asset management plan 2012 - 2022
TRANSCRIPT
Asset Management PlanA 10 Year Management Plan for Westpower’s Electricity NetworkFrom 1 April 2012 to 31 March 2022
Westpower LimitedPO Box 375GreymouthWeb site www.westpower.co.nzPhone + 64 3 768 9300Fax + 64 3 768 27661st published March 1993
© Copyright: Westpower Ltd. 2012
This document is entitled to the full protection given by the Copyright Act 1994 to the holdersof the copyright. Reproduction of any substantial passage from this document is a breach of the copyright. This copyright extends to all forms of photocopying and any storing of material in any kind of informationretrieval system. All applications for reproduction in any form should be made to Westpower Ltd.
Plan compiled by: Asset Management Division
This issue approved by Westpower Board of Directors
March 2012
CONTENTS 1
Liability DisclaimerThisAssetManagementPlan(AMP)hasbeenpreparedandpubliclydisclosedinaccordancewiththerequirementsoftheElectricityInformationDisclosureRequirements2004andtheamendments2006.
SomeoftheinformationandstatementscontainedintheAMParecomprisedof,orarebasedon,assumptions,estimates,forecasts,predictionsandprojectionsmadebyWestpowerLimited(Westpower).Inaddition,someoftheinformationandstatementsintheAMParebasedonactionsthatWestpowercurrentlyintendstotakeinthefuture.Circumstanceswillchange,assumptionsandestimatesmayprovetobewrong,eventsmaynotoccurasforecasted,predictedorprojected,andWestpowermayatalaterdatedecidetotakedifferentactionstothoseitcurrentlyintendstotake.
Exceptforanystatutoryliabilitywhichcannotbeexcluded,Westpowerwillnotbeliable,whetherincontract,tort(includingnegligence),equityorotherwise,tocompensateorindemnifyanypersonforanyloss,injuryordamagearisingdirectlyorindirectlyfromanypersonusingorrelyingonanycontentoftheAMP.
When considering any content of the AMP, persons should take appropriate expert advice in relation to their owncircumstancesandmustrelysolelyontheirownjudgementandexpertadviceobtained.
2 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Contents
1.0 EXECUTIVE SUMMARY 41.1 PurposeofthePlan 4
1.2 ImprovementstotheAMP 4
1.3 Westpower’sNetwork 5
1.4 Westpower’sAssetManagement Process 5
1.5 AssetsCovered 9
1.6 AssetManagementPolicy 9
1.7 LevelsofService 11
1.8 ReliabilityTrends 11
1.9 SecurityofSupply 12
1.10 NetworkDevelopment 13
1.11 LifecycleManagementPlan 14
1.12 FinancialSummary 15
1.13 AssetManagementPractices 16
1.14 RiskManagement 18
1.15 PlanOutcomes 20
2.0 INTRODUCTION 21
2.1 Background 21
2.2 AssetOwnershipJustification 37
2.3 JustificationofAssets 37
2.4 AssetManagementDrivers 44
2.5 AssetManagementLinkage withWestpowerPerformance 45
2.6 PlanStructureandApproach 46
2.7 CoreandAdvancedAsset Management 46
2.8 AssetManagementSystems andProcesses 47
3.0 ASSETS COVERED 583.1 AssetCondition 58
3.2 TranspowerGXPs 61
3.3 SubtransmissionAssets 61
3.4 DistributionAssets 69
3.5 ReticulationAssets 75
3.6 Services 78
3.7 ZoneSubstations 79
3.8 DistributionSubstations 87
3.9 MVSwitchgear 92
3.10 SCADA,CommunicationsandProtection95
3.11 RippleInjectionPlants 98
3.12 OptimisedAssets 99
3.13 Generation 100
3.14 LoadandCustomerCharacteristics byGXP 100
3.15 VoltageSupportSystems 102
3.16 WestpowerMobileSubstation 103
3.17 SubstationBuildings 104
4.0 LEVELS OF SERVICE 1064.1 Introduction 106
4.2 Customer-OrientatedPerformance Targets 106
4.3 OtherTargets 114
4.4 JustificationforTargets 115
4.5 StakeholderNeeds 118
5.0 NETWORK DEVELOPMENT 1195.1 Introduction 119
5.2 PlanningCriteriaandAssumptions 119
5.3 PrioritisingNetworkDevelopment 123
5.4 LoadForecasting 125
5.5 DistributedGeneration 136
5.6 Non-NetworkOptions 140
5.7 NetworkDevelopmentOptions 141
5.8 NetworkDevelopmentProgrammes 144
CONTENTS 3
5.9 OverallWorkPlan 177
5.10 SubtransmissionAssets 181
5.11 DistributionAssets 186
5.12 ReticulationAssets 190
5.13 Services 194
5.14 Zonesubstations 195
5.15 DistributionSubstations 204
5.16 MVSwitchgear 206
5.17 SCADA,CommunicationsandProtection210
5.18 DistributionTransformers 214
5.19 Other 216
6.0 ASSET LIFECYCLE MANAGEMENT 2186.1 Introduction 218
6.2 MaintenanceandOperation 218
6.3 Disposal 221
6.4 MajorMaintenanceProjects 222
7.0 FINANCIAL SUMMARY 2287.1 FinancialForecasts 228
7.2 AssumptionsandSensitivityAnalysis 231
7.3 ActualDeviationsfromPreviousAMPs 234
8.0 ASSET MANAGEMENT PRACTICES 2418.1 Introduction 241
8.2 AssetManagementPolicy 242
8.3 Rationalisationofresponsibilities andprocedures 244
8.4 Networkservicesoperationalsupport 244
8.5 Informationsystemsdevelopment 244
8.6 Specifications,proceduresandmanuals 244
8.7 Deregulation/CompliancewithMEDand CommerceCommissionRequirements 245
8.8 AssetRenewalPolicy 245
8.9 CAPEXAnalysis 245
8.10 DistributedGeneration 246
8.11 AssetManagementSystem ImprovementProcess 246
8.12 DetailedFindings 250
8.13 AssetandWorksManagement SystemDevelopment 295
9.0 RISK MANAGEMENT PLAN 2989.1 RiskManagementPlanningFramework 298
9.2 RiskPlanningMethodology 298
9.3 FailureModeandEffects:Criticality Analysis 303
9.4 Safety 303
9.5 Environmental 304
9.6 KeyRisksIdentified 304
9.7 GeneralMitigationMeasures 306
9.8 WestCoastEngineeringLifelinesPlan: Survey2004/2005 306
9.9 TransmissionLines 307
9.10 Communications 309
9.11 DisasterRecovery 309
AppendixA: MainentanceActivity Definitions 311
AppendixB: CommerceCommisionCross ReferenceTable 315
AppendixC: NetworkReliabilitybyZone SubstationandFeeder 318
AppendixD: ExpenditureForecastand Reconciliation 322
AppendixE: GlossaryofTerms 323
4 WESTPOWERASSETMANAGEMENTPLAN2012-2022
1.0 EXECUTIVE SUMMARY
1.1 Purpose of the Plan
TheAssetManagementPlan(AMP)isafoundationdocumentthatdrivestheplanningforallworkundertakenonWestpower’sassets.Inparticular,itisakeyelementofWestpower’sassetmanagementframeworkandisusedtodemonstratecompliancewithgoodassetmanagementpracticeintermsoftheinternationalPAS-55standard.
Eachyear,acomprehensiveupdateoftheplaniscompleted,includingnetworkchangesthathavetakenplace.Furthermore,theresultsofaformal,externalpeerreviewprocessaretakenintoaccounttoensurethatthisplanmeetscurrentdisclosurerequirementsintermsoftheElectricityInformationDisclosureRequirements2008andiscontinuallyimproved,intermsofbothcontentandlayout.
1.1.1 PeriodCovered
ThisparticularplanwascompletedinJanuary2012andcoversaplanningperiodfrom1April2012throughto31March2022.Themainfocusisplacedonthenextthreeyears,withupdatesbeingcompletedannually.
This Executive Summary is prepared for peoplewhomay not be involvedwithin the business of electricitydistributionnetworksandassociatedservices,butwhounderstandandhaveaninterestinefficientmanagement.
ThisplanwasapprovedbyWestpower’sBoardofDirectorsonthe1stMarch2012.
1.1.2 ObjectiveoftheAMP
ThedefinedobjectiveoftheAMPis:
“Toprovideasystematicapproachtotheplanningofprogrammeswhichareintendedtoensurethattheconditionandperformanceof infrastructureassetsarebeingefficientlymaintainedor improvedtosatisfystakeholdersrequirements.”
1.1.3 CompanyMissionandStatementofCorporateIntent
Westpower’smissionistobe:
“AWest Coast Company operating successful businesses which provide first class electrical and technologysolutions,whereverourcustomerstakeus.”
Westpower’svisionistobe:
“Recognisedforexcellenceinalllinksoftheelectricityvaluechain.”
Salient statements fromtheStatementofCorporate Intent (SCI) that relate tomanagementofWestpower’sassetsinclude:
• TocontinuetoprovideWestCoastcommunitieswithasafe,secure,sustainableandcost-effectiveelectricitydistributionnetwork;
• ToensureobligationsundertheEnergyCompaniesAct1992,theElectricityAct1992,theElectricityIndustryReformAct1998andtheirvariousamendmentsandregulationsaremet;
• To continue to lobby on behalf of West Coast consumers to ensure that a reliabletransmissionnetworkismaintainedintotheWestCoast.
1.2 Improvements to the AMP
Westpower’sAMPfortheten-yearperiod1April2012through31March2022hasbeenthoroughlyreviewedandcomparedagainstotherElectricityLinesBusiness(ELB)plansandindustrycommentsandreports.
EXECUTIVESUMMARY 5
1.3 Westpower’s Network
This AMP includes Westpower’s assets that transport electricity (owned by the electricity retailers) fromTranspower’s sevenGrid Exit Points (GXPs) to over 13,000 electricity consumers on theWest Coast ofNewZealand’sSouthIsland.
TheWestpowernetworkconsistsof110kV,66kVand33kVsubtransmissionnetworkssupplying110/33/11kVsubstationsatReeftonandLogburnRoad,66/33/11kVsubstationsatDobsonandHokitika,66/11kVsubstationsatGreymouthandKumara,and33/11kVsubstationsatGlobe,Blackwater,PikeRiver,Ngahere,Arnold,Rapahoe,Ross,Waitaha,Harihari,Whataroa,Wahapo,FranzJosefandFoxGlacier.
Transpower’s seven GXPs supplyingWestpower’s networks are Reefton and Atarau at 110 kV; Greymouth,KumaraandHokitikaat66kV;Dobsonat33kVandOtiraat11kV.
Westpowerhasnetworkassetsthroughoutthe18,017squarekilometresoftheWestCoastfromLyell intheNorthtoParingainSouthWestlandwithatotalofsome40,000assetsin76classifications.
Thedistributionsystemcomprises2151circuitkilometresofhigh-voltageAlternatingCurrent(AC)distributionlines,21zonesubstationsandswitchyardsstrategicallylocatedthroughoutthenetwork(which,inturn,providean11kVsupplyfordistributionto2308distributionsubstations),onecontrolroomandatelecommunicationsnetwork.Figure1.1showsamapoftheWestpowernetworkareainrelationtotheotherSouthIslandELBs.Table1.2showsthenetworksummaryasat31March2012.
Westpower’sdistributionlinesconsistofvaryinglinecapacities,whicharedependentuponlocaldemandsandgeographicalconsiderations.Operatingvoltagesinclude110kV,66kV,33kVand11kV.Theselinesinvolvealargepopulationofpoles,transformers,disconnectersandotherassetsofvaryingtypesthatareessentialtothedistributionofelectricity.Figure1.4showsadiagramofWestpower’snetwork.
Both themanagement and themaintenance of the network is carried out by ElectroNet Services (based inGreymouth)asthepreferredcontractorandawhollyownedsubsidiaryofWestpower.TheAssetManagementDivisioncarriesoutallmanagementoftheassetsandrepresentstheassetowner.TheOperationsDivisioniscontracted toundertake the inspection, servicingand testing,alongwith fault calloutand fault repairwork.Majorlinereplacement,enhancementordevelopmentprojectsarealsoissuedtoElectroNetServicesasdesignbuildcontracts.Figure1.3showsaphotooftheirheadofficeinTainuiStinGreymouth.
1.4 Westpower’s Asset Management Process
Figure1.5illustratesWestpower’sassetmanagementprocess.TheassetmanagementpolicyprovidesthekeylinkagebetweenWestpower’sstrategicbusinessplanandtheassetmanagementprocess.ThisisconsistentwiththeSCIandisapprovedbytheBoardofDirectors.
6 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table 1.2 - Network Summary
Description Quantity
ConsumerConnections 13,032
NetworkMaximumDemand(MW) 50.52
NetworkDeliveries(GWh) *N/A
AnnualLoadFactor(%) 31
Lines&Cables(circuitkm) 2151
ZoneSubstations 21
DistributionSubstations 2347
NetworkOptimisedDepreciatedRe-placementCost($m) *N/A
Figure1.3-Westpower’sGreymouthHeadOffice
*Thesefiguresarenotavailabletilltheendofthefinancialyear.
Figure1.1-MapofWestpower’sNetwork
EXECUTIVESUMMARY 7
Figure1.4-Westpower’sNetworkDiagram
33kV11kV
PIKE
11kV
LOGBURN
AtarauSwitchingStation(ATU110)
11kV
33kV
11kV
BLACKWATER
66kV
DOBSON(ATU110)
NGAHERE
33kV
REEFTON(RFN110)
11kV
GLOBE
11kV
11kV
ARNOLD
G 3MW
3.3kV
66kV
11kV
GREYMOUTH(GYM066)
6.6kV
66kV
11kVOTIRA (OTI011)
11kV
33kV
66kV
HOKITIKA(HKK066)
ROSS
11kV
11kV
WAITAHA
HARIHARI
11kV
WHATAROA
WAHAPO
11kV
11kV
G3MW
FRANZJOSEF
11kV
11kV
FOXGLACIER
110kV
66kV
33kV
11kV
6.6kV
3.3kV
LEGEND
GXPs
TranspowerOwned
(HKK066)
TwoMileRoad
Kawhaka
Coleridge66kV
ArthursPass66kV
Ina
ng
ah
ua
11
0k
V
TRANSPOWER
TR
AN
SP
OW
ER
66kV
KUMARA(KUM066) 10MW
11kV
G
SwitchingStation
RAPAHOE
11kV
EXECUTIVESUMMARY 9
1.5 Assets Covered
Westpowerownselectricity reticulationassets thatareused toprovidedistributionandconnectionservicestoelectricityretailersandgenerators.TheseassetsgenerallycompriseequipmentthatiscommontoallNewZealand ELBs and,wherever possible, industry standard assets have been employed. In particular, theAMPcoverstheelectricityandassociatedsystemsownedbyWestpower,comprising:
• Subtransmissionassets–electriclinesandcables,includingassociatedeasementsandaccesswaysoperatingatvoltagesof33kVandhigher;
• Distributionassets–electriclinesandcables,includingassociatedeasementsandaccesswaysoperatingatavoltageof11kV;
• Reticulationassets–400Velectriclinesandcables,includingassociatedeasementsandaccessways;
• Services – connection assets at any voltage ownedbyWestpower for the purpose of supplying a singlecustomer(notincludingthelineonthecustomer’spremises).
• Zonesubstations–high-voltagesubstationsconnectedtothesubtransmissionnetwork.This includesallplant and equipment within the substations such as transformers, switchgear, structures and buswork,Supervisory Control and Data Acquisition (SCADA), protection and metering equipment, together withstationlandandbuildings;
• Distribution substations – substations connected to the distribution network. This includes plant andequipment within the substations such as fuses, platforms, lightning arrestors and maximum demandindicators,togetherwithlandandfibreglasscoversbutexcludingtransformers;
• MV switchgear – circuit breakers, reclosers, sectionalisers, regulators and disconnecters used in thedistributionandsubtransmissionsystems;
• SCADA,communicationsandprotectionequipment–SCADA,communicationsandprotectionequipment,and associated facilities not installed at zone substations. This includes control room equipment, radiorepeatersandfibre-opticsystemsinstalled,ownedandmaintainedbyWestpower;
• Distribution transformers–standard transformersused indistributionsubstations ranging from5kVAto1000kVAandgenerallyhavingaprimaryvoltageof11kV;
• Ripplecontrol–rippleinjectionequipment;
• Embeddedgeneration–generationunitsconnectedtoWestpower’snetworkbutnotnecessarilyownedbyWestpower;
• Capacitorunits–forvoltagesupport;
• Mobilesubstation–allowsimprovedmaintenanceaccesstoexistingsubstationsandforemergencyuseincaseofsubstationfailure;
• Buildings–substationbuildingswithintheWestpowernetwork.
WestpowerownsassetsthroughoutthelengthoftheWestCoastoftheSouthIsland,anditsareaextendsaboutasfarasthedistancefromChristchurchtoDunedin.
1.6 Asset Management Policy
Weare committed tomaximising our shareholders’ investments in a legally and environmentally compliantandsustainablemanner,withoutcompromisingthehealthandsafetyofouremployeesandconsumers,orthepublic.Weshallachievethisbyadoptingthefollowingpolicystatement.
Safety
• Safety-Safetyisofparamountimportanceineverythingwedoandwillnotbecompromisedforcost,timeoranyotherreason.
10 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Reliability
• Reliability of supply - Through continued investment in relevant technology and system configuration,reliabilitymustmeetapprovedtargetsatalltimes.
• Qualityofsupply-Qualityofsupply,commensuratewiththeloadtypeandcriticality,mustmeetWestpower’sstandardsRemedialactionwillbetakenwherestandardsarenotmet.
Security
• Securityofsupply–Thedesiredlevelofsecurityisdefinedbygoodindustrypractices,andlong-termplansmustbedevelopedtoachievetherequiredsecurity.
• Transpower–EveryeffortmustbemadetofocusTranspoweronsecurityofsupplyfortheWestCoast.
Sustainability
• Maintainservicepotential-ThefutureofWestpower’sbusinessiswhollydependentontheabilityofthenetworktocontinuetoprovideservicesfortheforeseeablefuture.Everyeffortmustbemadetomaintaintheongoingservicepotentialofthenetworkwhereappropriate.
• Supporting economic growth -We recognise the electricity infrastructure as a key enabler of economicgrowthandwillworkwithcurrentandfuturedeveloperstoprovideelectricitywiththecapacity,securityandqualityrequiredtosupporttheirbusiness.
• Continual improvement–Theassetmanagementsystemwillbereviewedonanannualbasisandwhereweaknessisfound,improvementswillbemade.CompliancewithPAS-55:2008shallbesupported.
• Strategicandlong-termplanning–Ourinfrastructurebusinessinvolveslong-terminvestmentsandwewillensureourdecisionsalignwithandsupporttheorganisation’sstrategicplan.
• New investment – Any new investmentmustmeet the shareholders’ expectations and approval wherenecessary.
• Communication – The requirements of the asset management system must be communicated to allstakeholderstoenablethemtobeawareoftheirobligationsandtoensuretheirexpectationsareconsideredinallaspectsofplanning.
Cost-efficiency
• Cost-efficiency-Allprojectsmustcompeteforfinancialresources.Prudentassetstewardshiprequirescarefulbudgetingandrobustfinancialreviewprocessestoensuremaximumcostefficiencyisassured.Opportunitiesfor improved productivity through training, technology, process improvements or othermeans shall beconstantlypursued.
• Energy-efficiency–Energy-efficiencyisencouragedinallareasofWestpower’sactivitiesandwillcontinuetobeakeyoutcomefromthedesignprocess.Whereopportunitiesexisttoenhanceenergy-efficiencyforexistingassets,theseareactivelypursuedandimplementedwheretechnicallyandeconomicallyfeasible.
• Technology-Technologyisseenasakeyenablerinprovidingimprovedserviceandvaluetoourconsumers.Wewillcontinuetokeepabreastofdevelopmentsinthefieldofnewandemergingtechnology,andapplythesetoWestpower’snetworkwhereappropriate.
• Fairpricing–Thepriceofelectricitytoconsumersmustbetransparentandfairtoallusersoftheassets.
• Capitalcontributions–Anyexpensefornetworkextensionstosupplynewloadswillbemetbyaconsumercontributiontowardsthecostsinvolved.
Environmental Impact
• Environmentalimpact-Westpowerisenvironmentallyresponsibleandcarefullyconsiderstheenvironmentalimpactofanyof itsactions. Furthermore,thecompanyworkshardtomitigateanynegativeeffectsandprovideanetenvironmentalbenefitwherethisispractical.
EXECUTIVESUMMARY 11
Risk Management
• Risk Management –Westpower adopts the AS/NZS ISO 31000:2009 standard in its approach to riskmanagementandhasagroupriskmanagementplanthat includesbusiness impactanalysisandbusinesscontinuityplanning. Theassetmanagement systemwill developa riskmanagementplan that is directlyrelatedtoWestpower’sdistributionassets.
1.7 Levels of Service
Westpower’sprimarybusinessistoprovideasecure,high-qualityelectricitysupplytoitsconsumersinacost-effectivemanner and to ensure that stakeholder’s interests aremet. To achieve theseobjectives,we are incontinuedconsultationwithconsumerstoensurethattheirrequirementsareconsidered.
Webelieve this consultationhas resulted ina strong focusoncontinuityof supply,which is reflected in thecomparisonofinternationalreliabilitymeasures(e.g.theSystemAverageInterruptionDurationIndexorSAIDI,withotherELBs).
Table1.6providesanoverviewofourperformanceinthekeyareasofservice.MoredetailedversionofthistableisshowninSection4(asTables4.3and4.4),whichbreakdowntheSAIDIandSAIFI(SystemAverageInterruptionFrequencyIndex)figuresintotheurban,ruralandremoteruralcategories.
ThetargetsshowninTable1.6arethesameasthosesetinthe2010-2011AMPandarebasedonnormaliseddatathatexcludeextremeevents,accordingtotheCommerceCommission’sdefinition.ThisapproachbetterrepresentstheunderlyingperformanceofthenetworkandprovidesforamoremeaningfulcomparisonwithotherELBs.
1.8 Reliability Trends
TheharshgeographicnatureandextremeweatherconditionsexperiencedontheWestCoastcancontributeto unpredictable supply outages.With this in mind, every effort has beenmade to mitigate these naturalenvironmental factors bymeans of protectiondevices such as automatic reclosers on distribution lines andlightningarrestorsonalldistributionsubstations.
Historicalreliabilitystatisticsindicatethatarelativelyhighnumberoffaultsareincurredduetotreestrikes.Forthisreason,anongoingandcomprehensivetree-trimmingprogrammehasbeeninstitutedtoreducethenumberofoutagesfromthissource.Figure1.7showsthereliabilitytrendsbasedon“tree-related”issuesonlyandtheimpactoftheprogrammesince2005-06.
Toassist inpreventingoutagesduringplannedmaintenance, contractorsareencouraged toemploy live linetechniqueswherepracticable.
Table 1.6 - Service Level Performance Summary
Service Criterion Quality Group Target Level of
Service Level of Service Indicator Measurement Process
Reliability Faults/100kmofcct 5.76 5.35 Figuresfortotalvaluesdis-closedinaccordancewiththeElectricityInformationDisclosureRequirements
2008
Westpowernetworkfaults,loggedasoutages
occur
TotalSAIDI 175 188
TotalSAIFI 1.99 2.62
TotalCAIDI 88 72
Efficiency CapacityUtilisation 30 31 %used Maximumdemand/transformercapacity
12 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure1.8belowdepictsWestpower’sreliabilitytrendoverthelastfiveyearsexcludingMajorEventDays(MEDs)asdefinedbytheCommerceCommission.
1.9 Security of Supply
Ingeneral,Westpower’ssecuritylevelsmeetacceptedguidelinesforloadsofthissizeandtype.
Forloadsof10MWandabove,ann-1securitylevelismaintained,sothatsupplycanbemaintainedintheeventofanysinglecomponentfailure.Forsmallloadsoflessthan1MW,nobackupisspecificallyprovided,exceptwherethereareconvenientlyavailablebackfeedsfortying11kVfeederstogether.
SupplytothecentralbusinessdistrictsofHokitikaandGreymouthissecure,withadequateredundancybuiltin,includingdiversecableroutes.
Figure1.7-NumberofVegetation-RelatedFaults
0
5
10
15
20
25
30
35
40
2006-07 2007-08 2008-09 2009-10 2010-11
No
. o
f Tree
Re
late
d F
au
lts
Year
Figure1.8-Westpower’sFour-YearReliabilityTrend(ExcludingMED’s)
0.0000
0.5000
1.0000
1.5000
2.0000
2.5000
3.0000
3.5000
0.00
50.00
100.00
150.00
200.00
250.00
2006-07 2007-08 2008-09 2009-10 2010-11
Min
ute
s L
os
t
Year
SAIDI
SAIFI
EXECUTIVESUMMARY 13
ThemajorrisktothesecurityofsupplytotheWestCoastlieswiththeTranspowernetwork.Therearetwolong,exposedtransmissionfeedsintotheWestCoastfromInangahuatothenorthviaReeftonandfromColeridgetotheeastviaOtira(seeFigure1.9),supportedbyTrustPowergenerationatpeaktimes.
Local generation has greatly reduced the riskof major system outages when a Transpowerfault occurs. Furthermore, the ability to use theWestpowermobilesubstationforplannedoutagesoramajorplantfaultprovidesadditionalsecurity.
TheTranspowerWestCoastGridUpgradeProject(WCGUP), which was approved by the ElectricityCommission* in 2008, will provide for additionaltransmission security to the West Coast throughtheconstructionofasecond110kVtransmissionline fromReefton toDobsonand installationofa14MvarcapacitorbankatHokitika.Thecapacitorbank was commissioned in May 2010, providingmuchneededinterimvoltagesupporttotheWestCoast. The second 110 kV transmission line fromReefton to Dobson and its associated equipmentwas commissioned in late 2011, significantlyimprovingthesecurityofsupplyinthearea.
Westpower losses, which stand at approximately5% of energy delivered, are managed throughoptimising conductors and transformers inaccordancewithgoodindustrydesignprinciples.
1.10 Network Development
AlthoughthekeydriverfordevelopmentoftheWestpowernetworkisdemand,systemsecurityisalsoamajorfactor.TheWestCoastareaiscurrentlyexperiencingrelativelyflateconomicgrowthfollowingabuoyantperiodoverrecentyears.ThePikeRiverminedisasterthatoccurredon19November2010hashadasignificantimpactonloadgrowthforecasts,andforthepurposesofthisplan,itisassumedthattheminewillnotrestartwithinthenexttwoyears.Notwithstandingthisimpact,underlyinggrowthinotherindustriescontinuestounderpineconomicperformanceinthearea.
To identify the future impact of this driver, load forecasting is carried out at the zone substation level inwhichthisiscriticaltoensuringthatsufficientcapacityisavailableinWestpower’ssub-transmissionandzonesubstation infrastructure. These forecasts are developedusing a zero-based approach from information andrequestsreceiveddirectlyfromcustomers,includingintelligenceonfutureloadtrendssuchasproposeddairyfarmconversions.AsummaryoftheresultsbymajorzonesubstationisshowninFigure1.10.Thisshowsthattheafterdiversitymaximumdemand(ADMD)is50.5MWandthatfuturedemandisexpectedtorisetoaround65MWby2021.
InWestpower’scase,mostofthesub-transmissioninfrastructurehasbeenbuiltwithinthelast25yearsandhasbeenprudentlydesignedtocaterforlikelyfuturedemand,whichmeansthatthereisusuallysufficientcapacitytocaterformarginalloadgrowth.Intheeventofproposalsformajornewloadscrystallising,eachcasewillbeconsideredbothinisolationandincombinationwithotherproposals,tomakesurethatanyimpactsonzonesubstationcapacityaretakenintoaccount.
Figure1.9-TranspowerFeedsfromReeftonandOtira.
KEY Substation
Subtrrans Line 33/66kV
Subtrans Line 110kV
BWR-IGH-A
DOB-BWR-A
AHA-DOB-A
GYM-KUM-A (Leased from Westpower)
KUM-KHA-A (Leased from Westpower)
AHA-OTI-A
ATARAUATARAU
BLACKWATERBLACKWATER
REEFTONREEFTON
DOBSONDOBSONGREYMOUTHGREYMOUTH
( WESTPOWER )( WESTPOWER )
HOKITIKAHOKITIKA( WESTPOWER )( WESTPOWER )
OTIRAOTIRA
ARTHURS PASSARTHURS PASS
KUMARAKUMARA
14 WESTPOWERASSETMANAGEMENTPLAN2012-2022
There isonemajorupgradeproject, tentativelyplannedfor2022, tocater for increasedgeneration inSouthWestland.ThisistheSouthWestlandGridUpgradeProject.
ThisprojectinvolvesupgradingasectionoftheHokitika-Harihari33kVlineto66kValongwithconversionoftheRoss,WaitahaandpossiblyHariharisubstationsto66kVoperation.ApossiblevariationtothisplaninvolvestheoptionofsupplyingtherelativelysmallWaitahaloadatalowervoltagefromnearbyRoss.Becauseofthepoorconditionoftheexistingasset,WestpowerhasalreadystartedtoreplacethepolestructuresbetweenRossandWaitaha,andisplanningtoreplacetheHokitika-Rosssectioncircuitby2012.TheWaitaha-Hariharisectionwillberefurbishedby2013.Thiswillbedoneinsuchawayastofacilitatefutureconversiontothehighervoltageifandwhenthisisrequired.
1.11 Life cycle Management Plan
Westpowerhasadoptedaprogrammetomanagethelifecycleofitsassetsfromdesignandplanningthroughtodisposal.ThemethodologyusedtoprioritiseprojectsisdescribedinmoredetailinSection6ofthisAMP.
Atypicallifecycleofanyassetconsistsofthefollowingstages:
• Designandplanning,
• Acquisitionandinstallation,
• Maintenanceandoperation,
• Disposal.
Forplanningpurposes,Westpowernowusesadecisionsupportsystemthatprioritisescapitalexpenditurebasedonanumberofkeydriverssuchasreliability,equipmentconditionandassetcriticality,andusesthisexpertsystemtoprioritisefutureinvestments.Thejustificationforusingthisapproachistheneedtohaveobjectiveassessmentsoftherelativeimportanceofeachprojectthatiscompetingforscarcecapitalresources.
Asfarasassessmentoffuturereliabilityperformanceisconcerned,probabilisticmethodsareusedfordistributedassetssuchasruraldistributionlines,whereasadeterministicapproachisstillusedforconnectionassetsfeedinglargeloadsasdiscussedinSection5.2.2
http://moss/asset/doc/amp/data/2012 AMP Data 26/01/2012
0
10
20
30
40
50
60
70
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
MW
Calendar Year
Load Trend(Actual/Forecast)
Dobson Greymouth Kumara Hokitika Reefton Otira Atarau
ADMD (50.5 MW)
Figure1.10-LoadTrend2000to2018ActualandForecast(IncludingLocalGeneration).
EXECUTIVESUMMARY 15
All equipment acquired and installed within Westpower’s network will be new, unless used equipment isacceptedbyWestpoweronanitem-by-itembasis.SuchequipmentwillbeacceptedonlyonconditionsspecifiedbyWestpower.
Maintenanceworkislargelybasedontheconditionoftheassets.Thereisanaturalbusinessdriverintheformoftaxbenefitstomaintainassetsratherthanreplacethem,andthisprovidesacountervailingforcetoapolicyofreplacingolderequipment,ensuringthatareasonablebalanceismaintainedbetweenthesetwoapproaches.
Decommissionedequipmentormaterialsareonlydisposedofwhentheyarenotrequiredascriticalsparesandthereisalowlikelihoodofthembeingrequiredinthefuture.
Themaindriversforthedecision-makingprocessindevelopingtheforwardworkprogrammeare:
• Reliability/securityandqualityofsupply,tomeetcustomerlevelsofserviceandcontractualobligations;
• Occupational health and safety, to establish a safeworking environment and complywith public safetymanagementrequirements;
• Regulatory,tomeetregulationsimposedbyexternalorganisations;
• Environmental,tocomplywithemissionregulationstoair,landandwater;
• Assetperformance/condition,tousehistoricaldatatoassesstheperformanceandconditionoftheassetsandtopredictpotentialremaininglife;
• Cost-efficiency,toensurethatmaximumcost-efficiencyisachievedinaccordancewiththeassetmanagementpolicy;
• Corporateimage,toensurethatanyactivitycarriedoutbytheassetmanagementteamandsubcontractorswillnotdamageWestpower’simage.
1.12 Financial Summary
Typically, 83%of currentmaintenance expenditure on network assets is scheduled in advance (i.e. plannedwork).Another5%ofmaintenanceisnotplannedbutisrequiredtobedoneasrepairstothenetwork’sassets.Theremaining12%ofmaintenanceexpenditureisforremedialwork(i.e.faultrepairs)torestorethenetworktoitsfullinitialservicepotentialfollowingtherestorationofsupplyafterafaultevent.
Capital expenditure typically represents 44%of the total AMP expenditure,whilemaintenance expenditurerepresentstheremaining56%.Table1.11showsthesummaryofforecastexpendituresforthe2013-2022period.
Noprovisionsforinflationhavebeenmadeinthesefiguresbutatransparentcontingencyhasbeenallowed.
16 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Tables1.11and1.12havealsobeenbrokendownintothecategorysub-groupsoffaults,repairsandinspection,serviceandtesting(I,S&T)formaintenanceexpenditure;andreplacement,enhancementanddevelopmentforcapitalexpenditure.
ActualcapitalexpenditurefortheyearendingMarch2011isclosetobudgetonceanumberofprojectsthatweredeferredbecausetheywereno longerrequiredare taken intoaccount.Baselinecapitalexpenditure infutureyearsis lowerthanpreviouslyforecastasaresultofanewfocusoncomponentlevelreplacementforsomeassets, wherebetterconditionassessment informationshows this tobeamoreappropriate strategy.Mostmajorreplacementprogrammesarecomingtoanendafterasustainedperiodofrenewal,andtheforwardcapitalworksprogrammereflectsthis.
1.13 Asset Management Practices
Westpowerisconstantlystrivingtofindmoreefficientwaystocarryoutitsdailyfunctions,byreducingcostsandimprovingproductivity.
The benchmark of best commercial practice is constantly moving, as demonstrated through the industryinformationdisclosureregime,whichlooksatfactorssuchaspriceandsupplyreliability.Therefore,Westpowermustbedynamicandinnovative,andthisculturestartswiththeBoardofDirectors,whichincludessignificantcommercialandfinancialexperience.
AkeystrategicgoalforthebusinessiscompliancewithPAS-55,aglobalspecificationforgoodassetmanagementpractice.Considerableprogresshasbeenmadeinthisarea,withWestpower’sassetmanagementpracticesnowassessedasbeing95%compliantwiththestandard.Section8ofthisdocumentoutlinesthecomplianceissuesindetail,alongwithagapanalysisshowingwherefurtherworkisneeded.Westpowerexpectstobefullycompliantwithinthenext12months.
Westpower encourages suppliers to improve their services and techniques continuously, and, at the sametime,negotiatescompetitivesupplyandmaintenancecontracts.AfullycommercialrelationshipexistsbetweenWestpower and its contracting subsidiary ElectroNet Services, which encourages price efficiency and highproductivitythroughcommercialdiscipline.
ElectroNetServicesprovidesassetmanagementservicestoWestpowerthroughtheassetmanagementgroup.AnumberofsystemsareemployedtooptimisethemanagementofWestpower’sassets.Theseinclude:
• Maximo®,proprietaryassetmanagementsoftwareproducedbyIBMtorecordandanalyseallofWestpower’sassets.Thisprovidesworkordersandfinancialtrackingalongwithassetvaluationmodules.
Table 1.11 - Summary by Category ($’000)
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
CapitalExpenditure 5962 2509 1804 2164 1979 2049 2292 2806 2782 2492
MaintenanceExpenditure 5023 5250 5410 5573 5701 5584 5818 6097 6406 6702
Total 10985 7759 7214 7737 7680 7633 8110 8903 9188 9194
Table 1.12 - Summary by Activity ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 4180 4361 4468 4580 4650 4477 4648 4862 5099 5323
Faults 541 571 607 641 680 717 759 803 850 899
Repairs 302 318 335 352 371 390 411 432 457 480
Replacement 2414 1235 611 881 727 842 669 1433 1374 1029
Enhancement 2111 260 246 188 228 203 543 164 223 194
Development 1437 1014 947 1095 1024 1004 1080 1209 1185 1269
Total 10985 7759 7214 7737 7680 7633 8110 8903 9188 9194
EXECUTIVESUMMARY 17
• ArcMap® Geographic Information Systems (GIS), to represent Westpower’s assets spatially, with toolsavailabletoprovideinformationsuchasoutagedata.TheGISisinterfacedtotheMaximosystem.
• RealFlex®SCADA,toallowrealtimedataacquisition,automationandremotecontrolofmanyofWestpower’soutstations.
• ETAP®Loadflowsoftwaretoanalysetheeffectofnewconnectionsandloadchangesonthenetwork.
• GentrackVelocity®(customerrelationshipmanagement)softwareisusedtointerfacetotheenergyretailersandMariaregistry,ensuringWestpoweriscompliantwithcurrentlegislation.Allcustomerdataarecollectedformassmarketandtimeofusemetering.
Theconditionofallequipmentisregularlyassessed,andequipmenttechnicalandconditiondataarestoredinacomprehensivedatabase.TheGISsystemisusedtopresentthesedatageographically.
Goodpracticemaintenancetechniquesareemployedwhereverpossibleandthecompanyregularlyexchangesinformationwithotherutilities.Furthermore,thetechnicalawarenessofstaffismaintainedthroughregularstafftrainingprogrammes.
1.13.1 AssetManagementSystemsandInformation
1.13.1.1Technology
Thebasictechnologyinvolvedinthetransmissionanddistributionofelectricalenergyhaschangedlittleoverthelast50years.Nevertheless,smallincrementalchangescontinuetobemadeinthematerialsemployed,leadingto improved performance and higher efficiency.Westpowerwill continue tomonitor these innovations andapplynewtechnologieswhereappropriate.
ThemajorimpactoftechnologyonWestpower’sactivitieswillbeintheareasofinformationtechnology,SCADAoperationofremotepiecesofplantandthepotentialimpactofdistributedgeneration.Bymeansofanongoingdistributionautomationprogrammetosupportthesetechnologies,Westpowerintendstocontinuallyimprovethereliabilityofitsnetworkbyreducingfaultrestorationtimes.
Inresponsetoalackofreliabledisconnectoractuatorproductsavailableonthemarket,Westpowerhasuseditsin-houseresourcestodevelopaninnovativeactuatorthatdeliversthekeyattributesofhighspeed,hightorqueandruggedreliabilityrequiredforthisspecificapplication.AlongwiththeSCADAandcommunicationssystem,thisallowsremotedisconnectorstobequicklyoperatedfromthecontrolroomoverradiolinks(whereasitcouldpreviouslyhavetakenuptoanhourormoreforfaultstafftoreachthesite),leadingtogreatlyreducedpoweroutagetimes.
Furthermore,aprogrammeofreplacingolder,unreliablereclosersandsectionaliserswithnew,highlyautomateddevices,supported,inmanycases,byhigh-speedwirelessradioconnections,iswellunderwayandisprovidingsubstantial benefits. The next stage of leveraging this technology investment tomove toward a smart-gridsolutionofself-healingnetworksisunderactiveinvestigation.
AGISallowsWestpowertovisualiseallaspectsofthenetworkspatially,includinganalysisoftheassetconditionandforwardworkcommitments.Inturn,thisallowsassetmanagementstafftomakeinformeddecisionsthatarecrucialtoachievingoptimalassetmanagementoutcomes.Additionally,theGIShasallowedWestpowertodevelopnewapplicationssuchasviewingthelocationoflightningstrikeswithinthenetworkareainnearrealtime,speedinguptherecoveryfromlightning-relatedfaultsandhelpingtoidentifylightning-proneareas.
Acomputerisedassetworksmanagementsystem(anIBMproductcalledMaximo®)isabest-of-breedsolutionthathasbeenintroducedtomaintainacompletemaintenancehistoryforeachassetandtoensurethatregularscheduledmaintenanceiscarriedoutwhenneeded.Thisincludesastructuredjobcostingsystem,whichensuresthatanycostsincurredonthenetworkareaccuratelyallocatedtotheappropriateassets.Thissystemdividesnetworkexpenditureintoappropriateactivities(namelyI,S&T;faults,repairs,replacements;enhancementsanddevelopment),aswellasassettypeandlocation.Detailedreportsincludingcapitalandoperatingexpendituremaybegeneratedatanytime.
18 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Whenmaintenanceisrequired,livelinemaintenancetechniqueswillbeusedwhereverpossibletoreducethenumberanddurationofpoweroutages.Westpower’s linecontractor is trained in live linegloveandbarriertechniques, and has all of the specialist equipment needed to provide a high level of repair service.Manymaintenancetasksinvolvingvoltagesfrom400Vto33,000Vcannowbecarriedoutwithouttakingthepowerofffromcustomers.
Newtechnologieswillcontinuetobeemployedwhereassetmanagementengineersaresatisfiedthatitcancost-effectivelyandreliablybeemployedtoimproveservicequalityandperformance.
1.13.1.2Information
Adequate and accurate information is a fundamental need in order to manage assets efficiently. Historicinformationabouttheassetscurrentlyinplaceexhibitedsomegapsbecausepreviousrecordswereinconsistentandlackedsufficientdetailinareassuchasequipmenttype.
Westpowernowhaspracticesestablishedforcontractorsto improvethis informationbycollecting“as-built”informationonsurroundingassetswheneversignificantworkiscarriedoutinthefield.Moreover,anongoingprogrammeofcollectingdatatoafinerlevelofgranularity,includinglowvoltageandserviceassets,ispayingdividends.
Accuraterecordsarealsobeingobtainedforallnewandreplacementworkcarriedoutonthenetwork.
1.14 Risk Management
Westpowerhas a separateRiskManagement Plan (RMP) completed as part of its overall business planningstrategy.Thisincludesbusinessimpactanalysisandbusinesscontinuityplanning.
Inaddition,WestpowerisactivelyinvolvedinaregionalLifelinesprojectlookingatwaysofmanagingtherisksinvolvedwithmajordisastersandensuringthatplansareinplacetodealwithmostofthelikelyscenarios.
Riskmanagementpracticeshavebeenembracedasameansofensuring thatall commercial risksare takenintoaccountandappropriatestrategiesareinplacetomanagetheserisks.Inthisway,thelong-termviabilityofWestpowerisprotected.
AfullRMPhasbeencompletedafteranin-depthlookatWestpower’soperationsandenvironmentinconjunctionwithriskmanagementconsultants.
Thefollowinggeneralriskcategoriesareconsidered:
• Futureplanning,
• Businessdevelopment,
• Operations,
• Contractormanagement,
• Financialmanagement,
• Staffmanagement,
• Occupationalhealthandsafety,
• Publicsafety,
• Emergencymanagement,
• Informationsystems,
• Informationmanagement,
• Environmental,
• Facilitiesmanagement,
EXECUTIVESUMMARY 19
Atallstagesthroughtheassetmanagementplanningprocess,Westpower’sstaffstrivestoreducetheimpactofsuchrisks.
1.14.1 BusinessContinuityPlan
The Business Continuity Plan is defined by each department and enables the re-establishment of normalprocessesandproceduresfollowingamajordisruptiveeventwhichresultsineitherthelossofbusinesspremises,resourcesorpeople.
1.14.2 EmergencyManagementTeam
TheEmergencyManagementTeam(EMT)hasStandardOperatingProceduresthatprescribetheappropriateprocessesandassignresponsibilitiesfortheconductoftheEMTintheeventofadisasterofsuchproportionsthatrequirescoordinatedcommandandcontrol.
1.14.3 HealthandSafetyManagement
Operatingandmaintaininganelectricalnetworkinvolveshazardoussituationsthatcannotfeasiblybeeliminatedentirely.Westpoweriscommittedtoprovidingasafe,reliablenetworkandahealthyworkenvironmentbytakingallpracticalstepstoseethatouroperationsdonotplaceourstaff,communityorenvironmentatrisk.Hazardoussituations are controlled through training, appropriate guidelines, andWestpower standards and operatingprocedures.Wealsorequirethatanyhazards,particularlyelectricalhazards,mustbetakenintoaccountwhennewnetworkinstallationsarebeingdesignedandconstructed.
UnderthenewElectricity(Safety)Regulations2010,Westpowerhasapositiveobligationtoinstituteapublicsafetymanagementsystemtoensurethathazardstothepublicareproperlyassessedandevaluatedandthateffectivemitigationplansareputinplace.Westpoweriswellalongthewaytohavingitssafetymanagementsystem,basedonNZS:7901,inplaceandreadyforauditbyApril2012.
1.14.4 EnvironmentalManagement
Westpoweriscommittedtoapolicyofenvironmentalsustainability,asdiscussedinitsEnvironmentalPolicy.
Thefollowingtopicsarecoveredinthispolicy:stakeholderconsultation,protectionofthebiosphere,sustainableuseofnaturalresources,reductionanddisposalofwaste,wiseuseofenergy,riskreduction,restorationoftheenvironment,disclosure,commitmentofmanagementresources,assessmentandannualauditing.
Oilspillmanagementsystemshavebeeninplaceformanyyearsnowand,todate,havesuccessfullymanagedanysignificantspills.ASF6monitoringprogrammeisalsobeingactivelypursuedtoreducetheriskofleakageofthisgreenhousegas,whichisusedinmosthigh-voltageswitchgear.
1.14.5 ImpactofNaturalDisasters
WestpowercommissionedareviewoftheWestCoastLifelinesstudyin2004andagainin2006toassesstheimpactofanaturaldisasterontheWestpowernetwork.Earthquakes,stormsandtornadosareWestpower’smajor natural disaster risks. Overall, the studies have concluded that there is a very high dependency oncommunicationsaswellasaclearneedtohavetheairportsandportsavailableaftertheevent.Anelectricitysupplywouldbeessentialforalmostallserviceauthoritiesintherestorationperiodfollowinganaturaldisaster.Sincetheoriginalstudyin2004,furtherdetailedstudiesandactionshavebeenimplementedtominimisetheoverallrisktothenetworkinacost-effectivemanner.
20 WESTPOWERASSETMANAGEMENTPLAN2012-2022
1.14.6 AssetFailure
Thefailureriskforallkeyassetshasbeenassessedbasedonknownpastperformance.Modernpartialdischargedetectiontechnologyhasbeenemployedtomanagetheriskofprematurefailureandtoplanforanend-of-lifereplacementstrategy,especiallywhere11kVmetal-cladswitchgearisconcerned.AregularDissolvedGasAnalysis (DGA) and Polarisation De-polarisation Current analysis (PDC) oil testing programme is carried outonWestpower’s zone substation transformers tomonitor their condition andhighlight potential issues. Thetwomajorassetclasses thatpresent thehighest riskof failureare the33kVand11kVmotorisedair-breakswitchesandDominionDropOut(DDO)fuselinks,andprogrammesareinplacetoupgradethesecomponentsprogressively.
Insulatorsoncriticaloverheadlinesarenowbeingcheckedwithacoronacamera.Thisisanewtechnologythatcanhighlightexcessivedischargeonlineinsulatorsthatisnotnormallydetectablebyothermeans.Itisbeingusedtodetectfaultsandtoassessthegeneralconditionofinsulators.
Allnewassetsthatareproposedforuseonthenetworkarethoroughlyvettedbyaninternalmaterialsevaluationgroupthatconsidersissuessuchassafety,technicalperformanceandlongevitybeforeapprovalfortheiruseisgiven.
1.15 Plan Outcomes
Themajoroutcomeofthisplanisaten-yearexpenditureforecastthatischaracterisedby:
• Arelativelyconstantlevelofinvestmentinnewconnectionsandextensionstothenetwork.Thisisbasedonanoverallmodestgrowthlevelwithpocketsofhighergrowthinspecificareas;
• Theongoingmaintenancecostofregulatorycompliancewiththetreeregulationsandadditionalrequirementsfortreeworkersafety;
• Materialcostincreasesthatarecontinuingtoaffectourconstructioncostsbecauseofthecombinedeffectofrawmaterialdemandandexchangeratefluctuations;
• Amoveawayfromreplacementstrategiestoamorefocussedandproactiveconditionassessmentregime,supported by repair and refurbishment programmes that reflect the very good overall condition of theexistingassets.Thisisreflectedinthereducingforwardcapitalexpenditurerequirement.
Thisdocumentispubliclyavailable,andwewelcomeconstructivecommentsandsuggestions.
Commentsmaybemadeinwritingto:-
RodgerGriffiths
GeneralManagerAssetsandEngineeringServices
WestpowerLimited
P.O.Box375
Greymouth7840
NewZealand
Email:[email protected]
INTRODUCTION 21
2.0 INTRODUCTIONThisisthe20thAssetManagementPlan(AMP)tobeproducedforWestpoweranditincludesonlyminorchangesfromlastyear,includingchangestoaddressthecommentsmadeintheCommerceCommission’sreviewoftheWestpowerAMPreportedin2011.SomeareasofnoteincludechangesinSection6tofocusontheplanningprocessesusedincreatingthenetworkdevelopmentplanand,inparticular,themethodologyusedtoprioritisedevelopments.Changeshavebeenmade to focusonmajorprojectsandprovide increaseddetail about theindividualprojectscopesandassociatedjustifications.
TheAMPdefinestheserviceobjectivesandgivesaclearfocusonlifecyclemanagementbypresentingoperations,maintenance and renewal policies, needs and programmes by asset type. The AMP processes adopted byWestpowerhavebeenchosentointegratebestpracticefeatureseffectively.Theseestablishtheservicestandardsandfuturedemandstomeetbusiness, legislativeandotherneeds,whiledevelopingoptimumlifecycleassetmanagement strategies, and resulting cash flowprojections, based on assessing non-asset solutions, failuremodes,cost/benefitsandrisk.
2.1 Background
2.1.1 PurposeStatement
ThepurposeofWestpower’sAMPistodocumenttheassetmanagementpracticesemployedbyWestpowerto strategicallymanage its assets and tomeet the requirements of the Electricity Distribution (InformationDisclosure)Requirements2008alongwithChapter4oftheElectricityInformationDisclosureHandbookissued31March2004andamended31October2008.
DeterminingofthelevelofcompliancewiththeaboverequirementsisassistedbyAppendixB,whichprovidesa cross-reference showingwhere the particular elements called for in the legislationmay be found. This isimportantbecausethedocumentisstructuredinsuchawayastogroupassettypestogether,ratherthantheactivitygroupingusedintheHandbook.Alloftherequiredinformationisprovidedtoahighlevelofdetail,butthecompliancereviewerisreferredtoAppendixBasameansofnavigatingthevarioussectionsofthisdocumenttodeterminewherethekeyelementsmaybefound.
Itisalsointendedforgeneralviewing,assuringWestpower’sstakeholdersthattheWestpowernetworkcontinuestobemanagedinaprofessionalandcost-effectivemanner.Figure2.1showsthebasisfortheassetmanagementsystemusedbyWestpower.
This AMP covers a period of ten yearsfrom the financial year beginning on 1April2012untiltheyearending31March2022. Themain focus of analysis is thefirst three tofive years; for this period,mostof thespecificprojectshavebeenidentified. Beyond this time, analysistends to be more indicative, based onlong-termtrendsanditislikelythatnewdevelopment project requirements willarise in the latter half of the planningperiod.Theseprojectrequirementsmaynotbedefinedhere.
Figure2.1-TheWestpowerAssetManagementSystem
22 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Toprovidea framework for assetmanagementwithin theplanningperiod, it is necessary todetermine thelonger-termdirectioninwhichthenetworkshouldbedeveloped.Forexample,itwouldnotbeprudenttoinvestheavily inenhancingasystemataparticularvoltage if,beyondtheplanninghorizonbutwellwithin the lifeofthoseassets,itislikelythattheywouldbeoverlaidbyanewhighervoltagesystem.Furthermore,strategicdevelopmentplanningmustberesponsivetoarangeofscenariosthatmightoccur.
ThisplanwasapprovedbyWestpower’sBoardofDirectorsonthe1stMarch2012
ThenextplanwillbepreparedandpublishedbyMarch2013.
2.1.2 ObjectiveofthePlan
ThedefinedobjectiveofthisWestpowerAMPis:
“ToprovideasystematicandcoordinatedapproachtotheoptimummanagementofWestpower’sphysicalassetsandtheirassociatedperformance,risksandexpendituresovertheirlifecycleforthepurposeofachievingtheorganisationalstrategicplanandtosatisfystakeholdersrequirements.”
2.1.3 RelationshipwithOtherPlanningDocuments
ItisimportantforstakeholdersthatthemannerandthebasisuponwhichthisAMPisintendedtooperateareclearlyunderstood.Forthepurposesofclarity,andinordertoavoidanyconfusion,thefollowingunderlyingassumptionsneedtobetakenintoaccountbythestakeholdersindealingwiththisAMP:
• ThisAMPinteractswithotherWestpowerworkingplans.Ofparticularimportancearetheannualbudgets,whichsetoutthespecificresourcesrequiredforassetmanagementactivities.Thosepartsof theannualestimatesrelatingtothemanagementofthesystemarebasedontheannualAMPs.
• AuthorisationofexpenditureresultsfromapprovaloftheannualestimatesbytheBoardofDirectorsandfromspecificapprovals.ThisAMPdoesnotrepresentanauthorisationbyWestpowerforexpenditure,nordoesitrepresentacommitmentonthepartofWestpowertoproceedwithanyspecificprojectsorprogrammes.
Figure2.2belowshowstheinteractionofthedifferentWestpowerplansandstakeholdersinvolved.
Figure2.2-RelationshipWithOtherPlansandApprovalProcess
INTRODUCTION 23
2.1.4 AssetsCoveredinthisPlan
This AMP includes Westpower’s assets that transport electricity (owned by the electricity retailers) fromTranspower’s seven Grid Exit Points (GXP) to over 13,000 electricity consumers on theWest Coast of NewZealand’sSouthIsland.
TheWestpowernetwork includes110kV,66kVand33kVsubtransmissionnetworks.The66kVnetwork issuppliedfromTranspowerGXPsatGreymouth,Hokitika,Kumara;the33kVnetworkfromDobsonandHokitika.An11kVsystemissuppliedfromTranspower’sOtiraGXPwhilstReeftonhasa110kVsupplyfromTranspower.
Westpowerhasnetworkassetsthroughoutthe18,017squarekilometresoftheWestCoastfromLyell inthenorthtoParingainSouthWestland,withatotalofaround40,000assetsin76classifications.
Thedistributionsystemcomprises2151circuitkilometresofAlternatingCurrent(AC)distributionlines,21zonesubstationsandswitchyardsstrategicallylocatedthroughoutthenetworkwhich,inturn,providean11kVsupplyfordistributionto2347distributionsubstations,onecontrolroomandatelecommunicationsnetwork.
Westpower’sdistributionlinesconsistofvaryinglinecapacities,dependentuponlocaldemandsandgeographicalconsiderations.Operatingvoltagesinclude110kV,66kV,33kVand11kV.Theselinesinvolvealargepopulationofpoles,transformers,disconnectorsandotherassetsofvaryingtypesthatareessentialtothedistributionofelectricity.
Themaintenanceofthenetwork iscarriedoutbyElectroNetServicesasthepreferredcontractor,which isawhollyownedsubsidiaryofWestpower.Theyarecontractedtoundertaketheinspection,servicingandtesting(I,S&T),alongwithfaultcalloutandfaultrepairwork.Majorlinereplacement,enhancementordevelopmentprojectsarealsoissuedtoElectroNetServicesasdesignbuildcontracts.
2.1.5 IssuesFacingWestpower
AMPsmustaddressgrowth.ProjectionsfortheWestCoastarecontinuallystudiedbyWestpowertoensurethatthecapacityandperformanceofthesubtransmissionanddistributionnetworksareadequateforthedemandandtypesofloadconnected.Thisplanprojectsthatthecurrenttotalloadofaround50.5MWwillbearound75MWintenyears’time.
Thisprojection isdependentonproposed industryprojectsproceedingbut in thecurrenteconomicclimate,thereisnocertaintyofthis.Forthisreason,thisAMPisfocussedonmaintaining(orimproving)thereliabilityofthenetworkandcateringforincrementalgrowthonthebasisthatlargerindustrialdevelopmentswillrequireproject-specificaugmentationsthatwillonlyproceedoncethevariousprojectsarecommittedandconnectioncontractsaresignedwithdevelopers.
KeyassetmanagementissuesfacingWestpowerare:
• Maintainingnetworkperformanceandreliability,includingsettingclearlydefinedservicelevelsandbackingtheseupwithcustomerguarantees(refertoSection4)
• Thecostofenvironmentalimprovementsandeasementsthatneedtobefactoredintoplanning;
• Decision-makingbetweenmaintenanceofassetsandtheirrenewalwillbeamajorpartofassetmanagement(refertoSection5)
• Acquiringrevenuefundingthroughapricingstructureatalevelthatisalsoacceptabletocustomers(refertoSection7)
24 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.1.6 Westpower’sOrganisationStructure
Westpower Limited is a stand-aloneElectricity Lines Business (ELB) witha contracting subsidiary, ElectroNetServices Limited. Westpower isessentially an electricity distributioncompany that is a shell or holdingcompany; however, it will continueto own the infrastructure assets. The100% owned subsidiary contractingcompany ElectroNet Services performsnot only work on the Westpowerinfrastructure assets but also the assetmanagement function under contractfrom Westpower. The structure of theWestpower Group is shown in Figure2.3.
• Mitton ElectroNet is based inChristchurchandistheresultofarecentmergerbetweenMittonConsultingandtheChristchurchofficeofElectroNetServices.MittonElectroNetLimitedis100%ownedbyElectroNetServicesLimited.
• AmethystHydroLimitedisajointventurecompanywithWestpower(88%ownership)andHarihariHydroLimited (12%ownership) tobuild, ownandoperate a6MWhydro schemeon theAmethystRivernearHarihari.
• ElectroNetTransmissionisarecentventureinvolvingtheacquisitionofABB’s linesdivisioninNelsonandGreymouthon1Aprilof2008.
ApartfromtheBoardofDirectors,aChiefExecutiveandtheWestpowerAssetManager,whoallworkdirectlyforWestpower,allotherstaffareemployedbyWestpower’ssubsidiaryElectroNetServices.
2.1.6.1 GovernanceandBoardApprovalProcesses
TheBoard sets thehigh-levelbusiness goals and strategies, and theChief ExecutiveandAssetManagerareresponsible for implementing them throughElectroNet Services. Inparticular, theBoard approves the assetmanagement policy that articulates the Board’s overarching expectations for management of Westpower’sassetsandthisprovidesavaluablegovernanceframeworkwithinwhichallassetmanagementactivitiesmusttakeplace.
TheAMP itself isapprovedby theBoardeachyearandprior to thestartof thefinancial year.This includesimplicitapprovalforallincludedprojectsuptoanindividualvalueof$50,000.
Allprojectswithavaluegreater than$50,000are subject toa furtherandseparateBoardapprovalprocessinvolvingthedevelopmentofaseparatebusinesscaseusingapre-definedtemplate.WhilefinancialmeasuressuchasNetPresentValue(NPV)andInternalRateofReturnareappropriateKeyPerformanceIndicators(KPIs)forsomeprojects,manyothersinvolvetheevaluationofkeydriverssuchasreliabilityofsupplyorhealthandsafety.MoredetailsareprovidedinSection6regardingtheparticularplanningcriteriathatareapplied.Theseprojectsmayonlyproceedafterspecificapprovalisgiven.
Financial Reports are provided to the Board on amonthly basis and these include budgeted versus actualexpenditureforallworkrolleduptotheoverallactivitylevel.Inaddition,individualjobcostreportsareprovidedforthemajorprojectsapprovedbytheBoardasdiscussedinthepreviousparagraph.
Fig2.3-WestpowerGroupCorporateStructure
INTRODUCTION 25
Exceptionreportsaretobeprovidedonallprojectswithavalueofmorethan$50,000thatexceed,orarelikelytoexceed,thebudgetedfigurebymorethan20%,includingthereasonsforthevariance.
2.1.6.2 BoardReport
Thefollowingadditionalreportsarealsoprovidedtotheboardeachmonth:-
• Billingstatistics-ThisreportshowstheallocationofsalesamongstthevariousretailersactiveonWestpower’snetwork,bytariffcategory.
• Network delivery performance - This shows monthly peak demands in megawatts and consumption inmegawatthoursforthecurrentyeartodateandtheprevioustwoyearsforcomparativepurposes.
• SAIDI - Amonthly progressive SAIDI report is provided in both tabular and graphical format, alongwithexplanationsofmajorevents.ThisreportshowsboththerawSAIDIstatisticsandthebaselineSAIDIresult,excludingMajorEventDays (MED’s)using the2.5betaapproachdevelopedby InstituteofElectricalandElectronicEngineers(IEEE).
• SAIFI-ThisreportisproducedingraphicalformatonlyandprovidessimilarinformationtotheSAIDIreportbutfocusesonSAIFI.
• Legislativecompliance-Areviewoflegislativecomplianceisprovidedtotheboardeachmonthandanynon-compliancesarenoted.
2.1.6.3 Westpower’sMissionandVision
MissionAWestCoastcompanyoperatingsuccessfulbusinesseswhichprovidefirst-classelectricaland
technologysolutions,whereverourcustomerstakeus.
VisionRecognisedforexcellenceinalllinksoftheelectricityvaluechain.
2.1.6.4 StatementofCorporateIntent
Salient statements fromtheStatementofCorporate Intent (SCI) that relate tomanagementofWestpower’sassetsinclude:
• TocontinuetoprovideWestCoastcommunitieswithasafe,secure,sustainableandcost-effectiveelectricitydistributionnetwork;
• ToensureobligationsundertheEnergyCompaniesAct1992,theElectricityAct1992,theElectricityIndustryreformAct1998andtheirvariousamendmentsandregulationsaremet;
• TocontinuetolobbyonbehalfofWestCoastconsumerstoensurethatareliabletransmissionnetworkismaintainedintotheWestCoast.
2.1.6.5 AssetManagementPolicyStatement
ThekeydocumentlinkingWestpower’sbusinessobjectives,asoutlinedintheSCI,withtheassetmanagementsystemistheAssetManagementPolicy,whichdefinesthehigh-levelpolicyobjectivesthattheBoardexpectsallassetmanagementplanningtoachieve.Assuch,itisanoverarchingdocumentthatisembeddedintheassetmanagementsystem.
26 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Thepolicyfollows:
Wearecommittedtomaximisingourshareholders’investmentsinalegallyandenvironmentallycompliantandsustainablemanner,withoutcompromisingthehealthandsafetyofouremployees,consumers,orthepublic.Weshallachievethisbyadoptingthefollowingpolicystatement.
Safety
• Safety-Safetyisofparamountimportanceineverythingwedoandwillnotbecompromisedforcost,timeoranyotherreason.
Reliability
• Reliability of supply - Through continued investment in relevant technology and system configuration,reliabilitymustmeetapprovedtargetsatalltimes.
• Qualityofsupply-Qualityofsupply,commensuratewiththeloadtypeandcriticality,mustmeetWestpower’sstandards.Remedialactionwillbetakenwherestandardsarenotmet.
Security
• Securityofsupply–Thedesiredlevelofsecurityisdefinedbygoodindustrypractices,andlong-termplansmustbedevelopedtoachievetherequiredsecurity.
• Transpower–EveryeffortmustbemadetofocusTranspoweronsecurityofsupplyfortheWestCoast.
Sustainability
• Maintainservicepotential-ThefutureofWestpower’sbusinessiswhollydependentontheabilityofthenetworktocontinuetoprovideservicefortheforeseeablefuture.Everyeffortmustbemadetomaintaintheongoingservicepotentialofthenetworkwhereappropriate.
• Supporting economic growth -We recognise the electricity infrastructure as a key enabler of economicgrowth,andwillworkwithcurrentandfuturedeveloperstoprovideelectricitywiththecapacity,securityandqualityrequiredtosupporttheirbusiness.
• Continual improvement–Theassetmanagementsystemwillbereviewedonanannualbasisandwhereweaknessisfound,improvementswillbemade.CompliancewithPAS-55:2008shallbesupported.
• Strategicandlong-termplanning–Ourinfrastructurebusinessinvolveslong-terminvestments,andwewillensureourdecisionsalignwithandsupporttheorganisation’sstrategicplan.
• New investment – Any new investmentmustmeet the shareholders’ expectations and approval wherenecessary.
• Communication – The requirements of the asset management system must be communicated to allstakeholders to enable them to be aware of their obligations and to ensure that their expectations areconsideredinallaspectsofplanning.
Cost-efficiency
• Cost-efficiency-Allprojectsmustcompeteforfinancialresources.Prudentassetstewardshiprequirescarefulbudgetingandrobustfinancialreviewprocessestoensuremaximumcost-efficiencyisassured.Opportunitiesfor improved productivity through training, technology, process improvements or othermeans shall beconstantlypursued.
• Energy-efficiency–Energy-efficiencyisencouragedinallareasofWestpower’sactivitiesandwillcontinuetobeakeyoutcomefromthedesignprocess.Whereopportunitiesexisttoenhanceenergy-efficiencyforexistingassets,theseareactivelypursuedandimplementedwheretechnicallyandeconomicallyfeasible.
INTRODUCTION 27
• Technology-Technologyisseenasakeyenablerinprovidingimprovedserviceandvaluetoourconsumers.WewillcontinuetokeepabreastofdevelopmentsinthefieldofnewandemergingtechnologyandapplythesetoWestpower’snetworkwhereappropriate.
• Fairpricing–Thepriceofelectricitytoconsumersmustbetransparentandfairtoallusersoftheassets.
• Capitalcontributions–Anyexpensefornetworkextensionstosupplynewloadswillbemetbyaconsumercontributiontowardsthecostsinvolved.
Environmental impact
• Environmentalimpact-Westpowerisenvironmentallyresponsibleandcarefullyconsiderstheenvironmentalimpactofanyofitsactions.Furthermore,thecompanyworkshardtomitigateanynegativeeffectsandtoprovideanetenvironmentalbenefitwherethisispractical.
Risk management
• Risk management – Westpower adopts the AS/NZS ISO 31000:2009 standard in its approach to riskmanagement and has a groupRiskManagement Plan (RMP) that includes business impact analysis andBusiness continuity planning. The asset management system will develop an RMP directly related toWestpower’sdistributionassets.
Legislation
• Legislativecompliance–TheAssetManagementSystem(AMS)mustmeet all relevant legislation. Where non-compliance issues areidentified,thesewillbedealtwithpromptlyandtransparently.
TheassetmanagementandplanningprocessesdiscussedthroughouttherestoftheAMPhavebeendevelopedtodirectlysupportthispolicyandmustadheretoit.
Theassetmanagementdivisionholdstherequisitetechnicalknowledgeandisresponsiblefortechnicaldecisionsregardingtheasset.Inaddition,thisdivisioniseffectivelythe“custodian”oftheassets,andtheirdutiesincludetakingresponsibilityforallperformanceandsafetyissues.
ThecompanystructureisshownintheFigure2.5andalsoinFigure2.6,detailingtheassetmanagementdivision.
2.1.6.6 CorporateStructure
Thekeyfunctionsofthegroupsare:
• BoardofDirectors
The Board provides overall governance of the Westpower group ofcompaniesandensuresthatthefollowingfourpillarsofgoodgovernancearemaintained(Figure2.4showstheprocessfor“Sign-off”bytheBoard)
1. Determinationofpurpose–Drivesthecompany’spurpose,goalsandstrategy.
2. Governanceculture–Ensuresoperationwithinahigh-performanceculture that deals effectively with the right issues in the rightmannerandencouragesdebateand candour. Itmaintainseffectiverelationshipswithshareholdersandotherstakeholders.
3. Holdingtoaccount–Holdsmanagementtoaccountthroughinformed,astute,effectiveandprofessionaloversight.
Figure2.4-ProcessforBoardSign-off
30 WESTPOWERASSETMANAGEMENTPLAN2012-2022
4. Compliance–Ensuresthecompanyisandremainssolvent,andensurestheprobityoffinancialreportsandcompliancewithregulatoryenvironments.
• CEO
The CEO oversees the financial performance of Westpower, management, the company secretariat andmaintenanceofrevenuestreams.
• GeneralManager–AssetsandEngineeringServices
The Manager oversees the network to maximise system availability. His/her duties include developingmaintenancestrategies,settingandmanagingpriorities,controllingstandardsandissuingworkorderstoensurereliabilityatminimumcost.He/shealsoactsasthekeycontactpointwithenergyandgenerationcompanieswishingtousetheWestpowernetworkforthedistributionofelectricity.
2.1.6.7 AssetManagementRoles
TheassetmanagementdepartmentisundertheoverallcontroloftheGeneralManager–AssetsandEngineeringServices.
Aseriesofteamleadersareresponsibleforthevariousactivitiescarriedoutbytheassetmanagementdivison.Therolesofeachoftheseteamleadersarediscussedbelow.
• SeniorElectricalEngineer
TheSeniorElectricalEngineerisresponsibleforsettingengineeringpolicyaswellasoverseeingallengineeringdesign. He/she is also responsible for reviewing non conformance in the network and ensuring that theappropriatestandardsareinplace.
• AssetSupportOfficer
TheAssetSupportOfficerisresponsibleforallmatterssurroundingthecollectionofmeteringdataandbillingofretailers.Thisincludesreconciliationactivities.
• NetworkManager-Lines
Thisroleinvolvesthemanagementofallhigh-voltage(HV)andlow-voltages(LV)linesassetsownedbyWestpower,includingcontrolandmanagementof theGeographic InformationSystem(GIS)andvegetationmanagementprogrammes.
• SCADA/CommunicationsEngineer
The SCADA/Communications Engineer is responsible for all of Westpower’s Supervisory Control and DataAcquisition (SCADA) and communication assets, including data communication in the network, and SCADAcontrolofsubstationsandswitchingassets.
• NetworkManager-Stations
TheNetworkManager -Stations looksafterall thezonesubstationsandnetworkswitchingassets, includingmaintenanceanddevelopment,andappliesthepoliciesdevelopedbytheSeniorElectricalEngineer.Thisrolealsoincludesresponsibilityforthecontrolroomandtheday-to-dayoperationsofthenetwork.
2.1.6.8 RelationshipbetweenAssetManagementandOperationsDivisions
TheassetmanagementdivisionassumestheroleoftheassetownerandisresponsibleformanagingtheinterestsofWestpowerand, inparticular,maintainingtheservicedeliverypotentialandperformanceofWestpower’sassets.
Theoperationsdivisionfulfilstheroleoftheserviceproviderandisresponsibleforcarryingoutallmaintenanceanddevelopmentontheassetsatthephysicallevel.
INTRODUCTION 31
The relationshipbetweenassetmanagementand theoperationsandfinancedivision isbasedonanarms’-lengthcontractbetweenWestpowerandtheoperationsdivisionofElectroNetServices,withassetmanagementeffectivelyactingasWestpower’sagentandbeingdirectlyunderthecontroloftheWestpowerassetmanager.
2.1.6.9 OperationsDivisionRoles
Withintheoperationsdivision,managersareresponsibleforparticularareasofworkasfollows:
• ElectricalSupervisor/ProjectManager
Thisroleisresponsibleforthetestroom,electriciansandelectricalfitterswithinzonesubstations.
• OperationsManager
TheOperationsManager isresponsibleforall linestaff, including linemechanicsandfaultstaff,alongwithasmallnumberoffitterswhoworkondistributionsubstations.
• OfficeManager/Accountant
ThisrolemanagesthebackofficefunctionsofElectroNetaswellasstoresandprocurement.
2.1.6.10BoardReport
2.1.7 Westpower’sStakeholders
Stakeholders aredefinedas thosepartieswithan interest inWestpower’s assetmanagement. Theprincipalstakeholdersare:
• Consumers;
• Shareholders(WestpowerisownedbytheWestCoast);
• ElectricPowerTrust,awhollyownedconsumerTrust;
• TheBoardofDirectors;
• Employees;
• Contractors;
• Retailers.
ThesecondarystakeholdersthatmayhaveaninterestoropinionintheaffairsofWestpowerare:
• Auditors,
• Governmentagencies,
• Suppliersandgenerators,
• Transpower,
• Landowners,
• Insurers,
• Financialinstitutions,
• Externaladvisors,
• Pressuregroups,
• Pressandmedia.
32 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.1.7.1 IdentificationofStakeholderInterests
Retailers and Customers
Westpowerhasliaisedcloselywithenergyretailerstodeterminetheexpectationsoftheircustomersandquantifytheseintermsofdesirablereliabilityindices.Westpowerhasconducteditsownconsultationwithits25largestcustomersanddiscussedalternativecombinationsofpriceandqualitythatmaybeavailabletocustomerswhocommittoacommercialcontract.
Massmarket customers have not expressed any dissatisfaction in the status quo combination of price andreliability.Someofthe25largestcustomershaveexpressedaninterestinpayingforadditionalreliability,mainlybasedonthecriticalityoftheiroperations.
Themaininterestsforretailersandcustomershavebeenidentifiedasreliabilityintermsofcontinuousavailabilityofsupply,restorationofsupplyandadequateshutdownnotification,aswellasreceivingtimelyandup-to-dateinformationifanoutageoccursonthenetworksothattheycanplanaccordingly.
OtherinterestsarethatWestpoweriscost-effectiveinitsservicedeliveryandprovidesagoodqualityofserviceintermsofbothmaintenanceandpowerquality.
Finally,stakeholderswishtobechargedafairprice,withsupportinginformationbeingmadeavailabletojustifythatprice.
Theseinterestsareaccommodatedintheplanby:
• TheSAlDlreliabilitytarget;
• Thegapanalysisonassetsegmentstoensureeachcustomerisreceivingthepromisedstandardofservice,andthetargetingofexpenditureaccordingly;
• Reinvestmentinrenewals;
• Strongcustomerconsultationcommitment;
• Directcustomerbilling,includingamoveawayfromenergy-basedtodemand-basedchargesforallcustomers;
• Supplypointand-density-basedpricingstructure;
• Customers’expectationsofgoodserviceatafairprice,aswellasacontinueddistributionbyshareholdertrusts;
• Theefficiencyofthecompanyasjudgedbycustomersbythesizeofthedistribution.
Retailers’ interests are identified through communication and direct discussion. Retailers are interested insellingenergytocustomerswithlittlebarrierstocompetition.TheirinterestsareaccommodatedintheplanbyWestpower’sdirectbillingprogramme.
Shareholders
Westpowershareholder’swishtoensure,asownersoftheassets,thattheirfinancialcapitalisprotectedinthelongtermbyensuringthattheoperatingcapabilityofthesystemisprotectedandthatthesystemismaintainedefficientlysothattheyearnanacceptablereturnontheirinvestment.
The shareholders also have an interest in howWestpower provides customer service and how itmeets itsobligationstootherparties(asdescribedbelow).
The interests of Westpower’s shareholders are identified through the SCI process and consultation withshareholders.Shareholdersareinterestedin:
• Anacceptablereturnbeingearnedfromtheassets;
• Anacceptablecashreturnfromthenetwork;
INTRODUCTION 33
• Thebusinessbeingsustainableinthelongterm;
• Areasonablestandardofservicebeingprovidedtocustomers;
• Thepricetocustomersbeingequivalenttothatchargedinotherruralareas;
• Customersatisfaction;
• Anetworkthatmeetsacceptableindustrysafetystandards.
Itisnotedthattheaboveinterestsarenotnecessarilyachievableintotalityifrevenuesarelimitedtobelowanacceptablereturn.
Theaboveinterestsareaccommodatedintheplanby:
• Therequirementthatanycustomer-drivendevelopmentworkcoversatleastitscostofcapital;
• Fundingdevelopmentworkthatisexpectedtoproducefuturerevenuebydebt,ratherthanreducingcashreturnstoexistingcustomers;
• TheSAlDlreliabilitytarget,i.e.strong,buttargetedre-investmentinrenewalstoprovidealong-termsafeandsustainablenetwork.
Westpower’sabilitytoearnanacceptablereturnonassets isconstrainedbytheneedforpricestability.Theorganisationcaneitherlimitinvestmentinnewcustomer-drivenworkifacceptablereturnscannotbeearnedor,alternatively,requireacapitalcontributionfromthecustomertocoveranyshortfall.Investmentinexistingassetsis,however,asunkcost.
Board of Directors
Westpower’ssharesareheldbytheWestCoastElectricPowerTrust(WCEPT)onbehalfofthecapitalbeneficiarieswhocomprisetheelectorswithinWestpower’sarea.Assuch,theWCEPTistreatedasthenominalshareholder,orownerofthebusiness,whichisadministeredbyaBoardofDirectors.
TheWCEPTisregularlykeptinformedofkeymattersthroughtheannualissueofanSCI,six-monthlyfinancialreports,andshareholders’newsletters.Eachyear,WestpowerandtheWCEPTmeettogetheraftertheirrespectiveAnnualGeneralMeetingstodiscussissuesofmutualinterest.Additionally,theChiefExecutiveorChairpersonwilloftenattendregularWCEPTmeetingswheninvitedtopromotegoodcommunicationandansweranyconcernsthatmayarise.
TheaboveinterestsareaccommodatedintheplanbyprovidingdirectreportingtotheBoardofDirectors intermsofannualbudgetproposals,majorprojectapprovals,monthlyfinancialreports,projectexceptionreportsandtheAMP.
Employees and Contractors
OtherpartieswithapotentialinterestinWestpower’sassetmanagementincludeworkers(includingcontractors)whophysicallyworkon thesystem; thepublic, throughwhose land thedistributionsystem isbuilt;andanyagencieswithwhichWestpowercomesintoregulatorycontact.
ElectroNetServices’assetmanagementteamhasresponsibilityfortheday-to-daymanagementofthecompanyanditsassets,andforcarryingoutcompanypolicies.Westpoweristhe“owner”oftheplan,whoisresponsibleforitscreationandforusingitasatoolforimprovingtheefficiencyandeffectivenessofmanagingWestpower’sassets.
Theinterestsofouremployeesareidentifiedthroughdirectdiscussionwiththemandtheirrepresentatives.Ouremployeesareinterestedin:
• Advancedknowledgeofworkrequirementssothattheycanplantheirlives;
• Asafenetworkandsafeworkingpracticessothattheyarenotharmed;
34 WESTPOWERASSETMANAGEMENTPLAN2012-2022
• Fairremuneration;
• Enjoyablework.
Theaboveinterestsareaccommodatedintheplanby:
• Thehighprioritygiventoeliminatingormitigatinghazards;
• Advancedplanningofwork;
• Therecognitionthatourstaffhaveuniqueskills;
• Creatingapositiveworkenvironmentthatcreatesahighlevelofself-worth.
Contractors’interestsareidentifiedthroughdirectdiscussion.Currently,theyareinterestedinhaving:
• Asecureworkprogrammeknownsufficientlyinadvancethattheycanplantheirresourceallocation;
• Asafenetworkandsafeworkingpractices,sothattheirstaffarenotharmed;
• Aprofitableworkstream.
Theaboveinterestsareaccommodatedintheplanby:
• Thehighprioritygiventoeliminatingormitigatinghazards;
• Advancedplanningofwork,includingcommitmenttoalong-termassetrenewalprogramme.
Thesecondarystakeholderinterestsareasfollows:
Auditors
• Systemsandprocessesmustbesuitabletomeetlegislationrequirements.
Government Agencies (this includes District and Regional Councils and Central Government).
• Processesareinplacetomeetcompliancerequirementsandreportingsystemsinplacetomeetdisclosurerequirements.
• DistrictCouncil interestsare identified throughdirectdiscussion.Currently, theyare interested inhavingsufficientinfrastructureavailablesothatgrowthintheirlocalcommunityisnothampered.
• The above interest is accommodated in the plan by the requirement that any customer-drivendevelopmentworkweundertakeproducesatleastourcostofcapital.
• RegionalCouncilinterestsareidentifiedmostlybycorrespondenceandwritteninformation.RegionalCouncilinterestsincludeprotectingtheenvironmentandemergencyresponse.
• Central government interests are identified mostly by correspondence, written information andlegislation.Centralgovernmentinterestsincludeensuringthatareliable,fairlypricedsupplyofelectricityisavailabletotheWestCoastregionandthatthenetworkissafe.
• TheinterestsofGovernmentagenciesarerecognisedthroughcomplianceandsubmissions.
Suppliers and Generators
Westpowerprovidesareliablenetworkthroughwhichtotransportenergy,sothatthenetworkhassufficientcapacitytoaccommodatetherequiredtransfersofenergy.ThechargesimposedinusingWestpower’snetworkareacceptableandthereisadequateaccesstoWestpower’snetwork.
Suppliersandgenerators’interestsareidentifiedthroughcommunicationanddirectdiscussion.Currently,thesegroupsareinterestedinprotectingtheirconnectedequipmentandtheelectricitysystemfromharmcausedbythenetworkandloadcustomerswhoareconnectedtotheWestpowernetwork.Westpowerisalsointerestedinreceivingrevenueandbeingchargedafairmarketpricefortransmissionservices.
INTRODUCTION 35
The above interests are recognised in the plan by the sums we have programmed for expenditure due toanticipatedgrowthindistributedgenerationandload.Asignificantproportionofthisistoensuretheprotectionofthegrid.
Transpower
Westpowerprovidesadequatemaintenancestandardstokeepthenetworkoperational.Thenetworkmustbereliable,andsufficientcommunicationshouldbemaintainedbetweenWestpowerandTranspower.
Transpower’s interestsare identifiedthroughcommunicationanddirectdiscussion. Currently,Transpower isinterestedinprotectionofitsgridandtheelectricitysystemfromharmcausedbygeneratorsandloadcustomerswhoareconnectedtotheWestpowernetwork.AnotherofTranspower’sinterestsisreceivingregulatedrevenuefromus.
The above interests are recognised in the plan by the sums we have programmed for expenditure due toanticipatedgrowthindistributedgenerationandload.Asignificantproportionofthisistoensuretheprotectionofthegrid.
Landowners
Issuesareidentifiedthroughdiscussionwiththeirrepresentatives(e.g.FederatedFarmers)andthepre-accessnotification process. Currently, they are interested in protecting areas of heritage value, protecting amenityvalue,havingtheirpropertytreatedwithrespect,protectingpropertyvaluesandhavinganelectricitysupplyatacompetitiveratewhichissuitablefortheactivitiesontheirland.Theseinterestsarerecogniseddirectlyandmanagedthroughstandardcustomerrelationshipapproaches.
Insurers
The interests of insurers are forWestpower to provide adequate risk management to meet the insurancerequirementsandtominimise riskswherepossible.These interestsaremetbyWestpowerhavingadequateinsurancesinplaceforidentifiedrisksandliabilitiestoemployees,assetsandthegeneralpublic.
Financial Institutions
Westpowershouldprovidesufficientfinancialperformancetocoverborrowingsandtomaintaintheircorporateidentitytoaconsistentstandard.TheseinterestsaremetbyWestpowerthroughreportingregularlyonfinancialperformanceandthroughregularaudits.
External Advisers
Theinterestsofexternaladvisorsincludecontinuityofwork,contractualrelationships(ifapplicable)andsafety.TheseinterestsaremetbyWestpowerthroughcommunicationwithrelevantpartiesasnecessary
Pressure Groups
Relevantinterestsincludepolicy,reliability,pricingandsafety.TheseinterestsaremetbyWestpowerthroughpubliclyissuedreports,andpressandmediareleases.
Press and Media
The interests of the Press and othermedia relate to news, public relations, alternative energy sources, theenvironment,informationchannelsandcrises.TheseinterestsaremetbyWestpowerthroughpubliclyissuedreports,andviapressandmediareleases.
36 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.1.7.2 ManagementofConflictingStakeholderInterests
Clearly,therewillbetimeswhentheindividualinterestsofvariousstakeholdersmaycreatepotentialconflicts,andWestpowertakesaconsultativeapproachbylisteningtotheconcernsofthepartiesinvolvedandtakingtheseintoaccountwhenmakingdecisions.
Theoverarchingdriversofprovidingasafeandreliablesupplyofelectricityatareasonablecost,whileensuringthat,whereverpossible,allstakeholdersaretreatedequitably, formaframeworkwithinwhichthebest-caseoutcomesaredetermined.Ofcourse,thiswillofteninvolvesomeformofcompromise,exceptwherehealthandsafetyissuesareconcerned.
WhereagoodcaseismadethatrequiresachangeintheAMP,thiscaneitherbereviewedduringtheyearifurgent,subjecttobudgetaryapprovalfromtheBoard,orincludedinthefollowingyear’sAMP.Insupportofthis,theassetmanagementdivisionmaintainsaregisterofrecommendedchangesthatare incorporatedintotheAMPeachyear.
Westpower’spolicy is thatnewconnections toWestpowernetwork shouldnotbe subsidisedby its existingcustomerbase,andthereforenewcustomersarechargedthefullcostofnewconnections.Thisistakenintoaccountwhendeterminingthebestsolutiontosupplyneworincreasedloads.
Communicationisthekeytoolusedtomanageresidualconflictbetweenstakeholders.Itisourexperiencethatwhenstakeholdershaveall the factsbefore them, theyarewilling toadopt thesolution that is for thebestoverallgood.Ourtaskistoensurethatstakeholdershavetherequiredlevelofinformation.
Examplesofhowconflictinginterestsaremanagedincludethefollowing:
1. Assetrenewal
OurshareholdersrequireinvestmenttoreturnWestpower’scostofcapital.Theyarenotwillingtolowercashreturnsreceivedinordertofundnetworkupgrades.Ontheotherhand,consumersareunwillingtomeethighprice increases.Bothgroupswantasustainablenetworkand improvements in reliability.Thisconflict ismetthroughatargetedrenewalsprogramme,whichensuresthatthenetworkdoesnotreceiveover-investment,andatargetedreliabilityprogrammetoensurethatreliabilitycontinuestoimprovewithoutasignificantincreaseinnetworkinvestment.Innovativepracticesalsoplayamajorpartinaligningtheseinterests.
2. Networkcapacitycharges
Historically,networkshavebasedchargesontransportedenergy,afixedcomponentand,perhaps,demand.Thecostoftransportingenergyalwayshasademandandfixedcomponent.Westpowerhaschangedthestructureofall linechargestobetterreflectcostsbyhavingseparatedemandanddedicatedassetcomponents.Inthemediumterm,energypassingthroughthemeterisusedtoestimatedemandusingacomplexalgorithm.Inthelong-term,itisproposedthatdemandmetersshallbeusedonallinstallations.
3. Contractorresourceconstraints
TheisolationoftheWestCoastmeansthatWestpowerisdirectlyreliantonthecapabilitiesandresourcesofitsmaincontractorforallworkontheassets.Attimes,thecontractormaybeover-committedduetootherworkwhenlargeexternalprojectsareunderway.ThisdichotomybetweenmaintainingWestpower’sassetstoahighstandardandmaximisingfinancialperformanceofthecontractorisresolvedthroughcarefulsupervisionoftheannualAMPprogressand regulardiscussionof forwardwork commitmentsat themanagement team level,includingstafffromboththeassetmanagementandoperationdivisions.Moreover,theChiefExecutiveretainsthepowertodirectthatprioritybegiventoassetworkasrequired,asaresultofhis/herdualroleofmanagingbothWestpowerandthecontractingsubsidiary,ElectroNetServices.
4. Safetyimprovements
ExperiencehasshownthatallofWestpower’sstakeholderswantasafenetwork.Determiningwhatissafeorunsafeisnotblackandwhite.Thedefinitionofwhatissafeandunsafeisconstantlyevolvingastimegoeson.Aseventsoccurandexpectationsadvance,safetycodesarerepeatedlyrewrittenandredrafted.Thismeansthatequipmentthatwasconsideredsafewheninstalled,isovertime,eclipsedbychangedandimprovedequipment.
INTRODUCTION 37
Whengrowthoccursinanetwork,equipmentisconstantlyreplacedandupdated.IntheWestpowernetwork,muchoftheoldlegacyequipmenthasnotbeenreplacedaspartofthenaturalgrowthcycle.Thisleadstoconflictbetween funding safety improvementworkandother renewalandCapitalExpenditure (CAPEX)work,alongwithdecisionsonthedefinitionofsafeandunsafe.Fortunately,muchoftherenewalassociatedwithsafetyalsoimprovessecurity,reliabilityandgeneralnetworkcapacity.Availableresourcestendtodominatetheconflictastohowmuchcanbedoneatonce.Theconflictbetweenwhatissafeandunsafeisbasedon:
• Observationsofobviousproblems;
• Industryaccidentreports;
• ThevariousActs,RegulationsandCodesthatcontroltheindustry;
• Theapplicationofongoingprinciplestohowequipmentoperatesandtherisksthatcomeaboutwhenthingsgowrong;
• Experiencefrominvestigatingandbeinginvolvedwithvariousindustryincidents.
5. Conflictbetweencustomerinterestsascustomersandshareholders
As shareholders, customersgeta return. Somecustomerswouldprefer lowerupfront chargesor to see themoneyreinvestedinthenetwork.WebelievethatthisistheresponsibilityoftheTrustees,whoareelectedbyourcustomers,toresolvethisconflictbyconsultationandadvisethecompanythroughtheSCIprocess.
2.2 Asset Ownership Justification
2.2.1 WestpowerYesterday
Inthelate1800stotheearly1900s,privatepowergeneratingschemeswerebeingbuiltthroughouttheWestCoast region, mainly to supply gold claims. Reefton was the first public supply connected in the SouthernHemisphereinDecember1887.OthersupplieswereatDillmanstownandKaniereintheHokitikaarea.
2.2.2 WestpowerToday
Westpower isacombinationofanumberof theearlypowercompaniesandgeneratorson theWestCoast.In 1972, theWestCoast Electric PowerBoardwas formedby the amalgamationof theAmethyst,Grey andWestlandElectricPowerBoards.
2.2.3 WestpowerTomorrow
AMPsmustaddressgrowth.ProjectionsfortheWestCoastarecontinuallyreviewedbyWestpowertoensurethatthesubtransmissionanddistributionnetworkisadequateforthedemand.
2.3 Justification of Assets
The sub transmissionanddistribution componentsof theWestpowernetworkhaveevolvedover anumberofyears,withtheincreaseofcustomerdemandintheregionbeingtheprimarydriver.ThelargeareaoftheWestCoastforwhichWestpowerisresponsible,coupledwiththediversegeologyencountered,hasresultedinstrategicallyplacedassetsthroughouttheregion,thatgenerallyprovideareliablesupplyandofferscalabilityforthefuture.
ManyofWestpower’slinescanbeverylongandtraverseextremelyruggedterrain,oftentosupplyverylightlypopulatedareas. Toensure that supplymeets customers’ requirements, these lineshavebeendesigned toreducelinelosses,andvoltagesupporthasbeenstrategicallyemployed.
Thecontinualloadincreasesin“remote”areassuchastheGlaciertownships(FoxandFranz),andthegrowthinindustrialloadssuchasmininganddairyfarmingareconsiderationswhenasubtransmissionordistributionassetisrefurbished,withrefurbishmentcostssometimesbeingsharedwithlargercommercialentities.
38 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Thelast10to15yearshaveseenapushtoensurethatassetsareuptothetaskexpected,withanextensiverenewalandreplacementprogrammeupgradingthevastmajorityofsubtransmissionanddistributionassets.
2.3.1 JustificationofGXPs
Connection/SupplyPoints
Westpowerownsthreedistinctclassesofsubtransmissionassetsrunningat110kV,66kVand33kV,emanatingfromsevenGXPpoints,withanadditionalGXPatOtiraprovidingan11kVsupply. TheprimaryGXPscanbefoundatDobson(33kV),Greymouth(66kV),Hokitika(66kV),Kumara(66kV),Reefton(110kV)andAtarau(110kV).DetailsofthecapacityandloadprofileforeachoftheGXPscanbeseeninTable3.4inSection3.
ThejustificationsforeachoftheseGXPsaredescribedbelow:
2.3.1.1 DobsonGXP
The Dobson 33 kV supply point provides capacity tosupply the Westpower network northwards to NgahereSubstation, the main supply point for the Ngahere GoldDredgingoperationandtheRoaCoalMine.EastofDobsonis the Arnold substation, which supplies the CMP KokiriMeatworksandalargefarmingarea,andalsoallowsfortheconnectionof Trustpower’s 3MWArnold generation. Thenorthwestern section of theDobsonGXP connects to theRapahoe substation, which supplies Solid Energy’s SpringCreekMineandtheCoastRoadarea.ThesesubstationsaresuppliedbytheDobsonGXP’sthree33kVfeeders.
TheDobsonGXPalsoconsistsoftwo11kVfeedersprovidingsupply to Dobson, Kaiata, Taylorville, Stillwater and CoalCreek.
ThisGXPwastheprimaryGXPfortheGreymoutharea,butwassituatedtoofarfromGreymouthtosupplythegrowingloadinthatarea;theGreymouthGXPwasthereforeconstructedinthelate1970s.
ThisGXPisessentialforsecurityofsupplyintheaforementionedareasaswellassupportingtheGreymouthGXPfromtimetotime.
2.3.1.2 GreymouthGXP
Supplying the greater Greymouth distribution networkfrom seven 11 kV feeders, the Greymouth 66 kV GXP issupplied primarily from theGYM-KUM66 kV cct and theTranspower’sDOB-GYM66kVcct.ThisGXP isrequiredtosupplythelargestdomesticloadontheWestCoast,aswellas significant industrial loads such as engineering, fishingandtimbermilling.
As theGreymouth loadhasgrownsignificantly in the last30 years, an independent GXP is required to satisfy thedemandpresentinthisarea.
Figure2.8-GreymouthGXP
Figure2.7-DobsonGXP
INTRODUCTION 39
2.3.1.3 HokitikaGXP
AswellassupplyingthegreaterHokitikadomesticload, there are large number of industrial, dairyfarmingand tourism-driven loadsemanating fromtheHokitikaGXP.IncludedintheseistheWestlandMilk Products Hokitika processing factory. ThisGXPisgeographicallythelargestintheWestpowerarea,supplyingtheSouthWestlandareatoParinga(some200kmaway)andtheflatsoftheKokatahi-Kowhitirangiarea.TheHokitikaGXPconsistsoften11kV feedersandone33kV feeder that suppliesSouthWestland.
Constructed in 2002, the Hokitika GXP wascommissioned due to the increasing demand intheareaandthedecommissioningofTranspower’sArahurasubstation.Withthisinmind,coupledwiththedistancebetweenGXPs, theHokitikaGXPwasdeemedtobeessential.
2.3.1.4 KumaraGXP
The Kumara GXP is mainly required to provide aGrid InjectionPoint (GIP) forTrustpower’s10MWKumara hydro scheme, but also supplies localload, via two 11 kV feeders, in the area betweenGladstoneinthenorthtoJacksonsintheeastandtoDuffers in the south.Apart from the significantgeneration, the load type is mainly farming andrural residential, although the IPL Plywoodmill atGladstonedemandssignificantload.
ThecloseproximityofTrustpower’shydroschemeis theprimary reason that theKumaraGXPexists.Without this injection, the Kumara area couldpossiblybesuppliedfromanalternateGXP.
2.3.1.5 ReeftonGXP
TheReeftonGXPsuppliesloadviatwo11kVfeedersbetweenLyell inthenorth,Berlins intheeastandBlackwatertothesouth.Theloadischaracterisedmainlybydairyfarminganddomesticload,althoughthere is somemining and commercial load in thetownofReefton.
TheReeftonGXPalsosuppliesBlackwatersubstationto the south and theOceanaGoldGlobemine totheeastviatwo33kVfeeders.
The distance from an alternate GXP deems theReeftonGXPnecessary,and thisGXP is integral insupplyingWestpower’snorthernnetwork.
Figure2.10-KumaraGXP
Figure2.11-ReeftonGXP
Figure2.9-HokitikaGXP
40 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.3.1.6 AtarauGXP
TheAtarauGXP is primarily to supply thePRCCCompany (PRCC)miningoperation,withone110kV feedersupplyingLogburnsubstation.
PRCC’sloadrequirementsaresignificantandcouldnotbesuppliedwithoutthisGXP.
TheAtarau switching station is ownedby Transpower,withother connectionassets, including transformers,beingsuppliedbyWestpower.
2.3.1.7 OtiraGXP
TheloadatOtiraistotallyisolatedfromotherGXPs,and,apartfromasmallhotelandafewhouses,themajorityoftheloadconsistsofthefanmotorsfortheOtirarailtunnel.Thisloadissuppliedfromasingle11kVfeeder.
AlthoughtheloadinOtiraisrelativelysmall,theisolationoftheareafromotherpartsofthedistributionnetworkmeansthattheOtiraGXPiscriticaltosupplythearea.ThisincludesthecriticaltunnelloadneededtosupportthecoalexporttradefromSolidEnergy’sWestCoastoperations,withnoalternativesourcebeingavailable.
TheOtirasubstationisownedbyTranspower.AnupgradeofthisGXPwascompletedin2010/11.
InadditiontothesevenGXPslistedabove,Westpowerhasafurther14zonesubstations.
2.3.2 JustificationofZoneSubstationAssets
The justification foreachof thesezonesubstations isasdescribedbelow:
2.3.2.1 BlackwaterZoneSubstation
CommissionedinDecember2009,thetwo11kVfeedersatBlackwaterzone substation primarily supply the PRCC coal load-out facility atIkamatuaaswellastheareafromMawheraitidowntotheAhauraPlains,whichpredominantlyincludesdairyfarming.TheBlackwaterzonesubstationhasbeenbuiltdue to the increaseddemand fromthecoalload-outfacility,whichcouldnotbesuppliedfromeithertheReeftonorNgahere11kVnetworks.
Anolderrefurbishedtransformerofoptimumcapacitywasusedforthisprojecttoallowforfuturegrowthwhilebeingcost-effective.
TheBlackwatersubstationcanalsoprovidebackupsupplytoNgahereandReefton,whenrequiredformaintenanceandfaults.
2.3.2.2 NgahereZoneSubstation
Thetwo11kVfeedersatNgaherezonesubstationsupplyanareafromAhaurainthenorth,downtheGreyValleyincludingRoaandBlackball,andinlandeastasfarasNelsonCreek.NgaherezonesubstationprimarilysuppliestheNgaheregolddredgeoperationandtheRoaCoalMine,aswellastheNgahereprocessingmill,NelsonCreekabattoirsandnumerousdairyfarms.TheNgaherezonesubstationisideallylocatedduetoitsproximitytoitsprimaryloads.
Figure2.12-BlackwaterZone
INTRODUCTION 41
2.3.2.3 ArnoldZoneSubstation
Situated next to Trustpower’s Arnold power station, thetwo 11 kV feeders at Arnold zone substation supply theCMPKokiriMeatworksandalargefarmingareaincludingseveralLandcorpdairyfarms,coveringanareafromKokiriinthewest,fromMoanatownshiptoInchbonnieintheeastandasfarasHaupiritothenorth.ArnoldzonesubstationalsoprovidesTrustpoweraconnectionfortheirgeneration(3MW)intoWestpower’snetwork.Duetofurthergrowthindairyfarming,especiallyLandcorp’sfarms,developmentinMoanatownshipandtheabilitytoprovideaconnectionpoint for Trustpower’s Generation, the Arnold zonesubstationisanecessaryasset.
2.3.2.4 RapahoeZoneSubstation
CoveringanareaalongtheCoastRoadareatoPunakaikiinthenorthdowntoCoalCreek inthesouth, includingthe townships of Barrytown, Runanga, Rapahoe andDunollie, the two 11 kV feeders at Rapahoe zonesubstation’s primary supply is to Solid Energy’s SpringCreek Mine at Dunollie and the abovementionedtownships. Thedistanceandhigh costs associatedwithsupplyingtheCoastRoadareafromDobsonviaan11kVlineandthedemandatSpringCreekdeemtheRapahoezonesubstationtobecriticaltosupplythisarea.
