ballast lcca

Upload: vanhhans

Post on 05-Apr-2018

224 views

Category:

Documents


0 download

TRANSCRIPT

  • 8/2/2019 Ballast Lcca

    1/38

    CHAPTER 4. LIFE-CYCLE COSTS AND PAYBACK PERIODS

    Ballasts that are more energy efficient than those required by the existing ballast standard

    would likely be more expensive to purchase but less expensive to operate. The net effect of these

    cost changes on commercial and industrial customers is analyzed by calculating life-cycle cost

    (LCC), using the equipment prices and engineering data from Chapter 3, together with an assumedelectricity price. Section 4.1 presents the LCC results for each energy-efficient ballast technology

    option, and Section 4.2 discusses the payback periods for these design options.

    The impact of changing energy-efficiency levels is expressed by two measures:

    ! Section 4.1: Change in Life-Cycle Cost (LCC) resulting from the purchase and useof an energy-efficient ballast,

    ! Section 4.2: Payback Period (PAY) for the more energy-efficient ballast.Section 4.3 presents the results of sensitivity analyses using high and low consumer discount ratesdifferent projections of future energy prices..

    4.1 LIFE-CYCLE COST FOR TECHNOLOGY OPTIONSLCC is the sum of purchase price (PC) and operating expense (OC) discounted at rate rover

    the lifetime (N) of the appliance. Installation costs, such as equipment and labor, are included in PC,

    N OCtLCC PC (4.1)

    t 1 (1 r)t

    and energy consumption and lamp replacements (and associated labor) during the life of a ballast

    are included in OC. Discounting means that money spent (or saved) at some future date has less

    value than the same expenditures (or savings) in the immediate present.

    If operating expenses are constant over time, Eq. 4.1 simplifies to:

    LCC PC PWF OC, (4.2)where the present worth factor (PWF) is:

    N1

    PWF1 1

    1 (4.3)t 1 (1 r)t r (1 r)N

    The LCC is calculated for each lamp/ballast combination.

    4-1

  • 8/2/2019 Ballast Lcca

    2/38

    4.1.1 LCC Data Inputs

    Data inputs to LCC calculations include end-user prices for ballasts and lamps, electricity

    rates ($/kWh), annual lighting operating hours, labor rates, installation times, analysis period,

    ballast lifetimes, lamp lifetimes, and discount rates.

    Ballast Price Distribution. Chapter 3 describes the methodology used to determine the end-

    user prices for ballasts. The LCC analysis uses incremental price for converting from the baseline

    EEM T12 ballast to a more efficient design option. These incremental prices are listed in Table 4.1

    below. A normal distribution with the mean equal to the incremental price and a standard deviation

    of 15% was used to describe the distribution of incremental ballast prices.

    Table 4.1 Average and Standard Deviation of Incremental Ballast Prices

    Incremental Ballast Price Distribution (1997$)

    Product Class Mean Value Standard Deviation

    CC T12 ERS T8 ERS CC T12 ERS T8 ERS

    1-Lamp Fixture 6.84 12.86 6.69 1.03 1.93 1.00

    2-Lamp Fixture 9.04 11.40 8.37 1.36 1.71 1.26

    3-Lamp Fixture (tw) 13.56 17.10 12.55 2.03 2.57 1.88

    3-Lamp Fixture (non tw) 15.88 10.47 -4.03 2.38 1.57 0.60

    4-Lamp Fixture 18.08 17.03 -1.45 2.71 2.55 0.22

    2F96/ES NA 17.37 NA 2.61

    2F96HO/ES 3.57 12.05 0.54 1.81

    Electricity Price Distribution. Marginal electricity prices in $1997/kWh are used. A

    detailed explanation of the process for deriving these marginal electricity rates can be found in

    Appendix B. Electricity prices projected for the year 2003 are used because that is the earliest year

    in which changes to the minimum ballast efficiency standards could occur. Each ballast type is

    assumed to be used primarily in either the commercial or industrial sector, and the appropriate

    electricity rate for that sector is used to calculate the LCC. Ballasts driving F40T12/ES and F32T8

    lamps are assumed to operate primarily in the commercial sector. We estimate that about 75% of

    2F96T12 and 65% of 2F06T12HO lamps, respectively, are operated in the commercial sector (seeAppendix A). Sensitivities are also done for 2F96T12 lamps and for 2F96T12HO lamps in the

    industrial sector.

    Electricity price is a function of the average price distribution obtained from the Energy

    Information Agencys data on revenue and sales, for the industrial and commercial sectors byutility,

    4-2

  • 8/2/2019 Ballast Lcca

    3/38

    and the epsilons discussed in Appendix B. Epsilon is the percent difference between the average

    electricity price and the marginal price calculated for each customer on each tariff (the average

    epsilon is 5.5%). Figures 4.1 and 4.2 present the distribution of sales-weighted average electricity

    rates in the commercial ($0.0762/kWh weighted average) and industrial sectors ($0.0455/kWh

    weighted average), and figure 4.3 presents the epsilon distribution. For each selected point on the

    average rate distribution, the software program Crystal Ball, selects an epsilon value. Thus, amarginal rate is calculated by the following equation:

    Marginal Electricity Rate = Sales Weighted Average Rate x (1 + Epsilon)

    Com. 97 Avg Elec Price

    .000

    .009

    .018

    .027

    .036

    1.29 11.72 22.15 32.57 43.00

    Figure 4.1 Distribution of 1997 Average Commercial Electricity Prices

    Industrial Price Dist.

    .056

    .042

    .028

    .014

    .000

    0.87 9.62 18.37 27.12 35.87

    Figure 4.2 Distribution of 1997 Average Industrial Electricity Prices

    4-3

  • 8/2/2019 Ballast Lcca

    4/38

    Epsilon

    .000

    .057

    .115

    .172

    .230

    -0.85 -0.51 -0.17 0.18 0.52

    Figure 4.3 Distribution of Epsilons

    Energy Price Forecast. Table 4.2 below shows the AEO 1999 forecast for the price of

    electricity relative to the 1997 baseline. Using the Reference case, these ratios were used to estimate

    the future marginal prices. Electricity prices are assumed to remain constant after 2020.

