CONCEPTUAL PLAN Modification and Expansion of Group Housing Project “Atharva” At Sector-109, Village Pawala Khusrupur, Gurugram, Haryana Project Proponent: M/s Raheja Developers Ltd. Environmental Consultant EQMS India Pvt. Ltd. 304-305, III rd Floor, Rishabh Tower, Plot No. 16, Karkardooma Community Centre, Karkardooma, Delhi-92 May, 2017

Upload: others

Post on 08-Oct-2020

3 views

Category:

Documents


0 download

TRANSCRIPT

Page 1: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

CONCEPTUAL PLAN

Modification and Expansion of Group

Housing Project “Atharva”

At

Sector-109, Village Pawala

Khusrupur, Gurugram, Haryana

Project Proponent: M/s Raheja Developers Ltd.

Environmental Consultant

EQMS India Pvt. Ltd.

304-305, IIIrd Floor, Rishabh Tower,

Plot No. 16, Karkardooma Community Centre,

Karkardooma, Delhi-92

May,

2017

Page 2: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Content-l

M/s Raheja Developers Ltd.

CONTENTS

SI. NO. DESCRIPTION PAGE NO.

1.0 Introduction 1

1.1 Applicable Environment Legislation 5

1.2 Location and Land Use of project Site 7

1.3 Surroundings and Connectivity of project Site 11

1.4 Land Requirement and Area Summary 13

1.5 Dwelling Units 13

1.6 Estimated Population 13

1.7 Water Requirement 14

1.8 Sewage Generation 14

1.9 Sewage Treatment Process (SAF) 18

1.10 Storm Water Management 21

1.11 Vehicle Parking Facilities 22

1.12 Power Requirement 23

1.13 Solid Waste Generation and Management 23

1.14 Green Area 25

1.15 Construction Material 28

Page 3: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

1

M/s Raheja Developers Ltd.

CONCEPTUAL PLAN

1.0 Introduction

M/s Raheja Developers Ltd. is a established company in the Indian Realty Sector since 1990 and

is maintaining highest standards of professionals of business with a good customer satisfaction

index and the best standards for the welfare of its staff, society as well as for the environment

and provides the cost effective and holistic solutions which are specific to contemporary

standards for Residential, Commercial, SEZ and Business Centers in the Delhi and NCR. They

have been successful in providing specifically designed housing solutions to the elite

professional keeping in mind their daily needs and their exquisite taste in lifestyle. Mr. Navin

Raheja Founder CMD of the company had been member of steering committee project Tiger

under MoEF &CC has made and released over 122 real wildlife films and had received “Green

Man of India Award”

The Company has traversed a path of steady growth & expansion. The systems have been

strengthened and new processes have been added. Company has well established sustainable

environmental parameters policy which mandates company to follow and adopt all the measures

to make projects sustainable and energy efficient. Company has strong CSR policy under which

Raheja group contributes in welfare of unprivileged sector and runs KMGS as NGO which is

providing education to hundreds of weaker section and underprivileged children’s and is

registered with national open school.

M/s Raheja Developers Ltd. had planned a Group Housing Project located at Village Pawala

Khushrupur Sector 109, Gurugram, Haryana for which environment clearance had been obtained

from SEIAA, Haryana vide Letter no. DEH/09/SEIAA/66 dated 01.04.2009 for an area

measuring 59,132.5722 m2

(14.812 acres) and Built-up area of 1, 57,917.34 m2

attached as

(Annexure I) for the proposed Development as listed below. The application was made under 8

(b).

After obtaining the environment clearance, there were amendment in Haryana Building Bye

Laws and allowable density of people/ha was increased than existing. To avail the allowable

benefit, planning for the project was modified. Modification proposed includes,

Reducing size/modification of unsold units to be constructed consequent increasing nos. of

DUs to 593. Construction of 72 nos. of servant units as required by Bye Laws.

Instead of developing 18 villas it was proposed to develop residential blocks of Independent

floors (G+3/G+5) leading to addition of 94 DUs.

Construction of additional tower “Tower IV” within the existing land as per available density

norms.

Construction of addition nursery school as per requirement of HUDA Bye Laws

Page 4: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

2

M/s Raheja Developers Ltd.

Increasing nos. of EWS units from 116 to 125 numbers as per statutory requirement.

Increasing area of basement by 2201 m2 (to be constructed)

Addition of 0.8 acres of licensed land (adjacent to existing site in East direction) increasing

area to 15.612 acres from 14.812 acres due to revised plan from DGTCP. On the additional

licensed land additional construction will be done after statutory approvals.

Due to increase in density as per Haryana Building Bylaws leading to modification of planning

and increase in nos. of DUs (703) from 528, EWS units from 116 to 125, plot area, basement

area, total built-up area, expected population, water demand and waste generation of the project.

Details of modification along with the details as approved in EC are given in Table 1 & 2.

Modified site plan as approved by Department of Town and Country Planning is attached as

Annexure II

Table 1: Area Summary of Group Housing as per Awarded EC

S. No Description Areas As

Approved in

EC Letter

(2009)

Areas as Per

Modified Planning

(Existing +

Modification)

1. Total Plot Area 59,941.9 63,179.4

2. Area under 24 m wide road surrendered to HUDA 5,913.3 5,913.3

3. Net Plot Area 54,028.6 57,266.1

4. Permissible Ground Coverage 20,979.7

(35 %)

22,112.8

(35%)

5. Achieved/Proposed Ground Coverage (%@ plot

area)

19.48 % 20.54%

6. Achieved/Proposed Ground Coverage

Residential Towers

Convenient Shopping

Community Building

EWS

Villas/Small Towers (IFs)

Tower IV

Villas in additional land patch

School-1

School-2

11,679.8

6,988.7

0

202.6

734.6

3,514.7

0

0

239.2

0

12,981.5

6,988.7

262.8

202.6

734.6

3,514.7

399.2

412.6

239.2

227.2

7. Permissible FAR (@1.75 of plot area) 1,04,898.4 11,0564.0

8. Proposed FAR

Residential Towers

Convenient Shopping

Community Building

EWS

Villas/Small Towers (IFs)

1,04,898

89,588.3

262.7

295.6

3020.7

11,730.7

11,0559.1

89,588.3

262.7

295.6

3020.7

14,844.5

Page 5: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

3

M/s Raheja Developers Ltd.

