plastic Weep/Vent: One-piece, flexible extrusion made from UV-resistant polypropylene copolymer, full height and width of head joint and depth 1/8 inch less than depth of outer wythe, in color selected from manufacturer's standard.

2.7 MASONRY CLEANERS

A. Proprietary Acidic Cleaner: Manufacturer's standard-strength cleaner designed for removing mortar/grout stains, efflorescence, and other new construction stains from new masonry without discoloring or damaging masonry surfaces. Use product expressly approved for intended use by cleaner manufacturer and manufacturer of masonry units being cleaned.

2.8 MORTAR AND GROUT MIXES

A. General: Do not use admixtures, including pigments, air-entraining agents, accelerators, retarders, water-repellent agents, antifreeze compounds, or other admixtures unless otherwise indicated.

1. Do not use calcium chloride in mortar or grout. 2. Use portland cement-lime mortar unless otherwise indicated. 3. Add cold-weather admixture (if used) at same rate for all mortar that will be

exposed to view, regardless of weather conditions, to ensure that mortar color is consistent.

B. Preblended, Dry Mortar Mix: Furnish dry mortar ingredients in form of a preblended mix. Measure quantities by weight to ensure accurate proportions, and thoroughly blend ingredients before delivering to Project site.

C. Mortar for Unit Masonry: Comply with ASTM C270, Proportion Specification. Provide the following types of mortar for applications stated unless another type is indicated.

Page 100: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

UNIT MASONRY 042000 - 7

1. For exterior, above-grade, load-bearing and nonload-bearing walls and parapet walls; for interior load-bearing walls; for interior nonload-bearing partitions; and for other applications where another type is not indicated, use Type N.

PART 3 - EXECUTION

3.1 PROTECTION

A. Prevent mortar from staining face of surrounding masonry and other surfaces.

1. Cover sills, ledges, and other projecting items to protect them from mortar droppings.

2. Keep wall area wet below rebuilding and repair work to discourage mortar from adhering.

3. Immediately remove mortar splatters in contact with exposed masonry and other surfaces.

B. Provide protection for building at set points for scaffolding and other equipment used to access the work area. Submit protection plan for review by Architect.

C. Provide plan and install materials for protection of occupants, vehicles and pedestrians at the project site for review by the Architect.

3.2 MASONRY REPAIR, GENERAL

A. Appearance Standard: Repaired surfaces are to have a uniform appearance as viewed from roof and surrounding grade as judged by the Architect.

3.3 SEAL CONTROL JOINTS

A. Cut away deteriorated and sound sealants from control joints to be resealed.

B. Clean joints and prime as determined by preconstruction testing.

C. Install backing material.

D. Install sealant and tool to a neat slightly concave joint profile.

E. Immediately remove any sealant that gets onto surrounding surfaces.

3.4 FLASHING, WEEP HOLES, AND CAVITY VENTS

A. General: Install embedded flashing and weep holes in masonry where indicated.

B. Install flashing as follows unless otherwise indicated:

Page 101: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

042000 - 8 UNIT MASONRY

1. Prepare masonry surfaces so they are smooth and free from projections that could puncture flashing. Where flashing is within mortar joint, place through-wall flashing on sloping bed of mortar and cover with mortar. Before covering with mortar, seal penetrations in flashing with adhesive, sealant, or tape as recommended by flashing manufacturer.

2. At masonry-veneer walls, extend flashing through veneer, across airspace behind veneer, and up face of back-up wall at least 4 inches; with upper edge stripped with flexible flashing membrane, lapping at least 4 inches onto through-wall flashing and extending up back-up wall minimum 4 inches. Fasten upper edge of flexible flashing to sheathing through termination bar.

C. Install weep holes in exterior wythes and veneers in head joints of first course of masonry immediately above embedded flashing.

1. Use specified weep/cavity vent products to form weep holes. 2. Space weep holes 24 inches o.c. unless otherwise indicated.

D. Place pea gravel in cavities as soon as practical to a height equal to height of first course above top of flashing, but not less than 2 inches, to maintain drainage.

3.5 REPOINTING MASONRY

A. Rake out and repoint mortar joints to the following extent:

1. All joints in areas indicated.

B. Do not rake out and repoint joints where not required.

C. Rake out joints as follows:

1. Remove mortar from joints to depth of 2-1/2 times joint width, but not less than 1/2 inch or not less than that required to expose sound, unweathered mortar.

2. Remove mortar from masonry surfaces within raked-out joints to provide reveals with square backs and to expose masonry for contact with pointing mortar. Brush, vacuum, or flush joints to remove dirt and loose debris.

3. Do not spall edges of masonry units or widen joints. Replace or patch damaged masonry units as directed by Engineer.

a. Do not use power-operated grinders without Engineer's written approval based on submission by Contractor of a satisfactory quality-control program and demonstrated ability of operators to use tools without damaging masonry. Quality-control program shall include provisions for supervising performance and preventing damage due to worker fatigue.

D. Notify Architect of unforeseen detrimental conditions including voids in mortar joints, cracks, loose masonry units, rotted wood, rusted metal, and other deteriorated items.

E. Point joints as follows:

Page 102: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

UNIT MASONRY 042000 - 9

1. Rinse masonry-joint surfaces with water to remove dust and mortar particles. Time rinsing application so, at time of pointing, joint surfaces are damp but free of standing water. If rinse water dries, dampen masonry-joint surfaces before pointing.

2. Apply pointing mortar first to areas where existing mortar was removed to depths greater than surrounding areas. Apply in layers not greater than 3/8 inch until a uniform depth is formed. Fully compact each layer thoroughly and allow it to become thumbprint hard before applying next layer.

3. After low areas have been filled to same depth as remaining joints, point all joints by placing mortar in layers not greater than 3/8 inch. Fully compact each layer and allow to partially cure before applying next layer. Where existing bricks have worn or rounded edges, slightly recess finished mortar surface below face of masonry to avoid widened joint faces. Take care not to spread mortar over edges onto exposed masonry surfaces or to featheredge mortar.

4. Tool joints to match original appearance of joints. Remove excess mortar from edge of joint by brushing.

F. Cure mortar by maintaining in thoroughly damp condition for at least 72 hours including weekends and holidays.

1. Acceptable curing methods include covering with wet burlap and plastic sheeting, periodic hand misting, and periodic mist spraying using system of pipes, mist heads, and timers.

2. Adjust curing methods to ensure that pointing mortar is damp throughout its depth without eroding surface mortar.

G. Where repointing work precedes cleaning of existing masonry, allow mortar to harden at least 30 days before beginning cleaning work.

3.6 GENERAL CLEANING

A. Proceed with cleaning in an orderly manner; work from top to bottom of each location. Perform cleaning in a manner that results in uniform coverage of all surfaces, including corners, moldings, and interstices, and that produces an even effect without streaking or damaging masonry surfaces.

B. Use only those cleaning methods that have been approved during the Mock-up process for each masonry material and location.

1. Do not use wire brushes. 2. Use spray equipment that provides controlled application at volume and pressure

indicated, measured at spray tip. Adjust pressure and volume to ensure that cleaning methods do not damage masonry.

a. Equip units with pressure gages.

3. For water spray application, use fan-shaped spray tip that disperses water at an angle of 25 to 50 degrees.

Page 103: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

042000 - 10 UNIT MASONRY

4. For water spray application, use only LOW PRESSURE (or lower) spray with fan-shaped spray tip that disperses water at an angle of at least 40 degrees.

5. Water Application Methods: Spray-apply water to surfaces to comply with requirements indicated for location, purpose, water temperature, pressure, volume, and equipment. Unless otherwise indicated, hold spray nozzle at least 6 inch from surface of stone and apply water from side to side in overlapping bands to produce uniform coverage and an even effect.

6. Detergent Cleaning – Use as required to augment basic water cleaning. Wet masonry with cold water applied by low-pressure spray. Scrub masonry with detergent solution using medium-soft brushes until soil is thoroughly dislodged and can be removed by rinsing. Use small brushes to remove soil from mortar joints and crevices. Dip brush in solution often to ensure that adequate fresh detergent is used and that masonry surface remains wet. Rinse with cold water applied by low-pressure spray to remove detergent solution and soil.

7. Repeat cleaning procedure above where required to produce cleaning effect established by mockup.

3.7 FINAL CLEANING

A. After mortar has fully hardened, thoroughly clean exposed masonry surfaces of excess mortar and foreign matter; use wood scrapers, stiff-nylon or -fiber brushes, and clean water applied by low-pressure spray.

1. Do not use metal scrapers or brushes. 2. Do not use acidic or alkaline cleaners.

B. Clean adjacent nonmasonry surfaces. Use detergent and soft brushes or cloths.

C. Clean mortar and debris from roof; remove debris from gutters and downspouts. Rinse off roof and flush gutters and downspouts.

D. Remove masking materials, leaving no residues that could trap dirt.

3.8 MASONRY WASTE DISPOSAL

A. Salvageable Materials: Unless otherwise indicated, excess masonry materials are Contractor's property. At completion of unit masonry work, remove from Project site.

B. Masonry Waste Recycling: Return broken CMUs not used as fill to manufacturer for recycling.

C. Excess Masonry Waste: Remove excess clean masonry waste that cannot be used as fill, as described above or recycled, and other masonry waste, and legally dispose of off Owner's property.

END OF SECTION 042000

Page 104: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PIPE AND TUBE RAILINGS 055213 - 1

SECTION 055213 - PIPE AND TUBE RAILINGS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Steel railing removal and reinstallation. 2. Ladder Modifications.

1.3 COORDINATION

A. Coordinate selection of field applied primers and topcoats to be applied over them. Comply with paint and coating manufacturers' written recommendations to ensure that shop primers and topcoats are compatible with one another.

B. Coordinate re-installation of anchorages for railings. Field mark all elements to ensure reinstallation of each is at original existing locations. Weld existing railing back to existing embedded.

C. Provide all required temporary protections for safety when railings are not in place.

1.4 ACTION SUBMITTALS

A. Product Data: For the following:

1. Paint products.

B. Shop Drawings: Include plans and connection details, and attachments to other work.

1.5 INFORMATIONAL SUBMITTALS

A. Welding certificates.

1.6 QUALITY ASSURANCE

A. Welding Qualifications: Qualify procedures and personnel according to the following:

Page 105: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

055213 - 2 PIPE AND TUBE RAILINGS

1. AWS D1.1/D1.1M, "Structural Welding Code - Steel."

1.7 DELIVERY, STORAGE, AND HANDLING

A. Protect mechanical finishes on exposed surfaces from damage by applying a strippable, temporary protective covering before shipping.

1.8 FIELD CONDITIONS

A. Field Measurements: Verify location of cuts in field as required to allow for railing to be welded to existing posts after all roofing and sheet metal materials have been installed.

PART 2 - PRODUCTS

2.1 GENERAL REQUIREMENTS

A. Welding Rods and Bare Electrodes: Select according to AWS specifications for metal alloy welded.

B. Epoxy Zinc-Rich Primer: Complying with MPI#20 and compatible with topcoat.

C. Epoxy Intermediate Coat: Complying with MPI #77 and compatible with primer and topcoat.

D. Polyurethane Topcoat: Complying with MPI #72 and compatible with undercoat. Color as selected by Architect from manufacturer standard color chart. Intent is to match existing rail finish.

2.2 FABRICATION

A. Cut existing posts cleanly and accurately. Remove burrs and ease edges to a radius of approximately 1/32 inch unless otherwise indicated. Remove sharp or rough areas on exposed surfaces.

B. Form work true to line and level with accurate angles and surfaces.

C. Fabricate connections that are exposed to weather in a manner that excludes water.

D. Connections: Reinstall existing railings with welded connections to existing embedded posts.

E. Welded Connections: Cope components at connections to provide close fit, or use fittings designed for this purpose. Weld all around at connections, including at fittings.

1. Use materials and methods that minimize distortion and develop strength and corrosion resistance of base metals.

2. Obtain fusion without undercut or overlap.

Page 106: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PIPE AND TUBE RAILINGS 055213 - 3

3. Remove flux immediately. 4. At exposed connections, grind and finish exposed surfaces smooth and blended

so no roughness shows after finishing and welded surface matches contours of adjoining surfaces.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Fit exposed connections together to form tight, hairline joints.

B. Adjust railings and ladder components before welding to ensure matching alignment at abutting joints.

3.2 CONNECTIONS

A. Welded Connections: Use fully welded joints for permanently connecting railing components. Comply with requirements for welded connections in "Fabrication" Article whether welding is performed in the shop or in the field.

3.3 STEEL FINISHES

A. Primer Application: Apply primer to prepared surfaces of railings unless otherwise indicated. Comply with requirements in SSPC-PA 1, "Shop, Field, and Maintenance Painting of Steel," for shop painting.

1. Prime areas of railings to be painted with zinc-rich primer.

B. High-Performance Coating: Apply epoxy intermediate and polyurethane topcoats to prime-coated surfaces. Comply with coating manufacturer's written instructions and with requirements in SSPC-PA 1, "Shop, Field, and Maintenance Painting of Steel," for shop painting. Apply at spreading rates recommended by coating manufacturer.

1. Blend finish paint with existing painted finishes.

3.4 PROTECTION

A. Protect finishes of railings from damage during construction period with temporary protective coverings approved by railing manufacturer. Remove protective coverings at time of Substantial Completion.

END OF SECTION 055213

Page 107: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

ROUGH CARPENTRY 061000 - 1

SECTION 061000 - ROUGH CARPENTRY

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Wood blocking and nailers.

1.3 DEFINITIONS

A. Boards or Strips: Lumber of less than 2 inches nominal size in least dimension.

B. Dimension Lumber: Lumber of 2 inches nominal size or greater but less than 5 inches nominal size in least dimension.

1.4 ACTION SUBMITTALS

A. Product Data: For each type of process and factory-fabricated product. Indicate component materials and dimensions and include construction and application details.

1. Include data for wood-preservative treatment from chemical treatment manufacturer and certification by treating plant that treated materials comply with requirements. Indicate type of preservative used and net amount of preservative retained.

2. For products receiving a waterborne treatment, include statement that moisture content of treated materials was reduced to levels specified before shipment to Project site.

1.5 INFORMATIONAL SUBMITTALS

A. Material Certificates: For dimension lumber specified to comply with minimum allowable unit stresses. Indicate species and grade selected for each use and design values approved by the ALSC Board of Review.

B. Evaluation Reports: For the following, from ICC-ES:

1. Wood-preservative-treated wood.

Page 108: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

061000 - 2 ROUGH CARPENTRY

1.6 QUALITY ASSURANCE

A. Testing Agency Qualifications: For testing agency providing classification marking for fire-retardant treated material, an inspection agency acceptable to authorities having jurisdiction that periodically performs inspections to verify that the material bearing the classification marking is representative of the material tested.

1.7 DELIVERY, STORAGE, AND HANDLING

A. Stack wood products flat with spacers beneath and between each bundle to provide air circulation. Protect wood products from weather by covering with waterproof sheeting, securely anchored. Provide for air circulation around stacks and under coverings.

PART 2 - PRODUCTS

2.1 WOOD PRODUCTS, GENERAL

A. Lumber: DOC PS 20 and applicable rules of grading agencies indicated. If no grading agency is indicated, comply with the applicable rules of any rules-writing agency certified by the ALSC Board of Review. Grade lumber by an agency certified by the ALSC Board of Review to inspect and grade lumber under the rules indicated.

1. Factory mark each piece of lumber with grade stamp of grading agency.

B. Maximum Moisture Content of Lumber: 19 percent unless otherwise indicated.

2.2 WOOD-PRESERVATIVE-TREATED LUMBER

A. Preservative Treatment by Pressure Process: AWPA U1; Use Category, Use Category UC3b for exterior construction not in contact with ground.