2.3.2.5 RossZoneSubstation
TheRosszonesubstationwasbuiltin1995duetothe66kVlinebetweenArahuraandHariharibeingchangedtoa33kVline.PrimarilysupplyingBirchfield’sRossminingoperationandRosstownship,thetwo11kVfeedersalsosupplyanumberof farms inthearea,coveringanareathat runs from just south of Ruatapu, including TotaraValley,as farsouthtoMikonui.Becauseof thedistanceandhigh costs associatedwith supplying theRoss areafromHokitika via an 11 kV line, the Ross Substation isideallylocated.
2.3.2.6 WaitahaZoneSubstation
Supplying primarily a farming area, the one 11 kV feeder atWaitaha Zone Substation covers the areas ofFergusonsBush,Kakapotahi,WaitahaValleyandPukekura,whichincludesthePukekuraHotel,theWildernessTouristCentreandKordia’sradiosite.LikethezonesubstationatRoss,theWaitahazonesubstationwasbuiltin1995.TheremotenessandhighcostsassociatedwithsupplyingtheWaitahaareafromRossorHarihariviaan11kVlinemakestheWaitahazonesubstationnecessaryatitscurrentlocation.
Figure2.13-ArnoldZoneSubstation
Figure2.14-RapahoeZoneSubstation
42 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.3.2.7 HarihariZoneSubstation
The Harihari zone substation was built in 1995 due tothe decommissioning of the Transpower switchyard onWanganuiFlatRoad.Supplyingprimarilyafarmingarea,the two 11 kV feeders at the Harihari zone substationcoveranareafromLakeIantheinthenorthtothePoeruaValley in the south, including the township ofHarihari.Due to the remoteness and high costs associatedwithsupplying theHarihari area fromWaitaha orWhataroaviaan11kVline,theHariharizonesubstationisrequired.
2.3.2.8 WhataroaZoneSubstation
Also supplying primarily a farming area, the one 11 kVfeederattheWhataroazonesubstationcoverstheareasofTeTaho,WhataroaFlatandWhataroatownship.Theremoteness and high costs associated with supplyingtheWhataroaarea fromHarihari via an11kV lineandisolation requirements for faults/maintenance on the33 kV circuit between Harihari andWahapo make theWhataroazonesubstationnecessary.
2.3.2.9 WahapoZoneSubstation
The Wahapo zone substation is located next toTrustpower’sWahapopowerstation.Itsone11kVfeederprimarilysuppliestheOkaritoareaandallowsTrustpowertohaveaconnectionfortheir3MWWahapogeneratorintoWestpower’snetwork.
2.3.2.10FranzJosefZoneSubstation
PrimarilysupplyingthetourismindustryintheFranzJoseftownshipandthefarmingindustryinthearea,thetwo11kVfeedersattheFranzJosefzonesubstationcoveranareafromWaihoFlatinthesouthtoLakeMapourikainthenorth.FranzJosefZoneSubstationisnecessarytocaterfortheexpansionoftheFranzJoseftownshipduethegrowthinthetourismindustryintheGlacierregion.
2.3.2.11FoxZoneSubstation
TheFox33kVzonesubstationwasbuilt in2003duetotheexpansionoftheTourismIndustry inFoxGlacierTownship.Theone11kVfeederattheFoxzonesubstationcoversalargeareafromtheFoxTownshipandCookFlatsinthenorthtoLakeParingainthesouth.LikethatofFranzJosef,FoxzonesubstationprimarilysuppliesthetourismindustryintheFoxGlaciertownshipandthefarmingindustryinthearea.Withthetourismindustrystillexpanding,thevastnessandremotenessoftheareadeemstheFoxzonesubstationtobenecessary.
Figure2.16-WhataroaZoneSubstation
Figure2.15-HarihariZoneSubstation
INTRODUCTION 43
2.3.2.12GlobeZoneSubstation
Thethree11kVfeedersandone6.6kVfeederattheGlobezonesubstationareforsupplyingtheOceanaGlobe Gold Mining operation outside of Reefton.DuetothedemandoftheOceanaGlobeGoldMineand the distance from Reefton, the Globe zonesubstationiscritical.
2.3.2.13LogburnZoneSubstation
Thethree11kVfeedersatLogburnzonesubstationprimarily supply the coal processing plant, bath-house and workshop for the PRCC, and alsosupplya33kVsupplytothePikezonesubstation.As well, Logburn zone substation also covers thepredominantly dairy farming area of Atarau fromCraigeburn toMoonlight. The demand fromPRCCandtheexpandingdairyfarmingintheGreyValleyarea deems the Logburn Zone Substation to benecessary.
2.3.2.14PikeZoneSubstation
Theseven11kVfeedersatthePikezonesubstationare for the supply associated with PRCC’sMiningoperations. The underground operations of themine and the associated surface operations PRCCrequired the substation to be built at its currentlocation. Due to the recent incident at the PRCCmine, a review of this substation’s requirementsmayberequiredinthecomingyear.
2.3.2.15 SpringCreekZoneSubstation
The Spring Creek 33 kV substation supplies SolidEnergy’scoalminingoperationsatSpringCreek.Thesubstationhastwo6.6kVandone3.3kVfeeders.Thesubstation issuppliedbya33kV feeder fromDobsonGXP.
TheSpringCreekzonesubstationisownedbySolidEnergy.
Figure2.18-GlobeZoneSubstation
Figure2.17-LogburnZoneSubstation
Figure2.19-PikeZoneSubstation
44 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.3.3 Justificationof110kVSub-transmissionLines
2.3.4 Justificationof66kVSub-transmissionLines
2.3.5 Justificationof33kVSub-transmissionLines
2.3.6 JustificationofDistributionandReticulationLines
Theselineshavebeeninstalledhistoricallytosupplyconsumers,bothasindividualsandgroups,andthegenericjustificationiscustomerdemand.
2.4 Asset Management Drivers
The factors that drive assetmanagement activities and their relationship toWestpower’s performance arederivedfromtheexternalperformancerequiredofWestpowerbyitscustomers,workers(includingcontractors),shareholdersandthepublic.
Thedriversforthisplanareasfollows(thesearecoveredinmoredetailinSection4-LevelsofService):
• Safety,
• Customerservice,
• Capacity(i.e.adequacyofservice),
2.20 Justification of 110 kV Lines Sub-transmission
Asset Use Length Optimum Justified
ATU-LGN SuppliestheLogburnSubstationfromTranspower’sAtarauGXP.Subsequentlysup-pliesthePikeRiverCoalMine 9km Yes Yes
2.21 Justification of 66 kV Lines Sub-transmission
Asset Use Length Optimum Justified
GYM-KUM SinglecctsuppliesGreymouthGXP.WestpowerownedTranspoweroperated.RequiredtoprovideN-1securitytotheGreymoutharea. 23km Yes Yes
KUM-KAW Doublecct.OnecctsuppliesKumaraGXPfromTranspower,theotherHKKGXPfromKumara.RequiredtosupplyHokitikasouthtoParinga 11km Yes Yes
HKK-TMR Doublecct.OnecctsuppliesHKKfromTranspower,theotherHKKfromKumaraGXP.RequiredtosupplyHokitikasouthtoParinga 8km Yes Yes
2.22 Justification of 33 kV Lines Sub-transmission
Asset Use Length Optimum Justified
HKK-HHI SpurlinefromHokitikatoHarihari.VitalsupplytoSouthWestlandwhichwillbeupgradedto66kV 69km Yes.Tobeupgradedto
66kV Yes
HHI-WAT SpurlineHariharitoWhataroa.SuppliesWhataroatownship-south 29km Yes Yes
WAT-FRZ Spurline–WhataroatoFranzJosef.SuppliesFranzJoseftownship–south.IsusedforinjectionfromTrustpower’sWahapoHydroScheme 28km Yes Yes
FRZ-FOX Spurline–FranzJoseftoFoxGlacier.SuppliesFoxGlaciertownship–south.Upgradedto33kVin2003 20km Yes Yes
ALD-DOBArnoldSubstationtoDobsonSubstation.UsedprimarilyforinjectionofTrustpower’sArnoldHydroScheme.AlsosuppliestheRotomanu,
Moana,Haupiriarea.17km Yes Yes
DOB-RFN DobsonSubstationtoReeftonSubstation 71km Yes Yes
DOB-RAP Spurline-DobsonSubstationtoRapahoeSubstation.SuppliesSpringCreekMineandRapahoeSubstation.EssentialforCoastRoadsupply 14km Yes Yes
LGN-PIKSpurline–LogburnRdSubtoPikeRiverMinesubstation.SuppliesthePikeRiverCoalMine.Significantenvironmentalfactorsjustified
theuseofHendrixinsulatedcable.6.5km Yes Yes
INTRODUCTION 45
• Reliability(i.e.continuityofservice),
• Economicefficiency,
• Environmentalresponsibility,
• Corporateprofile,
• Legislationandcompliance.
2.5 Asset Management Linkage with Westpower Performance
Figure2.23showstherelationshipbetweenassetmanagementandWestpower’sperformance.
Theserelationshipsserveasaframeworkforfocussingonthereasonswhyparticularassetmanagementactivitiesarerequired.
Ultimately, Westpower’s performance is judged externally and the drivers outlined in Section 2.4 are theparametersbywhichthisperformanceismeasured.
Figure2.23PerformanceLinkages
46 WESTPOWERASSETMANAGEMENTPLAN2012-2022
DifferentassetmanagementandoperationalresponsescanbeusedtomeetWestpower’sexternalperformancerequirements.Thesemay includemaintenanceto improvetheconditionoftheasset,developmentto installassetsinanewconfiguration,enhancementstotheexistingsystemorchangestothewayinwhichtheassetsareoperated.Effectivemanagementofthebusinessinvolvesselectingthemostappropriateassetmanagementoroperationalresponses,asproposedinthisplan.
2.6 Plan Structure and Approach
This plan uses a consistent set of defined activities and asset types to categorise work programmes andtheir associatedexpenditure. Budgeting andfinancial reportingwithinWestpower allows actual programmeachievementandexpenditureoutcomestobecomparedwiththeplan.Consistentuseofthisframeworkwillfacilitatecomparisonsovertime.
It should be noted that the activity and asset definitions are independent of accounting classifications ofexpenditure (i.e.betweenmaintenanceand capital expenditure). Therefore trends,overtimeshouldnotbealteredbyanychangesintheapplicationofaccountingpoliciesregardingthetreatmentofexpenditure.However,itshouldalsobenotedthat,underthecurrentapplicationofaccountingpolicies,allactivitiesareclassifiedaseitherentirelyoperatingexpenditure(OPEX)orentirelyCAPEX.
Similarly,theactivityandassettypedefinitionsarealsoindependentofWestpower’sorganisationalstructureandresponsibilities,althoughtheyarecloselyalignedwiththepresentstructure.Inthelongrun,adherencetothedefinitionswillensurethattheplanremainsmeaningfulinspiteofanychangesinorganisationalstructureorresponsibilities.
TheassetandactivityplanningcategoriesaredefinedinAppendixA.It isobviousthatnotallassettypeandactivitycombinationsareused.Inaddition,maintenanceactivitiescangenerallybeplannedatthedetailedassetlevel (e.g. servicingof transformers, circuit breakers),whereasdevelopmentprojects or programmes,whichtypically involve a combinationof different asset types (e.g. lines, transformers, circuit breakers, protection,communicationsandnetworkmanagement)arekeptintactratherthanattemptingtoallocatetheexpenditureagainstthecomponentassettypes.
A furtherdefinitionaldistinctionbetweenprojectsandprogrammes ismadethroughout thisplan.Theword“programme”isusedtodefineagenericactivitywithagenericjustification,butwhichmayapplyatanumberofdifferentsites.Replacementofdefectiveinsulators,fittingvibrationdamperstolinesandupgradingconnectorsarethereforeclassedasprogrammes.Ontheotherhand,“projects”aresite(orasset)specific,e.g.addingasecondcircuittoaparticularlineorupgradingaparticulartransformerbank.
2.7 Core and Advanced Asset Management
2.7.1 OutlineofCoretoAdvancedApproach
WestpoweriswelladvancedinaligningitsassetmanagementsystemtotheBritishStandardPAS-55:2008,AssetManagement.
PAS-55definesthesystematicandcoordinatedactivitiesandpracticesthroughwhichWestpoweroptimallyandsustainablymanagesitsassetsandassetsystems,andourapproachtoperformance,risksandexpenditureoverthelifecycleoftheassetsforthepurposeofachievingWestpower’sstrategicplan.
Goodassetmanagementconsidersandoptimisestheconflictingprioritiesofassetutilisationvs.assetcare,ofshort-termperformanceopportunitiesversus long-termsustainability,andcapital investmentvs. subsequentoperatingcosts,risksandperformance.
“Lifecycle”assetmanagement ismore thansimply theconsiderationof capitalandoperatingcostsover theasset’slife.Trulyoptimised,whole-lifeassetmanagementincludesriskexposureandperformanceattributes,andconsiderstheeconomiclifeasaresultofanoptimisationprocess.
INTRODUCTION 47
2.7.2 LimitationsofthisAMP
ThisAMPoutlinesWestpower’sintendedactivitiesoverthenexttenyearsbutshouldnotberelieduponasanyformofguaranteethatsuchactionswilloccurwithinthetimeframesstated.Peoplewantingcertaintyofanyactionsfordevelopmentshouldcontactthecompanyforfurtherinformation.
ThisAMPdoesnotcover:
• DetailsofWestpower’snetworkpricingderivationandapplication(theseareavailableonourwebsite);
• Vehicles,non-networkrelatedland,buildings,furnitureorgeneralofficecomputerequipment;
• Theoverheadcostsofoperatingthenetworkcontrolcentreandotherindirectoverheadcosts.
2.8 Asset Management Systems and Processes
Several systems and processes are used in Westpower’s assetmanagementtofacilitateroutinemaintenanceandinspections,planningfornetworkdevelopmentandmeasuringnetworkperformance.
Network data collection and reporting is performed and representedby GIS (spatially) and Maximo (the asset infrastructure framework).Although they are independent, GIS and Maximo share location andassetdataviaaseriesofsynchronisationsandsystemviews.Thesedataareusedtoevaluaterisk,informmanagersandprovidetheframeworkforpreventativemaintenance,allofwhichimproveoverallmanagementoftheWestpowernetwork.
These systems,and theaccurateandtimely information theyprovide,support the cost/benefit effect of maintenance. This results in bettermaintenanceoptimisationandpredictionsoflong-termeffects.
Thissectionoutlinesthefollowingsystemsandprocess:
• Newconnections,
• Preventativemaintenance,
• Asset maintenance and inspections (condition assessmentprogramme),
• Networkdevelopment,
• Networkperformance.
2.8.1 NewConnections
Workflow is an integral part of Westpower’s asset works management system and enforces Westpower’sbusinessprocesses.Figure2.25describes theworkflowused fornewconnections. Thekeyelementsof theworkflowincludenotificationtothecustomerandelectriciansotheyareinformed,andtheacknowledgementfromtheretailerensuringthatallcustomershavearetailercontractbeforetheyarelivened.
Allnewconnectionrequestsaremaintainedontheassetmanagementsystem,andsupportingdocumentationshowingconnectionpoints,connectionagreements,andliveningsheetsareattachedtotheserequests.
Figure2.24-FlowchartforDevelopmentofAMP
48 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.8.2 PreventativeMaintenance
WestpowerhasemployedPreventativeMaintenance(PM)planswhichareperformedregularly,basedonelapsedtimeormeterreadings.PMsarebeingdevelopedforeachasset/locationthatisactivewithinthenetworkandwhereconditionassessmentdoesnotapply.
The time-lapsed PMs are based on the manufacturer’s specifications/recommendations or engineeringassessments subject to thenatureof theequipment, its importance to thenetworkand theenvironmentalconditionsitmaybeexposedto.
AsthesePMsaredeveloped,jobplansareattachedthatdictatethenatureofmaintenancerequiredonatask-by-taskbasis.Whererelevant,thetasksequenceisalsodeterminedonthejobplan.Anyphotosormanufacturer’smanualsoftheequipmentorlocationarealsoattachedtothePM.
Whereappropriate,routesareappliedtoPMswhichorganiseworkpackagesintoalogicalandefficientorder.
Inadditiontoelapsedtimeormeterreading-basedpreventativemaintenanceinitiation,Westpowerisoptimisingoutagesandcoordinatingmaintenanceduringtheseperiods.
2.8.3 ConditionAssessmentProgramme
Fielddatacollection initiatives, in conjunctionwithworkauditprocesses,willensure thataccuratedataarecollectedinatimelyfashion,which,inturn,willinstilconfidenceinreportinghistoricalassetdata.
Figure2.25ProcessforNewConnections
INTRODUCTION 49
Figure2.26-ConditionAssessmentProcess
FIELD DATA
NEW DATA KEYED
AUTOMATED PROCESS
DATA ANALYSIS
YES NO
DATA ENTERED USING PORTABLE DEVICE
PROCESS FOR CONDITION ASSESSMENT OF
ASSETS
IDENTIFIED REQUIRED ASSESSMENT
50 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Thefirst stageof thedata collectionprogrammewas theupgradeof the conditionassessmentprogramme,which provides direct integration of theArcPad field data collection systemwith theArcSDE database. ThisinformationisthenpassedtoMaximoonanightlyschedule.Assetsareinspectedonatleastfive-yearlyintervals,andchangesarerecordedoncompletionofanyworkcarriedout.Thespatialandaspatialdatacollectedprovideanaccuratereflectionofthenetworkatanyonetime.
Auditscarriedoutatworkcompletionassistwiththeclosingoffoftheprocess.
Theprocessesoutlinedabovehavebeenactivatedandareprovingtobeverysuccessful.
Processeshavebeeninitiatedtoensureallassetsarerecorded.ThisfinancialyearwillseethecollectionofbothspatialandaspatialdatapertainingtoLVpillarandlinkboxes.Itisenvisagedthatallassets,includingLVlineand,willberecordedwithintwoyears.ThiswillenablemoreaccuratetrackingofworkhistoryandwillalignwiththeMaximohierarchy.
2.8.3.1 WestpowerConditionAssessmentSpecification
ToenableWestpower to assess the conditionof its network accurately, a conditionassessmentprogrammehasbeen initiated.Thisprogrammeinvolvesthecollectionofrelevantdataonprimarily linesandassociatedequipment.Thisdataarethenused,viaGIS,toforecastrequiredmaintenanceandcapitalworks,andalsotoidentifyareaswhichmayposehealthandsafetyrisks.
Collection is performed usingHewlett-Packard Ipaq hand-held and notebook computers, completewith theEnvironmentalSystemsResearchInstitute’s(ESRI)ArcPadsoftware,whicheliminatestheneedformanualdataentryintotheGIS.
Twentypercentofeachline(feeder)isassessedinayear,allowingthetotalnetworktobecompletedinafive-yearcycle.
Networkcomponentstobeassessedwillbedividedintocategories,namely:
• Poles,
• Pillarboxes,
• Linkboxes
• Crossarms,
• Fittings(bracebars,insulators,shackles,polesteps,LVfusesetc.),
• Stays,
• Disconnectors,
• Transformers,
• Drop-outfusesandlightningarrestors,
• Earthingsystems,
• LVConductors,
• HVconductors,
• CablesLV,
• CablesHV,
• Other(reclosers,sectionalisers,capacitors,etc.),
• Vegetation.
Allcatagoriesareassessedusingthesameterminologyasfollows:
INTRODUCTION 51
Excellent
Componentisnearnew,lessthantwoyearsold,and/orstillinexcellentcondition;
Good
Componentstillhasgreaterthanaten-yearlifeexpectancyandisgenerallyingoodcondition;
Fair
Componenthasalessthanten-yearlifeexpectancy,butwilllastlongerthanfiveyears;
Poor
Componentcouldlastuptofiveyearsbutisgenerallyinpoorcondition;
Needs replacing
Componentisconsideredcondemnedbutwilllastuptotwoyears;
Red tagged
Componentisinurgentneedofreplacement,andposesahealthandsafetyrisk.
2.8.3.2 Methodology
Theprocessforeachcomponentwillbecompletedasdescribedbelow.
Pillar boxes
Allpillarboxesshallbethoroughlyinspectedandearthresistancetestscarriedout.Theconditionoffuses,cablesandtheboxshallalsoberecorded.
Poles
Allwoodenpolesshallbethoroughlyinspectedbelowground(to600mm).Astandardprobetestshallbecarriedout,alongwithahammertest.Anyknot-holesorsplitsabovegroundshallbeprobedandassessedaccordingly.
Allpolesshallhaveadetailedvisualinspectionperformed.Thisincludestherecordingofanyspallingorcrackingfoundonconcretepoles.
Crossarms
All crossarms shall have a detailed visual inspection performed. Any suspect LV or service crossarms shallbeprobedandassessedaccordingly.AnysuspectHVorsubtransmissioncrossarmsshallbenoted for futureinspection.
Fittings
Fittings,suchasbracebars,insulators,shackles,polesteps,LVfuses,boltsetc.,aretobeassessedcollectivelyusingadetailedvisualinspection.Theworst-caseconditionoffittingsshallberecorded.Ifanyfittingisassessedas‘poor’or‘needsreplacing’,notesdescribingrelevantdetailsofthefittingshallberecorded.
Stays
Theconditionofstaysandtheirassociatedfittingsaretobeassessedcollectivelyusingadetailedvisualinspection.Thiswillincludetheconditionofstaywire,stayinsulators,staydead-end,hoses,eyeboltsetc.Theworst-caseconditionofstaysandtheirfittingsshallberecorded.
52 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Transformers
Transformersshallhaveadetailedvisualinspectionperformed,includingchecksonoillevels,crackedbushings,deteriorationofgasketsandanysignsofoildischarge.
Dropout Fuses and Lightning Arrestors
Dropout fusesand lightningarrestors shallhaveadetailed inspectionperformed,with their condition tobeassessedcollectively.Theworst-caseconditionofdropoutfusesandlightningarrestorsshallberecorded.
Earthing System
Theearthingsystemfortransformers,disconnectorsetc.shallbeassessedbymeansofadetailedvisualinspection.Onlyexposedcomponentsoftheearthingsystemneedtobeinspected,withtheworst-caseconditionoftheearthingsystembeingrecorded.
LV Conductors and HV Conductors
Generalconditionofoverheadconductorsshallberecorded.Conductorsshallbeassessedbyvoltage.Theworst-caseconditionoftheconductorsshallberecordedinthecaseofmultipleconductorsofthesamevoltage.
LV Cables and HV Cables
Generalconditionofundergroundcablesshallberecorded.Onlyexposedcomponentsofundergroundcablesneedtobeinspected,withtheworst-caseconditionofthecablesbeingrecordedinthecaseofmultiplecablesofthesamevoltage.
Vegetation
While assessing the conditionofWestpower’s network, the assessor shall note any vegetation thatmaybeencroachingtheline,oranyaccesstoequipmentthatmaybehinderedbyexcessivevegetation.
General Comments
TheassessorwillberequiredtonoteanygeneralcommentsthatcouldprovideinformationtoassisttheoverallsecurityofWestpower’snetwork.
Work Required
Anymaintenanceworkidentifiedshouldberecordedintheworkrequiredtextbox.Photosmustbetakenwherework is requiredand thenumber recorded in thephoto IDbox.Allwork requireddescriptionsshouldbeasdetailedaspossible,withadescriptionofthedefectandrecommendedactions.AnelectroniccopyofallphotosmustbesuppliedtotheassetmanagementdivisioninGreymouthoncompletionoftheassessment.
FielddataarethenuploadedintotheSpatialDatabaseEngine(SDE).Allconditioncodesareupdatedinstantlyasthesedataareuploaded,changingthestatusoftheasset’slastconditionanddateofassessment.AllworkrequiredisthenseparatedandanalysedusingArcGIS,andworkordersraisedwhereneeded.
These data can now be audited for analysis and further assessment when needed. Figure 2.26 shows theconditionassessmentprocess.
2.8.3.3 ConditionAssessmentDataRetrieval
AllassetdatacollectedinthefieldareuploadedtotheGISfromthehand-helddeviceupdatingcertainfieldsandtablesinthedatabase.Theconditionassessmentdateisalsoupdatedsotheseassetscanbeassessedagainwithinfiveyears.
INTRODUCTION 53
Work Required Table
Theworkrequiredtableuploadedfromthehand-helddeviceissplitintotwocategories:urgentandnon-urgent.
Urgentworkisgroupedintoareas.Aworkorderisthengeneratedforthisarea,includinganyassetsmarkedasneedingreplacementorredtaggedintheconditionattributeoftheassetdata.Anyassetthatrequiresinstantactionwillhaveaseparateworkorderraisedinordertorectifythisissueassoonaspossible.
Non-urgentwork isalsogroupedintoareasand issetasideforactionduringplannedoutagesorwhentimeallows.
Thedataretainedinthistablealsoenablestheassetteamtodesignefficientmaintenanceprogrammesbybeingabletoidentifyspecificassettypesandtheirlocation.
Condition Codes
Allassetdataarereturnedwithanupdatedconditioncode,andthesecodesareseparatedandanalysedforactionwhererequired.
Excellent condition
Nofurtheractionisrequiredontheseassetsbeforethenextscheduledassessment;
Good condition
Theseassetshavemorethantenyears’lifeexpectancyandwillbeassessedagainwithinthisterm;
Fair
Theseassetshavelessthantenyears’lifeexpectancy,butwilllastlongerthanfiveyearsandwillbeassessedagainwithinthisterm;
Poor
Thisassetcouldlastuptofiveyears;however,asitisinpoorcondition,futureassessmentwillberequiredduringthisterm;
Needs replacing
Anyassetswiththisconditioncodearegroupedintoareasalongwithanyotherurgentworkrequiredandaworkorderisraisedfortheasset(s)tobereplacedassoonaspossible;
Red tagged
Allredtaggedassetsareurgentlyinneedofreplacementandwork.UsingthenetworkanalysistoolbarintheGIS,theassetteamisabletoflagadisconnectorthatisplannedforfutureoutage,andtoidentifyanyoftheworkrequiredintheaffectedarea.
Workordersarethenraisedforthisworktobedoneduringtheplannedoutage.
2.8.4 NetworkDevelopment
A network development plan is required tomaintain, enhance and develop the operating capability of theWestpower network, and while there is no separate document published as a result of this process, it isnonethelessembodiedinthereplacement,enhancementanddevelopmentactivitiescontainedwithintheAMP.Thefollowingactivitiesarekeyelementsinthedevelopmentoftheplan:
54 WESTPOWERASSETMANAGEMENTPLAN2012-2022
1. Developandupdateaten-yearperiodloadforecastfollowingtherecordingofthesummerorwintermaximumdemandsand future development information. These load growthprojections are used as a basis for determining the likelytimingforthoseprojects.
2. Evaluate network limitations and select the bestdevelopment/configuration to alleviate each systemlimitation.
3. Complete the identificationof thenecessarymajorprojectonthebasisofrepeatedlyevaluatingthenetworklimitationsand selecting the best developments for each year of theforecastperiod,assumingcompletionoftheprojectsinthedesignandconstructionphaseandoftheprojectsidentifiedinearlieryearsoftheforecastperiod.
4. Collect any relevant data relating to the network’sperformanceorcapability.Theseincludesdataonswitchgearcondition,transformercondition,poorlyperformingfeeders,operationallimitations,etc.
5. Identify areas where future substation sites and/or futurecircuitsmayberequired.
6. Revisionmayberequiredintheperiodbetweentheannualreviewsifnewprojectsareidentifiedinthatareaorexistingprojectsaresignificantlychanged.
TherearetwodifferentplanningtypesconsideredbyWestpowerwhendevelopinganetworkdevelopmentplan:
• HVplanning,
• LVplanning.
HV planning incorporates a list of zone substations andassociated subtransmission feeders, a list of strategies fornetworkdevelopment,recommendationsfortheacquisitionoffuture substation sites, and HV circuit easements grouped byareatoensurethatsufficientcapacityisavailableinWestpowersubtransmissionandzonesubstationinfrastructure.
LVplanning isdevelopedtoensurethatadequatevoltage levelsaremaintained forall customersalongaLVdistributionatalltimesthroughoutthelifeoftheLVnetwork.Inordertoachievethis,accuratevoltagedropcalculationsarecarriedoutatthedesignstage.
Figure2.27showstheprocesstodeterminedevelopmentoptions.
2.8.5 AssetDataCollection
Historically,assetdatawerecollectedthroughas-builtdrawingsandrecordedonhardcopyfiles.TheinceptionoftheGISallowedthesedatatobeelectronicallyrecorded;however,muchofthesedatawereinitiallystillcapturedonpaperandmanuallytransferredtotheelectronicformat.AdvancesintechnologyhaveseenelectronicdatabeingcollectedinthefieldandautomaticallytransferredtotheGIS,creatingamoreaccurateandefficientdatacollectionsystemthanwasemployedinthepast.Thesedataarenowutilisedforanumberoftasksincludingassetconditionmonitoring,assetvaluation,workscoping,outageplanningandanumberofregulatorytasks.Confidenceintheintegrityofthedatahasgrownwiththecurrentdatacollectionmethodsusedandhighlevelsofaccuracyarenowbeingachieved.
Figure2.27-DataModelforReliabilityData
INTRODUCTION 55
Asmentioned,muchofthedatarelatingtoWestpower’sassetshavebeencollected.However,insomecases,dataaremissingorincomplete.ProgrammessuchasconditionassessmentandpillarboxinspectionshavebeeninitiatedtoensureallfielddataareincludedintheGISandMaximosystemsviathesynchronisationprocess.Thevariousassettypesandplansinplacetoensuredataaccuracyarelistedbelow.
2.8.5.1 PolesandSpans
Neworreplacementpolesandspansarerecordedduringthedesignphaseofeachjobandtransferredfromdesign software toGISwitha statusof “NotReady”. Once the line construction is completed, the status ischangedto“Active”andallrelevantattributionispopulated.
AnypoleorspanreplacementsnotrequiringdesignareupdatedontheGISbyelectronicmeansorthemanualpoledataform.
Pocketsofpoles and spanson thenetworkare yet tobe recorded;however, theseassets are rapidlybeingidentifiedandcorrected,primarilyviatheconditionassessmentprogramme.
2.8.5.2 UndergroundCables
Althoughmanyundergroundcableshavebeenelectronicallyrecorded,thereisstilla largenumbertoyetbeincluded.Programmes suchaspillarbox identificationand inspectionwill assist to identify those cablesnotcurrentlyincludedintheGIS.
Aprogrammetorecordmissingcablesandrelevantdatawasinitiatedin2010andwillcontinue,witheachareahavingcabledatasystematicallyrecorded.
Aswithspans,thespatialrecordingofundergroundcablesisintegraltoutilisingGISfunctionssuchasnetworktracing(connectivity),whichassetmanagementstaffarebecomingincreasinglydependentonforanumberoftasks.
2.8.5.3 PillarBoxes
Anidentificationandinspectionprogrammewasinitiatedin2008torecordallpillarboxesontheWestpowernetworkelectronically.Bothspatialandaspatialdataarerecorded,alongwithaseriesoftests.AnydefectsfoundarerecordedatthetimeofinspectionandareautomaticallyuploadedtotheGISwiththecoreinspectiondatatobeactioned.ThisprogrammewascompletedinFebruary2010.Anynewpillarboxadditionstothenetworkarespatiallyrecordedeithervialocalityplansorglobalpositioningsystem(GPS)readings.Similartopoledatacollection,attributiondatacanbegatheredelectronicallyorbycompletingthemanualpillarboxdataform.
2.8.5.4 TransformersandSwitchgear
There are a number ofmethods for collecting data for transformers and switchgear. As these componentsgenerally consist of a location (earths, fuses etc.) and an asset (transformers, disconnectors etc.), data arerecordedindependently.ThetransformerorswitchgearisrecordedonlyinMaximo,withthelocationdatabeingrecordedintheGISandbecomingavailabletoMaximouponnightlysynchronisation.Althoughtheyarestoredinadifferentdatabase,theassetdataareviewableontheGISwhenqueryingalocation.
AssethistoriesrecordedinMaximoincludeinformationsuchasassetmoves,servicinghistory(viaworkorders)andassetspecifications,whereasthelocationdataarerecordedinthefieldeitherbyhand-heldelectronicdevicesormanualdataentryforms.Averyhighlevelofconfidenceisawardedtothetransformerandswitchgeardata,withrecordsbeingperiodicallyaudited.
56 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2.8.5.5 Summary
Processespreviouslyunavailablearenowinplacetoensureanynetworkadditions,deletionsorassetmovesarerecordedintheappropriaterepositories.Maximoworkflowsandauditingprocessesallowassetmanagementstafftoauditeachworkorder,andtocheckthatalldocumentationanddataentryiscompletedbeforeclosingoffthejob.Withthisinmind,theintegrityofthedatacanbeassuredandcanbeutilisedwithahighdegreeofconfidence.
2.8.6 MeasuringNetworkPerformance
ThefollowingsectionoutlinestheprocessbywhichWestpowerrecordsitsoutagedatatocomplywithdisclosurerequirements.
AllinterruptionstoWestpower’snetworkarerecorded,includingthoseontheTranspowergrid.Fordisclosurepurposes,allrelevantoutagedataarereportedonandgroupedbyclass(i.e.ClassA,B,CandD.ClassesBandCrelatetoWestpower;ClassesAandDrelatetoTranspower).
2.8.6.1 DataCollection
Atthetimeofanoutage,therearetwocategoriesofnotificationthatmayoccur:Alarm/OperatorandInformant/Customer.Thesenotificationstriggertherecordingpartoftheprocess.
Alarm/Operator:
Ifacircuitbreakeropens,analarmwilltriggerontheSCADAsystemandtheoperator(ifonduty)willnotifytheretailer.Iftheoperatorisnotondutythenthealarmwilltriggerapagerandtheon-calloperatorwillbecalledin.
Informant/Customer:
Ifacircuitbreakerhasnotopenedandthecauseoftheoutageis localisedtoadistributiontransformer(forexample),thiswillnotcauseanalarmontheSCADAsystem.Thefaultwillgenerallybeforwardedtotheretailerfromtheaffectedconsumer.
TheoutagewillthenbepassedonfromtheretailertoCallCare,whowillthennotifyElectroNetServices,whowillinitiateanyworkrequiredtofixthefault.AControlRoomoperatorwillcollectthefollowingdatawheneveranetworkinterruptionisexperienced:
Dateandtime(timepowerwentoffandtimelastcustomerwasrestored),
• Location,
• Descriptionofevent,
• Typeofoutage(plannedorunplanned),
• Feeder,
• Notification,
• Componentaffected,
• Cause,
• Voltageaffected,
• Protectionunitinformation,
• Network(WestpowerorTranspower).
Thisoutage information is currently stored in a geodatabase viaWestpower’sGIS. TheGIS is used to selecttransformers affected by an outage and, along with all related information, is recorded as a entry in thegeodatabase.
INTRODUCTION 57
CustomerinformationsuchasInstallationConnectionPoint(ICP)numbers,retailernumbersandsitenumbersareautomaticallyupdatedeverynightandstoredasaCommaSeparatedVariable(CSV)file.Thisfileisuploadedtothegeodatabaseandusedincalculationstofindthenumberofcustomersaffectedbyoutages.Thecustomersarelinkedtotheirrespectivetransformernumbers,sowhentransformersareselectedfromtheGIS,anaccuratenumberofcustomerscanbefound.
2.8.6.2 DataProcessing
SAIDI,SAIFIandCustomerAverageInterruptionDurationIndex(CAIDI)arethemostwidelyacceptedKPIsforelectricitynetworks.
WestpowercollectsthedatarequiredfromseveraldifferentinternalsystemsincludingtheGISandMaximotoperformthefollowingcalculations:
SAIDI (TotalSystemMinutesLostxNumberofCustomersAffected)/TotalNumberofCustomers
SAIFI NumberofCustomerInterruptions/TotalNumberofCustomers
CAIDI CanbederivedbydividingSAIDIbySAIFI
Insomepoweroutageevents,noteverycustomerhastheirpowerrestoredatthesametime.Becauseofthis,itisunrealistictousethestartandendtimeofanoutagetocalculateSAIDIandSAIFI.
1. Eachswitchingoperationisrecorded,includingthenumberofcustomersaffectedandthetimepowerwentoffandthetimepowerwasrestored.
2. ASAIDI/SAIFIfigureiscalculatedforthisoperation.
3. Tocalculatethetotalfortheoutage,theSAIDI/SAIFIforeachoperationissummed.
Figure2.28showsthedataprocess.
Figure2.28DataModelforReliabilityData
58 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.0 ASSETS COVEREDWestpowerownselectricity reticulationassets thatareused toprovidedistributionandconnectionservicestoelectricityretailersandgenerators.TheseassetsgenerallycompriseequipmentthatiscommontoallNewZealand ELBs and,wherever possible, industry standard assets have been employed. In particular, theAMPcoverstheelectricityandassociatedsystemsownedbyWestpower,comprising:
• Subtransmissionassets-Electriclinesandcables,includingassociatedeasementsandaccessways,operatingatvoltagesof33kVandhigher;
• Distributionassets-Electriclinesandcables,includingassociatedeasementsandaccessways,operatingatavoltageof11kV;
• Reticulationassets-400Velectriclinesandcables,includingassociatedeasementsandaccessways;
• Services - Connection assets at any voltage owned by Westpower for the purpose ofsupplyingasinglecustomer(notincludingthelineonthecustomer’spremises);
• Zonesubstations -HVsubstationsconnectedto thesubtransmissionnetwork.This includesallplantandequipment within the substations such as transformers, switchgear, structures and buswork, SCADA,protectionandmeteringequipment,andstationlandandbuildings;
• Distribution substations - Substations connected to the distribution network. This includes plant andequipment within the substations such as fuses, platforms, lightning arrestors and maximum demandindicators,togetherwithlandandfibreglasscovers,butexcludingtransformers;
• MediumVoltageswitchgear-Circuitbreakers,reclosers,sectionalisers,regulatorsanddisconnectorsusedinthedistributionandsubtransmissionsystems;
• SCADA,communicationsandprotectionequipment-SCADA,communicationsandprotectionequipmentandassociatedfacilitiesnotinstalledatzonesubstations.Thisincludescontrolroomequipment,radiorepeatersandfibre-opticsystemsinstalled,ownedandmaintainedbyWestpower;
• Distribution transformers - Standard transformersused indistribution substations ranging from5kVA to1000kVAandgenerallyhavingaprimaryvoltageof11kV;
• Ripplecontrol-Rippleinjectionequipment;
• Embeddedgeneration-GenerationunitsconnectedtoWestpower’snetworkbutnotnecessarilyownedbyWestpower;
• Capacitorunits-Forvoltagesupport;
• Mobilesubstation-Allowsimprovedmaintenanceaccesstoexistingsubstationsandforemergencyuseincaseofsubstationfailure;
• Buildings-SubstationbuildingswithintheWestpowernetwork.
WestpowerownassetsthroughoutthelengthoftheWestCoastoftheSouthIsland,anditsareaextendsaboutasfarasthedistancefromChristchurchtoDunedin(refertoFigure3.1).
AnoverviewofWestpower’snetworkdiagramcanbeseeninFigure3.3.
3.1 Asset Condition
Thepresent conditionof theaboveasset types is alsodescribed in this section,basedon information fromroutineinspections.
ThereaderunfamiliarwiththegeographicallayoutofthesystemisreferredtothemapsthroughoutSection3.
Thisassessmentof thepresentconditionof theassets,andthe implicationsof thison futurenetworkassetperformanceaftertakingassetcriticalityintoaccount,isthebasisfortheproposedmaintenanceprogrammesandnetworkdevelopmentdescribedinSection5.Theprimaryassetmanagementdriversare:
ASSETSCOVERED 59
Figure3.1-Westpower’sOperationalAreainRelationtoOtherSouthIslandElectricityLinesBusinesses
• Safety,
• Networkperformance,
• Economicefficiency,
• Environmentalresponsibility,
• Corporateprofile,
• Regulatorycompliance.
ThemajorityofthesenetworkassetsareshowninvaluetermsasapercentageofOptimisedDepreciatedReplacementCost(ODRC)inthepiechartofFigure3.2.
Figure3.2-ODRC-OptimisedDepreciatedReplacementCostasaPercentageofTotalNetworkAssetODRC.
20.1%
2.7%
12.3%
0.5%50.7%
10.8%1.9% 0.7% 0.3%
Zone Substations MV Switchgear Distribution Transformers
Spares Overhead Lines Underground Cables
Services Scada Comms Land Values
60 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure3.3-DiagramofWestpower’sNetwork
33kV11kV
PIKE
11kV
LOGBURN
AtarauSwitchingStation(ATU110)
11kV
33kV
11kV
BLACKWATER
66kV
DOBSON(ATU110)
NGAHERE
33kV
REEFTON(RFN110)
11kV
GLOBE
11kV
11kV
ARNOLD
G 3MW
3.3kV
66kV
11kV
GREYMOUTH(GYM066)
6.6kV
66kV
11kVOTIRA (OTI011)
11kV
33kV
66kV
HOKITIKA(HKK066)
ROSS
11kV
11kV
WAITAHA
HARIHARI
11kV
WHATAROA
WAHAPO
11kV
11kV
G3MW
FRANZJOSEF
11kV
11kV
FOXGLACIER
110kV
66kV
33kV
11kV
6.6kV
3.3kV
LEGEND
GXPs
TranspowerOwned
(HKK066)
TwoMileRoad
Kawhaka
Coleridge66kV
ArthursPass66kV
Ina
nga
hu
a1
10
kV
TRANSPOWER
TR
AN
SP
OW
ER
66kV
KUMARA(KUM066) 10MW
11kV
G
SwitchingStation
RAPAHOE
11kV
ASSETSCOVERED 61
3.2 Transpower GXPs
Atarauswitchingstation,situatedonTranspower’sDobsontoReeftontoInangahuacircuit,wascommissionedbyTranspowerin2007tofeedthenewPikeRiverCoalMine.Westpowertakessupplyat110kVfromthisGXP.
TheElectricityCommission’sapprovalof theWCGUP in2008paved theway foranadditional110kVcircuitconstructedfromDobsontoReefton,andthiscircuitprovidestwogeographicallydiverseandrelativelystrongfeedsfromInangahuatoDobson,securingsupplyintotheWestCoastfromthenorth.Westpowerwasalreadywelladvancedwithsecuringpropertyrightsforthisroute,whichextendssome72kmthroughfarmlandandDepartmentofConservation(DOC)reserves,andhadbuiltupagoodrapportwithlocallandowners.
Thenewline,termedDOB-TEEA,wascommissionedinlate2011andprovidesn-1securitytotheAtarauGXP.AnagreementwasreachedbetweenTranspowerandWestpowerforWestpowertoconstructthenewlineandthensellittoTranspoweroncommissioning.
Priortothecompletionofthisline,therewasinsufficientcapacityintheTranspowernetworktosupplythisloadfromthesouthintheeventofafaultonthe110kVcircuitfromthenorth.Theloadwasthereforeinterruptible.
Thisproject,alongwitharelated14MvarswitchedcapacitorbankinstalledatHokitika,hasrestoredsecuritylevelstoagoodelectricityindustrypracticestandardforloadsofthesizeandtypesuppliedbyWestpower.
WestpowertakessupplyfromsevenTranspowerGXPsat110kV,66kV,33kVand11kVasshowninTable3.4.
MaintenanceofthemeteringequipmentattheseGXPsisTranspower’sresponsibility.
ThesouthernpartoftheWestpowernetworkisfedfromadouble-circuit66kVlinefromColeridge,whichissupportedbyalimitedcapacity66kVconnectionbetweenDobsonandKumara(seeFigure3.3).Thisprovidesanacceptablelevelofsupplysecurity,althoughsomeloadcurtailmentmaybenecessaryshouldacommonmodefaultaffectbothcircuitsofthe incomingdouble-circuit lineatthesametime.Theprobabilityofsucha faultoccurringisrelativelylow.
The constructionof the twin-circuit Kumara-Kawhaka line inMay1997byWestpowerhas greatly improvedsecurityofsupplytotheKumaraandGreymouthsupplypoints.ItisconsideredthatthelevelsofsecurityareappropriateforWestpower’snetworkinlinewithindustrybestpracticeforloadsofthissizeandtype.
3.3 Sub transmission Assets
Westpowerownsthreedistinctclassesofsubtransmissionassets,runningat110kV,66kVand33kV.The66kVassetsareleasedbacktoTranspowerforoperationaspartoftheirWestCoasttransmissionnetworkandtheseassetsareunderTranspower’soperationalcontrol.
*TheAtarauswitchingstationsuppliesLogburnRoadsubstationandthereforethetransformercapacityisapplicableforLogburnRoad
Table 3.4 - GXP Capacity and Load Profile
GXP Asset Owner Voltage (kV) Transformer Capacity (MVA)
Present Maximum Demand (MW)
Greymouth Westpower 66 2x15 13.444
Hokitika Westpower 66 2x20 18.452
Kumara Westpower 66 1x10 9.540
Dobson Transpower 110 2x17 13.793
Otira Transpower 11 1x2.5 0.694
Reefton Westpower 110 2x30 9.916
Atarau(SwitchingSta-tion)/LogburnRd* Transpower 110 1x30 1.104
62 WESTPOWERASSETMANAGEMENTPLAN2012-2022
KEY Substation
Subtrrans Line 33/66kV
Subtrans Line 110kV
BWR-IGH-A
DOB-BWR-A
AHA-DOB-A
GYM-KUM-A (Leased from Westpower)
KUM-KHA-A (Leased from Westpower)
AHA-OTI-A
ATARAUATARAU
BLACKWATERBLACKWATER
REEFTONREEFTON
DOBSONDOBSONGREYMOUTHGREYMOUTH
( WESTPOWER )( WESTPOWER )
HOKITIKAHOKITIKA( WESTPOWER )( WESTPOWER )
OTIRAOTIRA
ARTHURS PASSARTHURS PASS
KUMARAKUMARA
Figure3.5-MapofTranspowerLinestoWestpower’sNetwork
ASSETSCOVERED 63
The110kVassetsownedbyWestpowerincludetheReeftonsubstation,wheretheinterfacepointsbetweenWestpower’s and Transpower’s assets are the incomingdisconnectorson the line sideof the110 kV circuitbreaker.
Westpoweralsoownsan8kmstretchof110kVlinefromTranspower’sAtarauswitchingstationtoanassociated20/30MVA110/33/11kVsubstationatLogburn.ThiswascommissionedbyWestpowerin2007aspartofthereticulationtothePikeRiverCoalMine.
3.3.1 AssetJustification
Subtransmissionassets,eitherat110kV,66kVor33kV,arerequiredtotransmithighlevelsofelectricalenergyover significant distances, prior to stepping the voltage back down to 11 kV for local distribution. The longdistancesinvolvedinreticulationofelectricityontheWestCoastmeanthattheseassetsareessentialforthecapacityandloaddiversityinvolved.
3.3.2 SubtransmissionAssetCondition
The condition of the sub transmission assets largely reflects their age and the quality ofmaterials used inconstruction.Ingeneral,the33kVlinesareconstructedwithconcretepolesandthe66kVlineswithhardwoodpoles.
Figure3.6showstheageprofileofsubtransmissionlines,bycircuitkilometre.
Thepresentconditionofanysubtransmissionlineislargelyafactorofitsage,thequalityofmaterialsusedandtheenvironmentalcorrosivenessofthelocationittraverses.
Westpower’ssubtransmissionlinesfallintofourbroadgroups:110kVpolelines,66kVwoodpolelines,33kVpolelinesand33kVfullyinsulatedlinesas33kVHendrixSpacerCable.
0
10
20
30
40
50
60
70
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 40+
Leng
th o
f Lin
e (
Km
)
Age (years)
33kv 66kv
110 kV
Figure3.6-SubtransmissionLineAgeProfile
64 WESTPOWERASSETMANAGEMENTPLAN2012-2022
*AllDRCandODRCvaluesaretakendirectlyfromthe2004ODVrevaluationexcercise.Whilethesevaluesarenowsomewhatoutofdate,theyprovideaconstantbasisforcomparisonwiththevaluationsofotherELBsbyusingthelastindustry-widevaluationdate.
3.3.3 110kVLines
Westpowerownsone110kVlinefromAtarautoLogburnRoad.Thislineis8kmofconcretepolesstrungwithNeonAllAluminiumAlloyConductor(AAAC).
Table3.7summarisesthequantityofthe110kVlinebycircuitlength.
3.3.4 66kVLines
DRC* - $2,074,730
ODRC - $2,074,730
Westpowerownsthreeoverhead66kVsubtransmissionlines.TwooftheseareconnectedtotheWestpowerKumaraSubstation,whileanotherisanextensionoftheTranspower-ownedTMR-OTIcircuit.
Asdiscussedabove,allthreeoftheseassetsarecurrentlyleasedtoTranspoweronalong-termleasearrangement.
ThelinebetweenGreymouthandKumaraisa25kmhardwoodpolelinestrungwithDogAluminiumConductorSteelReinforced(ACSR)conductor.Thiswasconstructedin1977toconnecttheKumarapowerstationtotheWestpowerGreymouthsubstationandthentotheTranspowergrid.
The66kVdouble-circuittreatedhardwoodpolelinebetweenKumaraandKawhakawascommissionedin1997,andthiswassubsequentlyleasedtoTranspower,allowingthemtoreconfigurethegridontheWestCoast.Thelineis11kmlongandusesIodineAAACconductoronbothcircuits.
Themostrecentlyconstructed66kVline,betweentheTwoMileandHokitikasubstations,wascompletedinJuly2002.This,too,isadouble-circuitline;however,pre-stressedconcretepoleshavebeenusedtosupportthe7.8kmofIodineAAACconductor.
Westpowerhasnoundergroundcablesattransmissionvoltagesof66kVandabove.
Table3.8summarisesthequantityof66kVoverheadlinebycircuitkilometre.
3.3.4.1 66kVWoodPoleLines
TheGreymouth-Kumara66kVlineconstructedin1977wasconstructedwithde-sapped,untreatedhardwoodpoles,whicharenowshowingsignsofearlyground-linedeterioration.Arecentmajorground-lineinspectionhasshownthatthereisnoreasonforimmediateconcern,butamanagementplanneedstobeputintoplacewithinthenextfiveyearstocontainanyriskofprematurefailure.
Table 3.7 - 110 kV Lines Summary
Type Circuit Length (km)
LightOverhead 0
MediumOverhead 0
HeavyOverhead 9
Table 3.8 - 66 kV Lines Summary
Type Circuit Length (km)
LightOverhead 0
MediumOverhead 60
HeavyOverhead 0
ASSETSCOVERED 65
Figure3.9--Westpower’s33kVNorthandSouthNetworks
Westport
BLACKWATERBLACKWATER
GLOBEGLOBE
DOBSONDOBSON
REEFTONREEFTON
FOX GLACIERFOX GLACIER
FRANZ JOSEF.FRANZ JOSEF.
ROSS ROSS
RAPAHOERAPAHOE
ARNOLDARNOLD
HARIHARIHARIHARI
WAITAHAWAITAHA
GREYMOUTHGREYMOUTH
HOKITIKAHOKITIKA
WAHAPOWAHAPO
KUMARAKUMARA
PIKEPIKE
WHATAROAWHATAROA
NGAHERENGAHERE
KEY
33kV Subtransmission Line
66kV Transmission Line (Westpower)
66kV Transmission Line (Transpower)
110kV Transmission Line
Westpower Substations
66 WESTPOWERASSETMANAGEMENTPLAN2012-2022
TheKumara-Kawhakalinewascompletedin1997andusedtreatedhardwoodpoles,whichareexpectedtolastforatleast45years.Thislineisinexcellentcondition,withannualpatrolsshowingnosignsofdeterioration,aswouldbeexpectedfromabrandnewline.
Bothlinesusestand-offporcelaininsulatorsandthishasgreatlyreducedthecomponentcountoneachpole.
Ofnote,boththeGreymouthKumaraandKumaraKawhakacircuitsareleasedtoTranspower,whooperatesthemaspartofthenationalgrid.Aperformance-basedcontractexistsbetweenTranspowerandWestpower,wherebyWestpowerprovidesaminimumlevelofreliability,andthis,inturn,requiresahigherthanusualstandardofmaintenance.
Duringtheearly1990s,aprogrammeofpolebandagingwascarriedoutonapproximately50%of thepolesonthisline.Thisinvolvedcleaningoffanyrottensapwood,placingaheatshrinkbandagearoundthepoleatthe ground-line and injecting a fungicidal emulsion to halt any further deterioration. In 1994, however, thisprogrammewasdiscontinuedbecauseofconcernsovertheeffectivenessoftheprocess.
3.3.5 33kVLines
DRC - $6,566,784
ODRC - $6,566,784
Thereare twogeneral areas servedbyWestpower’s 33 kV subtransmissionnetwork,onebasedaround theDobsonandGreyValleyareas,andtheotherservingSouthWestland.ThesetwoareasareconnectedbetweenGreymouthandHokitikaviaKumarathroughthe66kVnetwork.
Figure3.9showsthegeographicalspreadofthesetwoassetareas.
Transpower’sDobsonpointofsupplyservesasthehubofthenorthernsubtransmissionsystemandisusedtofeedsubstationsatRapahoe,Ngahere,ReeftonandArnold.ThelinetoArnoldwasoriginallybuiltinthe1930sanduses7/.080”copperconductor.
ExceptforashortlengthofMinkACSRlineoverMtHerculesandsomefullyinsulated33kVoverheadlineinSouthWestland,therestofthesubtransmissionlinesarestrungwitheitherDogACSRorIodineAAACconductor.
The33kVsubtransmissionlinefromHokitikatoHarihari,originallyconstructedin1966,waspurchasedfromTranspower.Thelargemajorityoftheremaining33kVassetshavebeenconstructedsince1983andaremainlyofconcretepoleconstruction.
Table3.10summarisesthequantityof33kVoverheadlinebycircuitlength.
3.3.5.1 33kVPoleLines
These linesaremostlydouble-circuitunder-builtconstruction(33kVabovewith11kVand/or400Vcircuitsbelow)wiredinACSRandAAACconductor,andarebetween4and38yearsold.
Threedistinctconstructiontypesarepresentinthesubtransmissionnetwork:
• HardwoodpolesontheHarihari-WhataroaandDobson-Arnoldlines.
• Stresscrete12.2mpre-stressedconcretepoles(usedonthemajorityoflinesconstructedinthelast15years);
• Twotypesoffullyinsulatedconstructiononhardwoodpoles.
Table 3.10 - 33 kV Lines Summary
Type Circuit Length (km)
LightOverhead 267
MediumOverhead 0
HeavyOverhead 0
ASSETSCOVERED 67
3.3.5.2 33kVOverheadLineReliability
MostofWestpower’sreticulationconsistsofoverheadlines.
Overthepast15years,allofthemajor33kVand11kVfeedershavebeenreplacedorrefurbished,andareinverygoodconditionoverall.
Whileoverheadlinesaresubjecttomorefaultsthanundergroundcables,duetosuchthingsaslightningandbirdstrikes,itisrelativelyeasyandquicktogetthembackintoservice.
Themaximumrepairtime(aboutfourhours)isrequiredwhenacomplexpolestructureisdamageddueto,say,avehiclerunningintoit.
DistributionautomationequipmentinstalledoverrecentyearshasallowedWestpowertodiagnoseandlocateruralfaultsquickly,andthenrestoresupplyremotelytoadjacentareaswithouthavingtogetstaffonsite.
Sparesofalltypesofconductorsandpolesarekeptinstocktocovermosteventualities.Accesstoothernetworkcompanies’stocksislikelyintheeventofamajordisaster.
3.3.6 33kVCables
InWestpower’scase,thehighestvoltageundergroundcablesitoperatesareatavoltageof33kV.TheseareofstandardPaper-InsulatedLead-CoveredSteelWireArmoured(PILCSWA)constructionoveraveryshortdistanceoflessthan100mwithbackup.TheseareusedasfeedercablesattheDobsonsubstation.
In general, underground cables are very reliable as they are not exposed to the external environment and,if carefully laid, should give at least 50 yearsof good service. Themost likelymodeof failure is damagebycontractorsusinghydraulicexcavators.
Thefailurerateofcablesisrelativelylow;however,repairtimesarecritical.Undergroundcablesarethemajorconstraintinthisarea.
3.3.6.1 Hendrix33kVSpacerCable
InSouthWestland,therearetwosectionsoffullyinsulated33kVoverheadconductors,bothconstructedusingtheHendrixSpacerCableSystem.
Byusing this specialist conductor,Westpowerwas able tomitigate theenvironmental effectson a sensitiveenvironmentwithhighscenicvalues.Infact,thislinerunsthroughaNationalPark.A2kmstretchofthiscablealsorunsclosetoLakeWahapo(thisusesthreeseparate, fully insulatedconductors,heldapartby insulatedspacers).
TheHendrixsystemhasa40-yeartrackrecordintheUnitedStatesandhasproventobeveryreliable.
Spacer cablewas installed for a 6 km stretchof line around LakeMapourika in 2000, and this replaced theexistingAerialBundledCable(ABC)systemthathadproventobeunreliable.
Thisnewsystemalsoinvolvesfullyinsulatedoverheadconductors,butinsteadoftheindividualphasesbeingbundledtogether,theyarespacedapartbyinsulating“spacers”everytenmetres,andsupportedbyaseparate,highstrengthcatenarywire(Figure3.11).
Experiencetodatewiththissystemhasbeenexcellent,evenwhenlargetreeshavefallenacrossthecatenarywire,as thesystemcontinues tooperatewithout theconductorsbeingdamaged.Repairs canalsobemadequicklybecausethereisnoneedtoapplystresscontrolmeasureswhenjointing.
68 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.3.7 ConditionofSpecificLineComponents
3.3.7.1 WoodPoles
The Greymouth-Kumara 66 kV line wasconstructedin1977usinguntreatedhardwoodpoles and these are now beginning to showsignsofdeterioration.However,approximately50%of the linehad ground-linepreservationwork done on it in the early 1990s, whichshould extend the life of the poles involved.Overthenextfewyears,conditionassessmentofthelinewillbesteppedupanditislikelythatapolereplacementprogrammewillbeinitiatedtowardtheendoftheplanningperiod.
The 33 kV line south of Hokitika to Harihariwasconstructedinthemid-1960sandalargeproportion of the untreated hardwood poleshavenowreachedreplacementcriteria.Apolereplacementprogrammewasinitiatedin2008andthisisexpectedtocontinuethroughuntil2012.
3.3.7.2 ConductorsandConductorAccessories
Copper7/.080”conductorisfittedtotheDobson-Arnoldlines.Muchofitisstillinreasonableconditionandcanremaininserviceforafurthertenyears.However,vibrationdamageandcorrosionhastakenitstoll.
Noreplacementisplannedatthisstage,asanyfurtherhydrogenerationdevelopmentatArnoldwillrequiretheconductortobeupgradedanywaytoremoveaneffectiveconstraint.
Mostoftheconductorinstalledsincethe1960suptothemid-1990s,hasbeenconventionalDogACSRwithagreasedsteelcore.AllconventionalACSRispronetocorrosion,especiallywherethelineissubjecttowindbornesaltcontamination.Thiswillbecarefullywatched,althoughthereisnoevidencetodateofsuchdeterioration.
Since the mid-1990s, Iodine AAAC conductor has been used exclusively for subtransmission lines and theenhancedcorrosionprotectionaffordedbythisalloymaterialshouldresultinatleast60years’effectivelife.
Mostlinesarefittedwithspiralvibrationdampers,whereappropriate,andthishasgreatlyreducedtheincidenceofvibrationdamagetoconductorsandfittings.TheArnold-DobsonandGreymouth-Kumaralinesareexceptionstothis,andastudywillbecarriedouttodeterminewhetheraretrofittingprogrammeiswarrantedtominimiseanyriskofdamage.
3.3.7.3 InsulatorsandInsulatorFittings
Thereareanumberofolderporcelaindiscsnowknown tobeunreliabledue to inherentdesign faultsplusin-serviceinternaldeterioration.Thishasnotbeenamajorproblemonsubtransmissionlinesbecauseoftheuseofmultiplediscs,whichaffordssomeredundancy.Nevertheless,theeffectsofongoingdeteriorationwillhavetobetakenintoaccountinthelifecyclemanagementplan.
Replacementinsulatorsareeitherglassorpolymerdiscinsulatorswithroundpins.
Problemshavebeennotedwith the 33 kV EthylenePropyleneDieneMethylene (EPDM)polymer dead-endinsulatorsthathavefailedandshowedsignsofchalkingandcracking.Thecrackingisthroughthesheds,andaxialtothefibreglassstrengthmember,withnoapparentpenetrationtowardthecore.
Figure3.11-Hendrix33kVSpacerCable
ASSETSCOVERED 69
Aninvestigationwascarriedouttoassesstheseriousnessoftheproblemandtherisk,ifany,thatthisapparentdeteriorationposes.An independent consultant suggested that the LAPP-manufactured33kVunitshaveaneffectivein-servicelifeofapproximatelytenyears,whichsoonwillbeexceeded.Areplacementprogrammewillneedtobeinitiatedtomitigatetheriskoffuturefailure.
3.3.8 ConditionofAccessRoads
TheDobson-Arnoldlineisservicedbyagoodqualityaccessroadthatmaybeusedbytrucksandfour-wheeldrivevehicles.WhileitisnotWestpowerpolicytoprovideforthisstandardofaccessroad,itsexistenceowesmuchtotheline’sheritageasaTranspowerasset.Theroadisinexcellentconditionforthepurposeintended.
TheKumara-Kawhakalinehadanaccessroadconstructedtoallowthelinetobebuilt,andissuitableforfour-wheeldrivevehicleandexcavatoraccess.Thisroadisinreasonableconditionforthelevelofuserequired.
NospecificaccessroadshavebeenconstructedtogainaccesstotheGreymouth-KumaraorMtHerculeslines.
Acontingencysumisincludedintheannualbudgettoprovidemaintenanceonalreadyformedaccessroads.
3.4 Distribution Assets
DRC - $25,183,835
ODRC - $24,988,272
Electriclinesandcablesoperatingatavoltageof11kV,includingassociatedeasementsandaccessways,makeupthebulkofWestpower’sinfrastructureassets,intermsofbothvalueandnumber.
Figures3.12and3.13showtheextentofWestpowerdistributionlineassetsspreadthroughoutthelengthoftheWestCoast.
3.4.1 AssetJustification
ThesearecoreassetsforELBs,andcomprisethedistributionlinesandcablesthatdeliverelectricityat11kVtothedistributionsubstationsthatsupply415Vor230Vtoindividualinstallations.Theseassetsarethereforeessentialtotheoperationofthenetwork.
3.4.2 11kVOverheadLines
Table3.14belowliststhetotaloverheaddistributionlineassetsownedbyWestpower.
Westpowerownsalargevarietyofdistributionlinesandcablesthatcoverawideageprofile.Overheadlinescoverthreebroadgroupsincluding:
• Earlyhardwoodpolelines,
• Concretepolelines,
• Treatedsoftwoodpolelines.
Since1972,mostofthemajorlineshavebeenreconstructedwithconcretepoles,andAAACorACSRconductors,andthishasresultedinafewremainingpocketsofearlierhardwoodlinesintheGreymouthandReeftonareas.Notwithstandingthis,therearesomenotableexceptions,suchastheFox-ParingaandCoastRoadlines,whichusedtreatedsoftwoodpolesforenvironmentalandconstructabilityreasons.
Table 3.14 - 11 kV Lines Summary
Type Circuit Length (km)
LightOverhead 1007
MediumOverhead 391
HeavyOverhead 7
70 WESTPOWERASSETMANAGEMENTPLAN2012-2022
MOANAMOANA
INANGAHUAINANGAHUA
HAUPIRIHAUPIRI
PUNAKAIKIPUNAKAIKI
DOBSONDOBSON
REEFTONREEFTON
RAPAHOERAPAHOE
KOKIRIKOKIRI
GREYMOUTHGREYMOUTH
NGAHERE NGAHERE
KUMARA KUMARA
PIKE RIVERPIKE RIVER
KEY
Westpower Distribution Network 11 kV
Figure3.12-NorthernSectionofWestpower’sDistributionLineAssets
ASSETSCOVERED 71
OTIRAOTIRA
KANIEREKANIERE
PARINGAPARINGA
FOX GLACIERFOX GLACIER
FRANZ JOSEF.FRANZ JOSEF.
ROSSROSS
HARIHARIHARIHARI
WAITAHAWAITAHA
HOKITIKAHOKITIKA
WAHAPOWAHAPO
KUMARA KUMARA
WHATAROAWHATAROA
KEY
Westpower Distribution Network 11 kV
Figure3.13-SouthernSectionofWestpower’sDistributionLineAssets
72 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Softwood or concrete poles are used for allreplacement or new construction work, and thesetypesmakeupover60%ofthepolepopulation.AnexampleofamodernconstructionisshowninFigure3.15.
The insulators consist of porcelain pin insulators,andamixtureofporcelain,glassandpolymerstraininsulators. Westpower has used stand-off postinsulators in some environmentally sensitive areas.Apart from these sections, however, conventionaloverheadconstructioniswidelyemployed.
3.4.2.1 DistributionLineCondition
Theconstructionof lines inthepasthasoftenbeendrivenbycustomerdemandsandpoliticalinfluences,whichhasresultedintheseeminglyerraticnatureofthe line ages. Amajor undergrounding programmeextending throughout the 1980s, coupled with anoverhead feeder replacement extending from 1992throughto1999,hasresultedinanaveragelineageof20years.
Thepresentconditionofanydistributionlineislargelyafactorofitsage,thequalityofmaterialsusedandtheenvironmentalcorrosivenessofthelocationsittraverses.
Itisdifficulttogeneraliseabouttheconditionofdistributionlines.However,ifweexcludethoselinesinsevereenvironmentsandlookattherest,thenWestpower’slinestendtofallintothreebroadgroups.
Figure3.16showstheageprofileofdistributionlines,bycircuitkilometre.
0
50
100
150
200
250
300
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 40+ UNKNOWN
Leng
th of
Line
(km)
Age (years)
Figure3.16-DistributionLineAgeProfile
Figure3.15-ModernLineConstruction
ASSETSCOVERED 73
3.4.2.2 EarlyWoodPoles
Theselinesare11kVsingle-circuitanddouble-circuitconstruction,andmanyofthemarearound40yearsold.Fewofthe lineshavehadreplacementsofmajorcomponentstokeeptheminserviceand,overall, theyaregenerallyinpoorcondition.Generally,theconductors(usuallycopper)havesomelimitedremaininglife.
Becauseofthemajorreplacementprogrammerecentlycompleted,woodpolelinesaregenerallylimitedtospurlinesortheremoteendsofruralfeeders.
3.4.2.3 ConcretePoleLines
Theselinesaremostlysingle-circuit,wiredinACSRandAAACconductor,andarebetween1and25yearsold.
Twotypesofconcretepoleswereused:
• Theearlierheavy-reinforcedtypemanufacturedbyWestpowerfromthe1970suntiltheearly1980s.Theseareoftenreferredtoas“Hokitika”concretepolesbecauseofwheretheyweremanufactured;
• Pre-stressedconcretepolesmanufacturedsincetheearly1980sbyalocalbridge-beambuilderunderlicensetoStresscrete.
Thepolesarestructurallysoundandhaveanexpectedlifeof60years.
Therehasbeensomeconcernregardingthelong-termeffectoftheleachingoutofcementbelowgroundlevelinthe“Hokitika”concretepolesincertainsoilconditions;however,theextenttowhichthisaffectsthestructuralintegrityofthepoleisstillunderinvestigation.
3.4.2.4 TreatedSoftwoodPoleLines
Constructionoftreatedsoftwoodpolelinesbeganin1992foreconomicreasonsandcontinuedthroughuntil1994 formain lines,when the cost differential between concrete and treated softwood poles underwent areversal.TheselinesarewiredinACSRorAAACconductor.
3.4.3 11kVDistributionLineComponents
Table3.17summarisesthepresentnumbersofspecificdistributionlinecomponents.
Table 3.17 - Summary of Distribution Line Components
Components No. %
Structures (11 kV)
Poles-Wood Hardwood 2083 16%
SilverPine 13 0%
Softwood 1162 9%
Larch 4 0%
Poles-Concrete Hokitika 2992 23%
Stresscrete 6485 50%
Spuncrete 15 0%
Buller 42 0%
Other 205 2%
TotalStructures 13,001 100%
Crossarms
11kV 22296 70%
400V 7913 25%
Service 1503 5%
TotalCrossarms 31,712 100%
74 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.4.3.1 WoodPoles
Thereareapproximately2200distributionwoodpoles inservice.Anestimated252polesareassessedtobecurrentlyatreplacementcriteria,orwillreachthemwithinfiveyears.Approximatelyanother344areestimatedasneedingtobereplacedbetween2012and2015.
3.4.3.2 ConductorsandConductorAccessories
Copperconductorisfittedtothemajorityofolderlines.Muchofitisstillinreasonableconditionandcanremaininserviceforafurther10-20years.However,vibrationdamageandcorrosionhavetakentheirtoll.
Most of the conductor installed since the 1960s has been conventional ACSR with greased steel cores. AllconventionalACSRispronetocorrosion,especiallywherethelineissubjecttowindbornesaltcontamination.MuchoftheearlyACSRinexposedareashasbeenidentifiedforcarefulinspectionoverthenexttenyearstodeterminewhat,ifany,replacementprogrammeshouldbeundertaken.
3.4.3.3 InsulatorsandInsulatorFittings
Thereareanumberofolderporcelaindiscsnowknown tobeunreliabledue to inherentdesign faultsplusin-serviceinternaldeterioration.Inparticular,therelativelyrecentinternationaldiscoverythatolderconventionalporcelaincandevelopporosityduringitsservicelife(leadingtopuncturesandmechanicalseparation)plustheknownpoorqualityofmuchoftheolderporcelaininsulationhaveprovidedaddedweighttothereplacementprogramme.
Replacementinsulatorsareeitherglassorapolymerdiscinsulatorwithroundpins.
ProblemshavealsobeennoticedwithEPDMpolymerinsulatorsshowingsignsofchalkingandevencracking.Aninvestigationiscurrentlyunderwaytoassesstheseriousnessoftheproblemat11kVandtherisk,ifany,thatthisapparentdeteriorationposes.
Aconditionassessmentprogrammewasbeguntoconfirmtheservicelifeofanumberofolder33kVporcelainpininsulatorsusedonthe33kVsubtransmissionlinefromNgaheretoReefton.
Approximately800oftheseinsulatorswereinstalledsecond-handinthemid-1990sasacost-savingmeasure.Initially,theywereinstalledinthe1960sonthelinetoRuatapusouthofHokitika,butthenremovedabouttenyearslaterandplacedinstorageuntilbeingusedonthelinetoReefton.
Duringcommissioningofthelinein1999,twooftheseinsulatorsfailed,resultinginspectacularearthfaults.A further insulator failed in January2000 followinga severe lightning storm.Thesecombinedevents, raisedsomedoubtastotheongoingserviceabilityofthisparticulartypeofinsulator.Subsequentanalysisofarandomsampleofinsulatorsconfirmedthatthegeneralpopulationofinsulatorsisingoodcondition,however,andnofurtherremedialactionisrequired.
CorrosionproblemshaverecentlybeenidentifiedwiththeDulmisonpre-formedinsulatortiesusedtoattachaluminiumconductorstoinsulators.Whentheseareinstalledincoastalenvironments,severecorrosionoccursundertheneoprenecoverusedtocushioncontactbetweentheHelitieandtheinsulator,leadingtocompletefailureoftheunit.
Table 3.17 - Summary of Distribution Line Components
Components No. %
ConductorsandAccessories
11kVConductor(km) 1424
400VConductor(km) 163
Insulators 11kV 98320 61%
400V 47327 30%
Service 14402 9%
TotalInsulators 160,049 100%
ASSETSCOVERED 75
3.4.4 11kVCables
ThemajorityofWestpower’sundergroundHVcablenetworkconsistsof11kVcableofbothPILCSWAandCross-linkedPolyethylene (XLPE) construction.Bothof thesearedry-type constructions that allow for joints tobereadilymadewithinfourhoursafterthefaulthasbeenlocatedandthetrenchdug.
IntheGreymoutharea,thereticulationintheCentralBusinessDistrict(CBD)consistsofadouble-redundantringof11kVcables.At leasttwoseparateHVcableswouldhavetofail tocauseanoutageofadistributiontransformer.Evenifthiswastohappen,theLVnetworksarehighlyinterconnectedandwouldcontinuetosupplymostoftheload.
AllofWestpower’scablesareoperatingwellwithintheirthermalratings,eventakingaccountofthepossibilityofpoorthermalresistivitybackfill.
CablemakesupaverysmallportionofWestpower’stotalHVassets,andisgenerallylimitedtoCBDsorzonesubstations.Thereare,however,someexceptionstothis,suchastherecreationalareasofMoanaandPunakaiki.
Throughoutthe1980s,Westpowerhadapolicyofundergroundingcablesinurbanareasandthisresultedinasignificantamountoftheoverheadreticulationinthoseareasbeingreplaced.Asacaseinpoint,themajorityofHokitikaisreticulatedunderground,andundergroundHVcablesareusedthroughouttheCBDandneartheairport.
Whilesomeoftheolder11kVcablesaroundGreymouthwereinstalledinthe1950’s,manyofthesehavesincebeenoverlaidorreplacedwithmodernequivalents.PILCSWAwasthestandardfornormaldistributionpurposesuntilthemid-1980s,whenXLPEinsulationgraduallycameintovogue.
Table3.18showsthedistributionof11kVundergroundcablesintheWestpowernetwork.
3.5 Reticulation Assets
DRC - $5,306,762
ODRC - $5,306,762
Theseassetsinclude400Voverheadlinesandcablesusedtoreticulateelectricitytotheboundaryofconsumer’spremises.
3.5.1 AssetJustification
Oncetheelectricityis“steppeddown”from11,000Vto415Vatdistributionsubstations,the415Vreticulationassets,comprisingoverheadlinesandcables,arenecessarytodeliverelectricitytotheboundariesofindividualinstallations.Assuch,theseassetsareacorepartofWestpower’snetwork.
3.5.2 Overhead400VLines
Westpower uses a conventional overhead LV configuration with insulated conductors and cross arms; ABCconstructiontechniquesarenotemployed.
Intermsofconductorselection,copperwasusedextensivelyuntilthemid-1970s,butwasgraduallyreplacedwithaluminiumcoveredPolyvinylChloride(PVC)becauseofeconomicandconstructabilityconsiderations.
Table 3.18 - 11 kV Undergound Cable Summary
Type Circuit Length (km)
HeavyUnderground 0
MediumUnderground 42
LightUnderground 13
76 WESTPOWERASSETMANAGEMENTPLAN2012-2022
VirtuallyalloftheLVnetworksfromHokitikasouthwards,andsomewithintheurbanareaofGreymouth,havebeenreplacedinthelast20yearsbyundergroundcable.
However,insomeolderareassuchasReefton,therearestillsectionsofolderwoodpoleLVreticulation.
Westpowercurrentlyowns169circuitkmof400VLVlineassets,andthisisnotexpectedtochangedramaticallyovertheplanningperiod.ThelargestsinglecontributiontomoreLVlinesislikelytocomefromnewsubdivisions.Inthiscase,thereticulationwillalmostcertainlybeofundergroundconstructionbecauseoftherequirementsoflocalDistrictPlans.
ManyofthefactorsdescribedinSection3.4“DistributionAssets”–applyequallytotheirLVcounterparts.
Table3.19listsasummaryof400VoverheadlinesinWestpower’snetwork.
ThereasonforthisisthatmostoftheLVconstructionwascarriedoutatanearlytimeintheurbanareaswherethepopulationdensitywasthegreatest.Overtheyears,this largepopulationofassetsagedtogethertothepointwheretheyreachedtheendoftheirservicelife.This,inturn,requiredamajorrefurbishmentprogramme.
Ingeneral,theagedistributionoftheseassetsshowsanaverageageofaround20years.Figure3.20showstheagedistributionprofilefortheseassets.
3.5.2.1 SouthWestland
TheareasofHokitikaandSouthWestlandhavelargelybeenrebuiltoverthelast15years.Duringthistime,mostoftheurbanreconstructionhasbeencarriedoutusingundergroundreticulation,whichhasalifeofupto50years.LittlefurtherLVworkisthereforeplannedintheseareas.
0.00
10.00
20.00
30.00
40.00
50.00
60.00
70.00
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 40+
Le
ng
th o
f L
ine
(k
m)
Age (years)
Figure3.20-400VReticulationLineAgeProfile
Table 3.19 - 400 V Lines Summary
Type Circuit Length (km)
Light 125
Medium 49
Heavy 0
ASSETSCOVERED 77
3.5.2.2 Greymouth
InthecentralGreymoutharea,someoftheoldestlineswereplacedundergroundduringthe1980’s.Thechangeinfocusduringthelate1980’stoamorecommercialfootingledtothedemiseofundergroundingbecauseofthesubstantiallyhighercapitalcostinvolved.Fromtheearly1990son,theremainingrefurbishmentworkhasbeencarriedoutwithoverheadreticulation.
TheLVnetworksinthesatellitetownsofBlaketown,CobdenandRunangahavebeenreconstructedoverheadinthelasttenyearsandarecurrentlyingoodcondition.
3.5.2.3 Reefton
TheReeftonareaconsistsofsomeveryoldoverheadLVlineswhichareinneedofreplacement.Duringthe1980’stherewasanundergroundingprogrammeinplace,whichresultedinseveralstreets,includingthemainbusinessarea,beingundergrounded.InconjunctionwithTelecom,someareaswillcontinuetobeundergroundedwherecostsharingcanbeachieved.
Several small pocketsof LV lineswill alsoneedattentionduring theplanningperiod, and the required levelof replacement for these areaswill be identifiedduring condition assessment of the asset. Thiswill enablemaintenance to be effectively targeted and provide a solid foundation for the move to a Condition-BasedMaintenance(CBM)programme.
3.5.2.4 Underground400VCables
AvarietyofundergroundcabletypeshavebeenusedforLVreticulationspanningaperiodofsome30years.
Intheearlydays,single-corealuminiumcables,witheitherastrandedorsolidcore,werewidelyused.Overtime,however,multi-corecablesbecamepopularbecauseofthecostadvantages.
Astandardcablenowusedinresidentialareasis95mm2strandedaluminiumwithacopperneutralscreen.FordenserCBDareassuchasthetownofGreymouth,four-core185mm2cableswereused.
Currently,allnewurbansubdivisionsarereticulatedundergroundasarequirementoftheappropriateDistrictPlans.
Withtheexceptionofasmallnumberofold400VfeedercablesintheGreymouthCBD,mostoftheundergroundLVreticulationthroughoutWestpower’sareaislessthan20yearsoldandingoodcondition.
Theundergroundfittingsusedarealsoingoodcondition,mainlybecauseoftheirage;however,constantminormaintenanceisstillrequiredtoovercomeproblemsduetocorrosionorwateringress.
Table3.21showsthedistributionof400Vundergroundcable.
3.5.3 ConditionofSpecificLVLineComponents
3.5.3.1 WoodPoles
MostoftheLVwoodpolesareveryold,predominantlyhardwoods,andrangeinconditionfromverypoortogood.Theirconditionisbestassessedthroughanobjectivetestingprogramme.
Table 3.21 - 400 V Underground Cable Summary
Type Circuit Length (km)
Light 154
Medium 0
Heavy 0
78 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.5.3.2 ConductorsandConductorAccessories
All of theoverhead lines constructedover the last 20 years consistmainlyofPVC-coveredAAACandare ingenerallygoodcondition.
Forabout20yearspriortothis,PVC-coveredcopperconductorswereused,andthesealsoareingoodcondition.WhereaLVlineisreplacedorrefurbished,thistypeofconductorisreusedifitisingoodconditionandofanadequatecross-sectionalarea.
Alllinesover40yearsofagethathavenotbeenrefurbishedduringtheirlifestillusetheoriginalbraid-coveredconductors.Theconditionoftheseconductorsisverypoorandcouldbecomeasignificantsafetyhazardifnotattendedtointheshortterm.
Otheraccessoriesdemonstrateaconditioncommensuratewiththeageofthelineandarereplacedaspartoftheoverallreplacementprogramme.
3.6 Services
DRC - $637,381
ODRC - $637,381
Thisassetconsistsoftheequipmentusedtoconnectapproximately12,000consumerstoWestpower’snetwork.
Themajorcomponentsofthisassetaretheserviceprotectivedevices,whichmaybeoneofthefollowing:
• 400Vrewireablepolefuse,
• 400VHighRupturingCapacity(HRC)polefuse,
• 11kVdropoutfuse,
• 11kVcircuitbreaker.
Inthelastcase,theconsumerwouldownthe11kVcircuitbreakerandtheconnectionassetwouldbean11kVdisconnector.
Theservicelineonthepremisesoftheconsumerisownedandmaintainedbytheconsumer.
3.6.1 AssetJustification
Servicesincludeassetsrequiredtomakethefinalconnectionbetweenacustomer’sinstallationandWestpower’snetwork.ThesearenecessaryforanindividualcustomertotakesupplyfromWestpower.
3.6.2 ServiceLineCondition
Servicelinesoncustomers’premisesareownedandmaintainedbytheindividualcustomers.
Notwithstandingthis,therearesomeservicelineswhicharenotofanacceptablestandardduetoinsufficientclearanceorotherreasons.Westpowerisresponsibleforbringingtheseuptostandardbeforetransferringthemtothecustomer.
MostservicelinesareeitherPVC-coveredcopperorneutralscreenedcopper,andshouldgivegoodserviceformanyyears.Afewoftheveryoldservicesarestillofthebraidvariety,andthesearereplacedasamatterofcourseandatWestpower’scostwhenasectionofLVlineisrefurbishedorreplaced.
ASSETSCOVERED 79
3.7 Zone Substations
DRC - $11,810,454
ODRC - $11,786,895
Zonesubstationsareusedtotransformpowerfromtransmissionandsubtransmissionvoltagesof33kVandhigherdowntoWestpower’sstandarddistributionvoltageof11kV.
Thesesubstationscomprisebuildings,switchyardstructuresandassociatedhardware,HVcircuitbreakers,powertransformers,instrumenttransformersandamultitudeofotherassociatedpowersupplycablingandsupportequipment.Furthermore,thesubstationsrangeinsizefrom1MVAto40MVAandareusedtofeedlargeareasofWestpower’snetwork,thusplayingacriticalroleintheoverallreliabilityofWestpower’snetwork(pleaserefertoappendixC“NetworkReliabilitybyZoneSubstationandFeeder”forfurtherinformation).
Table3.22showsthezonesubstationcapacity,assetownerandcurrentmaximumdemandseenin2011.
Table 3.22 - Zone Substation Capacity and Maximum Demand
Substation Asset Owner Voltage (kV) Present Maximum Demand (MW)
Transformer Capacity (MVA)
Greymouth Westpower 66 13.444 2x15
Hokitika Westpower 66 18.452 2x20
Kumara Westpower 66 2.361 1x10
Dobson Westpower 33 1.875 1x5
Otira Transpower 11 0.694 1x2.5
Reefton Westpower 110 9.916 2x30
Blackwater Westpower 33 1.472 1x5
Ngahere Westpower 33 3.107 1x5
Arnold Westpower 33 3.357 1x5
Rapahoe Westpower 33 2.177 1x5
Ross Westpower 33 0.447 1x1
Waitaha Westpower 33 0.261 1x1
Harihari Westpower 33 1.044 1x1
Whataroa Westpower 33 0.772 1x1
Wahapo Westpower 33 3.091 1x5
FranzJosef Westpower 33 1.718 1x5
FoxGlacier Westpower 33 0.750 1x5
SpringCreek SolidEnergy 33 6.638 1x6/1x3
Globe Westpower 33 5.616 1x10
Logburn Westpower 110 1.104 1x30
Pike Westpower 33 0.761 1x20
80 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure3.23showsthelocationandsizeofWestpower’s19zonesubstations.
Figure3.23-Westpower’sZoneSubstations
BLACKWATERBLACKWATER
GLOBEGLOBE
LOGBURNLOGBURN
PIKEPIKE
DOBSONDOBSON
REEFTONREEFTON
FOX GLACIERFOX GLACIER
FRANZ JOSEF.FRANZ JOSEF.
ROSS ROSS
RAPAHOERAPAHOE
ARNOLDARNOLD
HARIHARIHARIHARI
WAITAHAWAITAHA
GREYMOUTHGREYMOUTH
HOKITIKAHOKITIKA
WAHAPOWAHAPO
KUMARAKUMARA
WHATAROAWHATAROA
NGAHERENGAHERE
Westpower's Zone Substations
1X 10 MVA Transformers
1X 5 MVA Transformers
2X 20 & 2X 5 MVA Transformers
1X 6 MVA Transformers
2X 10 MVA Transformers
2X 20 MVA Transformers
1X 1 MVA Transformers
1X 15 MVA Transformers
1X 20 MVA Transformers
33kV Subtransmission Line
66kV Transmission Line (Westpower)
66kV Transmission Line (Transpower)
110kV Transmission Line
ASSETSCOVERED 81
Figure 3.24 shows Westpower’s zone substation atGreymouth, which houses two 10 MVA 66/11 kVtransformerbanksandwasconstructedin1977.
The latticework steel structure is unique withinWestpower’sareaandreflectsthecommonstandardsusedbyTranspoweratthetime.
TheHVbusandequipmentinthissubstationisleasedto Transpower for operation as part of the nationalgrid.
At the other end of the scale are the 1MVA 33/11kV substations used at sites such as the Whataroasubstation,showninFigure3.25.
InstallationsatHarihari,RossandWaitahausesimilarstandarddesignstotheWhataroasite.
These substations use a small transformer with an externalregulatorforeconomicreasons.
Furthermore,theywereconstructedintheearly1990sandusemodernconstructiontechniques.
Westpoweralsoownsanumberofnominal5MVAsubstations,which are similar to the Arnold construction shown in Figure3.26.
ThesesubstationsuseOn-LoadTapChangers(OLTCs),andwereconstructed between 1984 and 2003. Sites included in thisclassificationareNgahere,Arnold,Rapahoe,WahapoandFranzJosef.
All zone substationsare connected toWestpower’s SCADA system for alarmmonitoringand remote controloperation.
3.7.1 AssetJustification
Zone substationsare required to transform subtransmission voltages (110kV,66 kVand33kV) to the localdistributionvoltageof11kV.TheseassetsformanintegralpartofthesupplychainandarestrategicallyspreadthroughoutWestpower’sarea.
3.7.2 PowerTransformers
Westpower has 43 power, voltage regulating and earthingtransformers installed at its zone substations (as opposedto distribution transformers, which are used in distributionsubstations).Ofthese,15arefittedwithOLTCs.
Figure3.24GreymouthZoneSubstation
Figure3.25-WhataroaZoneSubstation
Figure3.26-ArnoldZoneSubstation
82 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table3.27givesthegeneraldetailsofthepowertransformerpopulation.
Mostofthelargerpowertransformers(above1MVA)arethree-phaseunitsfittedwithOLTCs.
Earthing transformers areusedat zone substations connected to generating stations toprovide appropriatesourceearthingrequirements.Thesearehigh-impedanceunitsdesignedtolimitearthfaultcurrentsbyprovidingreactanceearthing.Theyalsocomprisea400Vsecondaryunittoprovidelocalservicetothesite.
3.7.3 OilContainment
Oilcontainmentfacilitieshavebeeninstalledatmajorsubstationsconstructedsince1993,includingtheDobson,Blackwater,Globe,Logburn,Pike,FoxGlacier,Reefton,ArnoldandHokitikasubstations.ThesefacilitieshavealsobeenretrofittedattheGreymouth,Kumara,Wahapo,Rapahoe,NgahereandFranzJosefsubstations.
3.7.4 Switchgear
Table3.29summarisesthepresentassetmixforthisequipmentusedinzonesubstations.
Table 3.29 - Circuit Breakers
Type 110 kV 66 kV 33 kV 11 kV Total Units
Outdoor
SF6 3 12 6 0 21
VacuumRecloser 0 0 22 16 38
Total Outdoor 3 12 28 16 59
Table 3.27 - Summary of Power Transformers
Type 110 kV 66 kV 33 kV 11 kV Total Units
PowerTransformers
Supply3phase 3 5 18 0 26
Subtotal 3 5 18 0 26
OtherTransformers
Earthing 0 0 2 1 3
VoltageRegulating 0 0 0 14 14
Subtotal 0 0 2 15 17
TotalTransformers 3 5 20 15 43
Figure3.28-PowerTransformersAgeProfile
0
0.5
1
1.5
2
2.5
3
3.5
4
4.5
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 40+
Numb
er of
Trans
forme
rs
Age (Year)
110kV
66kV
33kV
ASSETSCOVERED 83
3.7.5 GeneralCondition
MostofWestpower’szonesubstationsarelessthan30yearsoldanddemonstrateaconditioncommensuratewiththeirage.ThreeoftheoldersubstationsatHarihariandFranzJosefweresubstantiallyupgradedin2010,alongwithupgradesatFox,DobsonandNgaherein2011.
AlthoughtheGreymouthzonesubstationisnow35yearsold,upgradeandreplacementworkhasbeencarriedoutoverthelast10years,includingthereplacementofthe66kVcircuitbreakersoverthelastsixyears;all66kVbusworkinsulatorsandall11kVindoorcircuitbreakersin2002;andmid-liferefurbishmentsandprotectionupgradesonbothtransformersduringthe2009/10financialyear.
Thefollowingisalistofrecentlybuiltzonesubstations:
• Anew110/33/11kVzonesubstationwasbuiltatReeftonin2005.
• Anew110/33/11kVzonesubstationwasbuiltatLogburnRoadin2007.
• Anew33/11/6.6kVzonesubstationwasbuiltatGlobein2006.
• Anew33/11kVzonesubstationwasbuiltatPikein2007.
• Anew33/11kVzonesubstationwasbuiltatBlackwaterin2009.
TheenactmentofnewlegislationintheareasofoccupationalhealthandsafetyandtheResourceManagementAct(1991)mayrequireupgradingworkatstationsintheareasoffireprotection,stationearthingandsecurityfencing.
3.7.5.1 Transformers
Becauseofthetransformers’proximitytoacoastalenvironment,corrosionoftanksandfittingsisaconstantproblem,whichneedstobeaddressedbyanongoingpaintingprogramme.
Theremainingpopulationoftransformersisnowinagenerallygoodcondition,andnomajormaintenancewillberequiredthroughouttheplanningperiod.
DissolvedGasAnalysis(DGA)performedannuallyforthelastfewyears,hasallowedWestpowertomonitortheinternalconditionofitspowertransformerpopulationanddemonstratethat,ingeneral,thereislittleevidenceofinsulationagingordeterioration.
3.7.5.2 Switchgear
Ingeneral,all switchgear is inverygoodcondition,partlyduetoWestpower’svery lowfaultduty.However,theCoopertypeKFEVacuumreclosersareprovingtobeunreliableandhavebeenresponsibleforunplannedoutageswithfaultswiththeirauxiliaryswitches,CT’sandmicroswitches.AreplacementprogrammeisinplacetoreplacetheseunitswithViper-SReclosers.CircuitbreakersattheHarihariandFranzJosefsubstationshavebeencompleted in2010,and thoseatFox,Ngahere,Dobson in2011.TheWahapozonesubstation is tobecompletedin2012/13alongwiththeArnold,Whataroa,RossandWaitahazonesubstationsinthenearfuture.Vacuumreclosers,inparticular,haveverylowmaintenancerequirementsandareexpectedtoremaininserviceforatleastthenext20years.
Table 3.29 - Circuit Breakers
Type 110 kV 66 kV 33 kV 11 kV Total Units
Indoor
SF6 0 0 0 4 4
Vacuum 0 0 1 57 58
MetalcladPanels(BulkOil) 0 0 0 3 3
Total Indoor 0 0 1 64 65
TotalCircuitBreakers 3 12 29 80 124
84 WESTPOWERASSETMANAGEMENTPLAN2012-2022
AttheKumarasubstation,newSiemensSF666kVcircuitbreakerswereinstalledin1997aspartofanupgradeprojectalongwithanArevaSF666kVcircuitbreakerinstalledin2004;allareinexcellentcondition.FoursimilarArevaSF6circuitbreakerswereinstalledattheGreymouthsubstationandcompletedin2010.
Disconnectorsareconstantly subject tocorrosionofboltsandoperating linkages,andneedcontinualminormaintenancetokeepthemingoodorder.Afour-yearlypreventativemaintenanceprogrammeisinplaceforallzonesubstationstocounteractthis.
3.7.5.3 MinimumOilSwitchgear
ThelasttworemainingminimumoilcircuitbreakerswerereplacedattheGreymouthzonesubstationin2010.
3.7.5.4 OutdoorCircuitBreakers
ThispopulationhasanageprofileasshowninFigure3.30.
InternationalCouncil forLargeElectricSystems(CIGRE)studies indicatetypicalreplacementagesof40to45yearsforcircuitbreakersratedat80kVandbelow.
3.7.5.5 IndoorCircuitBreakers
Westpower’sindoorswitchgearinstallationscomprise59switchunitsintenlocationsofthefollowingtypes:
• 4SF6circuitbreakers,
• 52vacuumcircuitbreakers,
• 3bulkoilcircuitbreakers.
Inearly1999,Westpower’soldest11kVindoorswitchgearatKumarawasupgradedwiththeretrofittingofSF6circuitbreakertrucks.Alifeexpectancyof30yearsisnowexpectedfromthisequipment.
0
5
10
15
20
25
0-5 6-10 11-15 16-20 21-25 26-30 31-35 40+
Num
ber o
f Circ
uit B
reak
ers
Age (Year)
Figure3.30-OutdoorSwitchgearAgeDistribution(ZoneSubstations)
ASSETSCOVERED 85
Apotentialreliabilityproblemwas identifiedwiththe indoorbulkoilswitchgearatGreymouthafteraseriesofcatastrophic failureselsewhere inNewZealand.Prior to this, theSO-HI typeequipmenthadachequeredhistory,sufferingfromlowinternalclearances,resininsulationbreakdownandpoorimmunitytowateringress.Furthermore,theseindoorcircuitbreakers,whilebeingrelativelyyoungatanaverageageof22years,hadbeensubjected toaheavy-dutycycle throughout their lives.Accordingly, this switchboardwas replacedwithnewvacuumcircuitbreakersduring2003.
TheonlyotherbulkoilswitchgearinuseisGECtypeBVPequipmentinstalledatRapahoein1984.ThisequipmentisdueforreplacementwithReyrollevacuumtypemetalcladswitchgearin2014/15.
Figure3.31showstheageprofileofWestpower’sindoorswitchgear.
3.7.5.6 Disconnectors
DisconnectorsareHVswitches,whichareusedtodisconnectsectionsofoverheadlineorotherprimaryplant.
Newdisconnectorsgenerallygivesatisfactoryservice,butolderdesignsareunreliableandveryoldmodelsarenowbecomingelectricallyinadequate.Theonlyeffectiveremedyisreplacementoftheseunits.
SomeoftheolderCanterburyEngineeringtypeDA2disconnectorshavealsohadproblemswithfailinginsulators,but theoccurrenceof this typeof failurehasbeen infrequentenoughnot to require a special replacementprogramme.
The four-yearly preventativemaintenance programme checks the condition of all disconnectors in all zonesubstationsandcarriesoutgeneralmaintenancetoensurethedisconnectorsarekeptinagoodconditionforoperationandhavinganormaloperationallife.
3.7.5.7 Buswork
Mostbusworksystemsconsistofconcretepolesandtubularaluminiumbuses.Theseitemsrequirevirtuallynomaintenancethroughouttheirlives.
Figure3.31-AgeDistributionofIndoorSwitchgear
0
5
10
15
20
25
30
35
40
45
0-5 6-10 11-15 16-20 21-25 26-30 31-35 40+
Num
ber o
f Circ
uit B
reak
ers
Age (Years)
86 WESTPOWERASSETMANAGEMENTPLAN2012-2022
AttheGreymouthsubstation,agalvanisedsteellatticestructureisinplaceandisingoodcondition.Aconcernwiththistypeofconstructionoccurswhentheyreachanagewhererustingdevelops,whichrequirescontinuousmaintenancetocontain.Acommonproblemisadvanceddeteriorationofbolts,whichgraduallyreducestheoverall strength of the structure. Severe structural corrosion is generally found at substations located nearmarineenvironmentsandwhereindustrialworksnearbygiverisetoacorrosiveatmosphere.TheproximityoftheGreymouthsubstationtothecoastmeansthataregularinspectionprogrammewillhavetobemaintainedtocounterthis.Remedialmaintenancemayincludeperiodicpaintingofthestructure.Theolder66kVporcelaindiscinsulatorshavebeenreplaced.
Corrosionisalsoaprobleminthemetalpartsofcapandpininsulators,whichsupportbuswork.Onpostinsulatorsandstringinsulators,severerustingofthepinsleadstocrackingoftheporcelain,causingtheinsulatortofail.Also,theoldertypeofporcelainitselfhasbeenfoundtodeteriorate.Thesearethesameproblemsthataffectlineinsulators.Inthecaseofstrungbuswork,afailurecouldresultincollapseoftheconductor.Replacementwithmoderninsulatorsandgeneralupgradingofotherhardwarecomponentsisnecessarytoreducetheriskoffailures.
Crackingorspallingofconcretesupport structuresandrustingof the reinforcingsteelcanbeproblems thatrequireremedialaction.
3.7.5.8 InstrumentTransformers
Westpowerhasseveraloutdooroil-filledinstrumenttransformers,comprisingcurrent(excludingbushingtypes)andvoltageunitsinthe11kVto110kVrange.Itisestimatedthattheiraverageageisover15yearsandonlyasmallpercentageisinexcessof30yearsofage.
Generally,theyareinagoodconditionandrequireminimalmaintenance.Thecostofrefurbishmentandregularmonitoringissuchthat,inmostinstances,itismoreeconomictoreplacetheunitsiftheyfail.
Themostcommonformoffailureisduetostonedamagebyvandals,andthisishandledasrequired.
At the Greymouth substation, consideration is being given to replacing these transformers with modernequivalentsusingvandal-resistantcompositeinsulators.
3.7.5.9 EarthingSystems
Earthingsystemsinsubstationsconstructedwithinthelast15yearsweredesignedtoahighstandardandmeetcurrentindustryguidelines.
Alloftheolderzonesubstationsthatdidnotcomply,includingGreymouth,KumaraandWhataroa,underwentmajorupgradesoftheirearthingsystemscontemporaneouswithothersubstationenhancementworkcompletedwithinthelastsixyears.
AreviewiscurrentlyunderwaytochecktheimpactofEarthPotentialRise(EPR)onadjacentTelecomplant.
3.7.5.10ProtectionRelays
Most protection relays are in reasonable condition, and will only require minor inspection and servicingthroughouttheplanningperiod.
AminorproblemhasbeenidentifiedwithsealedbatteriesinCooperForm4CandForm3Areclosercontrolunits,wherebytheunitssuccumbtoahighrateofbatteryfailureafterthreeyearsofservice.Theinterimsolutionhasbeentocarryoutacyclicbatteryreplacementprogrammeofallrecloserbatteriesafterthreeyears,buteventhishasprovedineffectiveinisolatedcircumstances.Thenetresulthasbeensomelossofdiscriminationduringfaultevents,leadingtowiderpoweroutagesthanwouldhavebeenexpected.
Accordingly, all critical protection relays at zone substations will be brought up to the currentWestpowerstandard,whichincludesmodernnumericalSchweitzerprotectionrelays,overthenextthreeyears.Atthesametime,distanceelementsarenowbeingusedastheprimaryprotectionfor33kVfeeders.
ASSETSCOVERED 87
Somereplacementofprotectionrelaysduetoobsolescenceisscheduledwithintheplanningperiod.
3.7.5.11OtherStationEquipment
Batterybanksatstationswereoriginallyfittedwithautomotivelead-acidtypecells,whichtypicallygivealifeofabouttenyears.Thesehavenowbeenprogressivelyreplacedwithsealedlead-acid typebatteries,whichhaveahigher initial costbutgiveafargreaterlife(upto20years)andalsohavelowmaintenancerequirements.
