attachment y study presque isle 5, 6, 7, 8, & 9: 344 mw ......aug 15, 2014 · presque isle...
TRANSCRIPT
Attachment Y Study Presque Isle 5, 6, 7, 8, & 9: 344 MW Coal Retirement, Effective 10/15/2014
ATTACHMENT Y STUDY REPORT August 15, 2014
PUBLIC VERSION
2
EXECUTIVE SUMMARY
Pursuant to the Tariff, an Attachment Y Notification submitted by We Energies was received by MISO on April 15, 2014. The request was for the Retirement of Presque Isle Units 5, 6, 7, 8, & 9 effective October 15, 2014.
Previously, We Energies had provided an Attachment Y Notice to Suspend Presque Isle Units 5, 6, 7, 8, & 9 from February 1, 2014 until June 1, 2015. The Suspension request was denied by MISO and the units were designated System Support Resources (SSRs) due to the identification of transmission reliability issues that could not be mitigated prior to the requested change of status date, February 1, 2014. The units have continued to operate under an SSR agreement filed by MISO January 31, 2014.
MISO performed a transmission system reliability assessment that was reviewed and discussed with stakeholders at five Technical Studies Task Force (TSTF) meetings consistent with MISO’s FERC Order 890 planning practices as provided for in Attachment FF to the Tariff, and with section 38.2.7 of the Tariff (System Support Resources). Through this analysis, and stakeholder discussions, MISO determined that all five Presque Isle units are required to be System Support Resources for the requested Retirement date. These results are consistent with current operating practices that require the availability of all of the Presque Isle units for reliability commitments.
Reliability analysis was performed for both summer peak and shoulder peak load conditions (representative of spring and fall period loading levels). NERC Transmission Planning (TPL) standards were applied to determine whether system performance was within equipment design voltage and thermal limitations, and whether the system remained stable for applicable contingencies within these standards.
The results of the reliability analysis show system instabilities (voltage instability) for the following contingencies resulting from the change in status of Presque Isle generation for both summer peak and shoulder peak load levels:
NERC Category B Contingencies 1. [CEII REDACTED] 2. [CEII REDACTED] 3. [CEII REDACTED] 4. [CEII REDACTED] 5. [CEII REDACTED]
NERC Category C Contingencies 1. [CEII REDACTED] 2. [CEII REDACTED]
Additionally, for summer peak load conditions voltage instability would occur due to the change in status of Presque Isle for:
NERC Category B Contingencies 1. [CEII REDACTED]
NERC Category C Contingencies 1. [CEII REDACTED]
There are additional contingencies and conditions that are less severe which are further detailed in this report.
PUBLIC VERSION
3
MISO reviewed the reliability analysis and potential alternatives to the operation of Presque Isle with stakeholders. The alternatives considered include known new generation interconnection requests, commitments for demand response, system operational steps including reconfigurations, special protection schemes, and transmission system additions. No feasible alternatives have been identified to alleviate the reliability issues that would result in substantial and sustained loss of load without the continued availability of the Presque Isle plant considering the requested Retirement date.
After being reviewed for power system reliability impacts and feasible alternatives as provided for under Section 38.2.7 of the MISO’s Open Access Transmission, Energy & Operating Reserve Markets Tariff (“Tariff”), MISO has determined that Presque Isle Units 5, 6, 7, 8, & 9 should enter into an SSR agreement until sufficient mitigation measures are completely developed and implemented. MISO continues to work with stakeholders in regularly scheduled Technical Study Task Force meetings to evaluate alternatives to the SSR designation.
PUBLIC VERSION
4
ContentsI. Introduction ............................................................................................................................ 5
II. Study objectives ..................................................................................................................... 6
III. Models and Assumptions ....................................................................................................... 7
a. Study Models ..................................................................................................................... 7
b. Study Assumptions ............................................................................................................ 7
IV. Study Criteria and Methodology ............................................................................................ 8
a. Powerflow Analysis Tools .................................................................................................. 8
b. Transmission Owner Planning Criteria ............................................................................... 9
c. MISO Transmission Planning BPM – SSR Impacted Facility Criteria .............................. 10
d. Monitored Areas ............................................................................................................... 11
e. Contingencies .................................................................................................................. 11
f. Number of Units Required ................................................................................................ 11
V. Reliability Study Results ...................................................................................................... 12
a. Contingency Analysis Results .......................................................................................... 12
b. Voltage Stability Results .................................................................................................. 12
c. Number of SSR Units Required ....................................................................................... 13
VI. SSR Agreement Cost Allocation .......................................................................................... 14
VII. Alternatives Analysis ............................................................................................................ 15
a. System Reconfiguration and Operation Guidelines ......................................................... 15
b. Generation Redispatch .................................................................................................... 15
c. New Generation ............................................................................................................... 15
d. Demand Response .......................................................................................................... 17
Generic Demand Response ................................................................................................ 17
Empire Mine Demand Response ........................................................................................ 17
e. New Generation + Demand Response ............................................................................ 18
f. Transmission Projects ...................................................................................................... 19
Transmission Projects to eliminate Presque Isle SSR need: .............................................. 19
VIII. Conclusion ........................................................................................................................... 20
IX. List of Tables and Figures ................................................................................................... 21
X. Appendices .......................................................................................................................... 22
PUBLIC VERSION
5
I. INTRODUCTION
We Energies submitted an Attachment Y Notice to MISO on August 1, 2013 to provide notification of the planned Retirement of Presque Isle Units 5, 6, 7, 8, & 9 per MISO’s Tariff. The generating units are connected to the 138 kV American Transmission Company (ATC) transmission system. The load shape for this area is much flatter than normal with a shoulder peak load that is approximately 85% of the summer peak. Area load is primarily served by 6 sources: the Generation at Presque Isle, the Mackinac VSC, a flow control device, and the Highway 22 – Morgan – Plains 345 kV, Pulliam – Stiles 138 kV, Pulliam – Little Suamico - Stiles 138 kV, and Cranberry – Lakota Road 115 kV transmission lines.
Table 1: Presque Isle Unit Capabilities
Unit Nameplate
(MW)
Module E Net Capacity
(MW)
5 90 556 90 557 90 788 90 789 90 78
Total 450 344
PUBLIC VERSION
6
Figure 1: ATC Transmission map including the Presque Isle Generators in Marquette, MI
II. STUDY OBJECTIVES
Under Section 38.2.7 of MISO’s Tariff, SSR procedures maintain system reliability by providing a mechanism for MISO to enter into agreements with Market Participants (MP) that own or operate Generation Resources or Synchronous Condenser Units (SCUs) that have requested to either Retire or Suspend, but are required to maintain system reliability.
The principal objective of an Attachment Y study is to determine if the unit(s) for which a change in status is requested is necessary for transmission system reliability based on the criteria set forth in the MISO Business Practices Manuals. The study work included monitoring and identifying the steady state branch/voltage violations on transmission facilities due to the unavailability of the Generation Resource or SCU. The relevant MISO Transmission Owner and/or regional reliability criteria are used for monitoring such violations.
If reliability issues are identified during the study MISO will also conduct an open stakeholder planning process to evaluate feasible alternatives to an SSR agreement. The evaluation of alternatives will also be included in this report, if conducted.
PUBLIC VERSION
7
III. MODELS AND ASSUMPTIONS
a. Study Models
Corresponding to the anticipated Retirement of Presque Isle Units 5, 6, 7, 8, & 9 the following power system analysis models were used for the study:
2015 Summer Peak 2015 Shoulder Peak 2015 Shoulder Peak with future Mackinac VSC (flow control device)
The Attachment Y study models were created from the MTEP13 SCED reliability analysis models. The “before” model was created by fully dispatching the Presque Isle units and incorporating the modelling assumptions below. There are no other dispatchable generating units in the area to replace Presque Isle generation, therefore the “after” model was manually dispatched with Presque Isle units 5-9 offline. Replacement generation was sourced from remote generators in the MISO footprint. A comparison of the generation dispatch between the models with Presque Isle generation online and offline is included in Appendix C of this report.
