bentonite treatment for economical dust reduction on … · 2017-11-29 · field construction and...

99
;.,' ·1 "' I I I I I I\ I I I I I I I I I I I ·1 Fin al Re po rt Bentonite Treatment For Economical Dust Reduction on Limestone Surfaced Secondary Roads January 1995 Sponsored by the Highway Division of the Iowa Department of Transportation and the Iowa Highway Research Advisory Board Iowa DOT Project HR-351 ERi Project 3643 ISU-ERl-Ames 95-408 Iowa Department of Transportation College of Engineering Iowa State University

Upload: others

Post on 15-Aug-2020

1 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

;.,'

·1 ~ "'

I I I I I I\ I I I I I I I I I I I ·1

Fin al Re po rt

Bentonite Treatment For Economical Dust Reduction on Limestone Surfaced

Secondary Roads

January 1995

Sponsored by the Highway Division of the Iowa Department of Transportation and the Iowa Highway Research Advisory Board

Iowa DOT Project HR-351

ERi Project 3643

ISU-ERl-Ames 95-408

Iowa Department of Transportation

College of Engineering

Iowa State University

Page 2: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I. 'I I I I I I Ii I I I I ~1

I I .I 1. I

Bentonite Treatment for Economical Dust Reduction on Limestone Surf aced

Secondary Roads

Final Report January 1995

Kenneth L. Bergeson John W. Waddingham

Stacy G. Brocka Robert K. Lapke

Sponsored by the Highway Division of the Iowa Department of Transportation and the Iowa Highway Research Advisory Board

Iowa DOT :Project HR-351

Civil and Construction Engineering Department

engineering research institute ERI Project 3643 Iowa State University ISU-ERI-Ames 95-408

"The opinions, findings, and conclusions expressed in this publication are those of the authors and not necessarily those of the Highway Division of the Iowa Department of Transportation.

l

Page 3: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I 1· I I I I I I I I· I I I .I I I I 1. I

TABLE OF CONTENTS

ABSTRACT ....................................................................................................................................... iii

INTRODUCTION ............................................................................................................................... 1

LABORATORY TESTING .............................................................................................. ; .................. 2

TEST ROAD SELECTION ................................................................................................................. 9 Tama County Test Road (Phase I) ........................................................................................... 9 Appanoose County Test Road (Phase II) ................................................................................. 9 Hancock County Test Road (Phase II) ................................................................................... 11

TEST ROAD CONSTRUCTION ...................................................................................................... 13 Tama County Layout ............................................................................................................. 13 Tama County Construction .................................................................................................... 13 Appanoose County Layout ................................................................................................... :.15 Appanoose County Construction ........................................................................................... 15 Hancock County Layout ........................................................................................................ 17 Hancock County Construction ............................................................................................... 17

FIELD EVALUATION ...................................................................................................................... 19 Panel Selection ....................................................................................................................... 20 Evaluation Criteria ................................................................................................................. 20 Visual Inspection ... : ................................................................................................................ 20 Braking Characteristics .......................................................................................................... 32 Video Evaluation .................................................................................................................... 32

LABORATORY EVALUATION ........................ ~ ............................................................................ 34 Gradation Tests ...................................................................................................................... 35 Hydrometer Test .................................................................................................................... 37 X-Ray Fluorescence (XRF) ................................................................................................... 41 Thermogravimetric Analysis (TG) ......................................................................................... 41 X-Ray Diffraction (XRD) ...................................................................................................... 48 Scanning Electron Microscopy (SEM) .................................................................................. 57

ECONOMIC EVALUATION ........................................................................................................... 64 Cost Determination ................................................................................................................ 64 Cost Evaluation .................................................... : ............................................ , .................... 69

SUMMARY AND CONCLUSIONS ................................................................................................ 71

GENERAL RECOMMENDATIONS ............................................................................................... 74 -

CONSTRUCTION RECOMMENDATIONS ................................................................................... 75

ACKNOWLEDGMENTS ............................. ., .................................................. : ..... ;····· ..................... 76

REFERENCES ................................................................................................................................... 77

APPENDIX A APPENDIX B APPENDIXC

Page 4: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I. I I I I I I I I I . I I ·I. I. I ,,

Ill

ABSTRACT

This research project was directed at laboratory and field evaluation of sodium montmorillonite clay (Bentonite) as a dust palliative for limestone surfaced secondary roads. It was postulated that the electrically charged surfaces (negative) of the clay particles could interact with the charged surfaces (positive) of the limestone and act as a bonding agent to agglomerate fine (- #200) particulates, and also to bond the fine particulates to larger ( + #200) limestone particles.

One mile test roads were constructed in Tama, Appanoose, and Hancock counties in Iowa using Bentonite treatment levels (by weight of aggregate) ranging from 3.0 to 12.0 percent. · Construction was accomplished by adding dry Bentonite to the surfacing material and then dry road mixing. The soda ash/water solution (dispersing agent) was spray applied and the treated surfacing material wet mixed by motor graders to a consistency of 2 to 3 inch slump concrete. Two motor graders working in tandem provided rapid mixing. Following wet mixing the material was surface spread and compacted by local traffic.

Quantitative and qualitative periodic evaluations and testing of the test roads was conducted with respect to dust generation, crust development, roughness, and braking characteristics. As the Bentonite treatment level increased dust generation decreased. From a cost/benefit standpoint, an optimum level of treatment is about 8 percent (by weight of aggregate). For roads with light traffic, one application at this treatment level resulted in a 60-70 percent average dust reduction in the first season, 40-50 percent in the second season, and 20-30 percent in the third season. Crust development was rated at two times better than untreated control sections. No discernible trend was evident with respect to roughness. There was no evident difference in any of the test sections with respect to braking distance and braking handling characteristics, under wet surface conditions compared to the control sections.

Chloride treatments are more effective in dust reduction in the short term (3-4 months). Bentonite treatment is capable of dust reduction over the long term (2-3 seasons). Normal maintenance blading operations can be used on Bentonite treated areas.

Soda ash dispersed Bentonite treatment is conservatively estimated to be more than twice as cost effective per percent dust reduction than conventional chloride treatments, with respect to time. However, the disadvantage is that there is not the initial dramatic reduction in dust generation as with the chloride treatment. Although dust is reduced significantly after treatment there is still dust being generated. Video evidence indicates that the dust cloud in the Bentonite treated sections does not rise as high, or spread as wide as the cloud in the untreated section. It also settles faster than the cloud in the untreated section. This is considered important for driving safety of following traffic, and for nuisance dust invasion of residences and residential areas .

The Bentonite appears to be functioning as a bonding agent to bind small limestone particulates to larger particles and is acting to agglomerate fine particles of limestone as evidenced by laboratory sieve analysis data, and by SEM micrographs. This bonding capability appears recoverable from environmental effects of winter, and from alternating wet and dry periods. The Bentonite is able to interact with new applications of limestone maintenance material and maintains a dust reduction capability.

Page 5: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I ·1 I I I I .I I I I II I I I I I ·I 1.

1

INTRODUCTION

This final report presents the results of research project HR-351 entitled, "Bentonite

Treatment for Economical Dust Reduction on Limestone Surfaced Secondary Roads."

Surfaces of fractured calcium carbonate or limestone particles are known to exhibit a positive

electrochemical surface charge [1]. It had been postulated that introduction of a material of an

opposite surface charge might function as an "electrochemical glue". The oppositely charged

particle may act to bind small limestone dust particles together in an agglomerate that would not

become airborne dust under traffic. The oppositely charged particles might also bind small

limestone dust particles to surf aces of larger particles, again preventing them from becoming

airborne dust under traffic.

Previous laboratory research studies, [2] using a sodium montmorillonitic clay (Bentonite) as

the negatively charged material appeared promising for use to reduce dusting in a commercial

manufacturing application. Initial laboratory and field application for limestone surfaced secondary

roads was conducted under Iowa DOT project HR-297 [3]. This project focused on development of

field construction and application procedures using up to 3 percent Bentonite (by weight of loose

surfacing material). The percent Bentonite treatment was kept low in this project due to concern

with the influence that Bentonite might have on vehicular handling, braking, and stopping distance.

Results of this project indicated that Bentonite treatment could be accomplished using conventional

equipment available to most counties. Braking and handling characteristics were not adversely

affected. A 30 to 40 percent long-term (18-24 months) dust reduction was observed.

The purpose of project HR-351 was to evaluate the effectiveness of higher levels of

Bentonite treatment relative to dust generation, crust development, roughness and braking

characteristics on limestone surfaced roads. The project was separated into two phases.

Phase I: This phase involved additional laboratory testing to optimize the application

amount of the sodium carbonate (soda ash) disposing agent and construction of a test road using up

to 9 percent Bentonite treatment.

Page 6: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

2

Phase II: The result of Phase I were used to evaluate the feasibility of high application rates

and guide application amounts and construction procedures for additional test road construction.

Additional test roads were constructed in Appanoose and Hancock counties.

The following report presents .the research results for Phase I and Phase II of the HR-351

project.

LABORATORY TESTING

In order to separate the bentonite (clay) particles in a bentonite/water solution, a dispersing

agent is necessary. Sodium carbonate (soda ash) was used and acts to temporarily neutralize clay

particle charges, which minimizes agglomeration of the bentonite during the application process.

The following laboratory testing was conducted to optimize the amount of soda asp solution to use

as the dispersing agent for the bentonite treatments.

The standard hydrometer test specified by ASTM D 422 was modified and used to evaluate

effectiveness of the soda ash compared to the standard dispersing agent sodium hexametaphosphate

(Calgon). Modifications of the test were as follows.

1. Sample size was reduced from 50 grams to 25 grams.

2. Hydrometer readings were replaced with particle settlement observations.

Soda ash concentrations of 0.4, 0.8, 1.2 and 1.6 percent (by weight of water) were prepared.

Table 1 summarizes observations made during laboratory preparation of the samples.

Figure 1 presents the results of settlement observations of the standard Calgon solution as a

function of time. After 280 hours, the Calgon was acting to maintain most of the small particles in

suspension with only 15 ml of clear water observed in the hydrometer (1000 ml - 985 ml). However,

particle flocculation began to occur at 37 hours and continued to increase over time as indicated by

the dark bands at the bottom of the bars on Figure 1.

I I I I I I I ,, I ·I I I .I I I I I I I

Page 7: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-----~~--------~---

------ -----· ---

1000 1,000 1,000 1,000 1,000 995 990 990 990 990 990 985 985 -

~ s ~ Q.) ..... 800 Q.) -

s 0 .....

~ 600: c:: ·-Q.) ..... ·-c::

0 ..... c:: 400 Q.)

i:Q ~

0 ..... ..c: bl) ·- 200 Q.)

::i:=

0 J 3 4 6 23 26 37 109 133 157 181 205 280

Time, hrs

----------------1 1 ·--Particle Settlement J

Figure 1. Settlement of Bentonite in A Sodium Hexametaphosphate (Calgon) Solution

Page 8: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

---~---~-------------------------

4

Table 1. Observations made during hydrometer sample preparation.

Solution Initial Mixine Air Jet Mixin2

0.8% Calgon • Dispersed easily with a few small • Mixed very well. clumps left after stirring. • Sample was very liquid like.

0.4% Soda Ash • Did not mix very well. • Sample stuck to the sides of the • Many clumps left after stirring. hydrometer during mixing.

• Had to add an extra 50 ml of water in order to get the sample to disperse.

• Sample was very thick after mixing.

0.8% Soda Ash • Did not mix very well. • Mixed okay, but sample was still very • A few clumps left after stirring. thick. • Some material stuck to the sides of the • Had to add an extra 50 ml of water to

hydrometer. make it mixable.

1.2% Soda Ash •Mixed okay. • Sample mixed very well. • Dispersed easily with a few small • Sample was liquid like after mixing.

clumps left after stirring. • A few clumps were noticed after mixing.

1.6% Soda Ash • Mixed very easily. • Sample mixed very well. • Dispersed very well into a liquid with • Sample was liquid like after mixing.

only a couple clumps left after stirring.

Figures 2 through 5 present the results of the soda ash tests. There was no evidence of

flocculation and observable sediment at 280 hours for any of the treatment levels. This indicates that

the soda ash is highly effective at preventing agglomeration and flocculation of the bentoni~ particles.

The soda ash treatments were not as effective in maintaining the clay particles in complete

suspension for an extended period. This is evidenced by the clearing of the solution at the top of the

hydrometer and is shown on Figures 2 through 5. With increased soda ash

concentration, the solution clearing becomes more pronounced, especially after five hours. Since

construction proceeds rapidly, however, this should not be problematic in the field. The soda ash

appears highly effective at relatively low concentrations. Based on these results, construction

proceeded using the 0.4 percent soda ash solution. Observations during field construction, however,

indicated this may need to be adjusted, and will be discussed later in the report.

I I I I I I I I I I I I I I I I I

Page 9: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

.. - -' - .. - - - - - - -'- - - .. -·- ----~----

1000 ---- 990 985 985

....:! s ...:- 800 Q) -..... Q)

s 0 ....

~ 600 s= ·-Q) ..... ·a 0 ..... s= Q) 400 ~

C+-1 0 ..... -..c: bl) ·-Q)

:I: 200

0 3 ' 4 6 23 26 37 109 133 157 181 205 280

Time, hrs

Figure 2. Settlement of Bentonite in a 0.4 Percent Soda Ash Solution

Page 10: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

1000 - 970

~ 8

"' .... 800 (I) -Cl)

8 0 .... ~ :::r: 600 s:: ·-(I) -·-s:: 0 -s:: (I) 400 -~ f+-4 0 -..c:: bO ·-(I)

:::r: 200

0 2 3 5 22 25 36 108 132 156 180 204 279

Time, hrs

Figure 3. Settlement of Bentonite in a 0.8 Percent Soda Ash Solution

-------------------

Page 11: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-----~-------------

----

1000 - 970

~ e ..........

800 Q) .... Q)

e 0 $...,

R ::r: 600 -c:: ·-Q) .... ·-c:: 0 .... c:: Q) 400 ~ '-0 ....

..c: on ·-Q)

::r: 200

0 2 3 5 22 25 36 108 132 156 180 204 279

Time, hrs

Figure 4. Settlement of Bentonite in a 1.2 Percent Soda Ash Solution

Page 12: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

1000 985

~ 6

"' ...... 800 Q.) ..... Q.)

6 0 ......

R ::x:: 600 c:: ·-Q.) ..... ·-c:: 00 0 ..... c:: Q.) 400 -r:Q ~

0 ..... ..c= bJ) ·-Q.)

::x:: 200

0 1 2· 4 21 24 35 107 131 155 179 203 278

Time, hrs

Figure S. Settlement of Bentonite in a 1.6 Percent Soda Ash Solution

----~--~~--~-------

Page 13: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

9

TEST ROAD SELECTION

Desirable criteria for test road selection, in Phase I, included relatively flat topography and

uniform subgrade soils. A traffic count in the vicinity of 70 vehicles per day (vpd) and a minimal

number of residents was also desirable. The criteria used in Phase II was the same as that used in

Phase I except with the following changes. First, a higher traffic count (around 200 vpd) was

desired. Second, more truck traffic containing heavier loads was desirable. The engineers in

Appanoose and Warren County were visited for potential participation. The roads in Warren County

did not meet the desirable criteria. Appanoose County expressed a strong interest in participation.

Tama County Test Road (Phase I)

The test road is a north-south road located one mile north and one-half mile west of the town

Garwin, Iowa. It lies between sections 2 and 3, T85N and R16W in Tama County as shown on

Figure 6. The road exhibited a typical amount of crushed limestone surfacing material and is

reasonably flat with few residents along the road. The 1989 traffic count obtained from the Iowa

Department of Transportation (Iowa DOT) was 60 vpd.

The aggregate present was classified as an impure limestone from x-ray fluorescence

analysis. The aggregate is from the Montour quarry in Tama County. This aggregate has an

abrasion value of 38 which was obtained from the Iowa DOT quarry information. The abrasion

value of 38 is below 45 which is the maximum specification for a grading B in the American

Association of State Highway and Transportation Officials (AASHTO) T96 [4] and 4120.04

specification from the Iowa DOT [5].

Appanoose County Test Road (Phase II)

The test road is a north-south road located two and one-half miles west of Highway 5 on J46.

The road is located in sections 15 and 22, T68N and R18W, in Appanoose County as shown on

Figure 7. The test road is on T20 from J46 to the landfill located approximately two and four-tenths

miles south of J46. The road is reasonably flat with nine residents along the test sections. The 1990

Page 14: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

z v co

I .--

10

R-16W

Figure 6. Test road location in Tama County.

traffic count obtained from the Iowa DOT was 200 vpd with approximately 10 to 30 percent being

truck traffic.

The road was being reconstructed during preliminary evaluation. It was estimated that 600

tons per mil,e of crushed limestone was to be applied to the road. The road reconstruction was

completed on June 21, 1993. After the road was compacted by a roller and then a week of traffic

compaction, the road was treated with Bentonite.

The agregate present was classified as a limestone from x-ray fluorescence analysis. The

aggregate is from the Lemley East #5 quarry in Appanoose County. This aggregate has an abrasion

I I I I I I I I I I· I I I I I I I I I

Page 15: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

11

Figure 7. Test road location in Appanoose County

value of 26, which is an average of six tests conducted by the Iowa DOT from 1991 to 1993. The

abrasion value of 26 is below the specified maximum specification of 45.

Hancock County Test Road (Phase II)

Hancock County also expressed strong interest in participating in the research project. The

test road is a north-south road located south of Highway 18, six miles west of Britt. It lies between

sections 32 and 33, T96N and R26W in Hancock County as shown on Figure 8. The 1991 traffic

count obtained from the Iowa DOT was 110 vpd.

