Page 1: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy

City of Salisbury

ASSET MANAGEMENT STRATEGY

Version 6

June 2015

Page 2: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy

Document Control

Document Control NAMS.PLUS Asset Management

www.ipwea.org/namsplus

Document ID: asset management strategy version 5 (march 2015).doc

Rev No Date Revision Details Author Reviewer Approver

1 10/12/2014 First Draft JC

2 12/12/2014 Second Draft JC SAMG

3 13/01/2015 Third Draft JC EXEC

4 27/03/2015 Final Draft (Updated budgets for 2015/16) JC EXEC

5 02/04/2015 Included additional Strategy graphs JC EXEC

6a 30/06/2015 Minor changes and additions JC EXEC

6b 16/11/2015 Final version endorsed by Council JC EXEC Council

NAMS.PLUS Asset Management

The Institute of Public Works Engineering Australasia.

www.ipwea.org/namsplus

© Copyright 2012 – All rights reserved.

Page 3: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page i

Table of Contents

Executive Summary ................................................................................................................................. 1

1. Introduction .................................................................................................................................... 4

1.1 Legislative reform ................................................................................................................... 5

1.2 Asset Management Planning Process ..................................................................................... 6

2. What Assets do we have? ............................................................................................................... 7

3. The Organisation’s assets and their management? ........................................................................ 8

3.1 State of the Assets .................................................................................................................. 8

3.1.1 Financial State of the Assets ................................................................................................... 8

3.1.2 Projected Operations and Maintenance Expenditure ............................................................ 9

3.1.3 Summary of future renewal and replacement expenditure ................................................... 9

3.1.4 Summary of future upgrade/new assets expenditure .......................................................... 10

3.1.5 Financial Statements and Projections ................................................................................... 11

3.1.6 Asset management financial indicators ................................................................................ 11

3.1.7 Asset Consumption Ratio ...................................................................................................... 12

3.2 Life Cycle Cost ....................................................................................................................... 13

3.3 Asset Management Structure ............................................................................................... 15

3.3.1 Asset Management Framework ............................................................................................ 15

3.3.2 Roles and Responsibilities ..................................................................................................... 15

3.3.3 Asset Owner Structure .......................................................................................................... 16

3.4 Corporate Asset Management Team .................................................................................... 16

3.5 Financial & Asset Management Core Competencies ............................................................ 17

3.6 Strategy Outlook ................................................................................................................... 20

4. Where do we want to be? ............................................................................................................ 21

4.1 Council’s Vision, Mission, Goals and Objectives ................................................................... 21

4.2 Asset Management Policy ..................................................................................................... 23

4.3 Asset Management Vision .................................................................................................... 23

5. How will we get there? ................................................................................................................. 24

6. Asset Management Improvement Plan ........................................................................................ 25

Tables

Table 1: Assets used for providing Services ............................................................................................ 7

Table 2: Financial Status of the Assets .................................................................................................... 8

Table 3: Life Cycle Cost for Council Services ......................................................................................... 13

Table 4: Life Cycle Expenditure for Council Services ............................................................................ 13

Table 5: Life Cycle Indicators................................................................................................................. 14

Table 6: Asset Owner Structure ............................................................................................................ 16

Table 7: Key Directions and Objectives for Infrastructure Services ...................................................... 22

Table 8: Asset Management Strategies ................................................................................................ 24

Table 9: Asset Management Improvement Plan .................................................................................. 25

Page 4: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page ii

Figures

Figure 1: Asset Replacement Cost by Asset Management Plan ............................................................. 8

Figure 2: Projected Operations and Maintenance Expenditure ............................................................. 9

Figure 3: Projected Capital Renewal and Replacement Expenditure .................................................. 10

Figure 4: Projected Capital Renewal and Replacement Expenditure .................................................. 10

Figure 5: Projected Operating and Capital Expenditure ...................................................................... 11

Figure 6: Projected Operating and Capital Expenditure ...................................................................... 11

Figure 7: Asset Consumption Ratio ....................................................................................................... 12

Figure 8: Asset Management Framework ............................................................................................. 15

Figure 9: Core Asset Management Maturity Assessment (Sept 2013) ................................................. 18

Figure 10: Indicative Core Asset Management Maturity Assessment (Feb 2015) ............................... 18

Page 5: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 1

Executive Summary

This asset management strategy is prepared to assist council in improving the way it delivers services

from infrastructure including transport, drainage, fleet, buildings, parks & streetscapes, trees and

water business assets. These infrastructure assets have a replacement value of $1.4B.

