architect's guide for detailing & specifying access floor air plenums

18
1 Architect’s Guide for Detailing & Specifying Access Floor Air Plenums Access Floors to the Power of Access Floors

Upload: dangmien

Post on 30-Jan-2017

222 views

Category:

Documents


2 download

TRANSCRIPT

Page 1: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

1

Architect’s Guide for Detailing &Specifying Access Floor Air Plenums

Access Floorsto the Power of

Access F loors

Page 2: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

2

“”

Access floor air plenumintegrity begins with proper

design and specification.

“”

Access floor air plenumintegrity begins with proper

design and specification.

Page 3: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

Architect’s Guide for Detailing & Specifying Access Floor Air Plenums Plenum Integrity is one of the most important aspects of designing, constructing and maintaining an underfloor air delivery (UFAD) system. It is

vital that the entire design and construction team does their part to ensure the underfloor plenum is sealed properly. This process starts with the

architect. As the architect designing a building with a UFAD system you have the responsibility of providing specifications and details for con-

structing a plenum with proper sealing and integrity. Every contractor working in the plenum space needs to be aware of their responsibilities

and should be equipped with the information they need to successfully complete their work while maintaining plenum integrity.

Tate Access Floors is providing the following plenum seal integrity guidelines for consideration. The recommendations contained within this

guideline are based on lessons learned through working on a wide range of UFAD projects. To that end, Tate believes a holistic approach to

design and construction should be used and recommends regular consultation be held with key individuals on the construction team through-

out the entire design process.

There are six primary recommendations. An overview and explanation of each recommendations is provided below followed by proposed speci-

fication language and construction details.

Design: Specifications and performance requirements that create awareness and responsibility for plenum

sealing integrity should be included in all divisions of the CSI specifications. Drawings detailing the

construction requirements for the underfloor air delivery plenum should also be provided.

Pre-Bid Meeting: The requirement for pre-bid meetings to inform all subcontractors of the plenum sealing and

mock-up construction requirements should be specified.

Pre-Construction: Pre-construction meetings should also be specified to reaffirm the plenum sealing requirements to

each sub-contractor division.

Mock-up: Specify the construction and testing of a mock-up that includes all actual building conditions relative

to the UFAD system.

Quality Inspections: Specify the use of a commissioning agent to audit the construction process, perform air leakage

testing on the mock-up and final installation, and provide detailed reporting to the GC that ensures

the construction of the UFAD system follows the specified requirements.

Downloadable Specifications & DetailsVisit Tate’s website to download the sealing details and recommended specification language in this guide. The details are available in AutoCAD

dwg and PDF file formats. In addition a Microsoft word version of the specifications in this guide can be found in the architectural details under

the Product & Spec section of the website or by entering the following address into a web browser:

www.tateaccessfloors.com/architectural_details.html

3

Page 4: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CSI Specifications for ConsiderationThe following is Tate’s recommended access floor air plenum sealing specification language to insert into the CSI specifications for subcontrac-

tors. All of the specifications can be downloaded on-line at www.tateaccessfloors.com/architectural_details.html

DIVISION 01 - GENERAL REQUIREMENT SPECIFICATIONS

Pre-Bid & Pre-Construction Meetings: All sub-contractors intending to bid on or awarded work on the project are required to attend pre-bid

and pre-construction meetings respectively. The purpose of these meetings is to review all air plenum specifications and details including but not

limited to pre-construction mock-ups and plenum sealing requirements.

Quality Control: All walls passing through the access floor must have gypsum board extending completely to the slab and be sealed at the

slab line. All penetrations into cavity walls and slabs for air ducts, plumbing pipes, electrical conduit and voice/data cabling must be completely

sealed. All seams and/or holes that have been created for or resulting from the work performed by a specific trade should be properly sealed by

that trade and whenever possible performed prior to the installation of the access floor.

Quality Control: Special inspections must be conducted by an independent quality auditor or commissioning agent to ensure that plenum

sealing work is performed by all subcontractors in compliance with specifications and drawings. Inspections shall occur as work progresses

and whenever possible in the presence of a representative from the general contractor. Reports of inspections will be submitted to the general

contractor.

