    1. What do we consider to be a critical AQP Task?

    2. Identify the critical AQP tasks associated with fourprimary AQP activities

    3. Review each critical AQP task and what is expected

    when managing them4. Review case studies / real world examples

    What happened?

    How was it managed?

    What couldhave prevented it?

  • 7/30/2019 AQP Critical Tasks November2011

    3/47

    3

    4

    9

    2

    10

    PPAP Post V1 - Causal Factors

    Late Design Release

    Late Design Changes

    ManufacturingFeasibilitySupplier Program

    Management

    Total Case Studies: 25Product Teams: Truck/SRT, Minivan/MUV, SUV

  • 7/30/2019 AQP Critical Tasks November2011

    4/47

    4

    PSO/PDR

    Step 3Verification of

    Process (VP)

    Pre Volume

    Production

    (PVP)Job 1 Offline Commercial

    Launch

    Tooling PPAP

    LATE DESIGN

    RELEASE

    PSO/PDRTooling PPAP

    LATE DESIGN

    CHANGE

    PSO/PDR PPAP

    Step 5

    MANUFACTURING

    FEASIBILITY

    PSO/PDR PPAP

    Tooling

    Tooling

    SUPPLIER PROGRAM

    MANAGEMENT

  • 7/30/2019 AQP Critical Tasks November2011

    5/47

    5

    Late Design Release leads to late Tooling Kickoff

    Tooling has the largest impact on downstream deliverables

    Prototype tooling is a poor substitute!

    Late Design Changes

    Many late design changes can be traced back to a lack of, or

    failure during, DV Testing

    Manufacturing Feasibility

    Supplier unable to meet requirements

    Supplier Program ManagementMany reasons; one common one is inability to meet line

    speed requirements

  • 7/30/2019 AQP Critical Tasks November2011

    6/47

    6

    For SQ purposes, we would consider any AQP Task as

    critical if it:1. Has a major impact on downstream deliverables and

    other tasks

    2. Ensures the part, as designed, meets requirements3. Ensures the part, as manufactured, meets

    requirements

    4. Ensures the process can meet our production needs

    5. What else?

  • 7/30/2019 AQP Critical Tasks November2011

    7/477

    SUPPLIER:

    SUPPLIER CODE: MY/VEHICLE FAMILY:

    PART NUMBER(S):

    REVISION:

    PART NAME(S): REVISION DATE:

    AQP MEETING DATE:

    PART RISK (H/M/L): AQP MEETING LOCATION:

    VPPVPJob 1

    BEGIN

    PLAN ACT PLAN ACT

    SQE -

    SQE -

    SQE 1

    SQE -

    ENG -

    SQE -

    SQE -

    SQE -

    SQE -

    SQE -

    SQE -

    SQVL -

    ENG 2

    ENG -

    ENG -

    ENG -

    ENG -

    ENG -

    SQE -

    ENG -

    ENG 3

    ENG 4

    SQE -

    ENG -

    SQE 5

    SQE 6

    SQE 7

    SQE 7.8

    SQE: Supplier Quality Engineer SQVL: SQ Vehicle Lead Major milestones Secondary milestones RECOMMENDED EVENT / DELIVERABLEENG: Release Engineer MET: Metrology Center ACTUAL

    DO: Design Office CURRENTDAY

    Month-Date STATUS

    # of

    Days

    Review CNs and IAAs (including associated Risk)TAG Review (Chrysler-purchased tooling only)

    Confirm composition and commitment of Core

    AQP Team Members

    Part Development Plan Complete

    Status of Open Issues from Technical Review Risk

    Assessment (FIAT parts only)

    END

    If status is 1, 2, or 3 (Red

    or Yellow), you must

    provide a Risk Mitigation

    PlanEnter 1-5

    Process Flow Diagram & Mfg. Floor Plan

    CUSTOMER

    LEAD

    PSO

    Element

    Control Plan and Process Monitoring

    Supplier Quality Risk Assessment (SQRA)

    Month-Date Month-Date

    Production Tooling Complete (PTC)

    SUPPLIER

    RESPONSIBLE

    # of

    Veh

    AQP ACTIVITIES

    eCIMS / Lessons Learned Master PFMEA

    Reviewed

    Advance Quality Planning

    Build

    NameMRD

    Design Review - Customer Perception targets

    Manufacturing Feasibility Assessment (MFA)