The asset management strategy is to enable Council to show:

how its asset portfolio will meet the service delivery needs of its community into the future,

enable Council’s asset management policies to be achieved, and

ensure the integration of Council’s asset management with its long term strategic plan.1

Adopting this asset management strategy will assist council in meeting the requirements of national

sustainability frameworks, the South Australian Local Government Act 1999, Local Government

(Financial Management) Regulations 2011 and providing services needed by the community in a

financially sustainable manner.

The asset management strategy is prepared following a review of the council’s service delivery

practices, financial sustainability indicators, asset management maturity and fit with council’s vision

for the future outlined in the City Plan “Sustainable Futures 2020”. The strategy outlines an asset

management improvement plan detailing a program of tasks to be completed and resources

required to bring council to a minimum ‘core’ level of asset maturity and competence.

Strategy outlook

1. Council can maintain assets for the next 10 years at current funding and service levels within

the Long Term Financial Plan.

This includes:

Increased Street Trees renewal expenditure to increase the frequency of Streetscape

Renewal and prevent future increases to civil infrastructure maintenance budgets.

Air Conditioning Renewal increased expenditure to target high priority air conditioners

for renewal previously managed by sporting clubs.

Commencement of a bus shelter renewal program for bus shelters in poor condition and

nearing the end of their useful life.

2. The organisation’s current asset management maturity is nearing ‘core’ level as detailed in

section 3.5.

3. Investment is needed to:

Improve Information management - by increasing the quality of data in Council’s Asset

Management System, Confirm.

Improve Lifecycle management – by continually improving the data and assessment of

Council’s infrastructure

1 LGPMC, 2009, Framework 2 Asset Planning and Management, p 4.

Page 6: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 2

Include condition data in the Asset Management System and develop a process to maintain

the currency of condition across numerous asset categories.

Improve the collection of Key Performance Indicator data from the Community and Council

based on set levels of Service and condition.

4. Council commit to ensuring that it focuses on asset renewals and will prioritise funding to address infrastructure that is not providing a suitable level of service.

5. Focus new assets on meeting needs identified to be critical to enhancing community wellbeing and delivered sustainably across its lifecycle.

Asset Management Strategies

No Strategy Desired Outcome

1 Continued Long Term Financial Planning to achieve financial

sustainability.

The long term implications of

Council services are considered in

annual budget deliberations.

2 Develop and annually review Asset Management Plans covering at

least 10 years for all major asset classes (80% of asset value).

Identification of services needed

by the community and required

funding to optimise ‘whole of life’

costs.

3 Asset management plan expenditure projections covering 10

years to inform the Long Term Financial Plan with a sustainable

funding position outcome.

Sustainable funding model to

provide Council services.

4 Incorporate Year 1 of Long Term Financial Plan revenue and

expenditure projections into annual budgets.

Long term financial planning drives

budget deliberations.

5 Review and update asset management plans and long term

financial plans after adoption of annual budgets. Communicate

any consequence of funding decisions on service levels and

service risks.

Council and the community are

aware of changes to service levels

and costs arising from budget

decisions.

6 Report Council’s financial position relating to its assets at Fair

Value in accordance with Australian Accounting Standards,

financial sustainability and performance against strategic

objectives in Annual Reports.

Financial sustainability information

is available for Council and the

community.

7 Ensure Council’s decisions are made from accurate and current

information in asset registers, on service level performance and

costs and ’whole of life’ costs.

Improved decision making and

greater value for money.

8 Implement an Improvement Plan to realise ‘core’ maturity for the

financial and asset management competencies within 2 years.

Improved financial and asset

management capacity within

Council.

Page 7: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 3

Asset Management Improvement Plan

The program of tasks and resources required to achieve a minimum ‘core’ asset management

maturity was developed in the asset management strategy. The tasks and program are shown

below.

Ref Task Responsibility Target Date

1 Council endorsement of Asset Management Policy Council Nov 2015

2 Council endorsement of Asset Management Plans Council Nov 2015

3 Council endorsement of Asset Management

Strategy

Council Nov 2015

4 Implement a continuous improvement process to

manage the Asset Register and development of

Asset Management Plans

SAMG Ongoing

5 Undertake/update Asset Management maturity

assessment

SAMG April 2016

6 Condition assessments to be undertaken and

recorded against the discrete asset in the asset

register.

SAM Ongoing

7 Deliver objectives outlined in the Asset

Management Plan Operationalisation Project.

SAMG/AMIG/

Project Team

July 2017

8 Continue informing Elected Members and key staff

on Asset Management.

SAMG/SAM Ongoing

Page 8: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 4

1. Introduction

Assets deliver important services to communities. A key issue facing local governments throughout

Australia is the management of ageing assets in need of renewal and replacement.