    Table 4.2 AEO 1999 Average Electricity Price Forecast

    Commercial Electricity Price Industrial Electricity Price

    Year Reference High Low Reference High Low

    1997

    1998

    1999

    2000

    2001

    2002

    2003

    2004

    2005

    2006

    2007

    2008

    2009

    2010

    2011

    2012

    2013

    20142015

    2016

    2017

    2018

    2019

    2020

    1.00 1.00 1.00

    0.98 0.98 0.98

    0.96 0.97 0.95

    0.94 0.95 0.93

    0.93 0.94 0.91

    0.91 0.92 0.88

    0.91 0.93 0.87

    0.91 0.94 0.87

    0.90 0.94 0.86

    0.90 0.94 0.85

    0.89 0.93 0.83

    0.88 0.92 0.82

    0.87 0.92 0.81

    0.86 0.92 0.80

    0.85 0.91 0.78

    0.84 0.90 0.76

    0.83 0.89 0.75

    0.82 0.89 0.750.82 0.89 0.74

    0.81 0.88 0.73

    0.81 0.88 0.72

    0.81 0.88 0.71

    0.80 0.88 0.70

    0.79 0.87 0.69

    1.00 1.00 1.00

    0.97 0.97 0.97

    0.97 0.98 0.97

    0.96 0.97 0.95

    0.95 0.96 0.93

    0.94 0.96 0.92

    0.95 0.97 0.92

    0.94 0.97 0.91

    0.93 0.96 0.89

    0.91 0.95 0.87

    0.90 0.94 0.85

    0.89 0.93 0.83

    0.88 0.92 0.83

    0.88 0.92 0.82

    0.86 0.91 0.80

    0.84 0.90 0.78

    0.83 0.89 0.77

    0.83 0.89 0.760.82 0.88 0.75

    0.81 0.87 0.74

    0.81 0.87 0.73

    0.80 0.87 0.72

    0.79 0.86 0.71

    0.79 0.86 0.70

    4-4

  • 8/2/2019 Ballast Lcca

    5/38

    Annual Lighting Operating Hours. Annual lighting hours were derived from a large data

    set of lighting energy audits done throughout the U.S. Annual interior lighting hours were calculated

    for various commercial-sector building types: office, retail, grocery, restaurant, lodging, health,

    assembly, school, college, and warehouse. Interior lighting hours were also calculated for industrial

    buildings. Appendix A describes the derivation of the weighted averages for each lamp type. Figures4.4 through Figure 4.9 show the annual operating hours distributions for various lamp types. The

    average lighting hours are found in chapter 3.

    Oper. Hr - 1F40 (Com.)

    .000

    .036

    .071

    .107

    .143

    259 2,378 4,497 6,616 8,735

    Figure 4.4 Annual Lighting Operation Hours Distribution for 1F40T12 in Commercial Sector

    Oper. Hr - 2F40 (Com.)

    .143

    .107

    .071

    .036

    .000

    259 2,378 4,497 6,616 8,735

    Figure 4.5 Annual Lighting Operation Hours Distribution for 2F40T12 in Commercial Sector

    4-5

  • 8/2/2019 Ballast Lcca

    6/38

    Oper. Hr - 2F96 (Com.)

    .000

    .044

    .088

    .132

    .177

    237 1,806 3,375 4,944 6,513

    Figure 4.6 Annual Lighting Operation Hours Distribution for 2F96T12 in Commercial Sector

    31Oper. Hr - 2F96HO (Com.)

    .000

    .037

    .074

    .111

    .147

    209 2,193 4,177 6,162 8,146

    Figure 4.7 Annual Lighting Operation Hours Distribution for 2F96T12HO in Commercial

    Sector

    Oper. Hr - 2F96 (Ind.)

    .000

    .035

    .069

    .104

    .138

    147 2,146 4,146 6,145 8,144

    Figure 4.8 Annual Lighting Operation Hours Distribution for 2F96T12 in Industrial Sector

    4-6

  • 8/2/2019 Ballast Lcca

    7/38

    Oper. Hr - 2F96HO (Ind.)

    .000

    .033

    .066

    .099

    .132

    125 2,130 4,136 6,141 8,147

    Figure 4.9 Annual Lighting Operation Hours Distribution for 2F96T12HO in Industrial

    Sector

    Ballast Life. The period for this analysis is the ballast service life, which is the ballast rated

    lifetime divided by the annual lighting hours. The value of 50,000 hours for both magnetic andelectronic ballasts has been agreed to by most stakeholders and also used in the previous analysis.

    For a four-foot lamp with a life of 50,000 hours, operated 3,400 hours/year, the period of analysis

    would be 50,000 hours/ 3,600 hours/year = 14.7 years. The period of analysis therefore varies

    according the life of each ballast and its annual operating hours. Figure 4.10 shows the ballast life

    distribution assumed for this analysis. This is a Weibull distribution starting at 18,000 hour life.

    Weibull distributions describe data resulting from life and fatigue tests and are commonly used to

    describe failure time in reliability studies.

    Ballast Life (hr)

    18,000 35,907 53,814 71,721 89,628

    Figure 4.10 Ballast Life Distribution in hours

    Installation Costs. A detailed discussion of installation costs and lamp prices can be found

    in Appendix A.

    4-7

  • 8/2/2019 Ballast Lcca

    8/38

    Discount Rates. A discount rate of 8% real was chosen by the U.S. Department of Energy

    (DOE).

    4.1.2 LCC Results

    In this section, we describe probability-based life-cycle cost analyses performed to accountfor the full range of possible values for four of the most important LCC input variables: ballast life,

    ballast price, ballast operating hours, and electricity rate. LCC changes and payback periods are

    calculated using a probability distribution of possible values for the input variables weighted by their

    likelihood of occurrence and Monte Carlo simulation. The model used to calculate the LCC and

    payback periods can be found at the DOE Office of Codes and Standards website (URL:

    http://www.eren.doe.gov/buildings/codes_standards/applbrf/ballast.html). A description of the LCC

    model can also be found in Section A.7 of Appendix A of this document. The probability

    distributions for the key variables are shown in figures 4.1 to 4.10. Figures 4.11 to 4.32 present the

    changes in life-cycle cost as a result of switching from the baseline energy-efficient T12 magnetic

    ballast to one of the higher-efficiency product types. Figures 4.33 to 4.38 present the same changes

    for 1 and 2 lamp T8 Ballasts, but use an energy efficient T8 magnetic ballast as the baseline. Inparticular, the figures show the probability that a particular delta life-cycle cost will occur. This can

    be interpreted as the fraction of the ballast population that experiences a particular delta LCC.

    Energy Efficient T12 Magnetic Ballast Baseline. Table 4.3 summarizes the life-cycle cost

    savings (delta LCC) for each lamp/ballast combination. Delta LCC is the change in LCC when

    converting from the baseline option of an EEM ballast to the listed design option. Positive values

    mean there is a reduction in LCC. The column labeled % of Baseline LCC is the mean delta LCC

    divided by the baseline LCC (expressed as a percentage) obtained when average point values of the

    inputs are used. It can be seen, that in many cases the mean delta LCC is a small percentage of the

    total LCC. Changes in LCC of a few percent in either direction can be considered (within the

    uncertainty of the calculations) as negligible. The column titled % Reduced LCC represents theprobability of the design option resulting in reduced LCC. A positive number means that the LCC

    decreased relative to the baseline.

