balance of plant.doc

Upload: shringimahesh

Post on 03-Apr-2018

218 views

Category:

Documents


0 download

TRANSCRIPT

  • 7/29/2019 Balance of Plant.doc

    1/5

    Balance of Plants

    Balance of Plants was identified as critical items for timely commissioning of Thermal Power

    Projects. It was observed that a number of Thermal units were getting delayed due to delay in

    commissioning of Balance of Plants such as Coal Handling Plants (CHPs), Ash Handling Plants

    (AHPs), Cooling Tower (CTs) etc.

    A coal based thermal power plant consists of large number of integrated plants/systems and

    equipment having mechanical, electrical, instrumentation & control and civil components. Theplant systems and equipment can be broadly classified into following two categories:-

    i) Main Plant comprising of steam generator, steam turbine and generator along

    with their associated auxiliaries.

    ii) Balance of Plants (BOP) system which includes all plants and equipment other than those

    included in main plant system. The major components of BOP system include coal handling

    plant, ash handling plant, fuel oil handling & unloading system, water treatment system,

    circulating water system and fire protection, detection & alarm system. As regards BOP systems,

    a number of site specific input parameters are involved which have to be kept in view while

    designing various systems.

    For example while designing coal handling system the site specific points to be considered

    include station capacity, quality and source of coal, coal transportation mode, topography and

    geometry of the area while for ash handling system, station capacity, ash content in fuel, mode ofash disposal, ash utilization potential, layout and pumping distances have a bearing on the design

    of ash handling system. In view of site specific variations, it is very difficult to draft a standard

    technical specification incorporating for all possible alternatives of plant systems and equipment.

    Accordingly, attempt has been made to evolve standard design criteria/ guidelines which will bea useful reference document and help the utilities in sizing and selection of equipment and

    drawing up a detailed specification specific to the plant.

    There is a need to develop more vendors for the following Balance of Plants:

    i. Ash Handling Plant

    ii. Coal Handling Plant

    iii. DM Plants

    iv. Condensate PolishingUnits

    v. CW and Make up System

    vi. Cooling Towers

    vii. Air Compressors

    viii. Chimneys

    ix. Civil and MechanicalDesign consultancy

    packages

    x. De-salination Plants

  • 7/29/2019 Balance of Plant.doc

    2/5

    There are very limited vendors for each of the above BoPs and at times only

    Single Quotation is received. There is also a need to develop adequate

    erection and construction agencies for executing civil and mechanical works

    and engineering consultants for engineering and design of various packages.

    However, adequate capacity is available for the following BoPs as per the

    presentation given by the various vendors:

    a. Ventilation and Air conditioning

    b. Ash water recirculation

    c. Bus ducts

    d. HV/LV switchgear

    e. Insulation

    It was also suggested that each BoP should invariably be awarded as a

    package instead of breaking up into equipment, civil contracts and

    mechanical erection contractors to have single point responsibility.

    Supportive and developmental attitude should be adopted by the owners to

    encourage new vendors.

    Status of Bops For 11th plan Projects

    Name of the system BOPs required for projects under

    const. (Nos.)

    Coal Handling System 68

    Ash Handling System 68

    DM Plant 69

    Cooling Towers 145

    Chimneys 117

    Fuel Oil System 71

    PT Plant 76

  • 7/29/2019 Balance of Plant.doc

    3/5

    ORDERS FOR MAIN PLANT EQUIPMENT 11thPLAN (Figures in

    MW)

    MAIN PLANT

    EQUIPMENT

    SUPPLIER

    THERMAL HYDRO NUCLEAR TOTAL

    BHEL 36,531 6,017 500 43048

    (54%)

    OTHERS 25,192 9,490 2880 37562

    (46%)

    TOTAL 61,723 15,507 3,380 80,610

    Thermal and Hydro Main Plant Equipment -Need to augment existing

    indigenous manufacturing facilities and create additional capacity

    Current Status (BOPs And Main Plant)

    BHEL augmentation of manufacturing capacity

    To 10,000 MW/annum achieved by Dec 2007.

    To 15,000 MW by Dec. 2009 under progress (10,000 MW/annum for large

    sized boilers and TGs). Has collaboration with Alstom and Siemens for

    manufacture of super critical boilers and turbo-generators. In third phase by

    Dec 2011, proposed to augment

    JVs

    L&T/ MHI Boilers (4000 MW/annum) , TGs (4000 MW). Bharat Forge/

    Alstom- TGs (5000 MW).

    JSW-Toshiba - TGs (3000 MW).

    GB Eng.-Ansaldo-Boilers (2000 MW).

    Proposed Bulk tendering of 11X 660 MW units with mandatory

    indigenous manufacturing.

  • 7/29/2019 Balance of Plant.doc

    4/5

    Components of Major BOPs

    Each Balance of Plant activity consists of various components which

    include:

    Civil works

    Structural works

    Electro mechanical equipments and various types of motors, etc

    Control & Instrumentation

    Issues For Completion Of Bops In Time

    Placement of Order: Timely placement of order for BOPs.

    Review of Pre-qualification Requirements for BOP vendor. CEA

    already recommended revised PQ to allow entry of new players

    Enhancement of vendor base for Balance of Plants

    (BOPs) as the requirement has increased manifold during 11th plan

    and will further increase in 12th Plan.

    There are limited number of suppliers in each category and each

    having more work than what it can handle.

    Favourable conditions to be developed for new / additional vendors

    Actions For Completion Of Bops In Time

    Vendors must take approval for appointment of sub-contractors in

    advance from the project authorities.

    Vendors must place the orders for civil works as well as procurement

    of mechanical equipments in time.

    Timely releasing of civil construction drawings from consultants and

    construction agencies.

    Availability of adequate construction machinery at project site.

    Deployment of adequate skilled / unskilled man power at site.

    Proper coordination among various executing agencies engaged at

    project site.

  • 7/29/2019 Balance of Plant.doc

    5/5

    Loss To The Utilities On Account Of Delay In Completion Of Projects

    Cost of delay (Either due to Main Plant or BOPs)

    Loss on account of purchase of costlier power from alternate

    sourcesRs.2.5 to 6 crores /dayfora500MW pit head unit.

    Increase in IDC and consequently the fixed cost Component of tariff-

    Rs.45lakhs/dayfora500MWcoalbasedunit.

    Loss of return to developer - Rs. 25 lakhs / day for a 500 MW

    Unit@14%ROE.

    http://www.cea.nic.in/more_upload/standard_design_bop_sep10.pdf