Page 16: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

TEST ROAD LOCATION

z IS) en

I I-

R-2GW

I')

12

E u I srn.s~ I} ""'' '"'"" ,,

Figure 8. Test road location in Hancock County.

kl

630

T IS

IS

R38

The road was surfaced with gravel, which had to be removed. The County engineer, J.

William Waddingham, agreed to remove the gravel. Once the gravel was removed, approximately

150 tons per mile of crushed limestone surfacing material was applied. The road is reasonably flat

with only two residents and a golf course along the road.

The crushed limestone that was applied to the road is classified as a dolomite limestone. The

aggregate is from the Garner North quarry located in Hancock County. This aggregate has an

abrasion value of 25 which is an average of six tests conducted by the Iowa DOT from 1991 to 1993.

Again, this abrasion value of 25 is below the maximum specification of 45.

I I I I I I I I I I I I I I I I I I I

Page 17: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

13

TEST ROAD CONSTRUCTION

Tama County Layout

Construction of the one mile test road was completed on August 5, 1992. The test section

layout is shown in Figure 9. The layout indicates the locations of the control section, and various

Bentonite treated sections.

Tama County Construction

Materials and Egyipment

The construction materials consisted of the existing limestone surf acing materials, Bentonite,

soda ash, and water. The limestone surfacing materials were from the Montour quarry. The

Bentonite (feed grade) was purchased from the Iowa Limestone Company of Alden, Iowa and the

soda ash was purchased form Harcos Chemical of Omaha, Nebraska. The water for the project was

supplied by the City of Garwin.

Equipment and personnel consisted of one maintainer for blading operations, a dump truck

for Bentonite distribution, and two operators all supplied by Tama County. A 3000 gallon _water

truck distributor and operator were supplied by Peterson Construction Incorporated.

Procedure

All loose surfacing material was tight bladed and windrowed to one side of the road. Several

cross-section windrow measurements were taken to estimate the amount of loose limestone surfacing

material present to calculate the amount of Bentonite needed for treatment.

The spacings of the 50 pound Bentonite bags were calculated for 3, 5, 7 and 9 percent

treatment, by weight of air dry aggregate. The bags were placed manually at the calculated spacings

and then were manually spread on top of the windrowed aggregate. The aggregate and Bentonite

were dry mixed by blading the windrow four times followed by a center spread of the windrow.

Application of the soda ash solution and blade mixing proceeded simultaneously until a consistency

of a 2 to 3 inch slump concrete was obtained. This material was blade mixed a minimum of four

times after each soda ash application. After final mixing, the treated material was center spread and

Page 18: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

l

---~~ N

Control 3% lkntonite 5% Bentunite 7''/o Bcntonite 9% Bentonite

~ riQ' c: ., ~

~

-3 ~

3 ~

('j 0 c: = ..... ~ ..... ~ fJl .....

Begin Project ., End Project '" t-.> 0

0 ~ Q. Sta53+00 Sta 4 + 00 5-

;" ~ 0 ~ c: ;"

~ J:.>. .. J:.>. "-' l;J tJ '" u 00 J:.>. 0

'" 00 J:.>. 0 °' Iv 00 J:.>. 0 °' "J

t- + ·I I· c + + + I ·I ·I +. + 0 0 0 0 0 0 0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0 0 0 0 0 0 0

- - - - - - - - - - - - - - - - - - -

Page 19: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

15

left for compaction by traffic.

Obseryations

The following observations were made during construction of the.Tama County test road.

Construction was completed in one day. More expedient construction could be obtained using two

blading patrols. Agglomeration and balling of Bentonite treated materials occurred in the 5 percent

section and became more pronounced in the 7 percent and 9 percent sections. The use of two

blading patrols and a 1.2 percent soda ash solution were recommended after the construction of the

Tama County test road.

Appanoose County Layout

Construction of the 1.4 mile test road was completed on June 28, 1993. The test section

layout for construction of the road is shown in Figure 10. The layout indicates the locations of the

control section, calcium chloride section and various Bentonite treated sections.

Appanoose County Construction

Materials and Eguinment

The Bentonite (50 pound bags) used for the project was obtained from the Iowa Limestone

Company of Alden, Iowa and the soda ash from Harcros Chemical of Omaha, Nebraska. Water was

supplied by the city of Centerville.

Two motor graders, a flat bed truck for the distribution of Bentonite, and three operators were

supplied by Appanoose County. Two 1000 gallon water distributors were used, with one provided

by Appanoose County and the other provided by the city of Centerville. Two more operators were

provided by Appanoose County for the water distributors

Procedure

The procedure was the same as that used at the Tama County site, with the exception that two

motor graders were used and different percentages of Bentonite were also applied. The average of

Page 20: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

---11 .... ~ N

8%J Oentonite 10% nent•)llile Ca Cl 12°/) Lientonite 6% Bentonite

~ tJQ T 20 c ., ~ ,_. p

End Project Deg in Project

Sta 74 + 00 Sta I + 50

--._) °' V> ..... \;) ,_,

0 0 0 0 0 0 0 0

t· I t- + + I ' ·t

0 0 0 0 0 0 0 0

0 0 0 0 0 0 0 0

- - - - - - - - - - - - - - - - - - -

Page 21: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

17

the different sections indicated an approximate range of 94 to 146 tons per mile of loose surfacing

material. After windrow measurements were taken, Bentonite bag spacings were calculated for 6, 8,

10, and 12 percent (by weight of air dry aggregate) of Bentonite treatment. Mixing was performed

the same way as in Tama County. The amount of solution added to the sections was as follows:

approximately 1500 gallons of solution added to the 6 percent Bentonite treated section, 2000

gallons to the 8 and 10 percent sections, and 2500 gallons to the 12 percent section.

Obseryations

Construction proceeded rapidly and was completed in one day. Bag placement, bag

spreading, and dry mixing was completed in approximately 1 hour and 40 minutes. Using two

patrols expedited this part of the construction considerably. The most time consuming part was

waiting for the water trucks to fill up and return to the site to unload. For the four sections, it took

approximately five hours to complete the water application and wet mixing. It is recommended that

a 3000 or 5000 gallon water distributor be utilized to speed up this part of the process.

Slight agglomeration of the Bentonite was observed in the 12 percent Bentonite treated

section. The other sections did not show much evidence of agglomeration. This was mainly due to

the increased percentage of soda solution that was recommended after the Tama County test road

construction. Overall, the construction procedure worked very well.

Hancock County Layout

Construction of the 0.6 mile test road was completed on June 22, 1993. The test section

layout for construction of the road is shown in figure 11, and indicates the control section and

various Bentonite treatment sections.

Hancock County Construction

Materials and Equipment

The Bentonite and soda ash used for the project were obtained from the same sources as

those used for the Appanoose County project. Water was supplied by the city of Britt. One motor

Page 22: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

'Tl ~· c ., l'D .... .... ::i:: ~

= (')

~ ~

('1 0 c = -~ -l'D rlJ -., 0 ~ Q.

5' '< 0 c l""'

0 0: c r.n ::r:: :;::

c-2

00

w N

+ 0 0

End Project

Sta 33 + 80

tv 00

+ 0 0

N +.

+ 0 0

8% Bcntonitc

t-.J 0

+ 0 0

°' + 0 0

N

+ 0 0

5% Bcntonitc

00

+ 0 0

/ Begin Project

Sta I + 50

+.

+ 0 0

00

0

+ 0 0

..... 00

-------------- - - - - -

l

Page 23: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

19

grader, a dump truck, and flat bed trailer for the distribution of Bentonite, a 1000 gallon water truck,

a tractor and roller, and three operators were supplied by Hancock County.

Procedure

The procedure was the same as that used in Tama County. The average loose surfacing

material present for the different sections ranged from 90 to 96 tons per mile. Bentonite bag

spacings were calculated for 5 and 8 percent Bentonite treatment The construction process was the

same as the Tama County procedure. Approximately 2000 gallons of solution were added to each

section. After final mixing, the treated material was center spread and then compacted by one pass

of a roller.

Pre-construction work and construction proceeded rapidly and were completed in one day.

Pre-construction consisted of tight blading the loose surfacing material to one side, taking windrow

measurements, obtaining a loose unit weight, and then calculating bag spacings. Once this was

completed, construction proceeded with bag placement, spreading of Bentonite, dry mixing, soda ash

solution application, and final mixing.

Obseryations

The construction could have been expedited by using a 3,000 or 5,000 gallon water truck and

two patrols, but personnel were limited due to such a short notice to proceed with the construction.

Slight agglomeration of the Bentonite was noticed in the 8 percent Bentonite treated section.

FIELD EVALUATION

Field evaluation consisted of qualitative evaluation of dust generation, crust development,

roughness and braking characteristics. Evaluations began on August 7, 1992, and continued through

November 12, 1992, for Phase I. A relatively wet fall limited the number of observations of the road

under dry surface conditions for Phase I. Evaluations started up again on June 14, 1993, and

continued through October 6, 1993, for the three sites of Phase II. With an extremely wet summer

and relatively wet fall there were a limited number of observation days available when the roads

Page 24: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

20

were under a dry surf ace condition. Evaluation of the Tama and Appanoose Counties test roads

during 1994 started in May and continued until September.

Panel Selection

The following individuals assisted in conducting periodic qualitative evaluations for Tama,

Appanoose and Hancock Counties.

Dwight Surber Assistant County Engineer

Gary Harris Materials Research Assistant

Kenneth Bergeson

Stacy Brocka

Jay Waddingham

Associate Professor

Graduate Research Assistant

Graduate Research Assistant

Evaluation Criteria

Tama County

Iowa DOT

Iowa State University

Iowa State University

Iowa State University

An evaluation form was developed by Iowa State University personnel and was used by all

the panelists for their observations. The form contained the following information: weather

conditions (day of and day prior to evaluation), maintenance conditions and surfacing material

conditions either dry, damp or wet. The panel evaluated the amount of dust generation for each

Bentonite treated section compared to the control section and evaluated the crust development and

roughness of each section. The dust generation was expressed as a percentage of the control with the

control having a value of 100 percent. The crust development and roughness were evaluated on a

rating system from 0 to 5 with 0 being poor and 5 being excellent. Copies of the forms used in

Phases I and II are shown in Appendix A.

Visual Inspection

Visual inspection was initiated at the end of construction of the Tama County road in 1992.

It was used as one method to evaluate the effectiveness of the Bentonite treatment and was continued

throughout the 1992, 1993, and 1994 testing seasons to evaluate the duration of the treatment.

I I I I I I I I I I I I I I I I I I I

Page 25: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

·----

21

Visual Evaluation Procedure

For visual evaluation of dust generation the test roads were driven in both directions and the

effectiveness averaged between the two directions. Each test section was approached at 45 mph and

evaluated through the rearview mirror. Criteria included the opaqueness of the dust .cloud produced,

time it takes the cloud to settle, and the distance the dust cloud traveled perpendicular to the road.

Visual inspection included the roughness of the road, crust development, maintenance

conditions, and other notes that concern the roads conditions and dust generation. The roughness

was evaluated to determine if the clay addition to the surface material created washboarding or other

effects which may cause a hazardous driving environment. The crust development was evaluated to

give an indication of the wheel path size as compared to the control section's surface. Maintenance

conditions included such things as: approximations of the last blading, windrow size and which side

of the road, and how well maintained the road surface was kept.

visual Eyaluation Results

Tama County, Appanoose County, and Hancock County evaluations are tabulated in

Appendix B for the 1992, 1993, and 1994 testing years.

Shown in Tables 2 and 3 are the average year end results from observation at the Tama

County, Appanoose County, and Hancock County test road locations, respectively. All three

evaluation years are shown with the averages for dust reduction, crust development, and roughness.

The averages tabulated are for dry surfacing materials only.

Dust Generation

The dust generation value represents the comparison in dust reduction for the treated sections

compared to the untreated control section. The results tabulated are qualitative evaluations of the

conditions in the field. Caution must be taken in interpreting the results from visual observations.

The 1992, 1993, and 1994 dust generation results tabulated in Table 2 are also shown on

Figure 12 for the Tama County test road. Shown in Figure 12 is the dust generation percentages for

Page 26: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

22

Table2. Visual evaluation averages for dry surface materials in Tama County.

1992 I I 1993 I II 1994/ II

Evaluation Cat~orl'. Treatment Average !n=19} Average {n=2} Average !n=7}

Dust Generation Control 100 100 100

3 55 30 76

5 44 28 69

7 39 45 78

9 32 50 79

Crust Development* Control 1.4 2.0 1.7

3 2.2 4.0 3.0

5 3.2 4.5 3.4

7 3.1 3.0 3.3

9 3.1 2.5 3.0

Roughness * Control 3.7 2.5 3.7

3 3.9 4.0 4.1

5 3.9 5.0 4.3

7 3.7 3.5 4.0

9 3.2 2.5 3.9

*The rating system used goes from 0 to 5 with 0 being poor and 5 being excellent

dry surfacing materials averaged over the testing season for each year. As can be seen the dust

generated in each of the test sections is less than the dust generated in the control section. In the

1992 testing year the control had the most dust generated with each Bentonite section showing a

consecutive reduction. In 1993 only 2 observations were conducted due to a wet testing period. The

two observations showed the 3 percent and 5 percent had a slight increase in efficiency with the 7

percent and 9 percent Bentonite treatment levels showing a loss in efficiency. This maybe attributed

to the 7 percent and 9 percent sections being on the steeper slopes of a hill and the Bentonite may

have been washed down by the rain onto the 3 percent and 5 percent treatment sections increasing

I I I I I I I I I I I I I I I I I I I

Page 27: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

23

Table 3. Visual evaluation averages for dry surface material in Appanoose and Hancock Counties.

1993 /II 1994 I II 1993 I II Appanoose Appanoose Hancock

Evaluation Cat 0 Treatment Avera e n=3 Avera e n=S Treatment Avera e n=2

Dust Generation Control 100 100 Control 100

6 52 85 5 80

8 47 89 8 73

10 43 90

12 25 82

Crust Development * Control 4.0 3.4 Control 1

6 4.0 3.4 5 2

8 4.0 3.4 8 2

10 4.3 3.2

12 4.7 3.6

Roughness * Control 2.3 2.6 Control 3.5

6 2.3 2.6 5 3.5

8 2.3 2.6 8 3.5

10 2.3 2.6

12 2.0 2.6

*The rating system used goes from 0 to 5 with 0 being poor and 5 being excellent.

the amount of Bentonite and thus increasing the efficiency. Another possibility is that the 7 percent

and 9 percent lost some of its efficiency due to the routine addition of surfacing material during the

spring of 1993. The 1994 testing season also showed an increase in dust generation. This could be

due to addition of surfacing material in 1994 or washout of the Bentonite out of the system. From

Figure 12 we can see that the Bentonite treatment is still partially effective after three seasons of

testing and two additions of surfacing materials.

The 1993 and 1994 results tabulated in Table 3 for Appanoose County are also shown on

Figure 13. Figure 13 shows a similar trend as the Tama County test road showed for the first year.

Page 28: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

~ 0

c .2 1! QI c QI

C> .... Ill :s c

~ c ~ Cb c Cb 0 i;; :s 0

120

100

80

60

40

20

0 Control

24

I • 1992 D 1993 1211994 I

3 5 7 Pecent Bentonite Treatment, %

Dry surface materials Tama County

9

Figure 12. Dust generation for the Tama County test road.

120

I o 1993 o 1994 I 100

80

60

40

20

-0 Control 6 8 10 12

Percent Bentonite Treatment, % Dry surface materials Appanoose County

Figure 13. Dust generation for Appanoose County test road.

I I I I I I I I I I I I I I I I I I I

Page 29: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

25

The control section had the most dust generated with the Bentonite treated sections having less dust

generated. As the Bentonite tfeatment level increased for 1993 the dust generated decreased. The

trend was the same, but the Bentonite treatment at Appanoose County was not as effective as the

Tama County treatment. The Tama County location had reductions greater than 60 percent for the 7

percent and 9 percent section where the Appanoose County Test road had reductions only slightly

greater than 50 percent. In 1994, the Appanoose County location showed a much greater increase in

the dust generated in the treated sections. This increase may be due to the high fines content in the

Appanoose County surfacing materials and the higher amount of truck traffic on the test road .. Even

though there was a greater increase in the dust generated on the Appanoose County test road the

treated sections all showed reductions in dust generated after two testing seasons as compared to the

control section.

The high fines content and increased truck traffic of the Appanoose County test road may not

be the only reason this Bentonite treatment was less effective than the Tama County test road.

During construction of the Appanoose County test a 1.2 percent soda ash solution was used

compared to the 0.4 percent soda ash solution used during the Tama County test road construction.

This increased soda ash solution may have kept the bentonite dispersed longer. The longer

dispersion may have allowed the heavy rains during the summer of 1993 to wash the Bentonite from

the surfacing material. If the Bentonite did get washed out of the surfacing materials the amount of

Bentonite available to stabilize the limestone fines would be decreased. If there is not enough

Bentonite present there would be an increase in dust generation.

The dust generation observations for 1993 in Hancock County are also shown in Table 3.

The Hancock County test road also shows a decrease in dust generation with an increase in Bentonite.

treatments. The effectiveness of the treatments is not as good as the other two sites for this testing

year. This is probably due to having some loose gravel still remaining on the road, as well as a

gravel crust, that may affect the ability of the Bentonite to bond with the fine limestone particles.

This might be the case since gravel has a net negative surface charge which repels the Bentonite

Page 30: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

26

from attracting to particles effectively because Bentonite also has a net negative surface charge. A

thin layer of fine gravel particles was observed beneath the limestone surfacing material on the road.

To validate the visual evaluations a dust collector was developed to try and quantify the

amount of dust generated by a moving vehicle. This dust collector had a variability of+/- 10 percent

so exact quantitative evaluation wasn't possible. The dust collector could be used for qualitative

information and comparison to visual evaluations.