    For ballasts operating three or four lamps, we have analyzed two wiring alternatives. For the

    three lamp case, we analyzed a tandem-wired case where 2-lamp ballasts only are utilized and a case

    where a one-lamp and a two-lamp ballast are used together to operate three lamps. Dual switching

    is possible in either case assuming the area is wired appropriately. For the four lamp case, we

    analyzed a single 4-lamp T8 ballast operating all four lamps under two situations. One case is with

    ordinary wiring and the second case is with tandem-wiring added, which allows for dual switching.

    For the latter case, we have estimated an additional cost of $10 for materials and labor.

    4-8

    http://www.eren.doe.gov/buildings/codes_standards/applbrf/ballast.html)http://www.eren.doe.gov/buildings/codes_standards/applbrf/ballast.html)
  • 8/2/2019 Ballast Lcca

    9/38

    Table 4.3 Summary of Delta LCC* Results Using an T12 EEM Ballast as the Baseline

    Product Class Design Option Sector Delta LCC

    Mean

    (1997$)

    % of

    Baseline

    LCC

    %

    Reduced**

    LCC

    1F40

    T12 CC Commercial -4 -3% 7%

    T12 ERS Commercial 4 3% 68%

    T8 ERS Commercial 17 13% 98%

    2F40

    T12 CC Commercial -2 -1% 31%

    T12 ERS Commercial 6 3% 80%

    T8 ERS Commercial 18 9% 98%

    3F40

    Tandem-Wired T12 CC Commercial -2 -1% 33%

    T12 ERS Commercial 5 2% 68%

    T8 ERS Commercial 27 10% 98%

    Not Tandem-Wired T12 CC Commercial -4 -1% 23%

    T12 ERS Commercial 18 6% 98%

    T8 ERS Commercial 56 20% 100%

    4F40

    T12 CC Commercial -2 -1% 36%

    T12 ERS Commercial 12 4% 87%

    Tandem-Wired*** T8 ERS Commercial 44 13% 99%

    Not Tandem-Wired T8 ERS Commercial 54 16% 100%

    2F96

    T12 EIS Commercial 7 2% 75%

    T12 EIS Industrial -2 -1% 35%

    2F96HO

    T12 CC Commercial 11 2% 90%

    T12 ERS Commercial 28 5% 98%

    T12 CC Industrial 1 0% 50%

    T12 ERS Industrial 15 4% 94%* A positive Delta LCC implies a LCC savings whereas a negative number implies an increase in LCC.** % ballasts with reduced life cycle cost.*** 4F32T8 ERS ballast with Dual Switching includes a $10 incremental increase in labor and materials.

    4-9

  • 8/2/2019 Ballast Lcca

    10/38

    Frequency Chart

    Certainty is 6.78% from $0 to +Infinity

    Mean = ($4).000

    .097

    .195

    .292

    .389

    0

    973.5

    3894

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 1F40 (Commercial) - CC

    Figure 4.11 Life-Cycle Cost Savings for 1F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 68.26% from $0 to +Infinity

    .000

    .050

    .100

    .150

    .200

    0

    498.7

    997.5

    1995

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 1F40 (Commercial) - ERS

    Mean = $4

    Figure 4.12 Life-Cycle Cost Savings for 1F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 98.27% from $0 to +Infinity

    Mean = $17.000

    .036

    .072

    .107

    .143

    0

    358

    716

    1432

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 1F40 (Commercial) - T8 ERS

    Figure 4.13 Life-Cycle Cost Savings for 1F32T8 ERS in Commercial Sector

    4-10

  • 8/2/2019 Ballast Lcca

    11/38

    Frequency Chart

    Certainty is 30.84% from $0 to +Infinity

    Mean = ($2).000

    .064

    .128

    .192

    .256

    0

    638.7

    2555

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F40 (Commercial) - CC

    Figure 4.14 Life-Cycle Cost Savings for 2F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 80.49% from $0 to +Infinity

    .000

    .046

    .092

    .138

    .184

    0

    460.2

    920.5

    1841

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F40 (Commercial) - ERS

    Mean = $6

    Figure 4.15 Life-Cycle Cost Savings for 2F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 97.76% from $0 to +Infinity

    Mean = $18.000

    .030

    .060

    .089

    .119

    0

    298.2

    596.5

    894.7

    1193

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F40 (Commercial) - T8 ERS

    Figure 4.16 Life-Cycle Cost Savings for 2F32T8 ERS in Commercial Sector

    4-11

  • 8/2/2019 Ballast Lcca

    12/38

    Frequency Chart

    Certainty is 33.28% from $0 to +Infinity

    Mean = ($2).000

    .050

    .101

    .151

    .202

    0

    504.2

    2017

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 3F40 Tandem-Wired (Commercia

    Figure 4.17 Life-Cycle Cost Savings for Tandem-Wired 3F40T12 CC in Commercial

    Sector

    Frequency Chart

    Certainty is 68.46% from $0 to +Infinity

    Mean = $5.000

    .036

    .073

    .109

    .145

    0

    362.5

    725

    1450

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 3F40 Tandem-Wired (Commercia

    Figure 4.18 Life-Cycle Cost Savings for Tandem-Wired 3F40T12 ERS in Commercial

    Sector

    Frequency Chart

    Certainty is 97.61% from $0 to +Infinity

    Mean = $27.000

    .022

    .043

    .065

    .086

    0

    215

    430

    645

    860

    ($150) ($75) $0 $75 $150

    10,000 Trials 1 Outlier

    Forecast: LCC Savings 3F40 Tandem-Wired (Commercia

    Figure 4.19 Life-Cycle Cost Savings for Tandem-Wired 3F32T8 ERS in Commercial

    Sector

    4-12

  • 8/2/2019 Ballast Lcca

    13/38

    Frequency Chart

    Certainty is 23.26% from $0 to +Infinity

    Mean = ($4).000

    .050

    .100

    .150

    .201

    0

    501.2

    2005

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 3F40 Non-Tandem (Commercia)

    Figure 4.20 Life-Cycle Cost Savings for Non-Tandem-Wired 3F40T12 CC in Commercial

    Sector

    Frequency Chart

    Certainty is 97.02% from $0 to +Infinity

    Mean = $16.000

    .033

    .066

    .099

    .132

    0

    329.7

    659.5

    989.2

    1319

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 3F40 Non-Tandem (Commercial)

    Figure 4.21 Life-Cycle Cost Savings for Non-Tandem-Wired 3F40T12 ERS in Commercial

    Sector

    Frequency Chart

    Mean = $56.000

    .016

    .033

    .049

    .066

    0

    164

    328

    492

    656

    ($150) ($75) $0 $75 $150

    10,000 Trials 11 Outliers

    Forecast: LCC Savings 3F40 Non-Tandem (Commercial

    Figure 4.22 Life-Cycle Cost Savings for Non-Tandem-Wired 3F32T8 ERS in Commercial

