biadot transportation presentation oct11 09

49
IRR Program, Inventory and Funding Formula Update TRIBAL TRANSPORTATION AT A CROSSROAD: TRIBAL LEADERS FORUM ON THE CURRENT STATE OF TRIBAL TRANSPORTATION National Congress of American Indians Palm Springs, CA 10/11/09 1

Upload: nw-tribal-technical-assistance-program

Post on 12-Jun-2015

772 views

Category:

Education


0 download

DESCRIPTION

IRR and ARRA update presented to NCAI Oct. 9, 2009

TRANSCRIPT

Page 1: BIADOT Transportation Presentation Oct11 09

IRR Program, Inventory

and Funding Formula

UpdateTRIBAL TRANSPORTATION AT A

CROSSROAD: TRIBAL LEADERS FORUM ON THE CURRENT STATE OF TRIBAL

TRANSPORTATION

National Congress of American IndiansPalm Springs, CA

10/11/09

1

Page 2: BIADOT Transportation Presentation Oct11 09

Presenters• Mr. LeRoy Gishi

Chief – BIA Division of Transportation

Washington, DC

202-513-7711

[email protected]

• Mr. Robert Sparrow

FHWA - IRR Program Manager

Washington, DC

202-366-9483

[email protected]

Page 3: BIADOT Transportation Presentation Oct11 09

IRR Program Update

Page 4: BIADOT Transportation Presentation Oct11 09

Reauthorization• Both SAFETEA-LU and the DOT Appropriations

expired September 30– Currently operating under 31 day Extension and

Continuing Resolution (CR)

• What does this mean?– Continues FY09 funding levels

– 8.5% of funds being made available

– Additional extensions and continuing resolutions could result in negative impacts to the FY10 program delivery.

• Administration is developing a Reauthorization proposal.

Page 5: BIADOT Transportation Presentation Oct11 09

How are Federal Highway

Programs funded?

AuthorityHighway Authorizations

Multiple Year

Extensions

31 day Extension

$35 million

LimitationDOT Appropriations Bills

Single Year

Continuing Resolutions

31 day CR

$35 million

Page 6: BIADOT Transportation Presentation Oct11 09

IRR Program Funding

• In FY09

– $45 million in August Redistribution

• Will be returned to those Tribes that submitted it

back to BIA and FHWA

• SAFETEA-LU

– $1.88 billion made available

– Obligation of over 97%

Page 7: BIADOT Transportation Presentation Oct11 09

IRR Bridge Program

• FY09

– 13 BIA Bridges $9.6 million

– 11 non-BIA Bridges $3.5 million

• Total since FY98

– 134 BIA Bridges $74.6 million

– 142 non-BIA Bridges $77.7 million

• 100% of the funds were obligated

Page 8: BIADOT Transportation Presentation Oct11 09

ARRA• $310 million made available

– 186 tribal ARRA IRRTIPS approved for more than

$200 million (67%)

– Full obligation by September 30, 2010 or they expire.

• These funds are not subject to the extension or

CR.

• Funding being provided to Tribes via BIA, OSG,

and FHWA.

• Reporting requirements and process is still very

fluid.

• Risk Plan developed

Page 9: BIADOT Transportation Presentation Oct11 09

Program Risks• Fund Availability

– Per formula, redistribution in 2010

– Strict control, required documentation

• Fund Transparency

– Collecting and reporting correct data

• Project/Activity Oversight

– Training (all), Project Reviews & Site Visits

• Assuring Uniform Interpretation

– By BIA and FHWA

• Fund Obligation

– Contracting and monitoring

Page 10: BIADOT Transportation Presentation Oct11 09

ARRA Redistribution

• DOT Secretary given authority in ARRA to redistribute any unobligated funds within the program after 1 year.

• Policy developed with input from IRRPCC.

– Currently being reviewed by FHWA officials.

– Will be published in Federal Register

• All tribes will be provided numerous written notices of the status of their ARRA funds.

Page 11: BIADOT Transportation Presentation Oct11 09

ARRA Redistribution

• Expect a call for projects in December.

• Projects evaluated and ranked prior to Feb. 17, 2010.

• Initial awards in late February. Additional review and awards until mid-May 2010.