Infrastructure assets such as roads, drains, bridges, water and public buildings present particular

challenges. Their condition and longevity can be difficult to determine. Financing needs can be

large, requiring planning for large peaks and troughs in expenditure for renewing and replacing such

assets. The demand for new and improved services adds to the planning and financing complexity.2

The creation of new assets also presents challenges in funding the ongoing operating and

replacement costs necessary to provide the needed service over the assets’ full life cycle.3

The national frameworks on asset planning and management and financial planning and reporting

endorsed by the Local Government and Planning Ministers’ Council (LGPMC) require councils to

adopt a longer-term approach to service delivery and funding comprising:

A strategic longer-term plan covering, as a minimum, the term of office of the councillors

and:

o bringing together asset management and long term financial plans,

o demonstrating how council intends to resource the plan, and

o consulting with communities on the plan

Annual budget showing the connection to the strategic objectives, and

Annual report with:

o explanation to the community on variations between the budget and actual results ,

o any impact of such variances on the strategic longer-term plan,

o report of operations with review on the performance of the council against strategic

objectives.4

Framework 2 Asset Planning and Management has seven elements to assist in highlighting key

management issues , promote prudent, transparent and accountable management of local

government assets and introduce a strategic approach to meet current and emerging challenges.

Asset management policy,

Strategy and planning,

o asset management strategy,

o asset management plan,

Governance and management arrangements,

Defining levels of service,

Data and systems,

Skills and processes, and

Evaluation.5

2 LGPMC, 2009, Framework 2 Asset Planning and Management, p 2.

3 LGPMC, 2009, Framework 3 Financial Planning and Reporting, pp 2-3.

4 LGPMC, 2009, Framework 3 Financial Planning and Reporting, pp 4-5.

Page 9: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 5

The asset management strategy is to enable Council to show:

how its asset portfolio will meet the service delivery needs of its community into the future,

to enable Council’s asset management policies to be achieved, and

to ensure the integration of Council’s asset management with its long term strategic plan.6

The goal of asset management is to ensure that services are provided:

in the most cost effective manner,

through the creation, acquisition, maintenance, operation, rehabilitation and disposal of

assets,

for present and future consumers.

The objective of the Asset Management Strategy is to establish a framework to guide the planning,

construction, maintenance and operation of the infrastructure essential for council to provide

services to the community.

1.1 Legislative reform

The Local Government Act 1999 and its regulations require each Council to:

have an I&AMP, covering the management of infrastructure and other major assets of the Council for a period of at least 10 years7

have a long-term financial plan covering a period of at least 10 years8

maintain prudential management policies, practices and procedures for the assessment of all projects9

prepare and consider a specially-commissioned report on the prudential aspects of a contemplated major asset acquisition or construction project (not required for road construction/maintenance or drainage)10

have a policy on the sale and disposal of assets11

adopt an internal control policy which safeguards assets12

maintain accounting records of assets13

maintain a register of community land14

maintain a register of public roads15.

regularly estimate its “asset sustainability ratio” and include the updated estimate in its:

5 LGPMC, 2009, Framework 2 Asset Planning and Management, p 4.

6 LGPMC, 2009, Framework 2 Asset Planning and Management, p 4.

7 Local Government Act 1999 Section 122 (1a)(b)

8 Local Government Act 1999 Section 122 (1a)(a)

9 Local Government Act 1999 Section 48 (aa1). See also Financial Sustainability Information Paper

No. 27: Prudential Management at http://www.lga.sa.gov.au/goto/fsp 10

Local Government Act 1999 Section 48(1) and 48 (3) 11

Local Government Act 1999 Section 49 (1)(d) 12

Local Government Act 1999 Section 125 13

Local Government Act 1999 Section 124(1)(a) 14

Local Government Act 1999 Section 207(1) 15

Local Government Act 1999 Section 231(1)

Page 10: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 6

o long-term financial plans16 o annual budget and17 o mid-year budget review and18

regularly revalue its material non-current assets in accordance with the requirements of Australian Accounting Standards19

1.2 Asset Management Planning Process

Asset management planning is a

comprehensive process to ensure that

assets are managed and maintained in a

way that enables affordable services from

infrastructure to be provided in an

economically optimal way. In turn,

affordable service levels can only be

determined by assessing Council’s

financially sustainability under scenarios

with different proposed service levels.