    DV Testing Complete

    Month-Date Month-DateMonth-Date

    ADVANCE QUALITY PLANNING (AQP)

    TIMING CHART

    Month-DateMonth-Date

    YEAR

    Month-DateMonth-Date

    #NUM!FIAT PROGRAM

    REVIEW STATUS #NUM!CHRYSLER AQP

    STATUS

    RISK MITIGTION PLAN

    KEY MATERIAL/BUILD DATES

    Build DateMonth-DateMonth-Date Month-Date

    Source Package Review

    Test Sample Sizes and Frequencies

    YEAR

    Confirm Supplier PPAP Self-Certification status

    Volume, ramp-up curve, and product mix verified

    and capable - CPV, P.O, SP

    Design FMEA

    Verify deliverables timing to CPCP timing

    Process FMEA

    Part Inspection Standard

    Prior PSO Review (similar products)

    Initial Risk Evaluation (IRE)

    Supplier Tooling Kick-Off (TKO)

    Verify Tooling Capacity and Required Station CycleTime / Line Speed Plan

    Part Number, Description, and Change Level

    Design Model Status Review

    Part I/S Parts, 8 weeksbefore VP

    All Other

    Program &StyleApproval

    EF EFEF

    Step 2StyleFreeze

    Step 3ToolingKickoff

    EF

    Verification ofProcess

    VP EF

    Pre VolumeProduction

    PVP EF

    Job 1Offline

    EF

    CommercialLaunch

    EF

    Step 5 Prod.DesignsComplete

    EF

    Draft Final

    0

    0

    Identify -22 weeks prior to VP MRD

    Part Sourced + 2 weeks

  • 7/30/2019 AQP Critical Tasks November2011

    8/478

    VPPVP

    Job 1

    BEGIN

    P LAN ACT PLAN ACT

    SQE -

    SQE 1

    SQE -

    ENG -

    SQE -

    SQE -

    SQE -

    SQE -

    SQE -

    PTS -

    ENG -

    ENG -

    ENG -

    SQE -

    ENG -

    ENG 3

    ENG 4

    SQE -

    Review CNs and IAAs (including associated Risk)TAG Review (Chrysler-purchased tooling only)

    Confirm composition and commitment of Core

    AQP Team Members

    Part Development Plan Complete

    Status of Open Issues from Technical Review Risk

    Assessment (FIAT parts only)

    Supplier Quality Risk Assessment (SQRA)

    CUSTO

    MER

    LEAD

    PSO

    Element

    END

    Build

    NameMRDBuild Date

    Production Tooling Complete (PTC)

    SUPPLIER

    RESPONSIBLE

    # of

    Veh

    AQP ACTIVITIES

    eCIMS / Lessons Learned Reviewed

    Advance Quality Planning

    Design FMEA

    Test Sample Sizes and Frequencies

    # of

    Days

    Design Review - Customer Perception targets

    Initial Risk Evaluation (IRE)

    Source Package Review

    Confirm Supplier PPAP Self-Certification status

    KEY MATERIAL/BUILD DATES

    Verify deliverables timing to CPCP timing

    Prior PSO Review (similar products)

    Volume, ramp-up curve, and product mix verified

    and capable - CPV, P.O, SP

    1. Item or activity title

    Key AQP tasks and SQ deliverables(IRE, Production Tools Complete,IMDS, PPAP)

    All PSO Elements

    2. Tracks Supplier responsibilityfor each item, with begin/end

    dates

    3. Key build/MRD dates

    4. Details Chrysler lead for eachitem

    1

    2

    3

    4

  • 7/30/2019 AQP Critical Tasks November2011

    9/479

    If status is 1, 2, or 3 (Redor Yellow), you must

    provide a Risk Mitigation

    PlanEnter 1-5

    STATUS RISK MITIGTION PLAN

    9

    5 6

    5. Indicate the status of the task.

    6. Brief description of the risk mitigationplan (or reference to a more detailedaction plan)

    Score Chrysler Definition

    1

    Not present / not started and: Very late to required milestone and will cause other required

    deliverables to be late to their required milestone/vehicle launch

    Risk Mitigation Plan does not exist

    Extremely High Risk to milestone/vehicle launch (certain to cause

    delay in milestone/vehicle launch)