Safety permit ropes and stands are also part of the stationinventories.
3.8 Distribution Substations
DRC-$2,988,413
ODRC-$2,988,413
Distribution substations generally consist of a distributiontransformerandassociatedequipmentincluding:
• 11kVdrop-outfuses,
• Lightningarrestors,
• LVfuses,
• Supportcrossarms,
• Earthingsystem.
Figure3.32showsatypicalthree-phasedistributionsubstation.
Thefittingoflightningarrestorsisnowstandardonallsubstations,andaretrofittingprogrammeoverrecentyearshasensuredthatvirtuallyeveryexistingsubstationmeetsthisrequirement.
Inadditiontotheseitems,largersubstationsratedat100kVAandabove,suchasthatshowninFigure3.33,willoftenhavethefollowingadditionalcomponents:
• Galvanisedsteelplatform,
• Maximumdemandindicator.
Because of the extremely corrosive coastal environment thatWestpowerisconfrontedwith,galvanisedsteelorCoretensteeltanksarestandardforalldistributiontransformers.
Figure3.32-TypicalDistributionSubstation
Figure3.33-Distribution
Substation>100kVA<200kVA
88 WESTPOWERASSETMANAGEMENTPLAN2012-2022
For large substations over 200 kVA, pad-mountconstructionisnormallyused,wherethetransformerisplacedonthegroundasshowninFigure3.34.
Extraassetsrequiredforthesesubstationsare:
• Concretepad,
• Fibreglasscover,
• HVandLVfeedercables,
• DINLVfusegear.
Table 3.35 lists the overall range and transformercapacities of the distribution substation sites, sub-totalledbynumberandtotalcapacity.
All substation data, including servicing records, arestoredintheMaximosystem.Inaddition,allsubstationsarelogicallylinkedtoindividualICPsforthepurposesofoutagenotificationsandnetworkreliabilityanalysis.
3.8.1 AssetJustification
Distributionsubstationsarerequiredtobreakdownthedistributionvoltageof11,000volts,toeither400voltsor230voltssuitableforsupplyingindividualinstallations.
3.8.2 DistributionSubstationCondition
WithinWestpower’snetwork,therearearound2300distributionsubstationscomprisingsingleandthree-phaseunitsrangingfrom5kVAto1.5MVA,inthevoltagerangeof33kVto11kV.
Theconditionoftheseassetscoversthewholerangefrombeinginneedofimmediatereplacementtobrandnew.
Allmainlinesubstationshavebeenrebuiltoverthelast20yearsaspartofWestpower’srefurbishmentprogrammeandaregenerallyinverygoodcondition.Therearestillsomeveryoldsubstationsonsomespurlines,however,whichwillneedon-goingrefurbishmentthroughouttheplanningperiod.
3.8.3 DistributionTransformers
DRC - $5,996,168
ODRC - $5,996,168
Avarietyof styles exist on thenetwork, fromearlypainted steel tankunits through to the currentmoderngalvanisedtanktransformers.
Aso-calledstainlesssteeltankwasalsotrialledforashortperiod,butthepoorqualitytankmaterialexhibitedlowcorrosionresistanceandtheunitwasnolongeraccepted.
AllunitsusedinWestpower’snetworkmustnowhavegalvanisedorCoretensteeltanks,andusestainlesssteelboltstomaintainresistancefromcorrosion.
Anumberofsmalltransformerspurchasedinthe1990sareexhibitingbushinggasketdeterioration.Aprogrammeisinplacetorefurbishtheseunits.
Inaddition,allunitshaveanoff-loadtapswitchfittedtoprovidearangeof+2.5%to–7.5%(ontheHVside)forvoltageregulation.
Figure3.34-PadMountSubstation
ASSETSCOVERED 89
Twothree-phase33kV/400VunitswerepurchasedspecificallytosupplytheremoteSouthWestlandbroadcastingsiteatMtHercules;oneunitwasmaintainedinserviceandtheotherkeptasaspare.
Single-phase33kV/400VunitssupplycustomersintheSouthWestlandareawhoareremotefromWestpower’sdistributionnetwork,butclosetotheHokitika-Harihari33kVline.Thecustomersacceptthatnosparewillbeprovidedfortheseunits.
Table3.35summarisesthedistributiontransformersbytypeandsize.
Table 3.35 - Distribution Substation Transformers Number and Capacity
KVA Inside Building Concrete Pad-Mounted Pole-Mounted
1PH 2PH 1PH 2PH 1PH 2PH
1 0 0 0 0 1 0
5 0 0 0 0 19 1
7.5 0 0 0 0 27 0
10 0 0 0 0 280 11
15 0 0 0 1 570 59
16.5 0 0 0 0 0 1
20 0 0 0 0 33 24
22.5 0 0 0 0 1 0
25 0 0 0 0 2 21
30 0 4 1 11 52 557
35 0 0 0 0 0 1
40 0 0 0 0 1 0
50 0 0 0 3 0 179
66.6 1 0 0 0 0 0
75 0 1 0 4 0 85
100 4 1 1 25 1 72
125 0 1 0 1 0 13
150 0 0 0 7 0 31
175 0 0 0 0 0 1
200 0 1 0 81 0 27
250 0 1 0 1 0 3
300 0 2 0 44 0 6
325 0 1 0 0 0 0
500 0 5 0 40 0 5
750 0 0 0 8 0 0
1000 0 3 0 6 0 0
1250 0 0 0 2 0 0
1500 0 0 0 0 0 0
2000 0 0 0 2 0 0
Subtotal 5 20 2 236 987 1097
Total 2347
90 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figures3.36and3.37showtheageprofileandkVAprofileofthedistributiontransformers,respectively.
Figure3.36-AgeProfileofTransformers
0
50
100
150
200
250
0-2
2-4
4-6
6-8
8-10
10-12
12-14
14-16
16-18
18-20
20-22
22-24
24-26
26-28
28-30
30-32
32-34
34-36
36-38
38-40
40-42
42-44
44-46
46-48
48-50
50-52
52-54
54-56
56-58
58-60
60-62
62-64
64-66
66+
Num
ber o
f Dis
trib
utio
n Tr
ansf
orm
ers
Age in Years
Figure3.37-KVAProfileofDistributionTransformers
0
100
200
300
400
500
600
700
Num
ber o
f Tra
nsfo
rmer
s
KVA
ASSETSCOVERED 91
Table3.38summarisesthepopulationofdistributiontransformers.
3.8.3.1 AssetJustification
Distribution transformers are the key componentof adistribution substation, and the justification for theseassetsisthesameasfordistributionsubstationscoveredinSection3.8.1.
3.8.3.2 DistributionTransformerCondition
Themajorityoftransformersarelessthan30yearsold,withamedianageofjustover20yearsandanegligiblenumberbeyond50yearsold(3%).Thiscoincideswiththeperiodofsystemdevelopmentinthe1960sandearly1970s.
Transformersaregenerallyingoodcondition,althoughforsomeoftheolderpaintedtransformers,refurbishmentand/orreplacementisrequiredratherthangeneralmaintenance.
Aproblemhasbeenidentifiedwithdeteriorationofbushinggasketsonsmallerunitsinthesix-tenyearagebracketwheretheseareinstallednearthecoast.Itappearsthatthesurfaceleakagecurrentattacksthegasketmaterial,eventuallyleadingtofailureofthegasketandwateringress,resultinginelectricalfailureofthetransformer.Toaddressthisissue,arefurbishmentprogrammehasbeguntoreplaceat-riskgaskets,andtoinstallreplacementbushingswithapartialsemiconductivecoatingaroundtheflangearea.
3.8.4 DominionDrop-OutFuses
Asastandarddesignpolicy,aDominionDrop-Out(DDO)fuseunitfusesallthedistributiontransformers,whicharefeddirectlyfromanoverheadHVline.
Upuntil1996,allfuseunitswereoftheECGoughtypemanufacturedlocallyformanyyears.AmajorreliabilityproblemwiththeseunitscausedWestpowertomovetotheABChancestyleofDDO.However,theseunitswerefoundnot topivotopenproperlywhenexposed toacorrosiveenvironment foraperiodoftime.AEMtypedrop-outsimportedfromAustraliawerethenimplemented,withtheGoughandChanceunitsbeingreplacedasscheduledmaintenancetakesplaceondistributionsubstations.FurtherproblemswiththeAEMunitsmeantthatacompletetechnicalreviewwasundertaken,andSandCunitsarenowbeingpurchased.
3.8.5 EarthingSystems
TheElectricityRegulationssuggestthatallsubstationearthingsystemsshouldbebroughtuptoastandardof10Ω.InWestpower’ssituation,becauseoftheveryhighsoilresistivitythatisoftenencountered,adesiredearthresistanceof10Ωisnotpracticallyachievableinallcases.
Nevertheless,theregulationsrequirethatearthingsystemsbetestedeveryfiveyears,andWestpowerisnowaddressingthisissueinearnest.Tomeettherequirements,aprogrammeofregularfive-yearlytestshasbeeninstituted.
Basedonexperience,itisexpectedthatduringthetestingphase,severalsubstandardearthinginstallationswillbeidentifiedthatarecapableofbeingpracticallyupgraded.Aprogrammeofupgradingtheseearthingsystemsusingdrivenrodsandextracopperconductorswillfollowdirectlyfromtheearthtestingexercise.
Table 3.38 - Summary of Distribution Transformers
PrimaryVoltage
Type 66 kV 33 kV 11kV Total Units
PowerTransformers
Distribution1phase 0 3 991 994
Distribution3phase 0 4 1349 1353
TotalTransformers 0 7 2340 2347
92 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.9 MV Switchgear
DRC - $1,468,901
ODRC - $1,468,901
Thisclassofequipmentincludes:
• Regulators,
• Disconnectors,
• 11kVcircuitbreakers,
• Reclosers,
• Sectionalisers,
• Ringmainunits,
• 11kVdryfuseunits.
These are not installed at zone substations. (MV switchgearwithinzonesubstationsisincludedinthatclassification.)
Lineregulatorsareinstalledonlong11kVlineswithsignificantloads near the end. Westpower has such installations atLongfordCorner(nearKokatahi),Cronadun(northofReefton)andtheHaupiriarea,anda33kVregulatoratHarihari.
Ingeneral,disconnectorsarestandardtwo-threepostunitsmadebySchneider(ex-CanterburyEngineering),butDA2type.SomeunitsarefittedwithCEBreakload-breakheads.
Westpowerhasusedarangeofreclosingequipmentoverthelast50years,buthasnowstandardisedontheuseofG&WViperStvacuumreclosersandENTECloadbreakswitchesforallfutureinstallations.
AtypicalreclosercanbeseeninFigure3.39.
Smallnumbersofold11kVcircuitbreakersarestillinuseasdistributionsubstationbreakers.
TheringmainunitsaremainlyReyrolleorABB“Safelink”type,SF6SDinsulatorsorABBoilinsulators,andarealllessthan25yearsold.ThereisoneremainingAndelectringmainunit.SomeHazemeyerdry-typeequipmenthasalsobeeninstalledinthenetwork,butitsuseisnotwidespread.AvariantofthisequipmentmadebyKronehasbeenphasedoutandreplacedbecauseofreliabilityconcerns.
Table3.40summarisesthepresentpopulationofMVswitchgear.
Fig3.39-TypicalRecloser
Table 3.40 - MV Switchgear
Type 33 kV 11kV Total Units
Disconnectors 3 388 391
LoadBreakDisconnectors 0 20 20
MotorisedDisconnectors 11 12 23
VacuumRecloser 1 37 38
LoadBreakSwitch(ENTEC) 0 14 14
RingMainUnit 0 44 44
GangedExpulsionDrop-outs 0 34 34
TotalUnits 15 549 564
ASSETSCOVERED 93
3.9.1 AssetJustification
Theseassetscoveradiverserangeofdevices,butgenerallyincludeswitchesofvarioustypesthatareusedtoprotectandsectionalisethenetwork.Intheeventofafaultonthenetwork,fuses,reclosersandsectionalisersareneededtoisolatethefaultedsectionsafelyandquickly,andtherebymaintainsupplytoothercustomersonunfaultedsectionsofthenetwork.Thedevicesarealsonecessarytoisolatesectionsoflinetoallowmaintenancetobecarriedout.
0
20
40
60
80
100
120
140
160
180
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 41+
Mnu
mbe
r of S
witc
hgea
r
Age (Years)
Disconnectors
Load BreakDisconnectorsMotorisedDisconnectorsLoad Break Switch(ENTEC)
Fig3.41-MVSwitchgearAgeProfile
02468
101214161820
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 41+
Num
ber o
f RM
U's
Age (Years)Fig3.42-MVSwitchgearAgeProfile
94 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.9.2 MVSwitchgearCondition
MostofWestpower’sMVswitchgear isrelativelymodernand ingoodcondition.However,arecentseriesoffaultsontheAndelect0utdoortyperingmainunitshasgivencausetomostoftheseunitsbeingreplacedoverthelastfiveyearsusingnewSF6units.WestpowernolongerusesSeriesIAnderlectoil-insulatedABBringmainunitstocloseontoexpectedfaults.
Otherexceptionstothisarethelargeanddiversepopulationofdisconnectors,whichwillneedtobemanagedonanasset-widebasis(seeSection3.9.6).
3.9.3 Regulators
Amovingcoilthree-phaseregulatorwasinstalledatLongfordCornerandisabout30yearsold.The2MVAunitwasprovingtobeunreliableanddifficulttofindreplacementpartsfor.Theunitwasduetobereplacedinthe2012/13financialyearbutfailedinAugust2011.Thiswasreplacedbytwosingle-phaseunitsandreturnedtoserviceinSeptember2011. It isplannedtobringtheregulatorsiteuptoanacceptable level inthisfinancialperiod.
Intheearly1980s,sixCooperSR32single-phase32stepregulatorswerepurchasedforFoxandKokiri.ThethreeinstalledinFoxweremovedtothenewsubstationsitefromCookFlatRoadin2003.ThethreeatKokiriweremovedtoHarihariwhenthe33/11kVsubstationwasdevelopedthereandKokiri’sfunctionwasreplacedbytheArnold33/11kVsubstation.In2007,oneoftheFoxunitsfailed(lightningwassuspected)soanewCooperunitwaspurchasedtoreplaceit.WiththeincreasingloadatFox(presentpeakatabout50A),the100Aregulators’capacitywaslimited.Theseregulatorswerereplacedwith200Aunitsin2009.
ThelineregulatoratCronadunwasanoldtap-changingunitpurchasedsecond-handfromTranspower.Thisunitreachedtheendofitseconomiclifeandrequiredconstantmaintenance.Sparepartswerehardtosourceandtheunitwascostlytomaintain.Thisregulatorwasreplacedwithrefurbished(ex-Fox)100Aunitsin2009.TheSR32sareinrelativelygoodcondition,thoughthepaintworkwillneedattentionsoon.
At the end of the 2003 dairy season, it was identified that the Haupiri area needed a voltage regulator tocompensatefortheongoingdevelopments.AsetoftwoGE100AregulatorswereboughtandinstalledneartheoldMiersMillsite.
TheSouthWestlandPotentialSupportprojectwascompletedin2005,involvinginstallationofa10MVA33kVvoltageregulatoratHarihari.ThiswaspurchasedsecondhandfromAurora(ex-Queensberry).ItsfunctionistoprovidesupporttotheSouthWestlandareaforperiodswhenWahapoisnotgenerating.Thiswillberemovedfromservicewhen66kVisreturnedtoSouthWestlandfromHokitika.
Eachof theRoss,WaitahaandWhataroasubstationshasa1MVA inductionregulator installed.Theyareallsimilarandwerepurchasedsecond-handfromTranspower.Theirmanufacturedatesareunknownbuttheyarethoughttobeinexcessof60yearsold.Twohavehadpaintworkrefurbishedlatelyandthethirdisprogrammedforrepainting.Theseallworkwellatpresentbutwouldnotbeworthfixingifamajorfaultoccurredwithinthem.Theirconditionandoperationisbeingmonitored.
3.9.4 CircuitBreakers
Agedindoorbulkoilcircuitbreakerssupplyingindoordistributiontransformershavereachedtheendoftheireconomiclives.Thesewillbereplacedwithfusedswitchunitsormodernequivalentsoverthenextfiveyears.
3.9.5 Pole-MountedReclosers
Thereare38pole-mounted11kVreclosersatvariouslocationsthroughoutthenetwork.Thirty-sevenofthesereclosersarecontrolledremotelybySCADA.ThesereclosersareacombinationofCoopertypeKFMEandViperSTreclosers.
ASSETSCOVERED 95
Over the last two years, Cooper KFE type reclosers have been progressively replacedwithG&WViper STreclosers,protectedbymoderndigitalSEL651Rprotectionrelays.Thisprojectwascompletedinthe2011/12financialyear.
3.9.6 RemoteControlledMotorisedDisconnectors
For some time,Westpower has been having trouble sourcing a reliablemotor drive unit for themotoriseddisconnectors.Westpowerhasnowdevelopedahydraulicactuator.Thesearegraduallybeingfittedtovariouslocationsonthenetwork.
Also TheDulmisonmotor driveunits had alsobecomeunreliable. Thesehavebeen gradually replacedwithENTECloadbreakswitches,withthelastremainingDulmisonunitstobereplacedthisfinancialyear.
3.9.7 Disconnectors
Themostdiverseassetsarethedisconnectors,whichareconstantlypronetocorrosiondamage.Mostmainlinedisconnectorshavebeenreplacedwithnewunitsduringtherecentfeederupgradeprogramme.Afive-yearlypreventativemaintenanceprogrammeisinplacetoensurealldisconnectorsaremaintainedtoagoodandsafeoperatingcondition.
Asoldertwo-insulatormodelswithout“flicker”or“wiping”arcinghornsarenotsuitableforuseonmainlines,aprogrammeforreplacementhasbegun.Otherthree-insulatormodelsarealsounsuitableonsomelinesbecauseofsystemloadings.Aneffortwillbemadetoidentifyandreplacetheseunitswithinthenextfiveyears.
Other,newerunitsdonothavesufficientcurrentbreakingcapacitybecauseofindividuallineloadings.Theonlysolutioninthiscaseistofitsuitableloadbreakheads.
3.10 SCADA, Communications and Protection
DRC - $233,333
ODRC - $233,333
0
5
10
15
20
25
0-5 6-10 11-15 16-20 21-25 26-30 31-35 36-40 41+
Num
ber o
f Rec
lose
rs
Age (Years)Fig3.43-VacuumRecloserAgeProfile
96 WESTPOWERASSETMANAGEMENTPLAN2012-2022
This includes all communications equipmentand radio repeater sites, as well as vehicle-mounted equipment and the SCADA plantincludingthemasterstationinthecontrolroom.Anyequipmentinstalledatzonesubstationshasalreadybeencoveredunderthatarea.
3.10.1 AssetJustification
TheSCADAandcommunicationsnetworksareessential to allowWestpower tomonitor andoperateitsnetwork.Intheeventofafault,thesesystems allow safe isolation of the defectiveplant and also fast restoration of supply to asmany customers as possible. The system isalso required for Westpower to monitor therealtimeperformanceoftheasset.Protectionsystems are required by legislation to ensuresafeisolationoffaultedequipment.
3.10.2 SCADASystem
Westpower’smasterSCADAstationisbasedupontheRealFlex6productsuppliedbyDATACoperatingonIBMServerhardwarerunningaQNXNeutrinooperatingsystem.
TheHuman-MachineInterface(HMI)isaWindows-basedclientsrunningonstandarddesktopnetworkedPCs.StorageofhistoricaldataisviaaMySQLDBMS.ThemainSCADAenginewasupgradedtothelatestversionofRealFlex(6.5)in2010.
TheoperatorHMI fordataandcontrol isdoneviaFlexviewsoftware,which is run in thecontrol roomonastandardWindowsXPPCsfittedwiththree22-inchLCDs.ThisgivestheoperatortheabilitytonotonlyviewSCADAdatabutalsosimultaneouslyuseanyotherPCsoftware.TheabilityofFlexviewtorunonPCsallowstheSCADAinformationtobeviewedfromalmostanywherewithinWestpower’scomputernetwork.
Figure3.44showstheSCADAmasterstationlayout.
The information viewed within Flexview is captured byRealFlexwhichrunsonapairofdedicatedHPProLiantDL140IntelXEONServers located in thesecureserver room,onebeingtheonlineserver,whiletheotheractsasahotstandbyin case of hardware failure. These servers run the latestversionof RealFlex and runon anoperating system calledQNXNeutrinoRTOS,whichissimilartoUNIX,andprovidesanetworkoperatingsystemdesignedforreal-timeapplicationsuchasSCADA.
AllvitalSCADAequipmentispoweredviatheUninterruptiblePowerSupply,whichprovidesaneight-hourbackupincaseofamajorpoweroutage.Furthermore,athree-phasegeneratorhas been installed to provide power to all equipmentincluding the Uninterruptible Power Supply (UPS), furtherextendingthisback-upperiodifrequired.Figure3.45showsthethree-phasegeneratorused.
Figure3.44SCADAMasterStation
Figure3.45-3-PhaseGenerator
ASSETSCOVERED 97
3.10.3 RemoteTerminalUnits
RealFlexhas theability tocommunicatewithmanydifferent typesofRemoteTerminalUnits (RTU)andfieldequipmentsuchasprotectionrelaysandPLC’sviamostoftoday’sstandardcommunicationprotocols.
Forsmallerzonesubstationsandremotesitessuchasreclosersandautomateddisconnectorsinthedistributionnetwork,AbbeySystemsTopcatII,TopCat,ModuLinkandMicroLinkRTUsareinstalled.
TheTopCatIIisasmallunitwithfixedI/OandalsohastwolocalcommunicationportstoconnecttoaPLCorprotectionrelay,whichprovidesadditionalcontrolandequipmentstatusdata.
Afeatureoftheseunitsisthepre-emptivecommunicationsprotocol,whichallowstheRTUtobepolledveryinfrequently,whilesimultaneouslyprovidingtheabilityfortheRTUtoupdatethemasterstationwheneverachangeofstateoccurs.
AbbeyRTU’suseWestpower’sVHFspeechradiochannelstocommunicatewiththemasterstation.
3.10.4 CommunicationSystem
Westpower communications network provides vital SCADA, telephony and tele-protection services for theWestpower distribution network, Transpower transmission network, TrustPower and Pike River Coal. Thecommunicationnetworkisamixoffibre,VHFRadio,UHFradioanddigitalradio.
3.10.5 CommunicationCables
Afibre-opticcablerunsfromtheserverroomintheTainuiStbuildingtotheGreymouthsubstation.Thisfibrelinkisusedforspeech,SCADAandsurveillancemonitoringoftheGreymouthsubstation.
AsecondfibrecablerunsfromtheserverroomtoChapelSt.ThisfibrelinkisusedforSCADAandoffsitecomputerbackups.
3.10.6 VHFNetwork
TheVHFspeechnetworkisanextensivesystemusedbyWestpower,ElectroNetServicesandTrustPower(WestCoastGeneration).
Asvehiclesarereplaced,regularremovalandreinstallationofexistingmobilesetstakesplace.
3.10.7 UHFNetwork
TheUHFnetworkisusedexclusivelytoprovidecommunicationpathsfortheagingDatatermscurrentlyinstalledattheWhataroaandWahaposubstations.ThisequipmentisalmostexclusivelyTait300seriesequipment,withasmallamountof800seriesequipmentinstalledinrecentyears.RepeatersitesarelocatedatPaparoa(nearGreymouth),MtHercules(nearHarihari)andtheWhataroasubstation.Mainspowerisreticulatedtoallofthesesites.
3.10.8 DigitalNetwork
Thedigitalradionetworkconsistsofamixtureofradiotechnologies,mostlyconsistingoflicensedpoint-to-pointradiofrequencies.DigitalradiolinksprovideInternetProtocoland,whererequired,serialandvoicechannelstoallmajorWestpowersubstations.CurrentsitescoveredbythedigitalnetworkaretheGreymouth,Dobson,Hokitika,Reefton,Ngahere,Arnold,Rapahoe,Kumara,Globe,Logburn,BlackwaterandPikesubstations.
3.10.9 Protection
Protectionsystemsaremainlyrestrictedtozonesubstations,withthenotableexceptionoflinereclosers,whichuseinternalproprietaryprotectionrelays.
98 WESTPOWERASSETMANAGEMENTPLAN2012-2022
AsWestpowerusedtohaveusedCooperPowerSystemtypereclosersasthestandard,theprotectioninvolvedisoftenthatsuppliedwiththereclosers.TheseoftencompriseamixtureoftheKFEorKFMEreclosersandFXA/FXBprotectioncontrollers.
Duetothehighmaintenancecostsandunavailabilityofsparepartsforthesereclosers,Westpowerhasdecidedtodevelopaprogrammetoreplacethemby2013/2014.ThenewrecloserapprovedbyWestpowerisaG&WViperSTcontrolledbyaSEL651Rprotectionrelay.
Allprotectionunitsarelessthan25yearsoldandareofsolidstateconstruction.
AllotherprotectionsystemsareincludedinSection3.7.
MostoftheprotectionassetsownedbyWestpowerarerelatedtooverheadlineprotection,andthemajorityoflinesareprotectedbyovercurrentandearthfaultrelays.
The33kVand11kVfeederprotectionequipmentisgenerallyofthesameageastheswitchgear(at11kV,theprotectionisoftenanintegralpartofthecircuitbreaker).
SchweitzerEngineeringLabsprotectionrelaysarenowusedforallnewzonesubstationfeeders.
3.10.10CommunicationSystemCondition
AllVHFcommunicationequipmentisinexcellentconditionafteracompletereplacementprogrammethattookplaceintheearly1990s.Tait2000seriesequipmentisnowusedthroughoutthenetworkandrarelygivestrouble.
TheexistingUHFanaloguesysteminSouthWestlandwillbemaintainedforseveralyears.
3.11 Ripple Injection Plants
DRC - $180,000
ODRC - $180,000
Westpowerownsfourrippleinjectionplants,withoneeachatReefton,Greymouth,HokitikaandDobson.
Theseplantsareusedforloadcontrolpurposesaswellasprovidingtariff-switchingsignalsforusebyretailers.
Retailersalsousethissystem,bycontractualarrangementwithWestpower,toshiftloadfromhigh-costtolow-costperiods,providedthatloadcontroloperationalrequirementsarenotcompromised.
HokitikaandGreymouthhaveEnermetSFU-K303series120kVAinjectionplants installed,whileDobsonandReeftonhaveEnermetSFU-K203series80kVAplants.Allplantshaveassociatedinjectiontransformers,couplingcellsandHVcircuitbreakers.Inallcases,theinjectionplantandmajorcouplingcellcomponentsarehousedinsideabuilding.
TherewasonlyoneinjectionpointatGreymouthfrom1982until1996,whenthesupplementaryplantswereinstalled.Duringthisperiod,thesystemreliedontheTranspower66kVtransmissionsystemforasignalpathtooutlyingareas.
All plants are controlled remotely by the SCADA loadmanagement system and locally via Abbey PowerlinkInjectioncontrollers.
Thefouron-lineplantsrunsynchronously,i.e.theyareabletoinjecttheidenticalripplewaveformateachofthefoursitesatthesametime.GPStechnologyhasmadethispossiblebyprovidinganaccuratetimebaseateachsitewhichisperfectlysynchronisedinfrequencyandphasewiththeotherbases.
Astand-alonerippleplantistobeinstalledatWahapozonesubstationin2011/12.Thiswillbeinstalledintheexisting shedandwill beusedonoccasion toprovide ripple control to SouthWestlandareawhenWahapogenerationisrunningislandedfromtheremainderofWestpower’snetwork.
ASSETSCOVERED 99
ThisplantwillconsistofthebestavailablepartsfromthedecommissionedPlesseyTRseries75kVAplantsatReefton,GreymouthandHokitika.
3.11.1 AssetJustification
RippleinjectionplantsareakeypartofWestpower’sdemandsidemanagementstrategyandareusedtosendripple signals to receivers in customers’ premises that allow interruptible loads suchaswaterheating tobeswitchedonoroff.Thisiscriticaltomaximiseuseofexistingassetsandavoidunnecessaryassetexpendituretocoverunnecessarilyhighpeakdemands.
3.11.2 RippleControlCondition
Westpowersoldallofitsripplerelaystothenewincumbentretaileron31March1999alongwithexclusiveuseofchannelsexistingatthattime.Therippleinjectionplantswereretainedforthepurposeofloadcontrolaswellastoprovidealoadswitchingservicetoretailersundercontract.
Allrippleinjectionplantsareeitherneworingoodorder,aswouldbeexpectedfromtheirageprofile.
3.12 Optimised Assets
Other than the following asset optimisation, there has beennoother overdesign or over-investment in theWestpowernetwork.Table3.46summarisestheoptimisedassets.
TheHokitikatoHarihari66kVlinewaspurchasedfromTranspowerin2001buthasonlybeenrunningat33kVsince1993,whenaphysicaloptimisationtookplace.AnewgenerationschemeatWaitahainSouthWestland,tentativelyplannedfor2016/2017,willinvolverecommissioningthelineata66kVvoltagelevel,andupgradingtheexistingconductorandtheconnectedsubstationsfrom33kVto66kV.
ThePunakaikifeederwasbuiltat33kVinthemid-1990swhenanillmeniteminewasplannedforthearea,butthisprojecthassubsequentlybeenshelved.Thelineisnowonlyrequiredtooperateat11kV.Notwithstandingthis,thecoastalenvironmentinwhichthislineoperatesischaracterisedbyextremesaltmistpollution,andtheadditionalcreepagedistanceaffordedbythe33kVinsulatorsemployedisregardedasbeneficialandreducesthenumbersoftransientfaultsinthearea.
TheWahapoandFranzJosef6MVAtransformerswerepurchasedsecond-handforaverylowpricefollowingtheclosureoftheTarakohecementworksinthelate1980sandtheovercapacitynowapparentismoretodowithoptimalcapitalinvestment(i.e.agoodbargain)thanevidenceofperceived“gold-plating”.Inanycase,theloadatFranzJosefisforecasttorequirethefull6MVAcapacitybytheendoftheplanningperiod.
Table - 3.46 Optimised Assets
Asset Asset Type Physical Rating Optimised Rating
WahapoZoneSubtransformer ZoneSubstation 6MVA 4MVA
FranzZoneSubtransformer ZoneSubstation 6MVA 5MVA
PunakaikiFeeder DistributionLine 33kV 11kV
Hokitika-HarihariLine SubtransmisisonLine 66kV 33kV
100 WESTPOWERASSETMANAGEMENTPLAN2012-2022
On19November2010adisasteroccurredat thePikeRiverCoalMine,andthishas resulted inasignificantreductionatthesite.AtthetimeofpreparingthisAMP,thefuturerequirementforelectricitysupplyatthemineislargelyunknownandthismaywellresultinstrandedassetsthatmayrequirefutureoptimisation.
3.13 Generation
Westpowercurrentlyownsnogenerationplant,butisplanningtore-enterthismarketsegmentthroughajointventurewithotherpartnerstoconstructa7MWhydroschemenearHariharicalledtheAmethystscheme.A20MWschemenearWaitahaisalsobeinginvestigated.
Customer-embeddedgenerationontotheWestpowernetwork(greaterthan1MW)isasshowninTable3.47.
TrustPowerownsallofthisgenerationplant,whichisconnectedtoWestpower’s11kVnetwork.
3.14 Load and Customer Characteristics by GXP
AsdiscussedinSection3.2,WestpowerissuppliedbysixGXPsspreadthroughoutitsarea.ThefollowingdiscussestheloadcharacteristicsandlargeconsumersineachoftheareassuppliedbytheseGXPs.
3.14.1 Reefton(RFN110)
TheReeftonGXPsuppliesloadfromLyellinthenorth,BerlinsintheeastandBlackwatertothesouth.
Theloadischaracterisedmainlybydairyfarminganddomesticload,althoughthereissomesmallcommercialloadinthetownofReefton,alongwithsomemining.
Table3.48showsthebulkcustomerssuppliedfromthisGXP.
3.14.2 Atarau(ATU110)
Asnotedabove,thisGXPwascommissionedin2007tosupplythenewPikeRivercoalmine.
Apartfromafewsmallfarmsanddomesticdwellingsinthearea,thisGXPisdedicatedtothesupplyofthemine.Withtherecentminedisaster,thefutureprospectsforthisGXPareunknownatthisstage.
3.14.3 Dobson(DOB033)
DobsonsuppliestheGreyValleyfromBlackwaterinthenorthtoPunakaikiinthewest,tonorthofGreymouthinthesouthandRotomanuintheeast.
Table 3.48 - Bulk Customers from Reefton GXP
Bulk Load Load Type Load Size
SolidEnergy-TerraceMine UndergroundCoalMine 75kW
OceanaGoldLimited-ReeftonGoldProject OpenCastGoldMine 5300kW
Table 3.47 - TrustPower Embedded Generation
Site Owner Year in Service KW Generated Connection Point Connection Voltage
ArnoldPowerStation TrustPower 1932 3,000 Arnold 11kV
DillmansPowerStation TrustPower 1928 3,500 Dillmans 11kV
KumaraPowerStation TrustPower 1928 6,500 Kumara 11kV
McKaysCreek TrustPower 1931 1,100 McKaysCreek 11kV
Wahapo TrustPower 1991 3,000 Wahapo 11kV
KaniereForks Truspower 1931 600 KaniereForks 11kV
ASSETSCOVERED 101
ThisGXPcoversawideareawithamixoffarming,industrial,residentialandholidayhomeload,butrelativelylittlecommercialload.ItwasoriginallyconstructedtosupplythetownofGreymouthandthecoalminingloadinthelowerGreyValleyandRunangaareas,butwassituatedtoofarfromGreymouthtownshiptosupplythegrowingloadthere.AseparateGXPwasconstructedinGreymouthinthelate1970s.
Table3.49showsthebulkcustomerssuppliedfromthisGXP.
3.14.4 Greymouth(GYM066)
TheGreymouthGXPsuppliesthetownofGreymouthandthesatellitetownshipsofCobdenandBlaketown,aswellasSouthBeach,RutherglenandParoatothesouth.
Aswouldbeexpected,theloadismainlydomestic,commercialandlightindustrial,withasmallbutgrowingloadresultingfromincreasedtourismtothearea.
Table3.50showsthebulkcustomerssuppliedfromthisGXP.
3.14.5 Kumara(KUM066)
TheKumaraGXPismainlyrequiredtoprovideaGIPforTrustPower’s10MWKumarahydroscheme,butalsosupplieslocalloadintheareafromGladstoneinthenorthtoJacksonsintheeasttoDuffersinthesouth.Whenthegenerationisnotrunning,apeakexportdemandoflessthan2MWisprovidedfromthissubstation.
Apartfromthesignificantgeneration,theloadtypeismainlyfarmingandruralresidential,althoughthereisonesignificantindustrialloadconnectedtothisGXP,asshownbelowinTable3.51.
3.14.6 Otira(OTI011)
TheloadatOtiraistotallyisolatedfromotherGXPs.Apartfromasmallhotelandafewhousesandbaches,themajorityoftheloadconsistsofthefanmotorsfortheOtiraTunnel.ThisisdetailedinTable3.52below.
Table 3.50 - Bulk Customers from Greymouth GXP
Bulk Load Load Type Load Size
Kingsgate-KingsgateHotel-Greymouth Hotel 300kW
Westfleet-WestfleetFishProcessing-Greymouth FishProcessingPlant 230kW
FreshChoice-Greymouth Supermarket 220kW
MonteithsBrewery-Greymouth Brewery 200kW
NewWorld-Greymouth Supermarket 310kW
TheWarehouse-Greymouth RetailStore 200kW
CoastHealth-GreymouthHospital-Greymouth Hospital 410kW
IPL-Plywood-Gladstone TimberProcessor 650kW
Table 3.49 - Bulk Customers from Dobson GXP
Bulk Load Load Type Load Size
SolidEnergy-SpringCreekMine-Dunollie UndergroundCoalMine 6500kW
RoaCoalMine-Roa(nearBlackball) UndergroundCoalMine 1200kW
StillwaterLumber-StillwaterSawmill TimberMill 700kW
CMP-PhoenixMeatWorks,Kokiri Abattoir 1360kW
Table 3.51 - Bulk Customers from Kumara GXP
Bulk Load Load Type Load Size
IPL-PlywoodMill-Gladstone TimberProcessor 550kW
Table 3.52 - Bulk Customers from Otira GXP
Bulk Load Load Type Load Size
TranzRail-Otira FanLoad 600kW
102 WESTPOWERASSETMANAGEMENTPLAN2012-2022
3.14.7 Hokitika(HKK066)
TheHokitikaGXPsuppliesthetownofHokitikaandallareassouthofthereasfarasLakeParinga,some200kmaway.
Theloadisamixofdairyfarming,residential,commercial,lightindustrialandlargeindustrial.SouthofWhataroa,theloadispredominantlydrivenbythetouristcentresofFranzJosefandFoxGlaciers.
Table3.53showsthebulkcustomerssuppliedfromthisGXP.
3.15 Voltage Support Systems
Westpowerregularlyusesvoltageregulatorsthroughoutitsdistributionnetworkandhasalsoinstalledregulatorsinits33kVsubtransmissionnetworkatHariharitosupportthevoltageinSouthWestlandwhenTrustPower’sWahapogeneratorisnotrunning.Althoughthisregulatorisgenerouslyrated,itwasboughtsecond-handforapricewellbelowmodernreplacementcostandcouldbereplacedbyasmallerunitifithadtobereplacedinthefuture.
Table3.54showsthescheduleofvoltageregulatorsinstalledinWestpower’snetwork.
Inadditiontovoltageregulators,anumberofHVcapacitorshavebeenstrategicallyinstalledthroughoutthe11kVdistributionnetwork.ThisimprovestheapparentpowerfactoroftheloadsseenfromTranspower’sGXPs,resulting in improvedvoltage regulation throughout theWestCoast. It also improves the voltageprofiles inindividual11kVfeedersleadingtoimprovedcapacityandreducedlosses.
Capacitorshavebeeninstalledatvariouslocationsthroughoutthe11kVnetwork.Thereareatotalof16capacitorsites,varyinginsizefrom0.3Mvarto1.2Mvar,withatotalcapacityof11.0Mvar.Allofthesecapacitorlocationsarelessthantenyearsold,andareacombinationofpad-mountedandpole-mounted.AlloftheaboveareunderWestpower’soperationalcontrol.
Mostof the capacitors installed in thenetworkarefixed, asopposed to switchedbanks, although switchedcapacitor banks exist inGreymouth,Hokitika, Franz Josef and Shantytown. The Franz Josef and ShantytowncapacitorsbanksareLV.
Becausecapacitorscanabsorbripplesignals,dependingonthesizeofthecapacitorandthesystemconfiguration,theyareofteninstalledwithseparateblockingchokestoavoidthisproblem.
Table 3.54 - Voltage Regulators
Regulator Site Voltage Size
Cronadun(northofReefton) 11kV 2250kVA
LongfordCorner(eastofHokitika) 11kV 2000kVA
Haupiri(eastofDobson) 11kV 2000kVA
Harihari 33kV 10000kVA
Table 3.53 - Bulk Customers from Hokitika GXP
Bulk Load Load Type Load Size
WestlandDairy-HokitikaDairyFactory-Hokitika MilkProcessingFactory 8200kW
WestcoLagan-RuatapuSawmill-Ruatapu TimberMill 880kW
SilverFernFarms-HokitikaVenisonFactory-Hokitika VenisonAbattoir 250kW
NewWorld-Hokitika Supermarket 200kW
WestlandMotorInn-FranzJosef Hotel 330kW
ASSETSCOVERED 103
Table3.55detailsthe11kVdistributioncapacitorsinstalledonWestpower’snetworkandthezonesubstationthattheyareconnectedto.
Inaddition,a7MvarcapacitorbankatGreymouthsubstationanda19.2MvarbankatHokitikasubstationareunderTranspower’soperationalcontrol.
3.16 Westpower Mobile Substation
Westpower’smobilesubstationwasdevelopedtoprovideaneffectivemeansofmaintainingelectricitysuppliestoareasservedbyzonesubstationswithsingletransformers.Essentially,itisaself-containedzonesubstationonwheels,andisratedat33/11/3.3kVand8/10MVA.
The33and11kVcablesarestoredonreelsandrolledouton-sitetoconnecttothelocal33and11kVnetworks.Alloftheswitchgear,SCADA,controlandprotectionsystemsareonboardandreadytogoatshortnotice.
Thissubstationcanbeusedto:
• Reducerestorationtimeintheeventofaforcedoutageofatransformeratasingletransformersubstation;
• Provideforatemporaryoraugmentedsupplytoanareaneartothesubtransmissionsystemwhenanewbuildisnotwarrantedforshortdurationpeaksorloads;
• Allow for extended maintenance outages at substations without interrupting supply to consumers forsignificantperiods.
ThisisoneofonlythreesuchsubstationsthatWestpowerisawareof,withtwooftheseintheSouthIsland.ThisinnovationhasimprovedsecurityandreliabilityinWestpower’snetwork.Sofar,ithasbeenusedonseveraloccasions,savinglossofsupplyorextracostfromtemporaryhireofgenerators.
Table 3.55 - Capacitors
Location Zone Substation Voltage Capacity
SouthHighway6-Hokitika Hokitika 11kV 1000kVAr
KaniereTram Hokitika 11kV 1000kVAr
Strongman Rapahoe 11kV 1000kVAr
FoxGlacier FoxGlacier 11kV 500kVAr
ReeftonSaddle Reefton 11kV 500kVAr
Kokiri Arnold 11kV 1200kVAr
Wahapo Wahapo 11kV 500kVAr
SolidEnergyBathHouse Rapahoe 11kV 1000kVAr
Punakaiki Rapahoe 11kV 300kVAr
Rotomanu Arnold 11kV 500kVAr
Kokatahi Hokitika 11kV 1000kVAr
Kotuku Arnold 11kV 500kVAr
Haupiri Arnold 11kV 300kVAr
Gladstone Greymouth 11kV 500kVAr
Shantytown,Rutherglen(Switched) Greymouth 0.4kV 500kVAr
FranzJosef(Switched) Franz 0.4kV 500kVAr
104 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure3.56showsthecompletedmobilesubstation.
A number of substations have beenmodified to accommodate themobile substation and thismodificationprogramme will continue throughout this planning period. The zone substation sites prepared for mobilesubstationconnectionsofarareArnold,Dobson,Ngahere,Rapahoe,FranzJosef,FoxGlacier,Whataroa,Globe,HarihariandBlackwater.
TheWaitahazonesubstationsiteistobepreparedformobilesubstationconnectionthisfinancialyear.
3.17 Substation Buildings
Westpowerhasanumberofbuildingsofdifferenttypeslocatedarounditsnetwork.Somehousesubstationsandsomehousecontrolequipment.Table3.57liststhebuildingswithintheWestpowernetwork,theirlocation,purposeandtypeofconstruction.
BuildingmaintenanceisanimportantpartofmaintainingtheconditionofassetswithintheWestpowernetwork.Theconditionofthebuildingswasassessedinthe2004LifelinessurveyreportforWestpowerandanumberofissueswerehighlighted.Theseincludedcheckingforthepresenceofreinforcingsteelintheearlypermanentbuildingsandensuringthatthesandwichpanelbuildingswererestrainedsufficientlytomitigatetheeffectsofearthquakeloads.
Azonesubstationbuildingclimatecontrolprogrammehasseenairconditioningunitsinstalledatvariouszonesubstations.Overthelastthreeyears,unitshavebeeninstalledatReefton,Globe,Blackwater,Pike,Logburn,Rapahoe,Greymouth,FranzJosefandHokitika.Thesehavebeeninstalledtoprovideaconstanttemperatureinzonesubstations,allowingforamorestableenvironmentforallequipmentinzonesubstationcontrolrooms.
Figure3.56-Westpower’sMobileSubstation
ASSETSCOVERED 105
Table 3.57 - Summary of Substation Buildings
Building Location Purpose Materials of Construction
ArnoldSubstation Storageandoffice Lighttimberframed
BadgerLaneSubstation Switchgear Permanent
DobsonSubstation Controlequipment Transportablesandwichpanels
FoxSubstation Controlequipment Transportablesandwichpanels
FranzJosefSubstation Controlequipment Lighttimberframed
GreymouthSubstation Switchgear&controlgear Permanent
HarihariSubstation Controlequipment Transportablesandwichpanels
HokitikaSubstation Switchgear&controlgear Permanent
MawheraQuaySubstation Switchgear&controlgear Permanent
RapahoeSubstation Switchgear&controlgear Lighttimberframed
RossSubstation Controlequipment Transportablesandwichpanels
WahapoSubstation Controlequipment Lighttimberframed
WaitahaSubstation Controlequipment Transportablesandwichpanels
WhataroaSubstation Controlequipment Lighttimberframed
DobsonSubstation Switchgear&controlgear Lighttimberframed
ReeftonSubstation Switchgear&controlgear Permanent
LogburnSubstation Switchgear&controlgear Permanent
NgahereSubstation Controlequipment Lighttimberframed
HarihariRegulator Controlequipment Transportablesandwichpanels
GlobeSubstation Switchgear&controlgear Transportablesandwichpanels
PikeSubstation Switchgear&controlgear Transportablesandwichpanels
BlackwaterSubstation Switchgear&controlgear Transportablesandwichpanels
106 WESTPOWERASSETMANAGEMENTPLAN2012-2022
4.0 LEVELS OF SERVICE
4.1 Introduction
InordertoproperlymanagethedeliveryofservicetoWestpower’sconsumers,itiscriticalthatappropriateKPIsaredevelopedtomeasuretheperformanceofthenetworkobjectively,andtoensurethattheseKPIscanbeappliedconsistentlyacrossthenetworkandovertime.Furthermore,theseKPIsmustberelevanttotheservicebeingdeliveredandreadilyunderstandablebyinterestedstakeholders.
OncetheKPIsarecreatedandreportingmechanismsareputinplacetomonitorthemroutinelyonanongoingbasis, performance targets can be developed to set clear benchmarks against which the service deliveryperformanceofthebusinesscanbeassessed.Thishasatwofoldbenefitofproviding:
• Ameansofmonitoringtrendsovertimeandmeasuringjusthowwellthebusinessisdeliveringservicetoitsconsumers;
• Awayofcreatingrealisticgoalsforthefuturethatprovideaclearbasisfortheprovisionofwelltargetedreliabilitymaintenanceorenhancementprogrammes.
ThetargetscreatedthroughthisprocessneedtobeconsistentwithWestpower’sbusinessstrategiesandassetmanagementobjectives,which,inturn,arederivedfromtheassetmanagementpolicythatformsthekeylinkagebetweenthecorporatedirectionofthebusinessandtheassetmanagementfunction.
Overtime,theKPIsandtargetswillcontinuetoberefined,basedonhistoricalperformanceandstakeholderrequirements.Inaddition,thetargetsmustreflectwhatisrealisticallyachievable,giventhecurrentconditionofthenetworkandthefinancialexpenditurecapabilityofthebusiness.
Furthermore,byadoptingthisapproachofsettingtargetsandthenmeasuringperformanceagainstthetargets,itispossibletoobjectivelyassessthesuccessofprogrammesdesignedtoenhancetheservicedeliveryperformanceoftheassetandthenmakeadjustmentstoprovideoptimumlong-termoutcomes.
Thetargetlevelsofservicemaygenerallybesubdividedintothefollowingtwomainareas:-
• Consumer-orientedperformancetargets;
• Othertargetsrelatingtoassetperformance,assetefficiencyandeffectiveness,andtheefficiencyoftheELBactivity.
ThissectionexplainsthetargetlevelsofservicethathavebeenchosenbasedontheKPIsdeveloped.Historicalperformanceagainstthesetargetlevelsisprovided,alongwithcommentaryonthereasonsforanyunderlyingtrendsorsignificantperturbations.Finally,ajustificationisprovidedforcurrentandfuturetargetlevelsofservicebasedonconsumer,legislative,regulatory,stakeholderandotherconsiderations.Includedinthisjustificationisadiscussionofhowstakeholderneedswereascertainedandtranslatedintoservicetargetlevels.
4.2 Customer-Orientated Performance Targets
Thekeyperformanceindicescommonlyusedthroughouttheelectricityindustrytoassesscustomer-orientedperformanceareSAIDIandSAIFIasdefinedinIEEEStandard1366:2033.
These are the same indices as used by all ELBs. By adopting an approach consistent with this standard,benchmarkingofWestpower’sperformanceagainstotherELB’sissupported.
This sectiondescribeshistoricalperformanceof thenetworkaccording to these indicesandcompares themwith related targets currentlymandatedby the targetedcontrol regimeunder thecontrolof theCommerceCommission.
NETWORKDEVELOPMENT 107
AsWestpowerisnowexemptfromsuchregulation,ithasdevelopedmoremeaningfultargetsthatarespecifictoparticularcustomergroupsandtypesofoutages,asdiscussed in thefollowingsections.ThesehavebeenderivedfromhistoricalperformanceaswellasexpectationsoftheimpactofparticularimprovementinitiativesthatWestpowerhasundertakenoverrecentyears.Westpowerdoes,however,stillcomeundertheElectricity(InformationDisclosure)Requirements2008andmuststilldiscloseindustrystandardperformanceindices.
4.2.1 ExtremeEvents
AsWestpower’sareaissubjectedtoextremeweathereventsfromtimetotime,itisimportanttodisaggregatetheKPIsintobaselinevaluesthatreflecttheunderlyingperformanceofthebusiness,andextremeeventvaluesthatresultfromenvironmentalexternalitiesthatarebeyondthereasonablecontrolofWestpower.Thebaselinevalues(i.e.thoseexcludingmajorevents)arethekeyindicatorsusedconsistentlythroughoutthisplan,andthereaderneedstoexercisecautionincomparingthesenormalisedstatisticswithinformationpublishedundertheinformationdisclosureregime,whichincludesallevents.
ThemethodofachievingthenormalisationofthemeasuredvaluesisbasedonIEEEStandard1366:2003,whereaMajorEventDay(MED)isdefinedandthenusedasathresholdtoexcludestatisticsthatrelatetoamajorevent.
Thisprocessusedto identifyMEDs is termedthe“Betamethod”. Itspurpose is toallowmajorevents tobestudiedseparatelyfromdailyoperationand,intheprocess,tobetterrevealtrendsindailyoperationthatwouldbehiddenbythelargestatisticaleffectofmajorevents.
AMEDisadayinwhichthedailysystemSAIDIexceedsathresholdvalue,TMED.TheSAIDIindexisusedasthebasisofthisdefinitionsinceitleadstoconsistentresultsregardlessofutilitysize,andbecauseSAIDIisagoodindicatorofoperationalanddesignstress.EventhoughSAIDIisusedtodeterminetheMEDs,allindicesshouldbecalculatedbasedonremovaloftheidentifieddays.
IncalculatingdailysystemSAIDI,anyinterruptionthatspansmultipledaysisaccruedtothedayonwhichtheinterruptionbegins.
TheMEDidentificationthresholdvalue,TMED,iscalculatedattheendofeachreportingperiod(typicallyoneyear)foruseduringthenextreportingperiodasfollows:
1. Collect values of daily SAIDI for five sequential years ending on the last day of the last completereporting period. If fewer than five years of historical data are available, use all availablehistoricaldatauntilfiveyearsofhistoricaldataareavailable.
2. Only those days that have a SAIDI/day value will be used to calculate the TMED (do not includedaysthatdidnothaveanyinterruptions).
3. Takethenaturallogarithm(ln)ofeachdailySAIDIvalueinthedataset.
4. Findαtheaverageofthelogarithms(alsoknownasthelog-average)ofthedataset.
5. Findβthestandarddeviationofthelogarithms(alsoknownasthelog-standarddeviation)ofthedataset.
6. ComputetheMEDthreshold,TMED,usingthefollowingEquation:
TMED=e(α+2.5β)
7. AnydaywithadailySAIDIgreaterthanthethresholdvalueTMEDthatoccursduringthesubsequentreportingperiodisclassifiedasaMED.
ActivitiesthatoccurondaysclassifiedasMEDsareexcludedfromthemeasuredstatistics.
Westpowerhas calculatedaTMEDbasedonall outages recordedduringafive-yearoutageperiod coveringApril2004throughtoMarch2009andthishasyieldedaSAIDIfigureof18.14systemminutes.Accordingly,thereportedstatisticshavebeennormalisedbyexcludingalleventsthathadaSAIDIvalueinexcessofthisfigure.*
HistoricalperformancehasbeenbasedonusingthesamenumberfortheTMEDinallyears,asopposedtousingarollingfive-yeardataset,asthereissomequestionaroundtheaccuracyofdatacollectedpriorto2003.*NotethatthisisslightlydifferentfromtheCommerceCommissionapproach,wherethestatisticfortheMEDiscappedtoamaximumvalueratherthanexcluded.Thepurposeofthisservicelevelperformanceexerciseisbestservedbyexcludingthevaluessothatthestatisticaleffectsofmajoreventsondailyoperationsarecompletelyremoved.
108 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure4.1-AreasDefinedWithinWestpower’sNetwork-North
Legend
OHLINE BY TERRAIN
TERRAIN
REMOTE
RURAL
URBAN
NETWORKDEVELOPMENT 109
Figure4.2-AreasDefinedWithinWestpower’sNetwork-South
Legend
OHLINE BY TERRAIN
TERRAIN
REMOTE
RURAL
URBAN
110 WESTPOWERASSETMANAGEMENTPLAN2012-2022
4.2.2 BreakdownbyLocation
Tofurtherdisaggregatetheperformancedataandcreatemoremeaningfultargetsagainstwhichperformancecanbeassessed,thedataarebrokendownbythefollowinglocations:
• Urban–includingmajortownsandisolatedareaswithurbancharacteristics(e.g.undergrounddistribution);
• Rural–generallyfarmingareasoutsideofmajortowns;
• RemoteRural–areasof SouthWestland southofHokitikabutexcluding local feedersofRoss,Waitaha,HarihariandWhataroa.
ThedefinitionusedforRemoteRuralisslightlydifferentthanthatusedbytheCommerceCommission(i.e.morethan75kmfromthenearestbase),asallofSouthWestland,extendinguptoaround150kmsouthofHokitika,isfedbyasingle33kVfeeder.Analysisisgreatlysimplifiedbygroupingthisareatogetherfor33kVfaultsonly,asamixtureofareasareaffected.Localfaultsaretreatedasrural,asdiscussedabove.
Figure4.1and4.2overleafshowsthedefinedareas.
4.2.3 PlannedvsUnplannedPerformance
Inadditiontotheforegoinganalysisofthedata,namelyexclusionofMEDsanddisaggregatingthereliabilitydatabylocation,afurtherrefinementhasbeenappliedbysplittingtheservicelevelsintoplannedandunplanned(fault)categories.Therationalebehindthisapproachisthattherearedifferentdriversforeachtypeofservicelevel.
Plannedoutagesresultfromscheduledmaintenanceactivitiesthatareoftenpartofaproactivemaintenanceapproachtoimprovetheoverallperformanceofthenetworkoverthelongterm.Inaddition,consumersarenotifiedwellinadvanceofaplannedoutageandareoftenabletotakestepstominimisetheirexposuretotheeffectsoftheoutage.Inviewofthis,plannedoutagesarelessdisruptivethanunplannedoutages.Inaddition,theyaremoreacceptabletoconsumersinviewoftheperceivedlonger-termbenefits.
Ontheotherhand,unplannedoutagescancausesignificanteconomicdamageto industrialandcommercialconsumers,whileresidentialconsumersareoftensignificantlyinconvenienced.Accordingly,consumersarelesstolerantofthistypeofoutageandseparatetargetsneedtobedevelopedthatrecognisethedisparitybetweenthecustomerdamagefunctionsfromeachoftheseofoutages.
The data included in this section of theAMP allow for this disaggregationwherever possible, including thecomparisonofhistoricalperformanceagainsthistoricaltargets.
NETWORKDEVELOPMENT 111
4.2.4 HistoricalPerformance
ThehistoricalfiguresforSAIDIandSAIFIshowninTables4.3and4.4,andFigures4.5to4.8,havebeennormalisedbytheremovalofMEDs.
Table 4.3 - Planned and Unplanned SAIDI (Urban, Rural and Remote Rural)
2006-07 2007-08 2008-09 2009-10 2010-11
URBAN
Planned 19.11 8.05 19.56 26.97 12.88
Unplanned 26.34 33.12 36.21 31.95 35.41
Total 45.45 41.17 55.77 58.92 48.29
RURAL
Planned 30.54 30.32 21.42 16.68 31.48
Unplanned 48.7 52.08 54.91 67.78 62.13
Total 79.24 82.4 76.33 84.46 93.61
REMOTERURAL
Planned 6.00 6.09 2.74 10.19 2.55
Unplanned 23.95 20.86 43.96 56.59 44.03
Total 29.95 26.95 46.70 66.78 46.58
GrandTotal 154.64 150.52 178.80 210.16 188.48
PlannedActuals 55.65 44.46 43.72 53.84 46.91
PlannedTargets 40.00 40.00 40.00 55.00 60.00
UnplannedActuals 98.99 106.06 135.08 156.32 141.57
UnplannedTargets 70.00 70.00 70.00 95.00 115.00
Table 4.4 - Planned and Unplanned SAIFI (Urban, Rural and Remote Rural)
2006-07 2007-08 2008-09 2009-10 2010-11
URBAN
Planned 0.100 0.030 0.080 0.089 0.054
Unplanned 0.440 0.400 1.140 0.289 0.877
Total 0.540 0.430 1.220 0.378 0.932
RURAL
Planned 0.200 0.100 0.120 0.057 0.104
Unplanned 1.430 0.660 1.110 0.561 0.791
Total 1.630 0.760 1.230 0.618 0.895
REMOTERURAL
Planned 0.020 0.100 0.020 0.034 0.014
Unplanned 0.350 0.120 0.650 0.930 0.784
Total 0.370 0.220 0.670 0.964 0.798
GrandTotal 2.540 1.410 3.120 1.960 2.624
PlannedActuals 0.320 0.230 0.220 0.180 0.172
PlannedTargets 0.250 0.250 0.250 0.340 0.680
UnplannedActuals 2.220 1.180 2.900 1.780 2.452
UnplannedTargets 1.000 1.000 1.000 1.360 1.310
112 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure4.5-PlannedSAIDIProfileforLastFiveYears
0
5
10
15
20
25
30
35
2006-07 2007-08 2008-09 2009-10 2010-11
Min
ute
s L
ost
Year
URBAN
RURAL
REMOTE RURAL
Figure4.6-UnplannedSAIDIProfileforLastFiveYears
0
10
20
30
40
50
60
70
80
2006-07 2007-08 2008-09 2009-10 2010-11
Min
ute
s L
ost
Year
URBAN
RURAL
REMOTE RURAL
Figure4.7-PlannedSAIFIProfileforLastFiveYears
0.0000
0.0500
0.1000
0.1500
0.2000
0.2500
2006-07 2007-08 2008-09 2009-10 2010-11
Min
ute
s L
ost
Year
URBAN RURAL REMOTE RURAL
NETWORKDEVELOPMENT 113
ForthereasonsdiscussedinSection4.2.2,ruralareasappeartohavepoorerperformancethanremoteruralareas,butthisismainlyduetodifficultiesindisaggregationofthefaultdataforSouthWestland.
4.2.5 PerformanceTargets
Tables4.9to4.11belowshowthespecificperformancetargetssetbyWestpowerfortheplanningperiodinquestion.
TherationaleforsettingthespecifictargetlevelsisdiscussedinSection4.4.
Inadditiontothegenerictargetsdiscussedabove,additionaltargetshavebeendevelopedaround:
• Themaximumlengthofoutage;
• Thenumberofextendedfaultsthatconsumerswillbeexposedtoineachtypeofarea.
Thesetargetsareconstantthroughouttheplanningperiodandtheperformance.
Table 4.9 - SAIDI Targets Projected Forward 10 Years
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
PlannedTargets 49 49 49 49 49 49 49 49 49 49
UnplannedTargets 128 128 128 128 128 128 128 128 128 128
Totals 177 177 177 177 177 177 177 177 177 177
Table 4.10 - SAIFI Targets Projected Foward 10 Years
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
PlannedTargets 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22 0.22
UnplannedTargets 2.11 2.11 2.11 2.11 2.11 2.11 2.11 2.11 2.11 2.11
Totals 2.33 2.33 2.33 2.33 2.33 2.33 2.33 2.33 2.33 2.33
Figure4.8-UnplannedSAIFIProfileforLastFiveYears.
0.0000
0.2000
0.4000
0.6000
0.8000
1.0000
1.2000
1.4000
1.6000
2006-07 2007-08 2008-09 2009-10 2010-11
Min
ute
s L
ost
Year
URBAN
RURAL
REMOTE RURAL
114 WESTPOWERASSETMANAGEMENTPLAN2012-2022
4.3 Other Targets
Asmallnumberofkeyassetperformanceandefficiencytargetshavebeenchosenthatprovidethereaderwithaclearunderstandingofthewaythebusinessisperforming.Itisfeltthatthisisabetterapproachthantoincludea large number of less significant and often conflicting performance targets thatwould create unnecessaryconfusion.
Relevant standard performance and efficiency targets, as defined in the Electricity (Information Disclosure)Requirements2008havebeenchosenforinclusioninthisAMP.Theseare:
• OperationalExpenditure(OPEX)ratio(OPEX/systemassetsreplacementcost),
• CapitalExpenditure(CAPEX)ratio(CAPEX/systemassetsreplacementcost);
• Renewalratio(assetrenewal-refurbishmentOPEXandCAPEX/depreciation),
• Distributiontransformercapacityutilisation;
• Faultsper100circuitkm(disaggregatedbyvoltageandconductortype(overhead/underground).
TheseindicatorswillbemeasuredinamannerthatisconsistentwiththedefinitionsintheElectricityDistribution(InformationDisclosure)Requirements2008.
Table4.12belowshowsthehistoricalperformanceoftheseindicesandfuturetargetedperformance.
BasedonthehistoricalperformancedisclosedinTable4.12andthetargetsforthefinancialratiosalreadydefinedinWestpower’sSCI,thetargetsintable4.13areprovidedfortheplanningperiod.
AKPIintermsofassetperformanceisthefaultsper100kmindex.AscanbeseeninTable4.12,thisvaluewasrecentlyresettoreflectthevaluesachievedoverthelastfiveyearsmorerealistically.
Table 4.11 - Other Customer Service Targets
Service Area Customers Affected Performance Target
RestorationofSupply
UrbanAreas 95%offaultsrestoredwithinthreehoursofnoti-fication
RuralAreas 95%offaultsrestoredwithineighthoursofnoti-fication
RemoteRuralAreas(SouthofHokitikaexcludinglocal11kVFeedersofRoss,Whataroa,Waitaha,andHarihari)
95%offaultsrestoredwithin12hoursofnotifica-tion
CustomerOutageImpact
UrbanCustomersNomorethantwoplannedoutagesperannumNomorethantwounplannedoutagesperannum(for
90%ofcustomers)
RuralCustomersNomorethantwoplannedoutagesperannum
Nomorethanfourunplannedoutagesperannum(for90%ofcustomers)
RemoteRuralCustomersNomorethantwoplannedoutagesperannumNomorethaneightunplannedoutagesperannum
(for90%ofcustomers)
Table 4.12 - Historical and Future Targeted Performance
2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Projected
DistributionTrans-formerCapacity
Utilisation31% 30% 30% 31% 31% 30% 30% 30% 30% 30% 30% 30% 30% 30% 30%
Faultsper100kmCircuitLength 3.91 7.39 4.69 5.16 5.35 5.30 5.30 5.30 5.30 5.30 5.30 5.30 5.30 5.30 5.30
NETWORKDEVELOPMENT 115
4.4 Justification for Targets
In general, the targets reflect historic performance while consumer engagement indicates a high level ofsatisfaction with existing service levels. In addition, consumers have indicated an unwillingness to pay theadditionalcostsnecessaryifservicelevelsweretobesignificantlyimproved.
Ingeneral,thetargetsreflectfeedbackfromconsumersregardingcurrentandfutureperformance,alongwithhistoricperformanceachievedtodate.
ThefinancialratiotargetsarebasedonfiguresdisclosedtoandacceptedbythetrusteeownersofWestpoweronbehalfoftheconsumersasdisclosedintheSCI.
Thesehavebeencarefullyderived,basedon:
• Historicalperformance,
• Stakeholderrequirements,
• Industrybestpractice,
• Assetrenewalrequirements.
TheWCEPT considers the SCI each year, andeither approves thedocumentor requests further changes. Inconsidering a draft SCI, theWCEPTwill often take independent advice, which this allows benchmarking ofperformanceagainstsimilarcompanies.Suchscrutinyformsthebasisofaregularandongoingformalreviewthatensuresarobustoutcomethatisdesignedtomeetourconsumers’needs.
ThetargetsshowninTable4.13abovearebasedonWestpower’sten-yearbusinessplan,whichisbuiltupfromtheAMPforecasts.TheCAPEXratioandtherenewalratiodropovertimeasmuchoftheolderassetswillsoonbereplaced,leadingtoalowerlevelofsteadystatereplacement.
Assuch,thefinancialtargetsrepresentaclearmandatethatWestpowerisboundtoreflectinitsinternalplanningprocesses.
TheSAIDIandSAIFItargetsarebasedonafive-yearrollingaverageofperformancetodate.Thisisfelttobeavalidapproachbecausethekeydriversforthesestatisticsareexternal,subjecttolong-termweatherpatterns.Atthesametime,Westpowerwantstoensurethatperformancedoesnotdegrade;arollingaverageachievesthis.
4.4.1 ConsumerEngagement
Westpower carries out a consumer satisfaction survey every two years, with themost recent survey beingcompletedinDecember2009.
Thefollowingisanextractofthesummaryfromthismostrecentsurvey:
Thisreportsummarisestheviewsandpreferencesobtainedfromthefollowingtwosamplespace:
• Westpower’s25largestconsumers,
• Arandomsampleof497massmarketconsumerspro-ratedfromsixGXPareas.
Table 4.13 - Future Performance of Efficiency Targets Stated in Section 4.2
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
OPEXRatio 6.60% 7.00% 7.30% 7.30% 7.30% 7.30% 7.30% 7.30% 7.30% 7.30%
CAPEXRatio 4.90% 2.00% 1.50% 1.50% 1.50% 1.50% 1.50% 1.50% 1.50% 1.50%
RenewalRatio 39% 29% 35% 35% 35% 35% 35% 35% 35% 35%
116 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Thenumberofcompletedmassmarketsurveyswasonly30%,whichisslightlylowerthanthepreviousWestpowersurvey(38%)andalsolowerthansimilarsurveysperformedforotherELBs.Somereasonablyclearpatternshaveemerged,asfollow:
• Themostimportantaspectofelectricitysupplyiscontinuityofsupply.
• Thesecondmostimportantaspectofelectricitysupplyisrestorationofsupply.
• Thethirdmostimportantaspectofelectricitysupplytomassmarketconsumersistimelyshutdownnotices,withthetop25consumerspreferringnoflickerorsurgesastheirthirdpreference.
• MassmarketconsumersrateWestpower’sperformanceinthemostimportantaspectofcontinuityasverygood,withaslightskewtowardsexcellent.
• MassmarketconsumersrateWestpower’sperformanceinthesecondmostimportantareaofrestorationasbeingverygood,withaskewtowardgood.
• In the third most important aspect of shutdown notices, mass market consumers rate Westpower’sperformanceasverygood,withaskewtowardgood.
• Massmarketconsumershaveexpressedanobviouspreference(76%)forcontinuingtopayaboutthesamelinechargestoreceiveaboutthesamereliability.However,asmallerbutnonethelessdistinctminority(15%)expressedapreferenceforpayingslightlymoretoreceiveslightlymorereliability.
• Largeconsumersexpressedadistinctpreference(76%)forpayingaboutthesametoreceiveaboutthesamereliability,withonlythreeconsumersindicatingawillingnesstopayslightlymoretoreceiveslightlymorereliability.
• Consumerengagementindicatesahighlevelofsatisfactionwithexistingservicelevels.Inaddition,consumershaveindicatedanunwillingnesstopaytheadditionalcostsnecessaryifservicelevelsweretobesignificantlyimproved.
Asaresultofthisstrongcustomermandate,WestpowerwillstrivetoatleastmaintainitsSAIDIandSAIFIlevelsatrecentlevels.
4.4.2 HistoricalReliabilityPerformance
Westpowerhasalreadytakenanumberofstepstoimprovenetworkperformanceoverrecentyears,usingallreadilyavailablemeansandtosuchanextentthatfutureimprovementsareexpectedtobeincrementalatbest.Moreover,futureperformancewillcontinuetobestronglyinfluencedbyexternaldriverssuchasstorms,whichwillfaroutweighandeffectivelymaskanyimprovementsgainedthroughadditionaltechnologicalimprovements.
Afteranumberofyears,duringwhichtheactualSAIDIandSAIFIstatisticssignificantlyexceededthemandatedtargetsundertheprice/qualityregime,anopportunitywastakentoresetthetargetlevelstovaluesthatmoreaccuratelyandrealisticallyreflecttheexpectedperformancemovingforward.
Accordingly,after someconsideration, itwasdecided toadoptfive-year rollingaveragevalues forSAIDIandSAIFI,thusensuringthatthereisnooveralldegradationinservice,whilealsoprovidinganachievabletargetthatcontractorsandsystemoperationstaffcanconfidentlyaimfor.Tofurtheravoidunnecessaryvolatility,WestpowerwillcontinuetousefiguresthatexcludeMEDs,bothinthetargetsandtheactualperformanceindicesdisclosed.
Thetargetfiguresfor2011to2020arethusbasedontheaveragefiguresachievedoverthefive-yearperiodfrom2006to2010.Inaddition,asthereisnolikelihoodofsignificantstepimprovementsinthefuture,aflatprofilehasbeenprojectedthroughouttheplanningperiod,althoughthiswillcontinuetoberevisedeachyearsothatanyincrementalimprovementsgainedarereflectedinfuturetargets.
NETWORKDEVELOPMENT 117
Thisisimportant,asWestpowerwillcontinuetoseekoutcost-effectivereliabilityenhancementsolutionswherethesecanbeshowntoofferanopportunityforrealbenefits,suchastheforthcominginstallationofagroundfaultneutraliserattheGreymouthsubstation,whichsuppliesover30%ofWestpower’sconsumers.Byusingafive-yearrollingaverageforSAIDIandSAIFI,anymaterial improvementresultingfromthis innovationwillbecapturedinfutureforecastsandmaybecomeajustificationforprogressivelyextendingthistechnologytoothersubstations.
AscanbeseeninTable4.14,themaincausesforunplannedoutageshavebeentreecontactandhighwinds/rain. This is predicted to improve slowly over the planning period as initiatives such as better segregationof the network (more reclosers,more reliable replacement reclosers) and an improved focus on vegetationmanagementbegintotakeeffect.
TwofeedershavebeenidentifiedwithhighunplannedoutageSAIDIminutes:
Hokitika-Harihari33kVcircuit(HKK1012)
Acurrentprojectinvolvesthestagedreplacementofthisasset.Theconstructionhasbeendesignedtoallowforfutureupgradingbyensuringthatlineinsulationandclearancesaresuitablefor66kVoperation.Reliabilitywillbeprogressivelyimprovedwiththestagedcompletionofthisproject.
The33kVdisconnectorsatRoss,WaitahaandHarihariarebeingautomatedwithSCADAcontroltoreducefaultisolationswitchingtimesandrestorationofsupply.
Table 4.14 SAIDI CAUSE BREAKDOWN April 10 to March 11
DescriptionYear to Date
Events Time (Minutes) % of SAIDI
PlannedOutages 114 47.32 25%
Vehicle 2 0.22 0%
Wind/Rain 24 12.39 7%
Lightning 2 0.23 0%
Animal 0 0.00 0%
EarthmovingEquipment 2 0.34 0%
EquipmentFailure 22 18.76 10%
Deterioration 1 0.06 0%
Unknown 18 32.01 17%
HumanError 2 3.71 2%
Tree 34 68.54 36%
Overload 0 0.00 0%
BirdStrike 4 1.98 1%
SaltDeterioration 0 0.00 0%
Vandalism 1 0.04 0%
Snow 0 0.00 0%
Other 1 0.13 0%
Flood 1 2.44 1%
Fire 1 0.31 0%
UnplannedOutagesSubtotal 115 141.16 75%
TOTALS(PLANNEDANDUN-PLANNED) 229 188.48 100%
118 WESTPOWERASSETMANAGEMENTPLAN2012-2022
FOX1Feeder
TheFoxCB1feedersuppliesanareafromFoxGlaciertoParinga.Becauseoftheremotenessofthearea,faultisolationswitchingtimescanbe long.To reduce fault isolationtimes,a sectionaliser (ENTECswitch) is tobeinstalledintheBruceBayareatosegregatefaultsautomatically.
4.5 Stakeholder Needs
InordertosetreasonablesecuritystandardtargetsforWestpower’scustomersthatarecompatiblewithenduserexpectations,appropriateresearchmustbecarriedout.
The needs of electricity users have changed greatly over the last ten years with the rapid introduction oftechnologyintothedomesticmarket.Appliancesfromvideorecorderstobreadmakersandhomecomputersarenowcommonplace inmanyhomes,andhavegreatly increasedthesensitivityofhouseholders topoweroutagesandminor interruptions.Consultationwiththe25 largestcustomershasconfirmedthatadoptionofProgrammableLogicControllers(PLC)andSCADAbyindustryhasreducedtolerancetofleetingevents–rotatingandthermalplantthathassufficientinertiatocontinuethroughafleetingoutagewillnowprobablybetrippedwhenitscontrollerlosespowerforacycleortwo.
CustomerdamagefunctionreportsrecentlycarriedoutonbehalfoftheElectricityCommissioninsupportofTranspower’sapplicationfortheWCGUPshowedthatevenshortoutagescanresultinseveralhoursofproductiondowntimeformajorprocess-basedconsumers.Accordingly,solutionsthatprovideforcontinuousconnectiontothenetworkratherthan“change-over”schemesarepreferred.
PartofWestpower’s role is tomaintainanefficientandreliableelectricitydistributionnetworkontheWestCoast.Inthiscontext,“efficiency”and“reliability”arerelativetermsthataresubjecttopersonalperceptions.In turn, these perceptionsmust be viewed from the customer’s viewpoint, whichmust be actively sought.Westpowerintendstoliaisecloselywiththeenergyretailerstodeterminetheexpectationsoftheircustomersandtoquantifytheseintermsofdesirablereliabilityindices.
NETWORKDEVELOPMENT 119
5.0 NETWORK DEVELOPMENT
5.1 Introduction
Thissectionoutlinesthenetworkdevelopmentplanrequiredtomaintain,enhanceanddeveloptheoperatingcapabilityofthesystem.
ThemainfocusofthissectionistheuseofConditionBasedMaintenance(CBM)andriskmanagementtechniques(asdescribedinSection9)toscheduletheprojectsrequiredtomeetthereliabilitytargetsandremainwithinthebudgetarylimitationsimposedforthisplanningperiod,andtoappropriatelyschedulenetworkdevelopmentprogrammesforfutureperiods.
5.2 Planning Criteria and Assumptions
Futureloadprojectionisadifficulttaskandisbasedonacomplexmultivariateenvironment.
Someofthedriversthateffectfutureloadinclude:
• Climaticconditions,
• Economicactivity,
• Commodityprices,
• Foreignexchangerates,
• Majorsteploadincreases/decreases.
Arelativelywarmwinterhasasignificantimpactonwinterheatingloadsand,asaresult,hasamajoreffectontheannualpeakload.
Overalleconomicactivity,whichis,tosomeextent,alsolinkedtogoldpricesandcoalmarkets,hasafilterdowneffectonelectricityconsumption.Thiscantakeeffectslowlyoverthemediumterm.
With the relatively small overall demand,major step load changeshave a great impact on systemdemand.Unfortunately,thesearealsothemostdifficulttopredictorquantify,astheydependoninvestmentdecisionsfrommajorindustries.Historically,finalcommitmentsontheseprojectshavebeendeferredtoaverylatestage,ofteninvolvingsignificantlastminuteloadrevisions.ThisleavesWestpowerinadifficultsituationfromaplanningperspective.
ThePikeRiverminedisaster,whichoccurredon19November2010,hasresultedinamajorsteploaddecreaseofsome6MWforWestpower.Thetrickledowneffectonthelocaleconomyisstillsomewhatuncertain.However,loadforecastprojectionsfor2012/2013havebeenmoderatedforthepurposesofloadforecasting.Atthisstage,ithasbeenestimatedthatloadfromthePikeRiverminewillcomebackonstreaminaroundtwoyears’time;however,thisisonlytentativeatthisstageandtheforecastswillbereviewedonceafinaldecisionismadeonthefutureofthemine.
Acarefulandrigorousapproachhasbeentakentodevelopingfutureloadprojectionsbasedonhistoricaltrends,availableinformationandestimatesonfuturechanges.ALoadwatchspreadsheetisakeydatareceptacleusedtostoreinformationforlaterinputintothedemandforecastingprocess.Theloadgrowthprojectionswereusedasabasisfordeterminingthelikelytimingofthoseprojects,whicharejustifiedbyloadgrowth.
Firstly, load trendsateachGXPover theprevioussevenyearsarestudied to try to identifyhistoricbaselinechanges.Theeffectsofknownsteploadincreasesareextracted,leavingtheunderlyinglong-termhistoricloadprofile.
BasedonGXPdataandgeneralknowledgeofthelocaleconomyandotherdriversdiscussedabove,anestimateismadeofthelikelyfuturetrendinloadgrowthonaGXPbasis.Thisthenprovidesanewbaselineforfurtherwork.
120 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.2.1 EnhancementandDevelopmentCriteria
This activityoutlinesworkwhich is planned toenhanceanddevelop the system. Thismeans increasing thecapacityofthesystemandeliminatinganylimitationsinorderto:
• Providemoreload,
• Enhancevoltageregulation,
• Improvesecurityandreliability.
It includes projects (at specific sites) and programmes of relatedwork. Network limitationswhich relate tosystempeakloadingare:
• Acceptablestandardsofreliabilityofsupplycannotbemaintained.
• Theacceptablenetworkratingofplantandequipmentcannotbemaintained.
• Thethermalratingofplantandequipmentisexceeded.
Additionalnetworklimitationsare:
• Thefaultratingofequipmentisexceeded.
• Theageofequipmentrendersitscontinueduseoperationallyunsafeoruneconomic.
• Continuedoperationof theexistingnetwork isnoteconomic,e.g. small conductor sizesorhigh reactivepowerflowscausingexcessivelosses.
Theprocessforevaluatingnetworklimitationsissystematicandcoversallitemsofequipmentandallcircuits.Particularattentiontoallthemostcommonlimitationsisrequired(refertoTable5.1below).
5.2.2 ReliabilityandSecurityofSupply
5.2.2.1 SecurityGuidelines
Thesecurityguidelinesarethebasisforanalysisandfordeterminingthefutureperformanceofthedistributionsystem.Table5.2outlinessomeofthesecurityguidelinesfordistributionplanning.ThelevelsofsecuritythatcurrentlyexistsforeachzonesubstationaresummarisedinAppendixC.
Table 5.1 - Common Network Limitations
Equipment Common Limitations
Transformers Rating,ageingconditions,tappingrange,voltageregulation.
Switchgear Rating,age,insulation,faultrating,buszoneprotection,sparefeederunits,sensitiveearthfaultprotection.
Cables Rating,age,leaks,faultyjoints,longrepairtime,faultrating.
OverheadLines Rating,physicalconditions,reliability,losses,clearances,voltagedrops,faultrating.
Table 5.2 - Security Guidelines for Distribution Planning
Load (MW) Basic Security Level Transmission Circuits Busbars Transformers
Lessthan10 n Onecircuit Onebusorbussection.1x3-phaseunit,ifbackedupfromalternativesupply
points
Above10 n-1 Twocircuits Twobusbarsorbussections.
2x3-phaseunits,firmsup-plyofpeakdemandusinganyshort-termoverload
capacity.
NETWORKDEVELOPMENT 121
With regard to thedesignof systemchangesornetworkextensions,dueconsideration ismadeof the levelof security required for the connected consumers. An industrial customer, for instance,may require a non-interruptiblesupplyforaspecificmanufacturingprocess,whilstadomesticcustomercantolerateoccasionalsupply interruptions. Specific criteria for interruption and quality of supply may need to be developed forindividualcustomersbothfordesignconsiderationandcommercialcontractualobligations.
Table5.3showstheminimumsecuritylevelsforWestpower’sdistributionsystems.
Customerswhoarepreparedtoenter intocommercialagreementscanbeprovidedwithenhanced levelsofsecurity.
Westpower is currently investigating the use of probabilistic planning techniques to assist in the evaluationofsecurityandreliabilitybenefitsforspecifiedprojects.Thesetechniquesareapplicabletonetworkplanningprocesses,aspowersystembehaviourisstochasticinnature.Ajustificationfortheuseofthisapproachisthatitinstilsmoreobjectiveassessmentsintothedecision-makingprocess.
Inparticular,probabilistictechniquescanbeusedtoprovidemeasurableperformanceindicessuchas:
• Systemavailability,
• Estimatedunsuppliedenergy,
• Numberandsizeofloadcurtailments,
• Numberofhoursofinterruption,
• Excursionsbeyondsetvoltagelimits.
Whiletheuseofaprobabilisticplanningapproachofferssignificantbenefits intermsoftargetedCAPEX,theproperapplicationofthistechniquealsoinvolvessignificantinvestment,bothintermsofcostandresources.Inparticular,thefollowingprerequisitesapply:
• Competent staff, including experienced reliability engineers who are familiar with the application ofprobabilistictechniquestopowersystems;
• Accurateandcompletehistoricalfaultoutagerecordsoveralargenumberofyears;
• Expensiveandcomplexreliabilityevaluationsoftwarepackages,user-friendlyversionsofwhichhaveonlybecomegenerallyavailableinthelasttwoyears.
Accordingly,probabilisticplanningtechniquesarenotwidelyused,exceptsofarastheseareappliedfornetworkdevelopmentprioritisationasdiscussedinSection5.3.
5.2.3 RegulatoryFactorsandQualityofSupply
Programmesandprojectsaretypicallyjustifiedonthebasisofthefollowingbenefitsfromimprovedvoltagelevelorcontrols:
• Theabilitytomeetanyregulatoryrequirementswithrespecttovoltagestandards;
• Specificcustomerrequirementswhichthecustomeriswillingtopayfor;
• Savingsinlosses;
• ImprovementsintransmissioncircuitcapacityandtheconsequentialdefermentofCAPEX.
Table 5.3 - Minimum Security Levels for Distribution Networks
Circuit Type Maximum Demand Under Normal Conditions Minimum Circuit Arrangement
Overhead Upto1MVA Single-circuit
Underground Upto300kVAUpto1MVAforasinglecustomer Single-circuit
Overhead Greaterthan1MVAanduptotwo-thirdsoffeedercapac-ity Feederbackstopping
122 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Powerqualityisconsideredtobethestandardofthepowersuppliedinanenergisedsystem.Itincludesvoltageregulation,thelevelofharmonicdistortion,andthefrequencyandmagnitudeofpowersagsandsurges.Sagsandsurgesaremomentaryvoltagedipsorincreaseswithdurationoflessthanasecond,generallyfromafewmillisecondstohalfasecond.Powerinterruptionsofmorethanasecondareconsideredtobeoutages,afactorofpowerreliability.
5.2.3.1 VoltageRegulation
WherecustomersarefedfromaLVdistributionsystemthatsuppliesmorethanonecustomer,thedistributionsystemwillnormallybedesignedsothatthephasetoearthvoltageatthecustomer’spointofsupplyismaintainedwithinthelimitsassetoutintheElectricityRegulations(theElectricityRegulations1997allLVvariationsof±6%,exceptformomentaryfluctuationsofthenominalvoltage).Thecustomer’spointofsupplywillusuallybetakenasthecustomer’sservicefuseorpropertyboundary.
Inspecialsituations,orwherethecustomerissuppliedatavoltageotherthanthestandardLV,thedistributionsystemshouldbedesignedsothatthedeliveredvoltageismaintainedwithinthelimitsagreedbythecustomerandWestpower.Wherenosuchlimitsarespecificallyagreedon,thelimitsasstatedintheElectricityRegulationsshallbeapplied(theElectricityRegulations1997allowforvoltagevariationsof±5%oftheagreedvoltageforinstallationssuppliedatotherthanstandardLV).
5.2.3.2 VoltageDropAllowances
Regulated11kVbusbarsonWestpower’sdistributionnetworkareregulatedtoavoltageof102%ofnominalvoltage. The voltage drop across the network should accordingly be distributed as follows undermaximumdesignloadconditions:
• 11kVsystem 2%
• LVsystem 4%
• Servicemain 2%
Inruralareas, theallocationofvoltagedropsmustbedeterminedonacase-by-casebasis.Theactual11kVvoltagedropwill dependon thedistanceof the customer from the regulatedbusbar, and this voltagedropcouldexceed2%.Avoltagedropoflessthan4%ontheLVsystemisthusrequired.Ingeneral,thedesignshouldendeavourtoplacethe11kVsupplypointtotheLVnetworkasclosetothecustomeraspossible,resultingthusinrelativelyshortLVnetworks.
5.2.3.3 Harmonics
Harmonic voltages and currents are generally generated by customer’s equipment. The limits of harmonicvoltageorcurrentpermittedatthepointofconnectionbetweenthenetworkandthecustomer’sinstallation,orthepointofcommoncouplingwithanyothercustomers,areasspecifiedintheNewZealandElectricalCodeofPracticeforHarmonicLevels,NZECP36:1993.Ingeneral,thisrestrictsharmonicvoltagesatlessthan66kVto4%foranyodd-numberedharmonic,2%foranyevenharmonicand5%fortotalharmonicdistortion.
5.2.3.4 RatingofNetworkEquipment
Allequipmenttobeinstalledonthenetworkshallbeadequatelyratedbothintermsofloadcapacityandintermsof fault levelwithstandingcapability. Inassessing thecurrentor load rating,dueallowanceshouldbemadeforfutureloadgrowth.Whereappropriate,allowancemaybemadeforthecyclicalnatureofanyload.
In terms of fault ratings, before selecting the fault level withstanding rating of a network component, theactualfaultlevelatthelocationonthenetworkatwhichthenetworkcomponentistobeinstalledshouldbedetermined.Anyexpectednetworkreconfigurationshouldalsobetakenintoaccount.
AfterDiversityMaximumDemand(ADMD)isthemostcriticalvariablefactorinLVsystemdesign,asitsaccurateselectiondirectlyaffectstheoptimumcostsofaninstallationandqualityofsupply.
NETWORKDEVELOPMENT 123
ItisthereforeimportantthatemphasisisappliedtotheoptimumselectionofADMD.Accordingly,ADMDhasbeenrevisedanddependsmainlyonthedevelopmenttypeaspresentedbelow.
5.2.3.5 CommercialAreas
Innewcommercialdevelopments,wheresmallfactories,retailshopsorsimilarrequireLVdistribution,noADMDcanbepredicted,asitisnotknownwhatoperationswilloccupythepremises.Loadestimatesshouldbegenerous,becausethecostoflaterLVcablereinforcementcanbeconsiderable.Transformerloadestimatesmaybemoreconservative.ThedesignershoulddiscusseachcasewithdevelopersandWestpowerbeforeproceeding.
5.2.3.6 UrbanResidentialAreas
ThenetworkshallbedesignedforanormalresidentialADMDof5kWperdwelling.Inspecialareas,identifiedbyWestpower,thismaybeinsufficientandthedesignADMDshallbeasspecifiedbyWestpower.Inareaswherezoning allowsmultiple residential dwellings and theproperty areapermits, an allowancemustbemade formultipledwellingsperlot.
5.2.3.7 RuralAreas
CaremustbetakentodeterminetheADMDperconsumerinruralareas.Appropriateallowancemustbemadeiflargeirrigationpumpsaretobeconnectedorifsignificantelectricalheatingistobeinstalledinlargeresidentialbuildings.
Thedesignandselectionoftheequipmentusedfortheconstructionofoverheadlinesmustmeet,atleast,thefollowingrequirements:
• Safety-Thelinemustbesafeforlineworkerstoconstructandmaintain,andmustoffernohazardtothegeneralpublic.
• Electricalperformance-Thelinemustadequatelyservethepurposeforwhichithasbeendesigned.Itmustsafelycarryanyloadcurrentwhichitmaybecalledupontodowithoutcreatingproblemsofunacceptablevoltagedrop.Itmustalsobeabletowithstandanyfaultcurrentthatitmaycarryfromtimetotime.
• Mechanicalperformance-Thelinemustbeabletowithstandreasonablenaturalforcessuchaswind,rain,snowandearthquakes.
• Financialperformance-Thelineshouldbedesignedtobeaseconomicalaspossible,takingintoaccounttheoriginalcostofmaintenanceandcostoflinelosses.
• Appearance-Considerationmustbegiventotheimpactofthelineontheenvironmentinchoosingthelinerouteandtheaestheticappearanceoftheline.
5.3 Prioritising Network Development
Westpowerstrivestoensurethatoptimalcapitalefficiencyisgainedthroughtheapplicationofaformalprojectevaluationprocess forcapitalprojects,as thesemustcompete for scarcecapital resources. In thisway,onlyprojectsthatmeetWestpower’sstrictcriteriawillgoforwardandprojectswillalsobecompletedinthebestmeritorder.
As thekeydrivers fornetworkdevelopmentcomprisebothfinancialandnon-financial factors, the followingcategorieshavebeendeterminedsothattailoredplanningcriteriacanbeappliedwhilestillprovidingobjectiveoutcomes:
• CategoryA–projectswithnodirectfinancialjustification;
• CategoryB–projectswithmarginalfinancialbenefits;
• CategoryC–projectswithclearfinancialreturns.
ForCategoryAprojects, thereareanumberofdiversedrivers thatneedtobecarefullyevaluatedandthencomparedonanobjectiveandequivalentbasis.Theseareenumeratedbelow.
124 WESTPOWERASSETMANAGEMENTPLAN2012-2022
1. Reliability/securityofsupplytomeetcustomerlevelsofserviceandcontractualobligations;
2. Asset replacement and renewal requirements to maintain the service delivery potential of the asset,andavoidunnecessaryandunscheduledreactivemaintenance;
3. Occupational health and safety to establish a safe environment both for workers and the public, andcomplywithOccupationalHealthandSafety(OSH)legislativesafetyrequirements;
4. Regulatorycompliancetomeetregulationsimposedbyexternalgovernmentalagencies;
5. Environmentaltocomplywithemissionregulationstoair,landandwater;
6. Quality of supply to ensure that all consumers receive a quality of supply that meets Westpower’sminimumperformancestandards;
7. Technologicalefficiencytoensurethatappropriatecurrentbusinesstechnologyisappliedinthebusinesstoleverageoverallperformancegains;
8. CorporateimagetoensurethatanyactivitycarriedoutbytheassetmanagementteamandsubcontractorswillnotmateriallydamageWestpower’simage.
Anobjectivescoringsystemhasbeendevelopedtoprovideanequitablecomparisonbetweenprojectswithinthis category,even though theymighthavequite separatedrivers. For instance, in thecaseofDriver1, theassessedimpactonboththeSAIDIandSAIFIreliabilitystatisticsisdeterminedeitherbyempiricalorprobabilisticmeans,andtheweightedscoreforeachmetriciscombinedtogiveanoverallscore.Ontheotherhand,ifDriver7werethekeydriver,amultivariateapproachusingfactorssuchasproductivityeffects,equipmentcostsandlikelyusagewouldbeappliedtocomeupwithacomparablescore.
CategoryBprojectsarebasedonclearfinancialcriteriathatcanbeassessedusingfinancialevaluationtools.Thefollowingsub-categoriesareincluded:
1. Efficiency improvements resulting in a reduction in losses or costswhilemaintaining asset performancecriteria;
2. Demandsidemanagement,reducingWestpower’soverallpeakdemandcharges;
3. Renewalandreplacementwhereaclearbusinesscasecanbeprovidedforreplacementofanassetthroughreducedmaintenancecosts;
4. Capacity enhancement where additional capacity is required by a consumer and this can be fundedthroughincreasedlinecharges;
5. Strategic,leadingtolong-termquantifiablestrategicbenefitsforthecompany.
Westpower has developed a robust evaluation tool using industry best practice CAPEX software to provideobjectivityanddisciplinearoundthisprocess.Thisunderlyingapproach isbaseduponDiscountedCashFlow(DCF)analysisbuttheproducthasbeenadaptedforWestpower’sneedsbyaddingexpertdecisionsupporttools.
CategoryCprojectsaresimilartothoseincludedinCategoryB,butbecauseofthedifferentriskprofilesinvolved,theyhavedifferenthurdleratesandsuccesscriteriaappliedtothem.Theseprojectscouldinclude:
1. Networkextensions,includingnewsubstations;
2. Subdivisionreticulation;
3. Communication infrastructure, where there is an ability to share costs with third-party users of thenetwork;
4. Distributedgeneration,suchasthenewAmethysthydroschemethatWestpoweriscurrentlyassessingthefeasibilityof.
Asdiscussedabove,thesameevaluationtoolsareusedforbothCategoryBandCategoryCprojects.
NETWORKDEVELOPMENT 125
Eachoftheseabovecategoriesisevaluatedbyusingaweightedscoringsystemthatisbasedontheavailablemetrics.
Appropriateweighting factorsare thenapplied toensure thatprojects canbe comparedacrosseachof thecategoriestodevelopastackofprojectsthatcanbeprogressedinapredeterminedmeritorder.Thismethodthereforeprovidesafaircomparisonbetweenfinancialandnon-financiallydrivenprojects,andthisobviatestheneedtoapplyseparateenvelopetoolsforthenon-financiallydrivenprojects.
Whetherornotaprojectwillproceedinanygivenyearwilldependuponwhetherthescoreforthatprojectreaches the project inclusion threshold for that year. In turn, the thresholdwill be determined by financialperformancerequirementsandbudgetaryconstraints,andthesemayvaryfromyeartoyearduetoanumberofexternalbusinessdrivers.Ifaprojectfailstomeetthethresholdinthecurrentyear,itwillbemovedintothefollowingyearforreassessmentalongwithothercompetingprojects.
Thisprocessmakes sure thatonlyprojects thatmeetWestpower’s strict criteriaproceed, and thatnetworkinvestmentiscarriedoutefficientlyandintherightordertoensureoptimumuseofscarcecapitalresources.
Inadditiontothespecificratingsystemusedforkeyprojectsnotedabove,anumberofgeneralprinciplesareappliedwhendecidingtheorderinwhichprojectsshouldproceed.Thesegenerallyfallintothecategoriesbelow:
1. Toppriority isgiventomeetingthe loadrequirements fornew, large (mainlymining) industrial loads.Astherearenonewmajorloadsthathavecommittedatthisstage,noassociatedprojectsareincludedinthisAMP.
2. Secondpriorityisgiventosubtransmissionaugmentationrequiredtomeetcapacitylimitationsasaresultofincrementalloadgrowth.TheonlyseriesofprojectsthatfallunderthiscategoryaretheSouthWestlandGridReinforcement(SWGR)projects.TheseinvolveupgradingtheexistingHokitikatoHarihari33kVlineto66kVoperation,alongwiththeassociatedsubstationsatRoss,WaitahaandHarihari.Currently,projectedfor2019,theactualdatewilldependonmajorgenerationdevelopmentinSouthWestlandsuchasthepotentialWaitahahydroschemenotedinSection3.13.
3. Thirdpriority is given to subtransmission asset replacement, anddistributionnetworkdevelopment andreplacement.ThereplacementandrenewaloftheHokitikatoHarihari33kVlineisthemajorprojectinthiscategory.
5.4 Load Forecasting
5.4.1 Introduction
Acritical factor in consideringnetworkdevelopmentplans is theprojected loadgrowth.Theprojected loadgrowthispresentedinFigure5.4andrepresentsafterdiversitydemand, includingtheloadsuppliedthroughlocalgeneration.
Themethodologyusedtodeterminetheloadgrowthtakesonlyafterdiversitydemandintoconsideration.
Itisanticipatedthatthecurrentmaximumdemandofaround50MWwillrisetoabout65MWintenyears.
Typicalcustomerrequestsrelatetoissuesofcapacity,qualityand/orsecurityofsupply,andcanleadtoplansforassetenhancementordevelopment.TheseareoutlinedinSection4,withparticularreferencetoTable4.12and4.13.
Themostcommonupgradeinrelationtocapacityistheinstallationofnewortransferredsupplytransformersatconnectedpoints,thusprovidingsufficientcapacitytoallowforfuturedemandgrowth.Resolutionofsupplyquality issues typically includes provision of local voltage support in the formof regulators or capacitors tomaintainthesteady-statevoltagewithinspecifiedranges.
126 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Alternatively,networkanalysisincludingloadprojectionsatpointsofsupply,powerflows,networkandpointofsupplyperformanceleadstooptionsforconsiderationbycustomersandWestpowermanagement.Table5.5showsatypicalexampleofaloadtrendtable.
5.4.1.1 HistoricalFactors
Futureloadprojectionisadifficulttaskandisbasedonacomplexmultivariateenvironment.
Someofthefactorsthataffectfutureloadinclude:
• Climaticconditions,
• Economicactivity,
• Commodityprices,
• Foreignexchangerates,
• Majorsteploadincreases/decreases.
Arelativelywarmwinterhasasignificantimpactonwinterheatingloadsandasaresulthasamajoreffectontheannualpeakload.
Overall economic activityon theWestCoast,which is closely linked toworld commodityprices forprimaryproductssuchascoal,goldanddairyproducts,hasadirectfilterdowneffectonelectricityconsumption,andthisoftenhasmediumtolong-termeffectswhennewinvestmentdecisionsaretriggered.
Withtherelativelysmalloveralldemandof50MW,majorstep loadchangeshaveagreat impactonsystemdemand.Unfortunately,thesearealsothemostdifficulttopredictorquantify,astheydependoninvestmentdecisionsfrommajorindustries.Historically,finalcommitmentsontheseprojectshavebeendeferredtoaverylatestage,ofteninvolvingsignificantlast-minuteloadrevisions,leavingWestpowerinadifficultsituationfromaplanningperspective.
