august 2, 2007 tac meeting texas nodal program update tim pare
TRANSCRIPT
August 2, 2007TAC Meeting
Texas Nodal Program Update
Tim Pare
August 2, 2007TAC Meeting
Texas Nodal Program Update
Tim Pare
3Texas Nodal Program UpdateAugust 2, 2007 3
Agenda
Item Who Purpose
Nodal Program Status Tim Pare For Information
Nodal Organization Structure Tim Pare For Information
Nodal Schedule Update Tim Pare For Information
Nodal Scorecard Demonstration Tim Pare For Information
Market Readiness Update Tim Pare For Information
Testing Tim Pare For Information
Budget Update Tim Pare For Information
4Texas Nodal Program UpdateAugust 2, 2007 4
The program remains at overall Amber status with Scope / Quality improving following recent Change Control Baseline
CostScheduleScope / Quality
Legend
Summary
Green
The program is spending under budget through June’s actuals. Discussions with the ERCOT
Executive Committee outlined possible ways to ensure we are on
budget at completion.
Amber Amber
Baseline 1 & 2 were approved by the BoD on
July 17 and changes are now being
incorporated
Red
Amber
Green Estimate at Complete = <$248m
Estimate at Complete = $248 - $263m
Estimate at Complete = >$263m
Go-live = 12/1/08
Go-live = <30 days+
Go-live = >30 days+
Program is aligned with current protocols
Program is aligned to previous protocol version
Program is not aligned to protocols
There are several schedule risks in Baseline 1 & 2 which we are
analyzing.
Amber
Current product quality is not sufficient for Nodal launch
Most Nodal products currently achieve quality standards
All Nodal products currently achieve quality standards
All Nodal projects have submitted
Quality Assurance plans, and are in
the process of completing
internal Quality reviews.
Scope/Quality
Nodal
Cost
ScheduleScope/Quality
Schedule
Cost
Nodal Delivery
5Texas Nodal Program UpdateAugust 2, 2007 5
Nodal Organization Chart
July 2007
1 Murray Nixon assumes MMS effective July 23, and Al Hirsch retains EMS project management
2+3 Changes as a result of Steve Grendel assuming new roles in Zonal
1 2
3
6Texas Nodal Program UpdateAugust 2, 2007 6
Market Readiness Update - Market Readiness Metrics Scorecard
Metrics scorecard development late Hired new analyst (C. Wilkinson) Moved responsibility to Program Control Office
Scorecard Iteration 1 Lays foundation for future releases Provides top-level, drill-down, and individual MP results based on survey TPTF Beta available August 10, 2007 Anticipated full release August 17, 2007
Scorecard Iteration 2 in-progress Will display status of ERCOT internal readiness metrics (E1, E8, and E9) Begin to display related EDS metrics Planned go-live end of September
7Texas Nodal Program UpdateAugust 2, 2007 7
Market Readiness Update – Inventory Update & In-Progress and Near-Term Metrics
Current Readiness Metric Inventory to be reviewed by TPTF July 24, 2007
In Progress and Near-Term: ERCOT Departmental reporting
Training and Organization Design - In progress Internal procedures beginning August 1, 2007 Nodal Operating Guides beginning December 1, 2007
ERCOT-observable metrics MP Engagement – In progress EDS 1 Telemetry Alarm Processing – In progress
30 percent validated (30,000 points-to-points complete out of 100,000) MP Registration Activities – September 2007 MP EDS-2 Trials Participation – October 2007
MP Self Reporting First Self Reporting Questionnaire completed July 9, 2007
55 responses received Cleansing data now to ensure consistency across responses
Planned follow-up bi-monthly/quarterly thereafter
8Texas Nodal Program UpdateAugust 2, 2007 8
Market Readiness Update – Wall of Shame*
The following Market Participants have not completed the Self-Reporting Questionnaire:
APN Starfirst LP Barclays Bank PLC Pegasus Alliance Corporation DBA Onpac Energy Pepco Energy Services Inc Pre Buy Electric LLC Sitara Energy Inc Urban Energy Source LLC W Power And Light LP WCW International Inc Young Energy LLC
* Experience in other countries has proven the Terminology based on Hall of Fame / Wall of Shame to be effective.