Asset management planning commences

with defining stakeholder and legal

requirements and needs, incorporating

these needs into the organisation’s strategic

plan, developing an asset management

policy, strategy, asset management plan

and operational plans, linked to a long-term

financial plan with a funding plan.20

16 Local Government (Financial Management) Regulations 2011 Regulation 5(c)

17 Local Government (Financial Management) Regulations 2011 Regulation 7(d)

18 Local Government (Financial Management) Regulations 2011 Regulation 9(2)

19 Local Government (Financial Management) Regulations 2011 Regulation 12

20 IPWEA, 2009, AIFMG, Quick Guide, Sec 4, p 5.

Asset Management Planning Process

Legal and Stakeholder Requirements

and Expectations

Organisational Strategic PlanVision, Mission, Goals & Objectives,

Levels of Service, Business Policies, Risk

ASSET MANAGEMENT POLICY

ASSET MANAGEMENT STRATEGY Objectives, level of service target and plans

Asset

Management

Philosophy &

Framework

Service

Delivery OPERATIONAL PLANSService delivery in accordance with asset

management plans

Asset solutions – operate, maintain, renew,

enhance, retire

Non-asset solutions – partnerships, demand

management, insurance, failure management

KNOWLEDGE MANAGEMENTAsset data and information systems

Knowledge

AS

SE

T M

AN

AG

EM

EN

T P

LA

NN

ING

Op

era

tio

na

l T

actica

l S

tra

teg

ic

Pla

nn

ing

P

lan

nin

g P

lan

nin

g

ASSET MANAGEMENT PLANS Services & service levels to be provided,

funds required to provide services

Page 11: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 7

2. What Assets do we have?

Council uses infrastructure assets to provide services to the community. The range of infrastructure

assets and the services provided from the assets is shown in Table 1.

Table 1: Assets used for providing Services

Asset Management Plan Description

Transportation The Transportation Asset Management Plan includes; Roads, kerbing, footpath,

traffic devices, signage, lighting etc.

Building The Building Asset Management Plan includes; sporting clubs, reserve shelters,

libraries, recreation centres, municipal offices,

Parks and Streetscape The Parks & Streetscapes Asset Management Plan includes; playgrounds,

fencing, furniture, irrigation, landscaping, sporting reserves etc.

Drainage & Waterways The Drainage & Waterways Asset Management Plan includes; stormwater pits

& pipes, open drains, dams etc.

Salisbury Water The Salisbury Water Asset Management Plan includes; distribution &

harvesting pipes, pipes, filtration equipment, wells, bores, tanks pumps etc.

Street Trees The Street Trees Asset Management Plan includes street trees/streetscapes

Fleet The Plant and Fleet includes: heavy vehicles, light vehicles and trailers

Page 12: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 8

3. The Organisation’s assets and their management?

3.1 State of the Assets

3.1.1 Financial State of the Assets

The financial status of the organisation’s assets is shown in Table 2.

Table 2: Financial Status of the Assets

Asset

Management

Plan

Replacement

Cost

Residual

Value

Depreciable

Amount

Depreciated

Replacement

Cost

Depreciation

Expense

Transportation 765,757,000 0 765,757,000 460,396,000 11,241,000

Drainage &

Waterways

388,823,000 0 388,823,000 262,917,000 4,151,000

Buildings 98,037,000 49,936,000 48,101,000 73,679,000 1,068,000

Fleet 9,326,000 269,000 7,057,000 5,195,000 1,059,000

Parks &

Streetscapes

76,421,000 2,381,000 74,040,000 35,636,000 2,261,000

Street Trees 332,000 7,000 325,000 67,000 1,000

Salisbury Water 68,941,000 1,457,000 67,484,000 57,511,000 1,516,000

Total 1,407,637,000 54,050,000 1,351,587,000 895,317,000 21,297,000

Figure 1 shows the replacement values of Council’s assets of each Asset Management Plan as a

proportion of the total asset replacement value.

Figure 1: Asset Replacement Cost by Asset Management Plan

Page 13: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 9

3.1.2 Projected Operations and Maintenance Expenditure

Future operations and maintenance expenditure is forecast to trend in line with the value of the asset stock as shown in Figure2. Note that all costs are shown in current 2015 dollar values (i.e. real values).

Figure 2: Projected Operations and Maintenance Expenditure

3.1.3 Summary of future renewal and replacement expenditure

Projected future renewal and replacement expenditures are forecast to increase over time as the

asset stock increases from growth. The expenditure is summarised in Fig 3. Note that all costs are

shown in current 2015 dollar values (i.e. real values).

The projected capital renewal and replacement program is shown in Appendix A of each Asset

Management Plan.

Page 14: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 10

Figure 3: Projected Capital Renewal and Replacement Expenditure

3.1.4 Summary of future upgrade/new assets expenditure

Figure 4: Projected Capital Renewal and Replacement Expenditure

Projected upgrade/new asset expenditures are summarised in Fig 6. The projected upgrade/new

capital works program is shown in Appendix B of each Asset Management Plan. Note that all costs

are shown in current 2015 dollar values (i.e. real values).