    Sector

    4-13

  • 8/2/2019 Ballast Lcca

    14/38

    Frequency Chart

    Certainty is 36.26% from $0 to +Infinity

    Mean = ($2).000

    .039

    .078

    .117

    .156

    0

    390.2

    780.5

    1561

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 4F40 (Commercial) - CC

    Figure 4.23 Life-Cycle Cost Savings for 4F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 87.16% from $0 to +Infinity

    Mean = $12.000

    .029

    .058

    .088

    .117

    0

    291.7

    583.5

    875.2

    1167

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 4F40 (Commercial) - ERS

    Figure 4.24 Life-Cycle Cost Savings for 4F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 99.46% from $0 to +Infinity

    Mean = $44

    .000

    .017

    .033

    .050

    .067

    0

    166.7

    333.5

    500.2

    667

    ($150) ($75) $0 $75 $150

    10,000 Trials 10 Outliers

    Forecast: LCC Savings 4F40 (Commercial) - T8 ERS

    Figure 4.25 Life-Cycle Cost Savings for 4F32T8 ERS with Dual Switching Capability in

    Commercial Sector

    4-14

  • 8/2/2019 Ballast Lcca

    15/38

    Frequency Chart

    Mean = $54.000

    .016

    .032

    .047

    .063

    0

    157.7

    315.5

    473.2

    631

    ($150) ($75) $0 $75 $150

    10,000 Trials 15 Outliers

    Forecast: LCC Savings 4F40 (Commercial) - T8 ERS

    Figure 4.26 Life-Cycle Cost Savings for 4F32T8 ERS without Dual Switching Capability in

    Commercial Sector

    Frequency Chart

    Certainty is 74.54% from $0 to +Infinity

    Mean = $7.000

    .033

    .067

    .100

    .133

    0

    332.7

    665.5

    998.2

    1331

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F96 (Commercial) - EIS

    Figure 4.27 Life-Cycle Cost Savings for 2F96T12 EIS in Commercial Sector

    Frequency Chart

    Certainty is 35.35% from $0 to +Infinity

    Mean = ($2)

    .000

    .046

    .093

    .139

    .185

    0

    463.5

    927

    1854

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F96 (Industrial) - EIS

    Figure 4.28 Life-Cycle Cost Savings for 2F96T12 EIS in Industrial Sector

    4-15

  • 8/2/2019 Ballast Lcca

    16/38

    Frequency Chart

    Certainty is 90.02% from $0 to +Infinity

    Mean = $11.000

    .037

    .073

    .110

    .146

    0

    365.5

    731

    1462

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F96HO (Commercial) - CC

    Figure 4.29 Life-Cycle Cost Savings for 2F96T12HO CC in Commercial Sector

    Frequency Chart

    Certainty is 97.90% from $0 to +Infinity

    Mean = $28.000

    .021

    .042

    .063

    .084

    0

    210.7

    421.5

    632.2

    843

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F96HO (Commercial) - ERS

    Figure 4.30 Life-Cycle Cost Savings for 2F96T12HO ERS in Commercial Sector

    Frequency Chart

    Certainty is 50.10% from $0 to +Infinity

    Mean = $1.000

    .045

    .089

    .134

    .179

    0

    446.5

    893

    1786

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Savings 2F96HO (Industrial) - CC

    Figure 4.31 Life-Cycle Cost Savings for 2F96T12HO CC in Industrial Sector

    4-16

  • 8/2/2019 Ballast Lcca

    17/38

    Frequency Chart

    Certainty is 94.28% from $0 to +Infinity

    Mean = $15.000

    .030

    .061

    .091

    .122

    0

    304.2

    608.5

    912.7

    1217

    10,000 Trials 0 Outliers

    ($150) ($75) $0 $75 $150

    Forecast: LCC Savings 2F96HO (Industrial) - ERS

    Figure 4.32 Life-Cycle Cost Savings for 2F96T12HO ERS in Industrial Sector

    Energy Efficient T8 Magnetic Ballast Baseline. Table 4.4 and the following 5 figures

    present the results of an LCC analysis looking at switching from a T8 magnetic ballast baseline to

    a more energy efficient T8 ballast for 1 and 2 lamp fixtures. For the EIS and CC ballasts, there is areduction in lamp lifetime from 19,000 hours to 14,000 and 16,150 hours, respectively that is taken

    into account in the LCC analysis. The ballast prices used for this LCC analysis are shown below. The

    magnetic and cathode cutout ballast prices come from the July, 1997 ballast report. The ERS prices

    are shown in Chapter 3 and the EIS prices are assumed to be $1 less than the ERS ballast prices.

    Table 4.4 Summary of Delta LCC* Results Using an EEM T8 Ballast as a Baseline

    Product Class Design Option Sector Delta LCC

    Mean

    (1997$)

    % of

    Baseline

    LCC

    %

    Reduced**

    LCC1F32

    T8 ERS Commercial 6 5% 96%

    T8 EIS Commercial 1 1% 54%

    2F32

    T8 CC Commercial 0 0% 52%

    T8 ERS Commercial 9 4% 97%

    T8 EIS Commercial 6 3% 79%* A positive Delta LCC implies a LCC savings whereas a negative number implies an increase in LCC.

    ** % ballasts with reduced life cycle cost.

    4-17

  • 8/2/2019 Ballast Lcca

    18/38

    Table 4.5 T8 Ballast Prices for Use with T8 Ballast LCC Analysis

    Ballast Price (1997$)

    Product Class Baseline EEM CC ERS EIS

    1-lamp ballast 15.96 N/A 20.10 19.10

    2-lamp ballast 15.60 19.24 21.54 20.54

    Frequency Chart

    Certainty is 96.14% from $0 to +Infinity

    .000

    .082

    .164

    .245

    .327

    0

    818.2

    3273

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Sav 1F32 ERS Comm

    Figure 4.33 Life-Cycle Cost Savings for 1F32T8 ERS in Commercial Sector

    Frequency Chart

    Certainty is 53.76% from $0 to +Infinity

    .000

    .083

    .167

    .250

    .333

    0

    832.7

    3331

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC 1F32 EIS Comm

    Figure 4.34 Life-Cycle Cost Savings for 1F32T8 EIS in Commercial Sector

    4-18

  • 8/2/2019 Ballast Lcca

    19/38

    Frequency Chart

    Certainty is 52.20% from $0 to +Infinity

    .000

    .076

    .152

    .228

    .304

    0

    759.2

    3037

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Sav 2F32 CC Comm

    Figure 4.35 Life-Cycle Cost Savings for 2F32T8 CC in Commercial Sector

    Frequency Chart

    Certainty is 96.76% from $0 to +Infinity

    .000

    .055

    .110

    .165

    .220

    0

    550.2

    2201

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Sav 2F32 ERS Comm

    Figure 4.36 Life-Cycle Cost Savings for 2F32T8 ERS in Commercial Sector

    Frequency Chart

    Certainty is 78.93% from $0 to +Infinity

    .000

    .052

    .105

    .157

    .210

    0

    524.5

    2098

    ($150) ($75) $0 $75 $150

    10,000 Trials 0 Outliers

    Forecast: LCC Sav 2F32 EIS Comm

    Figure 4.37 Life-Cycle Cost Savings for 2F32T8 EIS in Commercial Sector

    4-19

  • 8/2/2019 Ballast Lcca

    20/38

    4.2 PAYBACK PERIODS BY ENERGY-EFFICIENCY LEVEL

    The payback period (PAY) is the amount of time needed to recover through lower operating

    costs, OC, the additional consumer investment, PC, in increased efficiency. PAY is found by

    solving the equation:

    PAY

    PC OCt

    O (4.4)t 1

    forPAY. In general,PAYis found by interpolating between the two years when the expression in

    Eq. 4.4 changes sign. If the operating cost is constant, the equation has the simple solution:

    PCPAY (4.5)

    OC

    Numerically, the payback period is the ratio of the difference in purchase (and installation)

    price between the base and the energy-efficient models to the decrease in annual operating

    expenditures (including maintenance). Annual operating costs for ballasts include annual lamp

    replacement cost plus annual electricity cost.

    PCPAY (4.6)

    EC LRC

    where EC is the electricity cost and LRC is the lamp replacement cost. Because the life of a lampwith a CC or EIS ballast is less than that of a lamp with an EEM or ERS ballast, lamp replacement

    costs may occur at different times during the life of the ballast, depending upon the ballast-lamp

    combination. A longer lamp life results in a lower operating cost. In order to account for differences

    in lamp life, the cost of lamp replacement has been divided over the life of the lamp so that an annual

    lamp replacement cost (LRC) is equal to:

    LRCCost of Lamp Replacement

    (4.7)Lamp Life

    For example, consider the payback calculation for going from an EEM to a CC ballast for the

    2F40T12/ES case. Suppose the ballast equipment and labor costs are $34.54 and $39.43 for the

    EEM and CC options, respectively. The annual electricity costs are $19.55 and $17.81, respectively,

    and the lamp equipment and labor cost is $14.78 for each. The lamp service life for EEM ballasts

    is 5.28 yrs and for CC it is 4.49 yrs. Thus, we have PC = $-4.89, EC = $1.74/yr and

    4-20

  • 8/2/2019 Ballast Lcca

    21/38

    14.78 14.78LRC $0.49/yr

    5.28 4.49

    This results in a payback period of equation as follows:4.89

    PAY 3.9yrs1.74 0.49

    Note there has been no discounting of lamp costs or electricity costs in this formulation of payback

    period.

    Payback periods are expressed in years. A payback period of three years means that the

    increased purchase price for an energy-efficient ballast relative to a baseline ballast is recovered in

    approximately three years because of lower operating expenses. Payback periods greater than the

    life of the product mean that the increased purchase price is not recovered through reduced operatingexpenses.

    4.2.1 Payback Period Results

    The output from the payback period analysis is a distribution of paybacks that may contain

    negative values. Occasionally, very large negative values (for cathode-cutout ballasts) distort the

    mean payback period value. For this reason, we present the median payback period. Therefore, for

    the 10,000 cases analyzed for each lamp/ballast combination, 5000 have payback periods below and

    5,000 have payback periods above the median values shown in the table. It is possible for the median

    payback period to be negative if the first cost of the ballast plus lamp is lower for the more efficient

    technology than for the baseline. We interpret negative payback periods (e.g., for three-lamp nontandem, T8 ERS and 4 lamp T8 ERS) as essentially immediate paybacks. A summary listing the

    median payback period for each lamp/ballast combination is presented in Table 4.6. The

    corresponding probability distributions are presented in Figures 4.38 to 4.59. Table 4.7 and Figures

    4.60 to 4.64 present the summary results and corresponding probability distributions using the energy

    efficient T8 magnetic ballast as the baseline. The last column in the summary table presents the

    percent of cases for which the median payback period is less than 15 years. A 15-year period was

    chosen because it approximates average ballast life for most of the lamp/ballast combinations.

    4-21

  • 8/2/2019 Ballast Lcca

    22/38

    Table 4.6 Summary of Payback Periods Using the T12 EEM as the Baseline

    Product Class Design

    Option

    Sector Median

    Payback

    Period (yrs)

    % With Payback

    Less Than 15 yrs

    1F40

    T12 CC Commercial 24.8 26

    T12 ERS Commercial 6.4 94

    T8 ERS Commercial 2.7 99

    2F40

    T12 CC Commercial 10.7 71

    T12 ERS Commercial 5.4 96

    T8 ERS Commercial 3.1 99

    3F40

    Tandem-Wired T12 CC Commercial 9.9 76

    T12 ERS Commercial 6.4 93

    T8 ERS Commercial 3.1 99

    Not Tandem-Wired T12 CC Commercial 11.5 68

    T12 ERS Commercial 3.3 99

    T8 ERS Commercial 0.0 100

    4F40

    T12 CC Commercial 9.3 80

    T12 ERS Commercial 4.8 97Dual Switching T8 ERS Commercial 1.9 100

    w/o Dual Switching T8 ERS Commercial 0.4 100

    2F96

    T12 EIS Commercial 5.9 94

    T12 EIS Industrial 8.8 84

    2F96HO

    T12 CC Commercial 2.1 98

    T12 ERS Commercial 2.4 99

    T12 CC Industrial 5.4 76

    T12 ERS Industrial 3.1 99

    4-22

  • 8/2/2019 Ballast Lcca

    23/38

    Frequency Chart

    Certainty is 26.42% from 0.0 to 15.0

    .000

    .003

    .005

    .008

    .010

    0

    25.75

    51.50

    77.25

    103

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 4,064 Outliers

    Forecast: Payback 1F40 (Commercial) - CC

    Figure 4.38 Payback Distribution for 1F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 93.54% from 0.0 to 15.0

    .000

    .011

    .022

    .033

    .044

    0

    109

    218

    327

    436

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 132 Outliers

    Forecast: Payback 1F40 (Commercial) - ERS

    Figure 4.39 Payback Distribution for 1F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 99.20% from 0.0 to 15.0