Tower IV

Villas in additional land patch

(villas)

0

0

820.9

1,726.4

9. Basements

Lower basement

Upper basement

Basement under Community Building

Basement under Convenient Shopping

53,019.3

0

0

0

0

55,686.4

26,330

28,891

202.7

262.7

10. Built-up/Covered Area as calculated in 2009* 1,57,917.3 1,66,245.5

11. Area of School*

School 1

School 2

804.7

804.7

0

1515.8

804.7

711.1

12. Non FAR (Service area, Balcony area ,stilt,

Mumty, Machine Room, Guard

Room /modification as per notification 2011 due

to change in definition)

23,707.0 30,302.5

13. Built-up Area (As defined in EIA Notification

amendment dated 2011)

1,82,429.1 1,99,616.3

14. No. of Dwelling Units 528 703

(593+94+16)

15. No. of Basements 2 2

16. No. of Floors G+16 G+13/G+3/G+5

17. After full completion Green Area (@% of Net

Plot Area

32.2 35.7

18. After full completion Green Area 17,385.1 20,447.0

* Built-up area of school, Non-FAR area at floors and area under services was not added in built-up

area. As these were School is free from FAR and other Non FAR area at floors and services not

considered as covered area by architect. In 2009 built-up area used to be assumed as covered area as

defined in plans. However clarity on definition of built-up area came with amendment, 2011 to EIA

Notification. Thus now we have calculated built-up in accordance to EIA Notification, 2011 (as per

revised definition)

Table 2: Summary of Built-up Area

S. No. Particulars Area (m2)

1. Proposed FAR (a+b+c+d) 1,10,559.1

a Residential FAR (Villa +Towers) 1,06,980.1

b EWS 3,020.7

c Convenient Shopping 262.7

d Community Building 295.6

2. Non FAR (Service area, Balcony area ,stilt, Mumty,

Machine Room, Guard Room /modification as per

notification 2011 due to change in definition)

30,302.5

3. Area of Schools 1,515.8

Page 6: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

4

M/s Raheja Developers Ltd.

4. Stilt 1,552.5

5. Basement Area 55,686.4

6. Total proposed Built-up Area 1,99,616.3

On assumption that since project is granted environment clearance under 8(b) activity which

covers the project having built-up area more than 1,50,000 sq m (no closing limit), they

considered that some extra construction will automatically be covered in this clearance M/s

Raheja Developers Ltd. has not applied for revised environment clearance to SEIAA, Haryana

initially for some increase in built-up area and modifications in the plan while they have made

provisions of all environmental requirements for increased levels as per the EC. Later M/s

Raheja Developers Ltd on realizing requirement of obtaining re-environment clearance, have

applied for revised environment clearance for expansion of the project to SEIAA, Haryana vide

letter dated 26.10.2015 as per modified planning without undertaking the increased construction.

Due to long with period of grant of clearance for increased built-up M/s Raheja Developers Ltd

has continued the construction at the site as per modified planning in anticipation that the work

can be conducted on the basis of EC granted for project in 2009 and application for re-

environment clearance for expansion is already in process. The intent was to expedite the

construction and optimize the time and money. Though above construction falls under violation

category, M/s Raheja Developers Ltd has not completely constructed the project as per modified

planning and status of the construction carried out till date as per modified planning is given in

Table 3 below.

Table 3s: Status of Construction at Site as Per Modified Planning

S.

No.

Development Covered

Area (m2)

No. of DU Status of Violation Remarks

1. Residential

Towers

89,588.3 593 general

& 72

servant units

FAR is same but nos. of

units to increase due to

increase in density norms.

Occupied-

OC Obtained

2. EWS 3,020.7 125 FAR is same but nos. of

units increased to 125 as

per requirement.

Occupied-

OC Obtained

3. Villas/Small

Towers (IFs)

14,844.5 94 FAR increased, 11730.7 sq

m approved for 18 villas

Under

Construction.

4. Basements 55,221.0 2 Area increased, 53019.34

sq m approved

Being used-

OC Obtained

5. Community

Building

295.6 -- No change. Constructed OC Obtained

Total 1,62,970 -- -- --

M/s Raheja Developers Ltd have complied with all the environmental regulations applicable to

the project apart from the above mentioned violation. M/s Raheja Developers Ltd has obtained

consent to establish from HSPCB and get it renewed as well (Annexure III a & b) for

construction as applicable under Air & Water Act. M/s Raheja Developers Ltd has also obtained

Page 7: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

5

M/s Raheja Developers Ltd.

consent to operate under Air & water Act (1981 & 1974) and Authorization under Hazardous

Waste Rules, 2008 (Annexure IV a, b & c) as applicable for the project from HSPCB.

Occupancy certificate was also obtained for the project from the DTCP, Haryana (Annexure V).

All the provision of parking, water requirement, green space, sewage management, structure

stability are made at site as per the modified planning so as to minimize the impact on the

environment and the society. Environmental Management Measures present at the site are listed

below:

1. Proper sewerage collection and treatment in STP of 550 KLD

2. Re-usage of STP treated water for landscaping and flushing purpose through dual plumbing

system

3. Installation of water conservation taps and fixtures to minimize water requirement

4. Provision of energy saving lighting at the site for internal and external lighting

5. Installation of grid connected SPV power plant of 40.3 KWp as per BIS/HAREDA/MNRE

specifications (NOC from HAREDA and satisfactory report are attached Annexure VI a &

b). Also solar street lights are provided in common areas

6. Proper collection and management of storm water and recharge of run-off to ground

through 6 nos. of filter packed RWH pits

7. Daily collection and disposal of municipal waste through local authorized vendor in the

area

8. Green area of 17,385.1 m2 already developed at the site which is 32.17 % of net plot area.

Green area includes peripheral green belt, avenue plantation, private lawns for each tower

and organized greens.

9. All the surface parking areas are provided with the grass pavers

10. DG sets are provided with acoustic enclosures

11. Provision of adequate parking and roads of adequate width

12. Provision of adequate fire-fighting equipment at the site

1.1 Applicable Environmental Legislation

Project involves expansion and modification of the project “Atharva Group Housing” located at

Sec-109, Gurugram, Haryana. Built-up area of the project after expansion and modification will

be 1,99,616.3 m2 thus the project will fall under activity 8 (b) of schedule 1 and is classified as

Category B. However as the project involves violation of EIA Notification, 2006 thus as per the

latest notification of MoEF&CC, i.e. “SO 804” dated 14.03.2017 all the cases of violation of EIA

Notification, 2006 will be treated as Category A and will be appraised by EAC at central level

irrespective of the development/built-up area, MoEF&CC vide its above mentioned notification

has given a chance to proponent to accept the violation, admit it and apply for environment

clearance within 6 month time from the day of issue of the notification. Other acts & rules

applicable to the project includes following

Page 8: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

6

M/s Raheja Developers Ltd.

