BAU:June 16, 2011 Planning is a legal Obligation • PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be approved by the Head of the Procuring Entity (HOPE) or by the officer empowered by the HOPE 1 PP for SPM BAU:June 16, 2011

Upload: isaac-knight

Post on 02-Jan-2016

218 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Planning is a legal Obligation

• PPA:Section-11 and PPR-16:

Procurement Planning is mandatory for all Procuring Entity (PE)

PP must be approved by the Head of the Procuring Entity (HOPE) or by the officer empowered by the HOPE

1PP for SPMBAU:June 16, 2011

Page 2: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

Four Key WordsFour Key Words

ItemItemA single article or unit in a list.

With an identified quantity ….. 1,2,3 etc

LotLotA number of items grouped together

Any number of items can form a lot

PackagePackageA group of lots forming a contract

No package can have more than 5 lots

ContractContract

The agreement between the PE and Supplier/Contractor/Consultant and enforceable by law

Through which the package is purchased

Page 3: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Package & Procurement MethodsPE decides

Splitting /Assembling packages

Applicability of the Procurement methods

considering the nature & size of the procurement , by carefully

reviewing the proposed procurement activities & issues

3PP for SPMBAU:June 16, 2011

Page 4: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Combination of Lot

• Items of same nature & generally supplied by a particular group of supplier and normally available in a single shop or in a market. (Computer and Air Cooler should not be in the same lot while scanner, printer and computer should be in a single lot)

• Suppliers availability and ability also to be considered

4PP for SPMBAU:June 16, 2011

Page 5: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Packages Few or More?? Large or Small ??Arguments in favour of Groupings into Few Large Procurement Packages

►Benefits from economics of scale-achievement of economy & efficiency

►Management aspects ( PE’s capacity to manage the whole project)

►Risk aspect (where failure of a sub-supplier may unduly affect critical path)

►Benefits from participation of large International Tenderers

►Administrative costs of tendering

5PP for SPMBAU:June 16, 2011

Page 6: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Packages Few or More?? Large or Small ??Arguments in favour of Splitting into

more small Packages

►Time element (procurement items are needed at different times)

►Business structure( some good or services are not available from a single source)

6PP for SPMBAU:June 16, 2011

Page 7: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Three Initial StepsThree Initial Steps1. Categorize procurement into:

2. Consider time scale and combine into contract packages….. assign a unique Code Number

3. Make packages as large as practicable for improved participation and competition.

GoodsGoods WorksWorks ServicesServices

7PP for SPMBAU:June 16, 2011

Page 8: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Packages

Splitting of Packages for avoiding particular method or sanction from Higher authority have been prohibited in the Act/Rules

But

HOPE or AO may approve splitting to smaller packages & lots on

justifiable grounds

8PP for SPMBAU:June 16, 2011

Page 9: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Splitting of Packages► PE shall not generally split a

Project components with the intention of avoiding either method or the approval of a higher authority

►PE shall not usually split a package into more than five ( 5) lots for keeping cross –discounts application simple

9PP for SPMBAU:June 16, 2011

Page 10: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Splitting of Packages (Contd.)►PE shall take into account the

following aspects for splitting single object of Procurement

the capacity of the local & international markets in submitting responsive Tenders

the convenience of implementation with due regard to geographical location of sites for potential Works contracts.

10PP for SPMBAU:June 16, 2011

Page 11: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

PackagesClassified by category such as

Goods, Works and Services

Separate for Development Project and Revenue Budget

Revenue Budget is not needed for SPM

11PP for SPMBAU:June 16, 2011

Page 12: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Key Issues► PE shall arrange to publish the

Procurement Plans on their notice boards, and where applicable in their websites & in the websites of the concerned Department or Directorate or organizations, bulletins and reports (PPR- 16.9)

►PE shall, for its own purposes, update the Procurement Plan on a quarterly basis to accommodate delays, re-tendering & other unforeseen changes or constraints (PPR-6.10).

12PP for SPMBAU:June 16, 2011

Page 13: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Key Issues (contd.)

Publication in CPTU website Procurement Plans, above the

threshold, specified in Schedule II shall be published in CPTU website on a regular basis (PPR- 16.11).

13PP for SPMBAU:June 16, 2011

Page 14: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Scheduling ProcessSeven Key Steps in preparing the

Procurement Plan1. List objects to be acquired under the Project or

Programme, categorizing procurement into:

►Goods (Section 2.16)( raw materials, products, equipment and objects in solid, liquid or gaseous form, electricity & related services) (readily useable)

► Works (section 2. 6)( construction, reconstruction, site preparation, demolition, repair, maintenance or renovation railways,roads, highways or building etc. as well as physical services)

► Services (section 2. 24 )(intellectual & professional services)

14PP for SPMBAU:June 16, 2011

Page 15: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Scheduling Process ( cont’d)

2. Consider time scale and determine target dates when each goods or works or services should be ready for use, within the overall project implementation framework

3. Identify Interrelationship between the processing of these procurement objects

4. Decide on the content of Individual Procurement Packages.

15PP for SPMBAU:June 16, 2011

Page 16: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Scheduling Process (contd.)

5. Determine the procurement lead times for each package & schedule the target date for each event in the procurement process

6. Prepare Implementation Schedule – Table, Bar Chart or list identifying key dates of each package ( Gantt Chart)

7. Develop a Monitoring System to ensure timely procurement decisions & Implementation follow-up actions.

16PP for SPMBAU:June 16, 2011

Page 17: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Plan Formats

Procurement Plan has been made an integral part of DPP by the Government.