Shown on Figure 14, are the results of the 1994 visual evaluations and the dust collector data.

Both Tama and Appanoose Counties results are shown. The data is also presented in Table B9 of

Appendix B. The visual evaluation of dust generated displayed on Figure 14 are the average values

for the days the dust collector was used. This shows that most of the differences of the two

evaluation techniques are within the range of the error of the dust collector. The results of this

testing validates the use of the visual method as an evaluation tool.

Crust Deyelopment

Crust development was evaluated by rating on a scale from 1 to 5. A rating of 1 would be an

. area with no crust and just having loose surfacing materials on the surface of the road. A rating of 5

would be an excellent crust development with little loose surfacing stone present in the wheel path

area. This rating system was used throughout field testing.

The Tama County average results of the 1992, 1993, and 1994 testing seasons for crust

development which were tabulated in Table 2 are shown on Figure 15. The control section exhibits

less crust development than the Bentonite treated sections. In 1992, the 3 percent section had

approximately one and a half times more crust development than the control and the 5 percent, 7

percent, and 9 percent sections had approximately twice the crust development as the control. In

1993, the 3 percent and 5 percent exhibited increased crust development and the 7 percent and 9

percent exhibited less crust development possibly due to the Bentonite being washed down the hill

by rain or addition of surface material in the 7 percent and 9 percent sections. In 1994, a reduction in

crust development was observed in the 3 percent and 5 percent treatment sections. This maybe

attributed to the addition of surfacing material to the road. Each year showed a crust

I I I I I I I I I I I I I I I I I I I

Page 31: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I

100

~ 0 80 ~

c: 0 ;; t! 60 Q) c: Q)

(!) ...,, "' 40 ::I c

20

0 Control 3

27

• Visual O Dust Collector

5 7 9 Control 6 8 Tama County Appanoose County

Percent Bentonite Treatment,% · Dry surface materials

10

Figure 14. 1994 dust collector and visual evaluation comparison.

12

development greater than the control section which also indicates the Bentonite treatment is still

functioning after three years.

The crust development results that were tabulated in Table 3 for the Appanoose County test

road are presented in Figure 16. There are really no trends in the data shown. The crust

development is fairly constant for all the test sections for both years. There is a difference between

the 1993 and 1994 testing years, but this maybe due to the difference in evaluator determination of

crust development. The relatively constant crust evaluations may be attributed to the high amount of

fines and the truck traffic present on the Appanoose County test road. The Appanoose County test

I road did not appear to be bladed as frequently as the Tama County test road. If blading operations

I

Page 32: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

28

Sr.=:============::=:::;~~~~~~~~--i

I • 19920 19930 19941 c4 Cl> E c.. .2 3 ~ Cl>

!: 2 "' ~ ._ 01

0

5

4 -c ~ ~3 ~ G> c u; 2 2

(.)

1

0

-

-

-

-

-

-

-

-

-

Control ,3 5 7 Pecent Bentonite Treatment, %

Dry surface materials Tama County

9

Figure 15. Crust development for Tama County.

,......,,---

....,___

""

Control

I I 0 1993 0 1994 -- -

.>--- ,.___ ,____

6 8 10 Percent Bentonite Treatment, %

Dry surface materials Appanoose County

,_...,....--

'----..

12

Figure 16. Crust development for Appanoose County.

I I I 1· I I I I I I I I I I I I I I I

Page 33: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

29

weren't as frequent the surfacing material would stay locked up in the crust and have a more uniform

crust evaluation. The observations in Hancock County show that the development was not very

good even though the treated sections were two times better than the control. Again it is anticipated

that the presence of gravel inhibited any wheelpath development.

Roughness

Roughness was evaluated on a scale from 1 to 5. A rating of 1 would be a ~urface with a lot

of pot holes and washboarding present. A rating of 5 would be an excellent rating with the surfacing

having a smooth ride and absence of potholes and washboarding. This system was also used

throughout Phase I and Phase II.

The data in Tables 2 and 3 for Tama and Appanoose Counties are presented on Figures 17

and 18. There are no definite trends present for either Tama, Appanoose or Hancock Counties. The

Tama County and Hancock County locations generally had higher roughness ratings meaning the

road were smoother to drive down. This could be because the Tama County and Hancock County

test roads had less vpd and less truck traffic which would require less maintenance. The Tama

County and Hancock County sites appeared to be maintained more frequently which might be a

reason for the better roughness ratings.

The rough.ness of each test road was tested by using the Iowa DOT roughometer to obtain

some quantitative values. The roughometer provides a measure of the roughness of a road tested at a

speed of 20 mph. The roughness is measured by the movement of a standard wheel on the

roughometer trailer. The roughness and revolutions of the wheel are recorded during the test. The

roughness of the road, in inches per mile (in/mi), is then calculated.

The intent of this test was to compare the roughness of each treated section at each site. The

comparison is not intended to compare the roughness between the different sites, but to compare

each section at a particular site.

The roughness was measured in each wheel path, both northbound and southbound. All of

the tests were averaged for each section per site and are shown graphically on Figure 19. The actual

data obtained from the Iowa DOT is given in Appendix C. The roughness obtained in Tama County

Page 34: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

5

:a 4 Cl) c -§,3 :::s 0

a:: 2

1

0

2.5

en 2 en Cl> c -§, 1.5 :J 0 a::

1

0.5

Control

30

• 1992 D 1993 D 1994

3 5 7 Pecent Bentonite Treabnent, °lo

Dry surface materials Tama County

Figure 17. Roughn~ evaluation forTama County.

,, • ..... ".

~·-: ';. ''

Control 6 8 10 Percent Bentonite Treatment, %

Dry surface materials Appanoose County

12

9

Figure 18. Roughness evaluation for Appanoose County.

I I I I I I I I I I I I I I I I I I I

Page 35: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-------------------I ffiI] Tama 183 Appanoose • Hancock I

300 289

250

.......

~ 200

159 154

I 122

1

m

4

1:::!.:;:1,::.1 .. ,:.

11'1

.·11 .... ll1I rn~ =·:: •...

0 L_l:~·llL___f.1~11·L--__J;l~"IL___L·~m~-.J.:t~'~~~....!..=>CL-..__L:>a_~-DL.l~_.OQ_~J>LJ.~~:i__~~

100

50

Control 3 5 .7 9 Control 6 8 10 12 CaCl 5 8 Sections

Figure 19. Average roughness measurements by the Iowa DOT roughometer.

Page 36: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-- --- -- ---------------------------------------~

32

ranged from 122.5 to 159 inches per mile. As seen on Figure 19, the 5 percent section is the

smoothest. The trend then continues with the 3, 7 and 9 percent sections, followed by the control

section. This is the same trend as the qualitative observations.

The roughness measured in Appanoose County does show a similar trend as that observed in

Tama County, as shown on Figure 19. The roughness for the treated sections starts out decreasing in

roughness with increased Bentonite treatment and then starts to increase with the calcium chloride

section being the worst section. The 10 percent section appears to be out of place and maybe due to

the turning traffic at the intersection located in this section.

There is a slight decrease in roughness with increased Bentonite treatment for Hancock

County as shown on Figure 19. The control section was unable to be tested due to the shortness of

the section.

Braking Characteristics

Again, a major concern at the start of the project in Appanoose County was the influence of

the high levels of Bentonite treatment on braking characteristics and safety. To test the braking

characteristics when the surface material was wet or saturated, a car was driven at 25 mph at which

time the brakes were locked to make the tires skid across the road surf ace. The distance to bnng the

car to a complete stop from the point of the brakes being locked was measured. Four runs were

tested in the wheelpaths in each section right after a heavy rain. These four tests were averaged and

then plotted as shown on Figure 20. There is no clear trend evident between braking distance and

the amount of Bentonite treatments.

Video Evaluation

A video camera was used to document actual site conditions on each day of testing. The

camera was setup in the same position each time which allows for comparison between different

testing days and times.

I I I I I I I I I I I I I I I I I I I

Page 37: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-------------------40 .--~~~~~~~~~-.-~~~~-,--~~~~---,--~~~~-,---,

i 1 30

I c!J I * ' ·--!---- ···--·------------------·-····-----·--···-----···1-·····-··-···-···-···--···· -- --·- --- -- _, ____ --·-·- --··- ----·- ·- --·-- ----1- --· -·- -- ----·-·- -- ·---·----- ---

1 : . I

'I I I I I ! -! --- l--------10

I I I 1- ------ --1-- -- ------ --\-- - -- --C--r --- - --1- --------- -

I I 0 Control 6

I Average Runl 0

8 Section

Run2 0

10

Run3 !:::,,

Run4 *

12

Figure 20. Braking distance per section in Appanoose County under wet surface conditions.

Ca Cl

Page 38: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

34

For the 1993 and 1994 testing periods the video camera was setup in the riders seat of the

pickup and pointed out the back window. The test road was then driven at a speed of 45 mph and

recorded on tape. After driving both directions on the road the camera was used to video tape the

crust development of the road as a record of what shape the road surf ace was in at the time of testing.

The crust taping was performed in each section at random intervals.

Some video taping was performed while the pickup operator drove by the camera at 45 mph.

This was done to try and evaluate how long the dust was suspended in the air.

The video camera is a powerful tool for evaluating what the conditions are in the field on a

particular day. It also allows an evaluator to go back and check the results of his visual inspection

and comparison to the dust collector results.

LABORATORY EVALUATION

Laboratory testing was carried out to aid evaluation of the Bentonite treatment and determine

how effective the Bentonite treatment will be for a dust suppressant. Washed and air dried gradation

tests, hydrometer analyses, X-Ray fluorescence, scanning electron microscopy, thennogravimetric

analysis, and x-ray diffra9tion lab tests were performed. Testing was performed on samples obtained

from the test roads described earlier. The gradation samples were obtained by randomly taking two

shovel widths across the road to obtain a representative sample from the test road location. The

samples where transported back to the laboratory in Iowa DOT sample bags. Each time a sample

was taken it was assumed it represented the rest of the material in that particular section. Crust

samples were obtained by taking a regular metal chisel and pounding it into the road surfacing crust

approximately 1 to 1 1/2" in depth. The chisel was then worked side ways to dislodge a small

section of crust material. The samples were placed in small air tight zip-lock bags to maintain

moisture and to ensure that none of the sample was lost. This crust procurement procedure was also

performed randomly in each section.

I I I I I I I I I I I I I I I I I I I

Page 39: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

35

Gradation Tests

The random bag samples obtained in the field were quartered down in an aggregate splitter to

obtain a sample that could be sieved easily without overloading the sieves. If it was deemed

necessary the sample was split into two and sieved separately so the sieves were not over loaded.

The washed gradation tests were run in accordance with ASTM C 117-90 and ASTM C 136-84a [6].

The air dry samples were run in accordance with ASTM C 136-84a except that the material was

sieved in the air dried state instead of oven drying the materials. Also, the sample size required for

both gradations was approximately 2000g by ASTM C 136-84a and some of the gradations were run

with slightly less material than required by this standard. The materials were all split before sieving

and did not deviate from this weight a great deal so they are assumed to be representative of the

material in the field.

Gradation Test Results

The washed gradation test results show a general trend of the treated sections having a lesser

amount of fines than the control section. This is attributed to the fines being locked up in the surface

crust developed. During the field observations it was documented that the treated sections developed

a better crust than the control sections. If more of the fines are locked up in the surf ace crust this

may be part of the reason that there is a dust reduction due to Bentonite treatment.

The washed gradation trends are shown on Figure 21. This shows the treated sections having

less fines than the control section for a washed gradation on the Appanoose County test road. The

trend was also evidenced by numerous other gradation tests. Some of the washed gradations showed

some of the sections having a higher percentage of fines than the control. The higher amount of

fines only occurs in the 6 percent and 10 percent sections. In the 6 percent section there are several

residences where cars would be turning often which may grind up particles finer and loosen them

from the crust. In the 10 percent section there is a reasonably sharp curve which the trucks and cars

must maneuver around also churning up the surface crust and loosening materials on the surface.

Also, in the 10 percent section there is a steep valley where the Bentonite could have washed down

Page 40: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

Sieve size (number or inches) :7l ~ g ~ ~ ~~ v ~

100 100

90 Washed Control 90 Washed6%

80 Washed8%

80

70 Washed 10% 70

bl) 60 .s Ill

~

60 bl) .s Ill Ill tU

Washed 12%

P-4 50 ..... i:I

50 P-1 VJ ..... i:I °' 8 .....

Cl) 40 P-4

8 ..... 40 Cl)

P-1

30 30

20 20

10 10

0 0 .-c oo ll"l N

~ ~ ~~

Screen opening in millimeters

Figure 21. Appanoose County washed gradation from 08/15/93.

- - - - - - - - - - - - - - - - - - -

Page 41: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

37

the road into the valley during the heavy rains of 1993, reducing the effectiveness of the Bentonite

treatment on the slopes of the hills and increasing the number of fines unable to be locked up in the

surface crust.

The same washed gradation trend is present in the Tama County test road location. Shown

on Figure 22 is a washed gradation plot from 1994. This gradation is from the test roads third year

of service. This gradation plot indicates that the Bentonite treatment is still operating three years

from the start of the project. Surfacing material was added to the road twice during this three year

period and the Bentonite treatment still maintained it ability to lock up material into the crust as

shown by Figure 22.

The air dry gradations show a trend of having somewhat less fines than the washed

,gradations do, shown by comparing Figures 22 and 23. This trend could possibly be caused by the

Bentonite agglomerates creating larger particles making the mixture coarser. This would indicate

that the Bentonite and limestone are agglomerating to create larger particles which may possibly

settle out of a dust cloud faster. This would help back up the observation that the treated dust clouds

settle faster than the untreated control section dust cloud.

Hydrometer Test

Hydrometer evaluations were run on some of the samples obtained in the 1994 testing year.

The hydrometer analysis was conducted in accordance with ASTM D 422-63 [7]. The hydrometer

analysis should give an indication of the amount of clay sized material in the surfacing material.

Clay sized particles start around 0.002 mm and with the hydrometer analysis can be determined the .,

amount of material smaller than this size. Shown on Figure 24 is a plot of the hydrometer analysis

run on a sample from the Appanoose County test road. The control section has the most material

passing the 0.002 mm size. This may be because the Bentonite is agglomerating to the small

limestone particles and these bonds are unable to be broken by the dispersant. This trend may also

be explained by the clay being in the crust material locking up the fines; therefore, there would be

Page 42: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I 'I I l'!

!j .0

74

-· I

~ '"' ~ N ~

.149

.1

80

I 1-3

~ =

Q .29

7 ~

Ci

C1I

I ~

g .4

20

=

"'t:I

.590

-~

• C1

I

~ §·

.840

I CT

CI =-

s· 1.

19

~

Q.

8 (J

Q

t::.:

I ;s

t:::

2.00

Q

. 8

2.38

a

C1I .....

-· C1

I 0

~

=

I ~

4.76

0

6.35

9 =

<

II

9.52

I

-1'-' QC

12.7

?.

I 19

.1

25.4

38.1

I 50

.8

63.5

I 76

.2

I I I

Per

cent

Pas

sing

,_..

·-0

0 ~

(,,.

)

0 .;:

.. 0

Vt

0 0

\ 0

25 0

0

0 \0

0

8

I nl rD1

1 Jl'

l I '

' I 1

l lf

111711~T1

11

1

rll I

I 1 I

1 I

I I

' !

I :

()

I I

I i\

O

1-...

l iV

t ~

0

1-n-.

I-' ·1-

rJ-t--

T-r

-.-

L -t.l

. . ~

i ~

I ~

i ~

~ a

·I-I

I t'

i I

I I

f j I

I ! <

:S I

<:S

l <:S

<:S

..,

I '

I I

I I

: .S2

.. I

1 Tt-·

-. t· .

... , 1

--_

, .... -

.J --

.i .

. t·

H: Jt±

± -cn

1 ~

I IB

+ Hi

. rrt+ {1

11-++L

L Tl=

fT

L.,J J

Jd. b.

t i.· J,

,. ,_ :J±

t1. ~~fa

..t ~ u =

1=r~t

JHJ :

ttL-1 I

20

0

~-irw1mr :q

11nnwnm1r~f"ltnmf

i I

r.\~ \I

I I

I i l

l i

i I i

I

! I I

! ! l

I !

I I I

! ! I

I I

i I

! I

1~

m~~~

-l1l-

1·1lt·1

+ 1r-r

-1-~-

-rr-r1 -t1

·1·ni-

l·hl-

1l~·1

, I In

. I· .

I.,,

1

, I

, 1 !

1,,

, I.:

11

,, I 1

i J 1

1I1

LU . .l\

:;:J ~ . .

L JLI

I _LI J

I JL

I .! JU

I . .LL

I i UJ

.l. .U

JJ. L

LU

'lfi

"\IN l

jl'

Ill'

111

1 ff'

l-H'i

!~Ii

'iii

'L~I

LT

--\';1

-,

., .. 1

-!--·

·· ·r-

-tt-

1 ,-

-··1

T +·

-i-·

r!

·l·r1-

· ·h

· t

I.

,,,ti

I '.

I ..

I I

I •

'1

I

I I

' I

' .

I I.

l-1-f-f

-~~~

-~·tl·

t·i .1

1.1.JT

1 !-H

·!·1

1-i 1

-i ! i

!L!J

! ~-·1

·1-1

rn.1

i. L

.l-!

.. l'-

.L·i

....

. L~

.:

·-... .L

l..L

.. L.l

-L. .

....

LL

..!

-. .J

-... l

l

._L

.L.!

J .. i

L !

.tJ.

J J

so ~

c;·

40

Ci Cf)

30

§.

,-....

20

t:

j c • ....

. , r

.Ii·;

,".]