b. Study Assumptions
1. Load a. Upper Peninsula shoulder peak load is modelled at 85% of summer peak
i. ATC supplied load forecast b. Upper Peninsula Mine Load
i. Empire Substation: 116.3 MW, 21.2 Mvar ii. Tilden Substation: 164.3 MW, 5.7 Mvar iii. Total Load: 280.6 MW, 26.9 Mvar iv. From ATC supplied load forecast
c. City of Marquette, Michigan net load: 15 MW i. Was enforced by adjusting the City of Marquette generation (non-market)
2. Generation a. Approved Attachment Y Units were excluded from the model b. Escanaba Generation (SSR Agreement)
i. Summer Peak: 2 of 2 units fully dispatched (25 MW) ii. Shoulder Peak: 2 of 2 units fully dispatched (25 MW)
c. Escanaba CT i. Summer Peak: fully dispatched (13 MW) ii. Shoulder Peak: fully dispatched (13 MW)
d. White Pine Generation i. Summer Peak: 2 of 2 units fully dispatched (36 MW) ii. Shoulder Peak: 2 of 2 units fully dispatched (36 MW)
e. West Marinette Generation i. Summer Peak: 4 of 4 units fully dispatched (213 MW) ii. Shoulder Peak: 1* of 4 units fully dispatched (71 MW)
1. *Due to air permit limitations confirmed by WPS f. Adjacent Wind Units offline:
i. Garden g. The numerous and small run of river units in the local area are not capable of re-
dispatch and were not adjusted in the model 3. System Configuration
PUBLIC VERSION
8
a. In models without the Mackinac VSC project (P2846), the transmission system is normally split between the upper and lower peninsulas of Michigan. The system split is currently at [CEII REDACTED] which has the following lines out of service for construction:
i. [CEII REDACTED] ii. [CEII REDACTED] iii. [CEII REDACTED]
4. Transmission Projects a. Included based on expected In-Service Date (ISD):
i. Indian Lake – Hiawatha 138 kV line, P333, ISD 10/1/2013 ii. Mackinac Flow Control Project, P2846, ISD 7/19/2014
1. The Mackinac VSC project will be included in a variation of the 2014 shoulder model with a 40 MW N -> S flow
2. The UP will be closed-in for this case 3. The adjacent Straits – Pine River 69 kV line rebuild, P3108, ISD
6/1/2014 will be included in this variation b. Excluded based on expected In-Service Date (ISD):
i. Arnold 345/138 kV transformer # 1, P3125, ISD 5/1/2015 ii. Bay Lake Project, P3679, ISD 12/31/2016 iii. North Appleton – Morgan 138 kV line, P3952, ISD 12/31/2016 iv. Berryville T-D, P4358, ISD 6/1/2017 v. Pulliam – Glory Rd Conversion, P3841, ISD 12/1/2016
5. Operating Guides referenced: a. Presque Isle Generation Operating Guide R10 (2010-S-011-E) b. Flow South Standing Op Guide R08 (2010-S-012-E)
Table 2: Table of Models
System Topology
Dispatch Source Model Att Y Gen VSC U.P. Split
2014 SP MTEP13 2015SP
Off N/A Yes
2014 SP MTEP13 2015SP
On N/A Yes
2014 SH MTEP13 2018SH
Off N/A Yes
2014 SH MTEP13 2018SH
On N/A Yes
2014 SH MTEP13 2018SH
Off 40 MW N -> S
No
2014 SH MTEP13 2018SH
On 40 MW N -> S
No
IV. STUDY CRITERIA AND METHODOLOGY
a. Powerflow Analysis Tools
Siemens Power System Simulator (PSS/E) was used to perform AC contingency analysis. Models were solved with automatic control of LTCs, phase shifters, DC taps, and switched shunts enabled. Contingency analysis was performed on before and after models. The results were compared to find if there were any criteria violations due to the unit(s) change of status.
PUBLIC VERSION
9
Powertech’s Voltage Security Assessment Tool (VSAT) was used to perform voltage stability analysis. Models were solved with automatic control of LTCs, phase shifters, switched shunts enabled pre-contingency. Using the before model, a transfer was created by decreasing Presque Isle generation, one unit at a time, starting with the smaller units (5, 6, then 7…). Generation was replaced by increasing Concord and Paris generation. Using MISO-wide generation to replace Presque Isle generation yielded the same result. The maximum transfer step size was 10 MW and the minimum was 1 MW. Contingencies that produced criteria violations during the contingency analysis were selected for simulation in the voltage stability analysis. Thermal and voltage criteria limits were both respected and ignored to determine the steady state operating limits (the first and most limiting thermal or voltage criteria violation that causes system insecurity) as well as the voltage stability limit. The system security limits for this analysis included in this report indicate thermal loadings at 100% of the emergency rating or voltages at emergency limits (0.9 and 1.1 p.u.).
V&R Energy’s Physical and Operational Margins (POM) and Optimal Mitigation Measures (OPM) powerflow analysis software was used to calculate the optimal load shed. Optimal load shed was calculated using the “after” model and the contingencies that produced criteria violations during the contingency analysis.
b. Transmission Owner Planning Criteria
ATC Transmission Planning Criteria applied for thermal analysis: For System Intact (Category A), all thermal loadings exceeding 100% of the normal
rating For Category B and C contingencies, all thermal loadings exceeding 100% of the
emergency rating ATC Transmission Planning Criteria applied for voltage analysis:
For System Intact (Category A), all substation voltages less than 95% or above 105% For Category B and C contingencies, all substation voltages less than 90% or above
110% DPC Transmission Planning Criteria applied for thermal analysis:
For System Intact (Category A), all thermal loadings exceeding 100% of the normal rating
For Category B and C contingencies, all thermal loadings exceeding 100% of the emergency rating
DPC Transmission Planning Criteria applied for voltage analysis: For System Intact (Category A), >100 kV substation voltages less than 90% or above
105% For System Intact (Category A), <100 kV substation voltages less than 95% or above
105% For Category B and C contingencies, all substation voltages less than 90% or above
110% XEL Transmission Planning Criteria applied for thermal analysis:
For System Intact (Category A), all thermal loadings exceeding 100% of the normal rating
For Category B and C contingencies, all thermal loadings exceeding 100% of the emergency rating
PUBLIC VERSION
10
XEL Transmission Planning Criteria applied for voltage analysis:
For System Intact (Category A), all substation voltages less than 95% or above 105% For Category B and C contingencies, all non-generator substation voltages less than
92% or above 105% For Category B and C contingencies, all generator substation voltages less than 95% or
above 105% For Category C3 contingencies, all generation substation voltages less than 92% or
above 105%
ITC Transmission Planning Criteria applied for thermal analysis: For System Intact (Category A), all thermal loadings exceeding 100% of the normal
rating For Category B and C contingencies, all thermal loadings exceeding 100% of the
emergency rating
ITC Transmission Planning Criteria applied for voltage analysis: For System Intact (Category A), all substation voltages less than 97% or above 107% For Category B and C contingencies all substation voltages less than 92% or above
107% ITC Transmission Planning Criteria applied for Load Shed analysis:
C1 Contingencies: Facilities > 300 kV, 0 MW; Facilities < 300 kV, 100 MW C2 Contingencies: Facilities > 300 kV, 0 MW; Facilities < 300 kV, 300 MW C3 Contingencies: 500 MW, after the second contingency C5 Contingencies: 300 MW
WPSC Transmission Planning Criteria applied for thermal analysis:
For System Intact (Category A), all thermal loadings exceeding 100% of the normal rating
For Category B and C contingencies, all thermal loadings exceeding 100% of the emergency rating
No cascading outages WPSC Transmission Planning Criteria applied for voltage analysis:
For System Intact (Category A), all substation voltages less than 95% or above 105% For Category B contingencies, all substation voltages less than 92% or above 106% For Category C contingencies, all substation voltages less than 90% or above 106%
Under category C contingencies, for the valid thermal and voltage violations as specified above, generation re-dispatch, system reconfiguration, and/or load shedding was considered, if applicable.
c. MISO Transmission Planning BPM – SSR Impacted Facility Criteria
As specified in the MISO BPM-020-r6, the System Support Resource criteria for determining if an identified facility is impacted by the generator change of status will be:
Under system intact and category B contingencies, branch thermal violations are only valid if the flow increase on the element in the “after” retirement scenario is equal to or greater than:
PUBLIC VERSION
11
a) 5% of the “to-be-retired” unit(s) MW amount (i.e. 5% PTDF) for a “base” violation compared with the “before” retirement scenario, or b) 3% of the “to-be-retired” unit(s) amount (i.e. 3% OTDF) for a “contingency” violation compared with the “before” retirement scenario.