9Texas Nodal Program UpdateAugust 2, 2007 9
Market Readiness Update – Wall of Shame*
The following QSEs Without Resources have not identified their NODAL Accountable Executive (AE):
Citadel Energy Products LLC Clearview Electric Inc DPI Energy LLC Duke Energy Ohio Inc Hwy 3 MHP LLC Kansas City Power and Light Company National Power Company Inc Northern States Power Company Texpo Power LP DBA Texpo Energy
These Market Participants have not been engaged in readiness to the degree QSEs With Resources and TSPs have been. ERCOT will increase contact with these Market Participants as the project approaches testing with QSEs Without Resources on MIS and/or API and other key activities.
* Experience in other countries has proven the Terminology based on Hall of Fame / Wall of Shame to be effective.
10Texas Nodal Program UpdateAugust 2, 2007 10
Testing - The approach to get there…
Start simple, incrementally add complexity, and repeat the process until it becomes second nature
Testing
11Texas Nodal Program UpdateAugust 2, 2007 11
The EDS Artifacts detailing the test effort…
EDS 1 Approach EDS 2
ApproachEDS 3
Approach EDS 4 Approach
SCED Handbook
LFC Handbook CRR
HandbookDAM
Handbook
ERCOT Nodal Transition Plan
_____________
Map to: ERCOT Nodal Transition Plan Sections Protocol Sections
Map to: Functional Requirements
Are based on the same inputs as internal testing artifacts, but the focus of the testing is different
12Texas Nodal Program UpdateAugust 2, 2007 12
Testing - Summary Release ScheduleE
DS
4
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
Alarms Processing
FAT
EMS 2A
ED
S 1
ED
S 2
ED
S 3
FAT – Rel 3
EMS 2B EDW 1
FAT – Release 4
NMMS 1 NMMS 2 EIP 1
FAT – Release 5
REG 1 MMS 1
EMS 2C
EIP 2 S&B 1MIS 1EIP 3
EDW 2
FAT – Release 6
EMS 3EDW 3
EIP 4
FAT – Release 7
EDW 4CRR 1CMM 1 EIP 5
FAT – Release 8
MMS 2S&B 2
EDW 5 EIP 6
FAT – Release 9
MMS 2S&B 2
OS
NMMS 3 EMS 4EDW 6
EIP 7EMS 5 DIS
P2P Checkout
SE Verification
ITEST
RTM Go-Live
DAM Go-Live
EDS 2 Release 3: SE VerEMS- State Estimator & Tel Perf Stds,NSA, SPS/RAP, SCADA and DynRatings for Single Model
EDW– SE Statistics
EDS 2 Release 4: NM VerNMMS- Network Model, NOMCR
EMS- EMS /NMMS Interface
EIP
EDS 3 Release 5: LMPsMMS– SCED
EMS- NSA, RLC
COMS- S&B (FIP, FOP,Ver Costs)- Registration
EIPMISEDW
EDS 3 Release 6: LFC TestingEMS- LFC
EIPEDW
EDS 3 Release 7: CRRCRRCOMS- CMM
EIPEDW
EDS 4 Release 8: RT SettlementsMMS- RT Settlements InterfaceS&BEIP, EDWEDS 4 Release 9: DAM, RUCMMS- All Markets- OSEMS – Load Forecast, Out EvalNMMSS&BEIP, EDW
ITEST
ITEST
LegendIntegration TestingProject FAT Activities
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
NOMCR Chk out Network Model Verification
Rel 1
Rel 2
EDS 1 Release 1:EMS COTS
EDS 1 Release 2:ICCP Upgrade
Rel 3
FAT
EDS
FAT
ITEST
EDS
FAT
ITEST
EDS
SCED TestingRegUpload Offers
Rel 4
Rel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC Comms Testing
ITEST
EDS
FAT
FAT
EDS
ITEST
ED
S 4 Go-Live
Activities
EDS 1 EDS 2 EDS 3 EDS 4
MP Interface Spec
Start of EDS activities
FAT milestones
EDS Preparatory Milestones
Rel 8
Rel 9
LFC Testing
ReadinessDeclaration
Readiness Declarations
13Texas Nodal Program UpdateAugust 2, 2007 13
EDS 1 – Testing Results
EDS 1 will verify each of the approximately 90,000 ICCP points, as the scheduled MP operator manually changes a point’s status or data value.