Figure5.4-LoadTrends
http://moss/asset/doc/amp/data/2012 AMP Data 26/01/2012
0
10
20
30
40
50
60
70
2003 2004 2005 2006 2007 2008 2009 2010 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021
MW
Calendar Year
Load Trend(Actual/Forecast)
Dobson Greymouth Kumara Hokitika Reefton Otira Atarau
ADMD (50.5 MW)
NETWORKDEVELOPMENT 127
Table5.5-Loa
dTren
dsand
Forecaststo
202
1
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
Reeft
on
-
----
----
-
---
----
---
---
----
---
---
----
---
100.0
0%
1.5
5%
-1.8
3%
17.4
9%
-0.9
0%
1.0
0%
0.9
9%
1.0
7%
1.0
6%
0.9
6%
0.9
5%
0.9
4%
0.9
3%
0.9
2%
0.9
2%
Ata
rau
-
----
----
-
---
----
---
---
----
---
---
----
---
---
----
---
100.0
0%
239.4
5%
75.9
5%
-89.1
2%
0.5
0%
0.5
0%
134.3
9%
57.3
4%
36.4
7%
0.1
0%
0.1
0%
0.1
0%
0.1
0%
0.1
0%
Dobson
6.0
8%
16.0
4%
10.5
1%
-17.0
9%
-30.1
7%
33.9
2%
41.1
4%
-14.6
5%
0.3
1%
1.1
8%
1.0
3%
11.6
7%
-0.0
3%
3.5
2%
5.8
6%
9.1
8%
7.5
7%
0.5
7%
0.5
7%
Gre
ym
outh
-3
8.3
6%
12.3
8%
-8.8
5%
-4.9
3%
3.7
1%
-7.1
7%
21.9
0%
-4.0
7%
8.6
4%
3.2
5%
1.9
8%
1.9
4%
1.9
0%
1.8
3%
1.8
0%
1.7
6%
1.7
3%
1.7
0%
1.6
8%
Kum
ara
10.1
5%
-21.1
0%
17.3
7%
15.3
9%
16.9
7%
-15.0
4%
-23.3
0%
-0.1
5%
16.7
8%
0.0
3%
0.0
3%
0.0
5%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
0.0
0%
Hokitik
a19.1
3%
-9.9
7%
12.6
8%
14.5
4%
1.0
9%
4.8
1%
-9.8
1%
5.7
0%
-5.2
2%
2.9
3%
-13.8
5%
3.2
2%
2.4
3%
3.0
7%
2.0
7%
2.0
3%
1.9
9%
3.2
2%
1.8
9%
Otira
-63.2
2%
5.4
7%
-71.8
5%
531.5
8%
-37.9
2%
69.8
0%
-90.1
2%
44.0
0%
341.6
7%
1.0
0%
0.9
9%
0.9
8%
0.9
7%
0.9
6%
0.9
5%
0.9
4%
108.6
7%
26.2
6%
0.3
5%
To
tal
Lo
ad
-6.5
5%
3.1
9%
5.7
0%
7.1
5%
3.8
1%
8.2
0%
12.5
9%
3.5
9%
-8.4
0%
2.0
8%
-3.4
7%
6.4
2%
2.8
2%
3.9
0%
2.7
3%
3.7
1%
3.9
3%
1.7
8%
1.1
4%
Actu
al
Actu
al
Actu
al
Actu
al
Actu
al
Actu
al
Actu
al
Actu
al
Actu
al
Fo
recast
Fo
recast
Fo
recast
Fo
recast
Fo
recast
Fo
recast
Fo
recast
Fo
recast
Fo
recast
Fo
recast
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
kW
2003
2004
2005
2006
2007
2008
2009
2010
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
Reeft
on
00
02986
7216
7328
7194
8452
8376
8460
8544
8635
8726
8810
8894
8978
9061
9145
9229
Ata
rau
00
00
336
948
3218
5662
616
619
622
1458
2294
3131
3134
3137
3140
3143
3147
Dobson
11155
12944
14305
11860
8282
11091
15654
13361
13402
13561
13701
15300
15295
15833
16761
18300
19686
19798
19909
Gre
ym
outh
8866
9964
9082
8634
8954
8312
10132
9720
10560
10903
11119
11335
11551
11762
11973
12184
12396
12607
12818
Kum
ara
1649
1301
1527
1762
2061
1751
1343
1341
1566
1566
1567
1568
1568
1568
1568
1568
1568
1568
1568
Hokitik
a
14098
12693
14302
16381
16560
17357
15655
16548
15685
16144
13908
14355
14705
15156
15470
15783
16097
16615
16929
Otira
256
270
76
480
298
506
50
72
318
321
324
328
331
334
337
340
710
896
900
To
tal
Lo
ad
36024
37172
39292
42103
43707
47293
53246
55156
50523
51574
49784
52978
54470
56594
58137
60291
62658
63772
64499
PE
RC
EN
T I
NC
RE
AS
E O
R D
EC
RE
AS
E
128 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Reefton Delivered
-
1.00
2.00
3.00
4.00
5.00
6.00
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
2.0
4.0
6.0
8.0
10.0
12.0
MD
(M
W)
GWh MD
Dobson 33 Delivered
-
1.00
2.00
3.00
4.00
5.00
6.00
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
5.0
10.0
15.0
MD
(M
W)
GWh MD
Greymouth Delivered
-
2.00
4.00
6.00
8.00
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
5.0
10.0
15.0
MD
(M
W)
GWh MD
Kumara Delivered
-
0.10
0.20
0.30
0.40
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
0.5
1.0
1.5
2.0
MD
(M
W)
GWh MD
Hokitika Delivered
-
2.00
4.00
6.00
8.00
10.00
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
5.0
10.0
15.0
20.0
MD
(M
W)
GWh MD
Otira Delivered
-
0.05
0.10
0.15
0.20
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
0.2
0.4
0.6
0.8
MD
(M
W)
GWh MD
Total Load ex Transpower
-
5.00
10.00
15.00
20.00
25.00
30.00
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
10.0
20.0
30.0
40.0
50.0
60.0
MD
(M
W)
GWh MD
Atarau Delivered
-
0.50
1.00
1.50
2.00
2.50
Jan
Feb
Mar
Apr
May
Jun
Jul
Aug
Sep
Oct
Nov
Dec
Month
GW
h
0.0
2.0
4.0
6.0
8.0
MD
(M
W)
GWh MD
Figure5.6-GXPEnergyandDemandStatistics-2011
NETWORKDEVELOPMENT 129
Acarefulandrigorousapproachhasbeentakentodevelopingfutureloadprojectionsbasedonhistoricaltrends,available informationandestimateson futurechanges.Theseprojectionsdonot takeanyof theembeddedgenerationonWestpower’snetworkintoaccountbecausethetotalenergydeliveredisnotaffectedbythem.
Firstly,loadtrendsateachGXPovertheprevioussevenyearsarestudiedtotryandidentifyhistoricbaselinechanges.Theeffectsofknownsteploadincreasesareextracted,leavingtheunderlyinglong-termhistoricloadprofile.
Figure5.6(previouspage)showstheGXPdemandforthe2011calendaryear.
Basedonthesedata,andgeneralknowledgeofthelocaleconomyandotherdriversdiscussedabove,anestimateismadeofthelikelyfuturetrendinloadgrowthonaGXPbasis.Thisthenprovidesanewbaselineforfurtherwork.
5.4.2 FutureGXPLoadProjections
Customerinputissoughtthroughforumswheremajorpotentialusersaregatheredandprovidedwithupdatesoncurrentloadtrendsandcapacityprojections.Followingthis,eachcustomerorcustomergroup(e.g.tourism)isaskedtoproviderealisticforwardloadprojectionsbasedontheirspecificindustryknowledge.Thisinformationhasprovedtobeextremelyvaluable,andthedatacollectedforthecurrentplanningexercisehaveresultedinasignificantlyimprovedprojectionforfutureloads.ThishasadirectimpactonWestpower’sfutureplansfornetworkreinforcement.
Thedatacollectedfromthecustomersareanalysedandadjustedwithaweightcoefficientbasedonthelikelihoodofoccurrence,andtheresultsareincludedintothezonesubstationloadforecasts.ThisistermedaLoadwatch.Thelikelihoodweightcoefficientsare:
• Loadisconfirmed=100%;
• Loadislikelytooccur=70%;
• Loadispossibletooccur=30%;
• Loadisspeculative=10%.
Table5.7belowshowsthecurrentmaximumdemand,firmcapacityandutilisationfactor.
This table showsnon-coincident demands at eachGXPand includes periodswhere loadhas been switchedbetweenGXPs.Nevertheless,itreflectstheloadthateachGXPmustbecapableofsupplying.
Although the local economyhasbeen significantly impactedby thePikeRiverminedisaster, theunderlyingeconomic growth on the West Coast from other sectors such as the dairy, gold and timber industries isunderpinning solid performance.Over the next two years, this underlying effect is expected to continue asworldwidedemandforcommoditiescontinuestorecover.
Currently,therearenomoreconstraintsinthetransmissionnetworkfeedingtheWestCoast,meaningthatmuchoftheloadcouldbeconsideredasuninterruptible,asthereissufficientn-1transmissioncapacityavailable.
Table 5.7 - GXP Maximum Demand and Current Capacity Utilisation
GXP Feeder Maximum Demand 2011 (MW)
Maximum Demand 2011 (MVA)**
Firm Capacity (MVA) Utilisation %
DOB0331 13.793 14.519 17 85.41%
GYM0661 13.444 14.152 15 94.34%
KUM0661 9.540 10.042 10 100.42%
HKK0661 18.452 19.423 20 97.12%
OTI0111 0.694 0.731 2.5 29.22%
RFN110 9.916 10.438 30 34.79%
ATU110(LGN110)* 1.104 1.162 20 5.81%
*TheAtarauswitchingstationsuppliesLogburnsubstationandthereforetheutilisedfactorisapplicabletoLogburn.
**Themaximumdemand(MVA)iscalculatedbasedontheassumptionthatthepowerfactoris0.95.
130 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Withsuchastrongcommunitysupport,theWCGUPwascompletedsuccessfullylate2011.Theoverallprojecthadthefollowingscopeofwork:
• Installasecond110kVcircuitbetweenReeftonandDobson;
• Installasecond110/66kVtransformerattheDobsonsubstation;
• Installanew14MvarfastswitchingcapacitorbankattheHokitikasubstation.
TheHokitikacapacitorsectionoftheprojectwascompletedinJune2010,andthe110kVlineandassociatedtransformerwascompletedinlate2011.
Thereasonfortheinstallationofthenew14MvarswitchingcapacitorbankatHokitikaistoprovidefastswitchingreactivesupporttohelppreventvoltagecollapseintheWestCoastareafollowinganemergency.
Thegreatestchallenge inplanning for futurenetworkdevelopment is toaccuratelydeterminethe likelihoodandsizeoffuturestepchanges.Toa largeextentthis isbasedondiscussionswithexistingorpotential largeconsumers.Earlyloadindicationsprovidedbytheseconsumersareoftenveryapproximateandaresubjecttomajorvariationsifandwhentheprojectproceeds.
Furthermore, theWest Coast has a history of prematuremajor development announcements beingmade,onlytofallthroughwhenmacro-environmentalchangesoccursuchasthegoldpricedroppingorachangeingovernmentpolicy.Forthisreason,theprojectedsteploadchangesmustbeviewedcircumspectlyuntilthereisafirmcommitment.
Twoofthelargerindustrialcustomershaveindicatedtheywillbeincreasingtheirloadoverthenextfiveyearsaspresentedbelow:
1. WestlandMilkProductsisplanningtoinstallafurtherdryerin2014andthiscouldaddanother2-4MWtotheirload.
2. SolidEnergyNewZealandLimitedis investigatinganewcoalminenearStrongman(about4MW),whichcouldhappenby2015.
Additionaltotheabovementionedloads,severalnewdairyfarmsmaybedevelopedintheFoxGlacierareaontheLandcorpFarmingLtdpropertyoverthenextfiveyearsnowthatWestlandMilkProductshasextendeditscollectionareatoincludethisregion.
Theimpactofsmallembeddedordistributedgenerationisnottakenintoaccountintheloadforecast,mainlybecause it isnotguaranteed that thisgenerationwillbeavailablewhen requiredandWestpowerprefers toadoptaprudentpeakdemandforecastapproach.
Theprojectedadditionaldemandoverthenexttenyearsisintheorderof15MW.PriortotheWCGUPbeingcommissioned,theTranspowersupplycapacityfromthenorthwasconstrainedtoabout24MWwhilethetotalafter diversity systemdemand is around 50.5MW. TheDOB-TEEA line effectively doubles the transmissioncapacity,thusprovidingsecuritytotheWestCoastgrid.
5.4.3 FutureZonesubstationLoadProjections
Loadforecastingiscarriedoutatthezonesubstationlevel,andthisiscriticaltoensurethatsufficientcapacityisavailableinWestpower’ssubtransmissionandzonesubstationinfrastructure.Theseforecastsaredevelopedusingazero-basedapproachandloaddemandmanagementfrominformationandrequestsreceiveddirectlyfromcustomers,includingintelligenceonfutureloadtrendssuchasproposeddairyfarmconversions.
FuturezonesubstationloadprojectionsdemonstratethatmostofWestpower’szonesubstationshavesufficientcapacitytodealwithexpected loadgrowththroughouttheplanningperiod,althoughsomesubstationsmayrequire capacity upgrades in eight to ten years. As these load forecasts are subject to change and involveconsiderableuncertainty,noprojectshavebeencommittedforthezonesubstationsatthisstage,butaclosewatchwillbekeptoncustomers’loadexpectationsandmaximumdemandtrends.
NETWORKDEVELOPMENT 131
InWestpower’scase,mostofthesubtransmissioninfrastructurehasbeenbuiltwithinthelast20yearsandhasbeenprudentlydesignedtocaterforfutureloadgrowth,whichmeansthatthereisusuallyamplecapacitytocaterformarginalloadgrowth.Intheeventofproposalsformajorloadstepscrystallising,eachcaseisconsideredinisolationandincombinationwithotherproposalstomakesurethatanyconstraintsduetosubstationcapacityaretakenintoaccount.
AsummaryoftheresultsbymajorzonesubstationisshowninTable5.8.
Table 5.8 - Zone Substation Forecast Demand
Zone Sub-station
Firm Capacity (MVA)
Peak 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Block Arnold 5 3.357 3.36 3.39 3.42 3.45 3.47 3.48 3.50 3.52 3.52 3.52 3.52
BaseGrowth 0.0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LoadwatchGrowth 0.03 0.03 0.04 0.02 0.02 0.02 0.02 0.00 0.00 0.00 0.00
PredictedLoad 3.39 3.42 3.45 3.47 3.48 3.50 3.52 3.52 3.52 3.52 3.52
Block Blackwa-ter 5 1.47 1.47 1.50 1.53 1.56 1.79 2.02 2.25 2.28 2.31 2.34 2.37
BaseGrowth 2.0% 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
LoadwatchGrowth 0.00 0.00 0.00 0.20 0.20 0.20 0.00 0.00 0.00 0.00 0.00
PredictedLoad 1.50 1.53 1.56 1.79 2.02 2.25 2.28 2.31 2.34 2.37 2.40
Block Dobson 5 1.875 1.88 1.94 2.01 2.08 2.15 2.21 2.28 2.33 2.39 2.43 2.47
BaseGrowth 2.0% 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
LoadwatchGrowth 0.03 0.03 0.03 0.03 0.03 0.03 0.01 0.03 0.00 0.00 0.00
PredictedLoad 1.94 2.01 2.08 2.15 2.21 2.28 2.33 2.39 2.43 2.47 2.51
Block FoxGla-cier 5 0.750 0.75 0.77 0.78 0.80 0.81 0.83 0.84 0.86 0.87 0.89 0.90
BaseGrowth 2.0% 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 0.77 0.78 0.80 0.81 0.83 0.84 0.86 0.87 0.89 0.90 0.92
Block FranzJosef 5 1.718 1.72 1.75 1.79 1.82 1.86 1.89 1.92 1.96 1.99 2.03 2.06
BaseGrowth 2.0% 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 1.75 1.79 1.82 1.86 1.89 1.92 1.96 1.99 2.03 2.06 2.10
Block Globe 8 5.616 5.62 5.84 6.07 6.20 6.23 6.26 6.28 6.31 6.34 6.37 6.40
132 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table 5.8 - Zone Substation Forecast Demand
Zone Sub-station
Firm Capacity (MVA)
Peak 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
BaseGrowth 0.5% 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03 0.03
LoadwatchGrowth 0.20 0.20 0.10 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 5.84 6.07 6.20 6.23 6.26 6.28 6.31 6.34 6.37 6.40 6.42
Block Grey-mouth 15 13.444 13.44 13.88 14.16 14.43 14.71 14.97 15.24 15.51 15.78 16.05 16.32
BaseGrowth 2.0% 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27 0.27
LoadwatchGrowth 0.17 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 13.88 14.16 14.43 14.71 14.97 15.24 15.51 15.78 16.05 16.32 16.59
Block Harihari 1 1.044 1.04 1.07 1.10 1.12 1.15 1.17 1.19 1.21 1.23 1.25 1.27
BaseGrowth 2.0% 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
LoadwatchGrowth 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 1.07 1.10 1.12 1.15 1.17 1.19 1.21 1.23 1.25 1.27 1.29
Block Hokitika 20 18.452 18.45 18.99 16.36 16.89 17.30 17.83 18.20 18.57 18.94 19.55 19.91
BaseGrowth 2.0% 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37 0.37
LoadwatchGrowth 0.17 -3.00 0.16 0.04 0.16 0.00 0.00 0.00 0.24 0.00 0.00
PredictedLoad 18.99 16.36 16.89 17.30 17.83 18.20 18.57 18.94 19.55 19.91 20.28
Block Kumara 10 9.540 9.54 9.54 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55
BaseGrowth 0.0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 9.54 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55 9.55
Block Logburn 20 1.104 1.10 1.11 1.12 2.61 4.11 5.61 5.62 5.62 5.63 5.63 5.64
BaseGrowth 0.5% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
LoadwatchGrowth 0.00 0.00 1.49 1.49 1.49 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 1.11 1.12 2.61 4.11 5.61 5.62 5.62 5.63 5.63 5.64 5.64
Block Ngahere 5 3.107 3.11 3.17 3.00 3.69 3.26 3.32 3.38 3.44 3.50 3.57 3.63
BaseGrowth 2.0% 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06 0.06
LoadwatchGrowth 0.00 -0.23 0.63 -0.50 0.00 0.00 0.00 0.00 0.00 0.00 0.00
NETWORKDEVELOPMENT 133
Table 5.8 - Zone Substation Forecast Demand
Zone Sub-station
Firm Capacity (MVA)
Peak 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
PredictedLoad 3.17 3.00 3.69 3.26 3.32 3.38 3.44 3.50 3.57 3.63 3.69
Block Otira 2.5 0.694 0.69 0.70 0.71 0.71 0.72 0.73 0.74 0.74 1.55 1.96 1.96
BaseGrowth 1.0% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.80 0.40 0.00 0.00
PredictedLoad 0.70 0.71 0.71 0.72 0.73 0.74 0.74 1.55 1.96 1.96 1.97
Block Pike 15 0.761 0.76 0.79 0.81 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83
BaseGrowth 0.0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LoadwatchGrowth 0.03 0.02 0.02 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 0.79 0.81 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83 0.83
Block Rapahoe 5 2.177 2.18 2.22 2.27 2.32 2.37 2.41 2.46 2.50 2.54 2.59 2.63
BaseGrowth 2.0% 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04 0.04
LoadwatchGrowth 0.00 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 2.22 2.27 2.32 2.37 2.41 2.46 2.50 2.54 2.59 2.63 2.67
Block Reefton 30 9.916 9.92 10.02 10.11 10.22 10.33 10.43 10.53 10.63 10.73 10.83 10.93
BaseGrowth 1.0% 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10 0.10
LoadwatchGrowth 0.00 0.00 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 10.02 10.11 10.22 10.33 10.43 10.53 10.63 10.73 10.83 10.93 11.02
Block Ross 1 0.447 0.45 0.46 0.47 0.47 0.48 0.49 0.50 0.51 0.52 0.53 0.54
BaseGrowth 2.0% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 0.46 0.47 0.47 0.48 0.49 0.50 0.51 0.52 0.53 0.54 0.55
Block SpringCreek 8 6.638 6.64 6.64 6.84 8.04 8.34 8.84 9.84 11.64 13.24 13.24 13.24
BaseGrowth 0.0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LoadwatchGrowth 0.00 0.20 1.20 0.30 0.50 1.00 1.80 1.60 0.00 0.00 0.00
PredictedLoad 6.64 6.84 8.04 8.34 8.84 9.84 11.64 13.24 13.24 13.24 13.24
134 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.4.4 PossibleConstraints
5.4.4.1 HarihariSubstation
Themaximumpeakdemandrecordedin2011wasabout1MVAandreachedthefirmcapacityofthesubstation.Toeliminatethisconstraint,thesubstationcapacityneedstobeincreasedoraloadmanagementprogrammeneedstobeimplemented.
TheInternationalElectrotechnicalCommission(IEC)standardsstatethateveryoil-filledtransformermanufacturedinaccordancewiththestandard,hastowithstanda25%loadincreaseoveritsnominalcapacitycontinuously.Therefore,eventhoughthepeakloadhasreachedthefirmcapacityofthesubstation,thetransformershouldwithstandanextra25%ofloadincrease.
Basedontheloadforecast,theloadincreaseby2019is23%abovethefirmcapacityofthesubstation.
Consequently,thetransformerneedstobereplacedwithinthistimeframebyupgradingjustthetransformerintheexistingsubstationiftheloadisincreasingmorethanwhatispredicted.
Table 5.8 - Zone Substation Forecast Demand
Zone Sub-station
Firm Capacity (MVA)
Peak 2011 2012 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Block Wahapo 5 3.091 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09
BaseGrowth 0.0% 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09 3.09
Block Waitaha 1 0.261 0.26 0.27 0.27 0.28 0.28 0.29 0.29 0.30 0.30 0.31 0.31
BaseGrowth 2.0% 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01 0.01
LoadwatchGrowth 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 0.27 0.27 0.28 0.28 0.29 0.29 0.30 0.30 0.31 0.31 0.32
Block Whataroa 1 0.772 0.77 0.80 0.82 0.84 0.85 0.87 0.89 0.90 0.92 0.93 0.95
BaseGrowth 2.0% 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02 0.02
LoadwatchGrowth 0.01 0.01 0.01 0.00 0.00 0.00 0.00 0.00 0.00 0.00 0.00
PredictedLoad 0.80 0.82 0.84 0.85 0.87 0.89 0.90 0.92 0.93 0.95 0.96
Legend:
-representsfirmcapacityoverloadedbyupto25%
-representsfirmcapacityoverloadedbyover25%
NETWORKDEVELOPMENT 135
5.4.4.2 HokitikaSubstation
MaximumpeakdemandrecordedforHokitikasubstationin2011wasabout18.5MVAand,accordingtoourloadforecast,by2019,thetotalloadwillreachthefirmcapacityofthesubstation.AstheHokitikasubstationhastwotransformersinparallel,theconstraintmainlyappliesduringmaintenanceperiodswhenonetransformerwouldbeoutofservice.Thiscouldberesolvedatthemaintenanceplanningstageand/orbyimplementingaloadmanagementprogramme.
5.4.4.3 GreymouthSubstation
Recordingamaximumpeakdemandof13.4MVAlastyearandconsidering2%loadgrowthforthefollowingyears,thedemandforthissubstationcouldreachthefirmcapacityby2017.
Byinstallingoilcirculatingpumpsandfansonbothtransformers,thecapacityhasalreadybeenincreasedfrom10-15MVApertransformer.Therefore,iftheloadreachesfirmcapacitysomemaintenanceconstraintscouldarise.Asmentionedabove,thiscouldberesolvedatthemaintenanceplanningstageand/orbyimplementingaloadmanagementprogramme.
5.4.4.4 SpringCreekSubstation
Eventhoughthepredictedloadwillreachthefirmcapacityofthesubstationby2014,there isnoconstraintidentifiedforthe33kVline.ThesubstationisnotownedbyWestpowerandisincludedinTable5.8onlyforloadforecastpurposes.
5.4.5 ImpactofDemandManagementonLoadForecast
RipplecontrolofwaterheatingformsacorepartofWestpower’sloadmanagementstrategyandprovidestheability todefernetworkexpenditure inareaswhereasset loadingshaveexceededavailablecapacityatpeaktimes.Moreover,oncetheHVDirectCurrent(HVDC)upgradeiscompletedin2012andNewZealandeffectivelybecomesasinglereservesmarket,additionalvaluemaybecomeavailablethroughtheabilitytobidinterruptibleloadintothemarket.
Thereareestimatedtobearound9000waterheaterssuppliedbyWestpower.Approximatelyhalfoftheseareon a fixed night-only ripple control programme that ensures they are not energised during coincident peakperiods.TheafterdiversitydemandoftheremainingwaterheatersintheWestpowernetworkthatareavailableforcontrolbyWestpower’sloadmanagementsystemisestimatedtototal4.5MWatthetimeoftheregionalcoincidentpeakonacoldwinterevening.
Westpower supports injection telegrams for both the older Plessey Rhythmatic receivers as well as newerDecabitunits.However,Westpowerdoesnotownripplecontrolreceiversandthereforehaslimitedabilitytocontroltheirinstallationandmaintenance.
Therippleinjectionsystemismodernandwellmaintained,withsignificantredundancybuiltinthroughtheuseoftime-synchronisedsimultaneousinjectionacrossallfourrippleplantsspreadthroughoutWestpower’sarea.Asaresultofsignificantsignal“spill”,thefailureofasingleplanthasaminimalimpactonoverallsignallevels.
Afterdiversityloadsusedforforecastingloadgrowthinherentlytakeintoaccounttheabilitytoshedloadatpeaktimes,asthesedemandsarebasedonhistoricalloadingfiguresderivedfromactualnetworkperformance.Thisisparticularlytruefornewerhousesusingelectricwaterheating,asgenerouscylindercapacitiesaresupplementedbyadditionalvirtualstoragethroughtheuseoftemperingvalves,leadingtotheabilitytosupplytheloadfullyoff-peakwithanightrateonlytariff.
However, for existing installationswith limited storage, the increasingeffectsofdiversity result in adilutionoftheamountofafterdiversitydemandonthenetworkandloadavailabletoshedatthetimeoflocalpeakdemands,astheloadsareaggregatedacrosszonesubstations,GXPsandentireregions.
136 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Magnifyingthisphenomenon,recentchangestothetransmissionpricingmethodologyhaveledtoWestpowerbecomingapartofajointloadcontrolschemedrivenbyOrionthatfocusesonminimisingtheRegionalCoincidentPeakDemand(RCPD)onTranspower’supperSouthIslandnetwork,ratherthanjustcontrollingWestpower’sownpeakdemandsatlocalGXPs.Thischangeinphilosophyhasresultedinmarkedlydifferentpeakdemandsheddingbehaviour,andtheresultingimpactondiversityandindividualGXPpeakdemandsisstillbeinganalysed.
Oncetheseeffectsareclearlyunderstood,itmaywellresultinWestpowermovingbacktowardsupplementarycontroloflocalGXPdemandinadditiontotheupperSouthIslandcontrolschemeiftherearetangiblebenefitstobehad.Theforecastswouldthenbeupdatedaccordingly.Inthemeantime,theloadforecastsarebaseduponthecurrentdemandmanagementregimeofregionalloadcontrol.
Inanycase,becauseWestpower’snetworkisgenerallyunconstrainedatthedistributionandsubtransmissionlevel, it isunlikelythatevenasignificantchangeindemandmanagementpracticeswouldhaveadiscernibleimpactonshort-to-mediumtermnetworkinvestmentdecisions.
5.5 Distributed Generation
Westpower’spolicy regardingdistributedgeneration is toassistany individualsororganisations through theapplicationprocessandallowtheconnectionofdistributedgenerationtoitsnetwork.
Westpowerwillalsoensurethatanynewdistributedgenerationconnectedtoitsnetworkwillcomplywithallrelevantstatutoryandregulatoryrequirements,andapplicablesafetystandards.
The main framework for implementing this policy is established by Electricity Governance (Connection ofDistributedGeneration)Regulations2007.
Dependingonthemaximumcapacityofthedistributedgenerationtobeinstalled,theapplicationprocessdifferssignificantly.Therefore,for10kWorlessofcapacity,theapplicationwillbeaone-stageprocess;forover10kWofcapacity,itwillbeatwo-stageprocess.
Figure5.9showsthedistributedgenerationprocess.
I. System Selection
Usually,distributedgenerationabove10kWconsistsofdiesel,windorhydrogenerators; thatbelow10kWconsistsoflargearraysofsolarpanelsorrotatingplantssuchaswindturbines.
Theselectionof theequipmentusedaspartof thedistributedgenerationsystemshouldbeplannedaheadtoensurethattheentiresystemcomplieswiththerequirementsoftheHealthandSafetyinEmploymentAct1992,theElectricityAct1992,andtherulesandregulationsmadeundertheElectricityAct1992.ItalsoshallbeinstalledinaccordancewithWestpower’sConnectionandOperationStandardsandAS4777,NZECP4:1993and/orNZS/AS3000:2000-ElectricalInstallations(knownastheAustralian/NewZealandWiringRules)oranysubsequentrevision.
II. Submission of Application
Anypersonororganisationwhowishestoconnectdistributedgenerationcapableofgeneratingelectricityat10kWorlesstothenetworkmustsubmitanapplicationtoWestpowerandprovidealltheinformationrequiredinrespectofthedistributedgenerationproposedtobeconnected.
Theapplicationformhastobeaccompaniedbythefollowingattachments:
1. Informationaboutthenameplateratingorothersuitableevidencethatthegeneratingunitis(orwillbe)onlycapableofgeneratingelectricityatarateof10kWorless;
2. Detailedinformationabouttheinverterand/orbattery(ifapplicable);
3. Technicalspecificationsoftheequipmentthatallowthedistributedgenerationtobedisconnectedfromthenetworkonlossofmainsvoltage;
NETWORKDEVELOPMENT 137
I
II
III
IV
V
VI
VII
VIII
IX
X
XI
XII
Distributed Generation
Process
10 kW
Capacity or
Less
YES NO
Initial Application
Final Application
Submission of Initial
Application
Initial Application
Evaluation Process
Initial Application
Completed
Submission of Final
Application
Final Application
Approval Process
Notice of Intention to
Proceed
Connection Contract
Negotiation
Installation, Inspection
and Testing
Connection
Established
Application Approval
Process
Submission of
Application
System Selection
Application Process
Connection Process
Figure5.9-DistributedGenerationProcess
138 WESTPOWERASSETMANAGEMENTPLAN2012-2022
4. Information and justification showing how the distributed generation complies with AS4777 (whereappropriate);
5. InformationandjustificationshowinghowthedistributedgenerationcomplieswithWestpower’sconnectionandoperationstandards;
6. Theapplicationfee.
III. Application Approval process
Basedontheinformationprovidedintheapplication,Westpowerwillassessif:
1. TheapplicantcomplieswiththerequirementsoftheHealthandSafetyinEmploymentAct1992;and
2. The distributed generation complies with the Electricity Act 1992, and the regulations and rulesmadeunderthisAct;and
3. The connection of the distributed generation complies with Westpower’s Connection and Operationstandards(Westpower’sDistributionCode).
IV. Submission of Initial Application
Similartothe“SubmissionofApplication”stagefordistributedgenerationwithacapacitylessthan10kW,theapplicantshavetosubmitaninitialapplicationformaccompaniedbydetailedinformationasrequestedintheformandtheapplicationfee.
V. Initial Application Evaluation Process
Afterreceivingacompleteapplicationforadistributedgenerationwithacapacitygreaterthan10kW,Westpowerwillprovidetheapplicantwiththefollowinginformation:
1. Thecapacityofournetwork,includingboththedesigncapacity(includingfaultlevels)andactualoperatinglevels;
2. Theextenttowhichconnectionandoperationofthedistributedgenerationmayresultinabreachoftherelevantstandardsforsafety,voltage,powerqualityandreliabilityofsupplytootherconnectedparties;
3. Anymeasuresorconditions,includingmodificationstothedesignandoperationofWestpower’snetworkortotheoperationofthedistributedgeneration;
4. Theapproximatecostsofanynetwork-relatedmeasuresorconditionsidentifiedabove,andanestimateoftimeconstraintsorrestrictionsthatmaydelaytheconnectionofthedistributedgeneration;
5. Any furtherdetailed investigativestudies thatWestpowerreasonablyconsidersnecessary to identifyanypotentialadverseeffectsonthesystemresultingfromtheproposedconnection;
6. Anyobligationstootherpartiesthatcouldaffectthedistributedgeneration;
7. AnyadditionalinformationordocumentsthatWestpowerconsiderslikelytoassisttheapplication;
8. Informationabout theextent towhichplannedandunplannedoutagesmayaffect theoperationof thedistributedgeneration.
VI. Initial Application Completed
Westpowerwillprovide,ifrequestedbytheapplicant,furtherinformationthatisreasonablynecessarytoenabletheapplicanttoconsiderandactontheinformationprovidedduringtheinitialapplicationprocess.
VII. Submission of Final Application
The final application has to be submitted toWestpower within 12months after the initial application wascompletedandhastobeaccompaniedbyanyinvestigativestudiesthatwereidentifiedduringthatstage.
NETWORKDEVELOPMENT 139
VIII. Final Application Approval Process
Similartothe“ApplicationApprovalProcess”stagefordistributedgenerationwithacapacitylessthan10kW,basedontheinformationprovidedintheapplication,Westpowerwillassessif:
• TheapplicantcomplieswiththerequirementsoftheHealthandSafetyinEmploymentAct1992;
• ThedistributedgenerationcomplieswiththeElectricityAct1992,andtheregulationsandrulesmadeunderthisAct;
• The connection of the distributed generation complies with Westpower’s Connection and Operationstandards(Westpower’sDistributionCode).
IX. Notice of Intention to Proceed
Oncethefinalapplicationforconnectionofthedistributedgenerationisapproved,theapplicantmustsendawrittennoticetoWestpowerconfirminghis/herintentiontoproceedwiththeconnection.Theapplicantalsohastoacceptalltheconditions(orothermeasures)whichWestpowerhasspecifiedasconditionsoftheconnectionandprovidedetailsofthegenerationtobeconnected.
FailuretoprovideWestpowerwithanoticeofintentionwithinthetimeframespecifiedwillleadtocancellationoftheapplicationandcessationofWestpower’sresponsibilitiesundertheElectricityGovernance(ConnectionofDistributedGeneration)Regulations2007.Thisdoesnotpreventtheapplicantfromsubmittinganewapplicationforconnectionofdistributedgeneration.
X. Connection Contract Negotiation
Afterreceivingthenoticeofintentiontoproceed,boththeapplicantandWestpowershould,ingoodfaith,trytonegotiateaconnectioncontract.
Ifnoconnectioncontractisnegotiatedwithinthepredefinedtimeframe,theregulatedtermsestablishedbytheElectricityGovernance(ConnectionofDistributedGeneration)Regulations2007willapplytothenewconnection.
Theperiodfornegotiatingaconnectioncontractmaybeextendedbymutualagreementbetweenbothparties.
XI. Installation, Inspection and Testing
All wiring associated with the distributed generation system must comply with AS/NZS 3000 - ElectricalInstallations(Australian/NewZealandWiringRules)oranysuccessivestandardorlegislation,andbeundertakenbyaregisteredelectricianwhererequiredbylegislation.
WhileAS4777.1dealsprimarilywiththeconnectionofinverterbasedsystems,theprinciplescoveredbythisStandardshallalsobefollowedfordistributedgenerationsystemsthatdonotemployinverters.Also,theElectricalEngineersAssociation’s(EEA)–“GuidefortheConnectionofGeneratingPlant”mayassisttheapplicantwithdeterminingthemostappropriateelectricalarrangementsfortheconnectionandprotectionofthedistributedgenerator.
BeforeconnectingthedistributedgenerationtoWestpower’snetwork,ithastobeinspectedandtested.Asaminimum,theapplicantmustensurethat:
1. Theinspectionandtestshavebeenarranged;
2. Westpower has received adequate notice regarding the inspection and tests so they can send qualifiedpersonneltothesiteforobservation;
3. Awrittentestreport,includingsuitableevidencethatthemeteringinstallationcomplieswiththemeteringstandardsandrules,isprovidedtoWestpower;
4. ThefeespecifiedbyWestpowerforobservingthetestingandinspectionhasbeenpaid.
140 WESTPOWERASSETMANAGEMENTPLAN2012-2022
XII. Connection Established
Oncetheconnectionhasbeenestablished,theapplicantandWestpowermustperformallobligationsunderthenegotiatedconnectioncontractorregulatedtermsinaccordancewithconnectionandoperationstandards.
5.6 Non-Network Options
Anumberofstrategiesareavailablefordealingwithloadincreases,asshowninTable5.10.
Eachoftheseoptionsiscarefullyevaluatedbasedoneconomicefficiencyandtechnicalperformance.Whereverpossible,capitalintensivedevelopmentisdelayeduntilabsolutelynecessary,andnon-assetintensivesolutionsareusedwherethesearenotincompatiblewithfuturedevelopmentplans.
For instance, reactivesupportand/orvoltageregulation is routinelyemployedtosupportdairy farming loadgrowthinruralareasasthisisfarmorecost-effectivethanoverlayingwithahighervoltage.
Whereveryshorttimeframesareinvolvedandpermanentsolutionsarenotpossiblebeforetheloadcomesonstream,demandsidemanagementisoftenemployedbymakingatleastpartoftheadditionalloadinterruptibleuntilalong-termsolutioncanbeputinplace.
Ignoringsuchincreases,thefirstthreesolutionsidentifiedinthetable,areessentiallynon-assetintensive.
Table 5.10 - Options for Handling Load Increases
Strategy Application
EconomicTariffStructuremodels
Theseoptionsincludedemand-basedtariffs,off-peakdiscountsandpenaltiesforpoorpowerfactor.Bysignallingthetruemarginaleconomiccostsofnetworkextensions,theconsumerisabletorespondtothesepricingsignalsbymodifyingtheirconsumptionbehaviourandreducingtheircosts.Thisisbestappliedinthecaseofmarginalloadgrowthwhereoptimisationofthenetworkisabletounlockitsfull
potential.
DemandSideManagementDemandsidemanagementistypicallyappliedbymeansofripplecontrolswitchingofinterruptible
loadssuchaswaterheatingandnightstoreheaters.Westpowerroutinelyappliesthismethodtoreduceregionalpeakdemand,whichassistsTranspowerinmanagingexistingtransmissionconstraints.
LineDropCompensation
Onlongruralfeederswheremostoftheloadissituatedtowardthemiddleorfarendofthefeeder,linedropcompensationisavalidmeansofimprovingreceivingendvoltageregulationandmaximisingthelinecapacity.Thisisgenerallynotapplicablefor11kVfeederswithdistributedload,asnearendcus-tomerswouldbeadverselyaffectedbyvoltagerise.Cost-effective,butonlyapplicableinlimitedcases.
DistributedGeneration
DistributedgenerationisactivelyencouragedthroughoutWestpower’snetwork,butWestpowerisreliantonothersinvestinginthistechnology.Furthermore,unlessthegenerationisveryreliable,orsufficientlydiverse,thenetworkmuststillbesizedtoprovidefullloadwithoutthebenefitofgenera-tiontocaterfortimeswhenthegenerationisunavailableorbeingmaintained.Distributedgenerationisnotseenasapplicablewhereitistheonlymeanstosupplycontinuousloads,butmaybeusedbya
customerwhoishappytoputupwithoccasionalinterruptionsorconstraints.
VoltageRegulation
Onlong11kVor33kVfeeders,voltageconstraintscanbedealtwithbyinstallingeithercontinu-ouslyvariableorsteppedvoltageregulators.Westpowerappliesthistechnologyinareaswhereeithermarginalorsteploadsincreaseswouldotherwiseresultinunacceptablevoltageprofiles.Theseare
routinelyappliedinWestpower’s33kVor11kVnetworkstocaterforanincreaseindairyfarmloadingintheruralarea.
SystemReconfiguration
Wheresignificantloadsaresituatedattheendofameshedfeeder,itissometimespossibletopro-videenhancedcapacitybyswitchingtheloadtoanearbyfeeder.Inthecaseofonebulkcustomer,aplannedloadincrease(situatednearthetiepointbetweentwofeeders)willbecateredforbyspread-ingthefactoryloadacrosstwofeeders.Thisisverycost-effective,butdependsverymuchonfactors
suchaslocationoftheloadandthereforehaslimitedapplication.
ReactiveCompensation
Thistechniqueinvolvesinstallingcapacitorsonthe11kVdistributionnetworktoboostvoltageandimprovecapacity.WestpowerusesthistechniqueextensivelytosupportruralfeedersandsupportthetransmissiongridvoltagethroughouttheWestCoast.Sinceonlyacertainnumberoffixedcapacitorscanbeinstalledthroughoutthenetworkbeforevoltageriseproblemsoccur,muchmoreexpensive
switchedbanksarethenrequiredandthecost-benefitbalanceisshifted.Switchedcapacitorbanksarealsousedtosupportlargemotorstartingapplications.
NETWORKDEVELOPMENT 141
Demand-based tariffs give the end user strong incentives to reduce peak demand andmaximise plant loadfactors.ThisresultsinlesspeakdemandandbetterregulationontheWestpowernetwork.
Useofdemandsidemanagementislinkedtothetariffstructure,andallowstheplantorWestpowertocontrolitsinternaldemandbysheddingnonessentialloadatpeakperiods.
LineDropCompensation (LDC) canbeused in specific circumstances toboost the sendingendvoltageonafeedertoimprovedown-lineregulation.Thiseffectivelyincreasestheavailablecapacityonafeeder.
Westpowerhasalsobegunaprogrammeofinstallingcapacitorsatstrategicpointsinthenetworkwherevoltageconstraintsarepresentorimminent.Insomecases,loadgrowthforaparticularinstallationisdependentuponincreasedreactivesupport,andtheconsumerisrequiredtocontributetothecapitalexpenditureinvolved.
Distributed generation is seen as an excellentmeans of reducing demand on the Transpower network andenhancing theperformanceofWestpower’sdistributionnetwork.Assuch,Westpoweractivelysupports thisapproach.Atransparentpricingmethodology is inplacetoensurethat thereare lowentrybarriers fornewgenerators,and,iflargeenough,thatthesenewgeneratorsreceivethefullavoidedcostoftransmissionbenefitsthattheyareentitledto.
Technical requirements for connection of distributed generation are based on the industry standard EEAGuidelines.
Notwithstandingtheabovecomments,thequantumofloadincreasesinthatWestpoweriscurrentlyfacing,asdepictedinTable5.10,meansthatenergyconservation,distributedgenerationorsmallrenewablegenerationprojectsarenot,inthemselves,viablesolutionstotheconstraintsnowbeingfaced.Theydo,however,improvethequalityofsupplyandreducethemarginalcostsandlossesassociatedwithtransmittingenergyintothearea.
TheprocessthatWestpowerusestoidentifyandpursueeconomicallyandpracticalalternativestoconventionalnetworkaugmentationinaddressingnetworkconstraintsistoconsidereachofthefeasiblealternativesdiscussedabove in ascending order of cost and complexity until a solution is found that will meet the requirementsof Westpower and its consumers, without conflicting with Westpower’s medium and long-term planningrequirements.
Forinstance,theRoaMinerecentlysignalledasignificantincreaseindemanddrivenbyincreasedproduction.Themine is fed by a relatively long length of 11 kV line,which involves fewother consumers. In this case,additionalautomaticshuntreactivesupportallowedthedemandtobesuppliedwithoutviolatingacceptablevoltage limitsandalsoavoided theneed to invest inacostly reconductoringexercise.This savedmoney forWestpowerandultimatelytheconsumer,whowasrequiredtoprovideacapitalcontributiontofundthework.
Moreover,Westpowerisopentothedevelopmentofcommercialarrangementsthatcoulddefertheneedfornetworkinvestment(suchasthevoluntarycurtailmentofloadbymajorcustomersattimesofnetworkpeakdemand)andwouldwelcomediscussionwithstakeholdersonthismatter.
5.7 Network Development Options
5.7.1 ReeftonNetwork
Nosignificant loadgrowth iscontained in the loadwatchanalysis for theReeftonarea.Theexistingnetworkshouldbeadequatetohandleongoinggrowth.
In1999,Westpowerextendedits33kVsubtransmissionnetworkintheGreyValleyasfarasReeftonandbuiltanewzonesubstationonTranspower’sReeftonsubstationsite.ThisservedthebasedemandforseveralyearsuntilamajornewloaddevelopedintheformoftheReeftonGoldProject,whichiscurrentlyoperatedbyOceanaGoldLimited.
142 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Developmentofthisproject,involvingaloadof5.2MW,requiredsignificantstrengtheningofthesupplyintotheReeftonarea.Afterconsiderableinvestigation,thesolutionchosenbyWestpowerwastoconstructanew2x20MVA110/33/11kVzonesubstationatReeftonfedbytwo110kVlinesfromInangahua.OneoftheselineswastheexistingTranspowerDOB-IGH66kVcircuit,whichwasupgradedto110kV.Atthesametime,anew110kVspurfromInangahuatoReeftonwasconstructedbyWestpowerandthensoldtoTranspower.
Inaddition,anew33kVlineandsubstationwasconstructedtofeedtheminesiteandthishassufficientsparecapacitytohandleprojectedloadgrowththroughoutthelifeoftheexistingmine.
Alloftheseprojectswerecompletedin2005.
Thisworkwas designed to be compatiblewith Transpower’s own transmission development in the area toensurethatthegreatestsharedbenefitaccruestoconsumersintheareaintermsofbothcapacityandsecurity.ThismeansthattheReeftonareaisnowsuppliedbyastrongtransmissionnetworkwithn-1security,sofurtherdevelopmentwillbelimitedtothedistributionsystem.
Duetovoltageconstraintsonthe11kVcircuitsatIkamatua,anew33/11kVzonesubstationwasrequiredatBlackwatertoprovideanadditional500kWofdemandtothePikeRivercoalload-outfacilityatIkamatua.ThesubstationwascommissionedinDecember2009.
Thenetimpactoftheserecentdevelopmentsisthat,barringanysignificantandunexpectedloadgrowth,nofurtherstrengtheningofthesubtransmissionordistributionnetworkswillberequiredfortheremainderoftheplanningperiod.
5.7.2 GreymouthNetwork
SeveralsignificantcoalminingprojectswillpossiblybedevelopedinthefuturebySolidEnergy’sSpringCreekminenearRapahoe.
Thereisthepossibilityofuptoanadditional14MWbeingrequiredforSolidEnergy’sminesintheRapahoeareaandotherdevelopmentopportunitiesinthesameareawithinthenextfiveyears,butnoneofthisloadhasyetbeencommitted.
DuetothetragiceventthatoccurredatthePikeRivercoalmine,theloadatAtarauGXPhasdecreasedby6MW.Itishardtopredictwhetherthemineisgoingtobere-openedornot,butconsideringthattheinfrastructureisalreadyinplace,theminecouldbereopenedby2013.Ifthisisthecase,theloadcouldreach10-14MWasinitiallypredicted.
Anew110kVGXPswitchingstationatAtarauwascommissionedbyTranspowerin2007asabusontheDOB-RFN-IGHcircuit.Thisswitchingstation,alongwithassociated110kVand33kVlinesandsubstationsconstructedbyWestpower,willprovideforthefullprojectedloadatthissite.
Finally,baseloadgrowthandcontinuingexpansionintheexotictimbermillingandtourismindustrieswillrequirecapacityincreasesinthelongterm,probablyoutsidetheplanninghorizon.
TheexistingWestpower33kVsubtransmissionnetworkcansupportexpectedloadgrowth.TherecentupgradingoftheDOB-RFN-IGHlineto110kVhasalsostrengthenedthesupplyfromInangahuainthenorth,significantlyimprovingfirmcapacityintothearea.
IfTrustpowerproceedswithitsprojecttoupgradeArnoldpowerstation,anew66or110kVsubstationatKokirimaybe required to connect thepower station into the local transmission grid. Thenew substationmayberequiredby2016/17,dependingonafinaldecisiontoproceedfromTrustpower.
Olderdistributionlineswillberepairedandrefurbishedasrequiredbyongoingconditionassessment.
Voltagesupportmeasures, includingthe installationofcapacitorsandvoltageregulators,willcontinuetobeappliedatstrategicpointsinthenetworktomaximiseperformanceoftheexistingassets,improvepowerqualityandreducemarginallosses.
NETWORKDEVELOPMENT 143
Apartfromtheabove,nootherdevelopmentsareproposedthroughouttheplanningperiod.
5.7.3 HokitikaNetwork
Thecompletionof theWestlanddairy factorysupply in2002,comprisinganewWestpower2x15/20MVA66/33/11kVsubstationinHokitika,vastly improvedboththecapacityandsecurityofsupplytothetownofHokitikaandsurroundingdistricts,includingallofSouthWestland.ThiswillalsoprovideforcontinuingexpansionattheWestlanddairyproductsfactory,alongwithdownstreamgrowthinthedairyindustryingeneral,foratleastthenexttenyears.
TheWestlandDairyFactoryislikelytocontinuewithplansformajorsteploadincreasesthroughouttheplanningperiod,andthiswillrequiresomereconfigurationandpossibleaugmentationofthe11kVfeedercablesintotheplant,alongwithchangestothenetworkwithintheplantitself.
AspartoftheWCGRProject,Westpowerhassuppliedandinstalleda14MVarswitchedcapacitorbankconnectedtoan11kVcircuitattheHokitikasubstation.ThiswillprovidereactivesupportinordertomaintainandstabilisethevoltageofTranspower’s66kV transmission systemon theWestCoast. Theprojectwas fully fundedbyTranspower,whichtookovertheownershipofthesecapacitorsinJune2010.
Noothermajornetworkdevelopmentisplannedinthisareafortheremainderoftheplanningperiod.
5.7.4 SouthWestlandNetwork
AftertheamalgamationoftheGrey,WestlandandAmethystBoardsin1972,itwasfoundthattheinfrastructureassetsinSouthWestlandwereinaverypoorcondition.Considerableexpenditurehasoccurredoverthelast30yearstobringthereticulationsystemuptoanacceptablestandard.
Inaddition,anew33kVregulatorhasbeencommissionedatHarihari,andthishasprovidedsignificantadditionalcapacityintoareassouthofthatpoint,includingtheglacierregion.Also,threenewsingle-phaseregulatorshavereplacedtheexistingunitsatFoxtoincreasesecurityofsupplyforthatarea,alongwithprovidingadditionalcapacity.
MajorsteploadincreasesareconceivableintheFranzJosefareaifaresurgenttourismindustryshoulddecidetoinvestheavilyinnewaccommodationunits.Thishasbeenmadepossiblebytherecentdevelopmentofseverallarge,newsubdivisionsinthearea.
ItispossiblethattheSWGRmaybeimplementedin2018andthiswillinvolveupgradingasectionoftheHokitika-Harihari33kVlineto66kV,alongwithconversionoftheRoss,WaitahaandpossiblyHariharisubstationsto66kVoperations.ApossiblevariationtothisplaninvolvestheoptionofsupplyingtherelativelysmallWaitahaloadatalowervoltagefromnearbyRoss.Drivenbythepoorconditionoftheexistingasset,WestpowerhasalreadystartedtoupgradethepolestructuresbetweenRossandWaitahaandisplanningtoupgradetheHokitika-Rosssectioncircuitby2012andtheWaitaha-Hariharicircuitby2013.Thiswillbedoneinsuchawayastofacilitatefutureconversiontothehighervoltageifandwhenthisisrequired.
Securityofsupply isalwaysgoingtobeamajorconcerninthisarea,as it isfedbyavery longsingle-circuitlineandthebenefitofalternativesupplyfromlocalgeneration,particularlyfromTrustpower’sWahapopowerstation,isfastbecomingeclipsedbyloadgrowth.Theproposed6MWAmethystpowerschemebeingdevelopedbyWestpowerasajointventurewithourpartnerswillplayasignificantroleinimprovingsecurityofsupplytoSouthWestlandwhenitiscommissionedin2013.
5.7.5 WestpowerSubstations
WestpowercommissioneditsfirstgroundfaultneutraliserinGreymouthsubstationasatriallatein2010;thecommissioningdatehasbeenrescheduledforearly2012.
Duetonetworkinsulationcoordinationissues,thisislimitedtoamaximumconnectionperiodofoneminute,afterwhichthefaultedfeederistripped.
144 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Calledagroundfaultneutraliser,thetechnologygreatlyreducesearthfaultcurrentsatthepointafaultoccursonthenetwork,whichamelioratesthelevelofthreattohumanlifeandriskoffire.ItalsoallowstheWestpowercontrolcentretomaintainpowersupplytohomesandbusinesseswhilefieldstaffaredispatchedtofixthefault.
Transientormomentaryfaultscanbeneutralisedaswell,eliminatingmanycasesofflickeringlightsandshort-terminterruptionstopowersupply.
Inthenextfouryears,WestpowerhasdecidedtoreplaceallKFEcircuitbreakerswithnewvacuuminterruptercircuitbreakerstoimproveitsnetworkreliability.Thishasbeendrivenbyanumberofrecentfailuresofthisequipment,whichcannotbepredictedoradequatelycoveredbyanenhancedmaintenanceprogramme.Atthesametime,theoldprotectionsystemswillbeupgradedwithnewdigitalrelaystoimprovesensitivityandselectivity.
5.8 Network Development Programmes
Capital Projects
5.8.1 ZoneSubstations
5.8.1.1 Twelvemonthperiod(over$30,000)
Adetaileddescriptionofallcapitalprojectsover$30,000scheduledforthenext12monthsisgivenbelow:
Enhancement
54012: Waitaha Zone Substation – Prepare site for Westpower Mobile Substation (WMS) access
Costs: $36,000
Project Justification Score: 45
Supplyingprimarilyafarmingarea,theWaitahazonesubstationsuppliesanareacoveringFergusonsBushinthenorth,WaitahaValleytotheeastandPukekuratothesouth.ItisproposedtopreparetheWaitahazonesubstationforWMSaccessthisyear.Thiswillinvolveallowingfora33kVand11kVconnectionpointtothezonesubstation,sitepreparation(earthmat,etc.)andas-builtdrawings.
Justification
AllowingtheWMStoconnecttotheWaitahazonesubstationwillensurecriticalmaintenancecanbeconductedinasafeandefficientmannerwhilemaintainingsupplytotheWaitahaarea.
ThishasprovedgreatlybeneficialatotherzonesubstationswhereaconnectiontotheWMShasbeeninstalled.Powercanbe retained to thearea thezonesubstationsupplies, reducingoutages.This isvital,asnootheralternativesupplyisavailablefromtheWestpowerNetworkifthereisanoutageorfaultattheWaitahazonesubstation.
Recently,whileurgentmaintenancewasneededtobecarriedoutontheregulatoratWaitaha,anoutagewasneededtotaketheunitoutofserviceandanotherwhentheunitwasreturnedtoservice.WiththeWMS,nooutagewouldberequired.
WiththeWMSabletobeconnectedtothezonesubstation,thiswouldallowabetterutilisationofaWestpowerresourceasopposedtoextracostsincurredwithfindinganalternativesupplyfortheWaitahaareasuchasagenerator.
TheWMSwouldbeabletobeusedforproposedfutureprojectsattheWaitahazonesubstationsuchastheCB1replacement/protectionupgradeandthereplacementofthethree-phaseRegulatorwithsingle-phaseunits.
ThisisalsothelastzonesubstationtohaveaconnectiontotheWMSinstalled.
NETWORKDEVELOPMENT 145
Alternative Options Considered
Alternativeoptionswereconsideredincludingfeedingtheareaby11kVlinefromRossorHarihari,orusingageneratortosupplytheareaduringashutdownoroutage.Upgradingtheexisting11kVlinetomakeitcapableoffeedingtheWaitahaareawouldbeprohibitivelyexpensiveandusingtheWMSwouldbemorecost-efficientthanhiringagenerator,especiallyiftheWMSwasneededtobeconnectedforaprolongedperiod.TherearenohirecostsforusingtheWMSasopposedtohiringagenerator.
InstallingaconnectionpointfortheWMSwasconsideredtobethebestoption.
Replacement
44015: Wahapo Zone Substation – Replace Combiflex relay and protection settings upgrade
Costs: $108,000
Project Justification Score: 79
Wahapo’sCB1andprotectionisbeingreplacedthisyear.ThisprovidesanidealopportunitytoreplaceT1olderCombiflexprotectionwithmodernSEL751Arelays.AlloftherelayswillcommunicatetoSCADAviaaSEL3530communicationprocessor.
Justification
ReplacementofT1olderCombiflexrelayswillbringtheWahapo zone substation up toWestpower’s currentstandardforzonesubstationtransformerprotection.
Aspartofthisproject,thecommunicationsequipmentis to be upgraded. Better fault analysis, protectionsettings,loadtrendingandSCADAcommunicationsaretobeachievedwiththeupgradingofprotectionwithmodernSELprotectionrelays.
TheSELrelayscanbeinterrogatedforfaultanalysisandquality of supply, providing improved operating datatothecontrolroomviaSCADA.ThesedataalongwithhistoricaldatafromSCADA,arealsoinvaluabletotheEngineers.
Alternative Options Considered
ReplacementoftheolderCombiflexrelayswiththemodernSELrelayswasconsideredtobethebestoption.TheWahapozonesubstationisoneofthefewremainingzonesubstationsleftwiththeolderCombiflexRelays.TheserelaysarenowageingandcomparedwithnewmodernSELRelays,theyhavelimitedprotectiongradingandnoremoteinterrogation.Withtheupgrade,thiswillbringtheprotectionatWahapoinlinewithothernewandupgradedWestpowerzonesubstations.
44016: Wahapo Zone Substation – Replace CB1 and Protection upgrade
Costs: $71,000
Project Justification Score: 75
Mostofthezonesubstation11kVoutdoorcircuitbreakersareCooperOil-filledKFEtypereclosers.Overthelasttwoyears,areplacementprogrammehasbeeninplace,astheirsettinglimitationsareidentifiedasbeinglikelytocausenuisancetrippings.
Figure5.11-WahapoCombiflexRelayPanel
146 WESTPOWERASSETMANAGEMENTPLAN2012-2022
AnumberofzonesubstationsolderCombiflexprotectionrelayshavealsobeenidentifiedasneedingupgrading.Thesehavebeencompletedsimultaneouslyateachzonesubstations.
ItisplannedtoreplaceCB1withthenewVipervacuumreclosersandupgradetheprotectionwithamodernSEL351Arelay.Someequipmentforthisproject,liketheVipervacuumrecloser,hasbeenpurchased.
Justification
CooperKFEtypereclosersgivevariableandunreliableperformances.Theirsettingsselectionislimitedandtherehavebeenseveralauxiliaryswitchfailures.Theyhavehighmaintenancecosts,areunreliableduetohighdefectratesandarethecauseofunnecessaryoutagestocustomers.
Consequently,Westpower engineers have decided to replace all KFE type reclosers with themodern Vipervacuum Reclosers. These reclosers are practicallymaintenance free, except for periodic inspections. At thefeederlevel,reliablecircuitbreakeroperationiscriticaltomaintainingsupplytocustomersintheseareas.LatelytheCooperKFEReclosershavenotbeenprovidingthereliabilityexpected.
RemovaloftheCooperoil-filledbreakersalsoeliminatesthechanceofoilcontaminationintotheenvironmentasthesereclosersage.
Betterfaultanalysis,protectionsettings,loadtrendingandSCADAcommunicationsaretobeachievedwiththeupgradingofprotectionwithmodernSchweitzerEngineeringLaboratories(SEL)protectionrelays.
Alternative Options Considered
Alternative options were considered including on-going basic maintenance and refurbishment of the unit.Maintenancecostsoftheoil-filledreclosershaveincreasedconsiderablyinrecentyears.Reclosershavebeenrepairedwithnewpartsbutstillprovetobeunreliable,resultinginhighmaintenancecostsandunnecessarypoweroutages.
Modernvacuumreclosersarereliableandhaveminimalornomaintenancecosts.AplannedreplacementoftheCooperoil-filledrecloserswithnewviperrecloserswithSELprotectionrelayswasconsideredthemostcost-efficientoption.
44025: Kumara Zone Substation – Construct a new 11 kV switchroom
Costs: $760,000
Project Justification Score: 84
The Kumara GXP is mainly required to provide a GridInjectionPoint(GIP)toTrustpower’s10MWKumarahydroscheme, but also supplies local load in the area fromGladstoneinthenorthtoJacksonsintheeastandDuffersinthesouth.
TheKumarahydroschemewasconstructedbyWestpowerinthemidtolate1970’s.The11kVswitchgearandassociatedequipmentwereinstalledinsidethepowerhousebuildingatthetimeofconstruction.Duetogovernmentregulatorychanges in the 1990’s Westpower sold their generationassets to Trustpower in 1999. Westpower retainedownershipoftheadjacentswitchyard.
Figure5.12-WahapoCircuitBreaker1
NETWORKDEVELOPMENT 147
TrustpowerhaverequestedWestpowertoremovetheir11kVswitchgearfromthepowerstationbuildingby2013.TrustpowerwillberelocatingthegeneratorCB31tothegeneratorwellandWestpowerwillberelocatingCB’s1,2,3and38toanewcontrolroomintheswitchyard.
Justification
ThemaindrivingfactorforthisprojectisthatTrustpowerhasrequestedtheremovaloftheequipmentduetohealthandsafetyconcerns.Whenthepowerstationwasconstructed,thestaffwhomaintainedandserviceditwerebasedoff-site.NowthepowerstationbuildingisusedasaworkshopandofficeforTrustpowermaintenancestaffontheWestCoast.Theyhaverequestedthatthisbecompletedby2013.
Althoughhealthandsafetyarethemainfactorsforthisproject,constructionofthenewcontrolroomwillalsoensurethattheassociatedequipmentinstalledinthenewcontrolroomwillbethesameasotherneworupgradedSubstationsonWestpower’snetwork.Thishelpswithmaintaining standardisedoperationalproceduresandalsostandardisingthesparepartsrequired.ThisisapplicabletotheReyrolle11kVvacuumindoorMetalcladswitchgeartobeinstalled.Theyalsorequireminimalmaintenance,thusreducingmaintenancecosts.
Betterfaultanalysis,protectionsettings,loadtrendingandSCADAcommunicationsaretobeachievedwiththeupgradingofprotectionwithmodernSchweitzerEngineeringLaboratories(SEL)protectionrelays.
Design/drawings have been completed for this project. Out of the total costs of $760,000 for this project,Trustpoweristopay50%ofthesecosts.
Alternative Options Considered
Retainingthestatusquowasnotanoptionasadeadlineforshiftingoutofthepowerhousebuildingby2013hasbeenset.Westpoweralreadyownstheoutdoorswitchyardadjacenttothepowerstation.
Theonlyoptionavailableistoconstructanewcontrolroominsidetheswitchyard.
44027: Longford Corner – Upgrade regulator site
Costs: $70,000
Project Justification Code: 71
SituatedatLongfordCornernexttotheentrancetotheKokatahisettlement,theBrentford2MVAthree-phasemovingcoilregulatorprovidesvoltagesupporttothepredominantlydairyfarmingareaofKokatahi/Kowhitirangi.Manufacturedin1970,theexistingregulatorhasbeenexperiencingmoreregularfaultoccurrenceoflate,andsourcingsuitablepartsandsolutionstorectifythesefaultshasbeenquiteproblematic.
Itwasproposedtoreplacethecurrentregulatorwithtwo-singlephaseunits,which,combined,wouldincreasethecapacityoftheregulatorsitefrom2MVAto4MVAandprovideamorereliablevoltagesupporttothearea,withroomforfuturegrowth.However,inAugust2011,amajorfaultoccurredwiththeRegulator.Duetotherepaircosts,theageoftheunitandthefactthatitwasearmarkedforreplacementin2012/13,adecisionwasmadetoreplacetheunitwithtwo-singlephaseunits.ThesenewunitswereputinserviceinSeptember2011beforethestartofthe2011/12dairyseason.
Withtheregulatoralreadybeingreplaced,itisproposedtoupgradetheregulatorsiteinthe2012/13financialyear.
148 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Justification
With thenewregulator installed,a redesignof thecurrentsitecannowbeachieved.A redesignof thesitewiththenewunitswouldmakethesitesafer.Thethreeexistingdisconnectorsatthissitearetheoldbrowndisconnectors.Theseolderdisconnectorshavecausedissueswhenoperatingandhaveincreasedmaintenancecosts.Theyhavebeenprogressively replaced in theWestpowernetworkwithnewor refurbishedSchneiderdisconnectors,andveryfewremainonthenetwork.
Withthereplacementoftheregulator,itsremoteoperationcanbeachievedthroughSCADAcommunications,whichwasunabletobeaccomplishedwiththeoldone.AlsodatasuchaspowerqualityandhistoryofoperationwillbeavailabletothecontrolroomviaSCADA.
Alternative Options Considered
Alternativeoptionswere considered, includingupgrading theexisting11 kV line to22 kVor33 kV, andon-goingregulatormaintenance.Upgradingtheexisting11kVlinetoahighervoltageprovedtobeprohibitivelyexpensiveand,duetotheageoftheunit,partswerehardtosource.TheoldregulatorhadreachedtheendofitsserviceablelifeandinstallationoftheCoopertypeunitskeepstheregulatorsinlinewithotherregulatorsitesinstalledonthenetwork.
With thenewregulatorsalready installed,anupgradeof thecurrent regulator sitewasconsidered thebestoption.
Development
Therearenodevelopmentcapitalprojectsplannedforthenext12-monthperiod.
5.8.1.2 TwotoFive-YearperiodProjects
Thissectioncontainsasummaryofallcapitalprojectstooccurinthenext2-5years:
Enhancement
Thereisnoenhancementcapitalprojectsplannedinthe2-5yearperiod.
Replacement
44020: Rapahoe Zone Substation – 33 kV disconnector upgrade (2014/15) - $26,000
The disconnectors on the CB2302 structure are to allow bypassing and isolation of the circuit breaker formaintenance.TheclearancebetweenthedisconnectorsandtheCircuitBreaker(CB) isnotsufficientforsafeaccessformaintenance.Thestructureistoberedesignedandupgradedtorectifythisproblem.Thisprojectisplannedtocoincidewiththe11kVmetalcladswitchgearreplacementinthe2014/15financialyear.
44022: Whataroa Zone Substation – Replace CB1 and protection relay (2013/14) - $90,000
KFEtypereclosershaveprovedtobeunreliableoflate.Theirsettingselectionislimitedandtherehavebeenseveralauxiliaryswitchfailures.CB1Cooperoil-filledreclosersaretobereplacedwithviperreclosers.ProtectionwillbeupgradedwithaSEL351Styperelay,enablingbetterfaultanalysis,protectionsettings,loadtrendingandSCADAcommunications.
NETWORKDEVELOPMENT 149
44023: Rapahoe Zone Substation – Replace 11 kV Metalclad switchgear (2014/15) - $126,000
It is proposed to replace the last bulk oil 11 kV circuitbreakers on the Westpower network with new 11 kVReyrollevacuumreclosers.TheReyrollevacuumreclosersare installed throughout the Westpower network,maintainingastandardisedoperationalprocedurefor11kV indoor switchgear and also standardising the spareparts required. The Reyrolle vacuum reclosers requireminimalmaintenancethusreducingmaintenancecosts.
This project is planned to coincide with the 33 kVdisconnectorupgrade.CompletingbothprojectstogetherwhileusingtheWMStomaintainsupplyensuresreducedcosts associated with the WMS connection and betterutilisationofresources.
44024: Arnold Zone Substation – Replace CB3 and 4 with Vipers and upgrade protection (2015/16) - $300,000
KFE type reclosershaveproven tobeunreliableof late.Their setting selection is limited and there have beenseveral auxiliary switch failures. CB3 and 4 Cooper oil-filled reclosers are to be replaced with Viper reclosers.Protection will be upgraded with SEL351S type relays,enabling better fault analysis, protection settings, loadtrendingandSCADAcommunications.
44028: Whataroa Zone Substation – Replace CB1412 with WVE38X type recloser and T1 protection upgrade (2013/14) - $150,000
TheCooperRVEtype33kVoilrecloseristhelastofthistypeinstalledonthenetwork.ItisplannedtoreplacethisassetwithaWVE38xtypeVacuumrecloser.CB1412willthenbeinlinewithallofWestpower’sother33kVzonesubstationswhich,willensureastandardisedoperatingprocedureandonlyonesetofsparepartsrequiredtobemaintained.WiththereplacementofCB1andprotectionrelaysplannedforthesamefinancialyear,thisprovidesanidealtimetoupgradeT1protectionwithmodernSELrelaysinlinewithotherupgradedzonesubstations.
Waitaha Zone Substation – Replace regulator with single-phase units (2015/16 – 2016/17) - $194,000
Theexisting1MVAinductionregulatorwaspurchasedsecond-handfromTranspowerintheearly1990s.Themanufacturedateisunknownbutisthoughttobeinexcessof60years.Itisproposedtoreplacetheexistingthree-phaseunitwiththreesingle-phaseunits.
Duetoitscloseproximitytotheseaandthehighrainfallinthearea,theregulatorhasstartedrustingaroundthebottomandneedsattention.DissolvedGasAnalysis(DGA)testsalsoindicatethattheunitrequiresreplacing.Ithasbeendecidednottocarryoutanyexpensiverepairsonthisregulator.
Withthethreesingle-phaseunitsinstalled,theRegulatorwouldbeasperWestpower’sstandarddesign,(andthus spares are already in stock) andwould provide amore reliable voltage support, with room for futuregrowthinthearea.RemoteoperationcanbeachievedthroughSCADAcommunications,whichisunabletobeaccomplishedwiththecurrentregulator.SCADAcommunicationsarealreadyestablishedatthezonesubstation.$26,000hasbeenallowedfordesign/drawingsfor2015/16withtheremaining$168,000tocompletetheprojectin2016/17.
Figure5.13-Rapahoe11kVCircuitBreaker
150 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Waitaha Zone Substation – Replace CB1 with viper and protection relay (2016/17) - $95,000
KFEtypereclosershaveprovedtobeunreliableoflate.Theirsettingselectionislimitedandtherehavebeenseveralauxiliaryswitchfailures.CB1Cooperoil-filledrecloseristobereplacedwithViperrecloser.ProtectionwillbeupgradedwithaSEL351Styperelayenablingbetterfaultanalysis,protectionsettings,loadtrendingandSCADAcommunications.
Development
Therearenodevelopmentcapitalprojectsplannedinthe2-5yearperiod.
5.8.1.3 Excess5yearsProjects
Enhancement
Hokitika Protection Upgrade - Design and installation and as built drawings (2018/19) - $315,000
TheHokitikazonesubstationwascommissionedin2002.Duetoprogressincommunicationsandtechnology,theexpectedlifeofdigitalprotectionrelaysis15years.Thesumof$315,000hasbeenallowedtocompletethisupgrade.
Replacement
Ross Zone Substation - Replace CB1 and 3 with vipers and upgrade protection (2017/18) - $126,000
ReplaceCoopertypeKFErecloserswithVipervacuumreclosersandreplaceprotectionwithSELrelays.
Ross Zone Substation – T1 protection upgrade (2017/18) - $95,000
ReplaceT1olderCombiflexprotectionwithamodernSELrelay.TocoincidewithCB1and3replacementandprotectionupgrade.
Dobson Zone Substation – Replace T6 (2019/20) - $735,000
ReplaceexistingDOBT6transformer.
Fox Zone Substation – Replace T1 (2020/21) - $735,000
ReplaceexistingFOXT1transformer.
Whataroa Zone Substation – Replace regulator with single phase units (2021/22) - $147,000
Replaceexistingthreephaseregulatorwiththreesingle-phaseregulators.
Ross Zone Substation - Replace regulator with single phase units (2021/22) - $147,000
Replaceexistingthree-phaseregulatorwiththreesingle-phaseregulators
Development
Therearenodevelopmentcapitalprojectsplannedinexcessoffiveyears.
5.8.2 MVSwitchgear
5.8.2.1 Twelve-monthperiod(over$30,000)
Detaileddescriptionofcapitalworksover$30,000inthenext12months.Someoftheseprojectsareon-goingthroughouttheentireAMPtimeframe:
NETWORKDEVELOPMENT 151
Enhancement
56005: Install Automation to Various Disconnectors
Costs: $71,000
Project Justification Score: 64
Remoteautomateddisconnectorshaveprovidedsignificantbenefitsto the network, and allow controllers to open and close switcheswithout having to call on standby staff. Each year, Westpower isupgradingitsstrategicswitcheswithautomatedunits.Twolocationshavebeenidentifiedthisyear.AllnewautomationistobeachievedwiththeuseofNTECloadbreakswitches.
Justification
NetworkfaultanalysishasidentifiedkeyareasontheWestpower11kVnetworkwhichrequireautomaticisolationoffaultsandremoteoperationoftieswitchestoretainsupplytobuilt-upareasandlargecustomers.
Theadditionofextraautomation to thenetwork improves systemreliabilityandfaultselectivity.TheNTECloadbreakswitchesarealsocapableofautomaticfaultisolationonsmallerspurlines.
TheNTEC loadbreakswitcheshavenoexternalmovingpartsandarethereforemorereliable.Theyarealsovirtuallymaintenancefree.
TheEntecloadbreakswitchescanbeinterrogatedforfaultanalysisandqualityofsupply,providingimprovedoperatingdatatothecontrolroomSCADAandtheengineersviaremoteaccess.
Alternative Options Considered
ThenextbestoptiontousingtheNTECwastofitmotordriveunitstodisconnectors.Thiswasrejectedasmotordriveunitshaveproventobeunreliablewhenrequiredforoperation.Theycansitforlongperiodsoftimeandexternal parts seize up.NTEChaveno externalmovingparts, have internal CT’s andVT’s, are competitivelypriced,andprovidefaultselectivityandfaultinterrogation.
InstallingNTECloadbreakswitchesatidentifiedlocationswasconsideredthebestoption.
56008: Fusing of Spur Lines by Feeder Classification
Costs: $40,000
Project Justification Score: 66
AdetailedstudyhasbeenconductedtoclassifyallfeedersandlinesontheWestpowernetwork.Thereasoningtogive these feedersand lines classificationwas tohelp indeterminingwhat levelof securitywas requiredtomaintain supply to these feeders/lines. Factors taken into accountwith this study included feederswithhospitals,CBDs,commercialandlargeindustrialcustomers;feedersectionswithhighSAIDIhistories,criticalsubtransmissionlineswithnoalternativemeansofsupply;sectionsalreadyprotectedbyreclosers/sectionalisersorfused;andvegetation.Thesefeeders/lineswereclassifiedrangingfromF1(Critical),F2(VeryHigh)throughtoF5(Low).
Overthenextfewyears,itisplannedtofuseallpossiblespurlinesofffeeders/linesclassifiedasF1andF2.
Figure5.14-ENTECLoadBreakSwitch
152 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Justification
Further investigationwillbedone todeterminewhichspur linescanbe fusedbyDDOFuses.This is tohelpmaintainsecurityonmainfeederLines,reduceSAIDI,andtohelpreducetheoutageareaaffectedandtobepatrolledwhenafaultoccursonthesespurlines.
Alternatives Options Considered
WhereitispossibletoinstallDDOfuses,previousexperiencehasshownthatDDOfusesareagoodoptionbothinperformanceonspurlinesandinprice.Quiteoften,itmakessensetofuseaspurline,ratherthanincurringthecostsofclearingtreesorlineupgrade.Largerspurlineswithgreaterloadwillbeidentifiedandconsideredforinstallationofarecloser(newspurlinereclosersbudget).
Replacement
46002: Replace Faulty Actuators - ENTEC load break switch or hydraulic actuator
Costs: $45,000
Project Justification Score: 77
ExistingremoteautomateddisconnectorsfittedwithDulmisonmotordriveunitshaveproventobeunreliableandhavehighmaintenance/repaircosts.
Overthelastthreeyears,theseunitshavebeenreplacedwiththeENTECloadbreakswitches.TheENTECloadbreakswitcheshaveproventobemorereliable,andhavenoexternalmovingpartsandconsequentlyrequireminimalmaintenance.
Onlyoneunitremainsonthenetwork,whichisplannedforreplacementitthisyear.Thisunitisusedasatieswitchandhasbeencausingproblemsoverthelast12months.Currently,remoteoperationoftheswitchisnotpossible.Operationismanualonlyatpresent.
Thisisthelastyearforthisproject.
Justification
This location has previously been assessed as necessary. The replacementwith an Entec load break switchimprovesthenetwork’ssystemreliability,faultselectivity,qualityofsupplyanalysis,unplannedoutages,SAIDIandcustomersatisfaction.
AlloftheotherDulmisonautomateddisconnectorshavebeenremovedfromthenetworkandreplacedwithEntecloadbreakswitches,becausetheDulmisonunitsnolongerworkingorbeingunreliable.Thislastremainingunitisusedasatieswitchtoretainsupplytobuilt-upareasandlargercustomers.
TheEntecloadbreakswitchesarevirtuallymaintenance-free.Theycanbeinterrogatedforfaultanalysisandqualityofsupply,providingimprovedoperatingdatatothecontrolroomandtheengineersviaSCADA.
Removal of the last Dulmison unit with an NTEC ensures that all automated switches and tie switches arestandardised,thereforeonlyonestandardoperatingprocedureisrequiredandonlyonespareunitisrequiredaswell.
Alternative Options Considered
ThenextbestoptioninsteadofusingtheNTECwastofitmotordriveUnitstodisconnectors.ThiswasrejectedasMotorDriveunitshaveprovedtobeunreliablewhenrequiredforoperation.Theycansitforlongperiodsoftimeandexternalpartsseizeup.Entecshavenoexternalmovingparts,haveinternalCT’sandVT’s,arecompetitivelypriced,andprovidefaultselectivityandfaultinterrogation.
NETWORKDEVELOPMENT 153
InstallingNTECloadbreakswitchesatidentifiedlocationswasconsideredthebestoption.
46003: Disconnector Replacements
Costs: $32,000
Project Justification Score: 78
Disconnectorsnormallyfailduetodeteriorationoftheoperatingarmswithcorrosion,orfromanarcdevelopingacross two ormore phases. By identifying under-rated or defective disconnectors and replacing these, theincidenceofarcingfaultsshouldbereduced.
This isanongoingproject; fundsareallocatedeachyear.With thedisconnectormaintenanceprogramme inplacedisconnectorsare identified that aremore costefficientand safer to replace thanmaintain, thereforethenumberofdisconnectorstobereplacedvariesfromyeartoyear.Thisbudgetallowsfordisconnectortobereplacedwhentheyhavebeenidentifiedasreachingtheendoftheireconomicandserviceablelife.
46006: Ring Main Unit Replacement
Costs: $40,000
Project Justification Score: 75
Anumberofoil-filled ringmainunitshavebeen identifiedas reaching replacementage.Abudgethasbeenallowedforaprogressivereplacementprogrammewhichwillseeoneunitperyearreplacedeveryfouryears.Furtherinvestigationisneededtodeterminethelocationtobereplacedinthisfinancialperiod.
Justification
Theolderoil-filledringmainunitshavebeenprogressivelyreplacedovertheyearswiththemodernABBSafelinkSF6Gasfilledringmainunits.Replacingtheoilfilledunitsreducestheriskofoilcontaminationtotheenvironment.ThenewerSafelinkunitscanberemotelycontrollediffittedwithamotordriveunitviaSCADA,givingthecontrolroommoreflexibilityinafaultsituationandreducingtheneedtocalloutaFaultmen.Replacingtheoil-filledunitwithanABBSafelinkringmainunitensuresthatthereplacementisthesameasothersreplacedorinstalledonthenetwork.Thishelpswithmaintainingstandardisedoperationalproceduresandalsostandardisingthesparepartsrequired.
Alternative Options Considered
Theoptionofrefurbishingandmaintainingtheexistingunitswasrejectedbecauseastheoil-filledringmainunitsage,theirmaintenancecostsincreasedandsparepartsfortheseunitsbecomehardertosource,andsomeoftheseunits,dependingontheirlocation,havehadtohavesectionsoftheoutsidebodyreplacedorrepairedduetoRust.
The ABB Safelink units are virtuallymaintenance-free and therefore, apart from periodic checks, they havereducedmaintenancecosts. InstallingaSafelinkunithelpstomaintainastandardisedoperationalprocedureacrossthenetworkandalsostandardisesthesparepartsrequired.Gradualreplacementoftheoil-filledRingMainunitswithABBSafelinkunitswasdeterminedtobethebestoption.
154 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Development
66002: New Spur Line Reclosers on various Spur Lines
Costs: $40,000
Project Justification Score: 63
ReclosersarebeingstrategicallypositionedthroughouttheWestpowernetworktoisolateproblematicspurlines,reducemainlinetrippingsandreduceinconveniencetoconsumersandSAIDI.
Reclosersarebeingfittedtospur lines,wherethenumberandsizeofconsumers are too great to fitDDOs. Three new locations have beenidentifiedthisyear.ItisproposedtoinstallKFMEtyperecloserstotheselocations.
Justification
NetworkfaultanalysishasidentifiedkeyareasontheWestpower11kVnetworkwhichrequiresautomaticisolationoffaultstoretainsupplytobuilt-upareasandlargercustomers.
Theadditionofextrarecloserstothenetworkimprovessystemreliability,faultselectivity,unplannedoutages,SAIDIandcustomersatisfaction.
Due to several recloser locationsonmain linesbeingupgraded toViper reclosers,Westpower currentlyhasenoughKFME reclosers in good condition in stock to re-useon thenetwork. TheKFME type reclosershaveprovidedgoodserviceonthenetwork.
InstallingKFMEtypereclosersonspurlinesdownstreamofViperreclosershashelpedinreducingtheoutageareaaffected ina fault, reducingmain lineoutagesand reducing thearea required tobepatrolled for faultfinding.
Alternative Options Considered
Forreliabilityandfault isolation,reclosersarethebestoption.Thenextbestsolutionof installingNTECloadbreak switcheswas rejected. The load break switches are not ideal formain line fault isolation, protectiongradingisrestrictedandtheoperationofthemainfeederrecloseratthezonesubstationisrequiredtotriggertheloadbreakswitchtoopen.Thismeansallcustomersonthatfeedersupplyisbeinginterruptedunnecessarilytoisolatethefaultedsection.
66005: Automate Capacitors at various Locations
Costs: $42,000
Project Justification Score: 59
SupplytotheWestCoastingeneralisvoltage-constrainedandthisispartlyduetothelonginductivetransmissionlines.Whenalineoutageoccursduetofaultsorplannedmaintenanceevents,voltagecollapsecanoccurunlesssignificantsupportisavailablefromlocalgeneration;this,inturn,maydependonwateravailability.
Westpowerhave installed capacitors throughout the11kVnetwork tohelpmaintain voltage levels in areaswherethereisalargeindustrialloadorwherethereisloadonalongfeeder.Itisproposedtocarryoutadetailedinvestigationtodetermineasolutiontoautomateexistingcapacitorlocationsonthenetwork.
Figure5.15-ViperRecloser
NETWORKDEVELOPMENT 155
Justification
Currently in areaswhere capacitors are installedwithlargeindustrialloads,voltagescanrisewhenthissignificantloadisreducede.g.atnightwhenproductionceases,orwhenplannedmaintenanceiscarriedoutandtheloadisturnoff.Atpresent,the capacitors are in service at all times. Withautomationof thesites, thecapacitorswouldbetakenoutofserviceswhenthevoltagesincreases,or by remote control from the control room viaSCADA. This will help Westpower maintain thevoltagewithinregulatedlimits.
Alternative Options Considered
As part of the investigation, all options will beconsidered.
66010: Amethyst Hydro – 33 kV connection
Costs: $200,000
Project Justification Score: Customer Driven
AspartoftheconstructionoftheAmethystHydroschemeaconnectiontotheSouthWestland33kVnetworkisrequired.Thiswillinvolvetheinstallationoftwonew33kVdisconnectorsandreclosers,andvoltagetransformerwillberequired.
Justification
ThisprojectiscustomerdrivenbyAmethystHydroLimited.Asstatedpreviously,aconnectionisrequiredfromthepowerstationtothe33kVWestpowernetwork.All(100%)ofthecostsfromthisprojectaretobepaidbyAmethystHydroLimited.
5.8.2.2 Twelve-monthperiod(under$30,000)
A summary of capital projects under $30,000 in the next 12months,someoftheseprojectswillbeon-goingthroughouttheentireAMPtimeframe.
Enhancement
56004: Distribution Intelligent Fault Isolation System – Study/design - $2000
AdetailedstudyofWestpower’snetworkistobecarriedouttodeterminethebestlocationforreclosers,GEDO’s,sectionalisingdisconnectors, automated disconnectors, etc. for isolation offaults and automatic restoration of supply to customers. Thenumber of customers affected, length of line and possiblealternative points of supply are some of the items to beconsideredinthestudy.
Figure5.16-CapacitormountedinsidePad-mountedcabinet
Figure5.17-EarthFaultIndicator
156 WESTPOWERASSETMANAGEMENTPLAN2012-2022
56006: Fit Earth Fault Indicators - $6000
Earth fault indicatorsare tobefitted tochosenunprotectedcables todetectcurrentpassagedue toa faultdownstream.Thesewillallowfaultcrewtoquicklyidentifyafaultycabletospeeditsisolationandrestorethefeederpromptly.
Replacement
46004: Remote Locations Battery Replacement - $6000
Afive-yearreplacementprogrammeisinplaceforbatteriesatremotelocationsinthenetwork.Thisisanon-goingprojectandfundshavebeenallocatedtoachievethis.
Development
66001: New Main Line Recloser Sites (Dilmans) - $25,000
MainlinereclosersarebeingstrategicallypositionedthroughouttheWestpower network to reduce the number of consumeroutagesincurredduringfaults,thusreducingSAIDI.
AViperistobeinstalledintheDilmansareathisyear.Thiswillallow for the DIL4 recloser and associated equipment to beremovedfromTrustpower’sDilmanspowerstation.
66007: New Disconnectors - $27,000
Several new disconnectors are to be installed to furthersectionalisethenetworkandtoreducethenumberofcustomersaffected by 11 kV switching operations. These disconnectorinstallationswillalsoassistinthelocationoffaults.
66008: New Ganged DDO Fuse Unit Locations - $10,000
Ganged DDO fuse units (Figure 5.19) are being strategicallypositioned throughout the Westpower Network to isolateproblematic spur lines, and to reduce inconvenience toconsumersandSAIDIoutageminutes.
5.8.3 SCADA,CommunicationsandProtection
5.8.3.1 Twelve-monthperiod(over$30,000)
Detaileddescriptionofallcapitalprojectsover$30,000inthenext12months:
Enhancement
Noplannedenhancementprojectexceeds$30,000.
Replacement
Noreplacementprojectexceeds$30,000.
Figure5.18-PolemountedRecloser
Figure5.19-GangedDDOfuse
NETWORKDEVELOPMENT 157
Development
67011: South Westland, IP Expansion VHF Digital Radio Costs: $70,000
This isaprojectwillbebrokenup intoseveral smaller jobs, includingextending the footprintofWestpowerdigitalIPnetworksouthofGreymouth.WiththisexpansionofthedigitalIPfootprint,anumberofcurrentzonesubstationsandpoletopdeviceswillnowbeabletobeconvertedtoIP.
Justification
Convertingthesesitesallowsremoteengineeringaccess,real-timeSCADAmonitoringandprotectionsignallingifrequired.
67036: Comms to New 11 kV Switch Room Kumara: $40,000
Justification
TrustpowerhaverequestedWestpowertoremovetheir11kVswitchgearfromthepowerstationbuildingby2013.TrustpowerwillberelocatingthegeneratorCB31tothegeneratorwellandWestpowerwillberelocatingCB’s1,2,3and38toanewcontrolroomintheswitchyard.
WiththeconstructionofthenewswitchroomatKumara(seeStationsproject44025)communicationswillhavetobeinstalledtoallowremoteengineeringaccess,real-timeSCADAmonitoringandprotectionsignalling.
Alternative Options Considered
Retainingthestatusquowasnotanoptionasadeadlineofshiftingoutofthepowerhousebuildingby2013hasbeenset.Westpoweralreadyownstheoutdoorswitchyardadjacenttothepowerstation.
Theonlyoptionavailableistoconstructanewcontrolroominsidetheswitchyard.
67037: Amethyst 33 kV Connection: $100,000
Justification
With the construction of the new power station at Amethyst, communicationswill have to bemodified toallowremoteengineeringaccess,real-timeSCADAmonitoringandprotectionsignalling. Thismodificationtocommunications systemwill require constructionof anew radiopath toMtHercules that is capableof therequirementsforprotectionsignalling.
5.8.3.2 ProjectsoverFive-Years
57001: Modification of the Load Control System - $10,000
TheWestpower loadcontrol system isacritical componentof theSCADAsystem. Withchanges in thewayTranspowerchargeWestpower,loadcontrolsneedtobemodifiedtosuittheirrequirements.
57003: Mt Bonar Repeater - $4000
Generalhardware/sitedevelopmentforthisradiorepeater.
57011: SCADA Critical Spares - $15,000
Asnewtechnologiesarepurchased,spareunitsarerequired.
57012: IP Firewall/Security/Remote Secure Access - $6000
Withtheincreasednumberofradiolinksusingpublicbandfrequencies,securingofthecommunicationsnetwork,dataandequipmentfromhackersandvirusesneedstobeaddressedandkeptcurrent.
158 WESTPOWERASSETMANAGEMENTPLAN2012-2022
57022: SCADA Master Station - $10,000
TheSCADAmastersystemneedstobekeptuptodatewithsoftwarechangestoenablethesystemtohavemaximumfunctionalityandtoextendthelifeofthecurrentsystem.
57025: Inter-Control Centre Communication Protocol Feed from Transpower - $10,000
TranspowerhaveidentifiedthatanInter-ControlCentreCommunicationProtocol(ICCP)linktogenerators/ELBs/directlyconnectedcustomersisastrategicpriority.
Development
67009: Whataroa Communications - $30,000
With theplanned zone substationprotection relay upgrade (seeproject 44022), significant communicationsmodificationstothesubstationwillberequiredforremoteengineeringaccess,real-timeSCADAmonitoringandprotectionsignalling.
67011: SCADA Off-Site Backup - $5000
ForextrasecurityoftheSCADAsystem,off-sitebackupofdataneedstobeaddressed.
67013: Paparoa move all Antennae to Triangle Tower - $15,000
WiththechangeinratingofthePaparoasitebyKordiatoaG2site,Westpowerstaffcannownolongerclimbthelargetowertomaintaincriticalaerialequipment.Itisproposedthatallaerialsbemovedtoastrengthenedtriangletower,asourstaffhaveaconcessiontoclimbthistower.
67014: Fast IP Comms to Recloser Sites for DIFIS Project - $20,000
Investigateandimplementthebestcommsoptionsforallnewpoletopcommssites.Thisisrequiredfortheimplantation ofDistribution Intelligent Fault Isolation System (DIFIS). The new circuit breakers and switchesbeinginstalledintoWestpower’slinesnetworkrequireanewhigh-speedcommunicationslinktoeachsite.Thislinkwillgivethecontrolsystemtheabilitytoautomatically,reconfigurethepowerflowthroughthenetworkwithintheallowedtimestoisolatethefault,thussavingvaluableSAIDIs.
67017: International Standard 61850 Rollout - $10,000
WiththeplannedchangetotheInternationalStandard61860communicationsprotocol,newequipmentwillberequiredfortestingandimplementation.
67018: Meter Reading - $10,000
Thenewmeteringequipmentmodificationtothenetworkandreadingsoftwareneedstobeinstalled.
67019: VMWare Server Configuration/Equipment - $10,000
AsthecreationofnewvirtualserversisrequiredonVMWarehardware,licencesandextraequipmentmayneedtobepurchased.
67026: Blue Spur Repeater Site - $30,000
MetservicehavebuiltanewrainradaratBlueSpur.Thisnewsiteistobedevelopedasarepeatersite.
67031: Comms to MV Switchgear Disconnector Automation and New Reclosers - $30,000
Anallowance for threenewdisconnectors, threeKFMEand fourViper reclosershasbeenallocated fornewcomms.
NETWORKDEVELOPMENT 159
67033: Comms to Automate Capacitors - $15,000
ThisisanallowancefornewcapacitorsthataretobemonitoredbySCADA.
67034: Comms to Ring Main Unit’s - $20,000
AnallowancefornewRMU’stobemonitoredbySCADA.
Inspection, Service and Testing
BelowisalistofallmaintenanceworkstobecompletedforSCADACommsinthenext12months.Theseareallon-goingbudgetsthatarecarriedoutyearlyforthedurationoftheAMPperiod.
17001: Communications Configuration in Server Room - $6000
AsequipmentinthemainserverroomiscriticaltoSCADAasumhasbeenallowedforISTofthisequipment.
17002: Abbey Support Contract - $4000
ThisisanannualmaintenancefeeforAbbeySystemssupport.
17003: Power System Consultants Support Contract - $20,000
ThisisanannualmaintenancefeeforPowerSystemConsultants(PSC)support.
17004: Realflex Datac Support Contract - $18,000
ThisisanannualmaintenancefeeforRealflexDatacSupportContract.
17005: SCADA General Licences - $19,000
RockwellandTelemecaniquenlicenseagreementsrequiredforSCADAsystemtooperate.Alsoacontingencyhasbeenallowedforothersoftwarelicensesasneeded.
17006: MED Radio Licences - $12,000
AnnuallicencefeestotheMinistryofEconomicDevelopmentfortheradiofrequenciesusedbyWestpower.
17007: Repeater Site Co-locations Fees - $90,000
AnnuallicensefeestothesiteownersforradiorepeatersitesusedbyWestpower.
17008: General Battery Testing and Replacement - $30,000
Most control devices in the network are supplied from batteries. These are regularly discharge tested andwhenfoundtobenearingtheendoftheirlife,arereplaced.Thisbudgetallowsfortestingnewbatteriestobepurchasedwhenrequired.
17009: Continual Document and As-build all Comms - $6000
AnallowanceforcontinuedimprovementofWestpower’scommunicationsrecords.
17010: Abbey Sites SCADA, Comms, I,S&T - $20,000
SumforthemaintenancevisitstoWestpowerpoletopsitesthesesitesareusuallyAbbeysitesbutmoreIPpoletops.
17011: Repeater Sites SCADA, Comms, I,S&T - $30,000
SumforthemaintenancevisitstoWestpowerrepeaterSites.
160 WESTPOWERASSETMANAGEMENTPLAN2012-2022
17012: Zone Subs SCADA,Comms, I,S&T - $40,000
SumforthemaintenancevisitstoWestpowerzonesubstations.
17013: Mt Bonar RSM 25 kHz Frequency Change - $15,000
Configuresitetobecompliantforchancesto25kHzfrequencyChangerrequiredby1November2015.
17014: Mt Kak RSM 25 kHz Frequency Change - $15,000
ConfiguresitetobecompliantforChancesto25kHzfrequencyChangerrequiredby1November2015.
17015: ICCP I,S&T - $35,000
WiththenewproposeddirectICCPlinktoTranspower,anannualconnectionfeeisrequired.Transpowerhasprovidedanestimatedoffuturecosts.
5.8.4 Subtransmission
5.8.4.1 Twelve-monthlyperiod(over$30,000)
Replacement
40005: HKK-WTH 33 kV Pole Replacement
Costs: $780,000 Project Timeline: April 2012 – December 2012
Project Justification Score: 50
ThehardwoodpolelinebuiltoriginallybytheStateHydroCommissionin1965betweentheHokitikasubstation(whichreplacedtheoldArahurasubstation)andtheHariharisubstationhasreachedtheendofitsserviceablelife.Manyofthepolesareinpoorcondition.TwoyearsagoaprojectwasinitiatedtoreplacethepolesbetweenWaitaha andHokitika. A significant section of pole replacement has been completed between theWaitahasubstationandtheRosssubstation;however,thependingconductorupgradebetweenWaitahaandHokitikahashastenedtherestofthepolereplacementprogramme.Originallyplannedtobecarriedoutoverthreeyears,thisprojectisnowtobecompletedbyDecember2012tocoincidewiththecommissioningoftheAmethystHydropowerstation.Thescopeofthisprojectwillincludethedesignandsubsequentreplacementofallhardwoodpoles andwill be reconfigured to complywith the standard66 kV17mStresscretedeltapoledesign. It isestimatedthat$780,000willbespenttocompletetheproject.
It must be noted that a number of poles between the Waitaha Substation and the Amethyst PowerStation that may need replacement while outages are still possible. Several poles (yet to be identified)may not be able to be replaced using live line techniques, and with outages likely to be few and farbetween when Amethyst power station becomes operational, pole replacement would become extremelydifficult.
Justification
TheSouthWestlandareafromRosstoParingaisdependentonsupplyfromthis33kVspurline,withonlylimitedredundancyinareasaroundtheWahapopowerstation.Althoughcapableofwithstandingdesignloads,thepoorconditionofmanyofthepolescouldfailifsubjectedtoextremeweathereventsfrequentlyexperiencedinSouthWestland.Failureofanyofthesepolesinanunplannedeventcouldposeseriousaccessissuesandsignificantlyextendedoutagetimes.TheintroductionoftheAmethysthydroschemewillprovideadditionaldriversfortheproject,particularlytoprovidesuitablesupportforthestringingoftheheavyOxygenconductor.
NETWORKDEVELOPMENT 161
Alternative Options Considered
Noalternateoptionsareavailable,asthissupplytoSouthWestlandisaspurlinewithonlylimitedalternatefeedvialocalgeneration.
40006: Replace Waitangitaroa River Crossing
Costs: $43,000 Project Timeline: May 2012 – June 2012
Thegradualincreaseofriverbedgravelbeneaththe33kVlinecrossingtheWaitangitaroaRiverinSouthWestlandhascompromisedthepreviouslycompliantclearancetotheriver.Areportwascommissionedin2011toobtainthemosteffectivemethodtoregainsufficientclearance,withtherecommendationtoreducethespanlengthsbyinstallingapiledstructureinthemiddleoftheriverbeingadopted.Thisoptionwouldservetoincreasethegroundclearancetoalevelwheretheeffectsofriverbedbuild-upisminimisedandalsoreducetheexcessiveloadsonallexistingequipment.
Theexistingspanis343mlongwhich,byanystandards,isalongspan.Thisismadeworsebythefactisthespanisessentiallyflat,meaningallgroundclearanceisachievedbyusingtallpolesorincreasingtheconductortensiontoreduceconductorsag.
The existing structures at each end of the river crossing span are in relatively good condition. They areapproximately13.7mlongonwoodenpileswhichsupportthepolesoasthefulllengthofthepoleisutilised(thebottomofpoleisatgroundlevel).Cross-armsareSteeltrefoiltypeasusedontheFoxtoParingaLine.Thesepoleswillnotrequireupgradingtoimprovethegroundclearanceissues.
Justification
TheSouthWestlandareafromWhataroatoParingaisdependentonsupplyfromthis33kVspurline,withonlylimitedredundancyinareasaroundtheWahapopowerstation.Withtheeverincreasingriseofriverbedgravel,theclearancefromthewatertothelinewillbecomeless,toapointwheredebrisfloatingdowntherivercouldstrikeanddamagetheconductors,resultinginlengthyoutagesforalargenumberofconsumers.
Alternative Options Considered
Re-tensioningtheconductortoachievetheregulatory6.5mgroundclearancewasconsidered;however,thiswouldincreaseloadingsonequipmenttoanunacceptablelevel.Adesktopstudyonthissectionoflineshowsthatalthoughthestructuresappearsound,theyareoverloaded.Thepolesoneachendoftherivercrossingspanareatriskshouldtheveryworstdesignweatherconditionseventuate.Forthesereasons,retensioningtheconductorshasnotbeenadopted.
Replacingtheexistingpoleswithtallerpoleswasalsoconsidered,howeveritwasdecidedthatthiswouldbeashorttermfixandalthoughtheywouldgainacceptablegroundclearance,thespanswouldnotbeanymoresecurethanatpresentandtheconductorwouldremainoverloaded.
40012: Replace Waiho River Crossing
Costs: $50,000 Project Timeline: May 2012 – June 2012
ThecontinualriseoftheWaihoRivernearFranzJosefandthesubsequentriseofthefloodbankhasagainbeguntothreatenthesecurityofthe11kVand33kVsupplyingSouthWestland.Todeterminethebestmethodtoensurethatallregulatoryclearancesareachieved,adesigniscurrentlyunderway.Thisdesign,whichmayincludeplacingpolesonraisedearthworksonbothsidesoftheriverwillbecompletedinFebruaryandwillincludeallpotentialmethodstoalleviatetheclearanceproblem.Acontingencysumof$50,000hasbeenallocatedforthiswork.
162 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Justification
TheSouthWestlandareafromFranzJoseftoParingaisdependentonsupplyfromthis33kVspurline,withnoredundancyinthearea.Withtheeverincreasingriseofthefloodwall,theclearancefromthetopofthewalltothelinewillbecomeless.Shouldthisworknotbecarriedout,theriskofheavyequipmentusedinraisingthefloodwallstrikingthelineisveryreal.
Alternative Options Considered
Althoughthedesignphasewillidentifyalloptionsforraisingtheline,itappearsatthistimethatconstructingraisedearthworkseithersideoftheriver,independentofthefloodwall,maybethebestoption.
40012: GYM-KUM 66 kV Pole Replacement
Costs: $40,000 Project Timeline: February 2013
In previous years, poles on theGYM-KUM66 kV cct have been replaced in sections. However, a change inreplacementstrategywillseepolesreplacedonlywhenthepoleshavebeenproventobeattheendoftheirserviceablelife.Acontingencysumof$40,000hasbeenallocatedtoallowthereplacementoffourstructures.