Under system intact and category B contingencies, high and low voltage violations are only valid if the change in voltage is greater than 1% as compared to the “before” retirement voltage calculation.
d. Monitored Areas
In the analysis, voltage and thermal loadings were monitored in the Wisconsin Electric (WEC), Alliant East (ALTE), Wisconsin Public Service (WPS), Dairyland Power Cooperative (DPC), and Michigan Electric Transmission Company* (METC) Control Areas from 69 – 345 kV. The Xcel Wisconsin Zone was also monitored from 69 – 345 kV.
*The METC Control area, including the Wolverine Zone, was only monitored in models where the VSC was in-service, due to the system configuration (split at Straits).
e. Contingencies
A subset of the MISO Transmission Expansion Plan (MTEP) contingencies in the ATC, DPC, and Xcel areas were used for AC contingency analysis.
The following NERC Categories of contingencies were evaluated for all models:
1. Category A when the system is under normal conditions. 2. Category B contingencies resulting in the loss of a single element. 3. Category C contingencies resulting in the loss of two or more (multiple) elements.
Maintenance outages with a forced outage were also evaluated in shoulder peak models.
f. Number of Units Required
Throughout this report there are references to both the number of units operating at Presque Isle and the number of units that would be needed in an SSR contract. Due to the system topology and the fact that Presque Isle is the largest plant in the region, there are no other generators that can be used to supplement power to support planned and/or forced outages of one of the Presque Isle units. The number of units operating at Presque Isle represent the number of units running pre-contingent, in order to meet post-contingent NERC reliability criteria. For shoulder load conditions, where unit maintenance is typically performed, it would be necessary to have one additional unit on an SSR contract, in order to meet NERC reliability criteria while one unit is out of service for planned maintenance (TPL-002-0b R1.3.12).
PUBLIC VERSION
12
V. RELIABILITY STUDY RESULTS
Significant voltage stability, thermal, and voltage criteria violations associated with the Retirement of Presque Isle 5, 6, 7, 8, and 9 were identified when compared to the continued availability of the units.
a. Contingency Analysis Results
Thermal Results
Table 13a in Appendix A shows numerous NERC Category B and C contingencies causing thermal criteria violations without Presque Isle 5, 6, 7, 8, and 9 operating and the improvements resulting from the operation of Presque Isle 5, 6, 7, 8, and 9. A majority of the constraints identified are along the high voltage transmission path that serves Eastern Wisconsin and the Upper Peninsula of Michigan.
Voltage Results
Table 13b in Appendix A shows a few NERC Category C contingencies causing voltage criteria violations without Presque Isle 5, 6, 7, 8, 9 and the improvements resulting from the operation of Presque isle 5, 6, 7, 8, and 9. There were several contingencies which did not solve and appeared to result in voltage instability that were further studied. The results of the voltage stability analysis are included below in Sections V.b and V.c.
b. Voltage Stability Results
Voltage stability analysis indicates that several NERC Category B and C contingencies would result in voltage instability for both Summer Peak and Shoulder Peak load conditions if Presque Isle generation is offline:
NERC Category B Contingencies 1. [CEII REDACTED] 2. [CEII REDACTED] 3. [CEII REDACTED] 4. [CEII REDACTED] 5. [CEII REDACTED]
NERC Category C Contingencies 1. [CEII REDACTED] 2. [CEII REDACTED]
Additionally, there are several contingencies that would result in voltage instability only for Summer Peak load conditions if Presque Isle generation is offline:
NERC Category B Contingencies 1. [CEII REDACTED]
NERC Category C Contingencies 1. [CEII REDACTED]
The voltage stability limits were determined using the methodology in Section IV.a. The minimum generation limits and the most severe contingencies are included below in Section V.c.
PUBLIC VERSION
13
c. Number of SSR Units Required
MISO performed voltage stability analysis to determine the most limiting constraints and the number of Presque Isle units required in order to meet transmission system reliability criteria. The detailed methodology of this analysis is included in Section IV.a. The voltage stability analysis indicates that all five Presque Isle units will be needed as System Support Resource (SSR) units. Four units operating are necessary due to both the steady state and voltage stability operating limits. One additional unit would be needed at Presque Isle to ensure unit maintenance and necessary environmental retrofits.
The highlighted row in the following tables indicates the number of Presque Isle units that would need to be operating to prevent the most limiting contingency – constraint pair. The minimum step size (Section IV.a) of 1 MW indicates that if Presque Isle Generation were decreased by 1 MW from what is shown in the table, the first security violation would occur due to the indicated contingency. The most limiting contingencies identified in this analysis were also shown to cause voltage instability if all generation at Presque Isle were offline. If the generation at Presque Isle continued to decrease from the value indicated in the table, additional thermal and voltage violations are expected occur until the voltage stability limit is reached.
Table 3: Most Limiting Contingency-Constraint Pairs - 2014 Shoulder Peak
Most Limiting Contingency
Con Type
Most Limiting Element Mead Loada
Min. PSQI Generation
PSQI Units Operating
[CEII REDACTED] C5 [CEII REDACTED] 40 MW 295 MW 5
[CEII REDACTED] C5 [CEII REDACTED] 0 MW 253 MW *4*
[CEII REDACTED] B [CEII REDACTED] 40 MW 181 MW 3
[CEII REDACTED] B [CEII REDACTED] 0 MW 128 MW 2
aMead Load is non-firm load that can be curtailed to reduce flows
PUBLIC VERSION
14
Table 4: Most Limiting Contingency-Constraint Pairs - 2014 Summer Peak
Most Limiting Contingency
Con Type
Most Limiting Element Mead Loada
Min. PSQI Generation
PSQI Units Operating
[CEII REDACTED] C5 [CEII REDACTED] 40 MW 343 MW 5
[CEII REDACTED] C5 [CEII REDACTED] 0 MW 277 MW *4*
[CEII REDACTED] B [CEII REDACTED] 40 MW 181 MW 3
[CEII REDACTED] B [CEII REDACTED] 0 MW 156 MW 3
aMead Load is non-firm load that can be curtailed to reduce flows
The voltage stability limits require 4 Presque Isle units to be operating in order to maintain system stability for the C5 loss of the [CEII REDACTED] and [CEII REDACTED] transmission lines. Load shed cannot be taken in advance of this event, so the load at Mead is not considered in this case.
Table 5: Voltage Stability Limits - 2014 Summer Peak
Most Limiting Contingency
Con Type
Min. PSQI Generation
PSQI Units Operating
[CEII REDACTED] C5 276 MW *4*
[CEII REDACTED] B 163 MW 3
VI. SSR AGREEMENT COST ALLOCATION
MISO utilizes a load shed methodology to determine the reliability benefits to each MISO Local Balancing Area (LBA) of operation, without the retired or suspended unit(s). The LBA shares that are calculated in this analysis are used for cost allocation if an SSR agreement is necessary. Although load shed is not permitted for NERC Category A or B events, this methodology determines the load shed amount needed to resolve the reliability issues identified due to the unit change of status, as a proxy for the reliability benefit of SSR unit operation. The load shed values for each contingency are organized by LBA and accumulated to determine the total load shed for each LBA along with the corresponding share ratio. The hypothetical SSR agreement shares that were calculated for this Attachment Y study are included below in Table 6.
PUBLIC VERSION
15
Table 6: SSR Agreement LBA Shares
LBA Load Shed (MW) Share WEC 6536.0 93.79%WPS 38.1 0.55% UPPC 394.6 5.66%
We Energies announced its intention to create a new MIUP LBA that will be comprised of a subset of loads presently contained within the existing WEC LBA. The effective date for this change is currently targeted for December 1, 2014. The load shed calculation itself is not changed due to the creation of or assignment of buses to the MIUP LBA. However, new share ratios would result from the creation of the new MIUP LBA.
VII. ALTERNATIVES ANALYSIS
MISO’s System Support Resource Tariff (Section 38.2.7.c) provides for an open stakeholder planning process to assess feasible alternatives to an SSR agreement. The reliability assessment of this Attachment Y request resulted in SSR eligibility. As provided for in the Tariff, MISO disclosed the Attachment Y Notice on the MISO OASIS and scheduled a stakeholder meeting to review the reliability issues identified in the Attachment Y reliability analysis. MISO solicited alternatives from stakeholders that were reviewed at subsequent meetings. The following is a summary of the alternatives that were reviewed for this study and the impact each may have towards reducing or eliminating the need for SSR status for the subject Attachment Y units.
a. System Reconfiguration and Operation Guidelines
No other tie-ins to the rest of the transmission system exist in this area for loss of critical elements. Any system switching would island or disconnect load.
b. Generation Redispatch
Available units at Escanaba, White Pine, and West Marinette were included in the models. The availability of West Marinette is limited, due to air permit restrictions. The other dispatchable units, Gladstone and Portage, are “Emergency Run Only” units due to air permit restrictions and require a Local Transmission Emergency declaration to run. They cannot be used to support planned maintenance or construction outages. Emergency cannot be called on pre-contingency to prevent voltage instability.
c. New Generation
Presently there are three generator interconnection requests in the MISO queue. At the time of this report, none of the generators have met their milestones to move forward to the Definitive Planning Phase (DPP), a required step prior to an Interconnection Agreement (IA) can be executed. Under the Attachment Y process, only future generators with signed interconnection agreements can be considered as alternatives to an SSR contract. Although it is not required, MISO may evaluate proposed generation in the queue that has not yet entered into an Interconnection Agreement to provide an indication of the potential benefits to the reliability issues caused by the unavailability of the units in an Attachment Y request.