    .000

    .027

    .053

    .080

    .106

    0

    265

    530

    795

    1060

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 19 Outliers

    Forecast: Payback 1F40 (Commercial) - T8 ERS

    Figure 4.40 Payback Distribution for 1F32T8 ERS in Commercial Sector

    4-23

  • 8/2/2019 Ballast Lcca

    24/38

    Frequency Chart

    Certainty is 70.92% from 0.0 to 15.0

    .000

    .006

    .012

    .018

    .024

    0

    60.75

    121.5

    182.2

    243

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 636 Outliers

    Forecast: Payback 2F40 (Commercial) - CC

    Figure 4.41 Payback Distribution for 2F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 95.90% from 0.0 to 15.0

    .000

    .013

    .026

    .039

    .052

    0

    129.2

    258.5

    387.7

    517

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 62 Outliers

    Forecast: Payback 2F40 (Commercial)- ERS

    Figure 4.42 Payback Distribution for 2F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 98.91% from 0.0 to 15.0

    .000

    .022

    .044

    .066

    .088

    0

    220.2

    440.5

    660.7

    881

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 23 Outliers

    Forecast: Payback 2F40 (Commercial)- T8 ERS

    Figure 4.43 Payback Distribution for 2F32T8 ERS in Commercial Sector

    4-24

  • 8/2/2019 Ballast Lcca

    25/38

    Frequency Chart

    Certainty is 76.21% from 0.0 to 15.0

    .000

    .006

    .013

    .019

    .025

    0

    62.75

    125.5

    188.2

    251

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 449 Outliers

    Forecast: Payback 3F40 Tandem-Wired (Commercial) -

    Figure 4.44 Payback Distribution for Tandem-Wired 3F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 93.37% from 0.0 to 15.0

    .000

    .011

    .022

    .033

    .044

    0

    109.2

    218.5

    327.7

    437

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 113 Outliers

    Forecast: Payback 3F40 Tandem-Wired (Commercial) -

    Figure 4.45 Payback Distribution for Tandem-Wired 3F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 98.90% from 0.0 to 15.0

    .000

    .022

    .043

    .065

    .086

    0

    215.5

    430.9

    646.5

    861.9999999

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 23 Outliers

    Forecast: Payback 3F40 Tandem-Wired (Commercial) -

    Figure 4.46 Payback Distribution for Tandem-Wired 3F32T8 ERS in Commercial Sector

    4-25

  • 8/2/2019 Ballast Lcca

    26/38

    Frequency Chart

    Certainty is 68.48% from 0.0 to 15.0

    .000

    .006

    .013

    .019

    .025

    0

    62.5

    125

    187.5

    250

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 628 Outliers

    Forecast: Payback 3F40 Non-Tandem (Commercial) - C

    Figure 4.47 Payback Distribution for Non-Tandem-Wired 3F40T12 CC in Commercial

    Sector

    Frequency Chart

    Certainty is 98.97% from 0.0 to 15.0

    .000

    .021

    .041

    .062

    .083

    0

    207

    414

    621

    828

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 23 Outliers

    Forecast: Payback 3F40 Non-Tandem (Commercial) - E

    Figure 4.48 Payback Distribution for Non-Tandem-Wired 3F40T12 ERS in Commercial

    Sector

    Frequency Chart

    .000

    .250

    .500

    .750

    1.000

    0

    9997

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 0 Outliers

    Forecast: Payback 3F40 Non-Tandem (Commercial) - T

    Figure 4.49 Payback Distribution for Non-Tandem-Wired 3F32T8 ERS in Commercial

    Sector

    4-26

  • 8/2/2019 Ballast Lcca

    27/38

    Frequency Chart

    Certainty is 79.66% from 0.0 to 15.0

    .000

    .007

    .014

    .021

    .028

    0

    69.75

    139.5

    209.2

    279

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 352 Outliers

    Forecast: Payback 4F40 (Commercial) - CC

    Figure 4.50 Payback Distribution for 4F40T12 CC in Commercial Sector

    Frequency Chart

    Certainty is 96.94% from 0.0 to 15.0

    .000

    .014

    .028

    .042

    .056

    0

    140

    280

    420

    559.9999999

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 46 Outliers

    Forecast: Payback 4F40 (Commercial) - ERS

    Figure 4.51 Payback Distribution for 4F40T12 ERS in Commercial Sector

    Frequency Chart

    Certainty is 99.61% from 0.0 to 15.0

    .000

    .035

    .069

    .104

    .138

    0

    345.2

    690.5

    1381

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 7 Outliers

    Forecast: Payback 4F40 (Commercial) - T8 ERS

    Figure 4.52 Payback Distribution for 4F32T8 ERS with Dual Switching Capability in

    Commercial Sector

    4-27

  • 8/2/2019 Ballast Lcca

    28/38

    Frequency Chart

    .000

    .122

    .245

    .367

    .490

    0

    4899

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 0 Outliers

    Forecast: Payback 4F40 (Commercial) - T8 ERS

    Figure 4.53 Payback Distribution for 4F32T8 ERS without Dual Switching Capability in

    Commercial Sector

    Frequency Chart

    Certainty is 93.38% from 0.0 to 15.0

    .000

    .012

    .024

    .035

    .047

    0

    118

    236

    354

    472

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 150 Outliers

    Forecast: Payback 2F96 (Commercial) - EIS

    Figure 4.54 Payback Distribution for 2F96T12 EIS in Commercial Sector

    Frequency Chart

    Certainty is 84.26% from 0.0 to 15.0

    .000

    .008

    .015

    .023

    .031

    0

    76.75

    153.5

    230.2

    307

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 150 Outliers

    Forecast: Payback 2F96 (Industrial) - EIS

    Figure 4.55 Payback Distribution for 2F96T12 EIS in Industrial Sector

    4-28

  • 8/2/2019 Ballast Lcca

    29/38

    Frequency Chart

    Certainty is 97.91% from 0.0 to 15.0

    .000

    .027

    .055

    .082

    .110

    0

    274.5

    549

    823.5

    1098

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 97 Outliers

    Forecast: Payback 2F96HO (Commercial) - CC

    Figure 4.56 Payback Distribution for 2F96T12HO CC in Commercial Sector

    Frequency Chart

    Certainty is 98.88% from 0.0 to 15.0

    .000

    .028

    .055

    .083

    .111

    0

    276.5

    553

    829.5

    1106

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 56 Outliers

    Forecast: Payback 2F96HO (Commercial) - ERS

    Figure 4.57 Payback Distribution for 2F96T12HO ERS in Commercial Sector

    Frequency Chart

    Certainty is 76.29% from 0.0 to 15.0

    .000

    .010

    .020

    .030

    .040

    0

    101

    202

    303

    404

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 1,782 Outliers

    Forecast: Payback 2F96HO (Industrial) - CC

    Figure 4.58 Payback Distribution for 2F96T12HO CC in Industrial Sector

    4-29

  • 8/2/2019 Ballast Lcca

    30/38

    Frequency Chart

    Certainty is 99.16% from 0.0 to 15.0

    .000

    .022

    .044

    .066

    .088

    0

    219

    438

    657

    876

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 20 Outliers

    Forecast: Payback 2F96HO (Industrial) - ERS

    Figure 4.59 Payback Distribution for 2F96T12HO ERS in Industrial Sector

    Table 4.7 Summary of Payback Periods Using a T8 EEM Ballast as the Baseline

    Product Class Design

    Option

    Sector Median

    Payback

    Period (yrs)