Procurement Plans for the both the Dev and Revenue Project are to be prepared in the Formats prescribed by the Government from time to time.

(For SPM World Bank Format as supplied)

17PP for SPMBAU:June 16, 2011

Page 18: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Total Procurement Plan for Total Procurement Plan for Development ProjectDevelopment Project

• Identifies: The packages for goods, works and

services that are required under the development project.

Each procurement package, giving it a unique code and considers the expected cost of the package (as per the PP/TAPP), and

The anticipated dates when the procurement package will be supplied

18PP for SPMBAU:June 16, 2011

Page 19: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Annual Procurement Plan for Annual Procurement Plan for Development & Revenue BudgetsDevelopment & Revenue Budgets

• Time bound PP assists a Procuring Entity to effectively plan its procurement requirements and is an important and useful tool used to monitor the progress of procurement

A. to ensure that it does not go astray;

B. to ensure that early problems with slippage can be dealt with promptly; and

C. can form a useful Annual Plan for procurement.

A. to ensure that it does not go astray;

B. to ensure that early problems with slippage can be dealt with promptly; and

C. can form a useful Annual Plan for procurement.

19PP for SPMBAU:June 16, 2011

Page 20: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Methods

•PPA section: 31-34

•PPR: 61-62, 69,74,83, & 103-104

20PP for SPMBAU:June 16, 2011

Page 21: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Frequently used Proc Methodsfor Goods & Works

• OTM (Open Tendering Method) (PPR-61)

(WB term it National Competitive Bidding NCB)• ICB (International Competitive Bidding)

(International Tender) (PPR-83)

• RFQ (request for Quotation) (PPR- 69)

• Direct Contacting (Direct Cash Purchase and Others methods) (PPR- 75)

21PP for SPMBAU:June 16, 2011

Page 22: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Proc Methods for services frequently used by SPM

• CQ (Consultant Qualification) (normally firm) (PPR-108)

• IC (Individual Consultant) (PPR-112 )

• FBS (fixed Budget Selection) (PPR- 106)

• LCS (Least Cost Selection) (PPR-107)

• QCBS (Quality Cost Based Selection) (PPR- 105)

22PP for SPMBAU:June 16, 2011

Page 23: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Plan Format

Column 4: Unit (unit of measurement)

Goods: Numbers, Pieces, Liter, meter, Lot etc

Works: Cubic Meter, Square meter, Lump sum etc

Service: Staff Months, Days, Hours , lump sum etc

23PP for SPMBAU:June 16, 2011

Page 24: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Plan Format

Column 10: Planned Date of Bid opening (Actual Date of Bid Opening)

• We are to follow the provision PPR-61(4), 64(5) 71(4) and 83 (1) (ka)

• Time from publication of invitation to bid opening depends on threshold and proc methods

24PP for SPMBAU:June 16, 2011

Page 25: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Plan Format

Column 11: Planned Date of Contract Signing (Actual Date of signing)

• Signing of Contact depends not only on PE but also on the Supplier/ contractor/ Consultant.

• Period of Evaluation, approval by the proper authority, issuance of NOA, Suppliers acceptance, Submission of performance security, are the factors to be considered

25PP for SPMBAU:June 16, 2011

Page 26: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Procurement Plan Format

Column 12: Planned Date of Completion (Actual date of completion)

• It depend on the Size/ Quantity/ Volume/ market situation/suppliers ability/ urgency/ weather/transport facilities/availability of funds and so many things. We are to consider all these.

26PP for SPMBAU:June 16, 2011

Page 27: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

World Bank Format for PP

Sl No

Contact Package No

Contact Description

1 2 3

1 G-1 Supply of a microbus

2 G-2 Printing of Lab Operation Manual

3 G-10 Printing Quarterly Newsletter

Page 28: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

World Bank Format for PP

Sl. No

Contact Package No.

Contact Description

1 2 3

1 W1 Sand filling to play ground

2 W2 Construction of two latrin for female students

3 W3 Repair of laboratory room of Physic dept

Page 29: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

World Bank Format for PP

Sl. No

Contract package No.

Contract description

1 2 3

1 S1 Website dev and maintenance for BUD

2 S2 Selection of local partnership for network design and implementation

3 S3 Selection of Digital Library specialist

Page 30: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

World Bank Format for PP

Unit Quantity/numbers

Estimated cost (Actual Contract Price)

Procurement Method

Procurement Guideline (PPA/BG)

4 5 6 7 8Unit of measurement

1,5,3 etc

US$

BDT.

OTM/ICB/RFQ/CQ/ IC etc

PPA/

BG

Page 31: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

World Bank Format for PP

Prior Review

(yes/no)

Planned Date of Bid opening/ Proposal Submission (Actual date of Bid opening/ )

Planned Date of contract signing (actual Date of contract signing)

Planned Date of Delivery/ completion (actual date of delivery/ completion

9 10 11 12

Page 32: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

• Basic principle is not to be adopt any ill tactics

• Keep budget provision for honurium

• Training and foreign visit not to be included in planning

• Lump Sum Contract: A contract for the performance of a specified amount of work by a specified date for a sum established in advance

Miscellaneous

32PP for SPMBAU:June 16, 2011

Page 33: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Queries ??

• If you have any query please do not hesitate to contact HEQEP procurement unit

Procurement specialists and procurement officers are always ready to response your queries.

Page 34: BAU:June 16, 2011 Planning is a legal Obligation PPA:Section-11 and PPR-16: Procurement Planning is mandatory for all Procuring Entity (PE) PP must be

BAU:June 16, 2011

Thanks.Md. Alamgir Hossain