Page 12: BIADOT Transportation Presentation Oct11 09

IRR National Inventory II• Scope of work

– To develop policy and standards for the inventory,

and to address trust responsibilities, stewardship

needs, and the processes used for the inventory.

• QA/QC of critical data fields

• Update of coding guide

• Benchmark to other inventories

• Cost tables

• Identification of input parameters for other modes. (no

generation of funding).

• Full undertaking FY10-FY11

– Recommendations implemented in FY10, 11, 12

inventory calculations.

Page 13: BIADOT Transportation Presentation Oct11 09

FHWA Leadership

• Administrator

– Victor Mendez - AZ

• Deputy Administrator

– Greg Nadeau - ME

• Executive Director

– Jeff Paniatti

Page 14: BIADOT Transportation Presentation Oct11 09
Page 15: BIADOT Transportation Presentation Oct11 09

The IRR Inventory and the Funding

Formula

• The most notable issue in the Indian

Reservation Roads (IRR) Program over

the past year has been the funding

formula, how it is being implemented, and

the resulting funding trend.

• This is an issue that impacts all tribes.

15

Page 16: BIADOT Transportation Presentation Oct11 09

IRR Program (Pre-2005)

• The IRR Program was a BIA Regional priority program– the only routes that generated funding were the BIA

routes included in their respective Inventories.

– ExceptionS for Oklahoma and Alaska

• Other routes (tribal, state, county, township, etc.) were included in the inventory but did not generate any funding.

• BIA Regions with numerous reservations and Indian lands had a majority of BIA Routes and therefore received a majority of the funding.

16

Page 17: BIADOT Transportation Presentation Oct11 09

IRR Program Today

• In FY2005, new regulations (25 CFR 170) were

implemented as a result of Negotiated

Rulemaking.

– The IRR Program became a Tribal Share Program

– The basic formula concept remained the same.

• 50% Cost to construct (CTC).

• 30% Vehicle Miles Traveled (VMT).

• 20% Population.

– All eligible public routes, regardless of ownership,

generated funding.

– All Tribes now able to participate in the program.

17

Page 18: BIADOT Transportation Presentation Oct11 09

Implementation of Formula

• Since FY2005, when the IRR Program

regulations were finalized, portions of the

regulations (formula) have not been fully

implemented because the inventory data could

not make a distinction as to which roads should

generate at 100 %, and which should be

factored at a lower percentage as intended in

the regulations. This portion of the regulation is

25 CFR 170, Appendix C to Subpart C, Q10.

18

Page 19: BIADOT Transportation Presentation Oct11 09

Implementation of Formula (cont.)

• 10. Do All IRR Transportation Facilities in the IRR Inventory Count at 100 Percent of Their CTC and VMT?

• No. The CTC and VMT must be computed at the non-Federal share requirement for matching funds for any transportation facility that is added to the IRR inventory and is eligible for funding for construction or reconstruction with Federal funds, other than Federal Lands Highway Program funds. However, if a facility falls into one or more of the following categories, then the CTC and VMT factors must be computed at 100 percent:

– (1) The transportation facility was approved, included, and funded at 100 percent of CTC and VMT in the IRR Inventory for funding purposes prior to the issuance of these regulations.

– (2) The facility is not eligible for funding for construction or reconstruction with Federal funds, other than Federal Lands Highway Program funds; or

– (3) The facility is eligible for funding for construction or reconstruction with Federal funds, however, the public authority responsible for maintenance of the facility provides certification of maintenance responsibility and its inability to provide funding for the project.

19

Page 20: BIADOT Transportation Presentation Oct11 09

Implementation of Formula (cont.)

• Summary

– Not all roads may generate 100% of CTC and VMT, the exceptions are described in three parts in Question 10:1. Roads which are „grandfathered‟

– These are roads that generated funding prior to the regulations being finalized – Pre 2005.

2. Roads which are “not eligible” for Federal funds, other than Federal Lands Highways Program funds.

3. Roads in which the owner certifies of its inability to provide funding for the project and that it has a maintenance responsibility for the facility.

20

Page 21: BIADOT Transportation Presentation Oct11 09

Observing A Trend

• Results:

– Inventory growth since FY2005 has been

primarily in routes other than BIA or Tribal.

– Because the existing database did not

distinguish which roads met the specific

exception under (2) of Q.10, all road

ownerships and classes, with the exception of

State roads, were computed at 100%.