ERCOT operations observes the update within the specified timeframe and records a pass or failure and the type of failure.
Market Participants
ESD1 Test Progress to-date
Missing Equipment Missing Points Mis-Mapped Points
No Change in Quality Code Value Polarity Reversed Scan Rate failure
Suspect Point Value
Testing Failures by Type of Failure
Start Date: 6/1/2007 End Date: 9/30/2007
Testing Schedule is on track.
Testing results and failure rate are within expectations.
Test observations
Total ICCP Points Verified = 33,040 of 90,132 ~ 40% complete, Error Rate ~ 4%
14Texas Nodal Program UpdateAugust 2, 2007 14
Testing – EDS3 & EDS4 Test Plans
EDS4EDS3
Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec Jan Feb Mar Apr May Jun Jul Aug Sep Oct Nov Dec
ED
S 3
LMP Data ValidationRegUpload OffersRel 5
Rel 7
Rel 6
6 month LMP Posting
CRR Data Validation Trial Ops of CRR
LFC COMs TestingEDS LFC Testing
ED
S 4
RTM Go-Live
DAM Go-Live
Settlements Statements
Upload Bids
Test Settlements
Outages DAM, RUC, SASMFull Nodal Functionality
24*7 Operation 168 Hr Test
EDS
Go-LiveActivities
MP Interface Spec
Rel 8
Rel 9
EDSApproach
EDS 3 Approach
SCED Handbook
Phase 1 to 4
LFC Handbook
Phase1 & 2
EDS 4 Approach
CRR Handbook
S&B Handbook
DAM Handbook
168 Hour Test
Handbook
Nodal Cutover
Handbook
Zonal Wind Down
HandbookOutage
Handbook
RUCHandbook
SASMHandbookEDS 3
EDS 4
Major milestones
EDS Preparation Milestones
Approved
In progress
TPTF Submission (approximate)
Legend
http://nodal.ercot.com/docs/pd/eds/eds3/eds3dp/EDS_3_Approach_v1.0_061107.dochttp://nodal.ercot.com/docs/pd/eds/eds3/scedhdbk/EDS_SCED_MP_Handbook_V1.02.doc
Approved Documents
Summary Release Schedule
On track for milestoneDocument Status
Ahead
Document Status
15Texas Nodal Program UpdateAugust 2, 2007 15
We have made improvements from our “Early” EDS3 experience
We have proved the “Cloning” process for migrating applications Installation of MMS SCED in the EDS environment is already complete Migration experience of MMS applications has improved internally Additional practice migrations were conducted to further reduce future
migration durations Cycle time for migration defect resolution has now been reduced from days to a
few hours
The good news is, we are addressing these issues today before the key critical path milestones
16Texas Nodal Program UpdateAugust 2, 2007 16
The cost impact of Baseline 1 & 2 will be negated through cost savings across the Program
Nodal Program Budget 263.0$
Fund savings from various projects (6.4) All Projects - anticipated staffing reductions, being analyzed
Other reductions, being analyzed
Total 263.0$
Nodal ProgramPlan to achieve $263 Budget
($ Millions)
(3.7)
Increased costs associated with Baseline 1 & 2 10.1