1. Preservative Chemicals: Acceptable to authorities having jurisdiction and containing no arsenic or chromium. Do not use inorganic boron (SBX) for sill plates.

B. Kiln-dry lumber after treatment to a maximum moisture content of 19 percent. Do not use material that is warped or that does not comply with requirements for untreated material.

C. Mark lumber with treatment quality mark of an inspection agency approved by the ALSC Board of Review.

1. For exposed lumber indicated to receive a stained or natural finish, mark end or back of each piece.

D. Application: Treat all rough carpentry unless otherwise indicated.

Page 109: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

ROUGH CARPENTRY 061000 - 3

2.3 MISCELLANEOUS LUMBER

A. General: Provide miscellaneous lumber indicated and lumber for support or attachment of other construction, including the following:

1. Blocking. 2. Nailers.

B. Dimension Lumber Items: Construction or No. 2 grade lumber of the following species:

1. Mixed southern pine or southern pine; SPIB.

C. For blocking and nailers used for attachment of other construction, select and cut lumber to eliminate knots and other defects that will interfere with attachment of other work.

2.4 FASTENERS

A. General: Fasteners shall be of size and type indicated and shall comply with requirements specified in this article for material and manufacture.

1. Where rough carpentry is pressure-preservative treated or in area of high relative humidity, provide fasteners of Type 304 stainless steel.

B. Nails, Brads, and Staples: ASTM F1667.

C. Power-Driven Fasteners: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC70.

D. Post-Installed Anchors: Fastener systems with an evaluation report acceptable to authorities having jurisdiction, based on ICC-ES AC193 as appropriate for the substrate.

1. Material: Stainless steel with bolts and nuts complying with ASTM F593 and ASTM F594, Alloy Group 1 or 2.

PART 3 - EXECUTION

3.1 INSTALLATION, GENERAL

A. Framing Standard: Comply with AF&PA's WCD 1, "Details for Conventional Wood Frame Construction," unless otherwise indicated.

B. Set rough carpentry to required levels and lines, with members plumb, true to line, cut, and fitted. Fit rough carpentry accurately to other construction. Locate nailers, blocking, and similar supports to comply with requirements for attaching other construction.

Page 110: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

061000 - 4 ROUGH CARPENTRY

C. Provide blocking and framing as indicated and as required to match thickness of adjacent insulation or as indicated on the Drawing.

D. Sort and select lumber so that natural characteristics do not interfere with installation or with fastening other materials to lumber. Do not use materials with defects that interfere with function of member or pieces that are too small to use with minimum number of joints or optimum joint arrangement.

E. Comply with AWPA M4 for applying field treatment to cut surfaces of preservative-treated lumber.

1. Use inorganic boron for items that are continuously protected from liquid water. 2. Use copper naphthenate for items not continuously protected from liquid water.

F. Securely attach rough carpentry work to substrate by anchoring and fastening as indicated, and to comply with the following, whichever is more stringent:

1. Table 2304.10.1 "Fastening Schedule," in the Virginia Construction Code (VCC).

G. Use stainless steel common nails unless otherwise indicated. Select fasteners of size that will not fully penetrate members where opposite side will be exposed to view or will receive finish materials. Make tight connections between members. Install fasteners without splitting wood. Drive nails snug but do not countersink nail heads unless otherwise indicated.

3.2 WOOD BLOCKING, AND NAILER INSTALLATION

A. Install where indicated and where required for attaching other work. Form to shapes indicated and cut as required for true line and level of attached work. Coordinate locations with other work involved.

B. Attach items to substrates to support applied loading. Recess bolts and nuts flush with surfaces unless otherwise indicated.

3.3 PROTECTION

A. Protect wood that has been treated with inorganic boron (SBX) from weather. If, despite protection, inorganic boron-treated wood becomes wet, apply EPA-registered borate treatment. Apply borate solution by spraying to comply with EPA-registered label.

B. Protect rough carpentry from weather. If, despite protection, rough carpentry becomes wet, apply EPA-registered borate treatment. Apply borate solution by spraying to comply with EPA-registered label.

END OF SECTION 061000

Page 111: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PREPARATION FOR ROOF REPLACEMENT 070150 - 1

SECTION 070150 - PREPARATION FOR ROOF REPLACEMENT

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Roof tear-off. 2. Removal of base flashings. 3. Removal of sheet metal flashing

B. Related Sections:

1. Division 06 Section "Rough Carpentry". 2. Division 07 Section “Sheet Metal Flashing and Trim”. 3. Division 07 Section “Built-Up Asphalt Roofing”.

1.3 MATERIALS OWNERSHIP

A. Except for items or materials indicated to be reused, reinstalled, or otherwise indicated to remain Owner's property, demolished materials shall become Contractor's property and shall be removed from Project site. Contractor shall remove from roof to street (staging area) those materials that are owner owned and not being reused.

1.4 DEFINITIONS

A. Roofing Terminology: Refer to ASTM D 1079 and glossary in NRCA's "The NRCA Roofing and Waterproofing Manual" for definition of terms related to roofing work in this Section.

B. Existing Membrane Roofing System: Single-ply EPDM roofing membrane and flashing, roof insulation, gravel ballast, precast concrete paver ballast, and components and accessories between deck and ballast surfacing.

C. Roof Tear-Off: Removal of existing membrane roofing system from deck.

D. Remove: Detach items from existing construction and legally dispose of them off-site unless indicated to be removed and reinstalled.

Page 112: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

070150 - 2 PREPARATION FOR ROOF REPLACEMENT

E. Existing to Remain: Existing items of construction that are not indicated to be removed.

1.5 SUBMITTALS

A. Photographs or Videotape: Show existing conditions of adjoining construction and site improvements, including exterior and interior finish surfaces, that might be misconstrued as having been damaged by reroofing operations. Submit before Work begins.

1.6 QUALITY ASSURANCE

A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning membrane roofing removal. Comply with hauling and disposal regulations of authorities having jurisdiction.

1.7 PROJECT CONDITIONS

A. Owner will occupy portions of building immediately below reroofing area. Conduct reroofing so Owner's operations will not be disrupted. Provide Owner with not less than 72 hours notice of activities that may affect Owner's operations.

1. Coordinate work activities daily with Owner so Contractor can place protective dust or water leakage covers over sensitive equipment or furnishings. Owner to shut down HVAC and fire-alarm or -detection equipment if needed, and evacuate occupants from below the work area.

2. Before working over structurally impaired areas of deck, notify Owner to evacuate occupants from below the affected area. Verify that occupants below the work area have been evacuated before proceeding with work over the impaired deck area.

B. Protect building to be reroofed, adjacent buildings, walkways, site improvements, exterior plantings, and landscaping from damage or soiling from reroofing operations.

C. Maintain access to existing walkways, corridors, and other adjacent occupied or used facilities.

D. Notify Engineer of discrepancies between existing conditions and Drawings before proceeding with selective demolition.

E. Limit construction loads on roof and rooftop equipment wheel loads according to limitations listed on Drawings.

F. Weather Limitations: Proceed with reroofing preparation only when existing and forecasted weather conditions permit Work to proceed without water entering existing roofing system or building.

Page 113: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PREPARATION FOR ROOF REPLACEMENT 070150 - 3

G. Hazardous Materials: It is not expected that hazardous materials such as asbestos-containing materials will be encountered in the Work.

1. If materials suspected of containing hazardous materials are encountered, do not disturb; immediately notify Engineer and Owner. Hazardous materials will be removed by Owner under a separate contract.

H. Storage or sale of removed items or materials on-site is not permitted.

I. Utility Service: Maintain existing utilities indicated to remain in service and protect them against damage during selective demolition operations.

1. Maintain fire-protection facilities in service during selective demolition operations.

1.8 WARRANTY

A. Existing Warranties: Remove, replace, patch, and repair materials and surfaces cut or damaged during selective demolition, by methods and with materials so as not to void existing warranties.

PART 2 - PRODUCTS (NOT USED)

PART 3 - EXECUTION

3.1 SELECTIVE DEMOLITION, GENERAL

A. General: Demolish and remove existing construction only to the extent required by new construction and as indicated. Use methods required to complete the Work within limitations of governing regulations and as follows:

1. Proceed with selective demolition systematically, from roof high point to low point.

2. Neatly cut openings and holes plumb, square, and true to dimensions required. Use cutting methods least likely to damage construction to remain or adjoining construction. Use hand tools or small power tools designed for sawing or grinding, not hammering and chopping, to minimize disturbance of adjacent surfaces. Temporarily cover openings to remain.

3. Cut or drill from the exposed or finished side into concealed surfaces to avoid marring existing finished surfaces.

4. Do not use cutting torches until work area is cleared of flammable materials. At concealed spaces, such as duct and pipe interiors, verify condition and contents of hidden space before starting flame-cutting operations. Maintain fire watch and portable fire-suppression devices during flame-cutting operations.

5. Maintain adequate ventilation when using cutting torches. 6. Remove decayed, vermin-infested, or otherwise dangerous or unsuitable

materials and promptly dispose of off-site.

Page 114: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

070150 - 4 PREPARATION FOR ROOF REPLACEMENT

7. Remove structural framing members and lower to ground by method suitable to avoid free fall and to prevent ground impact or dust generation.

8. Locate selective demolition equipment and remove debris and materials so as not to impose excessive loads on supporting walls, floors, or framing.

9. Dispose of demolished items and materials promptly.

3.2 PREPARATION

A. Coordinate with Owner before proceeding with reroofing work that could affect indoor air quality or activate smoke detectors in the ductwork and all other safety systems.

B. When unanticipated mechanical, electrical, or structural elements that conflict with intended function or design are encountered, investigate and measure the nature and extent of conflict. Promptly submit a written report to Engineer.

C. During removal operations, have sufficient and suitable materials on-site to facilitate rapid installation of temporary protection in the event of unexpected rain. Maintain a watertight roof system at the end of each working day. At no time should the roof be left unwaterproofed at the end of a work day.

D. Proceed with the tear-off and installation of roofing only when existing and forecasted weather conditions will permit work to be performed in accordance with this specification, manufacturer's specification and warranty requirements, and will not subject the occupied spaces below to water damage.

E. Prior to any demolition, water test all roof drains and storm drain lines with a 3/4 inch diameter garden hose flowing at maximum capacity, about 5 gallons per minute. Report all blockages to the Owner and Engineer immediately. All blocked drains and storm drain lines discovered after demolition has begun, will be cleaned out and made free draining (> 5 gallons per minute) at no cost to the Owner.

F. All mechanical equipment, utility and service piping should be protected before beginning work.

G. Maintain roof drains in functioning condition to ensure roof drainage at end of each workday. Prevent debris from entering or blocking roof drains and conductors. Use roof-drain plugs specifically designed for this purpose. Remove roof-drain plugs at end of each workday, when no work is taking place, or when rain is forecast. All utility and service piping should be protected before beginning work.

1. If roof drains are temporarily blocked or unserviceable due to roofing system removal or partial installation of new membrane roofing system, provide alternative drainage method to remove water and eliminate ponding. Do not permit water to enter into or under existing membrane roofing system components that are to remain.

H. Verify that rooftop utilities and service piping have been shut off before beginning the Work.

Page 115: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PREPARATION FOR ROOF REPLACEMENT 070150 - 5

3.3 ROOF TEAR-OFF

A. General: Notify Owner each day of extent of roof tear-off proposed for that day.

B. Remove aggregate ballast from surface and dispose of. Do not overload building and existing structural components. Do not store ballast and other materials at a single location for concern of roof load. Review and adhere to load limitations.

C. Remove pavers and accessories from roofing membrane. Store and protect pavers and accessories for reuse. Review paver conditions with Owner and establish protocol for what constitutes a damaged paver. Remove and dispose of damaged pavers. Review and adhere to load limitations.

D. Remove extruded-polystyrene insulation.

E. Roof Tear-Off: Remove existing roofing membrane and other membrane roofing system components down to the deck.

1. Remove filter fabric. 2. Remove base flashings. 3. Remove metal counterflashings and trim. Protect existing counterflashing

components indicated for reuse (reglets, through-wall flashing, etc.). 4. Cut existing through-wall flashing to provide 1-inch flange extending out from

parapet wall. Turn flange up at interior face of parapet.

F. LIGHTNING PROTECTION SYSTEM

1. Do not damage existing lightning protection system. 2. Provide temporary protection for all lightning protection elements. 3. Support in place during construction and re-anchor to new coping at completion

of roof replacement work. 4. Support lighting protection cables in place during constriction. Anchor to new

counterflashing at completion of roof replacement work.

G. Remove existing threshold at all roof access doors to allow for roofing system installation. Reset at completion of roof replacement work.

H. Determine finish elevation of new roofing system at base of West Penthouse Roof access ladder. Cut base of ladder off minimum 12-inches above finished roof surface. Relocate anchor points as required. Weld anchor points to side rails with 5/16-inch fillet welds, all around. Anchor ladder to wall with epoxy sleeve anchors.

I. Remove camera and related electrical equipment at north corner of the 4th Floor Roof – South Side. Remount to parapet wall at completion of roof replacement work

3.4 DECK PREPARATION

A. Inspect deck after tear-off of membrane roofing system.

B. Verify that concrete substrate is visibly dry and free of moisture. Test for capillary moisture by plastic sheet method according to ASTM D 4263 following tear off and

Page 116: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

070150 - 6 PREPARATION FOR ROOF REPLACEMENT

prior to membrane application each day and at start of each day's work and at start of each roof area or plane. Do not proceed with roofing work if moisture condenses under the plastic sheet.

C. If deck surface is not suitable for receiving new roofing or if structural integrity of deck is suspect, immediately notify Owner. Do not proceed with installation until directed by Owner.

D. Repair concrete deck as required to provide proper surface for membrane.

3.5 EXISTING BASE FLASHINGS

A. Remove existing base flashings around parapets, curbs, walls, and penetrations.

1. Clean substrates of contaminants such as asphalt, sheet materials, dirt, and debris.

B. Do not damage metal counterflashings that are to remain. Replace metal counterflashings and components damaged during removal that is indicated to remain or be reused with counterflashings specified in Division 07 Section "Sheet Metal Flashing and Trim."

C. Inspect wall and deck surfaces for deterioration and damage. Immediately notify Owner of any observed deterioration or damage.

3.6 BRICK MASONRY

A. At location indicated on the Drawing remove first courses of brick masonry to trim existing through-wall flashing and insert new expansion joint cover.

B. Temporarily support upper courses of brick masonry to remain in place during work

3.7 DISPOSAL

A. Collect demolished materials and place in containers. Promptly dispose of demolished materials. Do not allow demolished materials to accumulate on-site.

1. Storage or sale of demolished items or materials on-site is not permitted.

B. Transport and legally dispose of demolished materials off Owner's property.

3.8 CLEANING

A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.

END OF SECTION 070150

Page 117: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 1

SECTION 075113 - BUILT-UP ASPHALT ROOFING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

B. DGS-30-326 “Special Requirements for Low Slope Roofing Membrane”.

1.2 SUMMARY

A. Section Includes:

1. Built-up asphalt roofing. 2. Vapor retarder. 3. Roof insulation. 4. Cover board.

B. Related Requirements:

1. Section 061000 "Rough Carpentry" for wood nailers, curbs, and blocking. 2. Section 076200 "Sheet Metal Flashing and Trim" for metal roof flashings and

counterflashings.

1.3 DEFINITIONS

A. Roofing Terminology: Definitions in ASTM D1079 and glossary of NRCA's "The NRCA Roofing Manual: Membrane Roof Systems" apply to Work of this Section.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Roofing Conference: Conduct conference at Project site.