· \!

i: ;

·j

-L;:

-H

.! ;

t·i

i; +

1::

l +

·I.:

i-·r'.l

-i i."·

1·-L-1

Y l ·~ l

t l

'H-...

~ i !

1· r I

i 1 rr I

i i r

i I -1

, i i

H · ! I

i -, I

i-r rh

!ii!

llJ'f~:}

JJl 111

.l lll

l lll

i Iii

! 11

1111

11 i

ll!

8 16

g-

i !

I I

I :

I I

!,;•

;·i\

!'

I I

i I

I I

! i

I !

I i

I !

; !

i !

i I

i I

! I

I i

! !

i H

-' I i

IJ. I

! I [

' "~ :

%tl

"\.

, I ! I

i I

' l I

[ I j

J I

I i

l±t I

I '

i i

i I i i

1-

t-'"

'. --1

-· ·1·+

-l._ -

:;,.· ... _.

~ _,

__T

.. ·f--

r-...

, ! -

·t -.·1

1-r· ..

. -r,-,

I I

I I

I 11

f~kt

· I

I i

I I

! i

I '

i !

1 .. ~r

l -~J

+ ·r·

.-..... 1-+

1 ~'Ll.

1 1-1. 1

J•·1

-·1J1

. r_L

, -lilJ

_,_

1 .. j...

L 1

! ;

! I

I I

I I

. I

i !

! ! ~t'N I

I

I !

I -t.

! I

I I !

i i

! !

I I

i

i i-u

· ... u·

'L I

r I I

-y

·-i i

. ·un·

~ ..:.

t.r.:r r

. ·u·

I i i-[

TI

11· rt

• 1-r

-c1

LI-

. J_

..

-Li.-

... !.

.. 1 .. .L

. •.•.

-...

.. ~ ....

-•. :

J ..

.. --·

_, ..

.. ,..

. ... L

..

r ,_ ..

, ...

·-

,_ .

....

... ,

._

-H-.

. ,. ....

. J

-·1·

·~-

,., ,

...

......

---

r ·-·

-i-·1

+-..

... ,

. -·1

.

I 1

I.

I l

I ·

. ,:.

.;:.

_.

•..

I I

I I

l •

.., 0 .., 10

. t:l

8 g.

C1

I ~

4

. , +,

1 r.

, I

" .

:I '

, r-1

. ,

•••. ,

1~

......

,

.J ,

, ,

, I

• 1

, ,

1,

.25

tt-t-+

· ;1

J-f-

H 1

F +;

-. : :

h I

: · r-!

-1 1

-tr"·-

-cl.-

· ·I

·1-r

.t+

, t·r1

rt:r

fi-Trn·

::h~1 T

· d:fl

Tfi' i ·

i fl ·1

~tr1 i

·-r:-l

:i~r~

i rfi

·375

! 111

111

1 11

11

1111

11

11

111

! 11

1 !

1111

11

11 '"P

NJ.

~s

0

rrrr

-rnr

·nll

nrr ·

n1r r

r-r1· ·1

rl1 r

nT TI

Ti ·-rr

lr~, · s

, I

-t ,

I I

, I

,

1 I

1,

, i

1, t 1

1. l 1

;

, r·J

i i

1 i L i

,

• ,

I ,

1,

1

1-J---

.-··

11-L

r ·

i ·-·-

· 11

--

.-·

•·

1·1

·1-i

·-.. 1.

·1· ..

. !.-i

-·1··

-i

,I

I.

I 1 ..

1

! ..

I.

,I,.

,

I .

!11

l.1

15

r-iTi

iTTl

.I ri I

Ll 1

1 'TU

I u l

l Ji

! I

:-..rn

!Ill

: iTI

0

2 !.

!.l-i.

l. J

..W .. -

l...LI

L . U

-1. i

.. LL

Li.

1-!.!.

I -U

l-I

--i.1

-1 1.1

-1-!.

. U JJ

z.s

!-

! -~

~-.. q

i-.

J-.L

J

t i·

I !

i i

t--1-I

·! -·I

J.

! I

·f· I-

! !

--~L

!

H-~

I !

l .. !-

l ; r

r-1-

-l-t 1·

... '1-

1 t-

;· ·

1 ·1· i

"i

.. L-'-

-t 1·

· t .. 1

·· I 1

·1

--t l

·1· · t

..... t.

· i ·

t4'·1

i'

1-1 ;

·

3 "''i

I ;T

l '' i

I

·f"i

I ·H

·i.

-h

I ·1

1·;

: ..

!-I

i·h··

.

j·;

,_..

0 ~

(,,.

) 0

~

Vt

0 0

\ 0

Per

cent

Pas

sing

-...l

0 co

\0

0

0 - 8

Page 43: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

~

~- '"I ~

N ~

~ = =

n 0 = =

~ = -· '"I Q

. '"

I ;·

Q.

IJQ

'"

I =

Q. =

.....

5· = a =

5: -~ ~

0 ,....

.. 0

t5 w

0

Per

cent

Pas

sing

.+::-.

0 V

i 0

0\

0 -i

0 0

0

·\O

0

0

,...... 8

i 111

1 !

n 1 :r

1 1 -:r

l ~ 1 1• ! 1

T JT:

I r 1

1 1

1

11 1

1

·TT

1 rn

I I

I I

I I 1

I I I

I "" I I

I

I I

I ~

; 1

I I

11

Iii

111

\0

1..

...J

U

1 w

0

-~L __ ,

_ 1-.

-~JJ_

1 _____ ,. ~ -1 1· ·r

,<:)

,

... o

... o

... o

= L:

_ '

i I I

i I

I I I

I I

o"-

I o"

"l o"

"l o"

"l ~

i 'I i

1t1

IL

l II·

1

it

I g.

L -

, -.-if

' -T

l-.. L

·-

--r

·r· ! 1

-· ·-H

+

1..

I I

I 1 I'

I

11

.. 'I

I I

I' I

I ..

'

LI I

I 11

L . L

-_._

... it' _

__!_

L _L

U...L

m' 'il

1 1

, ,

_1 1 1 1

.. !-

. -~

. L

ii

I'

I fl

! I

Iii

mT

ill'

H'I

L-

. .... LL

_ f

-' I ~

.L _r

1.ll.

p

l J_t

--1

_,_~}

_l_L.i

~--

· _..I

· 1·

I .

I r

I r I

I I

I

I I

: ·I

I I

I !

I I

I

.:r.ltl

-~.Ju ~

d iJ J

i.rt -l

d+ Jt

1t tt

rt. -~j

1J ·i=

ttl tc.

·r 20

0 ·0

74

-r~+

l tt

tt · r

-·1-1-

i---'-

-1··1-

r-H

it· 1

-q t

t1·:

t· .

.. i '\"

:-·'

t-t+

-i· -r

-;-r-r

1Tu1

tflT 'M

1f rm TiT

f TI~1 r

TT ff rm

rm: Tf n

•14

9 I

ii~\!

, i I

I I

I I

! i

! I

I I

I I

i I

I I

I i

! i

! i

! !

! l

I I

I !

I I

! I

.180

M'

\' ,,

'-j tt 1

l..

I l t

I • •

' I

I •

I t_j

.L

H '

' I

. I

• I I '

I '

' l

' · ,-

~~r-1

-, , ·1

T ___ ·

r-rr1

·1 fT

T :-,·

-·11rT

·rtrT

1·1-rT

·1-n!

(/).

297

I I b

\ I I I

I • I

I i

l I I 1

!

i i !

: i !

! I

I I I

I !

I I

I I

I I

I i !

~ • 42

0 Ll.

tf:\1

N1Jll

1 Jl.

l.J ... L

i LLJ

.11.l

.lli.L.

LLLL

JLI

JJLU

1:1

.

i I

i I\

. ·.~.

I I \I

I

I I

I I

' I

I i

I I

J I

I I

l I I

I

I '

I 1·

' I

I I

i I i

! · o

tT

1-I'

\i:'t1

x r

n ..

.. -n

t 1 '!

l r +

r ! 1 ·

n ·1

t -··

H ·J-

f"rr

r· n

1il ·

590

.f..l-i

.i \·c.

:r:t--1

l-~ i.

L .. ;.

11 i-~

. ii

!-i-

-~-l t

-!----

_! .j.

).\ ..

1--i-.L

\ . .l.1

.J,. !

.1.1, I

i 8

, l .

i j

, ··i

' I ...

,f , ! •

I •

, l

~ ;

I ,

, •

• •

! I

I ,

, 1

! j

! i

, •

=· ·840

•t•

p:·t·

J'.f.\

.\~.

N;-.!·-

t· ;:.

·:i.::i.

f·.; ~;·

I· j ..

··~···i·

; i

.·.~·~.;

:; ~--

.:1:_+~7

·--~·

··.·~~f-

~:!~ i ...

.. ;~f.

~i i'

O'Q

i....

;..11-l

·1··

.I \·

.. 1···1,

1

t •.

, . ··t

-·1·-r

j-

...

• ·

I-··

t-i

,

, -l-

-• ·

I· -i-

-•· ·_

--!·

··• f-

~ 1

-, ..

.,

.. •

I :

I I

j\"·1

\j

I I

I I

I !

! 1

! 1

I l

! :

! !

I :

I i

l !

I I

' I

I !

i

= 1 ·19

j i I

1· I

I <{·

\:.{t

i i

i !

i i ;

i I

I I i

i I i

j i

I I I I

i i

I I

11 i I

8

I l

)" \l

\I!

' I

I I

I .

' ' I .

.

i l

I •

I.

'1'

' I

I

_ I I

1 ,

11 r ,

~-· ..

:·,i

11

• 1

: ..

, I

i :

• 11

,,

1

, 1

, ;

, ,

, , ..

,

. '

1\

,. 1·~

I

I I

I i

I I

' i

I I

. I

I I

i I

' .

t="!

200

1 !

'. .

• °'..

_ ~

' •

• I

~ ;

; ;

1 :

~ :

; :

: ;

' '

'. '

; •

: '

;

8 I!

t

I! I

)-.

_;•J

~ .. \!:I

1'

I l

'I'!

I!'

I !

! !

I !-

Ii!

! !

I I

(l)

2.38

.

! I

I I

u I I

i I"

''('-

"-; .. ~:

i :

i l

I I I !

. +

l

! !

I I I I

i i

: I

i I I

;

"'1

I

I I

I I I

"·'· '~

-l

' '

. I '

. I

I .

' .

' I

' '

I I I

~ .Lt

'_Llf ..

. _L

-H

_..,·.:

s._;5

.J"1'_

1 H

f+ ir

1·!-

-,···+

-, h+T

·1'--r

11-·+

1·-1+

Cl

> •

' I

l'<·'~ ~

-.

! !

! I

I I

. I

! I

I I

! !

I '

I I

. ,--, J

.... ~

11_.1

i

• 'J

. _,_ .... ~.

~! l.

'· .. ,

.. J..'

..

.,

I r

' ·I_

·.,.-

.. :

.. ,

'T' r

., ...

• '"I'"

.. Ii

I I

111

! I!

I

I! i

""~~~~!

I!!!

I 1

, !

! !

! I

i 11

I

I ii

4.76

:

~ :.

· ....

!" .....

-i

.... ·1

· .. n

.. ·-· ·

I •

• ~-

"""'

i ·

.L iJ.

. -~J

.U

d I

+ ..

. Ll

:LL

I JJ

..i

6.35

I

I I

I l !-t 1·

I '

l '

' ,.

; ; I

' . I '

i I

TfTf

._.].

!Tl T

JJLI

l !';"

JJ1T

1Tl

~.:i

:t

.. t ·

. .__

,. ~

·; ., ..

.... 1

··1· ;.

1· '

!' r·

., i

! ·"·

I I

t ·

1 · l

; I

· I

I I

I 1·

. I

I .

. .

I'.

'.

I I I .

, I!!

1 !

, ,

I i

! I

'i

l I!

I

. ,

i

l2.7

i I

i I i I

i I

I i i

I '

1 I

I ' . I

I I

I :

! !

I I I

i

I i

111

19.1

25.4

38.1

50.8

63.5

T ·

j-1•·

·i-11

I

iT -

'-P .

T1 T

1 -t

Ti''

. n-r

I

' I

I !

! I

I '

' I

I I i

I

; '

' I

II

' I

I I

! I

I :

I •

i '

J I '

l l

i :

I i

I .. l

· 1-.

... -1

-·1·+.

. ·1-

·1-·-h

-1

... , ..

-;+

-1,·+

·tt --, ·

-j-

1 !

I I

' .

: :

I.

• '

! l:

! 'I I

! !

I l

l I

I I

! 'I

! I

I

I ! T

I ·1

: ! T ]

I

1 i 1

! TT

T1 'I

JTT

T T

I .!

I. l.I

J

! ~J

JL

.J.t !

I Ll.~.l-

.l.L

l.l

.! .I

I ..

'

. '

'.'

76.2

++

r~r.

r-=-1

--1-l-!

·-I-+

i ++

+++

H

"-t

t-·1· 1

·1-t 'I

'! I !

:· tTH~ 1

1 i~

r-,

.......

1·, .. :.

· :

~ ~

t I·+

1· i

,

:. ;.

H-H

-i;

i·H

·1·'

l l!

-f-l

·-!-

li-.;

-1 . ..;

l-~

i-4

! ;

I 1 ··

f1'-i-

l I ;

111

1 t·

1· t·1

·1-1

1·q-

1-1··1·

'T' :-:

T

! ~

! · r

·~ ~ i

·,

i

; :

f i

1 :

; i ·

, j

· ·!

I · i

i

0 ,_

.. N

0

0 w

0

. .+:

:-. 0

Vi

0 0

\.

0

Per

cent

Pas

sing

-i

0 0

0

0 \0

0

- 8 100 80

50

40

30

20

16

10 8 4

.25

.375

.5

.75

1.5 2

2.5 3

en

......

$g

0 Cl> -· N (l)

,,-...

, c:s

c: 9 er

0 "1

0 "1 ......

c:s g.

(l)

Cl>

'-"

I I I I I I I I I I I I I I I I I I I

Page 44: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

M Q)

~ ...... ~

~ Q)

8 Q)

~

3

2.5 Control

2 I- 6o/o - • - ·0-. - .

1.5 8%

-·· -·£>-·· -··

10o/o

1 - -o- -

12°/o ••·····D·····••

I,· .} _/,· .; ~ '.'

!f

V .o· .~ .;;·" ,ci

.- .;.ft.;: ....... · tr' .-·:.:- .··

VV , .. o~: ..• ····;·.:.. ·;..u- ..••• o···· ....... e•" _d ,.5'1 ...... :-.. ,..,. ... ... _ ......... ..

i----1----1---+v_,,i-=-.. ..... - ...... ···-. ~ ... iO' .......... .

/. -;: ... L,a- ... .P.· ........ .a

0 5 l~====r:=---6.o<~~ .er" - ... . L.<: ... • . ·;ti o" ..

-~~~~:.....:.~::;.~~-,.o-··~_ .. _ .. -~ .. _·-~---l-+--+------l----1-----l----+--l----+-t-1-l

1

0.5

0 L--~~~L--~__J___~L---L....._.....l---l.--.L..-.J....-L....._~~~--1-~---'-~~-'----'---'----'---'-' 0 0.001 0.002 0.003 0.005 0.01 0.02 0.03 0.05 0.1

Particle Diameter (mm)

Figure 24. Appanoose County hydrom~ter analysis from 07 /12/94.

- ~ - - - - -i - -; - - - - - -·- - - -

Page 45: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

41

less fines in the surf acing material. This testing would back up the results from the washed

gradations. The trend is also present in the Tama County material as shown on Figure 25.

X-Ray Fluorescence (XRF)

Samples were obtained from the control sections (Phase in in all three counties. The samples

were washed over a 1/2 inch sieve to remove any fines and/or clay particles. Once the plus 1/2 inch

material was washed, it was then crushed in a jaw crusher to reduce the size to run them through a

grinder. After crushing, the samples were ground to a fine powder. An elemental analysis was

performed on the samples by XRF. An elemental analysis was also performed on the powdered

Bentonite. The results of those tests are given in Table 4 along with the typical ranges from different

quarries located throughout Iowa. The sum is a quick check of the reliability of the analysis since

the oxide total should approach 100 percent. All of the values are fairly close to 100 percent,

therefore the tests appear reliable. A copy of the XRF report is given in Appendix C.

From the ranges in Table 4, the Tama aggregate would be classified as a limestone with some

impurities. Some of the oxides for the Tama County aggregate falls outside some of the typical

ranges, but the oxides are much closer to the limestone range than the dolomite range. The

Appanoose County aggregate would be classified as a limestone. Almost all of the oxides are the

same as the limestone typical ranges. The Hancock County aggregate would be classified as a

dolomite. This is evident from the typical dolomite values shown in Table 4.

Thermogravimetric Analysis'(TG)

The system that was used for testing was a Hi-Res TGA 2950 thermogravimetric analyzer by

TA Instruments. This analyzer is equipped with a 16 sample carousel which allows for many

samples to be prepared and tested under automatic operation. A typical TG analysis setup for this

project used a scanning rate of 40°C per minute with a resolution = 5, sample mass of 55.5

milligrams, air as the atmosphere at a rate of 100 ml per minute, platinum sample cups, and heated

from 30°C to about 850°C.

Page 46: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

L-(]} c:: ·-LL

8 Control

3% 6 ,_ -·-·O-·-·

5%

4 - 7% - -o- -

,_ 9o/o

~

·I/ 1-~r----r~t---t--i-t-t-+-~~~--1--~-1-~-~-+-~L-+-l---f-l 8

t-1-----1-t--t-t--+--l---l·---t--+----l---.-i---V~.~-+-(

·--·--·· / _,, ____ _ .' JI ,

J ,· 113

L-Q)

6 .s LL ....., c:: Q)

~ Q)

a..