PUBLIC VERSION
16
The following analysis indicates how the addition of proposed generators may reduce or eliminate the need for the Attachment Y units to remain designated SSR units. This analysis does not determine what new issues may arise from the interconnection of new generation or any network upgrades that would be needed to support such an interconnection. The issues caused by an interconnection and any needed upgrades would be determined within a generator interconnection study.
Generator interconnection request J317 is for 112 MW of proposed natural gas fueled generation interconnecting to the Empire 138 kV substation. The requested in service date is June 1, 2016. The developer of this project indicated that it may be possible to accelerate the unit in-service date of the proposed unit so that it would be in-service prior to the MATS compliance deadline faced by Presque Isle (April 16, 2016).
For the purposes of this study, this hypothetical unit was assumed to have a 118 MVA base, with a 0.95 power factor giving it 112.1 MW and ± 36.8 Mvar capabilities. Given the expected in-service date of the unit, both the Arnold 345/138 kV transformer and Holmes – Old Mead Road 138 kV transmission line projects were assumed to be in service.
The addition of this proposed generator at Empire did not affect the number of units required in order to meet system reliability criteria. The limits were determined through a voltage stability analysis, reducing the generation at Presque Isle until the first constraint was identified. The limits determining the number of units required are highlighted in the tables below.
Table 7: Most Limiting Contingency-Constraint Pairs with J317
Load Most Limiting Contingency
Con Type
Most Limiting Element
Min. PSQI Generation
PSQI Units Operating
SP [CEII REDACTED] C5 [CEII REDACTED] 246 MW *4*
SP [CEII REDACTED] B [CEII REDACTED] 153 MW 2
Table 8: Voltage Stability Analysis with J317
Load Most Limiting Contingency
Con Type
Min. PSQI Generation
PSQI Units Operating
SP [CEII REDACTED] C5 [CEII REDACTED]
*2*
SP [CEII REDACTED] B [CEII REDACTED]
2
MISO received two interconnection requests after the Attachment Y Notice for Retirement was submitted by WEC. These two projects are J352 and J353 for a 342 and 690 MW, respectively, generating facility connecting to the 345 kV substation at Arnold, the 345 kV substation at Plains, or the 138 kV substation at Plains. The requested in-service date of both of these
PUBLIC VERSION
17
generator proposals is August 1, 2017. MISO is still evaluating the effectiveness of these two proposed generator alternatives and will include the details of that analysis in future revisions of this report.
d. Demand Response
Generic Demand Response
Using optimal powerflow analysis software, MISO determined the optimal and minimum amount of load shed necessary to eliminate all voltage stability, thermal, and voltage criteria violations for 2014 summer peak and shoulder peak load conditions. This provides an indication of the minimum amount of demand response that would be necessary to alleviate all system constraints with all Presque Isle generating units offline. The amount of demand response indicated is for the most severe contingency for each NERC category.
Table 9: Generic Demand Response Values
NERC Category
2014SP Model
2014SH Model
B 237 MW 311 MW
C 287 MW 323 MW
Empire Mine Demand Response
In addition to the generic demand response, MISO also analyzed a theoretical load reduction at the Empire mine at the request of stakeholders. The Empire mine presently has firm transmission service. No demand side management options have been proposed by a Load Serving Entity (LSE) to date. For the purposes of this analysis, it was assumed that this load would be entirely offline or disconnected. If this load were to be disconnected, only 4 Presque Isle units may be needed for an SSR contract, to ensure that 3 may remain operating.
The steady state limits require only 2 Presque Isle units to be operating, as shown in the following table.
PUBLIC VERSION
18
Table 10: Empire Mine Demand Response - Most Limiting Contingency-Constraint Pairs
Load Most Limiting Contingency
Con Type
Most Limiting Element
Mead Loada
Min. PSQI Generation
PSQI Units Operating
SP [CEII REDACTED] C5 [CEII REDACTED]
39 MW
225 MW 3
SP [CEII REDACTED] C5 [CEII REDACTED]
0 MW 150 MW *2*
SH [CEII REDACTED] C5 [CEII REDACTED]
0 MW 136 MW 2
SP [CEII REDACTED] B [CEII REDACTED]
39 MW
79 MW 2
SP [CEII REDACTED] B [CEII REDACTED]
0 MW 61 MW 1
SH [CEII REDACTED] B [CEII REDACTED]
0 MW 12 MW 1
aMead Load is non-firm load that can be curtailed to reduce flows
The voltage stability limits require 3 Presque Isle units to be operating in order to maintain system stability for the C5 loss of the [CEII REDACTED] and [CEII REDACTED] transmission lines. Load shed cannot be taken in advance of this event, so the load at Mead is not considered in this case.
Table 11: Empire Mine Demand Response – Voltage Stability Limits
Load Most Limiting Contingency
Con Type
Most Limiting Element
Min. PSQI Generation
PSQI Units Operating
SP [CEII REDACTED]
C5 Voltage Stability
157 MW *3*
SP [CEII REDACTED]
B Voltage Stability
78 MW 2
e. New Generation + Demand Response
A combination of 116 MW of theoretical demand response at Empire (complete removal of load) was also studied in conjunction with the proposed generator J317. With both of these alternatives in place, only the 3 largest units at Presque Isle (7, 8, & 9) may be required for SSR status.
PUBLIC VERSION
19
Table 12: Most Limiting Contingency-Constraint Pairs with J317 and Empire Demand Response
Load Most Limiting Contingency
Con Type
Most Limiting Element
Min. PSQI Generation
PSQI Units Operating
SP [CEII REDACTED] C5 [CEII REDACTED]
129 MW 2
f. Transmission Projects
MISO asked ATC to identify a set of transmission projects that would eliminate the SSR need for any units at Presque Isle. ATC reviewed several transmission projects, including previously approved projects and proposed projects that support multiple system needs, in developing a high-level proposal. The projects considered are a stand-alone proposal that do not include other potential alternatives. ATC’s analysis indicates that the approved projects P3679 and P3952 may eliminate the need of 1 SSR unit (4 on SSR contract). The expected in-service dates for both of these approved projects are still several years away. The incremental set of transmission projects is expected to take 5-7 years to implement. ATC and MISO are continuing to evaluate and determine the transmission upgrades necessary to eliminate the SSR need of Presque Isle.
Transmission Projects to eliminate Presque Isle SSR need:
1. Previously Approved Projects a. P3679, estimated in-service date 12/31/2016
i. North Appleton – Morgan 345 kV line ii. North Appleton 345 kV substation iii. De-bifurcate Morgan – Stiles 138 kV lines iv. Benson Lake (near Amberg) 150 Mvar 138 kV SVC v. Holmes – Old Mead Road 138 kV line
b. P3952, estimated in-service date 12/31/2016 i. North Appleton – Morgan 138 kV line ii. North Appleton 345/138 kV transformer
2. Projects with multiple potential need drivers a. [PRIVILEGED REDACTED] b. [PRIVILEGED REDACTED]
3. Additional Projects to eliminate SSR a. [PRIVILEGED REDACTED] b. [PRIVILEGED REDACTED] c. [PRIVILEGED REDACTED] d. [PRIVILEGED REDACTED] e. [PRIVILEGED REDACTED] f. [PRIVILEGED REDACTED]
PUBLIC VERSION
20
VIII. CONCLUSION
The reliability study for the Retirement of all 5 units at Presque Isle identified reliability issues that cannot be mitigated prior to the unit change of status and thus qualifies Presque Isle for SSR designation. MISO has reviewed these reliability issues and potential alternatives with stakeholders at several Technical Study Task Force (TSTF) meetings from November 2013 until August 2014. The analysis of the proposed alternatives identified no near term solutions that would eliminate or reduce the number of units needed to address the reliability issues that are caused by the Retirement of Presque Isle 5, 6, 7, 8, and 9. Until such time any sufficient alternative can be contracted and implemented, all 5 units at Presque isle should be included in the SSR agreement to ensure that 4 units may be in operating condition at any time, with one unit able to be inoperable for maintenance, retrofit, or other planned outages.