    2

    Incomplete and:

    Late to required milestone and may cause other deliverables to be

    late to their required milestone/vehicle launch

    Risk Mitigation Plan exists but is not acceptable or requires

    unrealistic timing to meet milestone High Risk to milestone/vehicle launch (may cause delay in

    milestone/vehicle launch)

    3

    Incomplete and:

    Late to required milestone

    Risk Mitigation Plan exists and is acceptable

    Low Risk to milestone/vehicle launch

    4Incomplete and:

    Progressing according to required milestone timing

    No Risk to milestone/vehicle launch

    5 Complete and approved

  • 7/30/2019 AQP Critical Tasks November2011

    10/47

  • 7/30/2019 AQP Critical Tasks November2011

    11/4711

    Tooling Design & Development

    Tasks involved withmanaging the proper

    design and on-time kick-

    off and construction of

    production tooling

    Capacity Verification

    Tasks involved withensuring the process will

    meet (or exceed)

    Chryslers volume

    requirements

    Testing

    Tasks involved with ensuring

    the part, as designed andmanufactured, functions as

    intended and meets

    requirements

  • 7/30/2019 AQP Critical Tasks November2011

    12/4712

    What is impacted by Tooling?

    Process FMEA

    Control Plan

    Set-up Instructions

    Work Instructions Error / Mistake Proofing

    Layered Process Audit

    Preventive Maintenance Plans

    Part Qualification Process

    Supplier Readiness Evaluation

    PV Testing

    PSO On-Site Visit

    Production Demonstration Run

    Initial Process Study /Capability

    Appearance Approval

    Color Harmony / Match

    PPAP What Else?

    Red = Key Performance Indicators

  • 7/30/2019 AQP Critical Tasks November2011

    13/4713

    AQP Tasks directly related to managing Tooling

    Design & Development: Design FMEA

    Design Model Status Review

    Supplier Tooling Kick-Off (TKO) Production Tooling Complete

    TAG Review

  • 7/30/2019 AQP Critical Tasks November2011

    14/4714

    Design FMEA

    Expectations: Supplier-designed parts require a DFMEA developed by the

    Supplier with Chrysler Engineering input & approval

    Should include evidence that Lessons Learned from previous /

    similar designs have been considered Highest risk items should have action plans

    Items with Severity of 8 or higher should have Error /MistakeProofing planned for the tooling and assembly equipment

    DFMEA should be complete early enough to allow for toolingdesign

    If no DFMEA exists for a Chrysler-designed part, we need to askthe question Why?

  • 7/30/2019 AQP Critical Tasks November2011

    15/4715

    Managing the DFMEA task

    DFMEA does not exist (Supplier-design) DFMEA incomplete prior to TKO

    No input from the Chrysler Engineer or

    No evidence of Lessons Learned

    No Error/Mistake Proofing for Severity 8+ or

    Risk Mitigation

    Focus should be on completing the DFMEA before TKO.

    High risk or high severity items should have actions plan with afocus on total prevention of errors.

    Chrysler Engineer should review and approve.

    1

    2

    2

    1

    2

    2

    3

  • 7/30/2019 AQP Critical Tasks November2011

    16/4716

    Design Model Status Review

    Expectations: Supplier has latest design model

    Design model release occurs in time for TKO

    Latest CN revisions are incorporated into the tool design

    Managing the Design Model Status Review task Design Model will not be complete in time for TKO or TKO

    occurs without a finalized design

    Proposed design changes result in late tool completion or

    Risk Mitigation Focus should be on completion of Design Model before TKO

    2

    2 3

  • 7/30/2019 AQP Critical Tasks November2011

    17/4717

    Supplier Tooling Kickoff (TKO)

    Expectations: Ensure all production part and tooling POs are written and

    released, prior to the TKO process start.

    Assist Engineer to ensure the Supplier understands the TKO

    process and their role, and help address roadblocks. TKO should occur by CAD Step 3; should be enough time to

    complete production tools by VP!

    Attend the Form Signing event Form Signing: The Chrysler internal team level event where the checklist

    will be reviewed and approved by the individual lead responsibleapprovers.