– Impacts are trending to favor roads owned by

others and away from the BIA and tribal

routes. 21

Page 22: BIADOT Transportation Presentation Oct11 09

Observing A Trend

22

Fiscal

Year BIA Tribal State Urban

County

Township Other BIA Other Fed

Other Non-

Fed No Owner

FY2008 30,367.0 14,984.0 17,680.0 1,882.0 48,978.0 144.0 4,300.0 1,756.0 0.0 120,092.0

FY2007 29,750.7 9,734.2 13,666.4 1,465.3 43,180.2 144.5 2,294.0 1,631.8 330.4 102,197.5

FY2006 28,706.2 4,276.7 13,198.7 897.8 34,295.8 138.8 2,302.8 1,445.5 127.5 85,481.5

FY2005 27,384.9 2,851.2 9,048.7 544.7 22,323.7 134.1 370.8 121.6 90.2 62,869.9

TOTAL IRR

Miles

Public Authority Responsible for Maintaining/Improving Roads

Page 23: BIADOT Transportation Presentation Oct11 09

IRR Mileage

0

10000

20000

30000

40000

50000

60000

70000

80000

2005 2006 2007 2008

BIA & Tribal

County & State

Other

Page 24: BIADOT Transportation Presentation Oct11 09

% IRR Fund Distribution(CTC and VMT only)

0

10

20

30

40

50

60

70

2005 2006 2007 2008 2009

BIA & Tribal

County & State

Other

Page 25: BIADOT Transportation Presentation Oct11 09

Recognizing a Problem and

Seeking a Solution

• 25 CFR 170 established the IRR Program

Coordinating Committee (IRRPCC).

– Provides input and recommendations to the

Secretaries of DOI and DOT regarding

regulatory policy and implementation issues

that are brought to its attention.

25

Page 26: BIADOT Transportation Presentation Oct11 09

Role of IRRPCC

• The IRRPCC has reviewed and discussed this

issue over the past years and has not able to

come up with a recommendation

– The Committee reviewed all of the eligible roads and

their corresponding classification

– Numerous data runs were requested and analyzed.

– A matrix was developed to show where some

agreement might be possible (see next slide)

– But because of diverse interests, no consensus could

be reached.

26

Page 27: BIADOT Transportation Presentation Oct11 09

27

Page 28: BIADOT Transportation Presentation Oct11 09

Summary• Recognizing a Problem

– Because of the significant increase in mileage being added to the inventory and the fact that Q10 cannot be implemented as written: • The majority of the IRR funding is now generated by

non-BIA/tribal roads. Most of these roads did not generate funding prior to 2005.

• BIA and tribal roads are not generating enough funding in the formula to adequately keep pace with the deteriorating infrastructure.

• The responsible public authority of non-BIA/tribal roads has other sources of funding made available to it for road infrastructure. BIA and tribal roads do not.

28

Page 29: BIADOT Transportation Presentation Oct11 09

Summary

• Seeking a solution.

– A preliminary Federal recommendation has

been developed that closely coincides to the

IRRPCC views.

– This has been presented at several regional

and national tribal meetings in the near future.

– BIA and FHWA will continue to work with

Tribes and the IRRPCC to develop a final

resolution to this issue.

29

Page 30: BIADOT Transportation Presentation Oct11 09

Data Runs(Using FY 07‟ Inventory Data)

• Run 1 – Baseline – Current implementation

• (similar to FY 05‟, 06‟, 07‟)

– All ownership except Ownership 3 (State) calculated at 100% CTC and VMT

– Ownership 3 calculated at Non-Federal Share

30

Page 31: BIADOT Transportation Presentation Oct11 09

Data Runs(Using FY 07‟ Inventory Data)

• Run 2 – Ownership 1 & 2 100% CTC and VMT

– Ownership 5, Class 4&5 100% CTC and VMT

– All Other Non-Federal Share

• Run 3– Ownership 1 & 2 100% CTC and VMT

– Ownership 3-9, Class 4&5100% CTC and VMT

– All Others Non-Federal Share

31

Page 32: BIADOT Transportation Presentation Oct11 09

Requested Data Cont‟d

• Run 4

– Ownership 1 & 2 100% CTC and VMT

– Ownership 4 & 5 Non-Federal Share

– All Others 0% CTC and VMT

• Run 5 (Preliminary Federal

Recommendation)