    % With Payback

    Less Than 15 yrs

    1F32

    T8 ERS Commercial 3.4 99%

    T8 EIS Commercial 6.6 81%

    2F32

    T8 CC Commercial 8.2 78%

    T8 ERS Commercial 3.3 100%

    T8 EIS Commercial 4.0 95%

    Frequency Chart

    Certainty is 98.57% from 0.0 to 15.0

    .000

    .021

    .042

    .062

    .083

    0

    208.2

    416.5

    624.7

    833

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 31 Outliers

    Forecast: Payback 1F32 ERS Comm

    Figure 4.60 Payback Distribution for 1F32T8 ERS in Commercial Sector

    4-30

  • 8/2/2019 Ballast Lcca

    31/38

    Frequency Chart

    Certainty is 80.53% from 0.0 to 15.0

    .000

    .009

    .017

    .026

    .035

    0

    86.5

    173

    259.5

    346

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 886 Outliers

    Forecast: Payback 1F32 EIS Comm

    Figure 4.61 Payback Distribution for 1F32T8 EIS in Commercial Sector

    Frequency Chart

    Certainty is 77.89% from 0.0 to 15.0

    .000

    .007

    .014

    .021

    .028

    0

    69.75

    139.5

    209.2

    279

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 704 Outliers

    Forecast: Payback 2F32 CC Comm

    Figure 4.62 Payback Distribution for 2F32T8 CC in Commercial Sector

    Frequency Chart

    Certainty is 99.77% from 0.0 to 30.0

    .000

    .021

    .043

    .064

    .085

    0

    213.5

    427

    640.5

    854

    0.0 7.5 15.0 22.5 30.0

    10,000 Trials 23 Outliers

    Forecast: Payback 2F32 ERS Comm

    Figure 4.63 Payback Distribution for 2F32T8 ERS in Commercial Sector

    4-31

  • 8/2/2019 Ballast Lcca

    32/38

    Frequency Chart

    Certainty is 94.54% from 0.0 to 15.0

    .000

    .014

    .028

    .042

    .057

    0

    141.5

    283

    424.5

    566

    10,000 Trials 180 Outliers

    0.0 7.5 15.0 22.5 30.0

    Forecast: Payback 2F32 EIS Comm

    Figure 4.64 Payback Distribution for 2F32T8 EIS in Commercial Sector

    4.3 SENSITIVITY ANALYSIS

    In order to observe the sensitivity of LCC to discount rates and electricity prices, we

    performed additional analyses. For discount rates, we recalculated the LCC savings using a low (4%)

    and a high (15%) estimate of the consumer discount rate. Tables 4.8 and 4.9 show the results of this

    sensitivity analysis for each case respectively.

    For electricity prices, we recalculated the LCC savings and the Payback using the both the

    AEO 1999 High Economic Growth Forecast, and the AEO 1999 Low Economic Growth Forecast.

    Tables 4.10 and 4.11 show the LCC and Payback results for the High Growth Forecast. Tables 4.12

    and 4.13 show the results for the Low Growth Forecast.

    4-32

  • 8/2/2019 Ballast Lcca

    33/38

    Table 4.8 Summary of Delta LCC* Sensitivity Results with 4% Discount Rate

    Product Class Design Option Sector Delta LCC

    Mean

    (1997$)

    % of

    Baseline

    LCC

    %

    Reduced**

    LCC

    1F40

    T12 CC Commercial -4 -3% 18%

    T12 ERS Commercial 9 6% 87%

    T8 ERS Commercial 24 15% 100%

    2F40

    T12 CC Commercial 0 0% 49%

    T12 ERS Commercial 11 5% 93%

    T8 ERS Commercial 27 11% 99%

    3F40

    Tandem-Wired T12 CC Commercial 1 0% 52%

    T12 ERS Commercial 12 4% 86%

    T8 ERS Commercial 39 12% 99%

    Not Tandem-Wired T12 CC Commercial -1 0% 42%

    T12 ERS Commercial 24 7% 99%

    T8 ERS Commercial 72 21% 100%

    4F40

    T12 CC Commercial 3 1% 56%

    T12 ERS Commercial 21 5% 96%

    Tandem-Wired*** T8 ERS Commercial 61 14% 100%

    Not Tandem-Wired T8 ERS Commercial 70 17% 100%

    2F96

    T12 EIS Commercial 15 4% 91%

    T12 EIS Industrial 3 1% 59%

    2F96HO

    T12 CC Commercial 14 2% 91%

    T12 ERS Commercial 40 6% 99%

    T12 CC Industrial 2 0% 54%

    T12 ERS Industrial 22 4% 97%* A positive Delta LCC implies a LCC savings whereas a negative number implies an increase in LCC.** % ballasts with reduced life-cycle costs.*** 4F32T8 ERS ballast with Dual Switching includes a $10 incremental increase in materials and labor

    4-33

  • 8/2/2019 Ballast Lcca

    34/38

    Table 4.9 Summary of Delta LCC* Sensitivity Results with 15% Discount Rate

    Product Class Design Option Sector Delta LCC

    Mean

    (1997$)

    % of

    Baseline

    LCC

    %

    Reduced**

    LCC

    1F40

    T12 CC Commercial -5 -5% 1%

    T12 ERS Commercial -1 -1% 35%

    T8 ERS Commercial 9 9% 93%

    2F40

    T12 CC Commercial -4 -3% 12%

    T12 ERS Commercial 1 1% 50%

    T8 ERS Commercial 10 7% 90%

    3F40

    Tandem-Wired T12 CC Commercial -5 -3% 13%

    T12 ERS Commercial -2 -1% 36%

    T8 ERS Commercial 14 7% 90%

    Not Tandem-Wired T12 CC Commercial -8 -4% 7%

    T12 ERS Commercial 8 4% 86%

    T8 ERS Commercial 40 19% 100%

    4F40

    T12 CC Commercial -7 -3% 15%

    T12 ERS Commercial 3 1% 61%

    Tandem-Wired*** T8 ERS Commercial 27 11% 97%

    Not Tandem-Wired T8 ERS Commercial 37 15% 100%

    2F96

    T12 EIS Commercial 0 0% 43%

    T12 EIS Industrial -6 -3% 13%

    2F96HO

    T12 CC Commercial 6 1% 85%

    T12 ERS Commercial 17 4% 93%

    T12 CC Industrial 0 0% 41%

    T12 ERS Industrial 8 2% 83%* A positive Delta LCC implies a LCC savings whereas a negative number implies an increase in LCC.** % ballasts with reduced life-cycle costs.*** 4F32T8 ERS ballast with Dual Switching includes a $10 incremental increase in materials and labor.