    TKO is the start of tooling, not tooling design or ordering

    material!

  • 7/30/2019 AQP Critical Tasks November2011

    18/4718

    Managing the Supplier TKO task

    TKO starts without a complete design or TKO starts without completed POs or

    TKO takes place late (post Step 3) or less (depends on how

    late this makes tooling)

    TKO form is signed, but Supplier verbally told not to beginconstruction of tools or less

    Risk Mitigation

    Focus should be on completion of all deliverables before TKO

    Target should be Production Tools Complete by VP

    TKO should not be signed until tooling is ready to start

    construction

    1 2

    2 3

    3

    3

  • 7/30/2019 AQP Critical Tasks November2011

    19/47

  • 7/30/2019 AQP Critical Tasks November2011

    20/4720

    Production Tooling Complete

    Expectations:

    Tooling should be scheduled for completion by the Verification of

    Process milestone (VP)

    Ensure timing takes potential transit time into account (both forcompletion and CN activity)

    Identify potential issues with tool makers (e.g., long distance,

    poor quality, etc.)

    Review the ongoing status of tooling at each AQP meeting(completion status)

    Ensure tool makers are aware of design changes and have the

    latest revision level

  • 7/30/2019 AQP Critical Tasks November2011

    21/4721

    Managing the Production Tooling Complete task

    Tooling Completion expected after VP or less Tooling Completion expected after PVP (or later) or less

    Concerns with effectiveness / quality of tool maker

    Tooling Completion timing beginning to slip

    Risk Mitigation

    Focus should be on completion of tooling by VP

    Plans will often rely on using prototype tooling longer than

    intendedensure process controls equal or exceed intended

    production levels!

    Ensure backup tools are capable of producing the quantity of

    parts required, both daily and in total

    2

    3

    3

    3

  • 7/30/2019 AQP Critical Tasks November2011

    22/4722

    TAG Review

    Expectations: TAG follows some tooling (Chrysler-built)

    Hold regular reviews with the TAG SQE to follow status of

    tooling

    Managing the TAG Review task Same as for Production Tooling Complete

    Risk Mitigation Same as for Production Tooling Complete

  • 7/30/2019 AQP Critical Tasks November2011

    23/47

    23

    What could happen when a Supplier is unable to

    meet our releases?

    Expedited parts shipments

    Hiring of new or temporary personnel w/o process knowledge

    Unapproved process changes or rework/repair Skipping time-consuming steps (like inspections)

    Turning off Error/Mistake-Proofing

    Running the process 24/7 (no PM, 1st Piece Approval, etc.)

    Expedited construction of new tools

    What else?

  • 7/30/2019 AQP Critical Tasks November2011

    24/47

    24

    AQP Tasks related to Capacity Verification:

    Volume, ramp-up curve, and product mix verified andcapable - CPV, P.O., SP

    Verify Tooling Capacity and Required Station Cycle Time

    / Line Speed Supplier Readiness Evaluation

    Production Demonstration Run

    Part Delivery Plan Review (for VP, PVP, V1, etc.)

  • 7/30/2019 AQP Critical Tasks November2011

    25/47

    25

    Volume, ramp-up curve, and product mix verified

    and capable - CPV, P.O., SP

    Expectations:

    Review program volume requirements, planned product mix, and

    planned launch ramp-up curve. Ensure the Source Package details the required information and

    that the Supplier understands the requirements.

    Ensure the Purchase Order is complete by the required timing

    and that it correctly lists Daily Tooling Capacity, Capacity PlanningVolume, and Shift Pattern

    Buyer and Supply/Logistics should be at the meetings to discuss

  • 7/30/2019 AQP Critical Tasks November2011

    26/47

    26

    Managing the Volume, ramp-up curve task

    Volume requirements or product mix unknown Purchase Order incomplete or showing incorrect volumes or

    Tooling as designed cannot meet volume assumptions

    Volumes increase after beginning of tooling or less

    Risk Mitigation

    Focus should be on ensuring volumes are correct and the

    Supplier understands what they are.

    Additional focus on understanding volumes prior to TKO

    2

    32

    1

    3

  • 7/30/2019 AQP Critical Tasks November2011

    27/47

    27

    Verify Tooling Capacity and Required Station Cycle

    Time / Line SpeedExpectations:

    Ensure the Daily Tooling Capacity is sufficient to meet Chrysler'sneeds and meets or exceeds the Capacity Planning Volume.

