Procurement of Works
Bid and PQ, Documents, Guidelines, and Procedures
WORLD BANK
Pre-qualification (PQ)
• Very desirable if not mandatory for large contracts
• Optional for mid-size contracts
• Usually replaced by Post-qualification in small contracts
• PQ does not eliminate need for Post bid verification of qualification, which must be done anyway to ensure veracity of info provided at PQ and whether it is still valid at the time of award.
2
Structure of SBD Large Works
3
Broken into 3 Parts, 9 Sections
Explanation of Sections (1 of 3)
4
Explanation of Sections (1 of 3)
Explanation of Sections (2 of 3)
5
Explanation of Sections (3 of 3)
6
Sound familiar? (SCC)
When to Use it?
• Procurement of Works (large contracts)
• May include supply/installation of some plant
• Design provided by Employer
• Alternative SBDs:
– Civil Law Version of SBD (affects French speaking countries having a tradition
of civil law for the for civil works contracts by international Public invitation to tender).
– SBD for Smaller Contracts
7
BID DATA SHEETSOME IMPORTANT Entries
• Number and identification of lots (contracts) and packages (ITB 1.1)
• Pre-Bid Meeting and Site visit (ITB 7.4)
• Language of the bid (ITB 10.1)
• Alternative Bids (ITB 13)
• Bid Prices and Discounts (ITB 14)
• Fixed or Adjustable Prices (ITB 14.5)
8
BID DATA SHEETSOME IMPORTANT Entries
• Currencies of Bid and Payment (ITB 15)
• Period of Validity of Bids (ITB 18)
• Bid Security (ITB 19)
• Source and Date of Exchange Rates and procedure for Conversion of Currencies (ITB 32.1)
9
SOME OTHER TERMS RELEVANT FOR CIVIL WORKS CONTRACTS
• Temporary and Permanent works
• Provisional Sum
• Daywork
• Variations and their procedure
• Value Engineering
• Nominated Subcontractor
10
EVALUATION AND QUALIFICATION CRITERIA
• Bid Evaluation Criteria, and
• Bidder Qualification Criteria
are applied separately!
11
BID EVALUATION CRITERIA
• Technical Compliance/ Non Compliance
• Bid Price
• Alternative Completions Time and/or Technical Alternatives evaluated in accordance with ITB (Instuctions to Bidders) and BDS (Bid Data Sheet)
• Adjustments for non material deviations if any
• No Use of Merit Point System
12
BIDDER QUALIFICATION CRITERIA
Two alternatives:
• Pre-Qualification
• No Pre-Qualification
13
PARTICULAR CONDITIONS
• Part A - Contract Data
• Time for Completion
• Performance Security
• Sections of Works
• Delay Damages (LDs)
• Advance Payment and Reimbursement
• Retention Money
• Maximum Liability of Contractor to Employer
• Insurance Specifics
• Resolution of Disputes Mechanism –Dispute Board
14
PARTICULAR CONDITIONS
• Part B – Specific Provisions
• Provision on Import Duties on Contractor’s Equipment
15
Appendix to Bid
Includes Critical Contract Data:
• Schedule of Adjustment Data (Price Adjustment) for local and foreign currency payments
• Summary of Payment Currencies (breakdown) for the various Sections of Works
16
Procurement of WorksAdmeasurement & Bill of Quantities
Most Works Contracts use Admeasurement to calculate amounts due to the Contractor. This is based on multiplying, for each item of construction, the unit price shown on the Bill of Quantities by the quantity executed as shown on the Monthly Invoices. This is a complex procedure, requiring certification by the “Engineer” and careful supervision and measurement of the work done.
17
Item no. Description Unit Quantity Rate Amount
201 Excavate topsoil to maximum depth 25 cm and
stockpile for reuse, maximum haul distance 1 km
m3 95,000
202 Excavate topsoil to maximum depth 25–50 cm, and
dispose
m3 15,000
203 —etc.—
206 Excavate fill material from cuttings or approved
borrow pits, haul up to 1 km, deposit, shape, and
compact to fill
m3 258,000
207 Excavate rock in cuttings and dispose, any depth m3 25,000
208 —etc.—
18
Bill of Quantity (BoQ) (Slide 1 of 2)
19
Bill of Quantity (BoQ) (Slide 2 of 2)
So what’s difference out Works type contracts? ….Let’s start with Packaging Works Contracts
Slice and Package presents huge advantage because contractors of different size and qualifications may qualify for different size slices.
This increases competition and optimizes the bidding process.
Slices to accommodate small and large contractors.
20
Packaging Example
• Highway 150 km long.
• Estimated cost US $150 million.
• Developing Country.
• 3,000,000 m3 excavation.
• 900,000 m3 pavement concrete.
• Execution period 3 years. Rainy season with no work possible happens 4 months per year.
• 25 small bridges ($200,000 each).
• Employer estimates minimum 6 weeks to process invoices approved by the Engineer.
21
What Number of Slices to Make?
• 10 of 15 km? (Large firms not interested)
• 5 to 30 km? (Still does not attract large firms)
• 3 of 50 km (Better)
Factors to consider: local contractors, interest of international contractors in the country, previous good or bad experiences……
For an example let’s take 10 of 15km
22
Calculating Qualification Requirements(Say) 15 km slice - estimated at $ 15 million
Calculating Cash on hand (Liquid assets needed):
First Calculate Cash needed per month… Account for rainy seasons
Number of “work” months = 3 yrs*(12-4) = 24 months
Cash per month =$15 mil / 24 mo. = $.625 mil
Next Calculate “lag time” until payments…
Between execution and invoice = 1 monthApproval by Engineer = 1 monthPayment by Employer = 1.5 monthSafety = 0.5 month
Therefore – minimum Liquid Assets should be…
$.625 mil * 4 (months of cash) = $ 2.5 mil Liquid Assets
23
Calculating Qualification Requirements(Say) 15 km slice - estimated at $ 15 million
Calculating Average Annual Turnover requirements:
Annual disbursement = $15 mil / 3 yrs = $5 mil annually
Using factor of x2 = $ 10 million annual turnover
Using Factor of x2.5 = $ 12.5 million annual turnover
Using factor of x3 = $ 15 million annual turnover
Recommend 2.5!