Environment protection Act, 1986

EIA Notification, 2006 as amended

MSW Rules, 2016

Construction & Demolition Waste Management Rules, 2016

Plastic waste Management Rules, 2016

Hazardous & Other waste Management Rules, 2016

E-Waste Rules, 2011 as amended in 2016

Air Act, 1981

Water Act, 1974

Noise Rules, 2000

Water Cess Act, 1977

Building Bye Laws of HUDA

Forest Act 1927 & 1980

M/s Raheja Developers Ltd has attempted to comply with the environmental legislations

applicable to the project and details of the permits obtained by Raheja group for the project are

listed in Table 3.

Table 3: Status of Compliance to Other Environmental Legislations:

Permit/NOC Legislation Remarks

Environment Clearance in

2009

EIA Notification, 2006 Letter No. DEH/09/SEIAA/66 dated

1/04/2009-Annexure I

Consent to Establish Water Act, 1974 & Air Act

1981

Letter No. HSPCB/TAC/2011/355 dated

09.02.2011-Annexure III a

Consent to Establish

Renewal

Water Act, 1974 & Air Act

1981

Letter No. HSPCB/ Consent/ :

2821215GUNOCTE1801186 dated

18.03.2015-Annexure III b

Consent to Operate Under

Water Act, 1974

Water Act, 1974 Letter No. HSPCB/Consent/ :

2821216GUNOCTO2521460

dated:18/03/2016- Annexure IV a

Consent to Operate Under

Air Act, 1981

Air Act, 1981 Letter No. HSPCB/Consent/ :

2821216GUNOCTOHWM2521460

dated:18/03/2016- Annexure IV b

Authorization for Hazardous

Waste Storage and Disposal

Hazardous Waste

(Management, handling and

Trans-boundary Movement)

Rules, 2008 (Now Hazardous

and Other Rules, 2016)

Letter No. HSPCB/Consent/ :

2821216GUNOCTOHWM2521460

dated:18/03/2016- Annexure IV c

Occupancy Certificates Under HUDA Bye Laws Annexure V

Page 9: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

7

M/s Raheja Developers Ltd.

Compliance to Conditions of

EC Letter

EIA Notification, 2006 Annexure VII

NOC from Dy. Conservator

of Forest

Under Forest Act, 1928 &

1980, PLPA, 1900 Annexure VIII

NOC from Tehsildar Under Arravali Notification,

1992 Annexure IX

NOC from AAI Order No. GSR751 (E) dated

30.09.2016 Annexure X

NOC from Fire Department Letter No.

MCG/FS/SFSO/2016/2424

dated 23.07.2016

Annexure XI

License for carrying out the

planned development

Under HUDA Bye Laws Annexure XII a & b

1.2 Location and Land Use of Project Site

Project site is located at Sector 109, Village Pawala Khusrupur, Gurugram, Haryana. Location

map of the project site is given in Figure 1 below. Site is spread over the area of 15.612 acres

(63,179.4 m2). Entire land is in possession of the Raheja group. Details of the Killa Nos. and

areas is given in Table 4 below. Land use of the project site is residential as per the Master Plan

of Gurgaon, 2031. Master plan with the location of the project site is given in Figure 2. The

project had received license from Directorate of Town and Country Planning Chandigarh vide

memo of 257 dated 07.11.2007 and license no. 14 dated 13.02.2011 and copy of license are

attached as Annexure XII a & b. A 24 m wide road (as per Master Plan, 2031 of Gurgaon)

traverses through the plot. This road will be developed as per Master plan and handed over to

HUDA. Geographical coordinates of the centre of project site are 28°30'30.94"N &

77° 0'24.76"E. Geographical coordinates of all the corners of the project site are given in Table 5

& Figure 3. Photographs of the site are attached as Annexure XIII.

Page 10: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

8

M/s Raheja Developers Ltd.

Figure 1: Location Map of the Project Site

Page 11: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

9

M/s Raheja Developers Ltd.

Figure 2: Gurgaon Manesar Urban Complex Master Plan, 2031 and Project Site Location

Table 4: Details of Killa Nos. and Areas

S. No. Rect No. Killa No. Area (K-M) Area (Acres)

1. 5 8 8-0 --

9 8-0 --

12 8-0 --

13 7-3 --

18 8-0 --

19 8-0 --

22 8-0 --

26 0-17 --

S. Total 56-0 7

2 5 7 8-0

S. Total 8-0 1

3 5 11/2 3-13

20 8-0

21/1 1-7

6 14 7-14

Page 12: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

10

M/s Raheja Developers Ltd.

15 6-15

16 7-12

26 1-5

S. Total 36-6 4.537

4 5 10 7-11

5 11/1 4-7

6 6/2 6-6

S. Total 18-4 2.275

5 5 14/1 6-8

S. Total 6-8 0.8

Total 124-18 15.612

Table 5: Geographical Coordinates of the Project Site

Point as in Map (Figure 3) Latitude Longitude

A 28°30'31.86"N 77° 0'16.68"E

B 28°30'34.66"N 77° 0'21.04"E

C 28°30'34.63"N 77° 0'31.57"E

D 28°30'32.79"N 77° 0'31.56"E

E 28°30'32.77"N 77° 0'31.03"E

F 28°30'30.97"N 77° 0'30.94"E

G 28°30'31.03"N 77° 0'29.10"E

H 28°30'28.99"N 77° 0'28.97"E

I 28°30'28.87"N 77° 0'26.60"E

J 28°30'26.96"N 77° 0'26.60"E

K 28°30'26.99"N 77° 0'24.19"E

L 28°30'28.64"N 77° 0'24.15"E

M 28°30'28.72"N 77° 0'20.92"E

N 28°30'29.07"N 77° 0'20.84"E

O 28°30'29.11"N 77° 0'19.30"E

P 28°30'30.97"N 77° 0'19.34"E

Q 28°30'30.90"N 77° 0'16.80"E

Page 13: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

11

M/s Raheja Developers Ltd.