Page 15: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 11

3.1.5 Financial Statements and Projections

The financial projections are shown in Fig 5 for projected operating (operations and maintenance)

and capital expenditure (renewal and upgrade/expansion/new assets). Note that all costs are shown

in current 2015 dollar values (i.e. real values).

Figure 5: Projected Operating and Capital Expenditure

3.1.6 Asset management financial indicators

Figure 6 shows the asset management financial indicators over the 10 year planning period and for the long term life cycle.

Figure 6: Projected Operating and Capital Expenditure

Page 16: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 12

3.1.7 Asset Consumption Ratio

The asset consumption ratios of Council’s assets (average proportion of ‘as new’ condition left in

assets) are shown in Figure 7.

Figure 7: Asset Consumption Ratio

Note: Street Tree assets have not previously been capitalised and therefore the value in the asset register is

relatively low. There are 70,000 street trees in the City of Salisbury which will be capitalised as streetscape

renewal programs are completed.

The asset consumption ratio graph shows as expected that the Salisbury Water assets are relatively

new, fleet assets tend to be older due to deferring replacement of items while the remaining asset

classes are around halfway through their lifecycle.

Page 17: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 13

3.2 Life Cycle Cost

Life cycle costs (or whole of life costs) are the average costs that are required to sustain the service

levels over the longest asset life. Life cycle costs include operating and maintenance expenditure

and asset consumption (depreciation expense). The life cycle cost for the services covered in this

asset management plan is shown in Table 3.

Table 3: Life Cycle Cost for Council Services

Asset Management

Plan

2015/16 Expenditure 2014/15 Life Cycle Cost

($’000s/yr)

Operations

($’000s)

Maintenance

($’000s)

Depreciation Exp

($’000s)

Transportation 3,365 6,019 11,241 20,969

Drainage &

Waterways

272 2,212 4,151 6,858

Buildings 2,205 2,621 1,068 6,322

Fleet 1,774 837 1,059 3,692

Parks &

Streetscapes

2,725 12,049 2,261 17,290

Street Trees 0 2,730 1 2,731

Salisbury Water 2,119 809 1,516 4,443

All Services 12,460 27,277 21,297,000 62,305

Life cycle costs can be compared to life cycle expenditure to give an indicator of sustainability in

service provision. Life cycle expenditure includes operating, maintenance and capital renewal

expenditure in the previous year or preferably averaged over the past 3 years. Life cycle

expenditure will vary depending on the timing of asset renewals. The life cycle expenditure at the

start of the plan is shown in Table 4.

Table 4: Life Cycle Expenditure for Council Services

Asset

Management Plan 2015/16 Expenditure

Renewal Exp

($’000s/yr)

Life Cycle Exp

($’000s/yr)

Operations

($’000s)

Maintenance

($’000s)

Transportation 3,365 6,019 9,356 18,740

Drainage &

Waterways

272 2,212 1,335 3,819

Buildings 2,205 2,621 4,985 9,811

Fleet 1,774 837 1,484 4,095

Parks &

Streetscapes

2,725 12,049 1,315 16,089

Street Trees 0 2,730 1,100 3,830

Salisbury Water 2,119 809 147 3,075

All Services 12,460 27,277 19,722 59,459

The life cycle costs and life cycle expenditure comparison highlights any difference between present

outlays and the average cost of providing the service over the long term, If the life cycle expenditure

Page 18: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 14

is less than the life cycle cost, it is most likely that outlays will need to be increased or cuts in

services made in the future.

Knowing the extent and timing of any required increase in outlays and the service consequences if

funding is not available will assist organisations in providing service to their communities in a

financially sustainable manner. This is the purpose of the AM Plans and long term financial plan.

A shortfall between life cycle cost and life cycle expenditure gives an indication of the life cycle gap

to be addressed in the asset management and long term financial plan.

The life cycle gap and life cycle indicator for services covered by this asset management plan is

summarised in Table 5.

Table 5: Life Cycle Indicators

Asset Management

Plan

Life Cycle Cost

($’000s /yr)

Life Cycle Expenditure

($’000s /yr)

Life Cycle Gap *

($’000s /yr)

Life Cycle

Indicator

Transportation 20,969 18,740 -2,229 89%

Drainage &

Waterways

6,858 3,819 -3,039 56%

Buildings 6,322 9,811 3,489 155%

Fleet 3,692 4,095 403 111%

Parks &

Streetscapes

17,290 16,089 -1,201 93%

Street Trees 2,731 3,830 1,099 140%

Salisbury Water 4,443 3,075 -1,368 69%

All Services 62,305 59,459 -2,846 95%

Note: * A life cycle gap is reported as a negative value.