24
Assessing experience requirements:
• Completed 2 highway projects in the last 5 years at least $12 million each. Must include concrete pavement and small bridges. [15x0.8=12]
• Having done 120,000 m3 excavation per year. [3,000,000/10 =300,000 m3 per slice of 15 km; 300,000/2=150,000 m3 per year; 150,000x0.8=120,000 m3]
• Having done 36,000 m3 concrete pavement in one year [900,000/10=90,000 m3 per slice of 15 km; 90,000/2=45,000 m3 per year; 45,000x0.8= 36,000 m3 per year]
25
Calculating Qualification Requirements(Say) 15 km slice - estimated at $ 15 million
In case of Joint Ventures:
• The Figures of the partners shall be added together to meet technical and financial requirements.
• Each partner must satisfy no less than 25% of annual turnover and partner in charge no less than 40%.
26
Calculating Qualification Requirements(Say) 15 km slice - estimated at $ 15 million
SBD (Standard Bidding Documents) & SBDSW (SBD Small Works)
Major Works• Generally for large and/or
complex Works• Very thorough GC (General
Conditions) and PC (Particular
Conditions)
• Dispute Resolution is very Useful. Bank demands it. (Dispute Resolution Board)
• Based on FIDIC
Smaller Contracts• Generally for smaller or
simpler works• Simpler GCC and SCC, leaving
room for interpretation• The Contract can’t operate
without DR and Bank demands it. (Adjudicator)
• Developed by the Bank
27
Documents comprising the Bid
• The Bid, in the specified format
• Bid Security or Bid Securing Declaration
• Priced Bill of Quantities
• Qualification Information Forms and Documents
• Alternative offers where Invited
28
Bid Prices
• Contract shall be for the whole of Works
• Items not priced in the BoQ (Bill of Quantity) are deemed Free of charge.
• All taxes, duties, levies payable by the contractor (as of 28 days before submission) included in the price.
• Unless execution time < 18 months, there will be price adjustment formulae (plural).
29
Bid Prices
• Major works:
– Alternative A: Price quoted entirely in local currency but bid states percentage payable in specified foreign currency also giving rate of exchange to remain fixed during contract.
– Alternative B: Prices quoted in different currencies and payments in those currencies without exchange calculation.
• Small works: Only Alternative A
30
Pre-Bid Meeting
Whereas the PBM (Pre-Bid Meeting) is often useful for Goods, it is almost always necessary for Works. It provides:
• Opportunity to find errors in Bid Documents.
• Assess interest of bidders in participating.
• Increase competition.
31
Bid Opening - Evaluation
Requests for clarification of bids through contacting the
Bidder is almost always a bad idea. It makes sense when asking for breakdown of unit prices, or to request historical data for qualification purposes. It leads to corruption or problems when it opens the door for changes to the bid. Never ask “is item XYZ included in prices”.
32
Bid Opening – EvaluationResponsiveness
Substantial Deviations
Key sections not signed
Eligibility Criteria not met
Not accompanied by required securities
Not substantially responsive in respect of technical acceptance and time of execution
33
Bid Opening – EvaluationResponsiveness
The Bank will generally accept the position of the Borrower concerning deviations if the judgment applied is reasonable.
34
Bid Opening – EvaluationComparison - Alternative A
1. Breakdown into different currencies defined by bidders, using Bidders stated rates of exchange.
2. Conversion into single currency (Employer’s usually) using an established official rate at a defined rate shown on the Bidding Documents.
35
Bid Opening – Evaluation
1. Corrections for errors
2. Exclude Provisional Sums and Contingencies
3. Include Day-works priced competitively
4. Convert to common currency
5. Apply “quantifiable” adjustments to deviations
6. Allowances for variations of completion time
7. Apply discounts in case of multiple awards
36
Bid Opening – Evaluation
Unbalanced Bids
When, in a long execution contract, items to be executed first are priced higher than normal and contracts to be executed last are priced lower than normal. It gives the Contractor a financial advantage. (Also known as ” Front end loading”)
Borrower may ask for breakdown of unit prices, and even for ask additional Performance Security
37
Bid Opening – Evaluation
Domestic of preference of 7 ½%, if indicated in Bidding Data, provided that:
• Individual Firm– Registered in the country of the Borrower– More than 50% ownership by Nationals of the Country of
the Borrower– Does not subcontract more than 10% of the Contract price
to foreign contractors• JV
– Individual firms as above– JV registered in Borrower’s country– JV does not subcontract more than 10% to foreign firms
38
AWARD
• Award to LEB (Lowest Evaluated Bidder) meeting Qualification requirements
• Notification of Award constitutes the formation of the Contract. Therefore, Borrowers should not issue conditional notifications of award
• Published in
– UNDB (United Nations Development Business) online, and
– dgMarket (Development Gateway Market)
39
AWARD (Continued)
• Performance Security. Purpose. Difference between Retention and PS.
• Dispute Review Mechanism IN PLACE, meaning DRB (Dispute Review Board) personnel or DRE appointed and functioning!
40