    Review the shift pattern (shifts/hours/days) to ensure that itsupports production and allows enough time for PM activities.

    2/8/5 is the standard; if it exceeds this, why?

    Verify shift pattern on a regular basis; if it changes, why? Is there stillenough time for maintenance and similar activities?

    Verify whether or not the part(s) are included in a CommonProcess Group (CPG)

    Calculate the line speed required for the PDR and extrapolaterequired Station Cycle times for the SRE.

  • 7/30/2019 AQP Critical Tasks November2011

    28/47

    28

    Managing the Verify Tooling Capacity task

    Daily Tooling Capacity less than Capacity Planning Volume Operating shift pattern does not leave adequate time for PM or

    similar activities or

    Calculated required line speed or station cycle times exceeds

    what the Supplier expects to be able to produce or less Shift pattern increases from initial plan or less

    Risk Mitigation

    Plan should be to meet volume requirements without sacrificingquality activities

    Identify situations when additional tooling is necessary

    Purchasing and Supply/Logistics included on actions

    2

    21

    2

    3

  • 7/30/2019 AQP Critical Tasks November2011

    29/47

    29

    Supplier Readiness Evaluation & Production

    Demonstration RunExpectations:

    Verify required line speed and station cycle times required for

    both runs

    Verify the number of pieces to be run for each

    SRE should run enough to verify cycle time, FTC, and provide parts for PV

    testing

    PDR is minimum of 300 pieces or 2 hours (whichever is more)

    Determine if an Extended Run PSO will be done (Appendix D ofthe AQP/PSO Manual 7th Edition)

    Identify separate PDR dates for Stepped Tooling Plans

    SRE should be before VP, PDR prior to PVP

  • 7/30/2019 AQP Critical Tasks November2011

    30/47

  • 7/30/2019 AQP Critical Tasks November2011

    31/47

    31

    Part Delivery Plan Review (for VP, Pre Series, V1, etc.)

    Expectations:

    Review the Supplier's plan for part delivery for all pilot builds and

    launch

    Verify the plan has the latest quantities and timing/MRDs for

    each applicable build and build phase

    Ensure Tool completion date is sufficient to meet MRDs

  • 7/30/2019 AQP Critical Tasks November2011

    32/47

    32

    Managing the Part Delivery Plan task

    Supplier is unaware of requirements for pilot builds Tooling completion timing requires parts to be delivered to plant in

    multiple shipments (for the same build phase)

    Prototype material will have to be swapped out of the plant

    Prototype tooling to be used for VP or later or less

    Risk Mitigation

    Plan should be made to provide correct build quantities to Supplier

    Plan should also minimize any material built off of prototype

    tooling (i.e., staggered shipments are preferable to swapping

    material out of the plant)

    Ensure prototype parts, if used are properly marked and identified

    3

    3

    3

    2

  • 7/30/2019 AQP Critical Tasks November2011

    33/47

    33

    What can happen when we dont fully test the

    product design or function?

    Plant pilot build issues

    Late design changes / CNs

    Failure to meet regulatory or governmental regulations PRIs / Yardholds

    High Warranty / Safety Office campaigns

    What else?

  • 7/30/2019 AQP Critical Tasks November2011

    34/47

    34

    Lack of DV Testing /

    DV Testing

    incomplete

    Pilot Build

    IssueLate CN

    Abbreviated

    TestingQuality Spill

    High

    Warranty

  • 7/30/2019 AQP Critical Tasks November2011

    35/47

    35

    AQP Tasks related to Testing:

    Test Sample Sizes and Frequencies

    DV Testing Complete

    Production Validation Testing Complete

  • 7/30/2019 AQP Critical Tasks November2011

    36/47

    36

    Test Sample Sizes and Frequencies

    Expectations: Prior to DV / PV Testing start, review the DV / PV Test plan with

    the Supplier and Engineer: verify specific test method, sample

    sizes / frequencies, and timing for each DV / PV test (Engineering

    sign-off required) Engineering to verify which PV Tests are required by VP

    If DV Testing will not be performed, discuss as a team and

    determine if this is the right decision!