0 ~~~~_._~~.._____..___.__,__.__,_--'-'~~~~-1--~~L----1~_1_-L_L._J_.L.J 0 0.001 0.002 0.003 0.005 0.01 0.02 0.03 0.05 0.1

Particle Diameter (mm)

. Figure 25. Tama County hydrometer analysis from 05/18/94.

- - - - - - - - - - - -i - - - - - - -

Page 47: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

)

I I I I I I

I I I I I I I I

43

Table 4. Results of XRF analysis on Bentonite and carbonate stone.

Typical Iowa Topical Iowa Limestone Dolomite

Oxides Bentonite Tama Appanoose Hancock Ranges (6) Ranges (6) {wt. %l {wt. %1 {wt. %l {wt. %l {wt. %l {wt. %l

Sr03 0.04 0.02 0.04 0.02 0.02 -0.04 0.01- 0.02

MgO 1.61 6.54 0.84 17.09 0.29- 4.34 13.18 - 18.84

Cao 0.81 43.oo 50.79 33.6 47.40 - 54.89 29.76 - 34.38

Fe203 2.61 1.05 1.02 0.86 0.16- 0.60 0.20- 0.94

Ti02 0.11 0.02 0.03 0.30 <0.01 -0.02 0.01- 0.03

Si02 43.8 7.26 3.32 1.93 0.16- 3.99 0.76- 2.83

S03 0.40 0.07 0.08 0.04 <0.01 - 0.20 <0.01-0.27

K20 0.46 0.06 0.11 0.16 0.01 - 0.14 0.06- 0.18

P205 0.04 0.03 0.04 0.02 <0.01 - 0.03 <0.01-0.07

Al203 13.77 0.27 0.63 0.51 0.05 - 0.40 0.16 - 0.48

MnO 0.04 0.29 0.05 0.01 - 0.05 0.02- 0.05

LOP 34.12 40.66 42.00 45.69 42.30 - 44.10 45.00 - 46.80

Sum 97.67 99.02 99.19 100.27

aLOI = loss on ignition @ 950°C

The present method utilized by the Hi-Res TGA analyzer is a dynamic heating rate. This is

used to shorten the time needed to run a complete test and allows the heating rate to be varied. Once

a mass loss is detected, the heating rate is lowered l:llld after a mass loss is no longer detected, the

preset heating rate resumes.

Laboratory Sample Tests

To evaluate TG analysis for application to this project, laboratory samples from Tama

County were prepared. The minus number 200 material was obtained from the control section in

Tama County. Three different percentages of Bentonite (5, 10, and 15 percent) were added to the

' control material. The samples were then stirred for a minimum of five minutes to ensure that the

I Bentonite was equally distributed throughout the sample.

I I

Page 48: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

44

These samples were tested using the previously mentioned test condition parameters. A

sample of Bentonite was also tested to obtain its TG curve. The results of those tests are shown on

Figure 26. The limestone and Bentonite samples decomposed at about the same temperature. The

residues remaining from the control and treated sections were approximately uniformly spaced. This

should be the case since a uniform increase of Bentonite was added to the control material. The

actual residue amounts, at approximately 825°C, are shown in Figure 27. To confirm the previous

tests, another set of samples was prepared in the same manner. The second set of tests confirmed

that the analysis is repeatable.

Analysis of Figure 26, indicates a small dip in the curve from approximately 30 to 100°C.

This dip is associated with the moisture being removed from the samples. Since Bentonite can retain

a large amount of moisture, as shown on Figure 26, it was decided to oven dry the samples before

being tested. Drying was accomplished by placing the samples into an oven at 110°C until a

constant weight was obtained. Using this procedure the samples all start off at similar moisture

contents. Another set of Tama laboratory samples was prepared, oven dried and retested. This

process removed the initial dip, as shown on Figure 28.

One can theoretically calculate how much residual material, from the laboratory mixed

samples, should remain at the completion of the test. This is done by using linear interpretation and

by knowing the actual amount of Bentonite added. [8]. There may be some error due to the actual

weighing and mixing process. Calculations have shown that the error is very minimal and that the

linear interpretation may be utilized to approximate the amount of residual for any percentage of

Bentonite at approximately 825°C. Note that linear interpretation is only good for laboratory

mixtures and not for samples obtained from the field, since the amount of actual Bentonite remaining

in the field samples is unknown.

Fjeld Sample Tests

Since the samples need to be in a powder form, the samples which were obtained from the

road were sieved over a number 200 sieve. This material was saved and tagged in a small vial. The

samples were then oven dried to remove any moisture that might be present and prepared for testing.

I ,, I I I I I I I I I I I 1· I I I I I

Page 49: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-------------------100-~~~~~~~~~~:=;;;~~=;;;;;===------I '\~--.:::--_,................--__..__..._ \ ·····························································==·"'=="'=·=-...._,\

-------·-----

'--· ~·-·-·-·-·-·-·-·-·-·-·- ·---..... .......... 90-

--·-·-·---·-·--·-·---·-··--

:ii:: 80-~

.p Control .c ----··-OJ .,.., OJ

5% Bentonite Treatment ?- --------· <(

70 (.!) I- ---- 10% Bentonite Treatment

15% Bentonite Treatment

60- -·-·-·- Benton i te · '------------------

50-1--~~-.--~--~--.--­

o .----.-------

800 1000 200 400. 600 Temperature {°C)

Figure 26. TGA curves of first air dry Tama County samples and Bentonite.

Page 50: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

65---------.. v .... , ..... ,-----------------------·-··-------,, ' ...

63-

I I

\ \

~\ \ \ \ \

g 61-\ , ___ J_5_% _!1_e~~-on_i_t_·e ----------t.E.L_O~-----------------

.c 01 .... , QJ

3:

'\'- __ 1_0%_Be_nt_an_i_te ____ 1_5_9_.9_! _______ _

\ \

' ~ (!} 59-

\

''---~~-B:_n_!.~~~~!----------1-~~~~E!__ ______________ _ ·-....._ __ c_or_1t_·r_o_1 __________ 1 57.~2

57-

55-l-----..---~.----r----.-- I

650 700 750 800 I

850 900 Tempern tu re ( °C)

Figure 27. TGA curves of first air dry Tama County samples.

------~-------------

Page 51: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-------------------

ll'!

.p

.C Ol ..... Ill 3:

·:( l'J I-

100 -.---·~--......-..-..---.._, -..-,...__,,, ____ .....,. __ _,,--------··------·--

90-

00- ---·-- Control

--------· 5% Ben ton 1 te

10% Bentonite

70-- 15% Oentonite

60-

I

\ I I

\ ' \

\

I '·--------,\- - - -'---------

50-----.----~---r----r----.------,----.----T----·--.

0 200 400 600 000 Temperature (°C)

Figure 28. TGA curves of oven dry Tama County samples.

1000

Page 52: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

48

The same operator conducted all of the tests, to minimize any operator errors and variation. The

sample masses were kept as close as possible to minimize any errors which might arise from

different sample sizes. Using this procedure the curves should be comparable since all of the tests

were being conducted under the same parameters. The minus number 200 material from each test

section in Tama County was evaluated to determine if any Bentonite could be detected. Tests were

conducted on samples obtained on August 18, 1992, July 14, 1993, and August 4, 1993. Since the

general shapes of the curves below 700°C are similar to those previously shown, the curves were

analyzed at temperatures above 700°C.

The general trend from the Tama County samples which were sampled August 4, 1993,

indicated that maybe some of the Bentonite has moved between the sections, as shown on Figure 29.

The trend is that the 3 percent section has the most Bentonite, while the 9 percent section has the

least. This trend might be true after considering the topography of the road. The 7 and 9 percent

sections are located toward the top of the hill with the 5 percent located below the 7 percent section

and the 3 percent being located below the 5 percent section towards the bottom of the hill. With

these samples being taken after the heavy rains in July, it could be possible that some of the

Bentonite has been washed down the hill. To see how much Bentonite there was per section, x-ray

diffraction (XRD) analysis was utilized to verify the TG data.

X-Ray Diffraction (XRD)

X-ray diffraction was performed on some of the 1994 crust samples to determine if the

Bentonite was helping to lock up the fines in the limestone surface crust as was suggested in the

gradation results section. X-ray diffraction tests were run by Materials Analysis and Research

Laboratory (MARL) and the results presented on diffractograms.

Figures 30, 31, 32, 33, 34, and 35 are the diffractograms that were run on the samples.

Figures 30, 31, and 32 show all four treatments that were run for clay determination. On Figures 33,

34, and 35 the scales on the diffractograms were blown up to show an exaggerated scale. Only the

air dry and glycolated treatments are shown on the diffractograms.

I I I I I I I I I I I I I I I I I I I

Page 53: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

--------,------------

M~

.IJ

.C UJ •rl Q)

3:

rt (!) .._

GG-·---------0\\-------------------·----------------·--··

GJ!-

G2-

GO-

58-

\ ,,, ___ _?~ _ _§_!:~~!_~~--------------!~~~~~-------\ \ I

\ I I

\ I I

\ I

\ I I

\ I I

\ \

\ 5% Section 62.J!B - - - - - - - --1-- - - -

\ I I

\ \ 7% Section 59.07 ---------------------------!------------

9% Section 57.UO --·----~t-·-~---

57. 78 Control

56-~---~------,----.----.,-----.----1,----.-----,

650 700 750 800 050 Temp or rt lure ( °C)

Figure 29. TGA curves of oven dry field samples obtained 08/04/93 in Tama County.

900

Page 54: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

..... I 0 ~

><

* Cf) 0... u * >-+-' ·rl Cf)

c ID +-' c

H

266.8

200,1

133.4

66.7

T AMA-CClM"IFlOL;? TAMA-CONT2+GLYC TAMA-CONT2-400C TAMA-CONT2-550C ~~.n

Montmorillonite peaks

Heat at 550C

Heat at 400C

Glycolated

Air dry

O.OL...---'----...LL~-L----_J_--1.._,_ __ __t __ ~'----'----...__--..l..-..l..--'----L----_._ __ _._ __ __._ __ --::26. 2 5 8 11 14 17 20 23

Two-Theta *degrees*

Figure 30. XRD diffractogram of the· 1994 Tama County control section.

VI 0

-------------------

Page 55: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - -' - - - -· - - - - - - - - -

..... I 0 ...-t

x

* en Cl. u * >-

+.J ·rl Cf)

c Q.)

+.J c

H

266.8

200. 1

133.4

66.7

I.II IS I ··I AM~\· 5,~ DUST-TAMA-5%-GLY

UST-TAMA-5%-400 UST-TAMA-5%-550

peaks

Heat at 550 c

Heat at 400 c

Glycolated

Air dry O.OL-~-'--~-'-~--'-~--'-~~~-L~_._~__..~___..__~...._~_.__~_._~__.__~_._~_._~_,

2 5 8 11 14 17 20 23 26

Two-Theta *degrees*

Figure 31. XRD diffractogram of the 1994 Tama County 5 percent section.

1l ..

Ul -

Page 56: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

peaks

Heat at 550 C

~

I 0 ~ 266.8 x

:+:: U) (l_ Heat at 400 C u :+:: 200. 1

>-.µ ·rl

U1 c ID 133.4 .µ c

Glycolated H

66.7

~~Air dry O.OL-~-'-~__i__~_._~--1~~.__~J_~_,_~_J_~-'-~--ll..--~..__~_._~_,_~_._~_._~__.

2 5 8 · 11 14 17 20 23 26

Two-Theta *degrees*

Figure 32. XRD diffractogram of the 1994°Tama County 9 percent section

-----~-------------

Page 57: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-----~-------------

....... I 0 ~

x

* UJ 0.. u * >-+J ·rl (()

c 11> +J' c

H

206.4~~....-~-.-~-,-~-.-~-r-~--r~---"T~--,,-~.--~.-~~~.,-~-.--­

T M 1/\ -CCll,11 I !UL - 110 TAMA-CONTROL+GLY

Montmorillonite peaks

172.0

137.6

103.2

68.8

34.4

O.OL-~...._~--L~-L-~--'-~--'~~i__~-'--~-'-~--'-~---'-~---''--~-'--~_._~_._~_._~~

2.0 4.3 6.6 8.9 11.2 13.5 15.8 18. 1 20.4

Two-Theta *degrees*

Figure 33. XRD diffractogram of the 1994 Tama County control section.

VI \.>.)

Page 58: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

...... I 0 -M

x

* (/) 0... u * >-..µ ·rl (/)

c QJ ..µ c

H

206.4~~....-~..----,.-----,,-----.~-,~---.~-,~--.~-,.~~~-.~-r~-,...~~~,

TAMA-3%-AD TAMA-3%+GLYC

~ Montmorillonite peaks

172.0

137.6

103.2

68.8

34.4

o.ot__~...._~_.L_~_._~_L~_._~__i_~__.~__JL-~,__~.L.___~..L-~_.__~_._~-L-~-'-~-'

2.0 4.3 6.6 8.9 11.2 13.5 15.8 18.1 20.4

Two-Theta *degrees*

Figure 34. XRD diffractogram of the 1994 Tama County 3 percent section.

VI ,i:..

-------------------

Page 59: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

----~~-------------

~

I 0 ~

x

* Cf)

0.. u * >-..µ ·rl

Ul c ru

..µ c

H

172.0

137.6

103.2

68.8

34.4

T Af.IA- 7%- AD TAMA-7%+GLYC

Montmorillonite peaks

O.OL--~..__~_._~_._~--L-~-'-~--'-~-'-~--'"~---''--~'--~..__~_._~_._~-L--~-'-~--'

2.0 4.3 6.6 8.9 11.2 13.5 15.8 18. 1 20.4

Two-Theta *degrees*

Figure 35. XRD diffractogram of the 1994 Tama County 7 percent section.

Vl Vl

Page 60: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

------------------------------------------------

56

The XRD analysis was performed on the Tama County crust samples taken in the 1994

testing year. Figures 30, 31, and 32 show the control section, 5 percent section, and 9 percent

section, respectively. Figures 33, 34, and 35 show the control section, 3 percent section, and 7

percent section, respectively. The first peak on the diffractograms is the montmorillonite peak.

By comparing Figures 30 to Figures 31and32, the 5 percent and 9 percent sections have

more montmorillonite clay than the control section. The 5 percent section has a greater amount of

montmorillonite clay than the 9 percent section, which may explain the 5 percent sections better

effectiveness in the visual evaluations for 1994. The higher amount of the montmorillonite clay may

lead to better crust development which was also shown in the 1994 visual evaluations. This increase

in clay content is attributed to the migration of clay down hill from the 7 percent section into the 3

percent and 5 percent sections. The 5 percent and 9 percent sections have more montmorillonite clay

than the control section and both sections show a reduction in dust generation and better crust

development. There is some montmorillonite clay existing naturally in the subgrade as shown by the

control section XRD results. There is a definite increase in the amount of clay in the treated sections

which suggests the clay is still in place three testing seasons after the treatment was implemented.

Comparing Figure 33 to Figures 34 and 35 shows that the 3 percent and 7 percent sections

also have a higher percentage of clay than the control. Comparing Figures 34 and 35 shows that the

3 percent and 7 percent sections have similar amounts of clay which is attributed to the clay washing

down the hill out of the 7 percent section into the 3 percent and 5 percent section. Some of the

montmorillonite clay content of the 3 percent section could have also come from the water washing

over the road in 1993 since there is montmorillonite present in the native soils. The 3 percent and 7

percent sections both show a dust reduction and have better crust development than the control

section.

XRD testing demonstrates that some of the Bentonite treatment is still present after three

years of service. Some of the Bentonite shown in the diffractograms could come from the subgrade

materials since the chisel used for crust sampling penetrated into the surface 1 - 1 1/2 inches. This

I I I I I ·1 I I I I I I I I 1. I I I I

Page 61: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

57

testing however does show an increase in the amount of montmorillonite in all of the treated sections

and the relative amounts compare to visual observations of dust reduction well.

Scanning Electron Microscopy (SEM)

SEM studies were conducted on samples obtained from the control section and 7 percent

Bentonite treated section over three service seasons (1992, 1993, and 1994) from the Tama County

test road. testing was performed in a Hitachi low vacuum SEM so the samples could be tested

without having to apply special coatings. The system was equipped with an energy dispersive

chemical, dot mapping, and elemental analysis capabilities. The samples for testing were obtained

from the minus #200 fraction of dry sieve analysis testing of the loose surfacing material. Numerous

SEM micrographs were taken. The following micrographs represent the conditions that were

observed in the majority of those micrographs.

Figures 36 and 37 are 300x micrographs of samples of minus #200 material from the

untreated control section samples taken August 18, 1992, and July 14, 1993 respectively. Very few

small particulates are observed adhering to the larger particle surf aces and few agglomerates of

smaller particles are seen.

Figures 38, 39~ and 40 are 300x micrographs of minus #200 material from the 7 percent

Bentonite treated section sampled on August 18, 1992, August 4, 1993, and August 2, 1994

respectively. The abundance of small particulates attached to larger particle surfaces and

agglomerates of smaller particulates appears evident.

Figure 41 is a sample prepared in the laboratory using 7 percent Bentonite and minus #200

material from the untreated control section. The morphology is similar to those observed on Figures

38, 39, and 40.

These data indicate that Bentonite is present in the system for a period of at least three

seasons and appears to be functioning to adhere small limestone particulates to larger ones and to

agglomerate groups of smaller limestone particles.

Page 62: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

Figure 36. 300x SEM micrograph (minus #200), Tama County control section, sampled 08/18/92.

- - - - - - - - - - - - - - - - - - -

Page 63: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -

Figure 37. 300x SEM micrograph (minus #200), Tama County control section, sampled 07/14/93.

Page 64: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

Figure 38. 300x SEM micrograph (minus #200), Tama County, 7 percent section, sampled 08/18/92.