Justification
Builtin1977(approaching35yearsold),theGYM-KUM66kVcctiscriticaltothesecurityofsupplytoGreymouthandthesurroundingareas.Shouldapolefail,particularlyinsomeofthemoreremoteareas,securityofsupplytoGreymouthcouldbecompromised.
Alternative Options Considered
Asmentioned,thealternativetoapole-for-polereplacementstrategyisthatofsectionsoflinebeingreplacedasa‘project’.Asthisstrategyisnolongersupported,therearenootheroptionsavailable.
40013: Sub-transmission Condemned Pole Replacement
Costs: $30,000 Project Timeline: April 2012 - March 2013
Previously,mostsubtransmissionpolesreplacedwereincludedinprojectsthatreplacedsectionsoflinedeemedto be reaching replacement criteria.With the shift in assetmanagement strategy to bemoremaintenancefocused,onlysub-transmissionpolesthathavebeenproventohavereachedtheendoftheiroperationallifewillbereplaced.Toprovethis,thoroughinspection,includingscanningandanalysiswiththePortaSCANXBSpoledensityscanningsystem,willberequired.
Fiftyfivesubtransmissionpoleshavebeenidentifiedtobeinpoororworseconditionusingthetraditionaldigandprobemethodofassessment.ConsiderationmustbegiventoPortaSCANXBSresults,whichareverylikelytosignificantlyreducethenumberofpolesrequiringreplacementduetothemoreaccurateassessmentthatthePortaSCANXBSprovides.
Fromtimetotime,itmaybemoreprudenttoreplaceseveralpolesinasectionoflineifconsiderationssuchasreconfiguration,landownerissuesoroutagerestrictionswarrantthis.
Justification
Toensuresafetytoworkersandthepublic,andtoreducefaults,polesmustbereplacediffailureisimminent.Replacementmustbebalancedwith gaining themaximum life frompoles, hence theemphasis ondetailedassessmentbeforepolesarechangedout.
Alternative Options Considered
Polesattheendoftheiroperationallivesmustbereplaced.Therefore,noalternativeoptionsareavailable.
NETWORKDEVELOPMENT 163
Inspection, Service and Testing
10001: Sub-transmission Access Road Maintenance
Costs: $44,000 Project Timeline: April 2012 - March 2013
Keepingaccesstostructuresopenandclearisveryimportantformaintenanceandattimesoffaults.Sometimesaccesstostructurescanbeblockedbyslipsorwashoutsandneedclearing,generallyrequiringexcavatorstocarryoutthework.Occasionallyaculvertmaywashoutandrequirereplacement,furtherinhibitingaccesstostructures.Thebudgeted$44,000isacontingencyforsuchevents.
Justification
Attimeof faults, routine inspectionsor linemaintenance, it is crucial thataccess is clearandcrewscanbedeployedtostructureswithouthavingtomanoeuvrearoundobstaclesortoclearovergrownvegetation.Aswellas speedingupentry to structures, thehealthandsafetyaspectofkeepingaccesswaysclearmustbeconsidered.
Alternative Options Considered
Forthereasonslistedabove,accesstostructuresmustbecleared;therefore,therearenoalternativeoptions.
10011: River Protection Works
Costs: Subtransmission - $50,000 distribution - $66,000
Project Timeline: April 2012 - March 2013
ThefrequentheavyraineventsexperiencedontheWestCoastcanoftencauseriverstofloodandthreatensub-transmissionlines.AreasofconcernaretheTaramakauRiverandseveralriversinSouthWestlandthathavethepotentialtobreachtheirbanksandre-routeintothepathofWestpower’sstructures.Forthis,acontingencysumhasbeenallocatedforriverprotection,whichisgenerallyintheformofrockprotection.
Justification
Toensurestructuresareprotectedfromthethreatsthatrivererosionposes,fundsmustbeallocatedtoensurefloodprotectionworkiscarriedoutbeforeanextremeevent.Areasofconcernaregenerallyidentifiedduringroutineorspeciallineinspections.
Alternative Options Considered
Forthereasonslistedabove,structuresmustbeprotectedfromthethreatoferosionandtherefore,therearenoviablealternativeoptions.
10012: Weed Spray Access Tracks and various Line Routes
Costs: $60,000 Project Timeline: January 2013 - February 2013
Weedsprayingoftracksandlinerouteshasbecomeanintegralpartofthevegetationcontrolprocessthroughoutthenetwork. In recent years,overgrown trackshavebeenopenedupallowing safevehicleaccess tomostsub-transmissionstructures thusenablingmoreefficientpatrols,access forconditionassessmentand fasterresponsetime incaseof faults. These tracksneed to remainclearand inmostcases regular sprayingwithagrichemicalskeepsthebrushandscrubatbay.
164 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Justification
Aswiththeaccessroadmaintenanceproject,weedsprayingneedstobecarriedoutannuallytoallowspeedyaccesstostructuresandalsotokeeptroublesomescrubthatmaycontactthelineatbay.
Alternative Options Considered
Forthereasonslistedabove,accesstostructuresmustbekeptclear.Clearingscrubwithachainsawcouldbeseenasanoption;however,thatmethoddoesnotcontaintheregrowthrateasefficientlyassprayingagrichemicals.Inaddition,clearingscrubwithachainsawisslowandcumbersome.
Tree Trimming and Felling
Costs: $501,000 Project Timeline: April 2012 - March 2013
TheintroductionoftheHazardsfromTreesRegulations2003placedasubstantialemphasisontrimmingandremovingtreesnearpowerlines.From2003tothepresentday,significantprogresshasbeenmadeinkeepingvegetationclearoflinesontheWestpowernetwork.ThisactivityhashelpedtoreduceSAIDI’sandhasvastlyimprovingpublicsafety.Asmentioned,manytreeshavebeenremovedfromnearlinesandwillnotrequirearevisit,andalargenumberoftreeshavebecometheresponsibilityofthelandowner,havingreceivedthefirstcut.InaccordancewiththeHazardfromTreesRegulations2003,theselandownerswillberequiredtofundthenexttrim.Thefactorslistedabovearereflectedinthereductionofthetreetrimmingfundingintheupcomingyears.
Justification
ToadheretotheHazardsfromTreesRegulations2003andtheElectricitySafetyRegulations2010,Westpowermustcontinuetoadministerandcarryouttreetrimmingworktoanacceptablelevel.
Alternative Options Considered
Asthedriversforthecontinuedtrimmingandfellingoftreesissafetyandregulatory,therearenoalternativeoptionsavailable.
Sub-transmission Condition Assessment
Costs: $82,000 Project Timeline: April 2012 - March 2013
Conditionassessmentofalllineshasbecomeincreasinglyimportant,particularlywiththerecentlyintroducedmaintenance focused assetmanagement strategy. To ensure optimum life levels are gained for each asset,particularlypoles,assessmentneedstobetimelyandaccurate.
Thereareinexcessof700hardwoodsubtransmissionpolesonthenetwork,althoughsomearereasonablynew(68ontheKUM-KAW66cctconstructedin1997).Mostoftherestareagingandwillrequirecarefulandanalyticinspection,includingscanningwiththerecentlyimplementedPortaSCANpoledensitymeasuringdevice.
Givenafive-yearinspectionschedule,140woodensubtransmissionpoleswillrequiredetailedinspectionandassessmentannually. In addition to thewoodenpoles, thereare1861 concrete sub transmissionpoles thatrequireregularinspection.Asthereisnorequirementforundergroundinspection,inspectionandassessmenttimesforthesearefarlessthanwoodenequivalents;however,analysisofassessmentresultsremainssimilar.
Justification
Bestpracticeassetmanagementcallsforregularinspectionandassessmentofassets,andthereforeinspectionofsub-transmissionassetsisrequired.Theconditionassessmentprogrammeallowsidentificationofdefectivecomponentsandaidsinforecastingassetlives,providingaplatformforreplacementplanning.
NETWORKDEVELOPMENT 165
Alternative Options Considered
Asthedriversfortheconditionassessmentofsubtransmissionassetsaresafetyandregulatory,therearenoalternativeoptionsavailable.
Sub-transmission Line Patrols
Costs: $80,000 Project Timeline: April 2012 - March 2013
Overthe lastthreeyearsthenumbersofsub-transmission linepatrolshaveprogressively increasedwiththeuseofpreventativemaintenancescheduling.Manydefectshavebeenfoundandcorrectedbeforeafaulthasoccurredandtheresultingreportshaveprovedinvaluabletoprovideasnapshotofthestateofeachlineatanytime.
Apatroldiffers fromaconditionassessment inspectionas farasapatrol isabriskvisit toeachstructureoraccesswayandavisualinspectionisallthatisgenerallyrequiredwithanydefectsoranomaliesrecorded.
Aswellasroutinepatrolsotherpatrols,suchasafterextremeweatherevents,arealsocarriedoutandaidinpotentialfaultidentification.TheallocatedfundingallowsforthePreventativeMaintenance(PM)schedulestobecarriedoutandacontingencyforanyspecialpatrolsthatmayberequired.
Justification
Toensuresub-transmissionassetsremainsafeandoperational,regularpatrolsarecritical. Resultingreportscontaining information such as defective components, potential landowner issues, access issues and safetyconcernscangenerallybeaddressedbeforetheybecomeaproblem.
Alternative Options Considered
Thepatrollingoflinesonaregularbasishasbeenincarriedoutinearnestonlyrecentlyandhasalreadyprovidedinformationthatcouldhavepreventedfaultsand/orsafety issues. Toceasecarryingoutthesepatrolscouldcontravenepublicsafetyregulationsandcompromisesecurityofsupply.
General Maintenance of Subtransmission Lines
Costs: $70,000 Project Timeline: April 2012 - March 2013
Asum is included in thebudget foranygeneral linemaintenancework thatmayneed tobecarriedoutonanyofthesubtransmissionlinesoccasionally,minormaintenanceisrequired,suchasstepboltreplacements,replacementofdamagedearthleadsormaybearustyclamp.Asum,therefore,needstobeallocatedtoallowforthiswork.
Justification
Astheconditionassessmentandlinepatrollinghasbeenprogressivelyrampedup,sohastheidentificationofthistypeofmaintenancework.
Alternative Options Considered
Asmostdefects identifiedrequire remedialaction,noalternativeoptionsareavailable toensurea safeandreliablesub-transmissionsupply.
166 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Enhancement
50002: HKK-WTH 33 kV Conductor Upgrade
Costs: $1,800,000 Project Timeline: April 2012 – December 2012
Project Justification Score: 50
AmethystHydroisbuildinganewhydroschemeontheAmethystRivernearHarihariinSouthWestland.Thishydroschemewillgenerateupto6MWofelectricityintoWestpower’s33kVlinenearHarihari.ThevastmajorityofthisgenerationwillneedtobetransmittednorthwardtoHokitika,adistanceofsome65km.
Anassessmentwascarriedout todeterminethe losses involvedshouldtheexistingDogACSRconductorberetained.Theresultsofthisassessmentrevealedthatalargenumberoflosseswouldbelikely,whichpromptedastrategicreviewtodeterminethebestmethodoflossavoidanceonthecircuit.ItwasdecidedthatstringingthelargercapacityOxygenAAACfromtheWaitahasubstationtoHokitikawouldbethebestoptiontohelpensuretheoptimumtransmissionconfiguration.
Alternative Options Considered
Fouralternativeoptionswereconsideredforthisproject:
• Existingconductortype(Dog)energisedat33kV,
• UpgradingthelineconductortoOxygenandenergisedat33kV,
• Existingconductortype(Dog)energisedat66kV,
• UpgradingthelineconductortoOxygenenergisedat66kV.
5.8.4.2 TwotoFive-YearperiodProjects
Replacement
Mapourika, Replace Substandard Poles (2015-2018) $20,000 p/year
Condition assessment revealed thatmost of the poles on the Hendrix cable section of line traversing LakeMapourikaareinverypoorcondition.AsubsequentinspectionwiththePortaSCANXBSpolescanningsystemdisputedthetraditionalmethodsandfoundthemajorityofpolestohavemanyyearsofoperationalliferemaining,howeverseveralwillneedtobemonitoredandpossiblyreplaced.
Warrens Paddock - Replace structures (2013-2014) $50,000
Thewooden33kVand11kVstructuresatWarrenspaddocknearTaylorvillesupportanintegrallinktotheNorthviatheRapahoeandNgaheresubstations.Inparticular,the33kVlinetoRapahoedoesnotproviden-1security,andtheminesandsurroundingtownshipsrelyheavilyonthissupply.Atpresent,thestructurescouldbedeemedtheweakestlinkforthiscriticallineandalthoughPortaSCANresultindicatethepolesareinreasonableconditionandshouldwithstandnormalloadsplaceduponthem,thecriticalityoftheagingstructuresdeemthisprojectnecessary.Atminimalcost,risktothiscircuitcouldbeachievedbyreplacingthestructures.Itisintendedthatadesignwillbecarriedout2012-13toallowamoreaccuratecostassessment.
NETWORKDEVELOPMENT 167
5.8.5 Distribution
5.8.5.1 Twelve-monthperiod(over$30,000)
Replacement
41064: Distribution Condemned Pole Replacement
Costs: $150,000 Project Timeline: April 2012 - March 2013
Aswiththesub-transmissionpoles,mostdistributionpolesreplacedhavebeenincludedinprojectsthatreplacedsectionsof line thatweredeemed tobe reaching replacement criteria.With the shift inassetmanagementstrategytobemoremaintenancefocused,onlydistributionpolesthathavebeenproventohavereachedtheendoftheiroperational lifewillbereplaced. Toprovethis,thorough inspection, includingthescanningandanalysiswiththePortaSCANXBSpoledensityscanningsystemwillberequired.
Six hundred and twenty twodistributionpoles havebeen identified tobe in poororworse conditionusingthetraditionaldigandprobemethodofassessment. ConsiderationmustbegiventoPortaSCANXBSresultswhichwillmostlikelysignificantlyreducethenumberofpolesrequiringreplacementduetothemoreaccurateassessmentthatthePortaSCANXBSprovides.
Fromtimetotimeitmaybemoreprudenttoreplaceseveralpolesinasectionoflineifconsiderationssuchasre-configuration,landownerissuesoroutagerestrictionswarrantthis.
Justification
To ensure safety toworkers, the public and to reduce faults, polesmust be replaced if failure is imminent.Replacementmustbebalancedwith gaining themaximum life frompoles, hence theemphasis ondetailedassessmentbeforepolesarechangedout.
Alternative Options Considered
Polesattheendoftheiroperationallivesmustbereplaced,thereforenoalternativeoptionsareavailable.
41002: Blackball-Atarau Rd - 11 kV pole replacement
Costs: $80,000 Project Timeline: July 2012 - August 2012
The 11 kV line fromBlackball through toMoonlight/Atarau has beenprogressively replaced over a numberofyears.Thesectionoflineintendedforreplacementin2012-13isinverypoorconditionandasurveyandsubsequentlinedesignhasbeencarriedouttoprovideoptimumpoleplacementforreplacementpoles.Thisworkisrequiredasthelineneedsreconfigurationandtheconditionissuchthatreplacementonanasrequiredbasiswouldseemuchofthelinereplacednonetheless.
Justification
Thissectionof11kVlinerequiresreplacementtoprovideareliableandsafesupplytotheMoonlightandAtarauareas.Publicandworkersafetyconsiderationsmakethisamustdoproject.
Alternative Options Considered
Theonly other alternative to this project is to replace individual poles on an as requiredbasis, however asmentioned,most poleswould be replaced if thiswas the case. The opportunity to reconfigure the line toprovideoptimumpolepositionsalsolendsweighttocompletingasectionoflineasopposedtoindividualpolereplacement.
168 WESTPOWERASSETMANAGEMENTPLAN2012-2022
41016: Kumara Junction to Kumara 11 kV Line Replacement
Costs: $80,000 Project Timeline: July 2012 - August 2012
The line fromKumara Junction through to Kumarahas beenprogressively replacedover a numberof yearswiththefinalsectionofline,intendedtoreplacetheexisting54yearoldlineinverypoorcondition,theonlysectionyettobecompleted.Negotiationswithlandownersarelookingpositiveandafinallinerouteshouldbeestablishedinearly2012.Thelineneedstobereconfiguredtooptimisepolepositionsandtheconditionissuchthatreplacementonanasrequiredbasiswouldseemuchoftheremainingsectionoflinereplacednonetheless.
Justification
Thissectionof11kVlinerequiresreplacementtoprovideareliableandsafesupplytotheKumaraarea.Publicandworkersafetyconsiderationsmakethisamustdoproject.
Alternative Options Considered
Theonly other alternative to this project is to replace individual poles on an as requiredbasis, however asmentioned,most poleswould be replaced if thiswas the case. The opportunity to reconfigure the line toprovideoptimumpolepositionsalsolendsweighttocompletingasectionoflineasopposedtoindividualpolereplacement.
41060: Garvey’s Creek 11 kV Line Replacement
Costs: $45,000 Project Timeline: October 2012 - November 2012
The11kVlinefromtheStateHighwaytoGarvey’sCreekminehasbeenprogressivelyreplacedoveranumberofyearswitharelativelysmallnumberofcondemnedpolesremaining.AlthoughthesepoleshavenotbeeninspectedusingthePortaSCANpoledensitymeasuringdevice,previousinspectionshavemadeitclearthattheyneedtobereplaced.
Justification
Thissectionof11kVlinerequiresreplacementtoprovideareliableandsafesupplytotheGarvey’sCreek/CraigsFlatarea.Publicandworkersafetyconsiderationsmakethisamustdoproject.
Alternative Options Considered
Theonlyotheralternativetothisprojectistoreplaceindividualpolesonanasrequiredbasis,howevermostpoleswouldbereplacedifthiswasthecase.Theopportunitytoreconfigurethelinetoprovideoptimumpolepositionsalsolendsweighttocompletingasectionoflineasopposedtoindividualpolereplacement.
41062: S670, Ahaura - Relocate 11 kV Line
Costs: $45,000 Project Timeline: April 2012 – May 2012
Apublicsafetyinvestigationwasinitiatedafteracontractorhadestablishedagravelpiledirectlyunderthe11kV linetraversinghisgravelyard,severelyreducingtheconductorclearance. Duringthe investigation itwasdiscoveredthatthe11kVhardwoodpolescrossingthecontractorspropertyareinpoorconditionandareinapositionwheretheycouldbedamagedduetothenatureofthecontractorsbusinessandassociatedvehiclemovements. Itwasdecided that the sectionof11kV line inquestionbe relocatedclearof thecontractorsactivities.
Justification
Toensureasafe11kVsupplythesepolesneedreplacingawayfromthecontractorsyard.
NETWORKDEVELOPMENT 169
Alternative Options Considered
Protectivecoversorwarningflagscouldbeattachedtothelinetoprovideavisiblewarningforthecontractor,howevergiventhepoorconditionofthepolesandthattheyhavereachedreplacementcriteria, ithasbeendeemedprudenttoreplaceandrelocatetheline.
Inspection, Service & Testing
Distribution Condition Assessment
Costs: $150,000 Project Timeline: April 2012 - March 2013
Conditionassessmentofalllineshasbecomeincreasinglyimportant,particularlywiththerecentlyintroducedmaintenance focused assetmanagement strategy. To ensure optimum life levels are gained for each asset,particularlypoles,assessmentneedstobetimelyandaccurate.
Thereareinexcessof3390woodendistributionpolesonthenetwork,whichwillrequireathoroughinspectionincludingscanningwiththerecentlyimplementedPortaSCANXBSpoledensitymeasuringdevice.
Given a five year inspection schedule, 680 wooden distribution poles will require detailed inspection andassessmentannually.Inadditiontothewoodenpoles,thereare9748concretedistributionpolesthatrequireregularinspection.Asthereisnorequirementforundergroundinspection,inspectionandassessmenttimesarefarlessthanwoodenequivalents,howeveranalysisofassessmentresultsremainssimilar.
Justification
Best practice assetmanagement calls for regular inspection and assessment of assets, therefore inspectionof distribution assets is required. The condition assessment programme allows identification of defectivecomponentsandaidsinforecastingassetlives,providingaplatformforreplacementplanning.
Alternative Options Considered
As the drivers for the condition assessment of distribution assets are safety and regulatory, there are noalternativeoptionsavailable.
Distribution Line Patrols
Costs: $32,000 Project Timeline: April 2012 - March 2013
Generallydistribution linepatrolsarecarriedout toestablish thecauseofa fault,however it is intendedtoinclude11kVcriticallinesinPMschedulessimilartothatawardedtosub-transmissionlines.
Apatroldiffers fromaConditionAssessment inspectionasfarasapatrol isabriskvisit toeachstructureoraccesswayandavisualinspectionisallthatisgenerallyrequiredwithanydefectsoranomaliesrecorded.
Aswell as routine patrols, other patrols such as after extremeweather events are also carried out and aidin potential fault identification. The allocated funding allows for thePM schedules tobe carriedout and acontingencyforanyspecialpatrolsthatmayberequired.
Justification
Toensuredistributionassetsremainsafeandoperational,regularpatrolsarecritical.Resultingreportscontaininginformationsuchasdefectivecomponents,potentiallandownerissues,accessissuesandsafetyconcernscangenerallybeaddressedbeforetheybecomeaproblem.
170 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Alternative Options Considered
Thepatrollingoflinesonaregularbasishasbeencarriedoutinearnestonlyrecentlyandhasalreadyprovidedinformationthatcouldhavepreventedfaultsand/orsafety issues. Toceasecarryingoutthesepatrolscouldcontravenepublicsafetyregulationsandcompromisesecurityofsupply.
11011: 11 kV Crossarm Replacements
Costs: $50,000 Project Timeline: April 2012 - March 2013
Conditionassessmentandpatrolshaveidentifiedanumberofdistributioncrossarmsthathavedeterioratedtothepointwherereplacementisrequired.
Over600distributioncrossarmshavebeenidentifiedtobein“NeedsReplacing”orworsecondition,howeveritisplannedtocarryoutmoredetailedaerialinspectionstomoreaccuratelydeterminetheextentoftheissue.
Justification
Topreventconductordrop,allcrossarmsneedtobecapableofwithstandingtheloadsplaceduponthem,eveninthemostextremeweatherevents.Giventhis,crossarmsmustbecheckedandreplacedwhererequired.
Alternative Options Considered
Ascrossarmsarecriticaltotheoverallsupportofconductors,asmentioned,theymustbecapableofsupportingloadsexpectedofthem.Thereforethereisnoalternativeoptionthantoreplacedefectivecrossarms.
5.8.5.2 TwotoFiveYearPeriodProjects
Enhancement
Light Conductor Replacement (2014-2016) $50,000 p/year
Over recentyears the replacementof light conductor (Mullet,7/.064)hasbeencarriedout for twoprimaryreasons. Thefirstwastoensurethe lineswithina7kmradiusofzonesubstationscouldwithstandthefaultcurrents that theconductorcouldbesubjected towithout failing, theother reasonwas the lackof suitablespares,particularly jointingsparesfortheflatbodiedMulletACSR. Manyofthesetypesofconductorshavebeenreplaced,howeverpocketsstillremain.Althoughacontingencysumhasbeenallocatedeachyearfrom2014-2016replacementoftheseconductors,detailedanalysishasnotyetbeencarriedouttodeterminehowmuchremainsandthecosts toreplace. Inaddition,suitable jointingmethodshavebeendevelopedfor theMulletconductorwhichmayprovetobeanacceptableriskonthenetworkparticularlyininlandareas.Detailedanalysisistobeundertakeninthe2012-13yearwithascopeofworkresultingfromthesestudies.
Replacement
Nelson Creek State Farm, Re-route and Replace 11 kV Line (2013-2014) $80,000
An assessment in 2008 of hardwood poles at theNelson Creek State Farm showed that at least four polesneedreplacingwhileanumberofothersaredeemedtobeinverypoorcondition.Thisfinancialyearwillseeadesigncarriedouttoinvestigatethefeasibilityofre-routingthelinealongarecentlyformedroadtoavoidtheinhospitableterraincurrentlyencounteredbyworkers.
Park Street – Jollie Street 11 kV Overhead to Underground Conversion (2013-2014) $50,000
A public safety assessment has determined that the 11 kV overhead line, constructedwith concrete poles,traversesa schoolplayingfieldandcouldposeapotentialhazard.Tomitigate thishazardoptionsare tobeinvestigatedandconsideredinthe2012-13yearandifrequired,implementedthefollowingyear.Optionscouldincludetheconversionoftheoverheadlinetoanundergroundcircuit.
NETWORKDEVELOPMENT 171
Removal of the Seaview 11 kV Line (2013-2014) $85,000
With the relocationof themainHokitika feeders fromArahura toKaniereRoad coupledwith theverypoorconditionofthe11kVlinetraversingtherearoftheSeaviewcomplex,therequirementforthissectionoflinewasassessed.Astudywascarriedoutbydesignstafftodeterminewhetherthe lineshouldberetainedandupgraded,orremovedandhaveexistinginstallationssuppliedfromthe11kVlinetraversingtheStateHighway.
The result of the study,which also considered any potential landowner/easement/access issues and designconstraints,recommendedthatitismoreefficienttoreconfigurethecustomersuppliesthatconnecttothe11kValongtheStateHighwaythanattempttorebuildtheexistinglinemainlybecauseoftheinaccessibilitytomostofthelineduetothebrokennatureofthecountryandrestrictedaccess.
Thisprojectwillseetheremovaloffifteenhardwoodpoles,whichwouldotherwiserequirereplacement,frombushcladterrainandrelocateservicestotheeasilyaccessibleStateHighway.
5.8.6 Reticulation
5.8.6.1 Twelve-Monthperiod(over$30,000)
Replacement
42013: Kaiata LV Line Relocation
Costs: $40,000 Project Timeline: June 2012 - July 2013
ArequestwasreceivedfromalandowneratKaiatawhowishestodevelophispropertyandneedstheLVlinesupplyingneighbouringpropertiesremovedasitrestrictsdevelopments.Asurveyanddesignwascarriedoutandaplanhasbeenestablishedtorelocatetheline,suppliedfromthelineattheStateHighwayasopposedtotraversingrearsections.
Justification
Toensurethelineispositionedonaroutesuitabletoallparties,witheasementsgrantedovertherouteprotectingthelineinfuturethisworkneedstobecarriedout.Accesstothelineforinspectionormaintenancewillalsobeassured.
Alternative Options Considered
Severalalternativerouteswereconsidered,howeverconnectingtothelineontheStateHighwaywasdeemedthemostsuitableasitisdirectandthelandowneriswillingtogranteasementsacrosshisproperty.Shouldthelineremaininit’sexistinglocation,accesscannotbeguaranteed.
42014: Reticulation Condemned Pole Replacement
Costs: $50,000 Project Timeline: April 2012 - March 2013
Aswith thesub-transmissionpolesanddistributionpoles,manyreticulationreplacedhavebeen included inprojects that replaced sections of line deemed to be reaching replacement criteria.With the shift in AssetManagementstrategytobemoremaintenancefocused,onlyreticulationpolesthathavebeenproventohavereached theendof theiroperational lifewill be replaced. Toprove this, thorough inspection, including thescanningandanalysiswiththePortaSCANXBSpoledensityscanningsystemwillberequired.
Eightyfivereticulationpoleshavebeenidentifiedtobeinpoororworseconditionusingthetraditionaldigandprobemethodofassessment. Considerationmustbegiven toPortaSCANXBS resultswhichwillmost likelysignificantlyreducethenumberofpolesrequiringreplacementduetothemoreaccurateassessmentthatthePortaSCANXBSprovides.
172 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Fromtimetotimeitmaybemoreprudenttoreplaceseveralpolesinasectionoflineifconsiderationssuchasre-configuration,landownerissuesoroutagerestrictionswarrantthis.
Justification
To ensure safety toworkers, the public and to reduce faults, polesmust be replaced if failure is imminent.Replacementmustbebalancedwith gaining themaximum life frompoles, hence theemphasis ondetailedassessmentbeforepolesarechangedout.
Alternative Options Considered
Polesattheendoftheiroperationallivesmustbereplaced,thereforenoalternativeoptionsareavailable.
Inspection, Service & Testing
12014: Reticulation Condemned Crossarm Replacement
Costs: $45,000 Project Timeline: April 2012 - March 2013
ConditionAssessmentandpatrolshaveidentifiedanumberofreticulationcrossarmsthathavedeterioratedtothepointwherereplacementisrequired.
590reticulationcrossarmshavebeenidentifiedtobein‘Poor’orworsecondition,howeveritisplannedtocarryoutmoredetailedaerialinspectionstomoreaccuratelydeterminetheextentoftheissue.
Justification
Topreventconductordrop,allcrossarmsneedtobecapableofwithstandingtheloadsplaceduponthem,eveninthemostextremeweatherevents.Giventhis,crossarmsmustbecheckedandreplacedwhererequired.
Alternative Options Considered
Ascrossarmsarecriticaltotheoverallsupportofconductors,asmentioned,theymustbecapableofsupportingloadsexpectedofthem.Thereforethereisnoalternativeoptionthantoreplacedefectivecrossarms.
Reticulation Condition Assessment
Costs: $45,000 Project Timeline: April 2012 - March 2013
Conditionassessmentofalllineshasbecomeincreasinglyimportant,particularlywiththerecentlyintroducedmaintenance focused assetmanagement strategy. To ensure optimum life levels are gained for each asset,particularlypoles,assessmentneedstobetimelyandaccurate.
Thereareinexcessof2140woodendistributionpolesonthenetwork,whichwillrequireathoroughinspectionincludingscanningwiththerecentlyimplementedPortaSCANXBSpoledensitymeasuringdevice.
Given a five year inspection schedule, 428 wooden distribution poles will require detailed inspection andassessmentannually.Inadditiontothewoodenpoles,thereare1878concretereticulationpolesthatrequireregularinspection.Asthereisnorequirementforundergroundinspection,inspectionandassessmenttimesarefarlessthanwoodenequivalents,howeveranalysisofassessmentresultsremainssimilar.
Justification
Best practice assetmanagement calls for regular inspection and assessment of assets, therefore inspectionof reticulation assets is required. The condition assessment programme allows identification of defectivecomponentsandaidsinforecastingassetlives,providingaplatformforreplacementplanning.
NETWORKDEVELOPMENT 173
Alternative Options Considered
Asthedriversfortheconditionassessmentofreticulationassetsaresafetyandregulatory,therearenoalternativeoptionsavailable.
43001: Condemned Service Pole Replacement
Costs: $60,000 Project Timeline: April 2012 - March 2013
Overanumberofyearsmanyservicepoleshavebeendeemedtohavereachedreplacementcriteriaandhavebeenreplacedaccordingly.Thispracticeistocontinue,howevertheassessmentofservicepoleswillbemorethroughthan inthepast. Thenumberofservicepolesrequiringreplacementhasreducedoverthe last fewyears,hencetherelativereductioninfunding.
Justification
To ensure safety toworkers, the public and to reduce faults, polesmust be replaced if failure is imminent.Replacementmustbebalancedwith gaining themaximum life frompoles, hence theemphasis ondetailedassessmentbeforepolesarechangedout.
Alternative Options Considered
Polesattheendoftheiroperationallivesmustbereplaced,thereforenoalternativeoptionsareavailable.
5.8.6.2 TwotoFive-YearsPeriodProjects
Development
Cowper Street – Develop LV Link (2013-2014) $50,000
TheconstructionofthedistributionsubstationattheHighStreetBusinessParkextendedthenetworksufficientlytoallowaLVlinkalongCowperStreetbetweentheBusinessParkandintoCowperStreet.Installingapproximately55m(x2)ofLVcable intotheexistingductsfromtheBusinessParksubstationto join intotheexistingcablealongCowperStreetwillcreatemorediverseswitchingoptionsandallowforimprovedloadsharingbetweensubstationsinthearea.
5.8.7 DistributionSubstations
5.8.7.1 TwelveMonthPeriod(over$30,000)
Development
65003: New 11 kV Connections
Costs: $65,000 Project Timeline: April 2012 - March 2013
Aswithnewserviceconnections,new11kVconnectionsarelargelydrivenbydevelopmentinthearea.Numbersmayvary,forexample78applicationsfor11kVsupplywereprocessedin2008yetthenumberin2011reducedto38.Giventhisvariation,fundinghasbeensetatamedianleveloverthelast4years.
Justification
Westpowerprovides an11 kV connection servicewhich generally includes installationof appropriate fusing(networkconnectionpoint)andphysicalconnectiontothenetworkconnectionpoint.
Alternative Options Considered
Asthedriversfortheconnectingofnewservicesisbythecustomer,therearenoalternativeoptionsavailable.
174 WESTPOWERASSETMANAGEMENTPLAN2012-2022
68001: Purchase of New Transformers
Costs: $449,000 Project Timeline: April 2012 – March 2013
Aswithnewserviceconnectionsand11kVconnections,thepurchaseofnewtransformersarelargelydependentondevelopmentinthearea. Thepurchaseofnewtransformersfluctuatesrelativeto11kVconnections,forexample65transformerswerepurchasedin2008asopposedto31in2011.
Justification
Aswiththe11kVconnectionserviceWestpowerwillprovideatransformerandcontinuetoownandmaintainthetransformerforhose11kVconnectionsrequiringone.
Alternative Options Considered
As thedriver for thepurchaseof transformer is generallyby the customer, therearenoalternativeoptionsavailable.
Enhancement
55002: Increase Transformer Site Capacity (Uprate)
Costs: $35,000 Project Timeline: April 2012 - March 2013
Asmoreanalysisisbeingcarriedoutontransformerutilizationwithinthenetwork,thenumberoftransformersreplacedwithhigherratedunitshasincreased.Thishelpstoensureanacceptablequalityofsupply.
Justification
Westpowerisobligedtodeliveraqualitypowersupplyandacorrectlyratedtransformercanassisttoensuresuchasupply isavailable. WestpowerAssetManagementprocessesallowthemonitoringofthenumberofconnectionstoatransformerandsizeaccordingly.
Alternative Options Considered
Asthedriversfortheconnectingof installationstotransformers isbythecustomer,therearenoalternativeoptionsavailable.
55001: Greymouth CBD Sub Upgrade (S44 Badger Lane)
Costs: $66,000 Project Timeline: May 2012 - June 2012
The Greymouth CBD Subs Upgrade project has been in progress for a number of years, refurbishing CBDsubstationsasrequired.AreportrecentlysubmittedregardingtheconditionofS44atBadgerLanesuggestedthattheLVpanelsrequiredupgradetoensureasafeenvironmentandsecuresupply.
ItisintendedtoreplacetheagingmetalcladswitchboardwithamodernequivalentcompletewithJeanMullerfuseunits.ThiswillincludereconfiguringtheLVbusandre-routingsomecablestosuit.ThisprojectwillbealogisticalchallengeassupplywillneedtobemaintainedtotheCBDatalltimes.
Justification
It is critical that the supply to the Greymouth business area is maintained to a high standard. S44 wascommissionedin1958withmuchoftheoriginalequipmentstillinservice.Thisequipmenthasreachedtheendofitsoperationallifeandneedstobeupgradedwithmodernequivalentequipment.
NETWORKDEVELOPMENT 175
Alternative Options Considered
Astheequipmentinquestionisatanagewherereplacementisnecessary,nootheroptionsareavailable.
Replacement
45003: S1544 Otira – Upgrade LV panel
Costs: $30,000 Project Timeline: November 2012 - December 2012
S1544atOtira,aconcreteblockbuildingsubstation,housesageingLVswitchgearinpoorconditionthatneedstobereplacedwithmodernequivalents.Load intheareahasdecreaseddramaticallyoverrecentyears, thiscoupledwithKiwiRailabandoningtheswitchgearthattheypreviouslyownedandmaintainedhasresultedinanumberofredundantorunder-utilizedLVswitchingunits.
ItisintendedtooptimisetheexistingLVarrangement,replacingthe1960’sstylemetalcladswitchboardwithmodernLVpanelcompletewithJeanMullerfuseunits.Thesubstationbuildingwillalsoberefurbishedincludingpaintingandsealingtheinteriorandexterior.
Justification
Althoughasmentioned,theloadinOtirahasdeclinedoverrecentyears,areliablesupplyintheareaiscritical.Giventheremotelocation,faultresponsetimescanbelengthy,justifyinganyexpenditurewhichhelpstoreduceunplannedoutages.
Alternative Options Considered
Demolishingthebuildingandinstallingapadmountsubstationhasbeenconsideredhoweverthebenefitsthatthebuildingbringsforstorageoffaultsparesetc.lendsweighttomaintainingtheexistingstructure.
Inspection, Service & Testing
15006: Sub (Site) Upgrades
Costs: $348,000 Project Timeline: April 2012 - March 2013
Distributionsubstationupgradesarecarriedoutwhenasubstationhasbeenidentifiedashavingsubstandardequipmentattachedandneedtobeboughtuptoanacceptableleveltoprovideareliableandsafesupply.Thenumberofsubupgradesisexpectedtorisewiththeinceptionofthesubinspectionprogrammewhichwillseeeverysubvisited,testedandassessedinfiveyearlycycles.
Justification
To ensure a safe and reliable supply, transformer sites on the networkmust be kept at a high standard ofmaintenance.Publicsafetyisparamount,thereforeanyworkrequiredtominimiseoreliminatepotentialhazardsfromcomponentssuchasearthdroppersmustbepromptlyattendedto.
Alternative Options Considered
Assafetyandreliabilityofsupplyaretheforemostdriversforsubstationupgradestherearenoalternateoptionsavailable.
176 WESTPOWERASSETMANAGEMENTPLAN2012-2022
15012: Distribution Sub Inspections – Testing of Earths etc
Costs: $130,000 Project Timeline: May 2012 - June 2013
In accordancewith best industry practice, all distribution substations are to be visited and inspectedon anannualbasisandthoroughlyinspectedatfiveyearcycleswhichincludeearthtestingandageneralassessmentofconditionobservedandrecorded.Ofthe2320activedistributionsubsonthenetwork,464aretobethoroughlyinspectedeachyear.
Justification
To ensure a safe and reliable supply, transformer sites on the networkmust be kept at a high standard ofmaintenance.Publicsafetyisparamount,thereforeanyworkrequiredtominimiseoreliminatepotentialhazardsfrommustbepromptlyattendedto.
Alternative Options Considered
Assafetyandreliabilityofsupplyaretheforemostdriversforsubstationupgradestherearenoalternateoptionsavailable.
15009: Relocate Sub Fuses for 11 kV Spurs
Costs: $50,000 Project Timeline: April 2012 – March 2013
Toassistinminimisingoutagesonmainlinefeeders,aprojectistobeinitiatedtorelocateanyHVfusesonspurlinesfromthesubstationpoletothemainlinetake-off.Thiswillensurethatanyfaultedcomponentonthespurwillonlyblowthefusesonthespurandnottripthenearestmainlineprotectiondevice.
Justification
Relocatingspurlinefusestothemainlinetake-offwillreduceoutageson11kVfeedersbyisolatingthefaultedspurline,avoidingmainlinecircuitbreakertrips.
Alternative Options Considered
Asreliabilityofsupplyistheforemostdriverforrelocatingfusestothemainlinetakeoffpoles,therearenoalternateoptionsavailable.
5.8.8 Services
5.8.8.1 Twelve-MonthPeriod(over$30,000)
Development
63001: New Service Connections
Costs: $75,000 Project Timeline: April 2012 - March 2013
Newconnectionsarelargelydrivenbydevelopmentinthearea.Numbersmayvary,forexample309applicationsforsupplywereprocessedin2008yetthenumberin2011reducedto181.Giventhisvariation,fundinghasbeensetatamedianleveloverthelast4years.
Justification
Westpowerprovidesaconnectionservicewhichgenerallyincludesinstallationofappropriatefusing(networkconnectionpoint)andphysicalconnectiontothenetworkconnectionpoint.
NETWORKDEVELOPMENT 177
Alternative Options Considered
Asthedriversfortheconnectingofnewservicesiscustomer,therearenoalternativeoptionsavailable.
5.9 Overall Work Plan
Westpowerhasapolicyofretiringolderassetsthathavereachedtheendoftheireconomiclifewherethereisnoeconomicmeansofprovidinglifeextension.Someofthetriggerswhichwouldsuggestareplacementstrategybeingemployedratherthanongoingmaintenancewouldinclude:
• Morethan50%ofalinesectionreachingreplacementcriteriawithinthefollowingfive-yearperiod;
• Technicalobsolescence;
• Healthandsafetyconcerns(e.g.SeriesIAndelectoil-filledringmainunits);
• Difficultyinobtainingspareparts;
• Inabilitytomeetcurrentneeds.
Westpoweralsoexperiencesseverecorrosioninareasneartothecoast,anditisoftenmorecost-effectivetoinstallnewcorrosion-resistantfittings,forinstance,ratherthancontinuingtorepairexistingfittings.
Thereisanaturalbusinessdrivertomaintainratherthanreplaceintheformoftaxbenefits,andthisprovidesacountervailingforcethatensuresthatareasonablebalanceismaintainedbetweenthesetwoapproaches.
5.9.1 MaintenanceTriggers
Maintenanceworkislargelybasedontheconditionoftheassets,asdescribedinSection6.
ThescopeofworkplannedundereachmaintenanceactivityisquantifiedwhereverpossibletoassistinreviewingWestpower’sachievementinthefuture.Theestimatedmaintenanceexpenditureisprojectedinthissectionandwhere relevant, theconsequencesof theproposedmaintenanceprogrammesarenoted. It shouldbenotedthat analysis ofmaintenance strategies and programmes is an ongoing process and themost cost-effectivemeansofmaintainingthesystemisconstantlyunderreview.Insomeinstances(e.g.polereplacement),furtherinvestigationandanalysisisrequiredtodetermineasuitablestrategy.
Themaintenancerequirementsareinfluencedbydevelopmentprojects,manyofwhich, iftheyproceed,willleadtodismantlinganddecommissioningofassetswhichwouldotherwiserequiresignificantrepairs.
For consistency within this plan, the baseline planned maintenance expenditure projections assume, forconsistencywithin thisplan, thatdevelopmentprojectswill takeplaceasprojected in this section. Itwillbenecessarytomonitorthelikelihoodofeachprojectproceedingclosely,andadditionalremedialworkwillneedtobeprogrammedifcertainprojectsdonotproceedoraresignificantlydelayed.
Table5.20summarisestheplannedmaintenanceprojectsandprogrammesbycategoryfortheplanningperiod.
5.9.1.1 RepairsandRefurbishment
AlllinerepairsarecarriedouttotherequirementslaiddowninWestpower’slinemaintenancestandards.ThesearebasedoninternationalpracticecombinedwithlocalknowledgeandNewZealandlegislativerequirements.
Table 5.20 - Maintenance Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 4180 4446 4468 4580 4650 4477 4648 4862 5099 5323
Faults 541 571 607 641 680 717 759 803 850 899
Repairs 302 318 335 352 371 390 411 432 457 480
Total 5023 5335 5410 5573 5701 5584 5818 6097 6406 6702
178 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.9.2 ReplacementTriggers
5.9.2.1 MajorRefurbishments
Itisnecessarytoretaininservicesomeolderlines,whichareinpooroverallcondition.Theselinesrequireon-goingrepairsandrefurbishment.
Majorrefurbishmentonalllinetypesisestimatedtoabsorbonlyasmallproportionofthetotalmoneyproposedtobespentonlineworkinanyyear.
5.9.2.2 WoodPolesandCrossarms
Itiscurrentlyprojectedthatapproximately200poleswillneedchangingoverthenextyearinordertocopewithdefectsarisingontheexistingwoodpolelines.
Woodpolesarebeingchangedtoconcreteortreatedsoftwoodwhereverpossible,duetotheincreasinglypoorqualityandincreasingpriceofimportedhardwoodsfromAustralia.Localsoftwoodsoftheheightandstrengthsneeded are beginning to becomemore expensive andmay require ground-line preservation techniques toextendtheirin-servicelife.
Theuseofconcretepoles,providingtheycanbesourcedattherightpricefromthelocalsupplier,canresultinsignificantsavingsinon-goingmaintenance,increasedlinereliabilityandincreasedlineworkersafety.
5.9.2.3 ConductorsandAccessories
Asapolicy,allreplacementACSRisbeingpurchasedwithagreasedcorewire.Wherecorrosionresistanceiscriticalincoastalareas,allAAACisusedforitssuperiorcorrosionresistanceproperties.
Forlargerconductorswithanaluminiumcross-sectionalareaofover95mm2,WestpowerpolicyistouseAAACexclusively.
5.9.2.4 InsulatorsandInsulatorFittings
From the condition assessment programme it is estimated that there are approximately 300 33 kV EPDMstrain insulators requiring replacementover thenextfiveyears toavoidanunnecessary riskof linedroporfaultoutages.Theseinsulatorshavebeenproventodeterioraterapidlyaftertenyears;thereforeaproactiveapproachisrequiredtomanagetheriskoffailure.
Thereplacementofsuchinsulatorsisahighprioritybecauseofitsimmediateimpactonsystemreliability,andbecauseofthesafetyriskoflinedropsiftheworkisnotattendedto.
5.9.3 Enhancement
Table5.22summarisestheplannedenhancementworksfortheplanningperiod.
Thisactivityoutlinesworkwhich isplannedtoenhancethesystem.By this, itmeansthat this increases thecapacityofthesystemto:
• Providemoreload,
• Enhancevoltageregulation,
Table 5.21 - Replacement Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Replacement 2499 1150 611 881 727 842 669 1433 1374 1029
Table 5.22 - Enhancement Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Enhancement 2111 260 246 188 228 203 543 164 223 194
NETWORKDEVELOPMENT 179
• Improvesecurityandreliability.
Itincludesprojects(atspecificsites)andprogrammesofrelatedworkcoveringanumberofsites.
5.9.4 Development
Thissectionoutlinestheprojectscurrentlyanticipatedovertheplanningperiod.Thenatureofeachprojectisbrieflydescribedalongwiththereasonwhyitappearstoberequired.ThejustificationsforincludingeachoftheprojectsintheplanarecategorisedasdescribedinSection6,namely:
• Specificcustomerrequests(andcommitmenttoincurproject-relatedcharges);
• Anticipateddemandgrowth;
• Tomeetsecurityplanningguidelines;
• Economics(i.e.wheretheprojectproducesoverallcostsavings).
Table5.23summarisestheplanneddevelopmentworksfortheplanningperiod.
Table5.24outlinestheactivityandtheassettypenumbersusedfordevelopingtheprojectnumbers,whicharepresentedinthefollowingformat:year/activity/assettype/projectnumber.
Table 5.23 - Development Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Development 1437 1014 947 1095 1024 1004 1080 1209 1185 1269
Table 5.24 - Format of Project Numbers
Activity AssetType
1 IS&T 0 Sub-transmission
2 Faults 1 Distribution
3 Repairs 2 Reticulation
4 Replacement 3 Services
5 Enhancement 4 ZoneSubstations
6 Development 5 DistributionSubstations
6 MVSwitchgear
7 SCADA/Comms/Prot
8 DistributionTransformers
9 Other
180 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.10 Subtransmission Assets
Asdiscussed inSection3,thisassetclass involves33kVand66kVpower lines.The66kVassetsare leasedtoTranspowerandareacritical factor inthereliabilityofthenationalgrid inthearea.Accordingly,ahigherstandardofcareandmaintenanceisrequired.
Tables5.26to5.28expandontheIS&T,projectexpenditureplannedintermsofconditionassessmentprogrammesandtreetrimmingprogrammes.
Table 5.26 - Condition Assessment ($’000)
Asset Type 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Distribution 150 159 169 179 189 201 213 226 239 253
ReticulationLines 55 59 62 66 70 73 78 83 88 93
SubTransmissionLines 82 87 92 98 104 110 116 123 131 139
Total 287 305 323 343 363 384 407 432 458 485
Table 5.27 - Tree Trimming ($’000)
Asset Type 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Network 501 486 469 455 444 438 433 431 432 436
0
2000
4000
6000
8000
10000
12000
14000
16000
1 2 3 4 5 6 7 8 9 10
Year
$('
00
0)
Activity Inspection, Service & Testing Development
Replacement Faults Enhancement
Repairs
Figure5.25-ExpenditurebyActivity(incorporatingdatafromTable5.11to5.13)
NETWORKDEVELOPMENT 181
5.10.1 Greymouth-Kumara66kVLine
Theageofthisassetisapproachingmidlife,requiringincreasedlevelsofinspectiontomanageriskandidentifyearlysignsofdeterioration.
5.10.1.1Maintenance
Routine Patrols and Inspections
Anaerialandgroundpatrolofthislineisperformedannually.Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
Inadditiontopatrols,adetailedinspectionoftheentirelineisregularlycarriedout.Duringthisinspection,everyaspectofthelineischeckedandrecorded.Theresultswilldeterminetheextentofmaintenancetobecarriedoutinthecomingyears.
A 100% ground-line inspection, including ultrasonic pole density analysis,was carried out in 1998 to give abaselineforfutureinspections.
Thermographicsurveysarecarriedoutonanannualbasistocheckforhotjointsthatcouldleadtolaterfailure.Thesesurveysarenormallycarriedoutattimesofhighloadsuchasthewinterperiodtoincreasethechancesofdetectingamarginaljoint.
AtreetrimmingregimehasbeenestablishedduetothehighgrowthexperiencedontheWestCoast.Thisentailsthesubtransmissionlinesbeingclearedofvegetationeverytwoyearssoastoreducetheincidenceofaccidentalcontactduringstormyconditions.
5.10.1.2Faults
Theleveloffaultoccurrenceiscloselylinkedtoconditionoftheassetandtoexternalfactorssuchasclimaticconditions.
As far as climatic conditions are concerned, lightning and windstorms are usually the greatest sources ofproblems.Thislinehasalsodevelopedtransientearthfaultsduringwetweatherafterlongdryspells,possiblysymptomaticofinsulatorcontamination,butthisisveryrare.
Itisverydifficulttopredictthenumberoffaultsfromyeartoyearduetoclimaticconditions.AnestimateforfaultworkisprovidedbasedoninformationintheMaximoAssetWorksManagementSystem(AWMS)nowusedbytheassetmanagementdivision.
5.10.1.3RepairsandRefurbishment
AlllinerepairsarecarriedouttotherequirementslaiddowninWestpower’slinemaintenancestandards.Thesearebasedoninternationalpractice,combinedwithlocalknowledgeandlegislativerequirements.
Adecisionwill bemadeonpossible insulation replacement toward themiddleof theplanningperiodoncequantitativedatahavebeengatheredontheactualconditionofthecurrentinsulators.
Table 5.28 - Sub-Transmission - Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 654 674 697 726 759 782 819 865 916 966
Faults 22 23 25 26 28 29 31 33 35 37
Repairs 32 34 36 38 40 43 45 48 51 54
Replacement 948 125 98 102 105 93 97 102 107 113
Enhancement 1800 0 0 0 0 0 0 0 0 0
Development 50 0 0 0 0 0 0 0 0 0
Total 3506 856 856 892 932 947 992 1048 1109 1170
182 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.10.1.4Enhancement
Asa conditionof the leaseof thisasset toTranspower,a circuit ratingof35MVAmustbemaintained.ThecurrentDogACSRconductorhasa summertimeratingslightlybelowthisvalueand re-conductoringmayberequiredinthefuture.
Notwithstandingthis,Transpowerhaveyettorequestfullratinganditisveryunlikelythatloadgrowthwithintheplanningperiodwillrequiretheextracapacity.
5.10.2 Kumara-Kawhaka66kVLine
5.10.2.1Maintenance
Routine Patrols and Inspections
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
Thisline,althoughonly13yearsold,willbeincludedintheconditionassessmentprogramme,with20%ofthelinethoroughlyinspectedannually.Thiswillbeinadditiontoatwice-yearlygroundpatrolandannualpatrol.
Alljointsusedareofthecompressiontypeandwerecarefullytestedwithamicro-ohmmeterduringinstallation.Asaresult,thermographsurveysareunlikelytobeofanybenefitthroughouttheplanningperiodandarenotplannedfor.
5.10.2.2Faults
Theleveloffaultoccurrenceiscloselylinkedtoconditionoftheassetandtoexternalfactorssuchasclimaticconditions.
Asfarasclimaticconditionsareconcerned,lightningisthemostlikelycauseofproblems.Inthetimethatthelinehasbeeninservice,ithasonlysustainedonetransientfault,andthiswasduringaseverelightningstorm.
5.10.2.3RepairsandRefurbishment
Norepairsorrefurbishmentisplannedforthisline.Treeslikelytocauseaproblemwereclearedfromtheroutepriortoconstructionandwillnotimpactonthereliabilityofthelineduringthefirsthalfoftheplanningperiod.
5.10.2.4Enhancement
Withtheexceptionofthepossibleinstallationofenhancedlightningprotection,shouldthisprovenecessary,noenhancementprogrammesareplannedforthisasset.
5.10.3 NorthWestland33kVNetwork
WiththeexceptionoftheDobson-Arnoldline,allofthelinesinthisareawereconstructedsince1984,givingamaximumageofonly26years.Themedianageofthisassetgroupislessthantenyears.
TheageoftheDobson-Arnoldline(around60years)warrantshigherlevelsofinspectionandrefurbishment.Inaddressingthismatter,aprogrammehasbeenimplementedtorenewanypoleidentifiedasdefectiveoverafive-yearperiod.
5.10.3.1Maintenance
Routine Patrols and Inspections
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
NETWORKDEVELOPMENT 183
Inadditiontopatrols,adetailedinspectionofthislineistobecarriedoutonarollingfive-yearbasis,covering20%oftheroutelengthperyear.Duringtheinspection,everyaspectofthelineischecked.TheaimistoidentifyanddocumentallcomponentsthatdonotmeetWestpower’sstandards.
TheDobson-Arnoldlinehadamajorinspectioncompletedin1997whichincludedanassessmentofpoleandhardwareconditionaswellasanestimateofthepolesafetyfactorsintermsofbendingmoment.Allpoleswereshown tobeadequateat thetime;however, theageof the linemeans thatannual general inspectionswillcontinuetobecarriedout.
Allpolehardwarewillbeincludedintheinspections.
Aregularannualthermographicsurveywillbecarriedoutontheselinestomonitortheconditionofthejoints.
5.10.3.2Faults
Theleveloffaultoccurrenceiscloselylinkedtoconditionoftheassetandtoexternalfactorssuchasclimaticconditions.
Asfarasclimaticconditionsareconcerned,lightningandwindstormsareusuallythegreatestsourcesofproblems.
Itisverydifficulttopredictthenumberoffaultsfromyeartoyear,duetoclimaticconditions.AnestimateforfaultworkisprovidedbasedoninformationgatheredintheMaximoandGISsoftwarenowusedbytheassetmanagementgroup.
5.10.3.3RepairsandRefurbishment
AlllinerepairsarecarriedouttotherequirementslaiddowninWestpower’slinemaintenancestandards.Thesearebasedoninternationalpracticecombinedwithlocalknowledgeandlegislativerequirements.
Withtheaboveexceptions,norepairorrefurbishmentworkisrequiredontheconcretepolelinesbecauseofthelowaverageage.
The Arnold-Dobson linewill require individual pole replacement aswell as reconductoring and reinsulationwithinthenexttenyearsunlessaplannedenhancementprojectproceeds.
5.10.3.4Replacement
IfthelevelofrefurbishmentontheArnold-Dobsonlinebecomesgreaterthan50%oftheasset,completelinereplacementmaybemorecost-effective.Thiswillbereviewedtowardtheendoftheplanningperiod.
Noreplacementisforeseeableontheconcretepolelines.
5.10.3.5Enhancement
Enhancementofanyoftheconcretepolesectionsisnotenvisagedunlessdrivenbyamajorloadincrease.Inthiscase,reconductoringisthemostlikelyactivity.
ThecapacityoftheexistingArnold-Dobsonlineissufficientforthe3MWArnoldpowerstationtoconnectintothegrid,buthasnosparecapacity.Anysignificantincreaseintheinjectiondemandatthissiteuptoapproximately5MWwillrequiretheArnold-Dobsonlinetobeupgradedbyre-conductoringandpartialpolereplacement.
5.10.4 SouthWestland33kVNetwork
MuchofthenetworkinSouthWestlandwasconstructedatthesametimeasthatinNorthWestlandandthesamecommentsapplytobothareas.
SouthWestlanddoeshavesomeuniquefeatures,withthefullyinsulatedoverheadcableroutesaroundLakesWahapoandMapourika,requiringspecialmanagement.
184 WESTPOWERASSETMANAGEMENTPLAN2012-2022
TheMountHercules line,withanageof34years,hasbeen refurbishedover the last fouryearsdue to thedeteriorationofpolesandconductors.ThislineprovidesanessentiallinktoSouthWestland,thusdemandingprioritywithinmaintenanceprogrammes.
WiththeadditionoftheFoxGlacier33/11kVsubstationonthenetworkin2003,the11kVlinefromFranzJoseftoFoxGlacierwasupratedto33kV.Thislinehadmajorrefurbishmentworkcarriedoutatthistimeandshouldnotneedanyfurthermajormaintenanceworkforsomeyears.
5.10.4.1Maintenance
Routine Patrols and Inspections
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
Inadditiontopatrols,adetailedinspectionofthislineistobecarriedoutonarollingfive-yearbasis,covering20%oftheroutelengthperyear.Duringtheinspection,everyaspectofthelineischecked.TheaimistoidentifyanddocumentallcomponentsthatdonotmeetWestpower’sstandards.
Allpolehardwarewillbeincludedintheinspections.
Aregularannualthermographicsurveywillbecarriedoutontheselinestomonitortheconditionofjoints.
5.10.4.2Faults
TheleveloffaultsinthisareaissimilartothatinNorthWestland.Itmaybereasonablyargued,however,thattheincidenceofheavyrain,strongwindsandlightningisslightlyhigherthaninotherareas.
5.10.4.3RepairsandRefurbishment
AlllinerepairsarecarriedouttotherequirementslaiddowninWestpower’slinemaintenancestandards.Thesearebasedoninternationalpracticecombinedwithlocalknowledgeandlegislativerequirements.
5.10.4.4Enhancement
AstheloadinSouthWestlandrises,itwillbenecessarytoprovidemorecapacitybetweenHarihariandWhataroatomeetthesubstantiallyincreasedloadbeingsuppliedsouthofWhataroasubstation.Themaximumacceptableloadonthiscircuitwithoutincurringexcessivevoltagedropis2.0MVA.Thisgiveslittlemarginwhensupplyingthepresenttouristseasonpeakloadof1.6MVA.Additionalreactivesupporthasbeeninstalledalongwiththeinstallationof33kVregulatorsatHarihari in2004toovercomeunacceptablevoltageregulation,particularlywhenWahapopowerstationisnotrunning.AstheloadcontinuestogrowinSouthWestland,adecisionwillneedtobemadeonwhentoincreasethesubtransmissionvoltagefrom33kVto66kV.ThelinefromArahuratoHarihariwasoriginallybuiltasa66kVlinebytheNewZealandElectricityDepartmentinthemid-1960s,andwasthenleasedtoWestpowerforoperationat33kVin1993beforefinallybeingsoldtoWestpowerin2001.Itisthereforerelativelyeasytoreliventhelineat66kVinthefuture.
Ofcourse,thiswillalsomeanthatzonesubstationsatRossandWaitahaneedtobeupgradedtorunat66kVandanew66/33kVsubstationmustbeestablishedatHarihari.
5.10.4.5Development
Nomajordevelopmentworkisplannedonthisnetworkwithintheplanningperiod.Anydevelopmentthatdoescomeaboutwillprobablybedrivenbycustomerrequirements.
NETWORKDEVELOPMENT 185
5.10.5 Other33kVNetworkProjects
Table5.29summarisesthesubtransmissionprojectsforthisplanningperiod.
5.11 Distribution Assets
TheseassetscomprisethemajorityofWestpower’snetworkbydistanceandvalue.Asalogicalresultofthis,theassettypealsoaccountsforthegreatestshareofmaintenanceandenhancementexpenditure.
Table 5.29 - Sub Transmission Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
D Amethyst33kVConnec-tionLine 50 0 0 0 0 0 0 0 0 0
40005 RPL HKK-WTHPoleUpgrade 780 0 0 0 0 0 0 0 0 0
40010 RPL GYM-KUM66kVcctPoleReplacement 40 42 45 48 50 54 57 60 64 68
RPL Mapourika,Replacesubstandardpoles 0 0 20 21 22 24 25 27 28 30
40006 RPL ReplaceWaitangitaroaRivercrossing 43 0 0 0 0 0 0 0 0 0
40013 RPLSubtransmissioncon-demnedpolereplace-
ment30 33 33 33 33 15 15 15 15 15
40012 RPL ReplaceWaihoRiverCrossing 50 0 0 0 0 0 0 0 0 0
40011 RPL WarrensPaddock-Re-placeStructures 5 50 0 0 0 0 0 0 0 0
50002 E HKK-WTHConductorUpgrade 1800 0 0 0 0 0 0 0 0 0
10002 I ArnoldDobson33kVLinePoleReplacement 20 21 22 24 25 27 28 30 32 34
10012 IWeedSprayAccess
TracksandVariousLineRoutes
60 64 67 71 76 80 85 90 96 101
10006 IGeneralMaintenance
ofsubtransmissionlines(IS&T)
70 74 79 83 88 94 99 105 112 118
10011 IRiverProtectionWorksforSubtransmission
Lines50 53 56 60 63 67 71 75 80 84
10001 I AccessRoadMainte-nance 44 47 49 52 56 59 62 66 70 74
10004 ICoronaDischargeTestingatVariousSubtransmis-
sionLines5 5 6 6 6 7 7 8 8 8
10013 I SubtransmissionCros-sarmReplacement 25 25 25 25 25 10 10 10 10 10
10014 I AnalysisPortaSCANResults 3 3 3 4 4 4 4 5 5 5
Total 3075 417 405 427 448 441 463 491 520 547
186 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table5.30summarisesthedistributionprojectsandprogrammesforthisplanningperiodbycategory.
5.11.1 ReeftonArea
ThemainfeedersintheReeftonAreahavebeencompletelyreplacedoverthelasttenyears,withtheexceptionofpartsoftheReeftonTownshipandInangahuatotheIronBridge.
5.11.1.1Maintenance
Routine Patrols and Inspections
The2012-13financialyearwillseethecontinuationoftheconditionassessmentprogramme.Eachline(feeder)istobeinspectedonarollingfive-yearbasis,covering20%oftheroutelengthperyear.Duringtheinspection,everyaspectofthelineischecked.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
5.11.1.2Faults
FaultsintheReeftonarea,likemanyothers,aredependentonclimaticconditions.
Treeshavebeenamajorprobleminthisarea,particularlyontheGarvey’sCreekline,whichrunsthroughheavilyforestedareas,includingapineplantation.Amajortree-trimmingprojectin1998,coupledwithharvestingofmaturepinetreesinthepineplantation,hasreducedthisrisk,butitisstillconsiderable.
AfaultbasewillbemaintainedintheReeftonareacontractedtoElectroNetServicesfortheforeseeablefuturetominimisetherepairtimesthatareinvolvedduringoutage.
5.11.1.3RepairsandRefurbishment
The condition assessment project discussed previously is likely to highlight several components requiringreplacementonthose lines.Thiswillbehandledbya livelinerefurbishmentprogramme including individualpole,crossarm,insulatorandconductorreplacementwhererequired.
5.11.2 GreymouthArea
This is the largestareawithinWestpower’sdistrictandalso involves thegreatestdiversityof line typesandconditions.
5.11.2.1Maintenance
Routine Patrols and Inspections
The2012-13financialyearwillseethecontinuationoftheconditionassessmentprogramme.Eachline(feeder)istobeinspectedonarollingfive-yearbasis,covering20%oftheroutelengthperyear.Duringtheinspection,everyaspectofthelineischecked.
Table 5.30 - Distribution Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 1186 1203 1228 1232 1289 1337 1359 1414 1465 1505
Faults 324 343 364 386 409 434 460 487 516 548
Repairs 50 53 56 60 63 67 71 75 80 84
Replacement 435 325 110 110 110 110 110 110 110 110
Enhancement 0 50 50 50 0 0 0 0 0
Development 14 15 16 17 18 19 20 21 22 24
Total 2009 1989 1824 1855 1889 1967 2020 2107 2193 2271
NETWORKDEVELOPMENT 187
AsfortheReeftonarea,itisexpectedthatthiswillformthebasisofarepairprogrammeinvolvingindividualcomponentreplacementsthroughouttheplanningperiod.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
Aregularannualthermographsurveywillbecarriedoutonselectedhigh-densitylinestomonitortheconditionofjoints.
5.11.2.2Faults
FaultsintheGreymouthareaarenormallycausedbywindandlightning.
Treeshavebeenamajorprobleminthisarea,andaregulartree-trimmingprogrammecarriedoutatafeederlevelwillcontainthis.
ThebaseforWestpower’scontractorElectroNetServicesislocatedinGreymouth,andthiswillcontinuetoserveasafaultbaseforthearea.
5.11.2.3RepairsandRefurbishment
PreviousinspectionprojectshavehighlightedseveralcomponentsrequiringreplacementontheNelsonCreek,Blackball,HaupiriandKoparalines.
Anon-goingprogrammetoreplaceveryoldservicepoleswillcontinueasrequired.
5.11.2.4Replacement
WithseverallineswithintheGreymouthareaandsurroundingdistrictsreachingtheendoftheireconomiclives,projectshavebeeninitiatedtoreplacetheselines.Someprojects involvethereplacementofconductor,andpoles,whileotherswillonlyseethepolesbeingreplaced.
5.11.2.5Enhancement
AsforReefton,itispossiblethatunanticipatednewindustrialloadcouldtriggertheneedtoenhancethenetwork.Notwithstandingthis,thenetworkisrelativelystrongintheGreymouthandlowerGreyValleyareas,withsupplyfrommajorsubstationsatDobsonandGreymouth,andrelativelynewfeedersemanatingfrombothsites.
5.11.2.6Development
NomajordevelopmentprojectsareplannedfortheGreymoutharea.
5.11.3 HokitikaArea
TheoverallconditionofdistributionlinesintheHokitikaisverygood,withalmostall linesconstructedusingeitherconcreteortreatedwoodpoles.
5.11.3.1Maintenance
Routine Patrols and Inspections
A condition assessment programmewill be continued to identify substandard components or constructionmethods.
SimilartothatintheReeftonarea,itisexpectedthatthiswillformthebasisofarepairprogrammeinvolvingindividualcomponentreplacementsthroughouttheplanningperiod.Aftertheinitialinspection,thelineistobeinspectedonarollingfive-yearbasis,covering20%oftheroutelengthperyear.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
188 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.11.3.2Faults
FaultsintheHokitikaareaarenormallycausedbywindandlightning,withtreesfallingthroughthelinealsobeingacommonoccurrence.
AfaultbasewillbemaintainedintheHokitikaareaandcontractedtoElectroNetServices.
5.11.3.3RepairsandRefurbishment
Anon-goingprogrammetoreplaceveryoldservicepoleswillcontinueasrequired.
5.11.3.4Enhancement
Apartfromthespecificprojectsdiscussed,thereisnogeneralenhancementprogrammeplannedforHokitika.
5.11.3.5Development
The66/11kVHokitikasubstationprovidesastrong11kVbusneartothemajorloadsinHokitika,andthereforeremovesaneffectivevoltageconstraintthathasexistedforseveralyears.Thisallowsmajornewloadsintheareatobesuppliedwithoutsignificantdevelopmentofdistributionlineinfrastructure.
Ofcourse,anymajorloadseithersomedistancefromHokitikaorsomedistancefromtheassociateddistributionlineswillrequirenewlinedevelopment.
5.11.4 SouthWestlandArea
ThedistributionnetworkinSouthWestlandiscontainedinpocketsbasedaroundWaitaha,Harihari,WhataroaWahapo,FranzJosefGlacierandFoxGlaciersouthtoParinga,andisgenerallyingoodcondition.
5.11.4.1Maintenance
ThelinesaroundWaitaha,HarihariandWhataroahavebeensubstantiallyrebuiltoverthelasttenyearsandaregenerallyinexcellentcondition,requiringlittleplannedmaintenancework.
Routine Patrols and Inspections
TheOkaritoline(fromtheWahaposubstation)isawoodpolelineconstructedinthe1970s.Althoughthislineisinreasonableconditionforitsage,itwillnowrequireahigherlevelofinspectionandservicingasitreachesmid-life.
Asforotherareas,itisexpectedthatthiswillformthebasisofarepairprogrammeinvolvingindividualcomponentreplacementsthroughouttheplanningperiod.
Thelineistobeinspectedonarollingfive-yearbasis,covering20%oftheroutelengthperyear.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
5.11.4.2Faults
FaultsintheSouthWestlandareaarenormallycausedbywindandlightning.
AnotablefeatureofSouthWestland,particularlytheWhataroaarea, istheincidenceofverystrongeasterlywinds. This can, at times, result in outages as branches andother debris gets caught up in the distributionnetwork.
AfaultbasewillbemaintainedintheHarihariareaandcontractedtoElectroNetServices.
5.11.4.3RepairsandRefurbishment
Anongoingprogrammetoreplaceveryoldservicepoleswillcontinueasrequired.
NETWORKDEVELOPMENT 189
Any poles identified as reaching replacement criteria as a result of the pole inspection programmewill bereplacedasrequired,butthesearenotexpectedtocompriseasignificantnumberbecauseoftheageinvolved.
5.11.4.4Enhancement
AsmanyofthedistributionlinesintheSouthWestlandareahaverecentlybeenrebuiltorupgraded,thereisunlikelytobearequirementforcapacityenhancement.Thereisapossibilitythatsomesmallareasmayrequirethiswork,however,asaresultofin-filldevelopment.
5.11.4.5Development
Extensionofthe11kVundergroundnetworkislikelyinFranzJosefasthetownexpands.Amajornewresidentialsubdivisionprojectisunderway,butcurrentindicationsarethatitcouldbedevelopedinapiecemealfashionoverseveralyears.
Table5.31detailstheplannedexpenditureovertheAMPperiodforeachoftheabovedescribedprojects.
Table 5.31 - Distribution Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
E LightConductorRe-placement 0 50 50 50 0 0 0 0 0
41061 RPLMawheraitiThomp-
sonsRoad,11kVPoleReplacement
25 0 0 0 0 0 0 0 0 0
41002 RPL Blackball-AtarauRd-11kVPoleReplacement 80 0 0 0 0 0 0 0 0 0
41016 RPLKumaraJunctiontoKumara-11kVLine
Replacement80 0 0 0 0 0 0 0 0 0
41061 RPLNelsonCreekStateFarm,Re-routeandReplace
11kVLine10 80 0 0 0 0 0 0 0 0
41065 RPL RemovalofSeaviewFeeder 0 85 0 0 0 0 0 0 0 0
41062 RPL S670,Ahaura-Relocate11kVLine 35 0 0 0 0 0 0 0 0 0
41060 RPL GarveysCreek11kVPoleReplacement 45 0 0 0 0 0 0 0 0 0
41063 RPLParkSt-BonarDrive11kVOverheadtoUG
Conversion10 50 0 0 0 0 0 0 0 0
41064 RPL ReplaceCondemnedDistributionPoles 150 110 110 110 110 110 110 110 110 110
11003 I PurchaseofAerialPho-tography 25 5 5 5 25 25 25 25 25 5
11001 I FitPoleCapstoSoft-woodPoles 2 2 2 0 0 0 0 0 0 0
11005 I RiverProtectionWorksforDistributionLines 66 70 74 50 53 56 60 63 67 70
11008 I DevelopNetworkStan-dards 20 20 10 0 0 0 0 0 0 0
11006 I AnalysisofNetworkComponents 10 11 11 12 13 13 14 15 16 17
11011 I 11kVCrossarmreplace-ments 50 50 50 50 50 50 25 25 15 15
190 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.12 Reticulation Assets
Westpower owns a diverse range of reticulation assets, ranging frombrand new underground subdivisions,throughto50-year-oldoverheadwoodpolelines.
Tables5.32and5.33summarisetheplannedexpenditureovertheAMPperiodbycategoryforthereticulationassets.
5.12.1 ReeftonArea
TheReeftonareacomprisesamixtureofrelativelynewundergroundconstructionandveryoldoverheadwoodpolelines,withverylittleinbetween.OneadvantageofthisareaisthatitiswellawayfromtheseacoastandsufferslessfromtheeffectsofcorrosionthanmostotherareaswithinWestpower.Forthisreason,theoverheadlinescanstillbeinserviceableconditionatanolderagethaninotherareas.
Table 5.32 - Reticulation Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 234 245 245 235 189 180 191 203 215 227
Faults 22 23 25 26 28 29 31 33 35 37
Repairs 20 21 22 24 25 27 28 30 32 34
Replacement 90 27 29 30 32 20 21 22 24 25
Development 0 50 0 0 0 0 0 0 0 0
Total 366 366 321 315 274 256 271 288 306 323
Table 5.33 - Reticulation Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
12015 RPL KaiataLVLineRelocation 40 0 0 0 0 0 0 0 0 0
D CowperSt-DevelopLVLink 0 50 0 0 0 0 0 0 0 0
12005 RPL ReplaceCondemnedReticulationPoles 50 27 29 30 32 20 21 22 24 25
I Hokitika,HampdenSt-RemoveLV 0 0 0 0 0 0 0 0 0 0
12009 I PillarBoxReplacement 22 23 25 26 28 10 11 11 12 13
12008 I ReplaceLVLinks 5 5 6 6 6 7 7 8 8 8
12001 I DataCollectionofLVCircuits 25 25 25 5 0 0 0 0 0 0
12007 I Retrofitstreetlightswithindividualfusing 15 15 5 5 0 0 0 0 0 0
12014 I Replacecondemnedreticulationcrossarms 45 47 47 47 0 0 0 0 0 0
Total 202 192 137 119 66 37 39 41 44 46
Table 5.31 - Distribution Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
11012 I AnalysisPortaSCANResults 15 16 17 18 19 20 21 23 24 25
11013 I PortaSCANXBSLease 21 21 21 26 26 26 26 26 28 28
Total 644 570 350 321 296 300 281 287 285 270
NETWORKDEVELOPMENT 191
5.12.1.1Maintenance
Routine Patrols and Inspections
Aswiththedistributionlines,the2012-13financialyearwillseethecontinuationoftheconditionassessmentprogramme.Eachline(feeder)istobeinspectedonarollingfive-yearbasis,covering20%oftheroutelengthperyear.Duringtheinspection,everyaspectofthelineischecked.
Asforotherareas,itisexpectedthatthiswillformthebasisofarepairprogrammeinvolvingindividualcomponentreplacementsthroughouttheplanningperiod.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
5.12.1.2Faults
Faultsarelimitedtotheoccasionalsubstationfuseblowingorthefailureofapole,eitherduringhighwindsorwhenhitbyavehicle.Faultstaffintheareaareabletohandlethesefaultslocally.
5.12.1.3RepairsandRefurbishment
Anypolesidentifiedasreachingreplacementcriteriaasaresultofthepoleinspectionprogrammewillbereplacedasrequired,andifthelevelinparticularsectionsoflineexceeds50%ofthelinevalue,thiswillbeupgradedtoareplacementprogrammeforthatsection.
Itisexpectedthatmostremedialworkwillbeaccomplishedthroughsimplecomponentreplacement.
5.12.1.4Replacement
DuetopreviousreticulationlineupgradesintheReeftonarea,replacementsarenotrequiredinthisfinancialyear.Theon-goingconditionassessmentprogrammemayidentifyreplacementsforlateryears.
5.12.1.5Enhancement
Nomajorenhancementprogrammesareplannedforthisarea.
5.12.1.6Development
TherearenosignificantdevelopmentworksplannedfortheReeftonarea.Anydevelopmentthatdoesoccurwillbeonthebasisofnewcustomerrequirements.
5.12.2 GreymouthArea
The comments that applied toReefton reticulationassets apply also toGreymouth, except that the relativeamountofveryoldwoodpolelinesisgreatlyreduced.Thereasonforthisisthemajorreplacementprogrammecompletedinthe1990sasdiscussedinSection3.3.4.1.
5.12.2.1Maintenance
Routine Patrols and Inspections
AswithReefton,adetailedconditionassessmentprogrammewillbecontinued.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
5.12.2.2Faults
Faultsarelimitedtotheoccasionalsubstationfuseblowingorthefailureofapole,eitherduringhighwindsorwhenhitbyavehicle.
Faultstaffintheareaareabletohandlethesefaultslocally.
192 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.12.2.3RepairsandRefurbishment
Any poles identified as reaching replacement criteria as a result of the pole inspection programmewill bereplacedasrequired.Ifthelevelinparticularsectionsoflineexceeds50%ofthelinevalue,thiswillbeupgradedtoareplacementprogrammeforthatsection.
Itisexpectedthatmostremedialworkwillbeaccomplishedthroughsimplecomponentreplacement.
5.12.2.4Enhancement
AsmostofthereticulationintheGreymouthareahasrecentlybeenrebuilt,thereisunlikelytobearequirementforcapacityenhancement.There isapossibility thatsomesmallareasmayrequire thiswork,however,asaresultofin-filldevelopment.
5.12.2.5Development
NewsubdivisionsofteninvolvethedevelopmentofreticulationnetworksthatarehandedovertoWestpoweroncompletion.Inmostcases,thedeveloperbuildsthesetoWestpower’sstandards.
5.12.3 HokitikaArea
MostofthereticulationinHokitikahasbeenundergroundedaspartofmajorreplacementprogrammesinthe1980s.Asresult,theseassetsareinexcellentcondition.Onlyasmallnumberofpocketsofoverheadreticulationremain,andthosethatdoareconcretepolelines,alsoingoodcondition.
5.12.3.1Maintenance
Routine Patrols and Inspections
Noplannedinspectionsareplannedontheundergroundreticulation.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
5.12.3.2Faults
Faultsarelimitedtotheoccasionalsubstationfuseblowingorthefailureofapole,eitherduringhighwindsorhitbyavehicle.Faultstaffinthearea,areabletohandlethesefaultslocally.
5.12.3.3RepairsandRefurbishment
Itisexpectedthatmostremedialworkwillbeaccomplishedthroughsimplecomponentreplacement.
5.12.3.4Enhancement
AsmostofthereticulationintheHokitikaareaisalreadyundergroundwithsignificantsparecapacity,thereisunlikelytobearequirementforcapacityenhancement.
NofurtherundergroundingworkisplannedunlesssubsidisedbythelocalDistrictCouncilortheenduser.Anexceptiontothisisthecasewhereasmallsectionofoverheadlineisreplacedinanotherwiseundergroundarea,forinstance.
5.12.3.5Development
NewsubdivisionsofteninvolvethedevelopmentofreticulationnetworksthatarehandedovertoWestpoweroncompletion.Inmostcases,thedeveloperbuildsthesetoWestpower’sstandards.
NETWORKDEVELOPMENT 193
5.12.4 SouthWestland
MostofthereticulationinthetownshipsofHarihari,FranzJosefandFoxGlacierwasundergroundedaspartofmajorreplacementprogrammesinthe1980s.Asaresult,theseassetsareinexcellentcondition.Onlyasmallnumberofpocketsofoverhead reticulation remain,and those thatdoare concretepole lines, also ingoodcondition.
5.12.4.1Maintenance
Routine Patrols and Inspections
Noinspectionsareplannedontheundergroundreticulation.
Faultpatrolsandfaultrepairsarecarriedoutonanas-requiredbasis.
5.12.4.2Faults
Faultsarelimitedtotheoccasionalsubstationfuseblowingorthefailureofapole,orwhenapillarboxishitbyavehicle.Faultstafffromthearea,areabletohandlethesefaultslocally.
5.12.4.3RepairsandRefurbishment
Itisexpectedthatmostremedialworkwillbeaccomplishedthroughsimplecomponentreplacement.
5.12.4.4Enhancement
Noenhancementprojectsareplannedforthisarea,asthereisamplecapacitygenerallyavailable.
5.12.4.5Development
NewsubdivisionsofteninvolvethedevelopmentofreticulationnetworksthatarehandedovertoWestpoweroncompletion.Inmostcases,thedeveloperbuildsthesetoWestpower’sstandards.
5.13 Services
In general, Westpower does not carry out maintenance on customer-owned service lines. These are theresponsibilityofthecustomertomaintainandtheycanuseanycompetentcontractortodoso.Thereareseveralexceptionstothisgeneralrule,however,including:
• Replacementofblownservicefusesduetofaults;
• Repairofsubstandardservicelineswherethesewereneverbroughtuptostandardpriortotransferringtothecustomer;
• ReplacementofservicepolesonthestreetwherethesewerepreviouslysharedwithTelecomandarenowsubstandard;
• Repairstonetworkconnectionequipment;
• Repairstoservicespansacrossroadreserves.
Financialcontrolproceduresmeanthatonlyapprovedworkiscarriedout,andthatthecustomerwillberequiredtopayformostworkoncustomer-ownedservicelines.
194 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table5.34summarisestheplannedexpenditurebycategoryforservice-relatedprojectsduringtheAMPperiod.
Theon-goingreplacementofrewireablefuseswithHRCtypesaspartofLVreplacementprojectshassignificantlyreducedthenumberofprematureservicefusefailures,whichshouldbereflectedinareducedcostoffaultwork.
Servicelinesaregenerallyownedbytheendcustomerand,assuch,arenotmaintainedbyWestpower.However,as discussed above, there are some notable exceptions to this and these create amaintenance liability forWestpower.
Table5.35liststheplannedexpenditureforserviceprojectsovertheAMPperiod.
5.14 Zone substations
Table5.36summarisestheplannedexpenditurebycategoryforzonesubstationsprojectsduringtheAMPperiod.
5.14.1 Inspections,ServicingandTesting
Westpower’s station equipment is to be routinely inspected, tested and serviced in accordance with therequirements of Westpower’s maintenance standards relevant to the actual equipment. These standardrequirements, which define the scope and frequency of work, are reflected in maintenance schedules forindividualstations.
Preventativemaintenanceplans (PMs)havebeenprepared foreachstationasset typeset toa frequencyasdeterminedbyWestpower’smaintenancestandardsforthatspecificassettype.
JobplansareattachedtoeachPMdetailingtheworkplanforthemaintenancerequired.
Table 5.35 - Service Projects ($’000)
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
63001 D NewServiceConnec-tions 75 80 84 89 95 100 106 113 120 127
13002 RPL ServicePoleReplace-ment 60 64 67 71 76 80 85 90 96 101
13001 I Greymouth,UpgradeUnderverandaLighting 11 12 0 0 0 0 0 0 0 0
Total 146 156 151 160 171 180 191 203 216 228
Table 5.34 - Service Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 65 69 60 64 68 72 76 81 86 91
Faults 84 89 94 100 106 112 119 126 134 142
Repairs 6 6 7 7 8 8 9 9 10 10
Development 85 90 94 99 105 110 116 123 130 137
Replacement 60 64 67 71 76 80 85 90 96 101
Total 300 318 322 341 363 382 405 429 456 481
Table 5.36 - Zone Substation Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 645 706 777 873 823 867 911 959 1007 1057
Faults 12 14 15 16 17 18 19 20 21 22
Repairs 94 99 104 109 114 120 126 132 139 146
Replacement 668 620 173 348 286 245 25 761 761 321
Enhancement 36 0 0 0 0 0 315 0 0 0
Total 1455 1439 1069 1346 1240 1250 1396 1872 1928 1546
NETWORKDEVELOPMENT 195
Theintervalsvaryaccordingtotheequipmentanditslocation.Specialinspectionsandtestsarealsoincludedinmaintenanceschedulesormaybearrangedasrequired.
Workidentifiedasaresultoftheroutineinspectionsandtestsisbudgetedforasrepairsandrefurbishment.
5.14.1.1StationInspectionsandTesting
Westpower’sstationmaintenance involvesageneralmonthlystation inspection inaccordancewithspecifiedprocedures,fromwhichreportsarederived.OtherstationinspectionsincorporateannualThermovision,coronadischarge,partialdischargeinspections,fireprotectionandsecurity.
5.14.1.2Switchgear
Oil-insulatedswitchgearisregularlyinspectedandtheoilischangedasnecessarydependingontheresultsofbreakdowntests,orwhenthereareobviousvisualsignsofhighcarboncontent.Extraservicingiscarriedoutwheretheswitchgearhassustainedahigherthannormallevelof“heavy”faults.
Maleandfemalecontactsarecheckedforwear,anddressedorreplacedasnecessary.
VacuumorSF6gasinsulatedswitchgearundergoesregularvisualinspectionincludingchecksofSF6gaspressure.
Abaselineultrasonicdischarge investigationwas carriedout early in 1999 for substationswith11kV indoorswitchgear,andthishasformedthebasisforfuturestudies,whicharecarriedoutatregularintervals.
Thermovisionandpartialdischargeinspectionsarecarriedoutonallswitchgearonanannualbasis.
5.14.1.3PowerTransformerServicingandTesting
As part of Westpower’s maintenance programme, all major power transformers have an annual minormaintenanceservicewhichencompassesavisualinspection,routinediagnostictestsandminorrepairworkinaccordancewithWestpower’sstandardswhichincorporatemanufacturers’recommendationsandWestpower’sexperience.
Ingeneral,maintenanceonthetransformersconsistsofmaintainingoilwithinacceptabledielectricandaciditystandards,patchingupcorrosion,fixingoilleaksandannualdiagnostictestsontheinsulatingoil.Inaddition,theunitsfittedwithOLTCsrequireperiodicinspectionofthetapchangers,andthecontactsaredressedorreplacedasnecessary.AdditionalremedialworkrequiredoutsidethescopeofthemaintenancecontractisreferredtoWestpowerforfurtheractionandbudgetedasrepairsandrefurbishment.
5.14.1.4OilTesting-OilConductivityandDissolvedGasAnalysis
Over the last sevenyears,all zonesubstationshavehadDissolvedGasAnalysis (DGA) tests carriedout,andthesehaveidentifiedpotentialproblemsthatneedmonitoring.ThiswillbefollowedupbyfurtherannualoilconductivityandDGAtestsuntiltrendsarereliablyestablished.Oncethisisdone,theperiodwillbereviewed,possiblyonanindividualunitbasis.
Costingforminormaintenanceisverydependentonlocationandhasbeenbasedonthepresentmaintenanceexpenditure.
Costingformajormaintenance,e.g.OLTCs,isnotonlydependentonthelocationofthesitebutalsotheusageandtypesofunit.Someunitshavetobeservicedeverytwoyearsandotherseverysixyears.
5.14.1.5StructuresandBuswork
Theroutinemaintenanceofstructures,busworkanddisconnectorsisusuallyperformedsimultaneouslywhenaparticularcircuitorsectionofbusisreleasedfromservice.
196 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Disconnectorsarescheduledforservicingeveryfouryearsbutthismaybeextendedwhenthereareoperationaldifficulties in gettingamaintenanceoutage. The servicing is non-invasiveand is generally limited to checks,adjustments,lubrication,corrosioncontrolandcleaning.
Busworkandassociatedhardwareisinspectedandmaintainedwithdisconnectors,andincludescheckingandcleaningofinsulators.Atsiteswhicharesubjecttoatmosphericpollution,insulatorcleaningmustbedonemorefrequentlythanusual.Structuresaremaintaineduptoamaximumintervaloffouryears,andworkislimitedtocorrosioncontrol,generalcheckingoffixingsandremovalofanydebris.Woodpolesaresubjecttoacheckforsignsofrotting.Ithasbeendecidedthatformoststations,earthtestingcanbecarriedouteveryfiveyears,andthiswillbecomethepracticeinfuture.
5.14.1.6InstrumentTransformers
AspartofWestpower’smaintenanceprogramme,allinstrumenttransformershaveanannualminormaintenanceservice which encompasses a visual inspection, routine diagnostic tests and minor repair work. Additionalremedialwork required is outside the scopeof themaintenance contract and is referred toWestpower foraction.
5.14.1.7OtherStationEquipment
Thenewbatterybanksarevirtuallymaintenance-free,andonlyabasicinspectionandchargercheckisnecessary.
Fireprotectionandsecurityalarmsystemsaretobeinspectedeverythreemonthsandservicedannually.Otherswitchyardequipmentsuchaslocalservicetransformers,surgediverters,cables,etc.aremaintainedasnecessarywhentheassociatedcircuitistakenoutofservice.
5.14.2 MaintenanceWorks
Thefollowingisasummaryofallmaintenanceworks(I,S&T)tobecompletedinzonesubstationsinthenext12months.Theseareallon-goingbudgetsthatarecarriedoutforthedurationoftheoverallAMPperiod.
14014: Carry Out Thermovision Inspections of Zone Substation Equipment - $7,000
To identify high resistant joints present in zone substations, a Thermovision inspection programme is to becarriedoutatallzonesubstations.Strategiclinesshallalsobeinspectedonarotationalbasis,witheachlinebeingreviewedeverythreeyears.
14015: Corona Discharge Testing at Various Zone Substations - $14,000
To identify any failing insulation in zonesubstations, a Corona Discharge inspectionprogrammeistobecarriedouteverytwoyearsat all zone substations. Strategic lines shall alsobeinspectedonarotationalbasis,witheachlinereviewedeverythreeyears.
14017: Update Zone Substation Drawings and Filing System - $25,000
Fundshavebeenallocatedtoupdatethebacklogof Station drawings and develop a new filingsystem/audittrailforallfuturedrawingupdates.
ThermovisionInspectionPhoto
NETWORKDEVELOPMENT 197
14019: Oil Filter and Dry Out System for Transformers - $26,000
Anumberof thezonesubstationTransformershavemoisture ingresswhichseverely shortens their life.Theportablefilteranddryoutsystemistobemovedaroundthezonesubstationtransformerstoremovemuchofthismoistureviaonlinefiltering.
14020: Perform Oil Tests at Zone Substations (DGA) - $26,000
Anenhancedbaselineanalysisoftransformeroilconductivityanddissolvedgaseswillbecontinuedthisyeartogainabetterunderstandingoftheassets.
14024: Operator Training, Site Inductions and Site Familiarisation - $14,000
Afundhasbeenmadeavailableforoperatortraining,sitefamiliarisation,inductions,etc.atZonesubstationsandremotelocationsinthenetwork.
14027: Purchase of Portable Earths and Authorisation - $14,000
Ensureanadequatesupplyofportableearthsandpermitequipmentrequiredforoperatingtobeavailableonsite.
14029: Westpower Store – Storage of key assets in a controlled environment - $11,000
CarryoutastudythisyeartodeterminerequirementsforstoringWestpowerassetsinacontrolledenvironment.Studytoinclude–listofassetsandlocation,database,controlledprocedureforbookingin/outassets,locationofstore,indoor/outdoortemperaturecontrolledenvironment.
14031: Zone Substation – Landscaping and beautification - $14,000
Thisisanongoingprojectwhichincorporates,asthetitlesuggests,landscapingandgardeningworkaimedatimprovingtheamenityvaluesatWestpower’szonesubstationsites.
14032: Zone Substation – OLTC and Regulator maintenance - $75,000
Aplannedmaintenance/refurbishmentcyclehasbeendevelopedforallOLTCandregulatorassetstoprolongthelifeofthesecrucialassets.Fundshavebeenmadeavailablefortheongoingcostsrequiredeachyear.
14034: Zone Substation – Transformer refurbishment and maintenance - $50,000
Aplannedmaintenance/refurbishmentcyclehasbeendevelopedforallzonesubstationtransformerassetstoprolongthelifeofthesecrucialassets.Fundshavebeenmadeavailablefortheongoingcostsrequiredeachyear.
14035: Zone Substation – Building maintenance - $41,000
Thisisanongoingprojectwhichcanincludebuildingmaintenancesuchascladdingrepairs,spoutingrepairsetc.onallofWestpower’szonesubstationbuildings.
14037: Zone Substation – WMS relocation, site installation, disconnection costs - $27,000
ThisisanongoingprojectwhichincorporatesasthetitlesuggestsWMSrelocation,transportcosts,installationanddisconnection.
14040: WMS (Mobile Substation) Storage - $14,000
CoveredstorageisrequiredtoprotecttheWMSfortheperiodswhenitisnotinuse.
198 WESTPOWERASSETMANAGEMENTPLAN2012-2022
14041: Zone Substation Preventative Maintenance - $43,000
Four-yearlypreventitivemaintenanceplanshavebeendevelopedforsubstationdisconnectors,BUSsections,etc.toprolongthelifeofthesecrucialassets.Fundshavebeenmadeavailablefortheon-goingcostsrequiredeachyear.
5.14.3 FaultRepairs
Equipmentfailuresoccurrandomlyandwithoutwarning,andrangefromasimplecircuitbreakermechanismfailureduetoabrokencirclip,toacostlytransformerwindingfailure.Thecostbudgetedisthecosttorestoresupplyor the service following the failure,not the costof any repairworkafter supplyor servicehasbeenrestored.
It isestimated that thereareapproximately twosuch faultspermonth. It isexpected this frequencywillbereducedasaged/defectiveequipmentisrefurbishedorreplaced.
Theprojectedexpenditureisbasedonactualexpenditureincurredinrecentyears.Itisnotpracticabletoallocateprojectedexpenditureagainsteachsubstationassetcategory,giventherangeoffaultswhichcanoccur.
5.14.4 PlannedRepairsandRefurbishment
Thisareaofexpenditureincludescorrectiveworkidentifiedfollowinginspectionsandtests,andwhileundertakingroutinemaintenanceorfollowingequipmentfailures.Themagnitudeandcostsoftheworkcanvarygreatly.
Theplannedexpenditurealsoincludesthecostofmaterialsandspares.
Westpowerhasformulateditsreplacementprogrammebasedonthecriteriabelow.
5.14.4.1PowerTransformers
Themajorcausesofpowertransformerfailuresarewindingandinternalconnectionfaults.Thesearecaused,ingeneral,byelectricalcauses,e.g.throughfaultsorlightningstrikes.
Theothermajor internalmaintenanceonapowertransformer isoil refurbishmentanddesludging,which iscarriedoutasrequiredbasedonoilaciditytestresults.ItisnotexpectedthatthiswillberequiredonanyofWestpower’sunitswithintheplanningperiod.
Atmidlife,afulldry-outandcoreretightenisrecommended.
5.14.4.2RadiatorReplacement
Radiatorreplacement isonlycarriedoutoncoolerswherethedesignof theradiatorsorextentofcorrosionmeansrepairscannotbecarriedoutsatisfactorily.
Thecorrosionoccursafter20ormoreyearsofageintransformersincorrosiveenvironments(suchascoastal).The radiators are replaced only once in the life of a transformer. Only two ofWestpower’s current powertransformersmeetthiscriteria.
5.14.4.3Repainting
Paintingiscarriedoutonaregularbasisataperiodofgenerallybetween10and15years,dependingonsiteconditions.
5.14.4.4OtherEquipment
Ongoingrepairsarerequiredtoavarietyofotherstationequipmentincludingportableearthingequipmentandbatterybanks.
NETWORKDEVELOPMENT 199
5.14.4.5CircuitBreakers-Outdoor
InlinewiththepracticeofoverseasutilitiesasreportedbyCIGRE,Westpowerhasapolicy,subjecttoproject-specificeconomicanalysis,ofreplacementratherthanlifeextensionofagedordeficientbulkoilandminimumoilcircuitbreakersbymajorrefurbishment.
Circuitbreakersarealsoreplacedforthefollowingreasons:
• Wheretheyhavehighmaintenancecosts;
• Wheretheyareunreliableduetoanincreaseddefectrate;
• Whereasystemnoderequiresamaintenancefreecircuitbreaker;
• Wheremaintenanceoutagescannotbetolerated.
Itisinternationallyrecognisedthat40yearsisgenerallythe“timeexpired”lifeofcircuitbreakers.Sometypeshaveaneconomiclifegreaterorlessthanthisfigure.Bulkoilbreakersgenerallyhavealongerlife,whileminimumoilbreakerstypicallylastonly30to35years.
Whileageisnotitselfcriteriaforreplacement,analysisbasedonthelikelytotaleconomiclivesforeachtype,makeandmodelofcircuitbreakerprovidesameansofassessinglikelyfuturereplacementrequirements.Thereplacementsthemselveswouldbedeterminedbysafety,economicsandreliabilityassessmentsatthetime.
5.14.4.6CircuitBreakers-Indoor
Metalclad switchgear deteriorates with age,resulting in aging of insulation materials, e.g.formationofvoidsandpenetrationofmoisture.Visible compound leaks and audible coronadischargeoftenaccompanythis.
Replacementisjustifiedprimarilyonreliability/risk of failure grounds and customer serviceoperating limitations. There is potential forexplosive failure, which occurs infrequently(approximatelyonesuchfailureeverytenyears).PreviousfailuresofSO-HImetalcladswitchgearhaveledtotheGreymouth11kVswitchboard,theonlySO-HItypeinWestpower’sarea,beingreplacedin2003.
Ascontractorsworkclosetotheequipmentandtheequipmentisoil-filled,thereisanincreasedriskofpersonalinjury.Overseasutilitieshaveadopteddesignssuchthatnewoil-filledequipmentisnotinstalledindoors,andblastwallshavebeeninstalledbetweenoldequipmentandplaceswherecontractorsarerequiredtoworkforextendedperiods.
ModernSF6/vacuumreplacementinstallationswithair-insulatedbuschambers,ratherthantheoldcompoundinsulatedtypes,andarevirtuallymaintenance-free.Thereisahighcostassociatedwithmaintenanceofoldoil-filledandcompoundinsulatedequipment,whichrequiresannualmajorserviceandfrequentfaultmaintenance.
ThetypicaleconomiclifeofWestpower’sindoormetalcladswitchgearinstallations(typically11kV)hasbeenassessedtobe50yearsbasedonpastexperience.Atpresent,onlyasmallpercentageareover20yearsold.
5.14.4.7Structures,DisconnectorsandBuswork
Westpower’spolicyofusingeithergalvanisedsteelorconcretesupportcolumnsinswitchyardsmeansthatthereisonlyminimalmaintenancerequiredforbuswork.
Figure5.37-CircuitBreaker-Indoor
200 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Disconnectorsarescheduledforreplacementwhentheydevelopahistoryofunreliabilityorfailures,whentheirmaintenancecostsbecomeunacceptablyhigh,orwhentheyareidentifiedasbeingelectricallyunder-rated.
AprogrammeiscurrentlyunderwaytoreviewtheconditionandsuitabilityofeachdisconnectorinWestpower’snetwork.Ithasbeenfoundthattheoldertypeofdisconnectorwithoutflickerarcinghornsisnotsuitableforuseinmainlineswhenparallelingoffeedersisinvolved,althoughtheyarestillquitesuitableforuseonspurlines.Areplacementprogrammeisinplaceand,forthepurposesofthisplan,acontingencysumhasbeenallowed.
5.14.4.8InstrumentTransformers
Aged instrumenttransformersareonlyreplacedwhentheyfail,orwhentheyareaboutto failasdiagnosedby testing.Theyare thenreplacedwithasimilarunit,usuallyaspare.Other replacementsoccurduringsitedevelopmentworksand,dependingonwhethertheconditionandratingsetc.ofthetransformeraresuitableforuseatanothersite,theymaybescrapped.
AttheGreymouthsubstation,the66kVinstrumenttransformerswillbereplacedovertimewithvandal-resistantunitsusingcompositeinsulatorsbecauseoftheriskoffailureduetoongoingvandaldamage.
5.14.4.9PowerTransformers
DobsonT6andFoxT1Transformersarenearingtheendoftheirserviceablelives.AsumforbothTransformershasbeenallowedtoreplacethesein2019/20and2020/21respectively.
Therearenoplanstoreplaceanyoftheotherexistingpowertransformersduringtheplanningperiod,basedontheageandconditionoftheunits.
Thereisaconcernthatanincreasedreplacementrequirementduetodeterioratingconditionwillberequiredwithinthenext20to30years,sincethetransformerspurchasedinthe1970sarelikelytobegintofailataround50yearsofage.