The table above shows a $2.85M life cycle gap overall with the majority of this gap being present in

the asset categories with longer lives and/or newer assets. The Drainage & Waterways AMP shows

limited expenditure required in the short term but significant expenditure is required starting from

2040. The Salisbury Water AMP assets are generally new and are reflected in the lifecycle gap which

also indicates significant future expenditure. The Street Trees AMP shows an excess of $1.1M which

is due to the fact that street trees have not been historically capitalised and therefore have very little

depreciation.

The Life Cycle Gap is determined using the expenditure in the first year compared to the average

expenditure required for the life of the asset. As described above long lived assets with high value

such as drainage pipes & pits, road pavement and kerbing are still in generally good condition and

limited expenditure has occurred on these assets. As such an overall life cycle gap currently exists

but will not in the future when expenditure will increase as these assets near the end of their useful

lives.

Page 19: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 15

3.3 Asset Management Structure

3.3.1 Asset Management Framework

The Asset Management Policy, Strategy and Plans will be provided to Council for adoption. The

relationships between the Asset Management Policy, Strategy and Plans are outlined in Figure 8

below.

Figure 8: Asset Management Framework

3.3.2 Roles and Responsibilities

Council

Key Stakeholder

Responsible for adopting the Asset Management Policy, Strategy and Plans.

Chief Executive Officer

Responsible for implementing the Asset Management Policy, Strategy and Plans.

Strategic Asset Management Group

Responsible for developing strategic and systematic approach to the sustainable

management of Council’s Assets.

Asset Management Implementation Group

Responsible for developing the operational links and processes which enable the

implementation of the strategic management of Council’s Assets.

AM Strategy AM Objectives, AM

Practices, Action Plans for AM

Improvement, Audit and Review processes.

AM Policy Principles, requirements and

responsibilities for AM inked to

organisational strategic objectives.

AM Plan Asset/Service Description,

Levels of Service, Demand Forecasts,

Lifecycle Activities, Cash flow Forecasts

Page 20: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 16

3.3.3 Asset Owner Structure

The majority of infrastructure assets are managed with the City Infrastructure Department. As a

consequence the City Infrastructure Department has organisational responsibility to maintain the

Policy and Strategy as well as facilitate the continual improvement of Council’s Asset Management

System (Confirm).

The Asset Owners responsible for management and reporting on each asset class is provided in

Table 6 below.

Table 6: Asset Owner Structure

Asset Management Plan Asset Owner

Transportation Manager Civil & Waste

Drainage & Waterways Manager Civil & Waste

Buildings Manager Property & Buildings

Fleet Manager Business Support

Parks & Streetscapes Manager Parks & Landscape

Street Trees Manager Parks & Landscape

Salisbury Water Manager Salisbury Water

3.4 Corporate Asset Management Team

A ‘whole of organisation’ approach to asset management is led by the Strategic Asset Management

Group, in Technical Services. This team co-ordinates with Asset Owners, Finance, IT and Executive to

deliver Corporate Asset Management. The benefits of a corporate asset management team include:

demonstrate corporate support for sustainable asset management,

encourage corporate buy-in and responsibility,

coordinate strategic planning, information technology and asset management activities,

promote uniform asset management practices across the organisation,

information sharing across IT hardware and software,

pooling of corporate expertise

championing of asset management process,

wider accountability for achieving and reviewing sustainable asset management practices.

The role of the asset management team will evolve as the organisation maturity increases over

several phases.

Phase 1

strategy development and implementation of asset management improvement program,

Phase 2

asset management plan development and implementation,

reviews of data accuracy, levels of service and systems plan development,

Phase 3

asset management plan operation

evaluation and monitoring of asset management plan outputs

ongoing asset management plans review and continuous improvement.

Page 21: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 17

A large improvement project to operationalise the asset management plans is currently being

scoped. Some of the key objectives of the project are;

to ensure that CoS has correct and accurate data to deliver Asset Management modelling in

the future

to ensure that CoS has an accurate and complete asset register

to deliver efficiency improvement by

o Allowing for more realtime budget line management

o Deliver mobility in the field

o Reduce manual, paper based systems

o Reduce duplication of effort and data entry

to review, document and implement standardised business processes for repetitive asset

management tasks

3.5 Financial & Asset Management Core Competencies

The National Frameworks on Asset Planning and Management and Financial Planning and Reporting

define 10 elements. 11 core competencies have been developed from these elements to assess

‘core’ competency under the National Frameworks. The core competencies are:

Financial Planning and Reporting

Strategic Longer Term Plan

Annual Budget

Annual report

Asset Planning and Management

Asset Management Policy

Asset Management Strategy

Asset Management Plan

Governance & Management

Levels of Service

Data & Systems

Skills & processes

Evaluation

Council’s maturity assessment for the core competencies is detailed in Appendix A and summarised

in Figure 9. The current maturity level is shown by the blue bars. The maturity gap to be overcome

for Council to achieve a core financial and asset management competency is shown by the red bars.