Figure 3: Geographical Coordinates of the Project Site

1.3 Surroundings and Connectivity of Project Site

Project site is located in Gurgaon city. Gurgaon city is headquarters of Gurgaon district. Gurgaon

has experienced immense and rapid development in past 2 decade. Project site is surrounded by

residential colonies and villages majorly. Google map depicting the site and its surroundings

within 500 m, 2 km and 10 km is attached as Annexure XIII a, b & c. There are no drains,

forest area or environmentally sensitive area within 2 km of the project site. Nazafgarh drain is at

app. 2.3 km from the site in North direction. Details of the surroundings of the project site are

given in Table 6.

Site is well connected with the roads. A 24 m wide road as per the master plan, 2031 of Gurgaon

traverses through the site. This road will be developed and will be handed over to HUDA. This

road connects the site to other sector roads and ultimately connects to the Dwarka Expressway

which is app. 640 m from the site in South direction. Dwarka expressway connects the site to the

IGI airport and then to Delhi. A sector road abuts the site in North direction. Bajghera road is at

app. 1.7 km from site in East direction which connects the site to rest of the Gurgaon. Gurgaon

Railway station is at app. 2 km from the site in South direction and Delhi Cantt. Railway station

is at app. 16 km from site in East direction. Dwarka sec-21 metro station is at 7 km from site in

East direction and IFFCO Chowk metro station is at app. 8 km from site in South direction. IGI

airport is at app. 7 km from site in East direction. Connectivity map of the project site is given in

Figure 4. Details of the connectivity of the project site are given in Table 6.

Page 14: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

12

M/s Raheja Developers Ltd.

Table 6: Surroundings and Connectivity of the Project Site

S. No. Feature Distance and Direction

1. Residential

International City

Vill. Panwala Khusropur

Sector 110

Sector 105

Vill. Babupur

New Palam Vihar

Abuts site, NE

450 m, W

500 SE

1.1 km, S

600 m, NW

300 m, E

2. Commercial

Sector Markets

space by India Bulls, Neo Developers

and Conscient One

within sectors

200-250 m, S

3. Industrial

Sec 18, 19 & 20

Sec-37, 36, 24, 33 & 35

5-6 km, SE

6-7 km, SW

4. Nearest City

Gurgaon

Delhi

Site is located within Gurgaon City.

Delhi is app. 8 km from site in East direction

5. Nearest Highway

Dwarka Expressway

640 m, S

6. Nearest Railway Station

Gurgaon railway Station

Delhi Cantt Railway Station

2 km, S

16 km, E

7. Nearest Airport

Indira Gandhi international Airport

7 km, E

8. Near-by Water body

Nazafgarh Drain

2.3 km, N

9. Near-by Eco-Sensitive Zone

Sultanpur Bird Sanctuary

11.5 km, W

10. Near-by School

Planned schools (2 nos) within site

Eureka Pre-school

MMI

Chiranjivi Bharti School

Blue bells model school, Jiwan Jyoti

school & CCA school

Skylark school of business &

technology

Amity

Dronacharya Govt. college

Within site

1.7 km, SSE

2 km, E

3 km, E

3.5-4 km, S

2.3 km, S

6 km, E

5.0 km, S

11. Near-by Hospitals

Manipal Hospital

11.4 km, NW

Page 15: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

13

M/s Raheja Developers Ltd.

Max Vision Super Speciality Hospital 15 km, NW

Figure 4: Connectivity Map of the Project Site

1.4 Land Requirement and Area Summary

As discussed in section 1.1 as per modification, total area of the project site is 15.612 acres

(63,179.4 m2). Built-up area of the project after the modification and expansion will be

1,99,616.3 m2 Area detail and summary is given in Table 1 & 2 above.

1.5 Dwelling Units

As per the modified planning of the project, total nos. of dwelling units planned are 703 apart

from this there are 2 nos. of villas, 72 nos. servant units and 125 nos. of EWS units. Details of

dwelling units are given in Table 6.

Table 6: Details of Dwelling Unit

S. No. Block/Tower Units Servant Units

1. A 51 44

2. B 51 0

3. C 51 0

4. D 51 0

5. E 118 0

6. F 118 0

7. Block-I 51 0

Page 16: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

14

M/s Raheja Developers Ltd.

8. Block-II 51 0

9. Block-III 51 0

10. IF-I** 6 2

11. IF-II** 8 2

12. IF-III to VI** 40 16

13. IF-VII to X** 40 8

14. Tower IV* 16 0

Total 703 72

15. EWS 125 0

16. Villas* 2 0

*Not constructed yet

** Under construction

1.6 Estimated Population

Population at the site comprise of residents, staff & visitors. Details of existing (constructed

units) as well as estimated population at the site are given in Table 7.

Table 7: Existing (Constructed) & Estimated Population at Site

S.

NO Category Standard

Nos. of

Units-

Occupied/Co

nstructed

Populati

on

(Nos.)-

Existing

Nos. of

Units

Propos

ed

Populatio

n-

Proposed

Total

Population

A Residents

1

Residents-

Towers &

IFs

5 person per

unit 687 3435 16 80 3515

2

Residents-

Villas

5 person per

unit 0 0 2 10 10

3

Residents-

EWS

5 person per

unit 125 625 0 0 625

4 Staff

10% of total

population -- 406 -- 9 415

5 Visitors

10% of total

population -- 406 -- 9 415

Total Residential Population 4872 -- 108 4980

B

Communit

y Hall

1.5 sq

m/person 295.6 sq m 198 0 0 198

1 Staff 10% -- 20 0 0 20

2 Visitors 90% -- 178 0 0 178

C

Convenien

t

3 m2/

person 0 0

262.7

m2 88 88

Page 17: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

15

M/s Raheja Developers Ltd.

Shopping

1 Staff 10% 0 0 -- 9 9

2 Visitors 90% 0 0 -- 79 79

D

School 1

& 2

4 m2/

person 0 0

1515.8

sq m 379 379

1 Staff 15% 0 0 -- 57 57

2 Students 85% 0 0 -- 322 322

1.7 Water Requirement

Water requirement during construction phase is app. 50-60 KLD. Source of water during

construction is treated water from nearby CSTP of HUDA (at Manesar). Source of water during

operation phase is HUDA supply supplemented by private water tankers. Total water

requirement for the project is 732.68 KLD out of which 610 KLD is domestic water requirement,

122.68 KLD is horticulture water requirement and 44 KLD is used for road and car washing

during non rainy season. Fresh water requirement is 427 KLD and recycled water requirement is

349.68 KLD. Detailed water calculations are given in Table 8. Water balance diagram are given

in Figure 5 & 6.