PUBLIC VERSION
21
IX. LIST OF TABLES AND FIGURES
Tables
Table 1: Presque Isle Unit Capabilities ......................................................................................... 5 Table 2: Table of Models .............................................................................................................. 8 Table 3: Most Limiting Contingency-Constraint Pairs - 2014 Shoulder Peak ............................. 13 Table 4: Most Limiting Contingency-Constraint Pairs - 2014 Summer Peak .............................. 14 Table 5: Voltage Stability Limits - 2014 Summer Peak ............................................................... 14 Table 6: SSR Agreement LBA Shares ........................................................................................ 15 Table 7: Most Limiting Contingency-Constraint Pairs with J317 ................................................. 16 Table 8: Voltage Stability Analysis with J317 .............................................................................. 16 Table 9: Generic Demand Response Values .............................................................................. 17 Table 10: Empire Mine Demand Response - Most Limiting Contingency-Constraint Pairs ........ 18 Table 11: Empire Mine Demand Response – Voltage Stability Limits ........................................ 18 Table 12: Most Limiting Contingency-Constraint Pairs with J317 and Empire Demand Response .................................................................................................................................................... 19
Figures
Figure 1: ATC Transmission map including the Presque Isle Generators in Marquette, MI ......... 6
PUBLIC VERSION
22
X. APPENDICES
Appendix A: Steady State Contingency Analysis Results
Table 13a: Thermal Results
Table 13b: Voltage Results
Appendix B: Model Generation Dispatch Comparison
Appendix C: Area Transmission System Maps
PUBLIC VERSION
AppendixA: SteadyStateContingencyAnalysisResults
PUBLIC VERSION
MISO Attachment Y Study Results - Presque Isle 5,6,7,8,9 - CONFIDENTIALTable 13a: Compare Thermal ResultsModel VSC Contingency From Bus From Bus Name From kFrom ATo Bus To Bus Name To kV To AreCkt Rating Off MVA Off Pct. On MVA On Pct. OTDF MISO Comments2014SH N [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 846.6 102.37 728 88.03 34.48 Violation caused by suspension2014SH N [CEII REDACTED] 694000 ARPIN B1 345.00 345 694 699245 ARP 138 138.00 138 694 1 381 403.7 105.96 367.9 96.56 10.41 Violation caused by suspension2014SH N [CEII REDACTED] 694064 ROCKY RN B4 345.00 345 696 694065 ROCKY RN BV 345.00 345 696 Z 703 717.3 102.03 658.4 93.66 17.12 Violation caused by suspension2014SH N [CEII REDACTED] 694061 ROCKY RN B1 345.00 345 696 694068 ROCKY RN B8 345.00 345 696 Z 703 710.4 101.05 651.5 92.67 17.12 Violation caused by suspension2014SH N [CEII REDACTED] 694061 ROCKY RN B1 345.00 345 696 694068 ROCKY RN B8 345.00 345 696 Z 703 710.4 101.05 651.5 92.67 17.12 Violation caused by suspension2014SH N [CEII REDACTED] 603141 IRONRIV7 115.00 115 600 608632 DAHLBRG7 115.00 115 608 1 92.2 112.6 122.13 100.2 108.68 3.60 Violation made worse by suspension2014SH N [CEII REDACTED] 698800 MAINE115 115.00 115 696 699703 HILLTP 115.00 115 696 1 205 231.8 113.07 208.4 101.66 6.80 Violation made worse by suspension2014SH N [CEII REDACTED] 698800 MAINE115 115.00 115 696 699733 PINE 115.00 115 696 1 205 216.3 105.51 192.4 93.85 6.95 Violation caused by suspension2014SH N [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 872 105.44 750.9 90.80 35.20 Violation caused by suspension2014SH N [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 885.6 107.09 759.6 91.85 36.63 Violation caused by suspension2014SH N [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 848 102.54 729.4 88.20 34.48 Violation caused by suspension2014SH N [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 895.7 108.31 772 93.35 35.96 Violation caused by suspension2014SH N [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 878.1 106.18 754.6 91.25 35.90 Violation caused by suspension2014SH N [CEII REDACTED] 698561 SUMMITLK 115.00 115 696 699780 VENUS 115.00 115 696 1 150 159.3 106.20 133 88.67 7.65 Violation caused by suspension2014SH N [CEII REDACTED] 699667 ANTIGO 115.00 115 696 699784 BLACK BK 115.00 115 696 1 189 192.7 101.96 168.1 88.94 7.15 Violation caused by suspension2014SH N [CEII REDACTED] 699732 BUNKERHL 115.00 115 696 699784 BLACK BK 115.00 115 696 1 89 93.7 105.28 79.7 89.55 4.07 Violation caused by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 204.1 114.73 191 107.36 3.81 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 241.2 111.67 228.4 105.74 3.72 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 243.1 112.55 230.3 106.62 3.72 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 266.2 123.24 253.3 117.27 3.75 Violation made worse by suspension2014SH N [CEII REDACTED] 602023 LACROSS5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216.1 229.5 106.20 217.5 100.65 3.49 Violation made worse by suspension2014SH N [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 239.1 122.62 227.1 116.46 3.49 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 209.1 117.54 195.8 110.06 3.87 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 242.9 112.45 230.1 106.53 3.72 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 243.1 112.55 230.3 106.62 3.72 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 193.9 108.99 180.1 101.24 4.01 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 204.7 115.06 191.6 107.70 3.81 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 205.6 115.57 192.5 108.21 3.81 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 237.7 110.05 224.9 104.12 3.72 Violation made worse by suspension2014SH N [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 253.4 129.95 240.5 123.33 3.75 Violation made worse by suspension2014SH N [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 229.8 117.85 217.9 111.74 3.46 Violation made worse by suspension2014SH N [CEII REDACTED] 603141 IRONRIV7 115.00 115 600 608632 DAHLBRG7 115.00 115 608 1 92.2 112.3 121.80 100.2 108.68 3.52 Violation made worse by suspension2014SH N [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 253.4 129.95 240.5 123.33 3.75 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 195.1 109.67 182.1 102.36 3.78 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 192 107.93 174.6 98.15 5.06 Violation caused by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 204.1 114.73 191 107.36 3.81 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 224.6 126.25 211.6 118.94 3.78 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 234.6 131.87 220.8 124.11 4.01 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 217.6 122.32 204.5 114.95 3.81 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 230.8 106.85 217.9 