1. Meet with Owner, Architect, Owner's insurer if applicable, testing and inspecting agency representative, roofing Installer, roofing system manufacturer's representative, deck Installer, air barrier Installer, and installers whose work interfaces with or affects roofing, including installers of roof accessories and roof-mounted equipment.

2. Review methods and procedures related to roofing installation, including manufacturer's written instructions.

Page 118: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 2 BUILT-UP ASPHALT ROOFING

3. Review and finalize construction schedule, and verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

4. Examine deck substrate conditions and finishes for compliance with requirements, including flatness and fastening.

5. Review structural loading limitations of roof deck during and after roofing. 6. Review base flashings, special roofing details, roof drainage, roof penetrations,

equipment curbs, and condition of other construction that affects roofing. 7. Review governing regulations and requirements for insurance and certificates if

applicable. 8. Review temporary protection requirements for roofing system during and after

installation. 9. Review roof observation and repair procedures after roofing installation.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

1. For insulation and roof system component fasteners, include copy of FM Approvals' RoofNav listing.

B. Shop Drawings: Include plans, sections, details, and attachments to other work, including the following:

1. Layout and thickness of insulation. 2. Base flashings and roofing terminations. 3. Flashing details at penetrations. 4. Tapered insulation, including slopes. 5. Crickets, saddles, and tapered edge strips, including slopes. 6. Insulation-fastening patterns for corner, perimeter, and field-of-roof locations.

C. Samples for Verification: For the following products:

1. Cap Sheet: Samples of manufacturer's standard colors for selection by Architect. 2. Flashing Sheet: Samples of manufacturer's standard colors for selection by

Architect.

D. Wind Uplift Resistance Submittal: For roofing system indicating compliance with wind uplift performance requirements.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer, manufacturer and testing agency.

B. Manufacturer Certificates:

1. Performance Requirement Certificate: Signed by roof membrane manufacturer, certifying that roofing system complies with requirements specified in "Performance Requirements" Article.

Page 119: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 3

a. Submit evidence of compliance with performance requirements.

2. Special Warranty Certificate: Signed by roof membrane manufacturer, certifying that all materials supplied under this Section are acceptable for special warranty.

C. Product Test Reports: For roof insulation, tests performed by a qualified testing agency, indicating compliance with specified requirements.

D. Evaluation Reports: For components of roofing system, from ICC-ES.

E. Field Test Reports:

1. Fastener-pullout test results and manufacturer's revised requirements for fastener patterns.

F. Field quality-control reports.

G. Sample Warranties: For manufacturer's special warranties.

1.7 CLOSEOUT SUBMITTALS

A. Maintenance Data: For roofing system to include in maintenance manuals.

B. Certified statement from existing roof membrane manufacturer, stating that existing roof warranty has not been affected by Work performed under this Section.

1.8 QUALITY ASSURANCE

A. Manufacturer Qualifications: A qualified manufacturer that is listed in FM Approvals' RoofNav for roofing system identical to that used for this Project.

B. Installer Qualifications: A qualified firm that is approved, authorized, or licensed by roofing system manufacturer to install manufacturer's product and that is eligible to receive manufacturer's special warranty.

C. The Owner shall have a full-time inspector on site while the roof is being applied.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Deliver roofing materials to Project site in original containers with seals unbroken and labeled with manufacturer's name, product brand name and type, date of manufacture, approval or listing agency markings, and directions for storing and mixing with other components.

B. Store liquid materials in their original undamaged containers in a clean, dry, protected location and within the temperature range required by roofing manufacturer.

1. Protect stored liquid material from direct sunlight.

Page 120: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 4 BUILT-UP ASPHALT ROOFING

2. Discard and legally dispose of liquid material that cannot be applied within its stated shelf life.

C. Protect roof insulation materials from physical damage and from deterioration by sunlight, moisture, soiling, and other sources.

1. Store in a dry location. 2. Comply with insulation manufacturer's written instructions for handling, storing,

and protecting during installation. 3. Deliver insulation in packages and containers bearing label of an approved

agency showing the manufacturers name, product listing, product identification and information sufficient to determine that the end use will comply with code requirements.

D. Handle and store roofing materials, and place equipment in a manner to avoid permanent deflection of deck.

1.10 FIELD CONDITIONS

A. Weather Limitations: Proceed with installation only when existing and forecasted weather conditions permit roofing to be installed according to manufacturer's written instructions and warranty requirements.

1.11 WARRANTY

A. Special Warranty: Manufacturer agrees to repair or replace components of roofing system that fail in materials or workmanship within specified warranty period.

1. Special warranty includes roofing membrane, base flashings, roof insulation, fasteners, cover boards, vapor retarder, and other components of roofing system.

2. Warranty Period: 20 years from date of Substantial Completion.

B. Special Project Warranty: Submit roofing Installer's warranty, on Installer’s standard warranty form, signed by Installer, covering the Work of this Section, including all components of roofing system, such as roofing membrane, base flashing, roof insulation, fasteners, cover boards, and vapor retarders for the following warranty period:

1. Warranty Period: Two years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. General Performance: Installed roofing system and flashings shall withstand specified uplift pressures, thermally induced movement, and exposure to weather without failure

Page 121: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 5

due to defective manufacture, fabrication, installation, or other defects in construction. Roof system and flashings shall remain watertight.

1. Accelerated Weathering: Roof membrane shall withstand 2000 hours of exposure when tested according to ASTM G152, ASTM G154, or ASTM G155.

2. Impact Resistance: Roof membrane shall resist impact damage when tested according to ASTM D3746, ASTM D4272, or the "Resistance to Foot Traffic Test" in FM Approvals 4470.

B. Material Compatibility: Roofing materials shall be compatible with one another and adjacent materials under conditions of service and application required, as demonstrated by roof membrane manufacturer based on testing and field experience.

C. Wind Uplift Resistance: Design roofing system to resist the following wind-uplift pressures when tested according to FM Approvals 4474, UL 580, or UL 1897:

1. East Penthouse Roof a. Zone 1 (Roof Area Field): -30.1 lbf/sq. ft. b. Zone 2 (Roof Area Perimeter): -45.8 lbf/sq. ft. c. Zone 3 (Roof Area Corners): -64.5 lbf/sq. ft.

2. West Penthouse Roof: a. Zone 1 (Roof Area Field): -26.6 lbf/sq. ft. b. Zone 2 (Roof Area Perimeter): -41.8 lbf/sq. ft. c. Zone 3 (Roof Area Corners): -57.0 lbf/sq. ft.

3. 4th Floor Roof: a. Zone 1 (Roof Area Field): -28.0 lbf/sq. ft. b. Zone 2 (Roof Area Perimeter): -43.8 lbf/sq. ft. c. Zone 3 (Roof Area Corners): -59.7 lbf/sq. ft.

4. 2nd Floor Roof:

a. Zone 1 (Roof Area Field): -25.0 lbf/sq. ft. b. Zone 2 (Roof Area Perimeter): -39.3 lbf/sq. ft. c. Zone 3 (Roof Area Corners): -53.6 lbf/sq. ft.

5. 2nd Floor Terrace and All Balcony Roofs:

a. Reinstall existing precast concrete pavers and pedestals.

D. FM Approvals' RoofNav Listing: Roof membrane, base flashings, and component materials shall comply with requirements in FM Approvals 4450 or FM Approvals 4470 as part of a roofing system, and shall be listed in FM Approvals' RoofNav for Class 1 or noncombustible construction, as applicable. Identify materials with FM Approvals Certification markings.

1. Fire/Windstorm Classification: Class 1A-90. 2. Hail-Resistance Rating: MH.

E. ENERGY STAR Listing: Roofing system shall be listed on the DOE's ENERGY STAR "Roof Products Qualified Product List" for low-slope roof products.

Page 122: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 6 BUILT-UP ASPHALT ROOFING

F. Energy Performance: Roofing system shall have an initial solar reflectance of not less than 0.70 and an emissivity of not less than 0.75 when tested according to CRRC-1.

G. Exterior Fire-Test Exposure: ASTM E108 or UL 790, Class A; for application and roof slopes indicated; testing by a qualified testing agency.

H. Interior Fire-Test Exposure: UL 1256; for application and roof decks indicated; testing by a qualified testing agency.

2.2 MANUFACTURERS

A. Source Limitations: Obtain components for roofing system from same manufacturer as roofing membrane or manufacturer approved by roofing membrane manufacturer.

2.3 ROOFING MEMBRANE SHEET MATERIALS

A. Ply Sheet: ASTM D2178, Type VI, asphalt-impregnated, glass-fiber felt.

B. Cap Sheet: ASTM D3909, SBS modified asphalt-impregnated and -coated, glass-fiber cap sheet, with white coarse mineral-granule top surfacing and fine mineral surfacing on bottom surface.

2.4 BASE FLASHING SHEET MATERIALS

A. Backer Sheet: ASTM D4601, Type II, asphalt-impregnated and -coated, glass-fiber sheet, dusted with fine mineral surfacing on both sides.

B. Granule-Surfaced Flashing Sheet: ASTM D6163, Type I or II, Grade G, glass-fiber reinforced, granule-surfaced; suitable for application method specified, and as follows:

1. Granule Color: White.

C. Glass-Fiber Fabric: Woven glass-fiber cloth, treated with asphalt, complying with ASTM D1668, Type I.

D. Liquid Flashing System: Roof membrane manufacturer's standard one- or two-part moisture curing resin with low solvent content, consisting of a primer, flashing cement, and scrim.

2.5 ASPHALT MATERIALS

A. Asphalt Primer: ASTM D41.

B. Roofing Asphalt: ASTM D312/D312M, Type III or IV as recommended by roofing system manufacturer for application.

Page 123: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 7

2.6 AUXILIARY ROOFING MATERIALS

A. General: Auxiliary materials recommended by roofing manufacturer for intended use and compatible with other roofing components.

1. Adhesive and Sealants: Comply with VOC limits of authorities having jurisdiction.

B. Sheathing Paper: Red-rosin type, minimum 3 lb/100 sq. ft.

C. Metal Termination Bars: Manufacturer's standard, predrilled stainless-steel bars, approximately 1 by 1/8 inch thick; with anchors.

D. Cold-Applied Asphalt Adhesive: ASTM D3019, Type III, roof system manufacturer's standard asphalt-based, one- or two-part, asbestos-free, cold-applied adhesive, specially formulated for compatibility and use with roofing system and base flashings.

E. Asphalt Roofing Cement: ASTM D4586, asbestos free, of consistency required by roofing manufacturer for application.

F. Mastic Sealant: Polyisobutylene, plain or modified bitumen; nonhardening, nonmigrating, nonskinning, and nondrying.

G. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Approvals 4470, designed for fastening built-up roofing components to substrate; tested by manufacturer for required pullout strength, and acceptable to roofing manufacturer.

H. Miscellaneous Accessories: Provide those recommended by roofing system manufacturer.

2.7 VAPOR RETARDER

A. Self-Adhering Sheet Vapor Retarder: Polyethylene film laminated to layer of butyl rubber adhesive, minimum 30-mil-total thickness; maximum permeance rating of 0.1 perm; cold applied, with slip-resisting surface and release paper backing. Provide primer when recommended by vapor-retarder manufacturer.

2.8 ROOF INSULATION

A. General: Preformed roof insulation boards manufactured or approved by roof membrane manufacturer, approved for use in FM Approvals' RoofNav-listed roofing system identical to that used for this Project.

B. Provide products with flame spread rating of 75 or less and a smoke developed rating of 450 or less as tested in accordance with ASTM E-84 where tested in the maximum thickness intended for use in accordance with ASTM E-84 or UL 723.

C. Polyisocyanurate Board Insulation: ASTM C1289, Type II, Class 1, Grade 2, felt or glass-fiber mat facer on both major surfaces.

Page 124: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 8 BUILT-UP ASPHALT ROOFING

1. Compressive strength: 20 psi. 2. Size: 48 by 96 inches. 3. R-value: 5.6 per inch, aged, minimum. 4. Thickness:

a. Main Roofs 1) Base Layer: 1-1/2 inches. 2) Upper Layer: 1-1/2 inches.

b. 2nd Floor Terrace 1) Base Layer: 2 inches.

2.9 GLASS-FIBER BLANKET

A. Glass-Fiber Blanket, Unfaced (Batt Insulation): ASTM C665, Type I; with maximum flame-spread and smoke-developed indexes of 25 and 50, respectively, per ASTM E84; passing ASTM E136 for combustion characteristics.

2.10 INSULATION ACCESSORIES

A. General: Roof insulation accessories recommended by insulation manufacturer for intended use and compatible with other roofing system components.

B. Fasteners: Factory-coated steel fasteners and metal or plastic plates complying with corrosion-resistance provisions in FM Approvals 4470, designed for fastening roof insulation to substrate and acceptable to roofing manufacturer.

C. Insulation Adhesive: Insulation manufacturer's recommended adhesive formulated to attach roof insulation to substrate (over vapor retarder) as follows:

1. Bead-applied, low-rise, one-component or multicomponent urethane adhesive.

D. Insulation Cant Strips: ASTM C728, perlite insulation board.

E. Tapered Edge Strips (drain sumps and transitions): Minimum 1 inch/foot tapered closed-cell polyisocyanurate insulation board.

F. Cover Board: ASTM C728, Type I perlite board.

1. Size: 48 by 48 inches. 2. Thickness: 3/4 inch.

2.11 COLD-APPLIED LIQUID FLASHING

A. 100% solids, monolithic, self-terminating, two-part flashing system that is compatible with asphalt built-up roofing membrane. Must be approved by roofing membrane manufacturer.

Page 125: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 9

1. Reinforcing Fabric: 60 mil thick, 100% polyester, non-woven, needle punch fabric.

2.12 METAL ROOF DRAINS

A. Cast-Iron, Large-Sump, General-Purpose Roof Drains:

1. Standard: ASME A112.6.4. 2. Body Material: Cast iron. 3. Dimension of Body: Nominal 14-to 16-inch diameter (match existing). 4. Combination Flashing Ring and Gravel Stop: Required. 5. Outlet: Bottom. 6. Underdeck Clamp: Required. 7. Dome Material: Cast iron. 8. Drain Bearing Pan: Required.

2.13 WALKWAYS

A. Walkway Cap Sheet Strips (Slip Sheet Under Ballasted Railing – East Penthouse Roof): ASTM D6163, Type I or II, Grade G, glass-fiber-reinforced, SBS-modified asphalt sheet; granule surfaced; suitable for application method specified, and as follows:

1. Size: As required to extend minimum 4-inches beyond foot print of sled. 2. Granule Color: White.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements and other conditions affecting performance of the Work:

1. Verify that roof openings and penetrations are in place, curbs are set and braced, and roof-drain bodies are securely clamped in place.

2. Verify that wood cants, blocking, curbs, and nailers are securely anchored to roof deck at penetrations and terminations and that nailers match thicknesses of insulation.

3. Verify that substrate is visibly dry and free of moisture, and that minimum concrete internal relative humidity is not more than 75 percent, or as recommended by roofing system manufacturer, when tested according to ASTM F2170.

a. Test Frequency: One test probe per each 1000 sq. ft., or portion thereof, of roof deck, with not less than three test probes.

b. Submit test reports within 24 hours of performing tests.

Page 126: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 10 BUILT-UP ASPHALT ROOFING

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Clean substrate of dust, debris, moisture, and other substances detrimental to roofing installation according to roofing manufacturer's written instructions.

1. Remove sharp projections.

B. Prevent materials from entering and clogging roof drains and conductors and from spilling or migrating onto surfaces of other construction.

1. Remove roof-drain plugs when no work is taking place or when rain is forecast.

3.3 ROOF DRAIN INSTALLATION

A. Install roof drains at low points of roof areas in accordance with roof membrane manufacturer's written installation instructions.

