balance of plant.doc
TRANSCRIPT
-
7/29/2019 Balance of Plant.doc
1/5
Balance of Plants
Balance of Plants was identified as critical items for timely commissioning of Thermal Power
Projects. It was observed that a number of Thermal units were getting delayed due to delay in
commissioning of Balance of Plants such as Coal Handling Plants (CHPs), Ash Handling Plants
(AHPs), Cooling Tower (CTs) etc.
A coal based thermal power plant consists of large number of integrated plants/systems and
equipment having mechanical, electrical, instrumentation & control and civil components. Theplant systems and equipment can be broadly classified into following two categories:-
i) Main Plant comprising of steam generator, steam turbine and generator along
with their associated auxiliaries.
ii) Balance of Plants (BOP) system which includes all plants and equipment other than those
included in main plant system. The major components of BOP system include coal handling
plant, ash handling plant, fuel oil handling & unloading system, water treatment system,
circulating water system and fire protection, detection & alarm system. As regards BOP systems,
a number of site specific input parameters are involved which have to be kept in view while
designing various systems.
For example while designing coal handling system the site specific points to be considered
include station capacity, quality and source of coal, coal transportation mode, topography and
geometry of the area while for ash handling system, station capacity, ash content in fuel, mode ofash disposal, ash utilization potential, layout and pumping distances have a bearing on the design
of ash handling system. In view of site specific variations, it is very difficult to draft a standard
technical specification incorporating for all possible alternatives of plant systems and equipment.
Accordingly, attempt has been made to evolve standard design criteria/ guidelines which will bea useful reference document and help the utilities in sizing and selection of equipment and
drawing up a detailed specification specific to the plant.
There is a need to develop more vendors for the following Balance of Plants:
i. Ash Handling Plant
ii. Coal Handling Plant
iii. DM Plants
iv. Condensate PolishingUnits
v. CW and Make up System
vi. Cooling Towers
vii. Air Compressors
viii. Chimneys
ix. Civil and MechanicalDesign consultancy
packages
x. De-salination Plants
-
7/29/2019 Balance of Plant.doc
2/5
There are very limited vendors for each of the above BoPs and at times only
Single Quotation is received. There is also a need to develop adequate
erection and construction agencies for executing civil and mechanical works
and engineering consultants for engineering and design of various packages.
However, adequate capacity is available for the following BoPs as per the
presentation given by the various vendors:
a. Ventilation and Air conditioning
b. Ash water recirculation
c. Bus ducts
d. HV/LV switchgear
e. Insulation
It was also suggested that each BoP should invariably be awarded as a
package instead of breaking up into equipment, civil contracts and
mechanical erection contractors to have single point responsibility.
Supportive and developmental attitude should be adopted by the owners to
encourage new vendors.
Status of Bops For 11th plan Projects
Name of the system BOPs required for projects under
const. (Nos.)
Coal Handling System 68
Ash Handling System 68
DM Plant 69
Cooling Towers 145
Chimneys 117
Fuel Oil System 71
PT Plant 76
-
7/29/2019 Balance of Plant.doc
3/5
ORDERS FOR MAIN PLANT EQUIPMENT 11thPLAN (Figures in
MW)
MAIN PLANT
EQUIPMENT
SUPPLIER
THERMAL HYDRO NUCLEAR TOTAL
BHEL 36,531 6,017 500 43048
(54%)
OTHERS 25,192 9,490 2880 37562
(46%)
TOTAL 61,723 15,507 3,380 80,610
Thermal and Hydro Main Plant Equipment -Need to augment existing
indigenous manufacturing facilities and create additional capacity
Current Status (BOPs And Main Plant)
BHEL augmentation of manufacturing capacity
To 10,000 MW/annum achieved by Dec 2007.
To 15,000 MW by Dec. 2009 under progress (10,000 MW/annum for large
sized boilers and TGs). Has collaboration with Alstom and Siemens for
manufacture of super critical boilers and turbo-generators. In third phase by
Dec 2011, proposed to augment
JVs
L&T/ MHI Boilers (4000 MW/annum) , TGs (4000 MW). Bharat Forge/
Alstom- TGs (5000 MW).
JSW-Toshiba - TGs (3000 MW).
GB Eng.-Ansaldo-Boilers (2000 MW).
Proposed Bulk tendering of 11X 660 MW units with mandatory
indigenous manufacturing.
-
7/29/2019 Balance of Plant.doc
4/5
Components of Major BOPs
Each Balance of Plant activity consists of various components which
include:
Civil works
Structural works
Electro mechanical equipments and various types of motors, etc
Control & Instrumentation
Issues For Completion Of Bops In Time
Placement of Order: Timely placement of order for BOPs.
Review of Pre-qualification Requirements for BOP vendor. CEA
already recommended revised PQ to allow entry of new players
Enhancement of vendor base for Balance of Plants
(BOPs) as the requirement has increased manifold during 11th plan
and will further increase in 12th Plan.
There are limited number of suppliers in each category and each
having more work than what it can handle.
Favourable conditions to be developed for new / additional vendors
Actions For Completion Of Bops In Time
Vendors must take approval for appointment of sub-contractors in
advance from the project authorities.
Vendors must place the orders for civil works as well as procurement
of mechanical equipments in time.
Timely releasing of civil construction drawings from consultants and
construction agencies.
Availability of adequate construction machinery at project site.
Deployment of adequate skilled / unskilled man power at site.
Proper coordination among various executing agencies engaged at
project site.
-
7/29/2019 Balance of Plant.doc
5/5
Loss To The Utilities On Account Of Delay In Completion Of Projects
Cost of delay (Either due to Main Plant or BOPs)
Loss on account of purchase of costlier power from alternate
sourcesRs.2.5 to 6 crores /dayfora500MW pit head unit.
Increase in IDC and consequently the fixed cost Component of tariff-
Rs.45lakhs/dayfora500MWcoalbasedunit.
Loss of return to developer - Rs. 25 lakhs / day for a 500 MW
Unit@14%ROE.
http://www.cea.nic.in/more_upload/standard_design_bop_sep10.pdf