Plenum Mock-Up & Testing: All subcontractors responsible for constructing or penetrating the underfloor plenum must participate in the

construction of an on-site plenum mockup consisting of all planned plenum components, penetrations, seams and openings. The mock-up

plenum is to be inspected and tested by an independent commissioning agent for air leakage to verify that it was constructed and sealed in

accordance with specifications and drawings including meeting the air leakage requirements.

Building Plenum Inspections and Tests: The constructed plenum is to be inspected and tested by an independent commissioning agent for

air leakage to verify that it was constructed and sealed in accordance with specifications and drawings including meeting the air leakage

requirements.

Air Leakage Requirements: Total air leakage from the plenum should be no more than 15% of the design airflow for category 1 leakage, and

15% of the design airflow for category 2 leakage when tested at the typical static pressure range of .05 -.10” w.g. max.

(Note:There are two basic categories of UFAD air leakage. Category 1 leakage occurs outside of the intended occupied zone. Category 2 leak-

age is plenum air that leaks into the occupied zone through spaces other than the designed air distribution devices such as diffusers. Category

2 leakage is unique to UFAD systems because all of this leakage goes into the occupied space whereas in a traditional ducted overhead sys-

tem, all leakage and short-circuited air enters the return plenum and will not reach the intended zone.)

DIVISION 03 - CONCRETE SPECIFICATION - Cast in Place Concrete

The concrete contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the nec-

essary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any

penetrations or holes in the underfloor plenum resulting from the work performed by the division 3 contractors not intended for service utility

distribution are required to be properly sealed to prevent air leakage.

DIVISION 05 - METAL STAIRS SPECIFICATION

The metal stair contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the nec-

essary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any

penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 5 contractors are required to be

properly sealed to prevent air leakage.

4

Page 5: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

DIVISION 09 - FINISHES (WALLS) SPECIFICATION

The wall contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the necessary

precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any penetra-

tions or holes in the underfloor plenum created for or resulting from the work performed by the wall contractors are required to be properly

sealed to prevent air leakage.

DIVISION 09 - FINISHES (ACCESS FLOORING) SPECIFICATION

The access floor contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the

necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness.

Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the access flooring contractors are

required to be properly sealed to prevent air leakage.

DIVISION 09 - FINISHES (TILE CARPETING) SPECIFICATION

The carpeting contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the nec-

essary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any

penetrations or holes in the underfloor plenum created for or resulting from the work performed by the carpeting contractors are required to be

properly sealed to prevent air leakage.

DIVISION 14 - CONVEYING EQUIPMENT SPECIFICATION

The conveying equipment contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will

take the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and

cleanliness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 14 contractors

are required to be properly sealed to prevent air leakage.

DIVISION 22 - PLUMBING SPECIFICATION

The plumbing contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the nec-

essary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any

penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 22 plumbing contractors are

required to be properly sealed to prevent air leakage.

DIVISION 23 - HEATING VENTILATION AND AIR CONDITIONING SPECIFICATION

The HVAC contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the neces-

sary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any

penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 23 HVAC contractors are

required to be properly sealed to prevent air leakage.

DIVISION 26 - ELECTRICAL SPECIFICATION

The electrical contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take the nec-

essary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanliness. Any

penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division 26 electrical contractors are

required to be properly sealed to prevent air leakage.

DIVISION 27 - COMMUNICATIONS SPECIFICATION

The communications contractor is aware that the space beneath the access floor will be used as an air delivery plenum and as such will take

the necessary precautions when installing their work so as not to impact the integrity of the plenum space specific to air leakage and cleanli-

ness. Any penetrations or holes in the underfloor plenum created for or resulting from the work performed by the division

26 communications contractors are required to be properly sealed to prevent air leakage.