    4-34

  • 8/2/2019 Ballast Lcca

    35/38

    Table 4.10 Summary of Delta LCC* Sensitivity Results using AEO 1999 High Growth

    Forecast

    Product Class Design Option Sector Delta LCC

    Mean

    (1997$)

    % of

    Baseline

    LCC

    %

    Winners**

    1F40

    T12 CC Commercial -4 -3% 9%

    T12 ERS Commercial 5 4% 73%

    T8 ERS Commercial 18 13% 99%

    2F40

    T12 CC Commercial -1 -1% 35%

    T12 ERS Commercial 7 4% 84%

    T8 ERS Commercial 20 10% 98%

    3F40

    Tandem-Wired T12 CC Commercial -1 0% 38%

    T12 ERS Commercial 6 2% 73%

    T8 ERS Commercial 30 11% 98%

    Not Tandem-Wired T12 CC Commercial -3 1% 27%

    T12 ERS Commercial 18 6% 98%

    T8 ERS Commercial 59 20% 100%

    4F40

    T12 CC Commercial -1 0% 41%

    T12 ERS Commercial 14 4% 90%

    Dual Switching*** T8 ERS Commercial

    w/o Dual Switching T8 ERS Commercial 57 16% 100%

    2F96

    T12 EIS Commercial 8 1% 78%

    T12 EIS Industrial -1 0% 39%

    2F96HO

    T12 CC Commercial 12 2% 92%

    T12 ERS Commercial 30 5% 98%

    T12 CC Industrial 2 0% 54%

    T12 ERS Industrial 17 4% 95%* A positive Delta LCC implies a LCC savings whereas a negative number implies an increase in LCC.** % ballasts with reduced life-cycle costs (winners).*** 4F32T8 ERS ballast with Dual Switching includes a $10 incremental increase in purchase price.

    4-35

  • 8/2/2019 Ballast Lcca

    36/38

    Table 4.11 Summary of Payback Sensitivity using AEO 1999 High Growth Forecast

    Product Class Design

    Option

    Sector Median

    Payback

    Period (yrs)

    % With Payback

    Less Than 15 yrs

    1F40

    T12 CC Commercial 23.5 29%

    T12 ERS Commercial 6.3 93%

    T8 ERS Commercial 2.6 99%

    2F40

    T12 CC Commercial 10.3 74%

    T12 ERS Commercial 5.3 96%

    T8 ERS Commercial 3.0 99%

    3F40

    Tandem-Wired T12 CC Commercial 9.6 79%T12 ERS Commercial 6.2 94%

    T8 ERS Commercial 3.0 99%

    Not Tandem-Wired T12 CC Commercial 11.1 71%

    T12 ERS Commercial 3.2 99%

    T8 ERS Commercial 0.0 100%

    4F40

    T12 CC Commercial 9.1 82%

    T12 ERS Commercial 4.7 97%

    Dual Switching T8 ERS Commercial 1.8 100%

    w/o Dual Switching T8 ERS Commercial 0.4 100%

    2F96

    T12 EIS Commercial 5.7 94%

    T12 EIS Industrial 8.6 85%

    2F96HO

    T12 CC Commercial 2.0 98%

    T12 ERS Commercial 2.3 99%

    T12 CC Industrial 5.0 78%

    T12 ERS Industrial 3.1 99%

    4-36

  • 8/2/2019 Ballast Lcca

    37/38

    Table 4.12 Summary of Delta LCC* Sensitivity Results using AEO 1999 Low Growth

    Forecast

    Product Class Design Option Sector Delta LCC

    Mean

    (1997$)

    % of

    Baseline

    LCC

    %

    Winners**

    1F40

    T12 CC Commercial -5 -4% 6%

    T12 ERS Commercial 3 2% 61%

    T8 ERS Commercial 15 12% 98%

    2F40

    T12 CC Commercial -3 2% 25%

    T12 ERS Commercial 5 3% 76%

    T8 ERS Commercial 16 9% 97%

    3F40

    Tandem-Wired T12 CC Commercial -3 -1% 28%

    T12 ERS Commercial 3 1% 61%

    T8 ERS Commercial 24 10% 97%

    Not Tandem-Wired T12 CC Commercial -5 2% 18%

    T12 ERS Commercial 14 5% 96%

    T8 ERS Commercial 52 19% 100%

    4F40

    T12 CC Commercial -3 -1% 30%

    T12 ERS Commercial 10 3% 83%

    Dual Switching*** T8 ERS Commercial 40 12% 99%

    w/o Dual Switching T8 ERS Commercial 49 15% 100%

    2F96

    T12 EIS Commercial 6 2% 69%

    T12 EIS Industrial -2 -1% 31%

    2F96HO

    T12 CC Commercial 9 2% 86%

    T12 ERS Commercial 26 5% 97%

    T12 CC Industrial 0 0% 45%

    T12 ERS Industrial 14 3% 93%* A positive Delta LCC implies a LCC savings whereas a negative number implies an increase in LCC.** % ballasts with reduced life-cycle costs (winners).*** 4F32T8 ERS ballast with Dual Switching includes a $10 incremental increase in purchase price.

    4-37

  • 8/2/2019 Ballast Lcca

    38/38

    Table 4.13 Summary of Payback Sensitivity using AEO 1999 Low Growth Forecast

    Product Class Design

    Option

    Sector Median

    Payback

    Period (yrs)

    % With Payback

    Less Than 15 yrs

    1F40

    T12 CC Commercial 27.8 24

    T12 ERS Commercial 6.7 92

    T8 ERS Commercial 2.8 99

    2F40

    T12 CC Commercial 11.6 66

    T12 ERS Commercial 5.7 95

    T8 ERS Commercial 3.3 99

    3F40

    Tandem-Wired T12 CC Commercial 10.6 72T12 ERS Commercial 6.7 93

    T8 ERS Commercial 3.3 99

    Not Tandem-Wired T12 CC Commercial 12.3 64

    T12 ERS Commercial 3.5 99

    T8 ERS Commercial 0.0 100

    4F40

    T12 CC Commercial 10.0 76

    T12 ERS Commercial 5.1 96

    Dual Switching T8 ERS Commercial 2.0 100

    w/o Dual Switching T8 ERS Commercial 0.4 100

    2F96

    T12 EIS Commercial 6.1 93

    T12 EIS Industrial 9.1 83

    2F96HO

    T12 CC Commercial 2.3 98

    T12 ERS Commercial 2.5 99

    T12 CC Industrial 6.0 73

    T12 ERS Industrial 3.2 99