1.8 Sewage Generation

Sewage generation from the project site is expected to be 525 KLD which should be treated in

STP of capacity 630 KLD. STP of 550 KLD is already constructed at the site and is operational.

Remaining 80 KLD of STP will be constructed as second module. Treated water from the STP is

being used for flushing, horticulture and road &car washing. Remaining treated water is used for

construction at the site or can be given to nearby construction sites or can be disposed off in

sewer. STP with the SAF (Submerged Aerated filter) technology is constructed at the site and

same technology will be adopted for expansion. STP is open to air. Water is treated upto tertiary

level in the STP. Details of sewage treatment methodology and process are given in section 1.9.

Detail of sewage generation and STP capacity is mentioned in Table 8. Characteristics of the

sewage are given in Table 9.

Page 18: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

16

M/s Raheja Developers Ltd.

Table 8: Detail of Water Requirement

Category

Standar

ds

(LPCD)

Existing (Constructed) Expansion (Non-Constructed) Total

Populatio

n/Area

(sq m)-

Construc

ted Units

Water

Require

ment

(KLD)

Fresh

Water

-KLD

Recycl

ed

Water-

KLD

Populatio

n/Area

(sq m)

Water

Requir

ement

(sq m)

Fresh

Water

-KLD

Recycl

ed

Water-

KLD

Total

Water

Require

ment

(KLD)

Total

Fresh

Wate

r-

KLD

Total

Recycled

Water-

KLD

Residents 135 4060 548 384 164 90 13 9 4 561 393 168

Staff/Students 45 426 20 14 6 397 18 13 5 38 27 11

Visitors 15 584 9 6 3 88 2 1 1 11 7 4

Total

Domestic

Population

-- -- 577 404 173 -- 33 23 10 610 427 183

Green Area

(m2)

6 liters/sq

m

17385.1 104.31 0 104.31 3061.9 18.37 0 18.37 122.68 0 122.68

Road and Car

Washing

44

Total Water

Requirement

-- -- 681.31 404 277.31 -- 51.37 23 28.37 732.68 427 349.68

Sewage Generation 496 29 525

STP Capacity 550 80 630

Treated Water 397 23 420

Re-usage of Treated

Water

Flushing

Horticulture

Road and Car washing

349.68

183

122.68

44

Usage for construction at

site/Disposal in Sewer

only after treatment

70.32

Page 19: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

17

M/s Raheja Developers Ltd.

Figure 5: Water Balance Diagram-Dry Season

Total Water Requirement

732.68 KLD

Fresh Water Requirement

427 KLD

Recycled Water

Requirement

349.68 KLD

Flushing

183 KLD

Consumption

427 KLD

Horticulture

122.68 KLD

Road and Car

washing 44 KLD

Sewage

525 KLD

80%

100%

STP

630 KLD

80%

420 KLD

Sewer

70.32 KLD

349.6 KLD

Page 20: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

18

M/s Raheja Developers Ltd.

Figure 6: Water Balance Diagram-Monsoon Season

Total Water Requirement

732.68 KLD

Fresh Water Requirement

427 KLD

Recycled Water

Requirement

183 KLD

Flushing

183 KLD

Consumption

427 KLD

Horticulture

0 KLD

Road & Car

Washing 0KLD

Sewage

525 KLD

80%

100%

STP

630 KLD

80%

420 KLD

Sewer

237 KLD

183 KLD

Page 21: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

19

M/s Raheja Developers Ltd.

Table 9: Characteristics of Sewage

Parameters Characteristics

Temperature Maximum 32oC

pH 6-9.5

Colour Black

TSS (mg/l) 100-400 mg/l

BOD (mg/l) 200-300 mg/l

COD (mg/l) 500-700 mg/l

1.9 Sewage Treatment Process (SAF)

SAF is an extremely efficient and well-proven biological treatment process which is used

to biodegrade organic matter. It can also reduce nitrogen in the wastewater to deliver a treated

wastewater that exhibits a very high level of BOD, COD and Nitrogen reduction along with high

levels of reduction in suspended solids. The SAF could be described as a “box of media”. It

utilizes a rigid, corrugated, structured polypropylene media to give a high surface area for

biomass attachment. The media is arranged into cells-in-series where effluent is contacted with

the fully submerged media in the presence of co-current aeration. Air is supplied by two low-

maintenance regenerative blowers. Air enters the process below the media via fine bubble

membrane diffusers. A secondary clarifier tank follows the SAF for removal of any biomass that

sloughs off the media during operation. Biological phosphorus and nitrogen removal can be

achieved with the SAF since the design incorporates sequential staged operations as required for

BNR flow schemes. Phosphorus removal utilizes the anaerobic, balance tank (septic tank) used

prior to the SAF. Recycled sludge from the final clarifier is mixed with the influent in this stage.

Nitrogen removal is then achieved via denitrification in the first cell of the SAF where, with no

air injected, and the introduction of recycled nitrified effluent from the end of the process, the

process becomes anoxic. The latter SAF cells are fully aerated and BOD removal and

nitrification are achieved in these. Full BNR requires a fourcell SAF, minimum. Typically

effluent from a full BNR scheme will be:

BOD less than 10 mg/l

Total nitrogen less than 5 mg/l

Ammonia nitrogen less than 1 mg/l

Total phosphorus less than 0.5 mg/l

Process:

Raw sewage from the sewage pump station is pumped through the inlet works of the WWTP

where it undergoes screening for removal of inorganics prior to entering the balance tank. The

balance tank provides a buffer against peak inflows and provides a steady inflow to the

downstream process. Prior to entering the treated effluent storage tank the effluent may be

filtered (to achieve Class A quality). The treated effluent is stored in the irrigation tank prior to

discharge to the irrigation field or re-use, whichever is applicable.

Page 22: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

20

M/s Raheja Developers Ltd.

Inlet Works

All raw sewage is pumped to the inlet works of the waste water treatment plant. A mechanical

screen is installed to remove all the inorganic material from the sewage and dispose it to the

waste bin below.