100.88 3.75 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 194 109.05 178.2 100.17 4.59 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 229.1 106.06 218.4 101.11 3.11 Violation made worse by suspension2014SH N [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 234.4 120.21 222.4 114.05 3.49 Violation made worse by suspension2014SH N [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 203.6 104.41 192.9 98.92 3.11 Violation caused by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 230.8 106.85 217.9 100.88 3.75 Violation made worse by suspension2014SH N [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 229.1 106.06 218.4 101.11 3.11 Violation made worse by suspension2014SH Y [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 852.5 103.08 737.1 89.13 33.55 Violation caused by suspension2014SH Y [CEII REDACTED] 694000 ARPIN B1 345.00 345 694 699245 ARP 138 138.00 138 694 1 381 407.1 106.85 370.8 97.32 10.55 Violation caused by suspension2014SH Y [CEII REDACTED] 694064 ROCKY RN B4 345.00 345 696 694065 ROCKY RN BV 345.00 345 696 Z 703 718.9 102.26 660 93.88 17.12 Violation caused by suspension2014SH Y [CEII REDACTED] 694061 ROCKY RN B1 345.00 345 696 694068 ROCKY RN B8 345.00 345 696 Z 703 712 101.28 653.1 92.90 17.12 Violation caused by suspension2014SH Y [CEII REDACTED] 694061 ROCKY RN B1 345.00 345 696 694068 ROCKY RN B8 345.00 345 696 Z 703 712 101.28 653.1 92.90 17.12 Violation caused by suspension2014SH Y [CEII REDACTED] 603141 IRONRIV7 115.00 115 600 608632 DAHLBRG7 115.00 115 608 1 92.2 113.4 122.99 100.2 108.68 3.84 Violation made worse by suspension2014SH Y [CEII REDACTED] 698800 MAINE115 115.00 115 696 699733 PINE 115.00 115 696 1 205 221.5 108.05 196.3 95.76 7.33 Violation caused by suspension2014SH Y [CEII REDACTED] 698800 MAINE115 115.00 115 696 699703 HILLTP 115.00 115 696 1 205 236.7 115.46 212.2 103.51 7.12 Violation made worse by suspension
PUBLIC VERSION
MISO Attachment Y Study Results - Presque Isle 5,6,7,8,9 - CONFIDENTIALTable 13a: Compare Thermal ResultsModel VSC Contingency From Bus From Bus Name From kFrom ATo Bus To Bus Name To kV To AreCkt Rating Off MVA Off Pct. On MVA On Pct. OTDF MISO Comments2014SH Y [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 879.3 106.32 759.9 91.89 34.71 Violation caused by suspension2014SH Y [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 887.2 107.28 769.3 93.02 34.27 Violation caused by suspension2014SH Y [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 853.9 103.25 738.5 89.30 33.55 Violation caused by suspension2014SH Y [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 897.5 108.52 781.4 94.49 33.75 Violation caused by suspension2014SH Y [CEII REDACTED] 694082 WERNER W B4 345.00 345 295 694066 ROCKY RN B6 345.00 345 696 1 827 879.4 106.34 764.1 92.39 33.52 Violation caused by suspension2014SH Y [CEII REDACTED] 698561 SUMMITLK 115.00 115 696 699780 VENUS 115.00 115 696 1 150 163.4 108.93 139.3 92.87 7.01 Violation caused by suspension2014SH Y [CEII REDACTED] 699667 ANTIGO 115.00 115 696 699784 BLACK BK 115.00 115 696 1 189 197.1 104.29 173.3 91.69 6.92 Violation caused by suspension2014SH Y [CEII REDACTED] 699732 BUNKERHL 115.00 115 696 699784 BLACK BK 115.00 115 696 1 89 96.5 108.43 82.4 92.58 4.10 Violation caused by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 203.4 114.33 190.4 107.03 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 240.9 111.53 228.1 105.60 3.72 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 242.9 112.45 230 106.48 3.75 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 266.6 123.43 253.1 117.18 3.92 Violation made worse by suspension2014SH Y [CEII REDACTED] 602023 LACROSS5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216.1 230.3 106.57 217.2 100.51 3.81 Violation made worse by suspension2014SH Y [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 240.8 123.49 228.7 117.28 3.52 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 208.4 117.14 195.2 109.72 3.84 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 242.7 112.36 229.8 106.39 3.75 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 242.9 112.45 230 106.48 3.75 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 193.3 108.66 180.3 101.35 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 204.1 114.73 191.1 107.42 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 205 115.23 191.9 107.87 3.81 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 237.4 109.91 224.7 104.03 3.69 Violation made worse by suspension2014SH Y [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 254.7 130.62 242.5 124.36 3.55 Violation made worse by suspension2014SH Y [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 231.3 118.62 219.2 112.41 3.52 Violation made worse by suspension2014SH Y [CEII REDACTED] 603141 IRONRIV7 115.00 115 600 608632 DAHLBRG7 115.00 115 608 1 92.2 113.3 122.89 100.2 108.68 3.81 Violation made worse by suspension2014SH Y [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 254.7 130.62 242.5 124.36 3.55 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 194.6 109.39 181.6 102.08 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 191.3 107.53 178.2 100.17 3.81 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 203.4 114.33 190.4 107.03 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 224.1 125.97 211.1 118.66 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 234.3 131.70 220.5 123.95 4.01 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 216.9 121.92 203.9 114.61 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 230.2 106.57 217 100.46 3.84 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 681531 LAC TAP5 161.00 161 680 1 177.9 193.3 108.66 180.3 101.35 3.78 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 229.2 106.11 218.5 101.16 3.11 Violation made worse by suspension2014SH Y [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 236 121.03 223.9 114.82 3.52 Violation made worse by suspension2014SH Y [CEII REDACTED] 681519 STONEMAN 161.00 161 680 631060 TRK RIV5 161.00 161 627 1 195 205.3 105.28 194.5 99.74 3.14 Violation caused by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 230.2 106.57 217 100.46 3.84 Violation made worse by suspension2014SH Y [CEII REDACTED] 601043 BRIGGS RD 5 161.00 161 600 602026 MAYFAIR5 161.00 161 600 1 216 229.2 106.11 218.5 101.16 3.11 Violation made worse by suspension2014SP N [CEII REDACTED] 698606 LENA WPS 69.000 69 696 699199 PNR TAP 69.000 69 696 1 30 32.6 108.67 21.26 70.87 3.31 Violation caused by suspension2014SP N [CEII REDACTED] 698800 MAINE115 115.00 115 696 699703 HILLTP 115.00 115 696 1 205 254.7 124.24 232.3 113.32 6.51 Violation made worse by suspension2014SP N [CEII REDACTED] 698800 MAINE115 115.00 115 696 699733 PINE 115.00 115 696 1 205 235.5 114.88 212.6 103.71 6.66 Violation made worse by suspension2014SP N [CEII REDACTED] 698561 SUMMITLK 115.00 115 696 699780 VENUS 115.00 115 696 1 150 169.1 112.73 148.3 98.87 6.05 Violation caused by suspension2014SP N [CEII REDACTED] 699667 ANTIGO 115.00 115 696 699784 BLACK BK 115.00 115 696 1 189 210.4 111.32 188.9 99.95 6.25 Violation caused by suspension2014SP N [CEII REDACTED] 699732 BUNKERHL 115.00 115 696 699784 BLACK BK 115.00 115 696 1 89 101.7 114.27 88.6 99.55 3.81 Violation caused by suspension