5

Page 6: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CURTAIN WALL

CONCRETE DECK

SEAL AT SLAB LINE

INTERIOR WALL ASSEMBLY

Base Building Core & Shell Sealing DetailsA) PERIMETER SEAM ALONG SLAB AND EXTERIOR WALL

6

Construction Details for ConsiderationThe following are typical sealing details that should be considered to ensure UFAD plenum integrity. All of the details can be downloaded on-line

at: www.tateaccessfloors.com/ architectural_details.html

Underfloor Air Sealing LocationsPLAN VIEW WITHOUT ACCESS FLOOR

MECHANICAL

KITCHEN

JANITORMENS

WOMENS

ELECTRICALTELCOM

ELECTRICAL TELCOM

DETAIL A

DETAIL B

DETAIL N

DETAIL E

DETAIL D DETAIL F

DETAIL I & K

DETAIL G

DETAIL L & M

DETAIL CKITCHEN

MENS

WOMENS

Page 7: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

7

CONCRETE DECK

SEAL AT SLAB LINE

SCHEDULED GWB

C) DRYWALL PARTITION CONDITION

STRUCTURAL COLUMN WALL ASSEMBLY (TYP)

CONCRETE DECK

SEAL AT SLAB LINE

B) ENCLOSED COLUMN SEAM AT SLAB LINE

STAIR TREAD (TYP)

SEAL AT SLAB LINE

SEAL SEAM BETWEEN STAIRAND CURB OR OTHER SUPPORT

CONCRETE CURB OR STRUCTURALSTEEL WITH FULL ENCLOSURE

CONCRETE DECK

D) BASE OF STAIRS ON BUILDING SLAB

Page 8: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CONCRETE DECKSEAL JOINT

EXPANSION JOINT

G) EXPANSION JOINT IN CONCRETE DECK

SEAL AT SLAB LINE

CONCRETE DECK

STAIR TREAD (TYP)

TOP OF STAIR INTERFACE WITH CONCRETE DECK

CONCRETE CURB OR STRUCTURALSTEEL WITH FULL ENCLOSURE

E) TOP OF STAIR INTERFACE WITH CONCRETE DECK

SEAL AROUND FULL ENCLOSURE

ELEVATOR THRESHOLD

ELEVATOR DOORS

CONCRETE DECKCONCRETE CURB OR STRUCTURALSTEEL WITH FULL ENCLOSURE

F) ELEVATOR SHAFT BELOW ACCESS FLOOR LINE

8

Page 9: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CONCRETE DECK SEAL SPACE AROUND DUCTDUCT

THROUGHWALL

9

VERTICAL DUCT

SEAL SPACE AROUND DUCT

CONCRETE DECK

HVAC System Sealing DetailsH) OPENING IN SLAB FOR VERTICAL DUCTS

I) OPENING IN PLENUM WALLS FOR DUCTS

Page 10: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CONCRETE DECK

WALL ASSEMBLY

CONDUIT (ANDCABLE BUNDLE) O.D.

SEAL AROUND CONDUIT

CONDUIT

Electrical System Sealing Detailsl) CONDUIT THROUGH PLENUM WALLS

10

CONCRETE DECK

SEAL AROUND PIPE

SEAL AROUND PIPEPIPE O.D.

WALL ASSEMBLY

CONCRETE DECK

Plumbing Sealing DetailsJ) PIPE PENETRATION THROUGH CONCRETE DECK

K) PIPE PENETRATION THROUGH PLENUM WALLS

Page 11: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CONCRETE DECK

WALL ASSEMBLY

CABLE BUNDLE

CAPPED ENDS OF UNUSED CABLE SLEEVE (TYP)

SEAL AROUND CABLE SLEEVE CABLE SLEEVE O.D.