Balance Tank

The Balance Tank is designed to handle peak flows and allow a pre-determined and controlled

flow for subsequent treatment. The waste water is temporarily stored in the Balance Tank before

being pumped by a submersible Balance Pump to Primary Tank 1. The flow rate is set using the

flow control valves located in the Balance Tank. Excess flow is returned to the same tank.

The Balance Tank level is regulated by 3 float-type level switches. A coagulant is dosed into the

discharge of the Balance Pump by the Coagulant Dosing Pump whenever the Balance Pump

runs. The coagulant assists both in aiding the settlement of settleable solids in the plant and in

reducing the phosphorous level in the treated effluent. The Coagulant Dosing pump draws from a

bunded carboy of coagulant.]

Primary Tanks

Primary Tank 1 provides additional buffer capacity of inlet flow whilst Primary Tank 2 creates a

steady inflow for the Anoxic and the Aerobic Tanks. After the waste water is delivered to

Primary Tank 1, the top water level of the influent waste water is allowed to overflow into

Primary Tank 2. Both tanks encourage sedimentation of between 30 and 50% of the influent

suspended solids and allow anaerobic digestion to take place.

In anaerobic waste water treatment, bacteria digest organic material in the absence of oxygen and

transform part of the sludge to gases such as methane and carbon dioxide. In this design, the

anaerobic treatment occurs in Primary Tank 1 and Primary Tank 2.

Anoxic Tank

The top water level of the influent waste water is allowed to overflow from Primary Tank 2 to

the Anoxic Tank. The Anoxic Tank allows nitrate-specific bacteria to use nitrate (NO3) as an

oxygen source and a nutrient in a process called denitrification. This activity helps to remove

nitrogen based pollutants such as urea and ammonia by converting them into nitrate and nitrite

before releasing them as nitrogen gas into the atmosphere. The tank is enriched with returned

activated sludge (RAS) from the Clarifier to provide a plentiful supply of food for the bacteria.

The partially treated effluent from the Anoxic Tank contains approximately 65% of the pollution

load of the original sewage influent entering the waste water plant.

Aerobic Tank

The top water level of the influent waste water is allowed to overflow from the Anoxic Tank to

the Aerobic Tank where it is aerated. Air is introduced into the Aerobic Tank by the Biological

Air Blower through air diffusers located beneath a submerged media. Coarse air bubbles provide

favourable conditions for the growth of aerobic bacteria.

The Aerobic Tank which contains the submerged media has a large surface area, allowing

bacteria and other micro-organisms to thrive and form a biological film. These micro-organisms

Page 23: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

21

M/s Raheja Developers Ltd.

utilise the dissolved oxygen in the air bubbles in the waste water to consume dissolved matter

and by so doing remove a majority of the colloidal contaminants present in the waste water by

converting them into carbon dioxide and biological floc.

Floc is then allowed to settle in the Clarifier from where it is removed, thereby reducing the

accumulation of sludge. Friction from the coarse air bubbles further serves to scour and release

dead biomass from the media. This Aerobic Tank is partially divided by a baffle so as to prevent

under-aerated waste water from prematurely moving to the next stage in the treatment process.

This baffle also serves to alter the flow direction such that the partially treated waste water will

make intimate contact with the submerged media before entering the Clarifier.

Clarifier

The Clarifier removes heavier solids by means of settlement and separation from the liquid

phase. It is designed to have a large surface area with adequate retention time. The hopper

bottom channels the sediment to the centre of the Clarifier tank before the sediment is returned to

Primary Tank 1.

Clear liquor from the top of the Clarifier is decanted into the Chlorine Contact Tank. In this

process, clarification and thickening happen at the same time. Separation of solids from the

liquid stream occurs to produce a clarified effluent with low suspended solid levels. From

thickening, the conveyance of sludge particles to the bottom of the tank results in a

slightly concentrated underflow, known as return activated sludge (RAS).

Chlorine Contact

The top water level of the influent waste water is allowed to overflow from the Clarifier to the

Chlorine Contact Tank. The Chlorine Contact Tank contains chlorine in tablet form and it is

designed to provide 30 minutes minimum contact time for effective disinfection of the influent

with chlorine, a powerful disinfectant.

This is a process whereby chlorine compounds are added to the treated waste water for the

purpose of pathogen reduction. Calcium hypochlorite tablets are in constant contact with the

effluent to ensure that the effluent is safe for disposal.

Media Filter

A media filter is required to meet the quality to re-use it again. Before reaching the Irrigation

Tanks the effluent is filtered using a Media Filter which will remove particles above 10 microns

in size. When the pressure drop across the Media Filter reaches a pre-determined set point the

Media Filter is automatically backwashed by the Media Filter Backwash Pump which draws

water from the Irrigation Tank with the dirty backwash wash water going back to the Balance

Tank.

Page 24: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

22

M/s Raheja Developers Ltd.

Figure 7: Typical flow Diagram of SAF Process Cycle

1.10 Storm Water Management

Storm water drainage system is provided at project site for channelizing storm water and

prevents local flooding. Covered storm water drains are provided at the site. Run-off from the

site is collected and recharged into the ground through 6 nos. of RWH pits existing at the site.

Recharge of the rainfall run-off to ground not only prevents the local flooding during rains but

als helps in augmenting the ground water level of the aquifers. CGWB has declared entire

Gurgaon district as notified zone in 2011. Ground water level in project area is app. 50 m bgl.

Stage of ground water development in project area is app. 308%. Run-off available from the site

annually is calculated and is presented in the Table 11. Calculations for rain water harvesting

pits are given below in Table 12. Layout plan showing location of RWH pits is attached as

Annexure XIV. Schematic diagram of RWH pit is given on Figure 8

Table 11: Available Run-off from Site

S. No. Catchment Area (sq m) Run-off

Coefficient

Average

Annual

Rainfall

(mm)

Available

Annual

Run-off

(cum)

1. Roof top 12,981.5 0.9 596 15958.4

2. Hard green 10,966.3 0.6 596 3921.5

3. Soft green 9,480.7 0.2 596 1130.1

4. Paved Areas 29750.9 0.7 596 12412.1

Total Run-off 33,422.1

Page 25: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

23

M/s Raheja Developers Ltd.