32

Page 33: BIADOT Transportation Presentation Oct11 09

33

REGION

Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($)

A - GR. PLAINS 6.50% 19,194,818 7.62% 22,521,838 7.22% 21,335,200 6.87% 20,293,677 7.51% 22,175,231

B - SO. PLAINS 2.78% 8,216,738 3.34% 9,856,266 3.25% 9,593,942 2.32% 6,851,329 3.26% 9,617,834

C - ROCKY MTN 7.44% 21,988,927 8.44% 24,930,599 8.43% 24,890,233 7.98% 23,577,517 8.50% 25,101,548

E - ALASKA 12.21% 36,070,741 10.48% 30,963,959 11.18% 33,033,325 14.01% 41,379,198 11.01% 32,512,012

F - MIDWEST 13.38% 39,517,651 12.79% 37,777,619 13.28% 39,245,932 11.13% 32,891,678 12.20% 36,045,541

G - EASTERN OK 12.97% 38,317,409 15.08% 44,563,392 15.28% 45,143,901 7.93% 23,419,236 13.65% 40,314,074

H - WESTERN 6.27% 18,520,881 7.26% 21,442,171 6.95% 20,517,687 9.30% 27,477,141 7.57% 22,355,598

J - PACIFIC 2.34% 6,908,118 1.86% 5,499,835 1.94% 5,730,855 1.73% 5,121,581 1.89% 5,585,951

M - SOUTHWEST 4.41% 13,020,857 5.09% 15,047,024 4.80% 14,192,373 6.59% 19,457,253 5.32% 15,724,623

N - NAVAJO 23.50% 69,410,946 20.51% 60,599,412 19.26% 56,901,894 23.54% 69,547,773 21.38% 63,159,334

P - NORTHWEST 6.38% 18,840,531 5.34% 15,768,681 6.29% 18,594,459 5.97% 17,630,938 5.49% 16,212,378

S - EASTERN 1.83% 5,416,744 2.18% 6,453,565 2.11% 6,244,559 2.63% 7,777,040 2.24% 6,620,238

Max for Region

Min for Region

RUN 5

Comparison of DATA RUNS

BASELINE RUN 1 RUN 3 RUN 4

Page 34: BIADOT Transportation Presentation Oct11 09

Preliminary Federal

Recommendation• The percentage of CTC and VMT used in

the RNDF calculation is as follows:

– (a) For facilities identified in the IRR Inventory as Ownership 1 and 2, – 100 percent;

– (b) For facilities identified in the IRR Inventory as Ownership 5, Class 4 & 5 – The percentage used will be that shown under the 80% Federal, 20% State column in the “Sliding Scale Rates of Federal-aid Participation in Public Lands States for Projects not on the Interstate System”, pursuant to 23 U.S.C. 120(b)(2); and

34

Page 35: BIADOT Transportation Presentation Oct11 09

Preliminary Federal

Recommendation• Con‟t

– (c) For facilities not included in (a) or (b) above - The percentage used will be the difference between 100 and that shown under the 80% Federal, 20% State column in the “Sliding Scale Rates of Federal-aid Participation in Public Lands States for Projects not on the Interstate System”, pursuant to 23 U.S.C. 120(b)(2), except for Class 1 roads which shall have a percentage of zero.

35

Page 36: BIADOT Transportation Presentation Oct11 09

36

Page 37: BIADOT Transportation Presentation Oct11 09

Preliminary Federal

Recommendation

• In brief:

– (a) Roads owned by BIA and Tribal

Governments for all Classifications should be

factored into the formula at 100%.

37

Page 38: BIADOT Transportation Presentation Oct11 09

Preliminary Federal

Recommendation

– (b) For facilities identified in the IRR Inventory

as Ownership 5 (County/Local), Class 4 & 5 –

The percentage used will be the Federal

Share (+ 80% - 95%);

– (c) For facilities not included in (a) or (b)

above - The percentage used will be the Non-

Federal Share (+ 5 - 20%);

38

Page 39: BIADOT Transportation Presentation Oct11 09

Preliminary Federal

Recommendation

– (d) Class 1 roads for all road ownership other

than BIA or Tribal which are the responsibility

of other public authorities will not generate

funding in the formula (0%).