Page 22: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 18

Figure 9: Core Asset Management Maturity Assessment (Sept 2013)

A maturity assessment was undertaken in September 2013 (Figure 10) from which a project was

implemented to review and develop an Asset Management Policy, Strategy and Plans for major asset

classes. The adoption of this strategy, plans and policy will result in achieving core maturity for these

areas.

The maturity assessment has been updated to reflect the Asset Management Improvement Process

that has been undertaken and pending Council endorsement of the Asset Management Policy,

Strategy and Plans.

Figure 10: Indicative Core Asset Management Maturity Assessment (Feb 2015)

Core maturity will be achieved by implementing:

Page 23: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 19

a continuous improvement strategy to assess and report on the performance of council

controlled assets , and

a rigorous assessment of the asset register ensuring it satisfies the accounting valuation,

insurance and operational requirements of the organisation.

Page 24: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 20

3.6 Strategy Outlook

Strategy outlook

1. Council is able to maintain assets for the next ten years at current funding and service levels

within the Long Term Financial Plan.

This includes:

Street Trees renewal increased expenditure to increase the frequency of Streetscape

Renewal and prevent future increases to civil infrastructure maintenance budgets.

Air Conditioning Renewal increased expenditure to target high priority air conditioners

for renewal.

Commencement of a bus shelter renewal program for bus shelters in poor condition and

nearing the end of their useful life.

2. The organisation’s current asset management maturity is nearing ‘core’ level.

3. Investment is needed to:

Improve Information management - by increasing the quality of data in Council’s Asset

Management System, Confirm.

Improve Lifecycle management – by continually improving the data and assessment of

Council’s infrastructure

Include condition data in the Asset Management System and develop a process to maintain

the currency of condition across numerous asset categories.

Improve the collection of Key Performance Indicator data from the Community and Council

based on set levels of Service and condition.

4. Council commit to ensuring that it focuses on asset renewals and will prioritise funding to address infrastructure that is not providing a suitable level of service.

5. Focus new assets on meeting needs identified to be critical to enhancing community wellbeing and delivered sustainably across its lifecycle.

Page 25: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 21

4. Where do we want to be?

4.1 Council’s Vision, Mission, Goals and Objectives

Council has adopted a Vision and values for the future in the Council Strategic Plan.

‘Excellence in building a community of opportunity and spirit in a quality environment’.21

Our Values:

‘The City Plan articulates five core organisational values. These values are the principles we use to define what is critical to the City of Salisbury, both as a community and an organisation. They influence our behaviour and provide clear guidance on what is important for service delivery at both the strategic and operational level.’22

This is achieved via Salisbury’s City Plan – Sustainable Futures and the following four Key Directions:

The Strategic Plan sets goals and objectives to be achieved in the planning period. The Key

Directions set out where the organisation wants to be. The objectives are the steps needed to get

there. Goals and objectives relating to the delivery of services from infrastructure are shown in

Table 7.

21 City of Salisbury Annual Plan 2014/15

22 Sustainable Futures 2020

Page 26: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 22

Table 7: Key Directions and Objectives for Infrastructure Services

Key Direction Objectives

The Prosperous City To enhance and create quality urban areas with high

amenity and

integrated infrastructure

To deliver suitably integrated infrastructure that

maximises economic

efficiencies and opportunities for the community

The Sustainable City To have sustainable and resilient natural

environments that support

biodiversity and contribute to quality amenity

To reduce corporate carbon emissions via mitigation

as well as optimising

renewable energy options

To reduce resource consumption and minimise waste

generation

To deliver sustainable water management and

improve water security for

the city

To have sustainable and resilient built environments

that contribute to

quality amenity

The Living City To have a community that embraces healthy and

active lifestyles

To have a city where a quality of life is achievable

Achieving Excellence To deliver sustainable, creative and innovative

solutions that enable

excellent operations and service delivery

To ensure informed and transparent decision-making

that is accountable

and legally compliant

To apply business and resource management that

enables excellent

service delivery and financial sustainability

Council’s Asset Management Policy defines the council’s vision and service delivery objectives for

asset management in accordance with legislative requirements, community needs and affordability.