1. Install flashing collar or flange of roof drain to prevent leakage between drain and adjoining roofing. Maintain integrity of waterproof membranes where penetrated.

2. Construct wood nailers at perimeter of existing drain outlet. 3. Secure drain pan to wood nailers with screws. 4. Set drain body in place and secure with under-deck clamp. 5. Wrap drain body with fiberglass batt insulation and tape in place.

3.4 ROOFING INSTALLATION, GENERAL

A. Install roofing system according to manufacturer's written instructions, FM Approvals' RoofNav assembly requirements, and FM Global Property Loss Prevention Data Sheet 1-29.

B. Complete terminations and base flashings, and provide temporary seals to prevent water from entering completed sections of roofing system at the end of the workday or when rain is forecast.

1. Remove and discard temporary seals before beginning work on adjoining roofing.

C. Install roof membrane and auxiliary materials to tie in to existing roofing to maintain weathertightness of transition.

D. Asphalt Heating:

1. Heat asphalt to its equiviscous temperature, measured at the mop cart or mechanical spreader immediately before application.

2. Circulate asphalt during heating.

Page 127: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 11

a. Do not raise asphalt temperature above equiviscous temperature range more than one hour before time of application.

3. Do not exceed asphalt manufacturer's recommended temperature limits during asphalt heating.

4. Do not heat asphalt within 25 deg F of flash point. 5. Discard asphalt maintained at a temperature exceeding finished blowing

temperature for more than four hours.

a. Apply hot roofing asphalt within plus or minus 25 deg F of equiviscous temperature.

E. Asphalt Heating: Heat and apply SEBS-modified roofing asphalt according to roofing manufacturer's written instructions.

F. Substrate-Joint Penetrations: Prevent roofing asphalt and adhesives from penetrating substrate joints, entering building, or damaging roofing components or adjacent building construction.

3.5 VAPOR RETARDER INSTALLATION

A. Self-Adhering-Sheet Vapor Retarder: Prime substrate if required by manufacturer. Install self-adhering-sheet vapor retarder over area to receive vapor retarder, side and end lapping each sheet a minimum of 3-1/2 and 6 inches, respectively.

1. Extend vertically up parapet walls and projections to a minimum height equal to height of the insulation and cover board.

2. Seal laps by rolling.

B. Completely seal vapor retarder at terminations, obstructions, and penetrations to prevent air movement into roofing system.

3.6 INSULATION INSTALLATION

A. Coordinate installing roofing system components, so insulation is not exposed to precipitation or left exposed at the end of the workday.

B. Comply with roofing system and insulation manufacturer's written instructions for installing roof insulation.

C. Insulation Cant Strips: Install and secure preformed 45-degree insulation cant strips at junctures of roofing membrane with vertical surfaces or angle changes greater than 45 deg.

D. Installation Over Concrete Decks:

1. Install base layer of insulation with joints staggered not less than 24 inches in adjacent rows.

Page 128: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 12 BUILT-UP ASPHALT ROOFING

a. Make joints between adjacent insulation boards not more than 1/4 inch in width.

b. At internal roof drains, slope insulation to create a square drain sump, with each side equal to the diameter of the drain bowl plus 24 inches.

1) Trim insulation so that the flow of water is not restricted.

c. Fill gaps exceeding 1/4 inch with insulation. d. Cut and fit insulation within 1/4 inch of nailers, projections, and

penetrations. e. Adhere base layer of insulation to vapor retarder using insulation adhesive

(full cover or bead applied) according to manufacturer’s requirements to meet wind uplift resistance for each identified roof section and zone.

2. Install upper layers of insulation and tapered insulation, with joints of each layer offset not less than 12 inches from previous layer of insulation.

a. Staggered end joints within each layer not less than 24 inches in adjacent rows.

b. Install with long joints continuous and with end joints staggered not less than 12 inches in adjacent rows.

c. Trim insulation neatly to fit around penetrations and projections, and to fit tight to intersecting sloping roof decks.

d. Make joints between adjacent insulation boards not more than 1/4 inch in width.

e. At internal roof drains, slope insulation to create a square drain sump, with each side equal to the diameter of the drain bowl plus 24 inches.

1) Trim insulation so that the flow of water is not restricted.

f. Fill gaps exceeding 1/4 inch with insulation. g. Cut and fit insulation within 1/4 inch of nailers, projections, and

penetrations. a. Set each layer of insulation in a solid mopping of hot roofing asphalt,

applied within plus or minus 25 deg F of equiviscous temperature according to manufacturer’s requirements to meet wind uplift resistance for each identified roof section and zone.

3.7 INSTALLATION OF COVER BOARDS

A. Install cover boards over insulation with long joints in continuous straight lines, with end joints staggered between rows. Offset joints of insulation below a minimum of 6 inches in each direction.

1. Trim cover board neatly to fit around penetrations and projections, and to fit tight to intersecting sloping roof decks.

2. At internal roof drains, conform to slope of drain sump.

a. Trim cover board so that the flow of water is not restricted.

Page 129: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 13

3. Cut and fit cover board tight to nailers, projections, and penetrations. 4. Set cover board in a solid mopping of hot roofing asphalt, applied within plus or

minus 25 deg F of equiviscous temperature according to manufacturer’s requirements to meet wind uplift resistance for each identified roof section and zone.

3.8 BUILT-UP ROOFING MEMBRANE INSTALLATION

A. Install roofing according to roofing manufacturer's written instructions and applicable recommendations of ARMA/NRCA's "Quality Control Guidelines for the Application of Built-up Roofing" and as follows:

1. Number of Ply Sheets: Three. 2. Surfacing: Mineral-granule-surfaced cap sheet.

a. Mineral-granule-surfaced cap sheet is in addition to number of ply sheets specified.

B. Start installation of roofing in presence of roofing system manufacturer's technical personnel and Owner's testing and inspection agency.

C. Coordinate installation of roofing, so insulation and other components of roofing system not permanently exposed are not subjected to precipitation or left uncovered at the end of the workday or when rain is forecast.

1. Provide tie-offs at end of each day's work to cover exposed roofing membrane sheets and insulation with a course of coated felt set in roofing cement or hot roofing asphalt, with joints and edges sealed.

2. Complete terminations and base flashings, and provide temporary seals to prevent water from entering completed sections of roofing system.

3. Remove and discard temporary seals before beginning work on adjoining roofing.

D. Install lapped base sheet course, extending sheet over and terminating beyond cants. Attach base sheet as follows:

1. Adhere to substrate in a solid mopping of hot roofing asphalt.

E. Install three ply sheets, starting at low point of roof.

1. Align ply sheets without stretching. 2. Shingle side laps of ply sheets uniformly to achieve required number of plies

throughout thickness of roofing membrane.

a. Shingle in direction to shed water.

3. Extend ply sheets over and terminate above cants, minimum 2 inches. 4. Embed each ply sheet in a solid mopping of hot roofing asphalt applied at rate

required by roofing manufacturer, to form a uniform membrane without ply sheets touching.

5. Install ply sheets without wrinkles, tears, and free from air pockets.

Page 130: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 14 BUILT-UP ASPHALT ROOFING

F. Cap Sheet: Install lapped granulated cap sheet, starting at low point of roofing.

1. Offset laps from laps of preceding ply sheets, and align cap sheet without stretching.

2. Lap in direction to shed water. 3. Extend cap sheet over and terminate above cants, minimum 2 inches. 4. Embed cap sheet in a solid mopping of hot roofing asphalt applied at rate

required by roofing system manufacturer. 5. Install cap sheet without wrinkles, tears, and free from air pockets.

3.9 FLASHING AND STRIPPING INSTALLATION

A. Install base flashing over cant strips and other sloping and vertical surfaces, at roof edges, and at penetrations through roof; secure to substrates according to roofing system manufacturer's written instructions and as follows:

1. Prime substrates with asphalt primer if required by roofing system manufacturer. 2. Backer Sheet Application: Adhere backer sheet to substrate in a solid mopping of

hot roofing asphalt applied at not less than 425 deg F. 3. Flashing Sheet Application: Adhere flashing sheet to substrate in a solid mopping

of hot roofing asphalt applied at not less than 425 deg F. Apply hot roofing asphalt to back of flashing sheet if recommended by roofing manufacturer.

B. Extend base flashing up walls or parapets a minimum of 8 inches above built-up roofing and extend each ply minimum 4 inches onto field of roofing membrane/ beyond previous ply.

C. Mechanically fasten top of base flashing securely with termination bars as indicated. Seal top edge with mastic.

D. Install liquid flashing system according to manufacturer's recommendations.

1. Extend liquid flashing not less than 3 inches in all directions from edges of item being flashed.

2. Embed granules, matching color of roof membrane, into wet compound.

E. Install stripping according to roofing system manufacturer's written instructions, where metal flanges and edgings are set on roofing membrane.

1. Built-Up Stripping: Install stripping of not fewer than two roofing ply sheets, setting each ply in a solid mopping of hot roofing asphalt, and extend onto roofing membrane 4 inches each.

F. Roof Drains: Set 30-by-30-inch 4-pound lead flashing in bed of asphaltic adhesive on completed roofing membrane.

1. Cover metal flashing with built-up stripping and roofing cap sheet, and extend each ply a minimum of 4 inches beyond edge of metal flashing onto field of roofing membrane.

Page 131: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

BUILT-UP ASPHALT ROOFING 075113 - 15

2. Clamp roofing membrane, metal flashing, and stripping into roof-drain clamping ring.

3. Install stripping according to roofing manufacturer's written instructions.

3.10 COLD-APPLIED LIQUID FLASHING INSTALLAITON

A. Apply roofing system, abut tight to penetration.

B. After roofing membrane has cooled, apply a continuous bead of liquid-flashing around base of penetration.

C. Apply liquid-flashing system per manufacturer’s written instructions.

D. Extend flashing minimum 6 inches onto field membrane and up onto penetration minimum 8 inches (or as high as possible – lightning protection grounding penetrations).

3.11 WALKWAY INSTALLATION

A. Walkway Cap Sheet Strips (slip sheet at ballasted sleds): Install walkway cap sheet strips, approximately 36 inches wide and in lengths not exceeding 10 feet, over roofing membrane, using same application method as used for roofing cap sheet. Extend walkway cap sheet strips minimum 4 inches beyond footprint of ballasted sled.

1. Install walkways strips at following locations:

a. Under all ballasted sleds. b. Top and bottom of each roof access ladder. c. In front of each roof/penthouse access door. d. Locations indicated on Drawings. e. As required by roof membrane manufacturer’s warranty requirements.

3.12 FIELD QUALITY CONTROL

A. Testing Agency: Engage a qualified testing agency to inspect substrate conditions, surface preparation, roof membrane application, flashings, protection, and drainage components, and to furnish reports to Architect.

B. Perform the following tests:

1. Low-Voltage Electrical Conductance Testing: Testing agency shall survey entire roof area and flashings to locate discontinuity in the roof membrane using an exposed metal electrical loop to create an electrical field tested with hand-held probes or a scanning platform having integral perimeter electrical loops creating a complete electrical field.

a. Perform tests before overlying construction is placed.

Page 132: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

075113 - 16 BUILT-UP ASPHALT ROOFING

b. After testing, repair areas of discontinuities, repeat tests, and make further repairs until roofing and flashing installations are contiguous.

1) Cost of retesting is Contractor's responsibility.

c. Testing agency shall prepare survey report indicating locations of initial discontinuities, if any.

C. Final Roof Inspection: Arrange for roofing system manufacturer's technical personnel to inspect roofing installation on completion, in presence of Architect, and to prepare inspection report.

1. Notify Architect and Owner 48 hours in advance of date and time of inspection.

D. Repair or remove and replace components of roofing system where inspections indicate that they do not comply with specified requirements.

E. Roofing system will be considered defective if it does not pass tests and inspections.

1. Additional testing and inspecting, at Contractor's expense, will be performed to determine compliance of replaced or additional work with specified requirements.

3.13 PROTECTING AND CLEANING

A. Protect roofing system from damage and wear during remainder of construction period.

1. When remaining construction does not affect or endanger roofing, inspect roofing system for deterioration and damage, describing its nature and extent in a written report, with copies to Architect and Owner.

B. Correct deficiencies in or remove roofing components that do not comply with requirements, repair substrates, and repair or reinstall roofing to a condition free of damage and deterioration at time of Substantial Completion and according to warranty requirements.

C. Clean overspray and spillage from adjacent construction using cleaning agents and procedures recommended by manufacturer of affected construction.

END OF SECTION 075113

Page 133: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 1

SECTION 076200 - SHEET METAL FLASHING AND TRIM

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Formed roof-drainage sheet metal fabrications. 2. Formed low-slope roof sheet metal fabrications.

B. Related Requirements:

1. Section 061000 "Rough Carpentry" for wood nailers, curbs, and blocking. 2. Section 042000 "Unit Masonry" for materials and installation of sheet metal

through-wall flashing and trim integral with masonry. 3. Section 075113 "Built-Up Asphalt Roofing” for materials and installation of sheet

metal flashing and trim integral with roofing.

1.3 COORDINATION

A. Coordinate sheet metal flashing and trim layout and seams with sizes and locations of penetrations to be flashed, and joints and seams in adjacent materials.

B. Coordinate sheet metal flashing and trim installation with adjoining roofing and wall materials, joints, and seams to provide leakproof, secure, and noncorrosive installation.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review construction schedule. Verify availability of materials, Installer's personnel, equipment, and facilities needed to make progress and avoid delays.

2. Review special roof details, roof drainage, roof-penetration flashing, equipment curbs, and condition of other construction that affect sheet metal flashing and trim.

3. Review requirements for insurance and certificates if applicable. 4. Review sheet metal flashing observation and repair procedures after flashing

installation.

Page 134: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

076200 - 2 SHEET METAL FLASHING AND TRIM

1.5 ACTION SUBMITTALS

A. Product Data: For each of the following

1. Underlayment materials. 2. Elastomeric sealant.

B. Shop Drawings: For sheet metal flashing and trim.

1. Include plans and attachment details. 2. Detail fabrication and installation layouts, expansion-joint locations, and keyed

details. Distinguish between shop- and field-assembled Work. 3. Include identification of material, thickness, weight, and finish for each item and

location in Project. 4. Include details for forming, including profiles, shapes, seams, and dimensions. 5. Include details for joining, supporting, and securing, including layout and spacing

of fasteners, cleats, clips, and other attachments. Include pattern of seams. 6. Include details of termination points and assemblies. 7. Include details of expansion joints and expansion-joint covers, including showing

direction of expansion and contraction from fixed points. 8. Include details of roof-penetration flashing. 9. Include details of edge conditions, including flashings, and counterflashings. 10. Include details of special conditions. 11. Include details of connections to adjoining work. 12. Detail formed flashing and trim at scale of not less than 3 inches per 12 inches.

C. Samples: For each exposed product and for each color and texture specified, 12 inches long by actual width.

D. Samples for Initial Selection: For each type of sheet metal and accessory indicated with factory-applied finishes.

E. Samples for Verification: For each type of exposed finish.

1. Sheet Metal Flashing: 12 inches long by actual width of unit, including finished seam and in required profile. Include fasteners, cleats, clips, closures, and other attachments.

2. Trim, Metal Closures, Expansion Joints, Joint Intersections, and Miscellaneous Fabrications: 12 inches long and in required profile. Include fasteners and other exposed accessories.

3. Anodized Aluminum Samples: Samples to show full range to be expected for each color required.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For fabricator.