- - - - - - - - - - - - - - - - - - -

Page 65: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -

Figure 39. 300x SEM micrograph (minus #200), Tama County, 7 percent section, sampled 08/04/93.

Page 66: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

Figure 40. ]00x SEM micrograph (minus #200), Tama County, 7 percent section, sampled 08/02/94.

- - - - - - - - - - - - - - - - - -

O'. IJ

-

Page 67: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - - l

Figure 41. 300x SEM micrograph (minus #200), Tama County, 7 percent hand mixed, sampled 08/02/94.

Page 68: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

64

X-ray fluorescence (XRF) elemental analysis was performed on the control sample taken in

1992 and the 7 percent section sampled in 1992. The Bentonite clay used for a dust palliative should

have elements present such as aluminum, sodium, and silica. The limestone should have elements in

it like calcium and magnesium. Figures 42 and 43 present the XRF analysis data. The 7 percent

treated sections shown on Figure 43 has much higher silica and aluminum peaks than the control

section shown on Figure 42 does compared to the calcium peak in both plots. Also, in the.7 percent

section, there is a slight increase in the sodium peak which would be expected if there was a clay

addition. The results of this testing indicate that there was clay in the system.

ECONOMIC EVALUATION

Cost Determination

A cost evaluation was conducted for each section of Bentonite treatment and was compared

to calcium chloride treatment.

The Tama County Bentonite treatment costs are based on one motor grader plus operator at

$42.50 per hour, tandem dump truck plus operator at $20.00 per hour, and water truck plus operator

at $25.00 per hour. The Appanoose County construction costs for the Bentonite treatments are based

on two motor graders plus two operators at $45.00 per hour per machine, flat bed truck plus operator

at $35.00 per hour, and two water trucks plus operators at $35.00 per hour per truck. The Hancock

County construction costs are based on one motor grader plus operator at $50.00 per hour, tandem

truck with trailer plus operator at $47.00 per hour, and water truck plus operator at $25.00 per hour.

Material costs varied due to the fluctuations in the amount of surf acing material present in

each test section. They also varied due to the different lengths of each section and the different

amounts of water added to each section. The cost for the removal of the gravel and the addition of

limestone, prior to construction in Hancock County, was not considered in order to be able to

compare the construction costs with the other counties. Table 5 presents the break down of the costs

per section and per mile for the Tama County test road. Costs for Appanoose and Hancock counties

were determined in the same manner. For comparison each test section cost was normalized to a

I I I I I I I I I I I I I I I I I I I

Page 69: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-------------------

cps 250 ..... . . ... ---··-----···--- - ----·--·······------------------------------ ----

0

200 II Ca

I

150--·

100···· Si

50--

Ca

K -~-· ~_,....-....... ~-·_,..,I

(11 L

0 ---· -Lr·-··r-··~- 1--, --,---,----,--1---·r ·--,---y---,-r--,-.----.-- ,-r----,-----1--·-1--1- --1----,---.-,-----i----.-,-.·-r-1 ---,--.-,-·-1 I I ,-,--

1 2 3 4 Energy (keV)

Figure 42. XRF data, Tama County untreated control section, sampled 08/18/92.

Page 70: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

cps

250-0

I 4

Figure 43. XRF data, Tama County 7 percent Bentonite section, sampled 08/18/92.

Energy (keV)

- - - - - - - - - - - - - - - -· - - -

Page 71: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

-------------------

Table 5. Tama County test road breakdown of construction costs per 1000 feet and per mile.

3% Bentonite 5% Bentonite 7% Bentonite 9% Bentonite Cost for Cost for Cost for Cost for

1000 ft. 1 mile 1000 ft. 1 mile 1000 ft. 1 mile 1000 ft. 1 mile

Bentonite 57 300 85 450 102 540 261 1,377

Soda Ash 6 30 6 30 6 30 11 60

Water 7 37 7 37 7 37 14 74 Grader+ o rator 64 340 64 340 64 340 64 340 Tandem truck + 0 rat or 10 40 10 40 10 40 10 40 Water truck + 0 rat or 37 200 37 200 37 200 37 200 Actual Cost* of Construction 181 947 209 1,097 226 1,187 397 2 091

*Estimated amount of limestone present: 3% section => 109 ton/mile 5% section => 98 ton/mile 7% section => 124 ton/mile 9% section => 167 ton/mile .

**The shaded row presents normalized costs based on a typical secondary road average of 125 ton/mile of loose limestone surfacing material

0\ -.J

Page 72: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

68

basis of 125 ton per mile of loose limestone surfacinf material, which represents a typical secondary

road.

Table 6 presents the comparison between the annaul normalized Bentonite treatment costs

(for all test roads) and calcium chloride costs per mile. Information on calcium chloride costs was

obtained from Jerico Services of Indianola, Iowa. The calcium chloride cost is based on two

applications per year at a standard application rate of 0.25 gallons per square yard of a 38 percent

concentration of calcium chloride. Two applications were recommended by the suppliers, and is

considered to be the minimum. The number of applications depends on the climatic conditions and

the number of vehicles using the road. Therefore, the cost for calcium chloride given in Table 6

would be a minimum for the year. For cost comparison purposes, the Bentonite treated sections are

estimated to last for one year. This is believed to be a very conservative estimate since the Bentonite

treatment longevity is not yet exactly known. Evidence indicates it acts to reduce dust over an

extended period of time (greater than one year). As seen in Table 6, the Bentonite treatment costs

are considerably less than the calcium chloride treatment.

Table 6. Annual costs. of Bentonite and calcium chloride treatments.

County

Tama

Appanoose

Hancock

Treatment

3% Bentonite 5% Bentonite 7% Bentonite ' 9% Bentonite

6% Bentonite 8% Bentonite

10% Bentonite 12% Bentonite

5% Bentonite 8% Bentonite

Calcium Chloride

Total Cost $ I mile I year

990 1,222 1,447 1,750

1,485 1,720 1,950 2,200

1,340 1,650

3,228

I I I I I I I I I I I I I I I I I I I

Page 73: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I ~I

I

69

At the time this report was written, the longevity of the Bentonite treatments in Tama County

was at least 14 months and probably be longer. Calcium chloride has been estimated to last

approximately 3 to 4 months [8]. To compare the cost effectiveness of Bentonite treatments to

calcium chloride, the total construction costs, estimated dust reduction efficiency, and duration is

used. The total construction costs used here are for Tama County as shown in Table 5. The

estimated dust reduction efficiencies used were the estimated dust reduction levels from Phase I data.

The dust reduction values from Phase I were used because there were more data available for this

test road than during Phase II.

Cost Evaluation

It is difficult to develop a reasonable way to compare the costs of the different treatment

types. It was necessary to base the evaluation on the amount of dust reduction, but still show the

decrease in efficiency of the treatments over time. It was considered valid to compare the cost for

each treatment on a basis of percent dust generated. The average dust generations for the Bentonite

treatments were shown in Tables 2 and 3 with the CaCl treatment having an assumed efficiency of

60 percent over its life span. The effectiveness of the Bentonite decreased with time due to addition

of materials and possible leaching of materials out of the system. The decreased efficiency made it

necessary to evaluate the materials on a testing season basis. This was done by showing the

cost/percent dust generated then dividing by the number of months in service after the Bentonite

addition was made. To have the CaCl chloride on the same basis as the Bentonite treatment it is

necessary to replenish the CaCl section. The number of application of the CaCl was multiplied by

the application cost and then divided by the assumed efficiency of 60 percent and then divided by the

number of months in service. This method of economic evaluation should give a reasonable

estimate of the cost of the treatment methods evaluated.

The results of the economic evaluation for Tama County are tabulated in Table 7. The first

testing season at Tama County showed that the 5 percent section was the most economical for the

cost of construction and dust generated. During the 1992 testing season the CaCl and the 9 percent

Page 74: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

70

Table 7. Cost I Percent dust generated for test roads.

Months in Servicea

Tama County

(1992) 3

(1993) 14

(1994) 26

Months in Servicea

Appanoose County

(1993) 5

(1994) 16

Number of CaCl Treatmentsb

1

3

5

Number of CaCl Treatmentsb

1

3

aMonths in use at the end of each testing season

3%

22 (7)

14 (1)

41 (2)

6%

32 (6)

99 (6)

$ I % dust generated

$ I % dust generated/months of service

Treatment Levels

5% 7% 9%

19 24 26 (6) (8) (9)

17 26 35 (1) (2) (3)

39 (2)

66 (3)

83 (3)

$ I % dust generated

$ I % dust generated/months of service

Treatment Levels

8% 10% 12%

32 34 29 (6) (7) (6)

156 195 122 (10) (12) (8)

bNumber of CaCl treatments necessary to maintain the CaCl's effectiveness. $Stands for Cost.

Ca Cl

28 (9)

85 (6)

141 (5)

Ca Cl

28 (6)

85 (5)

section had reasonably the same cost per percent dust reduction. In the 1993 testing season the cost

per percent dust reduction per month of the 3, percent and 5 percent sections was the same. The Ca Cl

was the most expensive of the alternatives. In 1994, the cost per percent reduction and months of

service for the Bentonite treatment and CaCl treatment are shown merging. Also, there was an

increase in the cost per percent reduction per month for the Bentonite treatment. This shows that the

I I I I I I I I I I I I I I I I I I I

Page 75: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

71

effectiveness of the Bentonite treatment is diminishing and probably will need to be replenished.

This also shows that the life expectancy of the Bentonite treatment is around 3 years (seasons). After

the three testing seasons the Bentonite treatment is still more cost effective than the CaCl treatments.

The results of the Appanoose County site are also shown in Table 7. These results are not as

favorable for Bentonite treatment as the results from Tama County. The cost per percent reduction

per month for the first year are comparable to the CaCl section. However, the second year at

Appanoose County the CaCl is more economical. During construction of the Bentonite treated

sections at Appanoose County the soda ash to water percentage was increased from 0.4 percent to

1.2 percent. This may have decreased the efficiency of the Bentonite to bond with the limestone or

the Bentonite may have been washed off the road surface by the heavy rains in 1993. Also, the road

is very heavily traveled by garbage trucks and other vehicles. This may grind up the surfacing

materials more. This grinding effect on the surfacing material may overload the system with

limestone fines making the Bentonite less efficient. The heavy traffic may influence the CaCl

treatment by making the surface washboard and become potholed requiring maintenance of the

surface and more applications of CaCl which would increase the cost of CaCl treatment per percent

dust reduction per month. Therefore, this may not be a reasonable economic evaluation of the traffic

conditions present on the Appanoose County test road.

SUMMARY AND CONCLUSIONS

1. For dust control the results of this study indicated the optimum Bentonite amount, from a

cost/benefit standpoint, is approximately 8 percent by dry weight of aggregate. Following are

the results at about this level.

• The Tama County test road had a traffic count of 60 vpd with moderate truck traffic. The

following dust reduction averages were observed.

1992 60-70 percent

1993 40-50 percent

1994 20-30 percent

Page 76: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

72

Maintenance surfacing was applied to this road in 1993 and 1994. It is significant that the

Bentonite (applied in 1992) was able to interact with the new material and maintain a dust

reduction capability.

• The Appanoose County test road had a traffic count of 200 vpd with 10-30 percent truck

traffic. The following dust reduction averages were obseived.

1993 50-60 percent

1994 10-20 percent

For this traffic amount and type, dust control effectiveness was significantly reduced. The

truck traffic is believed to be abrading and generating more fines than the Bentonite can

effectively interact with.

• The Hancock County test road had a traffic count of 1150 vpd with light truck traffic. The

dust reduction average was obseived.

1993 20-30 percent

This road had a gravel base to which crushed limestone had been topically applied. The

Bentonite and stone were unable to interact with this material to form a wheelpath crust It is

not recommended for use on gravel based roads.

2. Even though dust was being generated after Bentonite treatment, field observations and video

evidence indicates the dust cloud does not rise very high or wide and settles rapidly.

• The dust cloud height reduction combined with increased dust settlement rate would result in

improved visibility and traveling safety for the traffic following.

• The dust cloud width reduction combined with increased dust settlement rate would result in

a reduction in nuisance dust invading residences and residential areas.

I I I I I I I I I I I I I I I I I I I

Page 77: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

73

3. With Bentonite treatment, wheelpath and crust development were improved by a factor of 2 or

more which should act to reduce maintenance surfacing requirements over time as well as

provide better driveability.

4. Braking and handling characteristics of Bentonite treated sections were not adversely affected

under wet surface conditions up to a 12 percent treatment level.

5. The cost of Bentonite treatment (on the efficiency basis of dollars per percent dust reduction) is

conservatively estimated at less than one-half that of calcium chloride treatment.

6. Evidence indicates that Bentonite is functioning as a dust suppressant by bonding small

limestone particulates to larger limestone particles and agglomerating small limestone particles.

7. The advantages of Bentonite treatment are as follows.

• Bentonite is a naturally occurring, environmentally sound material.

• Bentonite is low in cost and readily available.

• Construction is rapid and can be accomplished using county personnel and equipment.

• Normal maintenance grading practice can be followed.

• Bentonite is capable of interacting with new maintenance surfacing material, applied after

treatment, and maintaining a dust reduction capability.

• The dust reduction mechanism is recoverable from season to season and over a wide range of

environmental service conditions.

8. The disadvantage of Bentonite treatment is that there is not the initial dramatic reduction in dust

as with chloride treatment. Although dust is reduced 60-70 percent there is still dust being

generated. Where immediate and nearly total dust reduction is required, chloride treatment I

would remain the preferred alternative.

Page 78: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

74

GENERAL RECOMMENDATIONS

1. Bentonite treatment for dust suppression would have application to limestone surfaced secondary

feeder roads leading into small towns, secondary roads used as shortcuts, or other roads where

there are a number of residences located.

2. For roads where traffic is less than about 150 vpd with light truck traffic, the following would be

anticipated.

• For the first season an average dust reduction of 60-70 percent.

• For the second season an average dust reduction of 50-60 percen~ (assumes no new

maintenance surfacing applied).

• Retreatment required in the third season (assumes maintenance surfacing will also be needed).

3. For roads where traffic is greater than 150 vpd and/or high truck traffic, the following is

anticipated.

• For the first season an average dust reduction of 50-60 percent.

• Re treatment ~~required in the second season (especially if new maintenance surfacing

is required).

4. Prior to treatment, it is recommended that local residents be acquainted with what to anticipate

after treatment. For interested parties a video tape is available (at cost) for this purpose.

5. For higher dust suppression, in localized areas, chloride treatment remains the better alternative.

I I I I I I I I I I I I I I I I I I I

Page 79: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

75

CONSTRUCTION RECOMMENDATIONS

Materials

A. Bentonite - (fine grind or feed grade).

• Apply at 8 percent by weight of loose surfacing (typically 100 to 150 ton/mile).

• Available in 50 pound bag form or 20 ton bulk form (specify a pneumatic tanker).

B. Sodium Carbonate - (soda ash dispersing agent).

• Available in 100 pound bag form.

• Mix with water at a 0.5 percent solution by weight(= 50 lbs. per 1000 gallons water).

• Water - any potable supply.

Eguioment

A. Two patrols.

B. Dump truck - (for soda ash and bagged Bentonite).

C. Two water tankers with recirculating pumps - (minimum of 1000 gallons each).

Preconstruction

A. Determine Bentonite quantity.

• Tight blade loose surfacing into windrow on one side.

• Take windrow cross section measurements.

• Calculate loose aggregate volume.

• Determine loose unit weight of aggregate (approximately 120 lbs. per cubic foot).

• Determine Bentonite weight needed.

B. Determine Bentonite application rate.

• Calculate bag spacing (if bagged).

• Pneumatic tanker will require field determination of unloading rate.

Page 80: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

76

Construction

A. Bentonite - Apply manually or pneumatically next to windrow. Dry mix with two patrols by

moving the windrow from one side to the next a minimum of four times. Spread the dry mixed

material over an ±g foot width on one side of the road.

B. Soda ash - Add to tanker when approximately 1/4 full. As tanker loading proceeds, engage

recirculating pump to mix as it is being loaded. Continue recirculation after loading until time

for application.

C. Application and wet mixing - Thoroughly saturate ±g feet of treated surfacing with the

water/soda ash solution. Begin wet mixing with patrol. Continue adding solution and mixing

until a 2-3 inch slump consistency is obtained. Move the windrow a minimum of four times

across the road.

D. After wet mixing, spread the treated material uniformly over the road surface for traffic

compaction.

Construction Time

With proper equipment construction is rapid. A one mile section should be easily finished in a

half day. Loading and unloading water trucks is the most time consuming.

ACKNOWLEDGMENTS

This research project was sponsored by the Highway Division of the Iowa Department of

Transportation through the Iowa Highway Research Advisory Board.

We thank Bob Gumbert (Tama County engineer), Ed Tice (Appanoose County engineer), and

J. William Waddingham (Hancock County engineer) for their willingness to participate in this

project. A special thanks to Dwight Surb~r, assistant to the Tama County engineer, for his time and

I I I I I I I I I I I I I I I I I I I

Page 81: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

77

help in arranging for and assisting with construction and field evaluation. A special thanks also to

Gary Harris, Iowa DOT, for his diligent evaluation efforts and for helping in county engineer

solicitation for the project, and to Lowell Richardson, Iowa DOT for his advice and council.

The assistance of Jerry Amenson in the thermogravimetric analysis and scanning electron

microscopy testing, and Scott Schlorholtz in the x-ray diffraction analysis, and interpretation of x-ray

diffraction and thermogramitry data is greatly appreciated.

REFERENCES

1. Mertens, E.W., and Wright, J.R., "Cationic Asphalt Emulsions: How They Differ From Conventional Emulsions in Theory and Practice", Highway Research Board Proceedings, No. 381, pp. 386-397, 1959.

