bcwg - 16/11/20102 content why do we need a hw commissioning campaign? what are we going to do? how...
DESCRIPTION
BCWG - 16/11/20103 WHY Lots of activities will be performed in the LHC underground Activities cannot be fully controlled We cannot ensure a 100% correctly functioning machine protection system Cryogenic intervention: Warming up of the arc magnets below 80 K DFBs will warm up above 80 K (as already happened in short technical stops) M.Pojer/M.SolfaroliTRANSCRIPT
M.Pojer/M.Solfaroli
Preparation for2011 HWCcampaign
BCWG - 16/11/2010 2
Content
• WHY do we need a HW Commissioning campaign?
• WHAT are we going to do?
• HOW are we going to do it?
• ElQA
• QPS
• Powering Tests
• Planning (draft)
• Overlook (4TeV)
• Miscellaneous
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 3
WHY
• Lots of activities will be performed in the LHC underground
• Activities cannot be fully controlled• We cannot ensure a 100% correctly functioning
machine protection system
• Cryogenic intervention:• Warming up of the arc magnets below 80 K• DFBs will warm up above 80 K (as already
happened in short technical stops)
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 4
WHAT
• Assume operation at 3.5 TeV• Monitoring of electrical integrity of some circuits (high
current circuits of the arc and spool pieces) during warm-up and cool-down will be installed
• ELQA will be performed ONLY for the circuits with a current above 600A
• QPS – QH firing (scheduled once per year): as risk of damage during the test is higher than risk of failure when needed (redundancy of quench heaters and very limited number of beam induced quenches), heater firing tests ONLY for magnets whose cables are disconnected– no systematic heater firing for MB and for MQ magnets
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 5
WHAT
• Circuit protection requires correct operation of the interlocks (QPS, PIC, PC) and EE --> Almost all tests to verify the correct functioning of interlocks will be performed
• Reduced number of other tests, according to expert requirements
• Heat run for all circuits will be performed (8hours) as last step
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 6
HOW - ElQA
The ElQA team and equipment:• Equipment for testing up to 4 sectors in parallel
• 5 teams available inside the ElQA team (2 teams per
sector + 1 (per MIC) needed) –> up to 2 sectors in
parallel
NEEDS (for one sector)• 2 teams for HV ElQA
• 1 team for MICM.Pojer/M.Solfaroli
BCWG - 16/11/2010 7
• Snubber capacitors: Installed only for RB circuits– ONLY ONE SECTOR will be connected for testing
(assuming re-commissioning to 3.5TeV)– ELQA to be done (separately)
• Old global main bus-bar detector taken out in all sectors• Quench heater power supplies switches:
– test during switch off to identify weak switches• Test of the third (Z) switch of 600 A citrcuits (within test
step of HC)• Upgrade all Q9 and Q10 voltage divider (Q10 R2 done) –
test within the normal HWC sequence
HOW - QPS
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 8
HOW - PTs
Simplification of test execution:
• Excluding high current tests (RB, RQD) a test step with
same current level can be done before the previous test
step is signed
• Signature of tests to be cleaned up (not required that
several teams sign the same test)
• Parallel tests of several circuits - Global Power Abort will
be disabled (re-enabled after the tests)
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 9
HOW - PTs
Circuit type Test Estimation
RB(8)
PIC2 ~30 min
5/8 PIC tests4/13 other tests(+2 if 4TeV)
PLI1.d2 Unipolar Powering Failure ~10min
PLI2.b2 Energy Extraction from QPS I_Interm_1 ~20min
PLI3.d2 Unipolar Powering Failure ~15min
PNO.b2 Energy Extraction from QPS ~30min
RQD/F(16)
PIC2 ~30 min (per circuit)
5/8 PIC tests2/12 other tests
PLI2.b3 Energy Extraction from QPS 13kA ~20min
PNO.b3 Energy Extraction from QPS 13kA ~30min
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 10
HOW - PTs
Circuit type Sector Estimation
IPQs(78)
PIC2 ~15min 3/6 PIC tests1/7 other tests (+ PNO.a7)PNO.c3 Fast Power Abort IPQ ~35min
IT(8)
PIC2 ~20min 3/6 PIC tests2/16 other testsPNO.d12 PC Failure at +10% of PNO ~10min
PNO.d13 PC Failure at -10% of PNO ~10min
IPD(16)
PIC2 ~15min 3/6 PIC tests2/4 other testsPNO.c2 Fast Power Abort IPD ~20min
600A EE(202)
PIC2 ~10min
3/6 PIC tests2/6 other tests
PLI3.b1 Energy Extraction from QPS 600A ~5min
PNO.d3 Bipolar Powering Failure 600A ~15min
600A no EE(72)
PIC2 ~10min 3/6 PIC tests1/4 other testsPNO.d3 Bipolar Powering Failure 600A ~15min
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 11
HOW - PTs
Circuit type Sector Estimatio
n600A no EE crow
(136)
PIC2 ~10min 3/6 PIC tests1/4 other testsPNO.d3 Bipolar Powering
Failure 600A ~15min
80 – 120A(284)
PIC2 ~2min 1/3 PIC tests1/4 other testsPNO.d1 Bipolar Powering
Failure ~10min
60A(752)
PNO.d1 Bipolar Powering Failure ~10min 1/3 other tests
TOT
1792/3672 PIC tests - 49%1690/5878 other tests - 29%(of course including the 60A)…+8h Heat run and GPM check
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 12
Cryo Maintains
CRYO [email protected] Sector
19/01 56
20/01 67
22/01 78
26/01 34 – 81
27/01 12 – 45
01/02 23
M.Pojer/M.Solfaroli
13
DSO tests
2 shifts – 13h7am - 8pm
3 shifts7/7 days
3 shifts7/7 days
3 shifts7/7 days
First sector inPhase I powering
BCWG - 16/11/2010 14
Overlook - 4TeV
4 TeV considerations: We don’t expect a significant delay
• Current in RB: 6770 A instead of 5925 A (1 more step)• Values for current in corrector magnets (M.Giovannozzi)
• QPS rating might need to be reviewed• Snubber capacitors:
• needed for RB (to be connected)• to be clarified for RQD/F
• RQX.R1 – voltage reduction• Symm nQPS threshold (800 mV) to be lowered?• dI/dt: RB time constant to be increased to 68 s• RB.A78 high voltage tested only to 1.6 kV - to be confirmed• Splice safety to be confirmed by ongoing simulations
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 15
MISCELLANOUS
• RRR measurements• Simulation validation tests• Re-test of circuits where PC replaced• Inner Triplet tests: PC trips when power permit
removed• Some special test for selected circuit (refer to MP3)• Snubber caps: Energy extraction at different current
levels (0.76-2-4-6 kA)
M.Pojer/M.Solfaroli
BCWG - 16/11/2010 16
CONCLUSIONS
• We are confident that HWC will be short and quick– All SW already used– No heavy modification on circuits– No mayor modification on procedure– Strongly reduced number of tests
• Possible commissioning to 4 TeV wouldn’t take much– Studies on technical showstopper ongoing
• Difficulties in finding people to cover the shifts could slow down the commissioning time
• LHC should be ready for operation by 18 Feb.
M.Pojer/M.Solfaroli