Regardlessofwhetherapre-emptivereplacementprogrammeisundertaken,itseemslikelythatunitswillfailatanincreasingrateinfuture,andthiswillforcereplacement.Providedsufficientdiagnostictestsareundertakento identify imminent failure andprovided some suitable spare units are available, this should not lead to anoticeabledecreaseincustomersupplyreliability,andcouldbeacost-effectivereplacementstrategyoption.
5.14.5 MaintenanceSummary
Insummary,thezonesubstationmaintenanceexpenditureisshowninTable5.36.
Thereareconsistentexpenditurerequirementsforpowertransformerrepairwork, involvingradiatorrepairs,repainting,repairstointernalconnectionsandoilrefurbishment.
Overall,otherstationexpenditureprojectionsaresimilartopresentexpenditurelevels,withsomechangesandtrendsforspecificassetsandactivitiesresultingfromtheAMPanalysis.
5.14.6 Enhancement
TheageprofileofWestpower’szonesubstationsissuchthatonlyminimalenhancementexpenditureisrequiredthroughouttheplanninghorizon.Thecapacityofalloftheassetsissufficienttohandlenormalexpectedloadgrowthoverthenexttenyears.
NETWORKDEVELOPMENT 201
Oil Interception Facilities
Oil interception facilities are installed tomeet environmental requirements under theResource Management Act. Previous policydid not set a cut-off criterion for the amountofoilatasitebeforeoilcontainmentfacilitieswereinstalled.Thishasnowbeensetat1500litresinlinewithTranspowerstandards,whichwillpossiblybethemeasureforwhatcouldbeconsidered“reasonablynecessary”intermsoftheAct.
5.14.7 Development
Alldevelopmentprojectsaredependenteitheronnewinvestmentagreementsbeingreachedwith large customers or a clear economicjustification.
TherearenodevelopmentprojectsplannedforthisAMPperiod.
Table5.39liststheexpenditureforthezonesubstationprojectsplannedforthisAMPperiod.
Figure5.38-OilInterceptionFacility
Table 5.39 - Zone Substations Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
EWaitahaZoneSubstation-PreparesiteforWMS
access36 0 0 0 0 0 0 0 0 0
54021 E
HokitikaProtectionUpgradeDesignand
InstallationandAsBuiltDrawings
0 0 0 0 0 0 315 0 0 0
44010 RPL BatteryReplacementProgramme 19 20 21 22 23 24 25 26 26 27
44015 RPL
WahapoZoneSubsta-tion-ReplaceCombiflexRelays,ProtectionSet-
tingupgrade
108 0 0 0 0 0 0 0 0 0
RPLWahapoZoneSubstation-ReplaceCB1&Protec-
tionRelay71 0 0 0 0 0 0 0 0 0
44020 RPLRapahoeZoneSubsta-tion-33kVdisconnectorupgrade(1002structure)
0 0 26 0 0 0 0 0 0 0
44022 RPLWhataroaZoneSubsta-tion-ReplaceCB1&
protectionrelay0 90 0 0 0 0 0 0 0 0
44023 RPLRapahoeZoneSubsta-tion-Replace11kVmetalcladswitchgear
0 0 126 0 0 0 0 0 0 0
44024 RPL
ArnoldZoneSubsta-tion-ReplaceCB3&4withVipers&upgrade
protection
0 0 0 300 0 0 0 0 0 0
202 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table 5.39 - Zone Substations Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
44025 RPLKumaraZoneSubstation-Constructanew11kV
switchroom400 360 0 0 0 0 0 0 0 0
RPLLongfordCornerreplaceregulatorwithsingle
phaseunits70 0 0 0 0 0 0 0 0 0
44028 RPLWhataroaZoneSubsta-tion-ReplaceCB1412withWVE38xtype
0 150 0 0 0 0 0 0 0 0
RPL
RossZoneSubsta-tion-ReplaceCB1&3withVipers&upgrade
protection
0 0 0 0 0 126 0 0 0 0
RPL RossZoneSubstation-T1protectionupgrade 0 0 0 0 0 95 0 0 0 0
44029 RPLWaitahaZoneSubstation-Replaceregulatorwith
singlephaseunits0 0 0 26 168 0 0 0 0 0
44030 RPLWaitahaZoneSubsta-tion-ReplaceCB1&ProtectionRelay
0 0 0 0 95 0 0 0 0 0
RPLCrondanun-ReplaceRegulatorwithnewsinglephaseunits
0 0 0 0 0 0 0 0 0
RPL FoxZoneSubstation-ReplaceT1(TX:2438) 0 0 0 0 0 0 0 0 735 0
RPL DobsonZoneSub-Re-placeT6(TX:2240) 0 0 0 0 0 0 0 735 0 0
RPLWhataroaZoneSubsta-tion-Replaceregulatorwithsinglephaseunits
0 0 0 0 0 0 0 0 0 147
RPLRossZoneSubstation-Replaceregulatorwithsinglephaseunits
0 0 0 0 0 0 0 0 0 147
IKumaraZoneSubstation66kVCBMaintenance
(3)0 0 0 90 0 0 0 0 0 0
IRapahoeSubstation-PaintGantrySteelwork
andReinsulate0 0 33 0 0 0 0 0 0 0
14014 ICarryoutThermovisionInspectionsofZoneSub-
stationEquipment7 8 8 9 9 10 10 11 11 12
14015 ICoronaDischarge
TestingatvariousZoneSubstations
14 15 16 17 18 19 20 21 22 23
14017 I UpdateZoneSubstationDrawings&FilingSystem 25 15 16 17 18 19 20 21 22 23
14019 I OilFilterandDryOutSystemforTransformers 26 27 28 29 30 32 34 36 38 40
14020 I PerformOilTestsatZoneSubstations(DGA) 26 27 28 29 30 32 34 36 38 40
NETWORKDEVELOPMENT 203
5.15 Distribution Substations
Table5.40summarisestheplannedexpenditurebycategoryfordistributionsubstation-relatedprojectsduringthisAMPperiod.
5.15.1 Inspection,ServicingandTesting
AllofWestpower’sdistributionsubstationsrequireregulartestingeveryfiveyearsforsafetyreasonsinaccordancewiththeElectricityRegulations.Atthesametime,thegeneralconditionofthetransformerischeckedandanoilsampletakentomonitortheinternalstateoftheunit.
Table 5.39 - Zone Substations Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
14024 IOperatorTraining,SiteInductionsandSite
Familiarisation14 15 16 17 18 19 20 21 22 23
14027 IPurchaseofPortable
EarthsandAuthorisationEquipment
8 9 10 11 12 13 14 15 16 17
14029 IWestpowerStore-Stor-ageofKeyAssetsina
ControlledEnvironment11 12 13 14 15 16 17 18 19 20
I ZoneSubstationBuildingClimateControl 0 0 0 0 0 0 0 0 0 0
14031 I ZoneSubLandscapingandBeautification 14 15 16 17 18 19 20 21 22 23
14032 I ZoneSubOLTC&Regula-torMaintenance 75 79 83 87 91 96 100 105 110 115
14034 IZoneSubstationTrans-formerRefurbishmentandMaintenance
50 53 56 59 62 65 68 72 76 80
14035 I ZoneSubstationBuildingMaintenance 41 43 46 48 51 54 57 60 63 66
14037 IWMSRelocation,SiteInstallation/Disconnec-
tionCosts,etc27 28 29 30 31 32 34 35 36 38
14040 I WMS(MobileSubsta-tion)Storage 14 15 16 17 18 19 20 21 22 23
14041 I SubstationPreventitiveMaintenance 43 46 49 52 55 58 61 65 69 72
Total 1099 1027 636 891 762 748 869 1319 1347 936
Table 5.40 - Distribution Substation Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 750 778 792 770 814 485 512 543 577 613
Faults 17 18 19 20 21 23 24 26 27 29
Repairs 10 11 11 12 13 13 14 15 16 17
Replacement 30 0 0 0 0 0 0 0 0 0
Enhancement 101 37 39 42 44 47 50 53 56 59
Development 90 95 101 107 114 120 127 136 144 152
Total 998 939 962 951 1006 688 727 773 820 870
204 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table5.41liststheexpenditureforthedistributionsubstationprojectsplannedforthisAMPperiodasdescribedabove.
5.15.2 FaultRepairs
Lightningdamageandingressofwatercausesmosttransformerfaults.
Overthelasteightyears,westpowerhashadaprogrammeofretrofittinglightningarrestorsonallsubstationsthatdonotyethavethesefitted,andthisisnowcompleted.Pastexperiencehasshownthatlightningarrestorsgreatlyreducetheriskoftransformerdamage.
Regular inspection of transformers will also reduce the number of failures due to water ingress caused bydeterioratione.g.rustytanks.
Minorrepairssuchasbushingreplacementscanbecarriedoutonsiteifnecessary,butmostfaultrepairsinvolvetheswappingofatransformerunitwithasparefromthestore.
5.15.3 PlannedRepairsandRefurbishment
Corrosionandresultingwatercontaminationoftheinsulatingoilindistributiontransformersisamajorconcern.Aprogrammeofidentifyingbadlycorrodedtransformertankshasbeeninstigated.
Onceidentified,thesetransformerswillberemovedforrepair,retankingorreplacementasdictatedbythestateandageoftheunit.
Majorrewindsoftransformersarenotundertakenunlessthetransformer’ssizeisover50kVAandthetransformerislessthantenyearsold.Thisisbasedoneconomics.
Table 5.41 - Distribution Substation Projects ($’000)
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
65003 D New11kVConnections 65 69 73 77 82 87 92 98 104 110
65002 D NewTransformerSites 25 26 28 30 32 33 35 38 40 42
55002 E IncreaseTransformerSiteCapacity(Uprate) 35 37 39 42 44 47 50 53 56 59
55001 E GreymouthCBDSubsUpgrade(BadgerLane) 66 0 0 0 0 0 0 0 0 0
45003 RPL S1544Otira-UpgradeLVpanel 30 0 0 0 0 0 0 0 0 0
15006 I Sub(Site)Upgrades 348 369 391 414 439 100 106 112 119 126
15003 I ReplacementofLiveLineTaps 10 10 10 10 10 3 3 3 4 4
15002 IHokitika-RemovePilotConductorfromSubs
andPillarBoxes5 15 15 0 0 0 0 0 0 0
15004 I Installationofearthstir-rupstodropoutfuses 5 5 6 6 6 0 0 0 0 0
15012 IDistributionSubInspec-tions-Testingofsub
earthsetc130 138 146 155 164 174 184 195 207 220
15007 IUpgradeS634TudorSt-newpadandreconfig-
ureLV20 0 0 0 0 0 0 0 0 0
15008 I InstallJanitzaMDI’s 27 27 0 0 0 0 0 0 0
15009 I RelocateSubfusesfor11kVspurs 50 50 50 0 0 0 0 0 0 0
Total 816 746 758 734 777 444 470 499 530 561
NETWORKDEVELOPMENT 205
5.15.3.1OilRefurbishment/Desludging
Oilrefurbishmentisplannedfortendistributiontransformersperyear.
5.15.4 ReplacementProgrammes
Thereisamajorprogrammeinplaceforreplacingoldertransformersthathavefailedasaresultofoldageorlightning damage. The transformer technician individually assesses each transformerwhen returned to thestore,andanappropriaterecommendationonreplacementorrepairismadebytheengineer.
Thisisameansofprudentlymanagingtheassetandensuringthatanappropriateageprofileismaintained.Adistribution transformer conditionmonitoringprogramme is about to be introduced,whichwill identify theconditionofthecurrentpopulationandprovidesasubstantialbasisforassessinglikelycostsinfutureAMPs.
Current levelsof transformerreplacementsareplannedtocontinue.Typicalprices fornewunits range from$3,000forsmallsingle-phaseunitsto$20,000forurbanpad-mounttransformers.
5.16 MV Switchgear
Table5.42summarisestheplannedexpenditurebycategoryforMVswitchgear-relatedprojectsduringthisAMPperiod.
5.16.1 Inspection,ServicingandTesting
Circuitbreakersaresubjectedtominorand/ormajormaintenanceroutinesinaccordancewiththerequirementsofWestpower’s maintenance standards. Fault maintenance is also carried out when a circuit breaker hascompletedaspecifiednumberoffaulttrippings.
Modernvacuumcircuitbreakersaresubjectedtominorservicesandconditionmonitoringtestsatfour-yearlyintervalsonly.Invasivemajorservicesarenotscheduledandwouldbecarriedoutonlyifrequiredasindicatedbyconditionmonitoringtests.
Aswithpowertransformers,therearetwolevelsofservicing:
• Minorservicing,involvingexternalservicing(non-invasive);
• Majorservicing,whichinvolvesinvasiveservicing.
Belowisalistofallmaintenanceworks(IS&T)tobecompletedforMVswitchgearinthenext12months.TheseareallongoingbudgetsthatarecarriedoutyearlyforthedurationoftheAMPperiod.
16002: Disconnector Maintenance and Operation Check Programme - $95,000
Reliableandsafeoperationofdisconnectorsisimperativeduringswitching.Somedisconnectorsbecomedifficulttooperate(e.g.padlockseizesup).Afive-yearlymaintenanceprogrammeisinplacetomaintainandtest-operateeachofthe400plusdisconnectors.
Table 5.42 - MV Switchgear Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 186 193 173 181 192 203 216 228 241 253
Faults 6 6 7 7 8 8 8 9 10 10
Repairs 44 47 50 52 56 59 63 66 70 74
Replacement 123 39 42 105 48 50 53 133 61 64
Enhancement 119 78 82 40 43 45 47 50 52 54
Development 344 97 60 148 68 72 76 168 85 89
Total 822 460 414 533 415 437 463 654 519 544
206 WESTPOWERASSETMANAGEMENTPLAN2012-2022
16003: Recloser Maintenance – Protection, batteries, etc. - $32,000
Network reclosers require regularprotectiontestsand reclosermaintenanceasdeterminedbyWestpower’sstandards to ensure reliable and safe operation.Ongoing funds have beenmade available to complete thismaintenance.
16004: Perform Partial Discharge Tests on Network Switchgear - $14,000
Carryoutpartialdischargetestsonselectednetworkswitchgear.Thisisanongoingprojecttoassistintheearlydetectionoffaults.
Table5.43liststheexpenditurefortheMVswitchgearprojectsplannedforthisAMPperiodasdescribedabove.
Table 5.43 - MV Switchgear Projects ($’000)
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
DAmethyst33kVCon-
nection-InterconnectorStructureandProtection
200 0 0 0 0 0 0 0 0 0
46002 RPL
ReplaceFaultyActua-tors-(EntecloadbreakswitchorHydraulic
actuator)
45 0 0 0 0 0 0 0 0 0
46003 RPL DisconnectorReplace-ments 32 33 35 38 40 42 45 48 51 54
46004 RPL RemotelocationsBatteryReplacement 6 6 7 7 8 8 8 9 10 10
RPL RingMainUnitReplace-ment(FoxHotel) 40 0 0 60 0 0 0 76 0 0
56004 EDistributionIntelligentFaultIsolationSystem-
Study/Design2 2 2 2 3 3 3 4 4 4
56008 E Fusingofspurlinesbyfeederclassification 40 42 44 0 0 0 0 0 0 0
E InstallAutomationtoVariousDisconnections 71 34 36 38 40 42 44 46 48 50
E FitEarthFaultIndicators 6 0 0 0 0 0 0 0 0 0
D Newmainlinereclosersites(Dilmans) 25 0 0 84 0 0 0 88 0 0
D NewSpurLineReclosersonvariousSpurLines 40 14 15 16 17 18 19 20 21 22
66005 D AutomateCapacitorsatvariouslocations 42 44 0 0 0 0 0 0 0 0
66007 D NewDisconnectors 27 29 31 33 35 37 39 41 44 46
66008 D NewgangedDDOfuseunitlocations 10 10 14 15 16 17 18 19 20 21
I UpgradeEarthingatDis-connectorLocations 0 0 0 0 0 0 0 0 0 0
16002 IDisconnectormainte-nance,OperationCheck
Program95 100 78 82 87 92 98 103 109 114
IRemotelocationsmain-tenance-Protection,
Batteries,etc32 33 35 38 40 42 45 48 51 54
16004 IPerformpartialdis-
chargetestsonNetworkSwitchgear
14 15 15 16 17 18 19 20 21 22
Total 727 362 312 429 303 319 338 522 379 397
NETWORKDEVELOPMENT 207
5.16.2 FaultRepairs
5.16.2.1CircuitBreakers
Faultrepairstoswitchgeararecarriedoutasrequired,butasthepopulationofolderbulk-oiltypereclosersdiminishes in line with Westpower’s circuit breakerreplacement programme, the occurrence of thesefaultshasbeengreatlyreduced.
Failures in indoorswitchgeararealso relatively rare.With the planned upgrade of the indoor metalcladswitchgear at Rapahoe and Kumara in the not toodistant future, all ofWestpower’s indoor switchgearwillbeofayoungage,and isexpectedtoprovideareliableandsafeoperationforthisplanningperiod.
5.16.2.2Disconnectors
Disconnectorsnormallyfailduetodeteriorationoftheoperatingarmswithcorrosionorfromanarcdevelopingacrosstwoormorephases.Byidentifyingunder-rateddisconnectorsandreplacingthese,theincidenceofarcingfaultsshouldbereduced.Thepreventativemaintenanceprogrammefordisconnectorsisworkingverywellatidentifyingmostpotentialproblemsbeforetheyoccur.
5.16.3 PlannedRepairsandRefurbishment
5.16.3.1CircuitBreakers
Plannedrepairworkinrespecttocircuitbreakerswouldincludeadditionalcorrectiveworkandrefurbishmentidentified during routine services, inspections and tests or following failures. Refurbishment work plannedincludesoverhaulofdecommissionedcircuitbreakers,identifiedassparespriortoplacingtheminstorage.
5.16.4 ReplacementProgrammes
WestpowerhasdetermineditsreplacementprogrammeforHVswitchgearbasedonthefollowingcriteria:
• Safety-Whereequipmentpresentsahigherthannormalrisktopersonnelduringoperatingormaintainingtheequipmente.g.generictypesofagedbulkoilcircuitbreakerswithhistoryoffailures;Circuitbreakersthatrequirehandclosing.
• Technical suitability - This applies to equipment that is no longer suitable for its service application e.g.Disconnectorsandcircuitbreakersthatareunreliableorinconsistentinperformingtheirfunctionsduetoexcessivelywornmechanisms,equipmentwhichfailstomeetWestpower’sseismicrequirementsorUnder-ratedequipment.
• Economics-Thisiswherereplacementisjustifiedpurelyforeconomicreasons,e.g.equipmentisexcessivelyexpensive tomaintainor repair, thehigh costof sparesorwhere spares canno longerbepurchasedormaintenance-intensiveequipmentinstalledatasensitivesupplylocation.
5.16.4.1CircuitBreakers-Outdoor
InlinewiththepracticeofoverseasutilitiesasreportedbyCIGRE,Westpowerhasapolicy,subjecttoproject-specific economic analysis, of replacement rather than life extension of aged and/or deficient bulk oil andminimumoilcircuitbreakersbymajorrefurbishment.Circuitbreakersarealsoreplacedforthefollowingreasons:
• Wheretheyhavehighmaintenancecosts;
• Wheretheyareunreliableduetoanincreaseddefectrate;
Fig5.44-CircuitBreakers
208 WESTPOWERASSETMANAGEMENTPLAN2012-2022
• Where a system node requires amaintenance-free circuit breaker e.g.maintenance outages cannot betolerated.
Itisinternationallyrecognisedthat40yearsisgenerallythe“timeexpired”lifeofcircuitbreakers.Sometypeshaveaneconomiclifegreaterorlessthanthisfigure.Bulkoilbreakersgenerallyhavealongerlife,whileminimumoilbreakerstypicallylastonly30-35years.
While age is not itself criteria for replacement, analysis based on likely total economic lives for each type,makeandmodelofcircuitbreakerprovidesameansofassessinglikelyfuturereplacementrequirements.Thereplacementsthemselveswouldbedeterminedbysafety,economicsandreliabilityassessmentsatthetime.
Manyoftheexistingolderbulkoilreclosershavebeenreplacedwithmodernlow-maintenancevacuumcircuitbreakers.
Thecontinuingreplacementprogrammeforoutdoorcircuitbreakershasresulted intherebeingnobreakersover25yearsofage.
5.16.4.2AndelectUnits
Westpower has experienced two serious failures of Series Iversions of these oil switch units during routine operation, andtheyareconsideredtoconstituteaserioushealthandsafetyrisk.Areplacementprogrammewasinstitutedfiveyearsagotograduallyreplaceall theseunitswithnewSF6RMUtype.Atpresent, thereare no series 1 type oil switch units in the network.Westpowerstill has series 2 type oil filled Andelect switch units,which havebeen assessed as safe to operate. There are three of these unitsremaining,withnoimmediateplansforreplacement.
5.16.5 Enhancements
Several automated disconnections/sectionalisers (used to isolatefaults on rural lines) are reaching the end of their economiclife and are becoming unreliable. This results in prolonged andmorewidespread power outages than are necessary during faultconditions.
It is no longer possible to source replacement parts formany oftheseunits,andthemaintenancecostshaveincreasedsignificantly.
Areplacementprogrammehasbeeninplaceforthelasttwoyearsandisplannedtobecompletedthisyear.
Figure5.45-RingMainUnit
NETWORKDEVELOPMENT 209
5.16.6 Development
Reclosers are pole-mounted circuit breakers, which automaticallyisolate a faulted section of the line from the rest of the network(Figure5.35).Wherealargeradialnetworkexists,reclosersareoftenfittedonspur lines toprevent themain line fromtrippingoutduetoa spur line fault. Theadditionofextra reclosers to thenetworkimprovessystemreliabilityandfaultselectivity.Justificationofeachprojectiscarriedoutonacase-by-casebasis.
SupplytotheWestCoast ingeneral isvoltage-constrainedandthisis partly due to the long inductive transmission lines.Whena lineoutageoccursduetofaultsorplannedmaintenanceevents,voltagecollapsecanoccurunlesssignificantsupport isavailable from localgeneration;this,inturn,maydependonwateravailability.
Amethyst Hydro is planned to be completed this year, which willimprovereliabilityofsupplyandtheabilitytocarryoutmaintenanceintheSouthWestlandarea.
VoltagesupportutilisingcapacitorsontheWestpowernetworkhashadvaried success.Atnight,when the load is low, capacitorsmaynotberequired,butarerequiredatpeak loadtimes.Astudy is tobecarriedoutthisyeartofindacost-effectivesolutiontoautomatetheswitching inandoutofexistingcapacitorbanksas required toprovidethisvoltagesupport.
5.17 SCADA, Communications and Protection
Table5.47summarisestheplannedexpenditurebycategoryforSCADA,commsandprotectionrelatedprojectsduringthisAMPperiod.
5.17.1 PeriodicInspections,ServicingandTesting
5.17.1.1SCADASystem
Theintegrityofthemainhardwareandsoftwaresystematthecontrolroomisofthehighest importancetotheongoingmanagementandsafetyof thegridnetwork.Westpower’sassetmanagementstaffmanagethecomputersystemandmaintaintheoperationalstateofthesoftwareandhardwaresystems.Thisisa24-hourtask,withstaffoncall ifrequiredtoensurehighavailabilityofequipment.Themaincomputerhardwareandsoftwareareprotectedbyamaintenancecontractwiththesupplier.
AnapprovedcontractorwillmanageallcommunicationandSCADAequipmentexternaltothecomputersystem.Thisprovidesforcontinuousmaintenanceandfastresponseforfaultrepairs.
Figure5.46-RemoteControlledDisconnector
Table 5.47- SCADA and Comms Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 360 387 383 380 390 417 423 418 432 443
Faults 45 46 48 49 51 52 54 55 57 59
Repairs 45 46 48 49 51 52 54 55 57 59
Replacement 60 35 92 115 70 244 278 215 215 295
Enhancement 55 95 75 56 141 111 131 61 115 81
Development 405 191 172 189 152 82 104 86 88 108
Total 970 800 818 838 855 958 1044 890 964 1045
210 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.17.1.2Communications
Everyassetistobeinspectedsix-monthlyandservicedonanannualbasis.Thesix-monthlyinspectionis,asfaraspossible,non-intrusive.Noadjustmentsaremadeuntilitemsareoutoftoleranceorperformanceisaffected.
Antennasupportstructures,e.g.woodpoles,towersandmonopoles,areinspectedeverytwoorthreeyears.
AntennaearetobecheckedannuallywithaSpectrumAnalyser.
5.17.1.3Protection
Thepolicyinthisareaistomaintainprotectionschemeswithalternatemajorandminorserviceseverytwoyearsoneachcircuit.
It should be noted that “maintenance” on protection equipment is essentially “recalibration/testing” ratherthantheconventionalviewofmaintenance,whichwouldimplyreplacementofconsumableparts.Protectionmaintenanceismainlyrequiredtoreaffirmthattheprotectioniscalibratedwithintoleranceandwilloperatewhencalledupontodoso.
Thereareinternationaltrendstowardsreducedmaintenance.Typically,intervalsarebeingincreasedtobetweenthreeandfouryearsinotherutilitiescomparabletoWestpower,particularlywheremicroprocessor(numerical)protectionsystemsareused.Theseprotectionshavein-builtself-testingandmonitoringroutineswhichreducethenecessityformanuallydrivenmaintenancetesting.
Anewfully-automatedprotectionrelaytestsetisbeingintroducedtofacilitatemaintenancetesting.Thiswillbeusedforcommissioningofnewprotection(developmentsandenhancements)aswellasmaintenance.
5.17.2 PlannedRepairsandRefurbishment
5.17.2.1Communications
Westpowermaintainscommunicationsassetsatapproximately28basesites,83pole-toporRMUsitesandon10repeatersites.Theplannedrepairandrefurbishmentestimatesarebasedonpastexpenditure.
Contractmaintenancetechniciansareexpectedtorespondtoapproximately12majorfaultsperannum.
5.17.2.2Protection
Theprotectionexpenditureplannedoverthereviewperiodismainlyinthefollowingareas:
• Replacementofoutdoorjunctionboxes;
• Replacementofagedfeederprotectionandcontrols;
• Replacementoflead-acidbatterieswithsealedcells;
• Seismicstrengtheningofprotectionpanels;
• Seismicrestraintsforbatteries;
• InstallationofDirectCurrent(DC)monitoringanddistributionpanels.
5.17.3 ReplacementProgrammes
5.17.3.1Communications
Communicationsequipmenthas,ingeneral,ashorterlifeexpectancythanheavyelectricalequipment.Typicallyelectronicequipmentreachestechnicalobsolescencein5-10yearsalthoughtheequipmentcan,ingeneral,besupportedinservicefor10-15years.
NETWORKDEVELOPMENT 211
5.17.3.2SCADA
Aswithall computer-based systems, it isexpected that severalupgradesof theoperating system, software-applicationsandhardwarewillberequiredthroughouttheplanningperiod.
TheSCADAmastersystemneedstobekeptuptodatewithsoftwarechangestoenablethesystemtohavemaximumfunctionalityandtoextendthelifeofthecurrentsystem.
5.17.4 MaintenanceSummary
Table5.20atthebeginningofthissectionsummarisesexpectedsystemmaintenanceexpenditure.
5.17.5 Enhancement
ThereareseveralsmallupgradejobsplannedfortheSCADA,communicationandprotectionsystemsthroughouttheplanningperiod.
5.17.5.1RemoteControlledDisconnectors
Withtheadventofindustry-wideperformancemonitoring,WestpowerisnowbeingbenchmarkedagainstotherELBsintermsofsystemreliabilityandcontinuityofsupply.Furthermore,customersarebecomingmoreawareoffaultoutages,partlyduetotheincreaseinthenumberofelectronichomeappliancesandtheresultingrelianceonacontinualsupplyofelectricity.Forthesereasons,itisbecomingincreasinglyimportanttocutdownonfaultrestorationtimes.
Onewaytodothisisbyautomatingremoteairbreakswitches.Thisgreatlyreducesthetravellingtimerequiredforafaultworkerduringsectionalisingoffaultedlinesections.Thisalsomeansthatfewerstaffarerequiredtoisolatethefault,reducingtheoverallcostoffaultrestoration.
Table 5.48 - SCADA and Communications Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
67037 D Amethyst33kVConnec-tion-Communications 100 0 0 0 0 0 0 0 0 0
D ALDCommsUpgrade 0 0 0 40 0 0 0 0 0 0
67026 D BlueSpurRepeaterSiteDevelopment 30 20 0 0 0 0 0 0 0 0
D MtBonar,UpgradeRepeaterSite 0 0 80 50 50 0 0 0 0 0
D MtKakawau 0 0 0 0 20 0 0 0 0 0
67036 D Commstonew11kVswitchroomKumara 40 0 0 0 0 0 0 0 0 0
67013 DPaparoaProposalto
moveallaerialtosingletower
15 10 0 0 0 0 0 0 0 0
67009 D Whataroacommunica-tions 30 20 0 0 0 0 0 0 0 0
67018 D MeteringReading 10 10 10 10 11 11 11 11 11 11
67019 D VMWareServerConfigu-ration/Equipment 10 10 11 12 13 13 14 15 16 16
67011 D SCADAOffSiteBackup 5 5 5 5 5 5 5 5 5 5
67017 D 61850Rollout 10 11 11 12 13 13 14 15 16 16
67012 DSouthWestland,IP
ExpansionVHFDigitalRadio
70 40 0 0 0 0 0 0 0 0
212 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table 5.48 - SCADA and Communications Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
67014 DFastIPCommstoAllReclosersitesforDIFIS
Project20 20 20 20 20 20 20 20 20 20
67031 D
CommstoMVSwitch-gearDisconnectorAutomation&NewReclosers
30 20 20 40 20 20 40 20 20 40
67033 D CommstoAutomateCapacitors 15 15 15 0 0 0 0 0 0 0
67034 D CommstoRMU’s 20 10 0 0 0 0 0 0 0 0
E AtaruIPSwitch 0 0 0 0 0 0 0 0 0 8
57003 E MtBonarRepearer 4 4 4 5 5 5 5 5 6 6
E FibreLinktoGreymouthDepot 0 0 0 0 0 0 0 0 50 0
E ChapelStIPSwitch 0 0 0 0 0 0 0 0 0 8
E CommsModificationfornew66kVbay 0 0 0 0 0 0 20 0 0 0
E HKKProtectionupgrade 0 0 0 0 0 0 50 0 0 0
E RapahoeCommsUp-grade 0 0 20 0 0 0 0 0 0 0
E CommstoupgradedRossZoneSub 0 0 0 0 0 50 0 0 0 0
E WahapoCommsUp-grade 0 40 0 0 0 0 0 0 0 0
57001 E ModificationofLoadControlSytem 10 10 10 10 12 12 12 12 13 13
57022 E SCADAMasterStationEnhancement 10 10 10 10 12 12 12 12 13 13
57025 E ICCPFeed 10 10 10 10 10 10 10 10 10 10
E WaitahaDevelopment 0 0 0 0 40 0 0 0 0 0
E CommstoupgradedWaitahaZoneSub 0 0 0 0 40 0 0 0 0 0
57011 E SCADACriticalSpares 15 15 15 15 15 15 15 15 15 15
57012 E IPFireWall/Security/RemoteSecureaccess 6 6 6 6 7 7 7 7 8 8
RPL PAP-ALDRadioLink 0 0 0 20 0 0 0 0 0 0
RPL APA-ATUmicrotikhoriz 0 0 0 0 15 0 0 0 0 0
RPL AtaruSEL2411 0 0 0 0 0 0 0 0 0 5
RPL PAP-ATUmicrotikvert 0 0 0 0 15 0 0 0 0 0
RPL PAP-ATURadioLink 0 0 0 0 0 0 0 0 0 80
RPL BlackwaterRadioLinks 0 0 0 0 0 0 0 0 0 30
RPL RlackwaterRouter 0 0 0 0 0 0 0 0 0 10
RPL RlackwaterCommsProcessor 0 0 0 0 0 0 0 0 0 20
RPL PAP-CHAPELmicrotikhoriz 0 0 0 0 10 0 0 0 0 0
RPL PAP-CHAPELmicrotikvert 0 0 0 0 10 0 0 0 0 0
RPL Dobsoncommunicationsprocessor 0 0 0 0 0 0 0 25 0 0
NETWORKDEVELOPMENT 213
Table 5.48 - SCADA and Communications Projects
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
RPL PAP-DOBSONRadio 0 0 0 0 0 0 0 70 0 0
RPL PAP-DOBSONFibreCable 0 0 0 0 0 0 0 20 0 0
RPL T6replacement 0 0 0 0 0 0 0 20 0 0
RPL T1replacement 0 0 0 0 0 0 0 0 20 0
RPL CommsProcessor 0 0 0 0 0 0 0 0 20 0
RPL GlobeSubstationcom-municationsprocessor 0 0 0 0 0 0 20 0 0 0
RPL RFN-GLBRadioLink 0 0 0 0 0 20 0 0 0 0
RPL GreymouthsubCom-msprocessor 0 0 0 0 0 0 0 0 0 20
RPL GreymouthsubRouterandSwitches 0 0 0 0 0 0 0 0 0 20
RPLWestpowerControltoGreymouthSubstation
FibreLink0 0 0 40 0 0 0 0 0 0
RPL HKK-PAPRadioLink 0 0 0 0 0 0 70 0 0 0
RPL LandingHilltoIGHRadioLink 0 0 0 0 0 0 0 0 0 70
RPL PAP-KumaraRadioLink 0 0 0 0 0 0 0 0 70 0
47018 RPL Longfordcornerregula-torreplacement 25 0 0 0 0 0 0 0 0 0
RPL IPSwitch 0 0 0 0 0 6 0 0 0 0
RPL PAP-NGHradiolink 0 0 0 0 0 20 0 0 0 0
RPL AllanBradleyPLC 0 0 0 0 0 8 0 0 0 0
RPL PikeSubstationIPSwitch 0 0 0 0 0 0 0 0 0 10
RPL SEL2032 0 0 0 0 0 0 0 0 0 20
RPL RapahoeIPSwitch 0 0 7 0 0 0 0 0 0 0
RPL RapahoeRadioLink 0 0 20 0 0 0 0 0 25 0
RPL ReeftonSubstationIPSwitch 0 0 0 0 0 0 8 0 0 0
RPL RFNBCLtoRFNSubRadioLink 0 0 0 0 0 0 50 0 0 0
RPL SEL2032s 0 0 0 0 0 0 20 0 0 0
RPL ReeftonVoiceRepeater 0 0 40 0 0 0 0 0 0 0
RPL Rosscommunicationsprocessor 0 0 0 0 0 30 0 0 0 0
RPL SCADAMasterStationReplacement 0 0 0 0 10 150 100 70 50 0
RPL GYMCHAPELdepotmicrotikhorz 0 0 0 15 0 0 0 0 0 0
RPL GYMCHAPELdepotmicrotikvert 0 0 0 15 0 0 0 0 0 0
RPL RippleMasterInjector 0 0 0 0 0 0 0 0 20 0
47010 RPL ReplacePLC/RTUUnits 10 15 15 15 0 0 0 0 0 0
47016 RPLCommstoMVSwitch-gearReplacement
Program25 20 10 10 10 10 10 10 10 10
Total 520 321 339 360 363 437 513 362 418 484
214 WESTPOWERASSETMANAGEMENTPLAN2012-2022
5.18 Distribution Transformers
The population of distribution transformers covers a diverse range of sizes, types and ages. As such, it isimportantthatacomprehensivemanagementplanisputinplace,astheconditionoftheassetisnotalwayseasilydiscernibleonanoverallbasis.
Westpower’s policy is to extend the life of distribution transformerswhere this is economically feasible. Insupportofthispolicy,manydistributiontransformersrunwellbelowtheirratedvaluesformuchofthetime,resultinginlonglivesforthecoresandwindings.Providedthatthetanksandoilarewellmaintained,theoverallunitmaybekeptinserviceforupto55years.Inthisway,themaximumreturncanbeleveragedfromthesehighvalueassets.
Table5.49summarisestheplannedexpenditurebycategoryfordistributiontransformer-relatedprojectsduringthisAMPperiod.
5.18.1 Maintenance
5.18.1.1RoutinePatrolsandInspections
Smallerpole-mounteddistributiontransformersareregularlyinspectedonarollingfive-yearbasisinconjunctionwithWestpower’ssubstationearthtestingprogramme.
Theinspectionincludeschecksfor:
• Tankcorrosion,
• Paintchips,
• Breakdown,
• Oilleaks,
• Insulatordamage,
• Breathercondition,
• Terminationfaults.
Wherepossible,theoillevelischeckedandrecorded,andifanoilsamplevalveisavailable(standardissueonallnewtransformers),asampleoftheoilistakenandcheckedfordielectricbreakdown.
Largerpole-mountandallpad-mountunitshaveMaximumDemand Indicators (MDIs)whichare readeveryquarter.Theseindicateloadingtrendstobemonitoredandallowforearlyinterventionshouldaunitbecomeoverloaded.
VerylargetransformersinareassuchastheCBDsofGreymouthandHokitikahaveannualthermographsurveyscarriedouttocheckthetankandterminationtemperatures,aswellastoidentifyanyotherpotentialhotspots.Anyindicationssuggestingthatthetransformerrequiresattentionresultsinprompton-siterepairs;ifthisisnotpossible,thetransformerisswappedwithaspareunitfromthestoreandsentbacktothecontractor’sworkshopforrefurbishment.
Table 5.49 - Distribution Transformers Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 95 101 107 113 120 127 134 143 152 160
Faults 3 3 3 4 4 4 4 5 5 5
Development 449 476 504 535 567 601 637 675 716 759
Total 547 580 614 652 691 732 775 823 873 924
NETWORKDEVELOPMENT 215
5.18.1.2Faults
Themajorityof faultsarecausedby lightningdamage; it isvery rare foraunit to failbecauseofoldageordeteriorationbecauseoftheregularinspectionandservicingcarriedout.
Mostfaultsarehandledbyswappingthetransformerwithaspareandsendingthedamagedunitbacktothetransformerworkshopforinspectionandrepair,orscrappingifthedamageistoosevere.
Anexceptiontothisisbushingfaultsonlargeunits,wherethebushingcanbeeasilyrepairedorreplacedon-site.
5.18.1.3RepairsandRefurbishment
Repairscanrangefromaminorpainttouch-uponearlierpaintedunitsthroughto insulatorrepairsandboltreplacements.Refurbishmentmayincludeoilchanges,rewindsandeventankreplacements.
Rewinds are only attempted on relatively modern units where modular replacement windings are readilyavailable.
Tanksareoftensubjecttocorrosion,especiallyinthecaseofolderpaintedunits.Atthesametime,however,theinternalcoreandwindingsmaybeinexcellentcondition.Forthisreason,tanksareoftenrepairedorreplacediftheunitisotherwiseingoodcondition.
Eachunitisassessedonitsage,conditionandservicehistoryindeterminingwhethertorepairorreplacetheunit.
5.18.1.4Replacement
AllreplacementunitsarepurchasedtoWestpower’spurchasingspecifications,whichprescribegalvanisedtanks,stainlesssteelfixingsandoilsamplingvalvestominimisethecostoffuturemaintenance.
5.18.1.5Enhancement
Littleenhancementworkiscarriedoutondistributiontransformers,astheseareessentiallyastandardmodulewithnocapacityforupgrading.Occasionally,duplexarcinghornsmaybefittedtoexistingunitswherelightningarrestorscannotbeused.
5.18.1.6Development
NewunitsarepurchasedtoWestpower’spurchasingspecificationsasrequired.IndependentcontractorsinstallingnewsubstationsforcustomersmayprovidenewunitsandhandthemovertoWestpoweroncommissioning,providedthattestresultsaresatisfactory.
Table5.50liststheexpenditureforthedistributiontransformerprojectsplannedforthisAMPperiodasdescribedabove.
5.19 Other
Westpower’s four ripple injection plants are all of the samemake (Enermet SFU-K series),making lifecyclemanagementeasiertoimplement.
Laterthisyear,wewillbeinstallingastand-alonerippleplantattheWahapozonesubstation.ThiswillbeinstalledintheexistingshedandwillbeusedonoccasiontoprovideripplecontroltotheSouthWestlandareawhenWahapogenerationisrunningislandedfromtheremainderofWestpower’snetwork.
Table 5.50 - Distribution Transfomers Projects ($’000)
ID Act Description 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
68001 D Purchaseofnewtrans-formers 449 476 504 535 567 601 637 675 716 759
216 WESTPOWERASSETMANAGEMENTPLAN2012-2022
ThisplantwillconsistofthebestavailablepartsfromthedecommissionedPlesseyTRseries75kVAplantsatReefton,GreymouthandHokitika.
Table5.51summarisestheplannedexpenditurebycategoryforthe“Other”relatedprojectsduringthisAMPperiod.
5.19.1 Maintenance
5.19.1.1RoutinePatrolsandInspections
Monthlychecksarecarriedoutaspartofregularzonesubstationvisits,whichincludethevisualinspectionsofthe:
• Converters,
• Couplingtransformers,
• Couplingcells,
• GPStimebasereceivers.
Everythreeyears,independentexpertsdetermineinjectionlevels,currentbalance,optimumtuningandloadsharingwithotherunitsduringafullinspection.
5.19.1.2Faults
Thesolidstateconstructionoftheinjectionplantsandthefactthattheyoperatewellbelowtheirmaximumpowerlevelsmeansthatfaultsareveryuncommon.
Onrareoccasions,thehigh-poweroutputtransistorsmayrequirereplacementorthelogicboardmayrequirerepair.Atothertimes,verminmaygetintotheHVcouplingcells,causingflashover.
The redundancybuilt into the injectionnetworkmeans that the failureof any singleplantwill not severelyimpactonoverallripplesignalpropagation,andfaultsareabletobehandledwithoutunduetimepressureonrestoration.
5.19.1.3RepairsandRefurbishment
Minor repairsare requiredon thecouplingequipmentandconverters fromtimetotimeasa resultof faultevents.
Thereisnoplannedrepairandrefurbishmentprogrammeplannedforthisequipment,whichisrelativelyyoungandingoodcondition.Itisexpectedthattheplantswillgiveatleasttenyearsoftrouble-freeservice.
5.19.2 Replacement
ReplacementofalloftheoriginalTRseriesunitsisplannedoverthenextthreeyears.
5.19.3 Enhancement
Thecapacityoftheexistingequipmentisfixedandprovidesampleroomfornetworkexpansion.Noenhancementworkisplanned.
Table 5.51 - Other Projects and Programmes ($’000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
IS&T 5 5 6 6 6 7 7 8 8 8
Faults 6 6 7 7 8 8 9 9 10 10
Replacement 1 1 1 1 1 1 1 2 2 2
Total 12 12 14 14 15 16 17 19 20 20
NETWORKDEVELOPMENT 217
5.19.4 Development
Nonewrippleplants(exceptWahapo,whichhasalreadybeenbudgetedfor)areexpectedtoberequiredfortheforeseeablefuture;however,allowancehasbeenmadeforunspecifieddevelopmentprojectsthatultimatelyturnupandrequireinclusionwithintheAMP.
AfullsummaryoftheexpenditurebyactivityandassettypeisavailableinSection7-FinancialSummary.
218 WESTPOWERASSETMANAGEMENTPLAN2012-2022
6.0 ASSET LIFECYCLE MANAGEMENT
6.1 Introduction
ThissectiondescribestheprocessesusedbyWestpowertomanagethelifecycleofitsassetsfromdesignandplanningthroughtodisposal.Atypicallifecycleofanyassetconsistsofthefollowingstages:
• Designandplanning,
• Acquisitionandinstallation,
• Maintenanceandoperation,
• Disposal.
Themaindriversforlifecyclemanagementare:
• Reliability/securityandqualityofsupplytomeetcustomerlevelsofserviceandcontractualobligations;
• Occupationalhealthandsafety toestablishasafeworkingenvironmentandcomplywithOSH legislativesafetyrequirements;
• Regulatorytomeetregulationsimposedbyexternalorganisations;
• Environmentaltocomplywithemissionregulationstoair,landandwater;
• Assetperformance/conditionuseofhistoricaldatatoassestheperformanceandconditionoftheassetsandpredictpotentialremaininglife;
• Costefficiencytoensurethatmaximumcostefficiencyisachievedinaccordancewithassetmanagementpolicy;
• CorporateimagetoensurethatanyactivitycarriedoutbytheAssetManagementteamandsubcontractorswillnotdamageWestpower’simage.
DetailsofprojectedoperatingexpenditureareincludedinSection5undertheappropriateassettype.Inthisway,thereadercanreadilyseethetotalprojectedcostsforeachassettype,alongwiththeOPEXandCAPEXbreakdown.
6.2 Maintenance and Operation
6.2.1 ReplacementvsMaintenanceTrigger
Westpowerhasapolicyofretiringolderassetsthathavereachedtheendoftheireconomiclifewherethereisnoeconomicmeansofprovidinglifeextension.Someofthetriggersthatwouldsuggestareplacementstrategybeemployedratherthanongoingmaintenancewouldinclude:
• Morethan50%ofalinesectionreachingreplacementcriteriawithinthefollowingfive-yearperiodwhenotherworkhastobecarriedoutonthatline;
• Technicalobsolescence;
• Healthandsafetyconcerns(e.g.oldoil-filledringmainunits);
• Difficultyinobtainingspareparts;
• Inabilitytomeetcurrentneeds.
Westpoweralsoexperiencesseverecorrosioninareasneartotheseacoast,anditisoftenmorecosteffectivetoinstallnewcorrosionresistantfittingsratherthancontinuingtorepairexistingfittings.
Thereisanaturalbusinessdrivertomaintainratherthanreplaceintheformoftaxbenefits,andthisprovidesacountervailingforcewhichensuresthatareasonablebalanceismaintainedbetweenthesetwoapproaches.
TheMaintenancetriggersareoutlinedinTable6.1.
ASSETLIFECYCLEMANAGEMENT 219
6.2.2 Maintenance
Maintenanceworkislargelybasedontheconditionoftheassets,asoutlinedinSection5.
ThescopeofworkplannedundereachmaintenanceactivityisquantifiedwhereverpossibletoassistinreviewingWestpower’sachievementinfutureyears.Theestimatedmaintenanceexpenditureisprojectedinthissectionand,where relevant, theconsequencesof theproposedmaintenanceprogrammesarenoted. It shouldalsobenotedthatanalysisofmaintenancestrategiesandprogrammesisanongoingprocess,andthemostcost-effectivemeansofmaintainingthesystemisconstantlyunderreview.Insomeinstances(e.g.polereplacement),furtherinvestigationandanalysisarerequiredtodetermineasuitablestrategy.
Themaintenancerequirementsareinfluencedbydevelopmentprojects,manyofwhich, iftheyproceed,willleadtodismantlinganddecommissioningofassetswhichwouldotherwiserequiresignificantrepairs.
The base-line planned maintenance expenditure projections assume, for consistency within this plan, thatdevelopmentprojectstakeplaceasprojectedinthissection.Itwillbenecessarytomonitorcloselythelikelihoodofeachprojectproceeding,andadditionalremedialworkwillneedtobeprogrammedifcertainprojectsdonotproceedoraresignificantlydelayed.
Table 6.1 - Maintenance Triggers by Asset Category
Asset Category Components Maintenance Trigger
Zonesubstations
Fences&enclosures MonthlychecksmadeoffenceswithZoneSubchecks,breakagestoberepaired.Maintenancefitterstomonitorcorrosionatgroundofgalvanisedsupporttypes.
BuildingsLandscaping.Exteriorofbuildingstobekepttidy,especiallygardensandlawn.
Foamsandwichtypebuildingstobewashedonanannualbasis.Itemsnotedthatneedrepairtohaveservicerequestraised.
Transformers AnnualDGAOilsampling.Monthlyzonesubchecks,includingBuchholzinspection,insulatorintegrity,nooilleaks,etc.
11kV&33kVswitchgear Monthlycheckofgaspressure,insulatorintegrity,etc.Maintenanceinlinewithmanufacturersmanual.
Instrumentation CheckcalibrationwithCBreleaseasabove,particularlytransducerinputstoSCADA.
Sub-transmissionlines&cables
Poles,arms,stays&bolts Evidenceofpolemovement.Evidenceofdecay/splittingoftimber.Evidenceoflightningdamage.
Pins,insulators&binders Evidenceofpincorrosion-rusting/neckingofthepins.Visiblyloosebinder.Visiblychippedorbrokeninsulators.
Conductor Evidenceof“birdsnesting”followingstrand/sbreaking.Electricalloadincreasingbeyondconductorcapacity.
LVlines&cables
Poles,arms,stays&bolts Evidenceofrot.Loosebolts,movingstays.Displacedarms.
Pins,insulators&binders Obviouslyloosepins.Visiblychippedorbrokeninsulators.Visiblyloosebinder.
Conductor Visiblycorroded,splayingorbrokenconductor.
Distributionsub-stations
Poles,arms&bolts Evidenceofdry-rot.Loosebolts,movingstays.Displacedarms.
Enclosures Visiblerust.Crackedorbrokenmasonryorfibreglass.
Transformer Excessiveoilacidity(500kVAorgreater).Visiblesignsofoilleaks.Excessivemois-tureinbreather.Visiblychippedorbrokenbushings.
Switches&fuses Coronadischargemonitoringannually.
Distributionlines&cables
Poles,arms,stays&bolts Evidenceofdry-rot.Loosebolts,movingstays.Displacedarms.
Pins,insulators&binders Evidenceofpincorrosion-rusting/neckingofthepins.Visiblychippedorbrokeninsulators.
Conductor Evidenceof“birdsnesting”followingstrand/sbreaking.Evidenceofvibration-fitdamper.
Ground-mountedswitches Evidenceofpincorrosion-rusting/neckingofthepins.LongrodtypeschalkingifEPDMtype.
11kVSwitchgear Coronadischargemonitoringannually.
220 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Repairs and Refurbishment
AlllinerepairsarecarriedouttotherequirementslaiddowninWestpower’slinemaintenancestandards.ThesearebasedoninternationalpracticecombinedwithlocalknowledgeandNewZealandlegislativerequirements.
6.2.2.1 Maintenance
Routine Patrols and Inspections
Aerialandgroundpatrolsofsubtransmissionlinesareperformedannually.Faultpatrolsandfaultrepairsarecarriedoutonanasrequiredbasis.
Thermographicsurveysarecarriedoutonanannualbasistocheckforhotjointsthatcouldleadtolaterfailure.
Thesesurveysarenormallycarriedoutattimesofhighloadsuchasthewinterperiodtoincreasethechancesofdetectingamarginaljoint.
Atree-trimmingregimehasbeenestablishedduetothehighgrowthexperiencedontheWestCoast.
Table6.2,showspatrolandinspectionfrequencies.
6.2.3 Replacements
Major Refurbishments
Itisnecessarytoretaininservicesomeolderlines,whichareinpooroverallcondition,andtheselinesrequireongoingrepairsandrefurbishment.
Majorrefurbishmentonalllinetypesisestimatedtoabsorbonlyasmallproportionofthetotalmoneyproposedtobespentonlineworkinanyyear.
Wood Poles and Crossarms
Itiscurrentlyprojectedthatapproximately 250poleswouldneedchanging overthenextyearinordertocopewithdefectsarisingontheexistingwoodpolelines.
Woodpolesarebeingchangedtoconcretepoleswhereverpossible,duetothe increasingpriceof importedhardwoodsfromAustralia.
Theuse of concrete poles leads to significant savings in ongoingmaintenance, increased line reliability andincreasedlineworkersafety.
WestpowernowspecifiesPurpleHearthardwoodforallcrossarmsthatareusedonitsnetwork,andtheseareexpectedtohavealongservicelife.
Table 6.2 - Routine Patrol and Inspection Frequencies
Voltage RoutinePatrol ConditionAssess-ment
ThermographicSur-vey
Corona Discharge-Survey *Vegetation Survey
33kV+ 6monthly 5yearly 2yearly 2yearly 2-5yearly
11kV asrequired 5yearly asrequired - 2-5yearly
400V asrequired 5yearly - - 2-5yearly
33kVHendrixCable Monthly 5yearly - 12monthly Monthly
*Note:Vegetationsurveydependantonenvironmentalfactors.
ASSETLIFECYCLEMANAGEMENT 221
Conductors and Accessories
Asapolicy,allreplacementACSRisbeingpurchasedwithagreasedcorewire.Wherecorrosionresistanceiscriticalincoastalareas,AAACisusedforitssuperiorcorrosionresistanceproperties.
Forlargerconductorswithanaluminiumcross-sectionalareaofover95mm2,WestpowerpolicyistouseAAACexclusively.
Insulators and Insulator Fittings
Earlierconcernsabout theconditionofanumberofEPDM33kVstrain insulatorshave largelyprovedtobeunfounded,andsoaplannedreplacementfortheseunitsisnolongerscheduled.
With theexceptionof a numberof glass insulatorson the SouthWestland33 kV line,which aredue tobereplacedaspartofthelineupgrade,allotherinsulatorsandfittingsaregenerallyingoodcondition.
6.2.4 RectifyingWestpowerAssets
Networkdefectdatacapturedinthefieldareincorporatedintothegeneralworkplanviarelevantprocesses.Althoughtheprimaryfocusoftheconditionassessmentprogrammeisthemonitoringofpoleandspanassets,allassettypesaretobeincludedinthenearfuture,witheachawardedequalconsideration.
Dependingonthepriorityoftheidentifieddefect,workcouldbecarriedoutimmediatelytorectifytheproblem;alternatively,thejobcouldbescheduledtobeundertakenatamoresuitabletime.
The statusof theworkordergenerated indicates the job’s completion, fromwhich regularauditsensureallfollow-upadministrationtasksarecompleted.
All assetdataare returnedwithanupdated “ConditionCode”. Theseare separatedandanalysed for actionwhereneeded.Belowisalistoftheconditioncodesandthecorrespondingactionthattakesplace:
Excellent: Nofurtheractionisrequiredontheseassets.
Good: Theseassetshavemorethantenyears,lifeexpectancyandwillbeassessedagainwithinthisterm.
Fair: Theseassetshavelessthantenyears,lifeexpectancyandwillbeassessedagainwithinthisterm.
Poor: Thisassetcouldlastuptofiveyears,however,itisinpoorconditionandfutureassessmentwillberequired.
Needs replacing:Anyassetswiththiscodearegroupedintoareasalongwithanyotherurgentworkrequired.Aworkorderisraisedfortheasset(s)tobereplacedassoonaspossible.
Red-tagged:Allred-taggedassetsareurgentlyinneedofareplacementandbecauseofthis,workordersareraisedindividuallyfortheseassetsforpromptaction.
Aswell as condition codes, a “work required” table isutilised todriveanymaintenanceor replacements toassets.Theworkrequiredtableissplitintotwocategories,“urgent”and“non-urgent”.
• Urgent work:isgroupedintogeographicalareas.AworkorderisthengeneratedforthisareaincludinganyassetsmarkedasNeedsReplacingorRedTaggedinthe“condition”attributeintheassetdata.Anyassetthatrequiresinstantactionwillhaveaseparateworkorderraisedinordertorectifythisissueassoonaspossible.
• Non-urgent work: isalsogroupedintoareasand,dependingonthesituation,aworkorderwillberaisedstraightawayortheworkissetasideforactionduringplannedoutagesorwhentimeallows.
6.3 Disposal
Decommissionedequipmentormaterialsareonlydisposedofwhentheyarenotrequiredascriticalsparesandthereisalowlikelihoodofthembeingrequiredinthefuture.
222 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Wheretheequipmentinvolvespotentiallyhazardousmaterials,thisisclearlystatedandtherecipientisrequiredtoprovidedocumentaryevidencethatanyfurtherdisposaliscarriedoutinanapprovedmanner.
Alldecisions totransferordisposeoffixedassetsmustbeauthorisedbytheGeneralManager–AssetsandEngineeringServices.TheGeneralManager–AssetsandEngineeringServicessignsaDisposal/TransferAuthorityRequest(DTAR)form.
Following authorisation, the appropriate networkmanager is responsible for the reallocation/disposal of allequipment.
ThesemanagersareresponsibleformaintainingaregisterofWestpowerassetsthatareavailablefordisposalortransfer.Thisinformationisusedtoenabletheeffectivereallocationofplantandequipmentwithinthenetwork.Importantly,this informationalsoenablesWestpowertoassessopportunitiestodefercapitalexpenditurebyreallocatingassetsbetweensites.
6.4 Major Maintenance Projects
6.4.1 ProjectName:GYM–KUM66kVcctPoleReplacement
ProjectCode: 40010
EstimatedCost: $685,000
StartDate: April2010
CompletionDate: March2021
The 23 km 66 kV subtransmission line from theGreymouthSubstation toTrustpower’sKumaraPowerStation(Figure6.1)wasbuilt in1977tocoincidewiththecommissioningoftheGreymouthSubstation.
OwnedbyWestpower,thelineisleasedtoTranspowerand,alongwiththe66kVcircuitfromDobson,providesn-1securitytothegreaterGreymoutharea.
The line was constructed using de-sapped, untreatedhardwoodpoles,mostofwhichare inagenerally faircondition,however,aprogressivereplacementplanhasbeen initiatedtoavoid large-scale failure.Aroundhalfofthepoleswerefittedwithaheatshrinkbandageinthe1990sand injectedwithafungicidalemulsiontheeffectivenessofthisprocessisunknown.
The pole replacement programme allows for thereplacement of six to tenpoles per annum.Althoughcondition is a major factor when determining whichpolesaretobereplaced,theconditionofmostofthepoles is similar, so other drivers may be considered.Landownerissuesorfactorssuchaspolestabilitymaydeterminewhichpolesarereplaced,
ThestandardWestpowersubtransmission17m12kNpre-stressedconcreteI-beampolearmlessconstructionisemployedformostofthereplacements,withporcelainstand-offinsulators;however,pi-polesmayberequiredfromtimetotime.ItwasintendedtoreplacetheexistingDogACSRconductorprogressivelybeginningin2012,withahighercapacityconductortoensurethelinewascapableofcarryinga35MWload.However,thisistobereconsideredintheupcomingyear,withtheoriginaldriversnolongerapparent.
ASSETLIFECYCLEMANAGEMENT 223
Anearthwireisinstalledtheentirelengthofthelineandwillremainaspolesarereplaced.
Approximately16%of the total numberofpoleson the linehavebeenreplacedtodate.
CompletionoftheprojectisexpectedinMarch2022.
Justification:
Theestimatedlifeofwoodpolelinesis45yearsaccordingtoWestpower’s asset management policies and this coincideswiththesamenumberusedintheODVhandbook.Therefore,thelinewillreachtheendofitsscheduledeconomiclifein2022;however,anumberofpolesarealreadyreachingreplacementcriteria.
Althoughthepolesareinreasonablecondition,toavoidmassfailure of poles on the line at the end of their serviceablelife, the line needs gradual replacement. This approachwillminimiseoutagetimesandallowcoststobeapportionedovermany years. As this line is leased to Transpower tooperateaspartofthenationalgridandamainsupplyintothegreaterGreymouthandsurroundingareas,itisimperativethatahigherlevelofreliabilitybemaintainedatalltimes.
AlternativeOptionsConsidered:
Alternativesolutionswereconsideredincluding:
• Replaceentirelinewhenreplacementcriteriaarereached;
• Ongoingbasicmaintenance;replaceonfailure.
Other options such as distributed generation demand sidemanagementandadditionalvoltagesupportarenotapplicableinthiscase,astheissueisoneofreliabilitywiththelinesupplyingthemainhuboftheWestCoast.
Forreasonsdiscussedearlier,itwasdecidedthatreplacingtheentirelineoverafewyearswasnotprudentduetocostsandtheriskofblackoutsshouldthelinebeoutofserviceforextendedperiodsthatcoincidewithafailureofthenortherncircuit.
Figure6.3-showsonexistingpole
Figure6.4-showsthenewconfiguration
224 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Ongoingbasicmaintenancewouldresultinsuboptimaloutcomes,asanincreasingnumberofcomponentswouldbegintoapproachfailurecriteriaandtheoverallcostofsuchapiecemealapproachwouldresultinasignificantlyincreasedfinalcostalongsideconsiderablyreducedreliability.
AstagedreplacementwasconsideredtobethemosteffectivemeansofmaintainingareliablesupplyofelectricitytotheGreymouthareaatthelowestoveralleconomiccost.
6.4.2 ProjectName:Replacecondemneddistributionpoles
ProjectCode: 11004
EstimatedCost: $2,962,000(overplanningperiod)
StartDate: April2000
CompletionDate: March2020
ManyofWestpower’slinesbuilt inthe1960sthroughtothelate1980swereconstructedutilisinghardwoodpoles,manyofwhichhadbeenpreviouslyused.Withtheexpectedlifeofahardwoodpoletobearound45years,dependingon thesurroundingenvironment,manyof thesepoleswill require replacementwithin theplanningperiod.Theconditionassessmentprogrammeistheprimarytoolusedtoidentifythosepolesneedingurgentreplacementandastheconditionassessmentprogrammehas intensified,so,too,hasthenumberof
polesidentifiedtobein“RedTagged”condition.
AsthegraphinFigure6.5indicates,manyofthe11kVhardwoodpolesfoundonthenetworkhavereached,orarereaching,therecognisedreplacementage.Acontingencysumhasbeensetasideforreplacementofsuchpoles,withmanybeingreplacedaspartofanentirelinesegment,whileothersinurgentneedofreplacementwillbereplacedindividuallyunderOPEX.Thesepolesarenormallyreplacedduringplannedoutagesoremployinglivelinetechniqueswherepossible.
Figure6.5-11kVHardwoodpolesAgeDistribution
2% 4%3%
9%
9%
15%
25%
8%
17%
8%
0-5 6-10 11-15 16-20 21-25
26-30 31-35 36-40 40+ UNKNOWN
ASSETLIFECYCLEMANAGEMENT 225
Individual11kVpolereplacementhasbeencarriedoutforanumberofyearsandtherateofsuchreplacementisexpectedtoincreaseintheupcomingyears.Theemphasisonpolereplacementhasshiftedfromthatofcapitalworks,whereanumberofpolesinalinewouldbereplaced,toamoretargetedprogramme,whichwillresultinincreasedindividualpolereplacementexpenditure.
Justification:
Westpower is veryproactive in identifyingand rectifyingdefectivepoleswithin thenetwork. In adhering torelevantregulations,Westpowermustensurethesepolesarereplacedinatimelymanner.Ifadefectivepoleisnotincludedinacapitalreplacementproject,itistobereplacedundermaintenanceworks.ThecondemneddistributionpolereplacementprogrammeisjustifiedthoughWestpower’sobligationtoprovideareliablepowersupplyandadheretoregulationsandactssuchastheHealthandSafetyinEmployment(HSE)act1992.
Alternativeoptionsconsidered:
Thecondemneddistributionpolereplacementprogrammehasnoeffectivealternativesthatmeetthehealthandsafetyandregulatorydriversasdiscussed,andthereforenoalternateoptionshavebeenconsidered.
6.4.3 ProjectName:Distributionsubstationupgrades
ProjectCode: 15006
EstimatedCost: $3,663,000(overplanningperiod)
StartDate: April2000
CompletionDate: March2020
Due to the inherent dangers a substandard distribution substationmay pose, funds have been allocated toensuretheconditionofthesesitesarekeptuptoasuitablelevel.AlldistributionsubstationsontheWestpowernetwork are fitted with lightning arrestors, approved drop-out fuses and an earthing system installed to astandardapprovedbyWestpowerandwhichmeetallregulatoryrequirements.ToavoidpotentialEPRissuesandtoensureasafereliablesupplyisprovidedfromadistributionsubstation,frequentearthtestsarecarriedout and replacement of substation components are undertakenwhere required. Although theprobabilisticapproachtodistributionearthingasdiscussed in theEEAearthingguidewillbeadoptedbyWestpowerandthependingcommissioningoftheGroundFaultNeutraliser(GFN)willmitigatedangersposedbyinadequateearthingofdistributionsubstationsintheGreymoutharea,all2300distributionsubstationsonthenetworkwillneedtoremainingoodcondition.
The last fewyearshaveseenapushtohave9kV lightningarrestors replacedwith12kVunits,primarilyonsubstationsemanatingfromtheReeftonandGreymouthzonesubstationfeeders.ThiswasduetotheinstallationofaNERunitinReeftonandtheGFNinGreymouthwhichnecessitated12kVarrestorsbeinstalled.Astheseareashavebeencompleted,distributionsubsinotherareaswillbeinspectedfirstandupgradedifrequired.
Justification:
Asmentioned,Westpowerintendstoadoptaprobabilisticapproachtodistributionsubstationearthing,whichwillseeahigherdegreeofpreventivemeasurestomitigatepotentialEPRproblemsinareasfrequentedbythepublicsuchasschools,parksandmeetingplaces.Thisdoesnot,however,absolveWestpowerofitsresponsibilitytoensurealldistributionsubstationsare safeand reliable.With this inmind, theupgradeprogrammemustcontinuetoguaranteethattheseobligationsaremet.
Alternativeoptionsconsidered:
226 WESTPOWERASSETMANAGEMENTPLAN2012-2022
As suitable earthing, lightning arrestors, HV and LV fuses are all essential components on a distributiontransformersite,whichareallpronetoenvironmentallyinduceddegradation,noalternativeoptionshavebeenconsidered.WhiletheGFNinGreymouthand,toalesserextent,theNERinReeftonhaveeasedtheemphasispreviously placed on the earthing system impedance of distribution substations in those areas,maintainingeffectiveearthingsystemswillcontinuetobeafocusforthecompany.
6.4.4 ProjectName:Conditionassessment
ProjectCode: N/A
EstimatedCost: $141,000(perannum)
StartDate: April2011
CompletionDate: March2012
Westpower’sassetmanagementpracticeshaveevolvedoverthelastfiveyears,ashastheconditionassessmentprogramme. Initially, the condition assessment of lines was introduced as a sporadic inspection withoutprovidingadetailedreflectionoftheconditionofeachasset. Inlatteryears,asassetmanagementpracticeswereimproved,systemswereintroducedwhichwerecapableofcollectingdetailedfielddataandelectronicallytransferringthesedatatotheGISforanalysis.
Best industrypractice calls foreach lineasset tohave its conditionassessed inat leastfive-yearly intervals.Westpower is achieving this by developing periodic maintenance schedules, which provides a systematicapproachtoensureitslines,remaininasafeandreliablecondition.
AfulltimeassessorusesanotebookcomputerequippedwithGPStechnologytorecordhis/herfindings,alongwithupdatinganyattributionthatmaybemissingoneachoftheassets.TheresultsaredownloadedintotheGISsystem,whichprovidesinstantanalysiscapabilities.ManyprojectsincludedintheAMPhavebeenderivedfromtheconditionassessmentprogramme.
Condition assessment results are used to remedy defects noted, of which, depending on urgency, can bescheduledforrepairorimmediatelyattendedto.
Justification:
Theconditionassessmentprogramme isacriticalcomponentwithinWestpower’spreventativemaintenancestrategy.Onceperceivedasawetdayfill-injob,theprogrammehasbeentakenfarmoreseriouslyinthelastdecadeandiscrucialinallowingconstantmonitoringoftheconditionoftheofthenetwork.Toensuresuccessfulmanagement of Westpower’s assets a programme such as condition assessment must continue and, withadvancesintechnology,willbecomeanevenmoreintegralpartofthemaintenancestrategy.
Alternativeoptionsconsidered:
Condition assessment, regardless ofmethodology, hasbeenprovenas the industry standard formonitoringtheconditionofnetworkassetsandprovidingbasedataforanalysis.Withthisinmind,nootheroptionsareavailableforconsideration.Severalmethodsofobtainingresultshavebeenconsideredandwillcontinuetobeconsideredastechnologyadvances.
6.4.5 ProjectName:VegetationWorks
ProjectCode: NA
EstimatedCost: $736,000(perannum)
StartDate: April2011
CompletionDate: March2012
ASSETLIFECYCLEMANAGEMENT 227
The inceptionof theElectricity (Hazards fromTrees)Regulations2003promptedWestpower to significantlyincrease its budget to ensure vegetation control notonly compliedwith thenew regulations, butprovide asysteminwhichconsumerscouldbecomfortableknowingthatvegetationwouldbeclearedfromlinesontheirpropertywithoutthetemptationtocarryoutanyvegetationcontrolworknearpowerlinesalso.
Sufficientfundshavebeenallocatedtoensureafullyequippedcrewisworkingfull-timeonvegetationcontrolandafulltimevegetationadministratorensuresthattheworkiscarriedoutinasystematicmanner,thatfulfilsregulatoryandlandownerobligations.
DuetothenatureoftheWestCoast’senvironment,whichlendsitselftohighvegetativegrowth,andtheremote,sometimesinaccessibleareasmanylinestraverse,controlofvegetationcanbeextremelychallengingandtheintroductionofheavymachinerysuchasexcavatorshasbecomecommonplace.Thismethodgenerallyclearstroublesomeareastoapointwhereminimalmaintenanceisrequiredtokeeptheseareasmanageableinthefutureandalsoprovidessomedegreeofaccess.Inmanycases,onceanareaofvegetationhasbeencleared,asprayprogrammeisinitiatedtomaintaintheremnants.
Ahighpriorityhasbeenawardedto66kVsubtransmissionlines,particularlythosethatdonotboastn-1security,withmostareasclearedtofalldistancetoavoidanychanceoftreestrike.Landownersaregenerallyacceptingoftheconsequencesthatsuchastrikewouldhave,andWestpowerworkshardtoengagewiththeselandownerstoreachamicableagreementsregardingvegetationontheirpropertyandproximitytothelines.
Justification:
Aswellascomplyingwithrelevantregulations,Westpower’svegetationcontrolprogrammeproducesahigherdegreeofconfidenceinthesafetyofnetworkalongwithsignificantlyimprovednetworkreliability. Withthepreferredoptionoffellingtreesbeingadoptedwherepossible,asopposedtotheextensivetrimmingpreviouslycarriedout,lessongoingmaintenancecouldbeexpected.Althoughitcouldbesaidthatcostsshouldbelessduetothenumberoftreesbeingfelled,thefundsbudgetedactuallyincreaseastheamountofmaintenanceworkwouldremainstaticandinflationarymeasurehavebeentaken.
Alternativeoptionsconsidered:
Assafetyandregulatoryobligationsdeterminetheamountofvegetationworkrequiredtobecarriedout,nootheroptionswereconsidered.
228 WESTPOWERASSETMANAGEMENTPLAN2012-2022
7.0 FINANCIAL SUMMARY
7.1 Financial Forecasts
Thefinancialexpendituresinthissectionareforecastforaten-yearperiod.TheseforecastshavebeenbuiltupfromtheindividualprojectandprogrammeexpendituresdevelopedinSection5,anddemonstrateagenerallystableexpenditureoverthedurationoftheplanningperiod.
Formoredetailsregardingexpenditureforecastsandreconciliation,pleaserefertoAppendixD.
Table7.1belowshowstheprojectedten-yearAMPexpenditurebyactivityandTables7.2,7.3and7.4showthisexpenditurebyassettype.AgraphicalrepresentationofTable7.1isshowninFigure7.5.
Table 7.1 - Summary of Activity ($000)
Activity 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Inspect,ServiceandTest 4180 4361 4468 4580 4650 4477 4648 4862 5099 5323
Faults 541 571 607 641 680 717 759 803 850 899
Repairs 302 318 335 352 371 390 411 432 457 480
Maintenance Total 5023 5250 5410 5573 5701 5584 5818 6097 6406 6702
Replacement 2414 1235 611 881 727 842 669 1433 1374 1029
Enhancement 2111 260 246 188 228 203 543 164 223 194
Development 1437 1014 947 1095 1024 1004 1080 1209 1185 1269
Capital Total 5962 2509 1804 2164 1979 2049 2292 2806 2782 2492
Total 10985 7759 7214 7737 7680 7633 8110 8903 9188 9194
Table 7.2 - Opex - Summary by Asset Type (‘000)
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Sub-Transmission 708 731 758 790 827 854 895 946 1002 1057
Distribution 1560 1599 1648 1678 1761 1838 1890 1976 2061 2137
Reticulation 276 289 292 285 242 236 250 266 282 298
Service 155 164 161 171 182 192 204 216 230 243
ZoneSubsubstation 751 819 896 998 954 1005 1056 1111 1167 1225
DistributionSubstation 777 807 822 802 848 521 550 584 620 659
MVSwitchgear 236 246 230 240 256 270 287 303 321 337
Scada&Comms 450 479 479 478 492 521 531 528 546 561
DistributionTrans-former 98 104 110 117 124 131 138 148 157 165
Other 12 12 14 14 15 16 17 19 20 20
Total 5023 5250 5410 5573 5701 5584 5818 6097 6406 6702
Table 7.3 - Replacement Capex - Summary by Asset Type (‘000)
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Sub-transmission 948 125 98 102 105 93 97 102 107 113
Distribution 435 325 110 110 110 110 110 110 110 110
Reticulation 90 27 29 30 32 20 21 22 24 25
ZoneSubstation 668 620 173 348 286 245 25 761 761 321
DistributionSubstation 30 0 0 0 0 0 0 0 0 0
MVSwitchgear 123 39 42 105 48 50 53 133 61 64
SCADAComms 60 35 92 115 70 244 278 215 215 295
Services 60 64 67 71 76 80 85 90 96 101
Total 2414 1235 611 881 727 842 669 1433 1374 1029
FINANCIALSUMMARY 229
Itshouldbenotedthattheestimatesforthefirsthalfoftheplanningperiodarebasedonknowndriversandhencearemoreaccuratethanthoseforthesecondhalf,whicharemoreinthenatureofforecastsduetoalargenumberofunpredictablefactors.Nevertheless,indevelopingthesefigures,Westpowerhashadseveralyearsofexperienceinbudgetingandcontrollingthisexpenditure,andthereisahighdegreeofconfidenceinthesevalues.
Figure7.5showstherelativepercentagesofthetotalestimatedexpenditureasapiechartfor2012-13basedonthefiguresshowninTable7.1.Figure7.7showstherelativepercentagesofthetotalestimatedexpenditureasapiechartfor2012-13basedonthefiguresshowninTable7.2.
ThemanagementfeeincludedinI,SandT,ispartofafixedannualfeepaidtothemaintenancecontractortocovercostssuchassparetransformermanagementandtheprovisionofotherwiseuneconomicfaultbasesatReeftonandHarihari.
Acontingencysumhasalsobeenprovidedtoallowforunexpectedevents.Thisisespeciallynecessaryinthefaultactivityareawhereexpenditureishighlydependentonweatherconditions.Infact,justafewseverelightningstormscanhaveamajorimpactontheannualresult.
Previously, Westpower had a large proportion of older lines that were rapidly approaching failure, but areplacementprogrammeoverthelasttenyearshassubstantiallyovercomethisissue.
Figure7.5-RelativeExpenditurebyActivity2009-10
39%
5%3%
23%
20%
10%
Inspect, Service and Test Faults
Repairs Replacement
Enhancement Development
Table 7.4 - Development and Enhancement Capex - Summary by Asset Type (‘000)
Asset Type 2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
Sub-Transmission 1850 0 0 0 0 0 0 0 0 0
Distribution 14 65 66 67 18 19 20 21 22 24
Reticulation 0 50 0 0 0 0 0 0 0 0
Service 85 90 94 99 105 110 116 123 130 137
ZoneSubsubstation 36 0 0 0 0 0 315 0 0 0
DistributionSubstation 191 132 140 149 158 167 177 189 200 211
MVSwitchgear 463 175 142 188 111 117 123 218 137 143
Scada&Comms 460 286 247 245 293 193 235 147 203 189
DistributionTransformer 449 476 504 535 567 601 637 675 716 759
Other 0 0 0 0 0 0 0 0 0 0
Total 3548 1274 1193 1283 1252 1207 1623 1373 1408 1463
230 WESTPOWERASSETMANAGEMENTPLAN2012-2022
TheI,SandTexpenditurehasincreasedduetoamorerigorousconditionassessmentprogrammeincludingCATscanningofwoodenpolesforrot,alongwithanupwardmovementincontractorrates.
The enhancement expenditure reflects a continued emphasis on distribution automation as reclosers anddisconnectorsareprogressivelyautomated.Bydoingthis,Westpowerisabletogreatlyreduceoutagedurationsandswitchingtimes,resultinginanimprovedSAIDIreliabilitystatistic.
AssettypessuchasZoneSubstations,andSCADAComms,andprotectionexhibitarelativelyyoungageprofile,andlittleongoingmaintenanceisrequired.Notsurprisingly,theseassetsalsohavethelowestsusceptibilitytofaultfailure.Notwithstandingthesecomments,anumberofoldercircuitbreakersinstalledatthesmallerzonesubstationshavebeenfoundtobeunreliableandareplacementprogrammehasbeeninstituted,whichshouldbecompletedin2012/13.
Figure7.6-ExpenditurebyActivityforthePlanningPeriod2012-21
0
2000
4000
6000
8000
10000
12000
2013 2014 2015 2016 2017 2018 2019 2020 2021 2022
$('
000)
Year
Inspect, Service and Test Faults Repairs Replacement Enhancement Development
14%
31%
6%3%15%
15%
5%9%
2% 0%
Sub-Transmission Distribution Reticulation
Service Zone Subsubstation Distribution Substation
MV Switchgear Scada & Comms Distribution Transformer
Other
Figure7.7-RelativeExpenditurebyActivity2009-10
FINANCIALSUMMARY 231
7.2 Assumptions and Sensitivity Analysis
Somebasicassumptionshavebeenmade.Theseinclude:
• AsanELB’s,Westpowerwillcontinuetobeagoingconcernunderthenewregulatoryregime.
• AssetManagement,systemcontrolandcorporateservicesfunctionswillbeprovidedbyElectroNetServicesandbebasedinGreymouth.
• TheELB’swillcontinuetoownElectroNetServicesandtooperateitonanarms-lengthbasis.
• TheELB’smust satisfy the twinconstraintsofprovidinga risk-adjustednormalprofit for itsbeneficiariessufficient to retain investment, while simultaneously performing within the regulatory limits set bygovernmentregulations.
Otherfactorsthatwillimpactonnetworkexpenditurearediscussedbelow.
7.2.1 Weatherimpacts
Weatheraffectsthefaultexpenditurethroughthelevelofstormdamageexperienced.Asitisverydifficulttopredictweatherpatternsovera12-monthperiod, thebudget for faultexpenditurecanonlybeanestimatebasedonhistoricalaveragesandgeneralknowledgeoftheassetcondition.
The sensitivity of the network to storm damage has greatly reduced over the last 20 years as major sub-transmissionanddistributionfeedershavebeenprogressivelyreplacedwithbetterqualitymaterials.Lightningarrestorshavebeenplacedonallsubstationsandrecloserstoprotectthatequipmentduringlightningstorms.Inaddition,acontinuingdistributionautomationprogrammehasreducedtheamountoftimeandeffortrequiredforfaultlocationandrepair.
Ontheotherhand,extremeweathereventsoverthelastfive-yearshavehadanotableimpactonperformancestatistics suchasSAIDIand soa continuationof thefiveyear rollingaveragehasbeenassumed toestimateforwardfaultandrepairexpenditure.
7.2.2 GrowthForecasting
GrowthhasbeenallowedforatarateequivalenttotheStatisticsNewZealandhighgrowthprojectionsforthedistrict.TheAMPassumesthattheregion’spopulationwillincreasebyanaverageofapproximately0.4%perannum.
GrossDomesticProduct(GDP)ontheWestCoasthasadirecteffectonWestpower’srevenuestreamthroughreduceddistributiontolargecustomers.Italsohasanindirecteffectassecondaryandtertiarylevelconsumersinthecommercialanddomesticareacontract.
TheuseofaLoadwatchspreadsheettocollectallavailableinformationonfutureloadgrowthtrendshasbeenusedasastartingpointintheplanningprocess.Wheretheloadsarenotyetcommitted,probabilitieshavebeenappliedaccordingtoanassessmentofthelikelihoodofaprojectproceeding.Inaddition,thediversityofanyloadneedstobeconsideredandadiversityfactorof30%hasbeenapplied,asthisistheaverageloadfactorexperiencedonthenetwork.Wherea loadwill clearlyhaveadifferentprofile, suchasan industrialprocessindustrythatrunsaroundtheclock,anindividualdiversityfactorisappliedthatisrelevanttothatparticularload.
WithintheAMP,growthhasbeenbasedonknownstepchanges.Iftherearenoknownsteploads,thengrowthisassumedtobestraight-linebetweenyears.Theseassumptionshavebeenappliedwhenprojectingexpenditureandgrowthovertheten-yearperiod.Theprojectionsfordifferentassettypeswillvarydependingontheamountofsystemreinforcementrequiredforeachload.
232 WESTPOWERASSETMANAGEMENTPLAN2012-2022
7.2.3 ContinuanceofSupply
AkeyassumptionisthatWestpowerwillberequiredtocontinuetosupplyexistingcustomersonitsnetworkfortheforeseeablefutureandthatthekeyfeaturesoftheElectricityIndustryReformBillregardingcontinuanceofsupplywillbepassedintolaw.
7.2.4 GovernanceStructure
Itisassumedthatthegovernancestructurewillremaininthestateasanticipatedbythisplanoverthedurationofthisplan.
7.2.5 DevolutionsofResponsibility
Forthepurposesofthisplan,itisassumedthattherewillbenodevolutionsofadditionalresponsibilityfromaregulatoryperspective,particularlynotwithouttheabilitytorecoveranyincreasedcoststhroughacommensurateincreaseinrevenue.
7.2.6 AssumptionsastoActivitiesUndertakenandLevelsofServiceProvided
Westpowerisassumingthattherangeofactivitiesthatithassignalledtoundertakewillnotchange.
Westpowerisalsoassumingthatthelevelsofservicetowhichitsactivitiesareprovidedwillnotchange,exceptasaconsequenceofplannedexpenditureprogrammesmentionedinthisplan.Therealityisthatanychangetoserviceleveland/oractivitiesundertakenmayplaceanadditionalcostonWestpower,andtherecoveryofthiscostwouldneedtobefairlyandequitablyallocatedtothechiefbeneficiaries.
7.2.7 FixedAssetUsefulLife
Anumberof assumptionshavebeenmadeabout theuseful livesofWestpower’s infrastructureassets. ThedetailforeachassetcategoryisgenerallybasedontheguidelinesprovidedinthelatestODVhandbook.Theusefullivesareconsistentwiththeassumptionsappliedtovaluingeachassetcategoryandweredeterminedbyexperiencedandqualifiedassetengineeringstaff.
Individualassetlivesareappliedtoassetsthatareeitherexpectedtolastlongerorlessthanthestandardvaluesbecauseoftheasset,conditionorenvironmentalfactors,suchasproximitytoacorrosivecoastalenvironment.
7.2.8 ResourceConsents
Westpowerisassumingthatthemajorresourceconsentsthatitneedsfordeliveryoftheservicesoutlinedinthisplanwillbeobtainedandgrantedwithconditionsthatcanbemetwithinanticipatedexpenditureestimates.
7.2.9 VestingAssets
ForthepurposesofthisplanithasbeenassumedtherewillbevestingofassetsinWestpower.Thishasbeenbasedonhistoricalinformation.However,itisnotedthattheyare:
• BeyondWestpower’scontrolandtheirnumberandvalueareverydifficulttopredict;
• Likelytobeimmaterialinthecontextofoverallassetvalues;
• Beingbrandnew,unlikelytoimposeanysignificantextracostsfromthosegeneratedoverthelifeofthisplan.
FINANCIALSUMMARY 233
7.2.10 Sustainability
WestpowerhasconsideredthesustainabilityofeachofitsservicesandactivitiesinitspreparationoftheAMPalongsidehowtheservicesitprovideswillmeettheneedsofpresentandfuturegenerations,andhowitsactivitieswillprotectandenhancethenaturalenvironmentinthelongterm.Whilethecompanyisprimarilyrequiredtoact ina commercialmannerand remainagoing concern, it is also cognisantof its responsibilities to takeasustainabledevelopmentapproachtoprovidingforthesocial,economic,environmentalandculturalwellbeingof communities. This involves taking account of the needs of people and communities now, the reasonablyforeseeableneedsoffuturegenerations,andtheneedtomaintainandenhancethequalityoftheenvironment.
TakingasustainabledevelopmentapproachisreflectedinthewayWestpowerplansforasustainablesupplyofelectricitythroughoutitsarea,
Westpower has a significant role in the provision and operation of key infrastructure that is critical for thesustainabledevelopmentofthecommunitiesthatitserves.
7.2.10.1EffectsofClimateChange
ItisassumedthattheclimatechangereportsprovidedbytheIntergovernmentalPanelonClimateChange(IPCC)arereliableandprovideareasonableindicationofwhatWestpowerneedstoconsiderinitsplanningprocesses.BasedontheIPCCreports,itisassumedthatthesealevelwillriseby0.5moverthenext100years.
7.2.10.2EmissionsTradingScheme
ThisTen-yearAMPhasbeenpreparedbasedonthebroadscientificcommunityviewthathuman-inducedclimatechangethroughincreasedgreenhousegasemissionsisoccurringandmayaccelerateinthefuture.Nationalandinternationaleffortsareunderway tocontrolemissions in response toagreements that thegovernment isasignatoryto.
Manyoftheclimatechange-inducedchangesarelikelytoeventuateoverthelongertermandwilloccurbeyondthe ten-year horizon uponwhich the activities and their service levels are described in this AMP. They are,however,factorstobetakenintoaccountsuchasincreasedelectricitypricesdrivingadditionalinvestmentindistributedrenewablegenerationandthisneedstobecateredforinWestpower’splanningprocesses.
Table 7.8 – Sensitivity Analysis
Forecasting Assumption Level of Uncertainty Risk Assessment (Low/
Med/High) Reasoning for Assessment
LoadGrowthItislikelythatthepro-
jectedloadgrowthwillinrealitybedifferent
High
TheAssetManagementPlanhasassumedgrowthwilloccurbetweenthemid-highrangeoftheNZStatisticsprojections,
whichisthebestinformationwehaveavailable,supplementedbyknowledgeofparticularregionaldevelopmentsbasedontheLoadwatchspreadsheet.Theimpactofanychangeform
theprojectionwillbeoncapitalexpenditureasmanysteploadsrequireaugmentationofthenetwork.Theimpactonmainte-nanceexpenditureislesssignificant.Ifgrowthslowsthenex-penditurewillbedeferredandtheassetwillstillhavesufficientcapacity.Manyoftheengineeringsolutionscaterforgrowthupto20yearsout;howeverifgrowthisfasterthanforecastitmaymeanatsomestageinthefutureupgradesmayneedtooccursoonerthananticipated.Thisconsideredahighrisk,butlargely
beyondWestpower’scontrol.
234 WESTPOWERASSETMANAGEMENTPLAN2012-2022
7.3 Actual Deviations from Previous AMPs
7.3.1 UnallocatedWorks
Thefollowingexplainsadditionalworks(over$10,000)thatwerenotincludedinthe2010-11AMP,butwhichforvariousreasons,wereundertaken.
7.3.1.1 Network
PAS55 and SMS Consultancy Fees
ToassistwiththeimplementationofthePAS55andSMSsystems,aconsultantwasengagedtoprovideexpertiseinthesefieldsatacostof$36,750
Purchase and Installation of Productivity Plus and Template Manager
To assist in the development of Network Standards, appropriate softwarewas required. This included thepurchaseandinstallationofProductivityPlusandTemplateManageratacostof$15,365
7.3.1.2 Reticulation
Scandinavian Street, Stafford – Replace Overhead Line with Underground
ArequestfromalandownertorelocateacondemnedLVreticulationlinetraversingtheirpropertyatStaffordresultedinthelinebeingconvertedtoundergroundandinstalledonroadreserve.Thisremovedthelinefromprivatepropertyandhasallowedasafer,morereliableconfigurationatacostof$14,907
O’Conner Moonlight - Replace LV Line
TheLVlineemanatingfromS951ontheO’ConnorpropertyatMoonlightwasfoundtobeinasub-standardconditionandrequiresreplacement.Itappearsthepolesinstalledinthe1980’swerepre-usedandreachedtheendoftheirserviceablelives.Fourhardwoodpoleswerereplacedwithsixconcretepolestobringthelinetoregulatoryspecifications,eliminatingthelongspansthatwereoriginallyinstalledcosting$11,611
Table 7.8 – Sensitivity Analysis
Forecasting Assumption Level of Uncertainty Risk Assessment (Low/
Med/High) Reasoning for Assessment
ContinuanceofSupply
Itispossible,butun-likely,thatWestpower
willnotneedtocontinuesupplyingexistingcus-
tomers
Low
AkeyassumptionisthatWestpowerwillneedtocontinuetomaintainandreplaceolderlinesthatfeedcustomersinrural
areas.Itishardtoseeanygovernmentremovingtheprotectionthatmanyfarmingcommunitiesrelyonintermsofhavingalongtermguaranteethatelectricitysupplywillcontinuetobeavailableatcurrentprices,aftertakinginflationintoaccount.Atthesametime,Westpower’snetworkisinverygoodcondi-tionwithfewareasrequiringmajorrefurbishmentwithintheplanningperiodandsoanyextendedobligationwillhavelittle
impactintheshorttomediumterm.
GovernanceStructure
Itisimprobablethatthegovernancestructurewill
changeLow
Recentownershipreviewsandthecurrentlysupportiveregula-toryframeworkfortrust-ownedlinesbusinessesmeansthat
theredonotappeartobeanysignificantdriversforachangeinthecurrentgovernancestructure.
ActivitiesUndertaken
Itislikelythatnewactivi-tieswillbeundertaken. Low
AlthoughWestpowerisinvolvedinanumberofrelatedactivi-tiesthroughitssubsidiarycompanies,andthisislikelytoin-
creaseovertime,theimpactiontheAMPisnotgreatasaclearfocuswillalwaysbemaintainedontheasset.
FINANCIALSUMMARY 235
7.3.1.3 Distribution
Omoto – Kaiata 11 kV Line Replacement
IncludedinpreviousAMP’s,thereplacementofthe11kVlinebetweenOmotoandKaiatawasnotcompletedin2009-10asanticipated.The$39,369additionalexpenditurewascarriedoverfromthepreviousyearandtheprojectwascompleted.
Giles Creek 11 kV Reconstruction
ThelineroutefortherecentlyconstructedDOB-TEEA110kVccttraversedtheroadadjacenttothe11kVlineatGilesCreek.Thisnecessitatedrelocationofthe11kVlinetoaccommodatethe110kVcct.Duetothepoorconditionofthehardwoodpolesaffected,andthefactthattheywouldhavebeenreplacedinthenearfuture,Westpowerfundedthemajorityoftherelocationatacostof$17287.
7.3.1.4 Subtransmission
GYM-KUM 66 kV cct – Carry Out Rating Study
ToensureWestpoweradherestocontractualobligationsanddoesnotcompromiseregulationsbyintroducingconductor clearance violations, a study was undertaken to model the existing line configuration on theGreymouthtoKumara66kVcircuitusingLiDARtechnologyandPLSCADlinedesignsoftware.Severalscenarioswithdifferentoperatingparametersweremodeled,atacostof$11,815
KUM-KAW Install Conduit and Saddle Earths on KUM-KAW Circuit
AnassessmentoftheKUM-KAW66kVcctrevealedthatthehardwoodpolesonthelinehadexposedcopperearthleadstogroundlevel,whichgivenpublicsafetyconsiderations,requiredaprotectivesheathtobeinstalled.AllsixtyeightpoleshadPVChosesfittedovertheearthleadsatacostof$11,499
7.3.1.5 ZoneSubstations
44027: Longford Corner – Replace Regulator with Single Phase Units
Thisprojectwassetdownforthe2012/13financialyear.InSeptember2011amajorfaultoccurredwiththeunit.Duetoitsage,difficultyinsourcingpartsandthefactitwasalreadysetdownforreplacementitwasdecidedtoreplacetheunit.Totalcostsforthiswas$68,928
7.3.2 UncommencedWorks
Thefollowingexplainsprojects(over$10,000)thatwerenotcommencedinthe2010-11AMP.
7.3.2.1 Reticulation
61008 – Offload S119 Frickleton St ($50,000)
Relatedtotheabove,adistributionsubstationwasconsideredtoalleviatevoltageissuesintheFreybergTerracearea.Furtheranalysiswascarriedoutanditwasdiscoveredthatbyre-configuringtheexistingLVconfigurationvoltagecouldbesuppliedatacceptablelevels,negatingtheneedfortheadditionalsubstation.
42003 - Ruatapu Township - Replace LV ($22,000)
ItwasintendedtoreconfiguretheLVlinesaroundtheRuataputownship,howeveritwasfeltadditionalplanningwasrequiredbeforeworkcouldtakeplace.Thisplanningextendedoverthefinancialyearthereforetheprojectdidnotcommence.
236 WESTPOWERASSETMANAGEMENTPLAN2012-2022
12003 - Hokitika, Hampden St - Remove LV ($15,000)
Itwas intendedtoremovethesurplusLValongasectionofHampdenStreet inHokitika,however itwasfeltadditionalplanningwasrequiredbeforeworkcouldtakeplace.Thisplanningextendedoverthefinancialyearthereforetheprojectdidnotcommence.
7.3.2.2 Distribution
61003 - Construct 11 kV Line to Freyberg Terrace ($50,000)
Considerationwasgiventoconstructan11kVlinetoFreybergTerracetoalleviatevoltageissuesinthearea.Furtheranalysiswascarriedoutanditwasdiscoveredthatbyre-configuringtheexistingLVconfigurationvoltagecouldbesuppliedatacceptablelevels,negatingtheneedforthe11kVline.
41029 - Waitahu, Douglas Road - Replace 11 kV Line S1363 ($30,000)
Conditionassessmentofthe11kVlinetraversingDouglasRoadatWaitahurevealedthatthepoleswereredtaggedandrequiredreplacement.Fundsweremadeavailable,howeveritwaslaterdiscoveredthatthelinewasnolongerrequiredthereforedismantled.
61007 Replace 11 kV cable Fox Hotel ($100,000)
Replacementoftheageing11kVcable,creatingan11kVringintheFoxGlaciertownship,waslargelydependentonobtainingeasementsoveranumberofproperties.Asnegotiationswithlandownershadnotbeenfinalisedworkcouldnotcommence.
7.3.2.3 Subtransmission
10005 – Franz Josef - Fox Glacier 33 kV Line Maintenance ($22,000)
ContingencyfundsweremadeavailableforgeneralmaintenanceontheFRZ-FOX33kVcct,howeverpatrolsandassessmentdidnotidentifyanymajormaintenance.
40008 - Replace All 33 kV EPDM Strain Insulators ($28,000)
AcontingencysumwasallocatedtohaveallEPDMstraininsulatorsonthenetworkremovedandreplacedwithglassequivalents.ThiswasdependantonidentificationofEPDMstraininsulatorsandappropriateoutagestohavethemreplaced.Thisprojectdidnotcommenceduetothelackofidentifiedinsulators.
40006 - Replace Waitangitaroa River crossing ($40,000)
SignificantdesignwasrequiredtodeterminethebestoptiontohavetheWaitangitaroaRivercrossingreplaced,stallingtheconstructionaspectoftheproject.
7.3.2.4 ZoneSubstation
14005 – Greymouth Zone Substation Paint Gantry Steelwork $75,000
DetailedinspectionoftheGantryhasdeterminedthattheSteelworkisingoodconditionandrequiresnofurtheractionatthistime.Thiswasacontingencybudgetthathadbeenallowedforincaseoffurtherworkrequiredafterinspection.
14010 – Rapahoe Zone Substation Paint Gantry Steelwork and Reinsulate $33,000
ThisprojecthasbeendeferredtocoincidewithEquipmentandProtectionupgradeattheZoneSubstationin2014/15ensuringbetterutilisationoftheMobileSubstationandotherresources.
14023 – Zone Substation Lightning Protection Review $12,000
Thisprojecthasbeendeferredduetoengineeringresourceconstraints.
FINANCIALSUMMARY 237
14040 – WMS (Mobile Substation) Storage $12,000
DelaysinstoragebeingbuiltbyCroft’satStillwaterhaveseennocostsincurredonthiscontingencybudget.
44020 – Rapahoe Zone Substation 33kV Disconnector Upgrade $25,000
ThisprojecthasbeendeferredtocoincidewithotherprojectworkplannedattheZoneSubstationin2014/15ensuringbetterutilisationoftheMobileSubstationandotherresources.
44022 – Whataroa Zone Substation Design/Drawings for CB1412 and T1 Protection upgrade $12,000
Thisprojecthasbeendeferredto2012/13duetoengineeringresourceconstraints.
54018 – Wahapo Zone Substation 11kV BUS upgrade with RMU $50,000
PrioritisingofresourcesduetoexternalcommitmentsandEngineeringresourceconstraintshasresultedinthisprojectbeingdeferredto2012/13.
64008–Emergency backup Control Room $30,000
Thisprojecthasbeenputonhold.
7.3.2.5 MVSwitchgear
56004–Distribution intelligent fault isolation system, design/study $11,000
Timingforthisprojectwasnotsuitable.TheMVswitchgearupgradeworkbeingcarriedoutonthenetworkatpresent,whichisdueforcompletioninacoupleofyears,willallowthisprojecttocommencewithdevelopmentofasmartgrid.
66006–Install Ring Main Units – Unspecified Locations (1) $45,000
Thisisacontingencybudgetallowedforanyunplannedsuppliesfornewdevelopments(Subdivisions,etc.).Nonewdevelopmentsoccurredinthisfinancialperiodrequiringtheuseoftheallocatedfunds.
7.3.3 UncompletedWorks
Thefollowingexplainsprojectsthatwerestartedandhavemorethan$20,000remaininginthe2011-12AMP.
7.3.3.1 ZoneSubstations
14030 - Zone Substation Building Climate Control $44,000
ThisbudgetwasoriginallyallowedfortoinstallAirConditioningUnitsatallZoneSubstations.Adecisionhasnowbeenmade to not install the units in the smaller Zone Substation control rooms constructedwith the‘TransportableSandwich’Panels.Thishasresultedinanunderspendof$33,282.
14032 - Zone Substation OLTC & Regulator Maintenance $91,000
DuetoresourceconstraintsthenumberofOLTCandRegulatorstomaintainwasreduced.Allworkabletobecompletedwasdoneatacostof$14,900resultinginanunderspendof$76,100.
44015 - Wahapo Substation Replace Combiflex Relays, Protection Setting upgrade $ 53,000
PrioritisingofresourcesduetoexternalcommitmentsandEngineeringresourceconstraintshasresultedinthisprojectbeingdeferredto2012/13.Designworkhasbeencompleted,remainingbudgetof$42,421.
238 WESTPOWERASSETMANAGEMENTPLAN2012-2022
44021 - Ngahere Zone Substation – CB1 & 3 Replacement $108,000
Delaysinthedesigndrawingsandthelongleadtimeinorderingequipmentresultedinthisprojectbeingdeferredto2012/13,remainingbudgetof$84,813.
7.3.3.2 MVSwitchgear
16001 – Upgrade Earthing at Disconnector Locations $24,000
AdelayintheEarthingdesignhasseenthisprojectdelayedto2012/13,remainingbudgetof$22,936.
16003 – Recloser Maintenance – Protection, Batteries, etc. $28,000
AnumberoflocationsduefortestingandbatteryreplacementwereupgradedwithneworrefurbishedReclosers.Thisresultedinanunderspendof$25,644forthiscontingencybudget.
46001 – Replace KFE Reclosers with Viper-ST & SEL Protection $278,000
80%oftheplannedworkwascarriedout.Theremaining20%istobecompletedin2012/13.Resourceconstraintsandreducedcostsforthecompletedworkresultedinanunderspendof$67,052.
46006: Ring main unit Replacement $56,000.
ARingMainUnitwaspurchasedtoreplaceanexistingunitatFoxGlacier.Issueswereencounteredwithobtaininganeasementforthecables,thisalongwithresourceconstraintsresultedinanunderspendof$35,301.
56005: Install Automation to various Disconnectors $84,000.
Furtheranalysisdeterminedthat2locationswerenolongerrequired.Theremaininglocationswerecompletedresultinginanunderspendof$41,263.
56006: Fit Fault Passage Indicators $24,000.