2. Oren, G., Demirel, T., and Boylan, D., "Reducing Dusting of Limestone Finals", Final Research Report to the Iowa Limestone Company, Des Moines, Iowa, January, 1985.

3. Bergeson, K. L., Wahbeh, A. M., "Development of an Economic Dust Palliative for Limestone Surf aced Secondary Roads", Final Report to Iowa Department of Transportation, Project HR-297, Engineering Research Institute, Iowa State University, ISU-ERI-90407, Ames, Iowa, February, 1990.

4. American Association of State Highway and Transportation Officials, Standard Specifications for Tran~ortation Materiajs and Methods of Sampling and Testing, 15th ed., Part II Tests, 1990. '

5. Iowa Department of Transportation, Standard Specifications for Highway and Bridge Construction, Series of 1984, Ames, Iowa.

6. American Society for Testing and Materials, 1992 Annual Book of ASTM Standards, Vol. 4.02, Concrete and Aggregates, ASTM, Philadelphia, 1992.

7. American Society for Testing and Materials, 1988 Annual Book of ASTM Standards. ASTM, Philadelphia, 1988.

8. Schlorholtz, S., Bergeson, K. L., "Investigation of Rapid Thermal Analysis Procedures for Prediction of the Service Life of PCCP Carbonate Coarse Aggregate", Final Report to Iowa Department of Transportation, Project HR-337, Engineering Research Institute, Iowa State University, ISU-ERI- Ames, Iowa, June 1993.

Page 82: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

APPENDIX A

Phase I and Phase II Evaluation Worksheets

Page 83: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I·

EVALUATOR:

COUNTY:

Day of:

Day prior:

Section

Control

1

2

3

4

PHASE I-DUST CONTROL EVALUATION WORKSHEET

DATE:

TIME:

WEATHER CONDITIONS:

MAINTENANCE CONDITIONS:

SURF ACING MATERIAL CONDITIONS:

Dry:

Damp:

Wet:

% Bentonite

I Dust Generation

I Crust Development

% of Control 0-5 Rating

0

3

5 I 7

9

I Roughness

0-5 Rating

With 5 bemg best

NOTE: Dust generation percentage may be greater than I 00%.

Notes:

Page 84: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

II I I: I I I I I I I, I I I I I

Notes:

I I I I

-------------- - ~-- ------

EVALUATOR:

COUNTY:

Day of:

Day prior:

-~ ..

PHASE II - DUST CONTROL EVALUATION WORKSHEET

DATE:

TIME:

WEATHER CONDITIONS:

MAINTENANCE CONDITIONS:

SURFACING MATERIAL CONDITIONS:

Dry:

Damp:

Wet:

Section

I Dust Generation I Crust Development

I Roughness

I % of Control 0-5 Rating 0-5 Rating

Control I 100

1

2

3

4

5

6 With 5 bemg excellent

NOTE: Dust generation percentage may be greater than I 00%.

Page 85: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

APPENDIXB

Phase I and Phase II Dust Control Evaluation Data

Page 86: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -Table Bl. Phase I test road evaluations and averages.

Dusi Generation Crust Development Roulithness Weather Conditions Surfacing Material Percent Bentonito Percent Bcntonito Percent Bentonite

Date Time Evaluator Dav Prior Dav Of Conditions 0 3 s 7 9 0 3 s 7 9 0 3 s 7 9 04-Sep-92 03:00 PM Fichtner Sunny Sunny JOO 6S 60 60 70 I 4 s 3 2 3 s 4 2 I

07-Aug-92 07:00AM Surber Sunny Sunny Damp 100 17 IS 12 10 s s s s 4 s s s s 4 27-Aug-92 04:15 PM Brocka & Lapke Cloudy, 70 Partly cloudy, 75 Damp 100 50 40 30 20 2 3 4 4 s 4 4 3 3 2 03-Sep-92 03:00 PM Bergeson Rain Sunny, 80 Damp I 2 3 4 s 3 4 5 2 I 10-Sep-92 08:30AM Fichtner Rain Sunny, Heavy dew Damp 100 1S 15 70 70 2 4 s I 3 s 4 3 2 I IO-Sep-92 JO:SOAM Brocka & Lapke Rain, 70 Sunny, 6S Damp 100 SS SS 3S 20 I 2 2 2 2 4 4 4 4 3 tt-Sep-92 07:00AM Surber Sunny Sunny Damp 100 89 91 93 9S s s s 5 5 s s s 4 4 20-0cl-92 Ol:ISPM Harris Cloudy, 4S, damp Sunny, SS, dry Damp 100 40 40 30 20 0 I 2 2 2 5 4 3 3 3

06-Nov-92 02:00 PM Harris Cloudy, 31, flurries Cloudy, 29, flurries D=p 100 60 60 60 so ·2 2 3 3 3 s 4 4 4 4 12-Nov-92 02:30 PM Harris Sunny, 38 Damp 100 20 20 20 20 3 3 3 3 3 4 3 3 3 3 03-Sen-92 02:00 PM Harris Rain 73 Sunnv 83 Damn. Sliohtlv JOO so 40 40 3S I 2 2 2 2 5 s s 4 3

Average 90.9 47.4 45.1 40.9 37.3 2.09 3.00 3.SS 3.09 3.27 4.36 4.27 4.00 3.27 2.64 Starid. Deviation 0.0 21.3 22.3 23.8 27.3 1.56 1.28 1.23 1.24 1.21 0.77 0.62 o.ss 0.96 1.15

1 l-Aug-92 IO:OOAM Broeka & Lapke Sunny, SS Sunny, 70 Dry 100 40 3S 30 2S 2 3 4 4 s 4 4 4 3 2 ll-A'.ug-92 12:SS PM Harris Sunny, 90 Sunny, 82 Dry 100 80 70 60 50 0 0 0 0 0 5 s s s 5 14-Aug-92 03:30 PM Surber Sunny Sunny Dry 100 40 2S 4 4 4 4 4 4 4 4 4 4 17-Aug-92 01:00 PM Bergeson Partly cloudy Partly cloudy, 80 Dry 100 so 40 30 20 2 I 3 4 s 4 s 3 2 I 19-Aug-92 12:30 PM Brocka & Lapko Rain, 60 Partly cloudy, 80 Dry 100 so 35 30 20 I 2 3 3 4 4 4 4 3 2 21-Aug-92 02:00 PM Harris Sunny, 80 Sunny, 60 Dry 100 80 70 60 so 0 0 0 I I s 5 5 s s 21-Aug-92 07:00AM Surber Sunny Sunny Dry 100 9S 90 85 80 4 4 4 4 4 4 4 4 4 4 31-Aug-92 07:30AM Surber Sunny Sunny Dry 100 98 9S 93 90 s s s s s s s s s s 03-Sep-92 03:30 PM Brocka & Lapke Rain Sunny, 7S Dry 100 4S 3S 30 20 2 3 4 s s 4 4 3 3 2 11-Sep-92 02:1S PM Harris Sunny, 70 Sunny, 80 Dry 100 60 so 40 30 I I 2 2 2 s 4 4 4 4 17-Sep-92 02:20 PM Harris Cloudy, 80 Sunny, 60 Dry 100 so 40 30 20 0 I 3 2 I 4 4 2 4 4 2S-Sep-92 02:00 PM Harris Mos!ly cloudy, 73 Mos!ly cloudy, 70 Dry 100 60 so 30 30 0 I 2 I I 4 4 3 4 4 2S-Sep-92 02:SO PM Brocka & Lapke Sunny, 68 Cloudy, 67 Dry 100 SS 4S 3S 25 2 4 4 4 4 3 4 4 4 4 30-Scp-92 04:00 PM Surber Sunny Sunny Dry 100 40 36 32 30 s s s s s 4 4 4 4 4 01-0ct-92 12:00 PM Brocka & Lapko Sunny, 80 Sunny, 80 Dry 100 6S SS 4S 30 2 4 4 4 s 4 4 4 3 3 14-0ct-92 02:00 PM Harris Mostly Cloudy, S7 Mostly Cloudy, 60 Dry 100 60 so so 40 0 I 2 2 I 5 4 4 4 4 IS-Oct-92 03:00 PM Bergeson Cloudy, Cool Dry 100 60 40 so 60 2 3 5 4 2 2 3 s 4 2 22-0ct-92 02:15 PM Bergeson Sunny, 1S Sunny, 1S, windy Dry 100 4S 3S 3S 3S 0 3 s 4 2 0 3 s 4 2 22-0ct-92 03:40 PM Brocka & Lapke Sunny, 1S Sunny, 7S, windy Dry 100 so 3S 30 2S 2 3 3 4 4 4 4 4 4 3 27-0ct-92 02:25 PM Harris Sunny, 70 Sunny, 63 Dry 100 so so so 40 I 2 2 2 2 5 4 3 3 3 29-0ct-92 01:30 PM Brocka & Lapko Sunny, SO Sunny, SO Dry 100 SS 30 4S 30 3 3 4 5 s 4 4 4 4 3 01-0ct-92 03:35 PM Ber~eson Sunnv Sunnv 85 Dn1 Verv 100 so 40 30 30 I 2 5 3 4 I 2 s 3 4

Average 100 SS.I 46.6 41.8 36.6 1.77 2.SO 3.32 3.27 3.23 3.82 4.00 4.00 3.77 3.36 Stand. Deviation 0 16.1 17.7 17.7 18.5 1.56 1.47 1.46 1.42 1.68 1.27 0.67 0.80 0.73 1.11

2S-Aug-92 02:30 PM Bergeson Rain Rain Wet I 2 3 4 5 3 s 4 2 1 07-Auo-92 09:30AM Surber Sunnv Rain Wet Verv 0 0 0 0 0 5 5 5 5 4 s 5 5 s 4

Average 0 0 0 0 0 3.00 3.SO 4.00 4.50 4.SO 4.00 S.00 4.50 3.50 2.SO Stand. Deviation 0 0 0 O· 0 2.00 I.SO 1.00 o.so o.so 1.00 0.00 o.so I.SO I.SO

Page 87: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - ... - - -Table B2. Phase I test road notes and maintainance conditions.-

Date Timo Evaluator Maintenance Condilions Notes 04-Sep-92 03:00 PM Fichtner

07-Aug-92 07:00AM Surber Project was done 815192 Section scorns to be similar to spots that are chlorided 27-Aug-92 04:15 PM Drocka & Lapke Windrow east side 9 % a liltle washboarding.

03-Sep-92 03:00 PM Bergeson Windrow cast side, last maint. estimated@ 5 - 7 days Minor dust, could not tell differcnco, good wheel palh crusting, best to worst 9%, 7%, 5%, 3%, control. 10-Sep-92 08:30AM Fichtner Recently bladed Very little dust was generated in control section due to previous moisture. 10-Sep-92 10:50AM Drocka & Lapko Recently bladed 11-Sep-92 07:00AM Surber Because of rain 9/9192 ovorything was working well. 20-0ct-92 01:15 PM Harris Whccltracks evident in all test sections T osted at 40 mph.

06-Nov-92 02:00 PM Harris Heavy harvest traffic, no wash boarding or polholes evident, tested at 45 mph. 12-Nov-92 02:30 PM Harris Did not notice any braking problems with tho high bentonite section.

03-Seo-92 02:00 PM Harris Newly bladed No visible wheel tracks in control section all others have visible wheel tracks section 4 has some washboardin2

ll-Aug-92 IO:OOAM Brocka & Lapke Bladed day prior 11-Aug-92 12:55 PM Harris Newly bladed Tested at 40 mph.

14-Aug-92 03:30 PM Surber

17-Aug-92 01:00 PM Bergeson Windrow east sido, several days since malnt. 9 % section appears to be developing washboarding - rough, clumps of material still in windrow 19-Aug-92 12:30 PM Drocka & Lapke Windrow east side, start of defined wheel paths

21-Aug-92 02:00 PM Harris Newly bladed Talked lo patrol operator about project, he says that control section 4 doesn't blade the same as the other sections

21-Aug-92 07:00AM Surber T c=st sections have been maintained sinco placement lntial signs of washboarding beginning to appoar in wheelpaths in portions of section 4(9 % bentonitc) 31-Aug-92 07:30 AM Surber Can't tell much difference in dust from control to #4 but you can tell it is less in each section.

03-Sop-92 03:30 PM Brocka & Lapke Windrow on east side Good wheel path development in benlonite treated areas with 9 % being best, considerably better than control. l l-Sep-92 02:15 PM Harris Well bladed, perhaps recently Tested at 40 mph, wheel tracks evident last weok have been covered up in section 4. 17-Sep-92 02:20 PM Harris Well bladed Crust beginning to develop in section 2 in wheel tracks, some aggregate loss noticed, tasted at 40 mph. 25-Sep-92 02:00 PM Harris Well bladed except for section 2 Wheel track formation evident in section 2, may need to reblade windrows, tested at 40 mph. 25cSep-92 02:50 PM Drocka & Lapke Windrow east side, bladed within tho last week 3%, 5%, 1%, 9 % start of def med well paths, 0 % very little wheel path developed.

30-Sep-92 04:00PM Surber Has been maintained recently Chloride spot on south end was still better than section 4 but it is siarting to get worse Ol-Oct-92 12:00PM Drach & Lapko Bladed week prior Good wheel path development, first video tapo. 14-0ct-92 02:00 PM !larris Well bladed Wheel track formation evident in section 2 and 3, may need to reblade, tested at 40 mph.

15-0ct-92 03:00 PM Bergeson Windrow on cast side (small) Very little windrow, appeared during last maintenance ho had spread all loose material over road surface

22-0ct-92 02:15 PM Dergeson Small windrow on west side Good wheel path develop in all sections except control, did 9 % section have a lot of loose material to start with.

22-0ct-92 03:40 PM Brocka & Lapke Windrow west side, couple of weeks since maint. Good wheel path development on all 4 sections, video taped, camera set at 3.S n above road and 36 n from road. 27-0ct-92 02:25 PM Harris May need to bo rebladed as a result of heavy harvest work, tested at 45 mph. 29-0ct-92 01:30PM Brocka & Lapko Not recently maintained Video taped, camera set al 2.9 n above the road and 40 ft from west side of the road.

Ol-Oct-92 03:35 PM Bene son Windrow on east side no recent s:radimt No mudballs evident on 9% washboardina seemed less than in pasl on 90/o en.isl dcveloi> difficult to distinl!uish

25-Aug-92 02:30 PM Bergeson Windrow east side 5% very slight washboard, 7% slight washboarding, 9 % modtrate washboarding, mudballs still present in wind-row on 9% and 7% sections, locked brakes at 30 mph all test sections dW'ing heavy rain, observed no noticeable difference in any of the treated sections over coD..t:iol, some treated sections seemed to brake better than control

07-Aua-92 09:30AM Surbor Proiect was done 815/92 Seciton # 4 was muddv but it was not slick and seemed to drive OK all other sections were alrioht.

Page 88: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - ·- - - - - - - - - - - - - - - -Table B3. Phase I test road evaluations and averages for dry surface materials.

Dust Generation Crust Develoomenl Rouohncss

Weather Conditions Surfacing Materiol Percent Bentonitc Percent Bentonite Percent Bentonite Dalo Time Evaluator Dav Prior Dav Of Condi lions 0 3 s 1 9 0 3 s 1 9 0 3 s 1 9

I l-Aug-92 lO:OOAM Brocka & Lepke Sunny, SS Sunny, 70 Dry 100 40 3S 30 25 2 3 4 4 s 4 4 4 3 2

11-Aug-92 12:SS PM Harris Sunny, 90 Sunny, 82 Dry 100 80 70 60 ' "so 0 0 0 0 0 s s s s s 17-Aug-92 Ol:OOPM Bergeson Partly cloudy Partly cloudy, 80 Dry 100 so 40 30 20 2 I 3 4 s 4 s 3 2 I

19-Aug-92 12:30 PM Brock• & Lapko Rain, 80 Partly cloudy, 80 Dry 100 so 35 30 20 I 2 3 3 4 4 4 4 3 2

21-Aug-92 02:00 PM Harris l)unny, 80 Sunny, 80 Dry 100 80 70 60 so 0 0 0 1 1 s s s ·S s 03-Sep-92 03:30 PM Brocke & Lapko Rain Sunny, 1S Dry 100 45 3S 30 20 2 3 4 s s 4 4 3 3 2

1 l-Scp-92 02:15 PM Harris Sunny, 70 Sunny, 80 Dry 100 60 so 40 30 I I 2 2 2 s 4 4 4 4 17-Scp-92 02:20 PM Harris Cloudy, 80 Sunny, 80 Dry 100 so 40 30 20 0 1 3 2 1 4 4 2 4 4

2S-Sep-92 02:00 PM Harris Mostly cloudy, 73 Mostly cloudy, 70 Dry 100 60 so 30 30 0 I 2 I 1 4 4 3 4 4

2S-Scp-92 02:SO PM Brocka & Lepke Sunny, 68 Cloudy, 67 Dry 100 SS 4S JS 2S 2 4 4 4 4 3 4 4 4 4

30-Scp-92 04:00 PM Surber Sunny Sunny Dry 100 40 36 32 30 s s s s s 4 4 4 4 4

01-0ct-92 12:00 PM Brocka & Lapko Sunny, 80 Sunny, 80 Dry 100 6S SS 4S 30 2 4 4 4 s 4 4 4 3 3

14-0ct-92 02:00 PM Harris Mostly Cloudy, S1 Mostly Cloudy, 60 Dry 100 60 so so 40 0 1 2 2 1 s 4 4 4 4

IS-Oct-92 03:00PM Bergeson Cloudy, Cool Dry 100 60 40 so 60 2 3 s 4 2 2 3 s 4 2

22-0ct-92 02:15 PM Bergeson Sunny, 1S Sunny, 1s; windy Dry 100 4S 3S 3S 35 0 3 s 4 2 0 3 s 4 2