• They are still eligible IRR as required by law, but

will not generate formula output

39

Page 40: BIADOT Transportation Presentation Oct11 09

Preliminary Federal

Recommendation

• Results

– Roads owned by BIA and Tribes – 100%;

– Roads owned by others and which make up the

majority of roads in and around Indian Reservations,

communities, and villages (Ownership 5, Class 4 & 5

Roads) are factored into the formula at a high share;

– All remaining roads, except Class 1 are factored into

the formula at a lower share; and

– Non-BIA, Non-Tribal Class 1 roads are not factored

into the formula.

40

Page 41: BIADOT Transportation Presentation Oct11 09

41

Page 42: BIADOT Transportation Presentation Oct11 09

Federal Share

• The Federal Share referred to here is the maximum percentage of a project‟s cost for which Federal funds can be used.

– It is a uniformly published % and has been consistent since 1992. It is generally about 80% to 95% and is shown on the following table:

42

Page 43: BIADOT Transportation Presentation Oct11 09

43

Page 44: BIADOT Transportation Presentation Oct11 09

Non-Federal Share

• The Non-Federal Share referred to here is the minimum percentage of a project‟s cost for which state and local funds must contribute in order for Federal funds to be utilized on a project.

44

Page 45: BIADOT Transportation Presentation Oct11 09

45

Page 46: BIADOT Transportation Presentation Oct11 09

46

REGION

Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($) Share (%) Amount ($)

A - GR. PLAINS 6.50% 19,194,818 7.62% 22,521,838 7.22% 21,335,200 6.87% 20,293,677 7.51% 22,175,231

B - SO. PLAINS 2.78% 8,216,738 3.34% 9,856,266 3.25% 9,593,942 2.32% 6,851,329 3.26% 9,617,834

C - ROCKY MTN 7.44% 21,988,927 8.44% 24,930,599 8.43% 24,890,233 7.98% 23,577,517 8.50% 25,101,548

E - ALASKA 12.21% 36,070,741 10.48% 30,963,959 11.18% 33,033,325 14.01% 41,379,198 11.01% 32,512,012

F - MIDWEST 13.38% 39,517,651 12.79% 37,777,619 13.28% 39,245,932 11.13% 32,891,678 12.20% 36,045,541

G - EASTERN OK 12.97% 38,317,409 15.08% 44,563,392 15.28% 45,143,901 7.93% 23,419,236 13.65% 40,314,074

H - WESTERN 6.27% 18,520,881 7.26% 21,442,171 6.95% 20,517,687 9.30% 27,477,141 7.57% 22,355,598

J - PACIFIC 2.34% 6,908,118 1.86% 5,499,835 1.94% 5,730,855 1.73% 5,121,581 1.89% 5,585,951

M - SOUTHWEST 4.41% 13,020,857 5.09% 15,047,024 4.80% 14,192,373 6.59% 19,457,253 5.32% 15,724,623

N - NAVAJO 23.50% 69,410,946 20.51% 60,599,412 19.26% 56,901,894 23.54% 69,547,773 21.38% 63,159,334

P - NORTHWEST 6.38% 18,840,531 5.34% 15,768,681 6.29% 18,594,459 5.97% 17,630,938 5.49% 16,212,378

S - EASTERN 1.83% 5,416,744 2.18% 6,453,565 2.11% 6,244,559 2.63% 7,777,040 2.24% 6,620,238

Max for Region

Min for Region

RUN 5

Comparison of DATA RUNS

BASELINE RUN 1 RUN 3 RUN 4

Page 47: BIADOT Transportation Presentation Oct11 09

47

Future Issues

• The IRRPCC is also working to address

the following:

– How to determine lengths of eligible routes

when a Tribe does not have a recognized

Boundary?

– Definition and measurement of an access

route?

– How Proposed Routes should be considered?

Page 48: BIADOT Transportation Presentation Oct11 09

Contacts

• Mr. LeRoy Gishi

Chief – BIA Division of Transportation

Washington, DC

202-513-7711

[email protected]

• Mr. Robert Sparrow

FHWA - IRR Program Manager

Washington, DC

202-366-9483

[email protected]

Page 49: BIADOT Transportation Presentation Oct11 09

Comments

49