SEAL AROUND CABLES INSIDE SLEEVE

11

OUTLET

CONDUIT

CONDUIT

WALL ASSEMBLY

WALL ASSEMBLY

CONCRETE DECK

CONCRETE DECK

SEAL OPENING AT CONDUIT PENETRATION

SEAL OPENING AT CONDUIT PENETRATION

SEAL OPEN END OF CONDUIT IN PLENUM

SEAL OPEN END OF CONDUIT IN PLENUM

THERMOSTAT

M) OPEN ENDS OF CONDUIT IN THE PLENUM SPACE

Voice/Data System Sealing DetailsN) CABLE PENETRATIONS THROUGH PLENUM WALL WITH CABLE SLEEVE

Page 12: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

12

8’ LONG GALVANIZED STEEL HAT CHANNEL

26 GA. X 6’ STEEL BOTTOM ANGLE CUT AS REQUIRED SO THAT IT DOES NOT EXTEND ABOVE HAT CHANNEL

TAPE JOINTS WITH METAL FOIL TAPE

ACCESS FLOOR PANEL

FIELD APPLIED GASKET

FASTEN WITH TEK SCREWS

PANEL FASTENED TO PEDESTAL HEAD WITH COMBO CORNERLOCK SCREW

ATTACH PLENUM CHANNELWITH STRINGER SCREWS

TAPE JOINTS WITH METAL FOILTAPE WHERE BOTTOM ANGLE SECTIONS MEET AND WHERE HAT CHANNEL SECTIONS MEET

TAPE JOINTS WITH METAL FOILTAPE WHERE HAT CHANNELAND BOTTOM ANGLE MEET

BOTTOM ANGLE SET IN FIELD APPLIED CONTINUOUS ADHESIVE BEAD

FIELD APPLIED TATE PLENUM GASKET P/N 10626

Access Floor Sealing Details1) PLENUM DIVIDERS

Access Floor Air Sealing LocationsPLAN VIEW WITH ACCESS FLOOR INSTALLED

MECHANICAL

KITCHEN

JANITORMENS

WOMENS

ELECTRICALTELCOM

ELECTRICAL TELCOM

DETAIL 6 & 7DETAIL 2

DETAIL 14

DETAIL 13DETAIL 4 & 5

6” RAISED PODIUMDETAIL 8

DETAIL 9 & 10

DETAIL 12DETAIL 1 & 3

KITCHEN

MENS

WOMENS

Page 13: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

METAL FOIL TAPE AT JOINTS

PLENUM DIVIDER ASSEMBLY

SEAL TO FILL GAP (TYP)

WATER PIPE(S)

CONDUIT

CABLE SLEEVE(FIRESTOP OR PUTTY INSIDE OF SLEEVE)

SEAL AT SLAB LINE

WALL EXTENDS TO SUBFLOOR

SEAL AT FLOOR/WALL LINE

CUT PANELS TOWITHIN 1/16" OF WALL

ACCESS FLOOR PANEL

3) PENETRATIONS THROUGH PLENUM DIVIDERS

4) PERIMETER SEAM WITHOUT WALL BASE

13

NOTE: THE TYPICAL STATIC PRESSURE IN AN AIR HIGHWAYIS FROM 0.05” W.G. TO 0.10” W.G.

SEAL PANEL SEAMS WITH ALUMINUM FOIL TAPE FOR HVAC APPLICATIONS (REPLACE TAPE AS NEEDED WHEN PANELS ARE REMOVED)

ACCESS FLOOR PANELS

ALUMINIUM FOIL TAPE AT JOINTS

POSILOCK PEDESTAL (TYP)

HAT CHANNELPLENUM DIVIDER

FIELD APPLIED GASKET AT HAT CHANNEL (TYP)

2) AIR HIGHWAYS

Page 14: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

14

6) PERIMETER SEAM AT NON-SMOOTH WALLS & COLUMNS

7) ACCESS FLOOR SEAL AT FASCIA / EXPOSED EDGE

NON-SMOOTH WALL OR COLUMN

CAULK & FASTEN METAL ANGLE TO WALL

CUT CARPET TO WALL AND ADD OPTIONAL WALL BASE

CONCORE OR ALL STEEL FLOOR PANEL

GUARDRAIL POST

ATTACH TRIM ANGLE OVER CARPET AND FASCIA PLATECUT CARPET TO FASCIA PLACE AND ADHERETO ACCESS FLOOR WITH RELEASABLE ADHESIVE

ACCESS FLOOR PANELFASCIA PLATE (cut to meetedge of access floor)

BOTTOM ANGLE

WHERE GAPS OCCUR BETWEEN THEEDGE OF THE ACCESS FLOOR AND FASCIA,

APPLY DUCT OR METAL TAPE TO SEAL JOINT

TRIM ANGLE

FIRE RATED CAULK OR SEALANT

PRIOR TO APPLICATION OF CARPET.