PUBLIC VERSION
MISO Attachment Y Study Results - Presque Isle 5,6,7,8,9 - CONFIDENTIALTable 13b: Compare Voltage Results
Presque Isle Off Presque Isle OnModel VSC Contingency Bus Bus Name kV Area Vmin Vmax Contingent Voltage Contingent Voltage Voff-Von MISO Comments2014SH Y [CEII REDACTED] 698917 TILDEN2 138.00 138 295 0.9 1.1 0.8217 Violation caused by suspension2014SH Y [CEII REDACTED] 698918 TILDEN3 138.00 138 295 0.9 1.1 0.8219 Violation caused by suspension2014SH Y [CEII REDACTED] 698919 TILDEN4 138.00 138 295 0.9 1.1 0.8221 Violation caused by suspension2014SH Y [CEII REDACTED] 699915 TILDEN1 138.00 138 295 0.9 1.1 0.8217 Violation caused by suspension2014SP N [CEII REDACTED] 698917 TILDEN2 138.00 138 295 0.9 1.1 0.8041 Violation caused by suspension2014SP N [CEII REDACTED] 698918 TILDEN3 138.00 138 295 0.9 1.1 0.8042 Violation caused by suspension2014SP N [CEII REDACTED] 698919 TILDEN4 138.00 138 295 0.9 1.1 0.8044 Violation caused by suspension2014SP N [CEII REDACTED] 699915 TILDEN1 138.00 138 295 0.9 1.1 0.8040 Violation caused by suspension2014SP N [CEII REDACTED] 605537 GRT LKS8 88.000 88 600 0.92 1.05 0.8806 0.8908 -0.0102 Violation made worse by suspension2014SP N [CEII REDACTED] 605538 MINE RD8 88.000 88 600 0.92 1.05 0.8743 0.8845 -0.0102 Violation made worse by suspension2014SP N [CEII REDACTED] 605539 GOGEBIC8 88.000 88 600 0.92 1.05 0.8698 0.8800 -0.0102 Violation made worse by suspension
PUBLIC VERSION
AppendixB: ModelGenerationDispatchComparison
PUBLIC VERSION
Presque Isle Attachment Y Study
Model Dispatch Comparison
2014 SP Unit Dispatch Comparison
Bus Name MW On MW Off Delta MW %
6033 G531 57 75 18 31.6
256348 18ZELND3 0 80 80 999.9
345756 1SIOUX 1 484 519 35 7.2
345998 1GOSCK 1 18.2 72.2 54 295.9
346002 1GOSCK 5 51.5 71.5 20 38.8
364003 1BR FERRY N3 1179.1 1185.1 6 0.5
608763 SBAYP 1G 16.4 46.4 30 182.5
608775 BOSWE44G 500 620 120 24
608902 TAC HBRG3 37.3 85.3 48 128.8
638091 GENESEO8 8.1 26.1 18 222.2
698770 PSQI G5 56 0 ‐56 100
698771 PSQI G6 56 0 ‐56 100
698772 PSQI G7 77 0 ‐77 100
698773 PSQI G8 77 0 ‐77 100
698774 PSQI G9 77 0 ‐77 100
2014SH Unit Dispatch Comparison
Bus Name MW On MW Off Delta MW %
364003 1BR FERRY N3 1219.2 1267.4 48.2 4
608774 BOSWE43G 290.7 385.7 95 32.7
620315 BIGSTN1G 304.1 414.5 110.4 36.3
635213 NEAL 3G 530.3 535.3 5 0.9
661015 COYOTE1G 201 444 243 120.9
698770 PSQI G5 56 0 ‐56 100
698771 PSQI G6 56 0 ‐56 100
698772 PSQI G7 77 0 ‐77 100
698773 PSQI G8 77 0 ‐77 100
698774 PSQI G9 77 0 ‐77 100
2014SH_VSC Unit Dispatch Comparison
Bus Name MW On MW Off Delta MW %
364003 1BR FERRY N3 1227.2 1281.4 54.2 4.4
599956 PNM‐DC7 451.2 451.3 0.1 0
608774 BOSWE43G 290.7 385.7 95 32.7
620315 BIGSTN1G 304.1 414.5 110.4 36.3
635213 NEAL 3G 530.3 535.3 5 0.9
661015 COYOTE1G 201 444 243 120.9
698770 PSQI G5 56 0 ‐56 100
698771 PSQI G6 56 0 ‐56 100
698772 PSQI G7 77 0 ‐77 100
698773 PSQI G8 77 0 ‐77 100
698774 PSQI G9 77 0 ‐77 100
PUBLIC VERSION
AppendixC: AreaTransmissionSystemMaps
PUBLIC VERSION
L a k e S u p e r i o r
L a k e H u r o n
L a k e M i c h i g a n
C A N A D A
M I C H I G A N
KINGSFORD
O c o n t oO c o n t o
D o o rD o o r
O n e i d aO n e i d a
L a n g l a d eL a n g l a d e
F l o r e n c eF l o r e n c e
M a r i n e t t eM a r i n e t t e
L i n c o l nL i n c o l n
V i l a sV i l a s
F o r e s tF o r e s t
G o g e b i cG o g e b i c
S c h o o l c r a f tS c h o o l c r a f t
O n t o n a g o nO n t o n a g o n
H o u g h t o nH o u g h t o n
M a r q u e t t eM a r q u e t t e
C h i p p e w aC h i p p e w a
M e n o m i n e eM e n o m i n e e
D e l t aD e l t a
M a c k i n a cM a c k i n a c
L u c eL u c e
C h i p p e w aC h i p p e w a
K e w e e n a wK e w e e n a w
A l g e rA l g e r
B a r a g aB a r a g a
I r o nI r o n
Eagle River
Crandon
Tomahawk
Wausaukee
Merrill
Rhinelander
Crivitz
Hubbell
Negaunee
EscanabaGarden
Ontonagon
Baraga
Munising
Stambaugh
Powers
Stephenson
Marquette
Iron River
LakeLinden
Gwinn
Gaastra
Laurium
Daggett
IshpemingHarvey
De TourVillage
MackinacIsland
Kingsford
CrystalFalls
Alpha
Hancock
SouthRange
Carney
CopperCity
Sault Ste.Marie
BlaneyPark SW
STA
Detour
ForestLake
Sawyer Lumber
Brimley
MTU
Watson
DavesFalls
Hiawatha (ESE)
Nathan
Tilden
Eastom
Us Hydro9 & 10
PerchLake
Presque Isle SW YD
M-38
LakeheadRapidRiver
Delta(UPPCO)
NorthBluff
Seney(AD-REA)
Shingleton
Cranberry
BaragaVlg
Hiawatha(AD-REA)
Gladstone
Pines(UPPCO)
Manistique
Dafter
St Germain
AlgerTimberProducts
Conover
Talentino SW STA
GrandRapids Hy
Lincoln Ave (UPPCO)
Henry St.(UPPCO)
Chandler
Valley(ESE)
MichigammeFalls Hy
CrystalFalls
Perkins
Straits
Hulbert
Lakehead Naubinway
Bass Lake
Land OLakes
TwinLakes(UPP)
Newberry
Kincheloe Housing
Cornell-UP
RobertsSW STA
Osceola
St Ignace
McGulpin
Watersmeet
L'anse
FelchMountain
Metonga
Atlantic
Mead Paper
Barnum 3 Mile
Engadine
Goetzville
GouldCitySW STA
KincheloeMain
Tone
Seney(UPPCO)
Greenstone
CaldronFalls Hy
WhitePineMine
TroutLake
(CEC)
LoadingDock Sub
NiagraPaper Of
Wisconsin
ClearLake(WPS)
Elevation St
BruleSW STA
EscanabaSteamPlant
JH Warden
National
Big Bay
Rudyard
Winona
Harris
TwinLake
Curtis
Gwinn
Victoria Hy
Forsyth
Randville
LakeMine
FoxHills
SW STA
SaultEmpireMine
EagleRiver Mackinac
Holmes
Eckerman
Ingalls
MichTransmitterFacility
BruceCrossing
Pickford
StarSiding
ChalkHills Hy
Rexton
NewberryVlg
Stone Container
Humboldt Mine
Mead Pump
Raco
Thunder
Munising
Aspen
Venus
LakeheadIron River
Hodag
Pine Hy
Nordic
Mansfield
Norway
Arnold
Amberg
WhitePine Vlg
SummitLake(WPS)
MichWestern
Limestone
SilverCliff
Rockview
Brevort
Tomahawk -ATC 115kV
PineRiver
Sagola
IndianLake
Rockland(UPP)
SandstoneRapids Hy
TroutLake(ESE)
9 Mile SW STA
GredeFoundries
Mansfield
Plains
Keweenaw
UPSCO
Garden Corners
NorthLake
Lou Pac
Portage (UPPCO)
Toivola
Old Winona
Freeman
Aragon
PortageSt Hy
Goodman
RhinelanderPaper
Ontonagon
PeavyFalls Hy
Lakota RdIron Grove
Three Lakes
Marquette Diesel
Florence
Mass
Limeston
Powers
Woodmin
Pine Grove
K ISawyer
Masonville (UPPCO)
Chatham
M I C H I G A N
W I S C O N S I N
ZONE2
ZONE1
ZONE3
ZONE4
ZONE5
G:\GISDATA\WORKSPACE\ArcMap Templates\Zone Maps\Zone2 11x17.mxd Modified: March 7, 2012
Transmission Related FacilitiesP L A N N I N G Z O N E 2
E l e c t r i c T r a n s m i s s i o n N e t w o r k & S u b s t a t i o n s
Tap or Switching Structure
Substation or Switchyard
Generation
ATC Office Location
Transmission Line Voltage
0 20 4010Miles