B. Product Certificates: For each type of coping and roof edge flashing that is ANSI/SPRI/FM 4435/ES-1 tested.

Page 135: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 3

C. Product Test Reports: For each product, for tests performed by a qualified testing agency.

D. Evaluation Reports: For copings and roof edge flashing, from ICC-ES showing compliance with ANSI/SPRI/FM 4435/ES-1.

E. Sample Warranty: For special warranty.

1.7 CLOSEOUT SUBMITTALS

A. Maintenance Data: For sheet metal flashing and trim, and its accessories, to include in maintenance manuals.

B. Special warranty.

1.8 QUALITY ASSURANCE

A. Fabricator Qualifications: Employs skilled workers who custom fabricate sheet metal flashing and trim similar to that required for this Project and whose products have a record of successful in-service performance.

1. For copings and roof edge flashings that are ANSI/SPRI/FM 4435/ES-1 tested, shop shall be listed as able to fabricate required details as tested and approved.

B. Mockups: Build mockups to verify selections made under Sample submittals, to demonstrate aesthetic effects, and to set quality standards for fabrication and installation.

1. Build mockup of typical gravel stop, coping, expansion joint cover, scupper liner, through-wall flashing and counterflashing, pipe flashing boot (circular and square), and rain shield (circular and square), including supporting construction cleats, seams, attachments, underlayment, and accessories. For roof edge flashing/ covers mock-up shall be minimum 8 feet long.

2. Approval of mockups does not constitute approval of deviations from the Contract Documents contained in mockups unless Owner specifically approves such deviations in writing.

3. Subject to compliance with requirements, approved mockups may become part of the completed Work if undisturbed at time of Substantial Completion.

1.9 DELIVERY, STORAGE, AND HANDLING

A. Do not store sheet metal flashing and trim materials in contact with other materials that might cause staining, denting, or other surface damage.

1. Store sheet metal flashing and trim materials away from uncured concrete and masonry.

2. Protect stored sheet metal flashing and trim from contact with water.

Page 136: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

076200 - 4 SHEET METAL FLASHING AND TRIM

B. Protect strippable protective covering on sheet metal flashing and trim from exposure to sunlight and high humidity, except to extent necessary for period of sheet metal flashing and trim installation.

1.10 WARRANTY

A. Special Warranty on Finishes: Manufacturer agrees to repair finish or replace sheet metal flashing and trim that shows evidence of deterioration of factory-applied finishes within specified warranty period.

1. Exposed Finish: Deterioration includes, but is not limited to, the following:

a. Color fading more than 5 Delta units when tested in accordance with ASTM D2244.

b. Chalking in excess of a No. 8 rating when tested in accordance with ASTM D4214.

c. Cracking, checking, peeling, or failure of paint to adhere to bare metal.

2. Finish Warranty Period: 20 years from date of Substantial Completion.

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. General: Sheet metal flashing and trim assemblies, including cleats, anchors, and fasteners, shall withstand wind loads, structural movement, thermally induced movement, and exposure to weather without failure due to defective manufacture, fabrication, installation, or other defects in construction. Completed sheet metal flashing and trim shall not rattle, leak, or loosen, and shall remain watertight.

B. Sheet Metal Standard for Flashing and Trim: Comply with NRCA's "The NRCA Roofing Manual: Architectural Metal Flashing, Condensation and Air Leakage Control, and Reroofing" and SMACNA's "Architectural Sheet Metal Manual" requirements for dimensions and profiles shown unless more stringent requirements are indicated.

C. SPRI Wind Design Standard: Manufacture and install copings and roof edge flashings tested in accordance with ANSI/SPRI/FM 4435/ES-1 and capable of resisting the following design pressure:

1. Design Pressure: As indicated in Section 075113 “Built-Up Asphalt Roofing”.

D. Thermal Movements: Allow for thermal movements from ambient and surface temperature changes to prevent buckling, opening of joints, overstressing of components, failure of joint sealants, failure of connections, and other detrimental effects. Base calculations on surface temperatures of materials due to both solar heat gain and nighttime-sky heat loss.

1. Temperature Change: 120 deg F, ambient; 180 deg F, material surfaces.

Page 137: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 5

2.2 SHEET METALS

A. General: Protect mechanical and other finishes on exposed surfaces from damage by applying strippable, temporary protective film before shipping.

B. Aluminum Sheet: ASTM B209, alloy as standard with manufacturer for finish required, with temper as required to suit forming operations and performance required; with smooth, flat surface.

1. As-Milled Finish (cleats): Mill. 2. Prefinished: Color Anodic Finish, Coil Coated: AAMA 611, AA-M12C22A42/A44,

Class I, 0.018 mm or thicker.

a. Color: As selected by Architect from full range of industry colors and color densities.

b. Color Range: Noticeable variations in same piece are unacceptable. Variations in appearance of adjoining components are acceptable if they are within the range of approved Samples and are assembled or installed to minimize contrast.

C. Stainless Steel Sheet: ASTM A240, Type 304, dead soft, fully annealed; with smooth, flat surface.

1. Finish: ASTM A480, No. 2D dull, cold rolled.

a. Surface Preparation: Remove tool and die marks and stretch lines, or blend into finish.

b. Polished Finishes: Grind and polish surfaces to produce uniform finish, free of cross scratches.

1) Run grain of directional finishes with long dimension of each piece. 2) When polishing is completed, passivate and rinse surfaces. Remove

embedded foreign matter and leave surfaces chemically clean.

2.3 UNDERLAYMENT MATERIALS

A. Self-Adhering, High-Temperature Sheet Underlayment: Minimum 30 mils (0.76 mm) thick, consisting of a slip-resistant polyethylene- or polypropylene-film top surface laminated to a layer of butyl- or SBS-modified asphalt adhesive, with release-paper backing; specifically designed to withstand high metal temperatures beneath metal roofing. Provide primer in accordance with underlayment manufacturer's written instructions.

1. Source Limitations: Obtain underlayment from single source from single manufacturer.

2. Low-Temperature Flexibility: ASTM D1970/D1970M; passes after testing at minus 20 deg F or lower.

B. Slip Sheet: Rosin-sized building paper, 3 lb/100 sq. ft. minimum.

Page 138: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

076200 - 6 SHEET METAL FLASHING AND TRIM

2.4 MISCELLANEOUS MATERIALS

A. General: Provide materials and types of fasteners, solder, protective coatings, sealants, and other miscellaneous items as required for complete sheet metal flashing and trim installation and as recommended by manufacturer of primary sheet metal or manufactured item unless otherwise indicated.

B. Fasteners: Wood screws, annular threaded nails, self-tapping screws, self-locking rivets and bolts, and other suitable fasteners designed to withstand design loads and recommended by manufacturer of primary sheet metal or manufactured item.

1. General: Blind fasteners or self-drilling screws, gasketed, with hex-washer head.

a. Exposed Fasteners: Heads matching color of sheet metal using plastic caps or factory-applied coating. Provide metal-backed EPDM or PVC sealing washers under heads of exposed fasteners bearing on weather side of metal.

b. Blind Fasteners: High-strength aluminum or stainless steel rivets suitable for metal being fastened.

c. Spikes and Ferrules: Same material as gutter; with spike with ferrule matching internal gutter width.

2. Fasteners for Aluminum Sheet: Aluminum or Series 300 stainless steel. 3. Fasteners for Stainless Steel Sheet: Series 300 stainless steel.

C. Solder:

1. For Stainless Steel: ASTM B32, Grade Sn60, with acid flux of type recommended by stainless steel sheet manufacturer.

D. Sealant Tape: Pressure-sensitive, 100 percent solids, polyisobutylene compound sealant tape with release-paper backing. Provide permanently elastic, nonsag, nontoxic, nonstaining tape 1/2 inch wide and 1/8 inch thick.

E. Elastomeric Sealant: ASTM C920, elastomeric polyurethane polymer sealant; of type, grade, class, and use classifications required to seal joints in sheet metal flashing and trim and remain watertight.

F. Butyl Sealant: ASTM C1311, single-component, solvent-release butyl rubber sealant; polyisobutylene plasticized; heavy bodied for hooked-type expansion joints with limited movement.

2.5 FABRICATION, GENERAL

A. Custom fabricate sheet metal flashing and trim to comply with details indicated and recommendations in cited sheet metal standard that apply to design, dimensions, geometry, metal thickness, and other characteristics of item required.

1. Fabricate sheet metal flashing and trim in shop to greatest extent possible.

Page 139: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 7

2. Fabricate sheet metal flashing and trim in thickness or weight needed to comply with performance requirements, but not less than that specified for each application and metal.

3. Verify shapes and dimensions of surfaces to be covered and obtain field measurements for accurate fit before shop fabrication.

4. Form sheet metal flashing and trim to fit substrates without excessive oil-canning, buckling, and tool marks; true to line, levels, and slopes; and with exposed edges folded back to form hems.

5. Conceal fasteners and expansion provisions where possible. Do not use exposed fasteners on faces exposed to view.

B. Fabrication Tolerances:

1. Fabricate sheet metal flashing and trim that is capable of installation to a tolerance of 1/4 inch in 20 feet on slope and location lines indicated on Drawings and within 1/8-inch offset of adjoining faces and of alignment of matching profiles.

2. Fabricate sheet metal flashing and trim that is capable of installation to tolerances specified.

C. Expansion Provisions: Form metal for thermal expansion of exposed flashing and trim.

1. Form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with butyl sealant concealed within joints.

2. Use lapped expansion joints only where indicated on Drawings.

D. Sealant Joints: Where movable, nonexpansion-type joints are required, form metal in accordance with cited sheet metal standard to provide for proper installation of elastomeric sealant.

E. Fabricate cleats and attachment devices from same material as accessory being anchored or from compatible, noncorrosive metal.

F. Fabricate cleats and attachment devices of sizes as recommended by cited sheet metal standard and by FM Global Property Loss Prevention Data Sheet 1-49 for application, but not less than thickness of metal being secured.

G. Seams:

1. Fabricate nonmoving seams in solderable materials with flat-lock seams. Tin edges to be seamed, form seams, and solder.

2. Fabricate nonmoving seams in non-solderable materials with lapped, riveted and sealed construction.

H. Do not use graphite pencils to mark metal surfaces.

2.6 ROOF-DRAINAGE SHEET METAL FABRICATIONS

A. Parapet Scupper: Fabricate scupper to dimensions required, with closure flange trim to exterior, 4-inch-wide wall flanges to interior, and base extending 4 inches beyond cant

Page 140: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

076200 - 8 SHEET METAL FLASHING AND TRIM

or tapered strip into field of roof. Fabricate exterior frame as indicated on drawings and as needed to lock into scupper liner. Fabricate scupper elements from the following materials:

1. Stainless Steel: 0.018 inch thick.

2.7 LOW-SLOPE ROOF SHEET METAL FABRICATIONS

A. Copings: Fabricate in minimum 96-inch-long, but not exceeding 12-foot-long, sections. Fabricate joint plates of same thickness as copings. Furnish with continuous cleats to support edge of external leg and drill elongated holes for fasteners on interior leg. Fabricate corner sections to extend 24 inches each way from corners – miter, rivet and seal watertight. Shop fabricate interior and exterior corners.

1. Coping Profile: Fig. 3-4A in accordance with SMACNA's "Architectural Sheet Metal Manual."

2. Joint Style: Butted with expansion space and 12-inch-wide, concealed backup plate and 6-inch-wide, exposed cover plate.

3. Special Coping Section: Fabricate coping sections to cove unique precast concrete coping elements as indicated on the drawings.

4. Fabricate from the following materials:

a. Aluminum: 0.040 inch thick.

B. Counterflashing: Shop fabricate with connection leg to secure to existing/new receiver, with hemmed bottom edge and with crimped front face that through “spring action” causes the base of the counterflashing to hug the base flashing and 4 inch face height. Fabricate interior and exterior corners without holes or sharp edges. Fabricate counterflashing from the following materials:

1. Stainless Steel: 0.018 inch thick.

C. Rainshield: Fabricate rainshield to fit snugly around penetration and cover liquid-applied flashing 4 inches minimum (vertical lap). Solder rainshield seams watertight and secure with stainless steel band clamp. Fabricate from the following materials:

1. Stainless Steel: 0.018 inch thick.

D. Roof-Penetration Flashing Boots and Caps: Shop fabricate flashing boots 10 inches high with 4 inch flange all around. Size boot slightly larger than pipe to be flashed. Provide separate soldered cap long enough to lap flashing boot 2 inches and extend down 1 inch into top of pipe. Solder all joints watertight. Fabricate from the following materials:

1. Stainless Steel: 0.018 inch thick.

E. Opening Flashings in Frame Construction: Fabricate sill flashings with 2-inch-high, end dams. Fabricate with crimped front face that through “spring action” causes the base of the counterflashing to hug the base flashing and 4 inch face height. Fabricate from the following materials:

Page 141: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 9

1. Stainless Steel: 0.018 inch thick.

F. Expansion Joint Cover & Counterflashing: On roof side of expansion joint provide horizontal cleat with dimension to be the width of the expansion joint plus 2 inches. Secure counterflashing to curb with storm clips secured to the termination bar at 24 inches on center. Provide roof expansion joint cover of the width indicated on the Drawing. Turn one end of cover up at back-up wall and hook the roof side edge over and loose lock with the projecting flange of the counterflashing. Fabricate from the following materials:

1. Stainless Steel: 0.024 inch thick.

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with installer present, for compliance with requirements for installation tolerances, substrate, and other conditions affecting performance of the Work.

1. Verify compliance with requirements for installation tolerances of substrates. 2. Verify that substrate is sound, dry, smooth, clean, sloped for drainage, and

securely anchored. 3. Verify that air- or water-resistant barriers have been installed over sheathing or

backing substrate to prevent air infiltration or water penetration.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 INSTALLATION OF UNDERLAYMENT

A. Self-Adhering, High-Temperature Sheet Underlayment:

1. Install self-adhering, high-temperature sheet underlayment; wrinkle free. 2. Prime substrate if recommended by underlayment manufacturer. 3. Comply with temperature restrictions of underlayment manufacturer for

installation; use primer for installing underlayment at low temperatures. 4. Apply in shingle fashion to shed water, with end laps of not less than 6 inches

staggered 24 inches between courses. 5. Overlap side edges not less than 3-1/2 inches. Roll laps and edges with roller. 6. Roll laps and edges with roller. 7. Turn up at penetrations (railing posts). 8. Cover underlayment within 14 days.

B. Install slip sheet, wrinkle free, over underlayment before installing sheet metal flashing and trim.

1. Install in shingle fashion to shed water. 2. Lap joints not less than 4 inches.

Page 142: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

076200 - 10 SHEET METAL FLASHING AND TRIM

3.3 INSTALLATION, GENERAL

A. Install sheet metal flashing and trim to comply with details indicated and recommendations of cited sheet metal standard that apply to installation characteristics required unless otherwise indicated on Drawings.

1. Install fasteners, solder, protective coatings, separators, sealants, and other miscellaneous items as required to complete sheet metal flashing and trim system.

2. Install sheet metal flashing and trim true to line, levels, and slopes. Provide uniform, neat seams with minimum exposure of solder and sealant.

3. Anchor sheet metal flashing and trim and other components of the Work securely in place, with provisions for thermal and structural movement.

4. Install sheet metal flashing and trim to fit substrates and to result in watertight performance.

5. Install continuous cleats. Fasten as indicated on the Drawings. 6. Install exposed sheet metal flashing and trim with limited oil-canning, and free of

buckling and tool marks. 7. Do not field cut sheet metal flashing and trim by torch. 8. Do not use graphite pencils to mark metal surfaces.

B. Metal Protection: Where dissimilar metals contact each other, or where metal contacts pressure-treated wood or other corrosive substrates, protect against galvanic action or corrosion by painting contact surfaces with bituminous coating or by other permanent separation as recommended by sheet metal manufacturer or cited sheet metal standard.