Table 12: Calculation for RWH Pits

S. No. Catchment Area (m2) Run-off

Coefficient

Peak

Hourly

Rainfall

(m)

Available

Annual

Run-off

(cum)

1. Roof top 12,981.5 0.9 0.055 642.6

2. Hard green 10,966.3 0.6 0.055 361.9

3. Soft green 9,480.7 0.2 0.055 104.3

4. Paved Areas 29750.9 0.7 0.055 1145.4

Total Run-off 2254.2

Retention Time 10 min

Available Run-off in 10 min 225.4

Size of RWH Pit 36

Nos. of RWH Pit 6.3

Nos. of Pits proposed 7

No. of Pits Existing 6

No. of Pits to be Constructed 1

Figure 8: Schematic Diagram of RWH Pits

Page 26: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

24

M/s Raheja Developers Ltd.

1.11 Vehicle Parking Facilities

Adequate parking is provided to accommodate the expected vehicles during operation phase of

the project. Parking is provided in accordance to HUDA Bye Laws. Parking required and

proposed parking is described below;

Parking Required:

As per MoEF norms:

For Residential facilities = 1 ECS/ 100 m2 FAR area

= 1,10000.7548/100 = 1100 ECS

For Commercial & Community = 1 ECS/ 50 m2 FAR area

= 262.709/50 = 6 ECS

For Nursery school = 1 ECS/ 50 m2 FAR area

= 1515.868/50 = 30 ECS

Total parking required as per MoEF Norms = 1100+6+30 = 1,136 ECS

As per Haryana Bye laws:

For Main DU: 1.5 ECS per DU’s (705 DU’s) = 1057 ECS

Parking Proposed:

Area provided for parking in Basement = 37,380 m2

Area required for 1 ECS of Basement parking = 35 m²

Parking provided in Basement = 1,068 ECS

Area provided for parking on Surface = 5600 m²

Area required for 1 ECS of Surface parking = 25 m²

Parking provided on surface = 224 ECS

Total Parking Provided

(Residential, Commercial, EWS, Community, School) = 1068+224=1,292 ECS

Page 27: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

25

M/s Raheja Developers Ltd.

Car parking of 1,292 ECS will be provided within project site to accommodate expected

vehicles. Car Parking & Traffic circulation for surface and basement are attached as Annexure

XV a, b & c.

1.12 Power Requirement

Maximum power demand for the project is estimated to be 4158.26 KW. Source of power will be

DHBVNL.

Details of D.G Sets

During power failure the sauce of supply is through DFG sets which are acoustic in nature. The

total 750 kVA (500*1+250*1) DG sets are installed at site. 2 DG sets of total capacity 1000 kVA

(500*2) is proposed to be installed as per raise in demand. Layout showing electrical HT & LT

room and DG sets are given in Annexure XVI and electrical SLD is attached as Annexure

XVII.

1.13 Solid Waste Generation And Management

Solid waste is generated both during construction as well as during operation phase. Solid waste

generated during construction phase is majorly excavated materials, cement bags, bricks,

concrete, MS rods, tiles, wood etc. Table 13 details the solid waste management plan during

construction phase

Table 13: Solid Waste Management during Construction Phase

S. No. Solid waste Solid waste Management

1. Waste materials like MS

Rods, bricks, concrete,

broken tiles, wood pieces,

cement bags etc.

Construction waste should be segregated into

recyclable/reusable and discarded material. Recyclable

material should be sold to authorize dealers. Re-usable

material should be stored under covered conditions at

site and reject should be disposed off at the designated

locations by HUDA. Waste should be transported in

covered vehicles only.

2. Excavated Soil

Top soil should be stripped and stored in covered

condition. Top soil should be used for landscaping

within the project site. Remaining excavated soil should

be re-used within the site for filling and leveling and

construction of roads. Excess muck should be disposed

off at the designated locations.

3. Domestic Waste Waste generated from labour hutment should be

Page 28: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

26

M/s Raheja Developers Ltd.

segregated into recyclable and rejected fraction.

Recyclable waste should be sld to authorized vendor and

emaining should be disposed off through local agencies

in the area responsible for waste management

During operation phase, waste comprise of municipal waste. It is estimated that approx. 2436 kg

per day (@0.5 kg per capita per day for the guests, 0.15 kg per capita per day for the visitor, 0.25

kg per capita per day for the staff members, whereas 0.2 kg/acres/day is considered for landscape

wastes) is estimated to be generated from project site after expansion and modification.

Estimations for solid waste generation during operation phase are given in Table 14. Waste

management plan is given below.

Table 14: Calculation of Solid Waste Generation

Category

Standard

(kg/day)

Existing

Population/

Area (sq m)

Existing

Waste

Generatio

n (kg/day)

Expansion/

Modificatio

n

Population/

Area (sq m)

Expansion/M

odification

Waste

Generation

(kg/day)

Total

Waste

Genera

tion

Recyclabl

e/Re-

usable Rejects

Residents 0.5

4060 2030 90 45

2075 623

1452

Staff/Students 0.25

426 107 397 99

206 62

144

Visitors 0.15

584 88 88 13

101 30

71

Green Area

(acre)

0.2

kg/acre/

day

4.3 1 0.76 0.1 1 1 0

STP Sludge -- -- 50 -- 3 53 53 0

Total Waste

Generation -- --

2276 --

160 2436 769 1667

(Source: For Waste Collection, Chapter 3, Table 3.6, Page no. 49, & Bio-Medical waste

Chapter 7, page 148 of Central Public Health & Environment Engineering Organization,

Ministry of Urban Development, (Government of India, May 2000))

Collection and Segregation of waste

a. A door to door collection system is provided for collection of domestic waste

b. Local vendors are hired for waste collection and management

c. Separate colored bins for dry recyclables and rejected waste are provided to residents as

well as in common and open areas

Page 29: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

27

M/s Raheja Developers Ltd.

Treatment of waste

a. Sludge from STP is stabilized and is used as manure

b. Landscape waste is composted in pit and is used as manure

Disposal

a. Rejected fraction of the waste is collected and disposed by local agencies on daily basis.

b. Recyclable waste and E-waste is sold to authorized vendors

c. Used oil from DG sets is sold to authorized vendors

1.14 Green Area

Total green area measures 20,447 m2 i.e. 35.7 % of the net plot area is planned to be kept under

green cover. At present, 17,385.1 sq m of area is already under green cover at site. Evergreen

and native species are preferably planted at the project site. Native species are adapted to natural

conditions and also requires less aftercare and maintenance. Trees with large & round canopy are

planted. Plantation act as noise buffer and also provide surface for dust settlement. Green belt

development plan for the area is given below

Green Belt development Plan

All the developments are associated with the pollution of one or more environmental component.