Page 27: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 23

4.2 Asset Management Policy

Council’s Asset Management Policy defines the council’s vision and service delivery objectives for

asset management in accordance with the Strategic Plan and applicable legislation. This Policy has

been approved by the Strategic Asset Management Group and awaits endorsement by Council.

The asset management strategy is developed to support the asset management policy and is to

enable council to show:

how its asset portfolio will meet the affordable service delivery needs of the community into

the future,

enable Council’s asset management policies to be achieved, and

ensure the integration of Council’s asset management with its long term strategic plans.

4.3 Asset Management Vision

To ensure the long-term financial sustainability of Council, it is essential to balance the community’s

expectations for services with their ability to pay for the infrastructure assets used to provide the

services. Maintenance of service levels for infrastructure assets requires appropriate investment

over the whole of the asset life cycle. To assist in achieving this balance, Council aspires to:

Develop and maintain asset management governance, skills, process, systems and data in order to

provide the level of service the community need at present and in the futures, in the most cost-

effective and fit for purpose manner.

In line with the vision, the objectives of the asset management strategy are to:

ensure that the Council’s infrastructure services are provided in an economically optimal

way, with the appropriate level of service to residents, visitors and the environment

determined by reference to Council’s financial sustainability,

safeguard Council’s assets including physical assets and employees by implementing

appropriate asset management strategies and appropriate financial resources for those

assets,

adopt the long term financial plan as the basis for all service and budget funding decisions,

meet legislative requirements for all Council’s operations,

ensure resources and operational capabilities are identified and responsibility for asset

management is allocated,

provide high level oversight of financial and asset management responsibilities through

Audit Committee/CEO reporting to council on development and implementation of Asset

Management Strategy, Asset Management Plans and Long Term Financial Plan.

Strategies to achieve this position are outlined in Section 5.

Page 28: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 24

5. How will we get there?

The Asset Management Strategy proposes strategies to enable the objectives of the Strategic Plan,

Asset Management Policy and Asset Management Vision to be achieved.

Table 8: Asset Management Strategies

No Strategy Desired Outcome

1 Continued Long Term Financial Planning to achieve financial

sustainability.

The long term implications of

Council services are considered in

annual budget deliberations.

2 Develop and annually review Asset Management Plans covering at

least 10 years for all major asset classes (80% of asset value).

Identification of services needed

by the community and required

funding to optimise ‘whole of life’

costs.

3 Asset management plan expenditure projections covering 10

years to inform the Long Term Financial Plan with a sustainable

funding position outcome.

Sustainable funding model to

provide Council services.

4 Incorporate Year 1 of Long Term Financial Plan revenue and

expenditure projections into annual budgets.

Long term financial planning drives

budget deliberations.

5 Review and update asset management plans and long term

financial plans after adoption of annual budgets. Communicate

any consequence of funding decisions on service levels and

service risks.

Council and the community are

aware of changes to service levels

and costs arising from budget

decisions.

6 Report Council’s financial position relating to its assets at Fair

Value in accordance with Australian Accounting Standards,

financial sustainability and performance against strategic

objectives in Annual Reports.

Financial sustainability information

is available for Council and the

community.

7 Ensure Council’s decisions are made from accurate and current

information in asset registers, on service level performance and

costs and ’whole of life’ costs.

Improved decision making and

greater value for money.

8 Implement an Improvement Plan to realise ‘core’ maturity for the

financial and asset management competencies within 2 years.

Improved financial and asset

management capacity within

Council.

Page 29: ASSET MANAGEMENT STRATEGY - City of Salisbury · 2018. 9. 4. · The asset management strategy is prepared following a review of the council’s service delivery practices, financial

City of Salisbury Asset Management Strategy Page 25

6. Asset Management Improvement Plan

The tasks required to achieve a ‘core’ financial and asset management maturity are shown in priority

order in Table 9.

Table 9: Asset Management Improvement Plan

Ref Task Responsibility Target Date

1 Council endorsement of Asset Management Policy Council Nov 2015

2 Council endorsement of Asset Management Plans Council Nov 2015

3 Council endorsement of Asset Management

Strategy

Council Nov 2015

4 Implement a continuous improvement process to

manage the Asset Register and development of

Asset Management Plans

SAMG Ongoing

5 Undertake/update Asset Management maturity

assessment

SAMG April 2016

6 Condition assessments to be undertaken and

recorded against the discrete asset in the asset

register.

SAM Ongoing

7 Deliver objectives outlined in the Asset

Management Plan Operationalisation Project.

SAMG/AMIG/

Project Team

July 2017

8 Continue informing Elected Members and key staff

on Asset Management.

SAMG/SAM Ongoing