1. Underlayment: Where installing sheet metal flashing and trim directly on cementitious or wood substrates, install underlayment and cover with slip sheet.

C. Expansion Provisions: Provide for thermal expansion of exposed flashing and trim.

1. Space movement joints at maximum of 10 feet with no joints within 24 inches of corner or intersection.

2. Form expansion joints of intermeshing hooked flanges, not less than 1 inch deep, filled with sealant concealed within joints.

3. Use lapped expansion joints only where indicated on Drawings.

D. Fasteners: Use fastener sizes that penetrate wood blocking or sheathing not less than 1-1/4 inches for nails and not less than 3/4 inch for wood screws.

E. Conceal fasteners and expansion provisions where possible in exposed work and locate to minimize possibility of leakage. Cover and seal fasteners and anchors as required for a tight installation.

F. Seal joints as required for watertight construction.

1. Where material used for element is not solderable and joint is intended to be permanently stationary and watertight lap, rivet and seal joints to form waterptight seams.

Page 143: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 11

G. Soldered Joints: Clean surfaces to be soldered, removing oils and foreign matter.

1. Pretin edges of sheets with solder to width of 1-1/2 inches; however, reduce pretinning where pretinned surface would show in completed Work.

2. Do not solder aluminum sheet. 3. Do not use torches for soldering. 4. Heat surfaces to receive solder, and flow solder into joint.

a. Fill joint completely. b. Completely remove flux and spatter from exposed surfaces.

5. Stainless Steel Soldering:

a. Tin edges of uncoated sheets, using solder for stainless steel and acid flux. b. Promptly remove acid-flux residue from metal after tinning and soldering. c. Comply with solder manufacturer's recommended methods for cleaning

and neutralization.

H. Rivets: Rivet joints in uncoated aluminum where necessary for strength.

3.4 INSTALLATION OF ROOF-DRAINAGE SYSTEM

A. Install sheet metal roof-drainage items to produce complete roof-drainage system in accordance with cited sheet metal standard unless otherwise indicated. Coordinate installation of roof perimeter flashing with installation of roof-drainage system.

B. Parapet Scupper:

1. Continuously support scupper, set to correct elevation, and seal flanges to interior wall face, over cants or tapered edge strips, and under roofing membrane.

2. Anchor scupper closure trim flange to exterior wall and seal with elastomeric sealant to scupper.

3. Lock front edge of scupper with surface-mounted cleat. 4. Lock top edge of scupper to existing through-wall flashing. 5. Seal with elastomeric sealant exterior wall scupper flanges into back of conductor

head.

3.5 INSTALLATION OF ROOF FLASHINGS

A. Install sheet metal flashing and trim to comply with performance requirements, sheet metal manufacturer's written installation instructions, and cited sheet metal standard.

1. Provide concealed fasteners where possible, and set units true to line, levels, and slopes.

2. Install work with laps, joints, and seams that are permanently watertight and weather resistant.

B. Copings:

Page 144: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

076200 - 12 SHEET METAL FLASHING AND TRIM

1. Install roof edge flashings in accordance with ANSI/SPRI/FM 4435/ES-1. 2. Anchor to resist uplift and outward forces in accordance with recommendations in

cited sheet metal standard unless otherwise indicated.

a. Interlock exterior bottom edge of coping with continuous cleat anchored to substrate at 12-inch centers.

b. Anchor interior leg of coping with washers and screw fasteners through slotted holes at 24-inch centers.

C. Pipe or Post Counterflashing: Install counterflashing umbrella with close-fitting collar with top edge flared for elastomeric sealant, extending minimum of 4 inches over flashing boot. Install stainless steel draw band and tighten.

D. Counterflashing: Coordinate installation of counterflashing with installation of base flashing.

1. Insert counterflashing in reglets or receivers and fit tightly to base flashing. 2. Extend counterflashing 4 inches over base flashing. 3. Lap counterflashing joints minimum of 4 inches. 4. Secure receivers in saw-cut reglet with lead wedges spaced at 24 inches o.c.

Point reglet with mortar. 5. Secure counterflashing to receiver with washers and screw fasteners spaced at

24 inches o.c. unless otherwise indicated.

E. Roof-Penetration Flashing: Coordinate installation of roof-penetration flashing boots with installation of roofing and other items penetrating roof.

3.6 INSTALLATION TOLERANCES

A. Installation Tolerances: Shim and align sheet metal flashing and trim within installed tolerance of 1/4 inch in 20 feet on slope and location lines indicated on Drawings and within 1/8-inch offset of adjoining faces and of alignment of matching profiles.

3.7 CLEANING

A. Clean exposed metal surfaces of substances that interfere with uniform oxidation and weathering.

B. Clean and neutralize flux materials. Clean off excess solder.

C. Clean off excess sealants.

3.8 PROTECTION

A. Remove temporary protective coverings and strippable films as sheet metal flashing and trim are installed unless otherwise indicated in manufacturers written installation instructions.

Page 145: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

SHEET METAL FLASHING AND TRIM 076200 - 13

B. On completion of sheet metal flashing and trim installation, remove unused materials and clean finished surfaces as recommended in writing by sheet metal flashing and trim manufacturer.

C. Maintain sheet metal flashing and trim in clean condition during construction.

D. Replace sheet metal flashing and trim that have been damaged or that have deteriorated beyond successful repair by finish touchup or similar minor repair procedures, as determined by Architect.

END OF SECTION 076200

Page 146: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

APPLIED FIREPROOFING 078100 - 1

SECTION 078100 - APPLIED FIREPROOFING

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section includes sprayed fire-resistive materials.

1.3 DEFINITIONS

A. SFRM: Sprayed fire-resistive materials.

1.4 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1. Review products, design ratings, restrained and unrestrained conditions, densities, thicknesses, bond strengths, and other performance requirements.

1.5 ACTION SUBMITTALS

A. Product Data: For each type of product.

B. Shop Drawings: Framing plans or schedules, or both, indicating the following:

1. Extent of fireproofing for each construction and fire-resistance rating.2. Applicable fire-resistance design designations of a qualified testing and

inspecting agency acceptable to authorities having jurisdiction.3. Minimum fireproofing thicknesses needed to achieve required fire-resistance

rating of each structural component and assembly.4. Treatment of fireproofing after application.

1.6 INFORMATIONAL SUBMITTALS

A. Qualification Data: For Installer.

B. Product Certificates: For each type of fireproofing.

Page 147: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason University

Project ID No. 247-A9247-015

078100 - 2 APPLIED FIREPROOFING

C. Evaluation Reports: For fireproofing, from ICC-ES.

D. Preconstruction Test Reports: For fireproofing.

E. Field quality-control reports.

1.7 QUALITY ASSURANCE

A. Installer Qualifications: A firm or individual certified, licensed, or otherwise qualified by fireproofing manufacturer as experienced and with sufficient trained staff to install manufacturer's products according to specified requirements.

1.8 PRECONSTRUCTION TESTING

A. Preconstruction Testing Service: Engage a qualified testing agency to perform preconstruction testing on fireproofing.

1. Provide test specimens and assemblies representative of proposed materials and construction.

B. Preconstruction Adhesion and Compatibility Testing: Test for compliance with requirements for specified performance and test methods.

1. Bond Strength: Test for cohesive and adhesive strength according to ASTM E736. Provide bond strength indicated in referenced fire-resistance design, but not less than minimum specified in Part 2.

2. Density: Test for density according to ASTM E605. Provide density indicated in referenced fire-resistance design, but not less than minimum specified in Part 2.

3. Verify that manufacturer, through its own laboratory testing or field experience, attests that primers or coatings are compatible with fireproofing.

4. Schedule sufficient time for testing and analyzing results to prevent delaying the Work.

5. For materials failing tests, obtain applied-fireproofing manufacturer's written instructions for corrective measures including the use of specially formulated bonding agents or primers.

1.9 FIELD CONDITIONS

A. Environmental Limitations: Do not apply fireproofing when ambient or substrate temperature is 44 deg F or lower unless temporary protection and heat are provided to maintain temperature at or above this level for 24 hours before, during, and for 24 hours after product application.

B. Ventilation: Ventilate building spaces during and after application of fireproofing, providing complete air exchanges according to manufacturer's written instructions. Use natural means or, if they are inadequate, forced-air circulation until fireproofing dries thoroughly.

Page 148: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

APPLIED FIREPROOFING 078100 - 3

PART 2 - PRODUCTS

2.1 PERFORMANCE REQUIREMENTS

A. Assemblies: Provide fireproofing, including auxiliary materials, according to requirements of each fire-resistance design and manufacturer's written instructions.

B. Source Limitations: Obtain fireproofing from single source.

C. Fire-Resistance Tested according to ASTM E119 or UL 263; testing by a qualified testing agency. Identify products with appropriate markings of applicable testing agency.

D. Asbestos: Provide products containing no detectable asbestos.

2.2 SPRAYED FIRE-RESISTIVE MATERIALS

A. Sprayed Fire-Resistive Material: Manufacturer's standard, factory-mixed, lightweight, dry formulation, complying with indicated fire-resistance design, and mixed with water at Project site to form a slurry or mortar before conveyance and application or conveyed in a dry state and mixed with atomized water at place of application.

1. Manufacturers: Subject to compliance with requirements, available manufacturers offering products that may be incorporated into the Work include, but are not limited to the following:

a. Carboline Company; a subsidiary of RPM International.b. Isolatek International.c. Pyrok, Inc.

2. Application: Designated for exterior use by a qualified testing agency acceptable to authorities having jurisdiction.

3. Bond Strength: Minimum 150-lbf/sq. ft cohesive and adhesive strength based on field testing according to ASTM E736.

4. Density: Not less than density specified in the approved fire-resistance design, according to ASTM E605.

5. Thickness: As required for fire-resistance design indicated, measured according to requirements of fire-resistance design or ASTM E605, whichever is thicker, but not less than 0.375 inch.

6. Combustion Characteristics: ASTM E136.7. Surface-Burning Characteristics: Comply with ASTM E84; testing by a qualified

testing agency. Identify products with appropriate markings of applicable testing agency.

a. Flame-Spread Index: 10 or less.b. Smoke-Developed Index: 10 or less.

8. Compressive Strength: Minimum 10 lbf/sq. in according to ASTM E761.9. Corrosion Resistance: No evidence of corrosion according to ASTM E937.

Page 149: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason University

Project ID No. 247-A9247-015

078100 - 4 APPLIED FIREPROOFING

10. Deflection: No cracking, spalling, or delamination according to ASTM E759.11. Effect of Impact on Bonding: No cracking, spalling, or delamination according to

ASTM E760.12. Air Erosion: Maximum weight loss of 0.025 g/sq. ft. in 24 hours according to

ASTM E859.13. Fungal Resistance: Treat products with manufacturer's standard antimicrobial

formulation to result in no growth on specimens per ASTM G21.14. Sound Absorption: NRC of 0.50 to 0.75 according to ASTM C423 for Type A

mounting according to ASTM E795.15. Finish: As selected by Architect from manufacturer's standard finishes

a. Color: As selected by Architect from manufacturer's full range.

2.3 AUXILIARY MATERIALS

A. General: Provide auxiliary materials that are compatible with fireproofing and substrates and are approved by UL or another testing and inspecting agency acceptable to authorities having jurisdiction for use in fire-resistance designs indicated.

B. Substrate Primers: Primers approved by fireproofing manufacturer and complying with one or both of the following requirements:

1. Primer and substrate are identical to those tested in required fire-resistance design by UL or another testing and inspecting agency acceptable to authorities having jurisdiction.

2. Primer's bond strength in required fire-resistance design complies with specified bond strength for fireproofing and with requirements in UL's "Fire Resistance Directory" or in the listings of another qualified testing agency acceptable to authorities having jurisdiction, based on a series of bond tests according to ASTM E736.

C. Bonding Agent: Product approved by fireproofing manufacturer and complying with requirements in UL's "Fire Resistance Directory" or in the listings of another qualified testing agency acceptable to authorities having jurisdiction.

D. Reinforcing Mesh: Metallic mesh reinforcement of type, weight, and form required to comply with fire-resistance design indicated; approved and provided by fireproofing manufacturer. Include pins and attachment.

E. Sealer: Transparent-drying, water-dispersible, tinted protective coating recommended in writing by fireproofing manufacturer for each fire-resistance design.

Page 150: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

APPLIED FIREPROOFING 078100 - 5

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine substrates, areas, and conditions, with Installer present, for compliance with requirements for substrates and other conditions affecting performance of the Work and according to each fire-resistance design.

1. Verify that substrates are free of dirt, oil, grease, release agents, rolling compounds, mill scale, loose scale, incompatible primers, paints, and encapsulants, or other foreign substances capable of impairing bond of fireproofing with substrates under conditions of normal use or fire exposure.

2. Verify that objects penetrating fireproofing, including clips, hangers, support sleeves, and similar items, are securely attached to substrates.

3. Verify that substrates receiving fireproofing are not obstructed by ducts, piping, equipment, or other suspended construction that will interfere with fireproofing application.

B. Verify that concrete work on steel deck is complete before beginning fireproofing work.

C. Verify that roof construction, installation of rooftop HVAC equipment, and other related work are complete before beginning fireproofing work.

D. Conduct tests according to fireproofing manufacturer's written instructions to verify that substrates are free of substances capable of interfering with bond.

E. Prepare written report, endorsed by Installer, listing conditions detrimental to performance of the Work.

F. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Cover other work subject to damage from fallout or overspray of fireproofing materials during application.

B. Clean substrates of substances that could impair bond of fireproofing.

C. Prime substrates where included in fire-resistance design and where recommended in writing by fireproofing manufacturer unless compatible shop primer has been applied and is in satisfactory condition to receive fireproofing.

D. For applications visible on completion of Project, repair substrates to remove surface imperfections that could affect uniformity of texture and thickness in finished surface of fireproofing. Remove minor projections and fill voids that would telegraph through fire-resistive products after application.

Page 151: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason University

Project ID No. 247-A9247-015

078100 - 6 APPLIED FIREPROOFING

3.3 APPLICATION

A. Construct fireproofing assemblies that are identical to fire-resistance design indicated and products as specified, tested, and substantiated by test reports; for thickness, primers, sealers, topcoats, finishing, and other materials and procedures affecting fireproofing work.

B. Comply with fireproofing manufacturer's written instructions for mixing materials, application procedures, and types of equipment used to mix, convey, and apply fireproofing; as applicable to particular conditions of installation and as required to achieve fire-resistance ratings indicated.

C. Coordinate application of fireproofing with other construction to minimize need to cut or remove fireproofing.

1. Do not begin applying fireproofing until clips, hangers, supports, sleeves, and other items penetrating fireproofing are in place.

2. Defer installing ducts, piping, and other items that would interfere with applying fireproofing until application of fireproofing is completed.

D. Install auxiliary materials as required, as detailed, and according to fire-resistance design and fireproofing manufacturer's written instructions for conditions of exposure and intended use. For auxiliary materials, use attachment and anchorage devices of type recommended in writing by fireproofing manufacturer.

E. Spray apply fireproofing to maximum extent possible. After the spraying operation in each area, complete the coverage by trowel application or other placement method recommended in writing by fireproofing manufacturer.

F. Extend fireproofing in full thickness over entire area of each substrate to be protected.

G. Install body of fireproofing in a single course unless otherwise recommended in writing by fireproofing manufacturer.

H. For applications over encapsulant materials, including lockdown (post-removal) encapsulants, apply fireproofing that differs in color from that of encapsulant over which it is applied.

I. Where sealers are used, apply products that are tinted to differentiate them from fireproofing over which they are applied.