SEAL AT SLAB LINE

WALL EXTENDS TO SUBFLOOR

WALL BASE (WHERE USED)

CUT PANELS TOWITHIN 1/16" OF WALL

ACCESS FLOOR PANEL

CUT CARPET TO WALL ANDADHERE TO ACCESS FLOOR

WITH RELEASABLE ADHESIVE

5) PERIMETER SEAM WITH WALL BASE

Page 15: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

CONCRETE DECK

STAIR TREAD (TYP)

CONCRETE CURB OR STRUCTURALSTEEL WITH FULL ENCLOSURE

SEAL SEAM AROUND ENCLOSURE

CUT PANEL TO WITHIN1/16" OF STAIR

STAIR TREAD (TYP)

CONCRETE CURB OR STRUCTURALSTEEL WITH FULL ENCLOSURE

SEAL AROUND ENCLOSURE

CUT PANELS TO WITHIN 1/16" OF CURB

9) PERIMETER SEAM AT TOP OF STAIR LANDING

10) PERIMETER SEAM AT BASE OF STAIR LANDING

15

8) ACCESS FLOOR SEAL AT FASCIA / EXPOSED EDGE

Page 16: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

16

13) PERIMETER SEAM AT CURB WHERE FLOOR COVERING IS CONTINUOUS

12) PERIMETER SEAM AT FIRE BARRIER BELOW DOOR THRESHOLD

SHEETROCK FACED FIRE BARRIER SEAL AT SLAB LINE

CONCORE OR ALL STEEL ACCESS FLOOR PANEL

OPTION 1: ATTACH THRESHOLD WITH GASKET ON UNDERSIDE

OPTION 2: APPLY SEALANT OR ATTACH GASKET TO BARRIER TO SEAL JOINTS

PERIMETER PEDESTAL SUPPORT

CARPET TILE ADHERED TO ACCESS FLOOR AND CURB

ACCESS FLOOR PANEL

FOAM GASKET ATTACHEDTO CURB TO SEAL JOINT

CUT PANELS TO WITHIN 1/16" OF WALL.

11) PENETRATION IN WALL THROUGH ACCESS FLOOR

Page 17: Architect's Guide for Detailing & Specifying Access Floor Air Plenums

17

CONCRETE DECK

SEAL AROUND PIPE

15) CABLE CUTOUTS & GROMMETS

16) POWER, VOICE/DATA DISTRIBUTION BOXES IN ACCESS FLOOR PANELS

17) PIPE PENETRATION THROUGH ACCESS FLOOR

SECTION THROUGH CUTOUT

PLAN VIEW

FOAM PLENUM SEAL

FOAM PLENUM SEAL

CUTOUT TRIM MOLDING

FOAM PLENUM SEALS:THESE ARE PROVIDED BY THEACCESS FLOOR MANUFACTURER ANDARE RECOMMENDED TO SEALCABLE OPENINGS

LID IS 2 PART TWIST COVERFULLY CLOSED POSITION

PLAN VIEW

TO PREVENT AIR LEAKAGE

SEAL UNUSED DUPLEX OPENINGS

ATTACH BLANK INTERFACE PLATESTO UNUSED OPENINGS

OTHER COVERING ADHERED TO CURBTRANSITION STRIP OR THRESHOLD

CARPET TILE ADHERED TO ACCESS FLOORACCESS FLOOR PANEL

CUT PANELS TO WITHIN 1/16" OF WALL. IF GAP

14) PERIMETER SEAM AT CURB WHERE FLOOR COVERING IS NOT CONTINUOUS

Page 18: Architect's Guide for Detailing & Specifying Access Floor Air Plenums