    Review Continuing Conformance testing plan (test method,sample sizes / frequencies)

    Review the Suppliers Annual Validation plan and adherence

  • 7/30/2019 AQP Critical Tasks November2011

    37/47

    37

    Managing the Test Sample Sizes and Frequencies task

    DV Testing will not be performed or less unless team agrees DV or PV Testing begins without Engineering review of the plan

    DV or PV Testing timing late to VP or PVP or less

    Supplier has not considered Continuous Conformance testing in

    their test plan or Control Plan or less Supplier has not adhered to Annual Validation requirements

    Risk Mitigation

    Recovery plan should ensure all testing is performed (e.g., larger

    sample sizes, additional test equipment, etc.), not skipping tests.

    Failed parts require corrective action and repeating the full test, not

    just replacing the failed part.

    3

    2

    3

    2

    3

  • 7/30/2019 AQP Critical Tasks November2011

    38/47

    38

    DV Testing Complete

    Expectations: Review DV Testing results with the Supplier and Engineer

    (Engineering sign-off required)

    Review all test failures and verify corrective actions have been

    implemented and successfully retested

    Successful DV Testing is required before PV Testing can begin,

    unless waived in writing by the engineer

    If PV Testing will begin before a DV Test failure is retested

    (requires Engineering waiver), discuss the reason; is this thecorrect decision?

  • 7/30/2019 AQP Critical Tasks November2011

    39/47

    39

    Managing the DV Testing Complete task

    PV Testing to begin without successful DV Testing or less No corrective actions in place for DV Test failures

    Risk Mitigation

    Plan should require corrective actions for DV Test failures.

    If PV will be used to validate corrective actions for DV Test failures,

    ensure enough time exists (and backup plan is in place) to retest in

    the event of another failure

    3

    1

  • 7/30/2019 AQP Critical Tasks November2011

    40/47

    40

    PV Testing Complete

    Expectations: PV Testing timing should identify PV Tests required by VP

    PV Testing timing should allow for PPAP by PVP

    BSR/NVH should be accounted for in the PV Test plan (as

    applicable)

    Review the status of the PV Testing start date (still on-track,

    slipping, etc.)

    Review plan and status of Chrysler-responsible testing

  • 7/30/2019 AQP Critical Tasks November2011

    41/47

    41

    Managing the PV Testing Complete task

    Start date begins to slip or less PV Testing required by VP will be late or less

    PV Testing timing will result in late PPAP or less

    PV Test failure or less

    Risk Mitigation

    Corrective actions for testing failures implemented and re-tested

    Actions should not reduce or skip tests; to compress timing, focus

    should be on testing larger sample sizes

    3

    3

    4

    3

  • 7/30/2019 AQP Critical Tasks November2011

    42/47

    42

    Case Study #1

    Component: Roof RacksIssue: Part does not fit to sheet metal; the sheet metal

    was not to print (supplied from an internal stamping

    plant). Late tooling changes were required which pushed

    tooling completion, and therefore PDR & PPAP, late.

    What risk mitigation activities should be taken?

    What could have been done to catch this earlier?

  • 7/30/2019 AQP Critical Tasks November2011

    43/47

    43

    Case Study #2

    Component: SpoilersIssue: Deficiencies in the tool design and ergonomic issues

    at the Chrysler Assembly Plant required a late design

    change.

    What risk mitigation activities should be taken?

    What could have been done to catch this earlier?

  • 7/30/2019 AQP Critical Tasks November2011

    44/47

    44

    Case Study #3

    Component: HVAC Control HeadIssue: Part could not meet the Daily Tooling Capacity

    requirements (most recent PDR was short by 5 pieces per

    hour). Primary issue was excessive machine downtime.

    What risk mitigation activities should be taken?

    What could have been done to catch this earlier?

  • 7/30/2019 AQP Critical Tasks November2011

    45/47

    45

    All AQP Tasks are important; some require special

    attention Tasks that directly impact deliverables / timing

    Tasks that directly affect part ability to function andmeet requirements

    Tasks that impact the Supplier meeting productioncapacity needs

    Use the AQP/PSO Scoring system to raise the red flag(or the yellow one)

    Risk mitigation plans when a deliverable is late / at risk(yellow and red)