ThisisacontingencybudgetallowedforanynewlocationsidentifiedrequiringFaultPassageIndication.Only2locationswereidentifiedinthisperiodleaving$23,369unspent.
56007 - South Westland 33 kV disconnector automation $80,000
45%of locationshavebeencompleted,resourceconstraintsand issueswiththeActuatorsresultedwiththeremaininglocationsbeingdeferredto2012/13andanunderspendof$42,262.
66001 - New main line recloser sites $191,000
60%oftheplannedworkwascarriedout.Resourceconstraintsresultedintheremaininglocationsbeingdeferredto2012/13.Thisalongwithreducedcostswithcompletedworkresultedinanunderspendof$58,687.
66002 - New spur line recloser on various spur lines $191,000
50%oftheplannedworkwascarriedout.Resourceconstraintsresultedintheremaininglocationsbeingdeferredto2012/13.Thisalongwithreducedcostswithcompletedworkresultedinanunderspendof$93,070.
66005 – Install Capacitors at various Locations $40,000
TheEngineeringstaffisstillinvestigatingavailablecosteffectivesolutionsforautomationofCapacitorLocations.OnelocationwasidentifiedrequiringsmallersizedCapacitors.Thisresultedinanunderspendof$35,277.
FINANCIALSUMMARY 239
66006 - Install ring main units–unspecified locations $42,000
Therewerenonew locations identified for this financial period, resulting in an approximateunderspendon$33,000.
240 WESTPOWERASSETMANAGEMENTPLAN2012-2022
2010
-11
Deve
lopm
ent
Enha
ncem
ent
Repl
acem
ent
IS&
TFa
ults
Repa
irsTo
tal
Actual
Budg
etAc
tual
Budg
etAc
tual
Budg
etAc
tual
Budg
etAc
tual
Budg
etAc
tual
Budg
etAc
tual
Budg
et
0:Su
b-Tran
smis-
sion
672
018
600
4901
9249
0000
4088
0538
1000
2496
622
000
1003
428
000
9365
2892
1000
1:Distrib
ution
5397
312
0000
1198
5610
0000
9985
4738
3000
1799
719
1319
000
3283
1232
4000
1951
984
000
3319
926
2330
000
2:Re
ticulati
on51
070
5441
730
000
8198
40
2620
1125
8000
1985
522
000
1242
739
000
4358
0034
9000
3:Services
6695
30
00
2507
011
4172
010
6917
032
750
2938
240
4:Zo
neSub
sta-
tions
6075
630
000
1620
2514
2000
4491
9148
7000
6087
7068
2000
2951
1100
014
7382
6800
014
3107
614
2000
0
5:Distrib
ution
Su
bstatio
n52
607
1180
000
7400
059
637
3700
026
6418
4540
0046
634
1700
011
422
1100
043
6718
7110
00
6:MVSw
itch-
gear
2702
1531
0000
5014
019
9000
4057
8650
7000
1429
9115
9000
1806
850
0046
993
3900
093
4194
1219
000
7:SC
ADA/
Comms
1426
050
8957
00
3802
90
2358
600
3270
10
2900
80
5677
720
8:Distrib
ution
Tran
s31
6562
4000
000
014
816
6200
079
789
9600
00
3000
00
4111
6756
1000
9:Other
1568
00
00
030
1519
000
4325
6000
010
0089
0826
000
Total
9710
1897
8000
4778
6754
5000
2540
689
1966
000
3921
551
3368
000
5847
2941
0000
2800
5927
0000
8775
913
7537
000
Table7.9-A
ctua
lVBud
getP
erform
ancebyAssetT
ype
ASSETMANAGEMENTPRACTICES 241
8.0 ASSET MANAGEMENT PRACTICES
8.1 Introduction
The electricity distribution system is comprised of assets with long lives. Themanagement of these assets(includingmaintenance of existing assets and development of new assets) isWestpower’s primary focus inprovidinganeffectiveandefficientdistributionserviceto itscustomers.Furthermore,becausedistributionisonlyonepartofanintegratedelectricitysystem,consultationandcoordinationofplansisanessentialingredientfortheeffectivefunctioningofthatsystem.
Thisisanannuallyproducedplancoveringthenexttenyearsanddocumentslikelyorintendedassetmanagementrequirements.TheplanprovidesafocusforongoinganalysiswithinWestpoweraimedatcontinuouslyimprovingthemanagementofthedistributionsystemanditprovidesavehicleforcommunicatingAMPswithcustomers.
Inmanycases,particularlywhereassetdevelopmentisinvolved,theworkwillbedrivendirectlybycustomerrequirementsandassociatedfinancialcommitments.ThisplanisbasedonWestpower’spresentunderstandingofitscustomers’requirements.Itispartoftheprocessofcommunicationwithcustomers,andWestpowerwillberesponsivetocustomerinput,withregardbothtoactualexpenditurecommitmentandtolong-termfutureplanning.
TheplanisalsointendedtodemonstrateresponsiblestewardshipofassetsbyWestpowertoitscustomersandshareholders.Theplanshowsthemaintenanceandreplacementrequirementswhichareintendedtomaintaintheoperating capabilityof the systemover the long term.Eachyearaprocess is carriedoutwhich reviewsWestpower’sachievementwithrespecttothisplanandtheresultsofthisaresummarisedintheprevioussection.
ThissectionbroadlyoutlinesWestpower’snetworkservices,currentanddesiredassetmanagementpracticesandspecificimprovementinitiatives.
Toidentifyandprioritisetheassetmanagementpracticesandneedsofnetworkservices,assetmanagementimprovementtasksarediscussedunderbroadheadingsofprocesses,informationsystemsanddata.
• Processes are the business processes, analysis and evaluation techniques needed for lifecycle assetmanagement.
• Informationsystemsaretheinformationsupportsystemsusedtostoreandmanagethedata.
• Dataarethoserequiredforeffectivedecisionmaking(i.e.formanagingusinginformationsystems).
TablesthroughoutthissectionbroadlydescribethecurrentWestpowerassetmanagementpracticesandpossiblefuture(desired)businesspractices it is intendedtoultimatelydevelop.Theassetmanagement Improvementplandiscussesimprovementpriorities,timetablesandresourcesforthenextthreeyears.
Thefollowingarespecificissuesandassetmanagementproceduresthatarecurrentlybeingaddressed.
242 WESTPOWERASSETMANAGEMENTPLAN2012-2022
8.2 Asset Management Policy
The asset management policy is a direct communication from directors to management, employees andstakeholdersoftheorganisation’spositionandintentionswithregardtoassetmanagement.Itprovidesahighlevelstatementoftheorganisationsprinciples,approachandexpectationsrelatingtoassetmanagement.
Westpoweriscommittedtomaximisingshareholder’sinvestmentsinalegallyandenvironmentallycompliantandsustainablemanner,withoutcompromisingthehealthandsafetyofouremployees,consumersorthepublic.Thisshallbeachievedbyadoptingthefollowingpolicystatement:
1. Safety
• Safety-Safetyisofparamountimportanceineverythingwedoandwillnotbecompromisedforcost,timeoranyotherreason.
2. Reliability
• Reliability of Supply - Through continued investment in relevant technology and system configuration,reliabilitymustmeetapprovedtargetsatalltimes;and
• QualityofSupply-Qualityofsupply,commensuratewiththeloadtypeandcriticality,mustmeetWestpower’sStandardsandremedialactionwillbetakenwherestandardsarenotmet.
3. Security
• SecurityofSupply–Thedesiredlevelofsecurityisdefinedbygoodindustrypracticesandlongtermplansmustbedevelopedtoachievetherequiredsecurity;and
• Transpower–EveryeffortmustbemadetofocusTranspoweronsecurityofsupplyfortheWestCoast.
4. Sustainable
• MaintainServicePotential-ThefutureofWestpower’sbusinessiswhollydependentoftheabilityofthenetworktocontinuetoprovideservicefortheforeseeablefuture.Everyeffortmustbemadetomaintaintheongoingservicepotentialofthenetworkwhereappropriate;
• Supporting Economic Growth -We recognise the electricity infrastructure is a key enabler of economicgrowthandwillworkwithcurrentandfuturedeveloperstoprovideelectricitywiththecapacity,securityandqualityrequiredtosupporttheirbusiness;
Figure8.1-AssetManagementSystemElements
ASSETMANAGEMENTPRACTICES 243
• Continual Improvement–Theassetmanagementsystemwillbereviewedonanannualbasisandwhereweaknessisfound,improvementswillbemade.CompliancewithPAS55:2008,AssetManagement,shallbesupported;
• StrategicandLongTerm–Ourinfrastructurebusinessinvolveslongterminvestmentsandwewillensureourdecisionsalignwithandsupporttheorganisation’sstrategicplan;
• NewInvestment–Anynewinvestmenttoexpandtheassetbasemustmeetshareholderexpectationandapprovalwherenecessary;and
• Communication – The requirements of the asset management system must be communicated to allstakeholderstoenablethemtobeawareoftheirobligationsandtoensuretheirexpectationsareconsideredinallaspectsofplanning.
5. CostEfficiency
• CostEfficiency-Allprojectsmustcompeteforfinancialresourcesandprudentassetstewardshiprequirescareful budgeting and robust financial review processes are used to ensure maximum cost efficiency.Opportunitiesforimprovedproductivitythroughtraining,technology,processimprovementorothermeanswillbeconstantlypursued;
• EnergyEfficiency-EnergyefficiencyisencouragedinallareasofWestpower’sactivitiesandwillcontinuetobeakeyoutcomefromthedesignprocess.Whereopportunitiesexisttoenhanceenergyefficiencyforexistingassets,theseareactivelypursuedandimplementedwheretechnicallyandeconomicallyfeasible;
• Technology-Technologyisseenasakeyenablerinprovidingimprovedserviceandvaluetoourconsumers.WewillcontinuetokeepabreastofdevelopmentsinthefieldofnewandemergingtechnologyandapplythesetoWestpower’snetworkwhereappropriate;
• FairPricing-Thepriceofdeliveryofelectricitytocustomersmustbetransparentandfairtoallusersoftheassets;and
• CapitalContributions–Anyexpensefornetworkextensionstosupplynewloadswillbemetbyaconsumercontributiontowardsthecostsinvolved.
6. EnvironmentalImpact
• EnvironmentalImpact-Westpowerisenvironmentallyresponsibleandcarefullyconsiderstheenvironmentalimpactofanyof itsactions. Furthermore,thecompanyworkshardtomitigateanynegativeeffectsandprovideanetenvironmentalbenefitwherethisispractical.WestpowerconsiderstheclimatechangereportsprovidedbytheIntergovernmentalPanelonClimateChange(IPCC)arereliableandprovideareasonableindicationofwhatWestpowerneedstoconsiderinitsplanningprocesses.
7. RiskManagement
• Risk Management – Westpower adopts the AS/NZS ISO 31000:2009 standard in its approach to riskmanagementandhasaGroupRiskManagementPlanthatincludesBusinessImpactAnalysisandBusinessContinuityPlanning.TheAssetManagementSystemhasdevelopedariskmanagementplanrelatingdirectlytoWestpower’sdistributionassets.
8. Legislation
• Legislative Compliance – The AssetManagement Systemmustmeet all relevant legislation but the keylegislationistheElectricityActandtheHealthandSafetyinEmploymentAct.Wherenon-complianceissuesareidentified,thesewillbedealtwithpromptlyandtransparently.
9. AlignmentwithOtherPolicies
• TheassetmanagementsystempoliciesexpressedabovealignwithotherfunctionalpolicieswithinWestpower.
10.AuditandReview
Theassetmanagementpolicyshallbesubjecttoauditandreviewasperthefollowingprocess:
244 WESTPOWERASSETMANAGEMENTPLAN2012-2022
ReviewPeriod: FiveYears
PersonResponsible: WestpowerAssetManager
APPROVED:
Adopted: Date……………… Minuterecord………………….
RevisedDate……………… Minuterecord………………….
ChiefExecutive……………………………………………………………
8.3 Rationalisation of responsibilities and procedures
ThestructureofElectroNet’sassetmanagementgroup,reportingtoTheGeneralManager,AssetsandEngineeringServices,continuestodeveloptomeetbusinessneedsandlegislativechange.Responsibilities,reportinglines,workflowsandprocedureshavebeenimplementedforthedifferentactivitiescarriedoutintheoffice.Theseactivitiesincludeaction,planning,monitoringandreporting.
8.4 Network services operational support
WestpowerusesElectroNetServicesasitspreferredmaintenancecontractorforallnetworkassociatedinspectionservice and testing, faults, fault repair,maintenance replacement and network enhancement. Developmentprojectsarehandledinthesameway,althoughoutsidecontractorsmaybesub-contractedintocarryoutcarryoutsomeofthework.
Service level agreements are currently in place with ElectroNet services for asset management and assetmaintenance.Largerenhancementanddevelopmentprojectshavecontractspreparedonaspecificbasis.
8.5 Information systems development
TheassetmanagementgrouphasimplementedtheIBMMaximo®AssetWorksManagementSystem(AWMS)usedforassetandworksmanagementprocesses.Expenditurecanbetrackedbyactivityandbyassettype,andisauditedmonthly.
Improvements have been made to the Maximo® asset database, which keeps information on the typesof equipment installed at a site. This systemalso tracks themaintenancehistory of transformers andotherassociatedequipment.
8.6 Specifications, procedures and manuals
Westpowerisspendingconsiderableeffortinupdatingitsmanualsforeasierusebycontractors,whichdenoteWestpower’sspecifications, levelsofcompetency,networkreleasesandaccess tosites.Thecompletionofafullsuiteofmanualsandstandardssuitableforusebycontractorsisakeystrategicgoalduringthefirstyearoftheplanningperiod.Asetofnetworkdesignstandardsarealsoavailabletocontractorswhowishtoundertakenetworkextensionsandnetworkreconstruction.
ProcedureshavebeendevelopedanddeemedtobemandatoryforcontractorswhowishtocarryoutworkonWestpower’snetwork.
8.7 Deregulation/Compliance with MED and Commerce Commission Requirements
ThespecificexternalenvironmentinwhichWestpoweroperatesisthepowersupplyindustryingeneral.
ASSETMANAGEMENTPRACTICES 245
8.8 Asset Renewal Policy
Thegeneralrenewalpolicyistorehabilitateorreplaceassetswhenjustifiedbyassetperformance.
Renewalof an asset is requiredwhen it fails tomeet the required level of service. Themonitoringof assetreliability, capacityandefficiencyduringplannedmaintenance inspectionsandoperationalactivity identifiesnon-performingassets.Indicatorsofnon-performingassetsinclude:
• Structurallife,
• Repeatedfailure,
• Ineffectiveand/oruneconomicoperation,
• Economics,
Renewalsareprogrammedwiththeobjectiveofachieving:
• Thelowestlifecyclecostfortheasset(uneconomictocontinuerepairing),
• Anaffordablemediumtermcashflow,
• Savingsbyco-ordinatingrenewalworkswithotherplannedworks.
• Riskreduction.
Theriskoffailureandassociatedenvironmental,publicsafety,financialorsocialimpactjustifiesproactiveaction(e.g.impactandextentofsupplydiscontinuation,probableextentofpropertydamage,healthrisketc.).
Plannedandreactivereplacementworkscanbeprioritised inaccordancewiththepriority rankingshown inTable8.2.
8.9 CAPEX Analysis
CAPEXneeds tobe carefully targeted to ensure that the greatest benefit is reaped fromeach capital dollarexpended.
WestpowerhasdevelopedaformalprocessforoptimisingitsCAPEXandthisinvolvestheuseofadiscountedcashflow(DCF)analysis,wherefeasible,alongwithothermethodstodeterminetheoptimalCAPEXprofile.TheprocessusedhasbeenexplainedinmoredetailinSection5.2.
Table 8.2 - Asset Renewal Criteria
Priority Renewal Criteria
1(High)
AssetFailurehasoccured.
AssetFailureofcriticalsystemcomponentisimminent.
Regularmaintenancerequired.
Complaints.
2Failureofnon-criticalassetisimminentandrenewalisthemostefficientlifecyclecostalternative.
Maintenancerequiringmorethansixvisitsperyear.
3Reticulationmaintenanceinvolvingtwotothreevisitsannually.
Difficulttorepair,duetofragilenatureofmaterialobsolescence.
4 Existingassetshavelowlevelofflexibilityandefficiencycomparedwithreplacementalternative.
5(Low) Existingassetmaterialsortypesaresuchthatknownproblemswilldevelopintime.
246 WESTPOWERASSETMANAGEMENTPLAN2012-2022
8.10 Distributed Generation
Distributedgenerationiselectricitygenerationequipmentconnectedtothecustomers’installations,andcapableofgeneratingelectricitybacktotheelectricitynetwork,aswellassupplyingelectricityforthecustomers’ownuseatthelocationitisinstalled.
Usually,itwillbeafixedinstallationbutitmaybedisconnectableandmoveableifrequired.Theinstallationwillincludeallnecessaryprotectionequipmentrequiredforthesafeoperationofthedistributedgenerationsystem.
InthecontextofWestpower’sguidesforconnection,distributedgenerationcomprises:
• Smallsystemsoflessthan5kWcapacity;
• Mediumsystemsofbetween5kWand30kWcapacity;
• Largesystemsbetween30kWand1000kWcapacity;
Largesystemswouldnormallybeassociatedwithindustrialsitesorasdedicatedgenerationfacilities.
Westpower’spolicyistoactivelyencouragedistributedgenerationasameansofreducingsystemlossesandimprovingboththereliabilityandqualityofsupplytothearea.
CustomersinterestedindevelopingsuchfacilitiesareinvitedtocontactWestpower’sagentElectroNetServicestorequestacopyofthedistributedgenerationinformationpack.Thispackwillprovidevaluableassistanceinplanningandengineeringanacceptablesolution.
Formal application forms will be available to ensure that the appropriate information is provided to allowWestpowertoapproveconnectiontoitsnetworkandensurecompatibilitywiththeexistingreticulationnetwork.
Anynewdistributedgeneration installationalsorequirescontractualarrangementstobeput inplacewitharetailertopurchaseanyexcesselectricitygenerated.Westpowermaythencredittheretailerfortheenergythatisexportedatthesamepricethattheretailerischargedforthedeliveryofenergy,providinganetbenefittothedistributedgenerator.
RefertoSection5.7formoredetailedinformation.
8.11 Asset Management System Improvement Process
8.11.1 IntroductiontoPAS-55
Westpower has evaluated its assetmanagement systems by conformingwith theU.K. specification PAS-55-1:2008.
PAS-55isthepubliclyavailablespecificationfortheoptimisedmanagementofphysicalassetsandinfrastructure.DevelopmentofPAS-55wassponsoredintheUnitedKingdombytheInstituteofassetmanagementinresponsetoaneedidentifiedbyregulatorsandassetowners.Thiswasdevelopedinordertodefineassetmanagementinthecontextofphysicalinfrastructurebysettingoutthekeyattributesofeffectiveassetmanagementsystems.
PAS-55 consists of 24 key requirementswhich together provide a framework defining current best practiceforthewhole-of-lifemanagementofphysicalassets.The24keyelements,showndiagrammaticallyabove inFigure8.2,worktogethertoprovidearigorousprocessbasedontheplan-do-check-actcycle.Therequirementslinkstrategicbusinessobjectivestodetailedoperationalplans,ensuringthatoperatingandcapitalinvestmentis targetedat realisingassetperformanceand riskprofiles thatmeet stakeholderexpectationsandbusinessobjectives.
ASSETMANAGEMENTPRACTICES 247
PAS-55,whilenothavingthestatusofaBritishoranISOstandardisanauditablespecification.AssuchWestpowerwillseektoobtainindependentexternalcertificationverifyingconformancewiththedocumentedrequirements.Suchexternalcertification isbecomingrecognizedbyassetownersandregulators internationallyasausefulmeanstodemonstrategoodgovernance,duediligenceinthemanagementofassetrelatedriskandoptimizedassetmanagementdecisionmaking.
Todate,Westpowerhasdocumented95%oftheprocessesrequiredforconformitywithPAS-55andwillspendthenexttwelvemonthsimplementingtheseprocesses,reviewingtheireffectivenessandcommencingaprogramofcontinualimprovement
8.11.2 PurposeandObjectivesofthisReview
AdetailedgapanalysisofWestpower’sassetmanagementsystemhasbeenconductedagainsttherequirementsofPAS-55withtheobjectiveofconformanceorcertificationagainstthedocument.Theobjectivesofthisreviewwereto:
1. ProvideanunderstandingofWestpower’scurrentpositionwithconformancewithPAS-55.
2. Identify areaswhere changes to assetmanagement systemwould yield continual improvement in assetperformanceandriskmanagement.
4.4 Asset management enablers and controls
4.4.1 Structure, authority and responsibilities
4.4.2 Outsourcing of asset management activities
4.4.3 Training, awareness and competence
4.4.4 Communication, participation and consultation
4.4.5 Asset management system documentation
4.4.6 Information management
4.4.7 Risk management
4.4.8 Legal and other requirements
4.4.9 Management of change
4.5 Implementation of asset
management plans
4.5.1 Life cycle activities
4.5.2 Tools, facilities and equipment
4.3 Asset management strategy,
objectives and plans
4.3.1 Asset Management Strategy
4.3.2 Asset Management Objectives
4.3.3 Asset Management Plans
4.3.4 Contingency Plans
4.7 Management review 4.2 Asset Management Policy
4.1 General Requirements
PAS 55:2008
Management
system structure
Act Plan
Do
Check
4.6 Performance assessment
and improvement
4.6.1 Performance and condition
monitoring
4.6.2 Investigation of asset
related failures, incidents
and nonconformities
4.6.3 Evaluation of compliance
4.6.4 Audit
4.6.5 Improvement actions
4.6.6 Records
8.3-PASS-55AssetManagementSystemElements
248 WESTPOWERASSETMANAGEMENTPLAN2012-2022
8.11.3 ImprovementPlan
WestpowerhasadoptedprogressiontowardsPAS-55conformanceasakeyperformanceindicatorintheoverallbusinessStrategicPlan.
As part of this process, the Board signed off on the Asset Management Policy on (DATE), which providesthe governance framework for all asset management activities. This ensures strategic alignment betweenWestpower’sbusinessgoalsandmanagementoftheasset.
Overthenextyear,Westpowerplanstocompleteanumberofinitiativesaimedatreducingtheconformancegapsidentifiedintherestofthissection.
Keytargetsforthecomingyearinclude:
• AformalanddocumentedreviewoftheperformanceofthisAMPasrequiredbyPAS-55;
• Implementationoftheformallydocumentedassetmanagementsystem;and
• Attheendoftheperiod,reviewconformancewithPAS-55:2008;
• Preparingacompliancestrategyandtimeframe.
8.11.4 GapAnalysisAssessmentCriteria
PAS-55 contains 24 keymandatory requirementswhich canbe further subdivided to a total of 164discreteelements for evaluation. Questions chosen to reflect the intent of these elements were scored semi-quantitativelytoprovideameasureoftheorganisationalignmentormaturityinthatarea.AsummaryofthescoringmethodologyisshowninTable8.5below.
Figure8.4-PAS-55AssetManagementFramework
ASSETMANAGEMENTPRACTICES 249
8.12 Detailed Findings
8.12.1 AssetManagementSystem
“Theorganisationshallestablish,documentandmaintainandcontinuallyimproveanAMSinaccordancewiththerequirementsofPAS-55.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
The intent of this group of requirements is that the organisation recognises asset management as a corebusinessfunction,anddemonstratescommitmenttothedevelopmentandcontinualimprovementoftheassetmanagementfunction.ThisisclearlyevidentwithinWestpowerthroughtheAMP,theSCIandtheorganisationstructure.
Table 8.5 - Gap Analysis Assessment Criteria
Rating % PAS 55 Maturity Level Evaluation Criteria
1 0 Innocent ThiselementofPAS55isnotinplace;theorganisationisunawareoftheneedforthiselement.
2 20 Aware TheorganisationhasabasicunderstandingoftherequirementsofthiselementofPAS55andisintheprocessofdecidinghowthiselementwillbeapplied.
3 40 DevelopingTheorganisationhasasoundunderstandingofthiselementofPAS-55.IthasbeendecidinghowthisPAS-55elementwillbeappliedandworkisprogressing
onimplementation.
4 60 Compliant ThiselementofPAS-55isimplementedasrequired;minorinconsistenciesmayexist.
5 80 Excellence ThiselementofPAS-55iscomprehensivelyimplementedandintegratedwithotherelements.
6 100 BeyondPAS55UsingprocessesandapproachesthatgobeyondtherequirementsofPAS-55,pushingtheboundariesofassetmanagementtodevelopnewconceptsand
ideas.
0
1
2
3
4
5
6
Esta
blish
an
d m
ain
tain
AM
S th
at co
nfo
rms to
all
req
uire
me
nts
of P
AS
55
-1.
AM
S d
eta
il a
nd
co
mp
lexity fits th
e s
ize
of
the
co
mp
an
y.
AM
S b
ou
nd
ary
is w
ell
de
fin
ed
.
An
effe
ctive
ove
rall
syste
m d
raw
ing
on
oth
er
co
mp
an
y s
yste
ms.
PAS-55 Aligned
250 WESTPOWERASSETMANAGEMENTPLAN2012-2022
TheconciseandauditabledocumentdefiningWestpower’sassetmanagementsystemclarifiesassetmanagementprocessesandenhancesWestpower’sabilitytodemonstratecompliancewithPAS-55.
Recommended Actions
ThatWestpowerconcentratesonimplementationoftheprocessesdefinedinitsoverarchingassetmanagementsystemdocumentation.Attheendoftheperiod,WestpowermustreviewtheperformanceoftheassetandtheassetmanagementsystemforconformancewithPAS-55toenhanceitscontinualimprovementprogram.
ThatWestpowercompletesafullinternalauditagainstPAS-55usingacompetentauditorpriortoendofMarch2013
8.12.2 ReviewagainstPAS55-1
“The organisation shall conduct a review to compare the current management of its assets against therequirementofPAS55-1.”
Table 8.12.1 4.1 - General Requirements
Q# PAS-55 Criteria Score MaturityLevel Comments AMS
Section
4.1.1 Asset Management System
1 aEstablishandmaintainAMSthatconformstoallrequirementsof
PAS55-1.3 Developing
ThedraftAMSisagooddocumentforestab-lishingPAS55intoWestpower.Allelementsneedtobesatisfiedtoreceivefullcompliancescoreforestablishment.Unabletoscoreformaintainasnotfullyimplementedyet.PAS55wasusedin2008asatoolforpracticesreviewandreportedinthe2011AMP.
All
2 b AMSdetailandcomplexityfitsthesizeofthecompany. 4 Compliant ThedraftAMSisanappropriatesizefor
Westpower. All
3 c AMSboundaryiswelldefined. 4 Compliant
TheAMSboundaryisdefinedaselectricitydistributionfortheWestCoast.Therelation-shipwithElectronetisclearlydefinedandthe
linktoWestpowerforPAS55purposes.
2
4 d Aneffectiveoverallsystemdrawingonothercompanysystems. 4 Compliant
TheAMSlinkswelltootherexistingsystemsandthereisgoodlinkstoassociateddocu-
mentsinSection5.Therearelinkstoexistingpoliciesasnotedbelowin4.9.
All
ASSETMANAGEMENTPRACTICES 251
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Westpowerhasdevelopedastand-aloneassetmanagementsystemasrequiredbyPAS-55.ThedocumenthasbeenindependentlyreviewedbyAECOMandthegapanalysisispresentedhereinthisAMP.ThegapanalysisrelatesmainlytothedocumentedprocessesbutitstillremainsforWestpowertofullyimplementandreviewtheseprocesses.
Table 8.12.2 4.1 - General Requirements
Q# PAS-55 Criteria Score Maturity Level Comments AMS Sec-
tion
4.1.2 Review against PAS 55-1
5 a ReviewagainsttheStrategicPlan. 4 CompliantThedraftAMSisalignedwiththeSCIandStrategicPlan,Westpower’smainstrategic
plans.3
6 b Reviewcompliancewithlegislationandregulations. 4 Compliant
ThedraftAMSsummariseslegislativecom-plianceinAMPolicy,StrategyandObjec-tives,Sections4.8,5.8and6.6respectively.
Itisreportedtotheboardquarterly.
4.8,5.8,6.6
7 c Identificationandevaluationofas-setmanagementrisks. 4 Compliant
Ariskmanagementassessmenthasbeencompletedthatcoverslikelyriskevents
includingcriticalassets,operations,futureplanningandenvironmental.Eachidenti-fiedriskisassessedforimpact,effective-nessandlikelihoodratingsresultinginaconsequencesrating.ThisissummarisedindraftAMSSection5.7andtheassociated
documentriskmanagementanalysis.
5.7
0
1
2
3
4
5
6
Esta
blish
an
d m
ain
tain
AM
S th
at co
nfo
rms to
all
req
uire
me
nts
of P
AS
55
-1.
AM
S d
eta
il a
nd
co
mp
lexity fits th
e s
ize
of
the
co
mp
an
y.
AM
S b
ou
nd
ary
is w
ell
de
fin
ed
.
An
effe
ctive
ove
rall
syste
m d
raw
ing
on
oth
er
co
mp
an
y s
yste
ms.
PAS-55 Aligned
252 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Actions
Thattheassetmanagementsystembefullyimplementedandreviewedwiththeintentionofseekingtoobtainindependentexternalcertificationwithintwoyears,verifyingcompliancewiththedocumentedrequirements.Aninternalauditatthecompletionofthefirstyearwouldprovidequalityguidance.
8.12.3 AssetManagementPolicy
“Theorganisation’stopmanagementshallauthoriseanoverallassetmanagementpolicy.”
Table 8.12.2 4.1 - General Requirements
Q# PAS-55 Criteria Score Maturity Level Comments AMS Sec-
tion
8 d ExistingAMpracticesandproce-dures. 4 Compliant
Theexistingpracticesaredocumentedwellinthe2011AMP.Thiscouldbestrength-enedwithastatementinSection7AMPaboutthereviewofExistingAMpractices.
ExistingproceduresarestatedinthelinkstoassociateddocumentsintheAM
Strategy.
5,7
9 eReviewtheperformanceofassetsandassetsystem(suitability,utilisa-
tion,conditionandcosts).4 Compliant
Assetmanagementperformanceissum-marisedindraftAMSSection5.2,Reli-
ability.Therestillneedstobealinktothe2011AMP(Section3AssetsCovered).Itisstatedthatoveralltheassetsareingoodconditionbutthereneedstobeastate-mentthatWestpowerwishestoprotectthatposition.Weunderstandthatassetsarestillnotperformingandnotmeeting
thetargets.Thisshouldbeexplicitlystated
5.2
10 f Reviewfeedbackfrompreviousincidentinvestigations. 4 Compliant
Thereviewoffeedbackfrompreviousincidents,accidentsandemergenciesisprovidedinthedraftAMSSection6.1Safetyand16.2InvestigationofFailure,IncidentsandNonconformities.AnAM
ReviewProcesshasbeendevelopedwhichincludesperformanceofincidentinvestiga-
tions,andstartedin2011.
6.1,16.2
11 g Relevantmanagementsystems,competencyandresourcing. 4 Compliant
ThereisaninternalbusinessintelligencesystemTheVaultthatholdstraining
records.WeunderstandthatWestpowerhasaSharepointoperatingthathosts
dedicatedhealthandsafetyinformation,trainingrecordsandincidences.ThereisaformalHealthandSafetyCommittee,stafftrainingprogramsandHazardIdentifica-tionProgramasdetailedinAMStrategy.ThereisalsoadedicatedAssetManage-
mentGroupwithabout14peoplebasedatElectronet,reportingtoWestpower’sAssetManager.ThetrainingforthisgroupisnotcoveredbyTheVaultbutthereisasepa-ratetrainingrecordfortheAMGandthisis
anassociatedocumenttoSection10.
5.1,10
ASSETMANAGEMENTPRACTICES 253
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Theintentofrequiringanassetmanagementpolicyistoprovideareferencedocument,endorsedbythemostseniormanagementof thebusiness,defining theboundariesor frameworkwithinwhichassetmanagementdecisionsmustbemadewithintheorganisation.Westpowerhasdevelopedadraftpolicywhichisalignedwiththisrequirement.CompletionandendorsementofthepolicywouldseetheaboveratingsalignwithPAS55.
Table 8.12.3 4.2 - Asset Management Policy
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.2 Asset Management Policy
12 a Consistentwithstrategicplan. 4 Compliant
ThepolicyisbasedonWestpower’sSCI(dated2011-2013)andtheStrategicPlan(dated30September
2010).Thesearetheirmainstartegicplans.4
13 bAppropriateinnatureandscaleoforganisation’sas-
sets.4 Compliant
ThedraftAMPpolicyisthreepagesinlengthwhichisappropriateformostpoliciesandconsideringWest-
powerisarelativelysmallEDB.4
14 c Consistentwithotherpoli-cies. 4 Compliant
ThealignmentwithotherpoliciesissummarisedindraftAMSSection4.9includingtheMaintenanceandOperationPolicy,andhealthandsafety.TherearelinkstootherpoliceslistedattheendofAMSSection4.9.Itwouldbedesirabletohaveaseparateenvironment
policy.
4.9
15 dConsistentwithorganisa-tion’soverallriskmanage-
mentframework.4 Compliant ThisisadequatelyaddressedinAMSSection4.7. 4.7
0
1
2
3
4
5
6
Co
nsis
ten
t w
ith
str
ate
gic
pla
n.
Ap
pro
pria
te in
na
ture
an
d
sca
le o
f o
rga
nis
atio
n’s
asse
ts.
Co
nsis
ten
t w
ith
oth
er
po
licie
s.
Co
nsis
ten
t w
ith
org
an
isa
tio
n’s
ove
rall r
isk
ma
na
ge
me
nt fr
am
ew
ork
.
Fra
me
wo
rk e
na
ble
s A
M
str
ate
gy, o
bje
ctive
s a
nd
pla
ns to
be
im
ple
me
nte
d.
Co
mm
itm
en
t to
co
mp
ly
with
le
gis
latio
n.
Prin
cip
les to
be
ap
plie
d
su
ch
as h
ea
lth
an
d s
afe
ty,
an
d s
usta
ina
ble
de
ve
lop
me
nt.
Co
mm
itm
en
t to
co
ntin
ua
l
imp
rove
me
nt.
Do
cu
me
nte
d,
imp
lem
en
ted
an
d
ma
inta
ine
d.
Co
mm
un
ica
ted
to
sta
ke
ho
lde
rs
Re
vie
we
d p
erio
dic
ally.
PAS-55 Aligned
254 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Actions
That the draft asset management policy is formally endorsed by directors and the matter recorded in thecompanyminutes
• Thattheapprovaldateandauthorityberecordedonthepolicystatement;
• Thatthepolicybeformallycommunicatedthroughouttheorganisation;
• Setareviewcycle;itissuggestedthatthiscoincidewithfinalisationoftheSCIorotherstrategicplanningdocuments;
8.12.4 AssetManagementStrategy
“Theorganisationshallestablish,document,implementandmaintainalong-termassetmanagementstrategyauthorisedbytopmanagement.”
Table 8.12.3 4.2 - Asset Management Policy
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
16 eFrameworkenablesAMstrategy,objectivesandplanstobeimplemented.
4 Compliant
TheAMPolicyinSection4setstheframeworkfortheAMstrategy,andobjectiveswell.Weunderstandthattherearemultiplesourcesofworkneedsthatarenotwelllinkedtothefinancialpoliciesandbudgets.Frequentlytheplannedcapitalworksprogrammesarenotdelivered.Thereneedstobecontrolsandconse-quencesfornotdeliveringtheplannedprogramme.ThiswouldbebettercoveredinSection15Implemen-
tationofAMPs.
4
17 f Commitmenttocomplywithlegislation. 4 Compliant
ThisisaddressedadequatelyinAMSSection4.8althoughbrieflyandnowstatesthekeylegislation
suchasHealthandSafetyinEmploymentActandtheElectricityAct.
4.8
18 g
Principlestobeappliedsuchashealthandsafety,andsustainabledevelop-
ment.
4 Compliant
Thisisaddressedadequatelyforhealthandsafety,andsustainabilityinAMSSections4.1and4.4respectively.Moredepthtohealthandsafetyprincipleswouldbe
helpful.
4.1,4.4
19 h Commitmenttocontinualimprovement. 4 Compliant Thisisaddressedadequatelyundercontinualimprove-
mentinAMSSection4.4. 4.4
20 i Documented,implementedandmaintained. 3 Develop-
ing
TheAMPolicyisdocumentedasprovidedinAMSSec-tion4.ThereisaformalreviewnowasstatedindraftAMSSection4.10.Unabletoscoreformaintainasnot
fullyimplementedyet.
4.4,4.10
21 j Communicatedtostake-holders 4 Compliant
CommunicationwithstakeholdersissummarisedinAMSSection4.4SustainableunderCommunication.Thisissupportedbyanassociateddocumentshow-ingthekeystakeholdersandtheirinterestarea.ThepolicyiswritteninplainEnglishandiseasytoreadsoprovidesagoodplatformforcommunicationwithstakeholders.Itisimportantthatthereistopmanage-mentendorsementassuggestedwithCEOsignature
thatisvisibletostaffandserviceproviders.Weunder-standthattheAMSwillbeavailableontheintranet.
4.3,4.4
22 k Reviewedperiodically. 4 CompliantThereisastatementonannualreviewinAMSSection4.4asdiscussedabove.ThereviewhistorywillbeshowninSection4.10aftereveryannualreview.
4.4,4.10
ASSETMANAGEMENTPRACTICES 255
Review against PAS-55 Requirements
Observations and Improvement Opportunities
In thePAS-55context, asset strategies refer to theoverall approach tomanaginganasset class i.e.defininghowtheasset is tobemanaged,sothatdetailedoperationalplans for individualassetscanbederived.TheWestpowerassetmanagementsystemcontainsadescriptionofassetstrategiesbyassetclass.Improvementscouldbemadebylinkingassetstrategiestoariskmanagementprocess.
Table 8.12.4 4.3 - Asset Management Strategy, Objectives and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.3.1 Asset Management Strategy
23 aConsistentwithpolicyandorganisationalstrategicplan.
4 Compliant ThisisaddressedintheintroductionparagraphatthestartofAMSSection5. 5
24 bConsistentwithotherorganisationalpolicies
andstrategies.4 Compliant
Therearegoodlinkstoassociateddocumentsattheendofeachstrategysection,althoughmostofthesedocumentsarenotstrategiesorpolicies.ThestrategyisconsistentwiththeAMSpolicywiththesamefor-mat.ItwouldusefultoshownhowtheMaintenanceandOperationsPolicyrelatestotheAMStrategy,
especiallySection5.2Reliability.
5
0
1
2
3
4
5
6
Co
nsis
ten
t w
ith
po
licy a
nd
org
an
isa
tio
na
l str
ate
gic
pla
n.
Co
nsis
ten
t w
ith
oth
er
org
an
isa
tio
na
l p
olicie
s a
nd
str
ate
gie
s.
Co
nsid
ers
sta
ke
ho
lde
r re
qu
ire
me
nts
.
Life
cycle
ma
na
ge
me
nt
req
uir
em
en
ts o
f a
sse
ts.
Asse
t re
late
d r
isks,
an
d a
sse
t a
nd
asse
t syste
m
cri
tica
litie
s.
Ide
ntifie
s t
he
fu
nctio
n,
pe
rfo
rma
nce
an
d c
on
ditio
n o
f
exis
tin
g a
nd
cri
tica
l a
sse
ts.
Sta
te f
utu
re f
un
ctio
n,
pe
rfo
rma
nce
an
d c
on
ditio
n.
Cle
arl
y s
tate
s p
rin
cip
le m
eth
od
s o
f a
sse
t
ma
na
ge
me
nt.
Pro
vid
es s
uff
icie
nt
gu
ida
nce
fo
r A
M o
bje
ctive
s a
nd
AM
P t
o b
e p
rod
uce
d.
Cri
teri
a f
or
op
tim
isin
g A
M o
bje
ctive
s a
nd
pla
ns.
Co
mm
un
ica
ted
to
sta
ke
ho
lde
rs A
M s
tra
teg
y r
ela
ted
ob
lig
atio
ns.
Re
vie
we
d p
eri
od
ica
lly f
or
eff
ective
ne
ss
PAS-55 Aligned
256 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table 8.12.4 4.3 - Asset Management Strategy, Objectives and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
25 c Considersstakeholderrequirements. 4 Compliant
Thereisconsiderationofstakeholderrequirementsasfollows:1.Thereisageneralstatementaboutcommunicatingwithcon-tractorsandpublicattheendofSection5.1,Safe-
ty.2.ThereisageneralstatementaboutsurveyingconsumersonaregularbasisandacustomercomplaintsysteminSection5.2.3.ThereisageneralstatementaboutdiscussionswithTranspowerinSection5.3Security.4.Thereisageneralstatementaboutcommunicat-ingwiththeBoardaboutoilspillsinSection5.6EnvironmentalImpact.5.Thereisageneralstatementaboutdiscussion
withstakeholdersontheAMSattheendofAMSSection5.8,CompliancewithLegislation.ThereisgoodinformationabouttwoindustrygroupsENAandEEAthatWestpowerparticipateswith.
6.ThedraftAMSSection5.9summarisescommuni-cationwithstakeholders.Thisincludesalinktothe
Westpowerstakeholdermatrix.
5.1,5.2,5.3,5.6,5.8,5.9
26 d Lifecyclemanagementrequirementsofassets. 4 Compliant
AMSSection5.4SustainabilityprovidesastatementaboutassetlifecyclemanagementwithareferencetoSection6oftheAMP.Itcouldbestrengthenedby
identifyingthekeyassetissuesforWestpower.
5.4
27 eAssetrelatedrisks,andassetandassetsystem
criticalities.4 Compliant
AMSSection5.7detailstheriskprocessesWestpowerundertakeswithfiveassociateddocuments.Assetriskiscoveredundertheregularinspectionandthedesignstandardsinplace.ItisalsocoveredwithassetriskmanagementassessmentsummarisedinSection5.7withdetailinRiskManagementAnalysisandProcess.CriticalassetsaresummarisedinAMSSection5.7with
detailintheRiskManagementAnalysis.
5.7
28 f
Identifiesthefunction,performanceandcondi-
tionofexistingandcriticalassets.
4 Compliant
TheassessmentofperformanceandconditionofexistingandcriticalassetsiscoveredinAMSSection
5.2Reliability.Performanceisdiscussedatahighlevelbutdoesnotcovercriticalassetsasrequired.We
suggestthatthereisdetailontheactualperformanceofthecriticalassets.Referencescanbemadeto
therelevantAMPsectionsothereisnorepetitionofmaterial.Thereisgooddiscussiononassetcondition
oftheexistingandcriticalassets.
5.2
29 gStatefuturefunction,
performanceandcondi-tion.
4 Compliant
Thedesiredfuturefunction,performanceandcondi-tionoftheexistingandcriticalassetsissummarisedinAMSSection5.2Reliability.Thisincludesastatementthatyourcustomersaresatisfiedwiththecurrentas-setperformancefromrecentsurveysanddonotwishtheircoststoincrease.Assetperformanceismea-
suredbySAIDIandSAIFIwhichisconsistentwithyourStrategicPlan(forSAIDI).
5.2
ASSETMANAGEMENTPRACTICES 257
Recommended Actions
ThatWestpowercontinue itsdevelopmentofa formal riskmanagementsystemwhichprovides input totheassetstrategyprocess(seelaterrecommendations).
Document responsibility and target timeframes for implementation of the asset management strategy (forexampleanannualassetplanningcalendar)forthedevelopmentofdetailedoperationalplans.
8.12.5 AssetManagementObjectives
“The organisation shall establish and maintain documented asset management objectives which shall bemeasureable,consistentwiththestrategy,communicatedtostakeholdersandperiodicallyreviewed.”
Table 8.12.4 4.3 - Asset Management Strategy, Objectives and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
30 hClearlystatesprinciplemethodsofassetman-
agement.4 Compliant
Thestrategyprovidestheprinciplesforas-setmanagementinsomeareasandisweakin
otherareasasfollows:Se-curityofsupplyprinciplesarediscussedadequatelyinAMSSection5.3Security.Thefourwellbeingsarediscussedad-
equatelyinAMSSection5.4Sustainability.Riskmanagementprinciplesaredis-cussedadequatelyinAMSSection5.7.
WholeoflifecostingsisstatedinAMSSections5.4Sustainability.
5.3,5.4,5.7
31 i
ProvidessufficientguidanceforAMobjec-tivesandAMPtobe
produced.
4 CompliantThereisguidanceatquitehighlevelincludingsecurityprogrammessuchasTranspower’sWCGUPandregu-
larequipmentinspectionprogramme.5.3,5.7
32 jCriteriaforoptimis-
ingAMobjectivesandplans.
4 Compliant
TheoptimisationandprioritisationofAMobjectivesandplansissummarisedindraftAMSection5.4.
ThisismonitoredwiththeAMSReviewProcess.Thisshouldbeaddedformallyasanassociatedocument.
5.4
33 kCommunicatedtostake-holdersAMstrategyrelatedobligations.
4 Compliant
CommunicationwithstakeholdersissummarisedinAMStrategySection5aboutawarenessoftheirstrat-egyrelatedobligations.AMSSection5.1statesthattherearespecificforumswherestaffobligationsarediscussedattoolboxmeetingswiththeCEO.Thereisaspecificsectiononcommunicationwithstakehold-
ers,Section5.9.
5.1,5.8,5.9
34 l Reviewedperiodicallyforeffectiveness 4 Compliant ThereviewprocessforthestrategyisstatedinSection
5.10.ItisreviewedDecembereachyear. 17
258 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Review against PAS-55 Requirements
Observations and Improvement Opportunities
The intent of this requirement is that the assetmanagement organisation identifies a small number of keyassetmanagementobjectivesthatsetthedirectionforthedetailedplanningprocess.Thesecouldbehighleveldirection statements regarding asset performance, asset creation/replacement, safety and risk and financialperformance.
0
1
2
3
4
5
6
Ob
jective
s a
re
me
asu
rea
ble
.
Ob
jective
s a
re c
on
sis
ten
t
with
AM
Str
ate
gy.
Ob
jective
s a
re c
on
sis
ten
t
with
co
ntin
ua
l
imp
rove
me
nt.
Ob
jective
s a
re
co
mm
un
ica
ted
to
all
rele
va
nt
sta
ke
ho
lde
rs.
Ob
jective
s a
re
pe
rio
dic
ally r
evie
we
d.
Ob
jective
s c
on
sid
er
leg
al, r
eg
ula
tory
an
d
sta
tuto
ry r
eq
uir
em
en
ts.
Ob
jective
s t
ake
acco
un
t
of
the
exp
ecta
tio
ns o
f
sta
ke
ho
lde
rs a
nd
fin
an
cia
l, o
pe
ratio
na
l a
nd
bu
sin
ess r
eq
uir
em
en
ts.
Ob
jective
s t
ake
acco
un
t
of
asse
t m
an
ag
em
en
t
risk.
Ob
jective
s c
on
sid
er
imp
rove
me
nt
op
po
rtu
nitie
s,
inclu
din
g
ne
w t
ech
no
log
ies,
AM
too
ls a
nd
pra
ctice
s.
PAS-55 Aligned
Table 8.12.5 4.3 - Asset Management Strategy, Objective and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.3.2 Asset Management Objectives
35 a Objectivesaremea-sureable. 4 Compliant
Theobjectivesaresummarisedundereachstrategyareainbulletpointformatwithgoodlinkstoassociateddocuments.Theobjectivemeasuresforeachareaarelisted,relevantforWestpower,andcurrentlymeasured.Itwouldbehelpfuliftheobjectiveswerestatedinmea-surabletermsforeachobjective.Someareandsome
arejustreferenced.ThePAS55exampleis:Toachieveanaverageof97%systemavailabilityontheroute.Optimi-sationbetweenperformance,condition,costandriskis
addressedatahighlevelunderSustainability.
6,6.1,6.2,6.3,6.4,6.5,6.7,6.8
36 bObjectivesare
consistentwithAMStrategy.
4 Compliant Theobjectivesarelinkedtoeachstrategy,iesafety,reli-ability. 6
37 cObjectivesarecon-sistentwithcontinual
improvement.3 Develop-
ing
TheobjectivesarereviewedannuallyasstatedinSection6.11.ThiscouldbestrengthenedwithastatementthatthiscontinualimprovementisundertakenwiththeAMP
updateintheLOSsectioneveryyear.
6.11
ASSETMANAGEMENTPRACTICES 259
Westpowerhasanumberofobjectivespublishedintheassetmanagementplan(levelsofservicesection)andin the SCI thatmeet the intentof providingbroadobjectives that canbe furtherbrokendown into specificoperational targets and plans. Westpower’s asset management system clearly and concisely identifies anddocumentskeyassetmanagementobjectivesflowingdirectlyfromthecorporatestrategy.
Recommended Actions
That Westpower further develops key asset management objectives and clearly communicates these withstakeholders.Ensure thatwhendevelopingobjectives thatall requirementsofPAS-5514.3.2are taken intoconsiderationanddocumented.
8.12.6 AssetManagementPlans
“Theorganisationshallestablish,documentandmaintainAMPstorachievetheassetmanagementstrategyanddelivertheobjectivesacrossthelifecycleactivities.”
Table 8.12.5 4.3 - Asset Management Strategy, Objective and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
38 dObjectivesarecom-municatedtoall
relevantstakeholders.3 Develop-
ing
Communicationoftheobjectivestoallrelevantstake-holdersisstatedinAMSSection6.9.Itisstatedthatcommunicationhasbeenlimitedtodatebuttherearefutureplans.Thiscriterionisscoredasdevelopinguntil
theseareimplemented.
6.9
39 e Objectivesareperi-odicallyreviewed. 4 Compliant TheobjectivesarereviewedannuallyasstatedinSection
6.11. 6.11
40 f
Objectivesconsiderlegal,regulatoryandstatutoryrequire-
ments.
4 CompliantAMSSection6.7summariseslegislativecompliance.Itisnotedthatacompliancereportwillbeaddedasan
associatedocument.6.7
41 g
Objectivestakeac-countoftheexpecta-tionsofstakeholdersandfinancial,opera-tionalandbusiness
requirements.
4 Compliant
Stakeholdersandfinancial,operationalandbusinessrequirementsareconsideredunderReliability,Security,SustainabilityandCostefficiencyObjectives.ThesearereportedtostakeholderthroughInformationDisclosure.
6.2,6.3,6.4,6.5
42 hObjectivestake
accountofassetman-agementrisk.
4 CompliantRiskmanagementobjectivesaresummarisedinAMSSection6.6includingthemanagementofrisk,critical
assetsandemergencyplanning.
6.1,6.2,6.3,6.6,
6.7
43 i
Objectivesconsiderimprovementop-
portunities,includingnewtechnologies,AMtoolsandprac-
tices.
4 Compliant AMSSection6.10summarisesimprovementopportuni-tieswithcurrentinitiatives. 6.1
260 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Review against PAS-55 Requirements
Observations and Improvement Opportunities
While it is almost certain that activities areoptimisedandprioritisedby theassetmanagement teamusingcollectiveexperience,Westpowershouldconsiderimplementingaformalprojectranking/prioritisationschemeincorporatingtheriskmanagementmethodology.Suchanapproachcouldbeofassistanceinmanaginganygapbetweenavailablefunds/resourcesandproposedprojects. ItwasnotapparentfromthematerialpresentedthatWestpowerclearlyallocatesaccountabilitytoindividualsforallassetmanagementobjectivesoroutcomes,ifthisisthecasethenclearbenefitscanbeobtainedbyclarifyingthispoint.Alsonotapparentfrommaterialprovidedisaprocesstoclearlycontrolandmanageprojecttimingandcosts.
0
1
2
3
4
5
6A
MP
sp
ecifie
s t
asks a
nd
activitie
s r
eq
uir
ed
to
op
tim
ise
co
st,
ris
k a
nd
pe
rfo
rma
nce
.
AM
P d
esig
na
tes
resp
on
sib
ilitie
s a
nd
au
tho
ritie
s f
or
the
ach
ieve
me
nts
of
AM
ob
jective
s.
AM
P p
rovid
es t
he
me
an
s
an
d t
ime
sca
les f
or
actio
ns
to b
e a
ch
ieve
d.
PAS-55 Aligned
Table 8.12.6 4.3 - Asset Management Strategy, Objective and Plans
Q# PAS-55 Criteria Score MaturityLevel Comments AMP
Section
4.3.3 Asset Management Plans
44 aAMPspecifiestasksandac-tivitiesrequiredtooptimisecost,riskandperformance.
4 Compli-ant
TheoptimisationofcostandriskisstatedinAMSSection7withgoodreferencingtotheAMP.As-setperformanceisdiscussedwellindraftAMS
Section7,supportedwithgoodreferencingtotheAMP.
7
45 b
AMPdesignatesresponsi-bilitiesandauthoritiesfortheachievementsofAM
objectives.
4 Compli-ant
TheresponsibilitiesandauthoritiesfortheachievementofAMobjectivesarecoveredinthedraftAMSSection7byWestpower’sAssetMan-agerwithsupportfromElectroNetServiceLtd.
7
46 cAMPprovidesthemeansandtimescalesforactions
tobeachieved.4 Compli-
ant
ThedevelopmentoftheworkplanisdiscussedwellindraftAMSSection7,supportedwithgood
referencingtotheAMP.7
ASSETMANAGEMENTPRACTICES 261
Recommended Actions
ThatWestpower implement amethodology for ranking/rating assetmanagement initiatives to assist in theoptimisation,anddocumentationoftheoptimisationprocess.
ThatWestpowerconfirmsthatithasinplaceadetailedprogrammeofworkdefiningprojectsandinspectionandmaintenanceprogrammes.Theprogrammeshouldallocateaccountabilityforoutcomes,targetdates,andbudgets.Theprogramshouldbesupportedbyarobustprocessformonitoringdelivery,quality,safetyandcost.Thisisdrivenfurtherininformationdisclosurerequirements2008.
8.12.7 ContingencyPlanning
“The organisation shall establish, implement andmaintain appropriate plans and procedures for identifyingandrespondingtoincidentsandemergencysituationsandmaintainingthecontinuityofcriticalmanagementactivities.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
PAS-55requiresthatcredibleemergencyscenariosareconsideredandthatcontingencyplanningisinplace.
0
1
2
3
4
5
6
Co
ntin
uity p
lan
co
nsid
ers
asse
t re
late
d r
isk.
Co
ntin
uity p
lan
co
nsid
ers
po
ten
tia
l d
isru
ptio
n to
th
e
critica
l A
M a
ctivitie
s.
Co
ntin
uity p
lan
co
nsid
ers
the
mo
st a
pp
rop
ria
te
resp
on
se
actio
ns.
Co
ntin
uity p
lan
co
nsid
ers
the
co
mp
ete
ncy a
nd
tra
inin
g o
f p
ers
on
ne
l.
Co
ntin
uity p
lan
co
nsid
ers
the
ne
ed
s o
f th
e
sta
ke
ho
lde
rs a
ffe
cte
d b
y
the
em
erg
en
cy.
PAS-55 Aligned
262 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Action
Thatthecontingencyplanscurrentlyinplacebeformallyreviewedanddocumentedforeffectiveness.
8.12.8 ContingencyPlanningInformation
“The plans and procedures shall identify how the organisationwill respond to, andmanage, incidents andemergencysituations.”
Table 8.12.7 4.3 - Asset Management Strategy, Objective and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.3.4 Contingency Planning
47 a Continuityplanconsidersassetrelatedrisk. 4 Compli-
ant
ThedraftAMSSection8ontheContingencyPlanningsummarisesWestpower’scontingencyplanning.TheEmergencyResponsePlan(ERP)islistedasanassociateddocument.AssetrelatedriskisdetailedindraftAMSSection8.1whichis
mainlyfocusedonTranspower’sGXPs.
8.1
48 bContinuityplanconsiderspotentialdisruptiontothe
criticalAMactivities.4 Compli-
ant
ThedraftAMSSection8.1considersdisruptiontocriticalAMactivitiesespeciallyGXPsandCBD
areas.8.1
49 cContinuityplanconsid-ersthemostappropriate
responseactions.4 Compli-
antResponseactionsarecoveredindraftAMSSec-tion8.3andintheERP,Section4Planning. 8.3
50 dContinuityplanconsiders
thecompetencyandtrainingofpersonnel.
4 Compli-ant
ThecompetencyandtrainingofpersonnelinanemergencyresponseissummarisedindraftAMSSection8.4.Thelinktoothersectionsshouldbe
stated,ieSection10.
8.4
51 e
Continuityplanconsiderstheneedsofthestakehold-ersaffectedbytheemer-
gency.
4 Compli-ant
StakeholderneedsaresummarisedindraftAMSSection8.5withtheemergencycontactlist.ThereisalsoastatementaboutCivilDefence
EmergencyManagement(CDEM)requirementsasalifelineutility.
8.3
ASSETMANAGEMENTPRACTICES 263
Review against PAS-55 Requirements
Observations and Improvement Opportunities
PAS-55requiresthatcredibleemergencyresponsesareconsideredandthatcontingencyplanninginformationisinplace.
0
1
2
3
4
5
6
Co
ntin
uity p
lan
in
clu
de
s
info
rma
tio
n o
n e
sse
ntia
l
pe
rso
nn
el.
Arr
an
ge
me
nts
fo
r in
tern
al
an
d e
xte
rna
l
co
mm
un
ica
tio
n.
Ma
inta
in o
r re
sto
re its
cri
tica
l A
M a
ctivitie
s.
Pro
vis
ion
of
ne
ce
ssa
ry
reso
urc
es r
eq
uir
ed
du
rin
g
an
in
cid
en
t.
Re
co
rdin
g o
f e
sse
ntia
l
info
rma
tio
n.
Pro
ce
ss f
or
retu
rnin
g t
o
no
rma
l o
pe
ratio
n.
PAS-55 Aligned
Table 8.12.8 4.3 - Asset Management Strategy, Objective and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.3.4 Contingency Planning
52 1Continuityplanincludesinformationonessential
personnel.4 Compli-
ant
TheSummaryBCPshowstheorganisationstruc-tureanddesignatedstaffdetailsinSection3ERPwithcontactlistinAnnexE.Itisalsosummarised
indraftAMSSection8.1.
8.1
53 2Arrangementsforinternalandexternalcommunica-
tion.4 Compli-
antInternalandexternalcommunicationisprovided
inERPSection5.6. 8
54 3 Maintainorrestoreitscriti-calAMactivities. 4 Compli-
ant
RestorationofcriticalAMactivitiesisprovidedinERPSection4andindraftAMSSection8.1with
mobilesubstation.8.1
55 4Provisionofnecessary
resourcesrequiredduringanincident.
4 Compli-ant
RequiredresourcesareprovidedinERPSection3andAnnexEforpersonnel,internalitemsinAnnexD,andexternalitemsandpersonnelinAnnexF.
8
56 5 Recordingofessentialinfor-mation. 4 Compli-
ant EssentialinformationisprovidedinERPAnnexB. 8
264 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Action
Thatthecontingencyplanninginformationcurrentlyinplacebereviewedforeffectiveness.
8.12.9 Structure,AuthorityandResponsibility
“Theorganisationshallestablishandmaintainanorganisationalstructureofroles,responsibilitiesandauthoritiesconsistentwiththeachievementofitsassetmanagementpolicystrategy,objectivesandplans.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Westpower has an appropriate organisational structure within which to implement an effective assetmanagementsystem.Areasforimprovementarecentredonimplementationofpolicyandstrategydocumentsandaneffectiveriskmanagementsystem.
0
1
2
3
4
5
6
Ap
po
intin
g a
me
mb
er
of
top
ma
na
ge
me
nt
for
resp
on
sib
ility o
f th
e A
MS
.
Ap
po
int
me
mb
ers
of
ma
na
ge
me
nt
for
resp
on
sib
ility o
f
the
AM
S d
elive
ry.
Org
an
isa
tio
n id
en
tifie
s a
nd
mo
nito
rs t
he
exp
ecta
tio
ns
of
sta
ke
ho
lde
rs.
En
su
re t
he
po
licy a
nd
str
ate
gy is c
on
sis
ten
t w
ith
th
e
org
an
isa
tio
na
l str
ate
gic
pla
n.
Co
nsid
ers
ad
ve
rse
eff
ects
th
e A
MS
mig
ht
ha
ve
on
oth
er
asp
ects
.
Co
nsid
er
the
via
bility o
f th
e A
MS
.
Asse
t re
late
d r
isks a
re id
en
tifie
d a
nd
in
clu
de
d o
n
org
an
isa
tio
na
l ri
sk f
ram
ew
ork
.
En
su
re a
va
ila
bility o
f su
ffic
ien
t re
so
urc
es.
Co
mm
un
ica
te t
o a
ll r
ele
va
nt
sta
ke
ho
lde
rs t
he
imp
ort
an
ce
of
co
mp
lyin
g w
ith
th
e r
eq
uir
em
en
ts o
f A
MS
in o
rde
r to
ach
ieve
its
org
an
isa
tio
na
l str
ate
gic
pla
n.
PAS-55 Aligned
Table 8.12.8 4.3 - Asset Management Strategy, Objective and Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
57 6 Processforreturningtonormaloperation. 4 Compli-
ant
ProcessforreturningtonormaloperationisprovidedinERPSection4andindraftAMSSection
8.3.8.3
ASSETMANAGEMENTPRACTICES 265
Recommended Actions
• Implementriskmanagementmethodology.Inadditiontoassetrelatedrisks, includesomeassessmentofintangibleriskssuchasreputation,staffmoraleetc.
• Consider benefits of providing a regular summary risk report to senior management and board forconsideration.Thisshouldformpartoftherecommendedriskmanagementprocess.
• EnsurethatmanagementcommunicatestheimportanceofdeliveringAMPs(e.g.workprograms)toachievetheorganisationsgoals.
• Improvecommunicationthroughouttheorganisationoftheassetmanagementstrategyandpolicy.
Table 8.12.9 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria ScoreMa-
turity Level
Comments AMS Section
4.4.1 Structure, Authority and Responsibilities
58 aAppointingamemberoftopmanagementforresponsibil-
ityoftheAMS.4 Compli-
ant
AMSresponsibilityisWestpower’sAssetManagerwithsupportfromElectroNetServiceLtdasde-tailedindraftAMSSections2and9.Werecom-mendthatthePAS55requirementsatthestartofSection9beremovedasitisunnecessary.Also
removethesecondorganisationstructure.
2,9
59 bAppointmembersofman-
agementforresponsibilityoftheAMSdelivery.
4 Compli-ant
AMSresponsibilityissupportedwithElectroNetServiceLtdasdetailedindraftAMSSections2and
9.2,9
60 cOrganisationidentifiesandmonitorstheexpectationsof
stakeholders.4 Compli-
ant
StakeholderexpectationsaresummarisedinAMSSection9includingastatementontheindepen-dentsurveyofstakeholderseverytwoyears.TheConsumerEngagementResultsislinkedasanas-
sociateddocument.
5,9
61 dEnsurethepolicyandstrat-egyisconsistentwiththe
organisationalstrategicplan.4 Compli-
ant
ThepolicyandstrategyarealignedwiththeSCIthroughthesamecategoriesanddirectionsetbytheSCI.DraftAMSSection9statesthatthe
achievementofthestrategicplaniscommunicatedwithstakeholders.
3,4,5,9
62 eConsidersadverseeffectstheAMSmighthaveon
otheraspects.4 Compli-
antAgapanalysistoolisusedtomanagetheadverse
effectscreatedbytheAMS. 9
63 f ConsidertheviabilityoftheAMS. 4 Compli-
ant
TheviabilityofthisAMSwillbedependentonitsreviewtoensureitisaliveandusefuldocument.TheAMSiscontrolledbytheAssetManagerasstatedinAMSSection2withresourcesfromtheAssetManagementGroup(AMG)asstatedinSec-
tion9.
2,9
64 gAssetrelatedrisksareidenti-fiedandincludedonorgani-sationalriskframework.
4 Compli-ant
Theprocessandframeworkforassetriskassess-mentissummarisedindraftAMSSection9. 5.7,9
65 h Ensureavailabilityofsuf-ficientresources. 4 Compli-
ant
TherearesufficientresourceswiththeAMGledbytheAssetManagerasstatedindraftAMSSections
2and9.2,9
66 i
Communicatetoallrelevantstakeholderstheimportanceofcomplyingwiththere-
quirementsofAMSinordertoachieveitsorganisational
strategicplan.
4 Compli-ant
Thecommunicationtostakeholdersandtheimpor-tanceofcomplyingwiththerequirementsofAMSarediscussedinSections9and11.Themainfor-malcommunicationiswiththeWestCoastElectric
PowerTrustsupportedbyconsumersurvey.
9,11
266 WESTPOWERASSETMANAGEMENTPLAN2012-2022
8.12.10OutsourcingofAssetManagementActivities
“Whereassetmanagementactivitiesareoutsourcedtheorganisationshallensurecontroloversuchaspects.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Westpowerhas outsourced its assetmanagement activities to ElectroNet Services Limited (100%ownedbyWestpower)andWestpower’sGeneralManager,AssetsandEngineeringServicesheadstheassetmanagementgroupinElectroNet.ThisstructureensuresthatcontroloftheassetmanagementactivitiesremainfirmlywithWestpower.
0
1
2
3
4
5
6
Org
an
isa
tio
n id
en
tifie
s a
nd
do
cu
me
nts
th
e p
roce
ss
an
d a
ctivitie
s t
o b
e
ou
tso
urc
ed
.
Org
an
isa
tio
n id
en
tifie
s a
nd
do
cu
me
nts
th
e p
roce
ss
an
d s
co
pe
fo
r sh
ari
ng
of
kn
ow
led
ge
an
d
info
rma
tio
n.
Org
an
isa
tio
n id
en
tifie
s a
nd
do
cu
me
nts
th
e a
uth
ori
tie
s
an
d r
esp
on
sib
ilitie
s w
ith
in
the
org
an
isa
tio
n f
or
ma
na
gin
g t
he
ou
tso
urc
ed
pro
ce
sse
s a
nd
activitie
s.
PAS-55 Aligned
Table 8.12.10 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.4.2 Outsourcing of Asset Management Activities
67 aOrganisationidentifiesanddocumentstheprocessandactivitiestobeoutsourced.
4 Compli-ant
TheoutsourcedAMGatElectronetledbyWest-power’sAssetManagerisstatedinAMSSections
2and9.2,9
68 b
Organisationidentifiesanddocumentstheprocessandscopeforsharingofknowl-
edgeandinformation.
4 Compli-ant
WestpowerhasSharePointandTheVaultwheremostinformationisstoredandaccessedasstatedindraftAMSection9.TheAMGislocatedintheGreymouthWestpowerofficesasstatedinSec-
tions9and11.
2,9
69 c
Organisationidentifiesanddocumentstheauthoritiesandresponsibilitieswithintheorganisationformanag-ingtheoutsourcedprocess-
esandactivities.
4 Compli-ant
Theauthorityandresponsibilitywithintheorgani-sationformanagingtheoutsourcedprocessesandactivitiesisclearlyassignedtoWestpower’sAsset
ManagerasstatedinAMSSections2and9.
10
ASSETMANAGEMENTPRACTICES 267
Recommended Actions
• Thatdiscussionsbetweenthetwopartiesarefullydocumentedandperiodicallyreviewedforeffectiveness.
8.12.11Training,AwarenessandCompetence
“Theorganisationshallensurethatpersonnelunderitsdirectcontrolundertakingassetmanagementrelatedactivitieshaveanappropriatelevelofcompetenceintermsofeducation,trainingorexperience.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Theintentofthisgroupofrequirementsistoensurethatpersonnelinvolvedintheassetmanagementsystemhavetheappropriateskillsandcompetenciesnecessarytooperateallaspectsoftheassetmanagementsystem.
0
1
2
3
4
5
6
Pro
ce
sse
s fo
r p
ers
on
ne
l
to b
e a
wa
re o
f a
sse
t
rela
ted
ris
ks.
Pro
ce
sse
s fo
r p
ers
on
ne
l
to b
e a
wa
re o
f th
e
imp
ort
an
ce
of co
mp
lyin
g
with
th
e A
MS
.
Pro
ce
sse
s fo
r p
ers
on
ne
l
to b
e a
wa
re o
f th
e
co
nse
qu
en
ce
s o
f
de
pa
rtu
re fro
m th
e A
MS
.
PAS-55 Aligned
Table 8.12.11 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.4.3 Training, Awareness and Competence
70 aProcessesforpersonneltobeawareofassetrelated
risks.4 Compli-
ant
AMSSection10detailsthestafftraininginassetmanagement.Thesearediscussedatregular
meetings.Weareunabletoverifyifthisiscorrectwithadesktopreviewonly.
10
71 bProcessesforpersonneltobeawareoftheimportanceofcomplyingwiththeAMS.
4 Compli-ant
AMSSection10detailstheAssetManagementGroupwhichisresponsibleforensuringthatallpersonnelunderstandtheimportanceofcomply-ingwiththeAMS.Again,weareunabletoverifyif
thisiscorrectwithadesktopreviewonly.
10
268 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Actions
• Identifypolicies,proceduresandrequirementsthatarerelevanttoeachpartoftheorganisation.
• Implementaprogramofprocess/procedurediscussionandreview.Ensurethatdiscussionscoverindividual’srolesandresponsibilitiesandthatrecordsarekept.
• Ensurethatstaffareawareofwhykeyassetmanagementactivitiesarenecessaryandtheconsequencesofnotperformingtheactivityasrequired.
• Developa longtermskilldevelopmentplantoensurethatkeyskillsareavailabletoWestpower intothelongerterm.
8.12.12Communication,ParticipationandConsultation
“Theorganisation shall ensurepertinent assetmanagement information is effectively communicated to andfromemployeesandotherrelevantstakeholders,includingcontractedserviceproviders.”
Review against PAS-55 Requirements
0
1
2
3
4
5
6
Co
nsu
lta
tio
n w
ith
sta
ke
ho
lde
rs in
th
e
de
ve
lop
me
nt
of
po
licy,
str
ate
gy a
nd
ob
jective
s.
Co
nsu
lta
tio
n w
ith
sta
ke
ho
lde
rs in
th
e
de
ve
lop
me
nt
of
fun
ctio
na
l
po
licie
s,
sta
nd
ard
s a
nd
pro
ce
sse
s.
Co
nsu
lta
tio
n w
ith
sta
ke
ho
lde
rs in
th
e
asse
ssm
en
t o
f ri
sk a
nd
co
ntr
ols
.
Co
nsu
lta
tio
n w
ith
sta
ke
ho
lde
rs in
th
e
asse
ssm
en
t in
cid
en
t
inve
stig
atio
ns.
Co
nsu
lta
tio
n w
ith
em
plo
ye
es a
nd
re
leva
nt
sta
ke
ho
lde
rs in
th
e
pro
ce
ss o
f co
ntin
ua
l
imp
rove
me
nt
of
AM
S.
PAS-55 Aligned
Table 8.12.11 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
72 c
Processesforpersonneltobeawareoftheconse-quencesofdeparturefrom
theAMS.
4 Compli-ant
WeeklymeetingsareheldwithmanagementandstaffforstaffawarenessofdeparturefromAMS. 10
ASSETMANAGEMENTPRACTICES 269
Observations and Improvement Opportunities
WestpowerappearstohaveaconsultationandcommunicationprogramwithrespecttoitsAMP,appropriatetothescaleandscopeofitsassetmanagementbusiness.
Recommended Actions
That communication, participation and consultation be expanded for all aspects of the asset managementsystem,includingthepolicies,strategiesandobjectives.
8.12.13AssetManagementSystemDocumentation
“Theorganisationshallestablish,implementandmaintainup-to-datedocumentationtoensureitsAMScanbeadequatelyunderstood,communicatedandoperated.”
Table 8.12.12 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.4.4 Communication, Participation and Consultation
73 a
Consultationwithstakehold-ersinthedevelopmentofpolicy,strategyandobjec-
tives.
4 Compliant
ThereisformalconsultationwithWestpower’ssingleshareholderWestCoastElectricPowerTrust,theBoard,AMG,Transpowerandmajor
users,asdetailedindraftAMSSection11.Thereisgoodcommunicationwithemployeesand
serviceprovider.
11
74 b
Consultationwithstakehold-ersinthedevelopmentoffunctionalpolicies,stan-dardsandprocesses.
4 CompliantAMGconsultswithstakeholdersinthedevelop-mentoffunctionalpolicesasstatedindraftAMS
Section11.11
75 cConsultationwithstakehold-ersintheassessmentofrisk
andcontrols.4 Compliant
ThereisageneralstatementindraftAMSSec-tion11consultationwithstakeholdersinrisk
management.Thiscouldbestrengthenedwithstakeholderinvolvementontheassessmentofriskandcontrols,particularlyTranspowerand
largeusers.
11
76 dConsultationwithstake-holdersintheassessmentincidentinvestigations.
3 Developing
ThereisnoexplicitstatementindraftAMSSec-tion11ontheconsultationwithstakeholdersintheassessmentofincidentinvestigations.Itisgoodpracticetoinvolvestaffinincidentinvesti-gations.ThisshouldbestateddraftAMSSection
11(orsimilarstatement).
11
77 e
Consultationwithemploy-eesandrelevantstake-holdersintheprocessofcontinualimprovementof
AMS.
4 Compliant
ThediagramindraftAMSSection11showshowtheinformationinteractswithstakeholders.Thisissupportedbyastatementaboutcontinuous
improvement.
11
270 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Westpower’s asset management system provides references to all relevant internal policies and procedures and the document’s language is direct and in line with PAS-55 phraseology. The documentation is held within Sharepoint which provides excellent control.Recommended Actions
ThatwidespreadtrainingisprovidedtoallparticipantsinassetmanagementintheuseofSharepointanditscapabilities.
0
1
2
3
4
5
6
AM
S d
ocu
me
nta
tio
n
inclu
de
s a
fu
ll d
escri
ptio
n
of
AM
S a
nd
re
late
d
do
cu
me
nts
.
AM
S d
ocu
me
nta
tio
n
inclu
de
s a
fu
ll d
escri
ptio
n
of
AM
S p
olicy,
str
ate
gy
an
d o
bje
ctive
s.
AM
S d
ocu
me
nta
tio
n
inclu
de
s a
ll r
ele
va
nt
reco
rds.
PAS-55 Aligned
Table 8.12.13 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.4.5 Asset Management System Documentation
78 a
AMSdocumentationincludesafulldescriptionofAMSandrelateddocu-
ments.
4 Compliant
ThedraftAMSiswellpresentedandeasytoread.Therearegoodlinkstoassociateddocu-mentsattheendofsections.Thereisgood
layoutanditflowswell.ThedraftAMSisnotalargedocumentandisappropriateforWest-
power’sassetsize.
All
79 b
AMSdocumentationincludesafulldescriptionofAMSpolicy,strategyand
objectives.
4 CompliantThedraftAMSincludesthepolicy,strategyandobjectivesinonedocument.Itissummarised
indraftAMSSection12.12
80 c AMSdocumentationin-cludesallrelevantrecords. 4 Compliant
ThesupportingrecordsarekeptinTheVaultandWestpower’sdocumentmanagement
system,Sharepoint.12
ASSETMANAGEMENTPRACTICES 271
8.12.14InformationManagement
“Theorganisationshalldesign,implementandmaintainasystemformanagingassetmanagementinformation.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Inevaluatingthesecriteria,considerationmustbegiventothesizeandcomplexityofthebusinessandassetbaseandthestrategiesthataretobeusedtomanagetheassets.WestpowerhasintroducedMicrosoftSharepointforinformationmanagement.Thiscreatesdocumentaryevidencetodemonstratecompliancewhereitexists,createajustificationwhereitisdeemedappropriatetonotcollectdata,andidentifyareaswhereimproveddatawouldimproveassetmanagementcapabilityandoutcomes.
0
1
2
3
4
5
6
Ad
eq
ua
cy o
f in
form
atio
n
ap
pro
ve
d b
y a
uth
ori
se
d
pe
rso
nn
el.
Info
rma
tio
n p
eri
od
ica
l
revie
we
d a
nd
su
bje
ct
to
ve
rsio
n c
on
tro
l.
Allo
ca
tio
n o
r a
pp
rop
ria
te
role
s,
resp
on
sib
ilitie
s a
nd
au
tho
ritie
s.
Ob
so
lete
in
form
atio
n
pro
mp
tly r
em
ove
d.
Arc
hiv
al in
form
atio
n
reta
ine
d is id
en
tifie
d.
Info
rma
tio
n s
ecu
re,
ba
cke
d u
p a
nd
ab
le t
o b
e
reco
ve
red
.
PAS-55 Aligned
Table 8.12.14 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.4.6 Information Management
81 aAdequacyofinformationapprovedbyauthorised
personnel.4 Compliant
Overall,thedraftAMSSection13InformationManagementiswellwritten.TheinformationiscontrolledbytheAMGasstatedinthisSection
13.
13
82 bInformationperiodical
reviewedandsubjecttover-sioncontrol.
4 CompliantDocumentversioncontrolisprovidedbyShare-point.Maximomanagesaccuraterecordsfor
worksordersasstatedinSection11.13
83 cAllocationorappropriateroles,responsibilitiesand
authorities.4 Compliant AMGisresponsibleforinformationmanagement
asstatedinthisdraftAMSSection13. 13
272 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Actions
Sharepointisappropriatesoftwareforinformationmanagementbutitrequiresappropriateroles,responsibilitiesandauthoritiesbeallocatedandpoliciesbeintroducedtodealwithobsoleteandarchivalinformation.
8.12.15RiskManagementMethodology
“The organisation shall establish, implement and maintain documented processes and procedures for theongoingidentificationandassessmentofassetrelatedandassetmanagementrelatedrisks.”
Review against PAS-55 Requirements
0
1
2
3
4
5
6
Me
tho
do
log
y p
rop
ort
ion
ate
to t
he
le
ve
l o
f ri
sk.
Me
tho
do
log
y p
roa
ctive
with
re
sp
ect
to its
sco
pe
,
na
ture
an
d t
imin
g.
Me
tho
do
log
y a
sse
sse
s
ho
w r
isks c
ha
ng
e o
ve
r
tim
e a
nd
usa
ge
.
Me
tho
do
log
y p
rovid
es t
he
cla
ssific
atio
n o
f ri
sk a
nd
ide
ntifica
tio
n o
f ri
sks t
o b
e
avo
ide
d,
elim
ina
ted
or
co
ntr
olle
d.
Me
tho
do
log
y is c
on
sis
ten
t
with
th
e e
xp
eri
en
ce
an
d
ca
pa
bilitie
s o
f th
e
me
asu
res e
mp
loye
d.
Me
tho
do
log
y p
rovid
es f
or
the
mo
nito
rin
g o
f a
ctio
ns.
PAS-55 Aligned
Table 8.12.14 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
84 d Obsoleteinformationpromptlyremoved. 4 Compliant TheremovalofobsoleteinformationbyShare-
pointisstatedindraftAMSSection13. 13
85 e Archivalinformationre-tainedisidentified. 4 Compliant
Theprocessforarchivinginformationissum-marisedindraftAMSSection13.Notethatarchivedhasbeenspeltachievedinthefirst
paragraphonpage35.
13
86 f Informationsecure,backedupandabletoberecovered. 4 Compliant Informationsecurityandbackupiswellcovered
indraftAMSSection13. 13
ASSETMANAGEMENTPRACTICES 273
Observations and Improvement Opportunities
PAS-55recognisesriskmanagementasacriticalfeatureofanoverallassetmanagementsystem,andrequiresa comprehensive process be in place to ensure key risks are identified, appropriately considered and actedon.Westpower at presentmanages asset related risk through several separatemeans including the safetymanagement system, periodic external reviews and informal processes that occur during the routine assetmanagementprocess.WestpowerhasdevelopedanoverarchingriskmanagementstrategyalignedwithAS/NZSISO31000:2008,riskmanagement–principlesandguidelinesthattransparentlygroupassetrelatedrisksforassessmentandtreatment.
Recommended Actions
ThatWestpowerreviewsitsoverarchingriskmanagementprocessbasedupontherequirementsofAS/NZSISO31000:2008,riskmanagement–principlesandguidelines.
8.12.16RiskIdentificationandAssessment
“The identification and assessment of risks shall consider the probability of credible events and theirconsequences.”
Table 8.12.15 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.4.7.2 Risk Management Methodology
87 a Methodologyproportionatetothelevelofrisk. 4 Compliant
Westpowerhasaverysoundandestablishedriskmethodology.AlthoughWestpowerisa
smallEDB,itstillprovidesanessentialservicetotheWestCoastcommunitysothemethodology
isappropriate.
5.7
88 bMethodologyproactivewithrespecttoitsscope,nature
andtiming.4 Compliant
ItisstatedthattheRiskManagementPlanisregularlyupdatedsothiscoversbeingproactive
documenttoaddresschanges.5.7
89 cMethodologyassesseshowriskschangeovertimeand
usage.4 Compliant
TheriskprofileisreviewedannuallythroughtheRiskManagementAnalysissummarisedindraft
AMSSection5.7.5.7
90 d
Methodologyprovidestheclassificationofriskandidentificationofriskstobeavoided,eliminatedor
controlled.
4 Compliant RiskclassificationisprovidedinSection9.2,RiskManagementPlan. 5.7
91 e
Methodologyisconsistentwiththeexperienceand
capabilitiesofthemeasuresemployed.
4 Compliant CurrentcontroleffectivenesswasassessedbyWestpowerstaffwiththeinterviewprocess. 5.7
92 f Methodologyprovidesforthemonitoringofactions. 4 Compliant
TheRiskManagementTeammonitorstheactionsforriskwithratingat40orabove,as
statedintheRiskManagementPlan.5.7
274 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Westpower’sriskmanagementidentifiesandassessestherisksofphysicalfailure,operationalfailureandnaturalenvironmentaleventsbutfurtherimprovementscanbemadeforrisksbeyondthecontroloftheorganisationandotherstakeholderrisks
0
1
2
3
4
5
6
Ide
ntifica
tio
n a
nd
asse
ssm
en
t o
f ri
sk
co
nsid
er
the
ph
ysic
al
failu
re r
isks.
Ide
ntifica
tio
n a
nd
asse
ssm
en
t o
f ri
sk
co
nsid
er
the
op
era
tio
na
l
failu
re r
isks.
Ide
ntifica
tio
n a
nd
asse
ssm
en
t o
f ri
sk
co
nsid
er
the
na
tura
l
en
vir
on
me
nta
l e
ve
nts
.
Ide
ntifica
tio
n a
nd
asse
ssm
en
t o
f ri
sk
co
nsid
er
facto
rs o
uts
ide
the
co
ntr
ol o
f th
e
org
an
isa
tio
n.
Ide
ntifica
tio
n a
nd
asse
ssm
en
t o
f ri
sk
co
nsid
er
sta
ke
ho
lde
r ri
sks
su
ch
as f
ailu
re t
o m
ee
t
reg
ula
tory
pe
rfo
rma
nce
.
Ide
ntifica
tio
n a
nd
asse
ssm
en
t o
f ri
sk
co
nsid
er
risks a
sso
cia
ted
with
diffe
ren
t life
cycle
ph
ase
s o
f th
e a
sse
ts.
PAS-55 Aligned
Table 8.12.16 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.4.7.7 Risk Identification and Assessment
93 aIdentificationandassess-mentofriskconsiderthephysicalfailurerisks.
4 CompliantFunctionalfailureisprovidedinthe2011AMP,Sections3and6.Thedetailedriskassessment
coverstheotherphysicalrisks.5.7
94 bIdentificationandassess-mentofriskconsidertheoperationalfailurerisks.
4 Compliant Operationalrisksarecoveredinthe2011,AMPSection6. 5.7
95 c
Identificationandassess-mentofriskconsiderthenaturalenvironmental
events.
4 Compliant
NaturalenvironmentaleventswereassessedwiththedetailedriskassessmentintheRisk
ManagementPlan.ThisresultedinclimaticandseismicfactorsasthekeyrisksforWestpower.
5.7
96 d
Identificationandassess-mentofriskconsiderfactorsoutsidethecontrolofthe
organisation.
4 Compliant
Theriskfactorsoutsidethecontroloftheorganisationwereassessedaspartofdetailedriskassessmentincludingnewtechnologies,
exchangerate,andearthquakes.
5.7
ASSETMANAGEMENTPRACTICES 275
Recommended Actions
ThatWestpowerimplementanoverarchingriskmanagementprocessbasedupontherequirementsofPAS-551andAS/NZSISO31000:2008,RiskManagement–PrinciplesandGuidelines.
8.12.17UseandMaintenanceofAssetRiskInformation
“The organisation shall ensure the results of risk assessments and the effects of risk controlmeasures areconsidered.”
Review against PAS-55 Requirements
0
1
2
3
4
5
6
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
str
ate
gy.
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
ob
jective
s.
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
AM
P.
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
ide
ntifica
tio
n o
f a
de
qu
ate
reso
urc
es.
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
ide
ntifica
tio
n o
f tr
ain
ing
an
d c
om
pe
ten
cy n
ee
ds.
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
de
term
ina
tio
n o
f co
ntr
ols
for
asse
t life
cycle
activitie
s.
Re
su
lts o
f ri
sk a
sse
ssm
en
t
pro
vid
e in
pu
t in
to t
he
org
an
isa
tio
n's
ove
rall r
isk
ma
na
ge
me
nt
fra
me
wo
rk.
PAS-55 Aligned
Table 8.12.16 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
97 e
Identificationandassess-mentofriskconsider
stakeholderriskssuchasfailuretomeetregulatory
performance.
4 CompliantTheriskassessmentconsidersenvironmental,unethicalbehaviourandfinancialfactorswith
stakeholderrisks.5.7
98 f
Identificationandassess-mentofriskconsiderrisksassociatedwithdifferentlifecyclephasesoftheassets.
3 Developing
Thisiscoveredbythe2011AMPbutthiscouldbestrengthenedwithanexplicitstatementinthedraftAMSSection5.7.RegularinspectionsarestatedasastrategyindraftAMSSection5.7.
Thisisstilloutstanding
5.7
276 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Observations and Improvement Opportunities
Inordertomanageriskseffectively,theconsiderationofriskshouldbeembeddedintoallactivitiesandproceduresthroughouttheassetmanagementsystemandpreferablyassetrelatedrisksshouldbeaddressedaspartoftheorganisation’scorporateriskmanagementframework
Recommended Actions
ThatWestpowerreviewitsoverarchingriskmanagementprocessbasedupontherequirementsofPAS-551andAS/NZSISO31000:2008,RiskManagement–PrinciplesandGuidelines.
8.12.18LegalandOtherRequirements
“Theorganisationshallestablish,implementandmaintainprocessesandproceduresforidentifyingandaccessingthelegal,regulatory,statutoryandotherassetmanagementrequirements.”
Table 8.12.17 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.4.7.8 Use and Maintenance of Asset Risk Information
99 aResultsofriskassessmentprovideinputintothe
strategy.4 Compliant
StrategiesaredevelopedtomitigaterisksasstatedindraftAMSSection5.7.TheRiskMan-agementPlanSection1.3statesummariestheintegrationofriskprocessesincludingthatriskassessmentprovidesinputintothestrategy.
5.7
100 bResultsofriskassessment
provideinputintotheobjec-tives.
4 Compliant
TheRiskManagementPlanSection1.3statesummariestheintegrationofriskprocessesincludingthatriskassessmentprovidesinput
intotheobjectives.
5.7
101 c ResultsofriskassessmentprovideinputintotheAMP. 4 Compliant
TheRiskManagementPlanSection1.3statestheintegrationofriskprocessesincludingthatriskassessmentprovidesinputintotheAMP.
5.7
102 d
Resultsofriskassessmentprovideinputintothe
identificationofadequateresources.
4 Compliant ThisisdetailedintheRiskManagementPlan,anassociateddocument. 5.7
103 e
Resultsofriskassessmentprovideinputintothe
identificationoftrainingandcompetencyneeds.
4 CompliantRegularstafftrainingforsystemoperationandpermitissuingisdetailedindraftAMSSection
5.7.5.7
104 f
Resultsofriskassessmentprovideinputintothede-terminationofcontrolsforassetlifecycleactivities.
4 CompliantStrategiesaredevelopedtomitigaterisksas
statedindraftAMSSection5.7,suchasregularinspection,anddistributionautomation.
5.7
105 g
Resultsofriskassessmentprovideinputintothe
organisation’soverallriskmanagementframework.
4 Compliant
TheRiskManagementPlanstatesthatitispartofoverallbusinessplanningstrategyandpro-videsinputintotheorganisation’soverallrisk
managementframework.
5.7
ASSETMANAGEMENTPRACTICES 277
Review against PAS-55 requirements
Observations and Improvement Opportunities
Thiselement requires that theorganisationhaveaprocess formonitoring relevant legislation,codes,guidesandstandards.Anychangesshouldbeassessedforrelevanceandrequiredactionsimplemented.Westpowerhasdevelopedaregisteroflegislation,codes,guidelinesandstandardsthatareofsufficientimportancetotheassetmanagementsystem.A legislationsignoffwasviewed,which indicatesthatWestpower isawareof itsobligationsandthatithasassessedcompliance.Noevidencewaspresentedindicatinganongoingprocessformonitoringandreactingtochanges.
0
1
2
3
4
5
6
Org
an
isa
tio
n a
wa
re h
ow
its a
ctivitie
s a
re a
ffe
cte
d
by le
ga
l a
nd
oth
er
req
uire
me
nts
.
Org
an
isa
tio
n o
pe
rate
s a
syste
m to
id
en
tify
leg
isla
tio
n a
nd
mo
nito
r
fort
hco
min
g c
ha
ng
es.
Org
an
isa
tio
n h
as
ap
pro
pria
te m
ea
ns to
acce
ss in
form
atio
n.
Org
an
isa
tio
n h
as
gu
ida
nce
fro
m o
the
r
org
an
isa
tio
ns.
PAS-55 Aligned
Table 8.12.18 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.4.8 Legal and Other Requirements
106 aOrganisationawarehowitsactivitiesareaffectedbyle-galandotherrequirements.
4 Compliant Westpower’slegalrequirementsaresum-marisedindraftAMSSection5.8. 5.8
107 b
Organisationoperatesasystemtoidentifylegislationandmonitorforthcoming
changes.
4 CompliantWestpowerbelongstotwoorganisationsENAandEEAthatmonitorlegislationasstatedin
draftAMSSection5.8.5.8
108 cOrganisationhasappro-priatemeanstoaccess
information.4 Compliant
WestpoweraccessesrequiredinformationthroughserviceproviderENAasstatedindraft
AMSSection5.8.5.8
109 d Organisationhasguidancefromotherorganisations. 4 Compliant
GuidancefromotherorganisationsismainlythroughserviceproviderENAasstatedindraft
AMSSection5.8.5.8
278 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Actions
ThatWestpower develop an on-going process formonitoring and reacting to changes that are of sufficientimportancetotheassetmanagementsystemtowarrantmonitoringandassignresponsibilitytoanindividualtoperiodicallycheckforamendments,revisionsetc.Eachrevision/amendmentwouldbecheckedforrelevanceandrequiredactionidentifiedanddocumented.
8.12.19ManagementofChange
“Whereexistingarrangementsarerevisedornewarrangementsareintroducedthatcouldhaveanimpactonassetmanagement activities, theorganisation shall assess the associated risks before the arrangements areimplemented.”
ReviewagainstPAS-55requirements
Observations and Improvement Opportunities
Theorganisationshouldensurethatriskassessmentsareperformedforanysignificantchangestoelementsofassetmanagementsystems.Thisdoesnotnecessitateadditionalriskmanagementprocessesbutensuresthereareexistingarrangementsinplacetoprovideassurancethatriskassessmentiscarriedout.WestpowercarriesoutthisfunctionthroughitsMaterialEvaluationGroup(MEG)andcarriesthisovertotheintroductionofnewcontractors.
0
1
2
3
4
5
6
Co
nsid
er
revis
ed
org
an
isa
tio
na
l str
uctu
re,
role
s a
nd
re
sp
on
sib
ilitie
s.
Co
nsid
er
revis
ed
asse
t
ma
na
ge
me
nt p
olicy,
str
ate
gy, o
bje
ctive
s a
nd
pla
ns.
Co
nsid
er
revis
ed
pro
ce
sse
s a
nd
pro
ce
du
res.
Co
nsid
er
the
in
tro
du
ctio
n
of n
ew
asse
ts, syste
ms
an
d te
ch
no
log
y.
Co
nsid
er
the
in
tro
du
ctio
n
of n
ew
co
ntr
acto
rs.
PAS-55 Aligned
ASSETMANAGEMENTPRACTICES 279
Recommended Actions
ThatWestpowerensureallnewprocessesandproceduresareevaluatedviatheMEGcommittee.
8.12.20LifeCycleActivities
“Theorganisationshallestablish,implementandmaintainprocessesandproceduresfortheimplementationofitsassetmanagementplanandcontrolofactivitiesacrossthewholelifecycle.”
Review against PAS-55 requirements
0
1
2
3
4
5
6
AM
P in
clu
de
s t
he
cre
atio
n,
acq
uis
itio
n a
nd
en
ha
nce
me
nt
of
asse
ts.
AM
P in
clu
de
s t
he
utilisa
tio
n o
f a
sse
ts.
AM
P in
clu
de
s t
he
ma
inte
na
nce
of
asse
ts.
AM
P in
clu
de
s t
he
de
co
mm
issio
nin
g a
nd
dis
po
sa
l o
f a
sse
ts.
PAS-55 Aligned
Table 8.12.19 4.4 - Asset Management Enablers and Controls
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.4.9 Management of Change
110 aConsiderrevisedorganisa-tionalstructure,rolesand
responsibilities.4 Compliant
TheMaterialEvaluationGroup(MEG)isasubgroupoftheAssetManagementGroupandisresponsibleformonitoringandcontrolling
change.
14
111 bConsiderrevisedassetman-agementpolicy,strategy,objectivesandplans.
4 Compliant TheMEGcoversallaspectsofchangewithintheAMS. 14
112 c Considerrevisedprocessesandprocedures. 4 Compliant
ThisiscoveredindraftAMSSection14andinthesupportingchangemanagementdocu-
ment.MaterialEvaluationGroup(MEG)meetsmonthlyandconsidersnewprocesses.
14
113 dConsidertheintroductionofnewassets,systemsand
technology.4 Compliant
TheMEGcontrolsthemanagementofnewproductstobeusedontheWestpowernet-work.ChangestoassetsaretrackedinGISas
statedindraftAMSSection14.
14
114 e Considertheintroductionofnewcontractors. 4 Compliant TheMEGcontrolstheintroductionofnewcon-
tractorsasstatedindraftAMSSection14. 14
280 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Observations and Improvement Opportunities
The organisation should ensure the planned arrangements, functional policies, standards, processes andprocedures, asset management enablers and resources are utilised for the efficient and cost effectiveimplementation of assetmanagement across the full life cycle of the assets. Westpower carries out theseactivitiesincompliancewiththerequirementsofPAS-55.
Recommended Actions
ThatWestpowerperiodicallyreviewstheseactivitiestocontinuallyimprovelifecycleactivities.
8.12.21Tools,FacilitiesandEquipment
“Theorganisationshallensuretools,facilitiesandequipmentaremaintainedand,whereappropriate,calibrated.”
Review against PAS-55 requirements
0
1
2
3
4
5
6
To
ols
, fa
cilitie
s a
nd
eq
uip
me
nt
ca
lib
rate
d a
nd
ma
inta
ine
d f
or
the
imp
lem
en
tatio
n o
f th
e
AM
P.
To
ols
, fa
cilitie
s a
nd
eq
uip
me
nt
ca
lib
rate
d a
nd
ma
inta
ine
d t
o a
ch
ieve
th
e
req
uir
ed
fu
nctio
n a
nd
pe
rfo
rma
nce
fro
m t
he
asse
t a
nd
asse
t syste
ms.
To
ols
, fa
cilitie
s a
nd
eq
uip
me
nt
ca
lib
rate
d a
nd
ma
inta
ine
d t
o m
on
ito
r a
nd
me
asu
re p
erf
orm
an
ce
an
d
co
nd
itio
n.
PAS-55 Aligned
Table 8.12.20 4.5 - Implementation of Asset Management Plans
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.5.1 Life cycle Activities
115 aAMPincludesthecreation,acquisitionandenhance-
mentofassets.4 Compliant
Thisisprovidedinthe2011AMPinSections5and6.ThestatementaboutnotdeliveringtheplannedcapitalprogrammeinRequirement4.1.2eshouldbelocatedinSection15.
15
116 b AMPincludestheutilisationofassets. 4 Compliant Thisisprovidedinthe2011AMPinSection5. 15
117 c AMPincludesthemainte-nanceofassets. 4 Compliant Thisisprovidedinthe2011AMPinSection6. 15
118 dAMPincludesthedecom-missioninganddisposalof
assets.4 Compliant Thisisprovidedinthe2011AMPinSection6. 15
ASSETMANAGEMENTPRACTICES 281
Observations and Improvement Opportunities
Theorganisationshouldestablishandmaintainprocessesandprocedures tocontrol thesemaintenanceandcalibrationactivitieswheresuchtools,facilitiesandequipmentarenecessaryfortheimplementationofassetmanagement.WestpowercarriesoutsuchactivitiesandformallydocumentthemaintenanceandcalibrationresultsasrequiredbyPAS-55.
Recommended Actions
ThatWestpowerformallyreviewthedocumentedmaintenanceandcalibrationactivities.
8.12.22PerformanceandConditionMonitoring
“Theorganisationshallestablish,implementandmaintainprocessesandprocedurestomonitorandmeasuretheperformanceoftheassetmanagementsystemand/orconditionoftheassets.”
Review against PAS-55 requirements
0
1
2
3
4
5
6
Pro
ce
sse
s a
nd
pro
ce
du
res
imp
lem
en
ted
fo
r
co
nsid
era
tio
n o
f re
active
mo
nito
rin
g o
f th
e A
MS
.
Co
nsid
era
tio
n o
f p
roa
ctive
mo
nito
rin
g o
f th
e A
MS
.
Co
nsid
era
tio
n o
f le
ad
ing
pe
rfo
rma
nce
in
dic
ato
rs o
f
the
AM
S.
Co
nsid
era
tio
n o
f la
gg
ing
pe
rfo
rma
nce
in
dic
ato
rs o
f
the
AM
S.
Co
nsid
era
tio
n f
or
qu
alita
tive
an
d q
ua
ntita
tive
me
asu
res o
f th
e A
MS
.
Co
nsid
era
tio
n o
f o
ve
rall
eff
ective
ne
ss a
nd
eff
icie
ncy o
f th
e A
MS
.
Co
nsid
era
tio
n f
or
reco
rdin
g m
on
ito
rin
g a
nd
me
asu
rem
en
t d
ata
an
d
resu
lts.
PAS-55 Aligned
Table 8.12.21 4.5 - Implementation of Asset Management Plans
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.5.2 Tools, Facilities and Equipment
119 a
Tools,facilitiesandequip-mentcalibratedandmain-tainedfortheimplementa-
tionoftheAMP.
4 CompliantThisisdetailedinAMSSection15software
programmes,MaximoandSharepoint,fortheimplementationoftheAMP.
15
120 b
Tools,facilitiesandequip-mentcalibratedandmaintainedtoachieve
therequiredfunctionandperformancefromtheasset
andassetsystems.
4 Compliant ThisisdetailedinAMSSection15withrealtimemonitoring. 15
121 c
Tools,facilitiesandequip-mentcalibratedand
maintainedtomonitorandmeasureperformanceand
condition.
4 CompliantThisisdetailedinAMSSection15withMaximo.Equipmentisidentifiedandtrackedthroughthetestroomandrecordedinanassetregister.
15
282 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Observations and Improvement Opportunities
Theintentofthisgroupofrequirementsistoensurethattheassetmanagementsystemhaseffectivefeedbackloops formeasurement control and continual improvement.Westpower has a number of key performanceindicators inplaceforessentialssuchasSAIDIandSAIFI,but it isnotclearthatall informationnecessaryforoperationalcontrolandcontinualimprovementoftheoverallassetmanagementsystemisinplace.