Plants are the natural sink of that pollution. Plants help in abatement of the pollution and restore

the degraded environment. Green belt lowers down the air pollution by providing a surface to

settle down or by absorbing the pollutants, attenuate noise level and uses the waste water. Phyto-

remediation is one of the most successful available technologies of restoring the degraded

environment. For this project area of 20,447 m2

is proposed to be put under green cover. Green

cover will comprise of:

A peripheral green belt

Avenue plantation (along road)

Lawns/parks & grass cretes/pavers

Planters

Page 30: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

28

M/s Raheja Developers Ltd.

Selection of Plant Species for Green Belt Development

Selection of plant species for the development depends on various factors such as climate,

elevation and soil. The plants would exhibit the following desirable characteristics in order to be

selected for plantation

1. Species should be fast growing and providing optimum penetrability with minimal

maintenance. Perennial, evergreen & fast growing trees

2. Species should be wind-firm and deep rooted

3. Indigenous and locally available species will be planted

4. Trees with high foliage density, leaves with larger leaf area and hairy on both the surfaces.

Round, thick & spreading canopy is preferred for peripheral green belt and oblong canopy

for road side plantation

5. Ability to withstand conditions like inundation and drought

6. Soil improving plants (Nitrogen fixing rapidly decomposable leaf litter)

7. Bird and insect attracting tree species

8. Tolerant to climatic conditions of the area and with less water requirement & after care will

preferable be planted. Species tolerance to air pollutants like SO2 and NO2 should be

preferred

9. Plantation trees with ornamental foliage & shrubs with fragrant flowers will enhance scenic

beauty of the area. Attractive appearance with good flowering and fruit bearing

10. Plantation should be such that it maintains ecological & hydrological balance of the region.

Trees and shrubs to be planted at project site as per CPCB guidelines for green belt development

are given below in Table 15 below

Table 15: List of Trees

S. No. Botanical Name Common Name

Trees

1 Albizzia lebbek Woman’s tongue tree

2 Anthocephalus cadamba Cadamba

3 Bauhinia blakeana Hong Kong Orchid

4 Bismarckia nobilis Bismarckia Palm

5 Cassia fistula Amaltas

6 Cassia javanica Apple blossom

Page 31: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

29

M/s Raheja Developers Ltd.

7 Crataeva adansonii Caper tree

8 Delonix regia Gulmohar

9 Ficus Alii Carrion Plant

10 Ficus Benjamina Weeping fig

11 Ficus lyrata Fiddle leaf

12 Ficus reginald Fig tree

13 Pterospermum acerifolium Kanak Champa

14 Plumeria obtusa/Rubra Frangipani

15 Wodiatia bifurcate Fox tail palm

16 Azadirachta indica Neem

Shrubs

1 Dypsis lutescens Arcea palm

2 Cestrum nocturnum Raatrani

3 Cycus revolute Japanese sago palm

4 Jatropha integerrima Peregrina

5 Rhapis palms Broad leaf lady palm

6 Duranta goldeana Golden dewdrop

7 Ficus panda Golden ficus

8 Tecoma gaudichaudi Yellow bells

9 Pittosporum tobira Japanese Mock Orange

10 Tecoma capensis Cape honeysuckle

11 Cyperus alternifolius Umberella palm

12 Anthrostylidium urbanii Dry yellow bamboo

Grass/herbs

1 Alternethera ficoidea Red fine leaf

2 Ophiopogon japonicas Monkey grass

3 Lantana sellowiana Lantana

4 Wedelia calendulacea Creeping oxeyes

5 Phalaris arundinacea Ribbon grass

6 Zephyranthes rosea Pink rain lily

7 Asparagus plumosa Asparagus

Creepers

1 Clerodendron splendens Glory tree

2 Bignonia venusta Flame vine

3 Bougainvillea bonsai Bougainvillea

(Source: Guidelines for developing Green Belts by CPCB, 2000)

After Care and Monitoring

Plants grown are monitored for first three years. Nutrients are supplemented and the juveniles are

provided protection. Following measures are taken:

1. Adequate nutrient supply is maintained by providing manure timely

2. Absence of water stress

Page 32: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

30

M/s Raheja Developers Ltd.

3. Construction of the protection wall all around to protect from animals and outsiders from

damage

Regular inspection of the site is done to check the survival. Record keeping of number of

saplings planted and surviving is kept. Regular pruning of road side trees is done as per

requirement. Weeding is carried out along with regular manuring & watering. Treated water

from STP is used for watering plant which is rich in nutrients. Landscape Plane for the project

site is attached as Annexure XVIII.

1.15 Construction Material

Material for the construction can be sourced from Rewari, Alwar and Delhi. Detail of different

type of construction material with their U values is given in Table 16. List of machinery which

may be used for construction is given below.

Table 16: List of Construction Materials

Type of Construction U values (in W/m2deg C)

Walls:

Brick:

Plastered both sides 3.24

Solid Unplastered 2.67

Plastered both sides 2.24

Concrete, Ordinary, Dense:

-152mm 3.58

-203mm 3.18

Concrete block:

CLC Fly ash block 1.19

Hollow Concrete block, 220mm, single skin, outside rendered, inside plastered:

CLC Fly ash block 1.70

Roofs Flat

Reinforced concrete slab, 100mm, scered 63-

12 mm, 3 layers bituminous felt

3.35

Floors:

Concrete on ground or hardcore fill 1.13

+ Grano, Terrazze or tile finish 1.13

+ Wood block finish 0.85

Exposure South Shelterd:

Single glazing 3.97

Double glazing 6 mm space 2.67

Page 33: At Sector-109, Village Pawala Khusrupur, Gurugram, Haryanaenvironmentclearance.nic.in/writereaddata/Online/... · Raheja Founder CMD of the company had been member of steering committee

Conceptual Plan

Modification and Expansion of Group Housing Project “Atharva Group Housing”

At Sec-109, Village Pawala Khurupur, Gurugram, Haryana

31

M/s Raheja Developers Ltd.

LIST OF MACHINERY USED DURING CONSTRUCTION

Dumper

Concrete mixer with hopper

Excavator

Concrete Batching Plant

Cranes

Road roller

Bulldozer

Tower Cranes

Hoist

Labor Lifts

Concrete pressure pumps

Mobile transit mixer