J. Cure fireproofing according to fireproofing manufacturer's written instructions.

K. Do not install enclosing or concealing construction until after fireproofing has been applied, inspected, and tested and corrections have been made to deficient applications.

L. Finishes: Where indicated, apply fireproofing to produce the following finishes:

1. Manufacturer's Standard Finishes: Finish according to manufacturer's written instructions for each finish selected.

Page 152: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof ReplacementGeorge Mason UniversityProject ID No. 247-A9247-015

APPLIED FIREPROOFING 078100 - 7

2. Spray-Textured Finish: Finish left as spray applied with no further treatment.

3.4 FIELD QUALITY CONTROL

A. Special Inspections: Engage a qualified special inspector to perform the following special inspections:

1. Test and inspect as required by the IBC, Subsection 1705.13, "Sprayed Fire-Resistant Materials."

B. Perform the tests and inspections of completed Work in successive stages. Do not proceed with application of fireproofing for the next area until test results for previously completed applications of fireproofing show compliance with requirements. Tested values must equal or exceed values as specified and as indicated and required for approved fire-resistance design.

C. Fireproofing will be considered defective if it does not pass tests and inspections.

1. Remove and replace fireproofing that does not pass tests and inspections, and retest.

2. Apply additional fireproofing, per manufacturer's written instructions, where test results indicate insufficient thickness, and retest.

D. Prepare test and inspection reports.

3.5 CLEANING, PROTECTING, AND REPAIRING

A. Cleaning: Immediately after completing spraying operations in each containable area of Project, remove material overspray and fallout from surfaces of other construction and clean exposed surfaces to remove evidence of soiling.

B. Protect fireproofing, according to advice of manufacturer and Installer, from damage resulting from construction operations or other causes, so fireproofing is without damage or deterioration at time of Substantial Completion.

C. As installation of other construction proceeds, inspect fireproofing and repair damaged areas and fireproofing removed due to work of other trades.

D. Repair fireproofing damaged by other work before concealing it with other construction.

E. Repair fireproofing by reapplying it using same method as original installation or using manufacturer's recommended trowel-applied product.

END OF SECTION 078100

Page 153: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

JOINT SEALANTS 079200 - 1

SECTION 079200 - JOINT SEALANTS

PART 1 - GENERAL

1.1 RELATED DOCUMENTS

A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.

1.2 SUMMARY

A. Section Includes:

1. Joint sealants.

B. Related Requirements:

1. Section 076200 "Sheet Metal Flashing and Trim" for metal flashings.

1.3 PREINSTALLATION MEETINGS

A. Preinstallation Conference: Conduct conference at Project site.

1.4 ACTION SUBMITTALS

A. Product Data: For each joint-sealant product.

B. Samples for Verification: For each kind and color of joint sealant required, provide Samples with joint sealants in 1/2-inch-wide joints formed between two 6-inch-long strips of material matching the appearance of exposed surfaces adjacent to joint sealants.

1.5 INFORMATIONAL SUBMITTALS

A. Qualification Data: For installer and testing agency.

B. Field-Adhesion-Test Reports: For each type of sealant and substrate application.

C. Sample Warranties: For special warranties.

1.6 QUALITY ASSURANCE

A. Installer Qualifications: A construction company specializing in the application and installation of joint sealant on facades that is approved applicator acknowledged by the

Page 154: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

079200 - 2 JOINT SEALANTS

sealant material manufacturer. Contractor and mechanics performing the work must demonstrate 5-years of experience in application of materials identical to those to be used on this project.

B. Product Testing: Test joint sealants using a qualified testing agency.

1. Testing Agency Qualifications: Qualified according to ASTM C1021 to conduct the testing indicated.

C. Mockups:

1. Cut out and prepare existing joint to demonstrate removal of existing materials and surface preparation of joint surfaces to receive sealant. Five (5) feet long.

2. Install backing material and sealant in prepared joint (not the mock-up above) to demonstrate application of materials and final finished appearance. Five (5) feet long.

3. Perform pull test on approved mock-up.

1.7 PRECONSTRUCTION TESTING

A. Preconstruction Laboratory Testing: Submit to joint-sealant manufacturers, for testing indicated below, samples of materials that will contact or affect joint sealants.

1. Adhesion Testing: Use ASTM C794 to determine whether priming and other specific joint preparation techniques are required to obtain rapid, optimum adhesion of joint sealants to joint substrates.

2. Stain Testing: Use ASTM C1248 to determine stain potential of sealant when in contact with masonry substrates.

3. Submit manufacturer's recommended number of pieces of each type of material, including joint substrates, joint-sealant backings, and miscellaneous materials.

4. Schedule sufficient time for testing and analyzing results to prevent delaying the Work.

5. For materials failing tests, obtain joint-sealant manufacturer's written instructions for corrective measures, including use of specially formulated primers.

6. Testing will not be required if joint-sealant manufacturers submit data that are based on previous testing, not older than 24 months, of sealant products for adhesion to, staining of, and compatibility with joint substrates and other materials matching those submitted.

B. Preconstruction Field-Adhesion Testing: Before installing sealants, field test their adhesion to Project joint substrates as follows:

1. Locate test joints as directed by Architect. 2. Conduct field tests for each kind of sealant and joint substrate. 3. Notify Architect seven days in advance of dates and times when test joints will be

erected. 4. Arrange for tests to take place with joint-sealant manufacturer's technical

representative present.

Page 155: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

JOINT SEALANTS 079200 - 3

a. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1.1 in ASTM C1193 or Method A, Tail Procedure, in ASTM C1521.

1) For joints with dissimilar substrates, verify adhesion to each substrate separately; extend cut along one side, verifying adhesion to opposite side. Repeat procedure for opposite side.

5. Report whether sealant failed to adhere to joint substrates or tore cohesively. Include data on pull distance used to test each kind of product and joint substrate. For sealants that fail adhesively, retest until satisfactory adhesion is obtained.

6. Evaluation of Preconstruction Field-Adhesion-Test Results: Sealants not evidencing adhesive failure from testing, in absence of other indications of noncompliance with requirements, will be considered satisfactory. Do not use sealants that fail to adhere to joint substrates during testing.

1.8 FIELD CONDITIONS

A. Do not proceed with installation of joint sealants under the following conditions:

1. When ambient and substrate temperature conditions are outside limits permitted by joint-sealant manufacturer or are below 40 deg F.

2. When joint substrates are wet. 3. Where joint widths are less than those allowed by joint-sealant manufacturer for

applications indicated. 4. Where contaminants capable of interfering with adhesion have not yet been

removed from joint substrates.

1.9 WARRANTY

A. Special Installer's Warranty: Installer agrees to repair or replace joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Two years from date of Substantial Completion.

B. Special Manufacturer's Warranty: Manufacturer agrees to furnish joint sealants to repair or replace those joint sealants that do not comply with performance and other requirements specified in this Section within specified warranty period.

1. Warranty Period: Five years from date of Substantial Completion.

Page 156: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

079200 - 4 JOINT SEALANTS

PART 2 - PRODUCTS

2.1 JOINT SEALANTS, GENERAL

A. Compatibility: Provide joint sealants, backings, and other related materials that are compatible with one another and with joint substrates under conditions of service and application, as demonstrated by joint-sealant manufacturer, based on testing and field experience.

B. Colors of Exposed Joint Sealants: As selected by Architect from manufacturer's full range.

2.2 URETHANE JOINT SEALANTS

A. Urethane, S, NS, 50, NT: Single-component, nonsag, nontraffic-use, plus 50 percent and minus 50 percent movement capability, urethane joint sealant; ASTM C920, Type S, Grade NS, Class 50, Use NT.

2.3 JOINT-SEALANT BACKING

A. Sealant Backing Material, General: Nonstaining; compatible with joint substrates, sealants, primers, and other joint fillers; and approved for applications indicated by sealant manufacturer based on field experience and laboratory testing.

B. Cylindrical Sealant Backings: ASTM C1330, Type C (closed-cell material with a surface skin), and of size and density to control sealant depth and otherwise contribute to producing optimum sealant performance.

C. Bond-Breaker Tape: Polyethylene tape or other plastic tape recommended by sealant manufacturer for preventing sealant from adhering to rigid, inflexible joint-filler materials or joint surfaces at back of joint. Provide self-adhesive tape where applicable.

2.4 MISCELLANEOUS MATERIALS

A. Primer: Material recommended by joint-sealant manufacturer where required for adhesion of sealant to joint substrates indicated, as determined from preconstruction joint-sealant-substrate tests and field tests.

B. Cleaners for Nonporous Surfaces: Chemical cleaners acceptable to manufacturers of sealants and sealant backing materials, free of oily residues or other substances capable of staining or harming joint substrates and adjacent nonporous surfaces in any way, and formulated to promote optimum adhesion of sealants to joint substrates.

C. Masking Tape: Nonstaining, nonabsorbent material compatible with joint sealants and surfaces adjacent to joints.

Page 157: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

JOINT SEALANTS 079200 - 5

PART 3 - EXECUTION

3.1 EXAMINATION

A. Examine joints indicated to receive joint sealants, with Installer present, for compliance with requirements for joint configuration, installation tolerances, and other conditions affecting performance of the Work.

B. Proceed with installation only after unsatisfactory conditions have been corrected.

3.2 PREPARATION

A. Surface Cleaning of Joints: Clean out joints immediately before installing joint sealants to comply with joint-sealant manufacturer's written instructions and the following requirements:

1. Remove all foreign material from joint substrates that could interfere with adhesion of joint sealant, including dust, paints (except for permanent, protective coatings tested and approved for sealant adhesion and compatibility by sealant manufacturer), old joint sealants, oil, grease, waterproofing, water repellents, water, surface dirt, and frost.

2. Clean porous joint substrate surfaces by brushing, grinding, mechanical abrading, or a combination of these methods to produce a clean, sound substrate capable of developing optimum bond with joint sealants. Remove loose particles remaining after cleaning operations above by vacuuming or blowing out joints with oil-free compressed air. Porous joint substrates include the following:

a. Concrete. b. Masonry.

3. Remove laitance and form-release agents from concrete. 4. Clean nonporous joint substrate surfaces with chemical cleaners or other means

that do not stain, harm substrates, or leave residues capable of interfering with adhesion of joint sealants. Nonporous joint substrates include the following:

a. Metal.

B. Joint Priming: Prime joint substrates where recommended by joint-sealant manufacturer or as indicated by preconstruction joint-sealant-substrate tests or prior experience. Apply primer to comply with joint-sealant manufacturer's written instructions. Confine primers to areas of joint-sealant bond; do not allow spillage or migration onto adjoining surfaces.

C. Masking Tape: Use masking tape where required to prevent contact of sealant or primer with adjoining surfaces that otherwise would be permanently stained or damaged by such contact or by cleaning methods required to remove sealant smears. Remove tape immediately after tooling without disturbing joint seal.

Page 158: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

079200 - 6 JOINT SEALANTS

3.3 INSTALLATION OF JOINT SEALANTS

A. General: Comply with joint-sealant manufacturer's written installation instructions for products and applications indicated, unless more stringent requirements apply.

B. Sealant Installation Standard: Comply with recommendations in ASTM C1193 for use of joint sealants as applicable to materials, applications, and conditions indicated.

C. Install sealant backings of kind indicated to support sealants during application and at position required to produce cross-sectional shapes and depths of installed sealants relative to joint widths that allow optimum sealant movement capability.

1. Do not leave gaps between ends of sealant backings. 2. Do not stretch, twist, puncture, or tear sealant backings. 3. Remove absorbent sealant backings that have become wet before sealant

application, and replace them with dry materials.

D. Install bond-breaker tape behind sealants where sealant backings are not used between sealants and backs of joints.

E. Install sealants using proven techniques that comply with the following and at the same time backings are installed:

1. Place sealants so they directly contact and fully wet joint substrates. 2. Completely fill recesses in each joint configuration. 3. Produce uniform, cross-sectional shapes and depths relative to joint widths that

allow optimum sealant movement capability.

F. Tooling of Nonsag Sealants: Immediately after sealant application and before skinning or curing begins, tool sealants according to requirements specified in subparagraphs below to form smooth, uniform beads of configuration indicated; to eliminate air pockets; and to ensure contact and adhesion of sealant with sides of joint.

1. Remove excess sealant from surfaces adjacent to joints. 2. Use tooling agents that are approved in writing by sealant manufacturer and that

do not discolor sealants or adjacent surfaces. 3. Provide concave joint profile per Figure 8A in ASTM C1193 unless otherwise

indicated.

3.4 FIELD QUALITY CONTROL

A. Field-Adhesion Testing: Field test joint-sealant adhesion to joint substrates as follows:

1. Extent of Testing: Test completed and cured sealant joints as follows:

a. Perform 10 tests for the first 1000 feet of joint length for each kind of sealant and joint substrate.

b. Perform one test for each 1000 feet of joint length thereafter or one test per each floor per elevation.

Page 159: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

JOINT SEALANTS 079200 - 7

2. Test Method: Test joint sealants according to Method A, Field-Applied Sealant Joint Hand Pull Tab, in Appendix X1 in ASTM C1193 or Method A, Tail Procedure, in ASTM C1521.

a. For joints with dissimilar substrates, verify adhesion to each substrate separately; extend cut along one side, verifying adhesion to opposite side. Repeat procedure for opposite side.

3. Inspect tested joints and report on the following:

a. Whether sealants filled joint cavities and are free of voids. b. Whether sealant dimensions and configurations comply with specified

requirements. c. Whether sealants in joints connected to pulled-out portion failed to adhere

to joint substrates or tore cohesively. Include data on pull distance used to test each kind of product and joint substrate. Compare these results to determine if adhesion complies with sealant manufacturer's field-adhesion hand-pull test criteria.

4. Record test results in a field-adhesion-test log. Include dates when sealants were installed, names of persons who installed sealants, test dates, test locations, whether joints were primed, adhesion results and percent elongations, sealant material, sealant configuration, and sealant dimensions.

5. Repair sealants pulled from test area by applying new sealants following same procedures used originally to seal joints. Ensure that original sealant surfaces are clean and that new sealant contacts original sealant.

B. Evaluation of Field-Adhesion-Test Results: Sealants not evidencing adhesive failure from testing or noncompliance with other indicated requirements will be considered satisfactory. Remove sealants that fail to adhere to joint substrates during testing or to comply with other requirements. Retest failed applications until test results prove sealants comply with indicated requirements.

3.5 CLEANING

A. Clean off excess sealant or sealant smears adjacent to joints as the Work progresses by methods and with cleaning materials approved in writing by manufacturers of joint sealants and of products in which joints occur.

3.6 PROTECTION

A. Protect joint sealants during and after curing period from contact with contaminating substances and from damage resulting from construction operations or other causes so sealants are without deterioration or damage at time of Substantial Completion. If, despite such protection, damage or deterioration occurs, cut out, remove, and repair damaged or deteriorated joint sealants immediately so installations with repaired areas are indistinguishable from original work.

Page 160: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

079200 - 8 JOINT SEALANTS

END OF SECTION 079200

Page 161: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PAINTING 099100 - 1

SECTION 09 9100 - PAINTING

PART 1 - GENERAL

1.1 SUMMARY

A. Extent of painting work is indicated on the Drawings and as specified in this Section.

B. Work includes painting and finishing of exterior exposed items and surfaces throughout Project, except as otherwise indicated.

1. Surface preparation, priming, and coats of paint specified are in addition to shop-priming and surface treatment that may be specified under other sections of work.

C. “Paint” as used herein means all coating systems materials, including pri-mers, emulsions, enamels, stains, sealers, fillers, and other applied materials whether used as prime, intermediate or finish coats.