Recommended Actions
ThatWestpowerimplementperformancemeasurestoprovideimprovedmeasurementandcontroloftheassetmanagementprocesses.IndevelopingKPIensurethattheresultsofriskassessmentsaretakenintoconsiderationtoensurethatriskissueshaveappropriatelevelsofmeasurementandcontrol.
8.12.23InvestigationofAssetRelatedFailures,IncidentsandNon-Conformities
“The organisation shall establish, implement and maintain processes and procedures for the handling ofinvestigationsoffailures,incidentsandnonconformitiesassociatedwithassetsandassetmanagementsystem.”
Table 8.12.22 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.6.1 Performance and Condition Monitoring
122 a
Processesandproceduresimplementedforconsider-ationofreactivemonitoring
oftheAMS.
4 Compliant
ReactivemonitoringofassetperformanceisdetailedindraftAMSSection16.1.ThisalsoincludeshowtheAMSismeasuredusingthe
gapanalysis.
16.1
123 b ConsiderationofproactivemonitoringoftheAMS. 4 Compliant
ProactivemonitoringofassetperformanceisdetailedindraftAMSSection16.1.TheAMS
effectivenessisreviewedannually.16.1
124 cConsiderationofleadingperformanceindicatorsof
theAMS.3 Developing
TheleadingperformanceindicatorforassetperformanceisassetinspectionasdetailedindraftAMSSection16.1.Staffmoraleissug-
gestedastheleadingKPIfortheAMS.Perhapsharderordirectmeasuresaremoreappropri-atesuchasspecificcustomerfeedbacktrends,trendsinnumberofreportsofnoncompliance,
andAMSauditresults.
16.1
125 dConsiderationoflaggingperformanceindicatorsof
theAMS.4 Compliant
ThelaggingperformanceindicatorforassetperformanceisSAIDIandSAIFIasdetailedindraftAMSSection16.1.Thelaggingperfor-
manceindicatorforAMSisannualauditsofPAS55gapanalysis.
16
126 eConsiderationforqualitativeandquantitativemeasures
oftheAMS.4 Compliant
TheAMSismeasuredqualitativelyandquan-titatively.TheAMSismeasuredqualitativelythroughtheCommerceCommissionreviews
andcomparisons.TheAMSismeasuredquan-titativelythroughSAIDIandreportedtothe
Boardmonthly.
16
127 fConsiderationofoverallef-fectivenessandefficiencyof
theAMS.4 Compliant
TheeffectivenessandefficiencyoftheAMSismeasuredthroughthePAS55gapanalysisandannualaudit,andtheCommerceCommission
reviewsandcomparisons.
16
128 gConsiderationforrecordingmonitoringandmeasure-mentdataandresults.
4 Compliant
TherecordingofdataisdetailedindraftAMSSection16.1includingdatacollectionpro-
grammeandoutageinformationtoallowforanalysis.
16
ASSETMANAGEMENTPRACTICES 283
Review against PAS-55 requirements
Observations and Improvement Opportunities
Westpower has a formalised processes for investigating, learning from and correcting the root causes ofequipment failures and process non-conformances. Such a process provides guidance onwhat level issuesneedtobeescalatedbasedonseverity,providefortimeframesforcompletionofinvestigationsandprocessfortrackingtheprogressofcorrectiveactions.
0
1
2
3
4
5
6
Pro
ce
sse
s a
nd
pro
ce
du
res
to d
efin
e r
esp
on
sib
ilitie
s
an
d a
uth
ori
ty f
or
takin
g
actio
n t
o m
itig
ate
co
nse
qu
en
ce
s a
risin
g
fro
m a
fa
ilu
re.
Inve
stig
atin
g f
ailu
res,
incid
en
ts a
nd
no
nco
nfo
rmitie
s t
o
de
term
ine
th
eir
ro
ot
ca
use
.
Eva
lua
tin
g t
he
ne
ed
fo
r
pre
ve
nta
tive
actio
n t
o
avo
id f
ailu
res o
ccu
rrin
g.
Co
mm
un
ica
tin
g t
o r
ele
va
nt
sta
ke
ho
lde
rs,
the
re
su
lts
of
inve
stig
atio
ns.
PAS-55 Aligned
Table 8.12.23 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.6.2 Investigation of Asset-related Failures, Incidents and Nonconformities
129 a
Processesandprocedurestodefineresponsibilitiesandauthorityfortakingactiontomitigateconsequencesarisingfromafailure.
3 Developing
TheAMGisresponsiblefordebriefingsessionsforinvestigatingassetrelatedfailures,incidencesandnonconformitiesassummarisedindraft
AMSSection16.2.Thereisnoformaldocumen-tationforthisprocessbutminutesaretakenofthesemeetings.Formaldocumentationcoveringallmatters(assetfailuresandAMSnonconfor-
mities)isrequiredtorateascompliant.
16.2
130 b
Investigatingfailures,incidentsandnonconformi-tiestodeterminetheirroot
cause.
3 Developing
Rootcausesaredeterminedthroughthedebrief-ingsessionsasabove.ThereisanewIncidentInvestigationReportsetuptodocumentthe
findings.
16.2
284 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Action
ThatWestpower summarises and reviews its process for investigating asset failures and assetmanagementsystemnon-conformancesincludingaprocessfortrackingtheprogressofcorrectiveactions.
8.12.24EvaluationofCompliance
“The organisation shall establish, implement and maintain processes and procedures for evaluation of itscompliancewithapplicablelegalandotherregulatoryrequirements.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
ItisunderstandthatWestpoweroperatesunderheavyregulatoryrequirementsandhasprocessesandproceduresinplacetoevaluateitscompliance.
0
1
2
3
4
5
6
Org
an
isa
tio
n e
sta
blish
ed
,
imp
lem
en
ted
an
d
ma
inta
ine
d p
roce
sse
s a
nd
pro
ce
du
res f
or
eva
lua
tio
n
of
its c
om
plia
nce
with
le
ga
l
an
d o
the
r re
gu
lato
ry
req
uir
em
en
ts.
PAS-55 Aligned
Table 8.12.23 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
131 cEvaluatingtheneedfor
preventativeactiontoavoidfailuresoccurring.
3 DevelopingMajorassetfailuresareinvestigatedwithcorrec-tiveactionsaresummarisedindraftAMSSection
16.2.16.2
132 dCommunicatingtorelevantstakeholders,theresultsof
investigations.3 Developing
TheresultsofinvestigationsarecommunicatedtostakeholdersassummarisedindraftAMS
Section16.2.16.2
ASSETMANAGEMENTPRACTICES 285
Recommended Actions
ThatWestpowersummarisesitscompliancereportsandholdsthedocumentationinSharepointsothereviewprocesscanmonitorcompliance.
8.12.25Audit
“Auditprogramsshallbeplanned,established,implementedandmaintainedbytheorganisation,basedontheresultsofriskassessmentsandpreviousaudits.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Westpowerdoesnotappeartohaveaformalprogrammeofauditsoftheassetmanagementsystemanditsprocesses.Itisrecommendedthatanauditprogramofkeyprocessesandactivitiesbeimplementedfollowingtheimplementationofformalassetmanagementsystem.
0
1
2
3
4
5
6
Au
dits c
on
du
cte
d to
de
term
ine
if th
e A
MS
co
nfo
rms to
pla
nn
ed
arr
an
ge
me
nts
fo
r a
sse
t
ma
na
ge
me
nt.
Au
dits c
on
du
cte
d to
de
term
ine
if th
e A
MS
ha
s
be
en
im
ple
me
nte
d a
nd
ma
inta
ine
d.
Au
dits c
on
du
cte
d to
de
term
ine
if th
e A
MS
is
effe
ctive
in
me
etin
g th
e
org
an
isa
tio
n's
po
licy,
str
ate
gy a
nd
ob
jective
s.
Pro
vid
e in
form
atio
n to
ma
na
ge
me
nt.
PAS-55 Aligned
Table 8.12.24 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.6.3 Evaluation of Compliance
133 a
Organisationestablished,implementedandmain-tainedprocessesandpro-ceduresforevaluationofitscompliancewithlegalandotherregulatoryrequire-
ments.
4 CompliantLegalcomplianceisreportedtotheBoardas
detailedindraftAMSSection17alongwithKPIonzeroregulatorybreaches.
16
286 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Recommended Action
ThatWestpowerimplementanauditprogramtoidentifynon-conformitiesandimprovementopportunitiesforkeyassetmanagementsystemprocesses.
8.12.26CorrectiveandPreventativeAction
“Theorganisationshallestablish,implementandmaintainprocessesandproceduresforinvestigatingcorrectiveactionforeliminatingthecausesofpoorperformanceandnonconformities.”
Review against PAS-55 Requirements
0
1
2
3
4
5
6
Inve
stig
atin
g c
orr
ective
actio
ns f
or
elim
ina
tin
g
po
or
pe
rfo
rma
nce
an
d
no
nco
nfo
rmitie
s.
Inve
stig
atin
g p
reve
nta
tive
actio
n f
or
elim
ina
tin
g t
he
po
ten
tia
l ca
use
s o
f
no
nco
nfo
rmitie
s o
r p
oo
r
pe
rfo
rma
nce
.
PAS-55 Aligned
Table 8.12.25 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.6.4 Audit
134 a
Auditsconductedtodeter-mineiftheAMSconformstoplannedarrangementsfor
assetmanagement.
3 Developing
TherehavebeenongoingauditsforAMplan-ningincludingPAS55auditsandreviewsas
summarisedindraftAMSSection18.TheAMSisstillnotcompliantsounabletorateascompli-
antuntilfullyimplemented.
18
135 b
Auditsconductedtodeter-mineiftheAMShasbeenimplementedandmain-
tained.
3 Developing
TherehavebeenongoingauditsincludinggapanalysisforWestpowertoseekfullPAS55com-plianceassummarisedindraftAMSSection18.Unabletogetfullmarksuntilfullyimplemented.
18
136 c
Auditsconductedtodeter-mineiftheAMSiseffectiveinmeetingtheorganisa-tion’spolicy,strategyand
objectives.
3 Developing
ThiscannotbeevaluateduntiltheAMSisfullyimplemented.ItisexpectedthatfutureauditswillevaluatetheAMSeffectivenesssounableto
rateascompliantuntilfullyimplemented.
18
137 d Provideinformationtoman-agement. 3 Developing
Theauditsfindingsneedtobeformallyprovidedtomanagement(andtheBoard).ThisshouldbeexplicitlystatedindraftAMSSection18.
18
ASSETMANAGEMENTPRACTICES 287
Observations and Improvement Opportunities
Where corrective or preventative action identifies new or changed risks, or the need for new or changedprocedures,theproposedactionsshallberiskassessedpriortoimplementation.
Recommended Action
ThatWestpowerformallyintroduceprocessesandproceduresthatassesstheriskofcorrectiveandpreventativeactions.
8.12.27ContinualImprovement
“Theorganisationshallestablish,implementandmaintainprocessesandproceduresforidentifyingopportunitiesandassessing,prioritisingandimplementingactionstoachievecontinualimprovement.”
Review against PAS-55 Requirements
Table 8.12.26 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.6.5.1 Corrective and Preventative Action
138 a
Investigatingcorrectiveactionsforeliminatingpoorperformanceandnoncon-
formities.
3 Developing
TheprocessforinvestigatingcorrectiveactionsissummarisedindraftAMSSection16.2for
assetfailuresandlargerfaults.Thereneedstobemoreactionstoaddresstherootcausesofidentifiednonconformancestorateascompli-ant.Thismayincludechangestoprocessorrisk
profiles.
16.2
139 b
Investigatingpreventativeactionforeliminatingthepotentialcausesofnoncon-formitiesorpoorperfor-
mance.
3 Developing
Therearedebriefingsessionsforlargerfaultswithminutestaken.TheIncidentInvestigationReportincludescorrectiveaction.Thereneedstobemoreactionstoaddresstherootcausesofidentifiednonconformancesbeforetheinci-
dentsoccurtorateascompliant.
16.2
0
1
2
3
4
5
6
Op
tim
al co
mb
ina
tio
n o
f
co
sts
, a
sse
t re
late
d r
isks
an
d t
he
pe
rfo
rma
nce
an
d
co
nd
itio
n o
f a
sse
ts a
nd
asse
t syste
ms a
cro
ss t
he
life
cycle
of
the
asse
ts.
Pe
rfo
rma
nce
of
the
AM
S.
Active
ly s
ee
k a
nd
acq
uir
e
kn
ow
led
ge
ab
ou
t n
ew
AM
rela
ted
te
ch
no
log
y a
nd
pra
ctice
s.
PAS-55 Aligned
288 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Observations and Improvement Opportunities
Theorganisationshallactivelyseekandacquireknowledgeaboutnewassetmanagement-relatedtechnologyand practices, including new tools and techniques, and these shall be evaluated to establish their potentialbenefittotheorganisation.
Recommended Action
ThatWestpowercontinueimprovementasanongoingprocessanddocumenttheactivitiesundertaken.
8.12.28Records
“The organisation shall establish and maintain records as necessary to demonstrate conformance to therequirementsofitsAMSandofPAS-55.”
Review against PAS-55 Requirements
0
1
2
3
4
5
6
Ke
ep
re
co
rds o
f e
sse
ntia
l in
form
atio
n g
en
era
ted
wh
ilst
resp
on
din
g t
o a
nd
ma
na
gin
g in
cid
en
ts a
nd
em
erg
en
cie
s.
Ke
ep
re
co
rds o
f th
e t
rain
ing
pro
vid
ed
.
Ke
ep
re
co
rds f
or
ma
inte
na
nce
an
d c
alib
ratio
n o
f to
ols
an
d e
qu
ipm
en
t.
Ke
ep
re
co
rds f
or
mo
nito
rin
g a
nd
me
asu
rem
en
t o
f
pe
rfo
rma
nce
of
the
asse
t syste
ms a
nd
AM
S.
Ke
ep
re
co
rds o
f e
va
lua
tio
ns o
f co
mp
lia
nce
with
le
ga
l
an
d o
the
r re
qu
ire
me
nts
.
Ke
ep
re
co
rds o
n t
he
re
su
lts o
f a
ud
its.
Ke
ep
re
co
rds o
n t
he
de
tails o
f co
rre
ctive
an
d
pre
ve
nta
tive
actio
ns.
Ke
ep
re
co
rds o
f m
an
ag
em
en
t re
vie
ws.
Ke
ep
re
co
rds o
f a
sse
t m
an
ag
em
en
t re
late
d
co
mp
lain
ts.
Ke
ep
re
co
rds o
f th
e r
esu
lts o
f id
en
tifica
tio
n o
f ri
sks.
Ke
ep
re
co
rds o
f p
ert
ine
nt
co
ntr
acto
r a
nd
su
pp
lie
r
info
rma
tio
n.
Ke
ep
re
co
rds o
f e
me
rge
ncy p
rep
are
dn
ess a
nd
resp
on
se
, in
clu
din
g t
he
re
su
lts o
f te
stin
g c
on
tin
ge
ncy
pla
ns.
PAS-55 Aligned
Table 8.12.27 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score MaturityLevel Comments AMSSec-
tion
4.6.5.2 Continual Improvement
140 a
Optimalcombinationofcosts,assetrelatedrisksandtheperformanceand
conditionofassetsandassetsystemsacrossthelifecycle
oftheassets.
3 Developing
ThecontinuousimprovementprocessisthroughtheAMPprocessandtheAMGasstatedindraftAMSSection19.Itisiterativebutitisrecog-
nisedthatthereisnoformaldocumentationforthereviewprocesssounabletoachievecompli-
ancestatus.
19
141 b PerformanceoftheAMS. 4 CompliantWestpowermonitorstheperformanceoftheAMSthroughtheirPAS55gapanalysis,as
statedindraftAMSSection19.19
142 c
ActivelyseekandacquireknowledgeaboutnewAMrelatedtechnologyand
practices.
4 CompliantWestpowerareactiveinthisareaincludingEEAconferences,subscribingtotechnicaljournalsas
detailedindraftAMSSection19.19
ASSETMANAGEMENTPRACTICES 289
Observations and Improvement Opportunities
WestpowerhasintroducedSharepointasameansofcompliancewithrecordkeeping.ThisprocessneedstobefullydevelopedtocomplywithPAS-55.
Table 8.12.28 4.6 - Performance Assessment and Improvement
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.6.6 Records
143 a
Keeprecordsofessentialin-formationgeneratedwhilstrespondingtoandmanagingincidentsandemergencies.
4 Compliant AllincidentsarefullyinvestigatedandrecordsarekeptofactionsinTheVault. 20
144 b Keeprecordsofthetrainingprovided. 4 Compliant
ThetrainingrecordsareheldinTheVaultforcontractorandAMG.TheassociateddocumentAMGtrainingrecordswereprovidedforthis
review.
20
145 cKeeprecordsformainte-nanceandcalibrationoftoolsandequipment.
4 CompliantThetestroomholdsrecordsofthemaintenanceandcalibrationoftoolsandequipment.ThesearetobescannedandputontoSharepoint.
20
146 d
Keeprecordsformonitoringandmeasurementofperfor-manceoftheassetsystems
andAMS.
3 Developing
RecordsformonitoringandmeasurementofperformanceoftheassetsystemsandAMShavenotyetstartedasitisanewprocess.There-
cordswillbekeptinSharepointasstatedindraftAMSSection20.Thiscriterioncannotachieve
complianceyetasnotunderway.
20
147 eKeeprecordsofevaluationsofcompliancewithlegaland
otherrequirements.4 Compliant TheRegulationRegisterrecordsevaluationsof
compliancewithlegalandotherrequirements. 20
148 f Keeprecordsontheresultsofaudits. 3 Developing
AformalAMSauditisstilltobecompletedbuttheauditfindingswillberecordedinSharepoint.Thiscriterioncannotachievecomplianceyetas
notunderway.
20
149 gKeeprecordsonthedetailsofcorrectiveandpreventa-
tiveactions.4 Compliant
RecordsarekeptinMaximoofallcorrectiveandpreventativeactions.AlsorefertothenewAM
ReviewProcessreport.16.2
150 h Keeprecordsofmanage-mentreviews. 4 Compliant
CurrentandfutureplannedmanagementreviewsaredetailedindraftAMSSection21.ThereisanewAMReviewProcesstemplatewhichislinkedasanassociateddocument.
21
151 i Keeprecordsofassetman-agementrelatedcomplaints. 4 Compliant
ThereisaformalcomplaintssystemthatisrecordedinTheVault.ThereisaComplaint
Guidelinewhichshouldbeaddedasanassoci-ateddocument.
20
152 j Keeprecordsoftheresultsofidentificationofrisks. 4 Compliant
RiskidentificationisdetailedintheRiskManage-mentAnalysis,anassociateddocument.Theassociateddocumentscontractorandsupplier
recordswereprovidedforthisreview.
20
153 kKeeprecordsofpertinentcontractorandsupplier
information.4 Compliant
ContractorandsupplierrecordsareapprovedbyAMGandmaintained.Theassociateddocu-mentscontractorandsupplierrecordswere
providedforthisreview.
20
154 l
Keeprecordsofemergencypreparednessandresponse,includingtheresultsoftest-
ingcontingencyplans.
3 Developing
TheERPisWestpower’sformalemergencypreparednessandresponseplan.Itneedstobeclearwheretheemergencydebriefrecordsarekept.ContingencyplantestinghasnotbeenrecordedtodatebutweunderstandthatWest-powerhasidentifiedthisasafutureaction.
20
290 WESTPOWERASSETMANAGEMENTPLAN2012-2022
0
1
2
3
4
5
6
Ma
na
ge
me
nt
revie
ws in
clu
de
th
e r
esu
lts o
f in
tern
al
au
dits a
nd
eva
lua
tio
n o
f co
mp
lia
nce
with
le
ga
l
req
uir
em
en
ts.
Inclu
de
th
e r
esu
lts o
f co
mm
un
ica
tio
n w
ith
em
plo
ye
es.
Inclu
de
co
mm
un
ica
tio
n w
ith
exte
rna
l sta
ke
ho
lde
rs.
Inclu
de
re
po
rts o
n a
sse
t m
an
ag
em
en
t.
Inclu
de
th
e e
xte
nt
to w
hic
h o
bje
ctive
s h
ave
be
en
me
t.
Inclu
de
pe
rfo
rma
nce
in
ad
dre
ssin
g in
cid
en
t
inve
stig
atio
ns a
nd
co
rre
ctive
an
d p
reve
nta
tive
actio
ns.
Inclu
de
fo
llo
w-u
p a
ctio
ns f
rom
pre
vio
us r
evie
ws.
Do
th
e m
an
ag
em
en
t re
vie
ws in
clu
de
ch
an
gin
g
cir
cu
msta
nce
s,
inclu
din
g d
eve
lop
me
nts
in
le
ga
l
req
uir
em
en
ts
Ou
tpu
ts f
rom
ma
na
ge
me
nt
revie
ws a
re c
on
sid
ere
d in
revie
ws o
f th
e o
rga
nis
atio
na
l str
ate
gic
pla
n
Re
co
rds o
f m
an
ag
em
en
t re
vie
ws
PAS-55 Aligned
Recommended Action
ThatWestpowercontinuetodevelopand implementSharepoint forthemanagementofassetandAMSandrecords.
8.12.29ManagementReview
“TheorganisationshallreviewtheAMStoensureitscontinuingsuitability,adequacyandeffectiveness.”
Review against PAS-55 Requirements
Observations and Improvement Opportunities
Reviews shall include assessing the need for changes to the asset management system, including assetmanagementpolicy,strategyandobjectives.
ASSETMANAGEMENTPRACTICES 291
Recommended Action
ThatWestpowerreviewitsAMSonanannualbasis.
8.12.30ConclusionsandRecommendations
The intent of the PAS-55 specification is to define a suite of requirements which form an effective assetmanagementsystemintendedtoensuretheconsistentdeliveryoftheorganisationsassetdependentobjectives.ThefocusofPAS-55isthereforeanendtoendprocessofdiscipline,governanceandcontrol.
Table 8.12.29 4.7 - Management Review
Q# PAS-55 Criteria Score Maturity Level Comments AMS
Section
4.7 Management Review
155 a
Managementreviewsin-cludetheresultsofinternalauditsandevaluationofcompliancewithlegalre-
quirements.
4 Compliant
PAS55gapanalysisandtheOSParethecurrentinternalsystemsforAMSmanagementreviewsasdetailedindraftAMSSection21.Anew
ReviewProcesstemplatehasbeendevelopedtoformalisetheprocessfurther.TheevaluationoflegalcomplianceissummarisedindraftAMSSection17.Asamplecompliancereportisstilltobeprovidedasanassociateddocument.
17,21
156 b Includetheresultsofcom-municationwithemployees. 4 Compliant
ThereisfullparticipationofthoseinvolvedwithallincidentinvestigationsasstatedindraftAMSSection21.OtherresultsofcommunicationwithemployeesandstakeholdersonAMSareevaluatedintheAMSReviewProcessReport
21
157 c Includecommunicationwithexternalstakeholders. 4 Compliant
Managementreviewcommunicationwithexter-nalstakeholdersisevaluatedintheAMSReview
ProcessReport.21
158 d Includereportsonassetmanagement. 4 Compliant
AssetmanagementisreviewedonanannualbasisthroughAMPandOSPprocessesasstated
indraftAMSSection21.21
159 e Includetheextenttowhichobjectiveshavebeenmet. 4 Compliant Theachievementoftheobjectivesisevaluated
intheAMSReviewProcessReport. 21
160 f
Includeperformanceinad-dressingincidentinvestiga-tionsandcorrectiveandpreventativeactions.
4 Compliant
AllincidentinvestigationsincludecorrectiveandpreventativeactionsasdetailedindraftAMS
Section16.2andarerecordedintheIncidentIn-vestigationReport.TheperformanceofIncidentinvestigationsisevaluatedintheAMSReview
ProcessReport.
16.2,21
161 g Includefollow-upactionsfrompreviousreviews. 4 Compliant Thefollow-upactionsfrompreviousreviewsare
evaluatedintheAMSReviewProcessReport. 21
162 h
Dothemanagementreviewsincludechangingcircum-stances,includingdevelop-mentsinlegalrequirements
3 Developing
ChangingcircumstancesisinferredwiththeiterativenatureofthemanagementprocessasshowninthediagramindraftAMSSection21.Thiscouldbestrengthenedbyexplicitlystating
this.
21
163 i
Outputsfrommanagementreviewsareconsideredin
reviewsoftheorganisationalstrategicplan
4 CompliantManagementreviewsfeedintothereviewoftheOSPasshowninthediagramindraftAMS
Section21.21
164 j Recordsofmanagementreviews 4 Compliant Theresultsofthemanagementreviewsare
documentedintheAMSReviewProcessReport. 21
292 WESTPOWERASSETMANAGEMENTPLAN2012-2022
ItshouldbenotedthatPAS-55isintendedtoapplytothemanagementofphysicalassetsbyorganisationsofallsizes,rangingfromlargenationalinfrastructureprovidersinheavilypopulatedcountries(forexampletheUKNationalGrid)tosmallregionalinfrastructureproviders.Organisationsofsuchvaryingsizewillhavedifferentneedsforthelevelofcorporategovernanceandprocessdocumentation.ItisimportantthatarelativelysmallregionalinfrastructuremanagersuchasWestpowerinterpretPAS-55inamannerthatwillassureconsistentriskmanagedperformance,withoutcreatingunnecessaryadministrativeburdenandcost.
Thekeyfindingsof this revieware centredonWestpower formally identifying, reviewing,documentingandimplementingkeyassetmanagementprocessestoformanoverallassetmanagementsystem.Ifdonesensitively,WestpowerwillbeabletodesignaPAS-55compliantsystemthatminimisestheneedforadministrativeburdenwhileassuringconsistentriskmanagedoutcomes.
WestpowerhasconsciouslydecidedanddocumentedhowitwillrespondtoeachPAS-55requirementtakingintoconsiderationthesizeandscopeoftheassetmanagementoperationandtheresourcesavailable.
AsummaryofWestpower’scurrentpositionwithrespecttodocumentationofPAS-55requirementsisshowninFigure8.4.ThischarthighlightsanumberofareaswhereWestpower’sdocumentationandsystemsaddress95%ofPAS-55requirementswithsomeminoradditionalworkrequiredtotakingthisscoreto100%
InordertoprogresstowardsfullPAS-55conformance it isrecommendedthatWestpowertakethefollowingbroadapproach:
1. Identifyandsetupaprogramofwork,includingtimelinesandresponsibilities,forfullimplementationofthedocumentedprocesses.
2. Considerthedatarequirementsandinformationflowforeachoftheidentifiedprocessesto identifyanddocumentthe‘musthave’dataandinformationrequirements.Ifgapsexistimplementadataimprovementplan.
3. Implementaformalriskmanagementprocessintegratedwiththeaboveprocesses.It issuggestedthataformalisedriskmanagementprocesswouldassistin:
• Providingassurancethatthekeyassetrelatedrisksareidentifiedandunderstood.
• Transparently demonstrating the prudence of asset management decisions whether they be to applyresourcestomitigatearisk,ortoacceptariskastolerable.
4. Implementanauditandreviewprogramtomeasureprocessconformanceanddrivecontinualimprovement.
ASSETMANAGEMENTPRACTICES 293
8.13 Asset and Works Management System Development
8.13.1 Background
TheimplementationofIBMMaximo®hasbeenextremelysuccessfulandpostimplementationWestpowerhasstarted to realizegenuinebenefits. Thesechangeshavebeen successfullyembedded into standardbusinessprocessandarebeingcontinuallymonitoredandupdatedasrequired.
During 2011,Westpower’s IBMMaximo® Asset andWorksManagement System (AWMS) was upgraded tothelatestavailablespecification.ThesystemintegratorinpartnershipwithWestpower’sAWMSprojectteam,providedacomprehensivesolutionwhichmetfunctional,financialandtimebasedtargets.
IntegratedwithGISandFMISsystems,Maximo®embodiescomprehensiveassetmanagementprocesseswhichsupportmanagers,contractorsandcustomers.
DaytodayassetmanagementactivitieshavebeenfullyintegratedintoMaximo®,includingmonthlyinvoicingandwork order reconciliations. Reports have been developed to assistmanger’s interpretation of data andstrategicplanningisbecomingmorefrequentasinformationandprocessesimprove.
Figure8.6-SummaryChartShowingWestpower’sCurrentCompliancewiththeRequirementsofPAS-55.
0%
10%
20%
30%
40%
50%
60%
70%
80%
90%
100%
4.1.1 Asset Management System
4.1.2 Review against PAS 55-1
4.2 Asset Management Policy
4.3.1 Asset Management Strategy
4.3.2 Asset Management Objectives
4.3.3 Asset Management Plans
4.3.4 Contingency Planning
4.3.4 Contingency Planning
4.4.1 Structure, Authority and Responsibilities
4.4.2 Outsourcing of Asset Management Activities
4.4.3 Training, Awareness and Competence
4.4.4 Communication, Participation and Consultation
4.4.5 Asset Management System Documentation
4.4.6 Information Management4.4.7.2 Risk Management Methodology4.4.7.7 Risk Identification and Assessment
4.4.7.8 Use and Maintenance of Asset Risk Information
4.4.8 Legal and Other Requirements
4.4.9 Management of Change
4.5.1 Life cycle Activities
4.5.2 Tools, Facilities and Equipment
4.6.1 Performance and Condition Monitoring
4.6.2 Investigation of Asset-related Failures, Incidents and
Nonconformities
4.6.3 Evaluation of Compliance
4.6.4 Audit
4.6.5.1 Corrective and Preventative Action
4.6.5.2 Continual Improvement
4.6.6 Records
4.7 Management Review
Current Practice
PAS-55 Aligned
Best Practice
294 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Figure8.7showsthemodelforthecurrentAWMS.
8.13.2 GeographicalInformationSystem(GIS)
GISistherepositoryforallNetworkspatialdata.Itcontainsandmanagesattributiondatarelatingtolocations,polesandcablespans,whichisusedtodescribethenatureandconditionofthelocation.Thisdataassistswiththedevelopmentofthepreventativemaintenanceprogramme.GISalsoprovidesnetworkconnectivity,whichisusedtoevaluatetheimpactonconsumers,orpackageworkonfeeders,duringoutages.Thisprocessminimisesconsumerdisruption,reducescostsandfacilitatessafeworkingenvironments.
8.13.3 Maximo
Maximoistherepositoryforallassetandworksmanagementdata.Italsostoresdatarelatingtolocations,whichissynchronisedeachnightfromGIS.Maximoalsomanagesthefollowingbusinessprocesses:
Budgets
Maintenance–preventative/defects
Workflows
Outagemanagement
Conditionassessment
ODV
Assetregister
Generalmaintenance
Figure8.7-ShowstheModelfortheCurrentAWMS
ASSETMANAGEMENTPRACTICES 295
Inventory
Invoicing
Workordermanagementandservicerequests
8.13.4 Maintenance
PreventativeMaintenance(PM)-Considerableeffortisbeingputtowardthepreventativemaintenanceplan.PMscheduleshavebeendevelopedwithjobplansandroutesandthesearenowusedforthemajorityofscheduledmaintenanceworkprogrammes
DuediligenceneedstobegiventothestructureappliedtothePMprocesstoensurethatitisnotoverlyarduousbutatthesametimecomprehensive.Westpowerhasconductedanengineeringassessmentofnetworkassetsand in conjunction with manufacturer’s recommendations is developing a maintenance programme, whichidentifiesthefrequencyofmaintenancerequiredandlistmaintenancetasks.ThemaintenanceprogrammeismonitoredviathePMReport.
Defects–Faultandfailuresarenowbeingreportedon.Afailurereportwhichidentifiestheproblem/cause/remedyisappliedtoall faultsandassessedbyengineers to identifyrecurringproblems.AdditionallycontractorsareencouragedtosubmitservicerequeststoWestpoweridentifyinganydamageorrepairsrequiredtothenetwork.WorkflowprocessesdirectthesetotheappropriateAssetManagementdepartment.Furtherdevelopmentworkisplannedtoprovidebetterreportingofdefectssothatfuturemaintenanceplansarebetterinformed.
8.13.5 Workflows
WorkflowsareanintegralpartofMXESandprovidesignificantbenefitstobothWestpowerandENS.Anumberofworkshopshavebeenconducteddiscussingbusinessprocessesandformulatingworkflows.Workflowsprovidethegreatestchallengesandhavethepotentialtoproducethemostsignificantbenefitstobusinessprocesses.
WestpowerhasassumedownershipofWorkflowcreationandmaintenance.Havingstaffwithintheorganisationwiththeseskillssimplifiescustomisationandensuresthatchangesaretimely.
8.13.6 OutageManagement
Throughregulatorylegislation,Westpowerisobligedtomaintaintransparentoutagemanagementsystems.In-housesystemsbasedontheGISsystemhavebeendevelopedtocarryoutthisfunction.
8.13.7 ConditionAssessment
Anadd-ontotheGISsystemhasprovidedforconditionassessmentdatacapture.ArcPad,an“outofthebox”GISpackage,hasprovidedconsiderablebenefitsovercustomisedprogramming.
ThedevelopmentofArcPadtomeettherequirementsofWestpower’sconditionassessmenthasprimarilybeendoneinhouse.
8.13.8 AssetRegister
Theassetregisteristheprimaryrepositoryforinformationrelatingtoassetlifecyclemanagementandtechnicalperformance. The asset register provides theWestpower assetmanagement groupwith the ability to trackequipment,associatedcosts,historiesandfailuresofallassets.
296 WESTPOWERASSETMANAGEMENTPLAN2012-2022
ThecurrentassetmodelisshowninsimplifiedforminFigure8.8.
WESTPOWERNetwork Model
GXPPoint of Supply
Sub Transmission
Zone Subs
SubTran SegmentLocations
TransformerLocations
SwitchgearLocations
VegetationLocations
SwitchgearLocations
BusLocations
CommonServices
SwitchgearLocations
SwitchgearAssets
SpanAssets
OtherAssets
SwitchgearAssets
Vegetation
Pole/TowerAssets
Zone TransformerAssets
SpanComponents
Pole/TowerComponents
Zone TransformerSpares
SwitchgearAssets
BusAssets
Asset ClassRecords
SwitchgearSpares
Attribute links
Location l inks
As set L inks
ASSETMANAGEMENTPRACTICES 297
8.13.9 AssetsHeldinMaximo
Attribution,meterandconditiondataisheldforthefollowingassettypes:
DuringtheimplementationofMaximodatawastransferredfromGentracktoMaximoSystems.Themajorityofthisdatahassincebeenpurifiedandwillcontinuetobeassessedandcorrectedasrequired.
GenerallyallhighvoltagelocationsandassetsarerecordedinGISandMaximo.Recentlyaprogrammehasbeenstarted to loadall400V locationandassetdata.Thisprogramme isongoingandexpected tobecompletedwithinthenextyear.
8.13.10GeneralMaintenance
ContinualimprovementisbeingmadetoallMaximo®integratedsoftwaremodules.AdedicatedMaximo/GISadministratorisfacilitatingcoordinatedsystemmanagement,whichwillguaranteeconstantimprovementandlongevity.
8.13.11StrategicManagement
AlltheelementsofMaximo®andGISsystemsmentionedabovehaveprovidedWestpowerwithaccurateandtimely information to support the decisionmaking process. Reports have been structured formanagers atvariouslevelsoftheorganisationtoassistthemineffectivelymanagingtheirrespectivedepartments.Improvedplanning,maintenanceandreportingarecontributingtoawellperformingnetworkalongwithimprovedsecurityofsupplyforconsumers.
Asset Asset Class
OperatingEquipment
PillarBoxes
CircuitBreakers CircuitBreakers(Oil/Vacuum)and
Reclosers
ControlPanels
Disconnectors
Machines Batteries,Rectifiers,Inverters,
DC/DcConverters
Poles AllMaterialTypes
Radios/SCADA
Regulators
Relays
Transformers ZoneSub,Distribution,Metering,
Voltage,Current,Earthing
LinesandCable UndergroundandOverhead
CapacitorsandInductors
298 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Table 9.1 - Example Risk Ratings
Risk Factor Rating Recommendations
PhysicalSecurity 30
Reviewsecurityrequirementsforeachofthesub-stations.
InvestigatebenefitsofinstallinganalarmsysteminFranzJosefsub-stationmonitoredthroughSCADAandpersonnelpagers.
KeyRegisterneedstobeupdatedandunreturnedkeysretrievedwherepossible.Ifthiscannotbedonethenanassessmentshouldbemadeofcriticalsecuritypointsandlocksreplacedinthese
places.
PlantMaintenance 24
Continuetheprocessofimprovementoftheexistingplantmaintenanceandlifecycleplanningandreportingstrategy.
EnsurethattheMaximoAssetWorksManagementSystem(AWMS)enhancementsarematchedwithanyrevisionstotheplantmaintenancestrategy.
ReviewtheprocessofissuingscheduledworkorderstoensureamatchtotheAssetManagementPlan.Needtoensurethereisahighdegreeofconsistency.
9.0 RISK MANAGEMENT PLANWestpowerhas a separateRiskManagement Plan (RMP) completed as part of its overall business planningstrategy.ThisincludesBusinessImpactAnalysisandBusinessContinuityPlanning.
Inaddition,WestpowerisactivelyinvolvedinaregionalLifelinesprojectlookingatwaysofmanagingtherisksinvolvedwithmajordisastersandensuringthatplansareinplacetodealwithmostofthelikelyscenarios.
Ageneraloverviewoftheriskmanagementprocessisincludedbelowtodemonstratetherobustandprofessionalapproachtakentothisimportantaspectofplanning.
TheRMPisalivingdocumentthatisregularlyupdated.
9.1 Risk Management Planning Framework
Adetailedriskassessmentwasconductedwhich:
• Definedspecificrisks;
• Assessedthepotentialimpactofeachriskonasix-pointscalefrom100[Minor]to600[Critical];
• Assignedmanagementresponsibilitytoeachrisk;
• Identifiedcurrentcontrolmeasuresforallriskswithapotentialimpactof300[Major]oraboveandratedtheeffectivenessofthecontrols;
• Exploredthelikelihoodofoccurrence;
• Documentedtheresults.
The methodology adopted was consistent with the joint Australian and New Zealand Standard AS/NZSISO31000:2009. It is a simple andeffectivemethod,but remains subjective. The validityof the risk controlassessmentsmayrequirefurtherinvestigationandanalysisbyWestpower,particularlywheretheriskiscriticaltothebusiness.AnexampleofoneoftheoutputsisshowninTable9.1.
9.2 Risk Planning Methodology
TheriskmanagementteamfacilitatedaworkshopwithWestpower’smanagementtoworkthroughandassesstheimpactof60riskspresentedinaframeworkunder13categories.
Figure9.2chartsthemethodologyusedforWestpower.Inthisdiagram,theprocessboxes,numbered1to10,correspondwiththeprocessmethodologystagedescriptionsthatfollow.
RISKMANAGEMENTPLAN 299
Stage 1. Assess Potential Risk Consequence
Riskismeasuredintermsofconsequenceandlikelihood.Attheworkshop,Westpowermanagementassessedthepotentialimpactofeachriskontheorganisation.TheirassessmentofthepotentialriskconsequencewasbasedonthefollowingtabledevelopedinconsultationwithseniorWestpowerManagement.
Figure9.2-WestpowerRiskPlanningMethodology
300 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Stage 2. Identify Responsibility
Oneofthetaskscompletedattheworkshopwastoidentifytheresponsiblepersonforeachoftherisksgivenaconsequencerating.Itisthepersonidentifiedthatisbestabletoratethecurrentcontroleffectiveness.
Stage 3. Identify High Consequence Risks
Akeyaimoftheriskworkshopwastoseparateoutthesignificant,high-impactrisksforfurtherattentionfromthosewithlesserimpacts.Usingacut-offriskimpactlevelof300thefollowinglistofriskswasshortlistedforfurtherattention.Eachoftheseriskswereassessedindetailininterviewsconductedwiththestaffresponsibleidentifiedattheworkshop.
Table 9.3 - Risk Consequences
Rating Level Possible Impact on Company Anualised Financial Impact
600 Critical
BoardapprovalforactionsandongoingsupportfromtheCompany’sbankersrequired.
Greaterthan$5millionHighPriorityactionsneededtorecoversituation.
Lossofstakeholdersupport.
Majorstakeholderconcern.
ViabilityofCompanythreatened.
500 Severe
DirectInterventionoftheBoard.
Between$1millionand$5million
UrgentandsustainedManagementactionrequiredtopreventcrisis.
Stakeholderuneaseandreducedsupport.
Highprofile,adversenationalmediacoverage(TV,radioandprint).
Highnumberofpeopleaffectedbyanincidentoroveryearbyinci-dents.
400 Major
ImmediateManagementactionneededtocontrolthesituation.
Between$500,000and$1million
Multipleincidentsaffectasignificantnumberofpeopleayearintotal(Non-random).
Majorstakeholderconcern.
Adversenationalmediacoverage(TV,radioandprint).
300 Significant
Managementactionneededtopreventescalation.
Between$100,000and$500,000
Multipleincidentsaffectasignificantnumberofpeopleayearintotal(Random).
Widespreadcomplaints(publicandcommunityorganisations).
Adversenationalmediacoverage(print).
200 Moderate
Actionneededtoconfirmcontrols.
Between$50,000and$100,000
Adverselocalmediacoverage(notpickedupnationally).
Localisedcomplaints(smallgroupsorcommunities).
Singleincidentaffectsasmallnumberofpeople.
100 Insignificant
CoveredundernormalManagementactions.
Lessthan$50,000Negativelocalmediacoverage.
Personalgrievanceclaim.
RISKMANAGEMENTPLAN 301
Stage 4. Identify Current Controls
Aspartoftheinterviewprocess,eachhighimpactriskwasdiscussedindetailandadescriptionofthecurrentcontrolmethodsdeveloped.Theseresultswerecapturedinrisktemplates.
Stage 5. Assess Control Effectiveness
Next,thecontroleffectivenessofthecurrentcontrolmethodswasassessedusingthefollowingratingscale.
Stage 6. Review Control Weakness and Loss History
Also,asapartoftheinterviewprocess,anassessmentwasmadeoftheweaknessesassociatedwiththecurrentcontrolmeasures.Atthesametime,suggestionsforimprovementswereputforwardbymanagersandabriefreviewoftherecentlosshistoryforthisriskwasnoted.
Stage 7. Assess Likelihood of Occurrence
Westpower staffwere asked to rate the likelihood of a loss against the risk exposure. The risk exposure isdeterminedbysubtractingthecontrolseffectivenessfromtheriskconsequence.
Thelikelihoodwasassessedbyusingthefollowingscale(Table9.6):
Table 9.4 - High Consequence Risks
Risk Consequence
FuturePlanning 400
CriticalAssets 336
ContractManagement 320
EmergencyManagement 300
InformationSystems 300
InformationManagement 300
UnethicalBehaviour 300
Table 9.5 - Control Effectiveness
Control Effectiveness Descriptor Definition
95% Excellent Thecontrolsinplacemitigatetherisktothemaximumextentandarebe-ingperformedinthemannerforwhichtheyweredesigned.
80% Verygood Thecontrolsandproceduresareverygood.Thereissmallroomforim-provement.
70% Good Themajorityoftheriskismanaged,howeverthereispotentialforthecontrolstofail.Animprovementisrecommended.
55% Adequate Thecontrolsandproceduresmanagetheriskatfacevalue.Thereisagreatrelianceonthemoperatingcorrectlywithoutanychecksorassurances.
45%+ Unacceptable Thecontrolsmanageonlysomeoftherisk.
30%+ Non-existent Thecontrolsarelargelypassive.
Table 9.6 - Likelihood of Occurrence
Likelihood Descripton Definition
0.95 AlmostCertain
Thereisanextremelyhighexposuretotherisk(frequency).Controlsareunlikelytopreventrealisationofpotentialimpact.
OR
Anexternalinfluencewillalmostcertainlyoccurandrendertheinternalcontrolsinoperative.
302 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Stage 8. Calculate Exposure and Residual Risk
Theresidualriskvaluecanbecalculatedusingthefollowingformula:
Stage 9. Prioritise Risks
Byusingtheriskassessmentformulashownabove,wewereabletoprioritisethetoprisksforWestpowerbasedupontheresidualrisklevel.TherisksareshowninorderinTable9.7.
Stage 10. Action Plan Development
TheRiskManagementTeambelievesthatanyriskwitharesidualratingof5oraboveshouldbematchedbyacorrespondingActionPlan.Therearesixrisksintheabovecategory.
Thesuggestedactionplanswereformulatedfromdiscussionsheldwithkeystaffduringtheinterviewphase.ThesewillbefurtherdevelopedbyWestpowerasthisiseffectivelyalivingdocument.
ANNUALISEDPOTENTIAL RISKCONSEQUENCE
CONTROLEFFECTIVENESS
RISKEXPOSURE
RISKLIKELIHOOD
RESIDUAL RISKLEVEL- = x =
Table 9.7 - Risk Priority
Risk Residual Rank
FuturePlanning 8.0 1
Operations 7.2 2
BusinessDevelopment 7.2 3
ContractManagement 7.0 4
Financial 6.9 5
Table 9.6 - Likelihood of Occurrence
Likelihood Descripton Definition
0.75 HighlyLikely
Thereisaveryhighexposuretotherisk(frequency).Noprovisiontoidentifythehigherpotentialimpactevents.Noconfidenceincontrolstopreventrealisationofpotentialimpact.
OR
Knownexternalinfluenceshavethepotentialtorendertheinternalcontrolenvironmentinoperative.
0.5 Likely
Thereisahighexposuretotherisk(frequency).Littleprovisiontoidentifythehigherpotentialimpactevents.Lowconfidenceincontrolstopreventrealisationofpotentialimpact.
OR
Goodreasontoexpectthatexternalinfluencesmaydegradetheinternalcontrolenvironmentinop-erative.
0.2 Possible
Thereisanexposuretotherisk(frequency).Someprovisiontoidentifyhigherimpactevents.Reason-ableconfidenceincontrolstopreventrealizationofpotentialimpact.
OR
Someuneasethatexternalinfluencesmaydegradetheinternalcontrolenvironment.
0.1 Unlikely
Thereislowexposuretotherisk(frequency).Provisionsinplacetoidentifyandtreathigherimpactevents.Goodconfidenceincontrolstopreventrealisationofpotentialimpact.
OR
Littlereasontobelievethatexternalinfluencesmaydegradetheinternalcontrolenvironment.
0.05 HighlyUn-likely
Thereislittleornoexposuretotherisk(frequency).Goodprovisionsinplacetoidentifyanddealwiththehigherimpactpotentialevents.Highconfidenceincontrolstopreventrealisationofpotential
impact.
OR
Externalinfluencesarenonexistentorrarewithlongreturnperiods.
RISKMANAGEMENTPLAN 303
9.3 Failure Mode and Effects: Criticality Analysis
Assetfailurewillbemanagedusingthefailuremodeandeffectscriticalityanalysisprocess.Thisformspartofthe“desiredpractice”foranoptimisedrenewalstrategy.
Having identified the failure modes, risk costs and treatment options for key assets, the appropriate risktreatmentoptionwillbeincludedintheAMP.Thisprocessandthetypicalfailuremodes,effectsandtreatmentsaresummarisedinFigures9.8and9.9.
9.4 Safety
SafetyisalwaysaprimedriverinanyriskmanagementstrategyandWestpowertakesthisseriously.Toensurethatthesemattersareproperlyaddressed,aformalhealthandsafetycommitteestructurehasbeencreatedandthiscommitteecomprisesawiderangeofstafffromallareasofthebusiness.
Inaddition,Westpower’scontractor,ElectroNetServicesLtd,hasbeenauditedbytheAccidentCompensationCommission,(ACC)andreceivedatertiarylevelgradingforitssafetyprocessesandsystems,thehighestgradingavailable.
Safetyiskepttotheforethroughregularrefreshercoursesandstafftrainingprogrammesdesignedtoenhancetheawarenessofsafetyissuesthroughoutallaspectsoftheworkplace.
Inadditiontotheabove,Westpowerensuresthatanactivehazardidentificationprogrammeisinplace,includingthedevelopmentofregistersforspecifictypesofhazard.Atzonesubstations,hazardidentificationnoticeboardsareusedtoinformallpersonnelcomingontositeofidentifiedhazards.Theyareencouragedtoaddanynewhazardsthatpresentthemselvestothelist.
Figure9.8-FailureModesAnalysisProcess
304 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Newequipmentisalwayscheckedforsafetyandspecificoperationalproceduresdevelopedwherenecessary.Allmanufacturersarerequiredtosupplymaterialsafetydatasheetsforsubstancesusedintheworkplace,andthesearekeptinareadilyavailableregister.
9.5 Environmental
OilspillsarethemostlikelyformofenvironmentaldamagetooccurasaresultofWestpower’sactivities.ThisriskhasbeenspecificallyidentifiedforfurtherattentionandhasbeenreportedatBoardlevel.
Tomitigatethisrisk,Westpowerhasinstalledbundingatallmajorsubstationswherethereareoilcontainmentvesselswithacapacityofmorethan1500litres.Allzonesubstationsarenowcompliant.
Spillresponsekitsaresuppliedtoallmajorsitesandstaffsaretrainedintheirusetomitigatetheimpactofanypotentialspill.
9.6 Key Risks Identified
KeyrisksforWestpoweraresimilarformostlinesbusinessesandaremainlyduetoclimaticandseismicfactors.
Westpowerhasidentifiedthefollowingmajorriskstoitsabilitytosupplyelectricity:
• Earthquakes,
• Storms(includinghighwinds),
• Lightning,
• Flooding,
• Rippleinjectionsystemfailure.
Figure9.9-TypicalFailureModes,EffectsandTreatments
RISKMANAGEMENTPLAN 305
9.6.1 Earthquake
ThelikelihoodofamajorearthquakeontheWestCoastduetoslippageontheAlpineFaultwithinthenext50yearsisconsideredtoberelativelyhigh.Thereisverylittlethatcanbedonetominimisetherisktooverheadlinesandcablesintheeventofanearthquake,butitisalsorelativelystraightforwardtostraightenpolesandrestringconductors,aslongasaccessandmaterialsareavailable.
ASeismicwithstandreportwaspreparedformostzonesubstationsinthe2003/04yeartoidentifyanyseismicstrengthening measures that can be taken to mitigate the impact of a major earthquake. Recommendedstrengtheningmeasuresidentifiedinthisreporthavebeenassessedandactionedwherenecessary.
Inaddition,Westpowercloselyco-operateswithotherELBsandusessimilar industrystandardequipmenttoensurethatareadysupplyofspareswillbeavailableifrequired.
9.6.2 StormDamage
Westpowerfacesthisriskregularly,withseveralmajorstormsexperiencedinanyoneyear.
Damageiscausedbypolesbeingblownoverand/ortreesorotherlargeobjectsbeingblownintotheoverheadlines.
Westpowermitigates this risk bymaintaining a regular pole inspection programme to check that poles areadequatelyratedandingoodcondition.Anypolesthatarefoundtobesubstandardarereplacedquickly.
AwiderangeofsparesarekeptbyWestpower’scontractor,includingpoles,conductors,fittingsandtransformerstoensurethatstormdamagecanbereadilydealtwith.Thelevelofsparesheldforvarioustypesofequipmenthasbeendevelopedthroughexperienceoveranumberofyears,andaregularreportingandreorderingprogrammeismaintainedtoensurethatminimumquantitiesaremaintained.
Inaddition,regionaldepotsaremaintainedatReefton,HokitikaandHariharisothatarapidresponsecanbeprovidedthroughoutWestpower’sarea.
9.6.3 Lightning
TheWestCoast is renownedas a significant lightning-prone regionofNewZealand, both in termsof strikedensityandintensity.
AsWestpowerhashad to livewith thisphenomenonovermanyyears, ithasdevelopeddesignpractices tominimise thedamage causedby lightning strikes. These include thefittingofmodern surgediverters on alldistributionsubstations,somethingnotcommoninmanypartsofthecountry.
Forzonesubstations,stationclass(linedischargelevel3)arrestorsarefittedontheterminalsofallmajorpowertransformers,andoverheadshieldwiresarefittedonincomingoverheadcircuits.
Asubstantialquantityofsparesareheldfortransformersaslightningisacommoncauseofdamageforthisplantandseverelightningeventscansometimeslastforseveraldays.
9.6.4 Flooding
Thisriskmainlyaffectsground-mountedassetssuchaspadmountdistributiontransformersandringmainunits.
Wherepossible,thelocationofthisequipmentischosensothatitisatleast300mmabovemaximumrecordedfloodlevels,althoughthisisnotalwaysfeasibleinareassuchastheCBDofGreymouth.
Intheeventofamajorflood,operationalplansareinplacetomakesurethatpowerisisolatedfromplantpriortofloodingreachinglevelswhereitcouldcauseanelectricalfaultandpossiblehazardstoworkersandthepublic.Ofcourse,thisisinadditiontothenormalprotectionsystemsusedtoisolateequipmentintheeventofafault.
306 WESTPOWERASSETMANAGEMENTPLAN2012-2022
9.6.5 RippleInjectionSystemFailure
TherippleinjectionsystemisanintegralpartofWestpower’scontrolsystemformanagingdemandonthenetworkandprovidingtariffswitchingsignalsforretailers.Afailureoftheripplesystemcouldresultinunmanageablepeaksbeingappliedtothesystem,eventuallyresultinginbrown-outsor,underextremecircumstances,black-outs.
Overrecentyears,WestpowerhasdiversifieditsbaseofrippleinjectionplantsandnowhasunitsinstalledatHokitika,Greymouth,DobsonandReefton.Thesearesynchronisedsothatifoneunitshouldfail,coverageisprovidedfromtheremainingunits.Inaddition,eachunitcanbeoperatedlocallyinanemergency.
9.7 General Mitigation Measures
AnumberofgeneralstrategiesandplansareinplacetomitigatetherisksidentifiedtoWestpower’snetworkandoperationalcapability:
1. Regularinspection,serviceandtestingiscarriedouttochecktheoperationalcapabilityofallequipment.Thisincludescheckingofvegetationincloseproximitytooverheadlinesandactivevegetationmanagement.
2. Distributionautomationhasbeenprogressivelyexpandedthroughoutthenetworkoverrecentyearsandthishasallowedadditionalplanttoberegularlymonitoredtogiveindicationsofanearlyfailure.
3. Westpowerhasnetworkdesignandconstructionstandardsaswellasamaterialsapprovalsystemtoensurethatonlyqualitymaterialsareusedandthatahighstandardofworkmanshipismaintained.Thisensuresthattheintegrityofthenetworkisprotected.
4. Regular staff training is implemented in systemoperationand the issueofpermits so thataccess to thenetworkisalwayscarriedoutinasafemanner.
5. Contingencyplansandemergencyproceduresareinplace.Includedwithintheseplansarethefollowing:
• EmergencyResponsePlan(ERP)
• Regionalemergencyloadsheddingplan
• Electricalindustryemergencycontactlist
• Zonesubstations-emergencyoperatingordertemplates. Anumberofengineeringmeasureshavebeentakentomitigateriskincluding:
• Ahealthycomplementofsparesismaintainedsothatmosteventualitiescanbecoveredwithoutresortingtoexternalsupport.
• Aseismicstrengtheningprogrammewillcontinueatzonesubstationsduringthecurrentfinancialyear.
• Afullymobile33/11kVsubstation,calledtheWestpowerMobileSubstation(WMS)hasbeenbuilttoprovidecoverageforsingle-transformerzonesubstations.Sufficientsparepowertransformersareavailabletocoverlong-termfaults.
• Sparecircuitbreakersandcontrollershavebeenpurchasedtocoverexpectedfailurerates.
9.8 West Coast Engineering Lifelines Plan: Survey 2004/2005
Executive Summary
AsanecessarypartofWestpower’songoingcommitmenttotheriskmanagementofitsWestCoastelectricitydistribution network, a selection of critical facilities within their operating area were surveyed to assesstheirvulnerabilitytodamagefromanumberofpredeterminednaturalhazards,e.g.windstormsandsevereearthquakes.
RISKMANAGEMENTPLAN 307
This survey is part of Westpower’s means of compliance with the requirements of the Civil Defence andEmergencyManagement Act 2002. The new act seeks to improveNew Zealand’s resilience to emergenciesthroughpromotingacomprehensiveall-hazardsapproachtomanagingrisk.
CompliancewiththeaboveActisbaseduponfour“R’s”,Reduction,Readiness,ResponseandRecovery.
Thefullreportcontainsadetailedsummaryoffindingstogetherwithcompletedvulnerabilitychartsthatquantifyriskandimportanceinasystematicway.ThesechartsarebaseduponthesystemoriginallyemployedfortheWellingtonandChristchurchengineeringlifelinestudies.Thequantificationlevelissufficienttoenablerelativerisk tobeassessed toassist aprocessofmitigatingareasof risk inaprogressivemanner fromhighest risk/vulnerability/importancetolowest.
TheWestpower network is operated from a Control Centre in the offices at their depot on Tainui Street,Greymouth.TheControlCentreisanessentialpartofWestpower’slifelinereadinessandisdesignedformaximumresilienceintheeventofamajordisaster.Whereverpossible,theControlRoomandassociatedfacilitieshavebeenbroughtup to the requirementsof the latest loadingsandmaterials standards,whichwill significantlyreducefuturevulnerabilityinthisarea.
Thefollowingmainsubstationsandswitchyardsweresurveyedaspartoftheexercise:
• Greymouthsubstation,
• Dobsonsubstation,
• Arnoldpowerstationswitchyard,
• Rapahoesubstation,
• Kumarapowerstationsswitchyard,
• Hokitikasubstation,
• Franzjosefsubstation,
• Foxsubstation.
In addition to the above, a selectionof less important substationswere surveyed to gain an assessment oftheoverall network. These included substations/switchyards atBadger Lane,Harihari,MawheraQuay,Ross,WahapoPowerStation,WaitahaandWilsonLane.
9.9 Transmission Lines
ThemajortransmissionlinesfeedingintotheWestpowerportionoftheWestCoastCivilDefenceEmergencyManagement(CDEM)areaare:
• Inangahua–BlackwaterA 110kVsingle-circuitonpoles
• Dobson–BlackwaterA 110kVsingle-circuitonpoles
• Arahura(Hokitika)–OtiraA 66kVdouble-circuitonpoles
• Arahura(Hokitika)–DobsonA 66kVsingle-circuitonpoles(betweenDobsonandGreymouth)
ThemajorTransmissionLinesthatWestpowerownthemselvesare:
• Greymouth–Kumara 66kVsingle-circuitonpoles 25km
• Kumara–Kawaka 66kVdouble-circuitonpoles 11km
• Hokitika–Harihari 66kVsingle-circuitonpoles 64km
• Two-Mile–Hokitika 66kVsingle-circuitonpoles 8km
308 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Westpower’stransmission/distributionlinescoverseveralroutesoverwidelyvaryingterrainfromcoastalplainstorelativelyunstableandruggedhillcountry.Someredundancyisbuiltintoportionsofthesystemwherebyanoutageonanyoneparticularline,dependingupontimeofday/timeofyear,maynotaffectsupplytootherareasofthenetwork.
Mostpolessupportingtransmissionanddistributionlinesarewellfoundedtopreventcollapseunderhighwinds/iceconditions,andthereforeareonlymoderatelyvulnerabletoearthquake-inducedslopeinstability.
Figure9.10showsthemainlinesfeedingintotheWestpowernetworkfromReeftonandOtira.
KEY Substation
Subtrrans Line 33/66kV
Subtrans Line 110kV
BWR-IGH-A
DOB-BWR-A
AHA-DOB-A
GYM-KUM-A (Leased from Westpower)
KUM-KHA-A (Leased from Westpower)
AHA-OTI-A
ATARAUATARAU
BLACKWATERBLACKWATER
REEFTONREEFTON
DOBSONDOBSONGREYMOUTHGREYMOUTH
( WESTPOWER )( WESTPOWER )
HOKITIKAHOKITIKA( WESTPOWER )( WESTPOWER )
OTIRAOTIRA
ARTHURS PASSARTHURS PASS
KUMARAKUMARA
Figure9.10-MapshowingtheTranspowerNetworksupplyingtheWestpowerDistributionNetwork.
RISKMANAGEMENTPLAN 309
9.10 Communications
Westpowerisabletouseanumberofindependentmeansofcommunicationtocontrolitsnetwork,namely:
• Two-wayradio,
• Telecomlandlinetelephonenetwork,
• Cellularphonenetwork(insomeareas).
Eachsystemisessentiallyindependentofeachotherandthereforethereissignificantredundancyintheeventofdisruption.
The following table (Table 9.11) is a summary of common findings throughoutWestpower’s network, withsuggestedmitigationmeasures.
9.11 Disaster Recovery
Westpower has adopted procedures and policieswhich define processes and assign responsibilities for theconductofemergencyresponseteamsanddepartmentsintheeventofadisaster.
TheseproceduresandpoliciesincludecomprehensiveEMTStandardOperatingProcedure(SOP)andDepartmentalBusinessContinuityPlans(DBCP)aswellastheEmergencyResponsePlan(ERP)andLoadSheddingPlan(LSP)asdiscussedinSection9.7,MitigationMeasures.
9.11.1 EmergencyManagementTeam
TheEMTSOPsprescribestheappropriateprocessesandassignsresponsibilitiesfortheconductoftheEMTintheeventofadisasterofsuchproportionsthatrequirescoordinatedcommandandcontrol.
TheSOPappliestoallelementsofElectroNetwhenperformingdutiesassignedbytheEMT.ThestructureoftheEMTmayaltersubjecttothenatureofthedisaster,resourcesavailableandthetacticalsituation.
TheEMTiscategorisedasfollows;
• Command&control:Includesdefinitionofrolesandresponsibilities,operatingcontrolandoverallcommandoncea‘Disaster’isdeclared.
• Planning:Whenadisasterhasbeendeclared,EMToperationswillbeconductedinthreephases.
Table 9.11 - Summary of Vulnerabilities and Suggested Mitigations
Vulnerability Suggested Mitigation
Transmissionlinespassingoverunstableterrain Adddiversificationwereeverpossible(longtermplanning)
Sometransformersandregulatorsnotrobustlyhelddown ModifyholddownsystemstocurrentEQstandards
Somebusworkvulnerabletoinsulatordamagefromsupportingpostsmovingdifferentially Provideslipjointsinbusworkatappropriatepoints
Someprefabricatedcontrolbuildingsnotrobustlyrestrained UpgradeholddownsystemstocopewithfullEQandwindloadings
Restrainbatteriesfromslidingwithsupportframesandpossiblydamagingcablesandterminals
Providecorrosionproofpackingandtiedownsmallcommuni-cationbatteries
Sometwowayradiosandaccessmanualsunrestrained Providelipstostorageshelvesandattachradiostowallsetc
Someequipmentsupportstandsungroutedwithlongholddownboltsvulnerableinbending Providesuitablenonshrinkgroutunderbaseplates
NewcontrolroomtobeasrobustaspossibleNewcontrolroomwillbeuptolateststandards.EnsureallVDU’s,computersandcommunicationequipmentwellre-
strained
Somecriticalsparesunrestrainedandvulnerable Appropriatelyrestrainallcriticalspares
310 WESTPOWERASSETMANAGEMENTPLAN2012-2022
• Admin and logistics: Defines the location of the EMT base of operations, including all communicationsandmaterialsavailableandalistofpriorityservices.Alsoincludedisalistofpersonnelavailableandtheircontacts.
Please refer to the document “Standard Operating ProcedureWP-01 SOP - EmergencyManagement TeamProcedures”.
9.11.2 BusinessContinuityPlans
TheBCPsaredefinedbyeachdepartmentandenablethere-establishmentofnormalprocessesandproceduresfollowingamajordisruptiveeventwhichresultsineitherthelossofbusinesspremises,resourcesorpeople.
Eachdepartmenthasdevelopedaworkableplanthatcanbeusedtopreventtheinterruptionofcriticalbusinessfunctionsintheeventofamajorinterruption.
Thedepartmentsincludestores,financial,assetmanagement,electriciansandlines.ForanoverviewoftheBCPstructure,refertoFigure9.12.
TheObjectiveoftheBCPsisasfollows:
• Todefineandprioritisethecriticalfunctionsofthedepartment;
• Toanalysetheemergencyriskstothedepartment;
• Todetailtheagreedresponsetoanemergency;
• Toidentifykeycontactsduringanemergency.
Forfurtherinformation,pleaserefertothedocument“BusinessContinuityPlanWP-BCP”
Figure9.12-BCPOrganisationStructure
APPENDIXA:MAINTENANCEACTIVITYDEFINITIONS 311
APPENDIX A: Maintenance Activity Definitions
Inspection, Service and Testing
Routine
This isexpenditureonpatrols, inspections,servicingandtestingofassetsonaroutinebasis.Typically, theseactivitiesareconductedatperiodicintervalsdefinedforeachassetortypeofasset.Thisworkdoesnotinvolveanyrepairsotherthansomeminorcomponentreplacementsinthecourseofservicing.
Special Inspection, Service and Testing
Expenditureonpatrols, inspections,servicingandtestingwhicharebasedonaspecificneed,asopposedtobeingtime-based,aswithperiodicinspectionsandservicing.
Faults
Repairsareundertakenduringfaultconditionstorestoresupply.Thisdoesnotincludetheeventualrepairofafaultedasset,whereitistakenoutofserviceinthecourseofrepairingthefault;onlytheexpenditurerequiredtorestoresupplyisincluded.
Planned Repairs and Refurbishment
Repairs toand refurbishmentofanasset,whichmay involvecomponent replacementbutnot thecompletereplacementoftheasset.This includescorrectiverepairsofdefects identifiedwithinayear,“special”repairs(e.g.basedonan identifiedtypefailureortypeweakness)andplannedrefurbishmentswhichmay involveasignificantproportionofcomponentreplacement.However,toidentifyrefurbishmentsasdistinctfromgeneralrepairswouldrequireidentificationofallspecificrefurbishmentprojectsovertheplanningperiod,andthishasnotprovedfeasibleforthisplan.
Planned Replacement
Replacementofanexistingassetwithamodernequivalentassetprovidingsimilarcapacity,orotheraspectofserviceprovided.Notethattheassetneednotbeidenticalincapacityetc.butshouldbemateriallysimilar.
Maintenance Contingency
Anexplicitplanningcontingency,whereitisnotfeasibletoidentifyallminorwork,orwhereitisexpectedthatworkwillarisebutitsclassificationcannotbeeasilypredicted.Allcontingenciesarespecificallyidentifiedandnoimplicitcontingenciesareincludedinthedetailedexpenditureprojectionsforotheractivityclassifications.
This contingency is converted into one of the above activity classifications once committed. “MaintenanceContingency”isnotarealactivityforreportingpurposes.
EnhancementandDevelopmentActivityDefinitions
Enhancement
Thisisthereplacementofanexistingassetwithamodernequivalentasset,whichmateriallyimprovesontheoriginalasset,ormodificationstoanexistingassetthathavethiseffect.Specifically,thiswillincludeimprovementstotheexistingassetconfiguration,whichareundertakenwiththepurposeof:
• Furtherimprovingtheinherentsafetyofthesystem(e.g.installingsmoke/heatdetectorsandentryalarmsinsubstations);
• Improvingthelevelofcustomerservice(e.g.increasingcapacitybyreplacingatransformerwithalargerunit,oraddinganextracircuittoittoincreasesecurity);
312 WESTPOWERASSETMANAGEMENTPLAN2012-2022
• Improvingeconomicefficiencyorinvestingtoimprovetheassetbyreducingoperatingormaintenancecosts(e.g.fittingvibrationdamperstospecificlinestoreducetherateofcomponentdeterioration);
• Improvingenvironmentalriskmanagement(e.g.fittingoilcontainmentfacilitiesatsubstations);
• Improvingthecorporateprofile(e.g.landscapingstationgrounds,althoughthisisalsofullyjustifiableonthebasisofreducedgroundsmaintenance).
Notethateachaspectofimprovementisrelatedtoaspecificassetmanagementperformancedriver.
Development
Thisisworkwhichinvolvestheinstallationofnewassetsinsitesorconfigurationswherenonepreviouslyexisted.Thismayalsoincludesubstantialupgradework(e.g.rebuildingasubstationatahighervoltage)inwhichtheoriginalconfigurationissignificantlyalteredorextended.
Development Contingency
An explicit planning contingencywhere it is not feasible to identify allminorwork, orwhere it is expectedthatworkwillarisebutitsclassificationcannotbeeasilypredicted.Noimplicitcontingenciesareincludedinthedetailedenhancementanddevelopmentexpenditureprojections.Forthesamereasonsasthosediscussedunder“MaintenanceContingency”,thisactivityisnotincludedinfinancialreports.
OtherActivityDefinitions
Operating
Any disconnection of a customer’s services for any reason except non-payment of electricity accounts. Thisincludesactivitiessuchashousepainting,transportationofhighloadsandlow-voltageswitching.Italsoincludesoperationofthehigh-voltagenetworkwherethisisnotdirectlyassociatedwithmaintenanceorenhancementwork.
Trees
Thisactivitycoversalltree-cuttingandtrimmingtomaintainsafeworkingclearancesfrompowerlinesandanycostsincurredduringnegotiationswithcustomersregardingtree-trimming.
AssetTypeDefinitions
High-voltage Lines
Includesallpowerdistributionandsubtransmissionlineswitharatedvoltageof11kVorhigher,togetherwithassociatedeasements.Withintheplan,lineworkisfurtherdesegregatedintomajorlinecomponents:
• Poles,
• Conductorsandaccessories,
• Insulatorsandhardware.
Low-voltage Lines
Includesalllowvoltagelineswitharatedvoltageof400Vorlower,togetherwithassociatedeasements,uptothecustomer’sservicefuse.Asforhighvoltagelines,lineworkisfurtherdesegregatedintomajorlinecomponents:
• Poles,
• Conductorsandaccessories,
• Insulatorsandhardware.
APPENDIXA:MAINTENANCEACTIVITYDEFINITIONS 313
Service Lines
Includesallservicelinesonroadreservefromthecustomer’sservicefusetothepointatwhichitcrossesthecustomer’sboundary.Theseinclude:
• Fusearms,
• Servicefuses,
• Servicelinesonroadreserve.
Zone Substations
These include substation sites and the power transformerswithin themwith a secondary voltage of 11 kVorhigher. Individual itemsofequipmentsuchasdisconnectors,circuitbreakersandbus-workarecovered inotherasset typedefinitions,whicharegeneric for thewholenetwork, i.e.nodistinction ismadebetweenadisconnectorinasubstationandoneonadistributionline.
• Powertransformers,
• Otherstationequipment,
• Regulatorsites.
Distribution Substations
Alldistributionsubstationequipmentincluding:
• Distributiontransformers,
• DDOfuses,
• Lightningarrestors,
• Earthingsystems.
Switchgear
Allhigh-voltageswitchgearandotheritemsofequipment,bothonlinesandwithinsubstations,including:
• Circuitbreakers,
• Structuresandbus-work,
• Instrumenttransformers,
• Capacitors,
• Protectionsystems,
• Metering,
• Buildings,grounds,fencesandotherservices.
SCADA, Communications and Protection
Includes SCADAMaster Station and RTUs at individual sites. Communication equipment comprises specificcommunicationssiteswithassociatedequipment,andradiocommunicationsequipmentwhichmaybeinstalledinvehicles,substationsorotherbases.Protectionassetsincludedinthisdefinitioncoverprotectionrelaysandequipment,whichisgenerallyinstalledatasubstationsite.
Buildings and Structures
Includesallbuildingassetsaswellassomeoftheolder“bunker”distributionsubstations.
314 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Ripple Control
Ripple Injection Plants installed in zone substations. This definition also includes the load control softwareincludedintheSCADAmasterstation.
APPENDIXB&C 315
APPENDIX B: Commerce Commission Cross Reference Table
AsourAMPhasbeenstructuredtosuitourpurposesitdoesnotstrictlyfollowtheorderaslaidoutinschedule2oftheElectricityinformationdisclosurerequirements.Toassistinfindingspecificinformationthiscrossreferencetablewillpointthereadertocorrectpage(s).
Framework Ref. Com.Com Schedule 2 Ref Com.Com Handbook Ref Westpower AMP Section Ref.
B.2 Item1 4.5.1 ThroughoutSection
B2A 4.4.3,4.5.1 1
B2B 4.4.4,4.5.1* 1
B3 AMPSummary 2
B3.1 4.5.2a 2.1.1,2.1.2
B3.1A Item2a 4.5.2a 2.1.1,2.1.2
B3.1B 4.5.2a 2.1.1,2.1.2
B3.1C 4.5.2a 2.1.2
B3.2 Item2b 4.5.2b 2.1.2
B3.2A 4.5.2b(i) 2.1.7.4,2.1.7.5
B3.2B 4.5.2b(ii) 2.1.3
B3.2C 4.5.2b(iii) 2.1.1,2.1.2,2.1.2&2.1.3
B3.2D 4.5.2b 2.1.3
B3.3 Item2c 4.5.2c 2.1.1,2.1.2
B3.3A 4.5.2c 2.1.1,2.1.2
B3.3B 4.5.2c 2.1.1,2.1.2
B3.4 Item2d 4.5.2d 2.1.7
B3.4A 4.5.2d 2.1.7
B3.4B 4.5.2d(i) 2.1.7
B3.4C 4.5.2d(ii) 2.1.7
B3.4D 4.5.2d(iii) 2.1.7
B3.4E 4.5.2d(iv) 2.1.7
B3.5 Item2e 4.5.2e 2.1.6
B3.5A 4.5.2e(i) 2.1.6.1
B3.5B 4.5.2e(ii) 2.1.6.8
B3.5C 4.5.2e(iii) 2.1.6.9,2.1.6.10
B3.6
B3.6A Item2f 4.5.2f 2.1
B3.6B 4.5.2f 2.8
B3.6C 4.5.2f 2.8
B3.6D 4.5.2f 2.8
B4 3
B4.1 Item3a 4.5.3a 3
B4.1A 4.5.3a(i) 3
B4.1B 4.5.3a(ii) 3.14
B4.1C 4.5.3a(iii) 3.14
B4.1D 4.5.3a(iv) 5.4
B4.2 Item3b 4.5.3b 3.2to3.14
B4.2A 4.5.3b(i) 3.2&3.14
316 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Framework Ref. Com.Com Schedule 2 Ref Com.Com Handbook Ref Westpower AMP Section Ref.
B4.2B 4.5.3b(i) 3.2
B4.2C 4.5.3b(ii) 3.3,3.7
B4.2D 4.5.3b(ii) 5.3.1,AppendixC
B4.2E 4.5.3b(iii) 3.4
B4.2F 4.5.3b(iv) 3.8
B4.2G 4.5.3b(v) 3.5&3.6
B4.2H 4.5.3b(vi) 3.9to3.11
B4.3 Item3c 4.5.3c 3.0(throughoutSection)
B4.3A 4.5.3c 3.0(throughoutSection)
B4.3B 3
B4.4 Item3d
B4.4A 4.5.3d 2.3&3.0(throughoutSection)
B5
B5.1 Item4a
B5.1A 4.5.4a 4.2
B5.2 Item4b
B5.2A 4.5.4b 4.3
B5.3 Item4c
B5.3A 4.5.4c 4.4
B6 4.5.5 6
B6.1 Item5a
B6.1A 4.5.5a 5.2&5.3
B6.1B 4.5.5a 5.2&5.3
B6.2 Item5b
B6.2A 4.5.5b 5.2
B6.3 Item5c
B6.3A 4.5.5c 5.4
B6.3B 4.5.5c 5.4
B6.3C 4.5.5c 5.4.2
B6.3D 4.5.5c 5.4.2
B6.3E 4.5.5c 5.4.5
B6.3F 4.5.5c 5.4.4
B6.4 Item5d
B6.4A 4.5.5d 5.7
B6.4B 4.5.5d 5.8.2
B6.5 Item5e 4.5.5e 5.4&5.5
B6.5A 4.5.5e Section5
B6.5B 4.5.5e Section5
B6.6 Item5f
B6.6A 4.5.5f 5.5
B6.6B 4.5.5g(i) 5.5
B6.6C 4.5.5g(ii) 5.5
B6.6D Item5g 4.5.5g(iii) 5.18
B6.6E 4.5.5g(note1) 5.5
B6.6F 4.5.5g(note1) 5.8-5.18
B6.6G 4.5.5g(note2) 5.8-5.18andSection7
APPENDIXB&C 317
Framework Ref. Com.Com Schedule 2 Ref Com.Com Handbook Ref Westpower AMP Section Ref.
B7
B7.1 Item6a
B7.1A 4.5.6a 6.1&6.2
B7.2 Item6b
B7.2A 4.5.6b 5.9-5.18
B7.2B 4.5.6b 5.9-5.18
B7.2C 4.5.6b 5.9-5.18
B7.2D 4.5.6b 5.9-5.18andSummarySection7
B7.3 Item6c 4.5.6c 5.9-5.18&6
B7.3A 4.5.6c 5.9-5.18,5.13.3
B7.3B Item6d 4.5.6d 5.9-5.18
B7.3C 4.5.6d(i) 5.9-5.18
B7.3D 4.5.6d(ii) 5.9-5.18
B7.3E 4.5.6d(iii) 5.9-5.18
B7.3F Item6e 4.5.6e 5.15-5.18&summaryinSection7
B8
B8A Item7 4.5.7 9
B8B Item7a 4.5.7a 9
B8C 9.5,9.6&9.11
B8D Item7b 4.5.7b 9.0(throughoutSection)
B8E 4.5.7b 9.7-9.11
B9 4.5.8 7
B9.1 Item8a
B9.1A 4.5.8a 7.3
B9.1B 4.5.8a 7.3
B9.1C 4.5.8a 7.3
B9.1D 4.5.8a 7.3
B9.2 Item8b
B9.2A 4.5.8b 4.2&4.3
B9.2B 4.5.8b 4.2&4.3
B9.3 Item8c 4.5.8c 8.13
B9.3A 4.5.8c 8.0(throughoutSection)
B9.3B 4.5.8c 8.0(throughoutSection)
B10
B10A 7.1
B10B 7.1
B10C 7.2
318 WESTPOWERASSETMANAGEMENTPLAN2012-2022
APPENDIX C: Network Reliability by Zone Substation and Feeder
ThetablebelowshowsthereliabilitylevelsforeachofWestpower’s19ZoneSubstations.
Substation Load (MW)
Sub-Trans Security
# HV Feeds Feeders
Restora-tion Time
(Hrs)Backup Comments
Reefton33kV 7.088 n-1 2 CB3012 <0.5 CB3072at
Sub
TherearetwotransformersfedfromInan-gahuaandAtarauthroughtwoseparate110kVcircuits.Thereisnoproblemwith
thebackup.
CB3072 <0.5 CB3012atSub
Reefton11kV 2.828 n-1 2 CB4 <0.5 CB5atSub
CB5 <0.5 CB4atSub
BWRCB1toReefton
town
Globe11kV 1.616 n 1 CB2 <1
AcceptedbyCustomer.Backupisavailablejustfor11kV.
CB3 <1
CB4 <1
MobileSubforallfeed-
ers
Globe6.6kV 4.000 n 1 CB39 NoBackup The6.6kVfeederonlysuppliestheGlobeBallMillandthereisnobackupwhichis
acceptedbyCustomer.
Ngahere 3.107 n 1 CB1 <1 DOBCB1 ThereisabackupfeedfromReeftonfora33kVfeederfault.BackupisavailablefortheBlackballfeedfromDobsonorArnold.TheCB3feedercanbefedfromBlack-water.Repairtimesareshort.Abackuptransformerisavailable.Inasubstation
fault,alternatefeedsarenotlargeenoughtosupplythemajorconnectedload,the
NgahereGoldDredge.
ALDCB3
CB3 <1 BWRCB2
MobileSubforbothfeeders
Rapahoe 2.177 n 1 CB1 <1 CB3atSubThereisnobackupfora33kVfeederfault.Backupisavailableviaabypassswitchfor33kVand11kVcircuitbreakerfaults.Dob-sonisabletosupplythedomestic11kV
load,andminimalindustrialload,e.g.minepumps.Abackuptransformerisavailable.
CB3 <1 DOBCB1
<1MobileSubforbothfeeders
Dobson33kV 13.793 n-1 2 CB1322 <0.5 CB1362at
SubThisisthemajor33kVsupplypointfor
theGreyValleyandissupplieddirectfromtheTransPowernetwork.Theradial33kVfeederscanbebypassedatthesubstationforcircuitbreakerfaultsbuttherearenoalternatefeedforthefeedersthemselves.
Repairtimesareshort.CB1382isnotprovidedwithabypass,asArnoldPower
Stationprovidesanalternatesourceonthe11kVnetwork.ThemobilesubstationcanbeusedasabackupforCB1342andT1.
CB1342 <0.5 MobileSub
CB1362 <0.5 CB1322atSub
CB1382 <0.5 33kVTietoArnold
CB3072Reefton
APPENDIXB&C 319
Substation Load (MW)
Sub-Trans Security
# HV Feeds Feeders
Restora-tion Time
(Hrs)Backup Comments
Dobson11kV 1.875 n 1 CB1 <0.5 RAPCB3 Thissubstationisfeddirectlyfromthe
TranspowerDobson33kVbus,andsoisnotsubjecttoWestpowerSubtransmissionLineFaults.The33/11kVtransformeralsoactsasaspare,whichcanbetransportedtoNgahere,Rapahoe,Hokitika,WahapoorFranzJosefifrequired.Several11kVtiesexistforthefeedersoutofthissubstation
andrepairtimesareshort.
ALDCB3
NGHCB1
CB3 <0.5 GYMCB13
MobileSubforbothfeeders
Blackwater 1.472 n 1 CB1 <1 RFNCB5
The33kVfeederbackupisavailablefromReeftonorDobson.
CB2 <1 NGHCB3
MobileSubforbothfeeders
Arnold 3.357 n 1 CB3 <0.5 DOBCB1 Thebackupfora33kVfeederfaultisthelocalgeneratingstationtiedinthroughthe11kVnetwork.BackupisavailablefortheStillwaterfeedfromDobson,andforthe
MoanafeedfromKumara.PartialbackfeedtoDobsonorTuriwhateispossible.Repairtimesareshort.Abackuptransformeris
available.
CB4 <0.5 DIL4
<0.5 MobileSub
Greymouth 13.444 n-1 2 CB7 <0.5 CB12&CB9
ThisisWestpower’slargestPointofSupplythatfeedstheGreymouthCentralBusinessDistrict(CBD).Thereareseveralradial11kVfeedersthatareintermeshedatseveralpointsprovidingasignificantamountof
diversity.TheCobdenFeederhasnobackuponceitcrossestheGreyRiver,howeverthereticulationisalloverheadwithlowrepairtimes.The11kVcablenetworkintheCBDishighlyintermeshedwitha“double-ring”construction.Allsubstationshavetwo,and
manythree,11kVcablefeeds.
CB13 <0.5 CB6
DOBCB3
CB6 <0.5 CB13
CB11
KUMCB1
CB12 <0.5 CB9
CB6
CB11 <0.5 CB6
CB12
CB9 <0.5 CB7
CB12
Kumara 2.361 n 1 CB1 <1 GYMCB6 ThissupplyisfeddirectlyfromtheKumara11kVbus,whichisinturnsuppliedbyaveryreliableTranspower66kVbus.
Both11kVfeederscanbebackfedfromGreymouth,ArnoldorHokitikaSubstations.AsparetransformerisavailablefromGrey-
mouthSubstation.
CB2 <1 ALDCB4
HKKCB10
320 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Substation Load (MW)
Sub-Trans Security
# HV Feeds Feeders
Restora-tion Time
(Hrs)Backup Comments
Hokitika 18.452 n-1 2 CB10 <0.5 CB4
ThissubstationfeedsHokitikaandallofSouthWestlanddowntoParinga.Inaddition,itsuppliesthreefeederstothe
WestlandDairy.
CB4 <0.5 CB10
CB12
CB12 <0.5 CB4
CB5 <0.5 CB9
CB11
CB9 <0.5 CB5
CB11
CB11 <0.5 CB5
CB9
Ross 0.447 n 1 CB1 <0.5 CB3atSub CB1isadedicatedfeederfortheBirchfieldMineralsminesite.DomesticloadonCB3canbefedfromCB10.Bothfeedershavea
shortrepairtime.
CB3 <0.5 HKK10
Waitaha 0.261 n 1 CB1 <5 NoBackup The33kVsubstationfeedcanbefromHokitikaorWahapoiftheWahapoPowerStationisavailable.Thisisaverysmallandisolatedsubstationandnobackupispossibleforthe11kVfeeders.Aspare
transformerisavailable.
MobileSub
Harihari 1.044 n 1 CB1 <0.5 CB3atSub The33kVsubstationfeedcanbefromHokitikaorWahapoiftheWahapoPowerStationisavailable.Thisisasmallandiso-latedsubstationandnobackupispossibleforthe11kVfeedersapartfromabypassforthe11kVcircuitbreakers.Asparetrans-
formerisavailable.
CB3 <0.5 CB1atSub
MobileSub
Whataroa 0.772 n 1 CB1 <5 NoBackup The33kVsubstationfeedcanbefromHok-itikaorWahapoiftheWahapoPowerSta-tionisavailable.Thisisasmallandisolatedsubstationandnobackupispossibleforthe
11kV.Asparetransformerisavailable.
MobileSub
Wahapo 3.091 n 1 CB1 <5 NoBackup The11kVsubstationbuscanbefedfromHokitikaorWahapoiftheWahapoPowerStationisavailable.Thisisanisolated
substationandnobackupispossibleforthe11kV.AsparetransformerisavailablefromDobson.ThissubstationalsoconnectsWahapoPowerStationintoWestpowers
sub-transmissionnetwork.
MobileSub
FranzJosef 1.718 n 1 CB1 <1.5 CB3atSub Thissubstation,fedfromHokitikafeedstheFranzJosefarea.TherearetwosectionsofAerialBundledCableinthisfeeder,whichhavesignificantrepairtimes.Theaerialroutesandterraincanbeverydif-ficult.Thereisnofeasiblesubtransmissionbackup.Themobilesubstationcanbackup
both11kVfeeders.
CB3 <1.5 CB1atSub
MobileSub
FoxGlacier 0.750 n 1 CB1 <5 NoBackup Thissubstationwasconstructedin2003tosupplytheFoxGlacierarea,southto
Paringa.MobileSub
APPENDIXB&C 321
Substation Load (MW)
Sub-Trans Security
# HV Feeds Feeders
Restora-tion Time
(Hrs)Backup Comments
LogburnRd33kV 0.761 n 1 CB3602 NoBackup
Thereisnobackupavailable.
LogburnRd11kV 0.343 n 1 CB1 <1 NGHCB1
BackupforCB1isavailablefromNgahereCB1viaDD22.CB2andCB3canalsobe
partiallybackedupfromNGHCB1.CB2 NoBackup
CB3 NoBackup
Pike11kV 0.761 n 1 CB1 NoBackup
AcceptedbyCustomer.Inemergency,themobilesubcouldbeinstalledtosupply
thesefeeders.
CB2 NoBackup
CB3 NoBackup
CB4 NoBackup
CB5 NoBackup
CB6 NoBackup
CB7 NoBackup
322 WESTPOWERASSETMANAGEMENTPLAN2012-2022
APPENDIX D: Expenditure Forecast and ReconciliationAc
tual
for
mos
t rec
ent
Fina
ncia
l Ye
ar ($
000)
Prev
ious
fo
reca
st fo
r Cu
rren
t Fi-
nanc
ial Y
ear
($00
0)
Fore
cast
Yea
r
For y
ear e
nded
2011
2012
2013
2014
2015
2016
2017
2018
2019
2020
2021
2022
CapitalExpen
diture:C
ustomer
Conn
ectio
n27
721
550
015
916
717
618
719
720
822
123
424
7
CapitalExpen
diture:System
Grow
th19
364
750
953
957
160
764
368
172
276
681
286
0
CapitalExpen
diture:A
ssetRe-
placem
enta
ndRen
ewal
2,48
23,19
724
1412
3561
188
172
784
266
914
3313
7410
29
CapitalExpen
diture:R
eliability,
Safetyand
Enviro
nmen
t97
91,45
325
3952
645
550
042
232
969
338
636
235
6
CapitalExpen
diture:A
ssetReloca-
tions
25-
050
00
00
00
00
Subtotal-Ca
pitalExpen
ditureon
AssetM
anagem
ent
3,95
65,51
25,96
22,50
91,80
42,16
41,97
92,04
92,29
22,80
62,78
22,49
2
Ope
ratio
nalExpen
diture:R
outin
ean
dPreven
tativ
eMainten
ance
3,25
83,73
736
0237
7138
2338
4439
6841
4042
9444
8947
0649
09
Ope
ratio
nalExpen
diture:R
efur-
bishmen
tand
Ren
ewalM
ainte-
nance
700
766
578
590
645
646
682
337
354
373
393
414
Ope
ratio
nalExpen
diture:Fau
ltan
dEm
ergencyMainten
ance
865
904
843
889
942
993
1051
1107
1170
1235
1307
1379
Subtotal-Ope
ratio
nalExpen
di-
tureonAssetM
anagem
ent
4,82
35,40
75,02
35,25
05,41
05,48
35,70
15,58
45,81
86,09
76,40
66,70
2
TotalD
irectExpen
ditureonDistri-
butio
nNetwork
8,77
910
,919
10,985
7,75
97,21
47,64
77,68
07,63
38,11
08,90
39,18
89,19
4
Overhea
dtoUnd
ergrou
ndCon
-versionExpe
nditu
re21
--
--
--
--
--
-
APPENDIXD:EXPENDITUREFORECASTANDRECONCILIATION 323
APPENDIX E: Glossary of TermsAAAC:AllAluminiumAlloyConductor-Usedasbareoverheadconductorforprimaryandsecondarydistribution.Designedutilizingahighstrengthaluminumalloytoachieveahighstrength-to-weightratio;affordsbettersagcharacteristics.AluminumalloygivesAAAChigherresistancetocorrosionthanACSR.
AAC:AllAluminiumConductor-Compactstrandconductorforuseinbareoverheadapplicationsorforusewithweather-resistantcoveringsorinsulationsisalsoavailable.
ACSR:AluminiumConductorSteelReinforced-Usedasbareoverheadtransmissioncableandasprimaryandsecondarydistributioncable.ACSRoffersoptimalstrengthforlinedesign.Variablesteelcorestrandingenablesdesiredstrengthtobeachievedwithoutsacrificingampacity.
Ampere(A):unitofelectricalcurrentflow,orrateofflowofelectrons.
AMP:AssetManagementPlan
CAIDI:aninternationalindexwhichmeasurestheaveragedurationofaninterruptiontosupplyforconsumersthathaveexperiencedaninterruption.Usuallycalculatedonaperannumbasis.
CAIDI=Sumof(numberofinterruptedconsumersxinterruptionduration)
Sumof(numberofinterruptedconsumers)
CapacityUtilisation:a ratiowhichmeasures theutilisationof transformers in thenetwork.Calculatedas themaximumdemandexperiencedonanelectricitynetworkinayeardividedbythetransformercapacityon
thatnetwork.
CircuitBreaker(CB):adevicewhichdetectsexcessivepowerdemandsinacircuitandcutsoffpowerwhentheyoccur.Nearlyalloftheseexcessivedemandsarecausedbyafaultofsomedescriptiononthenetwork.Intheurbannetwork,wheremostoftheseCBsare,theydonotattemptarecloseafterafaultastheLCBsdoontheruraloverheadnetwork.
ContinuousRating:theconstantloadwhichadevicecancarryatratedprimaryvoltageandfrequencywithoutdamagingand/oradverselyeffectingitcharacteristics.
Conductor:isthe‘wire’thatcarriestheelectricityandincludesoverheadlineswhichcanbecovered(insulated)orbare(notinsulated),andundergroundcableswhichareinsulated.
Actual for most recent
Financial Year ($000)
Previous forecast for Recent Fi-
nancial Year ($000)
% Variance
CapitalExpenditure:CustomerConnection 277 204 35.8%
CapitalExpenditure:SystemGrowth 193 535 -63.9%
CapitalExpenditure:AssetReplacementandRenewal 2,482 3,139 -20.9%
CapitalExpenditure:Reliability,SafetyandEnvironment 979 1,778 -44.9%
CapitalExpenditure:AssetRelocations 25 - Notdefined
Subtotal - Capital Expenditure on Asset Management 3,956 5,656 -30.1%
OperationalExpenditure:RoutineandPreventativeMaintenance 3,258 3,313 -1.7%
OperationalExpenditure:RefurbishmentandRenewalMaintenance 700 1,061 -34.0%
OperationalExpenditure:FaultandEmergencyMaintenance 865 875 -1.1%
Subtotal - Operational Expenditure on Asset Management 4,823 5,249 -8.1%
TotalDirectExpenditureonDistributionNetwork 8,779 10,905 -19.5%
324 WESTPOWERASSETMANAGEMENTPLAN2012-2022
Current:themovementofelectricitythroughaconductor,measuredinamperes(A).
DCF:DiscountedCashFlow-Methodforevaluatingprofitabilityofaninvestmentdecision.
DDO:DominionDropoutfuseusedonoverheadlinestoprovideapointofisolationandprotectionfordistributionsubstationsandfeeders.
DGA:DissolvedGasAnalysis-Testcarriedoutontransformeroilqualitytomeasurethelevelsofdissolvedgassesintheoil,thisgivesanindicationoftransformercondition.
DistributionSubstation:iseitherabuilding,akiosk,anoutdoorsubstationorpolesubstationtakingitssupplyat11kVanddistributingat400V.
DistrictSubstation:amajorbuildingsubstationand/orswitchyardwithassociatedhighvoltagestructurewhereeither;voltageistransformedfrom66or33kVto11kV,twoormoreincoming11kVfeedersfromagridexitpointareredistributedorarippleinjectionplantisinstalled.Sometimesknownasazonesubstation.
ELB:ElectricityLinesBusinessasdefinedbytheCommercecommissionandexcludingTranspower.
EPDM: Ethylene Propylene Diene Monomer rubber is used on dead end insulators. It exhibits satisfactorycompatibility with fireproof hydraulic fluids, ketones, hot and cold water, and alkalis, and unsatisfactorycompatibilitywithmostoils, gasoline, kerosene, aromaticandaliphatichydrocarbons,halogenated solvents,andconcentratedacids.
Fault Current:thecurrentfromtheconnectedpowersystemthatflowsinashortcircuitcausedbyafault.
Feeder:aphysicalgroupingofconductorsthatoriginatefromadistrictsubstationcircuitbreaker.
Flashover:adisruptivedischargearoundoroverthesurfaceofaninsulator.
Frequency:onACcircuits,thedesignatednumberoftimespersecondthatpolarityalternatesfrompositivetonegativeandbackagain,expressedinHertz(Hz)
Fuse: adevice thatwillheatup,meltandelectricallyopen thecircuitafteraperiodofprolongedabnormalcurrentflow.
GIS:GraphicalInformationSystemusedbyWestpowertoshowthephysicallocationofassetsintheirnetworkandisusedasatoolwiththeAssetWorksManagementSystem.
Gradient, Voltage:thevoltagedrop,orelectricaldifference,betweentwogivenpoints.
Grid Exit Point (GXP):apointwhereOrion’snetworkisconnectedtoTranspower’stransmissionnetwork.
Harmonics (Wave Form Distortion):changesanACvoltagewaveformfromsinusoidaltocomplexandcanbecaused by network equipment and equipment owned by consumers including electricmotors or computerequipment.
High Voltage:voltageexceeding1,000volts(1kV),inOrion’scasegenerally11kV,33kVor66kV.
Insulator:supportsliveconductors,ismadefrommaterialwhichdoesnotallowelectricitytoflowthroughit.
kVA: thekVA,orKilovolt-ampere,output ratingdesignates theoutputwhicha transformercandeliver foraspecifiedtimeatratedsecondaryvoltageandratedfrequency.
Line Circuit Breaker (LCB):acircuitbreakermountedonanoverhead linepolewhichquicklycutsoffpowerafterafaultsothatnopermanentdamageiscausedtoanyequipment.Itswitchespowerbackonafterafewsecondsandifthecauseofthefaulthasgone(eg.abranchhasblownoffaline)thenthepowerwillstayon.Iftheoffendingitemisstilltherethenpowerwillbecutagain.Thiscanhappenuptothreetimesbeforepowerwillstayoffuntilthefaultrepaired.SometimesaLCBisknownasarecloser.
Low Voltage:voltagenotexceeding1,000volts,generally230or400volts.
APPENDIXD:EXPENDITUREFORECASTANDRECONCILIATION 325
Maximum Demand:themaximumdemandforelectricity,atanyonetime,duringthecourseoftheyear.
MOCHED:Majoroutagecausinghugeeconomicdamage.
Network Deliveries:totalenergysuppliedtoournetworkthroughTranspower’sgridexitpoints,usually
measuredasenergysuppliedoverthecourseofayear.
Outage:aninterruptiontothesupplyofelectricity.
Proven Voltage Complaint:acomplaintfromaconsumerconcerningadisturbancetothevoltageoftheirsupplywhichhasproventobecausedbythenetworkcompany.
PILCSWA:FormofCableconstruction-PaperInsulatedLeadCoveredSteelWireArmouredcable.
ROI:ReturnonInvestment-financialratioforexpectedreturnforagiveninvestmentusuallyexpressedasapercentageperyear.
Ripple Control System:asystemusedtocontroltheelectricalloadonthenetworkby,forexample,switchingdomesticwaterheaters,orbysignalinglargeusersofahighpriceperiod.Alsousedtocontrolstreetlights.
RTU (Remote Terminal Unit):AnRTU isadevice installedata remote location thatcollectsdata,codes thedataintoaformatthatistransmittableandtransmitsthedatabacktoacentralstation,ormaster.ARTUalsocollectsinformationfromthemasterdeviceandimplementsprocessesthataredirectedbythemaster.RTUsareequippedwithinputchannelsforsensingormetering,outputchannelsforcontrol,indicationoralarmsandacommunicationsport.
SAIDI:SystemAverageInterruptionDurationIndex;aninternationalindexwhichmeasurestheaveragedurationofinterruptionstosupplythataconsumerexperiencesinagivenperiod.
SAIDI=Sumof(numberofinterruptedconsumersxinterruptionduration)
Totalnumberofconnectedconsumers
SAIFI:SystemAverageInterruptionFrequencyIndex;aninternationalindexwhichmeasurestheaveragenumberofinterruptionsthataconsumerexperiencesinagivenperiod.
SAIFI=Sumof(numberofinterruptedconsumers)= SAIDI
Totalnumberofconnectedconsumers SAIFI
SCADA:SystemControlandDataAcquisition.
Transformer:adevicethatchangesvoltageuptoahighervoltageordowntoalowervoltage.
Transpower:thestateownedenterprisethatoperatesNewZealand’stransmissionnetwork.Transpowerdeliverselectricityfromgeneratorstovariousnetworksaroundthecountry.
Voltage:electricpressure;theforcewhichcausescurrenttoflowthroughanelectricalconductor.
VoltageRegulator:anelectricaldevicethatkeepsvoltagewhichissuppliedtoconsumersataconstant level,regardlessofloadfluctuations.
XLPE:CrosslinkedPolyethylene-typeofcableinsulationXLPEcontainscross-linkbondswhichareintroducedintothepolymerstructure,changingthethermoplasticintoanelastomer.XLPE-insulatedcableshavearatedmaximumconductortemperatureof90°Candanemergencyratingofupto140°C,dependingonthestandardusedtorateXLPE-insulatedcables.CablesinsulatedwithXLPEalsohaveaconductorshort-circuitratingof250°C.XLPEhasexcellentdielectricpropertiesmakingitusefulforalargerangeofvoltageapplicationsfrom600Vto500kV.
ZoneSubstation:ZoneSubstationsareusedtotransformpowerfromtransmissionandsub-transmissionvoltagesof33kVandhigherdowntoWestpower’sstandarddistributionvoltageof11kV.