Currently, ATC owns or operates transmission facilities in Wisconsin, Illinois, Minnesota, and the Upper Peninsula of Michigan. Facilities include: * Approximately 9440 miles of transmission lines * 109 wholly owned substations * 410 jointly owned substations * ATC offices in Madison, Cottage Grove, Pewaukee, De Pere, and Kingsford, MI
The information presented in this map document represent the most current and accurategeoreferenced compilation of ATC owned and operated transmission facilities available - some facility locations may be approximate. This map is advisory and intended for reference purposes only. Please direct any revisions or corrections to ATC Asset Applications and GIS Group. Base Map Information: ATC, PSCW, MiDNR, WDNR
69 kV Double Circuit
345 kV
115 kV Double Circuit138 kV Double Circuit230 kV Double Circuit345 kV Double Circuit
69 kV115 kV138 kV230 kV
138 kV Underground
69 kV Underground
Non-ATC Line
115 kV Underground
Last Revision: January 2014
L ak e
Mi c
h ig a
n
G r ee n
B a y
Stephenson
Menominee
M e n o m i n e eM e n o m i n e e
W i n n e b a g oW i n n e b a g o
O c o n t oO c o n t o
D o o rD o o r
W a u s h a r aW a u s h a r a
S h e b o y g a nS h e b o y g a n
C o l u m b i aC o l u m b i a
D o d g eD o d g e
G r e e nG r e e nL a k eL a k e
O u t a g a m i eO u t a g a m i e
C a l u m e tC a l u m e t
L a n g l a d eL a n g l a d e
F o n d d uF o n d d uL a cL a c
W a s h i n g t o nW a s h i n g t o n
S h a w a n oS h a w a n o
B r o w nB r o w n
M a r i n e t t eM a r i n e t t e
K e w a u n e eK e w a u n e e
W a u p a c aW a u p a c a
F o r e s tF o r e s t
O z a u k e eO z a u k e e
M a n i t o w o cM a n i t o w o c
Tigerton
GreenLake
Clintonville
WhiteLake
Rosendale
Winneconne
Mayville
Kekoskee
Oshkosh
Cecil
Howard
Fredonia
RandomLake
St.Nazianz
Maribel
SturgeonBay
Marion
Neenah
Stockbridge
Sherwood
Pulaski
PortWashington
CedarGrove
Oconto
Sheboygan
Casco
Forestville
EggHarbor
Berlin
BigFalls
Weyauwega
Appleton
Nichols
Kiel
Wausaukee
Adell
Valders
Whitelaw
FrancisCreek
Fairwater
Fremont
Gresham
Menasha
BlackCreek
Seymour
Gillett
De Pere
Cascade
Oostburg
Mishicot
Luxemburg
Kewaunee
Ephraim
Bowler
Fox Lake
NewLondon
Manawa
Horicon
Bonduel
Eden
Newburg
Kellnersville
Omro
Hortonville
MountCalvary
Wrightstown
WestBend
Glenbeulah
Brillion
OcontoFalls
Crivitz
Waldo
HowardsGrove
Denmark
Manitowoc
Two Rivers
Waupaca
Ogdensburg
Embarrass
Theresa
Lomira
Oakfield
Campbellsport
St.Cloud
ElkhartLake
Chilton
Belgium
Plymouth
Cleveland
Peshtigo
Algoma
SisterBay
MarkesanBrandon
BearCreek
Shiocton
Suring
Kewaskum
Kaukauna
HilbertPotter
Pound
Coleman
Reedsville
Y-95
U-99
T-98
CRIY621
P-68
Y-59
Y-27
R-44
Y-92
Y-80
H-60
Y-68
D-30
Y-50
Y-77
Y-103
B-2
Y-25
J-140
Y-12
3
R-18
K-89
E-5
Y-26
I-87
C-55
Y-157
F-6
Z-130
FIRY11
B-28
WPS_X24
Z-26
Y-24
E-83
A-101
Y-13
3
J-10
Y-56
Y-93
J-88
Y-44
O-15
DYKY21
151
WERW
L61
L-CYP31
NAPL71
W-1
971L51
WERWL41
Y-311
HW22L31
W-5
F-31
8
R-304
971L71
121
111
L-SE
C31
Q-30
3
6832
796L41
HW22L21
111
796L41
L-CY
P31
121
HW22L21
3532
1
U-13J-36
X-1X-57
G-WEM23
MENG21
8222
971K
21
33542
6444
1
X-77X-4
64442
8650
2
X-97
W-75
75541
X-5
35351
X-96
6843
6851
971K11
N-118
X-47
80331
L-142
26523
6853
X-76
H-112
971K31
26522
W-101
WERW
G51
F-58
M-117
G-111
64451
M-39
80332
728K21
6862 6842
LSOG
21
G-85
X-3
WERWG3
1
E-57
X-64
G-INS11
H-86
M-143
I-113F-84
L-90
Y-51
8231
X-48
K-37
MCRG21
3815
1
HOLG
21
8032
971K
51
8232
40561
9752
82414035
G-BTB52
X-30
6084
1
971K
91
6445
264443
Ripon
CypressSW YD
ElkhartLake
Kellnersville
Fredonia
Tecumseh Rd
Lyndon
Canal
Brandon
Beardsley St
HighFalls Hy
Highway 22
Ellington
Neevin
Danz Ave SWSTA
Woodenshoe
Fairwater
Dartford
WestMarinette
SW YD
Auburn
New Holstein SW STA
Bay De NocPolar
Markesan
KettleMorraine(ALTE)
Mayville
Clintonville
Badger
Randolph
Barnett
EastScott St
Beaver Dam3rd St
Lost Dauphin
Willow Lawn
Glory Rd
Maes
Forest
Howard
LakePark
University(WPS)
Caroline
Revere Dr
Ohmstead
Booster
Butte DesMorts
Meyer Rd
OmroIndustrialPark
Ingalls
Shoto
Fitzgerald
BeaverDam East
Rockland (WPS)
Suamico
Casaloma
SouthSheboyganFalls
Butternut
Lawn Rd
Mountain
Bemis
ForwardEnergyCenter
Metomen
Lena
VelpAve
MearsCorners
Barton
PlymouthSub 4
Ashland Ave
SilverCliff
Ryan St
WhiteLake(WE)
SandstoneRapids Hy
Cloverleaf
Peshtigo
St Nazianz
EggHarbor
WernerWest
BayshorePound
Riverside(ALTE)
Mirro
EdgewaterSW YD
Hintz
StilesSW STA
Rosiere
NorthBeaverDam
Manawa
AppleHills
AlgomaCity
Luxemburg24.9
Random Lake
Northeast
Ellinwood
Melissa
Manrap
Menominee
MackfordPrairie
Dyckesville
Holland
PearlAve
Falls
Huebner
Oconto
Mystery Hills
Winneconne
Alto
Bayport SW STA
RiponInd Park
Center St
North Fond Du Lac
Berlin
Oshkosh
GrandRapids Hy
Koch Oil
Greenleaf
KewauneeSW YD
Waupun
Maplewood
ScottPaper Co
LittleSuamico
Michigan St
Red Maple
RiverRun
Dunn Rd
WhiteClay
Ogden St
Columbus St
North Gate
Industrial
Marion
SisterBay
PointBeachSW YD
Erdman
GravesvilleOmro
HowardsGrove
Progress
Rosendale
Sherwood
CaldronFalls Hy
Ontario
Aviation
Northside(sfm)
(ALTE)
EastShawano
Preble
NorthRandolph
Fox Lake(ALTE)
Mason St
FoxRiver
FordDrive
Glenview
Martin Rd
GreenLakeSW STA
Fox HillsSW STA
South Fond Du LacSW YD
Dewey
BrillionIron Works
Hickory St
WaupunMain
Plymouth Sub 3
Glacier
Thunder
Combined Locks
Brusbay
MulletRiver
Bluestone
BellePlaine
Custer
Kaukauna Central
Plymouth Muncipal
ForestJunction
Nicolet Paper Co
Algoma
NorthwestRipon
DeerTrail
Tayco
Horicon
KaukaunaNorth
Ledgeview
FountainValley
Morgan
2nd St (WPS)
Mishicot
NorthAppleton
Fox RiverSW YRD
30th Ave
Sobieski
HoriconInd Park
West Shawano
Mpu Plant
Hubbard
CedarRidge WindGeneration
Crivitz
EastKrok
Bowen St
Spring Brook
Wesmark
Oakfield
Pioneer(WPS)
Potts Avenue
G:\GISDATA\WORKSPACE\ArcMap Templates\Zone Maps\Zone4 11x17.mxd Modified: March 7, 2012
M I C H I G A N
W I S C O N S I N
ZONE2
ZONE1
ZONE3
ZONE4
ZONE5
P L A N N I N G Z O N E 4E l e c t r i c T r a n s m i s s i o n N e t w o r k & S u b s t a t i o n s
Currently, ATC owns or operates transmission facilities in Wisconsin, Illinois, Minnesota,and the Upper Peninsula of Michigan. Facilities include: * Approximately 9440 miles of transmission lines * 109 wholly owned substations * 410 jointly owned substations * ATC offices in Madison, Cottage Grove, Pewaukee, De Pere, and Kingsford, MI
The information presented in this map document represent the most current and accurategeoreferenced compilation of ATC owned and operated transmission facilities available - some facility locations may be approximate. This map is advisory and intended for reference purposes only. Please direct any revisions or corrections to ATC Asset Applications and GIS Group. Base Map Information: ATC, PSCW, MiDNR, WDNR
Transmission Related FacilitiesTransmission Line Voltage
Tap or Switching Structure
Substation or Switchyard
Generation
ATC Office Location
0 10 205Miles
69 kV Double Circuit
345 kV
115 kV Double Circuit
138 kV Double Circuit
230 kV Double Circuit
345 kV Double Circuit
69 kV115 kV138 kV
230 kV
138 kV Underground69 kV Underground
Non-ATC Line
Revised: January 2014