D. Surfaces to be painted: Except where natural finish of material is specifically noted as a surface not to be painted, paint exposed surfaces whether or not colors are designated in “schedules.” Where items or surfaces are not specif-ically mentioned, paint the same as similar adjacent materials or areas. If col-or or finish is not designated, Architect will select these from standard colors or finishes available.

E. Following categories of work are not included as part of field-applied finish work.

1. Pre-Finished Items: Unless otherwise indicated, do not include painting when factory- finishing is specified for such items as toilet enclosures, acoustic materials, architectural woodwork, finished mechanical and electrical equipment, light fixtures, switchgear and distribution cabinets.

2. Concealed Surfaces: Unless otherwise indicated, painting is not re-quired on surfaces such as walls or ceilings in concealed areas and generally inaccessible areas, foundation spaces, furred areas, utility and pipe spaces, and duct shafts.

3. Finished Metal Surfaces: Unless otherwise indicated, metal surfaces of anodized aluminum, stainless steel, chromium plate, copper, bronze and similar finished materials will not require finish painting.

4. Operating Parts: Moving parts of operating units, mechanical and elec-trical parts, such as valve and damper operators, linkages, sensing de-vices, motor and fan shafts will not require finish painting.

F. Following categories of work are included under other sections of these speci-fications.

1. Shop Primers: Unless otherwise specified, shop priming of ferrous metal items is included under various sections for structural steel, metal fabri-cations, hollow metal work and similar items.

2. Unless otherwise specified, shop priming of fabricated components such as architectural woodwork, wood casework and shop-fabricated or facto-ry-built mechanical and electrical equipment or accessories is included under other sections of these specifications.

Page 162: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

099100 - 2 PAINTING

G. Do not paint over any code-required labels, such as Underwriters' Laborato-ries and Factory Mutual, or any equipment identification, performance rating, name, or nomenclature plates.

1.2 QUALITY ASSURANCE

A. Single Source Responsibility: Provide primers, other undercoat paint, and fin-ish coat products produced by same manufacturer for each paint system. Use only thinners approved by paint manufacturer, and use only within recom-mended limits.

B. Coordination of Work: Review other sections of these specifications in which prime paints are to be provided to ensure compatibility of total coatings sys-tem for various substrates. Upon request from other trades, furnish infor-mation or characteristics of finish materials provided for use, to ensure com-patible prime coats are used.

C. Field Samples: On designated wall surfaces and other interior components, duplicate finishes of prepared samples. Provide full-coat finish samples on at least 60 sq. ft. of surface until required sheen, color and texture are obtained; simulate finished lighting conditions for review of in-place work.

D. Color Selection Sample Areas: Architect will designate required field sample area colors and locations when color schedule is issued. Final acceptance of those colors will be from job-applied samples.

1. Final acceptance of colors will be from job-applied samples.

1.3 SUBMITTALS

A. Product Data: Submit manufacturer's technical information including Paint la-bel analysis and application instructions for each material proposed. Include paint system schedule in the format used in this specification section.

1. For DTM enamel and water-borne epoxy enamel products, provide the following performance data.

a. Abrasion Resistance test data per ASTM D4060 with CS-17 wheel, 1000 gram load for 1000 cycles. (CS-10 wheel data not acceptable).

b. Direct Impact Resistance test data per ASTM D2794. c. Adhesion test data per ASTM D4541.

B. Include Material Safety Data Sheet (MSDS) for each paint product used. In-clude VOC content in grams per liter.

C. Color Chips: Submit color chips of manufacturer's complete range of colors for each paint type for Architect's review of color and texture (sheen). These will be used for color selections if the submitted range is adequate.

1. Based on products of the selected manufacturer and paint systems specified in this the Architect will indicate required colors by referencing the selected paint manufacturer's color chips, or by referencing draw-downs or other standard (such as “match laminate color”).

2. Provide 8-1/2 inch x 11 inch color samples (“drawdowns”) for all paint colors and sheens of all colors of the selected paint manufacturer for approval prior to application in the field. Provide paint drawdowns in fin-ish sheens applicable to those in the field.

Page 163: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PAINTING 099100 - 3

1.4 DELIVERY AND STORAGE

A. Deliver materials to job site in original, new and unopened packages and con-tainers bearing manufacturer's name and label, and following information:

1. Name or title of material. 2. Manufacturer's stock number and date of manufacture. 3. Manufacturer's name. 4. Contents by volume, for major pigment and vehicle constituents. 5. Thinning instructions. 6. Application instructions. 7. Color name and number.

B. Store materials not in actual use in tightly covered containers. Maintain con-tainers used in storage of paint in a clean condition, free of foreign materials and residue. Follow manufacturer’s instructions for storage and waste remov-al.

C. Protect from freezing where necessary. Keep storage area neat and orderly. Remove oily rags and waste daily. Take all precautions to ensure that work-men and work areas are adequately protected from fire hazards and health hazards resulting from handling, mixing and application of paints.

1.5 JOB CONDITIONS

A. Apply paints only when temperature of surfaces to be painted and surrounding air are between 50 degrees F and 90 degrees F for water-base paints; and between 45 degrees F and 95 degrees F for solvent-thinned paints, unless otherwise permitted by paint manufacturer's printed instructions.

B. Do not paint in snow, rain, fog or mist, or when relative humidity exceeds 85percent, or to damp or wet surfaces, unless otherwise permitted by paint manufacturer's printed instructions.

1. Painting may be continued during inclement weather if areas and sur-faces to be painted are enclosed and heated within temperature limits specified by paint manufacturer during application and drying periods.

PART 2 - PRODUCTS

2.1 ACCEPTABLE MANUFACTURERS

A. Basis-of-Design Product: Subject to compliance with requirements, provide paint products indicated on the Drawings by Duron or approved comparable products by one of the following:

1. Benjamin Moore and Co. (Moore). 2. The Sherwin-Williams Company (S-W). 3. ICI Dulux Paints

B. Special Coatings Manufacturer: Subject to compliance with requirements, provide moisture curing aliphatic urethane coating system products of one of the following or prequalified other manufacturers:

1. The Sherwin-Williams Company (S-W). 2. Tnemec 3. Wasser High-Tech Coatings, Inc. (Wasser) 4. McCormick Paints 5. Glidden Professional

Page 164: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

099100 - 4 PAINTING

2.2 MATERIALS

A. Sustainable Design Requirement: Provide products that comply with the test-ing and product requirements of the California Department of Health Services Standard Practice for the Testing of Volatile Organic Emissions from Various Sources Using Small-Scale Environmental Chambers, including 2004 Adden-da OR

B. Material Quality: Provide best quality grade of various types of coatings as regularly manufactured by acceptable paint materials manufacturers. Materi-als not displaying manufacturer's identification as a standard, best-grade product will not be acceptable.

C. Color Pigments: Pure, non-fading, applicable types to suit substrates and service indicated. Lead content in pigment, if any, is limited to contain not more than 0.06% lead, as lead metal based on the total non-volatile (dry-film) of paint by weight.

D. Colors: Colors shall be selected from the design standard manufacturer’s full range of colors. If a manufacturer other than design standard is approved for use, submit draw-down samples of paint colors matching selected colors, to the Architect for review.

PART 3 - PART 3 - EXECUTION

3.1 INSPECTION

A. Applicator must examine areas and conditions under which painting work is to be applied and notify Contractor in writing of conditions detrimental to proper and timely completion of work. Do not proceed with work until unsatisfactory conditions have been corrected in a manner acceptable to Applicator.

B. Maximum Moisture Content of Substrates: When measured with an electronic moisture meter as follows:

1. Masonry (Clay and CMU); 12 percent. 2. Wood; 15 Percent. 3. Gypsum Board: 12 Percent. 4. Concrete

C. Starting of painting work will be construed as Applicator's acceptance of sur-faces and conditions within any particular area.

D. Do not paint over dirt, rust, scale, grease, moisture, scuffed surfaces, or condi-tions otherwise detrimental to formation of a durable paint film.

3.2 SURFACE PREPARATION

A. General: Perform preparation and cleaning procedures in accordance with paint manufacturer's instructions and as herein specified, for each particular substrate condition.

1. Provide barrier coats over incompatible primers or remove and re-prime as required. Notify Architect in writing of any anticipated problems in us-ing the specified coating systems with substrates primed by others.

2. Remove hardware, hardware accessories, machined surfaces, plates, lighting fixtures, and similar items in place and not to be finish-painted, or provide surface-applied protection prior to surface preparation and painting operations. Remove, if necessary, for complete painting of

Page 165: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PAINTING 099100 - 5

items and adjacent surfaces. Following completion of painting of each space or area, reinstall removed items.

3. Clean surfaces to be painted before applying paint or surface treat-ments. Remove oil and grease prior to mechanical cleaning. Program cleaning and painting so that contaminants from cleaning process will not fall onto wet, newly-painted surfaces.

B. Previously Painted Surfaces: Prepare previously painted surfaces for new coatings in accordance with paint manufacturer's recommendations. General-ly, remove loose material and attain uncontaminated surfaces. Clean nonpo-rous surfaces with brush or steel wool and appropriate cleaner or solvent as recommended

C. Cementitious Materials: Prepare cementitious surfaces of concrete, concrete block and cement plaster to be painted by removing efflorescence, chalk, dust, dirt, grease, oils, and by roughening as required to remove glaze. Owner or Architect shall approve the painting application of all areas of concrete block that has had efflorescence removed from its surface.

1. Determine alkalinity and moisture content of surfaces to be painted by performing appropriate tests. Provide test results to Owner and Architect for review before proceeding with the work. If surfaces are found to be sufficiently alkaline to cause blistering and burning of finish paint, correct this condition before application of paint. Do not paint over surfaces where moisture content exceeds that permitted in manufacturer's printed directions.

D. Wood: Clean wood surfaces to be painted of dirt, oil, or other foreign sub-stances with scrapers, suitable solvent, and sandpaper, as required. Sandpa-per smooth those finished surfaces exposed to view, and dust off. Scrape and clean small, dry, seasoned knots and apply a thin coat of white shellac or oth-er recommended knot sealer, before application of priming coat. After prim-ing, fill holes and imperfections in finish surfaces with putty or plastic wood-filler. Sandpaper smooth when dried.

1. Prime, stain, or seal wood required to be job-painted immediately upon delivery to job. Prime edges, ends, faces, undersides, and backsides of such wood, including cabinets, counters, cases, paneling.

E. Ferrous Metals: Clean ferrous surfaces, which are not galvanized or shop-coated, of oil, grease, dirt, loose mill scale and other foreign substances by solvent or mechanical cleaning.

1. Touch-up shop-applied prime coats wherever damaged or bare, where required by other sections of these specifications. Clean and touch-up with same type shop primer.

F. Galvanized Surfaces: Clean free of oil and surface contaminants with non-petroleum-based solvent. Provide wash coat if required by paint system man-ufacturer for prepared substrate.

3.3 MATERIALS PREPARATION

A. Mix and prepare painting materials in accordance with manufacturer's direc-tions.

Page 166: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University

Project ID No. 247-A9247-015

099100 - 6 PAINTING

B. Maintain paint mixing and application containers in a clean condition, free offoreign materials and residue.

C. Stir materials before application to produce a mixture of uniform density, andstir as required during application. Do not stir surface film into material. Re-move film and, if necessary, strain material before using.

3.4 APPLICATION

A. General: Apply paint in accordance with manufacturer's directions. Use ap-plicators and techniques best suited for substrate and type of material beingapplied.

1. Provide access to representative of selected coating manufacturer forobservation of material application only at all times during painting work.Unless specifically indicated by Architect, this representative shall haveno authority to make decisions about the work.

2. Paint surface treatments, and finishes, are indicated in the contract doc-uments.

3. Provide finish coats that are compatible with prime paints used.4. Apply additional coats when undercoats, stains or other conditions show

through final coat of paint, until paint film is of uniform finish, color andappearance. Give special attention to insure that surfaces, includingedges, corners, crevices, welds, and exposed fasteners receive a dryfilm thickness equivalent to that of flat surfaces.

5. Paint surfaces behind movable and permanently fixed equipment andfurniture.

6. Paint interior surfaces of ducts visible through registers or grilles, withflat, non-specular black paint.

7. Paint back sides of access panels, and removable or hinged covers notalready pre-finished.

B. Scheduling Painting: Apply first-coat material to surfaces that have beencleaned, pretreated or otherwise prepared for painting as soon as practicableafter preparation and before subsequent surface deterioration.

1. Allow sufficient time between successive coatings to permit proper dry-ing. Do not recoat until paint has dried to where it feels firms, does notdeform or feel sticky under moderate thumb pressure, and application ofanother coat of paint does not cause lifting or loss of adhesion of theundercoat.

C. Minimum Coating Thickness: Apply materials at not less than manufacturer'srecommended spreading rate, to establish a total DFT as indicated or, if notindicated, as recommended by coating manufacturer.

D. Mechanical and Electrical Work: Paint items exposed to the elements. Do notpaint prefinished items, concealed surfaces, operating parts, and labels.

E. Prime Coats: Apply prime coat of material which is required to be painted orfinished, and which has not been prime coated by others. Recoat primed andsealed surfaces where there is evidence of suction spots or unsealed areas infirst coat, to assure a finish coat with no burn-through or other defects due toinsufficient sealing.

F. Finish Coats: Provide finish quality for new and repainted surfaces as follows:

Page 167: BID SET DRAWING SUBMISSION ENTERPRISE HALL ROOF

Enterprise Hall Roof Replacement George Mason University Project ID No. 247-A9247-015

PAINTING 099100 - 7

1. Pigmented (Opaque) Finishes: Completely cover to provide an opaque,smooth surface of uniform finish, color, appearance and coverage.Cloudiness, spotting, holidays, laps, brush marks, runs, sags, ropiness,or other surface imperfections will not be acceptable.

G. Tinting: Tint each undercoat a lighter shade to simplify identification of eachcoat when multiple coats of the same material are applied. Tint undercoats tomatch the color of the finish coat, but provide sufficient differences in shade ofundercoats to distinguish each separate coat.

H. Completed Work: Match approved samples for color, texture and coverage.Remove, refinish or repaint work not in compliance with specified require-ments.

3.5 CLEAN-UP AND PROTECTION

A. Clean-Up: During progress of work, remove from site discarded paint materi-als, rubbish, cans and rags daily. Upon completion of painting work, cleanglass and other paint spattered surfaces. Remove spattered paint by properwashing and scraping methods, to not scratch or damage finished surfaces.

B. Protection: Protect work of other trades, whether to be painted or not, againstdamage by painting and finishing work until date of Substantial Completion.Correct any damage by cleaning, repairing or replacing, and repainting, as ac-ceptable to Architect.

1. Provide “Wet Paint” signs to protect newly-painted finishes. Removetemporary protective wrappings provided by others for protection of theirwork, after completion of painting operations.

2. At completion of work of other trades, touch-up and restore all damagedor defaced painted surfaces.

3.6 WASTE MANAGEMENT

A. Separate and recycle waste materials to the greatest extent possible.

3.7 EXTERIOR PAINT SCHEDULE

A. Exterior Concrete: Exterior Acrylic Coating: Top coat(s) for total dry film thick-ness of 10.0 mils minimum over primer/sealer.

1. Prime Coat: Acrylic bonding masonry sealer.

S-W : Duration Exterior Acrylic, Satin – K32W02XX Moore: Regal High Build Low Lustre, Satin - N401 PPG: Hydrosealer-WB Primer, Flat – DRH6502

2. First and Second Finish Coats: Satin Acrylic Latex; premium grade

S-W: Duration Exterior Acrylic, Satin - K32W02XX Moore: Regal High Build Low Lustre, Satin - N401 PPG: Regency Exterior Satin Paint, Satin– RGN68XX.

END OF SECTION 09 9100