22-0ct-92 03:40 PM Brocka & Lapko Sunny, 1S Sunny, 7S, windy Dry 100 so 3S 30 25 2 3 3 4 4 4 4 4 4 3

27-0ct-92 02:2S PM Harris Sunny, 70 Sunny, 63 Dry 100 so so so 40 1 2 2 2 2 s 4 3 3 3

29-0ct-92 01:30 PM Brocka & Lapke Sunny, SO Sunny, SO Dry 100 SS 30 4S 30 3 3 4 s s 4 4 4 4 3

Ol-Oct-92 03:35 PM Bereeson Sunnv Sunnv. 8S Orv. Vcrv 100 so 40 30 30 I 2 s 3 4 I 2 s 3 4

Average 100.0 ss.o 44.3 39.1 32.1 1.37 2.21 3.16 3.11 3.0S 3.74 3.9S 3.95 3.68 3.21

Stand. Ooviation 0.0 10.9 I I.I 10.4 11.0 1.27 1.36 I.SO 1.4S 1.73 1.33 0.69 0.83 0.73 1.10

Page 89: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -Table B4. 1993 Phase II test roads evaluations and averagesJ

Tama County 1993 Dust Generation Crust Development Roughness

Weather Conditions Surfacing Material Percent Bentonite Percent Bentonite Percent Bentonite

Date Time Evaluator Day Prior Day Of Condi lions 0 3 5 7 9 0 3 5 7 9 0 3 5 7 9

14-Jun-93 Ol:OOPM Bergeson Rain Sunny, Windy, 75 Dry to damp 100 85 75 75 75 1.0 4.0 5.0 3.0 2.0 1.0 4.0 5.0 3.0 2.0

04-Aug-93 to:15AM Drocka/Waddingham Slight Rain, 78 Partly Cloudy, 70 Dry to damp 100 100 95 95 95 1.0 1.0 1.0 1.0 1.0 4.0 4.0 4.0 4.0 4.0

07-Sep-93 Ol:OOPM Brocka Sunny, 75 Dry 100 30 35 50 50 2.0 4.0 4.0 3.0 3.0 3.0 4.0 5.0 4.0 3.0

08-Sep-93 02:30PM Ber2eson Sunny, 75 Sunny, 75 Dry 100 30 20 40 50 2:0 4.0 5.0 3.0 2.0 2.0 4.0 s.o 3.0 2.0

07-Sep-93 Ol:OOPM Brock a Sunny, 7S Dry 100 30 3S 50 50 2.0 4.0 4.0 3.0 3.0 3.0 4.0 5.0 4.0 3.0

08-Sep-93 02:30PM Bergeson Sunny, ?S Sunny, 7S Dry 100 30 20 40 so 2.0 .4.0 5.0 3.0 2.0 2.0 4.0 5.0 3.0 2.0

Average 100 30 28 45 50 2.0 . 4.0 4.5 3.0 2.5 2.5 4.0 5.0 3.S 2.5

-

Appanoose County 1993 Dust Generation Crust Development Roughness

Weather Conditions Surfacing Material Percent Bentonite Percent Bentonite Percent Bentonite

Date Time Evaluator Day Prior Day Of Conditions 0 6 8 to 12 Ca Cl 0 6 8 10 12 Ca Cl 0 6 8 10 12 Ca Cl

05-Aug-93 Ol:OOPM Brocka/Waddingham Partly Cloudy, 70 Rain, 65 Wet 0 0 0 0 0 0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0 3.0

I l-Aug-93 01:35PM Drocka Partly Cloudy, 90 Mostly Cloudy, 88 Dry JOO 60 50 40 25 5 4.0 4.0 4.0 4.0 4.0 4.0 3.0 3.0 3.0 3.0 3.0 3.0

24-Aug-93 03:20PM Brocka Sunny, 88 Sunny, 91 Dry 100 60 50 50 20 10 3.0 3.0 3.0 4.0 5.0 3.0 3.0 3.0 3.0 3.0 2.0 3.0

05-0ct-93 02:00PM Waddingham Sunny, 85 Sunny, 90 Dry 100 35 40 40 30 10 s.o s.o 5.0 5.0 5.0 s.o 1.0 1.0 1.0 1.0 1.0 1.0

ll-Aug-93 01:35PM Brock a Partly Cloudy, 90 Moitly Cloudy, 88 Dry 100 60 so 40 25 5 4.0 4.0 4.0 4.0 4.0 4.0 3.0 3.0 3.0 3.0 3.0 3.0

24-Aug-93 03:20PM Brocka Sunny, 88 Sunny, 91 Dry 100 60 50 so 20 10 3.0 3.0 3.0 4.0 5.0 3.0 3.0 3.0 3.0 3.0 2.0 3.0

05-0ct-93 02:00PM Waddingham Sunny, BS Sunny, 90 Dry 100 35 40 40 30 10 5.0 s.o 5.0 5.0 5.0 5.0 1.0 1.0 1.0 1.0 1.0 1.0

Average 100 52 47 43 2S 8 4.0 4.0 4.0 4.3 4.7 4.0 2.3 2.3 2.3 2.3 2.0 2.3

Page 90: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -Table BS. 1993 Phase II test roads notes and maintainance conditions ..

~fama County 1993

Date Time Evaluator Maintenance Conditions Notes

14-Jun-93 Ol:OOPM Bergeson Windrow on cast side, unknown when bladed Dust cloud not heavy, wind made it difficult to estimate

04-Aug-93 10:15AM Brockaiwad<lingham Bladed within the past week, windrow east side

07-Sep-93 01:00 PM Brocka Hasn't been bladed recently, windrow on east side Video taped

08-Sep-93 02:30PM Bergeson No obvious windrow, well developed wheel paths Mud lower half of3% section (south)

Appanoose County 1993

Date Time Evaluator Maintenance Conditions Notes

05-Aug-93 01:00 PM Brocka/Waddingham Not bladed recently Slight wash boarding in all sections

I l-Aug-93 01:35 PM Brocka Bladed recently, windrow east side

24-Aug-93 03:20 PM Brocka Hasn't been bladed recently, windrow on west side

05-0ct-93 02:00PM Waddingham Hasn't been bladed recently Potholes throughout all test sections

Page 91: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - -~ - - - -Table B6. 1994 Phase II test roads evaluations and averages.

Tama Cowity 1994 Oust generation Crust Development Roughness

Weather Conditions Surfacing Material Percent Bentontle Percent Bentonlte Percent Bentonile

Date Time Evaluator Dey Prior Day or Conditions 0 3 5 7 9 0 3 6 7 9 0 3 5 7 9

18-Mey-94 01:10PM Weddlnghem Sunn)I, breezy Sunny, breezy Dry 100 90 80 80 70 2 3 3 3 4 6 5 6 5 5

os.June-94 10:45AM Bergeson Posslble llght rain Sunny, 85, still Dry lo slightly damp 100 90 80 70 70 2 2 3 4 6 3 3 3 3 3

09-June-94 01:00PM Weddlngham Cloudy, cool, 70 Sunny. breezy, 7~ Dry 100 60 60 90 80 1 4 3 3 2 4 4 4 4 4

02-August-94 12:00 PM Waddlngham Cloudy, breeze, 70 Humid, hazy Dry 100 90 85 93 90 2 2 2 2 2 6 5 5 5 5

15-August-94 12:30 PM Bergeson Sunny. cool, 70 Sunny, cool, 70 Dry 100 60 50 70 9(l 1 4 5 3 2 1 4 6 3 2

16-August-94 01:10PM Waddlngham Pertly cloudy, 80 Pertly cloudy, 82 Ory 100 80 70 70 75 2 3 4 4 3 4 4 4 4 4

19-Se~amber-94 03:00PM Waddinghem Cloudy, 70 Cloudy, 70 Ory 100 70 80 70 75 2 3 4 4 3 4 4 4 4 4

Average 100 78 69 78 79 1.7 3.0 3.4 3.3 3.0 3.7 4.1 4.3 4.0 3.9

Appanoose County 1994 Oust ganarellon Crust Development Roughness

Weather Conditions Surfacing Matertel Percent Ben1onlla Percent Bentonlte Percent Bantonlle

Data Time Evaluator OeyPrtor DeyOI Conditions 0 8 8 10 12 0 6 8 10 12 0 6 8 10 12

19-Mey-94 01:45 PM Waddlngham sunny, breezy. 80 Sunny, 80 Ory 100 75 85 76 70 5 5 5 5 5 2 2 2 2 2

14-June-94 03:00PM Weddlnghem Sunny. breeze, 95 Sunny, breeze, 9C Ory 100 80 85 95 60 3 3 3 2 4 3 3 3 3 3

12-July-94 01:30 PM Waddlnghem Cloudy, still, 80 Cloudy, still, 80 Ory 100 75 80 90 70 3 3 3 3 3 3 3 3 3 3

09-August-94 02:30PM Waddlngham Cloudy, breeze, 80 ~loudy, breeze, 8C Ory 100 100 100 100 100 3 3 3 3 3 3 3 3 3 3

17-August-94 03:01 PM Wadding ham Pertly Cloudy. 85 Partly Cloudy, 85 Ory 100 95 95 90 110 3 3 3 3 3 2 2 2 2 2

Average 100 85 89 90 82 3.4 3.4 3.4 3.2 3.6 2.6 2.8 2.8 2.6 2.6

Page 92: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -Table B7. 1994 Phase II test roads notes and maintainance conditions.

Tama County 1994

Data llrne Evaluator Maintc11411cc Conditiom Noles

18-May-94 01:10 PM Weddlngharn Good Condition .. 08-June-94 10:45AM Bergeson Wheel path developed, windrow on weal, est I wk. Checked against control on both ends •couidn'l tell any difference

09-June-94 01:00PM Weddlnghern windrow on weal aide, hasn't been bladed recently In front of dwy on 7% acction produced more dust

02-August-94 12:00PM Waddlnghern Freshly bladed. Wmdonv on West Side

15-August-94 12:30PM Bergeson Well developed wheelpalhs on 3,S,7 acc. Windrow W. aide

16-August-94 01:10PM Weddlnghern W1ndrow on weal side. CIUll developed well, bladed 2 wlca. Shrinkage cracks promedent in clay scctfons and not as well in conlrol

19-September-94 03:00PM Wedding ham Well maintained, 2 wka., wheel paths evident

Appanoose County 1994

Date TI me Evaluator MainlC1W1cc Conditions Notes

19-May-94 01:45PM Waddlnghern Vczy poor 6% had belier wheel palhs due lo exlra lraffic lo homes.(Less dust here)

14-June-94 03:00 PM Weddlngham Bladed recently, windroWI on cast side Changed fillers in coUcclor without discormecting tubes

12-July-94 01:30PM Weddlnghern Maintained approx. 2wb or more prior to observation Curves arc wash boarded and potholed.

09-Augusl-94 02:30 PM Waddlngham Rocked wirhin 2wks. not bladed recently, Bottom crust developed well with loose material on top

17-August-94 03:01 PM Weddingharn Fairly maintained, annrox. I wk.

Page 93: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - - - - - - - - - - - - - - - - -Table B8. 1993 visual and dust collector evaluation results.

Tama CoWlty 1993 Visual dust generation Dust collector dust generation

Weather Conditions Surfacing Malaria Percent Bentonlte Percent Bentonlte

Date I Time Evaluator Day Prior I Day or Conditions 0 I 3 I 5 I 7 I 9 0 I 3 I 5 I 7 I 9

07-September-93 01:00 PM Brock a - Sunny, Windy Dry 100 30 35 50 50 100 32 38 53 66

Appanoose CoWlty I 993 Dust generation Dust conector dust generation

Weather Conditions Surfacing Malaria Percent Bentonll& Percent Bentonlte

Date Time Evaluator Day Prior Day Of Conditions 0 6 8 10 12 0 8 8 10 12

19-May-94 01:45 PM Brock a Sunny, 88 Sunny,91 Dry 100 60 50 50 20 100 38 38 32 28

Page 94: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

- - - -·- - - - - - -·- - - - - - - -Table B9. 1994 visual and dust collector evaluation·results.

Tama County 1994 Vlsual dust generallon Oust collector dust generation

Weather CondHlons Surfacing Materlal Percent Bentonlte Percent Bentonlte

Date Time Evaluator Day Prior Day Of CondHlons 0 3 5 1. 9 0 3 5 7 9

18-May-94 01:10 PM Waddlngham Sunny, breezy Sunny; breezy Dry 100 90 80 80 70 100 79.87 68.52 73.61 64.84

09-June-94 01:00PM Waddlngham Cloudy, cool, 70 ~unny, breezy, 75 Dry 100 50 60 90 80 100 70.72 79.48 69.75 88.08

02-August-94 12:00 PM Waddlnghem :;loudy, breeze, 7C Humid, hazy Dry 100 90 85 93 90 100 87.77 78,15 78.44 90.49

16-August-94 01:10 PM Waddlngham Partly cloudy, 80 Partly cloudy, 82 Dry 100 80 70 70 75 100 63.05 55.1 50.04 87.34

Average 100 78 74 83 79 100 75 70 67 83

Appanoose County 1994 Oust generation Dust collector dust generation

Weather Conditions Surfacing Mater1al Percent Bentonlte Percent Benlonlte

Date Time Evaluator Day Prior Day or Conditions 0 6 8 10 12 0 e 8 10 12

19-May-94 01:45PM Waddlngham Sunny, breezy, 8~ Sunny,80 Dry 100 75 85 75 70 100 75.65 94.24 98.11 93.02

14-June-94 03:00 PM Wadding ham Sunny, breeze, 95 sunny, breeze, 90 Dry 100 80 85 95 60 100 102.8 83.96 97.00 91.42

12-July-94 01:30PM Waddlngham Cloudy, still, 80 Cloudy, stlll, 80 Dry 100 75 80 90 70 100 85.68 86.67 127.5 96.37

17-August-94 03:01 PM Waddlngham Partly Cloudy, 85 Partly Cloudy, 85 Dry 100 95 95 90 110 100 101.3 119.2

Avaraqa 100 81 86 88 78 100 88 92 86 94

Page 95: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

APPENDIXC

Roughness and XRF Data

u ~ Q z ~

=­=-____________________________________ __J<

Page 96: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

ROUGHNESS l\1EASURE1\1ENTS

HR-351, Tama County, Aug. 10, 1993

(Southbound)

Section Revolutions Roughness Roughness Cin!mi J

1 142 27 143 2 142 24 127 3 143 30 157 4 144 35 182

control 148 33 167

(Northbound)

Section Revolutions Roughness Roughness Cin!mi J

1 145 26 134 2 140 22 118 3 144 25 130 4 144 24 125

control 144 29 151

• All sections are 1000 ft. long. • The control section was arbitrarily chosen north of sect. 4.

Page 97: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

ROUGHNESS :MEASUREMENTS

HR-351, Hancock County, Sept. 1, 1993

(Southbound)

Section Revolutions Roughness Roughness (in/mi J

1 162 40 185 162 41 190 162 42 194

2 235 55 176 235 53 169 235 57 182

(Northbound)

Section Revolutions Roughness Roughness (in/mil

1

2

. 162 162 162 235 234 235

• Section 1 is 1000 ft long. • Section 2 is 1400 ft long. • 70° F, sunny and dry

46 48 46 61 62. 62

213 222 213 195 199 198

Page 98: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I I I I I I I I I I I

ROUGHNESS l\1EASURE1\1ENTS

HR-351, Appanoose County Sept. 13, 1993

(Southbound)

Section Revolutions Roughness Roughness fin/mi)

1 145 46 238 145 48 248

2 142 46 243 143 45 236

3 45 19 317 46 20 326

control 313 109 261 313 118 283

4 145 59 305 144 66 344

5 193 59 229 193 64 249

(Northbound)

section Revolutions Roughness Roughness Cin!mi)

1 146 48 247 146 48 247

2 143 49 257 142 46 243

3 44 15 .256 47 16 255

control 316 110 261 314 102 244

4 144 41 214 144 40 208

5 192 58 227 193 63 245

Page 99: Bentonite Treatment for Economical Dust Reduction on … · 2017-11-29 · field construction and application procedures using up to 3 percent Bentonite (by weight of loose surfacing

I I I I I I I I I

IOWA STATE UNIVERSITY College of Engineering

Materials Analysis and Research Laboratory

23 Town Engineering OF SCIENCE AND TECHNOLOGY

CLIENT

SAMPLE

Ames, Iowa 50011-3232

515 294-8752 or 8761

FAX 515 294-8216

X-RAY FLUORESCENCE REPORT.

Broka Stacy DATE REC'D

Mixed Carbonate Rock Samples REPORT DATE

* * * *

CONTRACT NO. : 474-20-09-00-3643

INSTRUMENT DETAILS

Siemens SR 200 sequential spectrometer. Cr tube operated at 50 kV and 50 MA. Spectrometer operated in vacuum mode. Fully computer controlled.

07/15/93

08/13/93

Test Results: The results of the XRF study are summarized in Table 1.

I Table 1

I I I I I I I I I

OXIDES

SrO MgO cao Fe203 Ti02 Si02 S03 K20 P2 Os Al203 MnO L.O.I.

Bentoni'te (wt.%)

0.04 1. 61 0. 8.1 2.61 0.11

43.80 0.40 0.36 0.04

13.77 -- --. 34.12

Hancock App. Tama (wt.%) (wt.%) (wt.%)

0.017 0.045 0.018 17.090 0.836 6.543 33.603 50.789 42.999

0.857 1.019 1.053 0.030 0.030 0.017 1.926 3.315 7.265 0.037 0.083 0.074 0.155 0.109 0.064 0.015 0.043 0.029 0.513 0.626 0.273 0.047 0.294 0.040

45.692 41.998 40.659